MTM DESIGN PRACTICE NOTE USE OF GUARD RAILS

Size: px
Start display at page:

Download "MTM DESIGN PRACTICE NOTE USE OF GUARD RAILS"

Transcription

1 Approval Amendment Record Approval Date Version Description 24/08/ Initial issue PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 6

2 Table of Contents 1. Purpose Scope Background The Issue Reference Documents Functional Requirements General Requirements Technical Requirements Guard Rail Assembly Positioning of Guard Rails Signalling and Electrical Requirements... 6 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 6

3 1. Purpose The purpose of this Design Practice Note (DPN) is to outline MTM requirements for the design and installation of guard rails, in accordance with AS 7640 Rail Infrastructure Rail Management. 2. Scope The DPN applies to all new infrastructure intended to be managed by MTM, where a risk assessment has identified the need to provide close containment of a derailed vehicle on a plain line track section. 3. Background Due to the tendency to construct new track alignments offline to the side of an existing corridor or above existing ground level, the operating railway is sometimes moved into closer proximity to existing public, residential and commercial areas. MTM has identified a need to consider the provision of derailment containment devices on some new track alignments in order to minimise the likelihood of a derailed vehicle damaging lineside infrastructure or falling from a structure. 4. The Issue Existing MTM requirements detailed in L1-CHE-INS-026 specifies the use of derailment kerbs or deflection barriers on underbridges. There may be a requirement for additional close containment at other locations such as on embankments, bridge approaches, or adjacent to high-risk infrastructure. The RISSB document AS 7640 Rail Infrastructure Rail Management outlines the high-level function and requirements for guard rails. MTM currently has no guidelines for the application of AS 7640 with regards to the use of guardrails for new installations. 5. Reference Documents The following standards and documents have been referenced in the development of this DPN. AS 7640 AS L0-SQE-PRO-031 L1-CHE-INS-026 Rail Infrastructure Rail Management Railway Track Materials Part 1: Steel Rails Enterprise Risk Management Procedure Design Practice Note: Derailment Control on Underbridges MTPR Welded Track Management Manual Chapter 8 Laying Rail Bolted, Welded and LWR NIST-2650 TA 0125 Use and Laying of Rail MTM Type Approval: Austral Full Depth Guardrail Sleeper and Guardrail Assembly In the event of an inconsistency between this DPN and the referenced material, the designer shall seek clarification from the MTM Chief Engineer. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 6

4 6. Functional Requirements The design and installation of guard rails shall be in accordance with the requirements listed in this DPN. For new track construction, the requirement to install guard rails shall be determined through a risk assessment process. The location of the new track alignment in relation to an identified hazard shall be assessed to determine if there is adequate restraint of a derailed vehicle, so far as is reasonably practicable, when using existing control measures and considering similar occurrences on the MTM network. Guard rails may be selected to provide further containment if deemed necessary. Examples of where/how this may occur include: Constructing the railway on a raised structure immediately adjacent to residential or commercial properties, areas used by the public, etc. where there is a risk of a vehicle falling from height at a near-vertical angle; Transitioning between different track forms, where there may be uneven settlement; or Tracks adjacent to high-risk assets such as pipelines and other services. The use of guard rails shall be limited to the extent of the hazard plus the necessary approach lengths outlined in section Excessive use of guard rails must be avoided in order to minimise impacts on future maintenance and renewal activities. Guard rails must not be used in lieu of collision or anti-snag protection requirements for existing or new structures. Guard rails are not required for existing or reconstructed track which is generally unchanged from its established alignment, unless a specific risk has been identified and installation has been deemed necessary by the Office of the Chief Engineer. Any existing guard rail assemblies are not subject to the requirements of this document. During track reconstruction, existing assemblies should be upgraded to comply with this DPN, where reasonably practical. 6.1 General Requirements The design shall demonstrate that all controls have been adopted, so far as is reasonably practicable, to ensure the use of guard rails as the primary derailment control device, or as part of the derailment control system, meets the following primary requirements: Keeps derailed or derailing bogies/wheels tracking parallel and in close proximity to the running rails, with the axles parallel to the plane of the running rails; Increase the likelihood that a derailed train will be kept upright and within gauge of the track it was travelling on; and Limits potential damage to rolling stock and lineside infrastructure. Guard rails may be considered for use on underbridges, in addition to derailment kerbs or deflection barriers, to form part of the derailment control system. Guard rails must not be used as the only derailment control device on underbridges. In other locations, including on approach to underbridges, guard rails may be used as the only form of derailment control if deemed sufficient. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 6

5 Guard rails shall only be used in conjunction with type approved concrete sleepers, or a form of direct fix track. Guard rails must be suitably insulated to suit the requirements of the signalling and electrical infrastructure in which they are located. Alternative systems which can provide the same functionality and performance as guard rails but are more suitable to a certain track system (such as a concrete kerb in conjunction with direct fix track), may be suitable subject to acceptance by MTM Head of Engineering Track and Structures. 6.2 Technical Requirements The designer shall provide design drawings to detail the installation extents and setout requirements to provide sufficient protection of the identified hazard. The Design shall be accepted by MTM Engineering prior to installation Guard Rail Assembly New guard rail assemblies shall use type approved equipment and the design shall demonstrate compliance with the following requirements: Each guard rail assembly shall consist of a guard rail nose set connected to two guard rails located between the running rails. A single guard rail is not deemed adequate; For bi-directional train running, a guard rail nose set shall be installed at each end of the guard rail installation. For uni-directional train running, a guard rail nose set shall be installed on the approach side of the guard rail installation; Guard rail shall be new rail manufactured to AS , or recycled rail subject to testing and prior acceptance by the MTM Head of Engineering Track and Structures; Guard rail section shall be the same as the running rail, or no greater than one section size less; The top of the guard rail shall be no higher than the adjacent running rail and no more than 50mm below the running rail; The minimum clear width between the guard rail and the running rail (face to face) shall be 380mm (+20/-0), measured 16mm below the top of rail; Guard rail size shall be consistent throughout the length of any installation; Guard rail section shall be secured at each sleeper (or equivalent spacing on direct fix track forms); The guard rail nose shall be splayed at 30 degrees to the track centreline and form a point at the centreline of the track which would not act to obstruct a derailed wheel, but guide it towards the running rail; Guard rails shall be fastened using a type approved assembly. If pandrol e-clip fastenings are adopted, left and right hand clips shall be alternated longitudinally to reduce the risk of a derailed train dislodging consecutive clips, and PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 6

6 Guard rails shall be connected by bolted joints consisting of 4 hole fishplates as a minimum. They shall be installed in accordance with the bolted rail requirements detailed in MTPR Welded Track Management Manual Chapter 8 Laying Rail Bolted, Welded and LWR, subject to the following specific amendments: o o o Positioning of Guard Rails 4 hole joints are considered sufficient for use on all guard rail sizes; The diameter of the holes in the rail shall be increased from 30mm to 31mm. Fishplate hole sizes are to remain to standard, and The heads of all bolts within a joint shall be to the outside of the guard rail (nearest to the running rail), to reduce the risk of damage by a derailed train; The design of the guard rail position must provide adequate protection for the extent of the identified hazard. Guard rails shall extend for the full length of the hazard they are intended to protect and beyond the hazard by a minimum distance of 20 metres. On uni-directional and bi-directional tracks, they shall extend in front of the hazard they are protecting, by the greater value of: The distance a train can travel in 2.5 seconds at maximum line speed, or 20 metres. Guard rail nose assemblies may be installed on curved track with a radius of 800m or greater. If the radius is less than 800m, guard rails must be extended into tangent track, unless otherwise agreed by the MTM Head of Engineering Track and Structures Guard rail nose assemblies must not be located on or within the following: Cant transitions; Level / Pedestrian crossings; Hi-rail access pads, and Turnouts and crossing work Signalling and Electrical Requirements The design must provide details for the insulation requirements identified by the signalling and electrical engineers. As a minimum, where any part of the guard rail is in a track circuited area or adjacent to a TPWS aerial, a single insulated joint shall be installed between the guard rail nose assembly and at least one of the adjacent guard rails. Where required, insulated joints shall be type approved assemblies. Where it is necessary to install an insulated joint, it must not replace a bolted joint that is required for expansion. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 6

MTST TRACK DESIGN AND CONSTRUCTION

MTST TRACK DESIGN AND CONSTRUCTION Engineering Standard Track and Civil Version: 2 Issued: November 2016 Owner: Chief Engineer Approved By: Phil Ellingworth Chief Engineer PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE

More information

MTSP MANUFACTURE AND SUPPLY OF INSULATED RAIL JOINTS

MTSP MANUFACTURE AND SUPPLY OF INSULATED RAIL JOINTS Engineering Specification Track MANUFACTURE AND SUPPLY OF INSULATED RAIL JOINTS Version: 2 Issued: December 2015 Owner: Engineering Division Approved By: Liam Palmer Cannon A/Head of Engineering Track

More information

TRACK SPECIFICATION LOW PROFILE CONCRETE SLEEPERS

TRACK SPECIFICATION LOW PROFILE CONCRETE SLEEPERS Approval Amendment Record Approval Date Version Description 19/04/2013 1 Initial issue under MTM. 19/02/2014 2 Details for Train Stop sleepers added and figures updated 27/04/2015 3 Amended the design

More information

L1-CHE-STD-040 BRIDGE STANDARD

L1-CHE-STD-040 BRIDGE STANDARD Engineering Standard L1-CHE-STD-040 Version: 2 Approval Amendment Record Approval Date Version Description 22/12/2017 1 Initial issue under MTM. Supersedes VRIOGS 011.1 (draft), L1-CHE-INS-013, L1-CHE-INS-026,

More information

Switches and Crossings

Switches and Crossings Switches and Crossings Synopsis This document sets out general requirements for the design, inspection and maintenance of switches and crossings (S&C). It also defines particular requirements for fixed

More information

Concrete Sleepers - Design

Concrete Sleepers - Design Division / Business Unit: Function: Document Type: Enterprise Services Track & Civil Standard Concrete Sleepers - Design Applicability ARTC Network Wide SMS Publication Requirement Internal / External

More information

SUPPLY OF RESILIENT RAIL FASTENING ASSEMBLIES. MTSP L2-TRK-SPE-004 Version: 4 Effective from: 27 th April Approval.

SUPPLY OF RESILIENT RAIL FASTENING ASSEMBLIES. MTSP L2-TRK-SPE-004 Version: 4 Effective from: 27 th April Approval. Approval Amendment Record Approval Date Version Description 20/05/2013 1 Initial issue under MTM. 02/08/2013 2 Alterations made to the maximum allowable axle load and line speed. Amendments added to include

More information

Rerailing and Anchoring

Rerailing and Anchoring Discipline: Engineering (Track & Civil) Category: Standard Rerailing and Anchoring ETM-01-03 Applicability New South Wales Primary Source ARTC NSW Standard TMP 16, TMP 08 Document Status Version Date Reviewed

More information

Rail Track Material. Steel Rails and Trak-Lok Steel Sleeper Systems. MEMBER OF

Rail Track Material. Steel Rails and Trak-Lok Steel Sleeper Systems.   MEMBER OF Rail Track Material Steel Rails and Trak-Lok Steel Sleeper Systems www.libertyonesteel.com MEMBER OF Liberty OneSteel has significant experience and expertise in the production of steel rail and steel

More information

T-39 Thriebeam. Product Manual. NCHRP 350 Test Level 3 & 4 Compliant Barrier. Release 01/11

T-39 Thriebeam.  Product Manual. NCHRP 350 Test Level 3 & 4 Compliant Barrier. Release 01/11 T-39 Thriebeam NCHRP 350 Test Level 3 & 4 Compliant Barrier Product Manual T-39 is licensed to Ingal Civil Products by Trinity Industries Inc. of the U.S.A. www.ingalcivil.com.au T-39 Thriebeam NCHRP 350

More information

Structural - Engineering Review Checklist

Structural - Engineering Review Checklist Structural - Engineering Review Checklist Project: List Corridor Criteria ID Review Priority (H,M,L) TOPICS S-_-## Structural Design Codes, Manuals and Specifications 6.1.0 REFERENCES DESIRED Criteria

More information

Flexbeam Guardrail Roadside Safety Barrier

Flexbeam Guardrail Roadside Safety Barrier Flexbeam Guardrail Roadside Safety Barrier Product Manual Release 09/15 www.ingalcivil.com.au Flexbeam Guardrail Roadside Safety Barrier 1.0 Introduction Roadside barriers have been developed over the

More information

PARAPET STANDARD & SPECIFICATION UPDATES

PARAPET STANDARD & SPECIFICATION UPDATES PARAPET STANDARD & SPECIFICATION UPDATES Richard Bowen Engineering Inspector National Roads Authority National Roads Authority Standards Section Training for New Developments April 2013 Context Presentation

More information

Use of Resilient Fastenings

Use of Resilient Fastenings Discipline: Engineering (Track & Civil) Category: Standard Use of Resilient Fastenings ETF-02-01 Applicability New South Wales CRIA (NSW CRN) Primary Source ARTC NSW Standard TCS 06, TCS 07, TCS 08 Document

More information

L1-CHE-STD-067 SIGNALLING PRINCIPLES - AXLE COUNTER APPLICATION

L1-CHE-STD-067 SIGNALLING PRINCIPLES - AXLE COUNTER APPLICATION Engineering Standard Signalling L1-CHE-STD-067 SIGNALLING PRINCIPLES - AXLE COUNTER APPLICATION Version: 1 ENGINEERING STANDARD SIGNALLING PRINCIPLES - AXLE COUNTER APPLICATION L1-CHE-STD-067 Version:

More information

Earthworks & Formation Standard

Earthworks & Formation Standard Engineering Standard Track and Structures Earthworks & Formation Standard Version: 2 Issued: December 2017 Owner: Chief Engineer Approved By: Phil Ellingworth Chief Engineer PRINTOUT MAY NOT BE UP-TO-DATE;

More information

Electrical Networks Principles and Performance

Electrical Networks Principles and Performance Engineering Standard Electrical Networks Electrical Networks Principles and Performance Version: 1 Issued: January 2015 Owner: Chief Engineer Approved By: Paul O Halloran Chief Engineer PRINTOUT MAY NOT

More information

Version # Date Reviewed Prepared by Reviewed by Endorsed Approved. Description of Amendment

Version # Date Reviewed Prepared by Reviewed by Endorsed Approved. Description of Amendment Division / Business Unit: Enterprise Services Function: Engineering (Track & Civil) Document Type: Code of Practice General Appendix Structures Inventory Applicability ARTC Network Wide SMS Publication

More information

URBAN TRACK Final Conference Alternative to Floating Track Slab High Attenuation Sleeper. Presented by Ian Robertson, ALSTOM 24 June 2010, Prague

URBAN TRACK Final Conference Alternative to Floating Track Slab High Attenuation Sleeper. Presented by Ian Robertson, ALSTOM 24 June 2010, Prague URBAN TRACK Final Conference Alternative to Floating Track Slab High Attenuation Sleeper Presented by Ian Robertson, ALSTOM 24 June 2010, Prague Contents Specific objectives of study Chosen concept Detailed

More information

MTM REQUIREMENTS METROPOLITAN TRAIN MAINTENANCE DEPOT

MTM REQUIREMENTS METROPOLITAN TRAIN MAINTENANCE DEPOT Approval Amendment Records Approval Date Version Description 14/11/2011 1 Initial Version Disclaimer Metro Trains Melbourne makes no warranties, express or implied, that compliance with the contents of

More information

B STEEL BEAM GUIDE RAIL - OPSS 721

B STEEL BEAM GUIDE RAIL - OPSS 721 B721-2 - - OPSS 721 721-2.1 GENERAL Design guidance and a description of Steel Beam Guide Rail systems, including various types and treatments, are provided in the Roadside Design Manual (RDM). 721-2.2

More information

Sleepers and Fastenings

Sleepers and Fastenings Division / Business Unit: Function: Document Type: Enterprise Services Track & Civil Code of Practice Sleepers and Fastenings Applicability ARTC Network Wide SMS Publication Requirement Internal / External

More information

Monoline. Mid barrier Installation manual. Leverandør: Vik: 6893 Vik i Sogn. Ørsta: Skorgeura 6150 Ørsta

Monoline. Mid barrier Installation manual. Leverandør: Vik: 6893 Vik i Sogn. Ørsta: Skorgeura 6150 Ørsta Mid barrier Installation manual Leverandør: Vik: 6893 Vik i Sogn Tlf: +47 57 69 86 50 Faks: +47 57 69 86 60 firmapost@vikorsta.no Ørsta: Skorgeura 6150 Ørsta Tlf: +47 70 04 70 00 Faks: +47 70 04 70 04

More information

MTM REQUIREMENTS SPARES FOR NEW ASSETS

MTM REQUIREMENTS SPARES FOR NEW ASSETS MTM REQUIREMENTS L1-CHE-STD-006 Version: 1 Effective from: 14 th November 2011 Approval Amendment Record Approval Date Version Description 14/11/2011 1 Initial Version Disclaimer Metro Trains Melbourne

More information

Guide for the application of the CR INF TSI

Guide for the application of the CR INF TSI European Railway Agency According to Framework Mandate C(2007)3371 final of 13/07/2007 Reference in ERA: ERA/GUI/07-2011/INT Version in ERA: 1. 00 Date: 26 August 2011 Document elaborated by Document Type:

More information

Sieve Size 2" 1" 3/8" No. 10 No. 40 No. 200 % Passing Size

Sieve Size 2 1 3/8 No. 10 No. 40 No. 200 % Passing Size VII. MATERIALS 7.01 SUBBALLAST Subballast shall be crusher-run stone (dense graded aggregate), preferably limestone or granite material and shall meet the requirements as set out in Chapter 1, Part 2,

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM Turnouts and Yard Tracks TM 2.1.8 Prepared by: Signed document on file 21 June 09 George Harris Date Checked by: Signed document on file 15 July 09 Thomas Carroll Date Approved by:

More information

City of St. Catharines Standard Drawings JULY Revised July 21, 2017 TES-ENG (SH)

City of St. Catharines Standard Drawings JULY Revised July 21, 2017 TES-ENG (SH) City of St. Catharines Standard Drawings JULY 2017 Revised July 21, 2017 TES-ENG (SH) Roads Dwg No. Revision Standard Sidewalk Detail 110-2001 1 Monolithic Curb-Faced Sidewalk for Concrete Road 110-2002

More information

March 3, Addendum No. 1

March 3, Addendum No. 1 March 3, 2017 Addendum No. 1 North Branch Riverwalk: Underbridge Connection at Addison Street from Clark Park to California Park CDOT Project No. E-9-121 Specification No. 133860 For which proposals will

More information

System DFF 21. Highly elastic rail fastening for conventional rail and metro the optimum single support point for slab track

System DFF 21. Highly elastic rail fastening for conventional rail and metro the optimum single support point for slab track System DFF 21 Highly elastic rail fastening for conventional rail and metro the optimum single support point for slab track System DFF 21 Highly elastic rail fastening for conventional rail and metro the

More information

B STEEL BEAM GUIDE RAIL - OPSS 552

B STEEL BEAM GUIDE RAIL - OPSS 552 B552-2 - - OPSS 552 552-2.1 GENERAL Steel Beam Guide Rail (SBGR) is a semi-rigid barrier system which restrains and redirects vehicles by a combination of beam bending (W-shaped steel section), tension,

More information

B STEEL BEAM GUIDE RAIL - OPSS 721

B STEEL BEAM GUIDE RAIL - OPSS 721 B721-2 - - OPSS 721 721-2.1 GENERAL Steel Beam Guide Rail (SBGR) is a semi-rigid barrier system which restrains and redirects vehicles by a combination of beam bending (W-shaped steel section), tension,

More information

BLACK RIVER RAILROAD SYSTEM 2015 TRACK STANDARDS & SPECIFICATIONS

BLACK RIVER RAILROAD SYSTEM 2015 TRACK STANDARDS & SPECIFICATIONS WOOD TIES 2015 TRACK STANDARDS & SPECIFICATIONS FOR NEW CONSTRUCTION & UPGRADES Ties shall be new 7"x 9" x 8' 6" creosoted grade hardwood. All new ties shall be spiked with four (4) new spikes and box

More information

MTM REQUIREMENTS METROPOLITAN TRAIN STABLING

MTM REQUIREMENTS METROPOLITAN TRAIN STABLING Approval Amendment Record Approval Date Version Description 14/11/2011 1 Initial Version. Disclaimer Metro Trains Melbourne makes no warranties, express or implied, that compliance with the contents of

More information

Interfacing Road Safety Cameras (Red light) with Level Crossing Equipment

Interfacing Road Safety Cameras (Red light) with Level Crossing Equipment Engineering Specification Signalling L1-CHE-SPE-040 Interfacing Road Safety Cameras (Red light) with Level Crossing Equipment Version: 1 Issued: December 2016 Owner: Engineering Approved By: Phil Ellingworth

More information

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2)

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2) Installation Manual Orion TL-3 Steel Barrier VHD (v2) 300914 Table of Contents Orion Introduction.......... 3 Limitations & Warnings. 4 Before Installation..... 3 System Design & Design Considerations

More information

The Design of Vehicle and Pedestrian Parapets

The Design of Vehicle and Pedestrian Parapets The Design of Vehicle and Pedestrian Parapets DN-STR-03011 January 2016 DN Design Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible

More information

Railway technology. PhD CE Jarosław Zwolski. 1. Technology of building a new line. 2. Track geometry measurement. 3. Maintenance and auxiliary works

Railway technology. PhD CE Jarosław Zwolski. 1. Technology of building a new line. 2. Track geometry measurement. 3. Maintenance and auxiliary works Railway technology 1. Technology of building a new line 2. Track geometry measurement 3. Maintenance and auxiliary works 4. Existing lines modernization PhD CE Jarosław Zwolski sleepers spacing rail ballast

More information

RRB TECHNICAL EXAM PAPER. Railway Engineering

RRB TECHNICAL EXAM PAPER. Railway Engineering RRB TECHNICAL EXAM PAPER Railway Engineering 1. The bent-up length of rail used in front of nose of crossing which help in channelising the train wheels in their proper routes are known as: (a) lead rail

More information

Specification for Road Works Series Road Restraints Systems (Vehicle and Pedestrian)

Specification for Road Works Series Road Restraints Systems (Vehicle and Pedestrian) Specification for Road Works Series 400 - Road Restraints Systems (Vehicle and Pedestrian) CC-SPW-00400 March 2013 CC Construction & Commissioning Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS

More information

B STEEL BEAM GUIDE RAIL - OPSS 721

B STEEL BEAM GUIDE RAIL - OPSS 721 B721-2 - - OPSS 721 721-2.1 GENERAL Steel Beam Guide Rail (SBGR) is a semi-rigid barrier system which restrains and redirects vehicles by a combination of beam bending (W-shaped steel section), tension,

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 092216 - NON-STRUCTURAL METAL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

STANDARD WAIVER PROCEDURE

STANDARD WAIVER PROCEDURE Engineering Procedure Chief Engineer L1-CHE-PRO-001 STANDARD WAIVER PROCEDURE Version: 2 Issued: September 2012 Owner: Chief Engineer Approved By: Norm Grady Chief Engineer Authorise For Use By: Norm Grady

More information

GURU GHASIDAS VISHWAVIDYALAYA, BILASPUR (C.G.) INSTITUTE OF TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING B.TECH

GURU GHASIDAS VISHWAVIDYALAYA, BILASPUR (C.G.) INSTITUTE OF TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING B.TECH GURU GHASIDAS VISHWAVIDYALAYA, BILASPUR (C.G.) INSTITUTE OF TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING B.TECH 3 rd YEAR, V th SEMESTER SUBJECT: TRANSPORTATION ENGINEERING-II COURSE CODE: 31CE05T MAXIMUM

More information

TRAFFIC DIRECTION FOR RAIL LAP AS SHOWN (SEE NOTE 7) "SPLICE BOLT" WITH NUT MIDWEST GUARDRAIL SYSTEM (STANDARD AND REDUCED POST SPACING)

TRAFFIC DIRECTION FOR RAIL LAP AS SHOWN (SEE NOTE 7) SPLICE BOLT WITH NUT MIDWEST GUARDRAIL SYSTEM (STANDARD AND REDUCED POST SPACING) TRAFFIC DIRECTION FOR RAIL LAP AS SHOWN GR-MGS1, 1A (SEE NOTE 7) NOTES: 1. 2. 3. 4. 5. 6. 236 6'-3" 6'-3" 3'-1 " 3'-1 " 3'-1 " 3'-1 " GR-MGS1 (6'-3" POST SPACING) SPLICE DETAIL W-BEAM RAIL SPLICE MID-SPAN

More information

B STEEL BEAM GUIDE RAIL - OPSS.PROV 721

B STEEL BEAM GUIDE RAIL - OPSS.PROV 721 B721-2 - - OPSS.PROV 721 721-2.1 GENERAL Steel beam guide rail (SBGR) is a semi-rigid barrier system which restrains and redirects vehicles by a combination of beam bending (W-shaped steel section), tension,

More information

Network Safeworking Rules and Procedures

Network Safeworking Rules and Procedures Network Safeworking Rules and Procedures Track Occupancy Authority Rule Number: 3005 Version 1.02, 1 April 2017 Track Occupancy Authority Rule Number: 3005 Document Control Identification Document title

More information

tracks for building maintenance units (BMU)

tracks for building maintenance units (BMU) 1/11 A track at roof level is required to allow the machine to traverse. Two different types of track may be considered: one in concrete and the other with two metal rails. 1. Concrete track During the

More information

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection

More information

Safeline Road railing

Safeline Road railing Safeline Road railing Safeline One-sided Tube formed guardrail Installation manual Installer: Vik: 6893 Vik i Sogn Tlf: +47 57 69 86 50 Faks: +47 57 69 86 60 firmapost@vikorsta.no Ørsta: Skorgeura 6150

More information

PART 920 CONSTRUCTION OF TRAM TRACKS

PART 920 CONSTRUCTION OF TRAM TRACKS PART 920 CONSTRUCTION OF TRAM TRACKS CONTENTS 1. General 2. Removal of Existing Track Work 3. Track Construction 4. Turnouts 5. Stray Current Control 6. Bonds 7. Tamping 8. Buffers 9. Signalling 10. Testing

More information

VIGNOLE TURNOUT SYSTEMS INNOVATIVE WEICHENSYSTEME

VIGNOLE TURNOUT SYSTEMS INNOVATIVE WEICHENSYSTEME IMG_VAE VIG_VAE _2 VIGNOLE TURNOUT SYSTEMS INNOVATIVE WEICHENSYSTEME voestalpine VAE Führend bei Weichen und Signaltechnik Efficient turnouts for standard- and non standard-gauge railways and metros voestalpine

More information

Code Compliance Research Report CCRR-0238

Code Compliance Research Report CCRR-0238 Code Compliance Research Report CCRR-0238 Issue Date: 11-09-2016 Revision Date: 11-29-2018 Renewal Date: 11-09-2019 DIVISION: 05 00 00 METALS Section: 05 52 00 Metal Railings CPG Building Products LLC

More information

Key Words Longitudinal sleeper, Ladder sleeper, Ladder track, Ballasted track, Continuously welded rail, Track Buckling, Lateral stability

Key Words Longitudinal sleeper, Ladder sleeper, Ladder track, Ballasted track, Continuously welded rail, Track Buckling, Lateral stability Lateral Stability Analysis of Ladder Sleeper Track Systems By Ernest J. Barenberg Professor Emeritus-Civil Engineering University of Illinois 205 N. Mathews; Urbana, Illinois 61801, U.S.A. Tel. 217-333-6252;

More information

Design Aid for Barrier-Free Accessibility in Existing Buildings

Design Aid for Barrier-Free Accessibility in Existing Buildings Design Aid for Barrier-Free Accessibility in Existing Buildings July 9, 2004 Table of Contents 1. Introduction 1 2. References 2 3. Access to the Building 2.1 Site Accessibility 2 4. Building Access 3.1

More information

Draft. Not yet Approved. American Railway Engineering and Maintenance of Way Association Letter Ballot

Draft. Not yet Approved. American Railway Engineering and Maintenance of Way Association Letter Ballot American Railway Engineering and Maintenance of Way Association Letter Ballot 1. Committee and Subcommittee: Committee 4 Subcommittee 6 2. Letter Ballot Number: 04-17-03 3. Assignment: For Board Approval

More information

Vehicle Impact Barriers for Elevated Structures

Vehicle Impact Barriers for Elevated Structures technical notes CAR IMPACT BARRIERS FOR ELEVATED STRUCTURES Wheel stops should not be relied upon to prevent cars falling off elevated structures. Impact barriers must be provided. Impact barriers must

More information

The Design of Road Bridge Parapets

The Design of Road Bridge Parapets Volume 2 Section 3 Part 3 NRA BD 52/07 The Design of Road Bridge Parapets April 2007 St. Martin s House, Waterloo Road, Dublin 4. Tel:+353 1 660 2511 Fax +353 1 668 0009 Email : info@nra.ie Web : www.nra.ie

More information

Status Date Prepared Reviewed Endorsed Approved

Status Date Prepared Reviewed Endorsed Approved Discipline Engineering Standard NSW Category Bridges and Structures Title Safety Refuges and Handrail Devices for Trackside Structures Reference Number BSS 01 (RIC Standard: C 4010) Document Control Status

More information

innostrail - installation instructions Subject to technical changes / January 2010 STRAIL level crossing systems & STRAILastic track damping systems

innostrail - installation instructions Subject to technical changes / January 2010 STRAIL level crossing systems & STRAILastic track damping systems innostrail - installation instructions Subject to technical changes / January 2010 STRAIL level crossing systems & STRAILastic track damping systems gummiwerk kraiburg elastik gmbh / D-84529 Tittmoning

More information

THE SASKATCHEWAN CODES OF PRACTICE GAS INSTALLATION SUPPLEMENT CSA-B PROPANE STORAGE AND HANDLING CODE

THE SASKATCHEWAN CODES OF PRACTICE GAS INSTALLATION SUPPLEMENT CSA-B PROPANE STORAGE AND HANDLING CODE THE SASKATCHEWAN CODES OF PRACTICE GAS INSTALLATION SUPPLEMENT CSA-B149.2-15 PROPANE STORAGE AND HANDLING CODE Revision Date: CONTENTS The following clauses have been amended, noted, explained or added

More information

MAINTENANCE OF TRACK GAUGE GUIDELINES. Produced by Civil Engineering Conference For use by all railway civil engineering staff

MAINTENANCE OF TRACK GAUGE GUIDELINES. Produced by Civil Engineering Conference For use by all railway civil engineering staff MAINTENANCE OF TRACK GAUGE GUIDELINES Produced by Civil Engineering Conference For use by all railway civil engineering staff CEC/DG/005 Issue 1 January 2001 Note These guidelines have been produced for

More information

Sport Systems Canada Inc. Section Angle Framed Bleachers Page 1

Sport Systems Canada Inc. Section Angle Framed Bleachers Page 1 Page 1 Part 1 GENERAL.1.1 Section Includes.1 Design, fabrication, engineering, and installation of continuous angle framed bleacher assembly, including the following:.1 Foundations.2 Galvanized steel framing

More information

TRACK TOLERANCES NEETHU NARAYANAN B060128CE MURSHID B060471CE

TRACK TOLERANCES NEETHU NARAYANAN B060128CE MURSHID B060471CE TRACK TOLERANCES NEETHU NARAYANAN B060128CE MURSHID B060471CE 1 Introduction The safety and comfort of rail travel depend primarily on the track geometry and the standard to which it has been maintained.

More information

INSTALLATION & MAINTENANCE NOTES FOR POLYSAFE LEVEL CROSSINGS

INSTALLATION & MAINTENANCE NOTES FOR POLYSAFE LEVEL CROSSINGS INSTALLATION & MAINTENANCE NOTES FOR POLYSAFE LEVEL CROSSINGS Pre-Installation Preparation It is essential that the following steps be undertaken to ensure a satisfactory installation. 1) Put trackwork

More information

VIK Veg H2. A profile barrier with w shaped backside beam, installed on Sigma posts Installation manual. Vik: 6893 Vik i Sogn

VIK Veg H2. A profile barrier with w shaped backside beam, installed on Sigma posts Installation manual. Vik: 6893 Vik i Sogn VIK Veg H2 A profile barrier with w shaped backside beam, installed on Sigma posts Installation manual Leverandør: Vik: 6893 Vik i Sogn Tlf: +47 57 69 86 50 Faks: +47 57 69 86 60 firmapost@vikorsta.no

More information

SAFETY ACCESSORIES. Accessories can help you to enhance safety in your warehouse

SAFETY ACCESSORIES. Accessories can help you to enhance safety in your warehouse SAFETY ACCESSORIES Accessories can help you to enhance safety in your warehouse Safety Accessories PROTECTORS Ensuring your warehouse is safe and complies with the latest legislation is critical. CSI

More information

Pedestrian Restraint Systems Bridge Rail

Pedestrian Restraint Systems Bridge Rail Pedestrian Restraint Systems Bridge Rail CONTAINMENT MDS TL5 H4a /W4 Pedestrian Restraint Systems Page 1 Pedestrian Guardrails PG1A Clear Vision Pedestrian Guardrails Pedestrian Guardrails - are used to

More information

SHERIDAN SEATING INC.

SHERIDAN SEATING INC. SHERIDAN SEATING INC. THEATER PLATFORM SEATING SPECIFICATIONS PART 1 GENERAL 1.1 Description A. Scope 1. Telescopic platform systems comprised of multi-tiered rows of seats, deck components and risers

More information

GB Requirements for Platform Height, Platform Offset and Platform Width

GB Requirements for Platform Height, Platform Offset and Platform Width GB Requirements for Platform Height, Platform Offset and Platform Width Synopsis This document sets out Great Britain (GB) requirements in scope of National Technical Rules for platform height, platform

More information

Recommendations for the Design of Bridges

Recommendations for the Design of Bridges Recommendations for the Design of Bridges Synopsis This Railway Group Approved Code of Practice gives recommendations for the design and loading for bridges. It supports Railway Group Standards GC/RT5112

More information

Introduction 2 The Guidance Existing Buildings Technical Specifications Materials and Workmanship Interpretation. Part K : The Requirement 3

Introduction 2 The Guidance Existing Buildings Technical Specifications Materials and Workmanship Interpretation. Part K : The Requirement 3 Contents Page Introduction 2 The Guidance Existing Buildings Technical Specifications Materials and Workmanship Interpretation Part K : The Requirement 3 Section 1 STAIRWAYS, LADDERS AND RAMPS 4 Introduction

More information

MCST METROPOLITAN RAILWAY STATIONS

MCST METROPOLITAN RAILWAY STATIONS Engineering Standard Structures and Facilities Version: 3 Issued: December 2016 Owner: Chief Engineer Approved By: Phil Ellingworth Chief Engineer PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET

More information

RAMSHIELD. New Zealand Edition. Product & Installation Manual. MASH TL3 Compliant W-Beam Barrier. Ref: PM 023/0

RAMSHIELD. New Zealand Edition. Product & Installation Manual. MASH TL3 Compliant W-Beam Barrier. Ref: PM 023/0 RAMSHIELD MASH TL3 Compliant W-Beam Barrier Product & Installation Manual New Zealand Edition Ref: PM 023/0 Table of Contents 1.0 Introduction... 5 2.0 Specifications... 5 3.0 How RAMSHIELD Works... 6

More information

Code Compliance Research Report CCRR-0238

Code Compliance Research Report CCRR-0238 Code Compliance Research Report CCRR-0238 Issued: 11-09-2016 Renewal Due: 11-09-2018 Revised: 11-10-2017 DIVISION: 05 00 00 METALS Section: 05 52 00 Metal Railings CPG Building Products LLC 894 Prairie

More information

PRODUCT SPECIFICATION

PRODUCT SPECIFICATION PRODUCT SPECIFICATION Part Name: PLASTICADE Modular Glare Screen System Description The Modular Glare Screen System is intended to be mounted to a barrier or median in order to delineate the barrier and

More information

Chapter 4 Bridge Program Drawings

Chapter 4 Bridge Program Drawings Chapter 4 Bridge Program Drawings Section 4.10-Bridge Railing Introduction Steel bridge railing and concrete bridge barrier rail are installed along the edge of the bridge roadway to keep errant vehicles

More information

Technical Memorandum: Road Safety Hardware Series. technical memorandum

Technical Memorandum: Road Safety Hardware Series. technical memorandum technical memorandum road safety hardware series Frequently Asked Questions - Barriers & Terminals TM-2000 October 2012 Purpose To provide a list of frequently asked questions with answers in regard to

More information

Standard Work Instruction Sheet

Standard Work Instruction Sheet STANDARD WORK METHOD Standard Work Instruction Sheet SWIS ID RA ID SOP.0738.01.SHE.Stockbay Inspection Stockbays:- Inspection Procedure Description: Stockbay Walls:- Visual Inspection Procedure (Various

More information

AS THE EFFECT ON BRIDGE BARRIERS

AS THE EFFECT ON BRIDGE BARRIERS ABSTRACT AS5100.2 2017 THE EFFECT ON BRIDGE BARRIERS David Coe, Senior Principal, Pitt & Sherry The revision to AS5100 in 2017 resulted in significant changes to the design loading and impact heights for

More information

2004 Specifications CSJ SPECIAL SPECIFICATION DIRECT FIXATION TRACK CONSTRUCTION

2004 Specifications CSJ SPECIAL SPECIFICATION DIRECT FIXATION TRACK CONSTRUCTION 2004 Specifications CSJ 0920-38-250 SPECIAL SPECIFICATION 7660 DIRECT FIXATION TRACK CONSTRUCTION 1. Description. This section specifies the construction of direct fixation (DF) track to the lines and

More information

10. Transportation Facilities.

10. Transportation Facilities. Last page revision- March 31st, 1999 TEXAS ACCESSIBILITY STANDARDS (TAS) TAS Table of Contents 10. Transportation Facilities. 10.1 General. Every station, bus stop, bus stop pad, terminal, building or

More information

CD 360 Use of Compressive Membrane Action in Bridge Decks

CD 360 Use of Compressive Membrane Action in Bridge Decks Design Manual for Roads and Bridges Highway Structures & Bridges Design CD 360 Use of Compressive Membrane Action in Bridge Decks (formerly BD 81/02) Revision 1 Summary This document provides requirements

More information

SECTION ORNAMENTAL ALUMINUM RAILING

SECTION ORNAMENTAL ALUMINUM RAILING SECTION 05730 ORNAMENTAL ALUMINUM RAILING PART 1 GENERAL 1.1 SECTION INCLUDES A. Aluminum Pipe Railing 1.2 RELATED SECTIONS A. Section 03300 Cast-In-Place Concrete: Placement of sleeves cast in concrete.

More information

ARCHITECTURAL TESTING, Inc. Code Compliance Research Report #0774 CCRR-0100

ARCHITECTURAL TESTING, Inc. Code Compliance Research Report #0774 CCRR-0100 ARCHITECTURAL TESTING, Inc. Code Compliance Research Report #0774 Subject to Renewal: 06/27/09 Date Issued: 06/27/07 Visit for current status Page 1 of 5 Mid Atlantic Vinyl Products, Inc. 5109 Commonwealth

More information

SPECIFICATION FOR TUBULAR STEEL LIGHTING COLUMN. Reference is made in this Specification to the following:

SPECIFICATION FOR TUBULAR STEEL LIGHTING COLUMN. Reference is made in this Specification to the following: SPECIFICATION FOR TUBULAR STEEL LIGHTING COLUMN 1. SCOPE This specification covers the design, fabrication and testing of tubular section, galvanised steel friction fit jointed street light columns of

More information

Guard Rail Standards: Proposed Changes Risk Assessment Report 17 March 2008 Rev 2 M AX S HUARD & ASSOCIATES P TY L TD Guard Rails Report rev 2.doc M AX S HUARD & ASSOCIATES P TY L TD ABN 47 094 481 697

More information

Sheet Pile Retaining Walls Design and Construction in Brown Fields Environment

Sheet Pile Retaining Walls Design and Construction in Brown Fields Environment 8th Australian Small Bridges Conference 2017 Sheet Pile Retaining Walls Design and Construction in Brown Fields Environment Level Crossing Removal Project 1 Burke Road, North Road, McKinnon Road and Centre

More information

BarrierGuard (02) GROUP. a new era in road safety

BarrierGuard (02) GROUP. a new era in road safety BarrierGuard a new era in road safety 800 GROUP (02) 9425 3000 The BarrierGuard 800 a new generation of state-of-the-art design The BarrierGuard 800 heralds a new era in road safety technology. This new

More information

MEJA URJA NIGAM PVT. LIMITED

MEJA URJA NIGAM PVT. LIMITED MEJA URJA NIGAM PVT. LIMITED NAME OF WORK: TENDER AND CONTRACT DOCUMENT FOR Supply of PSC Sleepers, P-Way materials (except rails) including Points & Crossings, Laying and linking of track including Points

More information

ENGINEERING STANDARDS DEVELOPMENT PROCEDURE

ENGINEERING STANDARDS DEVELOPMENT PROCEDURE Approval Amendment Record Approval Date Version Description 21/12/2016 1 Initial Release of MTM Engineering Standards Development Procedure PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE

More information

RECYCLED GLASS SAND SPECIFICATION

RECYCLED GLASS SAND SPECIFICATION Engineering Specification L1-CHE-SPE-313 Version: 1 Approval Amendment Record Approval Date Version Description 02/10/2018 1 Initial issue PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE

More information

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /

More information

Barrier systems on structures

Barrier systems on structures Page B 1 Appendix B Barrier systems on structures In this section Section Page B1 General B 2 B2 Types of barrier system and their applications B 2 B3 Barrier performance selection method B 5 B4 Barrier

More information

PRODUCT RANGE. Quick reference guide. Specialists in Palisade Gates, Barriers, Vehicle and Pedestrian Access.

PRODUCT RANGE. Quick reference guide. Specialists in Palisade Gates, Barriers, Vehicle and Pedestrian Access. GATEWAY STEEL F A B R I C A T I O N S SUB-CONTRACTORS TO THE CONTRACTED INDUSTRY PRODUCT RANGE Quick reference guide Specialists in Palisade Gates, Barriers, Vehicle and Pedestrian Access. Gateway Steel

More information

SOUTH AFRICAN NATIONAL STANDARD

SOUTH AFRICAN NATIONAL STANDARD ISBN 978-0-626-24057-8 SOUTH AFRICAN NATIONAL STANDARD The application of the National Building Regulations Part M: Stairways Published by SABS Standards Division 1 Dr Lategan Road Groenkloof Private Bag

More information

High Voltage Cable Routes

High Voltage Cable Routes Engineering Specification Electrical L1-CHE-SPE-070 High Voltage Cable Routes Version: 2 Issued: October 2017 Owner: Chief Engineer Approved By: Andrew Russack Head of Electrical Engineering PRINTOUT MAY

More information

Changes to the following sections of Tollway Structure Design Manual shall apply:

Changes to the following sections of Tollway Structure Design Manual shall apply: DESIGN BULLETIN No. 18-02 Changes to the following sections of Tollway Structure Design Manual shall apply: 1. Section 7.1.4 Note 25. (Revise to) Horizontal design loads for retaining walls with moment

More information

I 244 Arkansas River LRT Track & Bridge Design Criteria Report

I 244 Arkansas River LRT Track & Bridge Design Criteria Report OKLAHOMA DEPARTMENT OF TRANSPORTATION I 244 Arkansas River LRT Track & Bridge Design Criteria Report Lockwood, Andrews & Newnam, Inc. 7/20/2009 TABLE OF CONTENTS Chapter 1 Track Alignment... 1 1.1 Introduction...

More information

SMART CUSHION INNOVATIONS SCI100GM General Specifications

SMART CUSHION INNOVATIONS SCI100GM General Specifications SMART CUSHION INNOVATIONS SCI100GM General Specifications DESCRIPTION: The SCI100GM is a redirective, non-gating crash attenuator that consists of a base, supporting frames, a sled, side panels, a wire

More information