APPENDIX E PROJECT EVALUATION SUMMARY TABLE
|
|
- Randolf Park
- 6 years ago
- Views:
Transcription
1 APPENDIX E PROJECT EVALUATION SUMMARY TABLE
2 This page left blank intentionally.
3 Table of Contents E.1 INTRODUCTION... E-1 E.2 SURFACE WATER STORAGE SWRP COMPONENT EVALUATION SUMMARY... E-7 E.3 WATERSHED MANAGEMENT SWRP COMPONENT EVALUATION SUMMARY... E-9 E.4 STORMWATER MANAGEMENT SWRP COMPONENT EVALUATION SUMMARY... E-19 E.4.1 Structural... E-19 E.4.2 Non-Structural... E-33 LIST OF TABLES Table E.1 Example of Evaluation Summary Table... E-1 Table E.2 Example of Evaluation Summary Table - Sum of Criteria per Benefit Category... E-3 Table E.3 Overall Benefit Category Scores... E-4 Table E.4 Example of Evaluation Summary Table Overall Benefit Category Score.. E-5 Table E.5 Benefit Category Weights... E-5 Table E.6 Example of Evaluation Summary Table Weighted Score... E-6 i
4 This page left blank intentionally. ii
5 E.1 INTRODUCTION This appendix shows the summary of the project evaluation outcomes discussed in Appendix D. Table E.1 shows an example of a Evaluation Summary table. Table E.1 Example of Evaluation Summary Table Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name Type Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows and habitat protection and improvement Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way XXX EXAMPLE XXX A, B or C E-1
6 This page left blank intentionally. E-2
7 As discussed in Appendix D, each identified project is grouped by component and given a project ID. types were also assigned. More discussion on the project types and the overall evaluation approach can be found in Section 4 of the West Slope Stormwater Resource Plan (SWRP). Table E.1 shows an example score assigned to each criterion. The criteria scores range from 0 to 3, where 0 is generally not applicable and 3 is highest benefit. Table E.2 shows the sum of criteria scores are for this example project. Table E.2 Example of Evaluation Summary Table - Sum of Criteria per Benefit Category Sum of Criteria per Benefit Category Benefit Category Water Quality Water Supply Flood Cost Implementation Complexity In order to compare the benefit category scores for a project, the summed scores were normalized to a 0 to 3 range, where 0 is the lowest score and 3 is the highest score. Normalization allows for comparison between benefit category scores that are measured using different number of criteria. If a project had no benefits in a given benefit category, it received a 0. If only one criteria was applicable in a benefit category and scored a 1, then the normalized score would be 1. If all criteria in a benefit category were applicable and all scored 3, then the normalized score was 3. Table E.3 shows the possible sum of criteria scores per benefit category and the normalized overall benefit category score for each benefit category. For example, in Table E.2 the sum of criteria scores for Water Supply and Flood is 3. Referencing Table E.3, the overall benefit category score is normalized to 1.5 for Water Supply and 1.8 for Flood. Even though the benefit category score for Water Supply and Flood is 3, Water Supply and Flood benefit categories have different number of criteria so the possible sum of criteria scores and the normalization of overall benefit category score will be different. E-3
8 Table E.3 Overall Benefit Category Scores Sum of Criteria Score per Benefit Category Water Quality Water Supply Flood Overall Benefit Category Score Cost Implementation Complexity *Gray cells represent not applicable sum of criteria scores per benefit category E-4
9 Table E.4 shows the sum of criteria scores are calculated in Table E.2 for each benefit category normalized to an overall benefit category score for each benefit category based on Table E.3. After the overall benefit category score is calculated for the project, the weighted score for the project can be calculated using benefit category weights. Table E.4 Example of Evaluation Summary Table Overall Benefit Category Score Overall Benefit Category Score Water Quality Water Supply Flood Benefit Category Cost Implementation Complexity Benefit category weights, shown in Table E.5, were developed using a paired comparison analysis to determine the relative importance of each benefit category used in the West Slope SWRP. Development of benefit category weights is discussed in further detail in Section 4 and Appendix C of the West Slope SWRP. To calculate the project weighted score, the overall benefit category score is multiplied by the respective benefit category weight. Table E.6 shows the calculation of the example project weighted score in Table E.1. After the project weighted score are calculated, projects are organized within each component relative to their weighted score. Table E.5 Benefit Category Weights Benefit Category Water Quality Water Supply Flood Cost Implementation Complexity Benefit Category Weight* 15% 23% 11% 14% 10% 18% 9% *Reference: Development of benefit category weights is discussed in further detail in Section 4 and Appendix C of the West Slope SWRP. E-5
10 Table E.6 Example of Evaluation Summary Table Weighted Score Benefit Category Water Supply Flood Cost Implementation Complexity Weighted Score Overall Benefit Category Score Benefit Category Weight Weighted Score per Benefit Category n/a 15% 23% 11% 14% 10% 18% 9% n/a s are grouped into A, B or C group based on their weighted score within a given component. s in the A group received one of the top third weighted scores, projects in the B group received one of the middle third weighted scores, and projects in the C group received one of the bottom third weighted scores within a given component. A group projects typically have the highest potential to provide the greatest multi-benefits, B projects have moderate potential, and C projects have less potential. For a more accurate comparison between projects, the Stormwater component projects were evaluated based on whether they were Structural and Non-Structural projects. Further discussion on the types of projects identified as Structural and Non-Structural under the Stormwater Component may be found in Section 4.1 of the West Slope SWRP. The following sections summarizes the project evaluations per project type under each of the components: Surface Water Storage, Watershed and Stormwater (Structural and Non- Structural). E-6
