Completion of the new Operating Theatre Block

Size: px
Start display at page:

Download "Completion of the new Operating Theatre Block"

Transcription

1 Completion of the new Operating Theatre Block

2

3 The new theatre block was formally opened on 29 August This was a major building project, which took approximately 28 months to complete (from May 2010 to August 2012), and involved employment of approximately 35 local workers. The theatre block was designed to provide facilities lacking at the hospital, which had been built in Some of the problems identified which lead to the development of the new theatre block included a) Having only one operating theatre. This caused a problem when major operation was being performed and another patient requiring emergency surgery (usually a caesarean section) presented. Although we had developed a system for transforming the delivery suite into an emergency theatre room, a more permanent solution was needed. b) The theatre built in 1956 was clean, and was adequate for most of the operations being performed. However the tendency for dust to come through the ceiling meant that it was not sterile enough to safely insert foreign bodies such as plates and rods (for orthopaedic surgery after difficult fractures) or shunts (for hydrocephalus). In these operations any contamination during surgery will cause infection, often with disastrous results. This meant that it was safest to avoid doing these operations. c) Again the wards were adequate for most patients. However when a patient was very sick and needed extra care, it was difficult to provide such care in the wards. The short term solution had been to look after very sick patients in the nursing station. There therefore needed to develop a well equipped and monitored high dependency unit to help medical and nursing staff to look after the sickest patients in the hospital. d) There was also a significant shortage of storage space around the hospital. This meant that medical equipment which should have been in the hospital was often stored in containers. At times this lead to problems medical items such as monitors collecting too much dust (it is impossible to keep dust out of your house in Africa!) e) There was no hospital chapel, and no space inside the hospital for running functions, or for staff education. f) There was a shortage of office space in the hospital g) There was a need to help modernise and upgrade the hospital. The new theatre block therefore includes three operating theatres, sterilising rooms, three storerooms, staff changing areas, a tearoom, a 7-bed high dependency unit, two offices and staff toilets and a hospital chapel/ education room seating up to 200 with integral kitchen facility. The initial donation from Beit Trust of UK 50,000 provided the impetus and financial funding needed to start the project. However as is often the case the cost of such a large project is often larger than the initial estimated budget. In this context we would like to acknowledge many other groups and people whose donations made the completion of this project possible. These included generous donations from Medical Missionary News, Echoes of Service, CMML USA and MSC Canada, plus donations from many other church groups and individuals worldwide. Producing finished dust-free Operating theatres required a higher standard of building than previous Kalene building projects, such as extra sealing above and below the ceilings to stop dust. The high quality finish was made possible by UK missionary Paul Hannay who ran and supervised the completion of the project. Without his commitment and expertise over the last three years: including in the planning, ordering of equipment and the leadership of the work,

4 this project would not have been possible. The local building staff and those who supervised the work at critical times, such as Gordon McKillop, (welding the trusses) and Brass Tacks workers from the UK deserve special thanks. Design: while the initial sketches were drawn up by Paul Hannay, Richard Reed and John Woodfield, the formal plans were drawn up by David Thorpe a building engineer and a volunteer with Brass Tacks in the UK. The theatre block was planned to be a T shape with the theatres being in the horizontal limb and the high dependency unit and the chapel in the vertical limb of the T. This was placed into the open quadrangle between women s ward and maternity. As all the internal walls in the horizontal limb (including the theatres) were based on plasterboard and were not designed to carry weight this meant that all of the weight of the roof, which was 15m wide, would be supported on the outside walls. Sam Philip engineering company helped with the design of the roof. Foundations Digging and laying the foundations was commenced in May The channels for laying the foundation under the walls were dug using only manual labour, with picks, shovels and wheel barrows. As we had only two concrete mixers the foundation area had to be divided into about eight areas, with each area being laid as a separate slab, thus creating expansion joints. The whole area inside each slab had to be reinforced with mesh and filled completely with concrete, and the concrete surfaced had to be rubbed up before any of the concrete dried out. Supervision was provided by Brass Tacks, mainly by Colin Breeze, Paul Dodds and Jim Smith.

5 Walls As the external walls provided all the structural strength for the roof, special attention was paid to the quality of the bricks and the walls were reinforced by the use of a ring beam. The bricks, which were designed to fit in with the surrounding hospital brick work, were produced locally. This therefore provided local employment and was a cost saving measure. Mr Kasongu Muke who supervised the purchasing of bricks. Mr Jim Smith helped with the supervision of the brick work. At the height of the work of laying bricks there were 10 bricklayers at work. Roofing Gordon McKillop (from Nyangombe) provided much needed expertise and supervision with the production and placement of the 18 steel roof trusses and Robert Woodhouse from Brass Tacks came out to help and supervise the roofing. Forty-two tonnes of steel and roofing went into this construction. This part of the project was perhaps the most technically demanding, and we are particularly grateful to those who helped. A triangular jig was built to act as a template for the formation of the trusses. Once one side of the metal truss was welded, a group of approximately 30 workers would lift the truss off the jig, and turn it over and then place it back on the jig so that the second side could be welded. [Picture of truss being turned] Once all the trusses were completed a small truck with a crane to lift the ½ tonne truss was provided by Ross Ferguson (Zengamina Hydro and NWZDT North West Zambia Development Trust). This was used to help place the trusses in position, which were then welded in place. Each truss was then joined with C section channel to support the 8M long IT roof sheets. The placement of the roofing sheets was not without risk because of the height involved. There was initially some resistance from local staff to wearing a safety harnesses, but this improved after visiting a paraplegic man in the hospital who had fallen out of a tree. We are thankful that there were no accidents.

