1 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016

2 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2

3 Agenda item 2: Interaction and Feedback Live Streaming Feb 4, 2016 Jan 21, 2016 Unique Viewers: Streams: Average Minutes per stream:

4 Agenda item 2: Interaction and Feedback (continued) For the period Feb 2, Feb 16, 2016 Inbox: 4 ( and phone) 2 to be added to weekly traffic alert and newsletter distribution list 1 to be removed from alerts and newsletter list 1 regarding the need to cover sign at Hillsdale and Branchlands Web Provide Input: 1 comment exchange Report regarding condition of right-turn lane at Albemarle Square Project Hotline : 1 call 1 regarding the need to cover sign at Hillsdale and Branchlands 4

5 Agenda item 3: Report on Panel Feedback November 2015 v accident data Nov 2014: 11 recorded crashes Nov 2015: 2 currently recorded crashes Updates to Nov 2015 will be monitored Dec 2015 v will be reported when data available Signal phasing Agenda item 10 Detour map Agenda item 11 5

6 Agenda item 4: Panel Feedback and Suggestions for Future Agenda Items Open Discussion 6

7 Agenda item 5: Construction Milestones Status as of Feb 15, 2016 Rio Road GSI Sep 2, 2016 Dec 2, 2016 Rt. 29 Widening Oct 31, December January February March April May June July August September October November December Utility Relocation (95%) 100% Final Pavement and Markings Drive Abutment Piles - 100% Landscape, Hardscape, Staining Set retaining wall piles and widen roadway - (45%) 50% May 23 start - Rio Restricted Period - Sep 2 intersection open Final Signing Temp. Signals 100% Jack & Bore and Line Large Diameter Culverts Gas line relocation - 0% ROW Acquisition - (80%) 100% Phase 3 Drainage and Paving Waterline Relocation Phase 1 Grading, Drainage and Paving - (35%) 35% Phase 2 Grading, Drainage and Paving Phase 4 Grading, Drainage and Paving Construction Complete ROW Acquisition - (60%) 70% Clearing North of River Roadway Construction North of River Berkmar Oct 31, 2017 S. Abutment Excavation, Pile Driving - (90%) 95% North Abutment Construction Rough Grading South of River - (40%) 50% Utility Relocation - (40%) 40% Pier Construction ROW Acquisition - (40%) 50% Roadway Construction South of River Steel Girder Erection Deck Pans and Rebar Hillsdale Oct 31, 2017 Rt. 29/250 May 21, 2016 Under way Complete 90% Plans - (90%) 100% Final Design 10% Adv for Bids MSE Wall - 100% Pavement Widening - (40%) 60% Final Paving - (0%) 0% Sound Barrier - (20%) 30% Utility Relocation Construction Complete Late ( % ) %complete prior reporting period 7

8 Agenda item 6: Rt. 29 Solutions Project Updates Rt. 250 / 29 Interchange Work this week Continue subgrade preparation along Route 250 WB Complete storm drain installation in median of Route 250 Continue storm drain installation along Barracks Road exit ramp Continue sound barrier post installation for Sound Wall along Route 250 WB Continue installation of MSE leveling cap and coping 8

9 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 250 / 29 Interchange (continued) Significant lane closures this week Inside and outside lanes of Route 250 EB and WB from Hydraulic to Barracks (lane closure dependent upon work activity) Ramp shoulder closures for storm drain installations 9

10 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 250 / 29 Interchange (continued) Work next two weeks Continue sound barrier foundation drilling and post installation for Sound Walls Complete storm drain installation along Barracks Road exit ramp Complete subgrade preparation along Route 250 WB 10

11 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 250 / 29 Interchange (continued) Anticipated significant upcoming lane closures Inside and outside lanes of Route 250 EB and WB from Hydraulic to Barracks (lane closure dependent upon work activity) Ramp shoulder closures for storm drain installations 11

