Exposition Light Rail Transit Project

Size: px
Start display at page:

Download "Exposition Light Rail Transit Project"

Transcription

1 Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update January 14, 2008

2 PHASE 1

3 Phase 1 Project Status Design Design approximately 78% complete Construction Packages Negotiated 7 of the 18 construction packages Third Party Agreements Executed 5 of the 8 third party agreements

4 Phase 1 Project Status Current Construction Activities Completed driveway reconstruction on Flower Street between Washington Boulevard and 23 rd Street Continued drilling secant and CIDH piles for trench walls Continued utility relocations to support trench construction Completed jacking pits for construction of 61-inch waterline relocation Completed termination of 52 leases; 12 leases remain active Of the 21 parcels identified as being required for the project, 9 have been acquired

5 Phase 1 Project Status CPUC Grade Crossing Applications The CPUC approved 36 of the 38 requested grade crossings at their December 20 th, 2007 meeting The Commission ruled that evidentiary hearings are necessary for Farmdale (Dorsey H.S.) and the Harvard Pedestrian Crossing (Foshay Learning Center) The schedule for the evidentiary hearings is pending

6 Construction Progress Gas Line Installation at Washington & Flower

7 Construction Progress Tying Rebar Cages for CIDH Piles

8 Construction Progress Curb & Gutter Installation Along Flower Street

9 Construction Progress Boring Machine for 61 Water Line

10 Construction Progress Soil Caving at CIDH Piling

11 Construction Progress Excavating for Underground Utilities

12 Phase 1 Project Status Project Budget Summary Construction Budget 7 of 18 construction packages have been negotiated in an amount totaling $138,795,034 Currently under running the revised construction budget Project Budget All tasks are within the revised budget Remaining significant risks to the budget include: - Contracts yet to be negotiated - Contractor claims - Farmdale crossing - Yard & storage facility - Use of contaminated soil in embankment approaches to aerial structures

13 Phase 1 Project Status Project Schedule Summary FFP is currently showing a 16 week delay to Substantial Completion Impacts associated with the Segment A3 Trench work Contractor is developing an alternative sewer design for City approval Authority has asked contractor for a recovery schedule Other areas of Potential Delay Location and layout of Service and Inspection Facility Metro funded enhancements at the Blue Line Tie-In Aerial structures at La Cienega, La Brea and Ballona Creek Any changes to the Farmdale crossing

14 Phase 1 Project Status Project Issue Summary Service and Inspection Facility Originally located adjacent to Long Beach Blue Line Yard on Edison Property Edison will not allow permanent facilities under existing power lines Staff evaluating alternative sites Additional Environmental Studies Relocation of Traction Power Substations 3 & 4 require Environmental Assessment Modified location and layout of Service and Inspection Facility Alternatives require Environmental Assessment or Supplemental EIS/EIR Any potential changes to the Farmdale crossing

15 Phase 1 Project Status Project Issue Summary Sewer Pipe Cracking Along Exposition at USC Approximately 1,200 feet of newly installed sewer pipe has cracked and will need to be replaced Will uncover approximately 200 feet of 15-inch pipe to evaluate cause of failure and need for replacement Remaining pipe will be replaced in March or April 2008

16 Government/Community Relations Phase 1 Project Status Provided project status updates to the following organizations: Senator Mark Ridley-Thomas and Empowerment Congress Delta Senior Center West Angeles Church (Bishop Charles Blake) Participated in the following community events: GLAAACC Monthly Luncheon Assemblymember Karen Bass Year End Celebration Ted Alexander Math and Science Magnet s Winterfest Continued business assessments in Segment C Established Expo Project Informational Center at Foshay Learning Center and Ted Alexander Math and Science Magnet Attended regularly scheduled meetings with USC and Expo Park to discuss coordination of events and construction activities

17 Summary of Jobs Program Activities DECEMBER construction workers currently working on the Expo Project (Laborers, Carpenters, or Operators). 13 are from the Expo Corridor (12 minority/1 non-minority). All Expo Construction Jobs are Union Jobs. 83 people are currently working for FFP in non-union jobs (clerical or professional level positions). 15 workers are from the Expo Corridor. To date, FFP has sponsored 24 individuals into local unions (Laborers, Carpenters or Operators). Robnette Electric, a minority DBE firm located in the Expo Corridor on Crenshaw Blvd, was the successful bidder for the electrical and data/communications conduit installation for the Western and Crenshaw Blvd stations.

