1 National Institute of Building Sciences Provider Number: G168 Session TH1B: Utilizing Information Technology for Better Building Performance Case Study: COBie from Design to Operations Presented by: Kristine K. Fallon, FAIA Kristine Fallon Associates, Inc., Chicago January 12, 2017
2 Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non AIA members are available upon request. This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
3 Course Description This case study demonstrates that COBie can be successfully implemented in the private sector on a large scale across a broad range of facility types to achieve dramatic improvements in facility data turnover. This greenfield corporate campus consists of approximately 1.7 million square feet of Class-A improvements on a 72- acre site, including a six-story office building, several industrial buildings with multiple floors of embedded office, a climate-controlled warehouse, a parking garage, a central plant and significant site infrastructure. Eight record COBie files were generated and imported into the client s integrated workplace management system (IWMS) prior to substantial completion, allowing the FM team to query 1,600+ spaces, 1,200+ types, 14,000+ components and 8,700+ O&M documents on the first day of operations. Timely delivery of COBie data sets required active engagement by key project stakeholders over a two year period and a shared commitment to overcome hurdles, particularly in the areas of change management and data management. Collaborators included the developer, a broad range of internal client teams, architects and their subconsultants, general contractor, subcontractors, COBie and BIM consultants.
4 Learning Objectives At the end of the this course, participants will be able to: 1. Examine a new project delivery approach that builds data quality control into design and construction practices to ensure that the owner has correct and complete information to safely operate and maintain the facilities in a sustainable manner. 2. Understand the equipment data required from both the designers and the contractors that allow the Owner to determine the root causes of building systems performance failures, and how the Construction Operations to Building information exchange (COBie) standard can be deployed to make the transfer of these data from design and construction software to not only facility management systems, but to building control systems and fire alarm monitoring systems, among others.
5 FMC Technologies, Inc.: Project Greenfield 72 acre site 7 buildings 1.7 million square feet COBie, from Design to Operations, authored by Kristine K. Fallon, FAIA; George R. Farish II, LEED AP BD+C; and Danielle Gran, was published in the June 2016 issue of the Journal of the National Institute of Building Sciences (JNIBS), a publication of the Washington, D.C.-based National Institute of Building Sciences. Learn more about JNIBS at: and access your free issue(s) by subscribing at:
6 Client Goal: Load facility data into integrated workspace management system (IWMS) before occupancy using COBie Standard. Results: By Substantial Completion, loaded: 8 data sets: (7 buildings + site) 1,603 Rooms 14,177 pieces of equipment Maintenance Procedures Spare Parts Added Benefits: Construction Phase BIM coordinators found fewer problems and submitted fewer RFIs once models were fully populated with COBie data. Ability to search, export and report on building data: Allowed quick reaction to problems and requests for changes due to easy and rapid quantification and location of every equipment type Revealed missing safety equipment through COBie Punchlist reports Permitted loading of COBie equipment inventories and spare parts into 8 additional systems, saving data entry time and creating common naming Common naming allows these systems to communicate and, e.g., automatically produce work orders in the IWMS when a problem occurs
7 What is COBie? COBie: Construction to Operations Building information exchange A subset of international standard ISO Conforms to the IFC information model: IFC MVD Incorporated in the National BIM Standard US Focused on electronic delivery of data about Spaces and Equipment, not on geometric modeling Captures this information at the Source and at the Time Created
8 COBie Coverage Available COBie Tables Contact Facility Floor Space Type Component System Attributes Job Resources Spares Documents Zone Assembly Coordinate Issue Connection Impact FMC COBie Data Contact Facility Floor Space Type Component System Attributes Job Resources Spares Documents
9 COBie Benefits COBie provides a ready made framework for information turnover COBie worksheets (tables) define minimum content COBie provides a standard format for data delivery COTS products have COBie import and export capabilities
10 Project Greenfield COBie Participants Client: FMC Technologies Inc. Development Manager: Trammell Crow Houston Industrial Development Inc. BIM & COBie Consultant: Kristine Fallon Associates Inc. IWMS Configuration Team Facilities Management Team Development Management Team Architect: Gensler Civil Engineer : Cobb Fendley & Associates MEP Engineer: Wylie Consulting Engineers IT Infrastructure & Security Team Facility Data Construction Team Design Team General Contractor: D.E. Harvey Builders & Inc. COBie Coordinator & Preventive Maintenance Data Integrator: ENGworks
