CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS

Size: px
Start display at page:

Download "CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS"

Transcription

1 CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS WJ Martin 17.1 SCOPE Specialist construction systems refer to the construction systems falling outside of the normal reinforced and prestressed bridges that make up the bulk of bridges in South Africa. These structures generally fall outside of the experience of the average South African resident engineer. Specialist construction systems include: Bridges constructed using the Incremental Launch Method (ILM); Balanced Cantilever bridges (BC); Precast Segmental construction (PSC); Jacked bridges; Cable stayed bridges and suspension bridges; Concrete arch bridges; Steel bridges and composite steel bridges; Bridges constructed from timber, brick, stone or composite materials Although the other chapters in the Construction Monitoring Manual cover many aspects which are applicable to the above specialist construction systems, they do not cover all of the requirements on the construction site. This chapter deals very briefly with the specialist requirements but, as very few bridges of this nature are constructed in South Africa, this chapter cannot be considered as comprehensive. FOR THESE SPECIALIST CONSTRUCTION SYSTEMS, SPECIALIST LITERATURE SHOULD BE CONSULTED VOIDED SLAB DECKS Although voided slab decks are relatively common, problems do occur with the void formers. Because of this, it is discussed in more detail below. These comments also apply to any other formwork which may have resultant concrete pressures which are not horizontal Void formers In order to understand the need to have void formers that are strong and properly tied down, it is necessary understand the buoyant or hydrostatic properties of wet concrete. Wet concrete is about 2.5 times denser than water; therefore it is 2.5 times more buoyant than water. If you imagine the forces on a void former in water, then the forces of the same void former in concrete will be 2.5 times greater. When a void former is immersed in wet concrete, the hydrostatic forces trying to crush the void former are very large. Adequate stiffening inside the void former is required. Originally this used to be timber cross-bracing but recently polystyrene disks at frequent centres are used. The closures at the ends of void formers also need to withstand this hydrostatic pressure and be watertight. It is not adequate to have a few pop-rivets around the circumference there need to be quite a REHABILITATION AND REPAIR OF STRUCTURES 17-1

2 few closely spaced pop-rivets. If two void formers are butted up against each other, with a small gap, the hydrostatic pressure will be the same as if there was a large gap. Once again, the ends need to be adequately fixed. While concrete is being cast, the voids will want to float on top of the concrete. They must be tied down with sufficient ties to withstand this buoyancy. If concrete is cast higher on one side of a void than the other, as is inclined to happen, the void will want to move sideways as well. The ties must be able to resist this sideways movement. In summary, the site monitoring staff need to ensure that the contractor has considered the following: There is sufficient bracing inside the void formers; The ends of the void formers are firmly attached to the void formers; The ties holding the void formers down can resist the buoyancy forces; and The ties holding the void formers down will restrain lateral movement INCREMENTAL LAUNCH METHOD (ILM) ILM bridges have become more common recently. This section does not give guidance on construction monitoring of ILM bridges. It only highlights some major construction aspects that need to be monitored. When monitoring the construction of and ILM bridge, specialist literature must be referred to. Some of the major construction aspects include: Construction tolerances these are more critical than in normal construction. Special attention and accurate surveying is required to ensure millimetre accuracy. Temporary works: This is highly specialized Launching nose, temporary bearings, launching jacks, braking system, etc. Pier deflections: This must be limited to avoid damage to the piers and excessive movement when bearing friction is overcome. Launching nose and connection: This is a critical piece of equipment and needs to be properly fabricated and installed. If its stiffness varies from the design launching nose, it needs to be checked. Emergency stop equipment: When something goes wrong such as a bearing pad installed incorrectly, the launching must be stopped immediately to avoid damage or injury. Construction loads and superimposed dead loads (parapets, etc): do these comply with the design requirements? Cumulative deck length: allowance needs to be made for shortening due to prestressing, creep and shrinkage. Stability during construction: This is significant during the first few launchings. Lateral and longitudinal fixity between launches is also a consideration. Launching downhill will require braking and restraining devices. Launching bearing pads must resist rotation. Installation of the permanent bearings needs consideration. Concrete strength before prestressing and launching is an issue. REHABILITATION AND REPAIR OF STRUCTURES 17-2

