SECTION SITE CLEARING

Size: px
Start display at page:

Download "SECTION SITE CLEARING"

Transcription

1 SECTION SITE CLEARING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementaty Conditions and Division 01 Specification Sections, apply to this Section. B. Subsurface Exploration report No , prepared by Geotechnology Inc., dated AprillO, SUMMARY A. Section Includes: 1. Protecting existing vegetation to remain. 2. Removing existing vegetation. 3. Clearing and grubbing. 4. Stripping and stockpiling topsoil. 5. Removing above- and below-grade site improvements. 6. Disconnecting, capping or sealing, removing site utilities, and abandoning site utilities in place. B. Related Sections: 1. Division 01 Section "Construction Facilities and Temporaty Controls" for temporary utility services, construction and support facilities, security and protection facilities. 2. Division 01 Section(s) "Cleaning" for cleaning and waste disposal operations. 3. Division 02 Section "Demolition" for demolition of structures and site improvements. 4. Division 02 Sections for environmental remediation and handling of hazardous and contaminated materials. 5. Divisions 22, 23 and 26 Sections for capping, sealing or removing mechanical and electrical utilities. 6. Division 31 Section "Earth Moving" for excavation and backfill for structures. 1.3 DEFINITIONS A. Subsoil: Soil beneath the level of subgrade; soil beneath the topsoil layers of a naturally occurring soil profile, typified by less than 1 percent organic matter and few soil organisms. SITE CLEARING

2 B. Surface Soil: Soil that is present at the top layer of the existing soil profile. In undisturbed areas, surface soil is typically called "topsoil," but in disturbed areas such as urban environments, the surface soil can be subsoil. C. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or existing in-place surface soil; the zone where plant roots grow. Its appearance is generally friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects larger than 1 inches (25 mm) in diameter; and free of weeds, roots, toxic materials, or other non-soil materials. D. Tree-Protection Zone: Area surrounding individual trees or groups of trees to be protected during construction, defmed by a circle concentric with each tree with a radius equal to the diameter of the drip line unless otherwise indicated. E. Vegetation: Trees, shmbs, groundcovers, grass, and other plants. 1.4 MATERIAL OWNERSHIP A. Except for materials indicated to be stockpiled or otherwise remain Owner's property, cleared materials shall become Contractor's property and shall be removed from Project site. B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner. 1. Carefully salvage in a manner to prevent damage and promptly return to Owner. 1.5 SUBMITTALS A. Topsoil stripping and stockpiling program. B. Record Drawings: Identify and accurately show locations of capped utilities and other subsurface stmctural, electrical, and mechanical conditions. 1.6 QUALITY ASSURANCE A. Pre-constmction conference. To be held on-site. 1. Inspect and discuss condition of constmction to be demolished. 2. Review stmcturalload limitations of existing roads. 3. Review and finalize protection requirements. 4. Review procedures for noise control and dust control. 5. Review procedures for protection of adjacent buildings. 6. Review items to be salvaged and returned to Owner. B. Topsoil Stripping and Stockpiling Program: Prepare a written program to systematically demonstrate the ability of personnel to properly follow procedures and handle materials SITE CLEARING

3 and equipment during the Work. Include dimensioned diagrams for placement and protection of stockpiles. 1.7 PROJECT CONDITIONS A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations. 1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner's Construction Representative and authorities having jurisdiction. 2. Provide altemate routes around closed or obstructed traffic ways if required by Owner's Construction Representative or authorities having jurisdiction. B. Salvageable Improvements: Carefully remove items indicated to be salvaged and store on Owner's premises where indicated by Owner's Construction Representative. C. Utility Locator Service: Notify Missouri One Call for area where Project is located before site clearing. D. Do not commence site clearing operations until temporaty erosion- and sedimentationcontrol measures are in place. E. The following practices are prohibited within tree-protection zones: 1. Storage of construction materials, debris, or excavated material. 2. Parking vehicles or equipment. 3. Foot traffic. 4. Erection of sheds or structures. 5. Impoundment of water. 6. Excavation or other digging unless otherwise indicated. 7. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated. F. Do not direct vehicle or equipment exhaust towards protection zones. G. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones. H. Soil Stripping, Handling, and Stockpiling: Perform only when the soil is dty or slightly moist. PART 2 -PRODUCTS 2.1 MATERIALS A. Satisfactoty Soil Material: Requirements for satisfactmy soil material are specified in Section "Earth Moving." SITE CLEARING

4 1. Obtain approved borrow soil material off-site when satisfactory soil material is not available on-site. PART 3 -EXECUTION 3.1 PREPARATION A. Protect and maintain benchmarks and survey control points from disturbance during construction. B. Verify that sedimentation and erosion controls have been installed so that all work can be perfotmed in accordance with the State's Land Disturbance permit. C. Locate and clearly identify trees to remain. Flag each tree trunk at 54 inches (1372 mm) above the ground. D. Protect existing site improvements to remain from damage during construction. 1. Restore damaged improvements to their original condition, as acceptable to Owner's Constmction Representative. 3.2 TREE AND PLANT PROTECTION A. Repair or replace trees, shrubs, and other vegetation indicated to remain or be relocated that are damaged by construction operations in a manner approved by the Owner's Construction Representative. 3.3 EXISTING UTILITIES A. Locate, identify, disconnect, and seal or cap utilities indicated to be removed or abandoned in place. 1. Arrange with utility companies and Owner's Constmction Representative to have indicated utilities shut off. B. Locate, identify, and disconnect utilities indicated to be abandoned in place. C. Intermpting Existing Utilities: Do not intenupt utilities serving facilities occupied by Owner or others, unless permitted under the following conditions and then only after ananging to provide temporary utility services according to requirements indicated: 1. Notify Owner's Constmction Representative not less than two days in advance of proposed utility interruptions. 2. Do not proceed with utility intenuptions without Owner's Constmction Representative's written permission. D. Excavate for and remove underground utilities indicated to be removed. SITE CLEARING

