Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR

Size: px
Start display at page:

Download "Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR"

Transcription

1 Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR NIWA Client Report: CHC June 2010 NIWA Project: WCR10501

2

3 Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR Maurice J Duncan Jo Bind NIWA contact/corresponding author Maurice Duncan Prepared for West Coast Regional Council NIWA Client Report: CHC June 2010 NIWA Project: WCR National Institute of Water & Atmospheric Research Ltd 10 Kyle Street, Riccarton, Christchurch 8011 P O Box 8602, Christchurch 8440, New Zealand Phone , Fax All rights reserved. This publication may not be reproduced or copied in any form without the permission of the client. Such permission is to be given only in accordance with the terms of the client's contract with NIWA. This copyright extends to all forms of copying and any storage of material in any kind of information retrieval system.

4

5 Contents Executive Summary i 1. Introduction 1 2. Modelling methods Background 1 3. Model calibration Further recalibration 2 4. The flood modelling Introduction Boundary conditions Digital elevation model Hydraulic resistance Input hydrograph Tides and sea level Hot starts Determining the extent of inundation for flood models Determining the location and minimum height of stop banks for mitigating the 1% AEP event 9 5. Results Discussion General assumptions The role of the Orowaiti overflow and the Nine Mile Road Railway embankment The consequences of stop bank failure Global climate change: sea level rise and increased rainfall intensities Risk of a 1% AEP event Summary Disclaimer References 21 Appendix 1: Appendix 2: The role of the Orowaiti overflow and the Nine Mile Road Railway embankment Files used for the simulations

6 Reviewed by: Approved for release by: Graeme Smart Roddy Henderson

7 Executive Summary The West Coast Regional and Buller District Councils wish to quantify the extent of Westport s flood hazard with 2% and 1% AEP (i.e., annual exceedance probabilities of inundation with average recurrence intervals of 50 and 100 years respectively) and revisit mitigation options for the 1% AEP event, because more extensive elevation airborne laser survey (ALS) data has become available. The ALS data were also used to estimate hydraulic roughness and gave more varied and spatially detailed hydraulic roughness than in the previous study. The modelled inundation shows more water going down the Buller River than the earlier study resulting in more inundation of Westport than previous studies. Flooding in Westport could be substantially reduced by five kilometres of low stop banks. Overtopping of the railway embankment at Nine Mile Road and across the Orowaiti Estuary is a concern. The effect of erosion of the stop banks was not modelled. The largest uncertainty with the modelling is the amount of river bed scour at the flood peak. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR i

8

9 1. Introduction The West Coast Regional and Buller District Councils wish to quantify the extent of Westport s flood hazard with 2% and 1% AEP (i.e., annual exceedance probabilities of inundation with average recurrence intervals of 50 and 100 years respectively) subsequent to an airborne laser survey (ALS) of the Buller River flood plain. They also wished to revisit mitigation options for the 1% AEP event. NIWA was engaged to carry out the study. The approach was to use a two dimensional (2-D) hydrodynamic model, calibrated using data from the 1970 flood, to model the floods. NIWA has already reported on flood extents caused by 2% and 1% AEP events (Duncan et al. 2005) based primarily on ground based GPS data and a coarser model grid than used here. Duncan (2005) suggests locations and nominal elevations for stop banks to mitigate flooding from a 1% AEP event in Westport. This study uses the scour and grain-size-based hydraulic resistance information gained from earlier studies (Duncan 2004, Duncan and Smart 2004). This study differs from earlier ones because selection of hydraulic resistance coefficients for the flood plain is guided by the ALS data which gives more spatial variation information than that of the blanket vegetative cover data used in previous models. There are many possible combinations of sea-level and river flood that result in 1% and 2% AEP inundation events and they may result in different spatial distributions of inundation. The combinations of sea-level and river flood that are most likely are used here. All references in the report to sea levels are with respect to mean sea level Lyttelton 1937 datum. 2. Modelling methods 2.1. Background Details of the modelling methods are given in Duncan et al. (2003) and are summarised here: 1. A digital elevation model (DEM) of the Buller River flood plain downstream of Te Kuha was derived from ALS (Duncan et al. 2010) and for areas without ALS coverage, from contour maps of the land and sea bed, riverbed crosssection and river-bank surveys and an echo-sounder survey of the Buller River. (Duncan et al. 2003). Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 1

10 2. The DEM was sampled on a 4.8 m square grid (cf. 7 m for the previous models) to provide the bed boundary for the 2 dimensional hydrodynamic model Hydro 2de (Beffa and Connell 2001). The extent of the model is shown in Figure The model was re-calibrated, (Duncan et al. 2010) primarily by adjusting the amount of general riverbed and Orowaiti Estuary scour, so that water levels observed in Westport during the August 1970 flood were reflected by the predicted levels in the model. 3. Model calibration 3.1. Further recalibration Details of the model recalibration subsequent to the ALS are contained in Duncan et al. (2010). However, since that report further calibration runs were carried out where the scour in the Buller River bed was increased to the same level as reported in Duncan (2004) and the hydraulic roughness of the Orowaiti overflow channel reduced in the vicinity of the Nine Mile Road Bridge. The outcome of this further calibration was to achieve modelled water-levels in the Menzies/Roebuck Street and Chamberlain/Russell Street neighbourhoods (Figure 2) to within m and m of the average levels of the most reliable flood-level information. These results can be considered to be very good. The water-level at Rintoul Street was too low but marginally higher than reported in Duncan et al. (2010) (Table 1). Table 1: Comparison of measured and modelled levels for the 1970 flood at the flood peak for the February 2010 and current calibrations. Difference of simulated level minus measured level (mm). Site February 2010 calibration difference (mm) 1 Current calibration difference (mm) 1 Menzies/Roebuck Gladstone/Russell Rintoul Street Negative indicates model level is too low The flooding pattern has most flooding originating from the Buller River with floodwater entering the town via the Domain and over the wharf in the vicinity of Chamberlain Street (Figures 1, 2 and 3). Water from the Domain floods the Menzies/Roebuck Street area (Figure 3). Water from near Chamberlain Street flows east and ponds. Water from Mill Creek flows via Mill Street to Colvin and Rintoul Streets and the depth of flooding there is very sensitive to the duration of the overflow period. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 2

