The Indianapolis Deep Tunnel Surge Analysis: Debugging Future Operational Issues in the Present
|
|
- Geraldine Preston
- 6 years ago
- Views:
Transcription
1 The Indianapolis Deep Tunnel Surge Analysis: Debugging Future Operational Issues in the Present Karen Ridgway, P.E., Applied Science Inc. Chris Ranck, P.E., BCEE, D.WRE, RW Armstrong Dave Klunzinger, P.E., DLZ John Morgan, Citizens Water June 20, 2012
2 Agenda Background The Indianapolis Tunnel System & The TAP Model Precursors to TAP Analysis TAP Analysis TAP Model Refinements TAP Results Recommended Surge Strategy Discussion
3 Background Why Do a Surge Analysis?
4 Background The TAP Model (Transient Analysis Program) State-of-the-Art Computational Hydraulics Program Fully-dynamic one-dimensional program Uses a finite-volume solution technique Properly simulates open channel and pressurized wave fronts created during rapid filling Validated to laboratory data, Method of Characteristics (MOC) and Implicit Methods (i.e. WHAMO)
5 Background Indianapolis Tunnel System December 2010 CD Amendment: 250 MG Total Tunnel Storage 90 MGD Dewatering Pump Station Physical Parameters: ~ 130,000 ft, 18 diameter ~ 100 CSOs connected 3 Retrieval Shafts, 4 Working/Intermediate Shafts ~ 35 Drop Shafts Design Progress DRTC In Construction DRTCPS 90% Design Complete FCWRTS 60% Design In Progress PRDT AFP Complete LPgRT AFP Complete
6 Precursors to TAP Analysis Screening of Surge Relief Locations SWMM Model Review 10,700 MGD Aggregate Peak CSO System Discharge 4600 MGD (7000 cfs) Discharge at Consent Decree Perf. Criteria Four Events to Evaluate One Synthetic, Three Historical
7 TAP Analysis Level 1 Tunnel Only Level 2 Tunnel & Drop Shafts Level 3 Tunnel, Drop Shafts, Consolidation Sewers, CSO Outfalls, CSO Weirs Level 4 Ventilation
8 TAP Analysis TAP Model Schematic Level 1 (Tunnel) 7 Inflow Points 4 Shaft Overflows 3 Surge Tanks
9 TAP Analysis L1 Passive Preliminary Surge Tanks Pleasant Run = 0.0 MG Pogues Run = 0.1 MG Fall Creek = 1.0 MG Preliminary Shaft Overflow Peak Rates Southport = 1,500 cfs White River at Pleasant Run = 1,500 cfs White River at Pogues Run = 1,500 cfs White River at Fall Creek = 2,700 cfs
10 TAP Analysis L1 Gated 5 Min Gate Closure Single Control Fall Creek/White River Intermediate Working Shaft Open/Close Elevation Upstream Crown (534 feet) CLOSE Deadband OPEN
11 TAP Analysis L1 Gated No Surge Tanks Required Shaft Overflows May be Necessary if Too Many Gates Fail Gates Need to Convey the Flow Rate for the Consent Decree Perf. Criteria (~4600 MGD) 18 Tunnel System Cannot Convey 10,700 MGD Peak Restriction at Drop Shafts or Consolidation Sewers are Required
12 TAP Model Schematic Level 2: Gated Model 35 Gated Inflow Points 4 Shaft Overflows (w/ BC) 3 Surge Tanks
13 TAP Analysis Level 3 TAP Model All CSOs represented Incorporated Headloss Curves for Drop Shafts based on physical modeling Taper Approach Channel CSO Weir to Collection System CCS CSO OF Drop Shaft
14 IIHR Physical Model of Vortex Dropshaft TAP representation calibrated to Headloss data Scaled for other dropshafts TAP Analysis
15 TAP Analysis Evaluated impacts of gate closure and surge on CCS and existing CSO system
16 Level 3 TAP Model TAP Analysis
17 TAP Analysis Level 3 Tunnel -> CSO Weirs Refined Shaft Overflow Peak Rates Southport = 1,500 cfs 100 cfs / 0.5 MG stored White River at Pleasant Run = 1,500 cfs White River at Pogues Run = 1,500 cfs 700 cfs 600 cfs White River at Fall Creek = 2,700 cfs 500 cfs Gate Closure Elevation in Intermediate Working Shaft 534 feet 550 feet Identified 15 CSOs where backflow may occur over CSO weirs after inflow gates have closed
18 Maximum Allowable Flow (cfs) TAP Analysis When do we need redundancy for Gate Failure? 2,500 2,000 2,100 1,500 1,300 1, July 18, 1996 Event June 15, 1998 Event November 7, 1996 Event
19 Level 4 Ventilation Utility Shafts Required after Pump Station submerges Area of concern for trapped air pocket Vent Orifice restriction considered TAP Analysis
20 Level 4 Ventilation Retrieval Shaft Ventilation on all Branches TAP Analysis
21 TAP Model Refinements Model Size 250 Junctions -> 450 Junctions 150 Conduits -> 250 Conduits Air Volume Tracking Volume of water & air reported in all conduits at all time steps Allows for post-processing to track movement of air and calculate ventilation rates in shafts
22 Recommended Surge Strategy Restrict peak inflow to tunnel system 18 Tunnel has capacity for peak inflow per the Consent Decree requirement Inflow Gates at all Drop Shafts Central Monitoring Point at Intermediate Working Shaft Redundancy for Inflow Gates Passive Shaft Overflows based on real storms Or Redundant Inflow Gates at largest drop shafts
23 Current Status Analysis Completed December 2010 Intermediate Working Shaft Moved ~ 1.7 Miles Upstream Feb 2011 Monitoring site change close elevation from 550 to 560 feet No longer practical shaft overflow site Additional strain on remaining 3 shaft sites Constructability limitations for shaft peak flow rates Shifting Preference to redundancy on largest gates Additional Ventilation Study for Utility Shafts is under consideration
24 Lessons Learned Interface with SWMM model (and modelers) is essential Physical Geometry influences surge strategy Fixed Diameter (CD Amendment) Slope (Geology, Constructability) Shaft Overflow Envelope (River to CSO Weir) Shaft Proximity to Largest CSOs Need to keep model up to date Need to keep up to date on research Conveyance Capacity Passive Feasibility
25 Acknowledgements John Morgan Citizens Water Dave Klunzinger DLZ Surge Modelers: Brittany Vrzina, Stephen Rowe Iowa Institute of Hydraulic Research (IIHR) Tunnel Designers: AECOM, Black & Veatch, B&N
26 Questions? Discussion
Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel
5 Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel M. P. Cherian, Ari Pandian, Karen Ridgway and Gregory Barden The City of Columbus, Ohio, submitted a wet weather management plan
More informationFoster Park Retrieval Shaft
Fort Wayne Tunnel Works Foster Park Retrieval Shaft October 25, 2017 Agenda Brief review of the Tunnel & Shafts project Why we have to be in Foster Park Retrieval Shaft Drop Shaft What the project is going
More informationHydraulic Modeling of Deep Tunnel Provides Cost Savings
5 Hydraulic Modeling of Deep Tunnel Provides Cost Savings Taymour El-Hosseiny, Karen Reinhart and M. P. Cherian In 2005, the City of Columbus, Ohio submitted a plan to the Ohio Environmental Protection
More informationSanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River
Sanitation District No. 1 of Northern Kentucky Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River Ohio WEA Collection Systems Workshop May 5, 2011 Sanitation District No. 1
More informationFacilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station
City of St. Joseph, Missouri Hydraulic Analysis and Effluent Pump Station By Work Order No. 09-001 B&V Project 163509 May 20, 2010 Table of Contents 1.0 Executive Summary...1 2.0 Purpose of Study...2 3.0
More informationThe South Hartford Conveyance and Storage Tunnel
The South Hartford Conveyance and Storage Tunnel South Hartford The Metropolitan District June 16 th -17 th, 2015 Purpose of This Public Meeting Communicate with Residents Directly Adjacent to the Project
More informationIntegrated Long Term Control Plan Targeted Inflow Reduction for CSO Control. OWEA Conference June 29, 2016
Integrated Long Term Control Plan Targeted Inflow Reduction for CSO Control OWEA Conference June 29, 2016 WWTP Average Daily Flow 6 MGD Peak Flow (Primary Only) 12 MGD Collection System 123 Miles (8 to
More informationUsing SWMM 5 to Develop Wet Weather Operating Strategies in a Large Sewer System
15 Using SWMM 5 to Develop Wet Weather Operating Strategies in a Large Sewer System Mi Chen, Fang Cheng, Edward Burgess, Gregory Barden, Hunter Kelly and Timothy Fallara The City of Columbus wastewater
More informationA Study to Estimate Current and Future CSOs to Bubbly Creek and Identify Impacts on the Chicago Area Waterways (CAWS)
A Study to Estimate Current and Future CSOs to Bubbly Creek and Identify Impacts on the Chicago Area Waterways (CAWS) IWEA WATERCON 2012 Springfield, Illinois March 19, 2012 presented by David Kiel, USACE
More informationChapter 5: Conveyance Assessment 2020 Baseline Conditions
Chapter 5: Conveyance Assessment 2020 Baseline Conditions 5.1 Introduction The performance of the conveyance system for 2020 Baseline conditions is assessed in this chapter using the hydraulic models.
More informationDesign and Implementation of the South Hartford CSO Tunnel
Design and Implementation of the South Hartford CSO Tunnel Brian Canterbury, P.E., AECOM James Sullivan, P.E., AECOM Andrew Perham, The Metropolitan District The Metropolitan District NEWEA January 22,
More informationCity of Gardiner, Maine Wastewater Committee Meeting. CSO Storage Tank & Screening Evaluation
City of Gardiner, Maine Wastewater Committee Meeting CSO Storage Tank & Screening Evaluation December 11, 2013 Introduction - Update on field work - Flow monitoring - Survey - GIS - Borings - Assessment
More informationThis page is blank to facilitate double-sided printing.
Supplement No. 2 September 2013 This page is blank to facilitate double-sided printing. Introduction and Purpose The Metropolitan St. Louis Sewer District (MSD) prepared an update to its Combined Sewer
More informationReducing Overflows using a Baffling Solution. OWEA AWWA 2014 Technical Conference & Expo August 28, 2014 Columbus, Ohio
Reducing Overflows using a Baffling Solution OWEA AWWA 2014 Technical Conference & Expo August 28, 2014 Columbus, Ohio 1 Presented by: Steve Janosko, P.E. Project Manager Tony Margevicius, P.E. Vice President
More informationThe Wastewater Tsunami is Coming
The Wastewater Tsunami is Coming How do we stop it? Trooper Smith, PE, Freese and Nichols, Inc. Jennifer Baldwin, Ph.D., PE, Jacobs Outline Project Background Central Basin Rilling Road Storage 30% Design
More informationAnacostia River Tunnel Briefing For: ANC 6B
District of Columbia Water and Sewer Authority George S. Hawkins, General Manager Briefing On: Anacostia River Tunnel Briefing For: ANC 6B October 26, 2011 Agenda Welcome and Introductions DC Water Organization
More informationConsent Decree Appendix 1. Control Measures and Performance Criteria
Case: 1:10-cv-02895-DCN Doc #: 2-2 Filed: 12/22/10 1 of 6. PageID #: 82 United States and State of Ohio v. Northeast Ohio Regional Sewer District Consent Decree Appendix 1 Control Measures and Performance
More informationPre-Program Work. Omaha CSO Control Program. Agenda. City has worked on addressing CSOs for many years
Omaha CSO Control Program 2008 IWPCA Conference Session 3C- Collection Systems CSO Program Management Approach Agenda Pre-Program Work Summary of Program Approach Steps One through Four Refinement Period
More informationRefinement Task 19 Minne Lusa Basin Search for Hybrid Alternatives
Refinement Task 19 Minne Lusa Basin Search for Hybrid Alternatives TO: Roger Coffey, PMT Document Control Center, CH2M Hill COPY: Jim Theiler, City of Omaha Scott Aurit, PMT Tom Heinemann, PMT FROM: Jim
More informationSanitary Sewer Rates Now and in the Future
Sanitary Sewer Rates Now and in the Future December 2008 Steve Nielsen, Chief Engineer/Deputy Director Indianapolis Department of Public Works Mark C. Jacob, Program Manager Indianapolis Clean Stream Team
More informationInterim Interconnector Sewer Operational Plan
Interim Interconnector Sewer Operational Plan Gary Hickman Plant Manager Jackson Pike Wastewater Treatment Plant Jeff Hall Assistant Plant Manager Southerly Wastewater Treatment Plant Columbus Area Collection
More informationSILVER SPRINGS/RIVER POLLUTION REDUCTION PROJECT IMPROVING THE WATER QUALITY OF THE SILVER SPRINGS ECOSYSTEM
SILVER SPRINGS/RIVER POLLUTION REDUCTION PROJECT IMPROVING THE WATER QUALITY OF THE SILVER SPRINGS ECOSYSTEM Jonathan Steflik, PE JEA (Formerly Black & Veatch) Bruce Phillips, PE PLS, Tom Young, PE City
More informationCustomer Conference Speedway, IN 46224
Customer Conference Speedway, IN 46224 DigIndy and Citizens Capital Investment Plan Updates Mark C. Jacob Vice President Capital Programs & Engineering September 18, 2014 A Matter of Trust Challenges Annually
More informationOEPA CSO Overflow Reporting
OEPA CSO Overflow Reporting Lita Laven, PE, Northeast Ohio Regional Sewer District Jennie Celik, PE, HDR June 28, 2017 Agenda 1) NEORSD Background 2) Project Overview & Objectives 3) Field Investigations
More informationMilwaukee Metropolitan Sewerage District Conveyance and Treatment System. MACRO made available by
Milwaukee Metropolitan Sewerage District Conveyance and Treatment System MACRO made available by Eric Loucks,, CDM MMSD Collection System Operations MMSD operates an extensive system of sanitary sewers
More informationThe MDC s South Hartford Conveyance and Storage Tunnel
The MDC s South Hartford Conveyance and Storage Tunnel Presentation to CONN-OSHA Roundtable Andrew Perham, CHMM - MDC Brian J. McCarthy, PE, CCM, PMP September 19, 2017 Safety Moment Storm Watch: Be Prepared
More informationExecutive Summary. Introduction
Executive Summary Introduction The City of Terre Haute has developed a (CSO LTCP), which describes the measures they will take to reduce the combined sewer overflows and improve water quality in the Wabash
More informationMaximizing Your Investment
Maximizing Your Investment City of Lorain Collection System Optimization Eliminates SSOs Ohio Water Environment Association June 24, 2015 Mary Garza City of Lorain Laura McGinnis, P.E. ARCADIS Tim Ruggaber,
More informationGreen Infrastructure Modeling Strategies
District of Columbia Water and Sewer Authority George S. Hawkins, General Manager Green Infrastructure Modeling Strategies Steve Skripnik, P.E Environmental Engineer, LimnoTech American Water Resources
More informationCity of Ames. Water Pollution Control. Long Range Facility Plan
City of Ames Water Pollution Control Long Range Facility Plan Introduction Over 25 years ago, the City of Ames last completed a Wastewater Facility Plan. That Facility Plan prompted design and construction
More informationAssessing SWMM 5 Hydrologic Parameter Benefits for Model Calibration
Assessing SWMM 5 Hydrologic Parameter Benefits for Model Calibration Justin Siegrist, 1 Daniel Anderson, 2 Joseph Koran, 2 Mark Pribak, 3 Uzair M. (Sam) Shamsi 4 and Dave White 1 1 Wade Trim, Inc., Cincinnati,
More informationThe City of Baltimore Back River Wastewater. No more backups Reducing SSOs with headworks improvements in Baltimore
No more backups Reducing SSOs with headworks improvements in Baltimore Brian Balchunas, Meredith Welle, Jason Kerns, Gurminder Singh, Misrak Shiferaw, Ben Asavakarin, Thomas Demlow, and Kara Hurtig The
More informationMeeting CSO Capture Requirements & Local Expectations in an Urban Environment Greening the Gray
Meeting CSO Capture Requirements & Local Expectations in an Urban Environment Greening the Gray Bruce G. Munn Principal CC John Marino Presentation outline Program history Clinton CSO Storage Facility
More informationMinne Lusa Stormwater Tunnel and Pershing/Storz Detention Basins Hydraulic Evaluation
TECHNICAL MEMORANDUM OMAHA CSO CONTROL PROGRAM Minne Lusa Stormwater Tunnel and Pershing/Storz Detention Basins Hydraulic Evaluation TO: Jim Theiler, City of Omaha Eitan Tsabari, City of Omaha Scott Aurit,
More informationUsing SWMM EXTRAN to Simulate WWTP Hydraulics
11 Using SWMM EXTRAN to Simulate WWTP Hydraulics Derek Wride, Carl Chan, Ben Gamble, Joseph Koran and Susan Moisio SWMM EXTRAN has been successfully deployed to simulate wastewater treatment plant hydraulics
More informationDynamic Hydraulic Modeling of a Wastewater Treatment Plant. City of Fort Worth Case Study
Dynamic Hydraulic Modeling of a Wastewater Treatment Plant City of Fort Worth Case Study AGENDA Drivers for a Dynamic Integrated Large WWTP Hydraulic Model Model Development Modeling Conduits and Bends
More informationLong-Term CSO Control Plan for North Dorchester Bay and the Reserved Channel
Massachusetts Water Resources Authority Long-Term CSO Control Plan for North Dorchester Bay and the Reserved Channel Frederick A. Laskey Executive Director March 8, 2004 How Sewer Separation Works 2 How
More informationBloomingdale Neighborhood Flooding Mitigation Washington, DC
District of Columbia Water and Sewer Authority George S. Hawkins, General Manager Briefing on: Bloomingdale Neighborhood Flooding Mitigation Washington, DC Briefing for: Federal Water Quality Association
More informationDC Clean Rivers Project
District of Columbia Water and Sewer Authority George S. Hawkins, General Manager Briefing on: DC Clean Rivers Project Briefing for: Anacostia Watershed Restoration Partnership April 10, 2015 Agenda Background
More informationAppendix J Effluent Pump Station
Appendix J Effluent Pump Station TECHNICAL MEMORANDUM Salmon Creek Treatment Plant Effluent Pump Station Hydraulics and Phasing Analysis for the Phase 5A Project Columbia River Outfall and Effluent Pipeline
More informationSewer Separation and Stormwater Management (with Emphasis on Flood Control)
Sewer Separation and Stormwater Management (with Emphasis on Flood Control) July 15, 2002 Justin Wiedeman, P.E. NPU A Board Member Chastain Civic Association Board Member This Presentation Came About Because:
More informationMinne Lusa Basin Technology Screening TM
TECHNICAL MEMORANDUM OMAHA CSO CONTROL PROGRAM Minne Lusa Basin Screening TM TO: COPY: FROM: Document Control Center, CH2M Hill Rick Nelson, Basin Consultant Manager Marty Grate, CSO Manager Jim Theiler,
More informationRETENTION BASIN EXAMPLE
-7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary
More informationThe South Florida Water Management
FWRJ Design of Treatment Wetlands to Improve Everglades Water Quality Fernando Navarrete, Panneer Shanmugam, and Matthew Alexander The South Florida Water Management District (SFWMD) has finalized the
More informationTechnical Memorandum No. 1
DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Serving the Public Protecting the Environment Technical Memorandum No. 1 Multi-Jurisdictional Use Facilities Capital Cost Allocation DRAFT April 17, 2013
More informationSynergy: Addressing Combined Sewer Overflows and Nitrogen
District of Columbia Water and Sewer Authority Briefing on Synergy: Addressing Combined Sewer Overflows and Nitrogen to Anacostia Steering Committee August 27, 2009 1 Introduction Background Addressing
More informationReliability & Redundancy for CSO Facilities Using GWWTS as a Case Study. By Jeffrey A. Lundt, P.E.
Reliability & Redundancy for CSO Facilities Using GWWTS as a Case Study By Jeffrey A. Lundt, P.E. Presentation Content Purpose WTD CSO program and GWWTS project background Project hydrology GWWTS facilities
More informationWilmette - Background
Reducing Basement Backups through Intergovernmental Cooperation and Design-Build Presented By Michael N. Young, P.E. Brigitte Ann Berger, P.E. Wilmette - Background North Shore Suburb of Chicago 5 Square
More informationHIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE
City of Newark, Ohio HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE 22, 2011 High Rate Treatment Tanks/UV Wet Weather Screen Building JC2/Wet Weather Pump Station Wet Weather Control
More informationChapter 3 Previous Studies
Chapter 3 Previous Studies The Vista Grande stormwater conveyance system and watershed area has been evaluated in a number of reports and studies for the CCSF, the Daly City and San Mateo County over the
More informationHartford WPCF Master Plan Clean Water Project. Executive Summary. February 2010
Hartford WPCF Master Plan Clean Water Project Executive Summary February 2010 An outline of work at the Hartford Water Pollution Control Facility that will achieve compliance with regulatory requirements
More informationCombined Sewer Overflow - Long Term Control Plan Update
Combined Sewer Overflow - Long Term Control Plan Update DELCORA Public Participation Meeting No. 4 LTCPU Development and Evaluation of Alternatives for CSO Controls September 26, 2018 Aston Township Administration
More informationCommunity Open House
Mayor Kasim Reed The Department of Watershed Management & Atlanta Memorial Park Conservancy Community Open House 10/28/2016 1 AGENDA: Meet & Greet Opening Remarks & Introductions District 8 Council Member
More informationOptimizing Wastewater Upgrade Projects with Improved Hydraulics
Optimizing Wastewater Upgrade Projects with Improved Hydraulics Alden Webinar Series October 27, 2009 For audio, please dial 1 (866) 809-5996, participant code 6504656 Housekeeping Questions and Audio
More informationPanel 2 Public Initiatives and Return on Investment. Clean Rivers Project
District of Columbia Water and Sewer Authority George S. Hawkins, General Manager Capitol Riverfront BID Anacostia River Business Summit Panel 2 Public Initiatives and Return on Investment Presented By:
More informationPapillion Creek South Combined Sewer Backup and Major Street Flooding Recommended Approach TM
Rev. Draft TECHNICAL MEMORANDUM OMAHA CSO CONTROL PROGRAM Papillion Creek South Combined Sewer Backup and Major Street Flooding Recommended Approach TM TO: COPY: FROM: Document Control Center, CH2M HILL
More informationLower Mill Creek Partial Remedy. Alternatives Evaluation Preliminary Findings Report
Lower Mill Creek Partial Remedy Alternatives Evaluation Preliminary Findings Report Refined & Updated July 2012 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY...6 2 PURPOSE... 15 3 SCOPE... 16 3.1 LMCPR Scope of
More informationPHASE 1 OF THE CONSENT DECREE/ WET WEATHER IMPROVEMENT PROGRAM ACCOMPLISHMENTS THROUGH 2017
PHASE 1 OF THE CONSENT DECREE/ WET WEATHER IMPROVEMENT PROGRAM ACCOMPLISHMENTS THROUGH 2017 MSD is delivering Phase 1 is under the original cost estimate Improving Trends in Water Quality MSDGC has completed
More informationLong-Term Control Plan Orientation. July 1, 2009
Long-Term Control Plan Orientation July 1, 2009 Introductions City Staff Program Management Team Agenda LTCP Development CSO Controls & Costs Implementation Schedule Phases Implementation Approach LTCP
More informationTitle (28 pt Black Font, Arial) Title Line 2
Services of the San Francisco Public Utilities Commission Title (28 pt Black Font, Arial) Title Line 2 April 25, 2011 (date format)(18 pt black font, Arial) John Doe, (position/title), Division/Bureau
More informationBrightwater Conveyance System. Need for the Brightwater project. Final Conveyance Routes. Brightwater Siting Process. University of Washington
Founded in 1917 Over 7,500 employees worldwide Ranked number 16 by Engineering News-Record Brightwater Conveyance System University of Washington 400 Staff Locally Major Projects: 520 405 Alaskan Way October
More informationCity of Columbus Wet Weather Management Plan Update. Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage
City of Columbus Wet Weather Management Plan Update Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage City of Columbus, Ohio Population served ~ 1 Million 22 satellite
More informationReport. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI
Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,
More informationWater Infrastructure Resiliency Planning for the City of Norfolk. Cherryl Barnett, P.E., Engineering Manager, Department of Utilities
Water Infrastructure Resiliency Planning for the City of Norfolk Cherryl Barnett, P.E., Engineering Manager, Department of Utilities Agenda 1. City of Norfolk Resiliency Efforts 2. Norfolk s Water System
More informationHydraulic Modeling and System Optimization
DRINKING WATER ENERGY MANAGEMENT WORKSHOP SERIES TAKING ENERGY IMPROVEMENTS TO THE NEXT LEVEL: Hydraulic Modeling and System Optimization Steven Jones, M.S., P.E. September 4, 2013 What is a Water System
More informationCommunity Involvement Within Your Organization
Community Involvement Within Your Organization Purdue Road School March 8, 2016 Chris Gale, PE HNTB Corporation Vice President Indiana Office Leader Mark C. Jacob citizens energy group Vice President Capital
More informationReport. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI
Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,
More informationDRAFT. Technical Memorandum. Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update. Prepared For:
DRAFT Technical Memorandum Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update Prepared For: Pinellas County Department of Environment and Infrastructure Division of Engineering and
More informationBMP Design Aids. w w w. t r a n s p o r t a t i o n. o h i o. g o v. Equations / Programs
BMP Design Aids 1 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 2 Ohio Department of Transportation 1 Training Intent Introduction and overview of
More informationFinding Solutions to Sanitary Sewer System Capacity Deficiencies
23 Finding Solutions to Sanitary Sewer System Capacity Deficiencies Derek Wride, Joe Koran, Mi Chen, Ben Gamble and Edward H. Burgess In 2000, the Metropolitan Sewer District of Greater Cincinnati (MSDGC)
More informationDeep Tunnel, Shallow Pipe - How the City of Hamilton, OH plans to save millions on SSO control. Glenn Weist, P.E.
Deep Tunnel, Shallow Pipe - How the City of Hamilton, OH plans to save millions on SSO control Glenn Weist, P.E. Columbus, Ohio May 10, 2012 Agenda Background Project Description Regulatory Synopsis Stakeholder
More informationTunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions
City Utilities operates the largest municipally-owned wastewater collection and treatment system in Indiana. The system serves 161 square miles and includes 1,014 miles of sanitary sewer lines, 365 miles
More informationNorwalk, CT Water Pollution Control Facility (WPCF) CSO Capacity and Treatment Evaluation. Subject: Task 3 Existing Grit Removal System Assessment
A Technical Memorandum Date: Project: Norwalk, CT Water Pollution Control Facility (WPCF) CSO Capacity and Treatment Evaluation Subject: Task 3 Existing Grit Removal System Assessment This memorandum presents
More informationRegional Hydraulic Model Plan
APPENDIX 3 Regional Hydraulic Model Plan November 17, 2008 Contents Section 1 Introduction Section 2 Model Objectives and Capabilities 2.1 Model Software Capabilities... 2-1 Section 3 Model Development
More informationDesign Considerations for Selection of Pipe Material for Large Diameter CSO Force Main
Design Considerations for Selection of Pipe Material for Large Diameter CSO Force Main Pacific Northwest Clean Water Association 2010 Conference Presented By M. Patty Nelson, City of Portland Phil Roppo,,
More informationHey and Associates, Inc.
Hey and Associates, Inc. Table 1: 100-Year Study Existing Conditions Discharges and Elevations vs. FIS Results Location Existing FIS Q (cfs) Existing FIS Elevation Existing XP- SWMM Q (cfs) Existing XP-SWMM
More informationDESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS
DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano, P.E. May 29, 2014 PROJECT BACKGROUND Integrated Pipeline Project 149 miles of pipeline 3 booster
More informationBROAD CREEK AUGMENTATION PROJECT Conveyance System North Contract Community Meeting March 4, 2015
BROAD CREEK AUGMENTATION PROJECT Conveyance System North Contract Community Meeting March 4, 2015 Introduction Austin Freeman, PMP Project Manager John Beitler, PE Project Manager Dennis Funk, P.E. Gannett
More informationUpdate The Don River and Central Waterfront Project and The Ashbridges Bay Treatment Plant outfall
Cleaning Up Our Waterways: Update The Don River and Central Waterfront Project and The Ashbridges Bay Treatment Plant outfall Focus of projects : Lower Don River and Toronto s Inner Harbour & Ashbridges
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or
More informationENVIRONMENTAL ASSESSMENT
ENVIRONMENTAL ASSESSMENT Project Identification Project Name: Elyria East Side Relief Sewer Phase 1B South (CS390337-0018), Phase 1C (CS390337-0014), Phase 1D (CS390337-0017) Applicant: The Honorable Holly
More informationMetropolitan St. Louis Sewer District. CSO LTCP Update EXECUTIVE SUMMARY
Metropolitan St. Louis Sewer District Purpose The Metropolitan St. Louis Sewer District (MSD) provides wastewater and stormwater service to approximately 1.4 million people in a 535-square-mile service
More informationChakachamna Hydro. AEA Geothermal Conference
Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings
More informationTurning a Negative into a Positive Negotiating a Consent Decree to Develop a Reasonable Endpoint
Turning a Negative into a Positive Negotiating a Consent Decree to Develop a Reasonable Endpoint City of Haverhill s Story Mr. James Drake Mr. Robert Ward, Deputy Superintendent of Public Works, Haverhill
More informationLEHIGH COUNTY REGIONAL SEWER SYSTEM
LEHIGH COUNTY AUTHORITY Lowhill Township New Tripoli, PA 18066 LEHIGH COUNTY REGIONAL SEWER SYSTEM Kline s Island WWTP EPA Administrative Order Public Meeting Lehigh County Government Center November 13,
More informationSection 7 Hydraulic Model Development and Evaluation Criteria
Section 7 Hydraulic Model Development and Evaluation Criteria The hydraulic evaluation conducted to develop this master plan was performed using a computer model of the reclaimed water distribution system.
More informationLIMITED ENVIRONMENTAL REVIEW For. Northeast Ohio Regional Sewer District. Kingsbury Run Preliminary Engineering Early Action CSO CS
LIMITED ENVIRONMENTAL REVIEW For Kingsbury Run Preliminary Engineering Early Action CSO CS391430-0133 Applicant: Ms. Kyle Dreyfuss-Wells, Chief Executive Officer 3900 Euclid Avenue Cleveland, Ohio 44115
More informationPrepared for: City of Jeffersonville. November Prepared by
JEFFERSONVILLE STORMWATER MASTER PLAN HYDRAULICS APPENDIX JEFFERSONVILLE, INDIANA Prepared for: City of Jeffersonville November 2011 Prepared by Christopher B. Burke Engineering, Ltd. 115 W. Washington
More informationOdour and Air Management Studies: Key Tool in Determining Effective Odour Control
Odour and Air Management Studies: Key Tool in Determining Effective Odour Control Solutions Yuko Suda, P.Eng., Kerr Wood Leidal Associates Ltd. Ted Steele, P.Eng., Kerr Wood Leidal Associates Ltd. 200-4185A
More informationSomerset Raritan Valley Sewerage Authority SSO Abatement and Storm Control Treatment Facility
Somerset Raritan Valley Sewerage Authority SSO Abatement and Storm Control Treatment Facility Michael Sanders, P.E., Kleinfelder Collection Systems Specialty Conference NEWEA September 12, 2016 Presentation
More informationCSO and SEWERAGE CONVEYANCE TUNNEL DESIGN NACE CORROSION 2010
UNDERSTANDING CORROSION PROTECTION/PREVENTION NEEDS IN CSO and SEWERAGE CONVEYANCE TUNNEL DESIGN NACE CORROSION 2010 By Randy Nixon Senior Consultant Corrosion Probe, Inc. Centerbrook, CT OVERVIEW Types
More informationNJ Future CSO Permittee Meeting
NJ Future CSO Permittee Meeting 1 Best Practices Carter Strickland, JD HDR 2 Getting the Best LTCP CSO controls will be expensive Include Best Practices to Maximize visible and tangible benefits Create
More informationThe Metropolitan District Status of LTCP Update. January 9, 2017
The Metropolitan District Status of LTCP Update January 9, 2017 Agenda CH2M Hill LTCP Peer Review/Water Quality Analysis CDM Smith LTCP Update & CSO Meters Affordability Analysis 3 Hartford MDC - LTCP
More informationPermeable Pavement Hydrologic Modeling
Permeable Pavement Hydrologic Modeling Robin Kirschbaum, PE, LEED AP Alice Lancaster, PE April 24, 2013 Presentation Overview Overview of Hydrologic Modeling Performance Standards Modeling Guidelines,
More informationNewtown Creek Superfund Citizens Advisory Group Newtown Creek Combined Sewer Overflow Long Term Control Plan
Newtown Creek Superfund Citizens Advisory Group Newtown Creek Combined Sewer Overflow Long Term Control Plan Location: McCarren Park Community Center Date: July 25, 2017 Agenda 1 Topic Welcome; Recap of
More informationCoal Combustion Residuals Inflow Design Flood Control System Plan
gaiconsultants.com I transforming ideas into reality., Coal Combustion Residuals Inflow Design Flood Control System Plan Virginia Electric and Power Company Possum Point Power Station Surface Impoundment
More informationMSDGC MODELING GUIDELINES AND STANDARDS VOLUME I SYSTEM WIDE MODEL
MSDGC MODELING GUIDELINES AND STANDARDS VOLUME I SYSTEM WIDE MODEL REVISION 3 February 2013 Prepared for: METROPOLITAN SEWER DISTRICT OF GREATER CINCINNATI Project & Business Development Division 1600
More informationCity of Elmhurst Comprehensive Flood Plan Golden Meadows Park Flood Storage Facility
December 16, 2014 City of Elmhurst Comprehensive Flood Plan Golden Meadows Park Flood Storage Facility Prepared by CBBEL Project Background & Timeline June and July 2010 Severe storm events hit Elmhurst,
More informationIIoT Transformation of Cincinnati MSD Collection System
IIoT Transformation of Cincinnati MSD Collection System Presenters Ed Heyob, CDM Smith Automation Engineer Kim Brown, JPWWTP Supervisor II Ed Heyob CDM Smith Automation Engineer heyobes@cdmsmith.com Existing
More information