5 3.4 CLEARING AND GRUBBING A. Remove obstructions, trees, shrubs, and other vegetation to permit installation of new construction. 1. Do not remove trees, shrubs, and other vegetation not indicated for removal. 2. Remove stumps and remove roots, obstructions, and debris to a depth of 18 inches ( 450 mm) below exposed sub grade. 3. Root balls from large trees shall be completely removed. 4. Use only hand methods or air spade for grubbing within protection zones. 5. Chip removed tree branches and deliver to a mulching or recycling facility. B. Fill depressions caused by clearing and grubbing operations with satisfactory soil material unless further excavation or earthwork is indicated. 1. Place fill material in horizontal layers not exceeding a loose depth of 8 inches (200 mm), and compact each layer to a density equal to adjacent original ground. 3.5 TOPSOIL STRIPPING A. Remove sod and grass before stripping topsoil. B. Strip topsoil to depth of 6 inches (150 mm) in a manner to prevent intermingling with underlying subsoil or other waste materials. 1. Remove subsoil and nonsoil materials from topsoil, including clay lumps, gravel, and other objects larger than 2 inches (50 mm) in diameter; trash, debris, weeds, roots, and other waste materials. C. Stockpile topsoil away from edge of excavations without intennixing with subsoil or other materials. Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust and erosion by water. 1. Limit height of topsoil stockpiles to 72 inches ( 1800 mm). 2. Do not stockpile topsoil within protection zones. 3. Stockpile surplus topsoil for future phase work as available. 3.6 SITE IMPROVEMENTS A. Remove existing above- and below-grade improvements as indicated and necessary to facilitate new construction. B. Remove slabs, paving, curbs, gutters, and aggregate base as indicated. 1. Unless existing full-depth joints coincide with line of demolition, neatly saw-cut along line of existing pavement to remain before removing adjacent existing pavement. Saw-cut faces vertically. 2. Paint cut ends of steel reinforcement in concrete to remain with two coats of antirust coating, following coating manufacturer's written instructions. Keep paint off surfaces that will remain exposed. SITE CLEARING

6 3.7 DISPOSAL OF SURPLUS AND WASTE MATERIALS A. Remove unsuitable topsoil, obstructions, demolished materials, and waste materials including trash and debris, and legally dispose of them off Owner's property, or on-site at the direction of the Owner's Construction Representative. B. Separate recyclable materials produced during site clearing from other nonrecyclable materials. Store or stockpile without intermixing with other materials, and transport them to recycling facilities. Do not interfere with other Project work. END OF SECTION SITE CLEARING

7 SECTION EARTH MOVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementmy Conditions and Division 01 Specification Sections, apply to this Section. B. "Missouri Standard Specifications for Highway Construction, 2011," Missouri Highways and Transpmiation Commission. C. Subsmface Exploration repmi No. J , prepared by Geotechnology Inc., dated AprillO, SUMMARY A. Section Includes: 1. Excavating and filling for rough grading the Site. 2. Preparing sub grades for slabs-on-grade, walks, pavements, turf, grasses, and plants. 3. Excavating and backfilling for structures. 4. Excavating and backfilling trenches for utilities, tunnels and pits for buried utility structures. B. Related Sections: 1. Division 01 Section "Construction Facilities and Temporaty Controls" for temporaty controls, utilities, and support facilities; also for temporary site fencing if not in another Section. 2. Division 02 Section "Demolition" for demolition and removal of structures before mass excavation. 3. Division 02 Sections for environmental remediation and handling of hazardous and contaminated materials. 4. Division 22 and 23 Sections for capping, sealing or removing mechanical and electrical utilities. 5. Division 31 Section "Site Clearing" for site stripping, grubbing, stripping topsoil, and removal of above- and below-grade improvements and utilities. EARTH MOVING

8 1.3 UNIT PRICES A. There is no unit pncmg for this work. Any reference to MoDOT specifications specifically excludes any basis for payment provisions. 1.4 DEFINITIONS A. Backfill: Soil material or controlled low-strength material used to fill an excavation. 1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe. 2. Final Backfill: Backfill placed over initial backfill to fill a trench. B. Base Course: Aggregate layer placed between the subbase course and concrete paving. C. Bedding Course: Aggregate layer placed over the excavated subgrade in a trench before laying pipe. D. Borrow Soil: Satisfactmy soil imported from off-site for use as fill or backfill. E. Excavation: Removal of material encountered above sub grade elevations and to lines and dimensions indicated. 1. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Owner's Construction Representative. Authorized additional excavation and replacement material will be paid for at unit prices to be agreed upon by the Owner and the Contractor. 2. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Owner's Construction Representative. Unauthorized excavation, as well as remedial work directed by Owner's Construction Representative, shall be without additional compensation. 3. All earthwork is to be performed in accordance with Geotechnology, Inc. Subsurface Exploration repoti, Project No , dated April10, All earthwork, including the positive approach for Remediation of Existing Fill, as defined in the repoti is to be included in the base bid. 4. Rock Excavation: Material that requires jack hammering for its practical and effective removal. a. Materials include sandstone, limestone, shale, siltstone, or similar material, in masses measuring more than one (1) cubic yard in volume or in ledges 4" or more in thickness. b. Rock encountered in two or more ledges, being 3" or thicker, with interlaying emih strata~ 12" thick, the entire volume from the top of the top ledge to the bottom of the bottom ledge is classified as rock. F. Fill: Soil materials used to raise existing grades. EARTH MOVING

