To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM - Engineering and Operations. From: Juan M. Ulloa, P.E.

Size: px
Start display at page:

Download "To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM - Engineering and Operations. From: Juan M. Ulloa, P.E."

Transcription

1 AGENDA ITEM NO.: 5.C.1 ADMINISTRATIVE REPORT NO.: To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM - Engineering and Operations From: Juan M. Ulloa, P.E. Approved by: /s/ Engineering Supervisor Ronald V. Stassi Interim General Manager Subject: Authorize the General Manager to Award a Contract to California Trenchless Incorporated for the Installation of Approximately 1,700 Feet of 3-6 Inch High Density Polyethylene Conduits Across the Oakland Estuary to Coast Guard Island Via Horizontal Directional Drilling Per Specification No. CS for an Amount Not to Exceed $1,488,850 and Authorize the Interim General Manager to Approve a Contingency Amount Not to Exceed $148,000 for Change Orders RECOMMENDATION By resolution, authorize the Interim General Manager to award a contract to California Trenchless Inc. (CTI) for the installation of approximately 1,700 feet of 3-6 inch High Density Polyethylene (HDPE) conduits across the Oakland Estuary to Coast Guard Island (CGI) via Horizontal Directional Drilling (HDD) including the installation of two high voltage electric vaults, two fiber pull boxes, staging, compliance with regulatory agencies requirements, traffic control, dewatering, shoring, and restoration of the site per Specification No. CS , for an amount not to exceed $1,488,850 and authorize the Interim General Manager to approve a contingency amount not to exceed $148,000 for change orders. Deferral of action on this matter will delay construction on the first phase of this project, the Alameda to CGI Conduit Crossing, from the northern end of Grand Street to CGI athletic field across the Alameda/Oakland Estuary (Estuary). BACKGROUND Alameda Municipal Power (AMP) is responsible for providing electrical service to the City of Alameda, including CGI. Currently, CGI is served by a single radial 12 kilovolt (kv) submarine cable traversing the Estuary between Alameda Island (near the corner of Chestnut Street and Clement Avenue) and CGI (south of Dennison Street). The age of the submarine cable, operational redundancy and desired maintenance capacity for the system have necessitated the construction of a second 12 kv feeder crossing from Grand Street in the Main Island to Spencer Road (near McCulloch Drive) on CGI (Exhibit A). This work is the first phase of a two-phase project that will provide additional capacity to service the customer loads on CGI.

2 AGENDA ITEM NO.: 5.C.2 ADMINISTRATIVE REPORT NO.: The new electrical crossing, consisting of three HDPE conduits, will be installed beneath the Estuary using HDD methods. One conduit will be for a 12kV trunk feeder, a second conduit will remain empty as a spare, and a third conduit will be for the installation of communication cables (e.g., fiber optics). The HDD would occur under the Estuary at a minimum depth of 60 feet below the proposed dredging limits. On September 16, 2013, the Public Utilities Board (Board) adopted the Mitigated Negative Declaration for the Alameda to CGI Conduit Crossing project. And on September 23, 2013 AMP filed the Notice of Determination with the Alameda County Clerk as part of the California Environmental Quality Act (CEQA) process. DISCUSSION Copies of Construction Specification No CS were mailed to four building exchanges. The Notice-to-Bidders was published in the Alameda Journal starting on October 25, 2013 through November 22, A total of 21 copies of the specification were issued to directional drilling contractors. A pre-bid meeting, which was attended by eight contractors, was held on November 6, Three bids were received and opened on November 25, The bids ranged from $1,488,842 to $1,813,553 with an average of $1,629,814 for all bids. The summary of bid results is presented in Exhibit B. Staff carefully analyzed the bids and conducted reference checks on the lowest bidder and its sub-contractor. California Trenchless Inc. of Dublin, California submitted the lowest bid at $1,488,842 and met all of the requirements of the specification. CTI and its sub-contractor, J-C General Engineering, Inc., have 17 years and 30 years respectively of experience in directional drilling. CTI listed several projects in the reference form of equal or greater magnitude in comparison to the Alameda to CGI Crossing. Among its recent accomplishments was the installation of 4,060-LF (linear feet) of 8-inch HDPE conduit for the Central Contra Costa Sanitary District in California; that contract amount was over $2M. After careful evaluation, staff recommends award of a construction contract to CTI which demonstrated a thorough understanding of the project, submitted the lowest bid and provided all of the required documentation. CTI proposes to complete the project by May FINANCIAL IMPACT This project has been previously approved by the Board. The FY 2014 capital budget includes the line item, Install Second Crossing to Coast Guard Island, with $562,000 for contract work. The proposal from CTI came in approximately $926,842 above the Capital Improvement Project (CIP) contract budget. Funding for the overrun amount and the work order contingency amount of up to $148,000 will come from unspent fiscal year 2014 CIP dollars, such as the Replacement of Historic Streetlights project that will not be completed this fiscal year. The remaining funds will come from working capital.

3 AGENDA ITEM NO.: 5.C.3 ADMINISTRATIVE REPORT NO.: LINKS TO BOARD POLICY AND OBJECTIVES Strategy 8: Plan for long-term reliability of utility distribution system assets while ensuring that annual operations and maintenance are implemented. EXHIBITS A. Resolution B. Vicinity Map C. Summary of Bids

4 CITY OF ALAMEDA ALAMEDA MUNICIPAL POWER RESOLUTION NO. AUTHORIZE THE GENERAL MANAGER TO AWARD A CONTRACT TO CALIFORNIA TRENCHLESS INCORPORATED FOR THE INSTALLATION OF APPROXIMATELY 1,700 FEET OF 3-6 INCH HIGH DENSITY POLYETHYLENE CONDUITS ACROSS THE OAKLAND ESTUARY TO COAST GUARD ISLAND VIA HORIZONTAL DIRECTIONAL DRILLING PER SPECIFICATION NO. CS FOR AN AMOUNT NOT TO EXCEED $1,488,850 AND AUTHORIZE THE INTERIM GENERAL MANAGER TO APPROVE A CONTINGENCY AMOUNT NOT TO EXCEED $148,000 FOR CHANGE ORDERS WHEREAS, Specification No. CS , setting requirements for the installation of approximately 1,700 feet of 3-6 inch High Density Polyethylene (HDPE) conduits across the Oakland Estuary via Horizontal Directional Drilling (HDD) was issued on October 25, 2013 for the purpose of obtaining bids; and WHEREAS, Alameda Municipal Power (AMP) received three bids on November 25, 2013, and California Trenchless Inc. submitted the lowest bid of $1,488,842; and WHEREAS, staff has carefully evaluated all proposals and found California Trenchless Inc. s proposal to be complete, responsive and acceptable; and WHEREAS, this project has been previously approved by the Public Utilities Board (Board) as part of the Fiscal Year 2014 Capital Improvement Projects (CIP) and it includes the line item, Install Second Crossing to Coast Guard Island with $562,000 for contract work; and WHEREAS, the estimate from California Trenchless Inc. came in $926,842 above the CIP budget for this line item; and WHEREAS, the additional dollars, including ten percent of the contract amount, or $148,000, for contingency on any unforeseen Change Orders, if needed, will come from unspent fiscal year 2014 CIP dollars, such as the Replacement of Historic Streetlights project that will not be completed this fiscal year, and working capital. NOW, THEREFORE, BE IT RESOLVED that the Public Utilities Board of the City of Alameda hereby awards a contract for the installation of the specified substructures to California Trenchless Inc. for an amount not to exceed $1,488,850, and further authorize the Interim General Manager to sign said contract. BE IT FURTHER RESOLVED, that the Public Utilities Board of the City of Alameda hereby authorize the Interim General Manager to use funds from AMP working capital to cover contingency change orders for an amount not to exceed $148,000 for said contract. Approved as to Form By: Janet C. Kern City Attorney AGENDA ITEM NO: 5.C. EXHIBIT A - Page 1 of 1

5 AGENDA ITEM NO.: 5.C. EXHIBIT B

6 CITY OF ALAMEDA, CALIFORNIA ALAMEDA MUNICIPAL POWER SUMMARY OF BID RESULT (Bid Opening Date: November 25, :00 p.m.) CONTRACT SPECIFICATION NO. CS INSTALLATION OF APPROXIMATELY 1,700-LF OF 3-6" HIGH DENSITY POLYETHYLENE CONDUITS ACROSS THE OAKLAND ESTUARY TO COAST GUARD ISLAND VIA DIRECTIONAL DRILLING BIDDER MICHELS CORPORATION CALIFORNIA TRENCHLESS INC.* THE HDD COMPANY INC. TOTAL CONTRACT COST $1,813,553 $1,488,842 $1,587,047 NUMBER OF DAYS TO COMPLETE BID BOND SUBMITTED YES YES YES * Alameda Municipal Power recommends award of contract to California Trenchless Inc. AGENDA ITEM NO.: 5.C. EXHIBIT C

To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM-Engineering and Operations. From: Juan M. Ulloa Approved by: /s/

To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM-Engineering and Operations. From: Juan M. Ulloa Approved by: /s/ AGENDA ITEM NO.: 4.E.1 MEETING DATE: 02/24/2014 ADMINISTRATIVE REPORT NO.: 2014-44 To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM-Engineering and Operations From: Juan M. Ulloa

More information

REPORT TO MAYOR AND COUNCIL

REPORT TO MAYOR AND COUNCIL AGENDA ITEM NO. 3.i REPORT TO MAYOR AND COUNCIL TO THE HONORABLE MAYOR AND COUNCIL: DATE: July 24, 2012 SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $165,862.60 TO (FUNDED BY: SEWER ENTERPRISE

More information

JEFFREY C. PARKER, CITY MANAGER DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS /CITY ENGINEER

JEFFREY C. PARKER, CITY MANAGER DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS /CITY ENGINEER OW AGENDA REPORT Agenda Item Reviewed. City Manager Finance Director 5 CA MEETING DATE: OCTOBER 16, 2012 TO: JEFFREY C. PARKER, CITY MANAGER FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS /CITY ENGINEER

More information

INITIAL STUDY / DRAFT MITIGATED NEGATIVE DECLARATION

INITIAL STUDY / DRAFT MITIGATED NEGATIVE DECLARATION ALAMEDA TO COAST GUARD ISLAND HDPE CONDUIT CROSSING, ALAMEDA COUNTY INITIAL STUDY / DRAFT MITIGATED NEGATIVE DECLARATION Prepared for Alameda Municipal Power 2000 Grand Street, Alameda CA 94501 July 2013

More information

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT CITY OF ELK GROVE CITY COUNCIL STAFF REPORT AGENDA ITEM NO. 8.11 AGENDA TITLE: MEETING DATE: September 10, 2014 PREPARED BY: Adopt resolution finding the Corporation Yard Expansion Phase 2 Materials Bin

More information

SACRAMENTO AREA SEWER DISTRICT FREEPORT SEPTIC CONVERSION PROJECT CONTRACT NO NOTICE TO CONTRACTORS

SACRAMENTO AREA SEWER DISTRICT FREEPORT SEPTIC CONVERSION PROJECT CONTRACT NO NOTICE TO CONTRACTORS SACRAMENTO AREA SEWER DISTRICT FREEPORT SEPTIC CONVERSION PROJECT CONTRACT NO. 6004 NOTICE TO CONTRACTORS Notice is hereby given that the Board of Directors of Sacramento Area Sewer District of Sacramento

More information

Specification No. FC 6-126

Specification No. FC 6-126 NOTICE TO BIDDERS Specification No. FC 6-126 On May 21, 2013 the Board of Supervisors for the Alameda County Flood Control and Water Conservation District approved the following project for advertisement

More information

Page 1 of 6. Office of the City Manager CONSENT CALENDAR October 18, 2016

Page 1 of 6. Office of the City Manager CONSENT CALENDAR October 18, 2016 Page 1 of 6 Office of the City Manager CONSENT CALENDAR October 18, 2016 To: From: Honorable Mayor and Members of the City Council Dee Williams-Ridley, City Manager Submitted by: Phillip L. Harrington,

More information

FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE: JULY 9, 2007 CMR:251 A:07

FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE: JULY 9, 2007 CMR:251 A:07 TO: HONORABLE CITY COUNCIL FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE: JULY 9, 2007 CMR:251 A:07 SUBJECT: APPROVAL OF A CONTRACT WITH BOND BLACKTOP, INC., IN THE AMOUNT OF $556,812 FOR PHASE 1 AND

More information

City of Grand Island

City of Grand Island City of Grand Island Tuesday, June 08, 2004 Council Session Item G18 #2004-140 - Approving Certificate of Final Completion and Setting Board of Equalization Hearing Date for Street Improvement District

More information

COUNTY OF ALAMEDA PUBLIC WORKS AGENCY

COUNTY OF ALAMEDA PUBLIC WORKS AGENCY COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 399 ElmJHI(st Street Hnyward. CA 94544 -'307 (510) 670-5'~80 AGENDA ITEM NO. July 13,2010 June 29, 2010 Honorable Board of Supervisors County of Alameda 1221 Oak Street,

More information

SACRAMENTO AREA SEWER DISTRICT FREEPORT SEPTIC CONVERSION PROJECT CONTRACT NO. 6004R NOTICE TO CONTRACTORS

SACRAMENTO AREA SEWER DISTRICT FREEPORT SEPTIC CONVERSION PROJECT CONTRACT NO. 6004R NOTICE TO CONTRACTORS SACRAMENTO AREA SEWER DISTRICT FREEPORT SEPTIC CONVERSION PROJECT CONTRACT NO. 6004R NOTICE TO CONTRACTORS Notice is hereby given that the Board of Directors of Sacramento Area Sewer District of Sacramento

More information

Honorable Mayor and Members of the City Council

Honorable Mayor and Members of the City Council Office of the City Manager CONSENT CALENDAR October 15, 2013 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works

More information

REPORT TO MAYOR AND COUNCIL

REPORT TO MAYOR AND COUNCIL AGENDA ITEM NO. 3.f REPORT TO MAYOR AND COUNCIL TO THE HONORABLE MAYOR AND COUNCIL: DATE: April 5, 2011 SUBJECT: AWARD OF CONSTRUCTION CONTRACT IN THE AMOUNT OF $219,556 TO DON GARCIA EXCAVATING AND PAVING,

More information

To: Honorable Public Utilities Board Submitted by: Robert J. Orbeta Assistant General Manager - Administration. From: Chris Low Approved by:

To: Honorable Public Utilities Board Submitted by: Robert J. Orbeta Assistant General Manager - Administration. From: Chris Low Approved by: AGENDA ITEM NO.: 4.G To: Honorable Public Utilities Board Submitted by: Robert J. Orbeta Assistant General Manager - Administration From: Chris Low Approved by: Senior Human Resources Analyst Elizabeth

More information

Tim Tucker, City Engineer Veronica Nebb, Senior Assistant City Attorney Karen Majors, Assistant City Manager Community and Economic Development

Tim Tucker, City Engineer Veronica Nebb, Senior Assistant City Attorney Karen Majors, Assistant City Manager Community and Economic Development CITY OF MARTINEZ CITY COUNCIL AGENDA October 1, 2008 TO: FROM: SUBJECT: DATE: Mayor and City Council Tim Tucker, City Engineer Veronica Nebb, Senior Assistant City Attorney Karen Majors, Assistant City

More information

AGENDA ITEM NO. June 6, 2017

AGENDA ITEM NO. June 6, 2017 DocuSign Envelope ID: 7CA39164-0C90-42A5-B40D-ED361AA88939 AGENDA ITEM NO. June 6, 2017 May 23, 2017 Honorable Board of Supervisors County of Alameda 1221 Oak Street, Suite 536 Oakland, CA 94612-4305 Dear

More information

CITY OF ENCINITAS CITY COUNCIL AGENDA REPORT Meeting Date: May 15, 2013

CITY OF ENCINITAS CITY COUNCIL AGENDA REPORT Meeting Date: May 15, 2013 CITY OF ENCINITAS CITY COUNCIL AGENDA REPORT Meeting Date: May 15, 2013 TO: VIA: FROM: City Council Gus Vina, City Manager Glenn Pruim, Director of Engineering and Public Works Tim Nash, Director of Finance

More information

COMMUNICATIONS NETWORK UPGRADES AT VARIOUS LOCATIONS CITY OF SIOUX FALLS, SOUTH DAKOTA Bid Request No ADDENDUM NO.

COMMUNICATIONS NETWORK UPGRADES AT VARIOUS LOCATIONS CITY OF SIOUX FALLS, SOUTH DAKOTA Bid Request No ADDENDUM NO. COMMUNICATIONS NETWORK UPGRADES AT VARIOUS LOCATIONS CITY OF SIOUX FALLS, SOUTH DAKOTA Bid Request No. 15-1079 2015 CONTRACTOR S BID DATE: PLACE FOR CONTRACTOR S TO SUBMIT BIDS: Thursday, June 25th, 2015,

More information

Honorable Mayor and Members of the City Council. Contract: Andes Construction, Inc. for Sanitary Sewer Rehabilitation Project on Woolsey Street

Honorable Mayor and Members of the City Council. Contract: Andes Construction, Inc. for Sanitary Sewer Rehabilitation Project on Woolsey Street Office of the City Manager CONSENT CALENDAR October 1, 2013 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works

More information

DOCUMENT INVITATION TO BID

DOCUMENT INVITATION TO BID DOCUMENT 00 11 16 INVITATION TO BID 1. Notice is hereby given that the governing board ( Board ) of the Oakland School District ( District or Owner ) will receive sealed bids for the following: Project

More information

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department Peralta Community College District 501 5 th Avenue Oakland, California 94606 Phone (510) 466-7225 Fax (510) 587-7873 Purchasing Department Date: March 30, 2011 ADDENDUM No. 3 BID NO.: 10-11/27 PCCD Smart

More information

AGENDA REPORT. Attachments: 1. Resolution No. 18-R Joint Community Letter Dated April 17, 2018

AGENDA REPORT. Attachments: 1. Resolution No. 18-R Joint Community Letter Dated April 17, 2018 AGENDA REPORT Meeting Date: November 20, 2018 Item Number: E 15 To: From: Honorable Mayor & City Council Vincent Chee, Project Manager Subject: A CONTINUATION OF DECLARATION THAT THE PUBLIC INTEREST AND

More information

REPORT TO MAYOR AND COUNCIL

REPORT TO MAYOR AND COUNCIL AGENDA ITEM NO. 2.b REPORT TO MAYOR AND COUNCIL TO THE HONORABLE MAYOR AND COUNCIL: DATE: January 10, 2012 SUBJECT: ADOPT RESOLUTION NO. 12-1, AUTHORIZING THE CONTRA COSTA COUNTY FLOOD CONTROL & WATER

More information

SPRR TUPELO ST. R UNION CITY BLVD. ZON PADRE PASEO DEEP CREEK ROAD ARDENWOOD COYOTE HILLS REGIONAL PARK PROJECT LIMITS PATTERSON RANCH ROAD BLVD. COMM

SPRR TUPELO ST. R UNION CITY BLVD. ZON PADRE PASEO DEEP CREEK ROAD ARDENWOOD COYOTE HILLS REGIONAL PARK PROJECT LIMITS PATTERSON RANCH ROAD BLVD. COMM SPRR TUPELO ST. R UNION CITY BLVD. ZON PADRE PASEO DEEP CREEK ROAD ARDENWOOD COYOTE HILLS REGIONAL PARK PROJECT LIMITS PATTERSON RANCH ROAD BLVD. COMMERCE DR. PASEO PADRE PARKWAY KAISER DRIVE DUMBARTON

More information

Honorable Mayor and Members of the City Council. Contract: Andes Construction, Inc. for Sanitary Sewer Manhole Rehabilitation FY 2014 Phase 1 Project

Honorable Mayor and Members of the City Council. Contract: Andes Construction, Inc. for Sanitary Sewer Manhole Rehabilitation FY 2014 Phase 1 Project Office of the City Manager CONSENT CALENDAR October 15, 2013 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works

More information

Go Big, Go Fast, Trenchless Emergency Response to the City of Fort Lauderdale. Murphy Pipeline Contractors, Inc.

Go Big, Go Fast, Trenchless Emergency Response to the City of Fort Lauderdale. Murphy Pipeline Contractors, Inc. Go Big, Go Fast, Trenchless Emergency Response to the City of Fort Lauderdale Presentation Outline 1. About the Team 2. Project Background 3. The Challenges 4. Planning & Phasing Trenchless Technologies

More information

CITY AND COUNTY OF SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY INVITATION FOR BIDS. Replacement of Manual Trolley Switch System Phase 1

CITY AND COUNTY OF SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY INVITATION FOR BIDS. Replacement of Manual Trolley Switch System Phase 1 CITY AND COUNTY OF SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY INVITATION FOR BIDS This is an Invitation for Bids (IFB) for the following public work: Replacement of Manual Trolley Switch System Phase

More information

Addendum No. 2. Pre-Bid Meeting Notes and Scope of Work Clarifications

Addendum No. 2. Pre-Bid Meeting Notes and Scope of Work Clarifications Addendum No. 2 Project No. 2016-01EL West Barbour Street 12kV Underground Reconductoring Revisions to Drawings and Specifications Pre-Bid Meeting Notes and Scope of Work Clarifications Replace Section

More information

INFRASTRUCTURE FINANCING PLAN FOR THE WOODGLEN SPECIFIC PLAN

INFRASTRUCTURE FINANCING PLAN FOR THE WOODGLEN SPECIFIC PLAN FINAL REPORT INFRASTRUCTURE FINANCING PLAN FOR THE WOODGLEN SPECIFIC PLAN Prepared for: City of Modesto Prepared by: Willdan Financial Services Approved by Modesto City Council on July 9, 2013 Resolution

More information

COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 99 ';"lmhur~ ~tr> t Ha. ward, A (SlO) 70-5-l,'O

COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 99 ';lmhur~ ~tr> t Ha. ward, A (SlO) 70-5-l,'O FLOOD CONTROL AGENDA ITEM NO. May 24, 20 II COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 99 ';"lmhur~ ~tr> t Ha. ward, A94544-1307 (SlO) 70-5-l,'O April 29, 20 I J The Honorable Board of Supervisors County ofalameda

More information

UTILITIES COMMISSION CITY OF NEW SMYRNA BEACH, FLORIDA 200 CANAL STREET P.O. BOX 100 NEW SMYRNA BEACH, FL

UTILITIES COMMISSION CITY OF NEW SMYRNA BEACH, FLORIDA 200 CANAL STREET P.O. BOX 100 NEW SMYRNA BEACH, FL DATE: January 5, 2018 UTILITIES COMMISSION CITY OF NEW SMYRNA BEACH, FLORIDA 200 CANAL STREET P.O. BOX 100 NEW SMYRNA BEACH, FL 32170-010 ITB# 04-18 REPLACE 12 WATER MAIN AT TURNBULL BAY (DAMAGED DURING

More information

City of Sacramento City Council 915 I Street, Sacramento, CA,

City of Sacramento City Council 915 I Street, Sacramento, CA, City of Sacramento City Council 915 I Street, Sacramento, CA, 95814 www.cityofsacramento.org 8 Meeting Date: 8/14/2012 Report Type: Consent Title: Contract: Tree Pruning and Removal Services Report ID:

More information

BELLBROOK CITY COUNCIL AGENDA August 6, 2018

BELLBROOK CITY COUNCIL AGENDA August 6, 2018 BELLBROOK CITY COUNCIL AGENDA August 6, 2018 6:00 pm-special Meeting 1. Call to Order 2. Pledge of Allegiance 3. Roll Call 4. Resolutions Resolution 2018-Z A Resolution Approving Change Orders and Amending

More information

JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION

JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION FOR PROSPECTIVE SANDAG CONTRACTORS March 2, 2016 1 WELCOME & INTRODUCTIONS 2 AGENDA Overview of Job Order Contracting (JOC) SANDAG s JOC Program SANDAG

More information

REPORT TO MAYOR AND COUNCIL

REPORT TO MAYOR AND COUNCIL Concord REPORT TO MAYOR AND COUNCIL AGENDA ITEM NO. 3 n g TO THE HONORABLE MAYOR AND COUNCIL: DATE: January 26, 200 SUBJECT: AUTHORIZING THE CONTRA COSTA COUNTY FLOOD CONTROL & WATER CONSERVATION DISTRICT

More information

BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR 2014 WATER MAIN AND SEWER MAIN REPLACEMENT IN EASEMENTS

BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR 2014 WATER MAIN AND SEWER MAIN REPLACEMENT IN EASEMENTS BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR 2014 WATER MAIN AND SEWER MAIN REPLACEMENT IN EASEMENTS (Easement 6 & 11, 4200 block of Versailles Avenue and Belclaire Avenue and the 4300 block of Westway

More information

AGENDA ITEM 5. R Meeting August 13, 2014 AGENDA ITEM

AGENDA ITEM 5. R Meeting August 13, 2014 AGENDA ITEM R-14-104 Meeting 14-21 August 13, 2014 AGENDA ITEM AGENDA ITEM 5 Contract for Completion of the McDonald and Sherrill Remediation and Demolition Projects at La Honda Creek Open Space Preserve and Monte

More information

Agenda Item No. 9B February 28, Honorable Mayor and City Council Attention: Laura C. Kuhn, City Manager

Agenda Item No. 9B February 28, Honorable Mayor and City Council Attention: Laura C. Kuhn, City Manager Agenda Item No. 9B February 28, 2012 TO: Honorable Mayor and City Council Attention: Laura C. Kuhn, City Manager FROM: Rod Moresco, Interim Director of Utilities SUBJECT: RESOLUTION AUTHORIZING THE CITY

More information

Honorable Mayor and Members of the City Council. California Energy Commission Loan for Citywide LED Street Light Replacement

Honorable Mayor and Members of the City Council. California Energy Commission Loan for Citywide LED Street Light Replacement Office of the City Manager CONSENT CALENDAR October 29, 2013 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Public Works Director

More information

South Interceptor 3 rd Street Rehabilitation Phase 2

South Interceptor 3 rd Street Rehabilitation Phase 2 South Interceptor 3 rd Street Rehabilitation Phase 2 Planning Committee September 11, 2018 Agenda Background Project Scope Rehabilitation Method Schedule Potential Impacts and Mitigation Community Outreach

More information

Mayor and Members of the City Council through City Manager

Mayor and Members of the City Council through City Manager Agenda Item # 3. G DATE: June 18, 2018 TO: Honorable Mayor and Members of the City Council through City Manager FROM: Dan St. John, F.ASCE Director, Public Works & Utilities Tim Moresco, P. E. Associate

More information

Mustang Substation Bank I Replacement Project MAJ 15-SP5054

Mustang Substation Bank I Replacement Project MAJ 15-SP5054 CALIFORNIA POLYTECHNIC STATE UNIVERSITY FACILITIES PLANNING & CAPITAL PROJECTS San Luis Obispo, CA 93407-0690 p 805/756-2581 f 805.756.7566 http://www.afd.calpoly.edu/facilities/ Mustang Substation Bank

More information

BOARD AGENDA FACT SHEET

BOARD AGENDA FACT SHEET FOR CLERK USE ONLY DISCUSSION BOS ACTION BOARD AGENDA FACT SHEET Public Works Department /Agency October 16, 2012 Requested Board Date 1. Request: Board Approval Other (specify) XX Information Only/Presentation

More information

CONTINUED FROM~c.JkM~ ~#-7Y)

CONTINUED FROM~c.JkM~ ~#-7Y) ~'-;auii. ~r--r!!~ 61 \\ \~~ PUBLIC ~~... WORKS ~.sn:--...':= ources FLOOD CONTROL AGENDA ITEM NO. May 24, 20 II COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 399 Elmhurst Street l-layw.jrd, CA 94544-1307 Cl0)

More information

~E~RLY AGENDA REPORT. Meeting Date: April 11,2013 Item Number:

~E~RLY AGENDA REPORT. Meeting Date: April 11,2013 Item Number: ~E~RLY Meeting Date: April 11,2013 Item Number: To: From: Subject: F li AGENDA REPORT Honorable Mayor & City Council Anne Garvey-Zaworski, Principal Civil Engineer Kevin Watson, Water Operations Manager

More information

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT CITY OF ELK GROVE CITY COUNCIL STAFF REPORT AGENDA ITEM NO. 8.21 AGENDA TITLE: Adopt a resolution dispensing with competitive bidding pursuant to Elk Grove Municipal Code Section 3.42.188(B)(3), and authorizing

More information

Submitted by: Phillip L. Harrington, Director, Department of Public Works. Declaration of Intent - FY 2019 Street Lighting Assessment

Submitted by: Phillip L. Harrington, Director, Department of Public Works. Declaration of Intent - FY 2019 Street Lighting Assessment Page 1 of 16 Office of the City Manager CONSENT CALENDAR April 24, 2018 To: From: Honorable Mayor and Members of the City Council Dee Williams-Ridley, City Manager Submitted by: Phillip L. Harrington,

More information

1 Mountain Cascade, Inc. $2,050, Con-Quest Contractors, Inc. $2,170, Sierra National Construction, Inc. $2,170,300.

1 Mountain Cascade, Inc. $2,050, Con-Quest Contractors, Inc. $2,170, Sierra National Construction, Inc. $2,170,300. Agenda Item No. 9B September 9, 2014 TO: FROM: SUBJECT: Honorable Mayor and City Council Attention: Laura C. Kuhn, City Manager Steven L. Hartwig, Director of Public Works/City Engineer RESOLUTION TO WAIVE

More information

Clay County Utility Authority Utilization of Trenchless Water & Wastewater Pipeline Installation

Clay County Utility Authority Utilization of Trenchless Water & Wastewater Pipeline Installation North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 TA-T2-04 Clay County Utility Authority Utilization of Trenchless Water & Wastewater

More information

6/10/2015 Item #8C Page 1

6/10/2015 Item #8C Page 1 MEETING DATE: June 10, 2015 PREPARED BY: Greg Shields, P.E. Deputy City Engineer DEPT. DIRECTOR: Glenn Pruim, P.E. DEPARTMENT: Public Works CITY MANAGER: Larry Watt, Interim SUBJECT: THE FY2014-15 PAVEMENT

More information

AGENDA REPORT SUMMARY. Reject all bids of the City Hall HVAC System Upgrades, Project CF and re-advertise the project

AGENDA REPORT SUMMARY. Reject all bids of the City Hall HVAC System Upgrades, Project CF and re-advertise the project CONSENT CALENDAR Agenda Item # 6 Meeting Date: June 28, 2016 AGENDA REPORT SUMMARY Prepared by: Reviewed by: Approved by: Aida Fairman, Associate Civil Engineer Susanna Chan, Public Works Director Chris

More information

All Record Holding Contract Documents. This Addendum is issued to all registered plan holders pursuant to the Conditions of the Contract.

All Record Holding Contract Documents. This Addendum is issued to all registered plan holders pursuant to the Conditions of the Contract. 105 W. 2 nd Street Tuscumbia, AL 35674 T (256) 248-7030 F 1-866-225-7488 PROJECT: Rogersville Water Works & Sewer Board Sanitary Sewer System Improvements ADEM CWSRF # CS010862-01 KG Project No. 140026

More information

Subsurface Utility Engineering & Asset Management. American Council of Engineering Companies/Maryland

Subsurface Utility Engineering & Asset Management. American Council of Engineering Companies/Maryland PHI s Underground Use of SUE in Transmission Design Process Subsurface Utility Engineering & Asset Management American Council of Engineering Companies/Maryland Presented by: Pepco Underground Transmission

More information

Contract No Amendment: Conversion Management Associates, Inc. for the Center Street Garage Replacement Project

Contract No Amendment: Conversion Management Associates, Inc. for the Center Street Garage Replacement Project Office of the City Manager CONSENT CALENDAR April 28, 2015 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works Subject:

More information

AGENDA STAFF REPORT. CLERK OF THE BOARD Pending Review COUNTY COUNSEL REVIEW. Approved Agreement to Form. Current Year Cost: NI A

AGENDA STAFF REPORT. CLERK OF THE BOARD Pending Review COUNTY COUNSEL REVIEW. Approved Agreement to Form. Current Year Cost: NI A Agenda Item AGENDA STAFF REPORT ASR Control 16-001333 MEETING DATE: 02/14/ 17 LEGAL ENTITY TAKING ACTION: Board of Supervisors BOARD OF SUPERVISORS DISTRICT(S): 2 SUBMITTING AGENCY/DEPARTMENT: John Wayne

More information

Date March 9, Minutes. Board of Education of the Rocky River City School District RESOLUTIONS. Resolution To Adopt Agenda #

Date March 9, Minutes. Board of Education of the Rocky River City School District RESOLUTIONS. Resolution To Adopt Agenda # Date March 9, 2011 Page RESOLUTIONS Page Resolution To Adopt Agenda #74 11 62 Resolution To Approve Bid For Beach School Administrative Office Relocation Project Technology (Exhibit A) #7511 63 Resolution

More information

COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 399 Elmhurst Street I ayward, CA (510) June 5, 2012

COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 399 Elmhurst Street I ayward, CA (510) June 5, 2012 FLOOD CONTROL AGENDA ITEM NO.: June 19, 2012 COUNTY OF ALAMEDA PUBLIC WORKS AGENCY 399 Elmhurst Street I ayward, CA 94544-1307 (510) 670-54 0 June 5, 2012 The Honorable Board of Supervisors County Administration

More information

Memorandum CITY OF DALLAS. Right-of-Way Management: Proposed Process & Code Revisions

Memorandum CITY OF DALLAS. Right-of-Way Management: Proposed Process & Code Revisions Memorandum DATE March 15, 2019 CITY OF DALLAS TO Honorable Mayor and Members of the City Council SUBJECT Right-of-Way Management: Proposed Process & Code Revisions On Wednesday, March 20, 2019, Robert

More information

7/23/13. CITY OF ALAMEDA Memorandum. Honorable Mayor and Members of the City Council. John A. Russo City Manager. From: Date: July 23, 2013

7/23/13. CITY OF ALAMEDA Memorandum. Honorable Mayor and Members of the City Council. John A. Russo City Manager. From: Date: July 23, 2013 CITY OF ALAMEDA Memorandum To: From: Honorable Mayor and Members of the City Council John A. Russo City Manager Date: July 23, 2013 Re: Adopt a Resolution Authorizing the Commencement of Proceedings for

More information

ADDENDUM NO. 1 CITY OF FORT MORGAN OUTPOST SEWER LIFT STATION CONVERSION PROJECT (DOLA EIAF 07494) January 22, 2015

ADDENDUM NO. 1 CITY OF FORT MORGAN OUTPOST SEWER LIFT STATION CONVERSION PROJECT (DOLA EIAF 07494) January 22, 2015 ADDENDUM NO. 1 CITY OF FORT MORGAN OUTPOST SEWER LIFT STATION CONVERSION PROJECT (DOLA EIAF 07494) January 22, 2015 To all prospective bidders: This Addendum is part of the Bid Documents and modifies the

More information

I. CITY COUNCIL MEETING CALLED TO ORDER MAYOR, TOMMY SLOAN:

I. CITY COUNCIL MEETING CALLED TO ORDER MAYOR, TOMMY SLOAN: AGENDA CITY OF COLEMAN CITY COUNCIL MEETING THURSDAY, JANUARY 18, 2018; 6:00 P.M. LOCATED AT THE COLEMAN CITY HALL 200 W. LIVEOAK, COLEMAN, TEXAS 76834 A regular meeting of the City Council of the City

More information

CITY OF RICHMOND INVITATION TO TENDER

CITY OF RICHMOND INVITATION TO TENDER CITY OF RICHMOND INVITATION TO TENDER Contract T.2892 Contract: AC Watermain Replacement, Comstock Area The City of Richmond invites tenders for construction work at the above-mentioned locations. Work

More information

Honorable Mayor and Members of the City Council. Len Gorecki, Assistant City Manager/Director of Public Works Philip Wang, Associate Engineer

Honorable Mayor and Members of the City Council. Len Gorecki, Assistant City Manager/Director of Public Works Philip Wang, Associate Engineer 14-E TO: ATTENTION: FROM: Honorable Mayor and Members of the City Council Jeffrey L. Stewart, City Manager Len Gorecki, Assistant City Manager/Director of Public Works Philip Wang, Associate Engineer SUBJECT:

More information

Project Background for Trenchless Water Main Replacement Program Major Project Team Members : -City of Livonia and Department of Public Works - Prof.

Project Background for Trenchless Water Main Replacement Program Major Project Team Members : -City of Livonia and Department of Public Works - Prof. MI-AWWA / MWEA Joint Conference e August 13, 2010 Soaring Eagle Resort & Conference Center Livonia s Water System Winning Solution in Tough Times Concept to Construction HDPE Pipe Bursting / Prechlorinated

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of April 21, 2007 DATE: April 20, 2007 SUBJECT: Approve the Award of a Contract to Sagres Construction Corp. for the construction of Phase I

More information

REVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule

REVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule 1. Mobilization, Insurance, Bonds, General Requirements, BMPs, Record Drawings, Testing Requirements, Utility Location, Demobilization and Site Maintenance. 1 L.S. 2. Supply and install complete 384,238

More information

LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA Phone (916) FAX (916) Purchasing Department

LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA Phone (916) FAX (916) Purchasing Department Addendum 1 Text 5-9-17 LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA 95825 Phone (916) 568-3071 FAX (916) 568-3145 Purchasing Department Sacramento City College American River College

More information

Public members of the DNB must meet the following requirements:

Public members of the DNB must meet the following requirements: Purpose The purpose of this policy is to provide a deliberate, efficient and transparent process to identify, select, implement and complete overhead to underground utility facility conversions within

More information

PREQUALIFICATION APPLICATION INSTRUCTIONS

PREQUALIFICATION APPLICATION INSTRUCTIONS PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.

More information

PREQUALIFICATION APPLICATION INSTRUCTIONS

PREQUALIFICATION APPLICATION INSTRUCTIONS PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.

More information

Staff Report. Victoria Walker, Director of Community and Economic Development

Staff Report. Victoria Walker, Director of Community and Economic Development Staff Report 10.c Date: November 1, 2016 To: From: Reviewed by: Prepared by: Subject: City Council Valerie J. Barone, City Manager Victoria Walker, Director of Community and Economic Development Mark Migliore,

More information

Virgin Valley HDD Cased Crossing

Virgin Valley HDD Cased Crossing North American Society for Trenchless Technology (NASTT) NASTT s 2018 No-Dig Show Palm Springs, California March 25-29, 2018 TA-T6-04 Virgin Valley HDD Cased Crossing Sam Senn, Forsgren Associates, Inc.,

More information

Mitigating Risk to Underwater Crossings to Improve Water Supply Reliability: Two Case Studies

Mitigating Risk to Underwater Crossings to Improve Water Supply Reliability: Two Case Studies Mitigating Risk to Underwater Crossings to Improve Water Supply Reliability: Two Case Studies Serge Terentieff, Denise Cicala, Xavier Irias, and Raffi Moughamian ABSTRACT Isolated segments of the East

More information

HAYWARD CITY COUNCIL RESOLUTION NO. 16- Introduced by Council Member

HAYWARD CITY COUNCIL RESOLUTION NO. 16- Introduced by Council Member ATTACHMENT II HAYWARD CITY COUNCIL RESOLUTION NO. 16- Introduced by Council Member RESOLUTION AUTHORIZING THE EXECUTION OF A COMMUNITY WORKFORCE AGREEMENT WITH THE ALAMEDA COUNTY BUILDING TRADES COUNCIL

More information

November 2, 2018 CITY OF BERKELEY FY 2018 MEASURE M STREET REHABILITATION SPECIFICATION NO C (Re-Issued) ADDENDUM NO. 1

November 2, 2018 CITY OF BERKELEY FY 2018 MEASURE M STREET REHABILITATION SPECIFICATION NO C (Re-Issued) ADDENDUM NO. 1 Department of Public Works Engineering Division November 2, 2018 CITY OF BERKELEY FY 2018 MEASURE M STREET REHABILITATION ADDENDUM NO. 1 Dear Bidder: The following amendments are hereby made to the subject

More information

Job Order Sewer Repair Services

Job Order Sewer Repair Services Job Order Sewer Repair Services Bid Addendum No. 1 October 10, 2018 All Contractual Requirements as defined within the Contract Documents shall remain in full force to the extent that they are not modified

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report April 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER

More information

CALLEGUAS MUNICIPAL WATER DISTRICT THOUSAND OAKS, CALIFORNIA NOTICE INVITING BIDS

CALLEGUAS MUNICIPAL WATER DISTRICT THOUSAND OAKS, CALIFORNIA NOTICE INVITING BIDS CALLEGUAS MUNICIPAL WATER DISTRICT THOUSAND OAKS, CALIFORNIA NOTICE INVITING BIDS For the construction of the CCNB Broken Back Rehabilitation, Phase 3 located at 8 sites in the City of Simi Valley in the

More information

Request for Proposal. I. Background. Objectives. Summary Scope of Work. Park City Fire Service District Fiber Upgrade Duct Installation

Request for Proposal. I. Background. Objectives. Summary Scope of Work. Park City Fire Service District Fiber Upgrade Duct Installation Request for Proposal Park City Fire Service District Fiber Upgrade Duct Installation I. Background The Park City Fire Service District (PCFSD) provides emergency services and prevention programs to protect

More information

ADDENDUM NO. 2 ITB-PW-U CITY OF PALM COAST WTP 3 ELECTRICAL DISTRIBUTION FACILITIES TO SERVE WELL SITES PH 2

ADDENDUM NO. 2 ITB-PW-U CITY OF PALM COAST WTP 3 ELECTRICAL DISTRIBUTION FACILITIES TO SERVE WELL SITES PH 2 ADDENDUM NO. 2 ITB-PW-U-12-09 CITY OF PALM COAST WTP 3 ELECTRICAL DISTRIBUTION FACILITIES TO SERVE WELL SITES PH 2 ISSUE DATE: August 20, 2012 BID DATE: August 28, 2012, at 2:00 PM This addendum is issued

More information

Presentation to the Alameda County Board of Supervisors FY Budget Request April 12, 2016

Presentation to the Alameda County Board of Supervisors FY Budget Request April 12, 2016 Presentation to the Alameda County Board of Supervisors FY 2016 2017 Budget Request April 12, 2016 1 Overview Public Works Agency Vision, Mission, and Goals Statements CSAC/CEAC Project Award FY 2015-16

More information

AGENDA REQUEST AGENDA ITEM NO: VI.2. Unfinished Business. June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell SUBJECT:

AGENDA REQUEST AGENDA ITEM NO: VI.2. Unfinished Business. June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell SUBJECT: AGENDA HEADING: Unfinished Business AGENDA REQUEST COMMISSION MEETING DATE: June 15, 2015 BY Utilities Mitt Tidwell Utilities Director Tidwell AGENDA ITEM NO: VI.2. Originating Department SUBJECT: Department

More information

JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION

JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION FOR PROSPECTIVE SANDAG CONTRACTORS April 21, 2016 1 WELCOME & INTRODUCTIONS 2 AGENDA Overview of Job Order Contracting (JOC) What is the process for a JOC

More information

ROSEMEAD OVERSIGHT BOARD STAFF REPORT

ROSEMEAD OVERSIGHT BOARD STAFF REPORT ROSEMEAD OVERSIGHT BOARD STAFF REPORT TO FROM THE HONORABLE CHAIR AND BOARD MEMBERS CURTIS CANNON SPECIAL PROJECTS MANAGER DATE APRIL 18 2016 SUBJECT ZAPOPAN PARK IMPROVEMENTS PROJECT PROJECT No 41008

More information

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department Peralta Community College District 501 5 th Avenue Oakland, California 94606 Phone (510) 466-7225 Fax (510) 587-7873 Purchasing Department ADDENDUM No. 2 DATED JULY 2, 2013 TO THE PROJECT MANUAL and PLANS

More information

ASTM C857 A -16 AASHTO H -20 (for vaults beneath roadways) ASTM C857 A-8 (for vaults beneath incidental light truck traffic)

ASTM C857 A -16 AASHTO H -20 (for vaults beneath roadways) ASTM C857 A-8 (for vaults beneath incidental light truck traffic) 1 Scope This specification outlines the minimum requirements for 5i 7i (56I 84I) vaults to be used for three-phase sectionalizing cabinets and metering equipment. This specification applies to all 5i 7i

More information

ANNE ARUNDEL COUNTY Department of Public Works DATE: 01/25/2017 FROM: Rich Osborn, P.E., Prof.L.S., Project Manager, Bureau of Engineering SUBJECT: Minutes for Pre-Bid Meeting January 19, 2017 South Shore

More information

ITEM 5 - AUTHORIZATION TO ADVERTISE FOR BIDS FOR CONTRACT NO: CH- 010, WATER SYSTEM IMPROVEMENTS TOWN OF CHEEKTOWAGA, PROJECT NO.

ITEM 5 - AUTHORIZATION TO ADVERTISE FOR BIDS FOR CONTRACT NO: CH- 010, WATER SYSTEM IMPROVEMENTS TOWN OF CHEEKTOWAGA, PROJECT NO. ITEM 5 - AUTHORIZATION TO ADVERTISE FOR BIDS FOR CONTRACT NO: CH- 010, WATER SYSTEM IMPROVEMENTS TOWN OF CHEEKTOWAGA, PROJECT NO. 201800075 WHEREAS, Russell J. Stoll, Executive Engineer and Leonard Kowalski,

More information

Addendum No Variable Frequency Drives Section A, revise per following:

Addendum No Variable Frequency Drives Section A, revise per following: Date of Addendum: Jan. 7, 2013 CWA Contract: LPS-311 Addendum No. 2 Project: Lynchburg Pump Station VFD Replacement for P-208 & P-209 From: Rahim Tazeh, PE Infrastructure Associates 6117 Richmond, Suite

More information

Raymond Munch, Interim City Manager Marc Thorson, Information Technology Director

Raymond Munch, Interim City Manager Marc Thorson, Information Technology Director DATE: December 12, 2018 TO: FROM: SUBJECT: Honorable Mayor Jerry Smith City Council Raymond Munch, Interim City Manager Marc Thorson, Information Technology Director Authorizing the Design and Construction

More information

INTRODUCE AN ORDINANCE ADOPTING ADDITIONS TO CHAPTER 27 UTILITIES) OF THE TOWN CODE RELATING TO WATER

INTRODUCE AN ORDINANCE ADOPTING ADDITIONS TO CHAPTER 27 UTILITIES) OF THE TOWN CODE RELATING TO WATER fba _s os COUNCIL AGENDA REPORT MEETING DATE: 06/ 02/ 15 ITEM NO: Li DATE: TO: / FROM: LES WHITE, INTERIM TOWN MA SUBJECT: WATER CONSERVATION INTRODUCE AN ORDINANCE ADOPTING ADDITIONS TO CHAPTER 27 UTILITIES)

More information

Special Meeting of the Infrastructure & Franchise Committee

Special Meeting of the Infrastructure & Franchise Committee COMMITTEE MEMBERS Edi E. Birsan, Chair Laura M. Hoffmeister, Member Civic Center 1950 Parkside Drive Concord, CA 94519 www.cityofconcord.org Special Meeting of the Infrastructure & Franchise Committee

More information

MARTIN COUNTY UTILITIES AND SOLID WASTE P. O. BOX 9000 STUART, FL

MARTIN COUNTY UTILITIES AND SOLID WASTE P. O. BOX 9000 STUART, FL MARTIN COUNTY UTILITIES AND SOLID WASTE P. O. BOX 9000 STUART, FL 34995-9000 August 26, 2016 2nd Request Name and Address RE: Hibiscus Park/Paramount Estates Proposed Water Main Extension Parcel Control

More information

Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kerrie Romanow Barry Ng SUBJECT: SEE BELOW. DATE: August 2, SjH //6>

Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL. FROM: Kerrie Romanow Barry Ng SUBJECT: SEE BELOW. DATE: August 2, SjH //6> COUNCIL AGENDA: 8/23/16 ITEM: "4 3- CITY OF SAN JOSE CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL SUBJECT: SEE BELOW Memorandum FROM: Kerrie Romanow Barry Ng DATE: Approved Date SjH //6>

More information

CITY OF ENCINITAS CITY COUNCIL AGENDA REPORT Meeting Date: May 15, 2013

CITY OF ENCINITAS CITY COUNCIL AGENDA REPORT Meeting Date: May 15, 2013 CITY OF ENCINITAS CITY COUNCIL AGENDA REPORT Meeting Date: May 15, 2013 TO: VIA: FROM: SUBJECT: City Council Gus Vina, City Manager Glenn Pruim, Director of Engineering and Public Works Tim Nash, Director

More information

PUBLIC SAFETY and INFRASTRUCTURE & DEVELOPMENT 5/27/ E Grand River, Board Chambers, Howell, Michigan :30 PM

PUBLIC SAFETY and INFRASTRUCTURE & DEVELOPMENT 5/27/ E Grand River, Board Chambers, Howell, Michigan :30 PM PUBLIC SAFETY and INFRASTRUCTURE & DEVELOPMENT 5/27/2014 304 E Grand River, Board Chambers, Howell, Michigan 48843 7:30 PM AGENDA 1. CALL MEETING TO ORDER 2. APPROVAL OF MINUTES Meeting minutes dated:

More information

ALL BIDDERS shall acknowledge receipt of this Addendum No. 1 on the BID FORM or the BID will be deemed to be invalid for the purposes of this project.

ALL BIDDERS shall acknowledge receipt of this Addendum No. 1 on the BID FORM or the BID will be deemed to be invalid for the purposes of this project. LOS ANGELES COMMUNITY COLLEGES 770 Wilshire Boulevard, Los Angeles, CA 90017 Telephone: 213/891-2000 CITY EAST HARBOR MISSION PIERCE SOUTHWEST TRADE TECHNICAL VALLEY WEST ADMINISTRATIVE OFFICES Date: October

More information

ENGINEERING AND INFORMATION TECHNOLOGY COMMITTEE MEETING SUMMARY MINUTES Wednesday, August 8, :15 p.m.

ENGINEERING AND INFORMATION TECHNOLOGY COMMITTEE MEETING SUMMARY MINUTES Wednesday, August 8, :15 p.m. ENGINEERING AND INFORMATION TECHNOLOGY COMMITTEE MEETING SUMMARY MINUTES Wednesday, August 8, 2018 4:15 p.m. ATTENDANCE Director: John Weed (Chair), Aziz Akbari ftdr2_. Staff: Ed Stevenson, Toni Lyons,

More information