3 Construction Tolerance For ILM construction, the accuracy of the sliding surfaces and alignment plays a primary role in creating a stress-free construction site. Many problems during launching can be traced back poor accuracy or poor alignment. Incorrect deck or segment lengths: If there is an error here, especially if the shortening due to prestressing, shrinkage and creep has not been taken into account, then the deck ends up being too short and the bearing diaphragms or bearing attachments are in the incorrect position. Allow for shortening due to prestressing, creep and shrinkage; and Check the length of the bridge between launches, starting from the front of the deck. Levels on sliding surfaces in casting yard not to specification: If the levels are out, this causes additional friction and makes it difficult to feed the launching bearing pads in correctly. Horizontal alignment is not to specification: If the horizontal alignment between segments is out, this causes part of the deck or all of the deck to curve inwards or outwards during launching. This leads to problems with feeding in the side guide sliding pads. This occurs with curved decks as it is much easier to align straight decks. It also leads to problems where at some of the piers, the deck can be out transversely by more than 70 mm, affecting the positioning of the temporary launching bearings and the permanent bearings. Vertical alignment is not to specification: This can change the bearing reactions during launching significantly. It may overload some bearings, causing cracking in the deck and damage of the sliding surfaces. It will also increase the horizontal loads which can damage piers. Casting yard foundations too elastic: This affects the vertical alignment as discussed above. Before a segment is cast, the sliding surface levels are checked in the casting yard and found to be within specification. However, when the segment is cast, the foundations deflect downwards and sometimes tilts, causing the vertical alignment to now be out of specification. Launching bearing pad thickness: When the bearing pads arrive on site, their thicknesses should be checked against the specifications. Furthermore, they should be sorted in terms of thickness to the nearest 0.2 mm so that on each pier, all of the pads used are of similar thickness. This will reduce friction and bearing overload and make it easier to feed the pads in. REHABILITATION AND REPAIR OF STRUCTURES 17-3

4 Launching nose The contractor needs to produce calculations showing that the launching nose is strong enough to withstand the launching forces including any additional forces due to lack-of-fit caused by the construction tolerances. The prestressing in the launching nose connection should be correctly stressed. Too little stress will lead to the connection opening up and increasing the load on the next pier. The prestressing force in the launching nose connection should be checked from time to time between launches. During launching when the bending force in the launching nose is approaching its maximum, the connection should be checked for the nose lifting off the deck Monitoring pier deflections If pier deflections are within specification, this means that the friction generated during launching falls within design limits. When pier deflections exceed specification, this means that something has gone wrong. It is therefore important that pier deflections be monitored continuously during launching. Photo 17.1: Zambezi River Bridge constructed using ILM REHABILITATION AND REPAIR OF STRUCTURES 17-4

5 17.4 BALANCED CANTILEVER CONSTRUCTION (BC) Very few balanced cantilever bridges have been constructed in South Africa. The Mfolozi River Bridge on the north coast of KZN is an example. Photo 17.2: An abnormal load crossing the Mfolozi River Bridge Some issues needing specialist consideration include: During construction, the deck levels change continuously. Very careful calculation is required to ensure that the bridge reaches its required vertical alignment. Creep and shrinkage affects the vertical alignment and needs to be continually monitored on site. Constant correction is needed to ensured correct vertical alignment. The contractor s construction sequence and weight of temporary works will affect the alignment if these are different to the design assumptions. Stability during construction is an issue. Until the cantilevers are joined up, they are vulnerable, especially to wind loading Vertical alignment during construction As the deck is constructed, each load added or moved causes the deck to deflect. Creep and shrinkage increases the deflection. Once the joints between the cantilevers are closed and the deck made continuous, the deck continues to deflect due to creep and shrinkage. The objective is to get the vertical alignment correct for some stage after construction, usually when the bridge is opened to traffic or at some time after that. REHABILITATION AND REPAIR OF STRUCTURES 17-5

6 17.5 PRECAST SEGMENT CONSTRUCTION (PSC) One of the first PSC bridges in South Africa was the Buffalo River Bridge in East London. The Gautrain Viaducts were also constructed using this method. Some issues needing specialist consideration include: Segments need to be match-cast and glued together. Temporary prestressing is required during the gluing process. Operation of the launching gantry is important to prevent overloading of the segments during prestressing. Prestressing across the construction joints need attention to ensure durability. Photo 17.3: Buffalo River Bridge at East London: One of the precast segments can be seen in the foreground REHABILITATION AND REPAIR OF STRUCTURES 17-6

7 17.6 JACKED BRIDGES It is becoming more common to construct jacked bridges under railway line embankments these days. Photo 17.4: Bridge on the N17 about to be jacked under the rail embankment Some issues that need specialist consideration during bridge jacking include: Railway tracks need to be supported so that rail traffic can continue during construction. Jacking forces need to overcome very high friction between the sides of the structure and the retained earth. These forces need to be resisted in some way. The foundations need to be constructed first through the embankment, usually by pipe-jacking. These form the sliding surface during construction. Stability of the front excavation face needs careful consideration REHABILITATION AND REPAIR OF STRUCTURES 17-7

VIADUCTS BY PUSHING: INCREMENTALLY LAUNCHED BRIDGES

VIADUCTS BY PUSHING: INCREMENTALLY LAUNCHED BRIDGES Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey VIADUCTS BY PUSHING: INCREMENTALLY LAUNCHED BRIDGES J. E. Erdoğan 1 and Ö. Özkul 2 ABSTRACT Despite its widespread use around the world, constructing

More information

Bridge articulation No. 1.04

Bridge articulation No. 1.04 Bridge articulation Scope This Guidance Note gives advice on the selection of the articulation arrangements, the choice of bearing types and dispositions of bearings, for bridges where relative movement

More information

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure C.Y. Shao Shanghai Municipal Engineering Design & Research General Institute (Group) Co. Ltd.,