11 Wharf Domain Orowaiti Overflow Figure 1: Location map showing the approximate extent of the 2-D model. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 3

12 Chamberlain St. Figure 2: Westport street map (not to scale). Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 4

13 * Gladstone/ Russell Wharf Rintoul/Colvin * Domain * Menzies/Roebuck Figure 3: Westport showing the modelled depth of flooding from the calibration. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 5

14 High water levels in the Orowaiti Estuary back up into the creeks that drain the town, but are not a major source of flooding in this calibration event. 4. The flood modelling 4.1. Introduction The purpose of the flood modelling was to show the extent of flooding for 2% AEP (for Building Act purposes) and 1% AEP events (for exploring mitigation options). In doing this work we have assumed that the sea level and river flow peak at the same time during a flood, i.e. we have worked with coincident daily maximum river flows and daily maximum sea levels. This assumption will maximise flooding in Westport from those events. The peaks of large Buller River floods have a relatively broad shape, so it is quite likely that at some time during the river flood peak the tide will also peak Boundary conditions Digital elevation model The DEM for the determination of the flood extents differed from that of the DEM used for calibration in the flowing ways: The Buller River Bridge and approaches as they were in 1970 were digitally removed and replaced by the modern bridge and approaches as determined by the LIDAR. A railway bridge spanning the Orowaiti River overflow channel was replaced by an embankment. The steepness of sections of the true right river bank between Pakington and Henley streets was reduced for computational reasons Hydraulic resistance The hydraulic resistance of that part of the Orowaiti River Overflow channel to the east of the Lidar coverage was reduced to reflect the reduction in tall willow cover between 1970 and the present time as indicated by aerial photographs. The effect of this reduction will be to increase the proportion of the flood flow travelling down the Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 6

15 Orowaiti River overflow channel. However the increase will be limited by the reduction in waterway area as a result of the replacement of a bridge by an embankment as indicated in Section Input hydrograph The input hydrograph for the flood modelling was different to that used by Duncan et al. (2005). To obtain a hydrograph for this model the hydrographs of the five largest river floods from the Buller at Te Kuha record were centred on their flood peaks and the arithmetic average at each hour before and after the flood peak was calculated (Figure 4). This average flood was then scaled to the peaks required for the simulations. The flood peaks used for the 2% and.01 AEP inundation events were 8800 m 3 s -1 and 9400 m 3 s -1 respectively (Duncan et al. 2005). These flood peaks are similar to the 2% and 1% AEP river flood peaks of 8540 m 3 s -1 and 9340 m 3 s -1 determined by McKerchar (2004). Real floods with the same recorded peak as those used in the simulations but with peaks sharper than those used in the simulations will result in less inundation of Westport than is given in this report. Real floods with broader peaks than those used in the simulations would result in more inundation of Westport. 10,000 9,000 8,000 Discharge (m3/s) 7,000 6,000 5,000 4,000 3,000 2,000 1,000 0 Model durations Aug-70 Jul-93 May-88 Oct-83 May-79 Mean 0.02 AEP 0.01 AEP Time since nominal start of flood (h) 0.02 AEP 0.01 Figure 4: The largest five flood hydrographs on record for the Buller River at Te Kuha, their mean and the scaled 2% and 1% AEP floods. The mean hydrograph was scaled up to the required peak for flood simulations Tides and sea level The DEM for the model was surveyed to mean sea level Lyttelton 1937 vertical datum. For both the calibration and the modelling it has been assumed that the elevation of mean sea level at Westport was 0.0 m with respect to that datum. This Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 7

16 assumption has been discussed with Glen Rowe of Land Information New Zealand who states that mean sea level at Westport is -025 m with respect to mean sea level Lyttelton 1937 datum based on mean sea level at Westport for 1918 to 1922 and carrying precise levelling from Lyttelton to Westport. We conclude that while our assumption was not strictly correct this difference in mean sea level is unlikely to have any material effect on the outcome of the study. The peak tide levels and the peak flood flows (see Section 4.2.3) chosen for the simulations are the most likely combinations of peak tide levels and peak river flows to cause flooding of Westport for 2% and 1% inundation events. See Duncan et al. (2005) for a fuller explanation. For the peak tide levels used here of 1.24 m and 1.35 m above mean sea level for the 2% and 1% inundation events respectively, the tides used to obtain those peak levels are less than the peak levels for mean high water springs of 1.49 m above mean sea level (LINZ standard port tidal levels) and so there was no need to add storm surge to achieve the required sea level peak, i.e. no storm surge was used. Figure 5 shows the floods and tide levels used for the simulations Flood discharge (m3/s) Tide level (m MSL Lyttelton) 0.02 AEP flood 0.01 AEP flood 0.02 AEP tide 0.01 AEP tide Time since start of flood simulation (h) Figure 5: The flood hydrographs and tides used for simulating the 2% and 1% AEP Westport inundation events. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 8

