ARBORICULTURAL REPORT

Size: px
Start display at page:

Download "ARBORICULTURAL REPORT"

Transcription

1 ARBORICULTURAL REPORT Gardeners Road, Bourke Road South, Kent Road & Bridge 8/9 WestConnex New M5. Prepared for CDS-JV. Date 31 May

2

3 Contents 1. Introduction 4 2. Study Area 6 3. Scope of Works 8 4. Methodology 10 a. Site Observations 10 b. Visual Inspection 10 c. Documents, Meetings and Plans Referenced Locations Impact Assessment & Results 23 a. Value 23 b. Location 23 c. Encroachment in TPZ 23 d. Encroachment 24 e. Outcome 24 f. Reason for Outcome 24 g. Impact Assessment Results Recommendations 87 a. Protection 87 b. Inspections 87 c. Work 88 References Appendix A - Schedule Appendix B - Assessment 3

4 1. Introduction The WestConnex scheme is a NSW Government initiative connect Sydney s west and south-west with the Sydney Airport and Port Botany precinct. It is being delivered by the Sydney Morway Corporation (SMC), formerly the WestConnex Delivery Authority (WDA). Part of that project is the WestConnex Stage 2, referred as the New M5. The project will run from the existing M5 East corridor at Beverly Hills via a tunnel St Peters, providing improved access the airport, South Sydney and Port Botany precincts. The Project will substantially improve the east - west corridor access between the Sydney CBD, Port Botany and Sydney Airport precincts and the South West growth areas. The project will deliver approximately nine (9) kilometres of two-lane twin tunnels with capacity operate three lanes in the future, morway morway connections the King Georges Road Interchange Upgrade at Beverly Hills, and a new interchange at St Peters. Infrastructure Approval was granted for the project on 20 April Major works are expected commence in mid-2016 and the New M5 tunnel is scheduled open traffic in late The CPB Contracrs Dragados Samsung Joint Venture (CDS-JV) has been awarded the design and construction of the New M5. CPB Dragados Samsung Joint Venture (CDS-JV) has commissioned prepare an Arboricultural Impact Assessment Report for the proposed road construction along Gardeners Road, Bourke Road and the bridges (Bridges 8&9) connecting Gardeners Road and St Peters Interchange, along with ancillary infrastructure (footpaths and services). The proposed works are part of the WestConnex New M5 Development Project. The purpose of this report is : Identify trees that are likely be affected by the scope of works. Assess the current overall health and condition of the subject trees. Evaluate the significance of the subject trees and assess their suitability for retention. The Report has been developed mirror the same requirements of the reports previously approved Department of Planning and Environment (DPE) and addresses the requirements of Condition B63 in accordance with Table 1. 4

5 Table 1: Condition of Approval B63 Compliance Table Condition Requirement Addressed in: B63 The SSI must be designed retain as many trees as possible and provide a net increase in the number of replacement trees. The Proponent must commission an independent experienced and suitably qualified arborist, prepare a comprehensive Report(s) prior removing any trees on the periphery and/or outside the construction as identified in the figures in Section 6 of the document referred in condition A2(b), including any tree(s) removed along Eusn Road. The Report may be prepared for the entire SSI or separate reports may be prepared for individual areas where trees are required be removed. The report(s) must identify the impacts of the SSI on trees and vegetation within and adjacent the construction. The report(s) must include: This Report B63(a) B63(b) B63(c) A visual tree assessment with inputs from the design, landscape architect, construction team; Consideration of all options amend the SSI where a tree has been identified for removal, including realignment, re of services, redesign of or re of ancillary components (such as substations, fencing etc.) and reduction of standard offsets underground services. Measures avoid the removal of trees or minimise damage existing trees and is ensure the health and stability of those trees be protected. This includes details of any proposed canopy or root pruning, excavation works, site controls on waste disposal, vehicular access, and srage of materials and protection of public utilities. Section 4a: Site Observation Section 4c: Documents Inputs, Meetings and Plans Referenced Section 4c: Documents Inputs, Meetings and Plans Referenced Section 7: Recommendations In the event that trees are be removed, then replacement trees are be planted within, or in close proximity, the SSI boundary, including along Eusn Road where feasible and reasonable. The of the trees must be determined in consultation with the relevant council(s). The replacement trees are have a minimum pot size of 75 litres. A copy of the report(s) must be submitted the Secretary for approval prior the removal, damage and/or pruning of any trees, including those affected by site establishment works. All recommendations of the report must be implemented by the Proponent, unless otherwise agreed by the Secretary. Consistent with earlier approved Reports replanting will be detailed in the Urban Design and Landscape Plan in consultation with relevant councils. 5

6 2. Study Area The study area comprises of the following areas: Approximately 65ha of land situated along and surrounding Gardeners Road. The northern and southern extents of the study area are bound by industrial buildings and offices. The western end of the foot print extends from Gardeners Road through private land, over Alexandra Burrows Road. The eastern extent is the tie in of the upgraded Gardeners Road the existing road corridor. This is presented in Map 1. Any future works that may affect trees beyond the study area will be addressed in a tree report prepared and approved before any such works. 6

7 Map 1: The study area The study area Date: 21/04/2017 Legend The study area marked in blue. 7

8 3. Scope of Works Gardeners Road will be upgraded permanently a five (5) six (6) lane carriageway with access and egress the surrounding road networks. Works include: Demolition and clearing. Earthworks. Drainage and utility works. Provision of local parking. Shared cycle and pedestrian paths. Signal upgrades. Road construction. Ancillary works. The width of the upgrade cannot be lessened without compromising safety design considerations and for this reason the design width cannot be decreased. The of the road widening is provided in Chapter 5 and is represented by the full width of the Project Deed boundary. An overview of the Project Deed Boundary, relevant this report is presented in Map 2. 8

9 Map 2: Project Deed Boundary The project deed boundary, relevant this report. Date: 11/05/2017 Legend The project deed boundary shaded. Blue is relevant this Report. Green is addressed in approved tree reports: - Bourke Road Report (Rev03) - Removals and Plantings Surface Works (Rev03). 9

10 4. Methodology a. Site observations The subject trees were inspected between 1 st December 2016 and 20 th February 2017 by. All the trees, taling 383 trees (grouped as 364 trees), within and adjacent the boundary of the project have been surveyed by a surveyor from CDS-JV. These trees have been identified in Chapter 5. Details on species; measurements of height, canopy spread, diameter at breast height (DBH), Protection Zones (TPZ) and Structural Root Zones (SRZ); and an assessment of the health and structure of the subject trees is contained in Appendix A. s located outside of the specified study area have not been included in this report. If trees located outside of the study area are likely be impacted, additional arboricultural assessment will be required. b. Visual Inspection (VTA) The subject trees were assessed in accordance with a stage one Visual Assessment (VTA) as formulated by Mattheck & Breloer (1994), and practices consistent with modern arboriculture. The following limitations apply this methodology: s were inspected from ground level, without the use of any invasive or diagnostic ols and testing. s within adjacent properties or restricted areas were not subject a complete visual inspection (i.e. defects and abnormalities may be present but not recorded). No aerial inspections or root mapping was undertaken. heights, canopy spread and diameter at breast height (DBH) was estimated, unless otherwise stated. identification was based on broad taxonomical features present and visible from ground level at the time of inspection. 10

11 c. Documents, meetings and plans referenced Inputs from the design, landscape architect and construction teams were incorporated between December 2016 and March Representatives include: CDS-JV Construction Project Manager, Local Road Works CDS-JV Senior Environment Advisor, Local Road Works CDS-JV Design Coordinar, Local Road Works Hassell Studio Landscape Architect. The CDS-JV GIS was used review tree assessment in the study area and the road design. Options amend the State Significant Infrastructure (SSI) for this area were considered. The road corridor has been designed be as narrow as possible while conforming relevant design standards. The road corridor and supporting pedestrian and cycling networks are built the boundary. Altering pathways in order retain any trees in addition that already specified in this Report would require re of the pathway in the road corridor, in third party property, or complete removal. As a result, there are no further opportunities reduce the road corridor without compromising road safety, access and design standard compliance. Utilities and services (water, sewer, communications, power) are required be installed in the al set by the public utility provider (as owners of these assets). These als are typically located in the pathway construction allow future maintenance works be carried out without working in the road corridor. The construction methodology has also been considered in preparation for this report. Pruning, non-destructive digging techniques and changes design have been considered and will be implemented so as maximize opportunities retain as many trees as possible. The final urban design and landscape plan will address the planting of trees, where feasible and reasonable, within the SSI boundary in accordance with the Conditions of Approval. The conclusions and recommendations of this report incorporates the input from the design, urban landscape and construction, identifies both trees be retained and those needed be removed in order deliver the pieces of infrastructure required by the project and are based on Australian Standard AS : Protection of s on Development Sites. 11

12 5. Locations 12

13 13

14 14

15 15

16 16

17 17

18 18

19 19

20 20

21 21

22 22

23 6. Impact Assessment & Results This impact assessment has been undertaken in accordance with the Australian Standard, AS , Protection of s on Development Sites. It includes an assessment of retention, tree, in TPZ, cause of, proposed and reasons for proposed. Results are contained in Table 2. a. Value takes in account the significance of each of the subject trees and an assessment of their health and suitability for retention within the development site (refer Appendix B). b. The of a tree is one of the primary contributing facrs the level of impact likely be sustained by the proposed construction activities. s inside the - s located within the construction cannot be retained without design modification. In order retain significant trees, design modification or the use of tree sensitive (alternative) construction methods may be recommended. s outside the - s located outside of the construction, which are not likely be significantly impacted by the proposed works can be successfully retained. These trees will require tree protection and ongoing moniring throughout the entirety of the project. s adjacent - s located adjacent the construction or proposed construction activities may be impacted. These impacts will be determined by the level of that is likely occur within the TPZ. s located within areas not yet finalised/approved for construction will require further assessment. If the final level of cannot be determined based on information provided the arborist at the time of inspection, further assessment will be required. c. Encroachment in TPZ Encroachment includes, but is not limited : excavation, compacted fill, machine trenching, ground penetration, soil disturbance. None - The tree is located outside of the proposed and is unlikely be affected by construction activities. Minor Encroachment - If the proposed is less than 10 (tal area) of the TPZ, and outside of the SRZ, detailed root investigations should not be required. The area lost this should be compensated for elsewhere, and be contiguous with the TPZ. 23

24 Major Encroachment - If the proposed is greater than 10 of the TPZ or within the SRZ, the project arborist must demonstrate that the tree(s) remain viable. This may require root investigation by nondestructive methods. The area lost this should be compensated for elsewhere, and be contiguous with the TPZ. When determining the potential impacts of in the TPZ consideration will need be made the and distribution of the roots, including above or below ground restrictions affecting root growth. Location and distribution of roots may be determined through Non-Destructive Excavation (NDE) methods such as; hydro-vacuum excavation (sucker truck), air spade and manual excavation (hand ols). Root investigation is used determine the extent and of roots within the zone of conflict. Root investigation does not guarantee the retention of the tree. d. This determines which particular part of the proposed construction activities will cause the impact the tree. e. The proposed is the recommended solution for conflicts between trees and the proposed works. Remove - is recommended for complete removal. s may be recommended for removal regardless of their. Removal may be recommended based on the species, health, structure, or risk associated with the tree. Retain - can be successfully retained. s suitable for retention will require tree protection and / or minor pruning and cutting, and ongoing moniring in order ensure their ongoing health. f. Provides a brief explanation for why the proposed was recommended. 24

25 Table 2: Impact Assessment Results No Botanical 68 Melaleuca 69 Melaleuca 70 Populus nigra 71 Melaleuca 72 Eucalyptus microcorys construction. In this area construction. In this area construction. In this area construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 25

26 73 Melaleuca 74 Melaleuca 75 Melaleuca 76 Eucalyptus microcorys 77 Corymbia construction. In this area construction. In this area construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area 26

27 78 Eucalyptus microcorys 79 Eucalyptus microcorys 80 Corymbia 81 Ficus microcarpa 82 Ficus microcarpa 83 Syzygium species Outside fooprint Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area construction. In this area construction. In this area None 0 - Retain can be retained through 27

28 84 Ulmus parvifolia 85 Melaleuca Outside fooprint Outside fooprint 86 Populus nigra 87 Populus nigra 88 Tristaniopsis laurina 89 Platanus à acerifolia None 0 - Retain can be retained through None 0 - Retain can be retained through construction. In this area construction. In this area construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 28

29 90 Platanus acerifolia 91 Tristaniopsis laurina 92 Platanus acerifolia 93 Platanus à acerifolia 94 Tristaniopsis laurina Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area 29

30 95 Tristaniopsis laurina 96a Platanus à acerifolia 96b Tristaniopsis laurina 97 Platanus à acerifolia 98 Tristaniopsis laurina 99 Platanus à acerifolia construction. In this area construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area 30

31 100 Tristaniopsis laurina 101 Platanus à acerifolia 102 Casuarina glauca 103 Casuarina glauca 104 Casuarina glauca 105 Casuarina glauca construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area 31

32 106 Casuarina glauca 107 Casuarina glauca 108 Casuarina glauca 109 Cupaniopsis anacardioides 110 Melaleuca 111 Cupaniopsis anacardioides 112 Casuarina cunninghamian a Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area construction. In this area 32

33 113 Cupaniopsis anacardioides 114 Melaleuca 115 Casuarina cunninghamian a 116 Eucalyptus microcorys 117 Melaleuca 118 Corymbia Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area construction. In this area construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 33

34 119 Corymbia 120 Eucalyptus sideroxylon 121 Corymbia 122 Corymbia 123 Corymbia 124 Cupaniopsis anacardioides 125 Cupaniopsis anacardioides 126 Casuarina cunninghamian a 127 Casuarina cunninghamian a Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 34

35 128 Casuarina cunninghamian a 129 Melaleuca 130 Melaleuca 131 Melaleuca 132 Corymbia Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area 35

36 133 Casuarina cunninghamian a 134 Casuarina cunninghamian a 135 Corymbia 137 Casuarina cunninghamian a 138 Corymbia 139 Casuarina cunninghamian a 140 Melaleuca 141 Melaleuca 142 Melaleuca 143 Corymbia construction. In this area construction. In this area construction. In this area 36

37 144 Corymbia 145 Corymbia 146 Casuarina cunninghamian a 147 Corymbia 148 Casuarina cunninghamian a 149 Casuarina cunninghamian a 150 Corymbia 151 Casuarina cunninghamian a construction. In this area construction. In this area construction. In this area construction. In this area 37

38 152 Corymbia 153 Casuarina cunninghamian a 154 Casuarina cunninghamian a 155 Casuarina cunninghamian a 156 Casuarina cunninghamian a 157 Casuarina cunninghamian a construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area construction. In this area construction. In this area 38

39 158 Corymbia 159 Casuarina cunninghamian a 160 Eucalyptus species 161 Elaeocarpus eumundii 162 Elaeocarpus eumundii construction. In this area construction. In this area construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 39

40 163 Elaeocarpus eumundii 164 Elaeocarpus eumundii 165 Elaeocarpus eumundii 166 Elaeocarpus eumundii 167 Elaeocarpus eumundii Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 40

41 168 Elaeocarpus eumundii 169 Elaeocarpus eumundii 170 Casuarina cunninghamian a 171 Corymbia 172 Corymbia 173 Corymbia Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area construction. In this area construction. In this area 41

42 174 Corymbia 175 Corymbia 176 Corymbia 177 Corymbia 178 Corymbia construction. In this area construction. In this area construction. In this area construction. In this area construction. In this area 42

43 179 Corymbia 180 Corymbia 181 Corymbia 182 Corymbia 195 Corymbia Low construction. In this area construction. In this area construction. In this area construction. In this area construction. In this area 43

44 196 Corymbia 197 Corymbia 198 Callistemon viminalis 199 Eucalyptus nicholii 200 Eucalyptus nicholii 201 Corymbia 202 Corymbia 203 Corymbia construction. In this area construction. In this area construction. In this area construction. In this area 44

45 204 Corymbia 205 Corymbia 206 Eucalyptus robusta 207 Corymbia 208 Corymbia 209 Corymbia 210 Corymbia 211 Corymbia 212 Corymbia 213 Corymbia 214 Platanus à acerifolia 215 Platanus à acerifolia Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 45

46 216 Corymbia 217 Platanus à acerifolia 219 Platanus à acerifolia 220 Corymbia 221 Corymbia 222 Corymbia 224 Corymbia 225 Corymbia 226 Corymbia construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 46

47 227 Corymbia 228 Corymbia 229 Corymbia 230 Corymbia 231 Casuarina cunninghamian a Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the 47

48 232 Casuarina cunninghamian a 234 Casuarina cunninghamian a 235 Casuarina cunninghamian a 236 Corymbia 237 Casuarina cunninghamian a Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area 48

49 238 Casuarina cunninghamian a 239 Corymbia 240 Syagrus romanzoffiana 241 Casuarina cunninghamian a 242 Corymbia 243 Corymbia Low Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area, construction. In this area, construction. In this area, 49

50 244 Melaleuca species Low 245 Acmena smithii Low 246 Melaleuca 247 Syagrus romanzoffiana 248 Syagrus romanzoffiana Low Low Low construction. In this area, construction. In this area, construction. In this area, construction. In this area, construction. In this area, 50

51 249 Acer negundo 250 Melaleuca species 251 Syzygium species 252 Liquidambar styraciflua 253 Liquidambar styraciflua Low construction. In this area, construction. In this area, construction. In this area, construction. In this area, construction. In this area, 51

52 254 Acmena smithii Low 255 Acmena smithii Low 256 Liquidambar styraciflua 257 Liquidambar styraciflua 258 Liquidambar styraciflua construction. In this area, construction. In this area, construction. In this area, construction. In this area, construction. In this area, 52

53 259 Liquidambar styraciflua 260 Jacaranda mimosifolia 261 Liquidambar styraciflua 262 Acmena smithii 263 Liquidambar styraciflua construction. In this area, construction. In this area, construction. In this area, construction. In this area, construction. In this area, 53

54 264 Callistemon species 265 Syagrus romanzoffiana Low 266 Celtis australis 267 b Syzygium species 268 Cordyline specie Low construction. In this area, construction. In this area, construction. In this area, construction. In this area, construction. In this area, 54

55 267 Liquidambar styraciflua 269 Casuarina cunninghamian a 270 Syagrus romanzoffiana 271 Casuarina cunninghamian a 271 b Liquidambar styraciflua Low construction. In this area, construction. In this area, construction. In this area, construction. In this area, construction. In this area, 55

56 272 Liquidambar styraciflua 273 Casuarina cunninghamian a 274 Callistemon viminalis 275 Liquidambar styraciflua 276 Callistemon viminalis 277 Casuarina cunninghamian a construction. In this area, construction. In this area, construction. In this area, construction. In this area, construction. In this area, 56

57 278 Platanus à acerifolia 279 Platanus à acerifolia 280 Platanus à acerifolia 281 Callistemon species 283 Platanus à acerifolia 284 Melaleuca 285 Melaleuca 286 Melaleuca construction. In this area construction. In this area construction. In this area construction. In this area 57

58 287 Platanus à acerifolia 288 Melaleuca 289 Platanus à acerifolia 290 Platanus à acerifolia 291 Melaleuca 292 Melaleuca 293 Melaleuca construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area 58

59 294 Eucalyptus species 295 Pitsporum undulatum 296 Melaleuca 297 Eucalyptus species 298 Casuarina cunninghamian a 299 Melaleuca 300 Eucalyptus microcorys 301 Eucalyptus microcorys 302 Casuarina cunninghamian a construction. In this area Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area 59

60 303 Eucalyptus microcorys 304 Eucalyptus microcorys 305 Melaleuca 306 Melaleuca 308 Callistemon viminalis 309 Grevillea robusta Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area Minor <10 Construction Retain can be retained through encroach significantly in the construction. In this area, demolition, excavation, drainage installation and backfill using 60

61 310 Melaleuca 311 Melaleuca 312 Melaleuca 313 Melaleuca 314 Melaleuca construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using 61

62 315 Melaleuca 316 Melaleuca 317 Melaleuca 318 Melaleuca 319 Melaleuca construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using 62

63 320 Melaleuca 321 Melaleuca 322 Melaleuca 323 Melaleuca 324 Melaleuca Low construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using 63

64 325 Casuarina glauca 326 Casuarina glauca 327 Casuarina glauca 328 Casuarina glauca 329 Casuarina glauca Low construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using 64

65 330 Casuarina glauca 331 Casuarina glauca 332 Casuarina glauca 333 Casuarina glauca 334 Casuarina glauca construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using 65

66 335 Casuarina glauca 336 Casuarina glauca 337 Casuarina glauca 338 Casuarina glauca 339 Callistemon viminalis Low construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, demolition, excavation, drainage installation and backfill using construction. In this area, multiple 66

67 340 Tristaniopsis laurina 341 Tristaniopsis laurina 342 Tristaniopsis laurina 343 Casuarina glauca 344 Casuarina glauca construction. In this area construction. In this area construction. In this area construction. In this area, multiple construction. In this area, multiple 67

68 345 Casuarina glauca 346 Casuarina glauca 347 Casuarina glauca 348 Casuarina glauca 349 Casuarina glauca construction. In this area, multiple construction. In this area, multiple construction. In this area, multiple construction. In this area, multiple construction. In this area, multiple 68

69 350 Casuarina glauca 351 Casuarina glauca 352 Platanus orientalis 353 Platanus orientalis 354 Platanus orientalis construction. In this area, multiple construction. In this area, multiple construction. In this area, multiple construction. In this area, multiple construction. In this area, multiple 69

70 355 Platanus orientalis 366 Eucalyptus microcorys 367 Eucalyptus microcorys 368 Eucalyptus microcorys 369 Eucalyptus microcorys construction. In this area, multiple construction. In this area construction. In this area construction. In this area construction. In this area 70

71 403 Syagrus romanzoffiana 370 Melaleuca 372 Tristaniopsis laurina 373 Platanus orientalis 374 Tristaniopsis laurina Low Low construction. In this area construction. In this area construction. In this area, multiple construction. In this area construction. In this area 71

72 375 Tristaniopsis laurina 376 Tristaniopsis laurina 377 Tristaniopsis laurina 378 Tristaniopsis laurina 379 Tristaniopsis laurina Low Low Low construction. In this area construction. In this area encroach significantly in the construction. In this area construction. In this area 72

73 380 Alnus oblongifolia 381 Alnus oblongifolia 382 Alnus oblongifolia 383 Alnus oblongifolia 384 Alnus oblongifolia Low Low Low Low Low Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the 73

74 385 Eucalyptus microcorys 386 Jacaranda mimosifolia 387 Tristaniopsis laurina 388 Melaleuca 389 Tristaniopsis laurina Low construction. In this area Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area construction. In this area Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the 74

75 390 Tristaniopsis laurina 391 Eucalyptus microcorys 392 Tristaniopsis laurina 393 Tristaniopsis laurina 394 Tristaniopsis laurina Low construction. In this area construction. In this area construction. In this area construction. In this area construction. In this area 75

76 395 Tristaniopsis laurina 396 Tristaniopsis laurina 397 Alnus oblongifolia 398 Alnus oblongifolia 399 Alnus oblongifolia Low Low Low construction. In this area construction. In this area Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the 76

77 400 Alnus oblongifolia 401 Alnus oblongifolia 402 Alnus oblongifolia 404 Melaleuca 405 Melaleuca Low Low Low Low Low Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the construction. In this area construction. In this area 77