More information

Design of Steel-Concrete Composite Bridges

Design of Steel-Concrete Composite Bridges Design of Steel-Concrete Composite Bridges to Eurocodes Ioannis Vayas and Aristidis Iliopoulos CRC Press Taylor & Francis Croup Boca Raton London New York CRC Press is an imprint of the Taylor & Francis

More information

CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE

CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE By Masakazu Matsubara Resident Engineer for Approach & Main Bridge Suramadu Bridge Project 1. DESIGN 1.1. Concept of Design of Cantilever Erection

More information

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Design of continuity slabs and the 020 Gajanan Chaudhari Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Anand Panpate Senior Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

More information

Highway Bridge Structure Components

Highway Bridge Structure Components Highway Bridge Structure Components Basic Bridge Components 1 Deck and 2 Stringer 3 Bearing 4 Pedestal 5 Footing 6 Piles 7 Underpass 8 Embakment 9 Live Loading Basic Bridge Components 1-Deck & wearing

More information

Concrete Bridge Design and Construction series

Concrete Bridge Design and Construction series www.thestructuralengineer.org 41 CBDC series July 2014 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG). The group aims to promote

More information

Concrete Bridge Design and Construction series

Concrete Bridge Design and Construction series 40 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG). The group aims to promote excellence in the design, construction and management

More information

MIDAS Training Series

MIDAS Training Series MIDAS midas Civil Title: All-In-One Super and Sub Structure Design NAME Edgar De Los Santos / MIDAS IT United States 2016 Substructure Session 1: 3D substructure analysis and design midas Civil Session

More information

The bridge over the Georges River at Alfords Point has been duplicated with a new incrementally launched bridge.

The bridge over the Georges River at Alfords Point has been duplicated with a new incrementally launched bridge. The Design and Construction of Alfords Point Bridge Mark Bennett, Senior Bridge Engineer (New Design) RTA Harry Cheung, Project Engineer, RTA Trung Doan Project Engineer, RTA Synopsis The bridge over the

More information

Construction and design features of the Bridge over the Danube River. Bulgaria

Construction and design features of the Bridge over the Danube River. Bulgaria Construction and design features of the Bridge over the Danube River. Bulgaria Javier MANTEROLA Pr. Dr. jmanterola@cfcsl.com Antonio MARTÍNEZ Dr. amartinez@cfcsl.com Juan Antonio NAVARRO janavarro@cfcsl.com

More information

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit 2004 Specifications CSJ: 0028-09-111 SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit 1. Description. Construct cast-in-place segmental concrete box girder superstructure according to the plans,

More information

Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables

Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables J. Manterola A. Martínez Carlos Fernández Casado S.L., Spain B. Martín J.A. Navarro M. A:

More information

The content for this class has been provided by the following PB employees: With assistance from: Martine Klein, P.E. Narration by Greg Metzger, PB

The content for this class has been provided by the following PB employees: With assistance from: Martine Klein, P.E. Narration by Greg Metzger, PB 1 The content for this class has been provided by the following PB employees: With assistance from: Martine Klein, P.E. Narration by Greg Metzger, PB University If you have any questions about the content

More information

When building the arch, a provisional upright must be put on the pier placed on the roots of the arch.

When building the arch, a provisional upright must be put on the pier placed on the roots of the arch. The Cieza Viaduct Michael Müller Pondio Ingenieros, Madrid Summary: In the last few years the amount of arch bridges built in Spain has increased considerably. Even though these type of bridges are expensive

More information

4/14/2015 INTRODUCTION. Dr. AZ Department of Civil Engineering Brawijaya University BRIDGES

4/14/2015 INTRODUCTION. Dr. AZ Department of Civil Engineering Brawijaya University BRIDGES INTRODUCTION Dr. AZ Department of Civil Engineering Brawijaya University BRIDGES A bridge is a structure built to span a valley, road, body of water, or other physical obstacle, for the purpose of providing

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

Design and construction of Hechang Bridge, Quanzhou, China

Design and construction of Hechang Bridge, Quanzhou, China Design and construction of Hechang Bridge, Quanzhou, China G. Peng and B. Chen College of Civil Engineering, Fuzhou University, Fuzhou 302, China ABSTRACT: Hechang Bridge is a pedestrian bridge, located

More information

UNIT V PART A

UNIT V PART A 1. Why concrete bridges are used? [N/D 14] UNIT V PART A a. Reinforced concrete and prestressed concrete have been found most suited for the construction of high way bridges the former for small and medium

More information

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction Introduction This memo presents a summary of a three dimensional (3D) analysis of the Organic concept for the proposed St. Croix River bridge project. The Organic concept has several attributes that are

More information

STRESS-RIBBON BRIDGES STIFFENED BY ARCHES OR CABLES

STRESS-RIBBON BRIDGES STIFFENED BY ARCHES OR CABLES 2nd Int. PhD Symposium in Civil Engineering 1998 Budapest STRESS-RIBBON BRIDGES STIFFENED BY ARCHES OR CABLES Tomas Kulhavy Technical University of Brno, Department of Concrete and Masonry Structures Udolni

More information

New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia.