12 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rio Grade-Separated Intersection Work this week Prep Albemarle Square island for demolition Sidewalk demolition in NE quadrant Underdrain, grading, curbing for widening Island demolition (29SB to Rio WB) Pile installation for retaining walls and concreting Storm drain installation in all quadrants (Work this week continued next slide) 12

13 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rio Grade-Separated Intersection (continued) Work this week (continued) Continue Fashion square retaining wall Install tie-back anchors Abutment A formwork Backfill Fashion Square retaining wall Refresh pavement markings in intersection Remove existing signal poles 13

14 Gas line burn off at Rio GSI 14

15 Rio retaining wall auguring 15

16 Rio storm drain installation 16

17 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rio Grade-Separated Intersection (continued) Significant lane closures this week Feb 17 - Mar 9: Rt. 29 SB right turn lane closed during daytime from south of Myers Drive to Rio Road. Business entrances and Rio right turn will remain open. Rio crossover closed at nighttime restricting thru movements and left turn movements. Right turns will be open. Rt. 29 triple lane closures northbound and southbound 17

18 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rio Grade-Separated Intersection (continued) Work next two weeks Albemarle Square island demolition Sidewalk and retaining wall demolition in NE quadrant Begin BMP 4, SW quadrant Underdrain, grading, curbing for widening Pile installation for retaining walls and concreting Storm drain installation in all quadrants Install tie-back anchors Abutment B formwork 18

19 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rio Grade-Separated Intersection (continued) Anticipated significant upcoming lane closures Feb 17 - Mar 9: Route 29 SB right turn lane closed during daytime from south of Myers Drive to Rio Road. Business entrances and Rio right turn will remain open. Rio crossover closed at nighttime restricting thru movements and left turn movements. Right turns will be open. Rt. 29 triple lane closures northbound and southbound 19

20 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 29 Widening Work this week Install temporary drainage structures Continue median grading Utility relocations (CenturyLink, Dominion, Fiberlight, Lumos) Grading for pond 3 location Pond 2 construction entrance and clearing 20

21 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 29 Widening Significant lane closures this week (nighttime) Route 29 left lane closure NB and SB 21

22 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 29 Widening (continued) Work next two weeks Install temporary drainage structures Continue median grading Utility relocations (Dominion, Lumos, Charlottesville Gas) Grading for pond 3 location Culvert jack and bore installations Pond 2 construction entrance and clearing 22

23 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Rt. 29 Widening (continued) Anticipated significant upcoming lane closures (nighttime) Route 29 left lane closure NB and SB 23

24 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Berkmar Extended Work this week Abutment A pile driving and concrete placement MSE formwork Clear abutment B Grading at abutment B Significant lane closures this week None 24

25 Berkmar pile driving 25 25

26 Berkmar pile driving 26

27 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Berkmar Extended (continued) Work next two weeks Abutment A pile driving and concrete placement Construct leveling pad for MSE wall at abutment A MSE formwork Clear abutment B Grading at abutment B Mobilize crane and drive piles at abutment B Significant upcoming lane closures None 27

28 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Signal Updates Work this week Design of signal improvements and contract (task order) development Schedule April 1 through May 1, 2016 Significant lane closures this week None Work next two weeks Design of signal improvements and contract (task order) development Significant upcoming lane closures None 28

29 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Hillsdale Extended Work this week Complete appraisal work Request DBE goal determination Continue making offers to property owners Finalize MOU with County for Stormwater Management Basin Finalize settlement and closing documents for USPS property Continue Final Road & Bridge Plans Continue preparation of special provisions Continue final plat preparation 29

30 Agenda item 6: Rt. 29 Solutions Project Updates (continued) Hillsdale Extended (continued) Work next two weeks Continue preparation of Final Road & Bridge Plans Obtain approval for sole source and proprietary items Final plat submittal to VDOT for review Continue preparation of special provisions Complete ROW offers 30