11 BIM & COBie Consultant Role Defining and documenting COBie requirements Developing Division 1 language Validating COBie design and construction data Generating record COBie files from merged data
12 Philosophy Achieve targeted business results Capture information at the source Make that information available to the owner and other project team members as soon as it is created Build quality control into work processes Eliminate redundant work and costly rework cycles Select and/or create technology tools that make sense to users and make their jobs easier
13 COBie Requirements and Execution Plan
14 Who Provides Product Data? As designed and specified Provided by designers As procured Provided by trade contractors As commissioned Provided by Cx Agent
15 Example: Hollow Metal Door Designer Responsibility Contractor Responsibility
16 Example: Hollow Metal Door
17 COBie Workflow 100% CD Spares Jobs Resources Design Data Product Data Manager (PDM): Data Validation & Aggregation Document Repository Merged COBie File from PDM IWMS PDM checks Documents are complete and properly named O&M Documents Contractor Product Data Forms (CPDFs) Field Technology Installation Progress Barcodes
18 Contractor Product Data Form Page 1 Designer Provided Value Units Override Designer Specification System HVAC N/A Class Variable Air Volume Devices N/A Type VAV N/A TypeName (Standard) HV VAV2 N/A Type Description HVAC Variable Air Volume Terminal Units N/A Category (OmniClass Table 23) : Single Duct Variable Air Volume Terminal Units N/A Spec Section (MasterFormat) N/A Asset Type Fixed N/A Contractor Provided Inlet Size 10 Inches Manufacturer MFlynn@hdgrant.com N/A Maximum Depth (In) 14 Inches Model Number SDV5000 N/A NominalHeight 16 Inches NominalLength 20 Inches NominalWidth 16 Inches Organizations Preferred Contact Bsellers@letsos.com N/A Pressure Drop 0.25 N/A Submittal Documents List Variable Air Volume Devices N/A Warranty Duration Labor 12 N/A Warranty Duration Parts 12 N/A Warranty Duration Unit Month N/A WarrantyGuarantorLabor MFlynn@hdgrant.com WarrantyGuarantorParts MFlynn@hdgrant.com
19 Contractor Product Data Form Page 2 Will be Provided (Y or N) Document Type Document Association Y Manufacturer Certificates Type Y Manufacturer Installation Instructions Type Y Manufacturer Test Reports Type Y Material Test Reports Type Y Materials Certificates Type Y Operations & Maintenance Manual Type Y Product Certificates Type Y Product Data Type Y Product Test Reports Type Y Shop Drawings Type Y Warranty Type Y Field Test Reports Component Y Start Up Report Component Y Test and Balance Report Component Y Spare Parts List Type
20 The Challenge BIM is a Cross-Organizational, Data-Centric approach to design and construction Much attention has been given to the Cross-Organizational aspects Little attention has been paid to the Importance or Quality of the Data
21 Process Challenges Timing COBie Execution Plan was approved at the CD stage Required rework by designers Only the Architects were using BIM Contractor Product Data Forms were not submitted as part of the regular submittal process Additional rework for both designers and contractors The IWMS had not been selected when we developed the COBie Execution Plan Naming standards needed adjustment
22 Addressing Process Challenges Project team was able to catch up and deliver data by substantial completion In the future COBie Standards and Execution Plan should be developed before modeling begins Design data should be complete and validated at the end of CDs COBie naming standards should be informed by the IWMS data structure
23 Technology Gaps and Technology Management Challenges COBie process and tools were new to everyone and therefore hard to manage Although COBie is based on the idea of capturing data throughout the project, the COBie format only supports a one time turnover of all data COBie tools provided by major technology vendors are immature There is a lack of technology tools that support collaboration on and validation of data
24 Addressing Technology Gaps and Technology Management Challenges BIM & COBie Consultant provided tools to fill the technology gaps Product Data Manager (PDM) to validate and aggregate data Accepts data from multiple applications Contractor Product Data Forms, generated from PDM, that allowed the Contractor to: Know what product data was required Know what the design intent was for that product Easily provide required data in an electronic format Two way data passing with field technology Tools for checking that all documents were submitted and named correctly COBie punch lists
25 Human Factors Challenges Need to climb the learning curve Process Tools Information centric versus drawing centric approach Rigor of standard structured data Reluctance to change established organizational methods Modeling typicals versus complete models Drawing annotation versus COBie naming Primacy of drawings versus model or data