New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia. New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia. J. Manterola S. Fernández S. Fuente J. Muñoz-Rojas J. A. Navarro ABSTRACT The overall length of the new bridge over the River Magdalena

More information

Concrete Bridge Design and Construction series

Concrete Bridge Design and Construction series 42 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG) The group aims to promote excellence in the design, construction and management

More information

BRIDGES WITH PROGRESSIVELY ERECTED DECKS

BRIDGES WITH PROGRESSIVELY ERECTED DECKS Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey BRIDGES WITH PROGRESSIVELY ERECTED DECKS P. Novotny 1, P. Svoboda 2 and J. Strasky 3 ABSTRACT Two types of bridges with progressively erected

More information

AUGUST 2016 LRFD BRIDGE DESIGN 3-1

AUGUST 2016 LRFD BRIDGE DESIGN 3-1 AUGUST 2016 LRFD BRIDGE DESIGN 3-1 3. LOADS AND LOAD FACTORS The loads section of the AASHTO LRFD Specifications is greatly expanded over that found in the Standard Specifications. This section will present

More information

Earth Retaining Structures and Systems Submittal Checklist. Part One: Materials and Material Properties

Earth Retaining Structures and Systems Submittal Checklist. Part One: Materials and Material Properties Earth Retaining Structures and Systems Submittal Checklist Part One: Materials and Material Properties Provide a sample of the reinforcement material and material specifications describing the material

More information

2. Outline of the bridge 3-span continuous deck extradosed bridge Bridge length

2. Outline of the bridge 3-span continuous deck extradosed bridge Bridge length Construction of Extradosed Bridge in the Government Financed Section EUI-NAM PARK, PM, Incheon Bridge Section 5, Doosan Construction & Engineering corporation KYUNG-KUK JUNG, GM, Incheon Bridge Section

More information

Seismic Design of a Railway Viaduct in a High Seismic Zone

Seismic Design of a Railway Viaduct in a High Seismic Zone Seismic Design of a Railway Viaduct in a High Seismic Zone 9 th Small Bridges Conference, Australia 2019 Seismic Design of a Railway Viaduct in a High Seismic Zone 1. Project Overview 2. Typical Project

More information

Table of Contents. ACKNOWLEDGEMENTS...ii LIST OF FIGURES...xii LIST OF TABLES...xv LIST OF SYMBOLS...xvi CHAPTER 1:ABOUT THIS STUDY...

Table of Contents. ACKNOWLEDGEMENTS...ii LIST OF FIGURES...xii LIST OF TABLES...xv LIST OF SYMBOLS...xvi CHAPTER 1:ABOUT THIS STUDY... ACKNOWLEDGEMENTS...ii LIST OF FIGURES...xii LIST OF TABLES...xv LIST OF SYMBOLS...xvi CHAPTER 1:ABOUT THIS STUDY... 1 1.1 THESIS STATEMENT... 1 1.2 INTRODUCTION... 1 1.3 RESEARCH OBJECTIVES... 3 1.4 RESEARCH

More information

Release Note DESIGN OF CIVIL STRUCTURES. Release Date : SEP. 1, 2015 Product Ver. : Civil 2016 (v1.1)

Release Note DESIGN OF CIVIL STRUCTURES. Release Date : SEP. 1, 2015 Product Ver. : Civil 2016 (v1.1) Release Note Release Date : SEP. 1, 2015 Product Ver. : Civil 2016 (v1.1) DESIGN OF CIVIL STRUCTURES Integrated Solution System for Bridge and Civil Engineering Enhancements Analysis & Design 3 (1) UK

More information

BALANCED CANTILEVER GIRDER BRIDGE OVER THE DANUBE-BLACK SEA CHANNEL

BALANCED CANTILEVER GIRDER BRIDGE OVER THE DANUBE-BLACK SEA CHANNEL DOI: 10.1515/rjti-2015-0017 BALANCED CANTILEVER GIRDER BRIDGE OVER THE DANUBE-BLACK SEA CHANNEL Aldo Giordano, PH.D. Professor of Structural Engineering, ITALROM Inginerie Internationala, e-mail: a.giordano@italrominginerie.com

More information

SOFiSTiK. for BRIDGES Company presentation. Georg Pircher SOFiSTiK International sales

SOFiSTiK. for BRIDGES Company presentation. Georg Pircher SOFiSTiK International sales SOFiSTiK for BRIDGES Georg Pircher SOFiSTiK International sales 23.05.2016 Company presentation Bridge Types Any structural bridge system is supported. Including: Box girder bridges. Slab bridges. Composite

More information

CONCRETE TECHNOLOGY CORPORATION

CONCRETE TECHNOLOGY CORPORATION PRECAST, PRESTRESSED HOLLOW CORE SLABS DESIGN CRITERIA & SPAN-LOAD CHARTS Introduction 2 Design Criteria for Development of the Span-Load Charts 2 Related Publications 3 Manufacturing Tolerances 4 8" Bare

