INITIAL RUN-ON AND RUN-OFF CONTROLS PLAN NORTH VALMY GENERATING STATION (ASH LANDFILL) HUMBOLDT COUNTY, NEVADA OCTOBER 2016 PROJECT NO

Size: px
Start display at page:

Download "INITIAL RUN-ON AND RUN-OFF CONTROLS PLAN NORTH VALMY GENERATING STATION (ASH LANDFILL) HUMBOLDT COUNTY, NEVADA OCTOBER 2016 PROJECT NO"

Transcription

1 INITIAL RUN-ON AND RUN-OFF CONTROLS PLAN NORTH VALMY GENERATING STATION (ASH LANDFILL) HUMBOLDT COUNTY, NEVADA OCTOBER 2016 PROJECT NO R009 SUBMITTED TO: NV Energy, Inc W. Sahara Ave. M/S 30 Las Vegas, NV PREPARED BY: Geo-Logic Associates 56 Coney Island Drive Sparks, Nevada (775)

2

3 Initial Run-On and Run-Off Controls Plan North Valmy Generating Station (Ash Landfill) TABLE OF CONTENTS 1.0 INTRODUCTION RUN-ON RUN-OFF Method Rainfall Depth Landfill Surface Materials Drainage Areas Run-Off Flows and Volumes RUN-OFF CONTROLS Preexisting Run-Off Controls Perimeter Drainage Channel Detention Basin Additional Run-Off Controls SmartDitch Drainage Channels Culverts Arizona Crossings Toe Storage Basins Detention Basins CONSTRUCTION OF RUN-OFF CONTROLS General Periodic Observations As-Built Surveys ONGOING INSPECTIONS AND MAINTENANCE REFERENCES... 7 APPENDICES Appendix A Appendix B Figure 1 General Location Figure 2 Run-Off Controls Figure 3 Run-Off Control Details Attachment 1 Design Storm Data Attachment 2 Drainage Area Calculations Attachment 3 SmartDitch Sizing Attachment 4 Open Channel Sizing Attachment 5 Culvert Sizing Attachment 6 Basin Sizing 56 Coney Island Dr. Sparks, Nevada, T F

4 Initial Run-On and Run-Off Controls Plan North Valmy Generating Station (Ash Landfill) 1.0 INTRODUCTION Geo-Logic Associates, Inc. (GLA) has prepared this initial plan for run-on/run-off control systems (Initial Plan) for the existing coal ash landfill at NV Energy s North Valmy Generating Station, located in Humboldt County, Nevada. This Initial Plan has been prepared in accordance with the requirements of Federal Register, Vol. 80, No.74, Friday, April 17, 2015, Rule and Regulations, page 21480, Run-on and Run-off Controls for Coal Combustion Residuals (CCR) Landfills (the Rule). This Initial Plan presents how the run-on and run-off controls for the ash landfill were designed and constructed and includes relevant calculations and an as-built drawing showing the locations of installed run-off controls. Two categories of ash landfill run-off controls are presented based on when they were constructed. Preexisting run-off controls are controls that were in place prior to June Additional run-off controls were constructed in the July through September 2016 timeframe. Run-on is not an issue for the landfill as the surrounding topography slopes away from the landfill, so run-on controls are not necessary at this time. This Initial Plan includes the locations and sizing of ditches, channels, culverts, and basins required to collect and store landfill run-off from the 25 year, 24 hour storm event. The run-off controls are designed for the existing conditions of the ash landfill. Should future conditions change significantly this plan will require an update. As-built drawings and calculations are included in Appendices A and B, respectively. 2.0 RUN-ON Based on a review of surrounding topography and as reported in ASW 2013, run-on is not an issue for the Valmy coal ash landfill as the surrounding topography slopes away from the landfill. As such, recommendations regarding run-on controls are not necessary at this time. Should the surrounding topography be altered in the future, care should be taken to review proposed grading and implement controls should they be necessary. 3.0 RUN-OFF 3.1 Method AutoCAD Hydroflow Hydrograph extension was used to develop a Soil Conservation Service (SCS) hydrograph for each drainage area described in Section 3.4 below. The SCS hydrographs, in addition to the SCS curve number (CN), time of concentration (t c ) by the SCS Technical Release 55 (TR-55) method, and drainage area, described in the sections below, were used to determine the peak discharge from the 24-hour 25 year storm event. In calculating the surface hydrology, it is conservatively assumed that all run-off from the ash landfill is ultimately conveyed to designed drainage channels. It is also assumed that the design storm event will have a duration that exceeds the time of concentration of overland flow. Project No R009 Initial Run-On and Run-Off Controls Plan, North Valmy Generating Station (Ash Landfill) 1 October 2016

5 Initial Run-On and Run-Off Controls Plan North Valmy Generating Station (Ash Landfill) 3.2 Rainfall Depth The design rainfall depth was determined using the National Oceanic and Atmospheric Administration (NOAA) Atlas 14, Volume 1, Version 5, which is used as a basis for determining the run-off potential from the ash landfill and overall storage basin sizing. Appendix B, Attachment 1 includes the design storm data. 3.3 Landfill Surface Materials TABLE 1 - DESIGN STORM RAINFALL DEPTH STORM EVENT RAINFALL DEPTH (IN) 25 year, 24 hour 1.62 Landfill surface materials include coal ash materials as well as silty-gravelly-sand cover materials placed by the landfill operator. A conservative CN of 85 was utilized for all of the landfill surface materials. 3.4 Drainage Areas The ash landfill was divided into 15 drainage areas (DA) based on general flow direction and ultimate location of discharge. AutoCAD Civil 3D was used to create each drainage area. Appendix A, Figure 2 depicts the DAs. 3.5 Run-Off Flows and Volumes The calculated flows for the 25 year, 24-hour storm event for each DA are summarized in Table 2, below. Supporting calculations are provided in Appendix B, Attachment 2. TABLE 2 RUN-OFF FLOWS AND VOLUMES, 25 year, 24 hour DRAINAGE AREA RUN-OFF FLOW, cfs RUN-OFF VOLUME, ft 3 1A ,217 1B 5.4 9, ,559 3A ,172 3B , , , , , , , , , , ,439 Project No R009 Initial Run-On and Run-Off Controls Plan, North Valmy Generating Station (Ash Landfill) 2 October 2016

6 Initial Run-On and Run-Off Controls Plan North Valmy Generating Station (Ash Landfill) 4.0 RUN-OFF CONTROLS Two categories of ash landfill run-off controls are presented below based on when they were constructed. Preexisting run-off controls are controls that were in place prior to June Additional run-off controls are controls that were constructed in the July through September 2016 timeframe. The preexisting run-off controls were originally designed to accommodate the peak flow from the entire top deck of the landfill during the 25 year, 24 hour storm event. The additional run-off controls were designed to accommodate various areas of the landfill. As such, the preexisting run-off controls are larger than required to accommodate their current duty. Appendix A, Figure 2 shows the locations of run-off controls. Appendix A, Figure 3 includes run-off control details. 4.1 Preexisting Run-Off Controls Perimeter Drainage Channel A perimeter drainage channel is located along the south and west sides of the ash landfill. The drainage channel consists of a trapezoidal earthen channel. Sizing of the drainage channel was performed using Manning s equation and it was designed to accommodate the run-off flow rate from the entire top deck of the landfill. A Manning s n of 0.03 was used for the earthen channels and each channel was designed to a specific depth with 3H:1V sideslopes. The perimeter channel includes a 30 inch diameter corrugated steel culvert pipe where it crosses the main haul road. Sizing of the culvert was performed using the culvert design module in AutoCAD Hydraflow Express Extension. Figure 2 shows the location of the preexisting perimeter drainage channel and culvert. The detailed calculation and report sheet for drainage channel sizing are included in Appendix B, Attachment 4. The detailed calculation and report sheet for culvert sizing is included in Appendix B, Attachment Detention Basin 1 Detention Basin 1 is located to the northwest of the northwest corner of the landfill. The detention basin was designed and constructed to store landfill runoff received from the perimeter drainage channel. The Detention Basin 1 is roughly rectangular-shaped with an approximate length and width of 330 feet and 270 feet. The detention basin has a total depth of 6 feet (including 2 feet of freeboard) with interior side slopes of 3H : 1V (horizontal : vertical). AutoCad Hydraflow Hydrographs Extension was used to develop the runoff hydrograph and determine the stormwater volume used for detention basin sizing. Figure 2 shows the location of Detention Basin 1. The detailed calculation and report sheet for detention basin sizing is included in Appendix B, Attachment 6. Project No R009 Initial Run-On and Run-Off Controls Plan, North Valmy Generating Station (Ash Landfill) 3 October 2016

7 Initial Run-On and Run-Off Controls Plan North Valmy Generating Station (Ash Landfill) 4.2 Additional Run-Off Controls SmartDitch SmartDitch is a high density polyethylene (HDPE) channel lining system used to control and direct run-off from the top deck of the landfill to channels or detention basins at the toe of the landfill, along the landfill side slopes. SmartDitch sections consist of the 12 inch depth (nominal) trapezoidal product. Sizing of the SmartDitch was performed using Manning s equation and AutoCAD Hydraflow Express Extension. Inputs include the flow from the corresponding Drainage Area and the dimensions provided by the SmartDitch manufacturer. Manning s roughness coefficient (n) for the Smartditch product is provided as SmartDitch was designed and installed at four locations of the landfill, to accommodate flow from DA-2, DA-4, DA-5, and DA-7. Figure 2 shows SmartDitch locations. The detailed calculations and manufacturer product data sheets for SmartDitch sizing are included in Appendix B, Attachment Drainage Channels Various drainage channels were designed and constructed to collect run-off from the landfill and direct it to detention basins. In some cases, existing channels were utilized. The drainage channels consist of a v-shaped earthen channel. Sizing of the drainage channels was performed using Manning s equation and were designed to accommodate the run-off flow rate from the associated Drainage Area. A Manning s n of 0.03 was used for the earthen channels and each channel was designed to a specific depth with 3H:1V sideslopes. Drainage channels were designed and constructed around the entire landfill; except where toe storage containment was designed and constructed, discussed below, and at the southeast corner where a large cover material stockpile exists, which prevents runoff from flowing off the landfill. Figure 2 shows drainage channel locations. The detailed calculations and report sheets for drainage channel sizing are included in Appendix B, Attachment Culverts Culverts were designed and installed at three locations along the drainage channels to facilitate vehicular crossings. Culverts consist of 16 gage, corrugated steel culvert pipes of 18 inch or 24 inch diameter. Sizing of the culverts was performed using the culvert design module in AutoCAD Hydraflow Express Extension. This program takes into consideration the headwater depth (H w ), tail water depth (t w ), elevation and width of embankment, length of culvert, culvert material, and type of inlet structure. Culverts were designed and installed at three locations of the landfill, including, DA-1A, DA-12, and DA-10. Figure 2 shows culvert locations. Project No R009 Initial Run-On and Run-Off Controls Plan, North Valmy Generating Station (Ash Landfill) 4 October 2016

8 Initial Run-On and Run-Off Controls Plan North Valmy Generating Station (Ash Landfill) The detailed calculations and report sheets for culvert sizing are included in Appendix B, Attachment Arizona Crossings Arizona-style low-water crossings were designed and constructed at three locations to facilitate haul truck crossings. Arizona crossings generally consist of a depressed channel, constructed across a road, with shallow slopes on each side to facilitate vehicular traffic. Arizona crossings were designed as shallow wide channels using Manning s equation to determine depth based on a specified flow rate. Arizona crossings were designed and installed at two locations of the landfill, in DA-10. Figure 2 shows Arizona crossing locations. The detailed calculations and report sheets for Arizona crossing sizing are included in Appendix B, Attachment Toe Storage Basins Toe storage basins were designed and constructed at the toe of the perimeter landfill slopes to collect and store run-off from landfill slopes. Toe storage basins were constructed in locations where existing topography did not permit the use of an open channel to direct run-off to a detention basin. Toe storage basins generally consist of 1.) a trapezoidal channel constructed parallel to the slope of the landfill with a bottom width of approximately 10 feet that is sloped downward away from the landfill and a 1.5 feet tall berm at the downslope end; or, 2.) a 2.5 feet deep V-shaped channel with 3H : 1V side slopes. AutoCad Hydraflow Hydrographs Extension was used to develop the runoff hydrograph and determine the stormwater volumes used for road/storage basin sizing. Toe storage basins were designed and constructed at 2 locations of the landfill, including, DA- 1B and DA-6. Figure 2 shows road/storage basin locations. The detailed calculations and report sheets for road/storage basin sizing are included in Appendix B, Attachment Detention Basins Additional detention basins (Detention Basin 2 through Detention Basin 5) were designed and constructed at various locations around the landfill to store landfill runoff. Detention Basins receive run-off from the open channels. Detention basins are roughly rectangular-shaped except for Detention Basin 5, with varying lengths and widths and range from 3 feet to 4 feet in effective depth, with interior side slopes of 3H : 1V (horizontal : vertical). AutoCad Hydraflow Hydrographs Extension was used to develop the runoff hydrograph and determine the stormwater volumes used for detention basin sizing. Project No R009 Initial Run-On and Run-Off Controls Plan, North Valmy Generating Station (Ash Landfill) 5 October 2016

9 Initial Run-On and Run-Off Controls Plan North Valmy Generating Station (Ash Landfill) Additional detention basins were designed and constructed at 4 locations around the landfill. Figure 2 shows the locations of Detention Basin 2 through Detention Basin 5. The detailed calculations and report sheets for detention basin sizing are included in Appendix B, Attachment CONSTRUCTION OF RUN-OFF CONTROLS 5.1 General Construction of the preexisting run-off controls took place in Construction of the additional run-off controls was performed during the July through September 2016 timeframe. Construction of the additional run-off controls also included minor regrading of the top deck of the landfill at areas needing improvements to reduce the potential for ponding and promote drainage toward the run-off controls. 5.2 Periodic Observations Periodic observations were performed by GLA during construction. Periodic observations consisted of visually inspecting the run-off controls and taking measurements to check for recommended dimensions. Locations where measurements did not meet recommended dimensions were communicated to the contractor and improved. GLA performed follow-up observations after the locations were improved. 5.3 As-Built Surveys As-built surveys were performed by aerial survey as well as ground survey. The aerial survey was performed on September 5, 2016 and was used for the general as-built base map. The ground survey was performed on September 7, 2016 and focused on the run-off controls; SmartDitch, drainage channels, culverts, Arizona crossings, road/storage basins, and detention basins. 6.0 ONGOING INSPECTIONS AND MAINTENANCE Ongoing inspections and maintenance is a critical component of ensuring adequate function of run-off controls. It is recommended that routine inspections be performed of all run-off controls as part of the current 7 day inspections for the landfill. Inspections should consist of visually inspecting the existing run-off controls and looking for deficiencies, which may include: obstructions, berm failures, ponded water, etc. Measurements should be taken periodically to check for recommended dimensions. The landfill, including the top deck, should be inspected for areas of ponded water or areas with the potential to pond water. This is especially important because the landfill is currently active and the general topography of the top deck will change with ash disposal. Areas of obvious blocked drainage, depressions, or ponding should be remediated by removing the drainage obstruction, filling in the low spot, or constructing ditches that allow water to drain toward the run-off controls. All remediation should be documented on the 7 day inspection forms. Project No R009 Initial Run-On and Run-Off Controls Plan, North Valmy Generating Station (Ash Landfill) 6 October 2016

10 Initial Run-On and Run-Off Controls Plan North Valmy Generating Station (Ash Landfill) 7.0 REFERENCES Hydraflow Hydrographs Extension for AutoCAD Civil3D 2015 by Autodesk, Inc. v10.4 Hydraflow Express Extension for Autodesk AutoCAD Civil3D by Autodesk, Inc. PendaForm, November 2013, SmartDitch Technical Manual and Installation Guidelines. Applied Soil Water Technologies, LLC, August 2013, Engineering Design Report, Permit SW174R02 Modification, North Valmy Power Plant, Humboldt County, Nevada, prepared for NV Energy (ASW 2013). Project No R009 Initial Run-On and Run-Off Controls Plan, North Valmy Generating Station (Ash Landfill) 7 October 2016

11 APPENDIX A

12 NORTH VALMY GENERATING STATION PYRAMID LAKE WADS- WORTH FERNLEY LAKE TAHOE WALKER LAKE NV ENERGY NORTH VALMY GENERATING STATION HUMBOLDT COUNTY, NV FIGURE 1 GENERAL LOCATION MAP INITIAL RUN-ON AND RUN-OFF CONTROLS PLAN JOB NO R009 OCTOBER Coney Island Drive, Sparks, NV Ph: Fax:

13 Feet

14

15 APPENDIX B ATTACHMENT 1

16 NOAA Atlas 14, Volume 1, Version 5 Location name: Golconda, Nevada, USA* Latitude: , Longitude: Elevation: ft** * source: ESRI Maps ** source: USGS POINT PRECIPITATION FREQUENCY ESTIMATES Sanja Perica, Sarah Dietz, Sarah Heim, Lillian Hiner, Kazungu Maitaria, Deborah Martin, Sandra Pavlovic, Ishani Roy, Carl Trypaluk, Dale Unruh, Fenglin Yan, Michael Yekta, Tan Zhao, Geoffrey Bonnin, Daniel Brewer, Li-Chuan Chen, Tye Parzybok, John Yarchoan NOAA, National Weather Service, Silver Spring, Maryland PF_tabular PF_graphical Maps_&_aerials Duration 5-min 10-min 15-min 30-min 60-min 2-hr 3-hr 6-hr 12-hr 24-hr 2-day 3-day 4-day 7-day 10-day 20-day 30-day 45-day 60-day PF tabular PDS-based point precipitation frequency estimates with 90% confidence intervals (in inches) 1 Average recurrence interval (years) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) 1.13 ( ) 1.23 ( ) 1.53 ( ) 1.76 ( ) 2.10 ( ) 2.40 ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) 1.06 ( ) 1.14 ( ) 1.22 ( ) 1.41 ( ) 1.53 ( ) 1.91 ( ) 2.19 ( ) 2.61 ( ) 2.98 ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) 1.17 ( ) 1.32 ( ) 1.41 ( ) 1.50 ( ) 1.72 ( ) 1.88 ( ) 2.36 ( ) 2.70 ( ) 3.21 ( ) 3.66 ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) 1.18 ( ) 1.36 ( ) 1.52 ( ) 1.62 ( ) 1.71 ( ) 1.96 ( ) 2.15 ( ) 2.70 ( ) 3.08 ( ) 3.64 ( ) 4.17 ( ) ( ) ( ) ( ) ( ) ( ) ( ) ( ) 1.17 ( ) 1.42 ( ) 1.62 ( ) 1.79 ( ) 1.89 ( ) 2.00 ( ) 2.27 ( ) 2.49 ( ) 3.13 ( ) 3.57 ( ) 4.18 ( ) 4.82 ( ) ( ) ( ) ( ) ( ) ( ) 1.04 ( ) 1.10 ( ) 1.35 ( ) 1.62 ( ) 1.83 ( ) 1.99 ( ) 2.10 ( ) 2.21 ( ) 2.50 ( ) 2.75 ( ) 3.45 ( ) 3.92 ( ) 4.57 ( ) 5.28 ( ) ( ) ( ) ( ) ( ) 1.14 ( ) 1.24 ( ) 1.29 ( ) 1.55 ( ) 1.83 ( ) 2.05 ( ) 2.20 ( ) 2.31 ( ) 2.43 ( ) 2.72 ( ) 3.00 ( ) 3.76 ( ) 4.27 ( ) 4.92 ( ) 5.71 ( ) ( ) ( ) ( ) 1.11 ( ) 1.37 ( ) 1.46 ( ) 1.50 ( ) 1.76 ( ) 2.05 ( ) 2.27 ( ) 2.41 ( ) 2.53 ( ) 2.64 ( ) 2.93 ( ) 3.24 ( ) 4.06 ( ) 4.60 ( ) 5.24 ( ) 6.12 ( ) ( ) ( ) 1.04 ( ) 1.40 ( ) 1.73 ( ) 1.81 ( ) 1.83 ( ) 2.08 ( ) 2.36 ( ) 2.57 ( ) 2.68 ( ) 2.80 ( ) 2.92 ( ) 3.20 ( ) 3.54 ( ) 4.43 ( ) 5.01 ( ) 5.61 ( ) 6.60 ( ) ( ) ( ) 1.23 ( ) 1.66 ( ) 2.06 ( ) 2.12 ( ) 2.13 ( ) 2.36 ( ) 2.61 ( ) 2.81 ( ) 2.89 ( ) 3.01 ( ) 3.13 ( ) 3.39 ( ) 3.75 ( ) 4.68 ( ) 5.31 ( ) 5.83 ( ) 6.90 ( ) 1 Precipitation frequency (PF) estimates in this table are based on frequency analysis of partial duration series (PDS). Numbers in parenthesis are PF estimates at lower and upper bounds of the 90% confidence interval. The probability that precipitation frequency estimates (for a given duration and average recurrence interval) will be greater than the upper bound (or less than the lower bound) is 5%. Estimates at upper bounds are not checked against probable maximum precipitation (PMP) estimates and may be higher than currently valid PMP values. Please refer to NOAA Atlas 14 document for more information. Back to Top

17 APPENDIX B ATTACHMENT 2

18

19 Hydraflow Table of Contents Final AS-Built Hydro_ gpw Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / Year Summary Report... 1 Hydrograph Reports... 2 Hydrograph No. 1, SCS Runoff, DA Hydrograph No. 2, SCS Runoff, DA 1B... 3 Hydrograph No. 3, SCS Runoff, DA Hydrograph No. 4, SCS Runoff, DA Hydrograph No. 5, SCS Runoff, DA Hydrograph No. 6, SCS Runoff, DA Hydrograph No. 7, SCS Runoff, DA Hydrograph No. 8, SCS Runoff, DA Hydrograph No. 9, SCS Runoff, DA Hydrograph No. 10, SCS Runoff, DA Hydrograph No. 11, SCS Runoff, DA Hydrograph No. 12, SCS Runoff, DA Hydrograph No. 13, SCS Runoff, DA Hydrograph No. 14, SCS Runoff, DA 1A... 15

20 Hydrograph Summary Report Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 1 SCS Runoff , DA 13 2 SCS Runoff , DA 1B 3 SCS Runoff , DA 10 4 SCS Runoff , DA 12 5 SCS Runoff , DA 4 6 SCS Runoff , DA 11 7 SCS Runoff , DA 9 8 SCS Runoff , DA 8 9 SCS Runoff , DA 7 10 SCS Runoff , DA 6 11 SCS Runoff , DA 5 12 SCS Runoff , DA 2 13 SCS Runoff , DA 3 14 SCS Runoff , DA 1A Final AS-Built Hydro_ gpw Return Period: 25 Year Wednesday, 10 / 5 / 2016

21 Hydrograph Report 2 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 1 DA 13 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 719 min Time interval = 1 min Hyd. volume = 52,439 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 7.10 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 13 Hyd. No Year Q (cfs) Time (min) Hyd No. 1

22 Hydrograph Report 3 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 2 DA 1B Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 716 min Time interval = 1 min Hyd. volume = 9,425 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 2.90 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 1B Hyd. No Year Q (cfs) Time (min) Hyd No. 2

23 Hydrograph Report 4 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 3 DA 10 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 718 min Time interval = 1 min Hyd. volume = 100,423 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 6.40 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 10 Hyd. No Year Q (cfs) Time (min) Hyd No. 3

24 Hydrograph Report 5 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 4 DA 12 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 718 min Time interval = 1 min Hyd. volume = 5,253 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 6.10 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 12 Hyd. No Year Q (cfs) Time (min) Hyd No. 4

25 Hydrograph Report 6 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 5 DA 4 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 720 min Time interval = 1 min Hyd. volume = 23,259 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 8.40 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 4 Hyd. No Year Q (cfs) Time (min) Hyd No. 5

26 Hydrograph Report 7 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 6 DA 11 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 718 min Time interval = 1 min Hyd. volume = 32,074 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 5.90 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 11 Hyd. No Year Q (cfs) Time (min) Hyd No. 6

27 Hydrograph Report 8 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 7 DA 9 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 716 min Time interval = 1 min Hyd. volume = 7,731 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 2.50 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 9 Hyd. No Year Q (cfs) Time (min) Hyd No. 7

28 Hydrograph Report 9 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 8 DA 8 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 716 min Time interval = 1 min Hyd. volume = 2,703 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 2.00 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 8 Hyd. No Year Q (cfs) Time (min) Hyd No. 8

29 Hydrograph Report 10 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 9 DA 7 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 717 min Time interval = 1 min Hyd. volume = 8,592 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 4.60 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 7 Hyd. No Year Q (cfs) Time (min) Hyd No. 9

30 Hydrograph Report 11 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 10 DA 6 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 716 min Time interval = 1 min Hyd. volume = 4,812 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 2.00 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 6 Hyd. No Year Q (cfs) Time (min) Hyd No. 10

31 Hydrograph Report 12 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 11 DA 5 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 716 min Time interval = 1 min Hyd. volume = 9,389 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 2.90 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 5 Hyd. No Year Q (cfs) Time (min) Hyd No. 11

32 Hydrograph Report 13 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 12 DA 2 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 716 min Time interval = 1 min Hyd. volume = 4,559 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = TR55 Time of conc. (Tc) = 1.90 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 2 Hyd. No Year Q (cfs) Time (min) Hyd No. 12

33 Hydrograph Report 14 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 13 DA 3 Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 593 min Time interval = 1 min Hyd. volume = 4,199 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 2.00 min Total precip. = 1.62 in Distribution = Type I Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 3 Hyd. No Year Q (cfs) Time (min) Hyd No. 13

34 Hydrograph Report 15 Hydraflow Hydrographs Extension for AutoCAD Civil 3D 2015 by Autodesk, Inc. v10.4 Wednesday, 10 / 5 / 2016 Hyd. No. 14 DA 1A Hydrograph type = SCS Runoff Peak discharge = cfs Storm frequency = 25 yrs Time to peak = 716 min Time interval = 1 min Hyd. volume = 2,217 cuft Drainage area = ac Curve number = 85 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 2.00 min Total precip. = 1.62 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) DA 1A Hyd. No Year Q (cfs) Time (min) Hyd No. 14

35 APPENDIX B ATTACHMENT 3

36 Channel Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct Smart Ditch 12 Inch Triangular Side Slopes (z:1) = 2.00, 2.00 Total Depth (ft) = 1.20 Invert Elev (ft) = Slope (%) = N-Value = Calculations Compute by: Q vs Depth No. Increments = 10 Highlighted Depth (ft) = 1.20 Q (cfs) = Area (sqft) = 2.88 Velocity (ft/s) = Wetted Perim (ft) = 5.37 Crit Depth, Yc (ft) = 1.20 Top Width (ft) = 4.80 EGL (ft) = Elev (ft) Depth (ft) Section Reach (ft)

37 Product Data & Dimensions PRODUCT DATA The SmartDitch system is a corrugated section of HDPE sheet formed in a predetermined shape. In the thermoforming process, the plastic sheet is heated to forming temperatures, allowing it to conform to the mold. The minimum formed thickness in all of the channels is 55 mil. The versatility of this manufacturing process provides Penda with unmatched in-house sheet and thermoforming capabilities that enable us to deliver greater production efficiency on a full range of designs. Penda supports your operation at every level, right from the start. Our world-class design/engineering capabilities allow us to partner with you to meet virtually any project need. PRODUCT ATTRIBUTES, DIMENSIONS & WEIGHTS SmartDitch offers water management channels in the following specific depth/sizes: Trapezoidal design 12" depth series 24" depth series Semi-circular design (Above Ground) 24" depth series Note: The semi-circular design is for above ground installations only by use of saddles. E C E C ITEM DESCRIPTION ITEM # 12" DEPTH TRAPEZOIDAL 24" DEPTH TRAPEZOIDAL 24" DEPTH SEMI-CIRCULAR Overall exterior width A in / mm in / 2032 mm in / mm Overall exterior height B in / mm in / 762 mm in / mm Bottom channel exterior width C in / mm in / 387 mm N/A (Rounded Bottom) Overall exterior length D in / mm in / 2463 mm in / mm Lay length E in / mm in / 2356 mm in / mm For More Information: / Hotline: Penda Corp. 02/13

38 APPENDIX B ATTACHMENT 4

39 Channel Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct Pre-Existing Channel 2' Trapezoidal Bottom Width (ft) = 1.00 Side Slopes (z:1) = 3.00, 3.00 Total Depth (ft) = 2.00 Invert Elev (ft) = Slope (%) = 1.00 N-Value = Calculations Compute by: Q vs Depth No. Increments = 10 Highlighted Depth (ft) = 2.00 Q (cfs) = Area (sqft) = Velocity (ft/s) = 5.04 Wetted Perim (ft) = Crit Depth, Yc (ft) = 1.88 Top Width (ft) = EGL (ft) = 2.39 Elev (ft) Depth (ft) Section Reach (ft)

40 Channel Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct Pre-Existing Channel 2.5' Trapezoidal Bottom Width (ft) = 1.00 Side Slopes (z:1) = 3.00, 3.00 Total Depth (ft) = 2.50 Invert Elev (ft) = Slope (%) = 1.00 N-Value = Calculations Compute by: Q vs Depth No. Increments = 10 Highlighted Depth (ft) = 2.50 Q (cfs) = Area (sqft) = Velocity (ft/s) = 5.79 Wetted Perim (ft) = Crit Depth, Yc (ft) = 2.38 Top Width (ft) = EGL (ft) = 3.02 Elev (ft) Depth (ft) Section Reach (ft)

41 Channel Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct Pre-Existing Channel 3.5' Trapezoidal Bottom Width (ft) = 1.00 Side Slopes (z:1) = 3.00, 3.00 Total Depth (ft) = 3.50 Invert Elev (ft) = Slope (%) = 1.00 N-Value = Calculations Compute by: Q vs Depth No. Increments = 10 Highlighted Depth (ft) = 3.50 Q (cfs) = Area (sqft) = Velocity (ft/s) = 7.17 Wetted Perim (ft) = Crit Depth, Yc (ft) = 3.41 Top Width (ft) = EGL (ft) = 4.30 Elev (ft) Depth (ft) Section Reach (ft)

42 Channel Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct ' Channel Triangular Side Slopes (z:1) = 3.00, 3.00 Total Depth (ft) = 1.50 Invert Elev (ft) = Slope (%) = 0.30 N-Value = Calculations Compute by: Q vs Depth No. Increments = 10 Highlighted Depth (ft) = 1.50 Q (cfs) = Area (sqft) = 6.75 Velocity (ft/s) = 2.16 Wetted Perim (ft) = 9.49 Crit Depth, Yc (ft) = 1.09 Top Width (ft) = 9.00 EGL (ft) = 1.57 Elev (ft) Depth (ft) Section Reach (ft)

43 Channel Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct ' Channel Triangular Side Slopes (z:1) = 3.00, 3.00 Total Depth (ft) = 2.00 Invert Elev (ft) = Slope (%) = 0.30 N-Value = Calculations Compute by: Q vs Depth No. Increments = 10 Highlighted Depth (ft) = 2.00 Q (cfs) = Area (sqft) = Velocity (ft/s) = 2.62 Wetted Perim (ft) = Crit Depth, Yc (ft) = 1.47 Top Width (ft) = EGL (ft) = 2.11 Elev (ft) Depth (ft) Section Reach (ft)

44 Channel Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct ' Channel Triangular Side Slopes (z:1) = 3.00, 3.00 Total Depth (ft) = 2.50 Invert Elev (ft) = Slope (%) = 0.30 N-Value = Calculations Compute by: Q vs Depth No. Increments = 10 Highlighted Depth (ft) = 2.50 Q (cfs) = Area (sqft) = Velocity (ft/s) = 3.04 Wetted Perim (ft) = Crit Depth, Yc (ft) = 1.87 Top Width (ft) = EGL (ft) = 2.64 Elev (ft) Depth (ft) Section Reach (ft)

45 Channel Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct AZ Crossing 1 Triangular Side Slopes (z:1) = 25.00, Total Depth (ft) = 1.62 Invert Elev (ft) = Slope (%) = 3.13 N-Value = Calculations Compute by: Known Q Known Q (cfs) = Highlighted Depth (ft) = 0.67 Q (cfs) = Area (sqft) = Velocity (ft/s) = 4.17 Wetted Perim (ft) = Crit Depth, Yc (ft) = 0.74 Top Width (ft) = EGL (ft) = 0.94 Elev (ft) Depth (ft) Section Reach (ft)

46 Channel Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct AZ Crossing 2 Triangular Side Slopes (z:1) = 6.00, 9.00 Total Depth (ft) = 2.00 Invert Elev (ft) = Slope (%) = 3.28 N-Value = Calculations Compute by: Known Q Known Q (cfs) = Highlighted Depth (ft) = 0.99 Q (cfs) = Area (sqft) = 7.35 Velocity (ft/s) = 5.44 Wetted Perim (ft) = Crit Depth, Yc (ft) = 1.13 Top Width (ft) = EGL (ft) = 1.45 Elev (ft) Depth (ft) Section Reach (ft)

47 APPENDIX B ATTACHMENT 5

48 Culvert Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct inch CMP Culvert Invert Elev Dn (ft) = Pipe Length (ft) = Slope (%) = 1.83 Invert Elev Up (ft) = Rise (in) = 30.0 Shape = Circular Span (in) = 30.0 No. Barrels = 1 n-value = Culvert Type = Circular Corrugate Metal Pipe Culvert Entrance = Projecting Coeff. K,M,c,Y,k = 0.034, 1.5, , 0.54, 0.9 Embankment Top Elevation (ft) = Top Width (ft) = Crest Width (ft) = Calculations Qmin (cfs) = Qmax (cfs) = Tailwater Elev (ft) = (dc+d)/2 Highlighted Qtotal (cfs) = Qpipe (cfs) = Qovertop (cfs) = 0.00 Veloc Dn (ft/s) = 3.91 Veloc Up (ft/s) = 5.90 HGL Dn (ft) = HGL Up (ft) = Hw Elev (ft) = Hw/D (ft) = 0.84 Flow Regime = Inlet Control

49 Culvert Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct DA 1A 24inch CMP Invert Elev Dn (ft) = Pipe Length (ft) = Slope (%) = 5.43 Invert Elev Up (ft) = Rise (in) = 24.0 Shape = Circular Span (in) = 24.0 No. Barrels = 1 n-value = Culvert Type = Circular Corrugate Metal Pipe Culvert Entrance = Projecting Coeff. K,M,c,Y,k = 0.034, 1.5, , 0.54, 0.9 Embankment Top Elevation (ft) = Top Width (ft) = 8.00 Crest Width (ft) = Calculations Qmin (cfs) = 1.27 Qmax (cfs) = 1.27 Tailwater Elev (ft) = (dc+d)/2 Highlighted Qtotal (cfs) = 1.27 Qpipe (cfs) = 1.27 Qovertop (cfs) = 0.00 Veloc Dn (ft/s) = 0.65 Veloc Up (ft/s) = 2.96 HGL Dn (ft) = HGL Up (ft) = Hw Elev (ft) = Hw/D (ft) = 0.32 Flow Regime = Outlet Control

50 Culvert Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct DA 10 24inch CMP Invert Elev Dn (ft) = Pipe Length (ft) = Slope (%) = 1.54 Invert Elev Up (ft) = Rise (in) = 24.0 Shape = Circular Span (in) = 24.0 No. Barrels = 1 n-value = Culvert Type = Circular Corrugate Metal Pipe Culvert Entrance = Projecting Coeff. K,M,c,Y,k = 0.034, 1.5, , 0.54, 0.9 Embankment Top Elevation (ft) = Top Width (ft) = 8.00 Crest Width (ft) = Calculations Qmin (cfs) = 9.61 Qmax (cfs) = 9.61 Tailwater Elev (ft) = (dc+d)/2 Highlighted Qtotal (cfs) = 9.61 Qpipe (cfs) = 9.61 Qovertop (cfs) = 0.00 Veloc Dn (ft/s) = 3.67 Veloc Up (ft/s) = 5.38 HGL Dn (ft) = HGL Up (ft) = Hw Elev (ft) = Hw/D (ft) = 0.88 Flow Regime = Inlet Control

51 Culvert Report Hydraflow Express Extension for Autodesk AutoCAD Civil 3D by Autodesk, Inc. Wednesday, Oct DA 12 18inch CMP Invert Elev Dn (ft) = Pipe Length (ft) = Slope (%) = 3.83 Invert Elev Up (ft) = Rise (in) = 18.0 Shape = Circular Span (in) = 18.0 No. Barrels = 1 n-value = Culvert Type = Circular Corrugate Metal Pipe Culvert Entrance = Projecting Coeff. K,M,c,Y,k = 0.034, 1.5, , 0.54, 0.9 Embankment Top Elevation (ft) = Top Width (ft) = 6.00 Crest Width (ft) = Calculations Qmin (cfs) = 2.60 Qmax (cfs) = 2.60 Tailwater Elev (ft) = (dc+d)/2 Highlighted Qtotal (cfs) = 2.60 Qpipe (cfs) = 2.60 Qovertop (cfs) = 0.00 Veloc Dn (ft/s) = 1.96 Veloc Up (ft/s) = 3.85 HGL Dn (ft) = HGL Up (ft) = Hw Elev (ft) = Hw/D (ft) = 0.59 Flow Regime = Inlet Control

52 APPENDIX B ATTACHMENT 6

53 SUMMARY OF RUN-OFF AND STORAGE CAPACITY Run-Off (cubic feet) Basin 1 DA-1A DA-4 DA-13 DA-12 DA-10 DA-11 Total 2,217 23,259 52, ,423 5,253 32, ,665 cubic feet Basin Storage Capacity: 336,940 cubic feet Run-Off (cubic feet) Basin 2 DA-2 DA-3A Total 4,559 3,172 7,731 cubic feet Basin Storage Capacity: 26,567 cubic feet Run-Off (cubic feet) Basin 3 DA-5 DA-3B Total 9,389 1,027 10,416 cubic feet Basin Storage Capacity: 22,437 cubic feet Run-Off (cubic feet) Basin 4 DA-8 DA-7 Total 2,703 8,592 11,295 cubic feet Basin Storage Capacity: 17,375 cubic feet Run-Off (cubic feet) Basin 5 DA-9 Total 7,731 7,731 cubic feet Basin Storage Capacity: 13,717 cubic feet Run-Off (cubic feet) East Toe Storage DA-6 Total 4,812 4,812 cubic feet Basin Storage Capacity: 16,537 cubic feet Run-Off (cubic feet) North Toe Storage DA-1B Total 9,425 9,425 cubic feet Basin Storage Capacity: 11,905 cubic feet

54 Toe Storage Calculation Calc By: RTS 10/10/2016 Trapezoidal Channel- East Cross Sectional Area 15.8 square feet Channel Legnth 617 feet Total Storage Capacity 9,749 cubic feet 2.5' Triangular Basin-East Cross Sectional Area 19 square feet Channel Legnth 362 feet Total Storage Capacity 6,788 cubic feet Sum of East Toe Drain Storage 16,537 Trapezoidal Channel- North Cross Sectional Area 15.8 square feet Channel Legnth 754 feet Total Storage Capacity 11,905 cubic feet

55 file:///c:/users/rspreeman/appdata/local/temp/cutfillreport.xml Page 1 of 1 10/10/2016 Generated: :52:07 By user: Drawing: rspreeman Cut/Fill Report K:\000_GLA_new jobs\2016\2016.r021 NVE - Valmy Ash LF-Run-Off Controls Work Packages\New Hydro\K:\000_GLA_new jobs\2016\2016.r021 NVE - Valmy Ash LF-Run-Off Controls Work Packages\New Hydro\Basin 1 Volume.dwg Volume Summary Name Type Cut Factor Fill Factor 2d Area (Sq. Ft.) Cut (Cu. Yd.) Fill (Cu. Yd.) Net (Cu. Yd.) Basin 1 Volume full <Fill> Totals 2d Area (Sq. Ft.) Cut (Cu. Yd.) Fill (Cu. Yd.) Net (Cu. Yd.) Total <Fill> * Value adjusted by cut or fill factor other than 1.0

56 file:///c:/users/aristinen/appdata/local/temp/cutfillreport.xml Page 1 of 1 10/5/2016 Generated: :57:31 By user: Drawing: aristinen Cut/Fill Report K:\000_GLA_new jobs\2016\2016.r021 NVE - Valmy Ash LF-Run-Off Controls Work Packages\WP-6\K:\000_GLA_new jobs\2016\2016.r021 NVE - Valmy Ash LF-Run-Off Controls Work Packages\WP-6\Pond Volumes_ dwg Volume Summary Name Type Cut Factor Fill Factor 2d Area (Sq. Ft.) Cut (Cu. Yd.) Fill (Cu. Yd.) Net (Cu. Yd.) Basin 2 Basin 3 Basin 4 full <Fill> full <Fill> full <Fill> Totals 2d Area (Sq. Ft.) Cut (Cu. Yd.) Fill (Cu. Yd.) Net (Cu. Yd.) Total <Fill> * Value adjusted by cut or fill factor other than 1.0

57 file:///c:/users/rspreeman/appdata/local/temp/cutfillreport.xml Page 1 of 1 10/5/2016 Generated: :24:54 By user: Drawing: rspreeman Cut/Fill Report K:\000_GLA_new jobs\2016\2016.r021 NVE - Valmy Ash LF-Run-Off Controls Work Packages\New Hydro\K:\000_GLA_new jobs\2016\2016.r021 NVE - Valmy Ash LF-Run-Off Controls Work Packages\New Hydro\Basin 6 Volume.dwg Volume Summary Name Type Cut Factor Fill Factor 2d Area (Sq. Ft.) Cut (Cu. Yd.) Fill (Cu. Yd.) Net (Cu. Yd.) Basin 5 Volume full <Fill> Totals 2d Area (Sq. Ft.) Cut (Cu. Yd.) Fill (Cu. Yd.) Net (Cu. Yd.) Total <Fill> * Value adjusted by cut or fill factor other than 1.0

NC2 Ash Disposal Area Run-on and Run-off Control System Plan

NC2 Ash Disposal Area Run-on and Run-off Control System Plan NC2 Ash Disposal Area Run-on and Run-off Control System Plan Omaha Public Power District Nebraska City Station Nebraska City, Nebraska October 17, 2016 OPPD NC2 Ash Disposal Area Run-On and Run-Off Control

More information

North Omaha Ash Landfill Run-on and Run-off Control System Plan

North Omaha Ash Landfill Run-on and Run-off Control System Plan North Omaha Ash Landfill Run-on and Run-off Control System Plan Omaha Public Power District North Omaha Station Omaha, Nebraska October 17, 216 OPPD North Omaha Ash Landfill Run-On and Run-Off Control

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT BOWEN PRIVATE INDUSTRY SOLID WASTE DISPOSAL FACILITY (ASH LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals

More information

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion

More information

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan For Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Valmont Station - CCR Surface Impoundments Public Service Company of Colorado Denver, Colorado

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part 257.82 PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment

More information

DRAINAGE STUDY. 645 Beard Creek Trail Lot 8, Cordillera Valley Club Filing No. 4 Eagle County, Colorado. November 4, Project No.

DRAINAGE STUDY. 645 Beard Creek Trail Lot 8, Cordillera Valley Club Filing No. 4 Eagle County, Colorado. November 4, Project No. DRAINAGE STUDY 645 Beard Creek Trail Lot 8, Cordillera Valley Club Filing No. 4 Eagle County, Colorado November 4, 2014 Project No. 14-2953 Prepared for Mr. Robert Myers Caribbean Group P.O. Box N 1968

More information

Run-on and Run-off Control System Plan

Run-on and Run-off Control System Plan Run-on and Run-off Control System Plan J.H. CAMPBELL GENERATING FACILITY DRY ASH LANDFILL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN West Olive, Michigan Pursuant to 4 CFR 257.81 Submitted To: Consumers Energy

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

DRAINAGE STUDY. 645 Beard Creek Trail Lot 8, Cordillera Valley Club Filing No. 1 Eagle County, Colorado. November 25, Project No.

DRAINAGE STUDY. 645 Beard Creek Trail Lot 8, Cordillera Valley Club Filing No. 1 Eagle County, Colorado. November 25, Project No. DRAINAGE STUDY 645 Beard Creek Trail Lot 8, Cordillera Valley Club Filing No. 1 Eagle County, Colorado November 25, 2014 Project No. 14-2953 Prepared for Mr. Robert Myers Caribbean Group P.O. Box N 1968

More information

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan B.C. COBB GENERATING FACILITY BOTTOM ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN Muskegon, Michigan Pursuant to 40 CFR 257.82 Submitted To: Consumers Energy

More information

Report Issued: July 26, 2017 Revision 1

Report Issued: July 26, 2017 Revision 1 ALLIANT ENERGY Interstate Power and Light Company Burlington Generating Station CCR SURFACE IMPOUNDMENT INFLOW DESIGN FLOOD CONTROL PLAN Report Issued: July 26, 2017 Revision 1 EXECUTIVE SUMMARY This Inflow

More information

Technical Memorandum

Technical Memorandum Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum To: Kathy Arnold From: Greg Hemmen, P.E. Company: Rosemont Copper Company Date:

More information

RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN

RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN FOR THE: SOUTHWESTERN ELECTRIC POWER COMPANY FLINT CREEK POWER PLANT LANDFILL CLASS 3N LANDFILL PERMIT 0273-S3N-R2 PREPARED FOR: SOUTHWESTERN ELECTRIC POWER COMPANY

More information

Run-on and Run-off Control System Plan

Run-on and Run-off Control System Plan Run-on and Run-off Control System Plan CCR Temporary Storage Pad Lewis and Clark Station Prepared for Montana-Dakota Utilities Co. October 2016 Paul T. Swenson 2016.10.13 18:30:03-05'00' 234 West Century

More information

WELSH POWER PLANT ASH LANDFILL. Run-on and Run-off Control System Plan

WELSH POWER PLANT ASH LANDFILL. Run-on and Run-off Control System Plan WELSH POWER PLANT ASH LANDFILL Run-on and Run-off Control System Plan SEPTEMBER 27, 2016 PREPARED BY: MTG TEXAS FIRM REGISTRATION NUMBER: 354 MTG PROJECT NUMBER: 167003 WELSH POWER PLANT - ASH LANDFILL

More information

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR 257.82 EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part 257 and Part

More information

Foothills Solar & Substation

Foothills Solar & Substation Final Drainage Study Foothills Solar & Substation Loveland, CO Prepared for: City of Loveland 410 E. Fifth Street Loveland, CO 80537 December 12, 2015 1501 Academy Ct. Ste. 203 Fort Collins, Colorado 80524

More information

Run-on and Run-off Control System Plan

Run-on and Run-off Control System Plan Run-on and Run-off Control System Plan For Compliance with the Coal Combustion Residuals Rule (40 CFR 257.81) Pawnee Station CCR Landfill Public Service Company of Colorado Denver, Colorado October 17,

More information

Contents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek

Contents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek Contents SITE LOCATION / DESCRIPTION... 3 WESTPOINTE STORMWATER MANAGEMENT PLAN... 3 THE ENCLAVE AT WESTPOINTE DETENTION POND... 3 Table

More information

ASH FILTER PONDS INFLOW DESIGN FLOOD CONTROL SYSTEM INITIAL PLAN

ASH FILTER PONDS INFLOW DESIGN FLOOD CONTROL SYSTEM INITIAL PLAN CCR RULE COMPLIANCE ASH FILTER PONDS INFLOW DESIGN FLOOD CONTROL SYSTEM INITIAL PLAN Prepared for: GenOn Northeast Management Company Keystone Generating Station Shelocta, Pennsylvania Prepared by: CB&I

More information

Initial Inflow Design Flood Control System Plan Holding Pond

Initial Inflow Design Flood Control System Plan Holding Pond Submitted to: Submitted by: Marquette Board of Light and Power AECOM Shiras Steam Plant Marquette, Michigan Marquette, Michigan Project No. 60445171 October 2016 Initial Inflow Design Flood Control System

More information

Introduction to Storm Sewer Design

Introduction to Storm Sewer Design A SunCam online continuing education course Introduction to Storm Sewer Design by David F. Carter Introduction Storm sewer systems are vital in collection and conveyance of stormwater from the upstream

More information

Summary of Detention Pond Calculation Canyon Estates American Canyon, California

Summary of Detention Pond Calculation Canyon Estates American Canyon, California July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i

More information

CCR Certification: Initial Inflow Design Flood Control System Plan for the

CCR Certification: Initial Inflow Design Flood Control System Plan for the Submitted to Southern Indiana Gas & Electric Company dba Vectren Power Supply, Inc. (SIGECO) One Vectren Square Evansville, IN 4778 Submitted by AECOM 94 Amberglen Boulevard Austin, Texas 78729 October

More information

PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION

PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION US Army Corps of Engineers Philadelphia District PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION CECIL COUNTY MARYLAND STORMWATER MANAGEMENT PLAN NARRATIVE INITIAL SUBMISSION JUNE 2014 1 PEARCE CREEK

More information

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan Scrubber Ponds Lewis and Clark Station Prepared for Montana-Dakota Utilities Co. October 2016 Paul T. Swenson 2016.10.14 17:54:29-05'00' 234 West Century Avenue

More information

Green Station CCR Surface Impoundment

Green Station CCR Surface Impoundment Green Station CCR Surface Impoundment Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule Hydrologic and Hydraulic Capacity Assessment and Initial Inflow Design Flood Control

More information

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

Inflow Design Flood Control System Plan Plant McDonough-Atkinson Ash Pond 3 (AP-3) and Ash Pond 4 (AP-4)

Inflow Design Flood Control System Plan Plant McDonough-Atkinson Ash Pond 3 (AP-3) and Ash Pond 4 (AP-4) Inflow Design Flood Control System Plan Plant McDonough-Atkinson Ash Pond 3 (AP-3) and Ash Pond 4 (AP-4) Prepared for: Georgia Power Company Prepared by: Golder Associates Inc. 3730 Chamblee Tucker Road

More information

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan For Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Cherokee Station - CCR Surface Impoundments Public Service Company of Colorado Denver, Colorado

More information

Hydrologic and Hydraulic Analysis Report Mountaineer Plant Bottom Ash Pond Complex New Haven, West Virginia

Hydrologic and Hydraulic Analysis Report Mountaineer Plant Bottom Ash Pond Complex New Haven, West Virginia Hydrologic and Hydraulic Analysis Report Mountaineer Plant Bottom Ash Pond Complex New Haven, West Virginia September 2015 Terracon Project Number: N4155129 Prepared for: American Electric Power 1 Riverside

More information

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

APPENDIX K OPERATIONS AND FINAL COVER SURFACE WATER MANAGEMENT SYSTEM DESIGN

APPENDIX K OPERATIONS AND FINAL COVER SURFACE WATER MANAGEMENT SYSTEM DESIGN ONONDAGA LAKE SEDIMENT CONSOLIDATION AREA CIVIL & GEOTECHNICAL FINAL DESIGN APPENDIX K OPERATIONS AND FINAL COVER SURFACE WATER MANAGEMENT SYSTEM DESIGN PARSONS P:\Honeywell -SYR\44483 - Lake Detail Design\9

More information

January 20, Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO (303)

January 20, Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO (303) January 20, 2017 Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO 80229 (303) 538-7694 RE: Riverdale Five Retail Drainage Conformance Letter

More information

STORMWATER RUN-ON AND RUN-OFF CONTROL PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL

STORMWATER RUN-ON AND RUN-OFF CONTROL PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL STORMWATER RUN-ON AND RUN-OFF CONTROL PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO. 0200-S3N-R2 AFIN: 32-00042 OCTOBER 12, 2016 STORMWATER RUN-ON AND RUN-OFF CONTROL PLAN

More information

STORMWATER RUN-ON AND RUN-OFF CONTROL PLAN ENTERGY ARKANSAS, INC. WHITE BLUFF PLANT CLASS 3N CCR LANDFILL

STORMWATER RUN-ON AND RUN-OFF CONTROL PLAN ENTERGY ARKANSAS, INC. WHITE BLUFF PLANT CLASS 3N CCR LANDFILL STORMWATER RUN-ON AND RUN-OFF CONTROL PLAN ENTERGY ARKANSAS, INC. WHITE BLUFF PLANT CLASS 3N CCR LANDFILL PERMIT NO. 199-S3N-R3 AFIN: 3-11 OCTOBER 13, 216 STORMWATER RUN-ON AND RUN-OFF CONTROL PLAN ENTERGY

More information

BMP Design Aids. w w w. t r a n s p o r t a t i o n. o h i o. g o v. Equations / Programs

BMP Design Aids. w w w. t r a n s p o r t a t i o n. o h i o. g o v. Equations / Programs BMP Design Aids 1 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 2 Ohio Department of Transportation 1 Training Intent Introduction and overview of

More information

Final Drainage Report

Final Drainage Report Thornton Electric Substation Project Final Drainage Report December 14, 2016 DRAFT Prepared for: Xcel Energy, 1800 Larimer Street, Suite 400, Denver, Colorado 80202 Prepared by: 350 Indiana Street, Suite

More information

Development, Design, & Construction Standards

Development, Design, & Construction Standards South Weber City Corporation Development, Design, & Construction Standards October 2017 Prepared by JONES & ASSOCIATES Consulting Engineers Development, Design, and Construction Standards TABLE OF CONTENTS

More information

Development, Design, & Construction Standards

Development, Design, & Construction Standards South Weber City Corporation Development, Design, & Construction Standards October 2017 Prepared by JONES & ASSOCIATES Consulting Engineers Development, Design, and Construction Standards TABLE OF CONTENTS

More information

Table of Contents. List of Appendices. October 2016 i

Table of Contents. List of Appendices. October 2016 i October 2016 i 1663066 Table of Contents 1.0 INTRODUCTION... 1 2.0 REGULATORY REQUIREMENTS... 1 3.0 DESIGN METHODOLOGY... 1 3.1 Design Storm... 1 3.2 Rainfall Abstractions... 1 3.3 Routing Methodology...

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond INFLOW DESIGN FLOOD

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond INFLOW DESIGN FLOOD INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN Bremo Power Station CCR Surface Impoundment: North Ash Pond Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo

More information

RETENTION BASIN EXAMPLE

RETENTION BASIN EXAMPLE -7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary

More information

Hydrology Study. For Bella Terrazza Portion of Lot 1, Block 39, Subdivision of S Tract, Rancho El Cajon El Cajon, CA 92021

Hydrology Study. For Bella Terrazza Portion of Lot 1, Block 39, Subdivision of S Tract, Rancho El Cajon El Cajon, CA 92021 Hydrology Study For Bella Terrazza Portion of Lot 1, Block 39, Subdivision of S Tract, Rancho El Cajon El Cajon, CA 92021 Prepared for Daryl Priest - Priest Development Corporation 124 West Main Street,

More information

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan Scrubber Ponds Lewis & Clark Station Prepared for Montana-Dakota Utilities Co. November 2018 234 West Century Avenue Bismarck, ND 58503 701.255.5460 www.barr.com

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY (i) Site Name and Ownership Information: Site Name: Plant Hammond Site Location: Site Address:

More information

2017 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

2017 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN: 217 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO. 2-S3N-R2 AFIN: 32-42 JANUARY 17, 218 217 Landfill Inspection Report Entergy Independence Plant Class 3N

More information

Drainage Analysis. Appendix E

Drainage Analysis. Appendix E Drainage Analysis Appendix E The existing and proposed storm drainage systems have been modeled with Bentley CivilStorm V8 computer modeling software. The peak stormwater discharge was determined for

More information

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No Environmental Resources Management January 13, 2017 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0352436 CityCentre Four 840 West Sam Houston Parkway North, Suite 600 Houston,

More information

VISUAL SITE INSPECTION REPORT 2018

VISUAL SITE INSPECTION REPORT 2018 VISUAL SITE INSPECTION REPORT 2018 SOUTHERN INDIANA GAS AND ELECTRIC A. B. BROWN GENERATING STATION TYPE III RESTRICTED WASTE LANDFILL WEST FRANKLIN, IN ATC PROJECT NO. 170LF00614 January 9, 2019 PREPARED

More information

Stantec Consulting Services Inc Lebanon Road, Cincinnati, OH 45241

Stantec Consulting Services Inc Lebanon Road, Cincinnati, OH 45241 Stantec Consulting Services Inc. 11687 Lebanon Road, Cincinnati, OH 45241 File: 175534017 Revision 0 Ohio Valley Electric Corporation 3932 U.S. Route 23 P.O. Box 468 Piketon, Ohio 45661 RE: Run-on and

More information

ENVIRONMENTAL ENGINEERING LAND SURVEYING

ENVIRONMENTAL ENGINEERING LAND SURVEYING ENVIRONMENTAL ENGINEERING LAND SURVEYING Inflow Design Flood Control System Plan Bottom Ash Pond Sherburne County Generating Plant Introduction This report presents documentation and certification of the

More information

DRAINAGE & DESIGN OF DRAINAGE SYSTEM

DRAINAGE & DESIGN OF DRAINAGE SYSTEM Drainage on Highways DRAINAGE & DESIGN OF DRAINAGE SYSTEM P. R.D. Fernando Chartered Engineer B.Sc.(Hons), M.Eng. C.Eng., MIE(SL) Drainage Requirement of Highway Drainage System Introduction Drainage means

More information

ENVIRONMENTAL ENGINEERING LAND SURVEYING

ENVIRONMENTAL ENGINEERING LAND SURVEYING ENVIRONMENTAL ENGINEERING LAND SURVEYING Inflow Design Flood Control System Plan Scrubber Solids Pond No. 3 Sherburne County Generating Plant Introduction This report presents documentation and certification

More information

RE: Final Drainage Letter: Northwest Aurora Alley Improvements 2016

RE: Final Drainage Letter: Northwest Aurora Alley Improvements 2016 April 12, 2016 Mr. Craig Perl, P.E. Senior Engineer City of Aurora Public Works Department 15151 E. Alameda Parkway Aurora, CO 80012 RE: Final Drainage Letter: Northwest Aurora Alley Improvements 2016

More information

Culvert Sizing procedures for the 100-Year Peak Flow

Culvert Sizing procedures for the 100-Year Peak Flow CULVERT SIZING PROCEDURES FOR THE 100-YEAR PEAK FLOW 343 APPENDIX A: Culvert Sizing procedures for the 100-Year Peak Flow A. INTRODUCTION Several methods have been developed for estimating the peak flood

More information

Drainage Report. PDC Energy Metcalf Soil Treatment Facility. OA Project No

Drainage Report. PDC Energy Metcalf Soil Treatment Facility. OA Project No Drainage Report PDC Energy Metcalf Soil Treatment Facility OA Project No. 013-0036 760 Horizon Drive, Suite 102 Grand Junction, CO 81506 TEL 970.263.7800 FAX 970.263.7456 DRAINAGE REPORT PDC METCALF CENTRALIZED

More information

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228 Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA 30534 (706) 344-3500 x 42228 DAWSON COUNTY STORM WATER REVIEW CHECKLIST Project Name: Property Address: Engineer: Fax #/Email: Date:

More information

APPENDIX III Hydrologic and Hydraulic Evaluations

APPENDIX III Hydrologic and Hydraulic Evaluations APPENDI III Hydrologic and Hydraulic Evaluations Hydrologic and Hydraulic Analysis Related to Compliance Requirements South Fly Ash Pond, Boiler Slag Pond and Clearwater Pond Kyger Creek Power Plant, Gallia

More information

LAKE COUNTY HYDROLOGY DESIGN STANDARDS

LAKE COUNTY HYDROLOGY DESIGN STANDARDS LAKE COUNTY HYDROLOGY DESIGN STANDARDS Lake County Department of Public Works Water Resources Division 255 N. Forbes Street Lakeport, CA 95453 (707)263-2341 Adopted June 22, 1999 These Standards provide

More information

MODEL Stormwater Local Design Manual. City of Centerville

MODEL Stormwater Local Design Manual. City of Centerville MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO. 0200-S3N-R2 AFIN: 32-00042 JANUARY 15, 2016 ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

2016 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO

2016 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO 2016 LANDFILL INSPECTION REPORT GERS-16-004 CARDINAL PLANT BRILLIANT, OHIO PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Cardinal Plant Landfill Inspection

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116 (i) Site Name and Ownership Information: HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY Site Name: Site Location: Site Address: Owner: Owner Address:

More information

Environmental Design Group

Environmental Design Group SEDIMENT CONTROL DURING CONSTRUCTION, STORMWATER MANAGEMENT AND POST CONSTRUCTION BMP REPORT for Hudson Salt Storage and Bus Garage 5810 Hudson Drive HUDSON, OHIO SUMMIT COUNTY Prepared by Environmental

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

MIDAS CREEK PROJECT. FINAL DESIGN REPORT SKR Hydrotech 4/11/2012

MIDAS CREEK PROJECT. FINAL DESIGN REPORT SKR Hydrotech 4/11/2012 2012 MIDAS CREEK PROJECT FINAL DESIGN REPORT SKR Hydrotech 4/11/2012 Executive Summary... 1 Section 1 Introduction... 1 Background Information... 1 Purpose of Study... 1 Scope of Work... 1 Section 2 Description

More information

Warner Robins Stormwater Local Design Manual

Warner Robins Stormwater Local Design Manual Warner Robins Stormwater Local Design Manual Prepared for Houston County City of Warner Robins City of Perry City of Centerville May 17, 2005 Version 4 (As presented with adopted Stormwater Ordinance)

More information

Run-on and Run-off Control System Plan

Run-on and Run-off Control System Plan Run-on and Run-off Control System Plan SWEPCO John W. Turk, Jr. Power Plant Fulton, Arkansas Permit No. 0311-S3N-R1 AFIN: 29-00506 October 2016 Terracon Project No. 35167133 Prepared for: SWEPCO 3711 Highway

More information

APPENDIX G HYDRAULIC GRADE LINE

APPENDIX G HYDRAULIC GRADE LINE Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm

More information

VISUAL SITE INSPECTION REPORT

VISUAL SITE INSPECTION REPORT VISUAL SITE INSPECTION REPORT - 2016 SOUTHERN INDIANA GAS AND ELECTRIC A. B. BROWN GENERATING STATION TYPE III RESTRICTED WASTE LANDFILL WEST FRANKLIN, IN ATC PROJECT NO. 170LF00318 DECEMBER 20, 2016 PREPARED

More information

Technical Memorandum Mine Plan of Operations Stormwater Assessment

Technical Memorandum Mine Plan of Operations Stormwater Assessment Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum Mine Plan of Operations Stormwater Assessment To: Kathy Arnold From: David R.

More information

Background. October 7, American Electric Power 1 Riverside Plaza, 22nd Floor Columbus, Ohio 43215

Background. October 7, American Electric Power 1 Riverside Plaza, 22nd Floor Columbus, Ohio 43215 October 7, 2016 American Electric Power 1 Riverside Plaza, 22nd Floor Columbus, Ohio 43215 Attention: Reference: Mr. Brian G. Palmer Ash Pond Complex CCR Surface Impoundment Inflow Design Flood Assessment

More information

2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio

2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio Prepared for: FirstEnergy Generation, LLC 76 South Main St Akron, Ohio 44308 2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio Prepared by: 10211 Wincopin Circle, Floor 4 Columbia,

More information

FEMA (from current study - not yet adopted) Flow Data Table 2 Summary of Discharges Floodway Data

FEMA (from current study - not yet adopted) Flow Data Table 2 Summary of Discharges Floodway Data Table of Contents Report Cover Table of Contents General Information Methodology Existing Condition Analysis Proposed Condition Analysis Summary Conclusions and Recommendations Appendix Maps and Exhibits

More information

AMERICAN ELECTRIC POWER (SWEPCO)

AMERICAN ELECTRIC POWER (SWEPCO) 2016 DAM & DIKE INSPECTION REPORT ASH PONDS GERS-16-163 WELSH POWER PLANT AMERICAN ELECTRIC POWER (SWEPCO) CASON, TEXAS NATIONAL INVENTORY NO. TX4357 PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION

More information

HY-12 User Manual. Aquaveo. Contents

HY-12 User Manual. Aquaveo. Contents Y-12 User Manual Aquaveo Contents Overview...2 Watershed Parameters...3 Channel Parameters...3 Storm Drain Parameters...3 Design of new systems...4 Analysis of existing systems...4 Steady flow...4 ydrographic

More information

DRAINAGE BASICS Common Terminology & Reference Tools Drainage Components Determine Existing Conditions Calculate Development Requirements

DRAINAGE BASICS Common Terminology & Reference Tools Drainage Components Determine Existing Conditions Calculate Development Requirements DRAINAGE BASICS 1 Common Terminology & Reference Tools Drainage Components Determine Existing Conditions Calculate Development Requirements 2 Common Terminology & Useful Tools CFS= Cubic Feet per Second-

More information

CHOLLA POWER PLANT BOTTOM ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN CH_Inflowflood_003_

CHOLLA POWER PLANT BOTTOM ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN CH_Inflowflood_003_ CHOLLA POWER PLANT BOTTOM ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN CH_Inflowflood_003_20161017 This Inflow Design Flood Control System Plan (Plan) document has been prepared specifically for the

More information

The site slopes generally from the southwest to northeast at approximately 3.7 percent.

The site slopes generally from the southwest to northeast at approximately 3.7 percent. March 3, 2017 Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO 80229 (303) 538-7694 RE: Riverdale Five Retail Drainage Conformance Letter Dear

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT MCDONOUGH ASH POND 1 (AP-1) GEORGIA POWER COMPANY

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT MCDONOUGH ASH POND 1 (AP-1) GEORGIA POWER COMPANY HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i)-(xii) PLANT MCDONOUGH ASH POND 1 (AP-1) GEORGIA POWER COMPANY (i) Site Name and Ownership Information: Site Name: Site Location: Site Address: Owner: Address:

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Diversion Channels DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] The design of permanent

More information

Coal Combustion Residuals Inflow Design Flood Control System Plan

Coal Combustion Residuals Inflow Design Flood Control System Plan gaiconsultants.com I transforming ideas into reality., Coal Combustion Residuals Inflow Design Flood Control System Plan Virginia Electric and Power Company Possum Point Power Station Surface Impoundment

More information

Basketball Court Design

Basketball Court Design Basketball Court Design CENE 486C, Hamad Alqalaf and BASKETBALL COURT DESIGN TEAM Table of Contents 1.0 Introduction... 1 2.0 Acknowledgments... 1 3.0 Previous Work... 1 4.0 Project Description... 1 4.1

More information

Jacobi, Toombs, and Lanz, Inc.

Jacobi, Toombs, and Lanz, Inc. Area 5: Blackiston Mill Road at Dead Man's Hollow Flooding Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations

More information

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm

More information

2015 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO

2015 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO 2015 LANDFILL INSPECTION REPORT GERS-15-021 CARDINAL PLANT BRILLIANT, OHIO PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Cardinal Plant Landfill Inspection

More information

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges Detention Pond Design Considering Varying Design Storms Land Development Results in Increased Peak Flow Rates and Runoff Volumes Developed area Robert Pitt Department of Civil, Construction and Environmental

More information

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials.

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials. I. Drainage Report A. Executive Summary - Brief Overview of Project Drainage Design B. Project Description 1. Existing Conditions 2. Proposed Project Conditions 3. Project Justification Narrative - Basin

More information

NAU Flooding Mitigation, Garden Design, and Storm Water Utilization. Final Design Report

NAU Flooding Mitigation, Garden Design, and Storm Water Utilization. Final Design Report NAU Flooding Mitigation, Garden Design, and Storm Water Utilization Prepared By: ZABS Inc. Lucas Zirotti Naser Alqaoud Chelena Betoney Michael Swearingen Prepared For: CENE 486 Grading Instructor: Dianne

More information

Jim Bridger Power Plant

Jim Bridger Power Plant 2015 Coal Combustion Residuals Annual Inspection Jim Bridger Power Plant Industrial Landfill Prepared for PacifiCorp Energy North Temple Office 1407 West North Temple Salt Lake City, Utah 84116 Final December

More information

McElroy s Run Impoundment Inflow Design Flood Control System Plan

McElroy s Run Impoundment Inflow Design Flood Control System Plan McElroy s Run Impoundment Inflow Design Flood Control System Plan Allegheny Energy Supply Company, LLC A FirstEnergy Company Pleasants Power Station Pleasants County, West Virginia October 2016 Prepared

More information