78 600 Eucalyptus microcorys 601 Eucalyptus microcorys Low 602 Celtis australis Low 605 Melaleuca 606 Eucalyptus grandis 607 Casuarina cunninghamian a 608 Eucalyptus punctata Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 78

79 609 Melaleuca 610 Melaleuca 611 Melaleuca 612 Melaleuca 613 Melaleuca Low Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >40 - <100 Construction Remove Subject tree cannot be retained under encroach significantly in the 79

80 614 Melaleuca Low 616 Syzygium sp. Outside fooprint 617 Syzygium sp. Low Outside fooprint 618 Syzygium sp. Outside fooprint 619 Syzygium sp. Outside fooprint 620 Syzygium sp. Outside fooprint 621 Syzygium sp. Outside fooprint 622 Corymbia 623 Corymbia 624 Callistemon viminalis Low Outside fooprint construction. In this area None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through construction. In this area construction. In this area None 0 - Retain can be retained through 80

81 626 Casuarina glauca 627 Corymbia 628 Phoenix canariensis 630 Phoenix canariensis 634 Casuarina cunninghamian a 635 Melaleuca Low Low construction. In this area construction. In this area Minor <10 Construction Retain can be retained through Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the Major >25 - <40 Construction Remove Subject tree cannot be retained under encroach significantly in the 81

82 No 626 b 268 b B1 B2 B3 B4 B5 B6 B7 B8 B9 Botanical Corymbia Low Yakka sp. Low Corymbia Eucalyptus saligna Corymbia Cupaniopsis anacardioides Melaleuca Melaleuca Melaleuca Melaleuca Melaleuca Low construction. In this area encroach significantly in the None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through 82

83 No B10 B11 B12 B13 B14 Botanical Melaleuca Melaleuca Melaleuca Melaleuca Melaleuca Low within road corridor construction for bridges 8&9 and supporting utility work. In this area, excavation, conduit placement and backfill using geotechnically stable layers is required. within road corridor construction for bridges 8&9 and supporting utility work. In this area, excavation, conduit placement and backfill using geotechnically stable layers is required. within road corridor construction for bridges 8&9 and supporting utility work. In this area, excavation, conduit placement and backfill using geotechnically stable layers is required. within road corridor construction for bridges 8&9 and supporting utility work. In this area, excavation, conduit placement and backfill using geotechnically stable layers is required. within road corridor construction for bridges 8&9 and supporting utility work. In this area, excavation, conduit placement and backfill using geotechnically stable layers is required. 83

84 No B15 B16 B17 B18 B19 A1 A1 Botanical Melaleuca Melaleuca Melaleuca Melaleuca Melaleuca Casurina species Casurina species within road corridor construction for bridges 8&9 and supporting utility work. In this area, excavation, conduit placement and backfill using geotechnically stable layers is required. None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through None 0 - Retain can be retained through Major 100 Construction Remove Group of 20 trees between two points. Subject trees cannot be retained under construction not viable as trees are wholly within road corridor construction for bridges 8&9 and supporting utility work. In this area, demolition, excavation, drainage installation and backfill using Major 100 Construction Remove Group of 20 trees between two points. Subject trees cannot be retained under construction not viable as trees are wholly within road corridor construction for bridges 8&9 and supporting utility work. In this area, demolition, excavation, drainage installation and backfill using 84

85 No A2 Botanical Casurina species Major 100 Construction Remove Group of two trees. Subject trees cannot be retained under construction not viable as trees are wholly within road corridor construction for bridges 8&9 and supporting utility work. In this area, demolition, excavation, drainage installation and backfill using 85

86 7. Recommendations A tal of 383 trees (grouped as 364 trees) were inspected and assessed within the study area. 285 trees (grouped as 266 trees) are marked for removal. 98 trees are marked for retention. 219 trees (grouped as 200 trees) are located wholly within the development and cannot be retained due the need conduct significant excavation and / or filling in order deliver the required infrastructure. These trees are recommended for removal. 154 trees are adjacent the development. 66 have been recommended for removal as they will be significantly impacted by fill required build the road corridor, pedestrian and shared pathways, install utilities and deliver the new bridge connecting Gardeners Road the St Peters Interchange. Permission from the landholder must be obtained prior removal of trees on third party land. 88 trees have been recommended for retention. These trees are located adjacent the proposed works and will require tree sensitive construction techniques and/or further arboricultural input in order reduce impacts these trees. 10 trees are outside the and are not anticipated be impacted by the works. a. protection The following tree protection measures will be required for the 88 trees adjacent the works that are suitable for retention (see Table 2). protection fencing must be established around the perimeter of the TPZ of potentially affected trees. If the protective fencing requires temporary removal, trunk, branch and ground protection must be installed and must comply with AS Protection of trees on development sites. Any additional construction activities within the TPZ of the subject trees must be assessed and approved by the project arborist, and must comply with AS Protection of trees on development sites. If any changes are made Protection Fencing it must be authorised by the site arborist prior the fencing being removed. Further information and guidelines on tree protection if required can be provided by. b. Inspections The site arborist or equivalent will supervise excavations within the TPZ of trees being retained. Scheduled inspections should be undertaken for all subject trees assessed for retention during the course of construction. Normally this is every two (2) weeks. Site diary for Arboricultural works must be kept at the onsite 86

87 office for the duration of the project. All matters pertaining tree management must be documented in this diary and signed of as each issue is resolved. s outside of the study area that may be impacted during the works will require additional Arboricultural Assessment. 87

88 c. work All pruning and/or tree removal work is be carried out by, or under supervision of, an arborist with a minimum AQF Level 3 qualification in Arboriculture or equivalent. All pruning must be in accordance with Australian Standard AS , Pruning of Amenity s. All pruning and/or tree removal work is be carried out in accordance with the NSW WorkCover Code of Practice for the Amenity Industry (1998). Reference should also be undertaken for any tree works the SafeWork Australia Guide Managing Risks of Trimming and Removal Work Permission must be granted from the relevant consent authority, prior removing or pruning of any of the subject trees. material be used for landscaping where practical or disposed of offsite. 88

89 References Australian Standard, AS , Pruning of Amenity s. Australian Standard, AS , Protection of s on Development Sites. Mattheck, C & Breloer, H (1994) Field Guide for Visual Assessment Arboricultural Journal, Vol 18 pp SafeWork Australia Guide Managing Risks of Trimming and Removal Work WorkCover NSW Code of Practice: Amenity Industry 89

90 Appendix A: Schedule No Botanical Height Spread DBH TPZ SRZ Health Structure Coordinates Coordinates Groups (m) (m) (mm) (m) (m) 68 Melaleuca Good Good Melaleuca Good Good Populus nigra Good Good Melaleuca Good Good Eucalyptus microcorys Good Fair Melaleuca Good Good Melaleuca Good Good Melaleuca Good Good Eucalyptus microcorys Good Good Corymbia Good Good Eucalyptus microcorys Good Good Eucalyptus microcorys Good Good Corymbia Fair Good Ficus microcarpa Good Good Ficus microcarpa Good Good Syzygium species Good Good Ulmus parvifolia Good Good Melaleuca Good Good Populus nigra Good Fair Populus nigra Good Fair Tristaniopsis laurina Good Good Platanus à acerifolia Good Good Platanus acerifolia Good Good Tristaniopsis laurina Good Fair Platanus acerifolia Good Good Platanus à acerifolia Good Fair Tristaniopsis laurina Good Fair Tristaniopsis laurina Good Fair a Platanus à acerifolia Good Good b Tristaniopsis laurina Good Good Platanus à acerifolia Good Good

91 Height Spread DBH TPZ SRZ Health Structure Coordinates Coordinates Groups (m) (m) (mm) (m) (m) 98 Tristaniopsis laurina Good Good Platanus à acerifolia Good Good Tristaniopsis laurina Good Fair Platanus à acerifolia Good Good Casuarina glauca Good Fair Casuarina glauca Good Good Casuarina glauca Good Good Casuarina glauca Good Fair Casuarina glauca Good Fair Casuarina glauca Good Good Casuarina glauca Good Fair Cupaniopsis anacardioides Good Good Melaleuca Good Fair Cupaniopsis anacardioides Good Fair Casuarina cunninghamiana Good Fair Cupaniopsis anacardioides Good Good Melaleuca Fair Fair Casuarina cunninghamiana Fair Fair Eucalyptus microcorys Good Good Melaleuca Fair Fair Corymbia Good Good Corymbia Good Good Eucalyptus sideroxylon Fair Fair Corymbia Good Good Corymbia Good Good Corymbia Good Good Cupaniopsis anacardioides Good Good Cupaniopsis anacardioides Good Good Casuarina cunninghamiana Good Good Casuarina cunninghamiana Good Good Casuarina cunninghamiana Good Good Melaleuca Good Fair Melaleuca Good Fair Melaleuca Good Fair Corymbia Good Good

92 Height Spread DBH TPZ SRZ Health Structure Coordinates Coordinates Groups (m) (m) (mm) (m) (m) 133 Casuarina cunninghamiana Good Good Casuarina cunninghamiana Good Good Corymbia Good Good Casuarina cunninghamiana Good Good Corymbia Good Good Casuarina cunninghamiana Good Good Melaleuca Good Fair Melaleuca Good Good Melaleuca Good Good Corymbia Good Good Corymbia Good Good Corymbia Good Good Casuarina cunninghamiana Good Good Corymbia Good Good Casuarina cunninghamiana Good Good Casuarina cunninghamiana Good Good Corymbia Good Good Casuarina cunninghamiana Good Fair Corymbia Good Good Casuarina cunninghamiana Good Good Casuarina cunninghamiana Good Good Casuarina cunninghamiana Good Good Casuarina cunninghamiana Good Good Casuarina cunninghamiana Good Good Corymbia Good Good Casuarina cunninghamiana Good Good Eucalyptus species Good Good Elaeocarpus eumundii Good Good Elaeocarpus eumundii Good Good Elaeocarpus eumundii Good Good Elaeocarpus eumundii Good Good Elaeocarpus eumundii Fair Good Elaeocarpus eumundii Good Good Elaeocarpus eumundii Good Good Elaeocarpus eumundii Good Good

ARBORICULTURAL REPORT

ARBORICULTURAL REPORT ARBORICULTURAL REPORT Euston Rd Widening and 132kV Service Investigation WestConnex New M5. Prepared for CDS-JV. 03 March 2017 CDS-JV Document Number M5N-ES-RPT-LRW-0001 (Rev 03) ATC 16-130 Arboricultural

More information

CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION 7.1 TREE PROTECTION AREAS

CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION 7.1 TREE PROTECTION AREAS CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION Urban trees need to be protected from damage to maximize their health, safety, benefits and functionality. Mature, young and newly transplanted trees need

More information

Tree Management Plan

Tree Management Plan Tree Management Plan Project: Parnell Prepared For: By: Newmarket Level Crossing Cowie Street, Opus International Consultants Matthew Paul Date: 4/09/17 1 Contents 1.0 Scope of Tree Management Plan 2 2.0

More information

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION City of Santa Monica Community Maintenance Department Public Landscape Division 2600 Ocean Park Blvd. Santa Moni ca, CA 90405 (310) 458-8974

More information

SEARs project justification and conclusion

SEARs project justification and conclusion 31 Project justification and conclusion This chapter presents a justification for the project and a conclusion to the environmental impact statement (EIS). The justification is based on the strategic need

More information

An indicative program for works to be conducted within the Sydney Park construction compound is provided in Table 6-20.

An indicative program for works to be conducted within the Sydney Park construction compound is provided in Table 6-20. The land required for the Sydney Park construction compound would be used temporarily throughout construction only. The construction compound site would be rehabilitated at the completion of construction,

More information

Construction Contaminated Land Management Plan

Construction Contaminated Land Management Plan Construction Contaminated Land Project Name: WestConnex New M5 Project number: 15.7020.2597 Document number: M5N-ES-PLN-PWD-0033 Revision date: 1 June 2016 Revision: 01 Document Approval Rev. Date Prepared

More information

Table 1 below details the species, size and condition of the trees presently on the property.

Table 1 below details the species, size and condition of the trees presently on the property. Phil Castro Richcraft Group of Companies 2280 St. Laurent Blvd. Ottawa, ON K1G 4K1 P.O. Box 13593, Ottawa, ON K2K 1X6 Telephone: (613) 839-0101 Fax: (613) 839-0114 Website: www.ifsassociates.ca URBAN FORESTRY

More information

Chapter 4 Planning and statutory requirements. Chapter 4 Planning and statutory requirements

Chapter 4 Planning and statutory requirements. Chapter 4 Planning and statutory requirements Chapter 4 Planning and statutory requirements Chapter 4 Planning and statutory requirements Contents Page number 4. Planning and statutory requirements 4-1 4.1 Approval under the EPBC Act 4-1 4.1.1 Controlled

More information

Arbor Vitae Tree Consultants Tree Assessment Report

Arbor Vitae Tree Consultants Tree Assessment Report Arbor Vitae Tree Consultants Tree Assessment Report Bob Ambardar Manager City of White Rock Engineering and Aelicia Otto Arborist/Horticulturalist City of White Rock 1-October-2014 Re: Review of sidewalk

More information

Tree Protection Policy

Tree Protection Policy Appendix F Tree Protection Policy The following is according to the City of Hamilton s special provision SP-97. General Tree Protection shall be in accordance with OPSS 801 as amended by this special provision.

More information

DUKE UNIVERSITY DESIGN GUIDELINES

DUKE UNIVERSITY DESIGN GUIDELINES 1 Tree Protection Zones (TPZs) 1. Introduction A. Tree Protection Zones shall be established around all trees not slated for removal which are located within the construction envelope, or located within

More information

3 Resolution adopting the 2013 San Francisco Street Tree Recommendations List.

3 Resolution adopting the 2013 San Francisco Street Tree Recommendations List. File No. 201 3-03-UFC Resolution No. 003-13-UFC 1 [San Francisco Street Tree Recommendations List] 2 3 Resolution adopting the 2013 San Francisco Street Tree Recommendations List. 4 WHEREAS, The San Francisco

More information

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE14-00XXX Applicant: Job Description:

More information

B. The purpose of the meeting shall be to establish the conditions of all existing trees upon receipt of the Project site by the Contractor. Failure t

B. The purpose of the meeting shall be to establish the conditions of all existing trees upon receipt of the Project site by the Contractor. Failure t Standard Specification SECTION 01 56 39 TREE AND PLANT PROTECTION PART 1 - GENERAL 1.1 WORK INCLUDED A. Perform all Work necessary and required to protect and maintain all trees, shrubs, groundcover and

More information

TREE PRESERVATION SUMMARY

TREE PRESERVATION SUMMARY Froggers Creek Tree Consultants Ltd. 7763 McGregor Avenue Burnaby BC, V5J4H4 Telephone: 604-721-6002 glenn_murray@shaw.ca City of Vancouver May 19, 2016 Community Services 453 W. 12th Avenue Vancouver,

More information

Vegetation management on private land

Vegetation management on private land City Plan guideline Managing assessable vegetation Vegetation within the City of Gold Coast is managed through the Vegetation management code of the City Plan. The purpose of the code is to provide for

More information

ARBORIST REPORT. Report History: Report 1 New design

ARBORIST REPORT. Report History: Report 1 New design Community Development Department City of Saratoga 13777 Fruitvale Avenue Saratoga, California 95070 ARBORIST REPORT Application No. ARB15-0025 Prepared by Kate Bear, City Arborist Site: 21459 Saratoga

More information

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Appendix A RFP No. 894-2014 Page 1 of 1 Template Version: SrC120131129 - Consulting Services RFP APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Revision: 2014-09-22 DEFINITION OF

More information

Landscaping and Fencing

Landscaping and Fencing Landscaping and Fencing Fences, driveways, paving, retaining walls, landscaping & other garden features To be read in conjunction with General Requirements: A guide to building on properties containing

More information

SOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands

SOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands SOUTH FLORIDA WATER MANAGEMENT DISTRICT Question 13: Wetlands 1. The wetland responses and topographical data provided in the ADA for the 520- acre project site are conceptual in nature. The referenced

More information

Roads and Maritime Services

Roads and Maritime Services November 2015 Prepared for Prepared by AECOM Australia The concepts and information contained in this document are the property of Roads and Maritime Services. You must not reproduce any part of this document

More information

CITY OF BURNABY BYLAW NO *******

CITY OF BURNABY BYLAW NO ******* Burnaby Tree Bylaw Page 1 CITY OF BURNABY BYLAW NO. 10482 (Consolidated for convenience with Bylaw No. 10759, 10891, 10917, 10963, 10968, 11189, 11331, 11485, 11670, 11846, 12035, 12191, 12298, 12377,

More information

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON.