More information

Precast Prestressed Segmental Elevated Urban Motorway in Italy

Precast Prestressed Segmental Elevated Urban Motorway in Italy Precast Prestressed Segmental Elevated Urban Motorway in Italy Bruno Gentilini Lino Gentilini Consulting Engineers Trento, Italy Bruno Gentilini Lino Gentilini The authors, who were responsible for the

More information

3.4.2 DESIGN CONSIDERATIONS

3.4.2 DESIGN CONSIDERATIONS 3.4.2 DESIGN CONSIDERATIONS Formwork Where Flatdeck sheet is used as formwork, the profile provides resistance to wet concrete (G) and construction loads (Q). Maximum formwork spans given in Section 3.4.4.1

More information

Concrete Design Guide

Concrete Design Guide Number 7 38 TheStructuralEngineer Technical July 2015 Post-tensioned slabs Concrete Design Guide No. 7: Design of post-tensioned slabs This series is produced by The Concrete Centre to enable designers

More information

CONTRIBUTION TO BRIDGE CONSTRUCTION OF THE DEPARTMENT OF STRUCTURAL ENGINEERING BME

CONTRIBUTION TO BRIDGE CONSTRUCTION OF THE DEPARTMENT OF STRUCTURAL ENGINEERING BME Department of Structural Engineering Budapest University of Technology and Economics CONTRIBUTION TO BRIDGE CONSTRUCTION OF THE DEPARTMENT OF STRUCTURAL ENGINEERING BME György FARKAS, Miklós IVÁNYI, Géza

More information

The New, Balanced Cantilever, Bridge over Acheloos River in Greece

The New, Balanced Cantilever, Bridge over Acheloos River in Greece The New, Balanced Cantilever, Bridge over Acheloos River in Greece Chrysanthos Maraveas 1, Konstantina Tasiouli 1 and Konstantinos Miamis 1 1 C. MARAVEAS PARTNERSHIP Consulting Engineers, Athens, Greece.

More information

STUDY ON ERECTION CONTROL SCHEME FOR LONG SPAN STEEL ARCH BRIDGE AND ITS APPLICATION ON CHAOTIANMEN YANGTZE RIVER BRIDGES

STUDY ON ERECTION CONTROL SCHEME FOR LONG SPAN STEEL ARCH BRIDGE AND ITS APPLICATION ON CHAOTIANMEN YANGTZE RIVER BRIDGES STUDY ON ERECTION CONTROL SCHEME FOR LONG SPAN STEEL ARCH BRIDGE AND ITS APPLICATION ON CHAOTIANMEN YANGTZE RIVER BRIDGES Zhongfu XIANG, Xuesong ZHANG, Baisong DU, Jian MAO & Hongyue YU School of Civil

More information

printed on June 24, 2003 LECTURE 10 - CONCRETE DESIGN - II 10.1 OBJECTIVE

printed on June 24, 2003 LECTURE 10 - CONCRETE DESIGN - II 10.1 OBJECTIVE LECTURE 10 - CONCRETE DESIGN - II printed on June 24, 2003 10.1 OBJECTIVE The objective of the lesson is to explain the various LRFD provisions related to some of the component-specific or structurespecific

More information

Precast segmental design and construction in China

Precast segmental design and construction in China Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Precast segmental design and construction in China Dong, Xu, Huichi Li & Chao Liu

More information

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority SYNOPSIS In recent years, there has been heightened concern over the performance of half joints

More information

AN INNOVATIVE ERECTION TECHNIQUE FOR REDUCING TWO- THIRD OF CONSTRUCTIONAL BRIDGE DEFLECTIONS

AN INNOVATIVE ERECTION TECHNIQUE FOR REDUCING TWO- THIRD OF CONSTRUCTIONAL BRIDGE DEFLECTIONS AN INNOVATIVE ERECTION TECHNIQUE FOR REDUCING TWO- THIRD OF CONSTRUCTIONAL BRIDGE DEFLECTIONS Assist. Prof. Ala a M. Darwish Dr. Wameedh G. Abdul-Hussein Nawal D. Salman Building and Construction Engineering

More information

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc. Grade Separation Systems Single-Span Rail Bridge Construction Procedure An innovation from art engineering inc. GSS Single-Span Example Shown: An existing railroad grade crossing. Existing railroad Existing

More information

Launching Bridges in to the Future. CBDG Annual Conference. Simon Bourne Managing Director. 26 June 2008

Launching Bridges in to the Future. CBDG Annual Conference. Simon Bourne Managing Director. 26 June 2008 Launching Bridges in to the Future CBDG Annual Conference 26 June 2008 Simon Bourne Managing Director WWW.BENAIMGROUP.COM Use of Incremental Launching Deck lengths of more than 200m 30-70m spans, typically

More information

Progressive Erection Applied to Box Girder with Strutted Wing Slab

Progressive Erection Applied to Box Girder with Strutted Wing Slab Progressive Erection Applied to Box Girder with Strutted Wing Slab Koji Osada 1, Taketo Kanamoto 1, Kimito Saito 2, Takahiro Arai 2 1 Introduction The Uchimaki Viaduct is a multi-span continuous box girder

More information

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

QUESTION BANK CE6702 PRESTRESSED CONCRETE STRUCTURES UNIT 3 - DEFLECTION AND DESIGN OF ANCHORAGE ZONE PART A (2 marks) 1. What are the functions of water stopper (water bar) in water tank construction?