6

7

8 Internal work hanging ceiling, painting, floor tiles, walls and finishing. This part of the project was supervised by Paul Hannay. Extra sealing of the roof was provided by foil-backed 12mm taper edged plasterboard (tin foil) attached to metal hangers and rails, and by plastering the joints and painting below the hanging ceiling. Ceramic tiles were used in the floors of the theatres and high dependency unit with the help of Paul Dodds and Gavin and Adam Martin from NI. Thermoplastic tiles were used in the offices, toilets and in the chapel. Wiring, plumbing and tubing for the anaesthetic machines and power tools were brought through the roof space and into the plasterboard walls before the walls were sealed, by plastering the taper edged joints. Shelving in the three large storage areas was built by Paul and his co-workers. The shelving in the theatres, which was make out of melamine faced chipboard and glass doors were fitted in front of the selving which was incorporated into the plasterboard walls. The medical air compressors and air conditioners were stored in a small room next to the theatre block, with positive pressure and compressed air being brought into the theatres though the roof space ducts and pipes.

9

10 Preparations and opening day Once everything was in place all the equipment from the old theatre and from a number of containers was moved into the new operating theatre block complex. The new storage areas were particularly useful, with space for storing the image intensifier, laparoscopic tower and disposable medical and surgical equipment, and the electronic equipment store room enabled all the electronic medical equipment, spare parts and manuals to be brought together in one room. Beds were moved into the HDU and a medical library was moved into the theatre tearoom. Following the first theatre list on Tuesday 28 th of August the opening ceremony was held the next day. This was attended by local dignitaries including the chiefs, district and provincial health directors and the District Commissioner for the Ikelenge District.

11

12 The completion of the theatre complex has equipped the hospital to perform a major operation and a caesarean section at the same time, has provided an environment where sterile procedures can be safely performed, has provided an area where electronic medical equipment can be safely stored, and includes a high dependency ward where sick patients can be closely monitored. It is our prayer that this complex will help the hospital to both attract and retain well trained medical and nursing staff who will be able to use the facility to its full potential, and that this will in turn help with the future development of the hospital

The Otji-Toilet self builder manual The Clay House Project Otjiwarongo

The Otji-Toilet self builder manual The Clay House Project Otjiwarongo - - The Otji-Toilet self builder manual The Clay House Project Otjiwarongo - 2 - The Otji-Toilet self builder set Your self builder set consists of following material 1 Lid box with following parts a)

More information

Building Elements. Roof Wall. Slab/beam. Superstructure. Column. Basement. Substructure. Foundation

Building Elements. Roof Wall. Slab/beam. Superstructure. Column. Basement. Substructure. Foundation Development Process Learning Objective Understand the development process describe the roles and function of the construction team explain the communication means and essential documents for the development

More information

GRADE 11 NOVEMBER 2011 CIVIL TECHNOLOGY

GRADE 11 NOVEMBER 2011 CIVIL TECHNOLOGY Province of the EASTERN CAPE EDUCATION NATIONAL SENIOR CERTIFICATE GRADE 11 NOVEMBER 2011 CIVIL TECHNOLOGY MARKS: 200 TIME: 3 hours This question paper consists of 10 pages. 2 CIVIL TECHNOLOGY (NOVEMBER

More information

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION SECTION 21 05 00 COMMON WORK RESULTS FOR FIRE SUPPRESSION PART 1 - GENERAL 1.1 SUMMARY A. This section supplements all sections in this division, including pipe, fittings, valves, and connections for sprinkler

More information

The International Committee of the Red Cross

The International Committee of the Red Cross The International Committee of the Red Cross WATER & HABITAT DEPARTMENT Rozhawa / Hospital / Rehabiliation Phase II Rozhawa Hospital / Erbil City / Erbil 25 - February - 217 Rozhawa / Hospital / Rehabiliation

More information

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017 Premier Inn, Wilson Street, Middlesbrough, TS1 1AE Site progress report February 2017 Site set up Currently 4 weeks in to the build the site has been cleared and hoardings have been erected. Welfare cabins

More information

Renovation instructions

Renovation instructions ! 1(13) Renovation instructions The purpose of these instructions is to inform you of the things to consider when renovating an apartment. You can avoid many possible problems and additional costs following

More information

Quality specifications for my home

Quality specifications for my home Quality specifications for my home by 7 Benefits of a dospuntos home 2 Quality specifications Casa Banderas 01 02 Outside: Before you go in: Façades Your home will have a ceramic brick façade finished

More information

PROGRESS JAIPUR PH-II AS ON 20 JULY 2018

PROGRESS JAIPUR PH-II AS ON 20 JULY 2018 1. Mobilisation of manpower and material is progressively improving at site. The present labour strength is 345 and will progressively increased to 400 plus by end Jul 18. 2. Progress of Work:- The following

More information

SPOT THE SKILLS JOB DESCRIPTION CARDS

SPOT THE SKILLS JOB DESCRIPTION CARDS SPOT THE SKILLS JOB DESCRIPTION CARDS 1 Ceiling fixers Ceiling fixers specialise in fitting suspended ceilings. These are ceilings that are designed to hide wiring and pipework, as well as heating or air-

More information

PROGRESS REPORT NAMILANGI SCHOOL PROJECT PHASE III

PROGRESS REPORT NAMILANGI SCHOOL PROJECT PHASE III ZAMBIA OFFICE PROGRESS REPORT NAMILANGI SCHOOL PROJECT PHASE III December,2016 1 P a g e BACKGROUND In 2014, Lions Aid Norway (LAN) in partnership with Lions District 413, Zambia embarked on a project

More information

Click on the following link for more information and to review the complete WSIB OPM.