18 Summary of DBE Program Activities DBE Goals and Signed Contracts through December % DBE Goal 20% 20% To To date date 13.84% DBE Goal 20% 20% To Date 21.8% DBE Goal 20% 20% To date 34.7% DBE DBE Professional Professional Service Service Firms Firms $6.088 $6.088 Million Million DBE DBE Design Design Service Service Firms Firms $6.2 $6.2 Million Million 9 DBE DBE Construction Construction Service Service Firms Firms $32.9 $32.9 Million Million

19 PHASE 2

20 Phase 2 Project Status AA/EIS/Conceptual Engineering Continued preparation of draft technical background reports Initiated work on Colorado Street alternative and Olympic Blvd option per City of Santa Monica s request Advanced draft Milestone 2 grade crossing reports Advanced Overland Avenue drainage analysis Worked with Metro on ridership model corrections and recalibration Continued work on station/parking layouts and locations Government/Community Relations Conducted stakeholder briefing for: Metro s Westside/Central Governance Council Planned for next round of community meetings to take place in February

21 Phase 2 Project Status Phase 2 Milestones Activity Scheduled Completion Date Current Completion Date Status Comments Scoping Meetings & Report Mar-07 May-07 Complete Screening of Alternatives May-07 Oct-07 Complete Delay in receiving ridership model from Metro Administrative Draft to FTA Oct-07 Apr-08 In Progress Delay due to need to recalibrate model received from Metro Start Public Hearings on Draft DEIS/DEIR Submit New Starts 5309 Report Summer 2008 Summer 2008 Feb-08 Jul-08 FTA must sign off on Draft DEIS before document can be circulated Board Adoption of LPA May-08 Oct-08 Request to enter Preliminary Engineering (PE) May-08 Oct-08 Risks to Current Schedule: Ridership Model Colorado Street Alignment Analysis Maintenance Facility for Phase 2

22 Exposition Light Rail Transit Project December 2007 Disadvantaged Business Enterprise (DBE) and Local Jobs Program Update

23 Program Overview FFP LOCAL JOBS PROGRAM INITIATIVE AND DBE CONTRACTING OPPORTUNITIES The following information provides a status update of FFP s Jobs Program outreach and work activities in the month of December. This report will also detail the activities to be undertaken in the month of January to provide contracting and subcontracting opportunities for Disadvantaged Business Enterprise (DBE) firms and construction jobs for local residents.

24 Summary of Activities December Activities FFP s Local Jobs Program recruits skilled and unskilled labor from within the Expo Corridor. FFP anticipates that during the peak of construction, 250 construction jobs will be available on the Expo project. FFP s construction Jobs Program goal is to hire local residents to fill at least 30% of these construction jobs. Completed additional orientation sessions with PVJOBS. To date, 317 people have attended these sessions and are on a priority list to be considered for employment by the contractor as positions become available over the life of the project. These people are also eligible to receive pre-apprenticeship and life skills training as well as referrals to other construction jobs. FFP is working with PVJOBS on a methodology and database to accurately track and monitor these individuals. Coordinated a briefing for interested DBE subcontractors to discuss upcoming contracting opportunities. Coordinated monthly meeting with Local Unions 300 and 12 at the Construction Yard with the Segment Manager and Field Superintendents. Established DBE specific goals for upcoming construction contracts to be advertised.

25 Local Jobs Program Jobs Program Highlights Total # Construction Workers Currently working on the Expo project (Laborers, Carpenters or Operators) = workers from the Expo Corridor --All Expo Construction Jobs are Union Jobs Total # People that have attended the Local Jobs Program Orientations in order to be referred to PVJOBS and one of their collaborative partners for training and/or job-readiness assistance = 317 Total # People hired on the Expo Project through the Local Jobs Program (including referrals from the local unions) in the Laborer, Carpenter, or Operator fields= 33 Total # of FFP employees (non-union) currently working on the Expo project in a clerical or professional level position =83 total workers =16 from the Expo corridor Total number of people sponsored into a local union by the contractor (active or inactive) in the Laborer, Carpenter or Operator fields = 24

26 DBE Program DBE PROGRAM AND CONTRACTING OPPORTUNITIES FFP is committed to a diverse work force and is making significant progress in reaching the 20% DBE goal for Design, Professional Services as well as Construction. These goals are in addition to the 30% local resident hiring goal for construction work. Some DBE firms have already been hired as they were included on the design/build team when FFPs proposal was submitted to the Authority. Robnette Electric (a DBE firm) located within the Expo Corridor, was the successful bidder for electrical work on two stations and a subcontract will be issued in January. Conducted DBE Workshop that included potential bidders, FFP s Senior Estimator, Senior Contracts Manager and Jobs Program staff. DBE goals are developed based upon availability of qualified firms and past experience with other transit agencies. As additional DBE opportunities are identified, and as Work Packages are released, FFP will advertise these new opportunities in industry publications and will make efforts to reach out to new DBE businesses via , website postings, outreach letters, an assortment of local newspapers with a wide array of readership including the African-American and Hispanic communities, and other venues as they are identified.