11 E.2 SURFACE WATER STORAGE SWRP COMPONENT EVALUATION SUMMARY Surface Water Storage SWRP Component Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID 100 Name Alder Reservoir 104 Silver Lake Dam Remediation Proponent El Dorado County Water Agency El Dorado Irrigation District Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows Reservoir Creation and habitat protection and improvement A Reservoir Upgrade C Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way E-7
12 This page left blank intentionally. E-8
13 E.3 WATERSHED MANAGEMENT SWRP COMPONENT EVALUATION SUMMARY Watershed SWRP Component Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name 209 King Fire Watershed Restoration & Reforestation 210 Sand Fire Watershed Restoration & Reforestation 200 Biomass Plant- Union Mine 221 Camino Biomass Facility Proponent El Dorado County & Georgetown Divide Resource Conservation El Dorado County & Georgetown Divide Resource Conservation El Dorado County Water Agency El Dorado 213 Anaerobic El Digestion System Dorado at Union Mine WWTP 214 In-Vessel Composting System at Union Mine Landfill or MRF El Dorado 215 Compost Facility within El Dorado County Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Fire Restoration Reduced sanitary sewer overflows and habitat protection and improvement B B Renewable Energy A A B C El Dorado C Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way E-9
14 This page left blank intentionally. E-10
15 Watershed SWRP Component Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name 220 Caples Watershed Improvement Proponent Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Forest Reduced sanitary sewer overflows U.S. Forest Service A and habitat protection and improvement Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way 219 Fire Adaptive along Highway 50-Fuels Reduction U.S. Forest Service A Pompeii Fire Salvage Stewardship 232 Quidazoic Fire Salvage Stewardship 234 King Fire Pile Burning 229 Cesar Fire Salvage Stewardship U.S. Forest Service A U.S. Forest Service A U.S. Forest Service A U.S. Forest Service A John Don t Fuels Reduction U.S. Forest Service 226 Western U.S. Forest Georgetown Fuel Service Reduction Integrated Resource Timber Contract-Timber Sale A B Georgetown U.S. Forest Divide Fuelbreak Service B Jenkinson Lake Fuels Reduction U.S. Forest Service 235 Tobacco Gulch Integrated U.S. Forest Service Resource Timber Contract-Timber Sale & Thinning B B E-11
16 This page left blank intentionally. E-12
17 Watershed SWRP Component Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name Proponent Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows Forest (contd.) and habitat protection and improvement Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way Chaix Fire Thinning U.S. Forest Service 223 Two-fer Integrated U.S. Forest Service Resource Timber Contract-Timber Sale B B Fred s Noxious U.S. Forest Weed Treatment-Service Vegetation C Reservoir Thinning Integrated U.S. Forest Service Resource Timber Contract 225 Quintette U.S. Forest Integrated Service Resource Timber Contract Supplemental Information Report-Timber Sale 238 Trestle Integrated U.S. Forest Service Resource Timber Contract-Timber Sale C C C E-13
18 This page left blank intentionally. E-14
19 Information Result Overall Benefit Category Score Water Supply Watershed SWRP Component Flood Cost Implementation Complexity ID Name Proponent 237 O leary Cow Integrated Resource U.S. Forest Service Service Contract/ Integrated Resource Timber Contract-Timber Sale & Thinning 239 Georgetown Insect Salvage Timber Sale 222 General Sherman Integrated U.S. Forest Service Resource Timber Contract-Timber Sale 240 Middle Creek U.S. Forest Integrated Service Resource Timber Contract-Timber Sale & Fuels Reduction Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows Forest (contd.) and habitat protection and improvement C U.S. Forest Service C C C Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way E-15
20 This page left blank intentionally. E-16
21 Information Result Overall Benefit Category Score Water Supply Watershed SWRP Component Flood Cost Implementation Complexity ID Name Residual Lime Remediation near El Dorado Trail Slate Creek Monitoring Cosumnes River Monitoring Program Countywide Monitoring 208 Weber Creek Restoration 206 Carson Creek Restoration 207 New York Creek Restoration Proponent El Dorado El Dorado American River Conservancy El Dorado El Dorado El Dorado El Dorado Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows and habitat protection and improvement B B C C Creek Restoration A A A Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way E-17
22 This page left blank intentionally. E-18
23 E.4 STORMWATER MANAGEMENT SWRP COMPONENT EVALUATION SUMMARY E.4.1 Structural Stormwater SWRP Component Structural Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name Fairgrounds Improvements Countywide Park BMP Retrofit Improvements Sly Park Portal Subdivision Flood Canal Street LID s Town of El Dorado Green Street Stormwater Detention Basin- Hangtown Creek Flood Damage Reduction South East Connector- Expressway LID s Proponent Planning Area El Commu Dorado nities Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Water Capture Reduced sanitary sewer overflows and habitat protection and improvement A El Other A Dorado Farm El Trail Dorado East City of Placerville Commu nities El Commu Dorado nities City of Placerville Commu nities El El Dorado Dorado Hills South A A A A B Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way E-19
