GDOT s Design-Build Program Past, Present and Future
|
|
- Elaine Jenkins
- 5 years ago
- Views:
Transcription
1 GDOT s Design-Build Program Past, Present and Future John D. Hancock, P.E. Assistant State Innovative Program Delivery Engineer September 16, 2013
2 Agenda Program Overview GA Code (SB 70) Look Ahead 2
3 Program Overview 22 Design-Build Contracts Awarded ($693M) Lowest Qualified Bidder (Two Phase Low Bid Process) Projects Include o I-75 Express Lanes ($176M) o KIA Interchange ($81M) o Jimmy Deloach Connector ($73M) o Skidway Narrows Bridge Replacement ($22M) o Ridgewalk Parkway Interchange ($17M) o SR Hammond Drive Interchange ($17M) o I-285 Variable Speed Limit Signs ($5M) o Washington Road Lighting ($1M) 3
4 GA Code (SB 70) Signed into Law April 18, 2013 Allowable Design-Build Selection Methods o One Phase Low Bid o Two Phase Low Bid o Best Value Other Modifications o Removed Must receive three letters of interest o Removed May award if at least two proposals are received Adopt by Rule Procedures for Administering Design-Build Contracts 4
5 5 Rulemaking Next Steps Apr May June July Aug Sept Oct Nov Dec April 28 SB 70 Signed into Law May 15 Committee Meeting July 18 Board Meeting (Issuance of Notice of Intended Action) Aug 30 Comment Period Closed September 19 Board Meeting (Anticipated adoption date) Rules filed with Secretary of State Rules become final after 20 days of filing with Secretary of State
6 Project Type o Well defined project scope with minimal opportunity for innovative solutions o Minimal or no impacts to ROW and Utilities o Minor roadway widening, intersection improvement(s), lighting project(s), emergency projects or minor bridge replacement Selection and Award o Contractors and designers must be prequalified by GDOT to perform work o Design-Build teams submit price and qualifications package in one-step o Qualification packages evaluated by GDOT on a pass/fail basis o Awarded to lowest qualified and responsive bidder Benefits One Phase Low Bid o Procurement process reduced by 2-3 months o Creates opportunity for more contractors/designers to participate 6
7 Project Type Two Phase Low Bid o Moderate level of complexity o Limited opportunity for innovative solutions unless within scope, and provides some design and/or construction cost savings o Past performance or other Proposer qualifications need to be considered when selecting qualified Design-Build teams o Projects elements may include utility relocations, ROW acquisition activities, environmental permitting/environmental mitigation activities, major bridge, and hydraulic studies 7
8 Selection and Award Two Phase Low Bid o Advertise Request for Qualifications (RFQ) o Receive Letter of Interest (LOI)/Statement of Qualifications (SOQ) Pass/Fail requirements (e.g. area classes) Experience and Qualifications Past Performance o Issue Selection of Qualified Finalists o Advertise Request for Proposals (RFP) o Receive and evaluate Technical Proposal o Receive Price Proposals o Awarded to lowest responsive bidder 8
9 Project Type Best Value o Department is seeking innovative solutions o Larger complex projects or projects that include software development, integration or rapidly changing technologies o Projects with minimal up front design decisions which create opportunities for innovative solutions or different design concepts that achieve Department goals 9
10 Selection and Award Best Value o Advertise Request for Qualifications (RFQ) o Receive Letter of Interest (LOI)/Statement of Qualifications (SOQ) Pass/Fail requirements (e.g. area classes) Key personnel Demonstrated experience and qualifications Past performance o GDOT selects the highest ranked firms (no more than 5 Proposers) o Advertise Request for Proposals (RFP) o Receive and evaluate Technical Proposals o Receive Price Proposals o Awarded to Proposer with the Highest Combined Score 10
11 Benefits Best Value o Encourages and rewards innovative solutions o Allows utilization of confidential Alternative Technical Concepts (ATCs) o Allows utilization of one-on-one meetings with Proposers o Encourages Design-Build teams to focus on certain elements which will provide long term value to the citizens of Georgia 11
12 Project Selection Matrix 12
13 13 Variable Speed Limit Signs I-285 Variable Speed Limit Signs o Design-Build contract ($4,921,604.00) o Contract completion date of September 30, 2014 o VSLS on north end and static signs on south end o LED signs to regulate speed limit and traffic flow o Raise speed limit from 55 mph to 65 mph o VSLS to be implemented on I-85, I-75 and I-20