31 Agenda item 7: Budget Review and Update Route 29 Solutions Budget Update as of Feb 15, 2016 Construction Contracts Original Contract Value Expended (invoiced) as of February 15, 2016 Approved Change Orders Exposure (Anticipated COs) Remaining CV Total Anticipated Expenditures at Completion Rte. 29 Solutions Design-Build $116,746,000 $41,039,761 $130,883 $2,468,266 $75,837,122 $119,345,149 Rte. 29/250 Interchange Change $0 $31,734 ($31,734) ($31,734) $0 $11,121,078 $6,892,647 $109,216 $567,872 $4,337,646 $11,798,166 Change $663,603 $16,400 ($40,689) ($647,204) ($24,288) Adaptive Signals (Budget) $3,720,000 $2,226,433 $125,000 $50,000 $1,618,567 $3,895,000 Hillsdale Extended (Budget, Construction) Change $0 $0 $0 $0 $0 $11,198,000 Change $0 $0 $0 $0 $

32 Agenda item 8: Partial Daytime Closure Rt. 29 SB right-turn lane; south of Myers Drive to Rio Road Occurring Feb 17 through Mar 9 due to expected nighttime temperatures 15 work shifts accelerated by performing work in daytime temperatures At VDOT s reasonable discretion and approval, Lane-Corman may submit a request for additional lane closures (Section ) Requests limited to specific work tasks for specific durations Lane-Corman must demonstrate both a clear need and a public benefit VDOT and Lane-Corman jointly monitor traffic VDOT may withdraw approval Future requests, if any allowed, must be submitted at least 2 weeks before first day of requested additional closure 32

33 Agenda item 9: Woodburn Road Joint Construction Office Residents concerned about presence of trucks, speeding, stockpiled material, nighttime noise and condition of road Relocation of access road prohibited by steep grade (slide 34) One valid speeding matter addressed directly with driver of vehicle Certain equipment - but not all equipment - retrofitted with low noise emitting backup alarms Stockpiled aggregate moved away from Woodburn to eliminate aggregate hauling operations on Woodburn Road Street sweeper leased for daily cleaning, will be stored at Woodburn site Condition of road will be assessed post-construction and appropriate rehabilitation included in District workplan 33

34 34 34

35 Agenda item 10: Rio WB to Hillsdale Left Turn Signal Phasing during Nighttime Lane Closures VDOT observed Rio WB - Hillsdale movement Feb 16 pm, Feb 17 am, Feb 17midday During observations, Rio WB - Hillsdale movements functioned normally Rt. 29 signals being placed in flash mode nightly minutes after lane closures established; Rt. 29 in yellow, Rio in red VDOT will discuss May 23 - Sep 2 signal phasing with Lane-Corman for review at Mar 3 PDAP meeting 35

36 Agenda item 11: Detour Routes: May 23 - Sep 2, 2016 Detour routes, slide 37 Get-Around map developed by Business Assistance Subcommittee, slide 38 36

37 Detour routes, May 23 - Sep 2,

38 Get-around map developed by Business Assistance Subcommittee 38

39 Agenda item 12: New Business and Wrap Up 39

40 Agenda item 13: Adjourn 40

41 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 WELCOME IL 47 Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 MEETING PURPOSE MEETING AGENDA 1. Welcome/Introduction 2. Review Previous Public Involvement 3. Process/Schedule

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Route 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building

Route 7 Widening Project Project No , P101, R201, C501 UPC No January 15, a.m. NOVA District Building PROJECT SHOWING MINUTES Route 7 Widening Project January 15, 2013 10 a.m. NOVA District Building Overview / Welcome: Michael Gleasman, PE, Area Construction Engineer (VDOT) Overview: A question and answer

More information

Interstate 66 Widening from. RFQ Information Meeting. January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager

Interstate 66 Widening from. RFQ Information Meeting. January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager Interstate 66 Widening from Gainesville to Haymarket RFQ Information Meeting January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager John C. Daoulas, P.E. APD Project Manager and POC Introduction

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw

More information

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010 I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200 GRADING 219.101 Light Duty Straw

More information

Whittier Bridge/I-95 Improvement Project. Public Information Meeting

Whittier Bridge/I-95 Improvement Project. Public Information Meeting Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project

More information

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw

More information

I-35W Retaining Wall Design Exhibit A - Draft Scope of Work

I-35W Retaining Wall Design Exhibit A - Draft Scope of Work Background MnDOT, Metro Transit, Hennepin County, and the City of Minneapolis are in the process of developing a project for Interstate 35W between 43 rd Street in Minneapolis and 15 th Street in Minneapolis.