26 Addressing Human Factors Challenges Communication, Communication, Communication Bi weekly COBie Progress Meetings Provide advice and support Provide tools to help team members gauge progress Strong contract terms provide motivation to perform Detail BIM and COBie data delivery requirements in Division 1 Six figure retainage if delivery of COBie data, documents and photographs is not up to date or if the deliverables do not conform to the requirements and standards in the COBie Execution Plan and meet the quality standards
27 Project Management Challenges Getting the data delivered on time Prioritization of activities Understanding and staffing of new roles
28 Addressing Project Management Challenges COBie progress meetings Application of Lean techniques Value Stream mapping Look Ahead Schedules Commitment Tracking Need for new project roles BIM & COBie Consultant COBie Coordinator & Preventive Maintenance Data Integrator Dedicated BIM / Data Managers in design firms Data savvy Facilities staff
29 Value Stream Mapping
30 Look Ahead Schedules
31 Commitment Tracking
32 This concludes The American Institute of Architects Continuing Education Systems Course Kristine K. Fallon, FAIA President Kristine Fallon Associates, Inc. 11 E. Adams Street, Suite 1100 Chicago, IL inc.com
COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202
COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 Gerald J. Kettler, PE, CCP, CPMP 21 st National Conference on Building Commissioning AIA Quality Assurance The Building Commissioning
More informationRFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No.
SPECIAL CONDITIONS Article I, Section A delete this paragraph in its entirety and replace it with the following language: Owner s representative to act on its behalf with respect to this Agreement shall
More informationBIM Checklist. Introduction
Introduction This Building Information Modeling (BIM) Checklist is intended to be used as a guide for project stakeholders who are looking to implement BIM/VDC in a design-build project. Since integration
More informationCommissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015
1 Commissioning at NYP Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program
More informationLean Project Delivery Operating System
Lean Project Delivery Operating System David MacNeel & Dan Passick, On Point Lean OCTOBER 16, 2017 LCI Education & Training Lean Construction Institute Provider Number H561 LCI Learning Module: Introduction
More informationState of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements. Version 1.0
State of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements Version 1.0 April 22, 2013 Table of Contents 1. Introduction...... 1 1.1. Mission of the TN OSA
More informationBIM enhances structural analysis regardless of project size. By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders
BIM enhances structural analysis regardless of project size By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders MARCH 2013 BIM enhances structural analysis regardless of project size By Jeffrey Yoders
More informationEcoDomus, Inc
www.ecodomus.com Introduction BIM Data Requirements & Guidelines COBie: Data Entry and Responsibility Matrix COBie: Quality Control BIM and BAS Integration: Use Cases Mobile BIM and Work Orders Asset View
More informationHow We Retro-Cx 4M sf in Four Months. St. Louis Green Business Challenge
How We Retro-Cx 4M sf in Four Months St. Louis Green Business Challenge Presenters David Meyers, AIA, CxA, PMP, LEED AP Manager of Commissioning Mr. Meyers is a Certified Commissioning Authority and Program
More informationUse of Commissioning for LEED Projects. H. Jay Enck President Commissioning & Green Building Solutions, Inc.
Use of Commissioning for LEED Projects H. Jay Enck President Commissioning & Green Building Solutions, Inc. AIA Quality Assurance Learning Objectives 1. Use of the commissioning process for more efficient
More informationUSGBC National Capital Region MasterClass Series: The Ins and Outs of Existing Building Commissioning Analysis Credit
USGBC National Capital Region MasterClass Series: The Ins and Outs of Existing Building Commissioning Analysis Credit Jeffrey Salay, PE, CEM, LEED AP Senior Principal 13 December 2017 GHT Limited is a
More informationCreating an IWMS Implementation Plan
Creating an IWMS Implementation Plan Overview The increased information available through an Integrated Workplace Management System (IWMS) impacts every part of an organization and can dramatically increase
More informationBuilding Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506
AABC Commissioning Group AIA Provider Number: 50111116 Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 Dan Adam, RA, CxA, Facility Commissioning Group
More informationIV.E.8 - BIM Standards
Contents 1. General... 3 1.1. Strategy & Objective... 3 1.2. Road Map... 4 2. Process... 7 2.1. Start... 7 2.2. Plan... 9 2.3. Execute... 12 2.4. Monitor... 14 2.5. Close-out... 16 3. Execution... 19 3.1.
More informationBIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER
PROJECT NAME BIM EXECUTION PLAN PROJECT INFORMATION CLIENT PROJECT NAME PROJECT NUMBER XX XXXXX XX XXXXX XXXXXXXXXXXXXXXXXXXXXXXXX DATE XXXXXXXX 2016 PROJECT LOCATION & ADDRESS XXXXX, XXXXX. INTRODUCTION...
More informationa commentary to the NBIMS-US COBie standard
The COBie Guide: a commentary to the NBIMS-US COBie standard by Dr. Bill East, PhD, PE, F.ASCE 1, Mariangelica Carrasquillo-Mangual 2 EXECUTIVE SUMMARY The Construction-Operations Building information
More informationManage Deliverables - Construction Step 6 February 2015
Manage Deliverables - Construction Step 6 February 2015 1 Construction Phase Step 1: Needs Development Step 2: Scope Development Step 3: Selection of Design Team Step 4: Design Phase Step 5: Selection
More informationInterim Turnover Check List
Page 1 of 4 Quality Control Checklist Index 01701 - Interim Turnover Check List THIS CHECKSHEET IS NOT INTENDED TO BE ALL INCLUSIVE BUT TO BE A GUIDE TO CRITICAL ISSUES AND CAUSE QUESTIONS TO BE ASKED.
More informationFull-Scope Commissioning for High-Quality Buildings
Full-Scope Commissioning for High-Quality Buildings Pieter L. van der Mersch, PE, QCxP University of Colorado Boulder 21 st National Conference on Building Commissioning AIA Quality Assurance The Building
More informationStrategic Revit MEP Object Organization From BIM to Asset Management
MEP20732 Strategic Revit MEP Object Organization From BIM to Asset Management Jorge Quiroz Director DCV Consultores Sebastian Zaje Senior Technical Specialist - LATAM Autodesk George Broadbent Director
More informationWhat Contractors Need to Know about LEED Commissioning & IAQ Management
What Contractors Need to Know about LEED Commissioning & IAQ Management Presented by Energy Ace, Inc. Wayne Robertson, PE, CxA What is Commissioning? Commissioning is a systematic process of assuring that
More informationLEED Commissioning and Actual Energy Use. John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering
LEED Commissioning and Actual Energy Use John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering AIA Quality Assurance Learning Objectives 1. Why Best Practice and Fundamental Commissioning are
More information1.0 ABOUT THE NU GUIDELINES
Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner
More informationBuilding Commissioning
Building Commissioning Roles, Responsibilities, and Benefits 2010 ASHRAE Annual Meeting CxA WORKSHOP Saturday, June 26, 2010 Jim Magee, CxA, LEED-AP Facility Commissioning Group Overview Cx Advocacy, Economics,
More informationCommissioning Lighting Control Systems
AABC Commissioning Group AIA Provider Number 50111116 Commissioning Lighting Control Systems Course Number: CXENERGY1727 Jesse Felter, SSRCx Tom Divine, P.E., SSR April 27, 2017 Credit(s) earned on completion
More informationActivation, Transition & Close Out Step 7. July 13, 2012
Activation, Transition & Close Out Step 7 July 13, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement
More informationDon't Get Lost in the Labyrinth of Supplier Cost Flows into Projects. Dina Rotem John Sasali
Don't Get Lost in the Labyrinth of Supplier Cost Flows into Projects Dina Rotem John Sasali About RAFAEL About E-Business Suite in RAFAEL RAFAEL is an Israeli company. About 5100 employees. Revenue of
More informationMinnesota State Colleges and Universities. South Central College. Request for Proposals for Commissioning Agent. STEM and Healthcare Renovation
Minnesota State Colleges and Universities South Central College Request for Proposals for Commissioning Agent STEM and Healthcare Renovation Date: 12/18/2017 ADDENDUM #1 1. The Sign-In sheet for the voluntary
More informationAttachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone #
UCF Design, Construction, and Renovation Standards Attachment 04 Substantial and Final Completion Approval Form Project Description Project # Date of Completion Permit # Phone # Intent: This Substantial
More information23/01/1438. Management of BIMProject: BIM Management Plan. Mohamed Mohsen Kamel. Prof. Dr. Emad Elbeltagi
Management of BIMProject: BIM Management Plan Cairo University, Faculty of Engineering MSc in Integrated Engineering Design Management IEDM 611: BIM for Facility Management Prepared and Presented by: Mohamed
More informationAutodesk and the UK BIM Level 2 Mandate
Autodesk and the UK BIM Level 2 Mandate BIM Level 2 Mandate The UK Cabinet Office is in the midst of a multi-year effort to reform the way in which the UK government procures construction helping to ensure
More informationBIM Design & Construction Requirements. Follow-up Seminar. September 10,
BIM Design & Construction Requirements Follow-up Seminar September 10, 2009 www.indiana.edu/~uao/iubim.html Opening Comments Two years ago Indiana University began the process of embracing the use of Building
More informationCommissioning Guide. Transportation and Works Building Design and Construction Division
Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...