14 Express Lanes - Implementation 14
15 I-75 Express Lanes Total Project length of approximately 17miles Begins at SR 155/McDonough Road and terminates at SR 138/Stockbridge Highway One (1) reversible barrier-separated managed lane in the median of I-75 from SR 155 to north of SR 20 Two (2) reversible barrier separated managed lanes in the median of I-75 from north of SR 20 to SR 138 Northbound operations in the morning and reverses southbound operation in the evening Design-Build Contract ($176,247,661.51) Open to Tolling by December 31, 2016 Contract completion by June 30,
16 I-85 Express Lanes - Extension Project length of 10 miles Begins at Old Peachtree Road and terminates at Hamilton Mill Road One (1) bi-directional buffer-separated managed lane along the outside of I-85 from Old Peachtree Road to South of I-985 One (1) bi-directional buffer-separated managed lane along the inside shoulder of I- 85 from South of I-985 to Hamilton Mill Road Project procured by Design-Build delivery 16
17 17 Weigh-in-Motion Weigh-in-Motion (WIM) o WIM measures truck weights and axle configuration at highway speeds o Virtual WIM allows for real-time enforcement of overloaded vehicles o Best Value Selection Method - Project that Includes Software Development, Integration or Rapidly Changing Technologies o Upgrade all 19 total truck weigh stations o Procurement process to begin in January 2014
18 Weigh-in-Motion 18
19 Weigh-in-Motion 19
20 In Closing Complete Rulemaking process Revise GDOT s Design-Build Manual Evaluate/enhance the current Design-Build contract Continue to reach out to and listen to the industry 20
21 Contact Info/Resources John D. Hancock, P.E. Assistant State Innovative Program Delivery Engineer Darryl D. VanMeter, P.E. State Innovative Program Delivery Engineer
I-64 Capacity Improvements Segment III RFQ Information Meeting
I-64 Capacity Improvements Segment III RFQ Information Meeting April 5, 2017 Janet Hedrick, P.E. Design Project Manager Joseph Clarke, P.E. APD Project Manager and POC I-64 Capacity Improvements Segment
More informationGloucester Parkway Extension RFQ Information Meeting
Gloucester Parkway Extension RFQ Information Meeting May 24, 2013 Tim Hartzell, PE District Project Manager Kevin Reichert, PE APD Project Manager and POC Topics Project Location & Overview RFQ Information
More informationConstruction Division Update Upcoming Work. Greg Henion, P.E. Deputy State Construction Engineer
Construction Division Update Upcoming Work Greg Henion, P.E. Deputy State Construction Engineer Pre-Qualification 2 Why prequalification? Contractor s ability to perform the work: Quality Safety Experience
More informationInterstate 66 Widening from. RFQ Information Meeting. January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager
Interstate 66 Widening from Gainesville to Haymarket RFQ Information Meeting January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager John C. Daoulas, P.E. APD Project Manager and POC Introduction
More informationNORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV
Noise Technical Report 2015 Addendum NOISE TECHNICAL REPORT 2015 Addendum PREPARED FOR: Federal Highway Administration and Georgia Department of Transportation PREPARED BY: Parsons Brinckerhoff Project
More informationJoint House and Senate Transportation Committee Update to the Ten Year Plan
Joint House and Senate Transportation Committee 2019 Update to the Ten Year Plan Federal and State Funding Sources 2 AFY19 Budget Revenue Estimates 3 FY19 Federal & State Funds Federal Funds 38% State
More informationI-64/ Route 15 (Zion Crossroads) RFQ Information Meeting
I-64/ Route 15 (Zion Crossroads) Diverging Diamond Interchange RFQ Information Meeting December 13, 2011 Brian Arnold District Project Manager Ian Millikan, PE APD Project Manager and POC Introduction
More informationRoute 7 Truck Climbing Lane. RFQ Information Meeting
Route 7 Truck Climbing Lane From West Market Street to Route 9 RFQ Information Meeting November 9, 2012 Mark Gibney, PE District Project Manager Ian Millikan, PE APD Project Manager and POC Introduction
More informationVDOT Major Projects Update
VDOT Major Projects Update April 20, 2017 Agenda Introduction Peninsula Projects Southside Projects Harbor Crossing Questions/Comments 2 Summary Construction Execution Timeline I-64 Peninsula Seg. I PE