17 Hot starts Model runs were hot started from a model with a constant flow of 6500 m 3 /s and tide levels of 1.24 m and 0.4 m for the 2% and 1% AEP events respectively as these were the river flows and tide levels for the start of the flood simulations (Figure 5). At these flows and tide levels the model shows water flowing down the Buller River and the Orowaiti overflow, but no flooding in Westport. The model equilibrates with the inflow and tide level within one hour, that is, about the time that the flood wave takes to move from the upstream boundary of the model to Westport. There are a further 12 to 14 hours to the tide peak and the peak inflow to the model. One consequence of this timing is that the flood peak arrives at Westport about one hour after the tide peak. This may result in the inundation extent being less than it would have been had they coincided exactly, but will be close to the worst case inundation for the particular combination of river flood and sea level peak Determining the extent of inundation for flood models The program saves the maximum water-level, depth and velocity calculated for each cell and this is the value illustrated in the results. The maximum velocity and depth calculated for any cell may not occur at the same time. The maximum depths within the model may occur at different times as the flood wave moves downstream and as the tide floods and ebbs Determining the location and minimum height of stop banks for mitigating the 1% AEP event The 1% AEP model output was examined to determine where water was moving from rivers and channels on to the flood plain. Flow velocity vectors were used to help determine the direction of flow. Virtual stop banks were inserted into the DEM at locations indicated by the examination of the model outputs. The stop banks were two cells wide (9.5 m) and were made high enough to prevent overtopping. The model was rerun with the virtual stop banks in place. The water levels on the river side of the stop banks were extracted from the file containing the maximum water levels during the model run to determine the minimum stopbank heights to prevent overtopping. The DEM containing the stopbanks was interrogated to determine the lowest ground elevation along the stopbank line. This elevation was subtracted from the stopbank elevation to obtain the maximum bank height to stop overtopping. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 9

18 The stopbank locations will only be approximate as the model DEM comprises 4.8 m square grids where elevations have been averaged. Definitive locations should be obtained after detailed site investigations to determine foundation conditions, the line to minimise earth works while minimising interference with existing infrastructure, and allowing for free board and so on. Where stopbanks span existing drainage channels, e.g., Hunters Creek, it has been assumed that the relevant bridges or culverts have been fitted with well-maintained and effective flap valves to prevent flooding. 5. Results Figure 6 shows the extent of inundation for the most likely river flood and sea-levels for a 2% AEP inundation event. Figure 7 shows the extent of inundation for the most likely river flood and sea-levels for a 1% AEP inundation event. Comparison of these floods with those shown in Duncan et al (2005) shows that less water appears to go down the Orowaiti overflow and more is returned towards the Buller River with a portion of that flowing down the flood plain between the Buller River and the railway embankment alongside Nine Mile Road. Some of this water gets returned to the river, but some continues on and into Westport. Water from the Orowaiti River also overtops the terrace near McKenna and Soapworks Road and runs towards the town. The topography and hydraulic roughness in Duncan et al (2005) were less well defined than for this study. The difference in topography is the most likely cause of the different flooding pattern shown in this study. The 2% AEP inundation event shows much more inundation of Westport than was shown for the calibration event. This is attributed to the flood peak level being slightly larger and the coincidence of high tide and river flood peak whereas for the calibration flood the flood peak was at low tide. For both the 1% and 2% AEP floods the modelling shows that the railway embankments at Nine Mile Road and at the Westport to Ngakawau line as it crosses the Orowaiti estuary are both overtopped. This overtopping is likely to cause erosion of the banks which was not modelled. However, overtopping has implications for inundation of Westport. Erosion of the Nine Mile Road embankment would tend to increase Westport flooding from the Orowaiti System and reduce that from the Buller River. Overtopping of the Orowaiti embankment may reduce inundation in the south east of the town. The Nine Mile Road railway embankment is also overtopped with the virtual stopbanks in place. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 10

19 Figure 6: The Buller River flood plain showing an example of flooding for a 2% AEP inundation event. The river flood and sea level peaks used in this simulation were 8800 m 3 /s and 1.24 m. Red arrows indicate flow paths. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 11

20 Figure 7: The Buller River flood plain showing an example of flooding for 1% AEP inundation event. The river flood and sea level peaks used in this simulation were 9400 m 3 /s and 1.35 m. Red arrows indicate flow paths. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 12

21 Table 2 lists the stopbanks and their approximate lengths, minimum reduced level (RL) of the stopbank top to prevent overtopping and approximate stopbank height. The exact location of any stop banks needs to be checked by on ground survey to determine foundation condition, and exact location and alignment to avoid existing infrastructure. Design stop bank height needs to include a safety factor and allowance for wave action in addition to the modelled minimum stopbank height. The Hidden Lagoon stopbank height is the height above the existing stopbank. It is possible that the maximum height for this stop bank is overestimated as the height of the current stopbank may not have been properly captured in the model because it is so narrow. The listed stopbank lengths are maximum lengths and actual lengths would have to be confirmed by ground surveys. Table 2: List of stopbank locations approximate lengths, RL of top to prevent overtopping and maximum bank height. Location Length (m) RL of bank top (m) Height (approx. m) Easting (TM 2000)(m) Northing (TM 2000)(m) Hidden Lagoon Wharf d/s 4.62 u/s Esplanade d/s 4.78 u/s Domain d/s 5.30 u/s Stafford d/s 5.87 u/s Stafford Victoria Road d/s 9.78 u/s McKenna Road u/s 5.24 d/s Soapworks Road u/s 4.93 d/s Figure 8 shows the locations of the proposed stop banks and Figure 9 shows they were effective in reducing flooding in Westport. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 13