27 DBE Program DBE PROGRAM AND CONTRACTING OPPORTUNITIES DBE Firms/ Small-Sized Businesses for Design Services: The Design Services Allowance + Fee is $28,348,200 and the DBE Goal is 20%. To date, 12 DBE firms have subcontracts for design services on the project for a total contract value of $6.2 million. 10 of the 12 are minority firms. DBE Commitment through December = $6,203, or 21.88% DBE Attainment through December = $4,893, or 17.26%

28 DBE Program Design Services * Minority Firm Contractor Sub to Work Scope DBE Date of Award Comments Contract Value * B&C Transit Consultants Parsons Train control & communication design. Yes 8/25/07 Subcontract signed $200,000 * Bullock & Associates Parsons Engineering - Sewage Yes 9/8/06 Subcontract signed $435,000 * D'Leon Consulting Engineers Parsons Utility/Drainage Engineering and Admin Support Yes 4/10/06 Subcontract signed $700,000 * GC Tech, Inc (Engineering) Parsons Engineering and Admin Support Yes 4/10/06 Subcontract signed $870,000 * Cordoba GC Tech Design Support Yes 07/17/06 Subcontract signed $750,000 * Griego & Associates Parsons Systems Safety Engineering Yes 4/10/06 Subcontract signed $226,000 Elwood Associates Gruen Art Coordination Yes 7/25/06 Subcontract signed $46,000 * Advanced Building Group (formerly Jubany Architects) Gruen Station Architecture (National/Washington Station) Yes 7/25/06 Subcontract signed $214,000 * Miyamoto International Gruen Station Structural Design Yes 7/25/06 Subcontract signed $881,000 * RAW International Gruen Station Architecture (Western, Crenshaw Station) Yes 7/25/06 Subcontract signed $357,000 Selbert Perkins Gruen Environmental Graphics, Signage Yes 7/25/06 Subcontract signed $185,000 * Lin Consulting Parsons Traffic Signals and Street Lighting Design Yes 6/1/06 Subcontract signed $1,338,000

29 DBE Program DBE PROGRAM AND CONTRACTING OPPORTUNITIES DBE Firms/ Small-Sized Businesses for Professional Services: The Professional Services Allowance + Fee is $43,978,100 and the DBE Goal is 20%. There are 14 DBE firms that have subcontracts for professional services for a total contract value of $6.088 million. 9 of the 14 are minority firms. DBE Commitment through December = $6,088, or 13.84% DBE Attainment through December = $2,923, or 6.65%

30 DBE Program Professional Services * Minority Firm Contractor Sub to Work Scope DBE Date of Award Comments Contract Value * Anil Verma Assoc. FFP Project Controls, Document Control, Business Admin. Yes 5/15/06 Subcontract signed $1,249,000 AP Engineers Leighton Soil Testing Yes 9/1/06 Subcontract signed $50,000 * Asahi Surveying, Inc. Parsons Design Surveys Yes 4/7/06 Subcontract signed $959,500 C&L Drilling Leighton Drilling Yes 9/01/06 Subcontract signed $15,000 Elwood Associates Gruen Art Coordination Yes 7/25/06 Subcontract signed $20,000 * GC Tech, Inc. FFP Community Outreach Yes 01/15/07 Subcontract signed $1,830,000 * Advanced Building Group (formerly Jubany Architects Gruen Station Architecture Construction Support (National/Washington Station) Yes 07/25/06 Subcontract signed $6,220 * Lee Andrews GCTech Construction Claims Yes 4/11/06 Subcontract signed $150,000 * Lin Consulting Parsons Traffic Signals & Street Lighting Yes 6/01/06 Subcontract signed $64,000 * Miyamoto International Gruen Station Structural Design Construction Support Yes 7/25/06 Subcontract signed $30,000

31 DBE Program Professional Services (continued) Contractor Sub to Work Scope DBE Date of Award Comments Contract Value * Seville Construction Services, Inc. FFP Construction Inspection Services Yes 7/06/07 Subcontract signed $150,000 MB Professional Services FFP Inspection Services, Inc. Yes 8/23/07 Subcontract signed $150,000 * RAW International Gruen Station Architecture Construction Support (Western, Crenshaw Station) Yes 07/25/06 Subcontract signed $15,000 Wagner Engineering & Survey, Inc FFP Construction Surveying Yes 10/11/06 Professional Service Agreement Signed $1,400,000

32 DBE Program DBE PROGRAM AND CONTRACTING OPPORTUNITIES DBE Firms/ Small-Sized Businesses for Construction Services: The Construction Services Allowance + Fee is $94,754, and the DBE Goal is 20%. To date, 9 DBE firms have subcontracts for construction services for a total contract value of $32.91 million. 5 of the 9 are minority firms. DBE Commitment through December = $32,909, or 34.73% DBE Attainment through December = $3,045, or 3.21%

33 DBE Program Construction Services Phase * Minority Firms Contractor Sub to Work Scope DBE Date of Award Comments Contract Value Lincoln Pacific Builders, Inc. FFP Electrical Work Yes 6/18/07 Subcontract signed $2,719,060 * CPR Trucking FFP Trucking Yes 6/11/07 PO/Rental Agreement $250,000 * Cut Core & Demolition FFP Concrete sawing breaking & hauling Yes 11/01/06 PO/Rental Agreement $600,000 * Diversified Landscaping FFP Landscape, palm tree relocation Yes 11/16/06 Subcontract signed $379,000 High Light Electric FFP Traffic signal and street lighting Yes 10/01/06 Subcontract signed $1,941,570 * B & C Transit Consultants FFP Train control procurement, product integration and delivery of as-builts Yes 8/25/07 Subcontract Under development $23,000,000 United Steel Placers FFP Reinforcing steel Yes 05/29/07 Subcontract Signed $3,694,000 * Ortiz Paving FFP Asphalt Concrete Paving Yes 8/21/07 Subcontract Signed $322,000 Commtech, dba Premier Label Water FFP Metro Label Water Yes 09/27/07 PO/Rental Agreement $5000