More informationCONCURRENT SESSION C/Track 1 Alternative Delivery at GDOT: New Frontiers & Opportunities
CONCURRENT SESSION C/Track 1 Alternative Delivery at GDOT: New Frontiers & Opportunities Darryl D. VanMeter, P.E. GDOT Office of Innovative Delivery Stephen Lively, Butch Welch, Marlo Clowers, Andrew Hoenig,
More informationRFQC Bidders Conference (RFQC( No ) Tolling Systems Integrator/ I-85 Express Lanes and Back Office Conversion Project Terri Slack &
RFQC Bidders Conference (RFQC( No. 927-10-00002) Tolling Systems Integrator/ I-85 Express Lanes and Back Office Conversion Project Terri Slack & Chris Tomlinson September 3, 2009 Agenda Project History
More informationDerry-Londonderry I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing
Derry-Londonderry 13065 - I-93 Exit 4A Public Officials/Information Meeting/NHDOT Design-Build Public Hearing July 25, 2018 Purpose of Meeting Purpose and Need Current Project Status Alternatives Overview
More informationI-95 Southbound CD Lanes Rappahannock River Crossing Stafford County/ City of Fredericksburg, Virginia. RFQ Information Meeting - November 9, 2016
I-95 Southbound CD Lanes Rappahannock River Crossing Stafford County/ City of Fredericksburg, Virginia RFQ Information Meeting - November 9, 2016 Krishna Potturi, PE Project Manager Suril Shah APD Project
More informationAny discussions or marketing activities related to this specific project.
04-11-19 Posting Date South Sandusky Street Widening and Relocation PID No. Not Assigned City of Mount Vernon Response Due Date: 04-24-19 Communications Restrictions Please note the following policy concerning
More information2009 Louisiana Transportation Conference February 9, 2009 Session 9. LA DOTD s Design-Build Procurement For the I-12 Widening Project
2009 Louisiana Transportation Conference February 9, 2009 Session 9 LA DOTD s Design-Build Procurement For the I-12 Widening Project Jeff Burst, P.E. Project Management Administrator Louisiana Department
More informationIMPROVING I 81 IN MARYLAND
IMPROVING I 81 IN MARYLAND April 25, 2017 Stephen A. Bucy, P.E. Improving I 81 in Maryland Overview: Facts SHA s Comprehensive I 81 Strategy Current Phase 1 Widening Project Update Closing Improving I
More informationRoute 29 Solutions. September 11, 2014 Rt. 29 Project Delivery Advisory Panel Meeting
September 11, 2014 Rt. 29 Project Delivery Advisory Panel Meeting Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Viewers:
More informationPlanned Procurement Opportunities Report. September 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationSunrise Project South I-205 Corridor Improvement Project
Sunrise Project South I-205 Corridor Improvement Project January 24, 2007 Sunrise and I-205 Project Summary Conclusions Sunrise Scoping Study Key Results South I-205 Scoping Study Key Results South I-205
More informationGerald Desmond Bridge. Design-Build Industry Workshop August 10, 2010
Gerald Desmond Bridge Design-Build Industry Workshop August 10, 2010 Aug. 10 Workshop Questions? Email gdbridge@polb.com Or call 562.980.4983 Agenda Introduction and Purpose Scope of Work Budget & Funding
More informationNCDOT s Performance Based Contracting Experience in Charlotte. Jennifer Brandenburg, PE State Road Maintenance Engineer July 21, 2009
NCDOT s Performance Based Contracting Experience in Charlotte Jennifer Brandenburg, PE State Road Maintenance Engineer July 21, 2009 Overview Performance Base Contracting in NC Project Scope Contract Development
More informationTAMPA BAY NEXT MAJOR PROJECTS UPDATE
TAMPA BAY NEXT MAJOR PROJECTS UPDATE Marshall Hampton, FDOT District Seven Tampa Bay Next Program Manager January 18, 2019 1 2 Program Overview Funding Priorities Fiscal Year 2018 2019 2020 2021 2022 2023
More information395 Express Lanes Project Design-Build Procurement Industry Outreach. March 23, 2016
395 Express Lanes Project Design-Build Procurement Industry Outreach March 23, 2016 INTRODUCTIONS Karl Rohrer, Head of Delivery, Transurban Susan Shaw, Regional Transportation Program Director, VDOT Sean
More informationFinal Recommendations Identification of Improvements, Strategies, and Solutions
Identification of Improvements, Strategies, and Solutions Prepared by: December 2015 TABLE OF CONTENTS 1. Introduction... 1 1 2. Freight Policy Recommendations... 2 1 3. Freight Infrastructure Recommendations...
