VAV WITH ELECTRIC HEATER
|
|
- Brandon Carr
- 6 years ago
- Views:
Transcription
1 VAV WITH ELECTRIC HEATER
2 Electric Heater Electric heating coils are applied on VAV terminal units as terminal reheat devices. Electric heat coil capacity is rated in kilowatts (kw). Coils are available with the total capacity divided into one. two, or three stages. Electric heat coils are available in single-phase or three-phase models. This refers to the type of power source connected to the coil. Single-phase models have resistance elements internally connected in parallel. The current drawn for the electric coil will depend whether it is single phase coil or a three phase coil. The current drawn is necessary for determining what size wire should be used to power the electric coils and how big the primary power fusing should be. The equations for current draw for these coils are: 1 ö amps = kw x 1000 / Primary Voltage 3 ö amps = kw x 1000 / Primary Voltage x 3 It is important to note that these coils have certain minimum airflow rates for each amount of kw heat the coils can supply to operate safely. These airflow values are based upon a maximum rise across the electric heat coil of 50 F (28 C). The equation that relates the airflow across an electric coil to the temperature rise and the coil change in temperature is: CFM = kw x 3145 /?T Where: CFM = Minimum airflow rate across the coil kw = The heating capacity of the electric coil 3145 = A constant.?t = The maximum rise in air temperature across the coil (usually 50 F (28 C)) 3
3
4 SELECTION GUIDELINES: 1) Once the design air flow has been determined refer to the appropriate air flow limits to select the size of unit required to deliver the specified air flow. 2) With size and air flow known, electric reheat capacity can be calculated. Refer to the electric coil selection procedure below for details. 3) With the heating capacity known, confirm: a. Power Supply requirements from coil selection charts. b. The minimum air flow requirements are met (at least 70 cfm/kw), and that the discharge air temperature does not exceed 120 F. 4) Select coil options. 5. Static pressure loss of the coil elements is negligible, therefore minimum pressure is equal to the basic unit values. 6. For stable operation of heater controls minimum discharge static pressure of 0.2 in. w.g. is recommended. 4
5 How to Use the Chart Electric Coil Selection Procedure The selection of an electric coil for a single duct terminal unit requires the determination of the two comp onents of the heat loss. One component is the heat required to satisfy the space load. The second component is the heat required to raise the temperature of the primary air to that of the space. This can be determined as follows, using the Electric Reheat Selection Chart and the equation as given below. Reheat Selection Chart 1) Locate the room heat loss on the MBH scale on the far left side of the chart. Convert to kw by moving horizontally to the right to the kw scale (1 kw = MBH). 2) Calculate the kw required to heat the primary air to room temperature using the following equation: kw = ( cfm x 1.08 x?t / 3413 ) 5
6 3) Add the kw value obtained in step 2 to the kw scale at the left side. Move horizontally to the right to the point where the kw value and the air flow volume intersect. 4) With the point of intersection from step three, the air temperature rise (ATR), can be obtained by interpolating between the air temperature rise lines on the graph. 5) To verify the selection, sum the air temperature rise and the temperature of the primary air. The sum total should be less than 120 F. Selection Example Select electric coil for a size 12 in. with a minimum air flow of 700 cfm. Space heat loss is estimated at 20 MBH and space design temperature is 70 F. The temperature of the primary air flow is 58 F. 1) Space heat loss (20 MBH) = 5.9 kw. 2) Heat required to raise the temperature of the primary air: kw = (cfm x 1.08 x?t / 3413) kw = (700 x 1.08 x 12 / 3413) kw = 2.65 kw 3) Total heat required = = 8.6 Kw. 4) Air temperature rise (ATR) = 40 F (From graph) 5) Leaving air temperature = 58 F + 40 F = 98 F. Since the leaving air temperature is less than the recommended maximum limit of 120 F, the selection is satisfactory. 6) Select a suitable power supply from the Coil Selection Charts. 7) Verify minimum air flow requirements are met. (Minimum 70 cfm/kw) 700 cfm / 8.6 kw = 81 cfm/kw 6
7 Electric data Single duct VAV-PI-EH Electric coil kw guideline Minimum to maximum
8 Minimum and maximum Airflow per Inlet size and kw x x 8
9 Performance data - Electric data Single duct
10 Performance data - Electric data Single duct
11 Performance data - Electric data Single duct
12 Welding Robot
MF Product Specifications
Product Specifications MODULAR ELECTRIC FURNACE 2, 3, 4, and 5 TONS FEATURES Modular Blower Cabinet, Air Conditioning or Heat Pump ready Upflow, horizontal right or left applications Downflow requires
More informationSECTION AIR TERMINAL UNITS
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:
More informationMV Product Specifications
MODULAR VARIABLE SPEED BLOWER CABINET 2, 3, 4, and 5 TONS FEATURES Variable Speed modular blower Supports two-stage outdoor units Dehumidification Speed: 80% Airflow Efficient low continuous fan selection:
More information2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load.
Redesign Introduction This report is an in depth analysis of the mechanical systems of the Outreach Innovation Building located in University Park, PA and the impact these changes had on other systems
More informationSample Reports. for. HAP v4.90 Example Problem
Sample Reports for HAP v4.90 Example Problem December, 2014 Carrier Software Systems Copyright 2014 Carrier Corporation, All Rights Reserved Introduction This document contains reports generated using
More informationSample Reports. for. HAP v4.80 Example Problem
Sample Reports for HAP v4.80 Example Problem October, 2013 Carrier Software Systems Copyright 2013 Carrier Corporation, All Rights Reserved Introduction This document contains reports generated using the
More informationProduct Specifications
Product Specifications MODULAR ELECTRIC FURNACE 2, 3,4,and5TONS FEATURES S Modular Blower Cabinet, Air Conditioning or Heat Pump ready S Upflow, horizontal right or left applications S Downflow requires
More informationOUTDOOR AIR, HEAT WHEELS AND JCPENNEY: A NEW APPROACH TO RETAIL VENTILATION
OUTDOOR AIR, HEAT WHEELS AND JCPENNEY: A NEW APPROACH TO RETAIL VENTILATION Christopher S. Smith, E.I.T. and Thomas A. Bartlett, P.E. JCPenney Company, Inc. Construction Services Mechanical Engineering
More informationHVAC SYSTEM CONFIGURATIONS, AN ENERGY ASPECT
HVAC SYSTEM CONFIGURATIONS, AN ENERGY ASPECT Y Zhang 1,*, JA Wright 2 and VI Hanby 1 1 Institute of Energy and Sustainable Development, De Montfort University, Leicester, LE1 9BH, UK 2 Department of Civil
More informationW = ItV P = IV. P = W t FXA Candidates should be able to :
1 Candidates should be able to : Describe power as the rate of energy transfer. ELECTRICAL POWER (P) of an appliance or device is the rate at which it transfers electrical energy into other energy forms.
More informationDVPEC. Multi-Position, Variable-Speed air handler. Comfortnet Compatible ECM-based Internal EEV, Inverter-tuned 2 to 5 Tons
DVPEC Multi-Position, Variable-Speed air handler Comfortnet Compatible ECM-based Internal EEV, Inverter-tuned 2 to 5 Tons Contents Nomenclature... 2 Product Specifications... 3 Dimensions... 4 Airflow
More informationFundamentals of Acoustics
providing insights for today s hvac system designer Engineers Newsletter volume 47 4 Understanding VAV Sound Standards Acoustics are an important and often overlooked topic in HVAC&R. Many pieces of equipment
More informationOPTIMAL OPERATION OF VAV AIR-CONDITIONING SYSTEM
Nabil NASSIF *, Stanislaw KAJ *, Robert SABOURIN * Key words: VAV system, controller set point, optimization, genetic algorithm OPTIMAL OPERATION OF VAV AIR-CONDITIONING SYSTEM The detailed and simplified
More informationASPT Series. Multi-Position, Multi-Speed, ECM-Based Air Handler with Internal TXV 1½ to 5 Tons. Contents. Product Features
Series Multi-Position, Multi-Speed, ECM-Based Air Handler with Internal TXV ½ to Tons Contents Air Handler Nomenclature... Heater Kit Nomenclature... Product Specifications... Dimensions... Airflow Data...
More informationNV series. Induction VAV air volume control terminals
NV series Induction VAV Table of contents Description Page Type designation 1 Technical data - General 2 - Specification 3 - Installation instruction 3 overview / dimensions 4-5 Sound data NVOAOOB 6-7
More informationBLOWER COILS. 2 THRU 5 TONS SPLIT SYSTEM EBP Export Series FEATURES
BLOWER COILS 2 THRU 5 TONS SPLIT SYSTEM EBP Export Series FEATURES Representative photo only, some models may vary in appearance. 2 -- 5 ton sizes available Multipoise design for maximum versatility 2--speed
More informationARUF Series. Multi-Position, Multi-speed Air Handler with PSC Motor 1½ to 5 Tons. Contents. Product Features
Series Multi-Position, Multi-speed Air Handler with PSC Motor 1½ to 5 Tons Contents Nomenclature... 2 Product Specifications... 3 Heater Kit Nomenclature... 3 Dimensions... 4 Airflow Data... 5 Heat Kit
More informationModular Active Chilled Beams
Modular Active Chilled Beams Presented by: Darren Alexander, P.Eng. Modular Active Chilled Beams Current System Solutions Fan Coil Units - Medium/High energy, medium noise solution. Output = 100-200 w/m
More informationTLT-413 (02) METHOD TO ESTIMATE STANDARD PROCTOR MAXIMUM DRY DENSITY AND OPTIMUM MOISTURE CONTENT OF FINE GRAINED SOILS
METHOD TO ESTIMATE STANDARD PROCTOR MAXIMUM DRY DENSITY AND OPTIMUM MOISTURE CONTENT OF FINE GRAINED SOILS 1.0 SCOPE 1.1 This procedure is used for estimating the Standard Proctor maximum dry density and
More informationChapter 21 Electric Current & DC Circuits
Chapter 21 Electric Current & DC Circuits Optional: Ammeters and Voltmeters (21-8) Optional: RC Circuits (21-9) Water U Reservoirs store potential energy in water at high elevation. This energy comes
More informationASPT Series. Multi-Position, Multi-Speed, ECM-Based Air Handler with Internal TXV 1½ to 5 Tons. Contents. Product Features
Series Multi-Position, Multi-Speed, ECM-Based Air Handler with Internal TXV ½ to Tons Contents Air Handler Nomenclature... Heater Kit Nomenclature... Product Specifications... Dimensions... Airflow Data...
More informationENGINEERING UPDATE JULY VOLUME 11 THIS PACKAGE INCLUDES A COLLECTION OF ARTICLES FROM VOLUME 11 OF THE JULY 2013 ENGINEERING UPDATE.
ENGINEERING UPDATE JULY 2013 - VOLUME 11 THIS PACKAGE INCLUDES A COLLECTION OF ARTICLES FROM VOLUME 11 OF THE JULY 2013 ENGINEERING UPDATE. TABLE OF CONTENTS: Terminal Unit Acoustical Considerations...
More informationExisting Building Cx: Processes & Results A Cultural Journey. Barry Abramson Senior Vice President Servidyne
Existing Building Cx: Processes & Results A Cultural Journey Barry Abramson Senior Vice President Servidyne AIA Quality Assurance Learning Objectives 1. Define the key steps in the process of retrocommissioning
More informationARUF Series. Multi-Position, Multi-speed Air Handler with PSC Motor 1½ to 5 Tons. Contents. Product Features
Series Multi-Position, Multi-speed Air Handler with PSC Motor 1½ to 5 Tons Contents Nomenclature... 2 Product Specifications... 3 Heater Kit Nomenclature... 3 Dimensions... 4 Airflow Data... 5 Heat Kit
More informationBLOWER COILS. 1½ THRU 5 TONS SPLIT SYSTEM EBP / EBX / EBXX Series FEATURES EBP MODEL FEATURES EBX/EBXXMODELFEATURES
BLOWER COILS 1½ THRU 5 TONS SPLIT SYSTEM EBP / EBX / EBXX Series FEATURES Representative photo only, some models may vary in appearance. Grooved copper tubing Lanced sine--wave aluminum fin Fully wettable
More informationDAT Commercial ELECTRIC AIR HANDLERS FOR 7½ & 10-TON SPLIT SYSTEMS
DAT Commercial ELECTRIC AIR HANDLERS F 7½ & 0-TON SPLIT SYSTEMS Contents Nomenclature... Product Specifications... Airflow Data... Heating Kit Data...6 Dimensions...7 Wiring Diagrams...8 Standard Features
More informationCabinet air leakage less than 2.0% at 1.0 inch H₂O when cooling and heat pump applications.
AVPEC Multi-Position, Variable-Speed, ECM-Based Air Handler with Internal EEV, ComfortNet and Inverter Compatible to 5 Tons Contents Nomenclature... Product Specifications... Dimensions... Airflow Data...
More informationSECTION TESTING, ADJUSTING AND BALANCING (TAB) OF HEATING, VENTILATING & AIR CONDITIONING (HVAC) SYSTEMS
PART 1 GENERAL 1.1 SCOPE OF SERVICES: SECTION 15991 TESTING, ADJUSTING AND BALANCING (TAB) OF HEATING, VENTILATING & AIR CONDITIONING (HVAC) SYSTEMS A. The District, under separate contract, shall provide
More informationReducing Hospital Energy Use and Maintaining Savings. Glen Anderson, PE
Reducing Hospital Energy Use and Maintaining Savings Glen Anderson, PE AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing
More informationBLOWER COILS COMMERCIAL
BLOWER COILS COMMERCIAL 2 THRU 5 TONS SPLIT SYSTEM EBP / EBX / EBXX Series FEATURES Representative photo only, some models may vary in appearance. Listed By Underwriters Laboratories Grooved copper tubing
More informationI. Khoo, BEng(Hons), G.J. Levermore, BSc, ARCS, PhD, DIC, CEng, FCIBSE, MASHRAE, MInstE, K.M. Letherman, BSc, MSc, PhD, CEng, FIEE, FCIBSE.
Duct Loops and VAV Modelling and Control I. Khoo, BEng(Hons), G.J. Levermore, BSc, ARCS, PhD, DIC, CEng, FCIBSE, MASHRAE, MInstE, K.M. Letherman, BSc, MSc, PhD, CEng, FIEE, FCIBSE. Abstracts This paper
More informationUsing System Curves to Avoid Problems in VAV Systems
AMCA International Using System Curves to Avoid Problems in VAV Systems Ronald Wroblewski Owner, Productive Energy Solutions, LLC, Madison, Wisconsin, USA Ron@ProductiveEnergy.com Air System Engineering
More informationYou Can t Afford Discomfort. Dan Int-Hout Chief Engineer, Krueger Richardson, Texas
You Can t Afford Discomfort Dan Int-Hout Chief Engineer, Krueger Richardson, Texas Where We Are Today: So You Want To Save Money? Things to consider: 1. First Cost 2. Energy cost 3. Occupant Salary costs
More informationCFFWA-20-1-U Chilled/Hot Water Universal Mount Fan Coil 2-Pipe Heat / Cool Fan Coil 60,000 BTUH
CFFWA-20-1-U Chilled/Hot Water Universal Mount Fan Coil 2-Pipe Heat / Cool Fan Coil 60,000 BTUH Rev. 1.3 HVAC Guide Specifications Chilled and Hot Water Universal Mount Fan Coil 2-Pipe Nominal Size: 60,000
More informationCHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM
CHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM 1. Category (Check one and indicate New or Existing, if applicable) Commercial Buildings New or Existing Institutional Buildings: Educational Facilities New
More informationAdvanced Testing for Innovative Design
Advanced Testing for Innovative Design T he Norman Asbjornson Innovation Center (NAIC) solidifies AAON as the technological leader in high performance HVAC equipment. Since the groundbreaking of the research
More informationCanada Published online: 28 Feb 2011.
This article was downloaded by: [Bibliothèque ÉTS] On: 21 July 2015, At: 04:30 Publisher: Taylor & Francis Informa Ltd Registered in England and Wales Registered Number: 1072954 Registered office: 5 Howick
More informationFactor. For a building owner concerned with operating costs, the clear- How it Affects Operating Cost
006, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Published in ASHRAE Journal, (Vol. 48, February 006). For personal use only. Additional distribution
More informationTechnology and Engineering Development (TED) Building. ASHRAE Std and Std Compliance Report
Technology and Engineering Development (TED) Building Thomas Jefferson National Accelerator Facility Newport News, VA Tech Report I ASHRAE Std. 62.1-2007 and Std. 90.1-2007 Compliance Report 10/4/2010
More informationThe baseline building system for compliance with Senate Bill 668 is defined by Appendix G,
Project: North Carolina A&T State University New Student Health Center SCO #: 08-08109-01A 1.0 Heating, Ventilating and Air Conditioning (HVAC) Baseline Building Systems Senate Bill 668 Compliance The
More informationHourly Analysis Program v.4.1 Page 1 of 1
Air System Design Load Summary for Zona 11 DESIGN COOLING DESIGN HEATING COOLING DATA AT Dec 1700 HEATING DATA AT DES HTG COOLING OA DB / WB 33.1 C / 23.5 C HEATING OA DB / WB -0.6 C / -3.2 C Sensible
More information7 th NATIONAL CERTIFICATION EXAMINATION Nov FOR ENERGY MANAGERS & ENERGY AUDITORS
Regn No: Name: (To be written by the candidates) 7 th NATIONAL CERTIFICATION EXAMINATION Nov. 2008 FOR ENERGY MANAGERS & ENERGY AUDITORS PAPER 3: Energy Efficiency in Electrical Utilities Date: 23.11.2008
More informationFundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619
AABC Commissioning Group AIA Provider Number 50111116 Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 Jim Hall, PE, TBE, CxA Systems Management & Balancing,
More informationMechanical Technical Report Three Mechanical Systems Existing Conditions Evaluation
Mechanical Technical Report Three Mechanical Systems Existing Conditions Evaluation 2900 Fairview Park Drive, Prepared By: Charles Haack Mechancial Option November 21, 2008 Prepared For: Dr. William P.
More informationHourly Analysis Program v.4.1 Page 1 of 1
Air System Design Load Summary for Zona 6 DESIGN COOLING DESIGN HEATING COOLING DATA AT Feb 1600 HEATING DATA AT DES HTG COOLING OA DB / WB 34.5 C / 23.7 C HEATING OA DB / WB -0.6 C / -3.2 C Sensible Latent
More informationRetrocommissioning Investigation Report
Continuous Optimization for Commercial Buildings Program Retrocommissioning Investigation Report March 22, 2013 Prepared for: Thompson Rivers University International Building BC Hydro #:COP10-353 Prism
More informationThree Case Studies of the Application of Energy Systems Optimization Best Practices for Automatic Demand Response
Three Case Studies of the Application of Energy Systems Optimization Best Practices for Automatic Demand Response Yifu Shi Kelly Guiberteau Carlos Yagua, P.E. James Watt, P.E. Energy Systems Laboratory,
More informationProject Name: Example Building OFPC Project No.: 12345
Energy Impact Statement Project Name: Example Building OFPC Project : 12345 Building Description and Assumptions: The design professional shall provide a brief narrative describing various building related
More informationCOOLING COIL (35% ETHYLENE GLYCOL)
APPENDIX Contents A1.1 Existing Mechanical Equipment Schedules A1.2 Existing Mechanical System Schematic Drawings A2. Building Design Loads, Energy Loads and Cost Data Tables A3. Standard 62n-2001 Ventilation
More informationBLOWER COILS. 2 THRU 5 TONS SPLIT SYSTEM EBW 50 Hz Series FEATURES Sept. 2502
BLOWER COILS 2 THRU 5 TOS SPLIT SYSTEM EBW 50 Hz Series FEATURES Grooved copper tubing Lanced sine--wave aluminum fin Fully wettable coils High--impact thermoplastic condensate pan Primary and secondary
More informationSt. Monica Food Pantry Testing, Adjusting, & Balancing for HVAC sys-tek No
St. Monica Food Pantry 23 0593-1 HVAC WORK DIVISION 23 SECTION 230593 TESTING, ADJUSTING, & BALANCING FOR HVAC PART 1. GENERAL 1.1 DESCRIPTION OF WORK A. Air balancing of dedicated outside air systems
More informationGuided Reading Chapter 10: Electric Charges and Magnetic Fields
Name Number Date Guided Reading Chapter 10: Electric Charges and Magnetic Fields Section 10-1: Electricity, Magnetism, and Motion 1. The ability to move an object some distance is called 2. Complete the
More informationConservation of Energy by Installing Solar PV System
Conservation of Energy by Installing Solar PV System Abhishek R 1, Dilip Kumar M 2, Vivek S 3 1Assistant Professor Department of Civil engineering, JSS Academy of Technical Education, Karnataka, India
More informationHourly Analysis Program v.4.1 Page 1 of 1
Air System Design Load Summary for Zona 9 DESIGN COOLING DESIGN HEATING COOLING DATA AT Jan 1400 HEATING DATA AT DES HTG COOLING OA DB / WB 34.5 C / 23.7 C HEATING OA DB / WB -0.6 C / -3.2 C Sensible Latent
More informationDEVELOPMENT OF A LABORATORY VERIFIED SINGLE-DUCT VAV SYSTEM MODEL WITH FAN POWERED TERMINAL UNITS OPTIMIZED USING COMPUTATIONAL FLUID DYNAMICS
DEVELOPMENT OF A LABORATORY VERIFIED SINGLE-DUCT VAV SYSTEM MODEL WITH FAN POWERED TERMINAL UNITS OPTIMIZED USING COMPUTATIONAL FLUID DYNAMICS A Dissertation by MICHAEL A. DAVIS Submitted to the Office
More informationYORK BULKHEAD MOUNTED CHILLED BEAMS ENGINEERING GUIDE
YORK BULKHEAD MOUNTED CHILLED BEAMS ENGINEERING GUIDE Contents YORK Bulkhead Active Chilled Beams 3 CB-ABB-YK / CB-ABC-YK Performance Data 5 CB-ABB-YK Dimensions 10 CB-ABC-YK Dimensions 11 Specifications
More informationNorth Pocono High School
Building System Integration Energy and Cost Analysis Architectural Engineering Senior Thesis Presentation Pennsylvania State University Presentation Outline Project Outline Existing System Design Conditions
More informationSTART-UP CHECKLIST. Date: Job Name: Customer Name: Address: City: State: Zip: Model Number: Serial Number: Qualified Start-up Technician:
START-UP INSTRUCTION SERIES 20 J**YC/YD 90000 To 300000 BTU S SPLIT SYSTEM CONDENSING UNITS 7.5 To 25 TON START-UP CHECKLIST Date: _ Job Name: Customer Name: Address: City: State: Zip: Model Number: Serial
More informationHourly Analysis Program v.4.1 Page 1 of 1
Air System Design Load Summary for Zona 8 DESIGN COOLING DESIGN HEATING COOLING DATA AT Dec 1700 HEATING DATA AT DES HTG COOLING OA DB / WB 33.1 C / 23.5 C HEATING OA DB / WB -0.6 C / -3.2 C Sensible Latent
More informationXavier Energy Initiative
Xavier Energy Initiative By Ron Perkins Report of August Site Visit To paraphrase Blaise Pascal, if I had more time I would have written a shorter report. In deference to those who do not share my enthusiasm
More informationProduct Data. (Unit shown with optional economizer.)
COOLING ONLY/ELECTRIC HEAT PACKAGED ROOFTOP UNIT 15 TO 27.5 NOMINAL TONS Product Data (Unit shown with optional economizer.) C09316 Use of the AHRI Certified TM Mark indicates a manufacturer s participation
More informationPerformance Rated for Water Loop Applications Cooling capacities : entering air conditions of 80.6ºF db / 66.2º F wb, 86ºF entering water temperature
Performance Rated for Water Loop Applications Cooling capacities : entering air conditions of 80.6ºF db / 66.2º F wb, 86ºF entering water temperature Heating capacities : entering air conditions of 68ºF
More informationEBP. Product Specifications. EBP Fan Coils 2 THRU 5 TONS SPLIT SYSTEM FEATURES
ENVIRONMENTALLY SOUND REFRIGERANT EBP Product Specifications EBP Fan Coils 2 THRU 5 TONS SPLIT SYSTEM FEATURES Multipoise design for maximum versatility 2 speed motor in 24 and 36 sizes 3 speed motor in
More informationHourly Analysis Program v.4.1 Page 1 of 1
Air System Design Load Summary for Zona 3 Project Name: Av. Cabildo 3067, 4 piso 02/13/2011 DESIGN COOLING DESIGN HEATING COOLING DATA AT Feb 1500 HEATING DATA AT DES HTG COOLING OA DB / WB 34.9 C / 23.8
More informationModeling the Performance of ECM and SCR Series Fan-Powered Terminal Units in Single-Duct VAV Systems
CH-12-017 Modeling the Performance of ECM and SCR Series Fan-Powered Terminal Units in Single-Duct VAV Systems Michael A. Davis, PhD John A. Bryant, PhD, PE Dennis L. O Neal, PhD, PE Member ASHRAE Member
More informationGeorgetown University New Science Center
Georgetown University New Science Center Final Thesis Proposal PENN STATE UNIVERSITY Prepared For: Dr. William P. Bahnfleth Department of Architectural Engineering Prepared By: Kevin M Edstrom Mechanical
More informationDDK DUCT (IN-SLAB DUCT SYSTEM)
DDK DUCT (IN-SLAB DUCT SYSTEM) General information Components Fan sizing table Testing data MAX 3-H F & FT RATING Tested in accordance with ULC S115-M95 and ASTM E814-02 Distributed by: Dennis D.Kiselbach
More informationNavigating the Cooling, Heating and Reheat Process on the Psychrometric Chart
Navigating the Cooling, Heating and Reheat Process on the Psychrometric Chart Four examples of cooling will be reviewed in the following examples. The first is an example of sensible mechanical cooling,
More informationOklahoma University Children s Medical Office Building
Oklahoma University Children s Medical Office Building Oklahoma City, O.K., BAE Advisor: Laura Miller Presentation Outline VRF System Dedicated Outdoor Air System Evaluation VRF Indoor Units Design Criteria
More informationMHWW-09-H-1 Chilled/Hot Water Hi-Wall Fan Coil. Heat / Cool Fan Coil 9,000 BTUH. Rev. 1.3
MHWW-09-H-1 Chilled/Hot Water Hi-Wall Fan Coil Heat / Cool Fan Coil 9,000 BTUH Rev. 1.3 HVAC Guide Specifications Chilled and Hot Water Hi-Wall Fan Coil 2-Pipe Nominal Size: 9,000 BTUH Multiaqua Model
More informationMHWW-18-H-1 Chilled/Hot Water Hi-Wall Fan Coil. Heat / Cool Fan Coil 18,000 BTUH. Rev. 1.3
MHWW-18-H-1 Chilled/Hot Water Hi-Wall Fan Coil Heat / Cool Fan Coil 18,000 BTUH Rev. 1.3 HVAC Guide Specifications Chilled and Hot Water Hi-Wall Fan Coil 2-Pipe Nominal Size: 18,000 BTUH Multiaqua Model
More informationMHWW-12-H-1 Chilled/Hot Water Hi-Wall Fan Coil. Heat / Cool Fan Coil 12,000 BTUH. Rev. 1.3
MHWW-12-H-1 Chilled/Hot Water Hi-Wall Fan Coil Heat / Cool Fan Coil 12,000 BTUH Rev. 1.3 HVAC Guide Specifications Chilled and Hot Water Hi-Wall Fan Coil 2-Pipe Nominal Size: 12,000 BTUH Multiaqua Model
More informationRecommended Methods to Evaluate Performance of Variable Air Volume Fume Hood Systems
AIHEC VENT 2006 Recommended Methods to Evaluate Performance of Variable Air Volume Fume Hood Systems Thomas C. Smith Exposure Control Technologies, Inc. Safety is the Primary Objective Lab Occupancy 26%
More informationA Primer on Recovery Efficiency Ratio
A Primer on Recovery Efficiency Ratio By Tom Brooke PE, CEM 2/29/12 INTRODUCTION As well it should be, probably the most used metric in the applied HVAC equipment industry is the concept of Efficiency.
More informationSection A: CUSTOMER INFORMATION. Customer Name Electric Account Number Rate Application Number. Facility Address City State Zip Code
New Equipment & Construction 2017 VFD Incentive Section A: CUSTOMER INFORMATION Customer Name Electric Account Number Rate Number Facility Address City State Zip Code Service Location Identification Email
More informationNEBBinar: Technical Commissioning: The most effective commissioning process for new buildings. March 5, 2014
NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings March 5, 2014 0 Moderator Jim Huber, NEBB President-Elect and President of Complete Commissioning Jim Huber
More informationGerald R. Ford Museum
Gerald R. Ford Museum Grand Rapids, Michigan Executive Summary Building and Plant Energy Analysis Report: Part I Brendan J. Cullen The Pennsylvania State University AE Senior Thesis Mechanical Option September
More informationTroubleshooting Piping Systems
Troubleshooting Piping Systems Last of Three Parts by Ray Hardee (Engineered Software, Inc.) Parts 1 and 2 of this series (Pumps & Systems, September and October 2015) discussed the engineering principles
More informationMechanical Systems Proposal
Mechanical Systems Proposal Prepared for: Dr. William Bahnfleth, Professor The Pennsylvania State University, Department of Architectural Engineering Prepared by: Chris Nicolais Mechanical Option December
More informationBuilding X Retrocommissioning Final Report
Building X Retrocommissioning Final Report A study done by Portland Energy Conservation, Inc. (PECI) And Partner IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC
More informationTECHNICAL SUPPORT MANUAL Fan Coils FSM2X, FSM4X
Fan Coils FSM2X, FSM4X DANGER, WARNING, CAUTION, and NOTE The signal words DANGER, WARNING, CAU- TION, and NOTE are used to identify levels of hazard seriousness. The signal word DANGER is only used on
More informationCOMPARING RAYTEQ PARALLEL HEATING ELEMENT WIRING WITH SERIES ELEMENT WIRING
COMPARING RAYTEQ PARALLEL HEATING ELEMENT WIRING WITH SERIES ELEMENT WIRING SERIES-WIRED FURNACES Many electric resistance melting furnaces are equipped with series-wired heating elements that are usually
More informationSECTION AIR COILS
SECTION 23 82 16 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph
More informationSingle-Phase Meter Installation
Single-Phase Meter Installation S T U D E N T M A N U A L March 31, 2005 2 STUDENT TRAINING MANUAL Prerequisites: None Objectives: From memory, you will be able to explain single-phase meter test procedures,
More informationBUILDING ELECTRICAL AND SIGNAL SYSTEMS. Electricity Background
BUILDING ELECTRICAL AND SIGNAL SYSTEMS Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Grondzik 1 Electricity Background Electric charge was known to the ancient Greeks Magnetism was known historically
More informationEnergy aspects of HVAC system configurations problem definition and test cases
Loughborough University Institutional Repository Energy aspects of HVAC system configurations problem definition and test cases This item was submitted to Loughborough University's Institutional Repository
More informationSmall-Scale Resistance Welding for Medical and Industrial Applications
Small-Scale Resistance Welding for Medical and Industrial Applications Girish P. Kelkar, Ph.D. (author of The Weld Nugget ) http://www.welding-consultant.com/ Excellence In Material Joining Difference
More informationProduct Catalog. Odyssey Split System Heat Pumps R-22 Dry Charge 7½ - 20 Ton, 60 Hz SSP-PRC027-EN. June 2012
Product Catalog Odyssey Split System Heat Pumps R-22 Dry Charge 7½ - 20 Ton, 60 Hz June 2012 SSP-PRC027-EN General Data Table 1. General Data 7½ - 20 Ton Condensing Units 60 Hz 7½ Tons 10 Tons 15 Tons
More informationTHE USE OF HEAT RECOVERY DEVICES FOR REDUCING ENERGY CONSUMPTION OF TREATING VENTILATION AIR IN A TROPICAL OPERATING THEATRE
T13-O-15: Air conditioning components Proceedings: EERB-BEPH 2009 THE USE OF HEAT RECOVERY DEVICES FOR REDUCING ENERGY CONSUMPTION OF TREATING VENTILATION AIR IN A TROPICAL OPERATING THEATRE Y.H. Yau *
More informationFreetown Elementary School
Building and Plant Energy Analysis Technical Report 2 Freetown Elementary School Glen Burnie, MD Matthew R. Buda The Pennsylvania State University Architectural Engineering Mechanical Option Advisor: Dr.
More informationAVPTC. Multi-Position, Variable-Speed, ECM-Based Air Handler with Internal TXV ComfortNet Compatible 1½ to 5 Tons. Contents.
Multi-Position, Variable-Speed, ECM-Based Air Handler with Internal TXV ComfortNet Compatible 1½ to 5 Tons Contents Air Handler Nomenclature... 2 Heater Kit Nomenclature... 2 Product Specifications...
More informationCommissioning Under Floor Air Distribution System A Case Study and Lessons Learned
Commissioning Under Floor Air Distribution System A Case Study and Lessons Learned -or- Where in the world is Paul Tseng? Presented By Scott Nelson, P.E. Summit Building Engineering And in association
More informationANSI/ASHRAE STANDARD , METHODS OF TESTING CHILLED BEAMS
ANSI/ASHRAE STANDARD 200-2015, METHODS OF TESTING CHILLED BEAMS NEMIC 2017 Agenda 1. Foreword 2. Purpose & Scope 3. Definitions 4. Instrumentation & Facilities 5. Test Methods 6. Reporting 7. Normative
More informationDepth: Mechanical Redesign
Depth: Mechanical Redesign Redesign Objectives The most important objective of the mechanical redesign is to provide Greenbriar East with ventilation that meets the requirements of ASHRAE Standard 62-2001.
More informationERT 318/4 UNIT OPERATIONS SEMESTER 1 (2013/2014)
ERT 318/4 UNIT OPERATIONS SEMESTER 1 (2013/2014) WATER COOLING TOWER School of Bioprocess Engineering University Malaysia Perlis EXPERIMENT Water Cooling Tower 1.0 OBJECTIVES 1.1 To determine energy and
More informationAcutherm was spec d here. Building Automation Guide for Therma-Fuser Systems
Building Automation Guide for Therma-Fuser Systems Acutherm was spec d here BUILDING AUTOMATION OPTIONS FOR THERMA-FUSER SYSTEMS As energy costs continue to rise, the management of energy while balancing
More informationProduct Data. 38AUZ Air Cooled Condensing Unit Puronr (R---410A) Refrigerant 6to12.5NominalTons FEATURES/BENEFITS. Factory-installed options (FIOPs)
38AUZ Air Cooled Condensing Unit Puronr (R---410A) Refrigerant 6to12.5NominalTons Product Data Carrier s air-cooled air conditioning split systems: S provide a logical solution for commercial needs S have
More information2. The requirements of Sections 502, 503, 504 and 505. In addition, commercial buildings shall comply with either Section 506.2, or
Public Comment 3: Dave Hewitt, representing New Buildings Institute, Jessyca Henderson, representing American Institute of Architects, Ron Majette, representing U.S. Department of Energy requests Approval
More informationCharacteristics of Energy Consumption by building type of a U.S. Navy Installation in Hot and Humid Climate
Purdue University Purdue e-pubs International High Performance Buildings Conference School of Mechanical Engineering 216 Characteristics of Energy Consumption by building type of a U.S. Navy Installation
More informationMODELING AND VALIDATION OF EXISTING VAV SYSTEM COMPONENTS
MODELING AND VALIDATION OF EXISTING VAV SYSTEM COMPONENTS Nabil Nassif Stanislaw Kajl Robert Sabourin École de technologie supérieure Montreal, Canada nnassif@mec.etsmtl.ca skajl@mec.etsmtl.ca Robert.Sabourin@etsmtl.ca
More information