1 BMP Design Aids 1 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 2 Ohio Department of Transportation 1

2 Training Intent Introduction and overview of various design aids (equations and programs) Not a detailed training on how to use each one 3 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 4 Ohio Department of Transportation 2

3 For peak flow rate only Q = CiA Q: flow rate (cfs) C: coefficient of runoff i: rainfall intensity (in/hr) Based on time of concentration Sheet flow, shallow concentrated flow, and open channel or pipe flow A: tributary area (ac) 5 Q = CiA C: 6 Ohio Department of Transportation 3

4 7 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 8 Ohio Department of Transportation 4

5 (0.15 for Vegetated Biofilter) 9 10 Ohio Department of Transportation 5

6 Program or Spreadsheet Calculation Use bisection method (trial and error) Inputs: Channel geometry and slope Manning s roughness coefficient Flow rate Results: Normal depth Velocity 11 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 12 Ohio Department of Transportation 6

7 Discharge Equations Orifice flow Weir flow 13 Orifices Orifices 14 Ohio Department of Transportation 7

8 Post Construction BMP Selection & Design for Weir 15 Orifice www. t r a n s p o r t a t i o n. o h i o. g o v Orifice Flow 16 Ohio Department of Transportation www. t r a n s p o r t a t i o n. o h i o. g o v 8

9 Weir Flow L&D Vol. 2, Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 18 Ohio Department of Transportation 9

10 CDSS is a hydraulic design software developed by ODOT C Culvert Design D Ditch Design SS Storm Sewer Design 19 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 20 Ohio Department of Transportation 10

11 Technical Release 55 (TR-55) Technical Release 20 (TR-20) Urban Hydrology for Small Watersheds Determines runoff depth (inches) Combines with unit hydrograph theory Produces runoff hydrographs Peak flow and total volume 21 CN: depth of runoff abstracted Total P Abstracted P = Runoff Depth Runoff Depth * Area = Runoff Volume NRCS unit hydrograph gives runoff volume a shape (distribution over time) Produces a full runoff hydrograph 22 Runoff Flow Rate Time Ohio Department of Transportation 11

12 23 24 Ohio Department of Transportation 12

13 Analyses that require a full hydrograph Pre vs. post volumes (CSO areas) Routing a design storm through a detention basin, bioretention cell, or infiltration trench Still gives peak flow rate, but will likely be slightly different from Rational Method 25 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 26 Ohio Department of Transportation 13

14 Hydrograph and Pond Routing Programs Many different programs Different inputs Different calculations Different limitations Know your tool before you use it 27 Common Hydraulics and Hydrology Software Options Basic Pipe or Open Channel Capacity Calcs. Basin Inlet/Outlet Peak Flow and HGL Design Calculations Hydraflow Express Bentley CulvertMaster Bentley FlowMaster Urban Drainage HY22 HY-8, Steady/Unsteady Flow Open Channels Some Sediment Transport/Quality Often used in FEMA Floodplains HEC HEC-1 HEC-HMS HEC-2 HEC-RAS GEO-RAS Normal Gravity Sewer, Detention Pond Design Hydrology and Hydraulics Combined Rational/TR-55/SCS Hydrology Manning s/orifice/weir Hydraulic Calcs. Some Quality Calculations Available Simple Stormwater Routing Models HydraFlow Hydrographs HydraFlow Storm Sewers Bentley StormCAD Bentley PondPack HydroCAD Complex Drainage Systems that have: tail water, reverse flow, pump stations, surface flooding Horton/Green-Ampt Hydrology Hydrodynamic and Kinematic Wave Hydraulic Calcs. Detailed Quality Calculations Available Robust Stormwater Routing Models EPA SWMM Bentley CivilStorm AutoDesk SSA PCSWMM XP SWMM Ohio Department of Transportation 14

15 PondPack and HydroCAD Inputs for runoff hydrograph Area Curve number, land use, or runoff coefficient Time of concentration Design storm frequency Produces runoff hydrograph Then route that hydrograph into your BMP 29 PondPack and HydroCAD Inputs for BMP Stage vs storage curve (elevation vs. volume) Inputs for BMP discharge 800 Stage vs. depth curve Each outlet 797 WQ orifices Weirs, catch basin grates Overflow weirs Discharge pipe Downstream constraints (tailwater) Elevation (ft) Elevation vs. Volume Volume (ac-ft) 30 Ohio Department of Transportation 15

16 PondPack and HydroCAD Two types of analyses Hydrograph routing Drawdown analysis Split event into many short pieces and calculate: Volume entering Volume leaving Volume and depth in basin 31 PondPack and HydroCAD Make sure you have all of the potential discharge conveyances Make sure the BMP storage information in the model matches the design sheets Make sure the modeled discharge conveyance characteristics match the design sheets and site, including tailwater Make sure the results make sense 32 Ohio Department of Transportation 16

17 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats Ohio Department of Transportation 17

18 35 Equations / Programs Peak flow rate only Flow conditions (velocity and depth) at a given flow rate Outlet Discharge Equations Flow rate at a given outlet shape and hydraulic head Hydraulic design of culverts, ditches, and storm sewers Full runoff hydrograph (flow rate over time and full storm volume) Hydrograph and Pond Routing Programs Full hydrograph, detention, peak flow rate, and draw down analyses USGS StreamStats Peak design storm flow rates as well as other stream statistics 36 Ohio Department of Transportation 18

19 Questions? Jon Prier, P.E Ohio Department of Transportation 19

RETENTION BASIN EXAMPLE

RETENTION BASIN EXAMPLE -7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary

More information

Extended Detention Basin Design

Extended Detention Basin Design Extended Detention Basin Design 1 Extended Detention 2 Ohio Department of Transportation 1 Extended Detention Basin L&D Vol. 2 Section 1117.3 Provides quality and quantity treatment 3 Extended Detention

More information

COMPUTER APPLICATIONS HYDRAULIC ENGINEERING

COMPUTER APPLICATIONS HYDRAULIC ENGINEERING - 7535 COMPUTER APPLICATIONS IN HYDRAULIC ENGINEERING Connecting Theory to Practice Fifth Edition HAESTAD PRESS Table of Contents Revision History Foreword CHAPTER 1 BASIC HYDRAULIC PRINCIPLES 1 1.1 General

More information

EXTENDED DETENTION BASIN EXAMPLE

EXTENDED DETENTION BASIN EXAMPLE EXTENDED DETENTION BASIN EXAMPLE 1117 6 July 2015 REFERENCE SECTION 1117 Given: TotalTributaryArea=7.5 o TributaryAreawithinExistingR/W=7.2 o TributaryArea,Impervious,OutsideofR/W=0.3 o TributaryArea,Pervious,OutsideofR/W=0.0

More information

Drainage Analysis. Appendix E

Drainage Analysis. Appendix E Drainage Analysis Appendix E The existing and proposed storm drainage systems have been modeled with Bentley CivilStorm V8 computer modeling software. The peak stormwater discharge was determined for

More information

Project Drainage Report

Project Drainage Report Design Manual Chapter 2 - Stormwater 2A - General Information 2A-4 Project Drainage Report A. Purpose The purpose of the project drainage report is to identify and propose specific solutions to stormwater

More information

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or

More information

Design Example Residential Subdivision

Design Example Residential Subdivision Design Example Residential Subdivision Rhode Island Stormwater Design and Installation Standards Manual December 2010 Public Training March 22, 2010 Richard Claytor, P.E. 508-833-6600 Appendix D: Site

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part 257.82 PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Modeling Infiltration BMPs

Modeling Infiltration BMPs Modeling Infiltration BMPs CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) 696-4150 www.thcahill.com Design Goals for Calculations 1. Mitigate Peak Rates 2-Year to 100-Year 2. No Volume

More information

Applying the Water Quality Volume

Applying the Water Quality Volume Applying the Water Quality Volume Justin Reinhart, PE Division of Surface Water Northeast Ohio Stormwater Training Council Cleveland, Ohio & Richfield, Ohio July 12, 2018 July 25, 2018 Post-Construction

More information

Design of Stormwater Wetlands

Design of Stormwater Wetlands Hydraulic & Hydrologic Stormwater Engineering Design of Stormwater Wetlands Jon Hathaway, EI Extension Associate NCSU Bio. And Ag. Engineering 6 Step Process 1. Watershed Analysis (Runoff Volume and Peak

More information

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges Detention Pond Design Considering Varying Design Storms Land Development Results in Increased Peak Flow Rates and Runoff Volumes Developed area Robert Pitt Department of Civil, Construction and Environmental

More information

HORRY COUNTY. Stormwater Management Design Manual

HORRY COUNTY. Stormwater Management Design Manual HORRY COUNTY Stormwater Management Design Manual SEPTEMBER 2000 HORRY COUNTY STORMWATER MANAGEMENT DESIGN MANUAL Table of Contents Chapter 1...Introduction Chapter 2... Hydrology Chapter 3... Storm Drainage

More information

Index. Page numbers followed by f indicate figures.

Index. Page numbers followed by f indicate figures. Index Aerodynamic method, 103, 110 111 Algae, 131, 173, 175 Alternate depth, 88 Alternating block method, 132, 140 141 Attenuation, 106, 107f, 118, 120 Page numbers followed by f indicate figures. Baseflow

More information

Water Resources Management Plan

Water Resources Management Plan P L Y M O U T H M I N N E S O T A Appendix D: The developed a to analyze and minimize the impact of existing and future development on the City s natural resources. It is important to the City to have

More information

TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1

TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1 TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SECTION TITLE PAGE 105.1. SPECIFICATIONS AND SCOPE 105.1 105.2. METHODS OF ANALYSIS 105.1 105.2.1. Rational Method

More information

Hey and Associates, Inc.

Hey and Associates, Inc. Hey and Associates, Inc. Table 1: 100-Year Study Existing Conditions Discharges and Elevations vs. FIS Results Location Existing FIS Q (cfs) Existing FIS Elevation Existing XP- SWMM Q (cfs) Existing XP-SWMM

More information

Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond)

Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond) Chapter 10 Design Examples Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond) Example 2: Filter Design in a commercial development

More information

DETENTION BASIN DESIGN USING RATIONAL HYDROGRAPHS

DETENTION BASIN DESIGN USING RATIONAL HYDROGRAPHS DETENTION BASIN DESIGN USING RATIONAL HYDROGRAPHS By Thomas F. Smith, P.E., P.L.S. Bercek and Smith Engineering, Inc. www.bercekandsmith.com tfsmith2@bercekandsmith.com 1 Topics Covered: 2 1 Attributed

More information

Intelligent, Efficient Hydrology and Hydraulic Modelling and Analysis Using Autodesk Storm and Sanitary Analysis

Intelligent, Efficient Hydrology and Hydraulic Modelling and Analysis Using Autodesk Storm and Sanitary Analysis Autodesk Storm and Sanitary Analysis Intelligent, Efficient Hydrology and Hydraulic Modelling and Analysis Using Autodesk Storm and Sanitary Analysis Autodesk have provided a unique solution catering to

More information

Hydrologic Study Report for Single Lot Detention Basin Analysis

Hydrologic Study Report for Single Lot Detention Basin Analysis Hydrologic Study Report for Single Lot Detention Basin Analysis Prepared for: City of Vista, California August 18, 2006 Tory R. Walker, R.C.E. 45005 President W.O. 116-01 01/23/2007 Table of Contents Page

More information

Shawn Herring Civil Applications ProSoft, Inc

Shawn Herring Civil Applications ProSoft, Inc SSA for Highway Design Using Autodesk Storm and Sanitary Analysis for Simple or Complex Roads Shawn Herring Civil Applications Engineer @ ProSoft, Inc Win a Civil 3D Book!!! A Practical Guide to AutoCAD

More information

Storm Sewers, Page 2

Storm Sewers, Page 2 Storm Sewers storm sewer systems are dendritic systems used to collect and direct stormwater runoff storm sewer systems are integral components of any urban infrastructure curbs, gutters and storm inlets

More information

Green Infrastructure Flood Reduction Computations

Green Infrastructure Flood Reduction Computations Green Infrastructure Flood Reduction Computations Stephen Sands, PE, CFM ssands@hazenandsawyer.com March 24, 2016 Water JAM 2010 Discussion Topics Siting success Watershed-wide computations Individual

More information

DRAFT. Technical Memorandum. Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update. Prepared For:

DRAFT. Technical Memorandum. Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update. Prepared For: DRAFT Technical Memorandum Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update Prepared For: Pinellas County Department of Environment and Infrastructure Division of Engineering and

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

CHAPTER 3 STORMWATER HYDROLOGY. Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF

CHAPTER 3 STORMWATER HYDROLOGY. Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF CHAPTER 3 STORMWATER HYDROLOGY Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF 3.1.1 Introduction to Hydrologic Methods...3.1-1 3.1.2 Symbols and Definitions...3.1-3 3.1.3 Rainfall

More information

MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1. Precipitation

MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1. Precipitation Watershed MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1 A watershed is an area of land thaaptures rainfall and other precipitation and funnels it to a lake or stream or wetland. The area within the watershed

More information

APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY)

APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY) APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY) Hydromodification design criteria for the North Orange County permit area are based on the 2- yr, 24-hr

More information

Summary of Detention Pond Calculation Canyon Estates American Canyon, California

Summary of Detention Pond Calculation Canyon Estates American Canyon, California July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i

More information

HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR

HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR 1 INTRODUCTION 1.1 Project Description and Location Isabella Ocean Residences is a residential development to be constructed

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT BOWEN PRIVATE INDUSTRY SOLID WASTE DISPOSAL FACILITY (ASH LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals

More information

Chapter 9 STORMWATER DESIGN. Table 9-1 Hydrology Design Methods

Chapter 9 STORMWATER DESIGN. Table 9-1 Hydrology Design Methods www.knoxvilletn.gov/engineering/ 9.1 Hydrology Methods Chapter 9 STORMWATER DESIGN Table 9-1 shows the various hydrologic computation methods that can be used to compute peak flows in the City of Knoxville.

More information

Haestad Solutions. Bentley Systems Incorporated Haestad Solution Center Watertown, CT Toll-free: Fax:

Haestad Solutions. Bentley Systems Incorporated Haestad Solution Center Watertown, CT Toll-free: Fax: 1 Haestad Solutions Bentley Systems Incorporated Haestad Solution Center Watertown, CT 06795 Toll-free: 1-800-727-6555 Fax: 203-597-1488 www.bentley.com/www.haestad.com Who was Haestad Methods? World Leader

More information

Hydrology for Drainage Design. Design Considerations Use appropriate design tools for the job at hand:

Hydrology for Drainage Design. Design Considerations Use appropriate design tools for the job at hand: Hydrology for Drainage Design Robert Pitt Department of Civil and Environmental Engineering University of Alabama Tuscaloosa, AL Objectives for Urban Drainage Systems are Varied Ensure personal safety

More information

CE Hydraulics. Andrew Kennedy 168 Fitzpatrick

CE Hydraulics. Andrew Kennedy 168 Fitzpatrick CE 40450 Hydraulics Andrew Kennedy 168 Fitzpatrick Andrew.kennedy@nd.edu Final Exam, 8AM May 7, Will cover entire course 155 Fitzpatrick Around half on material since last midterm Like 1.5 midterms in

More information

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

STORM DRAINS AND IRRIGATION

STORM DRAINS AND IRRIGATION TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 STORM DRAINS AND IRRIGATION 105.1. STORM DRAINS... 105.1 105.2. METHODS OF ANALYSIS... 105.1 105.2.1. Rational Method... 105.1 105.2.2.

More information

SECTION IV WATERSHED TECHNICAL ANALYSIS

SECTION IV WATERSHED TECHNICAL ANALYSIS A. Watershed Modeling SECTION IV WATERSHED TECHNICAL ANALYSIS An initial step in the preparation of this stormwater management plan was the selection of a stormwater simulation model to be utilized. It

More information

STORMWATER HYDROLOGY

STORMWATER HYDROLOGY ..CHAPTER.. STORMWATER HYDROLOGY 3.1 Introduction to Hydrologic Methods Hydrology is the science dealing with the characteristics, distribution, and movement of water on and below the earth's surface and

More information

IBS Site Drainage: Senior Design Project

IBS Site Drainage: Senior Design Project IBS Site Drainage: Senior Design Project Len Wright, Ph.D., PE Lecturer, CEAE Wright.Len@gmail.com September 11, 2008 mwsw204i1.ppt/1 OUTLINE Motivation for Stormwater Management Quantity (both onsite,

More information

LAKE COUNTY HYDROLOGY DESIGN STANDARDS

LAKE COUNTY HYDROLOGY DESIGN STANDARDS LAKE COUNTY HYDROLOGY DESIGN STANDARDS Lake County Department of Public Works Water Resources Division 255 N. Forbes Street Lakeport, CA 95453 (707)263-2341 Adopted June 22, 1999 These Standards provide

More information

FORT COLLINS STORMWATER CRITERIA MANUAL Hydrology Standards (Ch. 5) 1.0 Overview

FORT COLLINS STORMWATER CRITERIA MANUAL Hydrology Standards (Ch. 5) 1.0 Overview Chapter 5: Hydrology Standards Contents 1.0 Overview... 1 1.1 Storm Runoff Determination... 1 1.2 Design Storm Frequencies... 1 1.3 Water Quality Storm Provisions... 2 1.4 Design Storm Return Periods...

More information

Section 600 Runoff Table of Contents

Section 600 Runoff Table of Contents Section 600 Runoff Table of Contents 601 INTRODUCTION...600-1 602 RATIONAL METHOD...600-1 602.1 Rational Method Formula...600-2 602.2 Time of Concentration...600-2 602.3 Intensity...600-4 602.4 Runoff

More information

DRAINAGE CRITERIA MANUAL (V. 1) RUNOFF

DRAINAGE CRITERIA MANUAL (V. 1) RUNOFF Section CONTENTS Page RO- 1.0 OVERVIEW... 1 2.0 RATIONAL METHOD... 3 2.1 Rational Formula... 3 2.2 Assumptions... 4 2.3 Limitations... 4 2.4 Time of Concentration... 5 2.4.1 Initial Flow Time... 5 2.4.2

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015

Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Urban Runoff Background How we got here What Problem?? Provenance of the Problem Unified Sizing Criteria What

More information

PRELIMINARY DRAINAGE STUDY

PRELIMINARY DRAINAGE STUDY PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,

More information

APPENDIX F RATIONAL METHOD

APPENDIX F RATIONAL METHOD 7-F-1 APPENDIX F RATIONAL METHOD 1.0 Introduction One of the most commonly used procedures for calculating peak flows from small drainages less than 200 acres is the Rational Method. This method is most

More information

Treatment Volume: Curve Numbers. Composite CN or Not? Treatment Volume: Curve Numbers. Treatment Volume: Calculation. Treatment Volume: Calculation

Treatment Volume: Curve Numbers. Composite CN or Not? Treatment Volume: Curve Numbers. Treatment Volume: Calculation. Treatment Volume: Calculation Stormwater Engineering Bioretention Design Bill Hunt, PE, Ph.D. Extension Specialist & Assistant Professor NCSU-BAE www.bae.ncsu.edu/stormwater Bioretention Design Six Step Process 1 Determine Volume to

More information

Outlet Structure Modeling

Outlet Structure Modeling Watershed Modeling using HEC-RAS Outlet Structure Modeling Jeff Wickenkamp, P.E., CFM, D.WRE Patrick Lach, P.E. Hey and Associates, Inc. Water Resources, Wetlands and Ecology Outline of Presentation Why

More information

Environmental Design Group

Environmental Design Group SEDIMENT CONTROL DURING CONSTRUCTION, STORMWATER MANAGEMENT AND POST CONSTRUCTION BMP REPORT for Hudson Salt Storage and Bus Garage 5810 Hudson Drive HUDSON, OHIO SUMMIT COUNTY Prepared by Environmental

More information

Technical Memorandum

Technical Memorandum Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum To: Kathy Arnold From: Greg Hemmen, P.E. Company: Rosemont Copper Company Date:

More information

FAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF

FAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF FAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF Factors Affecting Stormwater Runoff: Rainfall intensity % Impervious surfaces Watershed size Slope Soil type, soil compaction

More information

iswm TM Technical Manual Hydrology:

iswm TM Technical Manual Hydrology: : 1.0 2.0 Downstream Assessment 3.0 Streambank Protection 4.0 Water Balance 5.0 Rainfall Tables 6.0 Hydrologic Soils Data Table of Contents 1.0... HO-1 1.1 Estimating Runoff... HO-1 1.1.1 Introduction

More information

Learning objectives. Upon successful completion of this lecture, the participants will be able to describe:

Learning objectives. Upon successful completion of this lecture, the participants will be able to describe: Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to describe: The different approaches for estimating peak runoff for urban drainage network

More information

ENGN.4010 ENGINEERING CAPSTONE DESIGN Watershed Analysis. CiA

ENGN.4010 ENGINEERING CAPSTONE DESIGN Watershed Analysis. CiA RATIONAL METHOD Q CiA Where: Q = Maximum Rate of Runoff (cfs) C = Runoff Coefficient i = Average Rainfall Intensity (in/hr) A = Drainage Area (in acres) RATIONAL METHOD Assumptions and Limitations: Watershed

More information

Appendix F. Flow Duration Basin Design Guidance

Appendix F. Flow Duration Basin Design Guidance Appendix F Flow Duration Basin Design Guidance Appendix F FINAL REPORT F:\SC46\SC46.31\HMP Mar 05\Appendices\Appendix F FLY_HMP.doc MARCH 2005 Appendix F Flow Duration Basin Design Guidance Prepared by

More information

The prioritization list along with the estimated probable construction cost and future cost index is shown in Table 1.

The prioritization list along with the estimated probable construction cost and future cost index is shown in Table 1. EXECUTIVE SUMMARY To address flooding concerns and assess costs of potential capital improvement projects associated with flooding in the downtown Town Center Area Plan (TCAP), the Town of Cary commissioned

More information

SECTION III: WATERSHED TECHNICAL ANALYSIS

SECTION III: WATERSHED TECHNICAL ANALYSIS Trout Creek Watershed Stormwater Management Plan SECTION III: WATERSHED TECHNICAL ANALYSIS A. Watershed Modeling An initial step this study of the Trout Creek watershed was the selection of a stormwater

More information

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall 6.0 Introduction This chapter summarizes methodology for determining rainfall and runoff information for the design of stormwater management facilities in the City. The methodology is based on the procedures

More information

100-yr Design Runoff (cfs) Basin ID 103b A a B B C Totals

100-yr Design Runoff (cfs) Basin ID 103b A a B B C Totals PROPOSED DEVELOPMENT The drainage for this site has been designed to be less than the maximum allowable runoff from each basin as stated in the Overall Rigden Farm drainage plan. Table 1 compares the actual

More information

5/11/2007. WinTR-55 for Plan Reviews Small Watershed Hydrology Overview

5/11/2007. WinTR-55 for Plan Reviews Small Watershed Hydrology Overview WinTR-55 for Plan Reviews Small Watershed Hydrology Overview 1 Overview Course Outline Historical Background Program Description Model Capabilities and Limitations This is the Overview portion of the training.

More information

Table of Contents CHAPTER. Chapter 2 Hydrologic Analysis. 2.1 Estimating Runoff

Table of Contents CHAPTER. Chapter 2 Hydrologic Analysis. 2.1 Estimating Runoff CHAPTER Table of Contents 2 Chapter 2 Hydrologic Analysis 2.1 Estimating Runoff 2.1.1 Introduction to Hydrologic Methods...2.1-1 2.1.2 Symbols and Definitions...2.1-4 2.1.3 Rainfall Estimation...2.1-5

More information

GIS Enabled Automated Culvert Design

GIS Enabled Automated Culvert Design GIS Enabled Automated Culvert Design Andrew Graettinger, PhD Ashton Greer, Leah Clifton, Zachary Wilbanks, and Bradford Wilson The University of Alabama Civil, Construction, and Environmental Engineering

More information

Stormwater Manual. City of Mason, Ohio. May 2010

Stormwater Manual. City of Mason, Ohio. May 2010 City of Mason, Ohio May 2010 Contents City of Mason, Ohio Section 1 - Introduction... 1 1.1 Stormwater Policy Goals...1 1.2 Construction Plan Submittal Requirements...2 1.3 Symbols & Abbreviations...3

More information

Appendix A. Compliance Calculator Guidance

Appendix A. Compliance Calculator Guidance Compliance Calculator Guidance Appendix A Appendix A. Compliance Calculator Guidance A.1 Introduction The Center for Watershed Protection created the compliance calculator spreadsheet to allow a designer

More information

State Standard. for. Stormwater Detention/Retention

State Standard. for. Stormwater Detention/Retention ARIZONA DEPARTMENT OF WATER RESOURCES FLOOD MITIGATION SECTION State Standard for Stormwater Detention/Retention Under the authority outlined in ARS 48-3605(a) the Director of the Arizona Department of

More information

City of Morristown. Stormwater Program Standard Operating Procedures. Stormwater Design Guidance Manual. April 1, 2016.

City of Morristown. Stormwater Program Standard Operating Procedures. Stormwater Design Guidance Manual. April 1, 2016. City of Morristown Stormwater Program Standard Operating Procedures Stormwater Design Guidance Manual April 1, 2016 -Prepared By- City of Morristown 100 West First North Street Morristown, TN 37814 (423)

More information

3.3 Acceptable Downstream Conditions

3.3 Acceptable Downstream Conditions iswm TM Criteria Manual - = Not typically used or able to meet design criterion. 1 = The application and performance of proprietary commercial devices and systems must be provided by the manufacturer and

More information

City of Tulsa. Stormwater Design Criteria Manual

City of Tulsa. Stormwater Design Criteria Manual City of Tulsa Stormwater Design Criteria Manual 2014 Table of Contents Chapter 100 EXECUTIVE SUMMARY... 101 101 INTRODUCTION... 101 101.1 Manual Organization... 101 101.2 Manual Contents... 101 101.2.1

More information

FROM ROOFTOP TO DRAIN NON-TRADITIONAL APPLICATIONS OF HEC-RAS 2D FROM ROOFTOP. Calibration: A Hands-On Approach to Making a Model Reflect Reality

FROM ROOFTOP TO DRAIN NON-TRADITIONAL APPLICATIONS OF HEC-RAS 2D FROM ROOFTOP. Calibration: A Hands-On Approach to Making a Model Reflect Reality FROM ROOFTOP TO DRAIN NON-TRADITIONAL APPLICATIONS OF HEC-RAS 2D Andrew C. Yung, PE, CFM Andres A. Salazar, PhD, PE April 26, 2017 1 FROM ROOFTOP 2 Amphitheater: 97,000 SF flexible engineered fabric roof

More information

4.1 General Methodology and Data Base Development

4.1 General Methodology and Data Base Development Chapter 4 METHODOLOGY 4.1 General and Data Base Development This report project utilized several computer software models and analysis techniques to create the numeric data on which decisions for this

More information

Chapter Introduction. 5.2 Computational Standard Methods HYDROLOGY

Chapter Introduction. 5.2 Computational Standard Methods HYDROLOGY Chapter 5. HYDROLOGY 5.1 Introduction The definition of hydrology is the scientific study of water and its properties, distribution, and effects on the earth s surface, in the soil and the atmosphere.

More information

HERPIC County Storm Drainage Manual

HERPIC County Storm Drainage Manual HERPIC County Storm Drainage Manual C h r is t o p h e r B. B u r k e Research Assistant Highway Extension and Research Project for Indiana Counties Purdue University The HERPIC (Highway Extension and

More information

Contents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek

Contents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek Contents SITE LOCATION / DESCRIPTION... 3 WESTPOINTE STORMWATER MANAGEMENT PLAN... 3 THE ENCLAVE AT WESTPOINTE DETENTION POND... 3 Table

More information

HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS

HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS Project Name: Project Number: Reviewed By: Date: Telephone: Email: Address all items marked with an X Minimum Submittal Requirements 1. Conceptual Review

More information

Runoff Calculations. Time of Concentration (T c or t c ) from one location to another within a watershed. Travel

Runoff Calculations. Time of Concentration (T c or t c ) from one location to another within a watershed. Travel Runoff Calculations Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Time of Concentration and Travel Time (based on Chapter 3 of TR-55) Time of Concentration (T c ): time required

More information

A Stormwater Management Plan and Sediment Control Plan are required for all proposed developments within the City of Richmond.

A Stormwater Management Plan and Sediment Control Plan are required for all proposed developments within the City of Richmond. Engineering Page 3-1 3.0 STORM DRAINAGE 3.1 GENERAL Good drainage is vital to flat urban areas such as Lulu Island. It is essential that every storm sewer must be designed accurately minimizing conflicts

More information

Hydrologic Calibration:

Hydrologic Calibration: Hydrologic Calibration: UPDATE OF EFFECTIVE HYDROLOGY FOR MARYS CREEK October 2010 Agenda Background Hydrologic model Calibrated rainfall Hydrologic calibration 100 year discharges, Existing Conditions

More information

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

Appendix B Stormwater Site Plan Submittal Requirements Checklist

Appendix B Stormwater Site Plan Submittal Requirements Checklist Stormwater Site Plan Submittal Requirements Checklist The Submittal Requirements Checklist is intended to aid the design engineer in preparing a Stormwater Site Plan. All items included in the following

More information

FINAL DRAINAGE REPORT FALLBROOK FILING NO. 3 Thornton, CO

FINAL DRAINAGE REPORT FALLBROOK FILING NO. 3 Thornton, CO FINAL DRAINAGE REPORT FALLBROOK FILING NO. 3 Thornton, CO May 6, 2016 JN: 14053 Prepared for: Carlson Associates CalAtlantic Homes PO Box 247 6161 S. Syracuse Way, Suite 200 Eastlake, CO 80614 Greenwood

More information

CHELTENHAM TOWNSHIP Chapter 290: WATERSHED STORMWATER MANAGEMENT Article IV: Stormwater Management

CHELTENHAM TOWNSHIP Chapter 290: WATERSHED STORMWATER MANAGEMENT Article IV: Stormwater Management CHELTENHAM TOWNSHIP Chapter 290: WATERSHED STORMWATER MANAGEMENT Article IV: Stormwater Management Online ECode Available on Cheltenham Township Website at: http://ecode360.com/14477578 For all regulated

More information

Software Applications for Runoff Hydrological Assessment

Software Applications for Runoff Hydrological Assessment Bulletin UASVM Horticulture, 67(2)/2010 Print ISSN 1843-5254; Electronic ISSN 1843-5394 Software Applications for Runoff Hydrological Assessment Severin CAZANESCU 1), Sorin CIMPEANU 1), Oana GUI 2), Dana

More information

Introduction to Storm Sewer Design

Introduction to Storm Sewer Design A SunCam online continuing education course Introduction to Storm Sewer Design by David F. Carter Introduction Storm sewer systems are vital in collection and conveyance of stormwater from the upstream

More information

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228 Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA 30534 (706) 344-3500 x 42228 DAWSON COUNTY STORM WATER REVIEW CHECKLIST Project Name: Property Address: Engineer: Fax #/Email: Date:

More information

Stormwater Volume and Treatment Methods Simplifying the Numbers. IAFSM March 10, Presented by: Tom Powers P.E., CFM, LEED AP, CPESC

Stormwater Volume and Treatment Methods Simplifying the Numbers. IAFSM March 10, Presented by: Tom Powers P.E., CFM, LEED AP, CPESC Stormwater Volume and Treatment Methods Simplifying the Numbers IAFSM March 10, 2011 Presented by: Tom Powers P.E., CFM, LEED AP, CPESC Introduction GOALS: Improve understanding of Rate and Volume (Quantity)

More information

January 20, Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO (303)

January 20, Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO (303) January 20, 2017 Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO 80229 (303) 538-7694 RE: Riverdale Five Retail Drainage Conformance Letter

More information

Urban Drainage Introduction. A.Ramachandra Rao. C.B. Burke. T.T. Burke, Jr.

Urban Drainage Introduction. A.Ramachandra Rao. C.B. Burke. T.T. Burke, Jr. 32 Urban Drainage A.Ramachandra Rao Purdue University C.B. Burke Christopher B. Burke Engineering, Ltd. T.T. Burke, Jr. Christopher B. Burke Engineering, Ltd. 32.1 Introduction 32.2 The Rational Method

More information

Alternatives for Willow Creek Flood Mitigation Study

Alternatives for Willow Creek Flood Mitigation Study Alternatives for Willow Creek Flood Mitigation Study Presented by: Anil Tangirala, PE, CFM, ENV SP ms consultants, inc. June 22, 2016 Presentation Overview Introduction Project Background Willow Creek

More information

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01 Stormwater Management Studies PDS Engineering Services Division Revised Date: 2/28/08 INTRODUCTION The City of Overland Park requires submission of a stormwater management study as part of the development

More information