More information

Project Reference Catalogue

Project Reference Catalogue Bridge Bridge Taiwan High Speed Rail, Advancing Shoring Method Taiwan High Speed Rail Corporation. Over 127 km of 13 wide prestressed concrete viaducts were constructed; and 9 contractors designed and

More information

Steel-concrete Composite Bridges Designing with Eurocodes

Steel-concrete Composite Bridges Designing with Eurocodes Steel-concrete Composite Bridges Designing with Eurocodes Second edition David Coilings Independent consultant, Technical Director RB International Contents pefa ton h Preface to the second edition Acknowledgements

More information

CABLE STAYED FOOTBRIDGE MADE OF UHPC

CABLE STAYED FOOTBRIDGE MADE OF UHPC CABLE STAYED FOOTBRIDGE MADE OF UHPC J.L. Vitek (1), M. Kalný (2) and R. Coufal (3) (1) Metrostav a.s. and CTU Prague, Prague, Czech Republic (2) PONTEX, Ltd., Prague, Czech Republic (3) TBG Metrostav,

More information

Prestressed Concrete Girder Continuity Connection

Prestressed Concrete Girder Continuity Connection Report No: Title: Developing Organization: Precast/Prestressed Concrete Institute Technical Committee Phone - 888-700-5670 Email contact@pcine.org Website- www.pcine.org Report Date: Revision Date: Status

More information

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) SPECIAL PROVISION August 31, 2009 PROJECT # S-R399(42) PROJECT # S-R399(59) PIN # 6697/7236 SECTION 03253S BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) Add Section 03253S: PART

More information

Critical Structures Construction Issues

Critical Structures Construction Issues Critical Structures Construction Issues FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Specification 1-3: Definitions Contractor s Engineer of Record Specialty Engineer CLASS OF CONTRACTOR

More information

Expansion Control Solutions

Expansion Control Solutions RAILWAY BRIDGES CONTENTS Introduction... 3 Technical... 4 Application... 6 Installation... 11 Quality... 12 Projects... 13 2 INTRODUCTION Railway bridges like bridges in general have one critical point;

More information

Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge)

Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge) Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge) Chodai Co., Ltd., Nippon Engineering Consultants Co., Ltd., IHI Infrastructure Systems Co,. Ltd., and Sumitomo Mitsui Construction

More information

B R I D G E O F F I C E

B R I D G E O F F I C E LRFD Bridge Design Manual BRIDGE OFFICE MANUAL 5-392 MINNESOTA DEPARTMENT OF TRANSPORTATION Bridge Office LRFD Bridge Design Manual MnDOT BRIDGE OFFICE LRFD Bridge Design Manual Minnesota Department of

More information

Formwork being erected

Formwork being erected CONCRETE FORMWORK Formwork being erected Most of the pads and concrete footing poured Formwork for the parkade walls is built for each pour Most of the parkade walls been completed 2 TYPES OF FORMWORK

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

B R I D G E O F F I C E

B R I D G E O F F I C E LRFD Bridge Design Manual BRIDGE OFFICE MANUAL 5-392 MINNESOTA DEPARTMENT OF TRANSPORTATION Bridge Office LRFD Bridge Design Manual MnDOT BRIDGE OFFICE LRFD Bridge Design Manual Minnesota Department of

More information

Construction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey

Construction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey International Symposium on Industrial Chimneys and Cooling Towers, Prague, Oct 8-11, 2014 Construction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey M. Orçun TOKUÇ 1 and Tamer TUNCA 2 1 Engineer

More information

SOIL-STRUCTURE INTERACTION ANALYSIS OF A RAILWAY BRIDGE IN ROTTERDAM

SOIL-STRUCTURE INTERACTION ANALYSIS OF A RAILWAY BRIDGE IN ROTTERDAM SOIL-STRUCTURE INTERACTION ANALYSIS OF A RAILWAY BRIDGE IN ROTTERDAM Cenan OZKAYA Technical Consultant, Yüksel Proje International, Ankara, Türkiye Tel : +90 (312) 4957000 E-mail : kucukdahi@hotmail.com

More information

GEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY

GEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY GEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY Introduction Authors Jarrod Hitchcox Associate Technical Director Arcadis Australia Pacific jarrod.hitchcox@arcadis.com

More information

Design of offshore structures Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras

Design of offshore structures Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras Design of offshore structures Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras Module - 03 Lecture - 01 Steel tubular member design 1 (Refer Slide Time: 00:12)

