1 Scottish House Builders Health & Safety Forum SG 4:10 Preventing Falls in Scaffolding Presentation By Mark Clarke Clarke Health & Safety Consultants

2 The History of Scaffolders Falling From Scaffolds Prior 1999 SG4:10 SG 4:00 SG4:05 App A SG4:05

3 Pre-SG4:00

4

5

6 SG4:10 Have the four SG 4: procedures improved the standard of safety for scaffolders YES

7

8 SG4:10 There are still people who are working on sites and the streets who are putting themselves and other peoples lives at risk

9

10 Donning a Harness: STEP 1 Hold harness up by shoulder straps and ensure leg straps hang free 10

11 Clarke Health and Safety Consultants 11

12 Clarke Health and Safety Consultants

13 Clarke Health and Safety Consultants

14

15

16

17

18

19

20

21 SG4:10 For the majority of Scaffold Companies SG4:10 is working, there scaffolders are returning home from work each day. The SG4:10 Safe System of Work is not based on just one system or one method of working

22 Clarke Health and Safety Consultants

23 Clarke Health and Safety Consultants

24 Clarke Health and Safety Consultants

25 Clarke Health and Safety Consultants

26 Personnel Prohibition Notice The scaffolder was not using his harness Clarke Health and Safety Consultants

27 Clarke Health and Safety Consultants

28 SG4:10 Preventing Falls in Scaffolding 1 st January 2011 Clarke Health and Safety Consultants

29 This latest version of SG4 clearly defines the installation and use SCAFFOLDERS SAFE ZONE.for the life of the scaffolding structure as essential. This safe zone ensures collective fall protection is in place for the vast majority of the scaffolding operation. Clarke Health and Safety Consultants

30 HM Chief Inspector of Construction (HSE) states in his forward in SG4:10 that. Whether it is during or post installation of any scaffolding works, the HSE s inspectors will expect to see clear evidence of compliance YOU HAVE BEEN WARNED Clarke Health and Safety Consultants

31 The new SG4 gives a balanced view of collective fall prevention methods for creating the SCAFFOLDERS SAFE ZONE Collective fall protection MUST always be considered ahead of systems that rely on Personal Fall Protection Equipment Clarke Health and Safety Consultants

32 The HSE will no longer accept the unprotected traversing element of the tunnelling method YOU MUST USE THIS SYSTEM WITH SUITABLE EDGE PROTECTION Clarke Health and Safety Consultants

33 Scaffolder Safe Zone This is not a working platform this is your safe zone Clarke Health and Safety Consultants

34 Double Lanyards When erecting beams or temporary roofs double lanyards allow the Scaffolder to remain clipped on when crabbing along a beam. When using one lanyard, scaffolders should not wrap the other one around their body or attach to toolbelt as this could cause the energy absorbing lanyard to fail. It should be clipped in the same area, hang free or connected to a sacrificial lanyard parking point on the harness. Clarke Health and Safety Consultants

35 Scaffolders Step Up s Proprietary step up s have been designed for the erection of 2m lifts fixed to the standard or guardrail 1m above the working platform. 35

36 Clarke Health and Safety Consultants

37 The Scaffolders Safety Step Clarke Health and Safety Consultants

38 Clarke Health and Safety Consultants

39 Clarke Health and Safety Consultants

40 Safety Steps Clarke Health and Safety Consultants

41 Clarke Health and Safety Consultants

42 Clarke Health and Safety Consultants

43 Clarke Health and Safety Consultants

44 Clarke Health and Safety Consultants

45 Clarke Health and Safety Consultants

46 Clarke Health and Safety Consultants

47 Clarke Health and Safety Consultants

48 Clarke Health and Safety Consultants

49 Clarke Health and Safety Consultants

50 Clarke Health and Safety Consultants

51 When (moving boards) Clarke Health and Safety Consultants

52 When (safe handling platform) Clarke Health and Safety Consultants

53 Short Lift System By erecting scaffolding using short lift heights (1m) the ledgers of the next lift are erected as normal to form a 2m lift. Then a 1m intermediate lift is formed. As access is gained the ledgers form the next guardrails. Decking on the temporary intermediate lift can be raised to the next lift and any temporary transoms removed later to provide clear access for other trades on finished working lifts. System scaffold tower using short lift system 53

54 Clarke Health and Safety Consultants

55 Reaching below the platform You must have the single guardrail in place and you must be clipped on Clarke Health and Safety Consultants

56 Clarke Health and Safety Consultants

57 Clarke Health and Safety Consultants

58 Clarke Health and Safety Consultants

59 Clarke Health and Safety Consultants

60 Clarke Health and Safety Consultants

61 Clarke Health and Safety Consultants

62 What happens after a fall Clarke Health and Safety Consultants

63 The Rescue Plan Check the rescue plan. It must not quote Suspension Trauma It must give a site specific sequence of rescue plan

64 Rescue from height plan Are the operatives trained Risk Assessment Method Statements Rescue plan Rescue equipment Consultation with PC Site equipment,mewp, Crane, Scaffold Towers Location of Emergency Services

65 65

66

67

Generation Hop up brackets to be removed and boards moved to lift above.