34 Summary of DBE Program Activities DBE Goals and Signed Contracts through December % DBE Goal 20% 20% To To date date 13.84% DBE Goal 20% 20% To Date 21.8% DBE Goal 20% 20% To date 34.7% DBE DBE Professional Professional Service Service Firms Firms $6.088 $6.088 Million Million DBE DBE Design Design Service Service Firms Firms $6.2 $6.2 Million Million 9 DBE DBE Construction Construction Service Service Firms Firms $32.9 $32.9 Million Million

35 Planned Activities January Planned Activities Advertise to reach small-sized businesses and DBE s experienced in providing services in a variety of areas including but not limited to: fencing, architectural or structural metals, piling, glass & glazing, elevators, pre-cut concrete, station finishing, striping, signing, painting, trucking equipment rentals, expendable supplies, etc. Coordinate quarterly DBE & Small Business Contractors Workshops in order to provide information about contracting opportunities. Continue coordinating with PVJOBS to implement the screening and jobreadiness portion of the Local Jobs Program. Continue to coordinate with various Community/Faith Based Organizations and public agencies who partner with PVJOBS to provide guidance or assistance to the numerous job-seekers who are not hired through the EXPO Local Jobs Program. Continue to host monthly coordination meetings with representatives from various unions, such Laborers Union Local 300 and the Operators Union 12 to monitor the construction hiring progress.

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Expo Project Briefing Phase 1 and 2 For IRWA October 26, 2010 Phase 1 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015 Crenshaw/LAX Transit Project Construction Update Meeting July, 2015 1 Project Overview Design-Build Contract - Walsh Shea Corridor Constructors (WSCC) 8.5 mile Light Rail Line Eight (8) new stations Three

More information

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update December 3, 2015

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update December 3, 2015 Expo Board Presentation Monthly Project Status Update December 3, 215 Expo Phase 1 Phase 1 Project Status Closeout Status Completing Closeout of Remaining Elements of Work Working with Metro and City of

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Metro Blue Line Improvements & Project Update

Metro Blue Line Improvements & Project Update Metro Blue Line Improvements & Project Update February 9, 2018 MBL Operational Improvements - External Metro & LADOT coordination to identify traffic signal and intersection treatments aimed at increasing

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,

More information

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 1 Agenda Sections 1 & 2 Section 1 Construction Updates TBM Art and Naming Contest Project Construction Updates: Wilshire/Western

More information

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation. FACT SHEET GENERAL INFORMATION The project extends the existing No.7 Line subway service via a 1.5 mile extension from Times Square to the new 34 Street Hudson Yards station located at West 34th Street

More information

Click to edit Master title style I N D U S T R Y D AY O C T O B E R 1,

Click to edit Master title style I N D U S T R Y D AY O C T O B E R 1, Click to edit Master title style I N D U S T R Y D AY O C T O B E R 1, 2 0 1 4 Welcome Nevada Governor Brian Sandoval Nevada DOT Director Rudy Malfabon, PE Goals Goals Obtain the best value for the costs

More information

Outreach Meeting September 29, 2016

Outreach Meeting September 29, 2016 Outreach Meeting September 29, 2016 Introductions Project Overview Heavy Civil GC/CM Process S/DBE Goals Bid Package Breakdown SDBE Opportunities Working w/kiewit-hoffman E130 is initial section of Eastlink

More information

DBE AND SBE OPEN HOUSE. North Metro Rail Line BUILT FOR REGIONAL TRANSPORTATION DISTRICT (RTD) December 18, 2014

DBE AND SBE OPEN HOUSE. North Metro Rail Line BUILT FOR REGIONAL TRANSPORTATION DISTRICT (RTD) December 18, 2014 DBE AND SBE OPEN HOUSE December 18, 2014 North Metro Rail Line BUILT FOR REGIONAL TRANSPORTATION DISTRICT (RTD) KEY TEAM MEMBERS Dave Trent, Project Director Mike Salmon, Deputy Project Director Mike Chilcott,

More information

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006

More information

Forsyth County Procurement

Forsyth County Procurement August 1, 2017 Forsyth County Procurement Donna Kukarola, CPPO, CPPB, Procurement Director ADDENDUM #2 Bid 17-72-3340 For: Providing all materials, equipment and labor for the Jot em Down Road Water Tank

More information

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Appendix A RFP No. 894-2014 Page 1 of 1 Template Version: SrC120131129 - Consulting Services RFP APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Revision: 2014-09-22 DEFINITION OF

More information

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2 OMAHA BASEBALL STADIUM May 21, 2009 Report No. 2 METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority Omaha, Nebraska