More information

Class Topics & Objectives

Class Topics & Objectives EGCE 406: Bridge Design Design of Slab for Bridge Deck Praveen Chompreda, Ph.D. Mahidol University First Semester, 2010 Class Topics & Objectives Topics Objective Bridge Superstructures Students can identify

More information

PAN PAC PULPMILL TREATMENT TANK

PAN PAC PULPMILL TREATMENT TANK PAN PAC PULPMILL TREATMENT TANK B. PENG 1, M. ROMANES 2, P. GABY 1 1 Holmes Consulting Group 2 Concrete Structures (NZ) Ltd ABSTRACT The recently completed MBBR and AS tank is part of a multi-million dollar

More information

EGCE 406: Bridge Design

EGCE 406: Bridge Design EGCE 406: Bridge Design Design of Slab for Praveen Chompreda Mahidol University First Semester, 2006 Bridge Superstructure Outline Components of bridge Superstructure Types Materials Design of RC Deck

More information

Launching technique for the Viaduc de Millau

Launching technique for the Viaduc de Millau Launching technique for the Viaduc de Millau Introduction The Viaduc de Millau is part of the A75 linking Paris with Barcelona (Figure 1). It is currently the highest bridge in the world at 343m high with

More information

ST7008 PRESTRESSED CONCRETE

ST7008 PRESTRESSED CONCRETE ST7008 PRESTRESSED CONCRETE QUESTION BANK UNIT-I PRINCIPLES OF PRESTRESSING PART-A 1. Define modular ratio. 2. What is meant by creep coefficient? 3. Is the deflection control essential? Discuss. 4. Give

More information

HANDLING OF BRIDGE BEAMS ON SITE

HANDLING OF BRIDGE BEAMS ON SITE TECHNICAL ADVICE NOTE HANDLING OF BRIDGE BEAMS ON SITE PRESTRESSED CONCRETE ASSOCIATION Additional advice may be obtained direct from PCA member companies, who will assist at the earliest stages of planning,

More information

SECTION COLD-FORMED METAL FRAMING

SECTION COLD-FORMED METAL FRAMING SECTION 05 40 00 COLD-FORMED METAL FRAMING SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable in the section and renumber the

More information

MARTA Rapid Transit Bridges

MARTA Rapid Transit Bridges MARTA Rapid Transit Bridges his precast segmental post-tensioned concrete project for the T Metropolitan Atlanta Rapid Transit Authority demonstrates the ability of the segmental technique to economically

More information

Requirements for Measuring and Pricing of Structural Concrete

Requirements for Measuring and Pricing of Structural Concrete Requirements for Measuring and Pricing of Structural Concrete October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing

More information

Modeling and Design of Bridge Super Structure and Sub Structure

Modeling and Design of Bridge Super Structure and Sub Structure Topic 3 Day 2 Modeling and Design of Bridge Super Structure and Sub Structure Naveed Anwar 1. Over view of Bridge Design Process and Bridge Types 2. Advances and recent trends in Modeling and Analysis

More information

Kicking Horse Cantilever Structure. Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd.

Kicking Horse Cantilever Structure. Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd. Kicking Horse Cantilever Structure Bruce Hamersley, P.Eng., Klohn Crippen Berger Ltd. Keith Mitchell, P.Eng., Klohn Crippen Berger Ltd. Brian Borton, P. Eng., Klohn Crippen Berger Ltd. Paper prepared for

More information

Construction of Bridges

Construction of Bridges Construction of Bridges Materials suitable for the Construction of Long-span Bridges 1. Stone in arch masonry 2. Steel in girder or box-section constructed in steel plates and standard sections 3. Steel

More information

Basarab Cable Stayed Bridge in Bucharest

Basarab Cable Stayed Bridge in Bucharest Basarab Cable Stayed Bridge in Bucharest Javier MANTEROLA Pr. Dr. Civil Engineer Carlos Fernández Casado,S.L. Madrid, SPAIN jmanterola@cfcsl.com Antonio MARTÍNEZ Dr. Civil Engineer Carlos Fernández Casado,S.L.

More information

CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS

CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS DS Temple 13.1 SCOPE This section covers the inspection of mechanically stabilized earth walls and other patented earth

More information

Learning Objectives. A Brief History

Learning Objectives. A Brief History Slide 1 Precast Structures and Frames Miles L. Blackman, P.E. Slide 2 Learning Objectives Discuss precast concrete characteristics, advantages and benefits, typical construction methods and construction

More information

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong Geotechnical Engineering Office Civil Engineering Department The Government of the Hong Kong Special Administrative Region

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

INNOVATIVE PRECAST CONCRETE DECK SLABS

INNOVATIVE PRECAST CONCRETE DECK SLABS INNOVATIVE PRECAST CONCRETE DECK SLABS Dr. S. (Bala) Balakrishnan, Ph.D., P.Eng. Paper prepared for presentation At the Bridges for the 21 st Century Session (B) Of the 2006 Annual Conference of the Transportation