More informationVolume II- Project Development Processes
Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required
More informationOptimizing BAS Information for Operator Effectiveness and Optimal Control
Optimizing BAS Information for Operator Effectiveness and Optimal Control Len Beyea, CBCxP, EBCxP, HBDP, CEM, LEED AP Principal RetroCom Energy Strategies, Inc. AIA Quality Assurance The Building Commissioning
More informationPlease comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at
Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf when using this file. Thank you. Welcome to the 5 th Meeting
More informationBuilding Information Modeling (BIM) Execution Plan
10/19/2017 for [Stanford Project Name] [Stanford Project Number] Developed by [Primary A/E] TABLE OF CONTENTS USE OF THE BIM EXECUTION PLAN... 3 1. PROJECT INFORMATION... 3 2. PROJECT SCHEDULE AND MILESTONES...
More informationThe USC School of Cinematic Arts is the oldest and largest film school in the United States. In 2006, George Lucas donated US$175 million to expand
The USC School of Cinematic Arts is the oldest and largest film school in the United States. In 2006, George Lucas donated US$175 million to expand the film school with a new 137,000 square foot facility.
More informationCx at Penn State: A Program for Every Situation
Cx at Penn State: A Program for Every Situation AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems
More informationBuilding Information Modeling to Facilities Information Management and Beyond
Building Information Modeling to Facilities Information Management and Beyond Meghan Ruffo, Thomas Koltoniak, & Geoffrey Coon Carolinas HealthCare System Join the conversation #AU2016 Class summary Carolinas
More information- DATA REQUIREMENTS BIM
UHS BIM Protocol S E C T I O N 1 - DATA REQUIREMENTS BIM authoring software: The design team is required to use parametric BIM authoring software for creation of models that include all geometry, physical
More information3D Virtual Master Campus Planning and Management
3D Virtual Master Campus Planning and Management Dr. Thomas Furlani Charles Hixon Best Practices The Eastern Regional Association of Physical Plant Administrators (ERAPPA) is a Registered Provider with
More informationLife Cycle of BIM at the Port Authority
Life Cycle of BIM at the Port Authority Presenters Denise Berger, AIA Assistant Chief Engineer Operations Division Jorge Quiroz BIM/CAD Manager Engineering Solutions Sadia Janjua, LEED AP, PSP Senior Project
More information600 - Phase C Intermediate Review Checklist for the Architect- Engineer
600 Phase C Intermediate Review Checklist for the Architect Engineer This checklist is to be used by the ArchitectEngineer during Phase C of the Project and shall be included in the Intermediate Review
More informationQualifier Process and Safety Considerations Bi-Weekly Safety Meeting July 24, 2014
Subcontractor Independent Contractor and Staffing Agency Qualifier Process and Safety Considerations Bi-Weekly Safety Meeting July 24, 2014 What to Expect Subcontractors and Staffing Representation Various
More informationBLOCKCHAINS IN CONSTRUCTION & INFRASTRUCTURE HELIUM ALLIANCE
BLOCKCHAINS IN CONSTRUCTION & INFRASTRUCTURE HELIUM ALLIANCE DISTRIBUTED DATABASES SUPPLY CHAINS, WHOLE LIFE COSTING & ASSET MANAGEMENT KEEPING COST OS UPDATED FOR NEW STANDARDS COST OS NRM 3 MODULE, RELEASED
More informationSugar factory automation and optimization. Control. Visualize. Optimize.