More informationRoute 29 Solutions. October 23, 2014 Rt. 29 Project Delivery Advisory Panel Meeting
October 23, 2014 Rt. 29 Project Delivery Advisory Panel Meeting Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Viewers:
More informationRFQ Information Meeting
August 25, 2016 RFQ Information Meeting I-64 Southside Widening & High Rise Bridge Phase 1 Widen From 4 Lanes to 6 Lanes Rick Correa, PE Project Manager Jeff Roby, PE APD Project Manager and POC Agenda
More informationTransportation Investment Act (TIA) Industry Forum for Batch 3 Design Advertisement. August 22, 2014
Transportation Investment Act (TIA) Industry Forum for Batch 3 Design Advertisement August 22, 2014 Agenda Program Overview Update TIA Risk Management Solicitation Information Project Overviews TIA Overview
More informationOdd Fellows Road Interchange at US Route 29/460 and Road Improvements UPC # RFQ Information Meeting
Odd Fellows Road Interchange at US Route 29/460 and Road Improvements UPC #105515 RFQ Information Meeting Raina Rosado, PE District Project Manager Kevin Reichert, PE APD Project Manager and POC July 11,
More informationAppendix J RFP No (Addendum No. 1)
3. Current State 3.1. Overview This section evaluates SRTA s current ERP configuration environment related to the following functional areas: General Ledger Budget Procurement Project Management Contract/
More informationReconstruction Project Update
I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial
More informationOffice of Transportation Data (OTD)
Office of Transportation Data (OTD) Paul Tanner State Transp o rtatio n D ata A d m inistrato r Presentation Objectives Why do we collect data? State & Federal Code Requirements Who collects the data?
More informationVILLAGE OF BOSTON HEIGHTS 45 E. Boston Mills Road Hudson, OH REGULAR COUNCIL MEETING OF July 14, :00 PM
VILLAGE OF BOSTON HEIGHTS 45 E. Boston Mills Road Hudson, OH 44236 REGULAR COUNCIL MEETING OF July 14, 2010-8:00 PM AGENDA ROLL CALL PLEDGE OF ALLEGIANCE APPROVAL OF AGENDA MINUTES PRESENTED FOR CHANGE
More informationI-15 Corridor Reconstruction Salt Lake City, Utah. DFW Connector Dallas/Fort Worth, Texas. SH99/Grand Parkway F & G Houston, Texas
Accelerated Roadway Construction I-15 Corridor Reconstruction Salt Lake City, Utah $ 1.4 Billion 1,500 days (16 miles) I-25 T-REX Denver, Colorado $ 1.3 Billion 1,980 days (17 miles) SH130 5/6 Toll Road
More informationPRINCIPAL ENGINEER. 4. Prepare plans and studies to forecast section and division needs; implement recommendations.
PRINCIPAL ENGINEER Class specifications are intended to present a descriptive list of the range of duties performed by employees in the class. Specifications are not intended to reflect all duties performed
More informationAny discussions or marketing activities related to this specific project.