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON. REQUEST FOR TENDER - SERVICES 1. PURPOSE AND SCOPE This specification is intended to govern the supply of all labour, materials and equipment for the dismantling, demolition of a single dwelling on the

More information

RE: BANKSTOWN BUSINESS ESTATE - Site Remediation Strategy

RE: BANKSTOWN BUSINESS ESTATE - Site Remediation Strategy Gemma Wawn, Leda Holdings Pty Ltd, Level 11, 5 Hunter Street, SYDNEY NSW 2000 Email: g.wawn@ledaholdings.com.au 23 June 2015 RE: BANKSTOWN BUSINESS ESTATE - Site Remediation Strategy CES Ref: CES131004-LED-AB

More information

Hamilton Rapid Transit Preliminary Design and Feasibility Study

Hamilton Rapid Transit Preliminary Design and Feasibility Study Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT DESIGN BRIEF Version:1.0 Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 610S.1 This item shall govern the proper care and treatment of all trees and other vegetation

More information

Consultancy / Reports / Site Monitoring / Tree Surveying / Tree Safety Inspections / Design Reviews. Memorandum

Consultancy / Reports / Site Monitoring / Tree Surveying / Tree Safety Inspections / Design Reviews. Memorandum Consultancy / Reports / Site Monitoring / Tree Surveying / Tree Safety Inspections / Design Reviews Memorandum To: Benedict Free Arboricultural and Landscape Advisor, Auckland Council From: Sean McBride

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

CITY OF MAPLE RIDGE TREE PROTECTION & MANAGEMENT BYLAW BYLAW NO

CITY OF MAPLE RIDGE TREE PROTECTION & MANAGEMENT BYLAW BYLAW NO THE FOLLOWING DOCUMENT HAS BEEN REPRODUCED FOR CONVENIENCE ONLY and is a consolidation of the following: 1. Maple Ridge Tree Protection & Management Bylaw No. 7133-2015 2. Maple Ridge Tree Protection &

More information

ARBORICULTURAL REPORT ARBORICULTURAL IMPACT ASSESSMENT

ARBORICULTURAL REPORT ARBORICULTURAL IMPACT ASSESSMENT AUSTRALIAN CATHOLIC UNIVERSITY 115B VICTORIA PARADE, FITZROY PREPARED BY Simon Howe Consultant Arborist B.AppSci(Hort) GradDip Plan&Des (LandscpArch) MELB October 2016 TABLE OF CONTENTS 1 Introduction...

More information

Tree Protection & Preservation

Tree Protection & Preservation IV. Tree Protection & Preservation A. Participation at the Construction Planning Stage 1. All Contracted Design Services shall receive a copy Tree Care Plan Sections appropriate to the given project as

More information

Request for Proposal & Statement of Qualifications

Request for Proposal & Statement of Qualifications Request for Proposal & Statement of Qualifications TREE and ELDERBERRY RELOCATION/TRANSPLANTING Natomas Levee Improvement Program Mandatory Pre Proposal Site Walk: September 09, 2009 10:30 AM Submit Questions

More information

Construction Waste and Resource Sub-Plan

Construction Waste and Resource Sub-Plan Construction Waste and Resource Sub-Plan Project Name: WestConnex New M5 Project number: 15.7020.2597 Document number: M5N-ES-PLN-PWD-0008 Revision date: 9/08/2016 Revision: 06 Document Approval Rev. Date

More information

Stage 4 Geotechnical Investigations Information Sheet

Stage 4 Geotechnical Investigations Information Sheet Stage 4 Geotechnical Investigations Information Sheet Geotechnical specialists will use a range of equipment to examine ground conditions by either excavating small shallow test pits of soil, using a mechanical

More information

City of Kingston Tree By-Law Guidelines

City of Kingston Tree By-Law Guidelines City of Kingston The maintenance of mature tree cover is recognized as contributing to human health and quality of life and therefore it is the City s goal to increase the urban forest. Trees are an important

More information

Compliance Tracking Program

Compliance Tracking Program Tracking Program Project Name: WestConnex New M5 Project number: 15.7020.2597 number: M5N-ES-PRG-PWD-0002 Revision date: 21/07/2016 Revision: 01 Rev. Prepared by Reviewed by 00 06/06/16 CDS-JV 01 21/07/16

More information

(as amended) Adopted September 5, 2006 Reprint May 2011 BEACH LAND CODE SITE DEVELOPMENT FERNANDINA DESIGN REQUIR CHAPTER. Ordinance EMENTS

(as amended) Adopted September 5, 2006 Reprint May 2011 BEACH LAND CODE SITE DEVELOPMENT FERNANDINA DESIGN REQUIR CHAPTER. Ordinance EMENTS EQUIR.05.09 Tree Protection Requirements A. The intent of this section is to provide standards and regulations that will ensure a minimum number of trees on any lot or parcel, protect and preserve native

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

Chatswood to Sydenham Staging Report

Chatswood to Sydenham Staging Report Unclassified Chatswood to Sydenham Staging Report Project: City & Southwest Date: 15 February 2018 Group: City & Southwest Project Delivery Status: Final Author: Sydney Metro Delivery Office Revision:

More information

Tree Conservation Report 1960 Scott Street, Ottawa, Ontario

Tree Conservation Report 1960 Scott Street, Ottawa, Ontario 1960 Scott Street, Ottawa, Ontario April 2016 Prepared for Kelly Rhodenizer, Colonnade BridgePort Colonnade BridgePort April 18 th, 2016 100 Argyle Avenue, Suite 100 Ottawa, Ontario, K2P 1B6 Attn: Kelly

More information

TREE PROTECTION/PRESERVATION POLICY

TREE PROTECTION/PRESERVATION POLICY TREE PROTECTION/PRESERVATION POLICY THE CORPORATION OF THE TOWN OF AURORA PARKS AND RECREATION SERVICES 100 John West Way, Aurora, Ontario, L4G-6J1 T.905-727-3123 F.905-727-3903 www.aurora.ca JUNE 2015

More information

Sunnyside Heights (Grandview Heights Area #2) Neighbourhood Concept Plan (NCP) - Engineering Servicing and Financial Strategies

Sunnyside Heights (Grandview Heights Area #2) Neighbourhood Concept Plan (NCP) - Engineering Servicing and Financial Strategies CORPORATE REPORT NO: R236 COUNCIL DATE: November 15, 2010 REGULAR COUNCIL TO: Mayor & Council DATE: November 10, 2010 FROM: General Manager, Engineering FILE: 6520-20 (GH#2) SUBJECT: Sunnyside Heights

More information

Fax: (613) January 16, 2015 L3R 1R2. Dear David, by the City permit to. remove the. will be lost. Table 1. Tree No. 1. D.B.

Fax: (613) January 16, 2015 L3R 1R2. Dear David, by the City permit to. remove the. will be lost. Table 1. Tree No. 1. D.B. P.O. Box 13593, Ottawa, ON K2KK 1X6 Telephone: (613) 838-5717 Fax: (613) 839-0114 Website: www.ifsassociates.ca Urban Forestry & Forest Management Consulting January 16, 2015 David Johnston Architect Ltd.

More information

Application for Planning Consent

Application for Planning Consent Application for Planning Consent Essendon Airport Essendon Fields House Level 2, 7 English Street Essendon Fields, VIC, 3041 T: +61 3 9948 9400 The use of land and building works at Essendon Airport (including

More information

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES PART I GENERAL 1.02 The objective of this section is to reduce the negative impacts of construction on trees. Tree protection

More information

CITY OF VIRGINIA BEACH CITY CODE APPENDIX E TREE PLANTING, PRESERVATION AND REPLACEMENT*

CITY OF VIRGINIA BEACH CITY CODE APPENDIX E TREE PLANTING, PRESERVATION AND REPLACEMENT* City of Virginia Beach, VA City Code / Zoning Ordinance Abstracted January 2008 http://www.vbgov.com/file_source/dept/mcg/web%20page/hot%20topics/gree nribboncommittee/documents/naturalresourcemanagementsubcommittee/appen

More information

74 Subdivision Rules - Business 1, 2, 3, 4, Town Basin, Marsden Point Port, Port Nikau and Airport Environments

74 Subdivision Rules - Business 1, 2, 3, 4, Town Basin, Marsden Point Port, Port Nikau and Airport Environments 74 Subdivision Rules - Business 1, 2, 3, 4, Town Basin, Marsden Point Port, Port Nikau and Airport 74.1 Introduction This chapter contains subdivision rules for the Business 1, 2, 3, 4, Town Basin, Marsden

More information

TORONTO MUNICIPAL CODE CHAPTER 813, TREES. Chapter 813 TREES. ARTICLE I Inspection; Removal of Infested Trees

TORONTO MUNICIPAL CODE CHAPTER 813, TREES. Chapter 813 TREES. ARTICLE I Inspection; Removal of Infested Trees Chapter 813 TREES ARTICLE I Inspection; Removal of Infested Trees 813-1. Inspection for presence of Asian Long-Horned Beetles and other pests; removal of infested trees. 813-2. Right to enter private property.

More information

Draft Policy Review. Use of Shipping Containers

Draft Policy Review. Use of Shipping Containers Draft Policy Review Use of Shipping Containers Policy Number: Policy Section: Policy Title: T.01.02 Town Planning Use of Shipping Containers File Reference: OBJECTIVES: 1. To maintain the amenity of the

More information

BMPs TO CONSERVE WOODED AREAS AT THE SUBDIVISION LEVEL

BMPs TO CONSERVE WOODED AREAS AT THE SUBDIVISION LEVEL BMPs to Conserve Wooded Areas 31 BMPs TO CONSERVE WOODED AREAS AT THE SUBDIVISION LEVEL Audience This section is primarily directed toward: local units of government, landowners and developers, builders

More information

Auckland Transport Code of Practice 2013

Auckland Transport Code of Practice 2013 26 Corridor Access Management 26.1 Background Auckland Transport is the Road Controlling Authority and Corridor Manager for all public roads within the Auckland Region (except motorways and state highways

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT Principal Contractor: ROBERT LIVINGSTONE Project Address: 123 SYDNEY ROAD SYDNEY NSW 2000 High Risk Work Hazards and Risks Identified Control Measures Persons working at a height

More information

THAKAR ASSOCIATES DESIGN CONSULTANTS

THAKAR ASSOCIATES DESIGN CONSULTANTS THAKAR ASSOCIATES DESIGN CONSULTANTS 54 Bennett Street, Ottawa, Ontario K1V 9L4 Tel.:(613) 523-7602 Fax:(613) 523-2262 E-mail:mail@thakarassociates.com 25 September, 2012 Mr. Richard Martineau Longwood

More information

TREE PRESERVATION & PROTECTION PERMIT APPLICATION INSTRUCTIONS

TREE PRESERVATION & PROTECTION PERMIT APPLICATION INSTRUCTIONS TREE PRESERVATION & PROTECTION PERMIT APPLICATION INSTRUCTIONS Intent of Ordinance The Township finds that trees and woodlands are an important asset to the natural ecosystem, beneficially contribute to

More information

Sydney Metro Underground Corridor Protection

Sydney Metro Underground Corridor Protection Transport for NSW Sydney Metro Technical Services 16 October 2017 Document No: NWRLSRT-PBA-SRT-TU-REP-000008 Revision No: 1 Document information Client: Transport for NSW Title: Sydney Metro - Technical

More information

Parks, Forestry & Recreation Urban Forestry. Tree Protection Policy and Specifications for Construction Near Trees

Parks, Forestry & Recreation Urban Forestry. Tree Protection Policy and Specifications for Construction Near Trees Parks, Forestry & Recreation Urban Forestry Tree Protection Policy and Specifications for Construction Near Trees Table of Contents 1. Introduction... 3 Types of Tree Damage... 3 2. Protecting Trees...

More information

Landscape Services QA/QC Manual Sample Selected pages (not a complete plan)

Landscape Services QA/QC Manual Sample Selected pages (not a complete plan) Landscape Services QA/QC Manual Sample Selected pages (not a complete plan) Reporting Forms Inspection Forms Contact: Ed Caldeira 410-451-8006 Pat [Pick the date] [CompanyName] Landscape Services Operating

More information

7. Value Management Workshop

7. Value Management Workshop 7. Value Management Workshop 7.1 Introduction A two day Value Management Workshop (VMW) was held on 12 and 13 December 2005. The value management workshop was used to review and assess the four route options

More information

ADOPTION OF CHAPTER 120 (TREE CONSERVATION ORDINANCE) OF THE 1976 CODE OF THE COUNTY OF FAIRFAX, VIRGINIA

ADOPTION OF CHAPTER 120 (TREE CONSERVATION ORDINANCE) OF THE 1976 CODE OF THE COUNTY OF FAIRFAX, VIRGINIA ADOPTION OF CHAPTER 120 (TREE CONSERVATION ORDINANCE) 36-07-120 (Also see Heritage, Specimen, Memorial and Street Trees Ordinances 37-07-N adopted simultaneously on October 15, 2007) OF THE 1976 CODE OF

More information

TREE AND LARGE SHRUB REPORT Golden Gate Park Soccer Fields

TREE AND LARGE SHRUB REPORT Golden Gate Park Soccer Fields TREE AND LARGE SHRUB REPORT Golden Gate Park Soccer Fields PREPARED FOR: City Fields Foundation 1714 Stockton Street, Suite 400 San Francisco CA 94133 PREPARED BY: HortScience, Inc. 2150 Rheem Drive, Suite

More information

DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3

DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3 DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3 This chapter provides details regarding the scope of the proposed Gourikwa Power Station and Transmission Integration

More information

SPECIFICATION FOR NOISE MITIGATION

SPECIFICATION FOR NOISE MITIGATION SPECIFICATION FOR NOISE MITIGATION 1. SCOPE This specification covers the design, construction, documentation and postconstruction review of state highway road-traffic noise mitigation. This specification

More information

9.3.9 Industry uses code

9.3.9 Industry uses code 9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

Developer Services. Building over or near a sewer. DEV 005G Guidance notes and procedure. What is a public sewer?

Developer Services. Building over or near a sewer. DEV 005G Guidance notes and procedure. What is a public sewer? Developer Services DEV 005G Guidance notes and procedure Building over or near a sewer If you are thinking of building a structure (for example, a new building, extension, conservatory, garage etc.) you

More information

Table of Contents. TABLE OF CONTENTS i 1

Table of Contents. TABLE OF CONTENTS i 1 Table of Contents Section 1: DEFINITIONS... 1 Section 2: CAPITAL IMPROVEMENT PROJECTS... 1 2.1 PURPOSE... 1 2.2 PRE-PROJECT PROPOSAL... 1 2.3 DESIGN REVIEW... 2 2.4 PROJECT ADVERTISEMENT... 2 2.5 PROJECT

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

Leasing of Railway Land

Leasing of Railway Land Discipline: Engineering (Track & Civil) Category: Standard Leasing of Railway Land ETD-17-01 Applicability New South Wales CRIA (NSW CRN) Primary Source ARTC NSW Standard EGS 08 Document Status Version

More information

Rail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock

Rail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock 1/16 Management of Rolling Stock Revision Date Comments 1 January 2011 Procedure developed to support SMS and legislative requirements. 2 February 2012 Reviewed with RISSB Standards and change of titles

More information

JOSHUA TREE SURVEY REPORT FOR THE BURRTEC WASTE AND RECYCLING SERVICES YUCCA VALLEY FACILITY YUCCA VALLEY, SAN BERNARDINO COUNTY, CALIFORNIA

JOSHUA TREE SURVEY REPORT FOR THE BURRTEC WASTE AND RECYCLING SERVICES YUCCA VALLEY FACILITY YUCCA VALLEY, SAN BERNARDINO COUNTY, CALIFORNIA JOSHUA TREE SURVEY REPORT FOR THE BURRTEC WASTE AND RECYCLING SERVICES YUCCA VALLEY FACILITY YUCCA VALLEY, SAN BERNARDINO COUNTY, CALIFORNIA Prepared By: Lake Elsinore, California 92530 (909) 772-9009

More information

Events in the Park Lands

Events in the Park Lands Events in the Park Lands Overview The Adelaide Park Lands were set aside for public use more than 170 years ago and are highly valued by the people of South Australia as the City s primary community space.

More information

Windthrow of Trees: Storms or Management

Windthrow of Trees: Storms or Management Windthrow of Trees: Storms or Management Greg Moore School of Ecosystem and Forest Sciences International Society of Arboriculture Conference, Florida 12 August 2015 People often assume that trees fall

More information

CIRCULAR GENERAL PROVISIONS

CIRCULAR GENERAL PROVISIONS MINISTRY OF CONSTRUCTION -------- SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness --------------- No. 10/2013/TT-BXD Hanoi, July 25, 2013 CIRCULAR ON CONSTRUCTION QUALITY MANAGEMENT Pursuant

More information

Arboricultural Assessment

Arboricultural Assessment Arboricultural Assessment Site Address: Client: The Proposal: St Omer Park Lake Esplanade Queenstown Queenstown Lakes District Council Arboricultural assessment of a failed Lombardy poplar tree growing

More information

NTW.1 Network Utilities

NTW.1 Network Utilities NTW.1 Network Utilities NOTE: The following provisions apply district wide in addition to any other provisions in this Plan applicable to the same areas or site. Index NTW.1 Network Utilities NTW.1.1 NTW.1.2

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

LAND OFF PENRHOS ROAD, BANGOR REDROW HOMES NORTH WEST METHOD STATEMENT FOR PROTECTION OF TREES DURING DEVELOPMENT. tba. landscape architects

LAND OFF PENRHOS ROAD, BANGOR REDROW HOMES NORTH WEST METHOD STATEMENT FOR PROTECTION OF TREES DURING DEVELOPMENT. tba. landscape architects LAND OFF PENRHOS ROAD, BANGOR REDROW HOMES NORTH WEST METHOD STATEMENT FOR PROTECTION OF TREES DURING DEVELOPMENT tba landscape architects Landscape Architecture Urban Design Environmental Planning 1 st

More information

15. Network utilities

15. Network utilities 15. Network utilities Overview The Project will affect a number of existing network utilities within the Project area. This will require the protection and / or relocation of these utilities. The NZTA,

More information

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION SECTION 2B 1 - GROUND SURVEYS Survey Authorization... 2B-1 Interstate... 2B-1 Principal / Minor Arterial... 2B-1 Urban...

More information

Charging Arrangements for New Connection Services

Charging Arrangements for New Connection Services Charging Arrangements for New Connection Services 2018-2019 About South East Water Developer Services Developer Services Department For any new connections requests or issues please contact our Developer

More information

Arboricultural Assessment

Arboricultural Assessment Arboricultural Assessment Site Address: Client: The Proposal: St Omer Park Lake Esplanade Queenstown Queenstown Lakes District Council Arboricultural assessment of mature poplar trees growing within St

More information

ARTICLE XXIX TREE CONSERVATION

ARTICLE XXIX TREE CONSERVATION ARTICLE XXIX TREE CONSERVATION Section 2901 Intent. This article shall apply to all properties or portions hereof located within the corporate boundaries of the City. The Mayor and Council of the city

More information

WESTERN ENGINEERING CONSULTANTS, Inc LLC

WESTERN ENGINEERING CONSULTANTS, Inc LLC WESTERN ENGINEERING CONSULTANTS, Inc LLC 127 S. Denver Avenue, Ft. Lupton CO 80621 2501 Mill St. Brush, CO 80723 Ph. 303-913-7341, Fax 720-294-1330 Email: firstname.lastname@westerneci.com August 24, 2017

More information

Rural-Residential Rural-Residential Explanatory Statement Significant Issues Objectives and Policies...

Rural-Residential Rural-Residential Explanatory Statement Significant Issues Objectives and Policies... Section Contents Rural-Residential... 2 16. Rural-Residential... 2 Explanatory Statement... 2 16.1 Significant Issues... 2 16.2 Objectives and Policies... 3 16.3 Activity Lists... 3 16.4 Activity Performance

More information

Wokingham Borough Council Street Lighting Design, Adoption Process and Specification Guide

Wokingham Borough Council Street Lighting Design, Adoption Process and Specification Guide Wokingham Borough Council Street Lighting Design, Adoption Process and Specification Guide 1. Design Process 1.1 All street lighting layouts and equipment specifications on new housing developments will

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction) Civil Engineering Services Highways Maintenance (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

20 BUSINESS ZONE RULES

20 BUSINESS ZONE RULES 20 BUSINESS ZONE RULES Activities Tables Policies 3.4.1, 6.4.1, 16.4.7 20.1 Subdivision Activities Subdivision excluding unit title subdivision Subdivision which complies with the standards in rules 20.5

More information

CMPA Campus Wide Solar Array Installation 2 of 4

CMPA Campus Wide Solar Array Installation 2 of 4 Reference 27 This Campus Master Plan Amendment was adopted by the Board of Regents Facilities and Land Management Committee at the June 2013 Board of Regents meeting and placed on the consent agenda for

More information

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

LANDSCAPE RETAINING WALLS

LANDSCAPE RETAINING WALLS SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

18 Flooding and drainage

18 Flooding and drainage 18 Flooding and drainage This chapter assesses flooding and drainage impacts associated with the project. The assessment includes: The identification of existing flood behaviour and drainage infrastructure

More information

TRENCHING AND EXCAVATION

TRENCHING AND EXCAVATION TRENCHING AND EXCAVATION The following guide is an aid intended for students who have completed the ClickSafety training course or module associated with Trenching and Excavation. This guide is a resource

More information

I. Project Overview and Limits. Project Goal

I. Project Overview and Limits. Project Goal Scope of Work and Deliverables for Subsurface Utility Engineering (SUE) for both Underground and Overhead Utilities on T.H. 10, and its Connecting Roads under S.P. 8001-40 I. Project Overview and Limits

More information

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK APPENDIX D Contents 1 Introduction... 1 1.1 Purpose and Scope... 1 1.2 Status... 1 1.3 Environment and Sustainability Policy... 1 1.4 Project Description...

More information

Arboricultural Impact Assessment

Arboricultural Impact Assessment Planning Application for the Aylesbury Estate Regeneration Plot 18 Reserved Matters Application Arboricultural Impact Assessment Tamla Trees v1 BS5837 Arboricultural Impact Assessment Aylesbury Estate,

More information

TREE SERVICE STANDARD OF CARE

TREE SERVICE STANDARD OF CARE TREE SERVICE STANDARD OF CARE There are a wide variety of tree service companies and they are not all the same. While most tree service companies have the large truck(s) with a mechanical lift bucket and

More information

Management Plan for the Trees of the ANU

Management Plan for the Trees of the ANU Management Plan for the Trees of the ANU Features of the ANU treescape The most obvious and valuable landscape feature of the ANU campus is its vast and diverse treescape. There are approximately 10,600

More information