Sugar factory automation and optimization Control. Visualize. Optimize. Lowering energy consumption Increasing throughput Improving quality Maximizing traceability Reducing inventory cost Enabling lean
More informationNC State University OESAD GUIDELINES Contract Year
July 1, 2014 NC State University OESAD GUIDELINES Contract Year 2014-2016 I. Informal Projects A. Preface Based on the North Carolina Administrative Code (NCAC), Title 01, Subchapter 30D Section.0300 Selection
More informationOracle Prime Projects Cloud Service
Oracle Prime Projects Cloud Service Oracle Prime Projects Cloud Service is a complete, cloud-first success platform for all stages of the project lifecycle. It empowers executives, project managers, and
More informationDigital Project Administration for. Office 2 Office, LLC
Digital Project Administration for School Construction Office 2 Office, LLC Presenters Nicholas Paras - Nicholas Paras is the president of a computer services company with 20 years experience in networking,
More informationOpening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction
Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction Matthew Tunnard, PE, CCP, LEED AP, Senior Engineer Horizon Engineering Associates, LLP AIA Quality Assurance
More informationCode Compliance Alternatives for Historic Buildings
Code Compliance Alternatives for Historic Buildings A Greater Understanding of Ohio Building Code Chapter 34 2015 Heritage Ohio Annual Preservation & Revitalization Conference Presenter: Robert Vilkas,
More informationCOBie and the Demanding Client
COBie and the Demanding Client Bob Wakelam AEC3 About me Bob Wakelam AEC3 bw@aec3.com 37 years in architecture and construction 30 years in what is now called BIM Joined AEC3 UK Limited in 2010 Involved
More informationThe benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM
Page 1 of 5 The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM By Rick Oehmcke, S.E. Not that many years ago, few structural engineers
More informationAPPENDICES DESIGN REQUIREMENTS. Appendix A. Performance Criteria for Design Projects
PROVINCE OF NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND INFRASTRUCTURE RENEWAL DTIR Document DC350 APPENDICES DESIGN REQUIREMENTS Appendix A Performance Criteria for Design Projects 2010 EDITION Printed
More informationGeorge Bourassa, National Director, Commissioning Services Robert Bucey, Program Manager RETRO-COMMISSIONING
George Bourassa, National Director, Commissioning Services Robert Bucey, Program Manager RETRO-COMMISSIONING AIA Quality Assurance Learning Objectives Demonstrate global results of the analysis of energy
More informationGETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams
GETTING STARTED WITH LEAN CONSTRUCTION A guide for project teams HOW TO USE THIS DOCUMENT Outlined in this guide are foundational steps for helping project teams improve the predictability and profitability
More informationsiemens.com/simatic-it SIMATIC IT for Automotive Suppliers Answers for industry.
siemens.com/simatic-it SIMATIC IT for Automotive Suppliers Answers for industry. Automotive suppliers: A continuously changing environment A solution for effective manufacturing of automotive components
More informationFACILITIES MANAGEMENT
FACILITIES MANAGEMENT Planning, Design & Construction September 24, 2014 Re: Request for Proposals- Commissioning Services Hardin Library for Health Sciences Upgrade Building Systems # University of Iowa
More informationFIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF
ARCHITECTURE & BUILDING ENGINEERING AEC COLLECTION EBOOK FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF Get started > 01 02 03 04 05 DELIVER HIGHER- QUALITY WORK OPERATE MORE EFFICIENTLY EXPAND YOUR BILLABLE
More informationConstruction & Engineering Global Business Unit Service Descriptions and Metrics February 12, 2018
Construction & Engineering Global Business Unit Service Descriptions and Metrics February 12, 2018 Construction Engineering Service Descriptions 1 Table of Contents METRIC DEFINITIONS... 4 GLOSSARY...