08/28/17 Posting Date UNI/FRA-NW 33 Smart Mobility Corridor Project Implementation of the Advanced Transportation and Congestion Management Technologies Deployment Program Grant Project Management Consultant
More informationBuckhead Community Improvement District
Date Posted 7/17/2018 Buckhead Community Improvement District ADDENDUM #1 Request for Qualifications To Provide Surveying, Geotechnical and Subsurface Utility Engineering (SUE) Services for the PARK OVER
More informationRE Request for FY 2018 UPWP Budget Adjustments
November 30, 2017 William Eastin Southeast Georgia Branch Chief GDOT Office of Planning 600 W. Peachtree St. NW, 5th Floor Atlanta, GA 30308 RE Request for FY 2018 UPWP Budget Adjustments Dear Mr. Easton:
More informationCOMMUNICATIONS RESTRICTIONS:
02-18-18 Posting Date SUM-SR 91 and SR 303/Ravenna Signal and Roadway Improvements PID No. 102692 City of Hudson Engineering Department Response Due Date: Friday, March 16, 2018 The City of Hudson s Engineering
More informationPlease note the following policy concerning communication between Consultants and the City of Dublin during the announcement and selection process:
01-08-19 Posting Date FRA-33-3.70 Smart Technology Connected Vehicle Roundabout Application Project PID No. 109356 City of Dublin Response Due Date: 01-24-19 Communications Restrictions Please note the
More informationPlanned Procurement Opportunities Report. August 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationDesign-Build and Design-Bid-Build
Design-Build and Design-Bid-Build Comparison of Overall Cost and Time Question: How does the total cost and time to deliver a $55,000,000 and 814 day design-build project compare to using design-bid-build
More informationPlanned Procurement Opportunities Report. August 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationSustainable Safety at WSDOT
Sustainable Safety at WSDOT Saving lives and reducing serious injuries John C. Milton, Ph.D, PE Director - Enterprise Risk and Safety Applying or Misapplying CMFs CMF Clearinghouse webinar December 11,
More informationThe Gateway Expressway FTBA Conference. February 2-3, 2017
The Gateway Expressway FTBA Conference February 2-3, 2017 256996-1 SR 686 (Roosevelt Blvd.) at CR 611 (49th St. N) PD&E 256866-1 Segment 2A 256997-1 SR 686 (Roosevelt Blvd.) from 49th St. Bridge to north
More informationCUY-480-Valley View Bridge. Matchmaker April 20, 2017 Bureau of Workers Compensation 4800 E. 131 st Street
CUY-480-Valley View Bridge Matchmaker April 20, 2017 Bureau of Workers Compensation 4800 E. 131 st Street Agenda Welcome Project Overview Prequalification & Work types Procurement Overview Matchmaker 2
More informationI-395 Reconstruction MDX SR Improvements I-95 Concrete Pavement Reconstruction
I-395 Reconstruction MDX SR 83611 Improvements I-95 Concrete Pavement Reconstruction FTBA Conference February 10, 2016 Presentation Outline Project Overview I-395 Reconstruction MDX SR 83611 I-95 Pavement
More informationTHE PROJECT. Executive Summary. City of Industry. City of Diamond Bar. 57/60 Confluence.
THE PROJECT A freeway segment ranked 6th worst in the Nation, with levels of congestion, pollution and accidents that are simply unacceptable and which have Statewide and National implications. Executive
More informationRt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016
Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb
More informationTransportation Forum Coordinator: Wendy Dyson Next Forum Meeting Date: 11/01/2017
Transportation Forum Report ACEC Georgia September 6, 2017 Location: 4th Floor GDOT Office ~ 1 ~ Transportation Forum Coordinator: Wendy Dyson Next Forum Meeting Date: 11/01/2017 GENERAL ITEMS: Welcome
More informationENGINEERING SERVICES Phase III Construction Engineering Services for the Benedictine Parkway Improvement Project
VILLAGE OF LISLE REQUEST FOR QUALIFICATIONS ( RFQ ) #1267 ENGINEERING SERVICES Phase III Construction Engineering Services for the Benedictine Parkway Improvement Project DUE BY: FEBRUARY 5, 2018 @ 11:00
More informationEngineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida
Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida November 7, 2014 SUBMITTED BY: Dewberry Bowyer-Singleton 520 South
More informationWOO-SR Feasibility Study (PID 90541) Feasibility Study Report April 22, 2011
TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 CHAPTER 1: INTRODUCTION... 5 1.1 Study Purpose and background... 5 1.2 Study Approach... 6 1.3 Study Area... 6 CHAPTER 2: DESCRIPTIONS OF ALTERNATIVES... 7 2.1
More informationMAP-21 themes. Strengthens America s highway and public transportation systems. Creates jobs and supports economic growth
MAP-21 themes Strengthens America s highway and public transportation systems Creates jobs and supports economic growth Supports the Department s aggressive safety agenda Simplifies and focuses the Federal
More informationWhittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury
Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury EAE No. 14427 http://whittierbridge.mhd.state.ma.us/ Public Meeting 12.07.11 Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury
More informationBuckhead Community Improvement District
Date Posted 7/19/2018 Buckhead Community Improvement District ADDENDUM #2 Request for Qualifications To Provide Surveying, Geotechnical and Subsurface Utility Engineering (SUE) Services for the PARK OVER
More informationWELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017
WELCOME IL 47 Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 MEETING PURPOSE MEETING AGENDA 1. Welcome/Introduction 2. Review Previous Public Involvement 3. Process/Schedule
More informationFREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013
FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS June 1, 2013 For general guidance the following information is provided as an aid to those preparing submittals in response to Design-Build solicitations.