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.05 EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 The bid opening date is Thursday March 15, 2018 at 11:00 a.m. The following changes

More information

Status Report as of July 31, 2014

Status Report as of July 31, 2014 Dominion Boulevard Improvements AC # 01-6004-05 UPC: 56187 VDOT Project No: (FO) 6017-131-109, PE-101, RW-201, C-501, B608, B609, B610, B611, B614, B615, B616, D608, & C-502, B612, B613 FHWA No.: HPP-0017-5(023)

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure. Route 15/29 SBL Bridge Superstructure Replacement & Widening Existing Structure Scope Accelerated Procedure Staging (Superstructure) Preparatory Work (Substructure) NOVA District Questions EXISTING STRUCTURE

More information

STATE AID GUIDE FOR: Updated: December 16, 2005

STATE AID GUIDE FOR: Updated: December 16, 2005 STATE AID GUIDE FOR: Updated: December 16, 2005 1. AFTER THE FACT RIGHT OF WAY DEPARTMENT OF MINNESOTA TRANSPORTATION 2. MISCELLANEOUS AFTER THE FACT Traffic Signals, Lighting, Retaining Walls, Sidewalk,

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May

More information

Project Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce

Project Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce Project Team D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce D6 Design Project Manager Ali Toghiani, P.E. CEI: AIM Engineering and Surveying Francis Chin,

More information

Project Initiation Form

Project Initiation Form Meeting Date: The Project Initiation Form should be completed in conjunction with the Level 2 Screening Form. Process Leads and/or Planners should complete the Project Initiation Form to document coordination

More information

SUPPLEMENTAL ECMS ADVANCED INFORMATION JULY 14, 2016 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)

SUPPLEMENTAL ECMS ADVANCED INFORMATION JULY 14, 2016 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL) Updated June 27, 2016 BEAVER COUNTY SR 7446(LBB) #92912 PROPOSAL:$54.72 PLANS:$42.46 12X18:$52.11 24X36:$752.70 EXSTRUCT:$48.62 12X18:$59.67 24X36:$861.90 The description and location of the project is

More information

3.6 Construction Methods

3.6 Construction Methods Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required

More information

Pattullo Bridge Replacement Project. Cost Report

Pattullo Bridge Replacement Project. Cost Report Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada

More information

Rosslyn Circle Improvements, WB Lee Hwy. - US 29. April 6, :30 a.m North Fort Myer Drive, LL-10, Arlington, VA

Rosslyn Circle Improvements, WB Lee Hwy. - US 29. April 6, :30 a.m North Fort Myer Drive, LL-10, Arlington, VA REQUIRED PROJECT SHOWING MINUTES Project No. 0029-000-859, C501, B605 UPC No. 109813 PROJECT SHOWING MINUTES, WB Lee Hwy. - US 29 Project No. 0029-000-859, C501, B605 UPC No. 109813 April 6, 2017 10:30

More information

Categorical Exclusion (CE)

Categorical Exclusion (CE) Categorical Exclusion (CE) Project Information Project Name: Federal Project#: Project Number: 0029-002-135, D624, P101 Project Type: Construction UPC: 77383 Charge Number: Route Number: 29 Route Type:

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule

More information

Overall project. The $288 million Phase 2 DesignBuild project starts construction. this spring, with completion by December 31, 2016

Overall project. The $288 million Phase 2 DesignBuild project starts construction. this spring, with completion by December 31, 2016 Overall project Johnson County Gateway Interchange Project Improvements 87th Street The $288 million Phase 2 DesignBuild project starts construction this spring, with completion by December 31, 2016 Phase