More information

NEW JERSEY DEPARTMENT OF TRANSPORTATION DISADVANTAGED BUSINESS ENTERPRISE GOAL SUBMISSION FEDERAL FISCAL YEARS 2017 THROUGH 2019

NEW JERSEY DEPARTMENT OF TRANSPORTATION DISADVANTAGED BUSINESS ENTERPRISE GOAL SUBMISSION FEDERAL FISCAL YEARS 2017 THROUGH 2019 NEW JERSEY DEPARTMENT OF TRANSPORTATION DISADVANTAGED BUSINESS ENTERPRISE GOAL SUBMISSION FEDERAL FISCAL YEARS 2017 THROUGH 2019 The New Jersey Department of Transportation (NJDOT) has established a Disadvantaged

More information

REGIONAL LIGHT RAIL CONNECTOR DOWNTOWN

REGIONAL LIGHT RAIL CONNECTOR DOWNTOWN @ Metro 12. Los Angeles County One Gateway Plaza ~13.gzz.zooo Tei Metropolitan Transportation Authority Los Angeles, CA 90012-2952 metro.net * PLANNING AND PROGRAMMING COMMITTEE June 20,2007 SUBJECT: ACTION:

More information

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Agenda Wilshire/Rodeo Station Advance Utility Relocation Demo of former Ace Gallery MOA for Design-Build Century City/Constellation

More information

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010 I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD

More information

2.0 PROJ ECT D ESCRI PTION

2.0 PROJ ECT D ESCRI PTION 2.0 PROJ ECT D ESCRI PTION 2.1 PROJECT LOCATION The proposed project is in the City of Los Angeles (Figure 2.1-1, Regional Project Location Map) in the communities of Venice and Playa Del Rey (see Figure

More information

Recommend to Board. Final Action

Recommend to Board. Final Action MOTION NO. M2016-19 Tacoma Trestle Construction Contract MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 2/11/2016 2/25/2016 Recommend to Board Final Action Ahmad

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report February through April 2012 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction

More information

AGENDA ITEM NO. June 6, 2017

AGENDA ITEM NO. June 6, 2017 DocuSign Envelope ID: 7CA39164-0C90-42A5-B40D-ED361AA88939 AGENDA ITEM NO. June 6, 2017 May 23, 2017 Honorable Board of Supervisors County of Alameda 1221 Oak Street, Suite 536 Oakland, CA 94612-4305 Dear

More information

CITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES

CITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES CITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES SUMMARY AND INTENT OF PROJECT The City of Des Plaines Curb and Sidewalk Program is intended to repair hazardous sidewalk and

More information

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION City of Santa Monica Community Maintenance Department Public Landscape Division 2600 Ocean Park Blvd. Santa Moni ca, CA 90405 (310) 458-8974

More information

Step 1: Determination of Base Figure for Relative Availability of DBEs

Step 1: Determination of Base Figure for Relative Availability of DBEs MassDOT calculated the Transit Division goal utilizing a preliminary budget to identify federalaid service and supply contracts on USDOT-assisted projects to be performed. To determine the relative availability

More information

Mid-Coast Transit Constructors Quality Control & Quality Assurance August 15, 2017

Mid-Coast Transit Constructors Quality Control & Quality Assurance August 15, 2017 Mid-Coast Transit Constructors Quality Control & Quality Assurance August 15, 2017 Welcome and Introductions Introduction Cory Raymond, MCTC DBE/SB Compliance and Outreach (DBE Team: Alison Lobenstein;

More information

Metro Purple Line Extension

Metro Purple Line Extension metro.net/works Metro Purple Line Extension Construction Fact Sheet summer 2013 building the stations Construction at each station is estimated to take five to seven years. The station is a large box,

More information

Route 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building

Route 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building PROJECT SHOWING MINUTES Route 7 Widening Project January 15, 2013 10 a.m. NOVA District Building Overview / Welcome: Michael Gleasman, PE, Area Construction Engineer (VDOT) Overview: A question and answer

More information

Overview of City of Dallas and DART Interlocal Agreements

Overview of City of Dallas and DART Interlocal Agreements Overview of City of Dallas and DART Interlocal Agreements Council Transportation and Environment Committee Prepared by Transportation Programs Public Works and Transportation March 24, 2008 Purpose of

More information

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report July 2013 TABLE OF CONTENTS Project Manager

More information

Task Order Authorization

Task Order Authorization Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79,795.00 This Task Order pertains to the On-Call Agreement

More information

ATTACHMENT 4 Section Project Status Quarterly Report - Dec 31, 2015 Measure V - Clean Beaches and Ocean Parcel Tax

ATTACHMENT 4 Section Project Status Quarterly Report - Dec 31, 2015 Measure V - Clean Beaches and Ocean Parcel Tax ATTACHMENT 4 Section 3.0 - Project Status Quarterly Report - Dec 31, 2015 Completed Projects Description Bicknell Avenue Green Street Pier Storm Drain Improvement Pier Water Quality Improvement Permeable

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:

More information

Carpinteria Avenue Bridge Replacement Project Description Introduction

Carpinteria Avenue Bridge Replacement Project Description Introduction Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with

More information

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014 Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend

More information

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer,

More information

WINTERHAVEN PUBLIC SAFETY FACILITY PROJECT

WINTERHAVEN PUBLIC SAFETY FACILITY PROJECT WINTERHAVEN PUBLIC SAFETY FACILITY PROJECT Funded by: California Department of Housing and Community Development (HCD) through its Community Development Block Grant (CDBG) Program and the County of Imperial.