More informationPlanned Procurement Opportunities Report. November 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationTown of Bennington, Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11)
, Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11) Request for Qualifications Construction Inspection and Testing Services Issued: January 3, 2017 Due: January 24, 2017 I. INTRODUCTION
More informationMILTON-MADISON BRIDGE REPLACEMENT
MILTON-MADISON BRIDGE REPLACEMENT Andy Barber P.E. Kevin Hetrick P.E. 1 Presentation Overview KYTC lead Environmental Study TIGER Grant INDOT lead Design Build solution Bridge Sliding Project Status Questions
More informationREQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED MAXIMUM PRICE
CAYUCOS SANITARY DISTRICT 200 Ash Avenue P.O. Box 333, Cayucos, California 93430-0333 www.cayucossd.org 805-995-3290 REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED
More informationPlanned Procurement Opportunities Report. July 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationPRE-REQUEST FOR PROPOSAL (RFP) MEETING GENERAL ENGINEERING CONSULTANT (GEC) FOR I-2/I-69C INTERCHANGE PHARR DISTRICT
PRE-REQUEST FOR PROPOSAL (RFP) MEETING GENERAL ENGINEERING CONSULTANT (GEC) FOR I-2/I-69C INTERCHANGE PHARR DISTRICT RFQ No. 21-9SDP5001 601CT0000003698 November 19, 2018 Safety Minute Purpose of Meeting
More informationI-81 Exit 114 Bridge Replacement Project RFQ Information Meeting
I-81 Exit 114 Bridge Replacement Project RFQ Information Meeting July 25, 2017 Phil Hammack, P.E. Design Project Manager Stephen Kindy, P.E. APD Division Project Manager and POC I-81 Bridge Replacement
More informationPROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California.
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES FOR THE SPARTAN COMPLEX SEISMIC UPGRADE PROJECT SAN JOSE STATE UNIVERSITY ONE WASHINGTON SQUARE, SAN JOSE, CA 95192-0010 The Trustees of
More informationWednesday, October 17, Texas A&M University College Station, Texas
Wednesday, October 17, 2012 Texas A&M University College Station, Texas Presented by Dieter Billek, P.E. Interim Section Director, Strategic Projects Division Texas Department of Transportation Legislative
More informationSH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013)
SH 183 Managed Lanes Project RFQ Q & A MATRIX #2 (June 4, 2013) No. Current language states: Project experience provided by a parent or sister company of the Lead Engineering Firm, Lead Contractor or Lead
More informationAPPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report
APPENDIX B Excerpts from the October 2002 Interstate 83 and PA Route 921 The objective for the SR 921 interchange site was to study alternatives for construction of a new interchange. There are no short-term
More informationStudy Area Roadways for Road Diet / Lane Narrowing / Reconfiguration 11/11/2016
Study Area Roadways for Road Diet / Lane Narrowing / Reconfiguration 1 Road Road Diet Road Typical Section Cross Section ~100 Curb to Curb ~78 Road Diet Moving the Curbline Road Typical Section Cross Section
More informationNancy Daubenberger, MnDOT Assistant Commissioner Engineering Services
Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services Kevin Western, MnDOT State Bridge Engineer House Transportation Policy and Finance Committee April 11, 2016 Introduction to Design
More informationExisting FAST Act Funding. Wes Bolinger FHWA LA Division Administrator
Existing FAST Act Funding Wes Bolinger FHWA LA Division Administrator Existing FAST Act Funding Build America Bureau TIGER Questions? Thank You! Goal: $1.5 trillion investment over 10 years $200 billion
More informationMAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT AUBURN EXIT 75 TOLL SYSTEM UPGRADES AND STREAM RELOCATION (MM 75.3)
MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.17 AUBURN EXIT 75 TOLL SYSTEM UPGRADES AND STREAM RELOCATION (MM 75.3) KENNEBUNK EXIT 25 TOLL SYSTEM UPGRADES (MM 25.5) WELLS EXIT 19 DIRECTIONAL BORE
More informationREQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE Memphis Cook Convention Center Renovation City of Memphis, Department of Housing and Community Development
More informationLehigh Valley Transportation Study
ITEM: IV-A Lehigh Valley Transportation Study SUBJECT: PA 33 Preservation SR 22-Belfast COUNTY... Northampton FED.-AID SYSTEM... On-NHS S.R./SEC.... 33/07M DECADE OF INVESTMENT... No A.D.T.... 25,463 CAPITAL
More informationSR 417 Extension. June 2003 INTRODUCTION AND HISTORY PROJECT SCOPE AND PURPOSE STUDY OBJECTIVE STUDY PHASES
Planning Feasibility Study June 2003 INTRODUCTION AND HISTORY The SR 417 Extension Study was a yearlong effort undertaken by Florida s Turnpike Enterprise to investigate the feasibility of a new toll road
More informationFTBA 2018 Construction Conference Major Projects Update
FTBA 2018 Construction Conference Major Projects Update Bill Jones, P.E. FDOT District 7 Director of Transportation Development 1 2 3 FUNDED PROJECTS Howard Frankland Bridge Industry Forum September 2018
More informationTown of Brandon, Vermont US Route 7 (Center Street) Bridge 114 Improvements
Town of Brandon, Vermont US Route 7 (Center Street) Bridge 114 Improvements Request for Qualifications Construction Owners Representative & Inspection Services Issued: January 11, 2018 Due: February 5,
More informationAdvanced Construction Techniques
Alaskan Way Viaduct Replacement Program Organization University of Washington Date October 20, 2011 Presentation Overview SR 99 south end viaduct replacement. Design-build contracting. SR 99 tunnel project.
More informationMinnesota Statewide Freight Bottlenecks
Minnesota Statewide Freight Bottlenecks Transportation Performance Measures Reporting for MAP21 Compliance Oct. 1, 2018 2018 Minnesota Statewide Freight Bottlenecks Report Report Prepared by: Minnesota
More informationREQUEST FOR PROPOSAL KIPDA REGIONAL FREIGHT PLAN MARCH 30, 2018
REQUEST FOR PROPOSAL KIPDA REGIONAL FREIGHT PLAN MARCH 30, 2018 1 REQUEST FOR PROPOSAL KIPDA REGIONAL FREIGHT PLAN The Kentuckiana Regional Planning and Development Agency (KIPDA), the designated Metropolitan
More informationPlease note the following policy concerning communication between Consultants and Pike County Engineer during the announcement and selection process:
01-28-19 Posting Date PIK-CR50-3.40 PID No. 108463 Pike County Response Due Date: 03-08-19 Communications Restrictions Please note the following policy concerning communication between Consultants and
More informationThe Metropolitan Transportation Plan. Public Meetings January 2016
The Metropolitan Transportation Plan for North Central Texas Public Meetings January 2016 Presentation Agenda Mobility 2040 Draft Recommendations 2016 Transportation Conformity RTC Policy Bundle Concept
More informationREPORT Condition D19 Permanent Noise Barriers
REPORT Condition D19 Permanent Noise Barriers Project Name: WestConnex New M5 Project number: 15.7020.2597 Revision date: 19/08/2016 Revision: 1 Document Approval Rev. Prepared by Reviewed by Recommended
More informationMAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0
MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.05 EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 The bid opening date is Thursday March 15, 2018 at 11:00 a.m. The following changes
More informationAir Report. Project Information PPTA/LAP. Traffic Data I-495 NORTHERN SECTION SHOULDER USE. Project Number: , C501, P101 UPC:
Air Report Project Information Project Name: I-495 NORTHERN SECTION SHOULDER USE Project Number: 0495-029-123, C501, P101 UPC: 105130 Route Number: 495 Project Limit - From: South of Old Dominion Drive
More informationREQUEST FOR QUALIFICATIONS
REQUEST FOR QUALIFICATIONS PROJECT: ISSUE DATE: October 22, 2018 ISSUED BY: INQUIRIES: SUBMISSION DEADLINE: SUBMIT TO: City of Delaware, Ohio Public Works Department, Traffic & Engineering Services 440
More informationTown of Brandon, Vermont US Route 7 (Center Street) Segment 6 Improvements NH 019-3(496) Request for Qualifications