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 9 September 13, 2017 Agenda Welcome and Presenter Introductions Update on Construction and Demolition

More information

Route 606 Loudoun County Parkway/ Old Ox Road Reconstruction and Widening

Route 606 Loudoun County Parkway/ Old Ox Road Reconstruction and Widening R e s p o n s e t o Request for Proposals Route 606 Loudoun County Parkway/ Old Ox Road Reconstruction and Widening ORIGINAL A Design-Build Projec t From: 0.265 Miles South of Route 621 Evergreen Mills

More information

FTBA 2018 Construction Conference Major Projects Update

FTBA 2018 Construction Conference Major Projects Update FTBA 2018 Construction Conference Major Projects Update Bill Jones, P.E. FDOT District 7 Director of Transportation Development 1 2 3 FUNDED PROJECTS Howard Frankland Bridge Industry Forum September 2018

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

MANUAL OF THE STRUCTURE AND BRIDGE DIVISION

MANUAL OF THE STRUCTURE AND BRIDGE DIVISION MANUAL OF THE STRUCTURE AND BRIDGE DIVISION DESIGN AIDS AND TYPICAL DETAILS VIRGINIA DEPARTMENT OF TRANSPORTATION VDOT GOVERNANCE DOCUMENT VDOT Manual of the Structure and Bridge Division: Part 02: Design

More information

Glenmore Causeway Upgrades Project. Calvin T. McClary, P. Eng., Manager, Transportation Engineering, ISL Engineering and Land Services Ltd.

Glenmore Causeway Upgrades Project. Calvin T. McClary, P. Eng., Manager, Transportation Engineering, ISL Engineering and Land Services Ltd. Glenmore Causeway Upgrades Project Calvin T. McClary, P. Eng., Manager, Transportation Engineering, ISL Engineering and Land Services Ltd. Paper prepared for presentation At the Bridges - Links to a Sustainable

More information

State Project No.: , N501 Contract ID Number: C DB66

State Project No.: , N501 Contract ID Number: C DB66 Request for Proposal Letter of Submittal Design-Build I-64 Pavement Rehabilitation From: Hampton Roads Bridge Tunnel (East Abutment) To: Little Creek Road Bridge (West Abutment) Norfolk, Virginia State

More information

Carpinteria Avenue Bridge Replacement Project Description Introduction

Carpinteria Avenue Bridge Replacement Project Description Introduction Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with

More information

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES 4.0 INTRODUCTION The ability to accommodate high volumes of intersecting traffic safely and efficiently through the arrangement of one or more interconnecting

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions) FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM NY Susquehanna and Western Rail Line Bicycle/Pedestrian Path DBNUM: NS9803 / UPC: 058018 The 4.8 mile New York, Susquehanna, and Western Railway (NYS&W)

More information

ADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012

ADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012 ADOT Yuma District Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012 Active Construction Projects SR 95@ Bill Williams River NWR Rd CAP Intersection US 95, Castle

More information

SCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS

SCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS SCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS Each Technical Proposal (Volume A of Package 2 of the Proposal) should address each of the items and requests for information described in this

More information

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information

Ontario Structure Inspection Manual Inspection Form Structure Number: 12

Ontario Structure Inspection Manual Inspection Form Structure Number: 12 Inventory Data: Structure Name Gailbraith Road Bridge 1 Main Hwy/Road # On Under Crossing Navig. Water Non-Navig. Water Rail Type: Road Ped. Other Hwy/Road Name Structure Location Latitude Owner(s) Galbraith

More information

TxDOT Houston District Permit Requirements (Information contained herein is subject to change)

TxDOT Houston District Permit Requirements (Information contained herein is subject to change) Houston District Permit Requirements (Information contained herein is subject to change) Access Driveway for Commercial / Industrial Developments; or Street Tie-In / Drainage-Only 1) Complete the three

More information

District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016

District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016 District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016 Ohio Transportation Engineering Conference 2016 Columbus, Ohio Agenda About

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions) FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM ADA Central, Contract 3 DBNUM: 15419 / UPC: 154190 This contract will bring projects into compliance with current ADA design requirements that could

More information

G2-0 List of Active Ministry of Transportation of Ontario Drawings (MTOD s)

G2-0 List of Active Ministry of Transportation of Ontario Drawings (MTOD s) G2-0 List of Active Ministry of Transportation of Ontario Drawings ( s) DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings 01/04/1994 04/01/1994 TOS/TO For use with Pavement Marking items.