Click on the following link for more information and to review the complete WSIB OPM. The following is an excerpt from the Workplace Safety Insurance Board (WSIB) Operational Policy Manual (OPM): Employer Obligations Guideline for determining the labour portion of the contract. Click on

More information

Classic Living INCLUSIONS

Classic Living INCLUSIONS INCLUSIONS All construction to National, State and local building codes Brick Veneer construction with iron or tiled roof Engineers soil test and site assessment Contour Survey Engineers slab design Timber

More information

LUXURY LOG CABINS. Built under caravan regulations act 1960, 1968 Amendment 2006 BS VAT Zero rated 701/20

LUXURY LOG CABINS. Built under caravan regulations act 1960, 1968 Amendment 2006 BS VAT Zero rated 701/20 CARPENTRY & CONSTRUCTION LUXURY LOG CABINS Built under caravan regulations act 1960, 1968 Amendment 2006 BS 3632-2005 VAT Zero rated 701/20 Building Regulation 2010 Intro All the cabins built by PG Carpentry

More information

PRESENTATION CENTER SURREY, BC CANADA

PRESENTATION CENTER SURREY, BC CANADA PRESENTATION CENTER SURREY, BC CANADA 1 VIEW OF THE PROPOSED OPTIMA 3 TOWERS (AFTER OBTAINING THE HIGH DENSITY THAT IS UNDER STUDY) ALONG WEST WHALLEY RING ROAD 2 3 IHI WILL BUILD THE OPTIMA PRESENTATION

More information

Introduction. A publication by Aquamor

Introduction. A publication by Aquamor Introduction Very large numbers of family owned wells have been built in Zimbabwe. This number far exceeds 100 000. In almost every case the family itself has excavated the well and in many cases also

More information

Interiors Sources Decor LLC. Method Statement BLOCK WORK. Civil Works 6/26/2016

Interiors Sources Decor LLC. Method Statement BLOCK WORK. Civil Works 6/26/2016 Method Statement BLOCK WORK Civil Works 6/26/2016 The purpose of this Work Method Statement for Block Works (Concrete Masonry Units) is to outline and describe in detail the procedure such as setting and

More information

Chapter 13 - Finish Framing

Chapter 13 - Finish Framing Chapter 13 - Finish Framing Contents Chapter 13 - Finish Framing... 13-1 Timing & Prerequisites... 13-2 Remove Bottom Plates in Doorways... 13-2 Post LVLs and Girder Trusses... 13-2 Install Framing for

More information

Project Specifications

Project Specifications Project Specifications Unit 1, 2 & 3 / 1 Carmen Street, NEWPORT These specifications form part of the building contract. The owner shall therefore ensure that the project specifications are fully and accurately

More information

GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY

GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY Province of the EASTERN CAPE EDUCATION NATIONAL SENIOR CERTIFICATE GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY MARKS: 200 TIME: 3 hours *CVLTDM* This question paper consists of 13 pages, including 3 answer

More information

HOME & LAND $946,000 LOT 155 THE HILLS ESTATE BOX HILL BRONTE 182

HOME & LAND $946,000 LOT 155 THE HILLS ESTATE BOX HILL BRONTE 182 LOT 155 THE HILLS ESTATE BOX HILL BRONTE 182 FACADE IS AN ARTIST IMPRESSION ONLY. SOME VARIATION TO WINDOW POSITIONS, MATERIALS USED AND COLOURS MAY BE REQUIRED. PLEASE SEE DRAWINGS AND INCLUSIONS FOR

More information

REPORT OF BUILDING INSPECTIONS TECOLUCA, EL SALVADOR. Prepared by: Global Village Engineers

REPORT OF BUILDING INSPECTIONS TECOLUCA, EL SALVADOR. Prepared by: Global Village Engineers REPORT OF BUILDING INSPECTIONS TECOLUCA, EL SALVADOR Prepared by: Global Village Engineers 23 JANUARY, 2001 23 January 2001 Senor Carlos Cortez Hernandez Alcaldia Municipal de Tecoluca San Vicente, El

More information

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16 New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16 Date: March 1, 2010 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org More and more

More information

GMS Composite Ltd. Shardagonj, Kashimpur,Gazipur,Bangladesh ( , ) 22 March 2014

GMS Composite Ltd. Shardagonj, Kashimpur,Gazipur,Bangladesh ( , ) 22 March 2014 GMS Composite Ltd. Shardagonj, Kashimpur,Gazipur,Bangladesh (23.968661, 90.296963) 22 March 2014 1 2 Observations 3 Highly stressed columns Cursory calculations indicate that the working stresses of columns

More information

The Alcalá Residential Development combines the peace and quiet of a residential area with the convenience of living in the city.

The Alcalá Residential Development combines the peace and quiet of a residential area with the convenience of living in the city. Your new life starts here In Parque Almunia, one of the areas in Granada with the most growth, Inmobiliaria Osuna is building a development for you that is unique in its specifications, amenities, location

More information

LOT 25 Blueleaf Place. Brookfield $511,879 SUMMARY

LOT 25 Blueleaf Place. Brookfield $511,879 SUMMARY RENDERS ARE INDICATION ONLY Home size 27sq Land Size 512m2 LOT 25 Blueleaf Place Brookfield 5 2 2 $511,879 SUMMARY Land Price: $219,000 House Price: $292,879 (Fixed Price) Land Size: 512m2 House Size:

More information

LATRINE CONSTRUCTION SHELTER. Pour flush latrine 2. Pour flush micro septic tank 3. Initial investment, location, human resources 4.

LATRINE CONSTRUCTION SHELTER. Pour flush latrine 2. Pour flush micro septic tank 3. Initial investment, location, human resources 4. LATRINE CONSTRUCTION Pour flush latrine 2 Pour flush micro septic tank 3 Initial investment, location, human resources 4 Concrete rings 5 Box 6 Cover 7 Slab and ceramic pan 8 Ring mold 9 Structure and

More information

July 1, Houston Construction Leader:

July 1, Houston Construction Leader: July 1, 2016 Houston Construction Leader: As a member of an association and an employer in the Houston area, you and your employees are critical to a healthy and thriving economy. Taking a few minutes

More information

Construction Price Survey Form

Construction Price Survey Form International Comparison Program [04.05] Construction Price Survey Form 3 rd Regional Coordinators Meeting October 21-22, 2010 Washington DC Table of Contents 1. Form... 3 2. Purpose of the survey... 3

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Inclusions FRAMING GARAGE FIXED SITE COSTS & CONNECTIONS EXTERNAL. 90mm pine wall frames with stabilised pine roof trusses

Inclusions FRAMING GARAGE FIXED SITE COSTS & CONNECTIONS EXTERNAL. 90mm pine wall frames with stabilised pine roof trusses Inclusions FRAMING 90mm pine wall frames with stabilised pine roof trusses GARAGE Brick veneer garage including sectional overhead door to front (garage size product specific) Painted fibrous cement sheet

More information

1. FOUNDATIONS AND STRUCTURE

1. FOUNDATIONS AND STRUCTURE 1. FOUNDATIONS AND STRUCTURE A. Foundations to engineers design and specification. B. Concrete surface beds to engineers design and specification. C. Suspended concrete slabs to engineers design and specifications.

More information

SAVANNAH HILLS. DOUBLE STOREY SPECIFICATIONS - TYPE D (N) 186m² & D (S) 191m²

SAVANNAH HILLS. DOUBLE STOREY SPECIFICATIONS - TYPE D (N) 186m² & D (S) 191m² SAVANNAH HILLS Updated 14/11/2016 DOUBLE STOREY SPECIFICATIONS - TYPE D (N) 186m² & D (S) 191m² 1. Preliminary and General Engineers certificates for all slabs N H B R C Registration Geological engineer

More information

Temecula Medical Center Temecula, CA

Temecula Medical Center Temecula, CA Temecula Medical Center Temecula, CA Technical Assignment #2 Sean F. Beville The Pennsylvania State University Architectural Engineering Structural Option Senior Thesis Project Student Advisor: Thomas

More information

REHABILITATION OF DOLOW ORIENTATION CENTRE

REHABILITATION OF DOLOW ORIENTATION CENTRE REHABILITATION OF DOLOW ORIENTATION CENTRE Reintegration and Durable Solutions Sheet No. Content G-01 Index Sheet A-01 A-02 A-03 A-04 A-05 A-06 A-07 A-08 3D-01 3D-02 3D-03 3D-04 3D-05 Existing Site Plan

More information

Contracted Scope ABC of the Carolinas Excellence in Construction Awards Carolinas HealthCare System CMC Kitchen Healthcare.

Contracted Scope ABC of the Carolinas Excellence in Construction Awards Carolinas HealthCare System CMC Kitchen Healthcare. Contracted Scope Provide a detailed description of your scope for this project. Responses should include: type of construction; size of project; contract value; length of project; and percentage of labor

More information

5.0 BUILT FEATURES 5.5 AUDITORIUM (ASSEMBLY ROOM)

5.0 BUILT FEATURES 5.5 AUDITORIUM (ASSEMBLY ROOM) 5.5 AUDITORIUM (ASSEMBLY ROOM) auditorium for presentations, seminars with projection room behind east wall access behind west wall (stage wall) to basement stairs and exterior 6 rubber base 1/4 mahogany

More information

M7 Shelving for picking. for medium and heavy loads

M7 Shelving for picking. for medium and heavy loads M7 Shelving for picking for medium and heavy loads Storage system for manual picking of products following the man-togoods principle. Its main benefits are: - Possibility of storing medium to heavy loads.

More information

STRUCTURAL ASSESSMENT SURVEY REPORT

STRUCTURAL ASSESSMENT SURVEY REPORT Level 6, River Park House, 225 High Road, Wood Green, London N22 8HQ Tel: 020 8489 5504 Fax: 020 8489 5229 Email: building.control@haringey.gov.uk www.haringey.gov.uk Head of Building Control Robert McIver

More information

Estimate FOR THE SEPTIC TANK

Estimate FOR THE SEPTIC TANK Estimate FOR THE SEPTIC TANK S.NO ITEM DESCRIPTION. 1 Excavation in soil,soft & hard murum... Qty UNIT Rate Excavation for footing, machine foundation, plinth beams, wall footing, gutters,brick wall, tanks

More information

Renovation Progress. May 12 18, Week 32

Renovation Progress. May 12 18, Week 32 Renovation Progress May 12 18, 2012 Week 32 May 12 Furring strips along back wall of Sisters new Dining Area completed; projection room holes to be covered up when sheetrock is installed May 12 Another

More information

TENDER DOCUMENT PART-II

TENDER DOCUMENT PART-II NATIONAL BANK FOR AGRICULTURE AND RURAL DEVELOPMENT TAMILNADU REGIONAL OFFICE TENDER DOCUMENT PART-II (PRICE BID) RENOVATION OF SENIOR OFFICERS CABIN AT NABARD REGIONAL OFFICE NUNGAMBAKKAM CHENNAI-34 ISSUED

More information

GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA. N$2.00 WINDHOEK - 3 September 2008 No. 4115

GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA. N$2.00 WINDHOEK - 3 September 2008 No. 4115 GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA N$2.00 WINDHOEK - 3 September 2008 No. 4115 CONTENTS Page GOVERNMENT NOTICE No. 224 Declaration of registered collective agreement relating to employers and

More information

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES. Chapter 10

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES. Chapter 10 CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES 283 Chapter 10 FUNCTIONAL REQUIREMENTS FUNCTIONAL REQUIREMENTS 10.1 PLASTERWORK Workmanship i. All workmanship must be within the tolerances

More information

Stages of building a house

Stages of building a house Stages of building a house 1. Site Preparation 10. Tiling 2. Foundation 11. Painting 3. Framework 12. Aluminium Doors & Windows 4. Brickwork 13. External Wall Finishes 5. Plastering 14. Carpentry Reinforcing

More information

KOOKABURRA HOMES BRICK HOMES. Standard Inclusions. kookaburrahomes.com.au

KOOKABURRA HOMES BRICK HOMES. Standard Inclusions. kookaburrahomes.com.au KOOKABURRA HOMES Standard Inclusions BRICK HOMES kookaburrahomes.com.au 1 KOOKABURRA HOMES STANDARD INCLUSIONS PLANNING AND GENERAL WORKS Fixed price contract 3 month maintenance period Council application

More information

Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities. for LOCATED AT PRIMARY & SECONDARY SCHOOL.

Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities. for LOCATED AT PRIMARY & SECONDARY SCHOOL. Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities for SIX CHAMBER VIP LATRINE FACILITY LOCATED AT PRIMARY & SECONDARY SCHOOL YEI RIVER COUNTY South Sudan JUN,

More information

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK ND AND 3 RD FIX FINISHES

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK ND AND 3 RD FIX FINISHES CONTENTS 10.1 PLASTERWORK 10.2 2 ND AND 3 RD FIX FINISHES FUNCTIONAL REQUIREMENT 10.1 Plasterwork Workmanship Design Technical Manual TS-011-09-010412 i. All workmanship must be within defined tolerances

More information

Saraswathi. Floor Plans

Saraswathi. Floor Plans 1 / 15 Saraswathi Saraswathi is situated in a posh yet serene locality in Besant Nagar, a stone s throw away from Elliots Beach. The property covers 3 grounds and houses 8 apartments in a spacious 3 BHK

More information

Preventing Electrocutions:

Preventing Electrocutions: SAFETY CORNER Preventing Electrocutions: While Working with Scaffolds Near Overhead Power Lines Warning! Workers may be electrocuted when erecting, moving, or working from metal or conductive scaffolds

More information

What can I do with a bag of cement (Start simple and upgrade for toilets and wells)

What can I do with a bag of cement (Start simple and upgrade for toilets and wells) What can I do with a bag of cement (Start simple and upgrade for toilets and wells) Peter Morgan 2016 Introduction Start simple and upgrade over time sounds to me like a good idea. It s a method which

More information

COURTYARD INFILL STRUCTURE DESIGN

COURTYARD INFILL STRUCTURE DESIGN COURTYARD INFILL STRUCTURE DESIGN Executive Summary The existing design for the courtyard within the G wing is for a cast-in-place concrete structure. The design being proposed within this analysis is

More information

SIMULATED OFFICE PROJECT 2008 TECHNICAL REPORT

SIMULATED OFFICE PROJECT 2008 TECHNICAL REPORT SIMULATED OFFICE PROJECT 2008 TECHNICAL REPORT NEW FACILITY FOR ADULT BASIC EDUCATION AND VOCATIONAL TRAINING By Leigh Hartl Student Number: 207514952 A Report Submitted in Partial Fulfilment of the Requirements

More information

Construction and the Built Environment Level 2 Unit 4: Create the Built Environment: Structures Thursday 20 May 2010 Afternoon Time: 1 hour

Construction and the Built Environment Level 2 Unit 4: Create the Built Environment: Structures Thursday 20 May 2010 Afternoon Time: 1 hour Write your name here Surname Other names entre Number dexcel Principal Learning onstruction and the uilt nvironment Level 2 andidate Number Unit 4: reate the uilt nvironment: Structures Thursday 20 May

More information

Water for the World. 7 y

Water for the World. 7 y Water for the World For effective water storage and water system operation, ground level storage tanks should be built for sufficient, and even excess, capacity and must be watertight to prevent leakage.

More information

Our standard inclusions.

Our standard inclusions. Our standard inclusions. We pride ourselves on offering you certainty on a fixed price that includes everything you need in your new home. Before you make a final choice on your new home, check that all

More information

Construction Details 5-37

Construction Details 5-37 5-37 5-38 Construction Details 5-39 5-40 Construction Details 5-41 5-42 Construction Details 5-43 5-44 Construction Details 5-45 5-46 Construction Details 5-47 5-48 Construction Details 5-49 RING ANCHOR

More information

Standard Inclusions for

Standard Inclusions for Standard Inclusions for Preliminaries Soil test Contour Survey & Site Assessment Property Service Information Working Drawings Building permit and application fees Engineering Site & Connections Connections

More information

access INCLUSIONS With our Access range of inclusions, you can move in and just enjoy living.

access INCLUSIONS With our Access range of inclusions, you can move in and just enjoy living. access INCLUSIONS access INCLUSIONS Here at BOLD, we know all about creating utmost liveability on any budget. We believe in providing more for less, packing in space and style at budget friendly prices.

More information

5.3.1 Water seal Positioning the toilet pan 12

5.3.1 Water seal Positioning the toilet pan 12 Table of contents 5.0 Introduction 5 5.1 The toilet and its components 6 5.1.1 Purpose and importance of the toilet 6 5.1.2 General types and designs of toilets in rural areas 6 5.1.3 Important features

More information

METATEK POWER HOUSE CONSTRUCTION BUILDER S GUIDE CHECKLIST

METATEK POWER HOUSE CONSTRUCTION BUILDER S GUIDE CHECKLIST BUILDER S GUIDE & CHECKLIST 1 Table of Contents OVERVIEW... 2 CONSTRUCTION GUIDELINES... 2 DO NOT MODIFY LIST... 3 OPTIONAL LIST... 3 BUILDING DRAWINGS... 4 CHECKLIST... 4 MATERIALS LIST... 15 MATERIALS

More information

BILLS OF QUANTITIES FOR CONSTRUCTION OF MODEL DISPENSARY BLOCK AT MGUNGANI / SALAITA

BILLS OF QUANTITIES FOR CONSTRUCTION OF MODEL DISPENSARY BLOCK AT MGUNGANI / SALAITA BILLS OF QUANTITIES FOR CONSTRUCTION OF MODEL DISPENSARY BLOCK AT MGUNGANI / SALAITA CONSTRUCTION OF MODEL DISPENSARY BLOCK Item DESCRIPTION QTY UNIT RATE TOTAL(KS ELEMENT : SUBSTRUCTURE (ALL PROVISIONAL):

More information

Residencial Las Américas - Edificio California C/ Sierra de Gredos,

Residencial Las Américas - Edificio California C/ Sierra de Gredos, Don t you think it s time to change your life? Then, bear this in mind! One more step in the creation of one of the best urban developent conceptions in Almería: Residencial Las Américas. Edificio Californi

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

Name of work : Special Repairs to North West Mugamandapam of 1000 Pillar Mandapam of A/m. Aranganathaswamy temple, Srirangam.

Name of work : Special Repairs to North West Mugamandapam of 1000 Pillar Mandapam of A/m. Aranganathaswamy temple, Srirangam. Value of Contract Rs. 30,46,963.00/- EMD : Rs. 30,500/- 1 2 3 4 5 Probable Quantity 99.00 26.40 26.40 Dismantling of weathering course and disposing the same to outside the temple premises etc, Dismantling

More information

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #8

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #8 New Main Hospital, Site Park, and Underground Garage Construction Progress Update #8 Date: July 1, 2009 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org June was a very

More information

International GmbH ALUPURA

International GmbH ALUPURA International GmbH Recessed covers ALUPURA ALUPURA Recessed covers ALUPURA product line Aluminium manhole-covers with variable surface. The variable surface of ALUPURA recessed-covers make manholes, inspection

More information

DRY CONSTRUCTION SYSTEMS

DRY CONSTRUCTION SYSTEMS DRY CONSTRUCTION SYSTEMS Adrienn LEPEL BUTE Dry construction systems Prefabricated elements assembly on site Minimal use of water dry construction systems Assembled partitions Suspended ceilings Raised

More information

Since it was established in 1989, with a small manufacturing base in Qwa Qwa, Uni-Span has grown to become one

Since it was established in 1989, with a small manufacturing base in Qwa Qwa, Uni-Span has grown to become one access scaffolding Since it was established in 1989, with a small manufacturing base in Qwa Qwa, Uni-Span has grown to become one of the major players in the scaffolding and formwork industry in South

More information

BN SENA SPECIALIST HOSPITAL

BN SENA SPECIALIST HOSPITAL BN SENA SPECIALIST HOSPITAL Page1 Table of content: 1. PROJECT OVERVIEW... 3 1.1 PROJECT DESCRIPTION.... 3 1.2 PROJECT GENERAL INFORMATION... 4 1.3 SCOPE OF THE WORK..... 4 1.4 PROJECT DASHBOARD STATUS....

More information

New York City College of Technology Division of Continuing Education

New York City College of Technology Division of Continuing Education New York City College of Technology Building Information Modeling with Revit 2014 Module 06 : FH.03 Firehouse Beams, Trusses, Structure & Slabs Professor Paul C. King, RA, AIA, ARA Prof.Paul.King@Gmail.com

More information

FLOOR DRAINS GENERAL INFORMATION

FLOOR DRAINS GENERAL INFORMATION FLOOR DRAINS 11 FLOOR DRAINS GENERAL INFORMATION All floor drains and rodding eyes are made from stainless steel V2A (AISI 304) or V4A (AISI 316). The floor drain type depends on the load, amount of drained

More information

BRICKWORK 3.5 BRICKWORK 1 GENERAL

BRICKWORK 3.5 BRICKWORK 1 GENERAL BRICKWORK 1 GENERAL 1.1 INSPECTION Notice Give sufficient notice so that inspection may be made of the following: - Set out of brickwork to lintels, arches and other architectural features. - Damp-proof

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

TOWER-1A: TERRACE FLOOR SLAB

TOWER-1A: TERRACE FLOOR SLAB TOWER-1A: TERRACE FLOOR SLAB TOWER NO: 1A (Overall completion 70.10%) Total Floors: - Stilt + 12 Upper floors Total Flats: - 24 (Duplex Type-A1) 1. Structural works up to terrace floor slab completed.

More information

2016 FEBRUARY. all of which was built by 60 individuals, from 18 churches, from 8 states.

2016 FEBRUARY. all of which was built by 60 individuals, from 18 churches, from 8 states. When Missionary Air Group needed an administrative headquarters, flight training, and aircraft maintenance facility, they prayed, asking God to provide one. Here is what God did. The NUMBERS: $205K of

More information

Tender Schedule for the Work "Construction of Staff qtrs. at Tainda S/S (1no.)

Tender Schedule for the Work Construction of Staff qtrs. at Tainda S/S (1no.) 1.Amount put to Tender:- Rs 7,48,024/- 2.E.M.D. Required: - R 8,000/- 3. Class of contractor :- "D" & "C" 4. Cost of Tender Paper:- R 4,200/- Sl- No Tender Schedule for the Work "Construction of Staff

More information

PND Training Hall Conex Building, Kabul ABSTRACT OF COST

PND Training Hall Conex Building, Kabul ABSTRACT OF COST PND Training Hall Conex Building, Kabul ABSTRACT OF COST A Civil Works All work items shall be carried as per drawing, specification and instruction of the Engineer. 1 Sub-structure Works Earthwork in

More information

540 20th Avenue, Lachine, Qc, H8S 3T1 T TF MEZZANINE

540 20th Avenue, Lachine, Qc, H8S 3T1 T TF MEZZANINE 540 20th Avenue, Lachine, Qc, H8S 3T1 T 514.634.7292 TF 800.361.2242 Info@federalsteel.ca www.federalsteel.ca MEZZANINE 03 What s your challenge? Table of Content 04 05 06 Design load Bracing Floor options

More information

MEMORIAL HOSPITAL GULFPORT A PROJECT STUDY

MEMORIAL HOSPITAL GULFPORT A PROJECT STUDY MEMORIAL HOSPITAL GULFPORT A PROJECT STUDY Building a healthy community together 2005 u HURRICANE KATRINA REPAIRS 2012 u SURGERY MODERNIZATION 2001 u RADIOLOGY RENOVATION 2000 u CLINIC SUPPORT ADDITION

More information

MBC Building Project Update #34 02 December 2011

MBC Building Project Update #34 02 December 2011 Hi Everyone MBC Building Project Update #34 02 December 2011 Isn t it exciting? We are only a few short only weeks away from completion! An official move in date will be announced at Church on Sunday,

More information

PROGRESS JAIPUR PH-II AS ON 30 NOV 18

PROGRESS JAIPUR PH-II AS ON 30 NOV 18 S MILESTONE DESCRIPTION STATUS No 1. MS 01 (D+120 Days) (a) Work commence for all Towers (b) Slab casting for 20 DU (c) Brick work for 25 DU (d) Internal electrical 15 DU (e) Internal Plumbing & Sewage

More information

KOOKABURRA HOMES TWO STOREY HOMES. Standard Inclusions. kookaburrahomes.com.au

KOOKABURRA HOMES TWO STOREY HOMES. Standard Inclusions. kookaburrahomes.com.au KOOKABURRA HOMES Standard Inclusions TWO STOREY HOMES kookaburrahomes.com.au 2 CLASSIC TWO STOREY HOMES STANDARD INCLUSIONS PLANNING AND GENERAL WORKS Fixed price contract 3 month maintenance period Council

More information

1200 Oakman Blvd INDUSTRIAL INVESTMENT/ USER OPPORTUNITY. Building A 85,999 SF. Building D. Building C 11,495 SF 15,046 SF.

1200 Oakman Blvd INDUSTRIAL INVESTMENT/ USER OPPORTUNITY. Building A 85,999 SF. Building D. Building C 11,495 SF 15,046 SF. 1200 Oakman Blvd A 85,999 SF Detroit, MI 48238 C D 15,046 SF A C Below (4) Grade Level Replacement Cost Doors Shop Floor Height: Zoning M4-Intensive 18 3 Industrial District Immediate HVAC - 6 Ton Unit

More information

Home Inclusions $410, HOME & LAND PACKAGE MARCOOLA Land Content $ MARCOOLA. 4 Bedroom 2 Bathroom Multiple living zones Alfresco

Home Inclusions $410, HOME & LAND PACKAGE MARCOOLA Land Content $ MARCOOLA. 4 Bedroom 2 Bathroom Multiple living zones Alfresco HOME & LAND PACKAGE MARCOOLA Land Content $180000.00 $410,000.00 Please note: actual façade may vary slightly from picture. MARCOOLA 4 Bedroom 2 Bathroom Multiple living zones Alfresco Double Lockup Garage

More information

Aman Graphics and Design Ltd. Nazimnagar, Hemayetpur, Savar, Dhaka ( E, N) 29 April 2014

Aman Graphics and Design Ltd. Nazimnagar, Hemayetpur, Savar, Dhaka ( E, N) 29 April 2014 1 Aman Graphics and Design Ltd. Nazimnagar, Hemayetpur, Savar, Dhaka (23.79418E, 90.26393N) 29 April 2014 2 Building Observations 3 Building 1 - Columns appear to be stressed in excess of normal design

More information

WELCOME. to the Presentation on. Guest Lecture for Course CE- 401 at Department of Civil Engineering (Seminar Room) BUET, Dhaka

WELCOME. to the Presentation on. Guest Lecture for Course CE- 401 at Department of Civil Engineering (Seminar Room) BUET, Dhaka WELCOME to the Presentation on Guest Lecture for Course CE- 401 at Department of Civil Engineering (Seminar Room) BUET, Dhaka Prepared by Dr. Toufiq M. Seraj Engineer-Planner Managing Director, Sheltech

More information

How To Construct a Ferro Cement Tank

How To Construct a Ferro Cement Tank How To Construct a Ferro Cement Tank Be Advised The following power point presentation assumes that individuals using it to construct ferro-cement tanks have a basic knowledge of geometry and calculating

More information

Government Gazette Staatskoerant

Government Gazette Staatskoerant Government Gazette Staatskoerant REPUBLIC OF SOUTH AFRICA REPUBLIEK VAN SUID AFRIKA Regulation Gazette Vol. 629 No. 10177 10 November November Regulasiekoerant 2017 No. 41237 PART 1 OF 3 N.B. The Government

More information

BUYING GUIDE ALGOT. Storage across the home. DESIGN Francis Cayouette

BUYING GUIDE ALGOT. Storage across the home. DESIGN Francis Cayouette BUYING GUIDE ALGOT Storage across the home DESIGN Francis Cayouette QUALITY Designed for use throughout the home. ALGOT shelves are hardwearing, stain resistant and easy to keep clean. Brackets are made

More information

Powder Coated Merino. Colorbond Dune. Concrete Tiles- Concrete Tiles Slate Grey Finish. Colorbond Paperbark. Concrete Tiles- Concrete Tile -

Powder Coated Merino. Colorbond Dune. Concrete Tiles- Concrete Tiles Slate Grey Finish. Colorbond Paperbark. Concrete Tiles- Concrete Tile - Colorbond Dune Powder Coated Merino Colorbond Paperbark Concrete Tiles- Concrete Tile - Concrete Tiles Slate Grey Finish Dulux Whisper White PCWF6 Concrete Tiles- Concrete Tile - Dulux Beige Royal Half

More information

THE STRATA UNIT May 25, 2008

THE STRATA UNIT May 25, 2008 THE STRATA UNIT May 25, 2008 Over the years, we have been asked time and time again from our experience as a cost consultant and a project manager from both a restoration and renovation point of view What

More information

ASE SYSTEMS. The Ergonomics & Productivity Specialists! 5611 Guhn Road Ste: A1 * Houston Texas * fax: *

ASE SYSTEMS. The Ergonomics & Productivity Specialists! 5611 Guhn Road Ste: A1 * Houston Texas * fax: * Ceiling Mounted Bridge Cranes The safe, productive, ergonomic solution for overhead materials handling operations #1 In Safety In Productivity In Ease of Positioning and Movement In Ease of Installation

More information

One Meter Internal Dome Oven AVERAGE GUIDE

One Meter Internal Dome Oven AVERAGE GUIDE FIELD FURNACE REFRACTORIES Pty Ltd. 8 Arnott Place Wetherill Park NSW 2164 Phone: 02-9729-1799 Fax: 02-9729-1899 One Meter Internal Dome Oven AVERAGE GUIDE Quantity Description Unit price Total 192 Tapered

More information

SECTION COPPER/ SOLDERED RF SYSTEM SPECIFICATIONS

SECTION COPPER/ SOLDERED RF SYSTEM SPECIFICATIONS SECTION 13096 COPPER/ SOLDERED RF SYSTEM SPECIFICATIONS Prepared by: NELCO 125 Chenoweth Lane, Ste. 206 Louisville, KY 40207 (502) 899-3726 13096-1 SECTION 13096 COPPER RADIO FREQUENCY SHIELDING ENCLOSURE

More information

ABA Fashions Ltd. Plot #9, Block F, Tongi, Gazipur-1710 ( N, E) 08 MARCH 2014

ABA Fashions Ltd. Plot #9, Block F, Tongi, Gazipur-1710 ( N, E) 08 MARCH 2014 ABA Fashions Ltd. Plot #9, Block F, Tongi, Gazipur-1710 (23.885176N, 90.399821E) 08 MARCH 2014 1 2 Observations 3 Highly stressed columns Cursory calculations indicate column at a high working stress.

More information

ESCONDIDO FIRE DEPT TRAINING MANUAL Section Truck Module Page 1 of 7 High Rise Anatomy Revised

ESCONDIDO FIRE DEPT TRAINING MANUAL Section Truck Module Page 1 of 7 High Rise Anatomy Revised Truck Module Page 1 of 7 HIGH RISE BUILDING CONSTRUCTION The Truck Module 1000.00 sections are designed to be companion documents to EOM section 503.00 Objectives The objective of this section is to provide

More information

FACILITIES MAINTENANCE WORKER

FACILITIES MAINTENANCE WORKER FACILITIES MAINTENANCE WORKER Summary Statement: Under supervision, is responsible for performing routine building maintenance tasks and assisting Building Maintenance Supervisor with the performance of

More information

storage solutions Averys group PAL RACK The high quality pallet storage system for goods of all sizes and weights.

storage solutions Averys group PAL RACK The high quality pallet storage system for goods of all sizes and weights. storage solutions Averys group PAL RACK The high quality pallet storage system for goods of all sizes and weights. CONVENTIONAL PALLET RACKING The Stow Pal Rack system consists of a full range of basic

More information

NSC Shelving & Storage for Epworth

NSC Shelving & Storage for Epworth NSC Shelving & Storage for Epworth Providing a complete storage and shelving solution: customised for Epworth HealthCare National Surgical Corporation worked with Epworth HealthCare to design, supply and

More information