, Vermont US Route 7 (Center Street) Segment 6 Improvements NH 019-3(496) Request for Qualifications Construction Inspection Services Issued: January 18, 2017 Due: February 8, 2017 I. INTRODUCTION The,
More informationDELAWARE RIVER JOINT TOLL BRIDGE COMMISSION EXECUTIVE OFFICES 2492 RIVER ROAD NEW HOPE, PENNSYLVANIA
CONTRACT NO. T-668A, CAPITAL PROJECT 0301A SCUDDER FALLS BRIDGE REPLACEMENT PROJECT NOTICE TO CONTRACTORS September 13, 2016 Sealed bids for Contract No. T-668A, Capital Project 0301A, Scudder Falls Bridge
More informationClick to edit Master title style I N D U S T R Y D AY O C T O B E R 1,
Click to edit Master title style I N D U S T R Y D AY O C T O B E R 1, 2 0 1 4 Welcome Nevada Governor Brian Sandoval Nevada DOT Director Rudy Malfabon, PE Goals Goals Obtain the best value for the costs
More informationOklahoma s Ports of Entry Program. Richard Andrews, Project Management Division
Richard Andrews, Project Management Division January, 2008 The Oklahoma Department of Transportation, Oklahoma Corporation Commission, and Oklahoma Turnpike Authority announce partnership to develop new
More informationPlease note the following policy concerning communication between Consultants and Pike County Engineer during the announcement and selection process:
01-14-19 Posting Date PIK-CR50-3.32 PID No. 108129 Pike County Response Due Date: 02-22-19 Communications Restrictions Please note the following policy concerning communication between Consultants and
More informationTown of Shelburne, Vermont U.S. Route 7 and Falls Road Sidewalk Installation STP BP14(5) and STP SDWK(24)
, Vermont U.S. Route 7 and Falls Road Sidewalk Installation STP BP14(5) and STP SDWK(24) Request for Qualifications Construction Inspection and Testing Services Issued: January 5, 2017 Due: February 2,
More informationDesign-Build. Authorization. Criteria Selection/Award Process. Design-Build Construction Engineering and Inspection
DESIGN-BUILD Design-Build Authorization Project Selection Criteria Selection/Award Process Warranties Design-Build Construction Engineering and Inspection Materials Acceptance DESIGN-BUILD AUTHORIZATION
More informationAir Quality Analysis Technical Memorandum
Air Quality Analysis Technical Memorandum Segment 2: State Road 400 (SR 400) / Interstate 4 (I-4) from West of SR 528 (Beachline Expressway) to West of SR 435 (Kirkman Road) Orange County (75280), Florida
More informationI-91 Viaduct Public Information Briefing
I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 9 September 13, 2017 Agenda Welcome and Presenter Introductions Update on Construction and Demolition
More informationThe Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges
The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges I. ABSTRACT Keith A. Riniker, PE, PTOE This paper presents the Folded Interchange design and compares
More informationNew Governor Harry W. Nice Memorial Bridge (US 301) Will Pines, P.E.
New Governor Harry W. Nice Memorial Bridge (US 301) Will Pines, P.E. Director of Project Development April 9, 2018 www.newnicebridge.com 1 Project Background Construction dates: March 1938 December 1940
More informationAugust 31, To Whom It May Concern:
August 31, 2017 To Whom It May Concern: The Aerotropolis Atlanta Community Improvement Districts (AACIDs) is soliciting Statements of Qualifications (RFQ) from qualified firm(s) or organization(s) to develop
More informationPROFESSIONAL CONSULTANT SERVICES REQUEST FOR QUALIFICATIONS (RFQ)
PROFESSIONAL CONSULTANT SERVICES REQUEST FOR QUALIFICATIONS (RFQ) MARCH 2018 INTRODUCTION AND BACKGROUND The City of Keller is in search of the most qualified firms to provide professional expertise and
More informationOverview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations
Overview of the Project Development Process Brian Blanchard, PE Assistant Secretary for Engineering and Operations Overall Project Development Process The time it takes to produce a project varies significantly
More information