More information

Section XXV Preconstruction Assessments and Damage Mitigation Procedures

Section XXV Preconstruction Assessments and Damage Mitigation Procedures Section XXV Preconstruction Assessments and Damage Mitigation Procedures A. Introduction - In recent years, HRSD has received an increasing number of complaints from residents and locality staff regarding

More information

I-94/I-69 Interchange Bridge Construction

I-94/I-69 Interchange Bridge Construction I-94/I-69 Interchange Bridge Construction General Project Information Let in August 2013 Cost of $76 million Prime Contractor Walter Toebe Construction Company Reconstruction of I-94 from Griswold to Lapeer

More information

Select Subgrade Material, Compacted

Select Subgrade Material, Compacted 314.1 GENERAL B314 SHOULDER, SELECTED SUBGRADE, AND STOCKPILING OPSS.PROV 314 Granular materials meeting the requirements of OPSS.PROV 1010 are obtained from pits and quarries, and recycled materials.

More information

The State of Ohio Bridges

The State of Ohio Bridges Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director ABCD NEOH Chapter The State of Ohio Bridges Tim Keller, P.E. Administrator ODOT Office of Structural Engineering Agenda 1.

More information

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway in association with Design 151.66 Km (Existing Road Apr. 180 km) 2 OBJECTIVE: The Government of Timor Lestewishes to Engage Consultant to carry out the Preliminary, Detailed Engineering Design and Environment

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE

PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE GENERAL Final restoration of areas within the public right-of-way associated with Street Excavation Permits shall be completed as determined

More information

APPENDIX A TIER 1 ANALYSIS

APPENDIX A TIER 1 ANALYSIS SPN H.004100 FEASIBILITY STUDY APPENDIX A TIER 1 ANALYSIS 040-012-042AH Appendices Lead Sheets PROVIDENCE STATE PROJECT. H.004100 The following worksheets analyze various project alternatives at various

More information

Re: PW Appendix 3 - Part 8

Re: PW Appendix 3 - Part 8 Demolish S/W DVP ramp, FGE WBL (including Logan Ramp), Don River bridge WB, and existing LSB WBL Construct new S/W DVP ramp, FGE WBL ramp, Don River bridge WB, and remaining portion of LSB WB roadwork.

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:

More information

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014 Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend

More information

For Public Input Period

For Public Input Period 20142018 CAPITAL IMPROVEMENT PLAN ( Thousands) CITY OF HOUSTON STREET & TRAFFIC CONTROL Project: Kingwood Drive N100011 Loop 494 to Woodland Hills Project Description Project provides for the ROW acquisition,

More information

on the eastbound side of Route 29). identified in the table.

on the eastbound side of Route 29). identified in the table. To: Jeannie Swim, Memo From: Ken Demmons, P.E. Project: Route 29 Bridge Replacement over Little Rocky Run Per plans received on January 23, 2012 CC: File Date: February 21, 2012 Job No: P2464 RE: Review

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

To Design and Construct The Project Neon Design-Build Project. Design-Build Contract. Volume II Technical Provisions

To Design and Construct The Project Neon Design-Build Project. Design-Build Contract. Volume II Technical Provisions REQUEST FOR PROPOSALS (RFP) RFP Number: 001-15-015 To Design and Construct The Project Neon Design-Build Project through a Volume II Technical Provisions 1263 South Stewart Street, Room 101 Carson City,