More informationMedical Devices. Epicor for. Functionality. Meeting the Challenges for Medical Devices
Epicor for Medical Devices Functionality XXGlobal operations XXTraceability and quality XXCost management XXRapid configuration XXProduct lifecycle management XXRegulatory compliance XXFDA, cgmp, ISO,
More informationFundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619
AABC Commissioning Group AIA Provider Number 50111116 Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 Jim Hall, PE, TBE, CxA Systems Management & Balancing,
More informationApplied Research Briefing on KPI and Smart Cities
Applied Research Briefing on KPI and Smart Cities Calvin Kam PhD, AIA, PE, LEED AP Adjunct Professor Center for Integrated Facility Engineering, Stanford University calvin.kam@stanford.edu Founder & CEO
More informationViewpoint Construction Software Vista 6.14 Product Enhancement Brief
P a g e 1 Viewpoint Construction Software Vista 6.14 Product Enhancement Brief Packed with new enhancements, Vista 6.14 is easier to use, performs better, and now lets you work anywhere there is a Wi-Fi
More informationEnergy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort
Please add relevant logo here Energy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort Presented by: Peter J. Arsenault, FAIA, NCARB, LEED-AP Disclaimer: This presentation was developed by
More informationCITY OF CHICAGO DEPARTMENT OF BUILDINGS
CITY OF CHICAGO DEPARTMENT OF BUILDINGS GUIDELINES FOR THE PREPARATION OF REQUESTS FOR QUALIFICATIONS FOR THE SELECTION OF CONSULTING FIRMS TO PERFORM LIFE SAFETY EVALUATIONS The Chicago Department of
More informationWhy Projects Excel? The Business Case for Lean Construction
California Communities of Practice June 14-152017 Why Projects Excel? The Business Case for Lean Construction John Pemberton Lean Construction Institute Bevan Mace, Ph.D. National VP, Operations & Lean
More informationCommissioning Electrical Systems: An Expansion of LEED
Commissioning Electrical Systems: An Expansion of LEED IEEE-SF-IAS April 26, 2011 by Rick Miller, PE, LEED AP RNM Engineering, Inc. San Luis Obispo, CA Outline LEED commissioning. What clients are actually
More informationBack to Where We Once Belonged FM Global s road to SlimBIM
Back to Where We Once Belonged FM Global s road to SlimBIM By Thomas A. Gay Assistant Vice President FM Global - Engineering Plan Services Past Chair Board of Direction buildingsmart alliance Vice Chair
More informationPre-Construction Meeting Minutes
Project Name Project # Project Address Tel: Fax: Gilbane Building Company Pre-Construction Meeting Date Start End Next Meeting Next Time Prepared By Company Purpose Location Next Location General Notes
More informationBronx Mental Health Redevelopment Project
Bronx Mental Health Redevelopment Project Residential Village Bronx Campus Transitional Living Residences, Haven House Horizon House, and Studio Apartments BIM Orientation December 20, 2012 1 Bronx Mental
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationRice University Ancillary Furniture Request for Proposal February 14, 2017
Rice University Ancillary Furniture Request for Proposal February 14, 2017 Contents Project Background Information Project Profile... 04 Project Location... 05 Schedule... 06 Dealer Responsibilities and
More informationHow to Transition to a Paperless Construction Company Your Blueprint to Digital Transformation
Quickstart Guide How to Transition to a Paperless Construction Company Your Blueprint to Digital Transformation No matter which solution you choose, going digital will help reduce risk, increase ROI, and
More informationNAVFAC SOUTHWEST / OICC MCIWEST. World Class Construction Forum Commissioning
NAVFAC SOUTHWEST / OICC MCIWEST World Class Construction Forum Commissioning 17 August 2011 Agenda 0830-0845: Welcome Aboard & Forum Introduction 0845-0900: Commissioning 0900-1015: Commissioning Lessons
More informationErrata Sheet. LEED for Schools Reference Guide First Edition for the document titled:
Errata Sheet for the document titled: LEED for Schools Reference Guide First Edition 2007 Notes: Updates to this document are posted on the LEED for Schools Rating System page and the Reference Guide electronic
More informationNet Zero Building Commissioning. Phillip Saieg, CEM, LEED AP O+M Josh Harwood
Net Zero Building Commissioning Phillip Saieg, CEM, LEED AP O+M Josh Harwood AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects
More informationCommissioning: What Architects Need to Know
Commissioning: What Architects Need to Know Rino Zan P.Eng., Morrison Hershfield Ltd. rzan@morrisonhershfield.com Ontario Association of Architects May 12 & 13, 2016 Commissioning: What Architects need
More informationNational Institute of Building Sciences. Paul Totten, PE, LEED AP Vice President, National Practice Leader, Building Enclosures
