Invitation to Bid FIELD LIGHTING AND POLES BHS & SCH
|
|
- Dinah Brooks
- 6 years ago
- Views:
Transcription
1 Invitation to Bid FIELD LIGHTING AND POLES BHS & SCH Responses to an Invitation to Bid will be received by the Purchasing Coordinator, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN for FIELD LIGHTING AND POLES BHS & SCH until 9:00 A.M. Local Time Tuesday December 6, Bid responses will be opened at that time, taken under advisement and evaluated. All questions should be addressed to Tim Williams (615) All proposals are subject to the Board of Education s conditions and specifications which are available from Vicky Currey, Purchasing Coordinator (615) All bids can be viewed on line at
2 SPECIFICATIONS FOR INSTALLATION OF CONCRETE POLES AND SPORTS FIELD LIGHTING The Sumner County Board of Education (Owner) is currently seeking bids for the installation of concrete poles and sports field lighting at Beech High School football field located at 3126 Long Hollow Pike, Hendersonville, TN and Station Camp High soccer field located at 1040 Bison Trail Road, Gallatin, TN The successful bidder will be responsible for furnishing all tools, equipment, labor, materials, and miscellaneous items needed for a complete turnkey project. These projects are to be bid as a package with the successful bidder providing one quote for all poles, lights, and associated equipment to install a complete working system at both locations. SCOPE OF WORK The installing contractor s responsibilities shall include the following: 1. Provide required poles, fixtures, materials, labor, and associated equipment as described in these specifications for a complete football field lighting system and a complete soccer lighting system. Provide layout of pole locations and aiming diagram. Provide materials and equipment to off load equipment at each project site per scheduled delivery. 2. Provide project management assistance as needed. 3. Provide structural designs stamped by a Tennessee licensed structural engineer. 4. Provide a stamped electrical design by a Tennessee licensed electrical engineer for Owner s review prior to installation. Provide all materials and equipment to replace and upgrade the existing electrical service panels. All electrical work is to meet or exceed the National Electrical Code (NEC) and/or the requirements of the local jurisdiction. 5. Remove 3 existing wood poles, light fixtures, associated wiring, and electrical components at the Beech location and dispose of as directed by the Owner s representative. The light fixtures are to be returned to the Owner for disposal. The fourth remaining, existing concrete pole is to be re-used with new light fixtures, associated wiring, and electrical components installed per these specifications to match the three (3) new poles and lights. The holes where the existing poles were removed are to be backed filled with stone to allow for 12 of topsoil and seeded/strewn with a top quality turf seed. All trenches will also be backfilled to match existing grade and seeded/strewn. In addition, the contractor will furnish four (4) new concrete poles, light fixtures, associated wiring, and electrical components at the Station Camp location. 6. Provide storage containers for material as necessary and dumpsters for waste disposal if needed at both locations. The Owner will not be responsible for construction generated debris removal. Topsoil is not to be removed from either site per Board Policy FE. 7. Provide adequate security to protect delivered products from theft, vandalism, or other unspecified damage for the duration of the projects. The Owner will not be responsible for any materials stored on site for the duration of the projects. 1
3 8. Keep all heavy equipment off of the playing fields. Contractor will repair all damage to grounds which exceeds that which would be expected. Indentations caused by heavy equipment traveling over dry ground would be an example of expected damage. Ruts and sod damage caused by equipment traveling over wet grounds would be an example of damage requiring repair. The contractor will replace all property damaged by him including fences, trees, plants, grass, concrete walks, asphalt drives, building surfaces, stadium seating, etc. at no additional cost to the Owner. SPORTS FIELD LIGHTING Work covered under this section shall conform to the specifications and engineering plans as well as state and local codes. The purpose of these specifications is to define the performance and design standards for the Owner. The Manufacturer/contractor shall supply lighting equipment and poles to meet or exceed the standards set forth by the Tennessee Secondary School Athletic Association (TSSAA) for football field lighting and soccer field lighting. Those standards are included as part of these specifications. The primary goals of this sports lighting project are: A. Guaranteed light levels- Selection of appropriate light levels impact the safety of the players and the safety and enjoyment of the spectators. Therefore the lighting system shall be designed such that the light levels are guaranteed for a period of twenty five (25) years. B. Comprehensive Warranty- Lighting Manufacturer shall supply a signed warranty covering the entire system for twenty five (25) years. Warranty shall guarantee light levels; lamp replacements; system energy consumption; monitoring, maintenance and control services, spill light control, and structural integrity. Manufacturer shall maintain specifically-funded financial reserves to assure fulfillment of the warranty for the full term. Warranty may exclude fuses, storm damage, vandalism, abuse, and unauthorized repairs or alterations. C. Energy consumption- Based on a 5000 hour operating cycle, the average kwh consumption for the field lighting system shall be 56.3 or less. LIGHTING SYSTEM CONSTRUCTION Lighting system shall consist of the following: A. Mark locations and provide materials, labor, hardware, and equipment to deliver and erect three (3) centrifugally spun concrete poles at the Beech High location as specified per the Manufacturer s layout. The fourth pole is an existing concrete pole that is to be re-used with new cross arms, light fixtures, and associated equipment installed to match the three (3) new poles and assemblies as described in these specifications. Additionally, four (4) new centrifugally spun concrete poles are to be delivered and installed at the Station Camp High location. Installation at both locations is to include all cross arms, braces, wiring, and miscellaneous hardware necessary to affix 2
4 lighting fixtures. The poles are to be direct embedded centrifugally spun concrete, 80 feet long and buried at a depth of 10% of overall pole length, backfilled and tamped. Poles shall have 5/8 X 7 long step bolts complete with locking nuts on staggered 15 centers and 180 degrees apart. Steps will begin at 15 feet above ground line. A safety climbing cable shall be shipped loose for field installation. The cable shall be 5/16 diameter galvanized and stranded. It shall run the length of the pole attaching to the top of the platform to allow climber to enter platform prior to disengaging safety harness. The pole is to have an aluminum nameplate cast into the wall of the pole approximately 4 5 above the ground line identifying the Manufacturer, manufacture date, length, weight, class and fabrication number. Poles and other support structures, brackets, arms, bases, anchorages and foundations shall be determined based on the 2003 edition of the International Building Code (IBC), wind speed of 90 mph, exposure category C. Luminaries, visor, and cross arm shall withstand 150 mph winds and maintain luminaries aiming alignment. B. All luminaries shall be constructed with a die-cast aluminum housing to protect the luminaries reflector system from the elements. External visors and internal glare shields shall be utilized to minimize spill light, sky glow, and glare. C. Manufacturer will remote all ballasts and supporting electrical equipment in aluminum enclosures mounted approximately 10 above grade. The enclosures shall include energy efficient ballast, capacitor and fusing for each luminary. Safety disconnect per circuit for each pole structure will be located in the enclosure. A wire harness complete with an abrasion protection sleeve, strain relief and plug-in connections for fast, trouble-free installation shall be included. D. The contractor shall be responsible for providing the equipment and installation of a complete and operational system at the Beech High location commencing from the electrical service entrance and terminating at the safety disconnect within the electrical enclosure, 10 (feet) above grade, on each lighting pole. At the Station Camp High location, the contractor will be responsible for coordinating with the local power distributor for a new electrical service to be installed at the soccer field. Currently there is no electrical service to this field. All equipment and materials are to be provided to install a new lighting contactor cabinet and terminate all necessary wiring. The electrical contractor shall coordinate the transformer and switchgear locations as well as identify the voltage and phase of the service, with the local power company before any equipment is installed. The lighting contractor cabinet is to provide on-off control of the lighting system constructed of NEMA Type 4 aluminum. Communication method shall be provided by the Manufacturer. The cabinet shall contain custom configured contactor modules for 30, 60, and 100 amps, labeled to match field diagrams and electrical design. Manual off-on-auto selector switches shall be provided. All components shall be designed and manufactured as a system. All luminaries, wire harnesses, ballast, and other enclosures shall be factory assembled, aimed, wired, and tested. All system components shall be UL Listed for the appropriate application. Maximum total voltage drop to the disconnect switch located on the poles shall not exceed three (3) percent of the rated voltage per IESNA RP
