Pelican Lake SAGD Pilot Approval 11469A 2011 Update. ERCB Offices March 21, 2012.

Size: px
Start display at page:

Download "Pelican Lake SAGD Pilot Approval 11469A 2011 Update. ERCB Offices March 21, 2012."

Transcription

1 Approval 11469A 2011 Update ERCB Offices March 21, 2012.

2 Introduction and Overview Introduction Subsurface Issues Related to Resource Evaluation and Recovery Directive 054, Section Surface Operations, Compliance, and Issues Not Related to Resource Evaluation and Recovery Directive 054, Section 3.1.2

3 Subsurface Issues: Table of Contents 1. Brief Background of the Scheme 2. Geology / Geoscience 3. Drilling and Completions 4. Artificial Lift 5. Instrumentation in Wells 6. Seismic 7. Scheme Performance 8. Future Plans

4 Brief Background Subsurface Subsection 1 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

5 Brief Background

6 Project Overview SAGD Pilot to evaluate large resource base of ~ 5 Billion barrels OBIP 100% WI Other operations within the region Cenovus and Canadian Natural Resources operate enhanced recovery schemes Laricina has proposed a 155,000 bbls/d development in the Grand Rapids A to the north

7 Application History April 2010 June 2010 August 2010 November 2010 August 2011 November 2011 December 2011 ERCB Scheme application submitted ERCB Approval No granted ERCB Facility License F42085 granted AENV Approval No granted ERCB MARP approved ERCB D51 granted for 26P01/26I01 ERCB Scheme amendment for 2 nd well pair submitted ERCB Approval No A granted AENV & ERCB amendment for 3 rd OTSG, expanded surface lease and extended operating period to December 2017 Approval pending

8 Description of Recovery Process The Pelican Lake SAGD Pilot uses the dual-horizontal well SAGD (steam assisted gravity drainage) process to recover the bitumen from the Grand Rapids A formation Two horizontal wells one above the other ~5m apart Steam injected into the upper well to heat the bitumen and allow gravity to drain to the lower well Oil and water emulsion pumped to the surface and treated

9 Original Objectives Test longer well lengths (1200m+) Evaluate start up procedures Determine peak rates from the Grand Rapids Reservoir management with the lean zone

10 Geology / Geoscience Subsurface Subsection 2 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

11 Predictable SAGD Play with New Challenges Shore-face Deposit Depositional environment is ideal for SAGD. Sands are laterally and vertically continuous and predictable. SAGD Well pair lengths up to 1600m in length are proposed Bitumen deposit within Regional Grand Rapids Aquifer Non saline ground water Reservoir quality issues; lean zone (top water mobility), average SAGD Pay 18 m, average SAGD oil saturation 64%, permeability ~ 2,900 md, and reservoir operating pressure ~ 1,200 kpa Wells 26P01, 26I01 100/ / / / /12-2 VIKING CAP ROCK GDPD A TOP PAY LEAN ZONE SAGD PAY BASE PAY GDPD B GDPD B

12 Stratigraphic Correlation After Jackson, 1983 Cap Rock Bitumen & Source Water Wabiskaw Production ~23,000 bbls/day Disposal Zone NISKU

13 Paleogeography - Grand Rapids A mbr Pelican Lake Depositional environment - prograding shoreface (marine sediments forming shoreline sandstones) Very fine to medium grained Quartzose sand with minor feldspar, chert, muscovite and biotites Aerially extensive 10m+ thick bar sands Shoreline After Jackson, 1983

14 Type Log VIKING JOLI FOU GRAND RAPIDS A GRAND RAPIDS B

15 Grand Rapids A Top Structure Map

16 SAGD Base Structure Map

17 Grand Rapids B Top Structure Map

18 Cap Rock Isopach Map (Joli Fou Formation)

19 Grand Rapids A Lean Zone Isopach Map

20 Grand Rapids A SAGD Pay Isopach Map

21 Summary of Reservoir Properties Base of Grand Rapids A Average Gross Thickness Average SAGD Pay Thickness Average Porosity Average Water Saturation m Subsea 23 m 18 m 35 % 46 % (Gross ) Average Permeability 2.9 D 38 % (SAGD Pay Zone) OBIP 8.0 X10 6 m 3 (50.3 MMbbls ) Oil Viscosity Oil Gravity Initial Reservoir Pressure 1,000,000 cp API 1200 kpa

22 Grand Rapids A Mineralogic Petrographic Montage

23 Cap Rock Integrity - Joli Fou Fm 103/ W4M (221 mkb) Fracture closure pressure=4.75 MPa

24 Drilling and Completions Subsurface Subsection 3 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

25 Well Layout / Location Map 03/ /9-10 Thermocouples Piezometers 00/ /8-10 x 02/ / / / /4-11 Ground Water obs 02/ /16-3 x X New Drills 02/ /9-3 x 03/ /5-11 (Swab/Inj test)

26 Start-up Circulation Pad26P01 Producer Completion KB Elevation: m Ground Elevation: m Conductor mm kg/m H-40 ST&C Surface Casing landed at 20.0 mkb UWI: 102/ W4/00 *Notes: Outer Tubing Outer tubing crossover should be ~20m back from liner hanger WR Plug Weatherford At mkb Surface Casing mm 81.1 kg/m J-55 ST&C Surface Casing landed at 95.0 mkb Intermediate Casing mm kg/m L-80 QB2 Production casing landed at mkb MD Outer tubing mm J-55 R kg/m TKC40/40 tubing set at mkb MD mm J-55 R kg/m TKC40/40tubing c/w re-entry guide on end of tubing from m mkb MD Instrument string 31.7 mm coil to 1,558.0 mkb Smith Thermal Liner Hanger top at mkb MD Bottom at mkb MD Inner Tubing Inner tubing crossover should be ~10m above outer tubing crossover. (73.0mm 60.3mm) Inner tubing crossover from 60.3mm to 73.0mm should be right after outer tubing TD. (As soon as possible) Inner tubing should end ~15-20m back from Liner TD. Liner Slotting First Slot at mkb Last Slot at ~ mkb TOE at mkb MD Inner tubing 73.0 mm R2 L-80 TKC40/40 tubing to mKB (~10 15 m above outer crossover) 60.3 mm R2 L-80 TKC40/40 tubing from m mkb (~5-10 m after end of outer 114.3mm tbg 73.0 mm R2 L-80 TKC40/40 tubing c/w mule shoe on end from m mkb MD December 2010 Liner capacity: kg/m m3/m kg/m m3/m Liner mm 38.7 / 34.2 kg/m L-80 QB m mkb MD (end of guide shoe)

27 Start-up Circulation Pad26I01 Injector Completion Surface Casing 13 3/8 in mm kg/m H-40 ST&C Surface Casing landed at mkb UWI: 100/ W4/00 *Notes: Outer Tubing Outer tubing crossover should be ~20m back from liner hanger Inner Tubing Inner tubing crossover should be ~10m from outer tubing crossover. (73.0mm 60.3mm) Inner tubing crossover from 60.3mm to 73.0mm should be right after outer tubing TD. (As soon as possible) Inner tubing should end ~15-20m back from Liner TD. Intermediate Casing 9 5/8 in mm kg/m L-80 QB2 Production casing landed at mkb Outer tubing 5.5 in & 4.5 in mm tubing to mkb mm tubing from 400mKb to mkb Inner tubing 2 7/8 in 73.0 mm tubing to mkb (~10-15 m before outer Crossover) 60.3 mm tubing to mkb (~5-10 m after outer tubing bottom) 73.0 mm tubing to mkb December 2010 Liner Hanger mkb Liner mm = 7 in 38.7 / 34.2 kg/m L-80 QB mkb

28 26P01: Completion After Circulation with Suction Ports Surface Casing mm kg/m H-40 ST&C Surface Casing landed at mkb Intermediate Casing mm kg/m L80 QB2 Production casing mkb See next slide for discussion on challenges with this completion. Production Tubing: 4.5 in mm tubing to mkb ESP 380 mkb Instrument String 31.7 mm coil end of tail pipe Include bubble tube at Pump intake 4.5 Tail Pipe with 2 ports. April 2011 Liner mm 38.7 / 34.2 kg/m L-80 QB2 Liner Hanger mkb mkb

29 Producer Suction Ports: Discussion The suction ports were designed to increase the capacity of the 4.5 tubing in the horizontal section while minimizing the pressure drop in the annulus between the 7 liner and the 4.5 tubing. Fluid entering the liner upstream of a suction port will enter the 4.5 tubing through that port and thus be removed from the annulus before the next suction port. This system works very well when the well pair is uniformly heated. However, in this case there is a hot spot close to the heel of the producer and it was desirable to get the fluid from the hot spot to the toe thereby promoting uniform heating along the producer liner. The suction ports made it difficult to achieve this and were thus removed. We also needed to steam the producer and the suction ports which impeded steam to the toe.

30 26I01: Re-Completed with Steam Splitters Conductor mm kg/m H-40 ST&C landed at 20.0 mkb KB Elevation: m GL Elevation: m Surface Casing mm 81.1 kg/m J-55 ST&C Surface Casing landed at 92.0 mkb MD Intermediate Casing mm kg/m L-80 QB2 Production casing landed at mkb MD Injection Tubing mm J-55 R kg/m TKC40/40 tubing set at mkb MD 88.9 mm J-55 R kg/m TKC40/40tubing from m mkb MD April x88.9mm CrossOver mm TKC40/40 tubing with steam splitters to mkb

31 26P01: Suction Ports Removed Surface Casing mm kg/m H-40 ST&C Surface Casing landed at mkb Intermediate Casing mm kg/m L80 QB2 Production casing mkb Production Tubing: 4.5 in mm tubing to mkb ESP 380 mkb Instrument String 31.7 mm coil end of tail pipe Include bubble tube at Pump intake 4.5 Tail Pipe September 2011 Liner mm 38.7 / 34.2 kg/m L-80 QB2 Liner Hanger mkb mkb

32 Evolution of SAGD Well Pair Completions Wells 26P01, 26I01 Injector and Producer had similar completions during start up circulation. After start up, producer was re-completed with ESP and suction ports in the production tubing which extends to the toe. The injector was re-completed with 15 steam splitters to promote uniform steam injection down hole. Suction port design was not optimum and the producer was later re-completed with the suction ports removed.

33 Artificial Lift Subsurface Subsection 4 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

34 Artificial Lift The artificial lift mode for the Grand Rapids A SAGD Pilot producer is Electric Submersible Pump (ESP) Operating pressure range kpa, Bottom hole temperature limit of 207C during production. Can steam past pump at higher temperatures. Lift capacity up to 600 m3/d The artificial lift mode for the Grand Rapids B water source well is Electric Submersible Pump (ESP) Lift capacity up to 750 m3/d

35 Instrumentation in Wells Subsurface Subsection 5 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

36 Instrumentation In Wells SAGD Well Pair Instrumentation Gas blanket for injector bottom hole pressures. No down hole temperature measurements in injector. Bubble tube for producer bottom hole pressure measurements. Also equipped with 6 thermocouple coiled tubing to the toe. 6 Observation wells 3 are equipped with piezometers. 3 are equipped with thermocouples. Requirements under subsection a wellbore schematics, 5c and 5d are included in the Appendix.

37 Instrumentation In Wells 03/ /9-10 Thermocouples Piezometers 00/ /8-10 x 02/ / / / /4-11 Ground Water obs 02/ /16-3 x X New Drills 02/ /9-3 x 03/ /5-11 (Swab/Inj test)

38 Seismic Subsurface Subsection 6 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

39 Seismic Coverage Very small, 1 sq. km, small bin with 10 m size Baseline 3D was shot in winter Purpose: Baseline seismic for monitoring of steam chamber growth in pilot area Re-shot in winter, currently being processed

40 2010 & D/4D Seismic Programs

41 Scheme Performance Subsurface Subsection 7 Pelican Lake SAGD Pilot 2011 Annual Performance Presentation

42 Scheme Performance Prediction Well pair performance prediction was based on a correlation using a modified Butler s equation and sensitivities from reservoir simulation. CSOR was predicted for the well pair from published correlations for CSOR (Edmunds and Chhina 2002)

43 Wellhead Steam Quality Steam quality injected into the wells is estimated at 98% Steam is generated at 7500 kpa and saturation temperature of 290 C Actual wellhead injection pressure depends on steam injection rate but has not exceeded 5,000 kpa (264 C) to date

44 Summary Operating for ~ 15 months Progress has been slow: Had to deal with many unplanned issues Excellent learnings to date: Very relevant to the start up of the commercial project Good reservoir performance: Mechanical issues limited wellbore effectiveness - still less than ½ of the well length Second well pair drilled to achieve original pilot objectives. Major focus is start-up

45 Project Timelines Time Period Dec 10, 2010 to Apr 13, 2011 April 13 to May 11 May 11 to June 5 June 14 to July 7 July 7 to Aug 31 Sep 1 to Oct 10 Oct to Jan 24, 2012 Jan 24 to Mar 13 Mar 14 Activity Start-up and Circulation Recompletion Initial SAGD Operations Steam Injection Into Producer Extended SAGD Operations Steam injection into producer, turnaround, ESP replacement, producer recompletion SAGD Operations Steam injection into producer Resuming SAGD Operations

46 Startup and Circulation (Dec. 10 to April 13) Thermocouple string malfunction Lean Zone Pressure SAGD wells connected to lean zone days after startup / / / /3-11 Operations at low pressures Dec 18-Dec 23-Dec 28-Dec 2-Jan 7-Jan 12-Jan

47 Recompletions (April 13 to May 11, 2011) SAGD producer recompletion went well Casing liner failure and split tubing coupling in SAGD injection well Casing Liner Debris Split Coupling

48 Temperature Surveys and Thermocouples HEEL TOE Temp (Deg C) Injection Liner Failure Depth (m) Producer Injector_April16 Injector_April 15 Aug31 TC before SI Prd_Ports Injector_Jan Inj_Liner Problem Seismic Anomaly

49 SAGD Re Completions SAGD INJECTOR SAGD PRODUCER Thermocouple Tubing Bubble Tube ESP Suction Ports Steam Splitters

50 Initial SAGD Operations (May 11 to June 5) H2S produced almost immediately Temporary flare system installed to allow production Incinerator installation Relatively low and unstable production rates

51 July / August SAGD Operations Operations for 8 weeks < 400 m of 1,200 m horizontal well heated up 150 bbls/d SOR = 3 bbl/bbl Thermocouples2 [Generated from trend :27:04 AM] SAGD-SW026-TT1106F Daily Avg [degc] SAGD-SW026-TT1106E Daily Avg [degc] SAGD-SW026-TT1106D Daily Avg [degc] 225 SAGD-SW026-TT1106C Daily Avg [degc] SAGD-SW026-TT1106B Daily Avg [degc] SAGD-SW026-TT1106A Daily Avg [degc] degc Jul Fri 15 Fri 22 Fri 1 Mon 8 Mon 15 Mon 22 Mon 1 Thu

52 September and October Operations ESP failed due to damaged cable; removed and installed new ESP Removed producer suction ports Injected steam to toe of producer ESP startup today SAGD PRODUCER Thermocouple Tubing Bubble Tube ESP Scab Liner

53 2011 Cumulative Injection & Production Volumes December 10 th 2010 to March 1 st 2012 = 43,110 m 3 of steam Steam Fluid Volume (m^3) Oil Dec Jan Mar-11 8-May Jun Aug-11 5-Oct Nov Jan-12 Time

54 2011 Pilot Performance Total Fluid Oil Steam SOR Steaming Producer Steaming Producer Rate (m 3 /d) SOR Jul 28-Jul 18-Aug 8-Sep 29-Sep 20-Oct 10-Nov 1-Dec 22-Dec 12-Jan 2-Feb 23-Feb *Note: Site turnaround September 12-15th, 2011 Date

55 2011 Thermocouple Response 103/12-02 Thermocouple located at toe Temperature (C) mTVD 219 Depth (mkb) 229 January 8th April 1st 2011 August 15th 2011 December 31st mTVD Lateral distance from Observation well to the well pair = 4.0 m

56 2011 Thermocouple Response 102/13-02 Thermocouple 400m from toe toward heel Temperature (C) m TVD January 6th April 1st 2011 August 15th 2011 December 31st 2011 Depth (mkb) m TVD Lateral distance from Observation well to the well pair = 4.2 m

57 2011 Thermocouple Response 102/05-11 Thermocouple located at heel Temperature (C) m TVD 219 January 8th 2011 Depth (mkb) 229 April 1st 2011 August 15th 2011 December 31st m TVD Lateral distance from Observation well to the well pair = 21.4 m

58 Key Learnings 1. Project Design and Execution Cooling and gas handling required at low operating pressures 2. Drilling, Completions and Wellbores Improved mud system and larger drilling rigs Ensure wellbore heated up before SAGD operations Ability to divert steam to focus areas of wellbore is critical 3. Operations at Low Pressures 4. Reservoir and Production Lean zone management H 2 S presence

59 Future Plans Subsurface Subsection 8 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

60 Second Well Pair Profile & Observation wells 03/ /9-10 Thermocouples Piezometers 00/ /8-10 x 02/ / / / /4-11 Ground Water obs 02/ /16-3 x X New Drills 02/ /9-3 x 03/ /5-11 (Swab/Inj test)

61 Future Plans A second well pair has been drilled and is being completed. The wells are equipped with 9 5/8 intermediate casing and 1,200m long 7 slotted liner The well pair will have fibre-optic cables for temperature and pressure monitoring The second well pair also has three observation wells for monitoring the lean zone pressures, temperatures and steam chamber growth Waiting for approval to install a third steam generator (30 MMBtu) to increase steam capacity, expand the surface lease area and extend the operating life of the pilot

62 Pelican Lake SAGD Pilot Proposed Surface Heave Monitoring (InSAR) Scheme Boundary

63 Surface Operations, Compliance and Issues Not related to Resource Evaluation and Recovery Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

64 Surface Operations: Table of Contents 1. Facilities 2. Measurement and Reporting 3. Fresh and Brackish Water Sources and Uses 4. Water Treatment Technology 5. Water, Landfill waste and waste disposal wells 6. Sulphur Production 7. Summary of Environmental Issues 8. Compliance Confirmation 9. Future Plans

65 Facilities Surface Subsection 1 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation0

66 Current Site Plan N Planned site expansion

67 Block Diagram

68 Facilities Modifications Installed an incinerator to handle the casing gas Helped with the ESP pumping efficiency to evacuate producer casing

69 Plant Performance Overall stable plant performance Water Treatment works well Emulsion transported to Greater Pelican Lake battery with no issues Boilers have had minor issues

70 Measurement and Reporting Surface Subsection 2 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

71 MARP Schematic

72 MARP Updated MARP submitted March 12th Amendments New mass flow meters added Incinerator package added to handle casing gas A second casing gas meter added Planned Additions Meters associated with the second well pair

73 Fresh and Brackish water sources and uses Surface Subsection 3 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

74 Fresh Water Sources Two Fresh water wells 1. 1F1/ W4 in the Grand Rapids B formation 2. 1F1/ W4 in the Grand Rapids B formation No Brackish water wells

75 Fresh Water Daily Volumes 600 Water Source Well Rate: 1F1/ W4 500 Current Flow (m^3/day) Dec Jan Mar-11 9-May Jun Aug-11 6-Oct Nov Jan-12 4-Mar-12 Time

76 Water Treatment Technology Surface Subsection 4 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

77 Water Treatment Block Flow diagram Raw Water from Wells Raw Water Tank Ion Exchange Column Soft Water BFW Tank BFW to Boilers Ion Exchange Column Boiler Blow Down Tank Boiler BD from Boilers Blow down to Disposal Ion Exchange Regen. Waste Boiler Blow down / Regen. Waste Tank BD / Regen. Waste to Disposal Wells

78 Water Treatment Technology Media Filtering Primary Strong Acid Cation (SAC) Secondary SAC polisher Source water for brine regeneration

79 Water, Landfill waste and waste disposal wells Surface Subsection 5 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

80 Disposal Well One disposal well 105/ W4 Disposal of boiler blowdown and regeneration waste in the Wabamun/Gramina/Calmar/Nisku

81 Disposal Well Rates Disposal Volumes Disposal Pressures Volume (m^3) No Data during this period Dec Jan Mar Apr Jun Jul-11 8-Sep Oct-11 7-Dec Jan Time

82 Sulphur Production Surface Subsection 6 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

83 Sulphur Production No sulphur Production

84 Summary of Environmental Issues Surface Subsection 7 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

85 Environment Update No compliance issues Approval # amendment pending Addition of 3rd Steam Generator Extension of Pilot operating period to December 2017 Expansion of Pad 26 surface lease

86 Compliance Confirmation Surface Subsection 8 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

87 Compliance Confirmation 2 Non-compliance events have occurred since the last performance review December 2010 The maximum bottom hole pressure on the SAGD well pair 102/ W4 was exceeded Self-disclosure document submitted in October 2011 January 2012 The maximum wellhead pressure on the water disposal well 105/ W4 was exceeded Self-disclosure document submitted in February 2012

88 Future Plans Surface Subsection 9 Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

89 Site Plan with Second Well Pair Addition N Planned site expansion

90 Future Plans Pending approval a third OTSG will be installed in 2012, and the surface lease will be expanded A D-51 application has been submitted, and pending approval, the second well pair will be put into operation

91 Appendix Pelican Lake SAGD Pilot Approval 11469A 2011 Annual Performance Presentation

92 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic ECA ECOG A8 BRINT / W4 LSD W4M Conductor: Landed at 20 m KB / 244.5mm KB= mkb GRD= mkb PBTD = mkb Intermediate Casing: mm, kg/m, K-55 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Secondary Intermediate Casing: 88.9 mm, kg/m, J-55 Landed at mkb Cemented to surface with Thermal Cement 6.1m3 of returns Tubing String: 31.8mm, 1.697kg/m, Galvonized Steel Landed at mKB ESP Pump mKB (Pressure/Temperature sensor for fluid level mKB) Perforations: mKB mkb mkb PBTD Cement Top in Secondary Intermediate mkb Intended Purpose: Pressure (Fluid Level), Temperature, W ater quality monitoring of Grand R apids B aquifer

93 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic ECA ECOG A9 BRINT / W4 LSD W4M Conductor: Landed at 20 m KB / 244.5mm KB= mkb GRD= mkb PBTD = mkb Intermediate Casing: mm, kg/m, K-55 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Secondary Intermediate Casing: 88.9 mm, kg/m, J-55 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Tubing String: 31.8mm, 1.697kg/m, Galvonized Steel Landed at mKB ESP Pump mKB (Pressure/Temperature sensor for fluid level mKB) Perforations: mKB mkb mkb PBTD Cement Top in Secondary Intermediate mkb Intended Purpose: Pressure (Fluid Level), Temperature, W ater quality monitoring of Grand Rapids B aquifer

94 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic CVE BRINT / W4 LSD W4M Conductor: Landed at 20 m KB / 406.4mm KB= mkb GRD= mkb PBTD = mkb Surface Casing: mm, kg/m, H-40 Landed at 99.5 mkb Cemented to surface with Thermal Cement 1.0m3 of returns Intermediate Casing: mm, kg/m, L-80 Landed at mkb Cemented to surface with Thermal Cement 4.0m3 of returns Tubing String: 31.8mm, 1.697kg/m, Galvonized Steel Landed at mKB ESP Pump mKB (Pressure/Temperature sensor for fluid level mKB) Perforations: mkb mkb mkb Intended Purpose: Pressure (Fluid Level), Temperature, Water quality monitoring of Grand Rapids B aquifer

95 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic CVE 2C13 BRINT / W4 LSD W4M Conductor: Landed at 20 m KB / 406.4mm KB= mkb GRD= mkb PBTD = mkb Surface Casing: mm, kg/m, H-40 Landed at mkb Cemented to surface with Thermal Cement 1.5m3 of returns Intermediate Casing: mm, kg/m, L-80 Landed at mkb Cemented to surface with Thermal Cement 4.0m3 of returns Tubing String: 31.8mm, 1.697kg/m, Galvonized Steel Landed at mKB ESP Pump mKB (Pressure/Temperature sensor for fluid level mKB) Perforations: mkb mkb mkb Intended Purpose: Pressure (Fluid Level), Temperature, Water quality monitoring of Grand Rapids B aquifer

96 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic ECA ECOG B3 BRINT / W4 LSD W4M Conductor: Landed at 20 m KB / 244.5mm KB= mkb GRD= mkb PBTD = mkb Intermediate Casing: mm, kg/m, K-55 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Secondary Intermediate Casing: 88.9 mm, kg/m, J-55 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Tubing String: 31.8mm, 1.697kg/m, Galvonized Steel Landed at 149.1mKB ESP Pump mKB (Pressure/Temperature sensor for fluid level 149.5mKB) Perforations: mKB PBTD Cement Top in Secondary Intermediate mkb Intended Purpose: Pressure (Fluid Level), Temperature, W ater quality monitoring of Grand Rapids A aquifer

97 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic CVE C12 BRINT / W4 LSD W4M Conductor: Landed at 22 m KB / 244.5mm KB= mkb GRD= mkb PBTD = mkb Intermediate Casing: mm, kg/m, L-80 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Tubing String: 31.8mm, 1.697kg/m, Galvonized Steel Landed at 150.0mKB ESP Pump mKB (Pressure/Temperature sensor for fluid level 150.4mKB) Perforations: mkb Intended Purpose: Pressure (Fluid Level), Temperature, Water quality monitoring of Viking aquifer

98 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic CVE WS2 BRINT F2/ W4 LSD W4M Conductor: Landed at 20 m KB / 406.4mm KB= mkb GRD= mkb PBTD = mkb Intermediate Casing: mm, kg/m, J-55 Landed at 152.0mKB Cemented to surface with Thermal Cement 2.0m3 of returns Tubing String: 88.9mm, 13.84kg/m, J-55 Landed at 140.0mKB PCP 126.4mKB (Pressure/Temperature sensor for fluid level 97.0mKB) Liner: 139.7mm, 29.48kg/m, J mm slot size (15 thou) Set depth mkb (open hole from mkb) Intended Purpose: Pressure (Fluid Level), Temperature, W ater quality monitoring of Quaternary/Tertiary aquifer (well pumping consistantly as it provides fresh water for current Wabiskaw polymer flood in the area)

99 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic 2003 Camp Water Supply Well No NE W4 LSD W4M PBTD = mkb Intermediate Casing: mm, Plastic (PVC) Landed at 112.2mKB Bentonite Chips/Tablets to mKB Tubing String: 31.75mm, Plastic (PVC) Landed at 140.0mKB ESP 100.6mKB (Pressure/Temperature sensor for fluid level 95.0mKB) Liner: 152.4mm, Stainless Steel 0.381mm slot size (15 thou) Set depth mKB Intended Purpose: Pressure (Fluid Level), Temperature, Water quality monitoring of Quaternary aquifer (well pumping consistantly as it provides fresh water Pelican Lake Camp)

100 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic CVE BRINT / W4 LSD W4M Conductor: Landed at 22 m KB / 406.4mm KB= mkb GRD= mkb PBTD = mkb Surface Casing: mm, kg/m, J-55 Landed at 69.5 mkb Cemented to surface with Thermal Cement 2.0m3 of returns Intermediate Casing: mm, kg/m, L-80 Landed at mkb Cemented to surface with Thermal Cement 4.5m3 of returns Sensors: 8 Piezometers (Pressure) and Thermocouples (Temperature) Cemented to Casing Pressure/Temperature Sensor Set Depths: mkb mkb mkb mkb mkb mkb mkb mkb Intended Purpose: Pressure and Temperature through Grand Rapids A steam chamber

101 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic CVE 2B BRINT / W4 LSD W4M Conductor: Landed at 20 mkb / 406.4mm KB= mkb GRD= mkb PBTD = mkb Surface Casing: mm, kg/m, J-55 Landed at mkb Cemented to surface with Thermal Cement 3.0m3 of returns Intermediate Casing: mm, kg/m, L-80 Landed at mkb Cemented to surface with Thermal Cement 4.0m3 of returns Sensors: 8 Piezometers (Pressure) and Thermisters (Temperature) Cemented to Casing Pressure is calculated from capillary tubes set 60m below each piezometer/thermister gauge Temperature is calculated from the set depth of the piezometer/thermister gauge Pressure Measurement Depths: mkb mkb mkb mkb mkb mkb mkb mkb Intended Purpose: Pressure and Temperature through Grand Rapids A steam chamber

102 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic ECA ECOG B5 BRINT / W4 LSD W4M Conductor: Landed at 20 mkb / 244.5mm KB= mkb GRD= mkb PBTD = mkb Intermediate Casing: mm, kg/m, K-55 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Secondary Intermediate Casing: 88.9 mm, kg/m, J-55 Landed at mkb Cemented to surface with Thermal Cement 1.5m3 of returns Thermocouple String: WIKA 20 Point Thermocouple Landed mkb Each Thermocouple is 2 m apart along the landing depth length PBTD Cement Top in Secondary Intermediate mkb Intended Purpose: Temperature monitoring of Grand Rapids A steam chamber

103 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic ECA ECOG C13 BRINT / W4 LSD W4M Conductor: Landed at 23 mkb / 244.5mm KB= mkb GRD= mkb PBTD = mkb Intermediate Casing: mm, kg/m, L-80 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Thermocouple String: WIKA 20 Point Thermocouple Landed mkb Each Thermocouple is 2 m apart along the landing depth length Intended Purpose: Temperature monitoring of Grand Rapids A steam chamber

104 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic CVE BRINTNELL / W4 LSD W4M Conductor: Landed at 24.2 m KB / 406.4mm KB= mkb GRD= mkb PBTD = mkb Surface Casing: mm, kg/m, H-40 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Intermediate Casing: mm, kg/m, L-80 Landed at mkb Cemented to surface with Thermal Cement 1.0m3 of returns Thermocouple String: WIKA 20 Point Thermocouple Landed mkb Each Thermocouple is 2 m apart along the landing depth length Intended Purpose: Temperature monitoring of Grand Rapids A steam chamber

105 Appendix: Pelican Lake SAGD Pilot Observation Wellbore Schematic CVE B6 BRINT / W4 LSD W4M Conductor: Landed at 25 m KB / 244.5mm KB= mkb GRD= mkb PBTD = mkb Intermediate Casing: mm, kg/m, L-80 Landed at mkb Cemented to surface with Thermal Cement 2.0m3 of returns Tubing String: 73.0 mm, 9.67kg/m, J-55 Landed at mKB Packer to isolate zones landed at mKB Pressure/Temperature Sensor banded to tubing at 208.2mKB (above packer) Pressure/Temperature Sensor deployed through tubing landed at 241.6mKB (below packer) Perforations: mkb mkb Intended Purpose: Pressure (Fluid Level) and Temperature monitoring of Grand Rapids A zone

106 Appendix: Pelican Lake SAGD Pilot Observation wells data Table : Thermocouples in Observation wells UWI Location from SAGD well pair toe (m) Lateral Distance (m) 102/ W4/ / W4/ / W4/ Table : Piezometers in Observation wells UWI Location from SAGD well pair toe (m) Lateral Distance (m) 103/ W4/ / W4/ / W4/

107 Appendix: Pelican Lake SAGD Pilot Groundwater Observation wells data Table : Groundwater Observation wells UWI Perf. Interval TVD (m) Zone Lateral Difference from well pair (m) 102/ W4/ GR A 408 E 103/ W4/ VIKING 468 N 100/ W4/ / W4/ / W4/ / W4/ GR B GR B GR B GR B 252 N 179 W 20 E 10 E

108 Appendix: Pelican Lake SAGD Pilot Lean Zone Pressures Weekly Report- Lean Zone pressures [Generated from trend :34:37 AM] OW-09PT100A1 Daily Avg [kpa] OW-14PT100A8 Daily Avg [kpa] OW-16PT100A8 Daily Avg [kpa] OW-16PT100A8 Daily Avg [kpa] OW-09PT100A1 Daily Avg [kpa] OW-14PT100A8 Daily Avg [kpa] Apr Jul Oct Jan 2012

109 Appendix: Pelican Lake SAGD Pilot Downhole Pressures of Producer and Injector Injector SAGD-SW026-PIT2604 Daily Avg [kpa] [2 Pen] Historical Trend Producer SAGD-SW026-PIT2607 Daily Avg [kpa] kpa Apr Jul Oct Jan 2012

Pelican Lake SAGD Pilot

Pelican Lake SAGD Pilot Pelican Lake SAGD Pilot AER Approval 11469B April 16, 2015 Annual Update January 1, 2014 December 31, 2014 Disclaimer This Cenovus Pelican Lake SAGD Pilot January 1, 2014 to December 31, 2014 Update (

More information

Seal Main HCSS Pilot Subsurface Review

Seal Main HCSS Pilot Subsurface Review Seal Main HCSS Pilot Subsurface Review Subsurface Agenda 1. Background 2. Geology 3. Drilling and Completions 4. Artificial Lift 5. Well Instrumentation 6. 4D Seismic 7. Scheme Performance 8. Future Plans

More information

Air injection & displacement for recovery with oil horizontal (AIDROH) project Approval #11618 Performance presentation

Air injection & displacement for recovery with oil horizontal (AIDROH) project Approval #11618 Performance presentation Air injection & displacement for recovery with oil horizontal (AIDROH) project Approval #11618 Performance presentation ERCB offices Calgary February 2013 Advisory This document contains forward-looking

More information

Harmon Valley South HCSS Pilot Approval Annual Performance Presentation

Harmon Valley South HCSS Pilot Approval Annual Performance Presentation Harmon Valley South HCSS Pilot Approval 11895 Annual Performance Presentation 11-Feb-2015 Subsurface Agenda 1. Background 2. Geology 3. Drilling and Completions 4. Artificial Lift 5. Well Instrumentation

More information

Seal Main HCSS Pilot Approval Annual Performance Presentation

Seal Main HCSS Pilot Approval Annual Performance Presentation Seal Main HCSS Pilot Approval 11377 Annual Performance Presentation 11-Feb-2015 Agenda Introductions Seal Main Horizontal Cyclic Steam Stimulation (HCSS) Pilot Subsurface Surface Harmon Valley South HCSS

More information

Air injection & displacement for recovery with oil horizontal (AIDROH) project Approval #11618 Performance presentation

Air injection & displacement for recovery with oil horizontal (AIDROH) project Approval #11618 Performance presentation Air injection & displacement for recovery with oil horizontal (AIDROH) project Approval #11618 Performance presentation AER Office Calgary March 2014 Advisory This document contains forward-looking information

More information

January 2011 to September 2012 Kirby ERCB Directive 54 Annual Performance Presentation

January 2011 to September 2012 Kirby ERCB Directive 54 Annual Performance Presentation January 2011 to September 2012 Kirby ERCB Directive 54 Annual Performance Presentation September 26, 2012 Premium Value Defined Growth Independent OUTLINE PAGE # Kirby Approval 11475 (South) 5-69 Background

More information

Annual Performance Presentation

Annual Performance Presentation Annual Performance Presentation In Situ Oil Sands Schemes 9673 / 10147 / 10423 / 10787 March 2014 Premium Value Defined Growth Independent Agenda Current Approvals Geological Overview Drilling, Completions,

More information

Annual Performance Presentation

Annual Performance Presentation Annual Performance Presentation In Situ Oil Sands Schemes 9673 / 10147 / 10423 / 10787 April 2017 Premium Value Defined Growth Independent Agenda Current Approvals Geological Overview Drilling, Completions,

More information

Cenovus EnCAID approval #10440J Performance presentation

Cenovus EnCAID approval #10440J Performance presentation Cenovus EnCAID approval #10440J Performance presentation Claire Hong Staff Production/Completion Engineer Dubert Gutierrez Sr. Reservoir Engineer AER offices Calgary February 2015 Advisory This document

More information

VALUE I GROWTH I INNOVATION. AER 2014 Annual Presentation. Saleski Thermal Pilot AER Approval 11337

VALUE I GROWTH I INNOVATION. AER 2014 Annual Presentation. Saleski Thermal Pilot AER Approval 11337 VALUE I GROWTH I INNOVATION AER 2014 Annual Presentation Saleski Thermal Pilot AER Approval 11337 September 2014 Agenda Background Project Overview Geological Update Scheme Performance Facility Performance

More information

Murphy Oil Company LTD.

Murphy Oil Company LTD. Murphy Oil Company LTD. Seal Polymer Pilot Scheme Approval No. 11320B Annual ERCB Progress Presentation June 3, 2013 1 Agenda Subsurface Surface Conclusions 2 Subsurface Background Geology Drilling & Completions

More information

Pengrowth Energy Corporation Lindbergh SAGD Project 2013 Annual Performance Presentation Scheme Approval No. 6410I.

Pengrowth Energy Corporation Lindbergh SAGD Project 2013 Annual Performance Presentation Scheme Approval No. 6410I. Pengrowth Energy Corporation Lindbergh SAGD Project 2013 Annual Performance Presentation Scheme Approval No. 6410I October 1, 2013 Introduction and Overview Introduction Subsurface Issues Related to Resource

More information

2018 Directive 054 Performance Presentation

2018 Directive 054 Performance Presentation 2018 Directive 054 Performance Presentation Seal Scheme Approval No. 11320F September 2018 Agenda Subsurface 1. Overview 2. Geology / Geoscience 3. Drilling and Completions 4. Scheme Performance 5. Injection

More information

JAPAN CANADA OIL SANDS LTD. HANGINGSTONE DEMO PROJECT 2004 Presented on Monday, March 7, 2005 Presentation Outline

JAPAN CANADA OIL SANDS LTD. HANGINGSTONE DEMO PROJECT 2004 Presented on Monday, March 7, 2005 Presentation Outline Thermal In-Situ Scheme Progress Report JAPAN CANADA OIL SANDS LTD. HANGINGSTONE DEMO PROJECT 2004 Presented on Monday, March 7, 2005 Presentation Outline 1. Introduction Project Background, Activity Summary

More information

HILDA LAKE SAGD PILOT PERFORMANCE SUMMARY 2004 AEUB PRESENTATION BLACKROCK VENTURES INC

HILDA LAKE SAGD PILOT PERFORMANCE SUMMARY 2004 AEUB PRESENTATION BLACKROCK VENTURES INC HILDA LAKE SAGD PILOT PERFORMANCE SUMMARY 2004 AEUB PRESENTATION BLACKROCK VENTURES INC FEBRUARY, 2004 HILDA LAKE SAGD PILOT PERFORMANCE SUMMARY 2003-2004 PRESENTATION OUTLINE PRODUCTION SUMMARY P1 AND

More information

Sunshine Oilsands Ltd. BA Code A2TF WEST ELLS SAGD. Scheme No E AER In Situ Performance Presentation 2017

Sunshine Oilsands Ltd. BA Code A2TF WEST ELLS SAGD. Scheme No E AER In Situ Performance Presentation 2017 Sunshine Oilsands Ltd. BA Code A2TF WEST ELLS SAGD Scheme No. 11764E AER In Situ Performance Presentation 2017 Presenters Qi Jiang, P. Eng., Ph.D. Chief Technology Officer Eugene Dembicki, M.Sc., P.Geol.

More information

2017 Directive 54 Performance Presentation

2017 Directive 54 Performance Presentation 2017 Directive 54 Performance Presentation Seal Scheme Approval No. 11320E September 2017 Agenda Subsurface 1. Overview 2. Geology / Geoscience 3. Drilling and Completions 4. Scheme Performance 5. Injection

More information

6 DRILLING AND COMPLETIONS

6 DRILLING AND COMPLETIONS Cenovus FCCL Ltd. 6-1 Drilling and Completions 6 DRILLING AND COMPLETIONS 6.1 OVERVIEW This section contains information about the drilling and completion of wells within the CLTP. Well counts, locations

More information

Annual Surmont SAGD Performance Review Approvals 9426, 11596, and April 6, 2016 Calgary, Alberta, Canada

Annual Surmont SAGD Performance Review Approvals 9426, 11596, and April 6, 2016 Calgary, Alberta, Canada Annual Surmont SAGD Performance Review Approvals 9426, 11596, and 9460 April 6, 2016 Calgary, Alberta, Canada Introduction, Overview and Highlights Subsection 3.1.1 (1) Ownership and Approvals Ownership

More information

Outline of Presentation

Outline of Presentation 4 th Wellbore Integrity Network Meeting Monitoring i of Wellbore Performance at Penn West CO 2 -EOR Rick Chalaturnyk Geological Storage Research Group Department of Civil and Environmental Engineering

More information

VSD is a commercially proven technology for bitumen recovery that is used worldwide and in Western Canada by other operators.

VSD is a commercially proven technology for bitumen recovery that is used worldwide and in Western Canada by other operators. RECOVERY PROCESS Section 4.1 APPLICATION FOR APPROVAL OF THE CARMON CREEK PROJECT VOLUME 1: PROJECT DESCRIPTION SELECTED RECOVERY PROCESS 4.1.1 SELECTION BASIS Vertical steam drive (VSD), complemented

More information

Penn West Petroleum Ltd. Seal Main HCSS Pilot and Harmon Valley South Annual ERCB Progress Presentation

Penn West Petroleum Ltd. Seal Main HCSS Pilot and Harmon Valley South Annual ERCB Progress Presentation Penn West Petroleum Ltd. Seal Main HCSS Pilot and Harmon Valley South Annual ERCB Progress Presentation 2013-01-17 Advisory General: This presentation is for information purposes only and is not intended

More information

History Matching Field Results from a SAGD / Light Hydrocarbon Process (SAGD+ TM )

History Matching Field Results from a SAGD / Light Hydrocarbon Process (SAGD+ TM ) WHOC12-442 History Matching Field Results from a SAGD / Light Hydrocarbon Process (SAGD+ TM ) E.C. LAU, M.D. JOHNSON, T. LAU Connacher Oil & Gas Limited This paper has been selected for presentation and/or

More information

EnCana Christina Lake In Situ Oil Sands Scheme 2007 Update

EnCana Christina Lake In Situ Oil Sands Scheme 2007 Update EnCana Christina Lake In Situ Oil Sands Scheme 2007 Update June 8, 2007 June 8, 2007 Agenda Introduction Geology and Geophysics Project Performance Operations and Water Compliance Gas Over Bitumen SAP

More information

Alberta Energy Regulator Suite 1000, Street SW Calgary, Alberta T2P 0R4 Attention: Steve Thomas, P.Eng., Section Leader In-Situ Oil Sands

Alberta Energy Regulator Suite 1000, Street SW Calgary, Alberta T2P 0R4 Attention: Steve Thomas, P.Eng., Section Leader In-Situ Oil Sands East Tower, 5 th Ave Place Suite 800, 425-1 st Street S.W. Calgary, Alberta T2P 3L8 Tel: 403-750-0810 Fax: 403-263-0767 www.laricinaenergy.com August 7, 2013 Alberta Energy Regulator Suite 1000, 250 5

More information

Groundwater Supply Development at Canadian Natural Resources Limited s In Situ Oil Sands Operations

Groundwater Supply Development at Canadian Natural Resources Limited s In Situ Oil Sands Operations THE PREMIUM VALUE DEFINED GROWTH INDEPENDENT Groundwater Supply Development at Canadian Natural Resources Limited s In Situ Oil Sands Operations Overview, Challenges and Lessons Learned Dave Edwards, P.Geol.

More information

Thermal In-Situ Scheme Progress Report for 2016 Japan Canada Oil Sands Limited Hangingstone. Approval No (Demonstration Project)

Thermal In-Situ Scheme Progress Report for 2016 Japan Canada Oil Sands Limited Hangingstone. Approval No (Demonstration Project) Thermal In-Situ Scheme Progress Report for 2016 Japan Canada Oil Sands Limited Hangingstone Approval No. 8788 (Demonstration Project) 1. Background Hangingstone Expansion Project 2. Subsurface Geosciences

More information

2013 PERFORMANCE PRESENTATION (SUBSURFACE) LONG LAKE MARCH 19, 2014

2013 PERFORMANCE PRESENTATION (SUBSURFACE) LONG LAKE MARCH 19, 2014 2013 PERFORMANCE PRESENTATION (SUBSURFACE) LONG LAKE MARCH 19, 2014 PURPOSE This presentation contains information to comply with Alberta Energy Regulator s Directive 054 Performance Presentations, Auditing,

More information

Progressing C-SAGD recovery of bitumen from the Grosmont D reservoir

Progressing C-SAGD recovery of bitumen from the Grosmont D reservoir Progressing C-SAGD recovery of bitumen from the Grosmont D reservoir LARICINA ENERGY Steve Brand P. Eng. WHOC15-280 Organized by: Outline Project overview 1D experience and knowledge gained Early cycle

More information

PENGROWTH ENERGY CORPORATION LINDBERGH SAGD PROJECT 2017 ANNUAL PERFORMANCE PRESENTATION SCHEME APPROVAL 6410P

PENGROWTH ENERGY CORPORATION LINDBERGH SAGD PROJECT 2017 ANNUAL PERFORMANCE PRESENTATION SCHEME APPROVAL 6410P PENGROWTH ENERGY CORPORATION LINDBERGH SAGD PROJECT 2017 ANNUAL PERFORMANCE PRESENTATION SCHEME APPROVAL 6410P 2018 01 17 SUBSURFACE ISSUES: TABLE OF CONTENTS 1. Brief Background of the Scheme 2. Geology/Geoscience

More information

Telephone Lake project

Telephone Lake project Telephone Lake project Cenovus Energy Inc. is a Canadian oil company. We re committed to applying fresh, progressive thinking to safely and responsibly unlock energy resources the world needs. Our operations

More information

2012 Annual Performance Presentation McKay River Thermal Project

2012 Annual Performance Presentation McKay River Thermal Project 2012 Annual Performance Presentation McKay River Thermal Project Outline Introductions 3.1.1 Subsurface Overview Related to Resource Evaluation and Recovery 3.1.2 Surface Operations, Compliance, and Issues

More information

Monitoring Plan for a Cyclic Steam Stimulation (CSS) Pilot Test in Orinoco Oil Belt, Venezuela

Monitoring Plan for a Cyclic Steam Stimulation (CSS) Pilot Test in Orinoco Oil Belt, Venezuela Monitoring Plan for a Cyclic Steam Stimulation (CSS) Pilot Test in Orinoco Oil Belt, Venezuela Repsol Technology Center (CTR), Madrid PEA 2016 Aberdeen, Scotland, UK 1. What is Pilot Test? Why monitoring

More information

Orion In Situ Oil Sands 2015 Progress Update. Presented May 25, 2016

Orion In Situ Oil Sands 2015 Progress Update. Presented May 25, 2016 Orion In Situ Oil Sands 2015 Progress Update Presented May 25, 2016 Agenda Introduction Geoscience Scheme Performance Surface Operations Compliance Future Plans 2 Project Location Osum Production Corp.

More information

Overview of Completions

Overview of Completions Overview of Completions PESA Oil & Gas 101 21 May 2015 Nick Clem, Applications Engineering Director Ganesh Subbaraman, Engineering Manager Outline Background Drivers affecting selection of completion types

More information

Timber Creek Field Study for Improving Waterflooding

Timber Creek Field Study for Improving Waterflooding The 2 nd Minnelusa Workshop of EORI Timber Creek Field Study for Improving Waterflooding Shaochang Wo Gillette, Wyoming June 4, 2014 Project Summary and Timeline A collaborative study between EORI and

More information

William Wilmot Matrix Solutions Inc. 118, Avenue S.W., Calgary, Alberta, Canada

William Wilmot Matrix Solutions Inc. 118, Avenue S.W., Calgary, Alberta, Canada Hydrogeologic Assessment in Support of the Development of the Peace River Oil Sands Deposit: A Case Study Concerning a Pilot-Scale in-situ SAGD Operation William Wilmot Matrix Solutions Inc. 118, 319-2

More information

Well Abandonment Presentation West Central Stakeholders Rocky Mountain House. November 19, 2013

Well Abandonment Presentation West Central Stakeholders Rocky Mountain House. November 19, 2013 Well Abandonment Presentation West Central Stakeholders Rocky Mountain House November 19, 2013 Why are Wells Abandoned? The well has reached the end of its productive life and is no longer economical.

More information

MAY 2016 ALLAN ALBERTSON, P.ENG., TYLER HALLMAN, P.ENG.

MAY 2016 ALLAN ALBERTSON, P.ENG., TYLER HALLMAN, P.ENG. MULTILATERAL WELLS CAN BE EMPLOYED IN HEAVY OIL FORMATIONS REQUIRING ADDITIONAL RESERVOIR EXPOSURE TO ACHIEVE TARGET PRODUCTION RATES AND IMPROVE ECONOMICS MAY 2016 ALLAN ALBERTSON, P.ENG., TYLER HALLMAN,

More information

Annual Surmont SAGD Performance Review Approval April 4, 2018 Calgary, Alberta, Canada

Annual Surmont SAGD Performance Review Approval April 4, 2018 Calgary, Alberta, Canada Annual Surmont SAGD Performance Review Approval 9426 April 4, 2018 Calgary, Alberta, Canada Table of Contents AER Scheme Approval #9426 Subsurface Subsection 3.1.1 (1): Introduction, Overview and Highlights

More information

SPE Abstract. Introduction

SPE Abstract. Introduction SPE 149944 Succesful Application of Metal PCP Rechnology to Maximize Oil Recovery in SAGD Process R. Arystanbay, SPE, W. Bae, SPE, Huy X. Nguyen, SPE, Sejong University; S. Ryou, SPE, W. Lee, T. Jang,

More information

A Comparison Study between the Newly Developed Vertical Wells Steam Assisted Gravity Drainage and the Conventional SAGD Process

A Comparison Study between the Newly Developed Vertical Wells Steam Assisted Gravity Drainage and the Conventional SAGD Process Engineering, 217, 9, 575-59 http://www.scirp.org/journal/eng ISSN Online: 1947-394X ISSN Print: 1947-3931 A Comparison Study between the Newly Developed Vertical Wells Steam Assisted Gravity Drainage and

More information

Proposed East Manson Unit No. 5 Application for Enhanced Oil Recovery Waterflood Project Middle Bakken East Manson, Manitoba

Proposed East Manson Unit No. 5 Application for Enhanced Oil Recovery Waterflood Project Middle Bakken East Manson, Manitoba Proposed East Manson Unit No. 5 Application for Enhanced Oil Recovery Waterflood Project Middle Bakken East Manson, Manitoba April 23, 2015 Crescent Point Resources Partnership Table of Contents Section

More information

Well-Based Monitoring

Well-Based Monitoring Rick Chalaturnyk Petroleum Geomechanics Research Group Department of Civil and Environmental Engineering University of Alberta Well-Based Monitoring IEA MONITORING and VERIFICATION NETWORK Meeting 2006

More information

New Acid Stimulation Treatment to Sustain Production Los Angeles Downtown Oil Field U.S. Department of Energy Grant No.

New Acid Stimulation Treatment to Sustain Production Los Angeles Downtown Oil Field U.S. Department of Energy Grant No. New Acid Stimulation Treatment to Sustain Production Los Angeles Downtown Oil Field U.S. Department of Energy Grant No. DE-FG26-99BC15247 Richard C. Russell St. James Oil Corporation Abstract New Acid

More information

RDS Aberdeen. Thursday, May-05-11

RDS Aberdeen. Thursday, May-05-11 Heavy Oil Presentation for RDS Aberdeen Thursday, May-05-11 Heavy Oil Presentation for RDS Aberdeen Conclusions Overview of Heavy Oil Growth Reserves Growth in Heavy Oil What is applicable to North Sea

More information

Innovative Energy Technologies Program

Innovative Energy Technologies Program Alberta Department of Energy Innovative Energy Technologies Program BRINTNELL FIELD ORSETAIL POLYMER FLOOD PILOT PROJECT Canadian Natural Resources Limited Annual Report June 30th, 2009 Innovative Energy

More information

Husky Oil Operations Limited Tucker Thermal Project Commercial Scheme #9835

Husky Oil Operations Limited Tucker Thermal Project Commercial Scheme #9835 Husky Oil Operations Limited Tucker Thermal Project Commercial Scheme #9835 Annual Performance Presentation Energy Resources Conservation Board May 23 rd, 2013 1 3.1.1. Subsurface Issues Table of Contents

More information

Suncor MacKay River Project 2017 AER Performance Presentation. Reporting Period: September 1, 2016 to August 31, 2017

Suncor MacKay River Project 2017 AER Performance Presentation. Reporting Period: September 1, 2016 to August 31, 2017 Suncor MacKay River Project 2017 AER Performance Presentation Reporting Period: September 1, 2016 to August 31, 2017 Table of Contents Sub Surface Presentation Surface Presentation 1 Suncor MacKay River

More information

Recovery Process - Cold Heavy Oil

Recovery Process - Cold Heavy Oil Recovery Process - Cold Heavy Oil CHOPS (Cold Heavy Oil Production with Sand) CHOPS is a heavy oil recovery technique where the reservoir sand is deliberately produced to improve reservoir performance.

More information

Examining Reservoir Water Retention During SAGD. Thursday January 31 st, 2013

Examining Reservoir Water Retention During SAGD. Thursday January 31 st, 2013 Examining Reservoir Water Retention During SAGD Thursday January 31 st, 2013 Forward-looking information and advisories This presentation contains "forward-looking information" within the meaning of applicable

More information

Grizzly Oil Sands ULC

Grizzly Oil Sands ULC May River SAGD Project A-1 Appendix A Table A-1 ERCB Draft 23 Oil Sands Project Applications (ERCB 2013) 3 GENERAL APPLICATION REQUIREMENTS 3.3 Project Description Requirements 3.3.1 Applicant and the

More information

Draft Directive 051. Wellbore Injection Requirements. Contents. Revised edition August 14, Replaces previous edition issued March 1994.

Draft Directive 051. Wellbore Injection Requirements. Contents. Revised edition August 14, Replaces previous edition issued March 1994. Draft Directive 051 Revised edition August 14, 2012. Replaces previous edition issued March 1994. Wellbore Injection Requirements The Energy Resources Conservation Board (ERCB/Board) has approved this

More information

Suncor MacKay River Project 2017 AER Performance Presentation. Reporting Period: September 1, 2017 to August 31, 2018

Suncor MacKay River Project 2017 AER Performance Presentation. Reporting Period: September 1, 2017 to August 31, 2018 Suncor MacKay River Project 2017 AER Performance Presentation Reporting Period: September 1, 2017 to August 31, 2018 Table of Contents Sub Surface Presentation Surface Presentation Appendix A: 1 Suncor

More information

Sand Control. Gravel packing is the oldest and simplest method of sand control. Works in both on and off shore wells.

Sand Control. Gravel packing is the oldest and simplest method of sand control. Works in both on and off shore wells. Sand Control Marine deposited sands, most oil and gas reservoir sands, are often cemented with calcareous or siliceous minerals and may be strongly consolidated. In contrast, Miocene or younger sands are

More information

IMPERIAL COLLEGE LONDON. Department of Earth Science and Engineering. Centre for Petroleum Studies

IMPERIAL COLLEGE LONDON. Department of Earth Science and Engineering. Centre for Petroleum Studies IMPERIAL COLLEGE LONDON Department of Earth Science and Engineering Centre for Petroleum Studies Evaluation of the Design of Liner Deployed Inflow/Outflow Control Devices for SAGD Wells By Elena Spronk

More information

Steam Injection. Dr. Helmy Sayyouh Petroleum Engineering Cairo University

Steam Injection. Dr. Helmy Sayyouh Petroleum Engineering Cairo University Steam Injection Dr. Helmy Sayyouh Petroleum Engineering Cairo University 1 Increasing Temperature Lowers Viscosity... Fig. 11-1 2 Single-Parameter Viscosity Correlation Fig. 11-5 Two-parameter correlation

More information

Thermal Recovery Status and Development Prospect for Heavy Oil in China

Thermal Recovery Status and Development Prospect for Heavy Oil in China UNITAR Centre for Heavy Crude and Tar Sands 1998 1 No.1998.198 Thermal Recovery Status and Development Prospect for Heavy Oil in China Liu Wenzhang Research Institute of Petroleum Exploration and Development,

More information

For contact information, please visit our website:

For contact information, please visit our website: Weatherford s Integrated Laboratory Services (ILS) effectively combines the experience and expertise of leaders in the oil and gas service industry by integrating their considerable abilities under one

More information

Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency -

Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency - Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency - Nov-29, 2017 JAPEX (Japan Petroleum Exploration Co., Ltd) Canada Oil Sands Project Dept. Tanetomo (Tom) Izumi Japan

More information

Jared Wynveen, P. Eng McDaniel & Associates Consultants Ltd. 2014

Jared Wynveen, P. Eng McDaniel & Associates Consultants Ltd. 2014 Jared Wynveen, P. Eng McDaniel & Associates Consultants Ltd. 2014 Subcool Basics Idealized Subcool Real World Subcool Subcool Visualizations Subcool case study Subcool Management - New Technology Outflow

More information

Seal 9 barrier verification by xlot and Communication test

Seal 9 barrier verification by xlot and Communication test Seal 9 barrier verification by xlot and Communication test P&A Forum 18 th Oktober 2017 Daniel Tomczak and Roar Flatebø Content Valhall overview and P&A Strategy Qualifying External Barriers Coil Tubing

More information

Disposal and Injection Well Requirements

Disposal and Injection Well Requirements Directive PNG008 March 29, 2018 Revision 1.1 Governing Legislation: Act: The Oil and Gas Conservation Act Regulation: The Oil and Gas Conservation Regulations, 2012 Order: 101/18 Record of Change Revision

More information

Flow Testing Results from Habanero EGS Project

Flow Testing Results from Habanero EGS Project Proceedings Australian Geothermal Energy Conferences 2013 Brisbane, Australia, 14-15 November 2013 Flow Testing Results from Habanero EGS Project Robert Hogarth, Heinz Holl and Andrew McMahon Geodynamics

More information

Insulated Tubulars for use with Thermal Oil Recovery Processes

Insulated Tubulars for use with Thermal Oil Recovery Processes Insulated Tubulars for use with Thermal Oil Recovery Processes Presented by: Maurice Batallas, Shaw Pipe Protection Ltd. Project Team: Madhu Desai, Sanjay Shah, Hamid Sadeghi, Sasan Zadeh, Afolabi Lowrie,

More information

Measurement Schematics & Facility Delineation Requirements Required by September 11, 2014

Measurement Schematics & Facility Delineation Requirements Required by September 11, 2014 Alberta Energy Regulator (AER) Directive 017 - Measurement Requirements for Oil and Gas Operations Version - September 2012 Measurement Schematics & Facility Delineation Requirements Required by September

More information

Effects of Well Placement using Multi- Segmented Wells in a Full Field Thermal Model for SAGD: Athabasca Oil Sands

Effects of Well Placement using Multi- Segmented Wells in a Full Field Thermal Model for SAGD: Athabasca Oil Sands PAPER 2008-464 Effects of Well Placement using Multi- Segmented Wells in a Full Field Thermal Model for SAGD: Athabasca Oil Sands F. AKRAM Schlumberger Canada Limited This paper has been selected for presentation

More information

Tailings Storage and Heap Leaching in a Combined Facility A First for the Mining Industry

Tailings Storage and Heap Leaching in a Combined Facility A First for the Mining Industry Tailings Storage and Heap Leaching in a Combined Facility A First for the Mining Industry Thomas F. Kerr, P.E., Knight Piésold and Co. Michael G. Skurski, P.E., Newmont Mining Co. Peter D. Duryea, Ph.D.,

More information

AN OVERVIEW OF THE LOW AND HIGH TEMPERATURE WATER-OIL RELATIVE PERMEABILITY FOR OIL SANDS FROM DIFFERENT FORMATIONS IN WESTERN CANADA

AN OVERVIEW OF THE LOW AND HIGH TEMPERATURE WATER-OIL RELATIVE PERMEABILITY FOR OIL SANDS FROM DIFFERENT FORMATIONS IN WESTERN CANADA SCA2014-066 1/6 AN OVERVIEW OF THE LOW AND HIGH TEMPERATURE WATER-OIL RELATIVE PERMEABILITY FOR OIL SANDS FROM DIFFERENT FORMATIONS IN WESTERN CANADA U. Romanova 1, M. Piwowar and T. Ma Weatherford Laboratories

More information

Technological Enhancement of PC Pumps for Heavy Oil Production. Courtney Ward P.Eng.

Technological Enhancement of PC Pumps for Heavy Oil Production. Courtney Ward P.Eng. Technological Enhancement of PC Pumps for Heavy Oil Production Courtney Ward P.Eng. April 28, 2008 Development and Test Area * Lloydminster 1 History Initial PC Pump Installations Initial install occurred

More information

ESP experiences on the Mature Dunlin Field An integrated approach to optimise Field Performance

ESP experiences on the Mature Dunlin Field An integrated approach to optimise Field Performance ESP experiences on the Mature Dunlin Field An integrated approach to optimise Field Performance R Heath Fairfield Energy Limited J Cardozo - Schlumberger Content Reservoir History Block 10 Redevelopment

More information

SECTION 7.0 WATER SOURCE MANAGEMENT TABLE OF CONTENTS

SECTION 7.0 WATER SOURCE MANAGEMENT TABLE OF CONTENTS SECTION 7.0 WATER SOURCE MANAGEMENT TABLE OF CONTENTS PAGE 7.0 WATER SOURCE MANAGEMENT... 7-1 7.1 Introduction... 7-1 7.2 Dewatering... 7-1 7.3 Domestic Water Supply... 7-2 7.4 Process Water Supply...

More information

F. Kabus, G. Möllmann, F. Hoffmann and J. Bartels GTN Geothermie Neubrandenburg GmbH, Seestrasse 7A, Neubrandenburg, Germany

F. Kabus, G. Möllmann, F. Hoffmann and J. Bartels GTN Geothermie Neubrandenburg GmbH, Seestrasse 7A, Neubrandenburg, Germany The Tenth International Conference on Thermal Energy Storage TWO-YEAR EXPERIENCE IN THE OPERATION OF AN AQUIFER THERMAL ENERGY STORE BASED ON SURPLUS HEAT ARISING FROM A GAS AND STEAM COGENERATION PLANT

More information

California Dreamin. on such a winter s day. The Mommas and the Papas

California Dreamin. on such a winter s day. The Mommas and the Papas Stuart M. Heisler, P.E. Senior Technical Director PARSONS Bakersfield, California Michael Dejak, P. Eng. VP Business Development Eco-Tec Inc. Calgary, Alberta Presentation for Canadian Heavy Oil Association

More information

Thermal In-Situ Scheme Progress Report for 2015 Japan Canada Oil Sands Limited Hangingstone

Thermal In-Situ Scheme Progress Report for 2015 Japan Canada Oil Sands Limited Hangingstone Thermal In-Situ Scheme Progress Report for 2015 Japan Canada Oil Sands Limited Hangingstone Approval No. 8788 (Demonstration Project) Presented on February 23, 2016 1. Background Hangingstone Expansion

More information

ATHABASCA OIL CORPORATION AER LEISMER UPDATE

ATHABASCA OIL CORPORATION AER LEISMER UPDATE ATHABASCA OIL CORPORATION AER LEISMER UPDATE May 2017 INTRODUCTION 2 SUBSURFACE o o o Project Description & Status Geoscience 4-D Seismic & Monitoring Marcus Hoehn o o o o Well Design & Instrumentation

More information

Module 3 Design and Construction of Water Wells. For more information refer to the Water Wells That Last video (Part I Planning and Construction).

Module 3 Design and Construction of Water Wells. For more information refer to the Water Wells That Last video (Part I Planning and Construction). For more information refer to the Water Wells That Last video (Part I Planning and Construction). For more information see Module 1 "Understanding Groundwater" and Module 2 "Planning Your Water System".

More information

SOUTH CASPER CREEK: Steamflood Pilot Implementation

SOUTH CASPER CREEK: Steamflood Pilot Implementation SOUTH CASPER CREEK: Steamflood Pilot Implementation By: Jeremy Wagner, Citation Oil and Gas Corp. 2010 Wyoming EOR/IOR Conference Jackson, WY Sept 13-14, 2010 SCC South Casper Creek (SCC) brief overview

More information

CONDENSATION INDUCED WATER HAMMER

CONDENSATION INDUCED WATER HAMMER CONDENSATION INDUCED WATER HAMMER RISKS AND ISSUES ASSOCIATED WITH SAGD OPERATIONS Jeff Dancey, P. Eng. Baker Engineering and Risk Consultants, Inc. OUTLINE CONDENSATION INDUCED WATER HAMMER (CIWH) - EXPLANATION

More information

This presentation is based upon work supported by the Department of Energy National Energy Technology Laboratory under DE FC26 05NT42590 and was

This presentation is based upon work supported by the Department of Energy National Energy Technology Laboratory under DE FC26 05NT42590 and was Experimental Monitoring at SECARB s Citronelle Field Site (Coming soon to a CO 2 EOR project near you!) Prepared For: Surveillance and Monitoring of CO 2 Injection Projects Short Course Prepared By: George

More information

6 th Well Bore Integrity Network Meeting

6 th Well Bore Integrity Network Meeting 6 th Well Bore Integrity Network Meeting Alberta ERCB CO2 Injection Well Classification The Hague, The Netherlands April 28-29, 2010 Dr. Fran Hein, P.Geol., Chief Geologist ERCB Theresa Watson, P.Eng.

More information

Tomakomai CCS Demonstration Project

Tomakomai CCS Demonstration Project 1 Tomakomai CCS Demonstration Project CSLF TECHNICAL GROUP MEETING October 4, 2016 Japan CCS Co., Ltd. (JCCS) 2 Overview of Tomakomai Demonstration Project Hokkaido Is. Tomakomai TOKYO Tomakomai CCS Demonstration

More information

Well abandonment procedures and perforation with a slotted charge for cement squeeze applications

Well abandonment procedures and perforation with a slotted charge for cement squeeze applications Well abandonment procedures and perforation with a slotted charge for cement squeeze applications European and West African Perforating Symposium (EWAPS) 7 9 th November 2012 Presented by Co-Author Frank

More information

Grizzly Oil Sands. Algar Lake SAGD Project 2015 In Situ Performance Presentation Scheme Approval No C May 13, 2015

Grizzly Oil Sands. Algar Lake SAGD Project 2015 In Situ Performance Presentation Scheme Approval No C May 13, 2015 Algar Lake SAGD Project 2015 In Situ Performance Presentation Scheme Approval No. 11688C May 13, 2015 Outline and Presenters Introduction and Project Background Alan Stroich Geoscience Jinxiu Qi Drilling

More information

Feasibility Research of Steam-Assisted-Gravity-Drainage Process in Bohai Offshore Heavy Oil Reservoirs

Feasibility Research of Steam-Assisted-Gravity-Drainage Process in Bohai Offshore Heavy Oil Reservoirs Copyright 2013 Tech Science Press SL, vol.9, no.3, pp.197-205, 2013 Feasibility Research of Steam-Assisted-Gravity-Drainage Process in Bohai Offshore Heavy Oil Reservoirs Xiaohu Dong 1, Huiqing Liu 1,

More information

COPYRIGHT. Sand Control Fundamentals. Virtual Instructor Led Session #2

COPYRIGHT. Sand Control Fundamentals. Virtual Instructor Led Session #2 Sand Control Fundamentals Non-Gravel Pack Applications Virtual Instructor Led Session #2 Open Hole with Slotted Liner Open Hole with Screen or Prepacked Screen Slotted liners and screens in a non-gravel

More information

Dan Paul Ştefănescu*, Alexandru Nitulete** NONINVASIVE STIMULATION OPPORTUNITIES IN A MARGINAL GAS FIELD

Dan Paul Ştefănescu*, Alexandru Nitulete** NONINVASIVE STIMULATION OPPORTUNITIES IN A MARGINAL GAS FIELD AGH DRILLING, OIL, GAS Vol. 33 No. 2 2016 http://dx.doi.org/10.7494/drill.2016.33.2.507 Dan Paul Ştefănescu*, Alexandru Nitulete** NONINVASIVE STIMULATION OPPORTUNITIES IN A MARGINAL GAS FIELD 1. INTRODUCTION

More information

The SPE Foundation through member donations and a contribution from Offshore Europe

The SPE Foundation through member donations and a contribution from Offshore Europe Primary funding is provided by The SPE Foundation through member donations and a contribution from Offshore Europe The Society is grateful to those companies that allow their professionals to serve as

More information

Unconventional Resources

Unconventional Resources Houston, Texas (World Headquarters) 4620 Southerland Road Houston, TX, 77092 Phone: 1-800-462-7617 or 713-462-7617 E-mail: info@tamintl.com Aberdeen, Scotland Phone: 44-1224-875105 E-mail: info@tam-northsea.com

More information

Artificial Lift Optimization & Well Cleanout Technology

Artificial Lift Optimization & Well Cleanout Technology Artificial Lift Optimization & Well Cleanout Technology CJS The Company & its Business Model CJS Private Western Canadian company; head office in Calgary; Lloydminster service center Offers alternative

More information

Evaluation of Recovery Technology for the Grosmont Carbonate Reservoir

Evaluation of Recovery Technology for the Grosmont Carbonate Reservoir CIPC Paper 2009-067 Evaluation of Recovery Technology for the Grosmont Carbonate Reservoir Qi Jiang Jian-Yang Yuan Jen Russel-Houston Bruce Thornton Andrew Squires Osum Oil Sands Corp. Outline Geology

More information

Trican s Burst Port System (BPS)

Trican s Burst Port System (BPS) Trican s Burst Port System (BPS) (Patent Pending) A Cost Effective Method for Horizontal Well Stimulation Lewis Facca / Scott Sherman October 14, 2010 Review of Existing Methods for Horizontal Fracturing

More information

Multiple Zone Geothermal Stimulation Case Study: Fluid Diversion Using Thermo-Degradable Zonal Isolation Materials

Multiple Zone Geothermal Stimulation Case Study: Fluid Diversion Using Thermo-Degradable Zonal Isolation Materials GRC Transactions, Vol. 37, 2013 Multiple Zone Geothermal Stimulation Case Study: Fluid Diversion Using Thermo-Degradable Zonal Isolation Materials Y. Nordin, S. Petty, T. Cladouhos, M. Swyer, and T. DeRocher

More information

Stormwater Reuse Through Aquifer Storage & Recovery

Stormwater Reuse Through Aquifer Storage & Recovery Stormwater Reuse Through Aquifer Storage & Recovery CITY OF NAPLES, FLORIDA PRESENTED BY: GREGG R. STRAKALUSE, P.E. DIRECTOR-STREETS & STORMWATER DEPT. DECEMBER 12, 2014 FLORIDA STORMWATER ASSOCIATION

More information

Monell Unit CO 2 Flood

Monell Unit CO 2 Flood Monell Unit CO 2 Flood Patrick Draw Field Sweetwater County, Wyoming May 29 th, 2008 Prepared by: Jason Gaines Senior Reservoir Engineer APC Forward Looking Statement This presentation contains forward-looking

More information

PEACE RIVER IN SITU OIL SANDS PROJECT DIRECTIVE 54 ANNUAL PERFORMANCE PRESENTATION. December 13, 2017 PREMIUM VALUE. DEFINED GROWTH. INDEPENDENT.

PEACE RIVER IN SITU OIL SANDS PROJECT DIRECTIVE 54 ANNUAL PERFORMANCE PRESENTATION. December 13, 2017 PREMIUM VALUE. DEFINED GROWTH. INDEPENDENT. PEACE RIVER IN SITU OIL SANDS PROJECT DIRECTIVE 54 ANNUAL PERFORMANCE PRESENTATION December 13, 2017 PREMIUM VALUE. DEFINED GROWTH. INDEPENDENT. Outline Subsurface Directive 54 Section 3.1.1 Page Acronyms

More information

Production Performance Optimisation

Production Performance Optimisation Production Performance Optimisation Unlocking the Value of Marginal Assets: Production Optimisation through Effective Integrated Production System Modelling by Fortune Bikoro, Ph.D. Gas Lift Workshop -

More information

LNAPL Volume and Mobility Estimation to Assess When to Stop Active Recovery. by Louis Sabourin, P.Eng. and David Tarnocai, P.Geo.

LNAPL Volume and Mobility Estimation to Assess When to Stop Active Recovery. by Louis Sabourin, P.Eng. and David Tarnocai, P.Geo. LNAPL Volume and Mobility Estimation to Assess When to Stop Active Recovery by Louis Sabourin, P.Eng. and David Tarnocai, P.Geo. Presentation Outline Introduction, Issue and Importance LNAPL Migration

More information

Heavy Oil Systems Experience and expertise to enhance productivity

Heavy Oil Systems Experience and expertise to enhance productivity Heavy Oil Systems Experience and expertise to enhance productivity In the emerging and rapidly growing market of heavy oil extraction, production using conventional techniques can be difficult and costly.

More information