Generation Hop up brackets to be removed and boards moved to lift above. Denotes Ladder for Access from 2nd Lift to Extenda Bracket Generation Hop up brackets to be installed to manufacturer's instructions. Installed at 1200mm c/c max & 1050mm down from top of wall section.

More information

USER S MANUAL HAKI STAIR TOWER

USER S MANUAL HAKI STAIR TOWER USER S MANUAL HAKI STAIR TOWER HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made and supplied

More information

USER S MANUAL. HAKI Loading Tower

USER S MANUAL. HAKI Loading Tower USER S MANUAL HAKI Loading Tower HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made and

More information

QUORUM MINING & RELINING SERVICES HEALTH AND SAFETY MANAGEMENT

QUORUM MINING & RELINING SERVICES HEALTH AND SAFETY MANAGEMENT SCAFFOLDING AND ELEVATED WORK PROCEDURE STATEMENT OF PROCEDURE: This procedure reviews the hazards associated with the use of scaffolds and how to control or minimize those hazards. This procedure also

More information

USER S MANUAL HAKI COMPACT STAIR TOWER

USER S MANUAL HAKI COMPACT STAIR TOWER USER S MANUAL HAKI COMPACT STAIR TOWER HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

USER S MANUAL HAKI PUBLIC ACCESS STAIR

USER S MANUAL HAKI PUBLIC ACCESS STAIR USER S MANUAL HAKI PUBLIC ACCESS STAIR HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

USER S MANUAL HAKI COMPACT STAIR TOWER

USER S MANUAL HAKI COMPACT STAIR TOWER USER S MANUAL HAKI COMPACT STAIR TOWER HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

user s guide for ( Hand-Built )

user s guide for ( Hand-Built ) user s guide for hakitec 750 MONOPITCHED TEMPORARY ROOF with HAKI Trak Sheeting ( Hand-Built ) HAKI LTD 2011 INTRODUCTION Temporary roof structures are by their very nature amongst the most difficult and

More information

USER S MANUAL HAKI PUBLIC ACCESS STAIR

USER S MANUAL HAKI PUBLIC ACCESS STAIR USER S MANUAL HAKI PUBLIC ACCESS STAIR HAKI AB 2017 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

Fall Protection Plan Developer (FPPD) Unit Standard (229994) Target audience and relevance. Course content. Course duration

Fall Protection Plan Developer (FPPD) Unit Standard (229994) Target audience and relevance. Course content. Course duration Fall Protection Plan Developer (FPPD) Unit Standard (229994) The person wishing to acquire the competencies in this standard will be people responsible for the safety and protection of people working at

More information

Home Builders Health and Safety Forum Generic Scaffold Specification Template

Home Builders Health and Safety Forum Generic Scaffold Specification Template Home Builders Health and Safety Forum Generic Scaffold Specification Template Rev 2 Draft April 2014 Page 1 of 13 Contents Purpose Page 3 1.0 Scope Page 4 2.0 Standards Page 4 3.0 Materials Page 5 4.0

More information

USER S Manual. HAKI Bridge System (HBS)

USER S Manual. HAKI Bridge System (HBS) USER S Manual HAKI Bridge System (HBS) HAKI AB 2018 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have been made

More information

Erect and dismantle cantilever scaffolds

Erect and dismantle cantilever scaffolds Reference : K/506/5119 Level : Level 2 Credit Value : 18 Guided Learning Hours : 144 Grading Type : Graded Erect and dismantle cantilever scaffolds Aim : The aim of this unit is to provide the learner

More information

WORK AT HEIGHT PRESENTATION DAVE JONES GROUP HSE MANAGER 27/09/18

WORK AT HEIGHT PRESENTATION DAVE JONES GROUP HSE MANAGER 27/09/18 WORK AT HEIGHT PRESENTATION DAVE JONES GROUP HSE MANAGER 27/09/18 WORK AT HEIGHT CASE STUDY APRIL 2018 BACKGROUND Upon opening the hatches of a steel vessel berthed at PD Ports, it was recognised by the

More information

Management Plan for Walking/Working Surfaces & Fall Protection (29 CFR , 23, 66 App.C; 29 CFR ) ISD #535

Management Plan for Walking/Working Surfaces & Fall Protection (29 CFR , 23, 66 App.C; 29 CFR ) ISD #535 Management Plan for Walking/Working Surfaces & Fall Protection (29 CFR 1910.22, 23, 66 App.C; 29 CFR 1926.502) ISD #535 Health & Safety Office Maintenance Service Building 10 SE 9½ Street Rochester, MN

More information

Scaffold Users Safety Quiz

Scaffold Users Safety Quiz 01/04/1801/04/1801/04/181 Name: Instructor: Date: Scaffold Users Safety Quiz 1. Anyone using scaffold after September 2, 19_97_ must have training on the following: 1. _FALL PROTECTION 2. _FALLING OBJECTS

More information

Scaffolding Glossary of Terms A

Scaffolding Glossary of Terms A Scaffolding Glossary of Terms A ACCESS PLATFORM: A platform that gives access to and from places of work to persons, materials and equipment. ACCESSORY: A fitting that is able to be attached to a structural

More information

HIGH RISK ACTIVITIES. GD02 Scaffold planning and work at height activities checklist. Design stage. Tender stage. Element Yes No N/A Comments

HIGH RISK ACTIVITIES. GD02 Scaffold planning and work at height activities checklist. Design stage. Tender stage. Element Yes No N/A Comments GD02 Scaffold planning and work at height activities checklist Company name Location Project title Contract no. Design stage Considerations at design stage (pre-construction information/temporary works

More information

Uniscaff User Guide. Uniscaff. George Roberts Total Reliability of Supply. George Roberts Total Reliability of Supply

Uniscaff User Guide. Uniscaff.   George Roberts Total Reliability of Supply. George Roberts Total Reliability of Supply George Roberts Total Reliability of Supply User Guide George Roberts Total Reliability of Supply www.scaffoldingsales.co.uk Tubes Scaffold Staircases Beams Formwork Fencing K-Lok User Guide Contents Introduction

More information

ACT Scaffolding Services LTD METHOD STATEMENT Scaffold erection

ACT Scaffolding Services LTD METHOD STATEMENT Scaffold erection Address: 20 Bole Close, Wombwell, Barnsley, South Yorkshire. S73 8AZ Tel: 07883 780704 Email: enquiries@actscaffold.co.uk Web: www.actscaffold.co.uk Project/Contract Boiler Scaffolding Client Example Comp

More information

2017 AT-PAC RINGLOCK SAFETY MANUAL & USER GUIDES UNITED KINGDOM

2017 AT-PAC RINGLOCK SAFETY MANUAL & USER GUIDES UNITED KINGDOM 2017 AT-PAC RINGLOCK SAFETY MANUAL & USER GUIDES UNITED KINGDOM Table of Contents INTRODUCTION... 4 RINGLOCK QUALITY FACTORS... 5 DESIGNATION OF RINGLOCK... 5 SAFETY GUIDELINES AND SAFE USE... 6 NEVER...

More information

February 2001 Safe erection of Scaffolding Presentation by John Locke, SGB Services,

February 2001 Safe erection of Scaffolding Presentation by John Locke, SGB Services, February 2001 Safe erection of Scaffolding Presentation by John Locke, SGB Services, John prefaced his talk by saying that the erection method he was about to describe was a radical departure from the

More information

25 August Working at Height

25 August Working at Height 25 August 2016 Working at Height Contents 1. Hierarchy of Methods... 1 1.1 Hierarchy for selection Methods for Working at Height... 1 Introduction... 1 1.2 Basis of Hierarchy... 1 1.3 Collective Protection

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SWMS 002 Erect / Dismantle Single Bay Towers and/or Multiple Bay Towers Page of 9 ABN: 40 088 478 399 This SWMS has been prepared and authorised by OLDFIELDS ACCESS PTY LTD ACN: 088 478 399 Date: Issue

More information

Sample Written Program. For. Scaffolds

Sample Written Program. For. Scaffolds Sample Written Program For Scaffolds 1 Scaffold Safety Program (COMPANY NAME) Purpose The purpose of this safety policy and procedure is to establish guidelines for the protection of {COMPANY} employees

More information

Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification

Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

ANID GROUP SARL. For. Scaffolds

ANID GROUP SARL. For. Scaffolds ANID GROUP SARL For Scaffolds 1 Scaffold Safety Program Anid Group SARL Purpose The purpose of this safety policy and procedure is to establish guidelines for the protection of Anid Group employees who

More information

USER S GUIDE for HAKITEC 750. TEMPORARY ROOF with HAKI Trak Sheeting ( Hand-Built )

USER S GUIDE for HAKITEC 750. TEMPORARY ROOF with HAKI Trak Sheeting ( Hand-Built ) USER S GUIDE for HAKITEC 750 TEMPORARY ROOF with HAKI Trak Sheeting ( Hand-Built ) HAKI LTD 2007 INTRODUCTION Temporary roof structures are by their very nature amongst the most difficult and demanding

More information

Fall Protection Program For Working on Flat Roofs

Fall Protection Program For Working on Flat Roofs Fall Protection Program For Working on Flat Roofs Policy Sponsor: Responsible Unit: Facilities Management Approval Date: Revisions: January 2016 1. Introduction Facilities Management employees are required

More information

Cantilever Loading Platform Erection Procedures and Guidance Notes

Cantilever Loading Platform Erection Procedures and Guidance Notes Cantilever Loading Platform Erection Procedures and Guidance Notes Please note this is a six page document. 1 Introduction 1 Issue Date: January 2007 It is essential that the procedures are read and fully

More information

Scaffolding Update Including TG20:13 2 years on NEW SG4:15. Ray Johnson BSc Joint Managing Director

Scaffolding Update Including TG20:13 2 years on NEW SG4:15. Ray Johnson BSc Joint Managing Director Scaffolding Update Including TG20:13 2 years on NEW SG4:15 Ray Johnson BSc Joint Managing Director Impact of TG20:13 A new set of guidance, not merely a revision Changes are far reaching, effecting most

More information

BASIC SCAFFOLDING KNOWLEDGE QUESTIONS

BASIC SCAFFOLDING KNOWLEDGE QUESTIONS Garnsworthy Square 46, 62 & 64 Garnsworthy St Springvale rth Victoria 3171 Updated on 22/02/08 STC105 Name BASIC SCAFFOLDING KNOWLEDGE QUESTIONS THE PROFESSIONAL Scaffold Tools Scaffold Belts Couplers

More information

Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification

Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification ProQual 2015 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification

More information

HAKI AB, Sibbhult, Sweden

HAKI AB, Sibbhult, Sweden HAKI AB, Sibbhult, Sweden www.haki.com The HAKI Group HAKI is a manufacturer of system scaffold and weather protection solutions. HAKI temporary work-places ensure the highest standard in safety whilst

More information

NEBOSH International Certificate in Construction Safety and Health Unit ICC1 MANAGING AND CONTROLLING HAZARDS IN INTERNATINAL CONSTRUCTION ACTIVITIES

NEBOSH International Certificate in Construction Safety and Health Unit ICC1 MANAGING AND CONTROLLING HAZARDS IN INTERNATINAL CONSTRUCTION ACTIVITIES NEBOSH International Certificate in Construction Safety and Health Unit ICC1 MANAGING AND CONTROLLING HAZARDS IN INTERNATINAL CONSTRUCTION ACTIVITIES element 10: WORKING AT HEIGHT - HAZARDS AND RISK CONTROL

More information

Erection manual. Tube-Lock Concept. van Thiel United b.v Page: 1 of 15

Erection manual. Tube-Lock Concept. van Thiel United b.v Page: 1 of 15 Erection manual Tube-Lock Concept 2013-02 Page: 1 of 15 Contents Subject Page Illustration of Tube-Lock Concept 3 Parts of Tube-Lock concept 4 Legislation 5 Erecting a Tube-Lock Concept scaffold 6 Technical

More information

Scottish House Builders Health and Safety Forum. Graeme McMinn HM Principal Inspector

Scottish House Builders Health and Safety Forum. Graeme McMinn HM Principal Inspector Health and Safety Executive Scottish House Builders Health and Safety Forum May 2017 HSE Update Graeme McMinn HM Principal Inspector Helping GB Work Well 6 strategic themes Acting together, tackling ill

More information

WORKING AT HEIGHT. The company will comply with the Work at Height Regulations 2005, its schedules and Codes of Practice.

WORKING AT HEIGHT. The company will comply with the Work at Height Regulations 2005, its schedules and Codes of Practice. WORKING AT HEIGHT The company will comply with the Work at Height Regulations 2005, its schedules and Codes of Practice. Principally this means that we comply with the hierarchy of risk in that we shall:

More information

Health, Safety and Environment

Health, Safety and Environment Health, Safety and Environment SOP-06 Working at Height Produced by HSSE Facilities & GS Department Table of Contents 1 Overview... 1 1.1 Purpose... 1 1.2 Hazards and Risks... 1 1.3 Key Terminology...

More information

ROOFS PART 2 RESIDENTIAL BUILDINGS

ROOFS PART 2 RESIDENTIAL BUILDINGS SAFE WORK ON ROOFS PART 2 RESIDENTIAL BUILDINGS CODE OF PRACTICE 2004 WorkCover. Watching out for you. Disclaimer This publication may contain occupational health and safety and workers compensation information.

More information

As a scaffold user, Mr Scaffold recommends Method 1, but both options are suitable.

As a scaffold user, Mr Scaffold recommends Method 1, but both options are suitable. 20 EASYSCAF t TM The Next Level 1300 MR SCAFFOLD (1300 677 223) 12 Lagana Place Wetherill Park NSW 2164 Fax: (02)9725 5214 ABN: 65 088 652 144 Re: Workcover Update Feb 2011 Thankyou for purchasing your

More information

ESSENTIAL STANDARD no.17. Scaffolding

ESSENTIAL STANDARD no.17. Scaffolding ESSENTIAL STANDARD no.17 Scaffolding KEY MESSAGES Check that scaffolding meets the standards in this guidance. Ensure that regular inspections are carried out on scaffolding by a suitably qualified person.

More information

FALL HAZARD CONTROL PROCESS

FALL HAZARD CONTROL PROCESS Sugrema Consultancy N.V. FALL HAZARD CONTROL PROCESS 02 April 2014 1 Sugrema Consultancy N.V. 2 FALL HAZARD CONTROL PROCESS Start Fall control Program Improvement cycle Audit Fall control Program Training

More information

Hazard - Scaffolding and debris netting... 2 Control measure - Assess and monitor stability: Scaffolding... 3 Control measure - Specialist advice:

Hazard - Scaffolding and debris netting... 2 Control measure - Assess and monitor stability: Scaffolding... 3 Control measure - Specialist advice: Hazard - Scaffolding and debris netting... 2 Assess and monitor stability: Scaffolding... 3 Specialist advice: Scaffolding... 3 Assess debris netting... 4 Use scaffolding appropriately... 5 Hazard - Scaffolding

More information

TAKING YOU TO NEW HEIGHTS IN SAFETY... kwikstage

TAKING YOU TO NEW HEIGHTS IN SAFETY... kwikstage limited one bay kwikstage stair unit user guide One Bay Stair Tower used in conjunction with Kwikstage System Scaffolding and designed to conform to all current British and European Standards. With only

More information

BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC.

BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC. BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC www.uk-bar.org CONTENTS Introduction.... 3 Hazards.... 4 Accidents... 5 Working at Height... 6 Dunnage.... 7 Planning for a Safe Delivery....

More information

Scaffolding Safety. Scaffolding

Scaffolding Safety. Scaffolding Scaffolding Safety Scaffolding 1926.450 - Scope, Application Covers all scaffolds used in workplaces Does not apply to crane or derrick suspended personnel platforms, which are covered by 1926.550(g) Aerial

More information

Megashore system. Method statement

Megashore system. Method statement Megashore system Method statement Method statement Megashore system Contents Page Introduction 2 Disclaimer 2 Site safety 3 Your responsibilities 3 Safe working practice 4 Personal protective equipment

More information

GRIDFLEX The flexible slab formwork with safe accessible grid elements

GRIDFLEX The flexible slab formwork with safe accessible grid elements GRIDFLEX The flexible slab formwork with safe accessible grid elements 07044 Edition 04 2011 PERI GmbH Formwork Scaffolding Engineering P.O. Box 1264 89259 Weissenhorn Germany Tel +49 (0)7309.950-0 Fax

More information

USER S MANUAL HAKI UNIVERSAL ALUMINIUM

USER S MANUAL HAKI UNIVERSAL ALUMINIUM USER S MANU HAKI UNIVERS UMINIUM HAKI AB 2005 Important information HAKI s product liability and erection instructions apply only to scaffolds that are entirely composed of components that have been made

More information

BELL RINGER-JOURNAL IN YOUR BOOKS ABOUT FRIDAYS LESSON, TOOLS AND WELDING

BELL RINGER-JOURNAL IN YOUR BOOKS ABOUT FRIDAYS LESSON, TOOLS AND WELDING BELL RINGER-JOURNAL IN YOUR BOOKS ABOUT FRIDAYS LESSON, TOOLS AND WELDING OSHA lesson day 6, Subpart L Scaffolds -Definitions Adjustable suspension scaffold means a suspension scaffold equipped with a

More information

Preventing Falls from Equipment and Bridges

Preventing Falls from Equipment and Bridges Preventing Falls from Equipment and Bridges 1 Written Fall Protection Program Key issues to be discussed within this section include: 1. Purpose of the written program. 2. What the program should address.

More information

Rolling Towers. Layher Uni Light Tower Instructions for Assembly and Use. Mobile working platforms according to DIN EN 1004:

Rolling Towers. Layher Uni Light Tower Instructions for Assembly and Use. Mobile working platforms according to DIN EN 1004: Instructions for ssembly and Use Mobile working platforms according to DIN EN 00:00-03 Working platform 0.7 x.8 m max. working height: indoors.3 m outdoors.3 m Rolling Towers Load bearing capacity.0 kn/m

More information

St. Louis Audit of Fall Risks Revised July 2011 Foreman Name Address Visit # Date. General Safety Climate & Housekeeping

St. Louis Audit of Fall Risks Revised July 2011 Foreman Name Address Visit # Date. General Safety Climate & Housekeeping 1 St. Louis Audit of Fall Risks Revised July 2011 Foreman Name Address Visit # Date Type single 2-3 family 4+ family Cycle Time # in Crew # Jman/App Time Auditor Stage of Construction ground breaking/

More information

QUICK ALLY SCAFFOLD SPECIFICATIONS Standards: 1.0 m, 1.5 m, 2.0 m, 2.5 m, 3.0 m, 4.0 m. Ledgers: 0.5 m, 0.7 m, 1.2 m, 1.8 m, 2.4 m, 3.0 m. Polypropylene platforms: 0.7 m, 1.2 m, 1.8 m, 2.4 m, 3.0 m. Also

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 7

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 7 Safety Manual Page 1 of 7 Scaffolds 1. Purpose This policy establishes the basic safety requirements and safe work practices for the erection, use, inspection, movement, and dismantling of scaffolding.

More information

NZQA registered unit standard 9184 version 6 Page 1 of 5

NZQA registered unit standard 9184 version 6 Page 1 of 5 Page 1 of 5 Title Erect and dismantle non-notifiable prefabricated frame scaffolding up to five metres in height Level 3 Credits 5 Purpose People credited with this unit standard are able to: demonstrate

More information

Configuration. User Guide. Version: Copyright 2017 Computer and Design Services Ltd GLOBAL CONSTRUCTION SOFTWARE AND SERVICES

Configuration. User Guide. Version: Copyright 2017 Computer and Design Services Ltd GLOBAL CONSTRUCTION SOFTWARE AND SERVICES Configuration User Guide Version: 2018.0 Copyright 2017 Computer and Design Services Ltd GLOBAL CONSTRUCTION SOFTWARE AND SERVICES Contents Introduction... 1 Create a new project... 2 Open the configuration...

More information

Scaffolding Procedures

Scaffolding Procedures Procedures Purpose It is the purpose of this company in issuing these procedures to further ensure a safe workplace based on the following formal, written procedures for scaffold work. Application This

More information

Scaffolds. OSHA Office of Training & Education 1

Scaffolds. OSHA Office of Training & Education 1 Scaffolds OSHA Office of Training & Education 1 What Is A Scaffold? An elevated, temporary work platform Three basic types: Supported scaffolds -- platforms supported by rigid, load bearing members, such

More information

Are designed to provide a safe working environment, and Govern use of fall protection procedures and equipment.

Are designed to provide a safe working environment, and Govern use of fall protection procedures and equipment. Fall Protection Plan for Construction OSHA currently regulates fall protection for construction under Part 1926, Subpart M. The standards for regulating fall protection systems and procedures are intended

More information

Title: Scaffolding Safety Policy. University Division/Department: Environmental Health & Safety Effective Date: October 6, 2017 Page: 1 of 15

Title: Scaffolding Safety Policy. University Division/Department: Environmental Health & Safety Effective Date: October 6, 2017 Page: 1 of 15 Page: 1 of 15 Table of Contents I. Purpose 2 II. Scope & Application 2 III. Definitions 2 IV. Policy 3 V. Procedures 3 a. Roles & Responsibilities 3 b. Safe Scaffold Erection and Use 5 c. Types of Scaffolds

More information

Contents 2017 VR ACCESS SOLUTIONS ALL RIGHTS RESERVED.

Contents 2017 VR ACCESS SOLUTIONS ALL RIGHTS RESERVED. Issue 1 February 2017 Contents Introduction... 1 NASC Compliance... 2 Safety Information... 3 Component Details... 4 Component Load Capacities... 7 Deck Arrangements... 9 Bracing and Tying... 11 Safe Working

More information

TEMPORARY ROOFING SYSTEM USER GUIDE

TEMPORARY ROOFING SYSTEM USER GUIDE TEMPORARY ROOFING SYSTEM USER GUIDE Providing quality products and services at a competitive price. Valid Only For Genuine Equipment DISCLAIMER: Whilst TRAD Hire & Sales Ltd and the author have made every

More information

Scaffolds. OSHA Office of Training & Education 1

Scaffolds. OSHA Office of Training & Education 1 Scaffolds OSHA Office of Training & Education 1 What Is A Scaffold? An elevated, temporary work platform Three basic types: Supported scaffolds -- platforms supported by rigid, load bearing members, such

More information

SCAFFOLDS Revision No: 3

SCAFFOLDS Revision No: 3 PAGE 1 OF 6 1.0 PURPOSE/ SCOPE To communicate the safety requirements for the erection, inspection and safe use of scaffolds. Compliance with these requirements will assure employee safety while working

More information

Scaffolding Safety Procedures

Scaffolding Safety Procedures Safety & Health Program 10627 Midwest Industrial Boulevard, St. Louis, MO Phone: 314-785-6425 Fax: 314-785-6426 Scaffolding Safety Procedures Purpose It is this company's purpose in issuing these procedures

More information

TRAD HIRE & SALES SCAFFOLDING SUPPLIER USER GUIDE ALTRIX TEMPORARY ROOFING SYSTEM FOCUSSED ON SERVICE

TRAD HIRE & SALES SCAFFOLDING SUPPLIER USER GUIDE ALTRIX TEMPORARY ROOFING SYSTEM FOCUSSED ON SERVICE TRAD HIRE & SALES SCAFFOLDING SUPPLIER ALTRIX TEMPORARY ROOFING SYSTEM USER GUIDE FOCUSSED ON SERVICE DISCLAIMER: Whilst TRAD Hire & Sales Ltd and the author have made every reasonable effort to ensure

More information

WORKING AT HEIGHT PROCEDURE

WORKING AT HEIGHT PROCEDURE Page 1 of 8 AL-Yamama Engineering Company HSSE Department (s) WORKING AT HEIGHT PROCEDURE Page 1 of 8 Page 2 of 8 Introduction Work at height is any work activity that is performed where the work is to

More information

LADDERSPAN AGR. BoSS Camlock Advance Guardrail Mobile Aluminium Tower 1450/850 Frames USER GUIDE

LADDERSPAN AGR. BoSS Camlock Advance Guardrail Mobile Aluminium Tower 1450/850 Frames USER GUIDE LADDERSPAN AGR BoSS Camlock Advance Guardrail Mobile Aluminium Tower 1450/850 Frames USER GUIDE Contents Safety First Safety Checklist Quantity Schedules Assembly and Dismantling Procedure Toe Boards Stabilisers

More information

Layher. Aluminium Rolling Towers. Layher SuperKlaxTower. Instructions for Assembly and Use

Layher. Aluminium Rolling Towers. Layher SuperKlaxTower. Instructions for Assembly and Use Mobile access and working towers in accordance with: HD 1004; DIN 4422, Part 1 (Version 8/92) Working platform 2.8 x 2.8 m and 2.8 x 1.95 m Max. working height: in closed rooms 13.95 m, outdoors 10.0 m

More information

SCAFFOLDING SAFETY PROGRAM

SCAFFOLDING SAFETY PROGRAM SCAFFOLDING SAFETY PROGRAM Introduction Gay Construction Company has instituted plans and procedures to provide a stable, sound, secure and adequately constructed scaffold system on each job that requires

More information

DON T FALL FOR IT HUNTSMAN PNPP ADDRESSES 100% TIE-OFF POLICY

DON T FALL FOR IT HUNTSMAN PNPP ADDRESSES 100% TIE-OFF POLICY DON T FALL FOR IT HUNTSMAN PNPP ADDRESSES 100% TIE-OFF POLICY Corporate Is 100% tie-off required by your employer, when working from a scaffold? Why? What makes an employer think that 100% tie-off is safe?

More information

USER S MANUAL HAKI UNIVERSAL

USER S MANUAL HAKI UNIVERSAL USER S MANUAL HAKI UNIVERSAL International version HAKI AB 2015 Important information HAKI s product liability and user s manuals apply only to scaffolds that are entirely composed of components that have

More information

USER S manual HAKI UNIVERSAL. International version

USER S manual HAKI UNIVERSAL. International version USER S manual HAKI UNIVERSAL International version HAKI AB 2014 Important information HAKI s product liability and erection instructions apply only to scaffolds that are entirely composed of components

More information

Safe planning and operation for Mobile Elevated Working Platforms (MEWPs)

Safe planning and operation for Mobile Elevated Working Platforms (MEWPs) Safe planning and operation for Mobile Elevated Working Platforms (MEWPs) This document sets out the Morgan Sindall standards for the control of Mobile Elevated Work Platforms (MEWP) on its projects. It

More information

Approved By: R. Keen Date: March 6, 2014 Rev. No Scaffolding Procedure

Approved By: R. Keen Date: March 6, 2014 Rev. No Scaffolding Procedure Scaffolding Procedure A CONTROL DOCUMENT 1. PURPOSE The purpose of this section is to protect employees from harm by providing guidelines to ensure scaffolding is erected inspected, dismantled, used and

More information

INTER-DEPARTMENTAL PROCEDURE

INTER-DEPARTMENTAL PROCEDURE INTER-DEPARTMENTAL PROCEDURE OPERATIONS - DUKHAN FIELDS Operations Manager, Dukhan Fields Director Operations Rev. Date Reason A4 Mar13 Issued for use OSD / QC: Rev No. Rev Date DOCUMENT CHANGE HISTORY

More information

CHAPTER 10: FALL PROTECTION

CHAPTER 10: FALL PROTECTION CHAPTER 10: FALL PROTECTION PURPOSE The fall protection program provides information and procedures to minimize the occurrence of an accidental fall or falling object, resulting in injuries on a job site.

More information

SAFETY SYSTEM. G-Deck Consideration. Manual Handling

SAFETY SYSTEM. G-Deck Consideration. Manual Handling INTRODUCTION The G-Deck load deck system is a high strength, low cost access platform which is quick to erect, durable and flexible enough to meet your site access needs. Safety is a priority and G-Deck

More information

SCAFFOLDING - Part 2 SELF INSPECTION CHECKLIST

SCAFFOLDING - Part 2 SELF INSPECTION CHECKLIST OPTIONAL INFORMATION Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: SCAFFOLDING - Part 2 Instructions: This checklist covers some of the regulations issued

More information

PERI PD 8 The cost-effective shoring for slab tables and high loads

PERI PD 8 The cost-effective shoring for slab tables and high loads PERI PD 8 The cost-effective shoring for slab tables and high loads Edition 06/2010 PERI GmbH Formwork Scaffolding Engineering P.O. Box 1264 89259 Weissenhorn Germany Tel +49 (0)7309.950-0 Fax +49 (0)7309.951-0

More information

INSTRUCTIONmanual. BoSS COMPACT SIDE CANTILEVER TOWER SCAFFOLD 3T Method - Through the Trap Door

INSTRUCTIONmanual. BoSS COMPACT SIDE CANTILEVER TOWER SCAFFOLD 3T Method - Through the Trap Door INSTRUCTIONmanual BoSS COMPACT SIDE CANTILEVER TOWER SCAFFOLD 3T Method - Through the Trap Door Drawn: 26/02/2018 Issue: E Page: 2 OF 21 CONTENTS Safety First Component Diagram Component Quantities & Safety

More information

RMM 307 Scaffolds/Suspended Scaffolds and Powered Elevated Platforms Safety Program Page 2 November 2016

RMM 307 Scaffolds/Suspended Scaffolds and Powered Elevated Platforms Safety Program Page 2 November 2016 RMM 307 Scaffolds/Suspended Scaffolds and Powered Elevated Platforms Safety Program Page 2 3.3 Canadian Standards Association, Z271-10 (R2015): Safety Code for Suspended Elevating Platforms. 3.4 National

More information

PLETTAC METRIX USER GUIDE

PLETTAC METRIX USER GUIDE PLETTAC USER GUIDE Providing quality products and services at a competitive price. Valid Only For Genuine Equipment DISCLAIMER: Whilst TRAD Hire & Sales Ltd and the author have made every reasonable effort

More information

This User Guide provides you with step by step instructions to ensure your system is erected easily and safely.

This User Guide provides you with step by step instructions to ensure your system is erected easily and safely. INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative purposes only. Trade King 730 mobile aluminium towers are light-weight scaffold towers used throughout the

More information

SAMPLE FALL PROTECTION PLAN

SAMPLE FALL PROTECTION PLAN B SAMPLE FALL PROTECTION PLAN INDEX JOB SITE AND PLAN INFORMATION STATEMENT OF COMPANY POLICY TRAINING RESIDENTIAL CONSTRUCTION ALTERNATIVE WORK PRACTICES RESPONSIBILITIES OF FOREMAN OR COMPETENT PERSON

More information

Prepared by Andrew Panda. EXPANDA Fence System

Prepared by Andrew Panda. EXPANDA Fence System Prepared by Andrew Panda EXPANDA Fence System Index 1.Introduction Page 3 2.Background Page 4 3. Existing Fence Systems Page 5 4.Features 4.1 Packaging Page 6-8 4.2 Rubber flaps Page 9 4.3 Exclusion Zone

More information

JGJ Translated English of Chinese Standard: JGJ JGJ NATIONAL STANDARD OF THE

JGJ Translated English of Chinese Standard: JGJ JGJ NATIONAL STANDARD OF THE Translated English of Chinese Standard: JGJ80-1991 www.chinesestandard.net Sales@ChineseStandard.net NATIONAL STANDARD OF THE JGJ PEOPLE S REPUBLIC OF CHINA JGJ 80-1991 Technical Code for Safety of High

More information

Fall Prevention for scaffolders

Fall Prevention for scaffolders Guidance Note Fall Prevention for scaffolders This Guidance Note was developed in consultation with stakeholders to recommend the highest reasonably practicable level of fall protection for scaffolders

More information

TRAD HIRE & SALES SCAFFOLDING SUPPLIER USER GUIDE PLETTAC METRIX FOCUSSED ON SERVICE

TRAD HIRE & SALES SCAFFOLDING SUPPLIER USER GUIDE PLETTAC METRIX FOCUSSED ON SERVICE TRAD HIRE & SALES SCAFFOLDING SUPPLIER PLETTAC USER GUIDE FOCUSSED ON SERVICE DISCLAIMER: Whilst TRAD Hire & Sales Ltd and the author have made every reasonable effort to ensure that the information contained

More information

USER S MANUAL HAKI UNIVERSAL

USER S MANUAL HAKI UNIVERSAL USER S MANUAL HAKI UNIVERSAL Suspended scaffolding HAKI AB 2012 Important information HAKI s product liability and erection instructions apply only to scaffolds that are entirely composed of components

More information

CCM Policy 12.5 Working at Height

CCM Policy 12.5 Working at Height CCM Policy 12.5 Working at Height Document Ref: QA-0000-HS-P-0012.5 Revision: A 16-Oct-16 Document Temp: Issue Date: 1 November 2015 Status: Issued CCM P12.5: Page 1 of 33 Contents 12.5 Working at Height

More information

STA REPORT ON PLATFORM INSPECTION QUESTIONNAIRE

STA REPORT ON PLATFORM INSPECTION QUESTIONNAIRE STA REPORT ON PLATFORM INSPECTION QUESTIONNAIRE March 2016 STA report on Platform Inspection Questionnaire BACKGROUND The membership of the STA currently stands at approximately 160 companies and is made

More information

Fall Prevention For Scaffolders

Fall Prevention For Scaffolders Fall Prevention For Scaffolders Document Type: Guidance Note Keycode: web only Industry: Construction, Category: Falls Prevention, General, Manual Handling, Division Author: construction Current Version:

More information

Scaffolding Practice

Scaffolding Practice Health & Safety Scaffolding Practice Content Owner Custodian H&S Discipline Program COMS Document Number Manager, H&S Programs H&S Programs & Projects Health & Safety Scaffolding See COMS Standards CEN-EHS9552

More information

Safe Schools: A Health and Safety Check New Jersey Safe Schools Program/New Jersey Department of Education 473

Safe Schools: A Health and Safety Check New Jersey Safe Schools Program/New Jersey Department of Education 473 Optional Information Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: Scaffolding - Part 1 Self Inspection Checklist Instructions: This checklist covers some

More information

Tru-lift. The self lifting, core forming system from Forming Concepts Inc

Tru-lift. The self lifting, core forming system from Forming Concepts Inc Tru-lift The self lifting, core forming system from Forming Concepts Inc Features & Benefits Complete system raised during the lifting cycle, maximizing system effectiveness. Introduction Tru-lift is the

More information

The Layher Cassette roof

The Layher Cassette roof The Layher Cassette roof for weatherproofing and temporary halls low-cost, labour-saving roofing. Layher cassette roofs have established themselves as a firm favourite at construction sites for conversion,

More information