9 G. Maximum Density: Maximum dry weight in pounds per cubic foot of a specific material, as determined by ASTM D698, Standard Proctor Density. H. Optimum Moisture: Percentage of water at maximum density. I. Rock: Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders of rock material that exceed 1 cu. yd. (0.76 cu. m) for bulk excavation or 3/4 cu. yd. (0.57 cu. m) for trench and pit excavation that cannot be removed by rock-excavating equipment, without systematic drilling, ram hammering, ripping or blasting, when permitted. J. Rubble: Buried concrete foundations, beams, walls, and other material. K. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below the ground surface. L. Subbase Course: Aggregate layer placed between the subgrade and base course for hotmix asphalt pavement, or aggregate layer placed between the subgrade and a cement concrete pavement or a cement concrete walk. M. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill immediately below subbase or topsoil materials. N. Utilities: On-site underground pipes, conduits, ducts, and cables as well as underground services within buildings. 1.5 PRE-CONSTRUCTION MEETING A. Preinstallation Conference: Conduct pre-excavation conference at Project site. 1. Review methods and procedures related to eatihmoving, including, but not limited to, the following: a. b. c. d. e. f. g. h. Coordination of Work with other on-site Contractors. Coordination of Work while Owner operations are on-going. Submittal of plans and narratives for addressing procedures during unanticipated utility disruptions. Submittal of plans and narratives for addressing method of demolition of individual components Submittal of plans and narratives for addressing sequencing issues, and Contractor's understanding of these issues. Haul Route. Grading intent across the project site within this demolition phase. Utility abandonment. EARTH MOVING

10 1.6 SUBMITTALS A. Product Data: For each type of the following manufactured products required: 1. Controlled low-strength material, including design mixh1re. B. Pre-excavation Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including finish surfaces that might be misconstrued as damage caused by earth-moving operations. Submit before emth moving begins. 1.7 QUALITY ASSURANCE A. Geotechnical Testing Agency Qualifications: Qualified according to ASTM E 329 and ASTM D 3740 for testing indicated. 1.8 PROJECT CONDITIONS A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during earth-moving operations. 1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without petmission from Owner's Construction Representative and authorities having jurisdiction. 2. Provide alternate routes around closed or obstructed traffic ways if required by Owner's Constmction Representative or authorities having jurisdiction. B. Improvements in Public Right-of-Way: Authority for perfotming earth moving indicated in the public right-of-way adjoining Owner's property will be obtained by Contractor before beginning earth moving. 1. Do not proceed with work in public right-of-way until directed by Owner's Construction Representative. C. Utility Locator Service: Notify "Missouri One Call" for area where Project is located before beginning eatth moving operations. D. Do not commence eatth-moving operations until temporaty site fencing and erosion- and sedimentation-control measures are in place. E. The following practices are prohibited within tree protection zones: 1. Storage of construction materials, debris, or excavated material. 2. Parking vehicles or equipment. 3. Foot traffic. 4. Erection of sheds or structures. 5. Impoundment of water. 6. Excavation or other digging unless otherwise indicated. EARTH MOVING

11 7. Attachment of signs to or wrappmg materials around trees or plants unless otherwise indicated. F. Do not direct vehicle or equipment exhaust towards protection zones. G. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones. PART 2 -PRODUCTS 2.1 SOIL MATERIALS A. General: Provide borrow soil materials when sufficient satisfactmy soils are not available from excavation. B. Satisfactmy Soils: Off-site soils include low plasticity silty clay (liquid limit less than 45) and well-graded, crushed rock. On-site excavated soils include low plasticity silty clay materials Suitable soils shall be free of rock or gravel larger than 1" in any dimension, debris, waste, frozen materials, vegetation and other deleterious matter, or as defmed in the geotechnical report. I. Liquid Limit: less than Plasticity Index: 30. C. Satisfactmy Soil within 36" of finish grade in turf and landscape areas shall be as defined above, and free of rock or gravel larger than 1" in any dimension, debris, waste, frozen materials, vegetation and other deleterious matter, or as defined in the geotechnical report. Where conflicting, the geotechnical report shall prevail. D. Unsatisfactmy Soils: As defined in the geotechnical report. 1. Unsatisfactmy soils also include satisfactmy soils not maintained within 3 percent of optimum moisture content at time of compaction. 2. Unsatisfactmy soils also include deleterious materials such as concrete, rock and masomy fragments larger than 4 inches (100 mm) in any dimension, organic material, wood, plastic, metal, tires, trash and other debris. E. Structural Fill: Structural fill per geotechnical report. F. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand meeting the requirements of MoDOT Type 1 Base Aggregate. G. Granular Trench Backfill: 1. Under Pipe: All backfill under the banel of the pipe shall be free fi om debris, organic matter, and stones larger than one inch, and shall be tamped into place. Sand or stone crushed aggregate (95% passing a W' screen but not more than 10% passing a #200 sieve) are acceptable substitutes for soil. EARTHMOVING

12 2. Adjacent To and Top of Pipe: The first foot of backfill over the top of the pipe shall be "3/4" minus waste rock with fines" uncleaned crushed stone aggregate or suitable soil. Backfill shall be free of debris, brush, roots and stones or rubble more than one inch. 3. Under, Adjacent To, and top of Pipe in bedrock: Sand or fine rock (3/8" minus). This can be local creek run sand as approved by the Owner's Construction Representative. 4. Under Pavement: Full depth (3/4" minus) rock or crushed stone aggregate, or beginning one foot above pipe if in bedrock. H. Bedding Course: ASTM D Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand with 95 percent passing a Yzinch sieve and not more than 10 percent passing a No. 200 sieve. I. Sand: ASTM C 33; fine aggregate. 2.2 GEOTEXTILES A. Subsurface Drainage Geotextile: Nonwoven needle-punched geotextile, manufactured for subsurface drainage applications, made fi om polyolefins or polyesters; with elongation greater than 50 percent; complying with AASHTO M 288 and the following, measured per test methods referenced: 1. Survivability: Class 2; AASHTO M 288. a. Grab Tensile Strength: 157 lbf; ASTM D b. Sewn Seam Strength: 142lbf; ASTM D c. Tear Strength: 561bf; ASTM D d. Puncture Strength: 56 lbf; ASTM D e. Apparent Opening Size: No. 60 sieve, maximum; ASTM D f. Permittivity: 0.2 per second, minimum; ASTM D g. UV Stability: 50 percent after 500 hours' exposure; ASTM D CONTROLLED LOW-STRENGTH MATERIAL A. Controlled Low-Strength Material: produced fi om the following: Self-compacting, flowable concrete material 1. Portland Cement: ASTM C 150, Type I. 2. Normal-Weight Aggregate: ASTM C 33, 3/4-inch nominal maximum aggregate SIZe. 3. Water: ASTM C 94/C 94M. EARTH MOVING

13 4. Air-Entraining Admixture: ASTM C 260. B. Produce conventional-weight, controlled low-strength material with 140-psi compressive strength when tested according to ASTM C 495. PART 3 - EXECUTION 3.1 PREPARATION A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth-moving operations. B. Protect and maintain erosion and sedimentation controls during earth-moving operations. C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent materials. 3.2 SAFETY A. The means of the work and the safety of the Contractor's employees are solely the responsibility of the Contractor. The Contractor has a contractual obligation to comply with all applicable laws and regulations including those of OSHA. At no time will either the Owner or Owner's Construction Representative take responsibility for either the means of the work or the safety of the Contractor's employees. 3.3 DEWATERING A. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area. B. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation. 1. Reroute sutface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches. 3.4 EXPLOSIVES A. Explosives: Explosives are not authorized for this Project. 3.5 EXCAVATION, GENERAL A. Unclassified Excavation: Excavate to sub grade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include concrete, masonry, rock, soil materials, debris, organic materials and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for concrete, masomy, rock excavation or removal of any debris, organic materials or EARTHMOVING

14 obstructions. All excavation shall be performed in accordance with the site Geotechnical rep ott. 1. If excavated materials intended for fill and backfill include unsatisfactory soil materials, concrete, masonry and rock, replace with satisfactory soil materials. 2. Where stone, concrete or brick materials are used as fill, a well-graded mixture of particle sizes shall be maintained. B. Excavations at Edges of Tree-Protection Zones: 1. Excavate by hand to indicated lines, cross sections, elevations, and subgrades. Use compressed air or narrow-tine spading forks to comb soil and expose roots. Do not break, tear, or chop exposed roots. Do not use mechanical equipment that rips, tears, or pulls roots. C. Machine slope banks, to angle of repose or less, until shored. Excavations should be made in accordance with OSHA regulations. 3.6 EXCAVATION FOR STRUCTURES A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1 inch (25 mm). If applicable, extend excavations a sufficient distance from structures for placing and removing concrete formwork, for installing services and other construction, and for inspections. All excavation shall be performed in accordance with the site Geotechnical repott. 1. Excavation for Underground Utility Structures: Excavate to elevations and dimensions indicated within a tolerance of plus or minus 1 inch (25 mm). Do not disturb bottom of excavations intended as bearing surfaces. 3.7 EXCAVATION FOR UTILITY TRENCHES A. Excavate trenches to indicated gradients, lines, depths, and elevations. B. Excavate trenches to uniform widths to provide the following clearance on each side of pipe or conduit. Excavate trench walls vertically from trench bottom to 12 inches (300 mm) higher than top of pipe or conduit unless otherwise indicated. 1. Clearance: 6 inches (300 mm) each side of pipe or conduit unless otherwise indicated. C. Trench Bottoms: Excavate and shape trench bottoms to provide unifonn bearing and support of pipes. Shape subgrade to provide continuous support for bells, joints, and barrels of pipes. Remove projecting stones and sharp objects along trench subgrade. 1. Excavate trenches 6 inches (150 mm) deeper than elevation required in rock or other unyielding bearing material to allow for bedding course. EARTHMOVING

15 3.8 SUBGRADE INSPECTION A. Notify Owner's Construction Representative when excavations have reached required subgrade. B. If Owner's Construction Representative determines that unsatisfactory soil is present, continue excavation and replace with compacted backfill or fill material as directed. C. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by Owner's Construction Representative, without additional compensation. 3.9 UNAUTHORIZED EXCAVATION A. Fill unauthorized excavation with satisfactoty soils as directed by Owner's Construction Representative STORAGE OF SOIL MATERIALS A. Stockpile borrow soil materials and excavated satisfactory soil materials without intennixing, unless othetwise indicated by the Owner's Construction Representative. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust. 1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees BACKFILL A. Place and compact backfill in excavations promptlyand m accordance with the Geotechnical report, but not before completing the following: 1. Construction below finish grade. 2. Surveying locations of underground utilities for Record Documents. 3. Testing and inspecting underground utilities. 4. Removing concrete formwork. 5. Removing trash and debris. 6. Removing temporaty shoring and bracing, and sheeting. B. Place backfill on subgrades free of mud, frost, snow, or ice. C. Fill and backfill to be mechanically compacted in uniform lifts not exceeding 8 inches UTILITY TRENCH BACKFILL A. Place backfill on sub grades free of mud, frost, snow, or ice. EARTHMOVING

16 B. Place and compact bedding course on trench bottoms and where indicated. Shape bedding course to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits. C. Trenches under Roadways: Provide 4-inch- (1 00-mm-) thick, concrete-base slab support for piping or conduit less than 30 inches (750 mm) below surface of roadways. After installing and testing, completely encase piping or conduit in a minimum of 4 inches (1 00 mm) of concrete before backfilling or placing roadway subbase course. Concrete is specified in Section "Cast-in-Place Concrete." D. Backfill voids with satisfactmy soil while removing shoring and bracing. E. Place and compact initial backfill of bedding course, free of particles larger than 1 inch (25 mm) in any dimension, to a height of 6 inches (150 mm) over the pipe. 1. Carefully compact initial backfill under pipe haunches and compact evenly up on both sides and along the full length of piping to avoid damage or displacement of piping. Coordinate backfilling with utilities testing. F. Place and compact final backfill of satisfactmy soil to final sub grade elevation SOIL FILL A. Plow, scarify, bench, or break up sloped smfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing material. B. Place and compact fill material inlayers to required elevations as follows: 1. Under grass and planted areas, use satisfactory soil material. 2. Under walks and pavements, use satisfactory soil material. 3. Under building slabs, use satisfactory soil material. C. Place soil fill on subgrades free of mud, frost, snow, or ice SOIL MOISTURE CONTROL A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill soil layer before compaction to within 1 percent to 3 percent of optimum moisture content. 1. Do not place backfill or fill soil material on smfaces that are muddy, frozen, or contain frost or ice. 2. Remove and replace, or scarify and air dty, otherwise satisfactmy soil material that exceeds optimum moisture content by 3 percent and is too wet to compact to specified compaction requirements COMPACTION OF SOIL BACKFILLS AND FILLS A. EARTHMOVING

17 B. Place backfill and fill soil materials in layers not more than 8 inches (200 mm) in loose depth for material compacted by heavy compaction equipment and not more than 5 inches (125 mm) in loose depth for material compacted by hand-operated tampers. C. Place backfill and fill soil materials along the full length of each building pad. D. Compact soil materials to not less than the following percentages of maximum dty unit weight according to ASTM D 698: 1. General soil fill: compact each layer of backfill or fill soil material at 90 percent. 2. Crushed rock backfill: compact each layer of initial and final backfill rock material at 95 percent GRADING A. General: Unifotmly grade areas to a smooth surface, free of irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated. 1. Provide a smooth transition between adjacent existing grades and new grades. 2. Cut out soft spots, fill low spots, and trim high spots to comply with required surface tolerances. 3. Fill all holes and voids as a result of demolition tasks with suitable backfill material to pre-demolition ground elevation, unless otherwise specified. Modify surface as necessaty to provide positive drainage. B. Site Rough Grading: Slope grades to direct water away from buildings and to prevent ponding. Finish subgrades to elevations required to achieve indicated finish elevations, within the following subgrade tolerances: 1. Building Pads and Parking Lots: Plus or minus 1/2 inch (13 mm). 2. All Other Areas: Plus or minus 1 inch (25 mm). C. Grading inside Building Lines: Finish subgrade to a tolerance of 1/2 inch (13 mm) when tested with a 10-foot (3-m) straightedge SUBBASE AND BASE COURSES UNDER PAVEMENTS AND WALKS A. Place subbase course and base course on sub grades free of mud, frost, snow, or ice. B. On prepared subgrade, place subbase course and base course under pavements and walks as follows: Place base course material over subbase course under concrete pavement. Shape subbase course and base course to required crown elevations and crossslope grades. EARTHMOVING

18 3. Place subbase course and base course 6 inches or less in compacted thiclmess in a single layer. 4. Place subbase course and base course that exceeds 6 inches in compacted thiclmess in layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 inches thick. 5. Compact subbase course and base course at optimum moisture content to required grades, lines, cross sections, and thiclmess to not less than 95 percent of maximum dry unit weight according to ASTM D FIELD QUALITY CONTROL A. All bearing soil and backfill will be inspected and tested and at the discretion of the Owner's Construction Representative. Owner will retain the services of an engineering inspection and testing firm. Contractor will be responsible for coordinating and scheduling inspections. B. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earth moving only after test results for previously completed work comply with requirements. C. Testing agency will test compaction of soils in place according to ASTM D 1556, ASTM D 2167, ASTM D 2922, and ASTM D 2937, as applicable. Tests will be performed at the following locations and frequencies: 1. Building Pad Areas: At subgrade and at each compacted fill and backfill layer, at least one test for every 2,500 sq. ft. or less of building pad, but in no case fewer than three tests. 2. Trench Backfill: At each compacted initial and final backfill layer, at least one test for evety 200 feet or less of trench length, but no fewer than two tests. D. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required; recompact and retest until specified compaction is obtained PROTECTION A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris. B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions. 1. Scarify or remove and replace soil material to depth as directed by Owner's Construction Representative; reshape and re-compact. C. Where settling occurs before Project conection period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct smfacing. EARTHMOVING

19 3.20 DISPOSAL OF SURPLUS AND WASTE MATERIALS A. Transpoti surplus satisfactory soil to designated storage areas on Owner's property. Stockpile or spread soil as directed by Owner's Construction Representative. 1. Remove waste materials, including unsatisfactory soil, trash, and debris, and legally dispose ofthem off Owner's propetiy. END OF SECTION EARTH MOVING

20 TIDS PAGE INTENTIONALLY LEFT BLANK

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe. 31 20 00 EXCAVATION, TRENCHING AND BACKFILLING SECTION 1 - GENERAL 1.1 SUMMARY A. This section includes grading, excavation trenching, dewatering and backfilling for pipeline installation, roadways, walkways,

More information

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS. SECTION 1100 GRADING 1101 SCOPE. This section covers the performance of all work required for grading the project in coordination with all previous work performed at the locations shown on the contract

More information

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES SECTION 02215 EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES PART 1 - GENERAL 1.1 DESCRIPTION: This section includes materials, testing, and installation of earthwork for excavations, fills, and

More information

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis. PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and

More information

B. Subsurface data is available from the *Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the *Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 22 13 SITE GRADING PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the earthwork generally consisting of excavation, filling, backfilling and subgrade preparation as required for

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The Work of this Section shall be all labour, materials, equipment and supervision necessary

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014 1 0 1 0 1 0 1 SECTION 1. TRENCHING BASED ON DFD MASTER SPECIFICATION DATED // P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all work, materials, labor, equipment,

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

SECTION FLEXIBLE PAVING

SECTION FLEXIBLE PAVING SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation. SECTION 312333 TRENCHING AND BACKFILLING PART 1 - GENERAL 1.1 SUMMARY A. Excavate trenches for new electric and telephone conduits, gas lines, and their appurtenances from at least 5 feet outside the building

More information

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations.

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations. SPEC-1100 1/9 1.0 PURPOSE This specification describes the minimum requirements for general grading, excavation of earth, rock and solid slag, embankment construction, ditching, use of explosives, and

More information

SECTION BUILDING EARTHWORK

SECTION BUILDING EARTHWORK SECTION 02200 BUILDING EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification sections,

More information

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS 1. GENERAL CONDITIONS...1 3. DESCRIPTION...1 5. MATERIALS...1 5.1 General...1 5.2 Handling and Storage of Materials...1 5.3 Testing and Approval...1 5.4

More information

UNHSC Bioretention Soil Specification February, SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems

UNHSC Bioretention Soil Specification February, SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems PART 1 - GENERAL 1.1 SUMMARY A. Section includes soil media for the bioretention systems and rain gardens specified according to performance

More information

SECTION Section Excavation and Backfill For Structures Section Embedment and Base Course Aggregate

SECTION Section Excavation and Backfill For Structures Section Embedment and Base Course Aggregate SECTION 2110 EXCAVATION AND EMBANKMENT 1.00 GENERAL 1.01 Scope. Work to be performed under this section shall include all labor, equipment, materials and miscellaneous items necessary to perform all clearing

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

Section 1I-3 - Bioswales

Section 1I-3 - Bioswales BIOSWALES (Numbering pending) These specifications compliment the bioswale design portion of the Iowa Stormwater Management Manual in Chapter 2, Section 2I-3. Sections of the following documents, as referenced

More information

A. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):

A. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT): SECTION 31 32 13.16 CEMENT STABILIZATION PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the specifications for cement stabilization of sandy or silty soil and consists of pulverizing, addition

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

Michigan State University Construction Standards EARTHWORK PAGE SECTION EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS

Michigan State University Construction Standards EARTHWORK PAGE SECTION EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS PAGE 312300-1 SECTION 312300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

STANDARD SPECIFICATIONS WATER & SEWER SYSTEMS

STANDARD SPECIFICATIONS WATER & SEWER SYSTEMS 2015 STANDARD SPECIFICATIONS WATER & SEWER SYSTEMS CITY OF BUFORD, GEORGIA Prepared by Keck & Wood, Inc. STANDARD SPECIFICATIONS CITY OF BUFORD, GA 02/10/15 TABLE OF CONTENTS SECTION PAGE 311000 ROUTE

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

SECTION RIPRAP, BOULDERS, AND BEDDING

SECTION RIPRAP, BOULDERS, AND BEDDING SECTION 31 37 00 RIPRAP, BOULDERS, AND BEDDING PART 1 GENERAL 1.01 SECTION INCLUDES A. The WORK includes excavation, grading, and installation of riprap, boulders, soil riprap, void-filled riprap, and

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

TRENCH EXCAVATION AND BACKFILL

TRENCH EXCAVATION AND BACKFILL SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction Section 300 - Trench Excavation and Backfill TRENCH EXCAVATION AND BACKFILL PART - GENERAL.0 SECTION INCLUDES A. Trench Excavation

More information

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5 Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5 1.0 EXCAVATION AND FILL 1.1 GENERAL.1 The excavation or fill shall be made to provide proper grade, lines and crosssection for the laying of

More information

SECTION BITUMINOUS CONCRETE PAVEMENT

SECTION BITUMINOUS CONCRETE PAVEMENT SECTION 321216 BITUMINOUS CONCRETE PAVEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

File No Supplemental November Geotechnical and Environmental Consulting Engineers

File No Supplemental November Geotechnical and Environmental Consulting Engineers Supplemental Information & Geotechnical Recommendations Proposed New Solar Valley Location B (East of Building No. 7) Cañada Community College 4200 Farm Hill Boulevard Submitted to: Mr. Peter Hempel Construction

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02010 - PROJECT SURVEY AND LAYOUT PART 1 GENERAL 1.01 WORK INCLUDED A. The Contractor shall employ a New Jersey Licensed Land Surveyor to do all necessary surveying required to construct all elements

More information

BASE CONSTRUCTION MATERIALS A Aggregate

BASE CONSTRUCTION MATERIALS A Aggregate BASE CONSTRUCTION 2211 AGGREGATE BASE 2211.1 DESCRIPTION This work consists of placing aggregate base. 2211.2 MATERIALS A Aggregate... 3138 Provide the class of aggregate as required by the contract. 2211.3

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

SECTION SUBSURFACE INVESTIGATION

SECTION SUBSURFACE INVESTIGATION SECTION 02010 SUBSURFACE INVESTIGATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General and Supplementary Conditions and Division 1 through Division

More information

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General DESIGN STANDARDS Division 02 Existing Conditions- Site Work General I. This Division includes: A. Demolition B. Clearing and Grubbing C. Excavation, Backfill and Compaction D. Pavement Base E. Paving and

More information

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT). SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish

More information

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013 SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR

More information

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase.