More information

Movable and launched bridges: recent realizations and improved techniques

Movable and launched bridges: recent realizations and improved techniques Mobile and Rapidly Assembled Structures IV 245 Movable and launched bridges: recent realizations and improved techniques S. Hernández & A. N. Fontán Structural Mechanics Group, School of Civil Engineering,

More information

Highway Bridge Superstructure

Highway Bridge Superstructure Highway Bridge Superstructure Engineering LRFD Approaches to Design and Analysis Narendra Taly CRC Press Taylor & Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor & Francis

More information

Retrofit Measures for Superstructures, Bearings, and Seats

Retrofit Measures for Superstructures, Bearings, and Seats Retrofit Measures for Superstructures, Bearings, and Seats Presented by Richard V Nutt Elements to be Retrofitted Bridge Decks and Girders Bearings, Anchorages and Pedestals Expansion Joints 1 Elements

More information

NSBA. Prize Bridge. Awards

NSBA. Prize Bridge. Awards NSBA 2016 Prize Bridge Awards THE COUNTRY S BEST STEEL BRIDGES have been honored in this year s Prize Bridge Awards competition. Conducted every two years by the National Steel Bridge Alliance (NSBA),

More information

STRESS RIBBON BRIDGE

STRESS RIBBON BRIDGE A Seminar report On STRESS RIBBON BRIDGE Submitted in partial fulfillment of the requirement for the award of degree Of Civil SUBMITTED TO: SUBMITTED BY: www.studymafia.org www.studymafia.org Acknowledgement

More information

CASE STUDY OF LONG SPAN STEEL BRIDGE STABILITY DURING DESIGN AND CONSTRUCTION

CASE STUDY OF LONG SPAN STEEL BRIDGE STABILITY DURING DESIGN AND CONSTRUCTION CASE STUDY OF LONG SPAN STEEL BRIDGE STABILITY DURING DESIGN AND CONSTRUCTION KEVIN D. SEAR, PE SUSAN STEELE, PE BIOGRAPHY Kevin Sear has been a structural engineer for over 42 years, the first 10 years

More information

Behavior of a multiple spans cable-stayed bridge

Behavior of a multiple spans cable-stayed bridge Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Behavior of a multiple spans cable-stayed bridge S. Arnaud, N. Matsunaga, S. Nagano

More information

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan Possible solution to past CM exam question Question 2 July 2015 New city centre office block by Rajavel Inbarajan The information provided should be seen as an interpretation of the brief and a possible

More information

4 Casting Bed. Concrete Forms. Reinforcing. Splices. Prestressing. Elongation. Prestressing System. Initial Tensioning of Straight Strands

4 Casting Bed. Concrete Forms. Reinforcing. Splices. Prestressing. Elongation. Prestressing System. Initial Tensioning of Straight Strands 4 Casting Bed Concrete Forms Reinforcing Splices Prestressing Elongation Prestressing System Initial Tensioning of Straight Strands Initial Tensioning of Draped Strands Up-Lift and Hold-Down Devices Strand

More information

ERECTION ANALYSIS OF THE CFST ARCH BRIDGE BY VERTICAL SWING METHOD OVER THE JING-HANG CANAL IN XUZHOU, CHINA

ERECTION ANALYSIS OF THE CFST ARCH BRIDGE BY VERTICAL SWING METHOD OVER THE JING-HANG CANAL IN XUZHOU, CHINA Arch Bridges ARCH 04 P. Roca and E. Oñate (Eds) CIMNE, Barcelona, 2004 ERECTION ANALYSIS OF THE CFST ARCH BRIDGE BY VERTICAL SWING METHOD OVER THE JING-HANG CANAL IN XUZHOU, CHINA Chao SUN, Baochun Chen,

More information

About the Causes of the Koror Bridge Collapse

About the Causes of the Koror Bridge Collapse Open Journal of Safety Science and Technology, 2014, 4, 119-126 Published Online June 2014 in SciRes. http://www.scirp.org/journal/ojsst http://dx.doi.org/10.4236/ojsst.2014.42013 About the Causes of the

More information

John James Audubon Bridge

John James Audubon Bridge John James Audubon Bridge Cable-Stayed Main Span Over the Mississippi River Johns Hopkins University Whiting School of Engineering September 10, 2008 The Project Scheduled Time to Complete Estimated Number

More information

This paper will also report on the methodology of various strengthening concepts that were developed and tested using these models.

This paper will also report on the methodology of various strengthening concepts that were developed and tested using these models. Computer Models Developed for the Strengthening of the Approach Viaducts of the Westgate Bridge Grahme, Bridge Engineer, Sinclair Knight Merz Martin Pircher, Technical Director, ABES Pty Ltd Craig Allen,

More information

Design & technology characteristics of main bridge of Chaotianmen Yangtze River Bridge

Design & technology characteristics of main bridge of Chaotianmen Yangtze River Bridge Design & technology characteristics of main bridge of Chaotianmen Yangtze River Bridge Xuewei Duan, Xiaoyan Xiao and Wei Xu China Railway Bridge Reconnaissance & Design Institute Co., Ltd., Wuhan, China

More information