National Institute of Building Sciences Provider Number: G168 Design Considerations for Climate Change Session TU1A Paul Totten, PE, LEED AP Vice President, National Practice Leader, Building Enclosures
More informationIntroduction. ED02 White Paper Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff 1
Building Enclosure Commissioning as Part of LEED V4 Total Commissioning Package Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff Learning Objectives:
More informationBuilding Foreman s Workface Packages. WFP Conference 2010 Calgary, Alberta December 1, 2010
Building Foreman s Workface Packages WFP Conference 2010 Calgary, Alberta December 1, 2010 Introduction to FIWP Planning Plan the Work Release the Work Work the Plan Dedicated Planner Supervisor Materials
More informationMBCx: The Next Wave of Energy Savings in Utility Incentive Programs
AABC Commissioning Group AIA Provider Number 50111116 MBCx: The Next Wave of Energy Savings in Utility Incentive Programs Course Number: CXENERGY1716 Walid Guerfali, ComEd Ben Talbot, DLR Group Ruairi
More informationAddendum #02 New County Office Building Responses to RFP Questions
Sam Lin Manager Project Development Unit 1402 Maple Street Redwood City, CA 94063 650-369-4766 September 22, 2017 slin@smcgov.org Addendum #02 New County Office Building Responses to RFP Questions To All
More informationStreamline: Progressions in Product Compliance (Part 1 of 4)
Intertek 70 Codman Hill Road Boxborough, MA 01719 icenter@intertek.com 1-800-WORLDLAB www.intertek.com Chapter 1: Faster, Better, More Now Faced with adversity, resourceful manufacturers often find or
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Bishop Woods Landscape Restoration Response
More informationComputerized Maintenance Management System
Computerized Maintenance Management System The PSCS Computerized Maintenance Management System is a Windows based client-server application that is easy to learn, easy to understand and easy to use. PSCS
More informationTripla ensures sustainable growth and expansion for Helsinki
Tripla ensures sustainable growth and expansion for Helsinki Main image place OPEN BIM helps the development of this gigantic mixed use project in Helsinki, Finland. Project name: Tripla Location: Helsinki,
More informationStage: A Case Study. Course Description. Learning Objectives
Arena Stage: A Case Study Brought to Lifeto The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES), Provider #G516. Credit(s)
More informationThe National BIM Library
The National BIM Library BIM Object Guide: Platon Plaster Base Version 1.0 3 rd December 2012 www.nationalbimlibrary.com Version 1.0 3 rd December 2012 Page 1 of 9 Table of Contents 1.0 Introduction...
More informationThe Basics of ITIL Help Desk for SMB s
The Basics of ITIL Help Desk for SMB s This three-step process will provide you the information necessary to understand ITIL, help you write your strategic IT plan and develop the implementation plan for
More informationUnit Substation Transformer Construction Checklist (under 500 kva)
Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.
More informationMUD V.1. BIM-M Technology. masonry. Unit Database. Central RDBMS (Relational Database Management System)
BIM-M Technology Reveling in the Joys of MUD Imagine thousands of masonry colors, textures, finishes, shapes and sizes to design with all contained in BIM-M's Masonry Unit Database Data Input Data Storage
More informationMICROSOFT DYNAMICS GP. Product Capabilities and Business Ready Licensing Module Guide. Solutions
MICROSOFT DYNAMICS GP Product Capabilities and Business Ready Licensing Module Guide Solutions Become a Dynamic Business with Microsoft Dynamics GP For more than 25 years, Microsoft Dynamics GP has delivered
More informationElectronics and High Tech
Epicor for Electronics and High Tech Functionality XXSupports Global operations with comprehensive multisite capabilities XXDemand Planning and Forecasting to minimize obsolescence XXEmbedded robust quality
More informationCOST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL
SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,
More informationA Process for Data Requirements Analysis. David Loshin Knowledge Integrity, Inc. October 30, 2007
A Process for Data Requirements Analysis David Loshin Knowledge Integrity, Inc. loshin@knowledge-integrity.com October 30, 2007 1 Agenda The criticality of business information Data requirements analysis
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationFacilities Management. FM Key Performance Indicators
Facilities Management FM Key Performance Indicators September 21, 2017 Facilities Management Key Volume Indicators Key Volume FM Change Evanston Chicago Full Time Equivalent (FTE) 369 +5 304 65 Acres 296
More information