5 E. Provide all material and equipment to install all underground conduit, wiring, pull boxes, etc. and terminate wiring as required per the electrical design at both locations. At the end of the project and before the final payment is issued, the contractor is to provide a detailed as-built diagram showing the location and depth of the underground electrical system at both locations. The contractor is to confirm the existing underground utilities, irrigation systems, and Geothermal well fields have been located at both locations and are clearly marked so as to avoid damage from construction equipment. Any such damage will be repaired by the contractor at no additional expense to the Owner. Failure to locate and mark the utilities will not relieve the contractor of the responsibilities to make necessary repairs. FIELD QUALITY CONTROL A. Illumination Measurements: Upon substantial completion of the projects and in the presence of the contractor, project engineer, Owner s representative, and Manufacturer s representative, illumination measurements shall be taken and verified. The measurements shall be conducted in accordance with the Illuminating Engineering Society of North America (IESNA) RP-6-01, Appendix B. B. Correcting non-conformance: If, in the opinion of the Owner or his appointed representative, the actual performance levels including foot-candles, uniformity ratios, and maximum kilowatt consumptions are not in conformance with the requirements of the performance specifications and submitted information, the Manufacturer shall be liable to any or all of the following: 1. Manufacturer shall at his expense provide and install any necessary additional fixtures to meet the minimum lighting standards. The Manufacturer shall also either replace the existing poles to meet the new wind load (EPA) requirements or verify by certification by a licensed structural engineer that the existing poles will withstand the additional wind load. 2. Manufacturer shall minimize the Owner s additional long term fixture maintenance and energy consumption costs created by the additional fixtures by reimbursing the Owner the amount of $1, (one thousand dollars) for each additional fixture required. 3. Manufacturer shall remove the entire unacceptable lighting system and install a new lighting system that meets the specifications. INSURANCE AND BOND REQUIREMENTS A. The contractor shall provide a certificate of insurance for a minimum of $1,000, for public liability and property damage with the Sumner 4
6 County Board of Education named as the certificate holder. The policy shall provide for a combined single limit of $500, per occurrence for bodily and property damage with an aggregated limit of not less than $1,000, The certificate shall also provide for Comprehensive General and Vehicle Liability with minimum coverage of $1,000, per incident. The contractor shall provide Workers Compensation Insurance as required by Tennessee state law. The contractor shall prove compliance with Public Chapter No. 587, T.C.A (d), criminal background check and provide a Drug Free Workplace affidavit. B. The contractor shall furnish a performance bond in an amount equal to one hundred percent (100%) of the contract as security for the faithful performance of this contract, and a labor and material bond in an amount of one hundred percent (100%), or in the penal sum not greater than that prescribed by state, territory, or local law, as security for the payment of all persons performing labor on the project under this contract and furnishing materials in connection with this contract. The bonds shall be written by a surety licensed to do business in the locale in which the work is being performed and shall be satisfactory to the Owner. The contractor shall, upon completion of the projects, protect the Owner against defective materials or faulty workmanship for a period of two (2) years. CODES, PERMITS, AND LICENSES All work shall comply with the applicable rules of the National Electrical Code, the National Electrical Safety Code, the National Fire Codes (published by the National Fire Protection Association), State and local codes and ordinances, and the terms and conditions of the services of the electrical utility, as well as any other authorities that may have lawful jurisdiction pertaining to the work specified. None of the terms or provisions of this specification shall be construed as waiving any of the rules, regulations, or requirements of these authorities. The contractor shall procure all necessary permits or licenses to carry out his work and shall pay the lawful fee thereof as well as for any inspection fee or the cost of a certificate of approval. In any instance where these specifications call for materials for construction of a better quality or larger size than required by codes, the provisions of these specifications shall take precedence. The codes shall govern in the case of direct conflict between the codes and the plans and the specifications. 5
7 PRE-BID CONFERENCE There will be a mandatory pre-bid conference held at both sites on Tuesday, November 29 th at 9:00 a.m. CST starting at the Station Camp High location and then moving to the Beech High location. Bidders that do not attend this conference will not be considered for the work. For any questions concerning these specifications contact Tim Williams at or by at Tim.Williams@sumnerschools.org. BID SHEET (Bidder will be required to hold this quote for a period of ninety (90) days so bid can be approved by both the Sumner County Board of Education and the Sumner County Commission) PRICE TO PROVIDE AND INSTALL SEVEN (7) CONCRETE POLES AND EIGHT (8) LIGHTING RIGS PER THE SPECIFICATIONS AT THE BEECH HIGH AND STATION CAMP HIGH LOCATIONS: (IN WORDS) (IN NUMBERS) ALTERNATE PRICE TO PROVIDE AND INSTALL (7) GALVANIZED STEEL POLES AND EIGHT (8) LIGHTING RIGS PER THE SPECIFICATIONS IN LIEU OF CONCRETE POLES: (IN WORDS) (IN NUMBERS) COMPANY NAME: ADDRESS: PHONE: SIGNATURE OF AUTHORIZED COMPANY REPRESENTATIVE 6 DATE
8 Lighting Standards Tennessee Secondary School Athletic Association
9 Standards of Lighting The following guidelines are recommended by the Tennessee Secondary School Athletic Association. These standards apply to the lighting of all high school athletic activities sponsored by the TSSAA or its member schools. These standards incorporate the most current data available regarding the lighting, electrical and structural issues that apply to installation of a safe, effective lighting system. The standards are divided into recommended minimums and desirable features. The minimums establish criteria important to safe conduct of TSSAA activities and include evaluation of operating costs over the expected life of the lighting system. Desirable features are established to give added values where appropriate for a facility's needs. I. Recommended Minimum Standards These minimum standards are recommended for all lighting installations after the date of adoptions of these standards. Any modification in existing lighting systems after this date should be done so as to result in a lighting system in compliance with these standards. To be in compliance, a system must meet all recommended minimum standards. PART 1 GENERAL 1.1 LIGHTING PERFORMANCE The quantity of equipment needed is determined by the efficiency of the lighting system. Newest technology is capable of delivering equal or better results with as little as half the amount of equipment as typical floodlighting systems. A. Preferred Technology By utilizing a series of power adjustments, a lighting system is able to provide "constant light levels" and greatly extend the life of the lamps. In addition, this generation of lighting has high performance optic characteristics that enable reductions in the quantities of luminaires needed to meet design targets. B. Typical Floodlighting Computer designs are done using two sets of values. One predicts "initial light levels" when lamps are new. The other predicts "maintained light levels" after the lamps have passed through depreciation in light output. It is important to have the lighting designer use a maintenance factor adequate to account for this depreciation in light output throughout the life of the lamp. A value no greater than.70 shall be applied to initial light levels to predict these maintained values. Quality manufacturers are willing to provide guarantees of lighting performance. C. Performance Requirements Playing surfaces shall be lit to an average constant or target light level and uniformity as specified in the following chart. Lighting calculations shall be developed and field measurements taken on the grid spacing with the minimum number of grid points specified on page 12 of these standards with the light meter held horizontally 36 inches above the field surface. Measured average illumination level shall be +/- 10% of predicted mean in accordance with IESNA RP-6-01, and measured at the first 100 hours of operation.