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

KANSAS CITY REGIONAL TIGER PROJECT MONTHLY PROGESS REPORT

KANSAS CITY REGIONAL TIGER PROJECT MONTHLY PROGESS REPORT KANSAS CITY REGIONAL TIGER PROJECT MONTHLY PROGESS REPORT January 2012 Submitted February 15, 2012 PROJECT TYPE: Multimodal(bicycle, pedestrian, roadway, transit) LOCATION: Kansas City metropolitan area

More information

CITY OF SAFETY HARBOR ENGINEERING

CITY OF SAFETY HARBOR ENGINEERING CITY OF SAFETY HARBOR ENGINEERING The Engineering Department provides the city with technical services including design of construction and maintenance projects, review of development plans, field surveys,

More information

San Pablo Avenue and Buchanan Street Pedestrian Safety Improvements Project Contract Addendum No. 1 - Sidewalk Reconstruction

San Pablo Avenue and Buchanan Street Pedestrian Safety Improvements Project Contract Addendum No. 1 - Sidewalk Reconstruction BKF No. 20165089-11 June 15, 2017 Aleida Andrino-Chavez Transportation Planner City of Albany 1000 San Pablo Avenue Albany, CA 94706 Transmitted Via Email Subject: San Pablo Avenue and Buchanan Street

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

Subcontractor Pre-Qualification Form

Subcontractor Pre-Qualification Form Subcontractor Pre-Qualification Form Page 1 of 3 Today s Date (MO/DAY/YEAR): / / Person Completing Form: Company Information Company Name: Company Website: President/Owner/Partner Name: Other Contact Name/Title:

More information

EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS June 27, 2017

EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS June 27, 2017 EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS 21-17 June 27, 2017 TO: RE: Invited Firms Request for Submittals to El Paso Water - Public Service Board (EPWater) Statement of Work Professional

More information

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

Federal Transit Administration (FTA) Overall DBE Goal-Setting Methodology

Federal Transit Administration (FTA) Overall DBE Goal-Setting Methodology Federal Transit Administration (FTA) Overall DBE Goal-Setting Methodology for FFY 2017-2019 Goal Period Submitted in fulfillment of: Title 49 Code of Federal Regulations Part 26 This analysis is prepared

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

The Gateway Expressway FTBA Conference. February 2-3, 2017

The Gateway Expressway FTBA Conference. February 2-3, 2017 The Gateway Expressway FTBA Conference February 2-3, 2017 256996-1 SR 686 (Roosevelt Blvd.) at CR 611 (49th St. N) PD&E 256866-1 Segment 2A 256997-1 SR 686 (Roosevelt Blvd.) from 49th St. Bridge to north

More information

METRO BOARD OF DIRECTORS Capital and Strategic Planning

METRO BOARD OF DIRECTORS Capital and Strategic Planning Thomas C. Lambert PRESIDENT & CEO METRO BOARD OF DIRECTORS Capital and Strategic Planning Working Committee Meeting METRO Board Room, 2 nd Floor August 22, 2016, 1:30 PM ACTION COMMITTEE MEMBERS Christof

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY

More information

MOTION NO. M Design-Build Contract for Link Maintenance of Way Facility for University Link Extension

MOTION NO. M Design-Build Contract for Link Maintenance of Way Facility for University Link Extension MOTION NO. M2014-27 Design-Build Contract for Link Maintenance of Way Facility for University Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 04/10/2014 04/24/2014 Recommendation

More information

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013 SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR

More information

Filing Plans and Specifications

Filing Plans and Specifications Upcoming Utilities Department Projects Anticipated To Have Plans and Specifications Filed August, September, October Report for Council Infrastructure Committee on 7-19-2016 Water and WPC Plant Projects

More information

REQUEST FOR PROPOSAL ARCHITECTURAL & ENGINEERING SERVICES OTTAWA COUNTY ROAD COMMISSION COOPERSVILLE AREA MAINTENANCE COMPLEX

REQUEST FOR PROPOSAL ARCHITECTURAL & ENGINEERING SERVICES OTTAWA COUNTY ROAD COMMISSION COOPERSVILLE AREA MAINTENANCE COMPLEX REQUEST FOR PROPOSAL ARCHITECTURAL & ENGINEERING SERVICES OTTAWA COUNTY ROAD COMMISSION COOPERSVILLE AREA MAINTENANCE COMPLEX The Ottawa County Road Commission is seeking the submittal of written proposals

More information

Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project

Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project Kimberly Ong, P.E. LACMTA, Deputy Executive Officer Project Mgmt. Los Angeles, CA Matt Gallagher, P.E.

More information

Metro Board Action: Motion 22.1

Metro Board Action: Motion 22.1 Los Angeles County Metropolitan Transportation Authority Metro Board Action: Motion 22.1 Implementation Update presented to the Corridor Advisory Committee March 17, 2016 Background Motion 22.1 October

More information

Ongoing and Future Project Work. Construction Management

Ongoing and Future Project Work. Construction Management Ongoing and Future Project Work New Broward County Courthouse Tower 1,000 Car Courthouse Garage Midrise Building Renovations 714,000 square foot, 20-story Civil/Family Courthouse replacing 1950 s era

More information

Section XXV Preconstruction Assessments and Damage Mitigation Procedures

Section XXV Preconstruction Assessments and Damage Mitigation Procedures Section XXV Preconstruction Assessments and Damage Mitigation Procedures A. Introduction - In recent years, HRSD has received an increasing number of complaints from residents and locality staff regarding

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May

More information

SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS

SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS MARCH 2017 SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS 1.0 General A. All work activities within the SCRRA operating corridor and right-of-way, or work activities that

More information

Construction Project Briefing. November 19, 2014

Construction Project Briefing. November 19, 2014 Construction Project Briefing November 19, 2014 Today s Presentation Traction Power Farwell/Armitage/Hill Substations Kimball/Princeton/State Substations O Hare Blue Line Station Improvements (Damen, Western,

More information

Addendum No. 1 Page 1 of 2

Addendum No. 1 Page 1 of 2 Addendum No. 1 Page 1 of 2 DATE: March 14, 2016 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Bidders SUBJECT: Addendum No. 1 PROJECT NAME: Parking Lot S7 Improvements JJC PROJECT

More information

UCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017

UCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017 UCSF Mission Bay & Dogpatch Construction Community Meeting Agenda Welcome Project Communications Construction Context Project Updates Minnesota Housing Center for Vision Neuroscience Precision Cancer Medicine

More information

SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY

SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS Professional Construction Management Services Harrisburg International Airport Rehabilitate Runway 13-31 Susquehanna Area Regional

More information

RECOMMENDATION: Staff recommends approval and provides the following motion for the commission s consideration:

RECOMMENDATION: Staff recommends approval and provides the following motion for the commission s consideration: PZ Case No. 17-09 Planning & Zoning Commission COMMUNITY DEVELOPMENT DEPARTMENT March 13, 2017 Subject: Consider making a recommendation on PZ Case No. 17-09; the site plans for Amega Garage Doors at 4901

More information

Evergreen Line Rapid Transit Project

Evergreen Line Rapid Transit Project Evergreen Line Rapid Transit Project Burnaby, Port Moody, and Coquitlam, BC Completed in December 2016 Canadian Consulting Engineering Awards 2017 Project Category: B. Transportation Canadian Consulting

More information

PORT OF LONG BEACH UNIQUE DESIGN STANDARDS

PORT OF LONG BEACH UNIQUE DESIGN STANDARDS PORT OF LONG BEACH UNIQUE DESIGN STANDARDS As with most organizations the Port of Long Beach has many standards or policies which are unique to our organization. Most of these are due to the peculiarities

More information

1. FROM (Bidder): (Name)

1. FROM (Bidder): (Name) Tender No. [ ] Tender Forms Page 1 1. FROM (Bidder): (Name) (Address) TO: Alberta Transportation, Strategic Procurement Branch Main Floor, Twin Atria Building 4999 Avenue 5000 Edmonton, Alberta, T6B 2X3

More information

ADDENDUM NO 1. TO: All Prospective Bidders DATE: 8/17/17 PROJECT: New Residence Hall (WP B)

ADDENDUM NO 1. TO: All Prospective Bidders DATE: 8/17/17 PROJECT: New Residence Hall (WP B) Office of the Capital Planning, Design & Construction Phone: 973-720-2352 Fax: 973-720-2829 WWW.WPUNJ.EDU ADDENDUM NO 1 TO: All Prospective Bidders DATE: 8/17/17 PROJECT: New Residence Hall (WP-16-01-99-B)

More information

INSPECTION AND ACCEPTANCE FOR MAINTENANCE

INSPECTION AND ACCEPTANCE FOR MAINTENANCE Inspection and Acceptance For Maintenance Page 1 (Last revised 6/29/10) INSPECTION AND ACCEPTANCE FOR MAINTENANCE SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Acceptance Sewer As Built Drwg Example

More information

Municipality of Waterville Public Sidewalk Repair Policy

Municipality of Waterville Public Sidewalk Repair Policy Municipality of Waterville Public Sidewalk Repair Policy Purpose - The purpose of this policy is to protect the public health, safety and welfare of the citizens and inhabitants of the Municipality by

More information

ANNE ARUNDEL COUNTY Department of Public Works DATE: 01/25/2017 FROM: Rich Osborn, P.E., Prof.L.S., Project Manager, Bureau of Engineering SUBJECT: Minutes for Pre-Bid Meeting January 19, 2017 South Shore

More information

City of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT

City of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT City of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT TO: Planning and Zoning Board FROM: Carlos M. Rivero, City Planner DATE: August 10, 2015 RE: Storage Facility P&Z ITEM # 15-010 OWNER

