Regulatory Submittal Part I(R) DOL Comments to Remediation Work Plan Dated: January 17, 2007

Size: px
Start display at page:

Download "Regulatory Submittal Part I(R) DOL Comments to Remediation Work Plan Dated: January 17, 2007"

Transcription

1 Regulatory Submittal Part I(R) DOL Comments to Remediation Work Plan Dated: January 17, 2007 The Department has discussed aspects of the documents with the New York City Department of Environmental Protection (DEP), and DEP concurs with the Department's comments on the submitted documents. Several significant items within the work plan must still be revised to address Departmental concerns. Comments have been numbered to provide cross-reference with the revised work plan document. General Comments GC1 Throughout the work plan submittal, requirements are included for NYS DOL and NYC DEP licensed asbestos handlers". As previously indicated and as per ICR 56, asbestos contractors must be licensed and each individual handler must be appropriately trained and certified. The work plan requirements must be changed globally throughout the work plan document to indicate "asbestos contractor licensing and handler certification shall be consistent with NYS DOL ICR 56 requirements, as well as NYC DEP requirements". This language has been corrected throughout Part I(R) Remediation Operations Work Plan to refer to NYC DEP and NYS DOL certified asbestos handlers. In addition, the following language has been added to Section 6.0: For all asbestos abatement activities on this project, asbestos contractor licensing and handler certification shall be consistent with NYS DOL ICR 56 requirements, as well as NYC DEP requirements. Please note that NYC DEP does not license asbestos contractors. GC2 The concept that floors two through fifteen will comprise one work area, but three floor blocks will be split-up within the work area is problematic at best It is unclear if each three floor block is segregated from the other three floor blocks within the same work area, and do they share the same air source? If all the three floor blocks within the same work area share the same air source and there is no segregation or isolation of these separate portions of the same work area, then abatement, cleaning and clearance must occur throughout all portions of the work area at the same time. For example, the postabatement cleaning in floors 15, 14, and 13 is complete, but ACM is still being removed in the floors below floor 13. As floors 13, 14, & 15 apparently draw make-up air from the remainder of the work area, floors 13, 14, & 15 will likely be re-contaminated by the abatement operations occurring in the remainder of the same work area. All abatement and cleaning operations within each abatement work area must be entirely completed before the project monitor visual inspection commences. The satisfactory visual inspection

2 would then be followed by clearance air sampling of the entire work area. The definition of the work area has been clarified in the Work Plan. The following explanation has been added to Section 6.0: This project has been designed in response to the existing condition of Fiterman Hall. The overall concept of the remediation operations is for the entire interior of the Building to be placed under one comprehensive negative pressure containment for the removal of non-fixed items, building components and asbestos containing materials. In order to accomplish these removals a Clean Zone will be established on the First Floor to provide an area free of contamination for logistical operations in support of remediation activities. Cleaning activities shall follow directly after removals. In order accomplish the postremovals cleaning, the one containment will then be divided into separate, three floor blocks. Each three floor block will be segregated from the neighboring three floor blocks via the installation of critical barriers on all vertical means of air transfer. Cleaning activities will not begin on any floors until all remediation and abatement activities have been fully completed on all levels (interior & exterior) throughout the entire building. Barriers dividing the three floor blocks will remain in place until all adjacent three floor blocks have been cleaned and cleared. Please refer to the below Section 6.21 for the clearance criteria for this project. GC3 The concept that stairwell A & B will be cleaned and cleared simultaneously with the various 3 floor blocks of the upper floors is also problematic. As previously indicated, these portions of the same work area share the same air source and as there is no segregation or isolation of these separate portions of the same work area, cleaning and clearance must occur throughout the entire work area at the same time. See the above response and revision to Section 6.0. Segregation in the form of critical barriers will be installed after removals and prior to commencement of cleaning to prevent air transer between three floor blocks via the A & B stairwells. GC4 The concept that stairwell C will be cleaned and cleared simultaneously with the first floor clean zone is also problematic, as no correlation is included regarding cleaning and clearance of these two portions of the same work area at exactly the same time. As these two portions of the same work area share the same air source and there is no segregation or isolation of these separate portions of the same work area, cleaning and clearance must occur throughout both portions of the work area at the same time. For example, stairwell C is cleaned and cleared but ACM is still being removed in the first floor work area. As Stairwell C apparently draws make-up air from the remainder of the first floor work area, stairwell C will likely be re-contaminated by the abatement operations occurring in the remainder of the same work area. The operations within each abatement work area must be entirely completed before the project monitor visual inspection commences. The satisfactory visual inspection would then be followed by clearance air sampling of the entire work area. Further review of remediation operations has determined that it will be necessary to perform the cleaning and clearance of Stairwell C before commencing the removals,

3 cleaning and clearance in the First Floor Clean Zone in order to accommodate the installation of electrical requirements in Stairwell C. In order to maintain continuity, it will be necessary to change the numbering of the Sub- Sections of Section 6.1 to move the Cleaning of Stairwell C to the beginning. The Cleaning and Clearance of Stairwell C will now be Section All other Sub-Sections of Section 6.1 will follow sequentially behind Section in the order they were written in the original Part I(R) Remediation Operations Work Plan with the exception of new sections added in response to regulator comments. For example a comment regarding sub-section will be responded to in sub-section In this example, and are the same sub-section only now they are numbered differently in response to the revised sequencing. Below is the revised Sub-Section regarding the cleaning and clearance of Stairwell C: Section Cleaning and Clearance of Stairwell C The construction of Stairwell C is of the following materials: Painted Masonry Block Walls Concrete Floor Landings Concrete Deck Steel Stairs Steel Handrails Stand Pipe Light Fixtures Light Bulbs Electrical Conduit Prior to the cleaning and clearance of the First Floor Clean Zone, PAL will commence the cleaning and clearance of Stairwell C. It is necessary to clear the Stairwell C at the beginning of the remediation operations in order to install electric panels for the remediation work on the upper floors of the Building. All electrical power to the Stairwell C will be shutdown prior to the commencement of Cleaning and Clearance activities. A worker and waste decontamination facility will be constructed exterior to the Building on the ground level on the South Side in the Gash Area. NYS DOL and NYC DEP certified asbestos handlers will construct an access tunnel from the decontamination facility into the Building via the Gash Area. The tunnel shall be constructed of hard wood. Prior to constructing the tunnel, the wood panels will be encapsulated in order to render the surfaces cleanable. The tunnel will meet the Stairwell C at the south side of the First Floor landing. The existing painted sheetrock wall into the Stairwell C will be demolished by NYS DOL and NYC DEP certified asbestos handlers in order to create and opening from the south side. The access tunnel will be fully connected to this opening so that there is no air transfer into the tunnel from the First Floor. In order to connect the tunnel to the opening into Stairwell C it will also be necessary to demolish a masonry block wall that is in the path of the tunnel. Prior to commencing the demolition of the painted sheetrock and masonry block walls, the surfaces will be wetted down with amended water to control dust. Please note that it is not possible to fully saturate