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase. SECTION 20.22 LEVELING COURSE Article 22.1 General The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase. Article

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

EDITORIAL REVISION May Process Industry Practices Civil. PIP CVS02100 Site Preparation, Excavation, and Backfill Specification

EDITORIAL REVISION May Process Industry Practices Civil. PIP CVS02100 Site Preparation, Excavation, and Backfill Specification May 2014 Process Industry Practices Civil PIP CVS02100 Site Preparation, Excavation, and Backfill Specification PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process

More information

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 902 DECEMBER 1983 CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES 902.01 SCOPE 902.02 REFERENCES 902.03 DEFINITIONS TABLE OF

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

CONSTRUCTION SPECIFICATION FOR UNTREATED SUBBASE, BASE, SURFACE, SHOULDER, SELECTED SUBGRADE, AND STOCKPILING

CONSTRUCTION SPECIFICATION FOR UNTREATED SUBBASE, BASE, SURFACE, SHOULDER, SELECTED SUBGRADE, AND STOCKPILING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 314 NOVEMBER 2015 CONSTRUCTION SPECIFICATION FOR UNTREATED SUBBASE, BASE, SURFACE, SHOULDER, SELECTED SUBGRADE, AND STOCKPILING TABLE OF CONTENTS

More information

BIO-AQUIFER STORM SYSTEM

BIO-AQUIFER STORM SYSTEM BIO-AQUIFER STORM SYSTEM Specifications for Construction PART 1 GENERAL 1.01 SECTION INCLUDES A. Providing labor, materials, tools and equipment to furnish and install a permeable concrete paving stone

More information

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION IV. PIPELINE EXCAVATION AND BACKFILL SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include

More information

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows. 403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

CONSTRUCTION SPECIFICATIONS FOR CITY OF LINCOLN LINCOLN, NORTH DAKOTA

CONSTRUCTION SPECIFICATIONS FOR CITY OF LINCOLN LINCOLN, NORTH DAKOTA CONSTRUCTION SPECIFICATIONS FOR CITY OF LINCOLN LINCOLN, NORTH DAKOTA 74 Santee Road, Lincoln, ND 58504, Kadrmas, Lee & Jackson, Inc, City Engineer May, 2013 NOTE/DISCLAIMER: The specifications represented

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

2.1 Backfill - General

2.1 Backfill - General 2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately

More information

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION A. Section Includes B. References C. Quality Assurance D. Submittals E. Delivery, Storage and Handling F. Environmental Conditions G. Summary H. Concrete

More information

CHAPTER 500 STREET PAVEMENTS, CURB, GUTTER AND SIDEWALK CONSTRUCTION SPECIFICATIONS

CHAPTER 500 STREET PAVEMENTS, CURB, GUTTER AND SIDEWALK CONSTRUCTION SPECIFICATIONS CHAPTER 500 STREET PAVEMENTS, CURB, GUTTER AND SIDEWALK CONSTRUCTION SPECIFICATIONS The following list of Standard Documents defines the methods, materials, and testing to be utilized when designing and

More information

LANDSCAPE RETAINING WALLS

LANDSCAPE RETAINING WALLS SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls

More information

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM SECTION 32 32 23 SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM PART 1: GENERAL 1.01 Scope Work includes furnishing all materials, labor, equipment, and supervision to install a Stonebridge segmental

More information

ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)

ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) 275.1. Description. This Item shall govern for treating subgrade, new and/or existing base [with or without asphaltic concrete pavement (ACP)], or

More information

R-TANK SPECIFICATIONS

R-TANK SPECIFICATIONS TECHNICAL STORMWATER MANAGEMENT R-TANK SPECIFICATIONS PART 1 GENERAL 1.01 Related Documents A. Drawings, technical specification and general provisions of the Contract as modified herein apply to this

More information

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL

San Antonio Water System Standard Specifications for Construction ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL 804.1 DESCRIPTION: This section shall govern the excavation, trenching, and backfilling for water, sanitary sewer, and recycle mains construction, unless

More information

SPECIFICATIONS FOR CAST-IN-PLACE CONCRETE SLAB DUNN COUNTY TRANSFER STATION MENOMONIE, WISCONSIN

SPECIFICATIONS FOR CAST-IN-PLACE CONCRETE SLAB DUNN COUNTY TRANSFER STATION MENOMONIE, WISCONSIN SPECIFICATIONS FOR CAST-IN-PLACE CONCRETE SLAB DUNN COUNTY TRANSFER STATION MENOMONIE, WISCONSIN 1. SUMMARY A. Work includes: 1. Pavement removal, topsoil stripping, and site grading for concrete slab.

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19-1 19-1.01 Exploratory Excavation... 19-1 19-1.02 Trench... 19-1 19-1.02.AStorm Drain Pipe...

More information

EARTHWORK, SUBGRADE, AND SUBBASE

EARTHWORK, SUBGRADE, AND SUBBASE EARTHWORK, SUBGRADE, AND SUBBASE PART - GENERAL.0 SECTION INCLUDES A. Clearing and Grubbing B. Earthwork, Excavation, and Embankment Construction C. Subgrade Preparation D. Subbase Construction E. Topsoil.02

More information

SECTION GRADING AND SITE PREPARATION CITY OF LEE S SUMMIT, MISSOURI STANDARD SPECIFICATIONS

SECTION GRADING AND SITE PREPARATION CITY OF LEE S SUMMIT, MISSOURI STANDARD SPECIFICATIONS SECTION 2100 - GRADING AND SITE PREPARATION CITY OF LEE S SUMMIT, MISSOURI STANDARD SPECIFICATIONS The City of Lee s Summit hereby adopts Section 2100 of the Kansas City Metropolitan Chapter of APWA Construction

More information

Municipality of Waterville Public Sidewalk Repair Policy

Municipality of Waterville Public Sidewalk Repair Policy Municipality of Waterville Public Sidewalk Repair Policy Purpose - The purpose of this policy is to protect the public health, safety and welfare of the citizens and inhabitants of the Municipality by

More information

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material

More information

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown

More information

SECTION ASPHALT PAVING

SECTION ASPHALT PAVING SECTION 321216- ASPHALT PAVING PART I-GENERAL 1.1 SUMMARY A. Section Includes: 1. Hot-mix asphalt patching. 2. Hot-mix asphalt paving. B. Related Sections: 1. Division 31 Section "Earthwork and Aggregate

More information

Division 02 - Site Work Section

Division 02 - Site Work Section NWIT-11-26 Page 1 1 GENERAL 1.1 REQUIREMENTS INCLUDED.1 Furnish all labour, material, services and equipment necessary to carry out and complete excavation work and shoring, as indicated on the drawings

More information

SECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS

SECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS SECTION 321413.13 INTERLOCKING PRECAST CONCRETE UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Interlocking concrete paver units. 2. Sand setting bed. 3. Sand joint

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,

More information

PAVING SLABS ON A CONCRETE BASE

PAVING SLABS ON A CONCRETE BASE SECTION 32 14 13.16 PAVING SLABS ON A CONCRETE BASE (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs on a sand bed over concrete for pedestrian applications.

More information

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

Municipal Inspection and Construction Guidelines Section I Roadworks SECTION I ROADWORKS I-1 GENERAL

Municipal Inspection and Construction Guidelines Section I Roadworks SECTION I ROADWORKS I-1 GENERAL I-1 GENERAL SECTION I ROADWORKS The Consultant Engineer is to monitor all specified asphalt, granular materials and sub-grade preparation to ensure all road and curb construction is undertaken as outlined

More information

SECTION INTERLOCKING CONCRETE PAVERS

SECTION INTERLOCKING CONCRETE PAVERS SECTION 23 14 13 INTERLOCKING CONCRETE PAVERS (1995 MasterFormat Section 02780) Note: This guide specification for concrete paver applications in the U.S. for concrete pavers and bedding sand over a compacted

More information

Table of Contents. Section 10,010 - Demolition of Building Structures Section Includes Description of Work 1. 1.

Table of Contents. Section 10,010 - Demolition of Building Structures Section Includes Description of Work 1. 1. Table of Contents Page No. Part 1 - General 1.01 Section Includes 1 1.02 Description of Work 1 1.03 Submittals 1 1.04 Substitutions 1 1.05 Delivery, Storage, and Handling 1 1.06 Scheduling and Conflicts

More information

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 401 NOVEMBER 2010 CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING TABLE OF CONTENTS 401.01 SCOPE 401.02 REFERENCES 401.03 DEFINITIONS

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

SPECIFICATION FOR ENGINEERED FILLS

SPECIFICATION FOR ENGINEERED FILLS SPECIFICATION FOR ENGINEERED FILLS This specification is intended to be used for the engineered fill. The specification is suitable for most purposes but there may be special conditions existing at some

More information

Construction Specification for Concrete Unit Pavers

Construction Specification for Concrete Unit Pavers Engineering & Construction Services Division Standard Specifications for Road Works TS 3.80 September 2017 for Concrete Unit Pavers Table of Contents TS 3.80.01 SCOPE... 2 TS 3.80.02 REFERENCES... 2 TS

More information

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING SECTION 334701 - WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. The Contractor shall provide all labor, materials, tools, and equipment required

More information

SECTION Exterior steel pipe and tube guard rail system. A. Definitions in ASTM E 985 for railing-related terms apply to this section.

SECTION Exterior steel pipe and tube guard rail system. A. Definitions in ASTM E 985 for railing-related terms apply to this section. SECTION 055213 PIPE AND TUBE RAILINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification

More information

SECTION 3: SUB BASE AND BASE COURSES

SECTION 3: SUB BASE AND BASE COURSES SECTION 3: SUB BASE AND BASE COURSES Page i TABLE OF CONTENTS SECTION 3: SUB BASE AND BASE COURSES i SECTION 3.01 MATERIALS FOR SUB-BASE AND BASE COURSES 1 3.01.01 SCOPE 1 3.01.02 GENERAL 1 3.01.03 GRANULAR

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration

More information

CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR, SUBBASE, BASE, SURFACE SHOULDER AND STOCKPILING

CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR, SUBBASE, BASE, SURFACE SHOULDER AND STOCKPILING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 314 DECEMBER 1993 CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR, SUBBASE, BASE, SURFACE SHOULDER AND STOCKPILING 314.01 SCOPE 314.02 REFERENCES

More information

City of Brandon Division 2 Standard Construction Specifications Section January 2000 Page 1 of 10 SOIL CEMENT BASE COURSE PART 1 GENERAL

City of Brandon Division 2 Standard Construction Specifications Section January 2000 Page 1 of 10 SOIL CEMENT BASE COURSE PART 1 GENERAL January 2000 Page 1 of 10 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 APPROVALS PART 2 PRODUCTS 2.01 CEMENT 2.02 WATER The General Conditions of the Contract,

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

SECTION AGGREGATES

SECTION AGGREGATES SECTION 32 05 00 AGGREGATES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Aggregate base 2. Engineered fill 3. Backfill 4. Fine filter aggregate (non-frost susceptible fill) 5. Riprap 6. Recreational

More information

SECTION STORM DRAIN

SECTION STORM DRAIN PART 1 - GENERAL 1-01 SECTION INCLUDED A. Furnishing and installing storm drainage facilities, including pipe, cleanout, manhole structures and inlet structures. 1-02 RELATED SECTIONS A. Division 00 Contract

More information

SECTION CONTROLLED LOW STRENGTH MATERIAL

SECTION CONTROLLED LOW STRENGTH MATERIAL SECTION 03300 CONTROLLED LOW STRENGTH MATERIAL PART 1 GENERAL 1.1 DESCRIPTION A. This Section specifies Controlled Low Strength Material (CLSM) to be used as described in this specification, including

More information

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1 SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL TABLE OF CONTENTS 2.1 General...2-1 2.2 Materials...2-1 2.2.1 Compacted Non-granular Material...2-1 2.2.2 Gravel Material and Crushed Aggregate

More information