Enviable water recovery in a desert environment a case study

Size: px
Start display at page:

Download "Enviable water recovery in a desert environment a case study"

Transcription

1 Mine Water Solutions 2013 J. Obemeyer, J. Enriquez and T. Alexieva 2013 InfoMine Inc, Vancouver, Canada, ISBN XXX Enviable water recovery in a desert environment a case study James R. Obermeyer, MWH Americas, Inc., USA Justo Enriquez, Sociedad Minera Cerro Verde S.A.A., Peru Tatyana G. Alexieva, MWH Americas, Inc., USA Key words Water Balance, Water Conservation, Water Consumption, Water Recovery, Tailing Dams, Desert Environment, Make-Up Water Abstract Cerro Verde is a large copper mine located approximately 20 miles southwest of Arequipa, Peru. The area is characterized by an arid climate, rapid urban population growth and a long tradition of agriculture irrigated by surface water. The mine has been in operation since the early 1970s. Initially, the processing circuit included heap leach pads, leachate solution ponds, and a solvent extraction and electrowinning (SX/EW) plant. In 2004, Sociedad Minera Cerro Verde S.A.A. (SMCV) undertook final design and construction of the Primary Sulfide Project involving construction of a 108,000 tonnes per day (t/d) concentrator at its Cerro Verde Copper Mine. An important component of the project is the tailing storage facility (TSF) which was permitted as a centerline method tailing embankment with an ultimate height of 260 meters (m) above the foundation at the centerline and 300 m above the downstream toe. The Primary Sulfide Project was commissioned in November A debottlenecking project was completed at the concentrator in 2010 to increase the concentrator throughput to its current capacity of 120,000 t/d. The mine operation is dependent on having sufficient water supply. In most mining operations, the Tailing Storage Facility (TSF) consumes the most water. The largest water losses are attributed to evaporation and water trapped in the voids of the deposited tailing. The average annual evaporation is 60 times the average annual precipitation at the Cerro Verde Mine where it is a standard operating procedure to account for every drop of water. A water balance model was created for the Quebrada Enlozada TSF during its design. The model has been updated and calibrated on a regular basis since the commissioning of the facility using actual information. This paper describes the TSF design and its operational process, presents the history of the water balance model development and the reasons for the low water losses that make the facility one of the most water-efficient tailing storage facilities in the world. Mine Water Solutions 2013, Lima, Peru 1

2 Introduction Water is used for a range of activities at a mine site: for dust suppression, for mineral processes, slurry transport, and other purposes. With the increased interest in developing large low grade deposits, the consumption of water per quantity of metal produced increases as well. This, together with the growing world s population leads to a rise in the competition for water, especially in dry climates. It is well known in the mining industry that the tailing management represents the largest water consumption at a mine site. Water lost to evaporation, wetting the foundation, unrecovered seepage, and water trapped in the voids of the tailing deposit are some of the biggest water losses. For this reason, the design of the modern tailing storage facilities requires careful planning and incorporation of features to minimize the losses and increase the water recovery and recycling. Described in this paper are the design and operation of the Enlozada TSF at the Cerro Verde Mine, which is one of the most water-efficient tailing storage facilities in the world. The history of the TSF water balance model development and calibration is also presented. Cerro Verde Mine is located approximately 20 kilometers southwest of Arequipa, Peru in the Andes Mountains. The elevation at the mine ranges between 2400 and 2700 m above mean sea level. The area is characterized by an arid climate, with mean annual precipitation based on data from a weather station at the mine of about 37 millimeters (mm), and a pan evaporation of about 6 mm/day. Construction of the Primary Sulfide Project began in 2005 and the Concentrator plant was commissioned in November Following a production ramp-up period of 8 months, the mine reached the planned production of 108,000 t/d. A debottlenecking project was completed at the concentrator in 2010 to increase the concentrator throughput to its current capacity of 120,000 t/d. Processing 120,000 t/d through the Concentrator requires a significant amount of water. Considering the water shortage in the area, an effort was made during the design and planning phase of the Primary Sulfide Project to incorporate features aimed at minimizing the water losses and maximizing the water recycling and reuse. Enlozada TSF Design The TSF was an important component of the Primary Sulfide Project. The design of the TSF began with defining the design objectives, design basis and criteria. The main objectives adopted for the TSF design were: To store the tailing materials in an environmentally responsible manner. To satisfy internationally accepted stability criteria for embankment construction in areas of high seismicity. To satisfy all relevant Peruvian regulatory requirements associated with construction of the TSF. To follow the concept of zero discharge, which means the use of proven and feasible state-ofthe-practice engineering and technology for the design, construction, operation and closure of a facility, in order to minimize discharges from the facilities to the environment. The principal design basis and criteria adopted for the Quebrada Enlozada TSF are presented in Table 1. Mine Water Solutions 2013, Lima, Peru 2

3 Table 1: Enlozada TSF design basis and criteria Total Capacity About 1 Bt Bt Billion metric tonnes Production Rate 108,000 t/d Ramp-up schedule for 1 st 6 months Percent Solids from Tailing Thickeners 55% Range 50-60% Percent Fines in Tailing Slurry 67.5% Weighted Average Tailing Sample Average Compacted Dry Density of Underflow 1.58 t/m 3 98% of max dry density (ASTM D 698); the 1.58 t/m 3 value will vary for different tailing materials over the life of the mine. Start-up Water Requirement 1,000,000 m 3 To provide water for the start of the operations Flood Storage Requirement Seismicity/Earthquake Load Min Freeboard (Vertical distance between embankment crest and max impoundment elevation) PMF MCE 3 m Min Static Factor of Safety (FOS) 1.5 Post-earthquake FOS 1.2 PMF Probable Maximum Flood PMP Probable Maximum Precipitation MCE Maximum Credible Earthquake M9 Magnitude 9 PGA peak ground acceleration Contain within impoundment, min 100 m from embankment crest during flood conditions. 72-hr PMP = 391 mm Canadian Dam Association, Dam Safety Guidelines, 1999; M9, PGA = 0.47g To provide sufficient flood storage and accommodate anticipated earthquake induced settlements. Canadian Dam Association, Dam Safety Guidelines, 1999; USBR, Chapter 4, 1987 ANCOLD Guidelines, 1998; USBR, Chapter 13, 2001 The required large capacity and production rate, high seismicity of the area and dry climate were major considerations in the design of the TSF. More than 10 sites were evaluated and compared in terms of technical, environmental, social and economic features, and the Quebrada Enlozada site was selected as the best TSF site. Conventional, thickened, paste and filtered tailing disposal methods were evaluated in the process of selecting the best TSF option for further development. The main considerations were water conservation, stability of the facility, potential impacts to the environment (seepage, dust, flora and fauna), and operational practicality. The large production rate made the use of tailing filtering and dry stacking, as well as the application of paste, not practical at that time. Conventional tailing disposal was selected as the preferred disposal method. Thickening of the tailing using conventional thickeners was adopted to reduce the amount of the recirculated water delivered to the tailing facility in the slurry and to potentially reduce the water losses. Following the selection of a TSF site and a tailing disposal method, an embankment alternatives study was performed to select an embankment type and embankment construction materials. The embankment selection study included consideration of centerline and downstream embankment types, and a variety of Mine Water Solutions 2013, Lima, Peru 3

4 construction materials including cycloned tailing underflow, mine waste rock and quarried rock. Due to the relatively low efficiency ratio of the selected site, water conservation considerations and economic factors, a centerline embankment type constructed of compacted cycloned tailing underflow was selected as the best alternative. The TSF is located in Quebrada Enlozada immediately north of the concentrator processing plant, as is shown on Figure 1. Figure 1: TSF plan view The TSF consists of an 85 m high zoned rockfill Starter Dam, a 260 m high embankment constructed of compacted cycloned tailing sand by the centerline method, and a tailing impoundment that will cover an area of approximately 453 hectares (Ha) at its ultimate configuration. The base of the Quebrada Enlozada at the location of the Starter Dam is at an approximate elevation of 2400 m above mean sea level (amsl). The elevation of the processing plant is about 2,700 m amsl. The Starter Dam crest elevation is at 2485 m amsl and the ultimate embankment crest elevation will be 2660 m amsl. A cross-section of the TSF embankment is shown on Figure 2. Mine Water Solutions 2013, Lima, Peru 4

5 Figure 2: TSF embankment cross-section The Starter Dam was sized to contain the tailing produced during the first year of operation and allow for raising the cyclone sand embankment to an elevation sufficient to provide the required freeboard. As per the material balance analysis, the estimated embankment rate of rise ranged from over 2 m per month in the first year of operation to about 1 meter per month during the first five years of operation, and reducing to less than 50 centimeters (cm) per month at the end of the operations. Some of the important factors for achieving this high rate of rise were the permeability of the underflow sand and the availability of an extensive embankment underdrains network that facilitates fast drainage of the deposited underflow. As per the design, the underflow was planned to be delivered at about 70% solids by weight, hydraulically deposited in 30 cm loose lifts, and compacted to 98% of the maximum dry density (ASTM D698) of the underflow. The specification for the cyclone tailing underflow called for maximum of 15% fines (particles finer than 75 micron), which was an important factor for achieving high permeability, fast drainage and a low phreatic surface within the embankment. The network of embankment underdrains was a critical element of the design because it promotes rapid drainage of the cycloned tailing sands, maintains the phreatic surface low in the embankment section and expedites recovery of water that drains from the underflow sands after deposition. The underdrains are planned to be constructed in phases, as shown in Figure 3, to spread capital expenditure over the life of the facility and to reduce potential contamination and erosion of the drains, if exposed over a long period of time. The water collected by the underdrains is conveyed to the Seepage Collection Sump. Mine Water Solutions 2013, Lima, Peru 5

6 Figure 3: Embankment underdrains plan The Seepage Collection Sump provides a pond from which the collected seepage and tailing embankment stormwater runoff are pumped to the cyclone station or to the concentrator plant for reuse. The Seepage Collection Sump includes design components to minimize the risk of seepage from the TSF bypassing the sump, and to satisfy the zero discharge concept criteria described above. The main design components of the Seepage Collection Sump are: An excavation through the alluvium across the valley down to fractured bedrock to create a sump. A geosynthetic liner on the downstream slope of the sump anchored to a concrete grout cap at the excavation bottom and side slopes. A grout curtain at the bottom of the excavation extending through the fractured bedrock into low permeability bedrock. A sump with a capacity to store runoff from the 100-year, 24-hour storm plus a small operating pond and operational flows to the sump during an assumed 12-hour power outage. A spillway designed to pass flows from the 500-year, 24-hour storm. Five monitoring wells located downstream of the sump to monitor groundwater quality. The wells are equipped with pumps to intercept subsurface seepage that bypasses the grout curtain. Other aspects of the TSF design that have an impact on the water consumption is the impoundment deposition practice and the size of the reclaim water pond. The main objectives of the impoundment deposition plan that was included in the TSF Operations Manual were to manage the size and location of the reclaim water pond, and to minimize development of isolated water ponds that would be inaccessible for recovery by the reclaim water system. This is achieved by deposition from strategic points around the Mine Water Solutions 2013, Lima, Peru 6

7 impoundment perimeter that force the water to the Southeast corner of the impoundment. Water from the reclaim water pond is pumped using barge-mounted pumps and conveyed to the processing plant for reuse and to the cyclone station for dilution. To provide a minimum barge operating pond depth, but maintain a small pond area despite the very flat beach slope (<0.5%), the barge is located in an excavated channel (see Figure 4). The barge is also designed to skim clear water from the surface of the reclaim water pond enabling the pumping system to deliver water with minimal total suspended solids to the concentrator with only 2.5 meters of pond depth. This is a significant factor in maintaining a reclaim water pond with a very small surface area and a volume that has normally ranged from only 200,000 to 550,000 m 3 during the first 6 years of TSF operation. Figure 4: Reclaim water barge channel at the completion of the capital construction TSF Operation The construction of the Enlozada TSF began in May 2005 and was completed in August During the design, it was estimated that a start-up water pond would be required to offset the larger water losses expected at the beginning of the operations due to wetting the foundation and time required to create a tailing beach and a clear water pond. Filling the startup water pond began in August 2006 and was completed in October The concentrator plant was commissioned on November 20, Mine Water Solutions 2013, Lima, Peru 7

8 Tailing generated in the flotation process is sent to two high capacity thickeners that thicken the tailing slurry from about 27% solids to about 55% solids by weight. The thickened slurry is conveyed by gravity through a 48-inch diameter HDPE SDR 21 pipeline to a cyclone station located on the right (East) abutment of the tailing embankment. At the cyclone station, the slurry undergoes two-stage cycloning to separate the sand fraction from the fine fraction. Due to delays in completing the cyclone station, deposition of tailing was initiated with whole tailing deposition at a single point located at the right abutment, followed with whole tailing deposition from spigots along the embankment crest. Deposition of underflow began by stockpiling sand on the blanket drain downstream of the Starter Dam toe on December 27, Deposition of underflow on the embankment began on January 3, Pumping of water from the Reclaim water pond back to the concentrator began immediately after the start of the operations, and pumping of water from the Seepage Collection Sump began a few days after deposition of underflow was initiated. Make-up water to the plant to compensate for the losses at the TSF is conveyed from Rio Chili via an 11.5 kilometers long freshwater delivery pipeline. This line was used prior to the start of the operations for filling the startup water pond. Figure 5 shows a recent photo of the Quebrada Enlozada TSF. The embankment height is approximately 150 m under the centerline as of October Figure 5: Enlozada TSF, October 2012 Mine Water Solutions 2013, Lima, Peru 8

9 Water Balance Model The main objective of the water balance model developed for the TSF during the detailed design stage was to estimate the water losses and the required make-up water. The main inputs to the water balance were deposition rate and method, percent solids of the deposited underflow and overflow tailing materials, elevation/area/capacity curves, evaporation and precipitation data, density of the in-situ tailing, pond size, wet and dry beach area ratio, moisture retained in the underflow and bank storage in the foundation materials. The results of the water balance include estimates of water loss due to evaporation, entrained water in the voids, seepage pump back rates, and estimates of required make-up water. Figure 6 presents a schematic diagram of the primary components of the water balance model. Figure 6: Water balance model schematic Based on an assessment of the available data and of the complexity of the model, it was decided that developing a spreadsheet-based deterministic model would be appropriate. The model was based on a monthly time-step and covered the entire operational life of the TSF. The water balance model was directly connected to the results of material balance model providing estimates of the embankment and impoundment raise with time. The density curve illustrating the change in average density of the impounded tailing used in the material balance analysis was also used in the water balance model. The density curve was created based on the results of laboratory testing of a pilot plant tailing sample, followed by consolidation modeling using the computer code FSConsol. It was assumed that the reclaim water pond size will remain constant throughout the operational life of the TSF, while the amount of reclaim water pumped back to the plant will vary based on availability. The climate of the area is mild and arid with temperatures fluctuating between 10 and 24 C and average annual precipitation of approximately 35 mm. The rainstorms occur seasonally and are typically of short Mine Water Solutions 2013, Lima, Peru 9

10 duration and high intensity. Over 90% of the annual rainfall is recorded during the months of January, February and March. The recorded evaporation at the project site exceeds the precipitation over 60 times. The estimated average annual evaporation rate is about 6.1 mm/day. The humidity ranges from about 30% in July to about 70% in February. It was decided that the climate data from the South Zone meteorological station located at the mine should be used despite the short period of record (about 9 years). Average monthly evaporation and precipitation values were used in the model. The sensitivity of using the wettest and driest year on record was also evaluated. The results of the water balance analysis performed during the design phase indicated that the required make-up water would range from over 700 liters per second (l/s) in the first year of operation to about 500 l/s during the later years of operation. The higher water consumption in the initial years of operation was related mostly to the rapid rate of rise and lower achieved average density of the impounded tailing. As the tailing materials consolidate with time, the recovery of water increases. Since the start of the operations, the model has been regularly updated with actual input information, including production rate, cyclone operating time and underflow sand deposition. The results of the updated analysis are illustrated in Figure 7 below. The actual make-up water consumption is plotted on the figure with circles representing average monthly make-up water consumption. As was mentioned above, it was assumed that the reclaim water pond would be maintained at a minimum constant value. In reality, the size of the pond has fluctuated (see Figure 7). It is interesting to note that the periods of recorded higher make-up water consumption have coincided with periods of accumulation of a larger pond and vice-versa. Maintaining a constant pond at about 250,000 m 3, as assumed for the water balance analysis, would have resulted in an even closer match between the estimated and actual results. Lower make-up water consumption was also observed during the unusually wet periods of 2008, 2011 and The variations in the estimated make-up water requirements represent the seasonal variation in the precipitation and evaporation. Peaks in the estimated make-up requirements represent the impact of the driest year on record, while the lowest estimated make-up requirements represent the impact of a wet year. Make-up Water Requirements, L/s Measured Data Design Adjusted with Actual Production Reclaim Pond Volume Year 2026 Figure 7: Make-up water requirements Design Assumed Dry Years Assumed Wet Year Pond Volume, Million m 3 Figure 8 presents the estimated and actual make-up water requirements at the Cerro Verde Concentrator plant in cubic meters of water per tonne of processed ore. The figure confirms the higher expected water Mine Water Solutions 2013, Lima, Peru 10

11 consumption during the first year of operation. As was described above, some variation of the water consumption is observed that is mostly due to fluctuations in the pond size and experiencing higher than usual precipitation. A comparison of these results with results from mines located in similar climatic regions (Arizona, Southern Peru and Chile) show that the Cerro Verde Mine has the lowest water consumption with an average actual make-up water of less than 0.38 m3/t, compared to reported make-up water from about 0.4 to over 0.7 m 3 /t for the other mines Measured Data Design Adjusted with Actual Production t water/t ore Design Figure 8: Make-up water requirements per tonne processed ore Factors for the Low Water Consumption Year Achieving low water consumption and minimizing potential impacts to the environment were some of the main objectives of the Quebrada Enlozada TSF design. Comparison of the design and actual water balance results indicate good correlation and provide confidence that the TSF water balance is about as expected. Some of the main factors influencing the low water consumption of the Concentrator operations are presented below: 1. Embankment Construction Method: As was described above, the TSF embankment is raised using tailing cyclone underflow sand. The hydraulically deposited sand drains within a few hours and remains at a moisture content of about 13%. This results in the recovery of a large portion of the water. Because the impoundment to embankment volume ratio is relatively low (about 3.3), a large amount of tailing is deposited on the embankment rather than in the impoundment. The high density and low moisture content of the embankment result in much higher water recovery from the embankment than from the impounded finer tailing, which Mine Water Solutions 2013, Lima, Peru 11

12 Closing remain saturated and at a lower density. Cycloning a significant portion of the tailing reduces the losses due to water trapped in the voids and increases the water efficiency of the TSF. In the case of the Quebrada Enlozada TSF, an average of about 25% to 30% of the tailing materials by weight are placed in the compacted underflow embankment. 2. Efficient Seepage Collection System: The network of embankment underdrains facilitates fast harvesting and reuse of water from the underflow. The low permeability of the impoundment foundation limits the amount of water lost due to foundation wetting and minimizes seepage from the impoundment. Seepage from the impoundment makes its way to the Seepage Collection Sump where it is collected and returned for reuse. 3. Small Impoundment and Reclaim Water Pond Surface Area: The TSF is located in a steep, bowl-shaped valley with small surface area, which results in low evaporation losses. Maintaining a small pond size, of about 40 Ha results in reduced evaporation losses, and is one of the priorities of the TSF operators. 4. Optimized Deposition Practice: The deposition plan was designed to minimize the development of clear water ponds in the side drainages by depositing from around the impoundment perimeter. Another important function of the deposition practice is maintaining a reclaim water pond in a confined area in the southeast corner of the impoundment. Minimizing the number and size of inaccessible water ponds results in an increase in the water reporting to the reclaim water pond from where it is pumped back for reuse. 5. Reclaim Water Pond Size: One of the keys to maintaining a small reclaim water pond on the TSF, in spite of the relatively flat bench slope within the impoundment, is the ability to pump water of suitable quality for the concentrator from a pond with a depth of only 2.5 meters. This is the result of a barge design for the pumping system that skims clear water from the surface of the pond. Operating the barge pumps in a pre-excavated channel along which the barge pumps move as the TSF grows is also a factor contributing to being able to maintain a small pond. 6. Tailing Thickeners: Two high capacity tailing thickeners are used to thicken the slurry exiting the concentrator plant from about 27% to about 55% solids by weight. Thickening the slurry prior to conveying it to the TSF results in the recovery of a significant amount of water close to the plant, and thus contributes to reduced pumping costs and water losses. 7. Closed-Circuit Water Balance: Performing a detailed water balance analysis early in the design of the TSF contributed to gaining a good understanding of the factors resulting in water losses and provided an opportunity for optimizing the design to achieve a better water efficiency. The water balance analysis is updated regularly to verify its accuracy, and adjust the operations to improve water recovery. The water balance, together with the results of the monitoring program, confirms that the facility is operating consistent with the zero discharge concept adopted for the design, and that the TSF water balance is as predicted during design of the facility. Water is a precious commodity, and in many cases, the ability of a mine to operate is contingent on having sufficient make-up water to compensate for the losses incurred during the operations, which are mostly accounted by the TSF. For this reason, considering water saving measures in the design of the TSF, and developing an accurate water balance model are important factors for the success of the project. The experience at the Cerro Verde Mine demonstrates that careful planning and attention to the established operation of the TSF has resulted in low water losses and having one of the most water efficient TSFs in the world. Mine Water Solutions 2013, Lima, Peru 12

Design, Construction and Operation of a Large Centerline Tailing Storage Facility with High Rate of Rise

Design, Construction and Operation of a Large Centerline Tailing Storage Facility with High Rate of Rise Proceedings Tailings and Mine Waste 2011 Design, Construction and Operation of a Large Centerline Tailing Storage Facility with High Rate of Rise James Obermeyer, Tatyana Alexieva MWH Americas, Inc., Denver,

More information

Conceptual model for estimating water recovery in tailings impoundments

Conceptual model for estimating water recovery in tailings impoundments Conceptual model for estimating water recovery in tailings impoundments C. Wels & A. MacG. Robertson Robertson GeoConsultants, Inc., Vancouver, Canada ABSTRACT: In most semi-arid and arid regions water

More information

Independent Expert Engineering Investigation and Review Panel. Report on Mount Polley Tailings Storage Facility Breach. Appendix G: Water Balance

Independent Expert Engineering Investigation and Review Panel. Report on Mount Polley Tailings Storage Facility Breach. Appendix G: Water Balance Independent Expert Engineering Investigation and Review Panel Report on Mount Polley Tailings Storage Facility Breach Appendix G: Water Balance January 30, 2015 Report on Mount Polley Tailings Storage

More information

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY REPORT ON STAGE 3C CONSTRUCTION (REF.NO. VA-101-1/5-1) Rev. No. Revision Date Approved 0 Issued in Final September 23, 2005 AMEC010485_0001

More information

Comparative Evaluation of Thickened versus Slurry Tailings Surface Disposal D. Johnson Golder Associates Ltd., Canada R. Moghaddam Golder Associates

Comparative Evaluation of Thickened versus Slurry Tailings Surface Disposal D. Johnson Golder Associates Ltd., Canada R. Moghaddam Golder Associates Comparative Evaluation of Thickened versus Slurry Tailings Surface Disposal D. Johnson Golder Associates Ltd., Canada R. Moghaddam Golder Associates Ltd., Canada I. Bin Ahmed Golder Associates Ltd., Canada

More information

Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria

Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria Terry Eldridge Golder Associates S.A., Chile Ben Wickland Golder Associates Ltd., Canada Adrian Goldstone Dundee Precious Metals

More information

Design of Zinc Tailings Storage Facility

Design of Zinc Tailings Storage Facility Proceedings of the 6 th International Mining and Industrial Waste Management Conference, 29, 30 & 31 October 2018 Legend Golf and Safari Resort, Limpopo Design of Zinc Tailings Storage Facility A. du Plessis

More information

SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY

SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY Phong Vo, Manager - Engineering/Gypsum, Mosaic Fertilizer, LLC. 13830 Circa Crossing Drive Lithia, Florida 33547, USA and Ashraf H. Riad, Ph.D., P.E.,

More information

In-pit tailings disposal at Langer Heinrich TSFs in a unique hydrogeological setting

In-pit tailings disposal at Langer Heinrich TSFs in a unique hydrogeological setting In-pit tailings disposal at Langer Heinrich TSFs in a unique hydrogeological setting Tailings and Mine Waste Management for the 21 st Century 2015 Page number 373 in proceedings Prepared by: Cameron Hore

More information

2018 TAILINGS AND MINE WASTE CONFERENCE ALTERNATIVE APPROACHES TO MANAGEMENT FACILITIES AND CLOSURE OF TAILINGS STORAGE

2018 TAILINGS AND MINE WASTE CONFERENCE ALTERNATIVE APPROACHES TO MANAGEMENT FACILITIES AND CLOSURE OF TAILINGS STORAGE 2018 TAILINGS AND MINE WASTE CONFERENCE ALTERNATIVE APPROACHES TO MANAGEMENT AND CLOSURE OF TAILINGS STORAGE FACILITIES Professor David Williams Director Geotechnical Engineering Centre The University

More information

APPENDIX A.4A: Tailings Management Facility Construction Material Alternatives

APPENDIX A.4A: Tailings Management Facility Construction Material Alternatives APPENDIX A.4A: Tailings Management Facility Construction Material Alternatives Volume VOLUME A.ii: A.II: Project PROJECT introduction INTRODUCTION & overview OVERVIEW A.1 Introduction A.4A Tailings Management

More information

Tailings Storage and Heap Leaching in a Combined Facility A First for the Mining Industry

Tailings Storage and Heap Leaching in a Combined Facility A First for the Mining Industry Tailings Storage and Heap Leaching in a Combined Facility A First for the Mining Industry Thomas F. Kerr, P.E., Knight Piésold and Co. Michael G. Skurski, P.E., Newmont Mining Co. Peter D. Duryea, Ph.D.,

More information

Magino Project Environmental Impact Statement. Technical Support Document Water Management Plan

Magino Project Environmental Impact Statement. Technical Support Document Water Management Plan EIS Techni cal Support Document 20-12 Magino Project Environmental Impact Statement Technical Support Document 20-12 Rev. No. Revision Date Approved 0 Document issued for EIS Table of Contents SECTION

More information

Converting slurry tailings facilities to filtered dry stacks a case history. John Lupo Newmont Mining Corporation Marcelo Mussé - Consultant

Converting slurry tailings facilities to filtered dry stacks a case history. John Lupo Newmont Mining Corporation Marcelo Mussé - Consultant Converting slurry tailings facilities to filtered dry stacks a case history John Lupo Newmont Mining Corporation Marcelo Mussé - Consultant Objectives General discussion on the geotechnical issues. Case

More information

BAP or BAT? A review of some dramatic changes in tailings management in the recent past and potential changes in the future

BAP or BAT? A review of some dramatic changes in tailings management in the recent past and potential changes in the future BAP or BAT? A review of some dramatic changes in tailings management in the recent past and potential changes in the future Andy Fourie School of Civil, Environmental & Mining Engineering 1 BAP or BAT?

More information

Tailings Storage Facility Conceptual Closure Plan Alternatives Assessment

Tailings Storage Facility Conceptual Closure Plan Alternatives Assessment Appendix 17.4-C Tailings Storage Facility Conceptual Closure Plan Alternatives Assessment AJAX PROJECT Environmental Assessment Certificate Application / Environmental Impact Statement for a Comprehensive

More information

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY OPERATION, MAINTENANCE AND SURVEILLANCE MANUAL Rev. No. Revision Date Approved 0 Issued in Final December 22, 2004 1 Issued in

More information

Landfill design General principles

Landfill design General principles Landfill design General principles Average height of a landfill should be at least 15 m Each section (cell) should accommodate waste to be landfilled during 5 years period Sections/cells should be hydraulically

More information

NICO Tailings and Mine Rock Co-disposal Facility (CDF) Design Concept

NICO Tailings and Mine Rock Co-disposal Facility (CDF) Design Concept NICO Tailings and Mine Rock Co-disposal Facility (CDF) Design Concept Open pit and underground mine The project has 31 Mt of ore reserve Ore to be processed at a rate of 4,650 t/d Life of mine is 20 years

More information

Phone (604) Local 233 Fax (604) RGC REPORT NO /7

Phone (604) Local 233 Fax (604) RGC REPORT NO /7 ROBERTSON GEOCONSULTANTS INC. A Robertson Group Company Consulting Geotechnical and Environmental Engineers Suite 640, 580 Hornby St., Vancouver BC, Canada V6C 3B6 Phone (604) 684-8072 Local 233 Fax (604)

More information

TAILING & HEAP LEACH FACILITY MANAGEMENT PURPOSE & OBJECTIVES CONTENT. 1. Planning & Design

TAILING & HEAP LEACH FACILITY MANAGEMENT PURPOSE & OBJECTIVES CONTENT. 1. Planning & Design PURPOSE & OBJECTIVES This Tailing & Heap Leach Facility Management Standard (the Standard ) sets the minimum Newmont requirements for the design and management of tailing storage facilities (TSF) and heap

More information

CCR Rule Operating Criteria Closure Plan

CCR Rule Operating Criteria Closure Plan CCR Rule Operating Criteria 257.102 Closure Plan FGD Pond 2 Jim Bridger Plant Point of Rocks, Wyoming PREPARED FOR PacifiCorp 1407 West North Temple Salt Lake City, UT 84116 (801) 521-0376 Fax (801) 220-4748

More information

Tailings mobilization estimates for dam breach studies

Tailings mobilization estimates for dam breach studies Tailings mobilization estimates for dam breach studies Daniel Fontaine, P.Eng, Violeta Martin, Ph.D., P.Eng, Knight Piésold Ltd., Vancouver, BC, Canada ABSTRACT Quantitative assessment of potential consequences

More information

Newmont Mining Corporation Tailing & Heap Leach Facility Management Standard

Newmont Mining Corporation Tailing & Heap Leach Facility Management Standard Page No: Page 1 of 5 1 PURPOSE AND OBJECTIVES This (the Standard ) sets the minimum Newmont requirements for the design and management of tailing storage facilities (TSF) and heap leach facilities (HLF)

More information

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Updated: November 2010 Directive 74 Appendix C Requirement Approval: 8512D Submitted to SHELL CANADA ENERGY MRM DDA PLAN-UPDATE NOV

More information

Glen Hall Falconbridge Ltd., Sudbury Operations Sudbury, Ontario

Glen Hall Falconbridge Ltd., Sudbury Operations Sudbury, Ontario A NEW APPROACH TO TAILINGS MANAGEMENT: THE GRANULAR COVER SYSTEM Glen Hall Falconbridge Ltd., Sudbury Operations Sudbury, Ontario Linda C. M. Elliott, Lakefield Research Ltd., PO Box 4300, 185 Concession

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM FOR INTERNAL DISCUSSION PURPOSES ONLY TECHNICAL MEMORANDUM TO: Augusta Resource Corp. ATTENTION: Jamie Sturgess FROM: Troy Meyer Project Manager, Vector Colorado LLC (Vector) DATE: June 5, 2006 SUBJECT:

More information

ET COVER SYSTEM IN ARID ENVIRONMENTS

ET COVER SYSTEM IN ARID ENVIRONMENTS ET COVER SYSTEM IN ARID ENVIRONMENTS JUSTIFYING THE USE OF AN EVAPO TRANSPIRATIVE COVER SYSTEM FOR CAPPING AN INDUSTRIAL WASTE PILE SAVES CLIENT MILLIONS Martin E. Carlson, PE May 8, 2018 PRESENTATION

More information

Tailings dam raise with reinforced walls

Tailings dam raise with reinforced walls Tailings dam raise with reinforced walls Jorge Alvarez Tiburcio Anddes Asociados S.A.C.,Peru ABSTRACT This paper presents the design of a tailings dam raise with reinforced walls lined with geomembrane,

More information

SRK Consulting Sukulu Phosphate Project Scoping Report. 6 Tailings Dams Introduction Tailings behaviour...

SRK Consulting Sukulu Phosphate Project Scoping Report. 6 Tailings Dams Introduction Tailings behaviour... Sukulu Phosphate Project Scoping Report Page i Table of Contents 6 Tailings Dams... 6-1 6.1 Introduction... 6-1 6.2 Tailings behaviour... 6-1 6.2.1 Magnetics tailings... 6-1 6.2.2 Flotation tailings...

More information

APPENDIX III Hydrologic and Hydraulic Evaluations

APPENDIX III Hydrologic and Hydraulic Evaluations APPENDI III Hydrologic and Hydraulic Evaluations Hydrologic and Hydraulic Analysis Related to Compliance Requirements South Fly Ash Pond, Boiler Slag Pond and Clearwater Pond Kyger Creek Power Plant, Gallia

More information

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE DESIGN OF THE TAILINGS STORAGE FACILITY TO ULTIMATE ELEVATION (REF. NO.

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE DESIGN OF THE TAILINGS STORAGE FACILITY TO ULTIMATE ELEVATION (REF. NO. MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE DESIGN OF THE TAILINGS STORAGE FACILITY TO ULTIMATE ELEVATION (REF. NO. VA101-001/08-1) Rev. No. Revision Date Approved 0 Issued for Report March 14, 2005

More information

Environmental Assessment Chapter 8 Surface Water

Environmental Assessment Chapter 8 Surface Water Environmental Assessment Chapter 8 Surface Water 8.2.7 Rainfall and Evaporation Based on recorded data for the area of interest, the mean annual rainfall is about 700mm, with maximum monthly rainfalls

More information

Bioreactor Landfill Design

Bioreactor Landfill Design Bioreactor Landfill Design Timothy Townsend, PhD, PE Department of Environmental Engineering Sciences University of Florida ttown@ufl.edu Bioreactor Landfill Design Modern landfill design entails many

More information

Abstract. 1 Introduction. Golder Associates Ltd, Canada

Abstract. 1 Introduction. Golder Associates Ltd, Canada https://papers.acg.uwa.edu.au/p/1752_05_gu/ Challenges associated with the design of a dewatering plant that will undergo a large increase in tailings throughput during the initial years of the project

More information

Keeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement

Keeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement Keeyask Generation Project Environmental Impact Statement Supporting Volume Physical Environment June 2012 KEEYASK GENERATION PROJECT SUPPORTING VOLUME EFFECTS OF THE ENVIRONMENT ON THE PROJECT June 2012

More information

Dry Stacking Operation at Pogo Mine, Alaska June 12, Sumitomo Metal Mining Pogo LLC

Dry Stacking Operation at Pogo Mine, Alaska June 12, Sumitomo Metal Mining Pogo LLC Dry Stacking Operation at Pogo Mine, Alaska June 12, 2014 Sumitomo Metal Mining Pogo LLC Contents 1. About Pogo Mine Geology Mining and paste backfill Process 2. Dry Stacking Operation About Dry Stack

More information

Geosynthetics Cost/Benefit Analysis for the Development of a Landfill Expansion Module in Monterey, California

Geosynthetics Cost/Benefit Analysis for the Development of a Landfill Expansion Module in Monterey, California The First Pan American Geosynthetics Conference & Exhibition 2-5 March 2008, Cancun, Mexico Geosynthetics Cost/Benefit Analysis for the Development of a Landfill Expansion Module in Monterey, California

More information

Hydraulic performance of permanent heap leach with intermediate drainage system

Hydraulic performance of permanent heap leach with intermediate drainage system Proceedings of Heap Leach Solutions, 2015 September 14-16, 2015, Reno, USA Published by InfoMine, 2015 InfoMine, ISBN: 978-0-9917905-8-6 Hydraulic performance of permanent heap leach with intermediate

More information

Dirk J.A. van Zyl, Ph.D., P.Eng. P.E. Tailings and Mine Rock Management

Dirk J.A. van Zyl, Ph.D., P.Eng. P.E. Tailings and Mine Rock Management Dirk J.A. van Zyl, Ph.D., P.Eng. P.E. Tailings and Mine Rock Management MEMORANDUM To: From: Subject: Mr. Brent Murphy, Vice President Environment Affairs Dirk van Zyl, Principal Engineer Review Comments

More information

Dankoe Mine. Report on 2014 Dam Safety Inspection of Tailings Storage Facility

Dankoe Mine. Report on 2014 Dam Safety Inspection of Tailings Storage Facility Peter Lighthall, P.Eng Consulting Geotechnical Engineer Dankoe Mine Report on of Tailings Storage Facility Report prepared for 439813 BC Ltd. December 4, 2014 Peter Lighthall, P.Eng. Consulting Geotechnical

More information

FOUR CORNERS POWER PLANT CLOSURE PLAN (b) DRY FLY ASH DISPOSAL AREA (DFADA) FC_ClosPlan_004_

FOUR CORNERS POWER PLANT CLOSURE PLAN (b) DRY FLY ASH DISPOSAL AREA (DFADA) FC_ClosPlan_004_ FOUR CORNERS POWER PLANT CLOSURE PLAN 257.102(b) DRY FLY ASH DISPOSAL AREA (DFADA) FC_ClosPlan_004_20161017 Closure Plan Contents 257.102(b)(1) The owner or operator of a CCR unit must prepare a written

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion

More information

Technical Memorandum

Technical Memorandum Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum To: Kathy Arnold From: Ronson Chee Company: Rosemont Copper Company Date: January

More information

CHOLLA POWER PLANT CLOSURE PLAN (b) BOTTOM ASH POND CH_ClosPlan_003_

CHOLLA POWER PLANT CLOSURE PLAN (b) BOTTOM ASH POND CH_ClosPlan_003_ CHOLLA POWER PLANT CLOSURE PLAN 257.102(b) BOTTOM ASH POND CH_ClosPlan_003_20161017 Closure Plan Contents 257.102(b)(1) The owner or operator of a CCR unit must prepare a written closure plan that describes

More information

Understanding of foundation conditions, water balance adequacy and filter adequacy at the closed Nickel Plate tailings impoundment near Hedley, BC

Understanding of foundation conditions, water balance adequacy and filter adequacy at the closed Nickel Plate tailings impoundment near Hedley, BC Barrick Gold Corporation 460 West 50 North, Suite 500 Salt Lake City, Utah 84101 27 June 2015 Al Hoffman, P.Eng. Chief Inspector and Executive Director, Health & Safety British Columbia Ministry of Energy

More information

Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps. Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band

Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps. Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band 11 August 2014 Presentation Outline General Introduction

More information

Black Butte Copper Project Mine Operating Permit Application (Revision 3) Water Management During Construction and Operations

Black Butte Copper Project Mine Operating Permit Application (Revision 3) Water Management During Construction and Operations Black Butte Copper Project Mine Operating Permit Application (Revision 3) APPENDIX K-2: Water Management During Construction and Operations Tintina Montana, Inc. July 2017 www.knightpiesold.com Mr. Bob

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY (i) Site Name and Ownership Information: Site Name: Plant Hammond Site Location: Site Address:

More information

To reduce the environmental impact we should ISOLATE or CONTAIN the waste in an IMPERMEABLE BARRIER

To reduce the environmental impact we should ISOLATE or CONTAIN the waste in an IMPERMEABLE BARRIER To reduce the environmental impact we should ISOLATE or CONTAIN the waste in an IMPERMEABLE BARRIER 1 COMPONENTS OF ENGINEERED LANDFILL a) A Liner System b) A Leachate Collection Facility c) A Gas Control

More information

Yanacocha S.R.L. Mining Company Conga Project Environmental Impact Assessment. Final Report. Volume III. February 2010

Yanacocha S.R.L. Mining Company Conga Project Environmental Impact Assessment. Final Report. Volume III. February 2010 Yanacocha S.R.L. Mining Company Conga Project Environmental Impact Assessment Final Report Volume III February 2010 Prepared for Yanacocha S.R.L. Mining Company Av. Víctor Andrés Belaúnde 147 Vía Principal

More information

Water balance and cost evaluation for different scenarios of impermeable covers (raincoats) in heap leach pad operations

Water balance and cost evaluation for different scenarios of impermeable covers (raincoats) in heap leach pad operations Water balance and cost evaluation for different scenarios of impermeable covers (raincoats) in heap leach pad operations Daniel Pulcha, Anddes Asociados S.A.C., Peru Carlos César, Anddes Asociados S.A.C.,

More information

AMERICAN ELECTRIC POWER (SWEPCO)

AMERICAN ELECTRIC POWER (SWEPCO) 2015 DAM & DIKE INSPECTION REPORT ASH PONDS GERS-15-034 WELSH POWER PLANT AMERICAN ELECTRIC POWER (SWEPCO) CASON, TEXAS NATIONAL INVENTORY NO. TX4357 PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION

More information

AMERICAN ELECTRIC POWER (SWEPCO)

AMERICAN ELECTRIC POWER (SWEPCO) 2016 DAM & DIKE INSPECTION REPORT ASH PONDS GERS-16-163 WELSH POWER PLANT AMERICAN ELECTRIC POWER (SWEPCO) CASON, TEXAS NATIONAL INVENTORY NO. TX4357 PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION

More information

Environmental Management Chapter ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER QUALITY PROGRAM ADMINISTRATIVE CODE

Environmental Management Chapter ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER QUALITY PROGRAM ADMINISTRATIVE CODE Environmental Management Chapter 335-6-9 ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER QUALITY PROGRAM ADMINISTRATIVE CODE CHAPTER 335-6-9 SURFACE MINING RULES TABLE OF CONTENTS

More information

WASTE TREATMENT LAGOON

WASTE TREATMENT LAGOON 359-1 NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE STANDARD WASTE TREATMENT LAGOON (No.) CODE 359 DEFINITION A waste treatment impoundment made by constructing an embankment and/or excavating

More information

POND SEALING OR LINING COMPACTED SOIL TREATMENT

POND SEALING OR LINING COMPACTED SOIL TREATMENT NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE STANDARD POND SEALING OR LINING COMPACTED SOIL TREATMENT CODE 520 (FT. 2 ) DEFINITION A liner for an impoundment constructed using compacted

More information

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION CHAPTER 23.105 GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION Sections 23.105.101 General... 1 23.105.102 Definitions... 1 23.105.103 Permits required... 3 23.105.104 Hazards.... 4 23.105.105 Permit

More information

STRUCTURAL STABILITY ASSESSMENT. Bremo Power Station CCR Surface Impoundment: North Ash Pond STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT. Bremo Power Station CCR Surface Impoundment: North Ash Pond STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT Bremo Power Station CCR Surface Impoundment: North Ash Pond ~,Dominion Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff,

More information

Material properties of Tailings from Swedish mines

Material properties of Tailings from Swedish mines Material properties of Tailings from Swedish mines I. Jantzer Luleå University of Technology, Sweden, Isabel.Jantzer@ltu.se A. Bjelkevik Sweco AB, Sweden, Annika.Bjelkevik@sweco.se K. Pousette Luleå University

More information

CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park

CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park CBC Case Study-1212 1 of 5 CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park More Than Geotechnical Engineering DAYTON 125 Westpark Road Centerville, OH 45459 Phone: 937-428-6150 HAZARD

More information

Karara Iron Ore TSF design considerations for a unique large scale dry stack facility

Karara Iron Ore TSF design considerations for a unique large scale dry stack facility Page 1 Karara Iron Ore TSF design considerations for a unique large scale dry stack facility C. Hore SRK Consulting, Perth, Western Australia, Australia D. Luppnow SRK Consulting, Perth, Western Australia,

More information

Suggested Stormwater Management Practices For Individual House Lots

Suggested Stormwater Management Practices For Individual House Lots Suggested Stormwater Management Practices For Individual House Lots These practices are necessary to satisfy the water quantity and water quality criteria of the Rappahannock Stormwater Ordinance. These

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration

More information

Oil sands tailings dewatering can it be done?

Oil sands tailings dewatering can it be done? Paste 2011 R.J. Jewell and A.B. Fourie (eds) 2011 Australian Centre for Geomechanics, Perth, ISBN 978-0-9806154-3-2 https://papers.acg.uwa.edu.au/p/1104_20_longo/ S. Longo Golder Paste Technology Ltd.,

More information

Review of ML/ARD Geochemistry & Water Quality Predictions

Review of ML/ARD Geochemistry & Water Quality Predictions Review of ML/ARD Geochemistry & Water Quality Predictions Presented by Kim Bellefontaine, M.Sc., P.Geo. Senior Mine Review Geologist, MEMPR With contributions from: Kelly Sexsmith, M.S., P.Geo. Senior

More information

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY OPERATION, MAINTENANCE AND SURVEILLANCE MANUAL Rev. No. Revision Date Approved 0 Issued in Final December 22, 2004 1 Issued in

More information

Coal Combustion Residuals Inflow Design Flood Control System Plan

Coal Combustion Residuals Inflow Design Flood Control System Plan gaiconsultants.com I transforming ideas into reality., Coal Combustion Residuals Inflow Design Flood Control System Plan Virginia Electric and Power Company Possum Point Power Station Surface Impoundment

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or

More information

Challenges in Tailings Water Balance Analysis Make-up Water, Seepage and Consolidation. By: Christoph Wels & Jack Caldwell

Challenges in Tailings Water Balance Analysis Make-up Water, Seepage and Consolidation. By: Christoph Wels & Jack Caldwell Challenges in Tailings Water Balance Analysis Make-up Water, Seepage and Consolidation By: Christoph Wels & Jack Caldwell Overview Background Rationale for TSF water balance studies Definitions & Concepts

More information

Water Management in the Australian Minerals Industry

Water Management in the Australian Minerals Industry 34 th IAHR World Congress - Balance and Uncertainty 26 June - 1 July 2011, Brisbane, Australia 33 rd Hydrology & Water Resources Symposium 10 th Hydraulics Conference Water Management in the Australian

More information

1.2 Below Normal Water Level and Outflow Conditions at Raft Lake Dam

1.2 Below Normal Water Level and Outflow Conditions at Raft Lake Dam DATE November 26, 2015 REFERENCE No. 1408383_3201_Rev 0 TO Cathryn Moffett, Sustainable Development Project Manager Canadian Malartic Corporation CC Darrin Johnson; Adam Auckland - Golder Associates Ltd.

More information

Technical Memorandum

Technical Memorandum Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum To: Kathy Arnold From: Ronson Chee Company: Rosemont Copper Company Date: January

More information

WQ-06 SAND FILTER. 1.0 Sand Filter. Greenville County Technical Specification for: 1.1 Description

WQ-06 SAND FILTER. 1.0 Sand Filter. Greenville County Technical Specification for: 1.1 Description Greenville County Technical Specification for: WQ-06 SAND FILTER 1.0 Sand Filter 1.1 Description Sand Filters remove pollutants through sedimentation and filtration within the sand. The primary components

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116 (i) Site Name and Ownership Information: HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY Site Name: Site Location: Site Address: Owner: Owner Address:

More information

June 30, 2015 Project No.: C Mr. Kent Christensen, P.Eng. General Manager Huckleberry Mines Limited PO Box 3000 Houston BC, V0J 1Z0

June 30, 2015 Project No.: C Mr. Kent Christensen, P.Eng. General Manager Huckleberry Mines Limited PO Box 3000 Houston BC, V0J 1Z0 Suite 500-980 Howe Street Vancouver, BC Canada V6Z 0C8 Telephone (604) 684-5900 Fax (604) 684-5909 June 30, 2015 Project No.: 1193-005-C Mr. Kent Christensen, P.Eng. General Manager Huckleberry Mines Limited

More information

CCE AWARD SUBMISSION BARRIE LANDFILL RECLAMATION AND RE-ENGINEERING

CCE AWARD SUBMISSION BARRIE LANDFILL RECLAMATION AND RE-ENGINEERING CCE AWARD SUBMISSION BARRIE LANDFILL RECLAMATION AND RE-ENGINEERING 2 CCE AWARD SUBMISSION GOLDER ASSOCIATES LTD. SUMMARY The City of Barrie landfill was impacting water resources and required remediation.

More information

Civil and Geotechnical Engineering

Civil and Geotechnical Engineering Imagine the result Imagine the result Civil and Geotechnical Engineering for the Mining Industry Innovative, Sustainable and Grounded Solutions At ARCADIS, we understand the environment and how to engineer

More information

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT THE GOVERNMENT OF MALAYSIA PRIME MINISTER S DEPARTMENT ECONOMIC PLANNING UNIT THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT VOL. 5: TECHNICAL

More information

Adding Value. Delivering Results. WAIMM New Techniques & Innovations for Tailings Dam Construction and Operational Efficiency

Adding Value. Delivering Results. WAIMM New Techniques & Innovations for Tailings Dam Construction and Operational Efficiency Adding Value. Delivering Results. WAIMM 2017 New Techniques & Innovations for Tailings Dam Construction and Operational Efficiency Outline Industry Practices/Innovations What Technology, When/Where? Typical

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond INFLOW DESIGN FLOOD

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN. Bremo Power Station CCR Surface Impoundment: North Ash Pond INFLOW DESIGN FLOOD INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN Bremo Power Station CCR Surface Impoundment: North Ash Pond Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo

More information

3.11 Sand Filter Basin

3.11 Sand Filter Basin 3.11 Sand Filter Basin Type of BMP Priority Level Treatment Mechanisms Maximum Drainage Area Flow-Through Treatment Priority 3 Treatment Control BMP Filtration 25 acres Description The Sand Filter Basin

More information

Base Metal and Iron Ore Mining

Base Metal and Iron Ore Mining Multilateral Investment Guarantee Agency Environmental Guidelines for Base Metal and Iron Ore Mining Industry Description and Practices This document addresses the mining of base metal ores (copper, lead

More information

Inlet Protection. Fe= (Depends on soil type)

Inlet Protection. Fe= (Depends on soil type) 3.4 DESIGN CRITERIA: KEY CONSIDERATIONS Evaluate drainage patterns to ensure inlet protection will not cause flooding of roadway, property or structures Never block entire inlet opening Size according

More information

Guidance for Liner Design for Demolition Debris or Industrial Solid Waste Landfills Waste/Solid Waste #5.02, October 2005

Guidance for Liner Design for Demolition Debris or Industrial Solid Waste Landfills Waste/Solid Waste #5.02, October 2005 Solid Waste Program Guidance for Liner Design for Demolition Debris or Industrial Solid Waste Landfills, October 2005 INTRODUCTION In Minnesota, ground water is owned by the people of the state until it

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Closure of Jarosite Pond Facility, Timmins, Ontario. Design and Construction

Closure of Jarosite Pond Facility, Timmins, Ontario. Design and Construction Closure of Jarosite Pond Facility, Timmins, Ontario Design and Construction Andy Small AMEC December 2013 Outline Introduction Site description Closure options Design criteria Design Construction Water

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any

More information

Technical Memorandum

Technical Memorandum Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum To: Kathy Arnold From: Greg Hemmen, P.E. Company: Rosemont Copper Company Date:

More information

Integration of Antapaccay Project with Tintaya progressive closure plan

Integration of Antapaccay Project with Tintaya progressive closure plan Integration of Antapaccay Project with Tintaya progressive closure plan Mauricio Quiroz Xstrata Copper Project Development Luis Espinoza Xstrata Tintaya Liz Espinoza Xstrata Tintaya 24 November 2010 Mine

More information

Characterization of gold inventory and impediments to recovery at an active heap leach facility

Characterization of gold inventory and impediments to recovery at an active heap leach facility Proceedings of Heap Leach Solutions, 2014 November 10 13, 2014, Lima, Peru Published by InfoMine, 2014 InfoMine, ISBN: 978-0-9917905-6-2 Characterization of gold inventory and impediments to recovery at

More information

McElroy s Run Impoundment Structural Stability Assessment Report

McElroy s Run Impoundment Structural Stability Assessment Report Allegheny Energy Supply Company, LLC A FirstEnergy Company Pleasants Power Station Pleasants County, West Virginia October 2016 Prepared for: Allegheny Energy Supply Company, LLC A FirstEnergy Company

More information

Pond Closure - Case Study[TP1]

Pond Closure - Case Study[TP1] 2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ Pond Closure - Case Study[TP1] By Pedro J Amaya, P.E. (1) (1) Civil Engineering and Geotechnical Engineering

More information

Geotechnical properties of zinc/lead mine tailings from Tara Mines, Ireland

Geotechnical properties of zinc/lead mine tailings from Tara Mines, Ireland Quille M.E. and O'Kelly B.C., Geotechnical properties of zinc/lead mine tailings from Tara Mines, Ireland, Proceedings ASCE GeoShanghai 21 Geoenvironmental Engineering and Geotechnics: Progress in Modeling

More information

BUREAU OF WATERSHED MANAGEMENT PROGRAM GUIDANCE. Feed Storage Area Runoff Controls for CAFOs X/X/2016. EGAD Number: 3800-XXXX-XX

BUREAU OF WATERSHED MANAGEMENT PROGRAM GUIDANCE. Feed Storage Area Runoff Controls for CAFOs X/X/2016. EGAD Number: 3800-XXXX-XX The Feed Storage Area Runoff Controls for CAFOs guidance was developed to provide assistance to the DNR Runoff Management Program, CAFO owners and operators, and consultants who work with CAFOs. The guidance

More information

Water Stewardship. Sustainable Mining CORPORATE WATER SUMMARY

Water Stewardship. Sustainable Mining CORPORATE WATER SUMMARY Water Stewardship. Sustainable Mining. 27 CORPORATE WATER SUMMARY GOLDCORP 27 CORPORATE WATER SUMMARY INTRODUCTION At Goldcorp, we recognize water stewardship as a significant concern shared by our company

More information

Technical Memorandum Mine Plan of Operations Stormwater Assessment

Technical Memorandum Mine Plan of Operations Stormwater Assessment Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum Mine Plan of Operations Stormwater Assessment To: Kathy Arnold From: David R.

More information

Filter-Pressed Dry Stacking: Design Considerations Based on Practical Experience

Filter-Pressed Dry Stacking: Design Considerations Based on Practical Experience Filter-Pressed Dry Stacking: Design Considerations Based on Practical Experience C. Crystal and C. Hore SRK Consulting, Vancouver, British Columbia, Canada I. Ezama SRK Consulting, Salta, Salta, Argentina

More information