4 painted sheetrock or masonry block as these materials do not absorb water. The painted sheetrock and masonry block walls will not be fully saturated with water during demolition. Water will be used to as a means of dust control at all times during the removal the painted sheetrock and masonry block walls to connect the access tunnel to Stairwell C. The painted sheetrock and masonry block walls will be demolished using a combination of manual and mechanical means Debris generated from the painted sheetrock and masonry block walls will be handled and disposed of as asbestos waste. All openings and penetrations into Stairwell C, including the doorway onto each floor will be sealed with two (2) layers of poly. Four (4) air changes with negative pressure differential of point zero two inch (0.02 ) water column will be established within the Stairwell C and the attached access tunnel. Make up air will be drawn from the decontamination unit. Negative air units will be installed in the stairwell on the Fifteenth Floor and vented onto the main roof level via the existing doorway. All light bulbs and fixtures will be detached. Light bulbs and fixtures will be handled and disposed of as universal waste. All interior surfaces of the stairwell and the attached access tunnel will be HEPA vacuumed and wet wiped to remove any residual dust and debris. All used cleaning materials generated during the remediation in the C Stairwell and access tunnel will be double bagged, properly labeled, processed through the waste decontamination facility and disposed of as asbestos waste. Please note that there are no asbestos containing materials present within Stairwell C. Wall, ceiling and floor surfaces will remain in place within the Stairwell C once remediation activities have been completed. After cleaning activities are completed one twelve hour settling/drying period will then be observed in order to allow all surfaces to dry. At the end of this settling period, the Owner s Environmental Consultant and PAL superintendent will perform a visual inspection of the C Stairwell work area. After the area has passed visual inspection by the Owner s Environmental Consultant, the regulators will be contacted to perform a regulatory visual inspection. Twenty-four (24) hour notice will be provided prior to the regulatory visual inspection. After the Stairwell C work area has passed regulatory visual inspection, aggressive clearance air sampling will be performed by the Owner s Environmental Consultant. Sampling will be performed as follows: 5 TEM air samples (1 sample for every 3 floors) and 5 Metals air samples (1 sample for every 3 floors) will be run for the entire stairwell. Sample locations will be evenly distributed vertically through the stairwell. Clearance testing for all work areas will be consistent with the work area Clearance Criteria noted in section Once successful clearance is achieved the modified full containment in the C Stairwell will remain in place in order to prevent recontamination from yet-to-be-cleaned areas. After decontaminated floors have been cleared the entrances into Stairwell C will be unsealed to provide clean access to clean areas. After the Stairwell C has been cleared GFCI equipped electrical panels will be installed on each floor level within the stairwell by licensed electricians. Power will be run from the electrical closets that abut the south side of the Stairwell C wall on Floors 2 through 15. Specific Comments REGULATORY SUBMITTAL PART I - WORK PLAN 3.1 ASBESTOS SURVEY SC1) This section refers the reader to the Environmental Characterization Report for results of the survey. A summary of the survey results listing the ACMs found and their

5 locations shall also be included within this section. A summary survey of results has been included with Part I(R) Remediation Operations Work Plan as Attachment VIII. 3.2 NYS DOL NOTIFICATION & 3.3 NYS DOL VARIANCE APPLICATIONS SC2) These sections indicate that a variance petition is included within Work Plan Attachment 11 for abatement work that is not in compliance with Industrial Code Rule 56 (ICR 56). However the variance petition is not apparent within the work plan. As previously indicated, if procedures must be specified that aren't consistent with (ICR 56) requirements, a site-specific variance decision must be obtained by the project designer as an agent for the owner, and the procedures and conditions contained within the sitespecific variance decision must then be incorporated into the work plan specified asbestos project procedures, prior to obtaining the necessary regulatory agency work plan approvals. o The site-specific variance petition, has yet to be submitted to the Department for an official decision. The variance petition must be submitted using the standard DOSH-751 form along with appropriate processing fee, prior to the Department issuing an official decision on the petition. Conditions/requirements may be added by the Department within the variance decision for adequate health and safety protection of all parties on the project, as well as thegeneral public. The variance petition must be submitted as soon as possible, to alleviate any potential project scheduling issues. As with Part I(S) SEO Work Plan, it was first necessary to elicit information as to whether the Remediation Operation Work Plan was generally acceptable to DOL prior to making the formal variance application. The formal variance application will be submitted, on the required form, with the required fee once the DOL comments and concerns have been addressed. 4.1 ELECTRIC SC3) This section indicates that GFCI equipped electric panels will be installed on each floor and attached directly to the electrical closet on that level. However, nothing is included regarding adequate protection of the live electric within the electrical closet that is not GFCI protected. At what point during work area preparation will the GFCI panels be installed? Also, how and when will the live electric within the electrical closet be protected and segregated from the work area on that specic floor. The following statement has been added to Section 4.1: Electric panels will be installed at each level required in Stairwell C after cleaning and clearance is completed in the stairwell. The panels will be attached to the electrical closets through the adjoining wall in Stairwell C. The entrances of the electrical closets shall be sealed off prior to the commencement of the remediation operation segregating the live electric from the work areas.

6 4.2 PLUMBING SC4) This section includes information for the water supply to be utilized during the asbestos project but nothing is included regarding drainage systems to be utilized for the asbestos project, filtering systems for the wastewater, discharge points or necessary discharge permits. All pertinent information regarding wastewater collection, temporary storage and disposal must be provided The following statement has been added to Section 4.2: At the beginning of work on the Remediation Operations, a characterization of waste water will be performed to determine proper disposal methodology. Waste water will be filtered to five (5) microns and containerized in a drum for testing. Should the characterziation determine that there are no contaminants present in the waste water it will be discharged into the existing sanitary sewage system in the Building. The procedure for the disposal of water for the entire Remediation Operations will then be to filter down to five (5) microns and discharge to the existing sanitary sewage system. Should characterization detect the presence of contaminants, the waste water generated during the Remediation Operations will be containerized and disposed as required by the characterization analysis. 4.5 ELEVATOR SERVICE SC5) This section does not include any information regarding venting of the elevator shafts or negative pressure engineering controls to filter and control the vented air. A summary of the proposed engineering controls for operation of the elevators must be included within this section. Specific details, procedures and requirements may be addressed within a more detailed section of the work plan. Please note that all asbestos project work plan procedures regarding elevator operation shall correspond with all conditions and procedures within existing site-specific variance decisions, decision amendments and decision reopenings for the project The following statement from Section 6.5 has been cut and moved to Section 4.5 In the Elevator Machine Rooms throughout the Building there are vents that handle air pushed up shafts during car operation. These vents cannot be sealed since the usage of the elevators is required to perform the remediation operations. Negative air filtration units are currently operating in these Elevator Machine Rooms maintaining negative pressure in order to prevent contaminated air from migrating out of the elevator shafts. Negative pressure will be maintained in the Elevator Machine Rooms during remediation operations. 5.4 VISUAL INSPECTION SC6) This section appears to include general information regarding completion of a work area visual inspection for completeness of abatement and cleanings. However, nothing is included regarding the actual personnel that are required to complete the inspection, and no reference is included to specific requirements for visual inspections as required by

7 ICR 56. The following statement has been added to Section 5.4: Visual inspection will be performed by the contractor supervisor and the Owner s Environmental Consultant. Visual inspection will be performed in accordance with ICR 56. SC7) Specific criteria must be defined and appropriate parties identified with responsibility for conducting visual inspections (e.g. ASTM E1368 requirements completed by owner's project monitor after satisfactory visual inspection by abatement contractor supervisor, etc.). Appropriate sections of ICR 56 must be referenced as necessary. In addition, provisions must also be included within the work plan to allow for regulatory agency visual inspections prior to commencement of clearance air sampling. The following language has been added to Section 5.4: After removals and cleanings are complete in a work area, the Owner s Environmental Consultant and Contractor representative will perform a visual inspection of the area. The Owner s Environmental Consultant representative performing a visual inspection shall be an NYS DOL and NYC DEP certified project monitor. OEC visual inspection will be conducted as per the provisions of ASTM Standard 1368 Standard Practice for Visual Inspection of Asbestos Abatement Projects in accordance with ICR 56 Section 56.9(d)(1). Once a work area has passed the OEC visual inspection, an OEC representative will contact the regulators to schedule a regulatory visual inspection of the work area. Twenty-four hour notice shall be provided to the regulators prior to the date of inspection. After the area has passed regulatory visual inspection, aggressive clearance air sampling will be performed by the Owner s Environmental Consultant. Please refer to the below Section 6.21 for clearance criteria. 6.0 REMEDIATION OPERATIONS SC8) This section indicates that the Office of the City Medical Examiner will perform a complete inspection of the building & site prior to commencement of remediation operations. Please provide a summary of inspection procedures and also indicate if any potential disturbance to ACM or WTC dust1residue will occur during these search operations. If a disturbance may potentially occur, indicate what engineering controls will be in place during the search to prevent any potential airborne release of asbestos fibers outside the building envelope. Following the submission of Part I(R) Remediation Operations Work Plan to the Regulators, the Office of the City Medical Examiner (OCME) performed an inspection of the Building and determined that search operations would not be required within the interior of the Building. This inspection was visual and did not distrub any ACM or dust