More information

Excavations and Blind Penetrations into Walls & Floors

Excavations and Blind Penetrations into Walls & Floors Excavations and Blind Penetrations into Walls & Floors (Instructions for using JLab DIGGING, EXCAVATING, FLOOR/WALL PENETRATION PERMIT REQUEST) Permits are required on JLAB property for any penetrations

More information

EQUAL EMPLOYMENT OPPORTUNITY AND AFFIRMATIVE ACTION POLICY UNDER EXECUTIVE ORDER 11246

EQUAL EMPLOYMENT OPPORTUNITY AND AFFIRMATIVE ACTION POLICY UNDER EXECUTIVE ORDER 11246 468 N. Rosemead Blvd. Pasadena, CA 91107 Fax 626.351.8880 Telephone 626.351.8800 EQUAL EMPLOYMENT OPPORTUNITY AND AFFIRMATIVE ACTION POLICY UNDER EXECUTIVE ORDER 11246 A. Statement of Policy. In order

More information

Progress Report Sounder Program

Progress Report Sounder Program Progress Report Sounder Program Continued construction work for the Tacoma Trestle at East 26th and East G Streets. March 2017 Prepared by Project Control l Design, Engineering & Construction Management

More information

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session Green Line Extension Environmental Impact Report Public Scoping Session Somerville High School October 16, 2006 Project Location Green Line Extension Project Purpose Implement enhancements to transit services

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

EXECUTIVE ORDER 11246

EXECUTIVE ORDER 11246 EXECUTIVE ORDER 11246 Standard Federal Equal Employment Opportunity Construction Contract Specifications (Executive Order 11246). Applicable to contracts/subcontracts exceeding $10,000.00) (1) As used

More information

INNOVATION STATION MIXED USE DEVELOPMENT A RECO DEVELOPMENT

INNOVATION STATION MIXED USE DEVELOPMENT A RECO DEVELOPMENT INNOVATION STATION MIXED USE DEVELOPMENT A RECO DEVELOPMENT ROCKS ENGINEERING COMPANY 1960 Gallows Road, Suite 300 Vienna, VA 22182 Voice (703) 556-4000 INNOVATION STATION MIXED USE DEVELOPMENT PROJECT

More information

Schedule Guidance Document

Schedule Guidance Document Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND RAIL-HWY PROJECT DEVELOPMENT GUIDE AND New procedures for Railroad Right-of-Entry Agreements & Bid Documents (SP Item 007) Bridge Division Webinar - July 18, 2013 GUIDE TO RAILROAD PROJECT DEVELOPMENT

More information

Science Technology Engineering and Mathematics (STEM) Initiative

Science Technology Engineering and Mathematics (STEM) Initiative DEPARTMENT of FACILITIES DESIGN December 17, 2013 and CONSTRUCTION REQUEST for PROPOSAL Science Technology Engineering and Mathematics (STEM) Initiative PRE-CONSTRUCTION SERVICES Facilities Design and

More information

Pattullo Bridge Replacement Project. Cost Report

Pattullo Bridge Replacement Project. Cost Report Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

Request for Proposals and Bids for Civil Engineering Services for Off-site Improvements for a Residential Neighborhood

Request for Proposals and Bids for Civil Engineering Services for Off-site Improvements for a Residential Neighborhood Request for Proposals and Bids for Civil Engineering Services for Off-site Improvements for a Residential Neighborhood The Quinault Indian Nation (QIN) is pleased to present a Request for Proposal and

More information

COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE DEPARTMENT OF PUBLIC WORKS

COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE DEPARTMENT OF PUBLIC WORKS CEE BS, Fulltime (3 positions) Posted 1/30/2017 COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE DEPARTMENT OF PUBLIC WORKS SUFFOLK COUNTY IS AN EQUAL OPPORTUNITY / AFFIRMATIVE ACTION EMPLOYER

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

Caltrans and Recycled Transportation Products

Caltrans and Recycled Transportation Products C&D Recycling Program Caltrans and Recycled Transportation Products INTRODUCTION The California Department of Transportation, or Caltrans, builds, maintains, and rehabilitates State roadways. Caltrans

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 14 DIVISION: Capital Programs and Construction BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Awarding San Francisco Municipal Transportation Agency

More information

Next PBDG Meeting: PBDG Holiday Gift Giving

Next PBDG Meeting: PBDG Holiday Gift Giving January 2018 UPDATE PROFESSIONAL BUSINESS DEVELOPMENT GROUP A Trade Association for Construction and Professional Services Prosperity Success Profitability Thriving We hope you all enjoyed your holidays

More information

GV 001 Equipment Bases and Enclosures General Information

GV 001 Equipment Bases and Enclosures General Information Eq u ip me n tba s e s a n d En c lo s u re s Ge n e ra lin fo rma tio n E n g in e e r :R.An th o n GV0 0 1 Ap p r o v e r :Jo s h u a Jo n e s Ap r 1 7 2 0 Ap r1 7 GV 001 Equipment Bases and Enclosures

More information