10 Area of Lighting Baseball / Softball Average Constant or Target Light Levels (Horizontal) 50 footcandles - Infield 30 footcandles - Outfield Maximum to Minimum Uniformity Ratio 2:1 infield 2.5:1 outfield Football / Soccer / Lacrosse / Field Hockey / Rugby Less than 2000 spectators More than 2000 spectators Gymnasium / Basketball With spectators No spectators Natatoriums 30 footcandles 50 footcandles 80 footcandles 50 footcandles 2.5:1 2:1 2:1 Consult an experienced lighting manufacturer or lighting specialist Tennis Track Competitive Use General Use (Walking track) Combination / Multipurpose 40 footcandles 30 footcandles 5 footcandles Highest minimum for activities played on the field 1.7:1 within lines 2:1 principal playing area 3:1 N/A Lowest minimum for activities played on the field D. Glare for Participants To achieve placement of lights in positions that enhance playability, pole locations and fixture placements should be as shown on the layouts in the appendix. 1.2 ENVIRONMENTAL LIGHT CONTROL Many facilities are located near residential properties or roadways, creating the possibility of spill and glare onto adjoining properties. Consideration should be given to this issue during the initial lighting design stage to minimize this effect. Some communities are implementing ordinances designed to minimize light pollution. Contact your local planning committee or zoning board. The lighting equipment manufacturer can assist in assessing this issue and provide drawings showing maximum footcandles at any points of concern on adjacent properties. Do not hesitate to investigate a manufacturer's reputation, abilities, and past experiences in working with local authorities and private property owners regarding glare and spill issues. 1.3 LIFE-CYCLE COSTS Because the efficiency of lighting systems currently available can vary greatly, a life-cycle operating cost analysis should be considered when evaluating lighting systems. Owners should expect a quality lighting system to last a minimum of 25 years. These standards provide a Life-Cycle Operating Cost Evaluation form to assist with the process. Items that should be included are energy consumption based upon the facility's expected usage, cost for group and spot relamping and maintenance, and any additional savings in energy or labor cost provided by automated on/off control systems. Contract price and life-cycle operating cost should both be considered in determining a lighting manufacturer for the project. 5
11 1.4 CONTROL AND MONITORING SYSTEM A remote control and monitoring system will provide ease of operation and management for your facility. Manufacturers providing systems with a 25 year warranty will utilize this system to ensure your lighting performs as required. A. Remote Monitoring The system shall monitor lighting performance and notify manufacturer if individual luminaire outage is detected so that appropriate maintenance can be scheduled. The manufacturer shall notify the owner of outages within 24 hours, or the next business day. The controller shall determine switch position (Manual or Auto) and contactor status (open or closed). B. Remote Lighting Control The system shall allow owner and users with a security code to schedule on/off system operation via a web site, phone, fax, or up to 10 years in advance. Manufacturer shall provide and maintain a two-way TCP/IP communication link. Trained staff shall be available 24/7 to provide scheduling support and assist with reporting needs. The owner may assign various security levels to schedulers by function and/or fields. This function must be flexible to allow a range of privileges, such as full scheduling capabilities for all fields, to only having permission to execute "early off' commands by phone. Control unit shall accept and store 7-day schedules, be protected against memory loss during power outages, and shall reboot once power is regained and execute any commands that would have occurred during outage. C. Management Tools Manufacturers shall provide a web-based database of actual field usage and provide reports by facility and user group. D. Communication Costs Manufacturers shall include communication costs for operating the controls and monitoring system for a period of 25 years. E. Cabinet Construction Controls and Monitoring Cabinet shall be constructed of aluminum and rated NEMA Type 4. Cabinet shall contain custom-configured contactor modules for 30, 60, and 100 amps, labeled to match field diagrams and electrical design. Manual Off-On-Auto selector switches shall be provided. 1.5 WARRANTY AND GUARANTEE Product warranties are a good gauge of a manufacturer's confidence in their products. Warranties for typical floodlighting equipment can range from five years to 10 years, and details of covered items and conditions vary greatly. New generation technology comes with warranty periods of up to 25 years and includes guaranteed light levels, parts, labor, lamp replacements, energy usage, monitoring and control services, spill light control, and structural integrity. The manufacturer should have financial reserves to assure fulfillment of the warranty for the full term. It is highly recommended you consider these allinclusive warranties to limit your school's future exposure to escalating costs and maintenance hassles. PART 2- PRODUCT 2.1 LIGHTING SYSTEM CONSTRUCTION A lighting system should consist of lighting, electrical and structural components designed to work together as a system that is durable and provides safety features. A. Outdoor lighting systems should consist of the following: I. Galvanized steel poles and crossann assembly. Wood poles or direct burial steel poles are not recommended. 2. Pre-stressed concrete base embedded in concrete backfill or a poured-in-place foundation containing reinforcing steel cured a minimum of 28 days before any stress load is applied. 3. Luminaires constructed with a die-cast aluminum housing or external hail shroud to protect the luminaire reflector system.
12 4. All ballasts and supporting electrical equipment mounted remotely in aluminum enclosures approximately 10' above grade. The enclosures shall include ballast, capacitor, and fusing for each luminaire. Safety disconnect per circuit for each pole structure must be located in the enclosure. 5. Wire harness complete with an abrasion protection sleeve, strain relief, and plug-in connections for fast, trouble-free installation. B. Interior sports lighting systems should consist of the following: 1. All luminaires shall consist of a lamp, lamp socket, reflector, lens, lamp cone, reinforcing retaining ring, and wire frame to mount glare reduction visor. 2. All ballasts and supporting electrical equipment shall be mounted remotely in aluminum enclosures located in an easily-accessible area but away from the playing area due to heat considerations. The enclosures shall include ballast, capacitor, and fusing for each luminaire. Safety disconnect per circuit for each pole structure must be located in the enclosure. C. Manufacturing Requirements All components should be designed and manufactured as a system. All luminaires, wire harnesses (if provided), and ballast and other enclosures should be factory assembled, aimed, wired, and tested for reduced installation time and trouble-free operation. D. Durability All exposed components shall be constructed of corrosion-resistant material and/or coated to help prevent corrosion. All exposed steel shall be hot dip galvanized per ASTM Al23. All exposed hardware and fasteners shall be stainless steel of at least 18-8 grade, passivated and polymer coated to prevent possible galvanic corrosion to adjoining metals. All exposed aluminum shall be powder coated with high performance polyester. All exterior reflective inserts shall be anodized, coated with a clear, high gloss, durable fluorocarbon, and protected from direct environmental exposure to prevent reflective degradation or corrosion. All wiring shall be enclosed within the crossarms, conduit, pole, or electrical components enclosure. E. Lightning Protection All outdoor structures shall be equipped with lightning protection meeting NFPA 780 standards. F. Safety All system components shall be UL Listed for the appropriate application. G. Maximum total voltage drop Voltage drop to the disconnect switch located on the poles should not exceed three (3) percent of the rated voltage per IESNA RP STRUCTURAL PARAMETERS A. Location Poles should be located as shown on the drawings in the appendix to these standards. Whenever possible, poles should be located outside of fences to avoid causing an obstruction or safety hazard to the participants. B. Foundation Strength Project-specific foundation drawings stamped by a registered Tennessee structural engineer illustrating that the foundation design is adequate to withstand the forces imposed from the pole, fixtures, and other attachments to prevent the structure from leaning should be provided by the manufacturer. C. Support Structure Wind Load Strength Poles and other support structures, brackets, arms, bases, anchorages, and foundations shall be determined based on the 50 year mean recurrent isotach wind maps for the appropriate county per the Tennessee State Building Code/International Building Code 2006 Edition. Luminaire, visor, and crossarm shall withstand 150 mph winds and maintain accurate aiming alignment. D. Structural Design The stress analysis and safety factor of the poles shall conform to AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signals.
13 Typical Facility Information Appendix Area of Lighting Playing Dimensions (feet) Grid Spacing (feet) Minimum # of Grids Baseball, Infield 90' x 90' 30' x 30' 25 Baseball, Outfield Dimensions Vary 30' x 30' Varies Softball, Infield 60' x 60' 20' x 20' 25 Softball, Outfield Dimensions Vary 20' x 20' Varies Football 360' x 160' 30' x 30' 72 Soccer 360 x 180' 30' x 30' 72 Lacrosse 330' x 180' 30' x 30' 66 Field Hockey 300' x 180' 30' x 30' 60 Rugby 330' x 180' 30' x 30' 66 Tennis 78' x 36' 20' x 20' 15 Gymnasiums 94' x 50' 10' x 10' 50 Track and Field Dimensions Vary 30' x 30' Varies Light Level Grid Point Layouts Baseball Softball O 0 O 0 0 O 0 0 O O 0 O x 20 ft. O 00 O O O O O 0 0 O 0 D O 0 0 O O O ' radius field shown 200' radius field shown
14 Football Gymnasium 360' x 160' field shown 94' x 50' court shown C C C CC a 0 C ,.) x 30 tt. a o a 0 a o o o a a o a o a I 0 10 x 10 ft Grid Points Tennis 78' x 36' court shown 20 x 20 ft. o o o 0 30 x 30 ft. o o o o o o o o o o 0 0 o o o o o o o 0 0 o o o o Tra 400 meter, 8 lane track shown 30 x 30 ft
15 (6-pole Option) Fl (6-pole Option) (6-pole OptIon) 10 III (6-pole Option) F4 Football Field 1. Shaded areas indicate recommended pole location. All poles should be at least 45 feet from sideline. 2. On a 4-pole design, poles should be located between the 20-yard line and the goal line. 3. For the 6-pole option, setback of middle poles will depend on the presence of bleachers. 4. For TV consideration on a 6-pole design, outside poles should be located toward the end zone line. Optimum placement for TV is feet off the end zone line for an end zone camera. 5. For practice facilities, the lighting should be approximately 20 footcandles with 2 poles on each side of the field with aiming angles of 25 degrees. Poles should be in position so not to pose a potential injury. Electrical and structural guidelines should be strictly adhered to as outlined in these standards. 18
16 (6-pole Option) 16-pole Option) S1 1 (6-pole Option) S2, I 00 I ' min. _ I ' CD ; (6-pole Option) s S4 (6-pole Option) $3 ; (6-pole Option) Soccer Field 1. Poles are shown in optimal locations. Other permissible pole locations are indicated by the shaded areas. All poles should be at least 20 feet from the sideline. 2. On a 4-pole design, the optimum pole locations are (.35 x field length) from center of field. 3. In general, football lighting standards apply to soccer with the following considerations: a. A corner kick is a specific visual task and general consideration should be given to facility design specifically for soccer. b. The corner grid point shall be lit to no less than 90% of the average light level. 4. For combination football and soccer facilities, soccer should take precedence. 5. Vertical aiming angles should be 21 degrees minimum. The angles are measured from below a horizontal plane at fixture height.
17 Glossary Aiming Angles The degrees below horizontal that light fixtures are aimed at the field. Angles are measured from a horizontal plane at fixture height. Critical in safe, playable lighting design. Ballast A transformer that delivers the proper operating voltage for high intensity discharge type lamps including metal halide lamps. Constant Light Levels The amount of light you can expect on the field at any given time over the life of the system. Footcandle The measurement of light on a surface. One footcandle equals one lumen spread over one square foot. Glare Light that interferes with the ability to see. Luminaire design, proper aiming angles, and pole locations are key to limiting glare for participants and spectators. IESNA Illuminating Engineering Society of North America. An organization that develops recommendations for sports lighting. Initial Light Levels The average light levels when your lamps are new. Manufacturers that do not provide constant illumination should provide scans showing what these levels will be. Lumen A quantity measurement of light, used mostly in measuring the amount of light a lamp develops. Metal Halide Lamp A lamp that generates light by passing electrical current through metallic gases. The first choice for sports facilities because of efficiency and color. NEC National Electric Code. A national safety code for electrical systems that is the basis for most local codes. NEMA Type A classification of reflectors. For example, a Nema 2 reflector gathers light in a narrow, focused beam, allowing it to be projected a long distance. A Nema 5 projects light a relatively short distance in a very wide beam. Most lighting designs use various combinations of Nema types to get the desired results. NFPA National Fire Protection Association. An organization that establishes and publishes various codes such as the Lightning Protection Code and the National Electric Code. Overturning Moment The amount of force applied to a lighting structure, mostly from wind. Pole foundations must be designed to withstand this force. Reflector Key element of lighting optics. It surrounds the lamp (bulb) and directs light to the field. The efficiency of the reflector is one factor that determines how many light fixtures you have to buy and maintain. Remote Electrical Enclosure A weatherproof enclosure that allows the electrical gear to be moved from the top of lighting structures to a lower point where it can be serviced easily. Smoothness The change in light levels between measuring points. The less change between points, the more even the lighting. (See also Uniformity.) Spill Light Wasted light that falls off the field or is projected into the sky. Systems that can re-direct spill light back onto the field save dollars and keep neighbors content. Target Light Levels The lowest average amount of light for which a lighting system should operate over its extended life to ensure performance requirements. Target values should be no more than 70% of initial values to be sure that lamp depreciation has been accounted for in the design. You should receive scans showing what this level will be.
18 Tilt Factor Most lamps generate fewer lumens when tilted off of either a horizontal or vertical position. Your design should show actual tilt factor used in your design. Underwriters Laboratories Independent, non-profit, product safety testing and certification organization. Visit for additional information. Uniformity The smoothness of light on the field. Also called uniformity ratio. A design criteria to assure that light is distributed evenly across the entire field. A max/min ratio of 2:1 means that the brightest point is no more than double any other point.
19 NOTICE TO RESPONDENTS Responses to an Request for Proposal will be received by the Purchasing Coordinator in the SUPORT SERVICE FACILITY CONFERENCE ROOM, Sumner County Board of Education, 1500 Airport Road Gallatin, TN They will be received until 9:00 A.M. Local Time TUESDAY DECEMBER 6, 2011 for FIELD LIGHTING AND POLES BHS & SCH, at which time the responses will be opened, taken under advisement and evaluated. BIDS WILL BE POSTED ON GENERAL REQUIREMENTS AND CONDITIONS 1. The Sumner County Board of Education reserves the right to accept or reject any and/or all responses in whole or in part, and to waive informalities therein. 2. Any responses received after the scheduled closing time for the receipt for responses will not be considered. 3. If a mistake is discovered after the responses are received, only the Sumner County Board of Education may allow the respondent to withdraw the entire response. 4. Partial payments will not be approved unless justification for such payment can be shown. Terms will be net 30 days. 5. Payment will not be made until the said FIELD LIGHTING AND POLES are inspected and approved as meeting all specifications by persons appointed by the Sumner County Board of Education. 6. Responses submitted must be in a sealed envelope and marked on the outside as follows: RESPONSE: FIELD LIGHTING AND POLES DEADLINE: 9:00 A.M. TUESDAY, DECEMBER 6, Facsimile responses will not be considered. 8. If a successful bidder violates any terms of their bid, the contract, school board policy or any law they may be disqualified from bidding for a period of two years for minor violations or longer for major violations. Bids from disqualified bidders will not be accepted during the period of disqualification. 9. Prices quoted on the response (if any) are to be considered firm and binding until the said FIELD LIGHTING AND POLES are in the possession of the Sumner County Board of Education. 10. No purchase or contract is authorized or valid until the issuance of a Board Purchase Order in accordance with Board Policy. No Board Employee is authorized to purchase equipment, supplies or services prior to the issuance of such a Purchase Order. 11. Any deviation from these stated terms, specifications and conditions must be coordinated with and approved in writing by the Purchasing Coordinator, Vicky Currey (615) All bids that exceed $25,000 must have the Company Name, License Number, Expiration Date thereof and License Classification of Contractor listed on outside of sealed envelope. As required by State of Tennessee Code Annotated The awarded bidder will be required to post a performance and payment bond in the amount of 25% of the contract price if it exceeds $100,000 as stated by State of Tennessee Code Annotated
CITY OF GOODLETTSVILLE PARKS AND RECREATION DEPARTMENT
CITY OF GOODLETTSVILLE PARKS AND RECREATION DEPARTMENT MINIMUM BID SPECS BALLFIELD LIGHTING Moss-Wright Park Baseball/Softball Fields 1 and 2 Fields to be 50/30 maintained footcandles All fixtures to be
More informationLighting Standards. Tennessee Secondary School Athletic Association
Lighting Standards Tennessee Secondary School Athletic Association Adopted March, 2016 TABLE OF CONTENTS Standards of Lighting... 4 I. Recommended Minimum Standards... 4 PART 1 GENERAL... 4 1.1 LIGHTING
More informationPHONE: (727) PURCHASING DEPARTMENT FAX: (727) GOVERNMENT DRIVE NEW PORT RICHEY, FL
PHONE: (727) 847-8194 PURCHASING DEPARTMENT FAX: (727) 847-8065 8919 GOVERNMENT DRIVE NEW PORT RICHEY, FL 34654 www.floridabidsystem.com December 12, 2012 TO: Concerned Bidders RE: Addendum No. 3 Bid No.
More informationSECTION EXTERIOR ATHLETIC LIGHTING
PART 1 GENERAL 1.1 SECTION INCLUDES A. Sports luminaries and accessories B. Poles 1.2 REFERENCES SECTION 26 58 68 EXTERIOR ATHLETIC LIGHTING A. ANSI C78.379 - Classification of Beam Patterns of Reflector
More informationRequest for Proposals. Addendum No. 01. New LED Lighting System. for. RSU No. 22. March 20, 2018
Request for Proposals Addendum No. 01 New LED Lighting System for RSU No. 22 March 20, 2018 To all Registered Bidders: The following questions/clarifications, changes, additions, and/or deletions are hereby
More informationSECTION SPORTS FIELD LIGHTING
SECTION 16500 SPORTS FIELD LIGHTING PART I - GENERAL 1.01 Related Documents Drawings and general provisions of the bid documents, including general and supplementary conditions apply to this section. 1.02
More informationInvitation to Bid MHM
Invitation to Bid FENCE @ MHM Responses to an Invitation to Bid will be received by the Purchasing Coordinator, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN 37066 for FENCE @ Merrol
More informationInvitation to Bid SAFETY TILE PLAYFILL - MULCH
Invitation to Bid 20160614-02 SAFETY TILE PLAYFILL - MULCH Responses to an Invitation to Bid will be received by the Purchasing Coordinator, Sumner County Board of Education, 1500 Airport Road, Gallatin,
More informationInvitation to Bid WHITE HOUSE HIGH GYM FLOOR
Invitation to Bid WHITE HOUSE HIGH GYM FLOOR Responses to an Invitation to Bid will be received by the Purchasing Coordinator, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN 37066 for
More information2017 Little League Lighting Standards & Safety Audit
2017 Little League Lighting Standards & Safety Audit Supplementing the Little League 2017 Operating Manual Lighting Information TABLE OF CONTENTS Introduction 1 I. Required Minimum Standards Part 1 -
More informationInvitation to Bid ALUMINUM WALKWAY CANOPY NBE
Invitation to Bid ALUMINUM WALKWAY CANOPY NBE Responses to an Invitation to Bid will be received by the Purchasing Coordinator, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN 37066 for
More informationInvitation to Bid SAFETY TILE PLAYFILL - MULCH
Invitation to Bid SAFETY TILE PLAYFILL - MULCH Responses to an Invitation to Bid will be received by the Purchasing Coordinator, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN 37066
More informationBID # ELLIS MIDDLE LOCKERS
BID # 20140729 ELLIS MIDDLE LOCKERS The Sumner County Board of Education, herein known as School System, is soliciting bids for the purchase and installation of new lockers. The vendor must include cost
More informationInvitation to Bid CUSTODIAL PAPER PRODUCTS
Invitation to Bid CUSTODIAL PAPER PRODUCTS 2013-2014 Responses to an Invitation to Bid will be received by the Purchasing Coordinator, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN
More informationInvitation to Bid THEATRE LIGHTING UPGRADE - MHM
Invitation to Bid THEATRE LIGHTING UPGRADE - MHM Responses to an Invitation to Bid will be received by the Purchasing Supervisor, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN 37066
More informationDMS HIGH MAST LIGHT FIXTURES
DMS - 11020 EFFECTIVE DATE: JANUARY 2012 11020.1. Description. This specification governs the materials, composition, and quality of 400 watt (W) high pressure sodium (HPS) tenon-mounted high mast light
More informationInvitation to Bid BOE TRASH LINERS
Invitation to Bid 20170328-2 -BOE TRASH LINERS Responses to an Invitation to Bid will be received by the Purchasing Supervisor, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN 37066 for
More informationInvitation to Bid BOE SANITIZER/DISINFECTANT
Invitation to Bid 20170328-BOE SANITIZER/DISINFECTANT Responses to an Invitation to Bid will be received by the Purchasing Supervisor, Sumner County Board of Education, and 1500 Airport Road, Gallatin,
More informationPenn State Forestland Management Office Multi-Strand High-Tensile Wire Fence Specifications
Penn State Forestland Management Office Multi-Strand High-Tensile Wire Fence Specifications 1. FENCE REQUIREMENTS Hazard Trees All hazard trees, which are within tree length of the fence, must be felled
More informationREQUEST FOR BIDS Public Works Contract SPECIFICATIONS FOR FENCE REPAIRS AND REPLACEMENT
REQUEST FOR BIDS Public Works Contract SPECIFICATIONS FOR FENCE REPAIRS AND REPLACEMENT DATE OF RELEASE: DATE OF CLOSING: RFB ID: July 18, 2013 at 8:00 am (cst) August 5, 2013 at 4:30 pm (cst) 0718201301
More informationA. Product Data shall be provided for each type of product indicated.
32 31 13 CHAIN LINK FENCES AND GATES SECTION 1 GENERAL 1.1 SUMMARY This Section includes the following: 1. Chain Link Fences 2. Gates for Chain Link Fences. See electrical specifications for electrical
More informationCONSTRUCTION SPECIFICATION FOR INSTALLATION OF ROADWAY LUMINAIRES
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 617 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ROADWAY LUMINAIRES TABLE OF CONTENTS 617.01 SCOPE 617.02 REFERENCES 617.03 DEFINITIONS
More informationMATERIAL SPECIFICATION FOR HIGH PRESSURE SODIUM LUMINAIRES FOR HIGHWAY LIGHTING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 2432 NOVEMBER 2015 MATERIAL SPECIFICATION FOR HIGH PRESSURE SODIUM LUMINAIRES FOR HIGHWAY LIGHTING TABLE OF CONTENTS 2432.01 SCOPE 2432.02 REFERENCES
More informationMinimum Standards for Construction of Aircraft Hangars MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS
Minimum Standards for Construction of Aircraft Hangars ARTICLE 1. MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS Section 1. - Purpose Section 2. - Goals Section 3. General Provisions Section 4.
More informationAutomated Cantilevered Aluminum Sliding Gate
Town of Derry, New Hampshire REQUEST FOR PROPOSALS B18-128 January 25, 2018 The Town of Derry - Department of Public Works is seeking proposals for: Automated Cantilevered Aluminum Sliding Gate Introduction
More informationCONSTRUCTION SPECIFICATION FOR INSTALLATION OF ROADWAY LUMINAIRES
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 617 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ROADWAY LUMINAIRES TABLE OF CONTENTS 617.01 SCOPE 617.02 REFERENCES 617.03 DEFINITIONS
More informationHIGH MAST CAMERA POLE ASSEMBLY GENERAL
10-3.24 HIGH MAST CAMERA POLE ASSEMBLY GENERAL The Contractor must furnish and install the following equipment for high mast camera pole assembly as described herein and as shown on the plans: 1. Camera
More informationSECTION CHAIN LINK FENCING
Section 02444 1 SECTION 02444 CHAIN LINK FENCING PART 1 - GENERAL 1.01 DESCRIPTION A. Requirement. Under these specifications, the Contractor shall furnish all materials, labor, tools, and equipment required
More informationSpecial Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control
Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control 1. DESCRIPTION 2. MATERIALS Furnish, install, relocate, or remove radar vehicle detection systems (RVDS) of
More informationSECTION GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL
1.01 DESCRIPTION SECTION 16000 GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL A. This Section includes the general provisions applicable to electrical work and testing of the completed electrical systems.
More informationOVERHEAD SERVICES - SECONDARY
OVERHEAD SERVICES - SECONDARY Contents - Overhead Services... O-1 General Requirements for Overhead Service... O-2 Names of Parts for Overhead Service... O-3 Service Attachment on an Unguyed Service Mast...
More informationSECTION 1101 TRAFFIC SIGNALS AND APPURTENANCES END OF SECTION
SECTION 1101 SIGNALS AND APPURTENANCES PART 1 GENERAL 1.4 SUBMITTALS E. Submit warranty for all supplied material and workmanship for a period of two years from final acceptance. The warranty must state
More informationSPECIAL SPECIFICATION 8710 Decorative Pole Lighting Assembly
2004 Specifications CSJ 0902-48-682, 0902-48-825 & 0902-48-826 SPECIAL SPECIFICATION 8710 Decorative Lighting Assembly 1. Description. Furnish and install a Decorative Lighting Assembly (Type A) as shown
More informationInvitation to Bid Running Track
Invitation to Bid 20160621-Running Track Responses to an Invitation to Bid will be received by the Purchasing Supervisor, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN 37066 for 20160621-Running
More informationREVISION OF SECTION 623 IRRIGATION SYSTEM GENERAL
623.01 SUMMARY: GENERAL Section Includes: Landscape irrigation system as shown on the drawings for complete coverage to landscape areas. Furnish design for layout, pipe sizing, valving and head types and
More informationSTATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY METRIC SPECIFICATIONS FOR HIGH PRESSURE SODIUM LUMINAIRES OFFSET TYPE
STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY 08625 METRIC SPECIFICATIONS FOR HIGH PRESSURE SODIUM LUMINAIRES OFFSET TYPE N.J. Specification No. Effective Date: July 1, 2001 New
More informationSTREET LIGHTING GENERAL INFORMATION
SECTION 1102 STREET LIGHTING GENERAL INFORMATION These specifications are for street lighting that is to be dedicated to the public and maintained by the City of Meridian. Such installations require a
More informationSpecial Specification 6156 LED High Mast Illumination Assemblies
Special Specification LED High Mast Illumination Assemblies 1. DESCRIPTION 2. MATERIALS 3. EQUIPMENT Installation. Furnish and install light emitting diode (LED) high mast illumination assemblies. Replace
More informationCity of New Haven. 101 FRONT STREET PO BOX 236 NEW HAVEN, MO Phone * * Fax
City of New Haven 101 FRONT STREET PO BOX 236 NEW HAVEN, MO 63068 Phone 573-237-2349 * www.newhavenmo.org * Fax 573-237-4696 February 19, 2013 Request for Bids New Haven City Park Bock Field fencing The
More informationSpecial Specification 6244 LED High Mast Illumination Assemblies
Special Specification 6244 LED High Mast Illumination Assemblies 1. DESCRIPTION 2. MATERIALS 3. EQUIPMENT Furnish and install light emitting diode (LED) high mast illumination assemblies. Provide new materials
More informationSTANDARD SHELTER SPECIFICATIONS ATTACHMENT A
STANDARD SHELTER SPECIFICATIONS 16-04 ATTACHMENT A Issued: November 2, 2015 Technical Specifications ---------------------------------------------------------------------------------------------------------------
More informationCONSTRUCTION STANDARDS SECTION CS 15 STREET LIGHTING
CONSTRUCTION STANDARDS SECTION CS 15 STREET LIGHTING CS 15-0l SCOPE: Street Lighting improvements shall be constructed in conformance with Section 86, Signals, Lighting and Electrical Systems, of the CALTRANS
More informationBus Facility
SECTION 32 31 13.53 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More informationINVITATION TO BID CITY OF HOPKINSVILLE
INVITATION TO BID CITY OF HOPKINSVILLE Office of the Procurement Specialist 715 South Virginia Street P. O. Box 707 Hopkinsville, Kentucky 42241-0707 TITLE: DESIGN BUILD BUIDLING FOR THE CITY OF HOPKINSVILLE,
More informationSECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 05 26 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph
More informationSECTION CHAIN-LINK FENCES AND GATES 02821/1
SECTION 02821 - CHAIN-LINK FENCES AND GATES 02821/1 PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Chain-Link Fences: 2. Gates: horizontal slide or swing. 3. Fences installed where
More informationELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION PAGE 1 SECTION EXTERIOR ATHLETIC LIGHTING
KNOXVILLE, TENNESSEE SECTION 16461 PAGE 1 SECTION 16526 EXTERIOR ATHLETIC LIGHTING 1PART - LIGHTING PERFORMANCE The lighting systems manufacturer shall supply equipment to meet or exceed the following
More informationGUIDE SPECIFICATION EXETER VERSA SHIELD SECURITY SCREEN SYSTEM
1 GUIDE SPECIFICATION EXETER VERSA SHIELD SECURITY SCREEN SYSTEM 1.01 WORK INCLUDED PART 1: GENERAL A. Provide for all labor, equipment, materials, and services to furnish and install VERSA SHIELD Window
More informationMATERIAL SPECIFICATION FOR HIGH PRESSURE SODIUM LUMINAIRES FOR UNDERPASS LIGHTING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 2434 November 2016 MATERIAL SPECIFICATION FOR HIGH PRESSURE SODIUM LUMINAIRES FOR UNDERPASS LIGHTING TABLE OF CONTENTS 2434.01 SCOPE 2434.02 REFERENCES
More informationPower Electronics, Inc. Packaged Equipment Center Standard Construction and Design Features
DESIGN CRITERIA FOR STANDARD CONSTRUCTION: These standard design elements of the P.E.I. Power Equipment Center are utilized to meet the following design criteria per ASCE 7-05 as adopted by the IBC (International
More informationSTREET LIGHTING. Springville City Power standard street lights will be installed in accordance with Springville City Power's Line Extension Policy.
General The following general requirements shall apply to street lights installed in new underground residential subdivisions or developments located within the service area of Springville City Power (within
More information6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.
6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection
More informationITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION
SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the
More informationOPERATING PROCEDURE NO. 310
OPERATING PROCEDURE NO. 310 Related Operating Procedures: 310A; 310B; 310C; 310D SUBJECT: Conditions of Service Issued: February 10, 2014 Revised: March 28, 2016 OBJECTIVE: To establish the rules, regulations
More informationSPECIAL SPECIFICATION 1276 Pedestrain Overpass Lighting
1993 Specifications CSJ 0074-06-199 SPECIAL SPECIFICATION 1276 Pedestrain Overpass Lighting 1. Description. This Item shall govern for furnishing and installing the various types of lighting fixtures,
More information1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK
1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for
More informationSECTION BASIC ELECTRICAL REQUIREMENTS
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions, apply to work of this section. 1.2 SUMMARY A. This section specifies
More information4. GENERAL REQUIREMENTS
4. GENERAL REQUIREMENTS 4.1 APPLICATION FOR SERVICE Application for service must be made to, and accepted by, the Company before service will be furnished. At the time of application, the Customer shall
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION
KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Sheet 1 of 7 NOTE: This special provision is generally written in the imperative mood. The subject, the
More informationA. Section Cast-in-Place Concrete: Materials and installation requirements for concrete bases for poles.
SECTION 265600 - EXTERIOR LIGHTING PART 1 GENERAL 1.1 SECTION INCLUDES A. Exterior luminaires. B. Ballasts. C. Lamps. D. Poles and accessories. E. Luminaire accessories. 1.2 RELATED REQUIREMENTS A. Section
More informationUNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:
SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract apply to this Section. 1.2 SUMMARY A. This Section
More informationITEM 555 CHAIN LINK FENCING
ITEM 555 AFTER MARCH 1, 2012 CHAIN LINK FENCING 555.1 Description. This item shall govern for furnishing the quantities of chain link fencing and gates as shown on the plans, including all posts, bracing
More informationSTATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY SPECIFICATIONS FOR HIGH PRESSURE SODIUM LUMINAIRES, CUTOFF TYPE
STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY 08625 SPECIFICATIONS FOR HIGH PRESSURE SODIUM LUMINAIRES, CUTOFF TYPE N.J. Specification No. Effective Date: July 1, 2001 New Jersey
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SPUN CONCRETE POLE AND DRILLED SHAFT FOUNDATION
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SPUN CONCRETE POLE AND DRILLED SHAFT FOUNDATION ITS:CLC 1 of 7 APPR:LWB:DBP:08-01-13 FHWA:APPR:09-23-13 a. Description. This work consists of
More informationThis Addendum Number One forms part of the Contract Documents and modifies the original Bidding Documents dated June 8, 2016.
ADDENDUM NUMBER ONE - June 15, 2016 CITY OF CLARKSVILLE TO: All Bidders of Record This Addendum Number One forms part of the Contract Documents and modifies the original Bidding Documents dated June 8,
More informationCITY OF PORTSMOUTH Department of Public Works. BID #31-16 South Mill Pond Tennis Courts ADDENDUM #1 May 18, 2016
CITY OF PORTSMOUTH Department of Public Works BID #31-16 South Mill Pond Tennis Courts ADDENDUM #1 May 18, 2016 This Addendum forms part of the original bid document marked Bid 31-16 South Mill Pond Tennis
More informationADDENDUM No. 4. Sealed Bid # New Improvements to Powder Springs Park Cobb County Parks, Recreation, and Cultural Affairs Department
ADDENDUM No. 4 Sealed Bid #14-5934 New Improvements to Powder Springs Park Cobb County Parks, Recreation, and Cultural Affairs Department Page 1 of 20 Date: July 11, 2014 The following addendum hereby
More informationTECHNICAL SPECIFICATION
SECTION -IV TECHNICAL SPECIFICATION OF ELECTRICAL MATERIALS LIGHT FITTINGS GROUP D Tender Notice No. NESCO Utility / O&M Materials/09 / 7519, dtd.08.07.16 Page 1 Group-D Sl no. Material Description Unit
More informationWEST BOUNTIFUL CITY, UTAH REQUEST FOR PROPOSAL. City Park Playground Equipment.
1.0 INTRODUCTION WEST BOUNTIFUL CITY, UTAH REQUEST FOR PROPOSAL City Park Playground Equipment The West Bountiful City, Utah is seeking proposals from interested Applicants to furnish and install playground
More informationA. Section includes busway and fittings including plug-in units.
SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:
More informationSWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS
Building Inspections SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Permit Applications Pool permit applications are now being accepted online at http://etrakit.flower-mound.com/. Starting November 1,
More information5-1 Street Lights Required Street Lights on Private Roadways Developer s Responsibility...5-1
SECTION 5 STREET LIGHTING CONTENTS Page 5-1 Street Lights Required...5-1 5-2 Street Lights on Private Roadways...5-1 5-3 Developer s Responsibility...5-1 5-4 Utility Company Authorization...5-1 5-5 General
More informationAttachment A Repair Knee Brace on High Arch Salt Building Fayette County, Mill Run Stockpile #24 Project # Building #PA
I. Base Bidding Requirements This is a Base Bid project; the following describes the Base Bid requirements. Contractors are to provide bids for Base Bid #1. A. BASE BID #1: II. Work Included The following
More informationProject: Type: Qty: Optics. Series. Reflector Mounting Lamping Finish Voltage Options BLC - S BLC-L 21 1 /4" 36 1 /4" 3 1 /2" O.D.
Project: Type: Qty: Series Optics Mounting Lamping Finish Voltage Options Pole Series Finish Pole Options Series Optics Mounting Lamping Finish Voltage Options BLC Beta Lantern L S Flat Glass Lens Sagged
More information~lamance <tount!' 9'~UUJ ;i)epwdment 124 We6t ElmStltm (j,taluun,.ncjjdli &vwfina 27253!Jefepfwae(336) :Jax(336)
~lamance
More informationJordan, Gilbert & Bain Landscape Architects, Inc. 459 North Ventura Avenue, Ventura, California (805) Phone; (805) Fax
ADDENDUM #2 Date: December 5, 2018 Issued By: Jordan, Gilbert & Bain Landscape Architects, Inc. 459 North Ventura Avenue, Ventura, California 93001 (805) 642-3641 Phone; (805) 653-7874 Fax Project: Freedom
More informationURS 101 Research Drive Columbia, SC Phone: (803) Fax: (803) Posted to USC Website May 24, 2013
URS 101 Research Drive Columbia, SC 29203 Phone: (803) 254-4400 Fax: (803) 771-6676 Posted to USC Website May 24, 2013 RE: Athletic Village Sand Volleyball Court Construction For the University of South
More informationDIVISION 1100 TRAFFIC
SECTION 1102 STREET LIGHTING GENERAL INFORMATION The Idaho State Electrical Board has determined that all street lights are to be provided with an external fuse disconnect, in a junction box between the
More informationCONSTRUCTION SPECIFICATION FOR INSTALLATION OF UNDERPASS LUMINAIRES
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 611 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF UNDERPASS LUMINAIRES TABLE OF CONTENTS 611.01 SCOPE 611.02 REFERENCES 611.03 DEFINITIONS
More informationCOMMUNITY COLLEGE DISTRICT OF JEFFERSON COUNTY, MISSOURI REQUEST FOR PROPOSAL: WINDOW, DOOR, AND FRAME REPLACEMENT
COMMUNITY COLLEGE DISTRICT OF JEFFERSON COUNTY, MISSOURI REQUEST FOR PROPOSAL: WINDOW, DOOR, AND FRAME REPLACEMENT RFP # 1710002 Sheree Bell Due Date: November 30, 2017 Procurement Coordinator Not later
More informationGARDEN CITY STNANDARD REVISIONS FOR ISPWC DIVISION 1102 STREETLIGHTS
GARDEN CITY STNANDARD REVISIONS FOR ISPWC DIVISION 1102 STREETLIGHTS General Information All work shall conform to the requirements of the latest edition of the Idaho Standards for Public Works Construction
More informationCAMINO REAL REGIONAL MOBILITY AUTHORITY BOARD RESOLUTION
CAMINO REAL REGIONAL MOBILITY AUTHORITY BOARD RESOLUTION WHEREAS, the Camino Real Regional Mobility Authority (CRRMA) entered into a construction contract dated October 24, 2016 (Contract) with International
More informationCONTRACT PROPOSAL/CONTRACT ACCEPTANCE HIGDON LOOP ROAD BRIDGE
CONTRACT PROPOSAL/CONTRACT ACCEPTANCE PROJECT # 2017-NC-001 For Construction of HIGDON LOOP ROAD BRIDGE located in Nelson County Kentucky 09/2017 REQUEST FOR BIDS HIGDON LOOP ROAD BRIDGE REPLACEMENT Nelson
More informationMade in U.S.A. Moai Bike Rack Submittal Sheet. Materials: Finishes: Mount Options: Capacity: Setbacks: 2 Bikes
Submittal Sheet Materials: 1. 5 Schedule 40 Steel Pipe (1.90 OD) Finishes: Galvanized An after fabrication hot dipped galvanized finish is available. Powder Coat Our powder coat finish assures a high level
More information***************************************************************************************************************
03365 POST-TENSIONED CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 38 00. ***************************************************************************************************************
More information4. GENERAL REQUIREMENTS
4. GENERAL REQUIREMENTS 4.1 APPLICATION FOR SERVICE Application for service must be made to, and accepted by, the Company before service will be furnished. At the time of application, the Customer shall
More informationCITY OF DE SOTO Miller Park Trail Extension and Picnic Table Pads
CITY OF DE SOTO Miller Park Trail Extension and Picnic Table Pads City of De Soto Johnson County, Kansas PREPARED BY: City of De Soto, Kansas 32905 West 84 th Street De Soto, Kansas 66018 SPECIFICATIONS
More informationURS 101 Research Drive Columbia, SC Phone: (803) Fax: (803) Posted to USC Website May 30, 2013
URS 101 Research Drive Columbia, SC 29203 Phone: (803) 254-4400 Fax: (803) 771-6676 Posted to USC Website May 30, 2013 RE: Athletic Village Sand Volleyball Court Construction For the University of South
More informationSPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work
2004 Specifications CSJ 0027-12-134 SPECIAL PROVISION 000--2823 Description of Project, Scope of Contract and Sequence of Work 1. General. The work to be performed on this project consists of furnishing,
More informationSpecifications. For Installation of Hurricane Shutters or Sliding Glass-Enclosure Doors. The Dunes of Naples I, II, Sea Grove
Specifications For Installation of Hurricane Shutters or Sliding Glass-Enclosure Doors The Dunes of Naples I, II, Sea Grove Table of Contents Resolution of the Board of Directors...Page 3 Insurance Requirements..Page
More informationRFP NO AMENDMENT No. 2 Page 1 of 11
RFP/Solicitation # 2017-0123 Richland County School District One Date Issued November 4, 2016 REQUEST FOR PROPOSAL Procurement Officer Harrison Joseph Phone 803.231.7052 AMENDMENT NO. 2 E-mail Address
More informationSECTION STRUCTURE MOUNT RAILING SYSTEM
SECTION 05520 STRUCTURE MOUNT RAILING SYSTEM Peak Fall Protection specializes in the design, engineering, fabrication, installation, and certification of fall protection safety systems. Our team of safety
More informationa) Line and load compartments must be separated by a stable barrier.
1.00 GENERAL 1.01 The electric utility shall furnish and connect all meters, instrument transformers, test switches, and meter control wiring necessary to complete the meter installation. 1.02 The customer
More informationSPECIAL SPECIFICATION 1924 Neighborhood Friendly High Mast Illumination System
1993 Specifications CSJ 2374-01-154 SPECIAL SPECIFICATION 1924 Neighborhood Friendly High Mast Illumination System 1. Description. This Item shall govern for furnishing and installing the various types
More informationATTACHMENT A. Bid # 6793
ATTACHMENT A SCOPE OF WORK TECHNICAL SPECIFICATIONS AND CONTRACT DRAWINGS STORAGE SHED INSTALLATION AT THE SAN JOAQUIN COUNTY HOUSEHOLD HAZARDOUS WASTE FACILITY Bid # 6793 Department of Public Works Solid
More informationSECTION LIGHTNING PROTECTION SYSTEM
SECTION 16670 - LIGHTNING PROTECTION SYSTEM PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. General: Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationSMALL CELL DESIGN GUIDELINES
Section 1: Collocations on Existing Wireless Support Structures (Type I and II Requests) 1.1 Collocations Encouraged. The collocation of wireless facilities on existing support structures engineered to
More informationFinance & Technology Administrator (815) ext 223
2017 PAVING IMPROVEMENTS BID PACKET Due: Location: April 26, 2017 by 10:00 am Oregon Park District Fairgrounds Park 607 Fair Park Drive Oregon, IL 61061 Bid Proposal: 2017 Paving Improvements Administrative
More informationSECTION MOTOR CONTROL CENTER
SECTION 16445 MOTOR CONTROL CENTER PART 1 GENERAL 1.01 DESCRIPTION A. This section covers the contract item Motor Control Center (MCC). The contract item includes demolition and removal of existing MCC;
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER. OPR:CT 1 of 5 APPR:JAR:DBP: FHWA:APPR:
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER OPR:CT 1 of 5 APPR:JAR:DBP:09-07-11 FHWA:APPR:09-07-11 a. Description. This work consists of furnishing and installing
More information