8 residue. The Office of the Chief Medical Examiner (OCME) completed a walk-through at Fiterman Hall on December 12, 2006 and issued a report dated December 20, Their inspection determined that only the exterior roof areas need to be searched for human remains. The interiors were free from any debris. Accordingly, after remediation work begins at the site, representatives of OCME will conduct this search. The following procedure has been added to Section 6.13: OCME has indicated that it will be necessary to perform search operations on the various roof levels of the Building. OCME will be supported by NYS DOL and NYC DEP certified asbestos handlers during their operations. The surface of the roof levels at the Building have been previously cleaned by others during WTC recovery operations. The contractor shall re-clean the ballast and surface of the membrane in conjunction with the Office of the City Medical Examiner investigation as outlined below. After cleaning and OCME inspection, the ballast material will be loaded into bags. Full bags of ballast will be left in place on the roof levels in order to provide weight to hold the membrane in place. Bags of ballast will be removed during the deconstruction operations and disposed of as conventional waste. The following procedure will be used during OCME inspection of roof levels: A screen filtration system consisting of a heavy duty rectangular screen laid flat over four cinder blocks leaving space of approximately one foot to the surface of the roof will be established. A decontamination unit will be installed on each roof level where OCME inspection will take place. NYS DOL and NYC DEP certified asbestos handlers will move sections of stone ballasts and accompanying fines onto the filtration screen. OCME personnel will inspect ballast and fines on the screen as well as the surface of roof membrane for the presence of human remains. Once directed by OCME personnel, NYS DOL and NYC DEP certified asbestos handlers will clean the ballast and fines on the screen with water. The surface of roof membrane where ballast and fines were removed from will also be cleaned by HEPA vacuuming and wet wiping. Run off water will be collected in basins set up below the screen. Collected water will be absorbed on a regular basis utilizing mops and rags or otherwise containerized in drums. Drummed water will be tested for NYC Sewer discharge parameters and eventual filtration to the NYC Sewer if analytical results allow. All used water collection materials will be double bagged, properly labeled, processed through the decontamination facility and removed from each roof level via the exterior pipe scaffolding system for disposal as asbestos waste or in accordance with any waste characterization results. Once cleaned ballast and fines will be moved from the screen and placed into bags and put back onto the roof surface.

9 After the cleaning of stone ballast and roof surfaces in conjuction with OCME, the Owner s Environmental Consultant will perform a visual inspection of the roof levels to verify the cleaning has been fully completed. This procedure will be repeated until OCME has completed their inspections on the roof levels. 6.1 ESTABLISHMENT OF CLEAN ZONE SC9) This section indicates that the personal decontamination facility utilized for remediation of the clean zone will be the existing decontamination facility at the northwest entrance of the building. However, the Decontamination of the Clean Zone and Upper Access Level Access Plan Drawing provided in Attachment V of the work plan does not accurately reflect this information. The provided plan drawing indicates no access to the building interior from the existing northwest entrance decontamination facility, and also indicates that a personal decontamination facility will be constructed at the West Broadway side of the building for access to the intended clean zone for decontamination. This plan drawing and the pertinent work plan text must be revised to appropriately reflect the intended location of the personal decontamination facility for this work. The logistics plan (Remediation Part I(R) Work Plan - Attachment V) entitled Decontamination of the Clean Zone and Upper Level Access shows a decontamination facility in the northwest corner of the First Floor. This decontamination unit will be used for the decontamination and abatement work in the First Clean Zone. SC 10) This section indicates that "asbestos handlers will clean the interior surfaces of all windows in the first floor clean zone work area by HEPA vacuuming and wet-wiping. Following cleaning, all windows, openings and building penetrations will be sealed with two layers of six-mil poly..." However, it is unclear how operable window hidden surfaces that may still contain WTC dust will be cleaned prior to sealing of the windows as critical barriers. The procedures must be revised accordingly. Cleaning of operable window mechanisms has been submitted as Amendment 7 to Part I(S) SEO Work Plan. The procedure will be performed as follows: Asbestos air sampling will be conducted by the Owner s Environmental Consultant outside the building on the scaffold on the perimeter of the active window cleaning work areas established by the Contractor. The number and location of samples will be determined by the Site Hygienist based on the number, location and configuration of the work area(s). The cleaning of windows and operable mechanisms will be performed by NYS DOL and NYC DEP certified asbestos handlers utilizing proper PPE. PPE for the cleaning of operable window mechanisms shall be: disposable coverall suits with hoods, half-face APR equipped with P100 filter cartridges,

10 nitrile gloves, safety goggles, work boots, rubber boot covers, hard hats and hearing protection (only if noise levels exceed OSHA decibel limits). The existing decontamination unit at the northwest entrance to the 1st Floor will be used for interior window related decontamination activities. The existing remote decontamination unit on the Greenwich Street side of the Building will be used for exterior window related decontamination activities. The affected windows are awning type windows that have an operable middle section which opens outward. The cleaning of operable window mechanisms shall occur on no more than three (3) floors at the same time. This operation is being limited in number to a manageable amount so that windows that are not scheduled for cleaning are not left unlatched or unsecured. The cleaning of windows and operable mechanisms will coincide with the installation of scaffolding on the exterior of the Building in order to provide a working platform from which to access the operable mechanisms. A separation of twenty-five feet (25 ) between asbestos and non-asbestos trades will be observed during the cleaning of the operable window mechanisms. Workers will enter the building to clean the interior surface of the operable section of each window will be cleaned via HEPA vacuuming and wet wiping prior to the installation of critical barriers. The installation of critical barriers will proceed from the affected floor upwards. Cleaning materials will be disposed of as asbestos wastes at a minimum or in accordance with any waste characterization testing deemed necessary by the Owner s Environmental Consultant. After interior cleaning is completed, windows will be left closed but unlatched to allow for the cleaning of the operable mechanism from the Building exterior. Critical barriers will be installed over the operable section of each window in order to prevent air transfer between the interior of the Building and the outside environment during cleaning activities. The inoperable fixed sections of the windows will not be sealed because there is no air transfer with the outside environment through these sections. The installation of critical barriers over all operable sections of windows on a given floor will be completed prior to the commencement of operable window mechanism cleaning activities on that floor. The installation of critical barriers will proceed from the lowest affected floor upwards. Once the critical barriers have been installed on a floor, NYS DOL and NYC DEP certified asbestos handlers will proceed to that level on the exterior scaffold platform. Workers, equipped with abatement work area PPE, will open the unlatched operable section of window and clean the interior surface and operable mechanism of each window by HEPA vacuuming and wet wiping. Cleaning will be performed from the lowest affected floor upwards utilizing the exterior scaffolding as a working platform. All cleaning materials generated during the cleaning of windows and operable mechanisms will be containerized, decontaminated and stored in the existing SEO waste storage facility for disposal as asbestos waste at a minimum, or in accordance with any waste characterization testing deemed necessary by the Owner s Environmental Consultant.

11 After the completion of window mechanism cleaning activities, the Owner s Environmental Consultant will perform visual inspections of the cleaned surfaces. After the windows have passed visual inspection they will be secured in place by self tapping screws installed into the frames by NYS DOL and NYC DEP certified asbestos handlers. SC 11) This section indicates that "airlocks will be installed at the entrances to all stairwells with the exception of stairwell C". Please explain the purpose and function of these airlocks, as these stairwells will not be included as part of the initial clean zone work area, and make up air to the intended "clean zone" will be entering the work area through these airlocks to contaminated stairwells. This section has been revised to state the following: All stairwells, with the exception of the cleaned and cleared Stairwell C, will be sealed off from the Clean Zone with critical barriers. Stairwell C will provide a clean area to install electrical panels and provide clean access to the upper floors. SC 12) This section indicates that 4 air changes per hour will be maintained in the clean zone and stairwell C work area, but "it will not be possible to maintain negative pressure of point zero two inch water column". If -0.02" of water column pressure differential, as evidenced by manometer, is not maintained within the work area, then adequate negative air ventilation has not been provided for the work area. Section 6.1 has been revised to state the following: Negative pressure ventilation equipment (micro traps) will be installed to establish negative pressure within the First Floor work area and the C Stairwell. Air volume shall be changed four times per hour in the First Floor Clean Zone work area and negative air pressure differential of point zero two inch (0.02 ) water column maintained. Evidence of negative air pressure shall be demonstrated by a manometer in the First Floor Clean Zone work area. SC13) Also calculations are provided for determining the minimum number of negative air units required. The calculations provided within this section do not appear to include a safety factor for reduced CFM capacity for each unit. An appropriate safety factor should always be utilized when calculating minimum number of negative air machines, as the manufacturer provided CFM capacity is provided for a new machine, with a new HEPA filter and no exhaust tube. Obviously, restrictions are introduced when the exhaust tube is attached to the machine and the HEPA filter is no longer new. All flow restrictions must be appropriately accounted for in negative air flow calculations. Microtrap calculations have been revised to account for reduced CFM and submitted to DOL for review in the revised Part I(R) - Remediation Operations Work Plan. Refer to Sections 6.1 and 6.5 for microtrap calculations. SC14) In addition, nothing is included within this section for any necessary selective

12 demolition required to complete the installation of the critical barriers and to completely isolate the work area from the exterior environment as well as the remainder of the building (e.g. openings/penetrations at columns, shafts, curtain walls, etc.). Obviously any selective demolition necessary must be completed at the conclusion of work area preparation (including establishment of negative air ventilation and installation of the remainder of the critical barriers). The following statement has been added to Section 6.1: It is not anticipated that any selective demolition will be required to complete the installation of critical barriers to completely the isolate the work area from the exterior environment. If selective demolition is determined to be necessary to complete the installation of critical barriers, it will be performed at the conclusion of work area preparation, including the establishment of negative pressure and the installation of the remainder of the critical barriers in that area NON-FIXED ITEMS (Now 6.1.2) SC15) This section does not include the requirement that itemsrcomponents with hidden or inaccessible void spaces, which can not be completely cleaned/decontaminated, must be disposed of as asbestos waste at a minimum. The following description is included in Section regarding the disposal of items that cannot be cleaned. If attempts to clean the above listed non-fixed items are not successful or possible due to compromised condition, they will be wrapped in two layers of poly, properly labeled, processed through the waste decontamination facility and disposed of as asbestos waste. Any non-fixed items that are porous or otherwise incapable of being cleaned will be wrapped in two layers of poly, properly labeled, processed through the waste decontamination facility and disposed of as asbestos waste. Section Please note that the removal of non-fixed items does not include the removal of components within hidden or inaccessible void spaces. Non-fixed items refers to movable objects that are present throughout the building and not attached to any surfaces (i.e. furniture, construction materials from the incomplete renovation work).the removal of fixed or attached components such as duct work or piping is detailed in Section INTERIOR WALLS AND CEILING SYSTEMS (Now 6.1.4) SC16) This section indicates that sheetrock, ceiling systems and other materials that do not readily absorb water will be thoroughly saturated during removal. There may be a misinterpretation of Section by this comment. Below is an excerpt from Section regarding wetting of non-hygroscopic materials:

13 Please note that it is not possible to fully saturate painted sheetrock, ceiling systems or other materials that do not absorb water. These items will not be fully saturated with water during removal. Water will be used to as a means of dust control at all times during the removal of interior sheetrock walls, ceiling systems or other materials do not absorb water. Section SC17) This section must be revised to indicate that materials to be removed shall be adequately wetted with amended water. Sufficient time shall be allowed for penetration to occur prior to abatement activities. All friable asbestos materials shall be thoroughly saturated. All non-hygroscopic (material that resists wetting) material shall be thoroughly wetted, prior to and during abatement. The following statement has been added to Section 6.1.4: Water will be applied continually as a means of dust control during the removal of interior sheetrock walls, ceiling systems or other non-asbestos materials that do not absorb water. Please note that work detailed in Section does not involve the removal of any asbestos material. The removal of asbestos material is addressed in Section SC18) This section does not include any prohibition of ACM disturbance during removal of non-acm systems. This requirement must be included within this section as ACM removals will commence following completion of the non-acm removals. Section has been revised to include the following statement: To the extent possible, workers will not disturb asbestos containing materials during the removal of non-acm systems. If it becomes necessary to remove ACM to access non- ACM systems, the ACM removal will be performed as outlined in Section prior to removal of the affected non-acm systems ASBESTOS-CONTAINING MATERIALS (Now 6.1.5) SC19) This section indicates that friable ACM pipe insulation and non-friable floor tiles will be removed simultaneously within the contained work area. However, ACM removal must be sequential as indicated within ICR All friable ACM must be removed first followed by an intermediate cleaning, and then all non-friable ACM shall be removed. This section must be revised to correspond with ICR 56 requirements. Section has been revised to include the following statement: In any areas where both friable and non-friable ACM are present within the same, immediate working area, all of the friable ACM in that area will be removed first. Following the removal of the friable ACM, the immediate working area will be cleaned by HEPA vacuuming and wet wiping. After this intermediate cleaning, the non-friable ACM in that immediate working area will be removed.

14 SC20) In addition, requirements consistent with ICR (o) must be included. This section of ICR 56 indicates that, power tools used to drill, cut, or otherwise disturb asbestos material in regulated abatement work areas, shall be manufacturer equipped with HEPA-filtered local exhaust ventilation'. Section has been revised to include the following statement: Any power tools used to disturb asbestos containing material will be equipped with HEPA filter exhaust ventilation CLEANING AND CLEARANCE OF THE FIRST FLOOR CLEAN ZONE SC21) This section must be revised to include the requirement that encapsulation of removal surfaces is prohibited until after satisfactory clearance air sample results have been obtained. The Cleaning and Clearance of Stairwell C has been revised. Please refer to the above response to the General Comment regarding Stairwell C to review this revision. SC22) In addition, please include a description of all anticipated remaining surfaces within the first floor clean zone following abatement, cleaning and clearance (e.g. masonry and steel construction with no interstitial spaces remaining at ceilings or walls... all exposed surfaces remaining at completion of cleaning and clearance are non-porous painted concrete or steel). The following list of surfaces to remain after the completion of clearance of the First Floor Clean Zone has been added at the end of Section 6.1: Steel Structurals Metal Hangers and Attachment Mechanisms Masonry Walls Concrete Deck Concrete Floor Slab Glass Window Wall Steel & Masonry Columns Cables Please note that all masonry surfaces that will remain will have been cleaned by HEPA vacuuming and wet wiping during remediation operations. These surfaces will have passed visual inspection and final air clearance and been encapsulated CLEANING AND CLEARANCE OF STAIRWELL C SC23) This section indicates that stairwell C will be cleaned and cleared simultaneously with the first floor clean zone, but no correlation is included regarding cleaning and clearance of these two portions of the same work area at exactly the same time. As these two portions of the same work area share the same air source and there is no segregation or isolation of these separate portions of the same work area, cleaning and clearance must

15 occur throughout both portions of the work area at the same time. As previously indicated, this approach is problematic at best The operations within each abatement work area must be entirely completed before the project monitor visual inspection commences. The satisfactory visual inspection would then be followed by clearance air sampling of the entire work area. The Cleaning and Clearance of Stairwell C has been revised. Please refer to the above response to the General Comment regarding Stairwell C to review this revision. SC24) In addition, as no wall, ceiling or other system removals are planned for Stairwell C, please include a description of Stairwell C construction, as well as a description of all remaining surfaces within the stairwell following cleaning and clearance (e.g. masonry and steel construction with no interstitial spaces at ceilings or walls... all exposed surfaces remaining at completion of cleaning and clearance are non-porous painted concrete or steel). The following list of the stairwell construction materials/surfaces to remain after the completion of clearance of Stairwell C has been added at the end of Section 6.1.7: Steel Structurals Metal Hangers and Attachment Mechanisms Steel Stairs Steel Handrails Stand Pipe Concrete Deck Concrete Slab Masonry Walls Please note that all masonry surfaces that will remain will have been cleaned by HEPA vacuuming and wet wiping during remediation operations. These surfaces will have passed visual inspection and final air clearance and been encapsulated. SC25) This section also indicates that Stairwell C barriers will be broken down following satisfactory clearance and then all accesses to the stairwell will be sealed from the upper floors. This requirement must be modified to prevent any access to stairwell C from upper floor contaminated areas. The critical barriers sealing upper floor access to Stairwell C should remain in place following completion of Stairwell C satisfactory clearance air sampling. This procedure should be included within the sitespecific variance petition. The Cleaning and Clearance of Stairwell C has been revised. Please refer to the above response to the General Comment regarding Stairwell C to review this revision FIRST FLOOR CLEAN ZONE AND C STAIRWELL CLEARANCE CRITERIA SC26) This section indicates that 5 TEM samples will be collected per floor of work area.

16 How does this requirement relate to clearance of Stairwell C? Does this mean that approximately 75 TEM samples will be collected from Stairwell C during clearance air sampling? Minimum clearance air sampling requirements must be further clarified. The follwowing clearance testing procedure is included in the revised Stairwell C cleaning and clearance procedure: After the Stairwell C work area has passed regulatory visual inspection, aggressive clearance air sampling will be performed by the Owner s Environmental Consultant. Sampling will be performed as follows: 5 TEM air samples (1 sample for every 3 floors) and 5 Metals air samples (1 sample for every 3 floors) will be run for the entire stairwell. Sample locations will be evenly distributed vertically through the stairwell. Clearance testing for all work areas will be consistent with the work area Clearance Criteria noted in section SC27) In addition, please include a description of all anticipated remaining surfaces within the first floor clean zone following abatement, cleaning and clearance (e.g. masonry and steel construction with no interstitial spaces remaining at ceilings or walls... all exposed surfaces remaining at completion of cleaning and clearance are non-porous painted concrete or steel). The following list of surfaces to remain after the completion of clearance of the First Floor Clean Zone has been added at the end of Section 6.1: Steel Structurals Metal Hangers and Attachment Mechanisms Masonry Walls Concrete Deck Concrete Floor Slab Glass Window Wall Steel & Masonry Columns Cables Please note that all masonry surfaces that will remain will have been cleaned by HEPA vacuuming and wet wiping during remediation operations. These surfaces will have passed visual inspection and final air clearance and been encapsulated. 6.2 UPPER LEVEL ACCESS SC28) This section indicates that the personal decontamination facility will be constructed at the West Broadway East side Lobby south entrance. However, the clean zone configuration plan drawing indicates that the personal decontamination facility shall be constructed within the building at the south interior entrance to the east Side Lobby. The plan drawing and work plan text must be revised accordingly. The logistics plan (Attachment V) entitled Decontamination of the Clean Zone and Upper Level Access shows that the location of the personal decontamination unit is

17 outside the Building attached to the East side Lobby south entrance as indicated in Section 6.2. The personal decontamination unit will not move inside of the Building until the Clean Zone has been cleared. It will be necessary to gain access to the upper levels during the work to decontaminate the Clean Zone, so it is necessary to have this decon exterior to the Building until the Clean Zone is established. SC29) In addition, this section indicates that upper floor access and abatement of the first floor clean zone will occur simultaneously. This simultaneous access would be impossible if the personal decontamination facility is actually located within the first floor work area. These inconsistencies must be appropriately addressed. Decontamination facilities are located outside of the Building during simultaneous work procedures on the Upper Floors. Refer to logistics plan (Attachment V, page 55 Decontamination of the Clean Zone and Upper Level Access). 6.3 SHREDDER INSTALLATION SC30) This section indicates that a section of north side curtain wall will be removed to allow installation of the shredder. However, nothing is mentioned regarding any impact to remaining exterior ACMs. Please clarify this section accordingly. The following statement has been added to Section 6.3: There are no exterior ACMs present at the north side curtain wall. This area of the Building is double height with no kneewall present. SC31) In addition, a minimum of eight air changes per hour must be maintained within the shredder area during shredder operations. A manometer shall be installed within this area to continuously document pressure differential readings within the shredder processing area. Please note that the Remediation Operations will be performed in one containment. The shredder will be inside of this containment. The following statement has been added to Section 6.3: The contractor will install negative pressure ventilation equipment, as demonstrated by calculations, to provide eight (8) air volume changes per hour in the Shredder Zone. Please note that the shredder zone is part of the one containment work area where air volume will be changed four (4) times per hour in accordance with ICR 56. A manometer shall be installed in the shredder zone to document pressure differential in this area. SC32) All processing of waste through the shredder must be completed using wet methods, and no visible emissions are allowed during the processing procedure. Waste to be processed must be adequately wet during processing operations and after processing

18 when loaded into waste containers. Please note that only non-acm will be processed through the shredder. As stated in Section 6.3 of Part I(R) Remediation Operations Work Plan, the shredder will be equipped with a misting systems. The shredder will be equipped with a water misting system to control dust while materials are processed through the hopper. Section 6.3, page 20 This language has been revised for clarification to state the following: The shredder will be equipped with a wet misting system for dust control. The misting system consists of a plastic attachment for a water hose. The attachment spreads water from the hose in an even and repetitive manner across the shredder loading hopper. The misting system shall be running continuously at all times while the shredder is being operated. The shredder area will be placed under negative pressure as part of the containment of the upper levels. SC33) The list of shreddable materials includes various metal items, wood and porcelain items. Further details must be provided regarding limitations of the shredder. What type of materials can not be processed by the shredder (other than ACM)? Can any thickness metal be processed? Also, are there any engineering controls at the shredder itself, such as localized HEPA-filtered negative air ventilation? It is not anticipated that building materials scheduled for removal during the Remediation Operations which cannot be processed through the shredder will be encountered. The following statement has been added to Section 6.3: Should any non-porous, non-asbestos materials be encountered that cannot be processed through the shredder, they will be cleaned for disposal as conventional waste after inspection by the Owner s Environmental Consultant or otherwise disposed of as asbestos waste or in accordance with any waste characterization results. Should any porous, non-asbestos materials be encountered that cannot be processed through the shredder, they will be disposed of as asbestos waste or in accordance with any waste characterization results. See the above comment SC32 regarding the shredder misting system. There will be enough negative pressure ventilation equipment to provide eight (8) air volume changes per hour in the shredder zone. No other engineering controls will be provided at the shredder itself. 6.4 ESTABLISHMENT OF SECONDARY LOADING DOCK SC34) This section indicates that a section of west side curtain wall will be removed to allow for loading dock conversion. However, nothing is mentioned regarding any impact to remaining exterior ACMs. Please clarify this section accordingly.

Regulatory Submittal Part I(S) Scaffold Erection Operation Work Plan

Regulatory Submittal Part I(S) Scaffold Erection Operation Work Plan Regulatory Submittal Part I(S) Scaffold Erection Operation Work Plan Project: Remediation and Deconstruction of Fiterman Hall 30 West Broadway New York, New York Prepared for: The Dormitory Authority of

More information

PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL

PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL At 130 Liberty Street New York, New York Lower Manhattan Development Corporation

More information

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Introduction 1 Scope 1 Policy Statement

More information

Regulatory Submittal Part IV(R) Remediation Phase. Waste Sampling and Management Plan

Regulatory Submittal Part IV(R) Remediation Phase. Waste Sampling and Management Plan Regulatory Submittal Part IV(R) Remediation Phase Waste Sampling and Management Plan Remediation and Deconstruction of Fiterman Hall 30 West Broadway New York, New York Prepared for: Dormitory Authority

More information

CLASS I AND II ABATEMENT PROJECT SUBMITTALS

CLASS I AND II ABATEMENT PROJECT SUBMITTALS 5.1 Pre-Work Submittals CLASS I AND II ABATEMENT PROJECT SUBMITTALS Abatement contractors shall submit the following in a bound notebook to AU or our designated representative at the mandatory pre-construction

More information

Project Monitoring & Air Sampling

Project Monitoring & Air Sampling Project Monitoring & Air Sampling 1. Qualifications of Air Sampling Personnel. The project air sampling shall be conducted by an asbestos project air sampling technician who has been trained in the selected

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information

Remediation and Deconstruction of Fiterman Hall

Remediation and Deconstruction of Fiterman Hall Remediation and Deconstruction of Fiterman Hall CUNY/DASNY Pei Cobb Freed Team Community Update October 30, 2006 Presentation Summary Introduction and Project History Project Update PAL Environmental Regulatory

More information

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS 1. DESCRIPTION OF WORK: ATTACHMENT A RFP # 024-0-2016BH ASBESTOS ABATEMENT REQUIREMENTS The work includes pre-cleaning, repair and/or removal and disposal of friable and non-friable asbestos containing

More information

Façade Characterization Report

Façade Characterization Report Preliminary Façade Characterization Report Remediation and Deconstruction of Fiterman Hall, 30 West Broadway, New York, New York Prepared for: Dormitory Authority of the State of New York & The City University

More information

DIVISION 02 SELECTIVE DEMOLITION

DIVISION 02 SELECTIVE DEMOLITION DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.

More information

APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION

APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION The following appendix includes information and standard drawings that are diagrammatic and are used only to convey intent. Guidelines for Use of Sample

More information

Section Asbestos Containment Procedures

Section Asbestos Containment Procedures Section Cover Page Section 02 82 05 2017-10-01 Use this Section where full containment will be required, or if a Contractor option, may be required, depending on the removal method(s) selected by the Contractor.

More information

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f:

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f: VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA 02189 www.vertexeng.com p: 781.952.6000 f: 781.335.3543 EZRA BAKER ELEMENTARY SCHOOL/GYMNASIUM ASBESTOS ABATEMENT WORK PLAN ASBESTOS CONTAINING

More information

UI Procedures for Asbestos Management

UI Procedures for Asbestos Management UI Procedures for Asbestos Management The University of Iowa Rev.10/22/08, 10/15/09 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work: 125 Syndicate Avenue, Thunder Bay, Ontario Page 1 of 5 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:.1 Removing asbestos-containing transite

More information

LEAD HAZARD CONTROL PROGRAM

LEAD HAZARD CONTROL PROGRAM LEAD HAZARD CONTROL PROGRAM Supervisor s Manual Prepared by Environmental Health and Safety Services Occupational Safety Programs GLOSSARY Abatement or Deleading CFR Control Measure Encapsulation EPA HEPA

More information

Risk Assessment and Preventive Measures Checklist for Construction and Renovation. Location of Construction: Project Start Date: Estimated Duration:

Risk Assessment and Preventive Measures Checklist for Construction and Renovation. Location of Construction: Project Start Date: Estimated Duration: Risk Assessment and Preventive Measures Checklist for Construction and Renovation Location of Construction: Project Start Date: Estimated Duration: Project Manager (PM): Contractor(s): Infection Prevention

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

Rowan University Asbestos Management Program

Rowan University Asbestos Management Program Rowan University Asbestos Management Program Table of Contents I. Introduction II. Regulatory Compliance III. Department Responsibilities for Asbestos A. EHS (Safety Specialist Staff) B. EHS (Asbestos

More information

ESTATES DEPARTMENT. Management of Asbestos Policy and Procedures Document. Rev 9

ESTATES DEPARTMENT. Management of Asbestos Policy and Procedures Document. Rev 9 ESTATES DEPARTMENT Management of Asbestos Policy and Procedures Document Rev 9 Contents SECTION 1: Estates Management of Asbestos Policy 1.1 Introduction 1.2 Policy Statement 1.3 Legal Requirements 1.4

More information

CITY OF ANDERSON BUILDING AND CODES 601 South Main Street

CITY OF ANDERSON BUILDING AND CODES 601 South Main Street CITY OF ANDERSON BUILDING AND CODES 601 South Main Street Plan Review Notes (STREET ADDRESS) ANDERSON, SC Plan Review Number: Building Plans prepared by: Plans Signed by: Project Name: Plans Received:

More information

CHAPTER 34 ASBESTOS. Where is it Found? 34 ASBESTOS. What is Asbestos?

CHAPTER 34 ASBESTOS. Where is it Found? 34 ASBESTOS. What is Asbestos? CHAPTER 34 ASBESTOS 34 ASBESTOS This chapter provides some brief information about asbestos in construction. If you encounter asbestos on the job, you will need more information. Here are the two main

More information

ASBESTOS SCIENCE TECHNOLOGIES, INC.

ASBESTOS SCIENCE TECHNOLOGIES, INC. ASBESTOS SCIENCE TECHNOLOGIES, INC. P.O. Box 505 Bangor, CA 95914 Phone (530) 518-0934 Email - astinc17@yahoo.com Report for Hoopa Valley Elementary School 11500 State Highway 96 Hoopa, Ca. 95546 Mold

More information

EPA s Lead Program Rule At-A-Glance

EPA s Lead Program Rule At-A-Glance EPA s Lead Program Rule At-A-Glance FLOW CHART 1: Do the Requirements Apply to the Renovation? If you will be getting paid to do work that disturbs painted surfaces in a pre-1978 home, apartment building,

More information

Asbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22

Asbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22 Page 1 of 22 Asbestos Survey Project Summary Pursuant to your request; Environmental, Inc., has performed an Asbestos Building Survey on 8/13/2014 and limited to the above referenced location. The Interior/Exterior/Roof

More information

Inspection of New One- and Two- Family Dwellings

Inspection of New One- and Two- Family Dwellings Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Inspection of New One- and Two- Family Dwellings Planning and Development

More information

Application for Commercial Plan Review and Building Permit. Address:

Application for Commercial Plan Review and Building Permit. Address: City of Warrenton 200 West Booneslick Warrenton, MO 63383 : 636-456-3535 Fax: 636-456-1336 www. war r ent o n- mo.org Application for Commercial Plan Review and Building Permit PERMIT# Purpose: Commercial

More information

MOLD REMEDIATION PROCEDURES

MOLD REMEDIATION PROCEDURES Page: 1 of 5 1.0 PROGRAM OBJECTIVE The purpose of this procedure is to define the responsibilities, methods, procedures and training required to safely and effectively remove or clean mold-contaminated

More information

Lead Based Paint Policy

Lead Based Paint Policy Lead Based Paint Policy 1. Guidance for the removal or maintenance of lead-based paint has undergone changes that affect the painting industry. The U.S. Department of Housing and Urban Development (HUD)

More information

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

SPACE TYPE: OUTSIDE PARKING (STRUCTURE) SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing following work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing following work: Page 1 of 6 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing following work:.1 Removing roofing materials that are suspected of containing asbestos using wet material

More information

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 Issued 6/1/95 Revised 11/08/2004; 3/6/06 Please direct any questions or comments about the applicability of this document to Luigi

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY

AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY ASBESTOS CONTROL PROGRAM September 22, 2006 Table of Contents 1.0 Introduction... 4 2.0 Purpose and Applicability... 4 3.0 Roles and Responsibilities... 5 3.1

More information

Module 3: Asbestos. 15 th Annual OSC Readiness Training Program.

Module 3: Asbestos. 15 th Annual OSC Readiness Training Program. Module 3: Asbestos 15 th Annual OSC Readiness Training Program www.oscreadiness.org Module Overview Asbestos Overview of asbestos Federal and State laws regulating asbestos Building Demolition Abatement

More information

BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02

BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02 BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02 Department Title: Safety Department Page: 2 Department Title: Safety Department Page:

More information

Asbestos and Lead Considerations in Construction Projects. Sean Purcer Senior Consultant Anthony Price Senior Consultant

Asbestos and Lead Considerations in Construction Projects. Sean Purcer Senior Consultant Anthony Price Senior Consultant Asbestos and Lead Considerations in Construction Projects Sean Purcer Senior Consultant Anthony Price Senior Consultant Who We Are History Founded in 1990 by Environmental, Health and Safety (EHS) managers

More information

PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT. Construction requirements for LOWER LEVEL DEVELOPMENT. in residential dwellings

PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT. Construction requirements for LOWER LEVEL DEVELOPMENT. in residential dwellings PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT Construction requirements for LOWER LEVEL DEVELOPMENT in residential dwellings January 2018 contents GENERAL INFORMATION... 3 BUILDING CODE REQUIREMENTS...

More information

GUIDELINES FOR SANITARY DESIGN AND CONSTRUCTION OF MILK PRODUCTS PLANTS (rev )

GUIDELINES FOR SANITARY DESIGN AND CONSTRUCTION OF MILK PRODUCTS PLANTS (rev ) Milk and Dairy Food Safety Branch 1220 N Street, Sacramento, CA 95814 GUIDELINES FOR SANITARY DESIGN AND CONSTRUCTION OF MILK PRODUCTS PLANTS (rev. 10-20-2011) The outline below lists sanitary requirements

More information

LOWE S INSTALLER LRRP CHECKLIST FOR RENOVATIONS PERFORMED IN PRE-1978 HOUSING AND CHILD-OCCUPIED FACILITIES

LOWE S INSTALLER LRRP CHECKLIST FOR RENOVATIONS PERFORMED IN PRE-1978 HOUSING AND CHILD-OCCUPIED FACILITIES LOWE S INSTALLER LRRP CHECKLIST FOR RENOVATIONS THE PURPOSE OF THIS FORM IS TO DOCUMENT COMPLIANCE WITH THE U.S. ENVIRONMENTAL PROTECTION AGENCY S LEAD RENOVATION, REPAIR, AND PAINTING RULE ( RRP RULE

More information

TABLE OF CONTENTS 4. PREPARATION, COMMUNICATIONS, AND CONTROLS

TABLE OF CONTENTS 4. PREPARATION, COMMUNICATIONS, AND CONTROLS TABLE OF CONTENTS SECTION PAGE NO. 1. INTRODUCTION... 1-1 1.1 Background... 1-1 1.2 Conceptual Site Model... 1-1 1.3 Plan Organization... 1-2 1.4 Certification... 1-3 2. SAMPLE COLLECTION, ANALYSIS, AND

More information

Abatement Scope of Work and Project Requirements for Library Painting Project Bay Shore Library Bret Harte Library Dana Library Long Beach, California

Abatement Scope of Work and Project Requirements for Library Painting Project Bay Shore Library Bret Harte Library Dana Library Long Beach, California for Bay Shore Library Bret Harte Library Dana Library Background Information Site/Building Owner: City of Long Beach Site Contact: The City of Long Beach Public Works Department, 333 West Ocean Blvd. Long

More information

Lead Management Program

Lead Management Program Syracuse University Lead Management Program Requirements for Departments Managing Projects That Involve Lead-Containing Materials 2017 Prepared by: Syracuse University Environmental Health & Safety Services

More information

Release: 1. CPCCDE3014A Remove non-friable asbestos

Release: 1. CPCCDE3014A Remove non-friable asbestos Release: 1 CPCCDE3014A Remove non-friable asbestos CPCCDE3014A Remove non-friable asbestos Modification History New to CPC08 Replaces unit CPCCDE3012A Encapsulate and remove asbestos Not equivalent Unit

More information

Repair or replace section of driveway, approach, or sidewalk that are a trip hazard.

Repair or replace section of driveway, approach, or sidewalk that are a trip hazard. City of Gibraltar Pre-Sale Inspection Report Checklist FLATWORK: Repair or replace section of driveway, approach, or sidewalk that are a trip hazard. EXTERIOR PROPERTY: Fences/Sheds/Retaining walls: Repair,

More information

LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for

LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Physical Plant Division Engineering and Architectural Services Department

More information

SECTION INDOOR AIR QUALITY MANAGEMENT PLAN. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION INDOOR AIR QUALITY MANAGEMENT PLAN. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 018119 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

CONTRACTOR INFORMATION NAME, ADDRESS, CITY, STATE, ZIP LICENSE# 058- LICENSE# SIGNATURE OF APPLICANT ADDRESS PHONE NUMBER

CONTRACTOR INFORMATION NAME, ADDRESS, CITY, STATE, ZIP LICENSE# 058- LICENSE# SIGNATURE OF APPLICANT ADDRESS PHONE NUMBER Sangamon County Department of Public Health Building Safety Section 2833 South Grand Avenue East Application for Plan Examination Springfield, Illinois 62703 Permit # & Building Permit Ph: (217)535-3145/Fax

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-07 84 00 (May 2010) Change 1-08/13 ------------------------ Preparing Activity: USACE Superseding UFGS-07 84 00 (October 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Figure 3-6. Sample ICRA Matrix of Precautions Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step 1: Using the following table, identify the Type of Construction

More information

SWCAA 476 Standards for Asbestos Control, Demolition, and Renovation

SWCAA 476 Standards for Asbestos Control, Demolition, and Renovation Standards for Asbestos Control, Demolition, and Renovation Effective: June 19, 2017 Filed with Code Reviser (CR-101) - WSR 16-23-079, November 15, 2016 Preliminary Notice Published - WSR 16-23, December

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department: Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,

More information

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step One: Using the following table, identify the Type of Construction Project Activity (Type A-D) TYPE A TYPE B TYPE

More information

PROJECT SPECIFICATIONS FOR THE REMOVAL OF PCB AND MERCURY

PROJECT SPECIFICATIONS FOR THE REMOVAL OF PCB AND MERCURY PROJECT SPECIFICATIONS FOR THE REMOVAL OF PCB AND MERCURY MARSHALL COURTS PHASE IV AND V 741 34 TH STREET NEWPORT NEWS, VIRGINIA ECS PROJECT NO. 47:3961 FOR VIA DESIGN ARCHITECTS, PC JUNE 9, 2017 PROJECT

More information

INVITATION TO BID. Prospective bidders are encouraged to conduct a pre-bid site visit to aid in their bidding assessments.

INVITATION TO BID. Prospective bidders are encouraged to conduct a pre-bid site visit to aid in their bidding assessments. February 12, 2014 INVITATION TO BID The City of Coffeyville, Kansas, is accepting sealed bids for the demolition and removal of certain structures located within the City. The proposed work will be on

More information

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control NAVSEA STANDARD ITEM ITEM NO: 009-10 DATE: 18 NOV 2016 CATEGORY: I 1. SCOPE: 1.1 Title: Asbestos-Containing Material (ACM); control 2. REFERENCES: 2.1 29 CFR 1915.1001, Occupational Safety and Health Standards

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work: 125 Syndicate Avenue Page 1 of 12 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following Work:.1 Removal of asbestos-containing pipe and duct insulation, as

More information

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit: TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be

More information

INTRODUCTION TO THE PROGRAM

INTRODUCTION TO THE PROGRAM INTRODUCTION TO THE PROGRAM Structure and Organization Information in this program is presented in a definite order, so that employees will see the relationships between the various groups of information

More information

Chapter 2: Foundation

Chapter 2: Foundation Chapter 2: Foundation Crawlspace [V502.1.2] [V502.1.2] [V502.1.3] Vents. Vents in the crawlspace help keep floor insulation and floor framing dry. Crawlspace vents also reduce the potential for radon buildup

More information

1420 Miner Street Des Plaines, IL P: desplaines.org COMMERCIAL STRUCTURES (INCLUDING ALTERATIONS AND ADDITIONS)

1420 Miner Street Des Plaines, IL P: desplaines.org COMMERCIAL STRUCTURES (INCLUDING ALTERATIONS AND ADDITIONS) 1420 Miner Street Des Plaines, IL 60016 P: 847.391.5380 desplaines.org COMMERCIAL STRUCTURES (INCLUDING ALTERATIONS AND ADDITIONS) Five sets of stamped plans and specifications (six sets if food establishment),

More information

Table of Contents. C. Recommended Remediation Firms: upon request

Table of Contents. C. Recommended Remediation Firms: upon request Table of Contents I. Job, Contact & Site Information II. Scope of Work III. Building Overview IV. Findings V. Conclusions and Recommendations VI. Expectations VII. References VIII. Limits of Liability

More information

Asbestos Management Plan. Program originated: 02/2000 Last updated: 6/2015. Wendel Reece University Safety Manager

Asbestos Management Plan. Program originated: 02/2000 Last updated: 6/2015. Wendel Reece University Safety Manager Asbestos Management Plan Program originated: 02/2000 Last updated: 6/2015 Wendel Reece University Safety Manager TABLE OF CONTENTS I. Introduction II. Purpose III. Operations and Maintenance Asbestos Related

More information

APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES

APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES TY PE 2 WOR K PR OCE DUR ES These procedures are to be followed by all maintenance personnel and contractors performing the following work at KPDSB buildings.

More information

1 AND 2 FAMILY DWELLING REQUIREMENTS

1 AND 2 FAMILY DWELLING REQUIREMENTS PLAN REQUIREMENTS: 1 AND 2 FAMILY DWELLING REQUIREMENTS All residential plans including additions and attached garages shall be designed to the current edition of the International Residential Code. Plans

More information

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested. Purpose 355 West Queens Road Single Family New Construction Required Inspection Stages Master Requirement GEN 110 Building Department: 604-990-2480, building@dnv.org, fax: 604-984-9683 The following procedure

More information

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843)

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843) ASBESTOS ABATEMENT PLAN 1814 PRINCE STREET 2-STORY Georgetown, South Carolina Asbestos Inspections, LLC Project # 2017-48 Performed in general accordance with SCDHEC Asbestos Regulation 61.86.1 Assessment

More information

ARTICLE 4: ASBESTOS CONTROL STANDARDS

ARTICLE 4: ASBESTOS CONTROL STANDARDS ARTICLE 4: ASBESTOS CONTROL STANDARDS SECTION 4.01 ASBESTOS DEFINITIONS Adopted 06/08/95 (818) Revised 02/12/98 (863), 07/13/00 (918), 09/26/02 (978), 02/27/03 (987), 03/26/09 (1148) (a) AHERA BUILDING

More information

UNIVERSITY OF COLORADO AT BOULDER

UNIVERSITY OF COLORADO AT BOULDER UNIVERSITY OF COLORADO AT BOULDER SPECIFICATION FOR INDUSTRIAL HYGIENE CONSULTING SERVICES ASBESTOS ABATEMENT PROJECTS IN FACILITIES FACILITY ASSESSMENTS- PROJECT SURVEILLANCE-AIR MONITORING PROCEDURES

More information

OLM Environmental, LLC PHONE: (919) LOCKWOOD FOLLY LANE; RALEIGH, NC CELLPHONE: (919)

OLM Environmental, LLC PHONE: (919) LOCKWOOD FOLLY LANE; RALEIGH, NC CELLPHONE: (919) OLM Environmental, LLC PHONE: (919) 212-3019 2317 LOCKWOOD FOLLY LANE; RALEIGH, NC 27610 CELLPHONE: (919) 931-0629 July 31, 2016 Zapolski Real Estate, LLC 501 Washington Street Durham, North Carolina 27701

More information

RESIDENTIAL CONSTRUCTION New Dwellings and Additions

RESIDENTIAL CONSTRUCTION New Dwellings and Additions How to Obtain a Building Permit For RESIDENTIAL CONSTRUCTION New Dwellings and Additions MIAMI COUNTY, KANSAS CODE SERVICES DEPARTMENT 201 South Pearl Street, Suite 201 Paola, Kansas 66071-1777 Phone:

More information

A Design Review of Waterproofing Codes

A Design Review of Waterproofing Codes A Design Review of Waterproofing Codes Section 1807 of Chapter 18 of the International Building Code addresses waterproofing under the section title of Dampproofing and Waterproofing. The section defines

More information

Safety Policy and Procedure

Safety Policy and Procedure Safety Policy and Procedure Policy Number 045 Authorized By: The Cianbro Companies Alan Burton Title: Asbestos Operations Effective Date: 03/25/09 Page 1 of 10 1 Status 1.1 Update of existing policy, effective

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

4. Number of drawings required: ( ) Locations of nearest streets

4. Number of drawings required: ( ) Locations of nearest streets CITY OF MANSFIELD BUREAU OF BUILDING AND CODES 30 NORTH DIAMOND STREET 3RD FLOOR MANSFIELD, OHIO 44902 Phone (419) 755-9688 Fax (419) 755-9453 www.ci.mansfield.oh.us COMMERCIAL BUILDING PLAN REQUIREMENTS

More information

CITY OF GLASGOW BUILDING PERMIT APPLICATION 126 E. Public Square Glasgow, KY Phone: (270) Fax: (270)

CITY OF GLASGOW BUILDING PERMIT APPLICATION 126 E. Public Square Glasgow, KY Phone: (270) Fax: (270) CITY OF GLASGOW BUILDING PERMIT APPLICATION 126 E. Public Square Glasgow, KY 42141 Phone: (270) 651-3921 Fax: (270) 651-9553 Permit # Filing Date: Total Fee: Property Property Owner: Subdivision: Lot #

More information

LEAD-BASED PAINT PRESENT

LEAD-BASED PAINT PRESENT June 5, 2009 Mr. A.L. 26 ##th Street ###, NY 11102 Via email: LEAD-BASED PAINT PRESENT Door Components Enclosed you will find the results of the Lead-Based Paint Inspection (utilizing an X-Ray Fluorescence

More information

RESIDENTIAL BUILDING PLAN REQUIREMENTS

RESIDENTIAL BUILDING PLAN REQUIREMENTS CITY OF MANSFIELD BUREAU OF BUILDING AND CODES 30 NORTH DIAMOND STREET 3RD FLOOR MANSFIELD, OHIO 44902 Phone (419) 755-9688 Fax (419) 755-9453 www.ci.mansfield.oh.us RESIDENTIAL BUILDING PLAN REQUIREMENTS

More information

HOW TO OBTAIN A BUILDING PERMIT

HOW TO OBTAIN A BUILDING PERMIT HOW TO OBTAIN A BUILDING PERMIT A GUIDE TO THE HOMEOWNER Copies of this Guide can be obtained from the Building Department upon request THE CORPORATION OF THE TOWNSHIP OF GEORGIAN BAY BUILDING DEPARTMENT

More information

Building Codes and Ordinances ARC 227

Building Codes and Ordinances ARC 227 Building Codes and Ordinances ARC 227 Week 6 Fire Resistive Construction 03.02.10 Instructor: Rick Staub, AIA Email: staub@pointonearchitects.com Phone: 860-434-7707 Fire Resistive Construction Passive

More information

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Building Inspections SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Permit Applications Pool permit applications are now being accepted online at http://etrakit.flower-mound.com/. Starting November 1,

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 1. Purpose This policy assists in protecting USPL workers from exposure to lead and to gain compliance with state and federal regulations.

More information

Asbestos Management Policy University of Wisconsin-Platteville Reviewed 4/2016

Asbestos Management Policy University of Wisconsin-Platteville Reviewed 4/2016 Asbestos Management Policy University of Wisconsin-Platteville Reviewed 4/2016 1.0 Purpose This written program is intended to comply with both state and federal asbestos regulations. Asbestos containing

More information

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843)

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843) ASBESTOS ABATEMENT PLAN 1814 PRINCE STREET Georgetown, South Carolina Asbestos Inspections, LLC Project # 2017-48 Performed in general accordance with SCDHEC Asbestos Regulation 61.86.1 Assessment Completed

More information

Encapsulated, Sealed & Closed Crawlspace Installation Manual

Encapsulated, Sealed & Closed Crawlspace Installation Manual YourCrawlSpace, Inc. 1007 Johnni4 Dodds Blvd. Mt. Pleasant, SC 29464 Toll Free: 877-44-CRAWL (27295) Local: (843) 593-1115 Encapsulated, Sealed & Closed Crawlspace Installation Manual Copyright 2017 Your

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

Siding and Soffit Installation Guidelines

Siding and Soffit Installation Guidelines Siding and Soffit Installation Guidelines email web phone 07 46 16 Longboard Siding & Soffit INTRODUCTION INSTALLATION GUIDELINES NOTE: These instructions are prepared for persons experienced in the field

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 8113.53 - SUSTAINABLE DESIGN REQUIREMENTS - GREEN GLOBES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

CONCRETE & STAINING TECHS SIMPLY WARRANTY

CONCRETE & STAINING TECHS SIMPLY WARRANTY THIS IS A WARRANTY AND NOT INSURANCE. THIS WARRANTY DOES NOT TAKE THE PLACE OF YOUR INSURANCE OR YOUR HOMEOWNERS INSURANCE. This warranty is on the task. If the Home is sold, each successor in title to

More information

September 30, Ted Sherman Saint Paul Public Schools 1930 Como Avenue Saint Paul, MN Dear Ted,

September 30, Ted Sherman Saint Paul Public Schools 1930 Como Avenue Saint Paul, MN Dear Ted, September 30, 2014 Providing Trusted Health and Safety Solutions Ted Sherman Saint Paul Public Schools 1930 Como Avenue Saint Paul, MN 55108 Dear Ted, Enclosed please find the Parkway Montessori School

More information

Demolition Safety!!!!

Demolition Safety!!!! Sample Written Program For Your Company For Demolition Safety Provided By: P.O. Box 2136 Slidell, LA 70458 Phone: 985-781-1444 Fax: 985-718-4957 Email: info@se-safety.com Demolition Safety Program Purpose

More information

Commercial Remodel Permit

Commercial Remodel Permit Commercial Remodel Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning districts, each

More information

BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS

BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS Please note: This construction plan component list is to be used as a guide to assist you with your project. There may be elements unique to your project not

More information

Asbestos Awareness Program

Asbestos Awareness Program Safety Manual 1 of 9 Safety Manual Sect: 1.0 Purpose 2.0 Scope Rel. Date: Last Review: This program covers Ardent policy related to asbestos, either discovered or suspected in the workplace. Ardent recognizes

More information

ADMINISTRATION CHAPTER 1

ADMINISTRATION CHAPTER 1 CHAPTER 1 ADMINISTRATION PART 1 SCOPE AND APPLICATION SECTION 101 SCOPE AND GENERAL REQUIREMENTS 101.1 Title. This code shall be known as the Florida Building Code, Energy Conservation, and shall be cited

More information

START WORK NOTIFICATION

START WORK NOTIFICATION START WORK NOTIFICATION This form must be submitted at least 3 buisness days before beginning work to the Rhode Island Department of Health by email at leadprogram@health.ri.gov or by fax at 401-222-2456.

More information

SECTION THROUGH-PENETRATION FIRESTOP SYSTEMS

SECTION THROUGH-PENETRATION FIRESTOP SYSTEMS SECTION 07841 - THROUGH-PENETRATION FIRESTOP SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

GUIDE FOR APPLYING FOR A BUILDING PERMIT

GUIDE FOR APPLYING FOR A BUILDING PERMIT Township Of Perry/Township Of Armour Township of McMurrich/Monteith GUIDE FOR APPLYING FOR A BUILDING PERMIT These next few pages are designed to assist you in applying for a building permit. This guide

More information