24 This page left blank intentionally. E-20
25 Stormwater SWRP Component Structural Information Resul t Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name Union Mine Landfill Retention Ponds Diamond Springs Parkway- Roadway and Drainage Improvement Sand Road Paving Urban Roadway Improvement - Western Placerville Interchange Proponent Planning Area El Dorado Farm Trail South El Dorado Farm Trail El Dorado South City of Placerville Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Water Capture (contd.) Reduced sanitary sewer overflows and habitat protection and improvement B Improvement A B B Mosquito Road City of Sewer Main Other B Placerville Replacement Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way E-21
26 This page left blank intentionally. E-22
27 Stormwater SWRP Component Structural Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name Proponent Planning Area Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows and habitat protection and improvement Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way Improvement (contd.) 305 Urban Roadway Improvement - City of Woodridge Placerville Court, Grind & Overlay C Urban Roadway Improvement City of - Martin Placerville Lane, Grind & Overlay Urban Roadway Improvement - City of Mosquito Road Placerville Stabilization, Grind & Overlay Sewer City of Relocation-Clay Placerville to Locust Placerville Station II-Park and Ride Facility Improvements City of Placerville C C C C E-23
28 This page left blank intentionally. E-24
29 Stormwater SWRP Component Structural Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name Proponent Planning Area Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows and habitat protection and improvement Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way Improvement (contd.) 323 Urban Roadway Improvement -Ray City of Lawyer Drive, Placerville Grind & Overlay C Non-Point Source Pollution Control 309 Headington Yard Wash Rack El Dorado A Future Bass Lake Maintenance Station El Dorado El Dorado Hills South A Maintenance Material El Dorado Storage Buildings at Missouri Flat Rd and Somerset Sand Mine & Farm Trail South B Facility Upgrades for the El Dorado Disposal MRF El Dorado B Street Sweeping Program El Dorado Other B Forni Road Slope Stabilization El Dorado C E-25
30 This page left blank intentionally. E-26
31 Stormwater SWRP Component Structural Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name Trash Amendments - TMDL Implementation Vactor Truck Program Proponent Planning Area Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows and habitat protection and improvement Non-Point Source Pollution Control (contd.) El Other C Dorado El Dorado Other C Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way Flood Damage Reduction 345 Cameron Park Drainage Improvements El Dorado Cameron Park A Fish and Wildlife Routine Maintenance Agreement El Dorado Other A Priority County Culvert Replacements Town of El Dorado Drainage Improvements Upper Main Ditch Stormwater Improvements El Dorado Other A El Dorado El Dorado Farm Trail Irrigation East District A A E-27
32 This page left blank intentionally. E-28
33 Stormwater SWRP Component Structural Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name Proponent Planning Area Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows and habitat protection and improvement Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way Flood Damage Reduction (contd.) 343 Culvert California Rehabilitation Department Farm Trail along Highway of North & 50 near the City Transportati of Placerville on B Headington Yard to Weber Creek Conveyance El Dorado B Culvert Rehabilitation along Highway 50 near Cameron Park and Shingle Springs Cedar Ravine Road Drainage Improvement California Department of Transportati on City of Placerville Airport Road/Broadway City of Culvert Storm Placerville Drain Improvement Debby Lane/Green Valley Road Culvert Improvement City of Placerville Cameron Park & B B B B E-29
34 This page left blank intentionally. E-30
35 Stormwater SWRP Component Structural Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name 351 Full Capture Storm Drain Inlet Replacements in Placerville Proponent City of Placerville Planning Area Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Reduced sanitary sewer overflows Flood Damage Reduction (contd.) and habitat protection and improvement C Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way 352 Lions Park Drainage Improvement City of Placerville C Pleasant Street Storm Drain Improvement City of Placerville C Wiltse Road Storm Drain Improvement City of Placerville C Pierroz Road at Hangtown Creek, Drainage Improvement City of Placerville C E-31
36 This page left blank intentionally. E-32
37 E.4.2 Non-Structural Stormwater SWRP Component Non-Structural Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity 320 ID 327* Name BMP Countywide Demonstration s El Dorado Hills Library Water Conservation Splash in the Class - Outreach Program Our Water Our World - Outreach Program Countywide Awareness Campaign Proponent El Dorado Planning Area El Dorado County & Georgetow El Dorado n Divide Hills South Resource Conservati on El Dorado El Dorado El Dorado Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Outreach Reduced sanitary sewer overflows Other A and habitat protection and improvement A Other A Other B Other B * 327 is classified as two project types: Outreach and Water Capture. Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way E-33
38 This page left blank intentionally. E-34
39 Stormwater SWRP Component Non-Structural Information Result Overall Benefit Category Score Water Supply Flood Cost Implementation Complexity ID Name Countywide Stormwater Asset Program West Slope BMP Manual Proponent El Dorado El Dorado BMP for Agricultural Erosion and El Dorado Sediment Control Manual County Water Quality Standards Improvement El Dorado West Slope Watershed and Pollutant El Dorado Generation Study Outingdale Stormwater Study/Pre- Design Planning Area American River Farm Trail Conservan South cy Grouping Water Supply Flood Cost Implementation Complexity Weighted Score Increased filtration and/or treatment of runoff Nonpoint source pollution control Reestablished natural water drainage and treatment Water supply reliability Water conservation Conjunctive use Decreased flood risk by reducing runoff rate and/or volume Programs Reduced sanitary sewer overflows Other A Other C Other C Other C Other C and habitat protection and improvement C Increased urban green space Reestablishment of the natural hydrograph Improved Air quality* Ecological Improvement* Energy footprint Water temperature improvements Public Education Involvement Justice* Recreational Benefit Employment opportunities provided Funding Mechanism Eligibility for External Funding Constructability Institutional Complexity Regulatory & Permitting Compliance Public Acceptance Right of Way E-35
40 This page left blank intentionally. E-36
APPENDIX C PROJECT EVALUATION AND PRIORITIZATION METHOD
APPENDIX C PROJECT EVALUATION AND PRIORITIZATION METHOD This page left blank intentionally. Table of Contents C. PROJECT EVALUATION METRICS AND SCORING... C- C. PAIRED COMPARISON ANALYSIS... C-5 ACTIVITY
More informationCity of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017
City of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017 Why is Water Quality Important? Water has always been important to Minnesota and is a key part of our history, culture, economy
More informationRainfall, runoff and sediment transport in the Napa River watershed: now and a possible future
Rainfall, runoff and sediment transport in the Napa River watershed: now and a possible future Lester McKee San Francisco Estuary Institute 5/24/2017 1 The importance of the natural water cycle of infiltration
More informationAppendix J. Existing Efforts for Identifying Multi-Benefit Projects
Appendix J Existing Efforts for Identifying Multi-Benefit Projects Water Purveyor Projects Existing Efforts for Identifying Multi Benefits Projects In-lieu groundwater recharge under RWA planning efforts
More informationRIPARIAN CORRIDOR STUDY FINAL CITY CREEK MANAGEMENT PLAN TABLE OF CONTENTS
TABLE OF CONTENTS 1.0 INTRODUCTION... 1-1 Riparian Corridor Study and Management Plan Goals... 1-1 Study Area... 1-2 Importance and Functions of Riparian Corridors... 1-2 Habitat for Mammals, Birds, and
More informationMADERA COUNTY STORM WATER RESOURCE PLAN. TAC Meeting #2. August 30th, 2017
MADERA COUNTY STORM WATER RESOURCE PLAN TAC Meeting #2 August 30th, 2017 Meeting Agenda 10:30 Introductions (10 mins) Meet the SWRP team and other TAC Members 10:40 Project Prioritization Approach with
More informationClean Water is Everyone s Business. A commercial & industrial property owner s guide to improving Lake Tahoe s clarity
Clean Water is Everyone s Business A commercial & industrial property owner s guide to improving Lake Tahoe s clarity this informational guide will help you understand the tahoe regional planning agency
More informationPOLLUTION PREVENTION AFTER CONSTRUCTION
POLLUTION PREVENTION AFTER CONSTRUCTION..CHAPTER.. 10 This chapter describes the pollution prevention measures to be taken once the site has been permanently and finally stabilized and no additional construction
More informationKing County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds
News Release Contact: Al Sanders 206-477-1016 August 31, 2015 Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds The Flood Control District
More informationMunicipal Separate Storm Sewer Systems (MS4) Implementation. Craig Carson Montgomery County Department of Environmental Protection
Montgomery County Maryland Municipal Separate Storm Sewer Systems (MS4) Implementation Craig Carson Montgomery County Department of Environmental Protection Montgomery County, Maryland 500 sq. miles 970,000
More information6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff
October 2003, Revised February 2005 Chapter 6.0, Runoff Page 1 6.1 Introduction 6.0 Runoff The timing, peak rates of discharge, and volume of stormwater runoff are the primary considerations in the design
More informationStormwater Control and Treatment
Stormwater Control and Treatment EXISTING CONDITIONS The topography of Pinellas County is mostly flat to gently sloping, characterized by sandy soils and high groundwater levels. Elevations range from
More informationGUIDELINES FOR STORMWATER BACTERIA REDUCTIONS THROUGH BMP IMPLEMENTATION NY/NJ HARBOR TMDL DEVELOPMENT
GUIDELINES FOR STORMWATER BACTERIA REDUCTIONS THROUGH BMP IMPLEMENTATION NY/NJ HARBOR TMDL DEVELOPMENT Elevated bacteria in stormwater runoff in urban areas are well documented by many researchers. Monitoring
More informationRIPARIAN CORRIDOR STUDY FINAL PARLEYS CREEK MANAGEMENT PLAN TABLE OF CONTENTS
TABLE OF CONTENTS 1.0 INTRODUCTION... 1-1 Riparian Corridor Study and Management Plan Goals... 1-1 Study Area... 1-2 Importance and Functions of Riparian Corridors... 1-2 Habitat for Mammals, Birds, and
More informationEngineering Department
Engineering Department Stormwater Mission: To provide for the efficient and effective cleaning and repair of the stormwater collection system and implement the federally mandated Stormwater Pollution Prevention
More informationWatershed master planning, City of Griffin, Georgia, USA
Water Resources Management VII 3 Watershed master planning, City of Griffin, Georgia, USA J. K. Kaplan & B. J. Watson Tetra Tech, Water Resources Group, Atlanta, Georgia, USA Abstract Tetra Tech has assisted
More informationATTACHMENT N ASSESSMENT OF PROGRAM EFFECTIVENESS
ATTACHMENT N ASSESSMENT OF PROGRAM EFFECTIVENESS [This page has been left blank intentionally] Assessment of Program Effectiveness 1. Assessment of your agency's compliance with permit requirements, based
More informationMunicipal Stormwater Ordinances Summary Table
APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which
More informationBijou Area Erosion Control Project
Join the City of South Lake Tahoe for a Ribbon Cutting Ceremony for the Bijou Area Erosion Control Project Thursday, October 30th at 3:30pm Ceremony will be held at the cul-de-sac at the end of Bal Bijou
More informationStormwater Quality Extended Detention Basin Operation and Maintenance (O&M) Manual. for: Located at: Prepared for: Prepared by:
Stormwater Quality Extended Detention Basin Operation and Maintenance (O&M) Manual for: Insert Development Name Located at: Insert Address Prepared for: Insert Property Owner Name, Address, and Phone Number
More informationIntegrated Water Resources Master Plan
Integrated Water Resources Master Plan El Dorado Irrigation District March 31, 2013 Robert H. Ellis NO. 24676 EXP. 12/31/13 Holly Kennedy NO. 74682 EXP. 12/31/13 Prepared under the responsible charge of
More informationIntegrated Regional. South Tahoe Public Utility District. Water Management Plan. July 2014 K/J Prepared By Kennedy/Jenks Consultants
Tahoe-Sierra Integrated Regional Water Management Plan July 2014 K/J 1270036 Photo courtesy of Matthew Grimm South Tahoe Public Utility District Prepared By Kennedy/Jenks Consultants 10850 Gold Center
More information2013 WATER RESOURCES SERVICE RELIABILITY REPORT AND. El Dorado Irrigation District 2890 Mosquito Road Placerville, California 95667
2013 WATER RESOURCES AND SERVICE RELIABILITY REPORT El Dorado Irrigation District 2890 Mosquito Road Placerville, California 95667 Presented to the EID Board of Directors August 12, 2013 TABLE OF CONTENTS
More informationRiparian Buffer Requirements. Department of Environmental Protection Bureau of Watershed Management
102.14 - Riparian Buffer Requirements Department of Environmental Protection Bureau of Watershed Management 102.2 Scope and Purpose BMPs to protect, maintain, and restore water quality and existing designated
More informationHIGH SCHOOL #2 Severance, CO MANAGEMENT PLAN November,
HIGH SCHOOL #2 Severance, CO MANAGEMENT PLAN November, 18 2016 1 VICINITY MAP Site Data Land Use Statistics o Proposed Developed Site 55 acres 22.8% o Flood Plain 6 acres 2.4% o Open Space 100.6 acres
More informationMS4 Programs: Quality, the Other Stormwater Q. Dan Bounds, PE, D.WRE IAFSM March 9, 2017
MS4 Programs: Quality, the Other Stormwater Q Dan Bounds, PE, D.WRE IAFSM March 9, 2017 MS4 Rule and Regulations MS4 Municipal Separate Storm Sewer System A conveyance or system of conveyances (catch basins,
More informationEl Dorado Water & Power Authority. El Dorado Water Reliability Project
El Dorado Water & Power Authority 1 WELCOME El Dorado Water Reliability Project EIR SCOPING MEETING El Dorado Water & Power Authority is implementing the El Dorado Water Reliability Project as a component
More informationWhat is a stormwater utility fee?
What is a stormwater utility fee? A stormwater utility fee is similar to a water or sewer utility fee. In essence, customers pay a fee to convey stormwater from their properties. The City of Goodlettsville
More informationSTREAM RESTORATION PURPOSE, PRACTICE, AND METHODS. By Marcus Rubenstein, CPESC
STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS By Marcus Rubenstein, CPESC WHAT IS STREAM RESTORATION? The return of a stream s lost natural functions, usually resulting from watershed alterations,
More informationBCWMC Capital Improvement Program (approved April 19, 2018; pending minor Plan amendment)
BCWMC Capital Improvement Program 2020 2024 (approved April 19, 2018; pending minor Plan amendment) Project Name City Number 2019 2020 2021 2022 2023 2024 2025 Totals Medicine Lake Rd and Winnetka Ave
More informationIII. INVENTORY OF EXISTING FACILITIES
III. INVENTORY OF EXISTING FACILITIES Within the Growth Management Boundary, the existing storm drainage facilities are largely associated with development that has historically occurred in the ten drainage
More informationCITY OF MERCER ISLAND 2017 STORMWATER MANAGEMENT PROGRAM (SWMP) PLAN
CITY OF MERCER ISLAND 2017 STORMWATER MANAGEMENT PROGRAM (SWMP) PLAN May, 2017 CITY OF MERCER ISLAND 2017 S T O R M W A T E R M A N A G E M E N T P R O G R A M ( S W M P ) P L A N May 2017 City of Mercer
More informationMunicipal Stormwater Management Planning
Municipal Stormwater Management Planning Christopher C. Obropta, Ph.D., P.E. Water Resources Extension Specialist with Rutgers Cooperative Extension Assistant Professor with Department of Environmental
More informationChapter 1. Introduction
Chapter 1 Introduction James P. Heaney, Robert Pitt, and Richard Field Introduction Stormwater has traditionally been considered a nuisance, requiring rapid and complete drainage from areas of habitation.
More informationSTORMWATER MANAGEMENT PROGRAM. Table of Contents
STORMWATER MANAGEMENT PROGRAM Yakima Valley College March 1st, 0 1 0 1 Table of Contents INTRODUCTION... PROGRAM COMPONENTS... S.D.1: PUBLIC EDUCATION AND OUTREACH... Label Storm Drain Inlets:... Public
More informationMinistry of the Environment and Climate Change. Transfer of Review. Presentation for Wastewater Practitioners Group.
Ministry of the Environment and Climate Change Transfer of Review Presentation for Wastewater Practitioners Group November 29, 2017 Outline of Presentation Transfer of Review (TOR) Program Context TOR
More information2016 WATER RESOURCES SERVICE RELIABILITY REPORT AND. El Dorado Irrigation District 2890 Mosquito Road Placerville, California 95667
2016 WATER RESOURCES AND SERVICE RELIABILITY REPORT El Dorado Irrigation District 2890 Mosquito Road Placerville, California 95667 Presented to the EID Board of Directors September 12, 2016 This page intentionally
More informationAPPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports
APPENDIX H H.1 Guidance for Preparing and Reviewing CEQA Initial Studies Step 1: Consider the Project Characteristics as Provided by the Project Applicant Review the project application and draft plan
More informationCounty of Calaveras Department of Planning
Date: July 18, 2013 To: From: Project: Advisory Agencies Amy Augustine, AICP - Planner County of Calaveras Department of Planning Rebecca L. Willis, AICP ~ Planning Director Phone (209) 754-6394 Fax (209)
More informationA Summary Guide to the. Rifle River WATERSHED MANAGEMENT PLAN. Know Your Watershed Protect Its Resources
A Summary Guide to the Rifle River WATERSHED MANAGEMENT PLAN Know Your Watershed Protect Its Resources Table of Contents The Watershed... 3 The Management Plan... 4 Designated and Desired Uses... 5 Sources
More informationAPPENDIX L Hydrology and Stormwater Pond Analysis
APPENDIX L Hydrology and Stormwater Pond Analysis This page is left intentionally blank. Hydrology and Stormwater Pond Analysis Liesch Associates, Inc. June 1, 2012 Minneapolis-St. Paul International Airport
More informationCity of Tacoma Surface Water Management Manual
City of Tacoma Surface Water Management Manual Volume IV Source Control BMPs Prepared by: Tacoma Public Works Environmental Services January 2003 Table of Contents Chapter 1 Introduction to Volume IV...
More informationFacility Runoff Control Plan FRCP. City of Papillion Public Works Facility
Facility Runoff Control Plan FRCP City of Papillion Public Works Facility Facility Draft FRCP October 13, 2015 This page intentionally left blank Facility Runoff Control Plan Table of Contents OVERVIEW
More informationProject Type: Drainage and Storm Systems
580 Dakin Avenue Box Culvert & Utility Improvements Project $944,952 Improvements to approx. 3,000 lf of existing 4'x5' concrete box culvert; clean interior, patch surface, fill joints/cracks; install
More informationSTREAM AND BUFFER AREA PROTECTION/RESTORATION
STREAM AND BUFFER AREA PROTECTION/RESTORATION AMENDMENT OPTIONS TO STRENGTHEN POLICY IN HEADWATERS AREAS DRAFT SUBSEQUENT TO THE JANUARY 25, 2007 MEETING OF THE PLANNING COMMISSION ENVIRONMENT COMMITTEE
More informationSTORM WATER MANAGEMENT PLAN
STORM WATER MANAGEMENT PLAN Table of Contents Executive Summary ES.1 Overview of pg. ES-1 ES.2 Program Management pg. ES-1 ES.3 Program Development and Implementation pg. ES-1 ES.4 Proposed Strom Water
More informationStormwater Programs. BIA Meeting June 5, Jason Uhley
Stormwater Programs BIA Meeting June 5, 2014 Jason Uhley Chief of Watershed Protection Riverside County Flood Control and Water Conservation District Presentation Outline Clean Water Act Stormwater Program
More informationBMP #: Water Quality Inserts
Structural BMP Criteria BMP #: Water Quality Inserts Catch basin inserts are commercially available (manufactured) devices and are generally configured to remove one or more of the following contaminants:
More informationBackground / Regulatory Requirements
Chapter 2 Background / Regulatory Requirements This Chapter summarizes the impacts of development on stormwater quality and quantity and explains the postconstruction stormwater control requirements for
More informationCOON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432
PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:
More informationStabilized Construction Entrance/Exit TC-1
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control WM Waste Management and Materials Pollution Control Legend: Primary Objective
More informationChallenges of Sustainable Infrastructure AAEES UCI
Challenges of Sustainable Infrastructure AAEES UCI Sam Ali, PE, LEED AP sam.ali@ocpw.ocgov.com January 16, 2013 Sustainable Infrastructure Defining Sustainable Infrastructure Sustainable Systems Sustainable
More informationBIG ROCHE A CRI LAKE CHARACTERISTICS
BIG ROCHE A CRI LAKE CHARACTERISTICS Lake Description Big Roche Cri Lake is located in north central Adams County and has a surface area of 205 acres, a shoreline length of 6.1 mile, a volume of 6,993
More informationChapter 4. Drainage Report and Construction Drawing Submittal Requirements
4.0 Introduction The requirements presented in this section shall be used to aid the design engineer or applicant in the preparation of drainage reports, drainage studies, and construction drawings for
More informationAPPENDIX G Fire BMPs
APPENDIX G Fire BMPs BEST MANAGEMENT PRACTICES Plan for URBAN RUNOFF MANAGEMENT PARTICIPATING RIVERSIDE COUNTY FIRE FIGHTING AGENCIES City of Corona Fire Department City of Hemet Fire Department City of
More informationPROTECTING OUR WATERWAYS: STORMWATER POLLUTION REDUCTION EFFORTS
PROTECTING OUR WATERWAYS: STORMWATER POLLUTION REDUCTION EFFORTS Public Information Meeting ~ May 2, 2018 Public Works Stormwater Management Division OVERVIEW Surface Water Quality Protection Municipal
More informationOutcomes. Kelly Karll-SEMCOG Margaret Barondess - MDOT
Eco-Logical: I-75 Corridor I-75 Conservation Transportation Action Planning in to Monroe Achieve County: Multiple Stormwater Environmental Considerations Outcomes Kelly Karll-SEMCOG Karll@semcog.org Margaret
More informationStreamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators
Page 1 of 5 STREAMLINES A Newsletter for North Carolina Water Supply Watershed Administrators Volume 2, Number 2 May 1997 Non-Point Source (NPS) Pollution This issue of Streamlines provides basic information
More informationALMY POND TMDL MANAGEMENT PLAN
ALMY POND TMDL MANAGEMENT PLAN PUBLIC WORKSHOP Presented by: City of Newport Department of Utilities And Pare Corporation May 7, 2014 Presentation Overview Introduction to Almy Pond Project Introduction
More informationV. DRAINAGE IMPROVEMENTS
V. DRAINAGE IMPROVEMENTS 5.1 Formulation of Drainage Improvements As indicated in Chapter 4, following the completion of the hydrologic analysis associated with future land use conditions, drainage improvements
More informationEAST TORRANCE SOIL AND WATER CONSERVATION DISTRICT. LONG RANGE PLAN July 1, 2009 June 30, 2019
EAST TORRANCE SOIL AND WATER CONSERVATION DISTRICT LONG RANGE PLAN July 1, 2009 June 30, 2019 INTRODUCTION The East Torrance Soil and Water Conservation District covers 1,142,028 acres of land in Torrance
More information16.0 Water Quality Management Criteria for Developed Land
October 2003, Revised February 2005 Criteria for Developed Land Page 1 16.1 Introduction 16.0 Water Quality Management Criteria for Developed Land Stormwater quality control is an integral part of any
More informationPA Municipal Separate Storm Sewer System (MS4) TMDL Plan
PA Municipal Separate Storm Sewer System (MS4) TMDL Plan Instructor: Bryan Seipp, Watershed Manager- CWP Lee Epstein, Director, Lands Program- CBF 1 To Adjust How the Slides Appear on Your Screen To make
More informationNez Perce National Forest Moose Creek Ranger District
United States Department of Agriculture Forest Service Nez Perce National Forest Moose Creek Ranger District 831 Selway Road Kooskia, ID 83539 208 926-4258 TTY 208 926-7725 File Code: 1950 Date: Dec 30,
More informationDESIGN BULLETIN #16/2003 (Revised July 2007) Drainage Guidelines for Highways Under Provincial Jurisdiction in Urban Areas.
Drainage Guidelines for Highways Under Provincial Jurisdiction in Urban Areas. July 2007 Update to Design Bulletin #16/2003: Added under Design Criteria Culverts of 600mm diameter are commonly used to
More informationPRESENTATION OUTLINE. Stormwater Program Update Stormwater Overview. Education Program Discussion. Sources and consequences of pollutants
PRESENTATION OUTLINE Stormwater Program Update Stormwater Overview Sources and consequences of pollutants Education Program Discussion Why Stormwater? 1972 Clean Water Act Established permitting program
More informationINFRASTRUCTURE ELEMENT STORMWATER SUB-ELEMENT GOALS, OBJECTIVES & POLICIES
INFRASTRUCTURE ELEMENT STORMWATER SUB-ELEMENT GOALS, OBJECTIVES & POLICIES GOALS, OBJECTIVES & POLICIES GOAL DR 1: STORMWATER MANAGEMENT/DRAINAGE SYSTEMS. It is the goal of the City of Casselberry to provide
More informationUsing GIS to Inventory and Map Rapid City, South Dakota s Major Drainage Elements
Using GIS to Inventory and Map Rapid City, South Dakota s Major Drainage Elements Jenifer Sorensen, PE, PhD FourFront Design, Inc. Dion Lowe, PE City of Rapid City Stormwater Program Stormwater - Definition
More informationPRINCESS ANNE DISTRICT STORMWATER PROJECTS
PRINCESS ANNE DISTRICT STORMWATER PROJECTS Topics o o o o o Sea Level Rise and the Southern Watersheds Ashville Park Sherwood Lakes Kingston Estates Drainage Operations & Maintenance in the Southern Watersheds
More informationFEMA s Mitigation Support for Resiliency: Innovative Drought and Flood Mitigation Projects
FEMA s Mitigation Support for Resiliency: Innovative Drought and Flood Mitigation Projects Jordan Williams, CFM Eric Kenney, PE, CFM May 4, 2017 2 Hazard Mitigation Purpose: Research climate resilient
More informationMark Egbert Karen Quidachay Rick Lind, Principal - Susan Britting, Ph.D Barry Callenberger Mike Bryan Dave Thomas Greg Suba Eric Berntsen
Georgetown Divide Resource Conservation District South Fork American River Watershed Stewardship Strategy Acknowledgements This project was made possible by a grant from the California Bay-Delta Authority
More informationStandards for SWMF s. (Stormwater Management Facilities) Lacombe County s Guide to Developing Stormwater Management Facilities
Standards for SWMF s (Stormwater Management Facilities) Lacombe County s Guide to Developing Stormwater Management Facilities August 2017 PREAMBLE Development results in a great amount of impervious area,
More informationWATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS
WATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS Sec. 26.001. DEFINITIONS. As used in this chapter: (1)
More informationE. STORMWATER MANAGEMENT
E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson
More informationPRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY
PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established
More informationTargets of Opportunity: Alexandria s Urban Retrofit Program
Targets of Opportunity: Alexandria s Urban Retrofit Program Warren Bell, P.E. City Engineer, City of Alexandria, Virginia Philip C. Champagne, P.E. Dewberry & Davis Fairfax, Virginia During 1992 preparations
More informationFunding Guidelines State Fiscal Year 2016
State Fiscal Year 2016 Water Quality Financial Assistance Centennial Clean Water Program Clean Water Act Section 319 Program Stormwater Financial Assistance Program Washington State Water Pollution Control
More informationUse of SWAT for Urban Water Management Projects in Texas
Use of SWAT for Urban Water Management Projects in Texas Jaehak Jeong and Allan Jones Texas AgriLife Research Presentation Outline Modeling of Urban Watersheds and Stormwater Best Management Practices
More informationParaprofessional Training Session 1
Paraprofessional Training Session 1 Part 2: Stormwater Basics November 26, 2012 Rutgers University, Cook Campus Christopher C. Obropta, Ph.D., P.E. Extension Specialist in Water Resources Associate Professor
More informationSOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands
SOUTH FLORIDA WATER MANAGEMENT DISTRICT Question 13: Wetlands 1. The wetland responses and topographical data provided in the ADA for the 520- acre project site are conceptual in nature. The referenced
More informationNPDES Phase II Permit
NPDES Phase II Permit 2013 Stormwater Management Program City of Vancouver 2013 Stormwater Management Program Introduction The purpose of this Stormwater Management Program (SWMP) document is to detail
More informationCHAPTER 7. San Dieguito River Flooding Adaptation
CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,
More informationProject Name: Add a unique name that appropriately identifies the submission
PTAPP Online Municipal Tracking Tool Instructions Project Name: Add a unique name that appropriately identifies the submission Municipal Project: Check this box if the project is part of municipal efforts
More informationGrants Pass Water Quality Monitoring
Grants Pass Water Quality Monitoring 2003-2005 Rogue Valley Council of Governments April 2005 Rogue Valley Council of Governments Natural Resources Department 155 North First Street Central Point, Oregon
More informationEFFECT OF UPSTREAM DEVELOPMENT ON THE CLEAR CREEK AREA
EFFECT OF UPSTREAM DEVELOPMENT ON THE CLEAR CREEK AREA Technical Memorandum Farming in the Floodplain Project Prepared for May 2017 PCC Farmland Trust Photo credit: Google Earth TABLE OF CONTENTS Page
More informationC Fish Lake C Rice Lake C Mud Lake C Weaver Lake C Elm Creek*
IV. PROBLEMS AND CORRECTIVE ACTIONS Outlined below is an assessment of existing and potential water resource-related issues that are known at this time. These issues have been identified based on Commission
More informationStormwater Management Program Plan (SWMPP) NPDES Permit ALR Revised May 31, Prepared By:
City of Fultondale 1210 Walker Chapel Road P.O. Box 699 Fultondale, Al 35068 Stormwater Management Program Plan () Revised May 31, 2017 Prepared By: 7110 University Court, Montgomery, Alabama 36117 (THIS
More informationRichard V. Busche, P.E., CFM
Florida Stormwater Association EXCELLENCE AWARDS STORMWATER PROGRAMS & PROJECTS 2015 NOMINATION FORM I. Nomination Information Nomination Category (please check only one box): Program (Department/Division)
More informationHydrology Study. Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated)
Hydrology Study Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated) Prepared for San Mateo Real Estate & Construction March 9, 21 Rev. 1 11-8-211 Rev.
More informationRegional Watershed Planning. Calumet Summit 2010: A Call to Connect Calumet Conference Center April 27, 2010
Regional Watershed Planning Calumet Summit 2010: A Call to Connect Calumet Conference Center April 27, 2010 Basins The Calumet Region Watershed Communities Land Cover- 2006 Impervious Cover 303d Listed
More informationSURFACE WATER MANAGEMENT ELEMENT
SURFACE WATER MANAGEMENT ELEMENT of the PINELLAS COUNTY COMPREHENSIVE PLAN Prepared By: The Pinellas County Planning Department as staff to the LOCAL PLANNING AGENCY for THE BOARD OF COUNTY COMMISSIONERS
More informationARTICLE III: LAND USE DISTRICTS EXCLUSIVE FOREST AND CONSERVATION DISTRICT (EFC)
ARTICLE III: LAND USE DISTRICTS III-129 342 EXCLUSIVE FOREST AND CONSERVATION DISTRICT (EFC) 342-1 Intent and Purpose The Exclusive Forest and Conservation District is intended to provide for forest uses
More informationCHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit)
CHESAPEAKE BAY TMDL ACTION PLAN (2013 2018 MS4 General Permit) Piedmont Virginia Community College A Plan for Achieving a 5% Reduction of Existing Loads June 30, 2015 Main Campus This plan satisfies the
More informationBUDGET AND RESOURCES
BUDGET AND RESOURCES Introduction NRDs administer multiple programs that focus on the management of water quantity and the improvement of water quality. While NRDs have taxing authorities they use to support
More informationNatural Systems Planning Primer
Natural Systems Planning Primer Lise.Guevremont@ottawa.ca Amy.Macpherson@ottawa.ca Land Use and Natural Systems Unit Planning and Growth Management November 2015 1 Welcome Policy Framework Development
More informationAppendix G Preliminary Hydrology Study
Appendix G Preliminary Hydrology Study Preliminary Hydrology Study VESTING TTM 72608 Long Beach, CA Prepared for: The Long Beach Project, LLC 888 San Clemente, Suite 100 New Port Beach, CA May 28, 2014
More informationChapter 2. The Great Lakes Protection Fund. Watershed Flow Regime Restoration Evaluaton Process Developing Stormwater BMP Quality Gallon Metrics
Chapter 2 Watershed Flow Regime Restoration Evaluaton Process Developing Stormwater BMP Quality Gallon Metrics Prepared with Funding from The Great Lakes Protection Fund September 2007 Study contact: Mark
More informationExtended Detention Basin Maintenance Plan for [[== Insert Project Name ==]]
Extended Detention Basin Plan for [[== Insert Project Name ==]] [[== Insert Date =]] Project Address and Cross Streets Assessor s Parcel No.: Property Owner: Phone No.: Designated Contact: Phone No.: Extended
More informationThe Village of Wellington NPDES Guidance/Reference Document
The Village of Wellington NPDES Guidance/Reference Document The following Permit Compliance Guidance/Reference Document has been compiled to assist the copermittee in fulfilling the requirements of the
More information