22 Hidden Lagoon Wharf Esplanade Domain Stafford 2 Stafford 1 Soapworks Road McKenna Road Victoria Road Figure 8: The Buller River flood plain showing the proposed locations of stop banks to reduce flooding of Westport by a 1% AEP inundation event. Red lines indicate the locations of the proposed stop banks. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 14

23 Figure 9: The 1% AEP flood with stopbanks in place showing they are effective in reducing flooding on the flood plain and in Westport. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 15

24 Figure 10 shows flooding from the 1% AEP event for Westport in more detail and Figure 11 the effectiveness of the stopbanks in reducing the extent of flooding. Figure 10: Flooding in Westport from the 1% AEP event. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 16

25 Figure 11. Westport showing the reduced extent of flooding from the 1% AEP event with the stopbanks in place. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 17

26 6. Discussion 6.1. General assumptions The aim of this study was to determine the extent of inundation of Westport with 2% and 1% AEP inundation events and to determine the locations of stop banks to prevent flooding of Westport from the most likely 1% AEP inundation event. It is clear from Duncan et al that there are many combinations of sea level peak and river flood peak that can result in 1% AEP inundation events in Westport. This report uses, as an example, a single combination close to the most likely 1% AEP event (9400 m 3 /s and 1.35m sea level), to illustrate the inundation mitigation options. This is referred to as the mitigation event. Mitigation measures were not checked against other combinations of river floods and peak sea level. However, stop banks proposed for the same mitigation event in an earlier study (Duncan 2005) provide protection for the most likely 90% of cases. Specifically, the peak flows and sea level combinations used in Duncan (2005) were: 9525 m 3 /s and 0.96 m, 9400 m 3 /s and 1.35 m, and 9095 m 3 /s and 1.98 m. The levels of inundation are based on models with the time of high tide almost coinciding with annual peak river levels using a flood hydrograph that is more peaked than the highest continuously recorded flood (the August 1970 flood). The assumption that the tide, storm surge and river flow peaks coincide during the flood is a conservative one that maximises flooding. It is unlikely that they will coincide, but the river flood peaks are relatively flat and there is about a 50:50 chance that a high part of the flood peak will coincide with the higher parts of a tide. The modelled river flood peaks at Westport reported here occur about one hour after the sea level peak. Examination of the timing of the modelled peak inundation of Westport shows that small river floods and large sea levels cause the inundation to peak at high tide. As the river floods increase, peak inundation levels are delayed to up to three hours after high tide. The delay is primarily because it takes some time for water to move from where it overflows to where it ponds. Three hours after the peak river flood, flood levels are likely to be dropping slowly in other parts of Westport. The comments in this paragraph apply where there are no stop banks. A further issue that affects the extent of inundation is the volume of water spilling over a bank and that is determined by both the water level in the river and the duration that it is above bank level, e.g. a flood with a high sharp peaked hydrograph could cause less flooding than a flood with a flat-topped, lower-peaked hydrograph. The main uncertainties with the modelling relate to the allowance for flood scour, and its variation down the river. Gravel build up varies with time and with dredging of the river. Flood scour will vary with flood duration and flow rates, but was kept constant Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 18

27 for the modelling exercises. A previous study (Duncan 2004) has shown that the extent of flooding is very sensitive to the amount of flood scour. The likelihood is that larger and/or longer flood peaks will result in more scour and less inundation than modelled and vice-versa for smaller floods. The amount of scour is also likely to vary with the tide phase, i.e., scour will be maximised when the flood peak coincides with low tide The role of the Orowaiti overflow and the Nine Mile Road Railway embankment There is a useful discussion on the role of these features in Duncan (2005). It is not repeated here but an amended version can be found in Appendix The consequences of stop bank failure Should the Victoria Road stop bank fail water would move north down the flood plain between the railway line and the Buller River and some of the water would flood into the town. Widespread failure of this bank would probably have a more serious effect on Westport than failure of any of the other stopbanks. Failure of either the McKenna or Soapworks Road banks is less serious as much of the water would be captured by Mill Creek and returned to the Orowaiti Estuary. If the Stratford 1, 2, Domain or Esplanade stopbanks fail, this would result in small area of the town being flooded and the degree of flooding would depend on the extent and duration of the failure of the bank. A Wharf bank failure would result in flooding of the north of the town with the deepest parts in the Gladstone/Russell Street neighbourhood. Failure of the Hidden Lagoon bank would inundate parts of the north part of the town, but the seriousness of the break would depend on its location and size Global climate change: sea level rise and increased rainfall intensities. This report is about mitigation for a 1% AEP inundation event assuming the current climate. The concept of global warming is now accepted by the scientific community. The most likely consequences are that rainfall intensities will increase causing larger floods, and sea levels will rise. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 19

28 Some relevant principles prescribed in the Resource Management Act for achieving the purpose of the Act include: having particular regard to:. the effects of climate change (Section 7 (i)). Thus in considering whether or not to adopt the mitigation measures suggested in this report particular regard should be given to their effectiveness in the light of projected climate change effects in New Zealand (Ministry for the environment 2008) Risk of a 1% AEP event A question arises as to the likelihood of exposure to a 1% AEP event. While an event as large as a 1% AEP can be expected, on average, once every 100 years, the probability of a 1% AEP event being exceeded at least once in a 10 year period is 9.6%, in 50 years 39.5% and in 100 years 63.4% (Beable and McKerchar 1982). 7. Summary 1. Inundation modelling of Westport and the Buller River flood plain has been undertaken using ALS based elevation and hydraulic resistance data using a smaller calculation grid than previous studies. 2. The most likely combinations of river flow and sea-level data from a previous study were used to indicate the extent of flooding of Westport for 1% and 2% inundation events. 3. The results show a greater relative flow down the Buller River and increased flooding of Westport compared with previous studies. 4. It appears that flooding in Westport could be substantially reduced by a series of low (<1.8 m high) stopbanks with a total length of 5.1 km. 5. River peak levels are primarily responsible for the inundation rather than high sea levels. However, as sea levels increase due to higher tides and/or storm surges the balance changes, but such combinations become less likely with higher sea levels. 8. Disclaimer Some of the mitigation suggestions will result in more water in the Buller River adjacent to the wharf at Westport. As part of any detailed design process Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 20

29 investigations should be made as to whether the extra water is likely to cause more scour in this area and or cause failure of the wharf structure and adjacent bank. Such concerns here and elsewhere in the modelled area have not been addressed in this report and NIWA accepts no responsibility or liability should the report recommendations be implemented and such failures occur. 9. References Beable, M.E., McKerchar, A.I Regional flood estimation in New Zealand. Water and Soil Technical Publication No. 10. MWD, Wellington. 132 p. Beffa, C.; Connell, R.J. (2001). Two-dimensional flood plain flow. 1:Model description. Journal of Hydrologic Engineering 6(5): Duncan, M.J. (2005). Potential mitigation measures for 1% AEP flood extents at Westport. NIWA Client Report CHC p. Duncan, M.J. (2004). The sensitivity of inundation in Westport to general scour in the Buller River. NIWA Client Report CHC Duncan, M.J.; Bind, J.; Smart, G.M. (2005). Calibration of the Westport 2D model based on Lidar. NIWA Client Report CHC p. Duncan, M.J.; Image, K.; Woods, R.A. (2005). Determining 1% and 2% AEP flood levels for Westport. NIWA Client Report CHC Duncan, M.J.; Smart, G.M. (2004). River bed grain size distributions in the Buller River downstream of Te Kuka. NIWA Client Report CHC p. Duncan, M.J.; Shankar, U.; Smart, G.M., Willsman, A. (2003). Westport flood mapping study. NIWA Client Report CHC p. McKerchar, A.I. (2004). Revision of flood frequency for the Buller River at Te Kuha. NIWA Client Report CHC Ministry for the Environment Coastal Hazards and Climate Change. A Guidance Manual for Local Government in New Zealand. 2nd edition. Revised by Ramsay, D, and Bell, R. (NIWA). Prepared for Ministry for the Environment. viii+127 p. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 21

30

31 Appendix 1: The role of the Orowaiti overflow and the Nine Mile Road Railway embankment The Orowaiti overflow For the purpose of this discussion the Orowaiti overflow system starts in the true right channel of the Buller River around Organs Island, from where water flows northeast over-bank towards the Nine Mile Road railway line embankment. At the embankment water flows northwest beside the railway line and most then flows southwest back to the river. The remainder overtops the south west trending terrace and continues north beside and to the west of the railway line. Some water flows back into the Buller River upstream of Westport and the remainder floods Westport. Some water flows under the rail bridges and culverts into the Orowaiti River and into the Estuary after passing under the road and rail bridges of, and along side, Stephen Road. In a large flood (e.g., AEP <4%) the railway embankments alongside Stephen Road may be overtopped. The role of the Orowaiti overflow in relieving flooding in Westport is somewhat contentious. There is no doubt that it reduces the flow in the main stem, and thus reduces flooding in Westport from the main stem, but there are a number of issues associated with it which caution against inducing too much change to the overflow system. The issues are: 1. Its capacity is limited, e.g., during the 1993 flood (7830 m 3 /s at Te Kuha) with an AEP of 4% (average return period 25 years) the railway line embankment adjacent to Stephen Road was overtopped and damaged. Thus any moves that increase the flood flows to the Orowaiti overflow could threaten this important piece of infrastructure. 2. The division of flow between the Buller River and the overflow is currently delicately balanced so as to minimise flooding in Westport, e.g., removing the willows from the overflow in the area immediately northwest of and adjacent to the Organs Island loop would increase the flow down the Orowaiti and increases the possibility of flooding of Westport from the Orowaiti. 3. The amount of water flowing in the Organs Island channel is dependent on the locations of gravel bars at its diversion with the Buller River, the location of groynes in the main stem of the Buller (such as those currently being constructed to protect State Highway 67), and the density of vegetation in and on the banks of the Organs Island channel. So, even if the willows were cleared from the overflow land adjacent to the channel and the weir reinstated, a variable amount of water may pass over the weir for the same flow in the Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 1

32 main stem of the river upstream of the diversion. Thus it is debatable as to whether the Orowaiti overflow upstream of the Nine Mile Road rail embankment should be engineered to maintain or to increase its capacity. 4. Modelling of the 1% AEP mitigation event peak flow (9400 m 3 /s) shows that in the area of the overflow much of the water leaving the Organs Island loop via the overflow channel is prevented from flowing down the Orowaiti River by the Nine Mile Road railway embankment. Instead some of the water flows northwest beside the railway line and then southwest back to the river or continues north towards Westport. Thus the railway embankment acts as the main hydraulic control on the amount of water entering the Orowaiti River. 5. Because some of the floodwaters turned back by the Nine Mile Road railway embankment flow towards Westport a stopbank is proposed between Nine Mile Road and Reedys Road to prevent flood waters from 1% AEP inundation event river floods from reaching Westport. The Nile Mile Road railway embankment Given that flows into the upstream end of the Orowaiti overflow may vary for the same flow in the Buller River upstream of Organs Island and that more flow in the downstream portion of the overflow is likely to increase Westport flooding, then consideration should be given to controlling the flows passing beyond the railway embankment. This control could take the form of floodgates incorporating a concrete floor designed to control scour. The modelling indicates there is overtopping of the lowest part of the embankment when subject to a main stem flow of 9400 m 3 /s (approximate AEP 1%). Overtopping may cause rapid failure of the bank because of the 1 to 1.5 m water elevation difference from one side of the bank to the other. A breached bank would most likely result in a much increased flood flow down the Orowaiti River with serious implications for the Stephen Road railway line and flooding in Westport. Accordingly, some consideration should be given to raising part of the railway embankment to give some free board. Further, consideration should be given to the design AEP that is appropriate for this structure. The modelling indicates that during the 1% AEP mitigation event river flood, hydraulic conditions are very harsh under and immediately downstream of the Nine Mile Road railway embankment bridges, with water velocities over 4 m/s, Froude numbers over 1.5 and bed shear stresses over 180 N/m 2. Such flows are capable of moving large boulders (>0.2 m median diameter) and could create large scour holes that threaten the integrity of the bridge piles and abutments should such flows Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 2

33 continue for too long. Their failure has the same implications for flooding in Westport as overtopping of the railway embankment. This study has not investigated the integrity of the embankment with respect to its ability to cope with scour from the discharges under the bridges or from spill over the top. Given the implications of failure of the embankment by either of these modes the integrity of the bank should be investigated. Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 3

34 Appendix 2: Files used for the simulations. Simulation Dain file DEM file z0 file Results file Hot start file Hot start time (h) Calibration daincalibl.txt dem100210_70s.asc z asc WPcalibla WPcalibl % AEP inund dainwp01aep.txt dem100430_rec.asc z0_100423_rec.asc WP01AEP Hotstart01i 3.2 2% AEP inund dainwp02aep.txt dem100430_rec.asc z0_100423_rec.asc WP02AEP Hotstart102a 2.1 1% AEP stopbank dainwp01aepstb_e. txt dem100603_stb.asc Z0_ asc WP01AEPstb_e Hotstart01n 2.59 Flood extents for 1% and 2% AEP floods and potential mitigation measures for 1% AEP flood extents at Westport based on LiDAR 4

Hydraulic Capacity Review Rangitaiki River and Reids Floodway

Hydraulic Capacity Review Rangitaiki River and Reids Floodway Hydraulic Capacity Review Rangitaiki River and Reids Floodway February 2011 Contents Executive Summary... 1 1 Introduction... 2 2 Hydrology and Sea Levels... 2 2.1 Design Hydrographs... 2 2.2 Sea Level...

More information

Effects on Flood Levels from the Proposed Whakatane Marina

Effects on Flood Levels from the Proposed Whakatane Marina Effects on Flood Levels from the Proposed Whakatane Marina Peter West, Graduate Engineer Environment Bay of Plenty September 2004 5 Quay Street P O Box 364 Whakatane NEW ZEALAND ISSN 1176-5550 Working

More information

3.5 Hydrology & Hydraulics

3.5 Hydrology & Hydraulics 3.5 Hydrology & Hydraulics 3.5.1 Purpose The purpose of this section is to provide results from the analysis and assessment of the impact of the proposed Carmichael Rail Alignment (Option 11 Revision 1)

More information

Flood Hazard Assessment of Potential Growth Areas Palmerston North City: Ashhurst

Flood Hazard Assessment of Potential Growth Areas Palmerston North City: Ashhurst Flood Hazard Assessment of Potential Growth Areas Palmerston North City: Ashhurst Report prepared for Palmerston North City Council by Philip Wallace River Edge Consulting Limited May 2013 Table of Contents

More information

Hydraulic Capacity Review of the Waioho Stream and Canal

Hydraulic Capacity Review of the Waioho Stream and Canal Hydraulic Capacity Review of the Waioho Stream and Canal Prepared by Ingrid Pak, Environmental Engineer Environment Bay of Plenty October 2006 5 Quay Street P O Box 364 Whakatane NEW ZEALAND ISSN 1176-5550

More information

498 AVE BRIDGE HYDRAULICS INVESTIGATION OF IMPACTS RELATED TO TOWN OF HIGH RIVER FLOOD MITIGATION WORKS

498 AVE BRIDGE HYDRAULICS INVESTIGATION OF IMPACTS RELATED TO TOWN OF HIGH RIVER FLOOD MITIGATION WORKS 498 AVE BRIDGE HYDRAULICS INVESTIGATION OF IMPACTS RELATED TO TOWN OF HIGH RIVER FLOOD MITIGATION WORKS Submitted to: M.D. of Foothills No. 31 High River, Alberta Submitted by: Amec Foster Wheeler Environment

More information

TULLAMORE FLOOD RISK ASSESSMENT AND MANAGEMENT STUDY

TULLAMORE FLOOD RISK ASSESSMENT AND MANAGEMENT STUDY TULLAMORE FLOOD RISK ASSESSMENT AND MANAGEMENT STUDY FINAL HYDRAULICS REPORT 1794/RP/004/C June 2008 FRAM Section Engineering Services Office of Public Works Doc. No. 1794/RP/004/C ii June 2008 INDEX OF

More information

NOT-MODELLING FOR STORMWATER AROUND THE KAIKOURA ALLUVIAL FANS

NOT-MODELLING FOR STORMWATER AROUND THE KAIKOURA ALLUVIAL FANS NOT-MODELLING FOR STORMWATER AROUND THE KAIKOURA ALLUVIAL FANS Mark Pennington Pattle Delamore Partners Limited, Kaikoura, New Zealand ABSTRACT The Kaikoura plains are formed by a process of coalescing

More information

ONE DIMENSIONAL DAM BREAK FLOOD ANALYSIS FOR KAMENG HYDRO ELECTRIC PROJECT, INDIA

ONE DIMENSIONAL DAM BREAK FLOOD ANALYSIS FOR KAMENG HYDRO ELECTRIC PROJECT, INDIA ONE DIMENSIONAL DAM BREAK FLOOD ANALYSIS FOR KAMENG HYDRO ELECTRIC PROJECT, INDIA S. Masood Husain Nitya Nand Rai Director Assistant Director Foundation Engineering & Special Analysis Directorate Central

More information

Prepared for: City of Jeffersonville. November Prepared by

Prepared for: City of Jeffersonville. November Prepared by JEFFERSONVILLE STORMWATER MASTER PLAN HYDRAULICS APPENDIX JEFFERSONVILLE, INDIANA Prepared for: City of Jeffersonville November 2011 Prepared by Christopher B. Burke Engineering, Ltd. 115 W. Washington

More information

Hydrology and Flooding

Hydrology and Flooding Hydrology and Flooding Background The 1996 flood Between February 4, 1996 and February 9, 1996 the Nehalem reporting station received 28.9 inches of rain. Approximately 14 inches fell in one 48 hour period.

More information

Appendix D Flood Assessment

Appendix D Flood Assessment Appendix D Flood Assessment Mount Pleasant Operation Rail Modification Flood Assessment MACH Energy Australia Pty Ltd 0744-09-B3, 19 December 2017 Report Title Client Report Number Mount Pleasant Operation

More information

Appendix E: Bridge Site Information Summary

Appendix E: Bridge Site Information Summary BRIDGE MANUAL E - 1 APPENDIX E: BRIDGE SITE INFORMATION SUMMARY Appendix E: Bridge Site Information Summary Table of Contents Notes..E 3 Section 1: Basic Information..E 4 Section 2: River Data..E 8 Section

More information

10(a) Bridge and culvert design information

10(a) Bridge and culvert design information 10(a) Bridge and culvert design information The following information is required to accompany resource consent applications for bridges or culverts on waterways. Please answer all questions if possible.

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

Northland Regional Council. Awanui Flood Scheme Preliminary Design

Northland Regional Council. Awanui Flood Scheme Preliminary Design REPORT Northland Regional Council Awanui Flood Scheme Preliminary Design REPORT Northland Regional Council Awanui Flood Scheme Preliminary Design Report prepared for: NORTHLAND REGIONAL COUNCIL Report

More information

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Distribution Restriction Statement Approved for public release; distribution is unlimited. CECW-EH-Y Regulation No. 1110-2-1464 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Engineering and Design HYDROLOGIC ANALYSIS OF WATERSHED RUNOFF Distribution Restriction

More information

Appendix 15.3 Hydraulic Assessment of Sewers

Appendix 15.3 Hydraulic Assessment of Sewers Appendix 15.3 Hydraulic Assessment of Sewers Irish Water Arklow Wastewater Treatment Plant Project EIA Report Issue September 2018 Arup \\GLOBAL\EUROPE\DUBLIN\JOBS\247000\247825-00\4. INTERNAL\4-03 DESIGN\4-03-02

More information

Development of a Stage-Discharge Rating for Site Van Bibber Creek at Route 93

Development of a Stage-Discharge Rating for Site Van Bibber Creek at Route 93 Development of a Stage-Discharge Rating for Site 330 - Van Bibber Creek at Route 93 Prepared for: Urban Drainage and Flood Control District 2480 W. 26 th Avenue Suite 156-B Denver, CO 80211 May 19, 2006

More information

of the Crump weir Modelling of composite type variation

of the Crump weir Modelling of composite type variation Modelling of composite type variation of the Crump weir Ashley Maritz BEng Honours Student Department of Civil Engineering University of Pretoria aamaritz9@gmail.com Dr Pieter Wessels Specialist Engineer

More information

APPENDIX R Flood Hazard Assessment

APPENDIX R Flood Hazard Assessment APPENDIX R Flood Hazard Assessment Fibreco Export Terminal Enhancement Permit Application Document APPENDIX R Flood Hazard Assessment - Executive Summary Purpose: To identify and assess the flood hazards

More information

APPENDIX J-3 Technical Report on Airport Drainage, Northern Sector Airport and Ordinance Creek Watershed, Airport Creek Hydrologic Models

APPENDIX J-3 Technical Report on Airport Drainage, Northern Sector Airport and Ordinance Creek Watershed, Airport Creek Hydrologic Models APPENDIX J-3 Technical Report on Airport Drainage, Northern Sector Airport and Ordinance Creek Watershed, Airport Creek Hydrologic Models Introduction Technical Report on Airport Drainage Appendix J-3:

More information

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS March 18, 2003 This page left blank intentionally. March 18, 2003 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method

More information

Freight Street Development Strategy

Freight Street Development Strategy Freight Street Development Strategy Appendix B: Naugatuck River Floodplain Analysis Freight Street Development Strategy DECEMBER 2017 Page B-1 1.0 NAUGATUCK RIVER FLOODPLAIN AT FREIGHT STREET 1.1 Watershed

More information

Failure Consequence Classification

Failure Consequence Classification Failure Consequence Classification Audience: Dam Safety Officers (DSO) Owners of small dams Community emergency preparedness coordinators Introduction This document provides an overview of failure consequence

More information

Hydrotechnical Design Guidelines for Stream Crossings

Hydrotechnical Design Guidelines for Stream Crossings Hydrotechnical Design Guidelines for Stream Crossings Introduction Design of stream crossings and other in-stream highway facilities requires estimation of design highwater elevation and mean channel velocity.

More information

REPORT Chapman Tripp on behalf of the Earthquake Commission (EQC)

REPORT Chapman Tripp on behalf of the Earthquake Commission (EQC) REPORT Chapman Tripp on behalf of the Earthquake Commission (EQC) Canterbury Earthquake Sequence: Increased Flooding Vulnerability River Modelling and Coastal Extensions Report REPORT Chapman Tripp on

More information

4. FISH PASSAGE CONCEPTS

4. FISH PASSAGE CONCEPTS Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group 4. FISH PASSAGE CONCEPTS Fish passage could be improved by rehabilitating the existing fish passage,

More information

Waikato Regional Council Technical Report 2013/42 Te Puru flood protection scheme design report

Waikato Regional Council Technical Report 2013/42 Te Puru flood protection scheme design report Waikato Regional Council Technical Report 2013/42 Te Puru flood protection scheme design report www.waikatoregion.govt.nz ISSN 2230-4355 (Print) ISSN 2230-4363 (Online) Prepared by: Megan Wood (Wainui

More information

DRAINAGE SUBMITTAL CHECKLIST

DRAINAGE SUBMITTAL CHECKLIST Project Name: Firm Name: Map ID: Engineer: Address: City: State: Zip: Phone Number: Fax Number: Property Owner: Address: City: State: Zip: Reviewed By: Date Received: Date Accepted for Review: The following

More information

Peer review of Taupō District flood hazard reports. Prepared for Taupō District Council

Peer review of Taupō District flood hazard reports. Prepared for Taupō District Council Peer review of Taupō District flood hazard reports Prepared for Taupō District Council March 2015 Prepared by: Mr Roddy Henderson Mr Maurice Duncan Dr Murray Hicks For any information regarding this report

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Entrance Modelling and the Influence on ICOLL Flood Behaviour

Entrance Modelling and the Influence on ICOLL Flood Behaviour Entrance Modelling and the Influence on ICOLL Flood Behaviour D Lyons 1, D Williams 1 1 BMT WBM, Newcastle, NSW ABSTRACT The morphological changes in the coastal entrance of estuaries and ICOLLs during

More information

Flood Risks to CMT Estates

Flood Risks to CMT Estates s Executive Summary Whilst the proximity of Chatham Maritime to the tidal Medway tends to lead people to worry about flooding from the river, the risk of this happening is considered to be very low. Parts

More information

The approach to managing natural hazards in this Plan is to: set out a clear regional framework for natural hazard management,

The approach to managing natural hazards in this Plan is to: set out a clear regional framework for natural hazard management, 9 Natural Hazards 9.1 Scope and Background This chapter establishes an overall framework for natural hazard management under the RMA. It also sets out the division of responsibilities between the Regional

More information

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS ESTIMATING RUNOFF FROM SMALL WATERSHEDS June 2011 THIS PAGE LEFT BLANK INTENTIONALLY. June 2011 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method Values June 2011

More information

Drainage Simulation of Detention Pond with Tidal Effect at the Outfall during a Storm Period

Drainage Simulation of Detention Pond with Tidal Effect at the Outfall during a Storm Period Drainage Simulation of Detention Pond with Tidal Effect at the Outfall during a Storm Period TIENFUAN KERH, JASON J. D. YEI and YU-MIN WANG Department of Civil Engineering National Pingtung University

More information

Hydraulic and Sediment Transport Modeling Strategy

Hydraulic and Sediment Transport Modeling Strategy Appendix B Hydraulic and Sediment Transport May 2014 Technical Memorandum Channel Capacity Report September 2014 San Joaquin River Restoration Program Hydraulic and Sediment Transport The San Joaquin River

More information

a. Title of Report Example: Final Hydrologic and Hydraulic Drainage Report For Tract #### (or Planning and Zoning Permit ##-###-###)

a. Title of Report Example: Final Hydrologic and Hydraulic Drainage Report For Tract #### (or Planning and Zoning Permit ##-###-###) CITY OF OXNARD ENGINEERING DIVISION REQUIRED FORMAT AND CONTENTS HYDROLOGIC AND HYDRAULIC DRAINAGE REPORTS This report will provide a basis for design of the drainage system for the subject project. The

More information

Brisbane River Catchment Flood Study overview

Brisbane River Catchment Flood Study overview Brisbane River Catchment Flood Study overview Brisbane River Catchment Flood Study overview Floods can and do occur in the Brisbane River catchment. The Queensland Government, local councils and the community

More information

FORM B: DAMMING AND DIVERSION OF WATER

FORM B: DAMMING AND DIVERSION OF WATER APPLICATION FOR RESOURCE CONSENT FORM B: DAMMING AND DIVERSION OF WATER NOTES Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan

More information

Drainage Report. New Braunfels Municipal Airport. Master Plan Update 2005

Drainage Report. New Braunfels Municipal Airport. Master Plan Update 2005 Drainage Report Master Plan Update 2005 General The Texas Department of Transportation (TxDOT), Aviation Division, retained the consulting engineering team of Parkhill, Smith & Cooper, