Export Limiting in Practice

Size: px
Start display at page:

Download "Export Limiting in Practice"

Transcription

1 Limiting in Practice James Hoare CEng MIET MEI BRE National Solar Centre -Associate Consultant LHW Partnership LLP - Partner 24th September 2014 Part of the BRE Trust

2 Limiting in Practice Grid Background Evolution Renewable & PV Development A Fictitious Application Example A Real Life Example Q&A

3 The UK Grid - Background Pre 1926 Decentralised System with local generating supply companies 1926 CEGB established with a Nationwide synchronised 132kV network kV Network established based around centralised power stations and decentralised demand customers Statistics at Privatisation in ,500 km 400 kv circuit, 9,800 km 275kV Circuit, 5250 km 132kV circuit. Essentially 1 GenCo (nearly no IPPs) 12 Regional Electricity companies Purpose with a centralised energy policy to get energy from Generators Consumers

4 The UK Grid 1989 The Electricity Act paved way for Privatisation in CEGB (Central Electricity Generating Board) broken up into National Grid (Transmission) & Powergen, National Power, Nuclear Electric with NGC controlling the Pumped Storage (principally Dinorwig / Ffestiniog) asset for emergency demand balancing. 12 Regional electricity Companies (now 6 DNOs) distributing from 132kV to 33/11 & LV customers. To that point both the transmission & distribution networks had ben designed and evolved for centralised and not local power generation

5 The UK Grid As part of 1989 Electricity Act introduced the NFFO (Non Fossil Fuel Obligation) a precursor to the RO (Renewables Obligation). The first tranche was October 1990 with a number of projects mainly Wind, Landfill Gas, Straw/Poultry litter & Hydro. (No PV) Local Cornwall projects were mainly wind Delabole Goonhilly Carland Cross St Breock Connecting these to the distribution network was uncomplicated, as though the network was designed for consumers, (not prosumers), the relative impact was minor, and plenty of generation capacity.

6 What is a Prosumer? A Prosumer is a term evolving in Europe to define an entity (domestic, commercial, public sector) that Produces energy & consumes Energy

7 The UK PV Industry First Grid tied PV System(s) were connected in 1994

8 The UK PV Industry year 2000 Total PV Connected Capacity c1mwp No FIT s or ROC s (nor in Germany) A large project was typically 12kWp G83 not in existence Largest UK PV programme at the time BP Solar Project Sunflower a 1098 kwp programme covering canopies on 76 UK petrol stations from 1996 to 2002

9 The UK PV Industry year 2015 Total PV Connected Capacity April 2015 c8gwp (8000 MWp) Circa 700,000 DNO grid connected Installations A large project is now MWp At peak PV output in July 2015 a sunny weekend day will meet c15% of UK early PM national demand (UK demand data - source gridwatch.templar.co.uk)

10 The UK PV Industry year 2015 The move from Centralised to Decentralised (prosumer) power generation, and the rapid growth of the Renewable market, has started to put pressure on the Distribution network that is evolving from consumer based demand system to a prosumer system. Consequently there are now network constraints on connecting DG

11 What is Network & Constraint? When the potential amount of locally generated electricity has reached a level when the DNO cannot accept any more without breaching its Licence conditions & ESQCR a constraint may be needed The solutions are impose an export constraint to limit the export of energy Upgrade the network to accommodate the requirement Currently The Electricity Regulator Ofgem s regulations means that the cost of network reinforcement for Distributed Generation Projects should be paid for by generator and not bill paying customers (DUOS). The DNO s have to enforce this.

12 ESQCR Electricity Safety Quality & Continuity Regulations Principal Stakeholders Reportable by Members of public, Meter operators, distribution and transmission companies, generators and suppliers Key aspect in context The DNO is licenced and legally bound to provide phase voltage to customers at 230V +/- 10% (ie between 207 & 253V) Demand Customers reduce voltage with increased demands, Prosumers can raise grid voltage with increased generation (G83/2 is 262V to allow 3% volts rise between DNO connection and

13 White Goods are built to work within ESQCR limits For European Harmonisation all electrical appliance are designed to work between 207 & 253V

14 White Goods are built to work within ESQCR limits For European Harmonisation all electrical appliance are designed to work between 207 & 253V A DNO can be prosecuted if for example was found to be caused by providing to a voltage outside ESQCR regulations

15 When is Limiting Network Reinforcement Required? The DNO may propose an export constraint or network reinforcement for 2 principal Reasons when you apply to connect a PV (or other DG system) 1. The voltage rise may put the network out of ESQRC compliance 2. The thermal capacity of the network has been reached If the network fault level has been reached, export constraint will not resolve the issue.

16 A Fictitious Worked Example to demonstrate the impact of export constraint, and options of how to manage the impact

17 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell

18 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell Assumed Annual Electricity Consumption c50,000 kwh Initial idea Install a 50kWp array to match annual consumption with a combination of onside consumption with some export

19 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell System Size 50 kwp System Annual generation 47,000 kwh Estimated On Site use 50% 50% Revenue from FITs,, Import offset Decent ROI & IRR To Proceed with project - No Planning needed, just DNO approval..

20 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell ENA Connection Application sent to DNO for 50kVA PV connection A few days later the DNO responds outlining You can connect a system to export 50kW Due to the level of existing DG connections in the area, network network upgrade costs in the order of 500,000 will be required, or you can connect a system that can export 20kW (KVA) with no additional reinforcement needed. NB Figures Entirely fictitious and fabricated

21 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell What do you do?

22 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell What do you do?

23 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell But what do you do?

24 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell The 2 key things you need to assimilate are 1. Relationship between kwp and real time kw system yield quantum. 1. On Site Energy Demand profile (if any) In context of ed Energy = Generated energy onsite demand

25 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell Generation Do annual / monthly yield and other such models help when there is an export constraint? Yes a bit, but in reality not very much

26 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell Generation

27 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell Generation PV Syst can output modeled Hourly generation data sets in CSV/Excel

28 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell Key Graph derived from PVSyst Hourly Generation

29 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell Key Graph derived from PVSyst Hourly Generation Mean operating output 11kW Max output 50kW Area under line Hours x % of max 50 kw = total kwh

30 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell Key Graph derived from PVSyst Findings PV System will be generating for 47% of year Max output is 50kW Average operating generation output is 11 kw (22%) (This is not generic and is project / location specific)

31 Fictitious Case Study 50 kwp Rooftop The Eden Project Offices, St Austell 20 kw limit total export Annual Hours of Unconstrained Outputs as a Percentage of Max 50kW Output Point for the example 50 kwp System where a 20kW export constraint will need to limit the outputs to keep within Unconstrained Output 20kW export 5 Periode gleit. Mittelw. (Unconstrained Output) Hours of Operation 250

32 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh none 0 100%

33 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh none 0 100%

34 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh none 0 100%

35 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 49kW %

36 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 48kW %

37 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 47kW %

38 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 46kW %

39 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 45kW

40 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 44kW %

41 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 43kW %

42 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 42kW %

43 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 41kW %

44 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 40kW %

45 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 39kW %

46 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 38kW %

47 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 37kW %

48 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 36kW %

49 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 35kW %

50 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 34kW %

51 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 33kW %

52 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 32kW %

53 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 31kW %

54 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 30kW %

55 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 29kW %

56 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 28kW %

57 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 27kW %

58 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 26kW %

59 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 25kW %

60 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 24kW %

61 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 23kW %

62 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 22kW %

63 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 21kW %

64 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW %

65 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW %

66 Conclusions from Model 84% of max yield in Cornwall with a 20kW export constraint on a 50kWp system is still probably higher than yields in North of England with no constraint There are lots of variables, so allowing sensitivity and contingency are important.

67 Model With on site Energy Demand 50kWp Array 20kW export Constraint On site Consumption

68 If Site Demand is added to the 50kwp system with an export constraint of 20kW max Assumption for model 5kW continuous at weekends (Sat & Sunday) Weekday model graded in incremental steps of 5kW (Historic HH consumption data is desirable if available) January sample HH Consumption Data

69 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW 0kW 84.0% 0kW

70 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW 0kW 84.0% 0kW

71 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW 5kW 5kW 88.1%

72 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW 10kW 5kW 90.5%

73 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW 15kW 5kW 92.5%

74 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW 20kW 5kW 94%

75 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW 25kW 5kW 95.1%

76 Max PV Gen Constraint On Site Demand (5d/weekend) % of Max 47 MWh 20kW 30kW 5kW 95.9%

77 Key Factors A Degree of sensitivity / contingency is required as both solar radiation and on site demands are intermittent and will vary year on year PVSyst estimates hourly outputs in kwh, so need to be careful when matching to on site demand as 1 kw for one hour = 1kWh (as does 0.5 kw for half an hour and 1.5KW for half an hour) Sensitivity needed The more consumption information the better Half hourly data, and a thorough energy consumption profile is helpful. (The more demand info the better)

78 Conclusions from Modeling The impact of network constraints is probably less than anticipated, and a larger array than anticipated may be possible. Choose a conservative and least optimistic solar dataset. Maybe use P90 irradiance data If you are modeling with historic Half Hourly consumption data remember this is historic and not assured year on year Allow contingency, and be cautious with energy yield projections the level of yield risk is higher than total export. If in doubt Ask BRE NSC for modeling assistance!

79 Limiting Case Study a 1.2 MWp Zero Rooftop Vegetable Storage Cambridgeshire 2013

80 Limiting Case Study a 1.2 MWp Zero Rooftop Vegetable Storage Cambridgeshire 2013 Large provider of parsnips to supermarkets Large onsite energy use for refrigeration DNO could not allow any export due to large wind farm on same circuit

81 Limiting Case Study a 1.2 MWp Zero Rooftop Vegetable Storage Cambridgeshire Undertook Modeling of 2 years historic consumption data Modeling showed 1.2MWp would provide 95% of maximum projected generation output with zero export constraint. System installed DNO Witness test on G59 & export limiting system Learning experience solar gain reduction on roof reduced energy consumption by a few %

82 Limiting Case Study a 1.2 MWp Zero Rooftop Vegetable Storage Cambridgeshire Commissioned March MWp 4,400 PV Modules 9 x 100 kw Inverters G59/2 Switchgear PLC based sensing Actuator & Controls

83 Limiting Case Study a 1.2 MWp Zero Rooftop Vegetable Storage Cambridgeshire Subsequent application to DNO for variable export allowance successful Site can export 97% of time, so nearly 100% of projected yield is attainable Ultimately Active Networks will prevail

84 Thank You Any Questions?

Green+ ELECTRICITY AUTHORITY OF CYPRUS. NER 300 European Program 2 nd call of proposals Zero Energy Mountains of Cyprus. Green

Green+ ELECTRICITY AUTHORITY OF CYPRUS. NER 300 European Program 2 nd call of proposals Zero Energy Mountains of Cyprus. Green ELECTRICITY AUTHORITY OF CYPRUS NER 300 European Program 2 nd call of proposals Zero Energy Mountains of Cyprus Green 1 About NER300 program About Green Project: Outline Green Project - General Overview

More information

The new role of DSO. David Trebolle Trebolle Manager, Active Networks and Network Analysis Applications Gas Natural Fenosa

The new role of DSO. David Trebolle Trebolle Manager, Active Networks and Network Analysis Applications Gas Natural Fenosa The new role of DSO David Trebolle Trebolle Manager, Active Networks and Network Analysis Applications Gas Natural Fenosa 1 1 About us Installed capacity: 15.443 MW 1- Figures at the end of 2011 2 Union

More information

ENABLING EMBEDDED GENERATION

ENABLING EMBEDDED GENERATION APRIL 2014 ENABLING EMBEDDED GENERATION Turning Australian electricity on its head WHAT IS EMBEDDED GENERATION? Energy supply systems around the world are being transformed by embedded (or distributed)

More information

La regulación del incierto futuro de los sistemas eléctricos

La regulación del incierto futuro de los sistemas eléctricos La regulación del incierto futuro de los sistemas eléctricos Foro XM-2017 El futuro de la energía eléctrica en Colombia 25 de mayo, Cartagena, Colombia Carlos Batlle https://energy.mit.edu/profile/carlos-batlle

More information

EXAMPLE TARIFF MID-SIZE COMMERCIAL

EXAMPLE TARIFF MID-SIZE COMMERCIAL SOLAR PV EXAMPLE TARIFF MID-SIZE COMMERCIAL CONTENTS 1 Contents 2 Introduction 3 Examples 4 Important 5 How to proceed Approved Installer Telephone 01843 855 019 1 INTRODUCTION A LITTLE ABOUT TARIFFS The

More information

Demystifying Rooftop Solar

Demystifying Rooftop Solar Demystifying Rooftop Solar Week 4 : Economics OLLI at Illinois Study Group Fall 2017 1:30 pm Tuesdays Blue Room Proposed Session Outline 1. Overview of solar power in general. How PV works with demos.

More information

npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme

npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme What s inside 3 Make money from the energy you generate An introduction to Feed In Tariffs 4-5 How it works Your

More information

Summary of Net Metered Projects as of June 30, Small Net Metered Projects as of 6/30/2016 Small Group Host Projects as of 6/30/2016

Summary of Net Metered Projects as of June 30, Small Net Metered Projects as of 6/30/2016 Small Group Host Projects as of 6/30/2016 Page 1 of 6 Summary of Net Metered Projects as of June 30, 2016 Small Net Metered Projects as of 6/30/2016 Small Group Host Projects as of 6/30/2016 Class # of Projects Capacity (kw) Annual Energy (kwh)

More information

Methodology for calculating subsidies to renewables

Methodology for calculating subsidies to renewables 1 Introduction Each of the World Energy Outlook scenarios envisages growth in the use of renewable energy sources over the Outlook period. World Energy Outlook 2012 includes estimates of the subsidies

More information

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS)

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS) SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS) This application, terms, and conditions, and Interconnection Agreement is for Xcel Energy customers requesting the installation of a small generation

More information

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India 450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India WEST BENGAL ELECTRICITY REGULATORY COMMISSION Cogeneration and Generation of Electricity

More information

Client Name/Presentation Title

Client Name/Presentation Title Client Name/Presentation Title MARCH 2 Introduction This presentation will address the following topics: Comparative levelized cost of energy for various technologies on a $/MWh basis, including sensitivities,

More information

GB regulatory approach RIIO price controls and distributed generation

GB regulatory approach RIIO price controls and distributed generation GB regulatory approach RIIO price controls and distributed generation October 2016 James Veaney Head of Connections and Constraints Management Background Much of network installed in 1950s and 60s with

More information

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence Consultation on Connecting Further Generation in Northern Ireland Call for Evidence 12 Table of Contents 1 Executive Summary... 3 2 Introduction... 6 2.1 Purpose of this Paper... 6 3 Alternative Connection

More information

Elmwood Golf Course Solar PV Initial Feasibility Study

Elmwood Golf Course Solar PV Initial Feasibility Study Elmwood Golf Course Solar PV Prepared by: SAC Consulting Contact: Email: Fiona Salter fiona.salter@sac.co.uk Phone: 0131 603 7513 Date: 27 th August 2015 1 Contents 1 Contents... 1 2 Introduction... 1

More information

Design of Grid Connected PV System Using Pvsyst

Design of Grid Connected PV System Using Pvsyst African Journal of Basic & Applied Sciences 9 (): 9-96, 017 ISSN 079-034 IDOSI Publications, 017 DOI: 10.589/idosi.ajbas.017.9.96 Design of Grid Connected PV System Using Pvsyst Rachit Srivastava and Vinod

More information

Open Networks Project

Open Networks Project Open Networks Project Charging Scenarios 16 August 2017 Document Ref: ON-WS4-P1 Charging Scenarios-170816 Restriction: None Document Control Version Control Version Issue Date Author Comments 2.0 16/08/17

More information

Northumbria Research Link

Northumbria Research Link Northumbria Research Link Walker, S. L. et al. (2005) 'Potential for microgeneration : study and analysis'. London: DTI, with Energy Saving Trust, Element Energy and E- Connect This report is available

More information

Renewable Energy - A technology overview and the new Feed in Tariffs. Jos Mister Energy Saving Trust

Renewable Energy - A technology overview and the new Feed in Tariffs. Jos Mister Energy Saving Trust Renewable Energy - A technology overview and the new Feed in Tariffs Jos Mister Energy Saving Trust Overview Renewable Technology Overview Generating electricity Generating heat Feed in Tariffs Clean Energy

More information

DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION

DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION TO THE COMMISSION FOR ELECTRICITY REGULATION Document No: DOC-140105-AIL 7/02/2000 Introduction: The Commission for Electricity Regulation (CER) have

More information

Reaching 100% Renewable Electricity Generation on Ovalau and Taveuni Islands in Fiji

Reaching 100% Renewable Electricity Generation on Ovalau and Taveuni Islands in Fiji Ministry of Economy Republic of Fiji Reaching 100% Renewable Electricity Generation on Ovalau and Taveuni Islands in Fiji Pre-feasibility Study Results December 2017 Context of National Policy and Nationally

More information

AGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM

AGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM AGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM BETWEEN AND (1) [Eastern / London / South Eastern] Power Networks plc Company Number [02366906 / 03929195

More information

Independent Power Producers (IPPs)

Independent Power Producers (IPPs) AGRI-SA Commodity Conference 2016 Independent Power Producers (IPPs) 26 February 2016 By: Title: W. Böhmer Regional Manager Eskom Grid Access Unit Overview of the presentation Introduction. Achievements

More information

Solar Photovoltaic Electricity Generation for Dairy Farms

Solar Photovoltaic Electricity Generation for Dairy Farms Improving the Welsh Dairy Supply Chain Solar Photovoltaic Electricity Generation for Dairy Farms www.ddc-wales.co.uk Dairy Development Centre Gelli Aur Carmarthen Carmarthenshire SA32 8NJ Telephone: 01554

More information

2016 Fall Reliability Conference MRO

2016 Fall Reliability Conference MRO 2016 Fall Reliability Conference MRO CAISO s Coordination, Tracking, and Monitoring Distributed Energy Resources Amber Motley; Manager, Short Term Forecasting November 2 nd, 2016 California ISO Overview

More information

Towards being a smart energy enabler - meeting customers expectations on the energy market. Annika Viklund, CEO Vattenfall Eldistribution, Sweden

Towards being a smart energy enabler - meeting customers expectations on the energy market. Annika Viklund, CEO Vattenfall Eldistribution, Sweden Towards being a smart energy enabler - meeting customers expectations on the energy market Annika Viklund, CEO Vattenfall Eldistribution, Sweden The European energy market is undergoing major changes Currently

More information

Gas Natural Fenosa s Experiences on Renewable Energy Integration

Gas Natural Fenosa s Experiences on Renewable Energy Integration Gas Natural Fenosa s Experiences on Renewable Energy Integration Julio Gonzalo García Asset Management 17 th October 2013 Outline 1.About us 2.Spanish Regulation 3.R+D projects 4.Conclusions 2 About us

More information

Engaging consumers in a decarbonized world with the right pricing

Engaging consumers in a decarbonized world with the right pricing Engaging consumers in a decarbonized world with the right pricing BEHAVE 2016 Coimbra, 9 th of September of 2016 Ana Quelhas Director of Energy Planning Department ana.quelhas@edp.pt Agenda Achieving decarbonization

More information

Tariffs January 1, 2017

Tariffs January 1, 2017 Tariffs January 1, 2017 Nova Scotia Power Inc. Tariffs & Regulations Approved by the Nova Scotia Utility and Review Board pursuant to The Public Utilities Act, R.S.N.S., 189,c.380 as amended Tariffs For

More information

Michael Sampson - June 21, Regulatory Challenges of Technical Innovation POWER SYSTEM TRANSFORMATION

Michael Sampson - June 21, Regulatory Challenges of Technical Innovation POWER SYSTEM TRANSFORMATION Michael Sampson - June 21, 2017 Regulatory Challenges of Technical Innovation POWER SYSTEM TRANSFORMATION Overview The Regulatory Challenges of Technical Innovation as seen on the Electric Power System

More information

Cost and Benefits of Embedded Generation in Ireland

Cost and Benefits of Embedded Generation in Ireland Cost and Benefits of Embedded Generation in Ireland September 2004 Report prepared for Sustainable Energy Ireland by: PB Power CONTENTS 1. Executive Summary 1 1.1 Representative Networks 2 1.2 Costs and

More information

Renewable energy: Investing in Africa

Renewable energy: Investing in Africa 1. Who is responsible for energy policy? 2. To what extent have generation, transmission and distribution activities been unbundled? 3. Who owns and operates the (grid-connected) generation, transmission

More information

RURAL ELECTRIFICATION USING RENEWABLE ENERGY SOURCES

RURAL ELECTRIFICATION USING RENEWABLE ENERGY SOURCES RURAL ELECTRIFICATION USING RENEWABLE ENERGY SOURCES Devesh M.Imade 1, Dr. Mangesh S.Thakare 2 1 Student, 2 Professor, 1,2, Department of Electrical Engineering Pune VidyarthiGriha s College of Engg. &

More information

Automatic Meter Reading

Automatic Meter Reading Automatic Meter Reading Technology with benefits Peter Kjeldmann Development Adviser Content Why AMR What is AMR? AMR technology Advantages of AMR Sarfannguaq and Qinngorput Perspectives of AMR Reasons

More information

10 years Renewable Energy Sources Act (EEG) - Lessons learned

10 years Renewable Energy Sources Act (EEG) - Lessons learned Energy 10 years Renewable Energy Sources Act (EEG) - Lessons learned November 9 th 2010, Lisbon, Portugal Christoph Urbschat, Partner eclareon GmbH Management Consultants on behalf of the German Federal

More information

MAUI SMART GRID PROJECT

MAUI SMART GRID PROJECT MANAGING DISTRIBUTION SYSTEM RESOURCES FOR IMPROVED SERVICE QUAILTY AND RELIABILTY, TRANSMISSION CONGESTION RELIEF, AND GRID SUPPORT FUNCTIONS MAUI SMART GRID PROJECT or Hawaii Natural Energy Institute

More information

Communication and Control for Microgrid Optimal Energy Efficiency

Communication and Control for Microgrid Optimal Energy Efficiency Communication and Control for Microgrid Optimal Energy Efficiency Rui Zhou, Sumit Bose, Santosh Veda Oct 10 th 2013 GE Global Research RPI Microgrid Workshop Overview Microgrid Characteristics Microgrid

More information

SOLAR IN ACTION. There are three basic types of solar voltaic systems:

SOLAR IN ACTION. There are three basic types of solar voltaic systems: SOLAR POWER BASICS The most common solar technologies used on buildings in the United States are solar photovoltaic (PV) panels, which generate electricity. An individual PV cell is usually small, typically

More information

Smart energy systems and the role of Power-to-Gas

Smart energy systems and the role of Power-to-Gas ENERGY Smart energy systems and the role of Power-to-Gas European Power-To-Gas Platform, second meeting 2016 Rob van Gerwen 1 SAFER, SMARTER, GREENER Role of Power-to-Gas Smart Energy Systems and the Energy

More information

Connecting New Generation in New Zealand. Len Gould Customer Services Manager Transpower New Zealand Ltd

Connecting New Generation in New Zealand. Len Gould Customer Services Manager Transpower New Zealand Ltd Connecting New Generation in New Zealand Len Gould Customer Services Manager Transpower New Zealand Ltd Outline New Zealand s power system & Transpower s roles The planning process for new generation The

More information

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems SUBCHAPTER 9 NET METERING AND INTERCONNECTION STANDARDS FOR CLASS I

More information

Renewable Energy in The Netherlands October 2016

Renewable Energy in The Netherlands October 2016 Renewable Energy in The Netherlands October 2016 Dr. Martien Visser Professor Energy Transition & Network Integration Hanze University of Applied Sciences Groningen Partner of the Energy Academy Europe

More information

Welcome / Bienvenue. RETScreen Training Institute RETScreen 101 Introduction to Clean Energy Project Analysis

Welcome / Bienvenue. RETScreen Training Institute RETScreen 101 Introduction to Clean Energy Project Analysis Welcome / Bienvenue RETScreen Training Institute RETScreen 101 Introduction to Clean Energy Project Analysis Hundreds Gather To Fight Global Warming! RETScreen s Mission: Empower Cleaner Energy Decisions

More information

Country Report Germany

Country Report Germany Country Report Germany IEA Task 14 Meeting Tokyo, October 30th Thomas Stetz (thomas.stetz@iwes.fraunhofer.de) Agenda Current Situation in Germany A Brief Research Overview for Germany An Example for High

More information

RES - Status Quo, Potential and Prospects Vasileios Tsolakidis, CRES

RES - Status Quo, Potential and Prospects Vasileios Tsolakidis, CRES RES - Status Quo, Potential and Prospects Vasileios Tsolakidis, CRES 20 June 2017, Thessaloniki Greek energy sector 2 Source: Eurostat (2017) RES targets Directive 2009/28/EC Gross final energy consumption

More information

Getting Smart Answers! Kevin W. Chiu. Siemens AG

Getting Smart Answers! Kevin W. Chiu. Siemens AG Getting Smart Answers! Siemens AG Getting Smart Answers Answers to What Questions? Page 2 Distribution of Population Source: Census from various countries Page 3 Projected Population Growth Source: UN

More information

Consumer s Guide to Solar Power

Consumer s Guide to Solar Power Consumer s Guide to Solar Power JEA Consumer s Guide to Solar Power What is Solar Energy? 3 Benefits of Solar Power 3 JEA Solar Programs 4 Types of Solar Energy Systems 6 Is Solar Right for You? 10 Installation

More information

OVERVIEW OF MUNICIPAL ROOFTOP PV INSTALLATION. Local Government Energy Support NETWORK MEETING October 2014

OVERVIEW OF MUNICIPAL ROOFTOP PV INSTALLATION. Local Government Energy Support NETWORK MEETING October 2014 OVERVIEW OF MUNICIPAL ROOFTOP PV INSTALLATION Local Government Energy Support NETWORK MEETING 30 31 October 2014 Background Rising electricity prices and fast reducing solar PV panels makes PV generation

More information

New England Electricity Outlook

New England Electricity Outlook O C T O B E R 2 1, 2 0 1 6 S O U T H P O R T L A N D, M E New England Electricity Outlook Environmental and Energy Technology Council of Maine (E2Tech) Eric Johnson D I R E C T O R, E X T E R N A L A F

More information

01/11/2010. Transmission issues for the Future. Mechanisms to Promote Renewable Energy

01/11/2010. Transmission issues for the Future. Mechanisms to Promote Renewable Energy NBS-M9 21 LOW CARBON BUSINESS REGULATION AND ENTREPRENEURSHIP Transmission issues for the Future Mechanisms to Promote Renewable Energy Non Fossil Fuel Obligation Renewable Obligation Marine Supply Obligation

More information

Accommodating High Levels of Distributed Energy Resources

Accommodating High Levels of Distributed Energy Resources Accommodating High Levels of Distributed Energy Resources John Moura, Director of Reliability Assessment and System Analysis 2017 NARUC Winter Committee Meetings February 14, 2017 About NERC: Mission To

More information

Con Edison. Evolution of Con Edison efforts in Energy Efficiency and Demand Management:

Con Edison. Evolution of Con Edison efforts in Energy Efficiency and Demand Management: Evolution of Con Edison efforts in Energy Efficiency and Demand Management: Innovative programs and technologies, and their impacts on customers, contractors and the markets Con Edison Con Edison - Overview

More information

The value of storage. Chris Elliott Senior Hydropower Engineer. 8 th November 2016

The value of storage. Chris Elliott Senior Hydropower Engineer. 8 th November 2016 The value of storage Chris Elliott Senior Hydropower Engineer 8 th November 2016 Overview Stroud, Gloucestershire Hydro is largest part of the business High and Low head systems Design Install Maintain

More information

DSR follow on final presentation

DSR follow on final presentation DSR follow on final presentation A presentation to DECC Andrew Nind, Oliver Pearce, Kostas Theodoropoulos 4 April 2011 Agenda 1. Objectives 2. Scenario assumptions 3. Scenario results 4. Next steps 2 Objectives

More information

Review of Analysis of Network Benefits from Smart Meter Message Flows

Review of Analysis of Network Benefits from Smart Meter Message Flows Review of Analysis of Network Benefits from Smart Meter Message Flows (Including RIIO ED1 and ED2 phasing and categorisation of benefits) 1 st July 2013 Version 1.0 1 Page 2 of 15 Review of Analysis of

More information

SOLAR PV STC ASSIGNMENT FORM

SOLAR PV STC ASSIGNMENT FORM Company / Agent / Installer Logo SOLAR PV STC ASSIGNMENT FORM MANDATORY FORM FIELDS 1 OWNER S DETAILS First Surname: Postal Address: State Postcode Telephone: (w) (h) Fax: (w) (h) Mobile: Email: 2 INSTALLATION

More information

GRID INTEGRATION OF PV

GRID INTEGRATION OF PV GRID INTEGRATION OF PV Dr.-Ing. Bernhard Wille-Haussmann Fraunhofer Institute for Solar Energy Systems ISE 6th PV Performance Modeling and Monitoring Workshop 24 th October 2016 AGENDA The Challenge Solutions

More information

e l r a Project Cost Benefit Analysis September Voltage Optimisation

e l r a Project Cost Benefit Analysis September Voltage Optimisation s k r o w et N e bon Future l r a C b i w o x L Fle for a Project Cost Analysis - Voltage Optimisation September 2015 Part A Costs of the trial and future roll-out 1. Introduction This document provides

More information

Acreage Needed in 2050 for Renewable Generation to Meet California s GHG Emission Reduction Goals California Energy Commission May 9, 2011

Acreage Needed in 2050 for Renewable Generation to Meet California s GHG Emission Reduction Goals California Energy Commission May 9, 2011 Acreage Needed in 2050 for Renewable Generation to Meet California s GHG Emission Reduction Goals California Energy Commission May 9, 2011 The Energy Commission has developed a calculator to assist the

More information

A SIMPLE MODEL OF DOMESTIC PV SYSTEMS AND THEIR INTEGRATION WITH BUILDING LOADS. Steven K. Firth, Richard A. Buswell and Kevin J.

A SIMPLE MODEL OF DOMESTIC PV SYSTEMS AND THEIR INTEGRATION WITH BUILDING LOADS. Steven K. Firth, Richard A. Buswell and Kevin J. Eleventh International IBPSA Conference Glasgow, Scotland July 7-3, 9 A SIMPLE MODEL OF DOMESTIC PV SYSTEMS AND THEIR INTEGRATION WITH BUILDING LOADS Steven K. Firth, Richard A. Buswell and Kevin J. Lomas

More information

GEOS / ENST Problem set #Grid Due: Tues. May 18

GEOS / ENST Problem set #Grid Due: Tues. May 18 GEOS 24705 / ENST 24705 Problem set #Grid Due: Tues. May 18 Problem 1: Three-phase power transmission The standard means by which electricity is transmitted in the U.S. is as 3-phase AC power. Each of

More information

Solar Power Realities

Solar Power Realities Solar Power Realities Supply-Demand Characteristics, Storage and Capital Costs by Peter Lang Abstract This paper provides a simple analysis of the capital cost of solar power and energy storage sufficient

More information

TasNetworks Transformation Roadmap 2025

TasNetworks Transformation Roadmap 2025 DRAFT TasNetworks Transformation Roadmap 2025 JUNE 2017 Trusted by our customers to deliver today and create a better tomorrow 2 TasNetworks Transformation Roadmap 2025 June 2017 Purpose We deliver electricity

More information

Report of Energy Reform Committee, National Reform Council Quick Win Proposal for Solar PV Rooftops for Residential and General Buildings

Report of Energy Reform Committee, National Reform Council Quick Win Proposal for Solar PV Rooftops for Residential and General Buildings Unofficial GIZ Translation of the Report of Energy Reform Committee, National Reform Council Quick Win Proposal for Solar PV Rooftops for Residential and General Buildings Original legal document: http://library2.parliament.go.th/giventake/content_nrc2557/d010558-01.pdf

More information

PV AND OTHER RENEWABLES THE FINANCIAL ADVANTAGE

PV AND OTHER RENEWABLES THE FINANCIAL ADVANTAGE PV AND OTHER RENEWABLES THE FINANCIAL ADVANTAGE Different Types of Renewables Most popular types: Solar, Wind & Biogas. Solar - uses the sun to generate electricity. Advantages: Sun is free. Passive source

More information

Bosch Energy Storage Solutions Smart integration of storage

Bosch Energy Storage Solutions Smart integration of storage Smart integration of storage Agenda 1. Energy Storage: Business field of Robert Bosch GmbH 2. : Introduction 3. Application cases for storage and references 4. Energy Management System: The brain of our

More information

Public Utility Regulatory Policy Act Standards

Public Utility Regulatory Policy Act Standards Document Type: EA Administrative Record Index Field: Final Environmental Document Project Name: PURPA Standards Project Number: 2007-4 FINAL ENVIRONMENTAL ASSESSMENT TENNESSEE VALLEY AUTHORITY Public Utility

More information

Energy Conserving Electrical Design and Analysis for Commercial Buildings

Energy Conserving Electrical Design and Analysis for Commercial Buildings J. Energy Power Sources Vol. 1, No. 2, 2014, pp. 79-89 Received: July 3, 2014, Published: August 30, 2014 Journal of Energy and Power Sources www.ethanpublishing.com Energy Conserving Electrical Design

More information

AN ASSESSMENT OF ENERGY AND EMISSIONS PERFORMANCE OF BUILDINGS AT TEACHERS MUTUAL BANK LTD

AN ASSESSMENT OF ENERGY AND EMISSIONS PERFORMANCE OF BUILDINGS AT TEACHERS MUTUAL BANK LTD AN ASSESSMENT OF ENERGY AND EMISSIONS PERFORMANCE OF BUILDINGS AT TEACHERS MUTUAL BANK LTD AUGUST 2016 Overview Teachers Mutual Bank Ltd, which includes Teachers Mutual Bank and Unibank, has invested significantly

More information

Energex. Tariff Structure Statement. 1 July 2017 to 30 June Energex s Tariff Structure Statement

Energex. Tariff Structure Statement. 1 July 2017 to 30 June Energex s Tariff Structure Statement Energex Tariff Structure Statement 1 July 2017 to 30 June 2020-1- Energex s 2017-20 Tariff Structure Statement Version control Version Date Description V.1 27 November 2015 TSS proposal submitted to the

More information

Patrick McHugh. Vice President Con Edison

Patrick McHugh. Vice President Con Edison Patrick McHugh Vice President Con Edison Agenda BQDM overview Utility-sided storage project Customer-sided storage project Marcus Garvey Clean virtual power plant Storage demonstration portfolio DR Auction

More information

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM January 2017 PRESENTED BY JENNY RIESZ SLIDE 1 AGENDA 1. Introduction to the NEM 2. Future Power System Security Program 3. Identifying

More information

MICRO-GENERATION IN YUKON

MICRO-GENERATION IN YUKON MICRO-GENERATION IN YUKON AN EXAMINATION OF PROGRAM IMPLICATIONS AFTER THREE YEARS OF OPERATION Copyright 2016 Energy branch, Department of Energy Mines and Resources, Government of Yukon Table of Contents

More information

Available online at ScienceDirect. Energy Procedia 50 (2014 )

Available online at  ScienceDirect. Energy Procedia 50 (2014 ) Available online at www.sciencedirect.com ScienceDirect Energy Procedia 50 (2014 ) 581 588 The International Conference on Technologies and Materials for Renewable Energy, Environment and Sustainability,

More information

Egyptian Renewable Energy plan

Egyptian Renewable Energy plan Ministry of Electricity and Renewable Energy Egyptian Holding Electricity company Egyptian Renewable Energy plan Eng.Ahmed Abo salem Contents 1 Current Status of the Egyptian Grid 2 Current Status of Renewable

More information

Importance of Intra-day Forecasts in Renewable Energy Sector to Reduce Imbalance & Congestion Costs in UK Power Grid

Importance of Intra-day Forecasts in Renewable Energy Sector to Reduce Imbalance & Congestion Costs in UK Power Grid January 218 Importance of Intra-day Forecasts in Renewable Energy Sector to Reduce Imbalance & Congestion Costs in UK Power Grid Mridul Chadha (Consultant Power Solutions) at Climate Connect Limited Since

More information

High School Lesson Plan: Photovoltaic Power Potential

High School Lesson Plan: Photovoltaic Power Potential High School Lesson Plan: Photovoltaic Power Potential 1. Introduction A. Author: Michael Cartwright B. Rationale: Physics students should be exposed to all kinds of physics applications. Renewable energy

More information

Smart Meters The Impact on Customer Service Operations

Smart Meters The Impact on Customer Service Operations Smart Meters The Impact on Customer Service Operations James Barnes Utility Customer Service Administrator City of Tallahassee Utilities Copyright 2010 Accenture All Rights Reserved. Accenture, its logo,

More information

Sustainable Energy for All (SE4ALL) Action Agenda for Ghana. Presented By: Gifty Delali Tettey (Mrs.) Deputy Director Ministry of Power

Sustainable Energy for All (SE4ALL) Action Agenda for Ghana. Presented By: Gifty Delali Tettey (Mrs.) Deputy Director Ministry of Power Sustainable Energy for All (SE4ALL) Action Agenda for Ghana Presented By: Gifty Delali Tettey (Mrs.) Deputy Director Ministry of Power Outline Ghana Overview Ghana s Energy Situation Policy Objectives

More information

AEP Ohio. Combined Heat and Power (CHP) May 24 th, 2017 Steve Giles Vice President Alternative Energy Hull & Associates, Inc.

AEP Ohio. Combined Heat and Power (CHP) May 24 th, 2017 Steve Giles Vice President Alternative Energy Hull & Associates, Inc. AEP Ohio Combined Heat and Power (CHP) May 24 th, 2017 Steve Giles Vice President Alternative Energy Hull & Associates, Inc. OUR MARKET AREAS Shale Oil & Gas Waste Management PROJECT DEVELOPMENT AND ASSET

More information

Integration of the hidden refrigeration capacity as a heat pump in smart energy systems

Integration of the hidden refrigeration capacity as a heat pump in smart energy systems Integration of the hidden refrigeration capacity as a heat pump in smart energy systems Torben Funder-Kristensen This presentation outlines the concepts behind the Danish EUDP-project (64016-0106) Super

More information

Energy Efficient Solar Milk Chiller

Energy Efficient Solar Milk Chiller Energy Efficient Solar Milk Chiller Muneeb Bin Muzzamal Abstract: Life stock is the major sector of agriculture which is of great importance for Pakistan. It has a major contribution towards the economy

More information

2015 Summary of Connecticut Electric Rates Last Updated: December 1, 2015

2015 Summary of Connecticut Electric Rates Last Updated: December 1, 2015 2015 Summary of Connecticut Electric Rates Last Updated: December 1, 2015 The following rates are available to customers and have been approved by the State of Connecticut Public Utilities Regulatory Authority.

More information

Summary of Connecticut Electric Rates Last Updated: January 1, 2018

Summary of Connecticut Electric Rates Last Updated: January 1, 2018 Summary of Connecticut Electric Rates Last Updated: January 1, 2018 The following rates are available to customers and have been approved by the State of Connecticut Public Utilities Regulatory Authority.

More information

An Energy Bill Proposal for the State of Colorado. BGE Consulting Angela Cook Erica Johnson Nick Goldstein Chris Bunch Jake Walter Kindra Priest

An Energy Bill Proposal for the State of Colorado. BGE Consulting Angela Cook Erica Johnson Nick Goldstein Chris Bunch Jake Walter Kindra Priest An Energy Bill Proposal for the State of Colorado BGE Consulting Angela Cook Erica Johnson Nick Goldstein Chris Bunch Jake Walter Kindra Priest Introduction The following report contains a realistic balanced

More information

Anchorage Alaska Solar Tour: Saturday, June 17th, 2017 Tour Starts At 10am

Anchorage Alaska Solar Tour: Saturday, June 17th, 2017 Tour Starts At 10am Please visit alaskasolartour.org for updates on this tour Anchorage Alaska Solar Tour: Saturday, June 17th, 2017 Tour Starts At 10am Sites Times Building Address Area of town Site #1 10 10:45am CIRI Office

More information

Using Clean Energy to Reshape the Way We Generate, Distribute, and Consume Electricity

Using Clean Energy to Reshape the Way We Generate, Distribute, and Consume Electricity 8FUTURE GRID Using Clean Energy to Reshape the Way We Generate, Distribute, and Consume Electricity Presented by: John Kelly, Director, Distributed Energy May 15, 2003 Midwest CHP Initiative Midwest Application

More information

SOLAR PV FROM OUTSIDE THE EU: TURKEY S POTENTIAL SEDAT YILDIRIM, GÜNDER

SOLAR PV FROM OUTSIDE THE EU: TURKEY S POTENTIAL SEDAT YILDIRIM, GÜNDER SOLAR PV FROM OUTSIDE THE EU: TURKEY S POTENTIAL SEDAT YILDIRIM, GÜNDER Date, name This project has received funding from the European Union s Horizon 2020 research and innovation programme under grant

More information

Readying States for New Greenhouse Gas Rules in the Electricity Sector

Readying States for New Greenhouse Gas Rules in the Electricity Sector Readying States for New Greenhouse Gas Rules in the Electricity Sector Sue Tierney Analysis Group National Governors Association Workshop for Governors Energy Advisors September 22, 2014 BOSTON CHICAGO

More information

TOWN OF NEWPORT SOLAR PROJECT A 2-MEGAWATT DC NET-METERED PV SYSTEM

TOWN OF NEWPORT SOLAR PROJECT A 2-MEGAWATT DC NET-METERED PV SYSTEM TOWN OF NEWPORT SOLAR PROJECT A 2-MEGAWATT DC NET-METERED PV SYSTEM AN HISTORIC PROJECT NH s Largest Municipal Solar Project Town & Schools Would Be Net-Zero 2 AN HISTORIC PROJECT The largest municipal

More information

Design Installation and Testing of 1.6 kwp GPV System

Design Installation and Testing of 1.6 kwp GPV System Design Installation and Testing of 1.6 kwp GPV System Napat Watjanatepin Rajamangala University of Technology Suvarnabhumi Nonthaburi Campus THAILAND Phone:+66-2969-1521, Fax:+66-2525-2682 Email:watjanatepin@yahoo.com

More information

Independent Power Production Policy

Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy October 2015 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy

More information

Active Distribution Networks

Active Distribution Networks Active Distribution Networks Nikos Hatziargyriou nh@power.ece.ntua.gr NTUA, Greece Distributed Generation Technologies Examples Advanced Turbines Reciprocating Engines Fuel Cells Photovoltaics Wind Thermally

More information

Linear Programming Approach to the Residential Load Energy Management System

Linear Programming Approach to the Residential Load Energy Management System Linear Programming Approach to the Residential Load Energy Management System Sunny Prakash 1, Punya 2 1,2 Department of EEE, Acharya Nagarjuna University Abstract: This paper proposes an effective method

More information

Protection Solutions for Embedded Power Plants & Renewables

Protection Solutions for Embedded Power Plants & Renewables Protection Solutions for Embedded Power Plants & Renewables Combined Heat & Power Combined heat & power (CHP) consists of an engine or turbine as its prime mover, driving an alternator (electrical generator).

More information

Tackling Tariff Design. Making distribution network costs work for consumers

Tackling Tariff Design. Making distribution network costs work for consumers Tackling Tariff Design Making distribution network costs work for consumers Contents Introduction 02 What s driving change? 05 Alternative tariff designs 07 Impacts on consumers bills 11 Reflections and

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org C5-1036 AORC Technical meeting 2014 Solar PV Rooftop System Connection to MEA s Distribution Network: Technic and Economic Aspects Tosak Thasananutariya Metropolitan Electricity

More information

SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM

SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM (Thailand, July 2013) The Thai government has recently introduced a generous subsidy scheme involving Feed in Tariffs. This means that you get paid a premium rate

More information

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh) For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold

More information

Distribution Value Added

Distribution Value Added Distribution Value Added Eng.. Carlos A. Pérez P MéndezM 1 CONTENTS 1. Introduction 2. How to calculate DVA 3. Costs by Voltage Levels 4. Required Revenue 5. NRV Optimization 6. Grid Operation Costs 2

More information