More information

I-81 Exit 114 Bridge Replacement Project RFQ Information Meeting

I-81 Exit 114 Bridge Replacement Project RFQ Information Meeting I-81 Exit 114 Bridge Replacement Project RFQ Information Meeting July 25, 2017 Phil Hammack, P.E. Design Project Manager Stephen Kindy, P.E. APD Division Project Manager and POC I-81 Bridge Replacement

More information

MAINE MEDICAL CENTER

MAINE MEDICAL CENTER MAINE MEDICAL CENTER Construction Projects at the East Tower, Visitor Garage, Central Utility Plant Construction Management Plan December 15, 2017 Prepared for: Portland Department of Planning & Urban

More information

Accelerated Bridge Construction (ABC) National Status

Accelerated Bridge Construction (ABC) National Status Accelerated Bridge Construction (ABC) National Status by Mary Lou Ralls, P.E., Ralls Newman, LLC 88 th Annual Transportation Short Course Texas A&M University College Station, Texas Session: Construction

More information

APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual)

APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual) APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual) PROJECT DESCRIPTION: (Enter Type of Project Planning Cost Estimate as Title)

More information

PRESENTATION FOR: Construction Engineering and Inspection-Wiles Road from Riverside Drive to Rock Island Road. RFP No. J P1

PRESENTATION FOR: Construction Engineering and Inspection-Wiles Road from Riverside Drive to Rock Island Road. RFP No. J P1 PRESENTATION FOR: Construction Engineering and Inspection-Wiles Road STAFFING MATRIX Construction Engineering and Inspection-Wiles Road JAMES JEFFERS, P.E. Senior Project Engineer Years of Experience:

More information

ALTERNATIVE PROJECT DELIVERY DIVISION

ALTERNATIVE PROJECT DELIVERY DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION ALTERNATIVE PROJECT DELIVERY DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design-Build Requirements for Advertisement SPECIFIC SUBJECT: APPROVED:

More information

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Americans with Disabilities Act Requirements of Maintenance and Operational

More information

ENGINEERING DESIGN & IMPROVEMENT STANDARDS

ENGINEERING DESIGN & IMPROVEMENT STANDARDS ENGINEERING DESIGN & IMPROVEMENT STANDARDS 2016 Prepared by: Engineering Division For latest edition of these Improvement Standards, refer to City of Visalia website at: www.visalia.city/engineeringdocuments

More information

Attachment D-1: Civil/Structural Scope of Work

Attachment D-1: Civil/Structural Scope of Work Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,

More information

Maine Turnpike Authority FINAL 4-year Capital Investment Plan ( )

Maine Turnpike Authority FINAL 4-year Capital Investment Plan ( ) Total preliminary Value for Project shown in initial year is for project duration. Projects have been listed in each year there are major Preliminary 4.8 Beech Ridge Road Underpass Repairs York $410,000

More information

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Washington State s Skagit River Bridge Emergency Slide Bijan Khaleghi

More information

JANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25

JANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25 General Info Number: PROJECT NO. 43-17-03 Description: BRIDGE DECK REPAIR AND REHABILITATION, ARLINGTON ROAD OVER OHIO TURNPIKE M.P. 122.3, JOPPA ROAD OVER OHIO TURNPIKE M.P. 128.5, DEAN ROAD OVER OHIO

More information

City of Denton On-system Project Status Report Prepared by ITS

City of Denton On-system Project Status Report Prepared by ITS City of Denton On-system Project Status Report Prepared by ITS December 2017 PROJECTS FM 2181 North-South... page 2 US 377/Fort Worth Drive... page 3 FM 2499, Section 5... page 5 IH-35E/Mayhill/FM 2499

More information

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan West Rail Tsing Kwai Tunnel Location of major Tunnel Portal West Rail Tsing Kwai Tunnel Construction Features -

More information

2001 Insertable Sheet List For Use With The 2001 Imperial Road and Bridge Standards February 2008

2001 Insertable Sheet List For Use With The 2001 Imperial Road and Bridge Standards February 2008 2001 Insertable Sheet List For Use With The 2001 Imperial Road and Bridge Standards February 2008 The following is a complete list of special design IMPERIAL insertable sheets that will be used with the

More information

Construction Forecast

Construction Forecast Construction Forecast October 7, 2015 Agenda Opening Remarks Introductions Capital Program Anticipated Bid Schedule Project Descriptions Procurement Process MBE/DBE Break-out Discussions Housekeeping items

More information

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature

More information

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 1 Agenda Sections 1 & 2 Section 1 Construction Updates TBM Art and Naming Contest Project Construction Updates: Wilshire/Western

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

Reason for Acceptance or Rejection

Reason for Acceptance or Rejection Value Engineering Approval Form Project: 25th Avenue & Union Pacific Grade Separation #6 VE Study Date: January 28 through February 1, 2013 Form updated: 5/7/2013 (Final) FHWA Functional ENV 1 ROW 1 The

More information

ENCROACHMENT/EXCAVATION PERMIT APPLICATION

ENCROACHMENT/EXCAVATION PERMIT APPLICATION PERMIT / PROJECT INFORMATION: PARCEL INFO: APPLICANT S INFO: Public Works/Engineering 595 SILVER LACE BLVD, FERNLEY, NV 89408 (775)-784-9910 ENCROACHMENT/EXCAVATION PERMIT APPLICATION PERMIT APPLICATIONS,

More information

Annual CSAH Needs Update for 2017

Annual CSAH Needs Update for 2017 Annual CSAH Needs Update for 2017 MnDOT - State Aid for Local Transportation CSAH Needs Unit These instructions provide guidance for updating CSAH Needs segments and project data using the SANeeds system.

More information

2016 TEAM Conference. Waverly Road Progressive Design Build Project Owner: City of Edgerton, KS. March 10, HDR, all rights reserved.

2016 TEAM Conference. Waverly Road Progressive Design Build Project Owner: City of Edgerton, KS. March 10, HDR, all rights reserved. 2016 TEAM Conference Waverly Road Progressive Design Build Project Owner: City of Edgerton, KS March 10, 2016 2015 HDR, all rights reserved. Project Location Project Location BNSF Transcon Tracks Gardner,

More information

SPECIFICATIONS SCOPE OF WORK

SPECIFICATIONS SCOPE OF WORK SPECIFICATIONS SCOPE OF WORK The intent of this contract is for the supply of all necessary labour, materials, and equipment to install underground traffic signal plant, vehicles detection loops, installation

More information

Quarterly Progress Report

Quarterly Progress Report 183A TURNPIKE - PHASE II Quarterly Progress Report No. 8 April 2012 INDEPENDENT ENGINEERING REPORT Board of Directors Ray A. Wilkerson, Chairman James H. Mills, Vice-Chairman Robert L. Bennett, Jr., Treasurer

More information

Project Type: Drainage and Storm Systems

Project Type: Drainage and Storm Systems 580 Dakin Avenue Box Culvert & Utility Improvements Project $944,952 Improvements to approx. 3,000 lf of existing 4'x5' concrete box culvert; clean interior, patch surface, fill joints/cracks; install

More information

2017 Highway Safety Improvement Program Call

2017 Highway Safety Improvement Program Call 2017 Highway Safety Improvement Program Call The Highway Safety Improvement Program (HSIP) is for highway safety projects that eliminate or reduce the number of fatalities and serious injuries on all public

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design Exceptions / Waivers SPECIFIC SUBJECT: Design Exception Request Form

More information

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:

More information

South Dakota Department of Transportation Average Unit Prices from Low Bids

South Dakota Department of Transportation Average Unit Prices from Low Bids Unit Prices from Low s January 0, 0 to December, 0 Office of Project Development - Letting 00E00 Blading Hour.00 $,0. $. 00E000 Construction and Maintenance of Detour(s) LS.00 $0,. $,. 00E000 Maintenance

More information

I-10 CONNECT. Public Meeting #1

I-10 CONNECT. Public Meeting #1 I-10 CONNECT Public Meeting #1 The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner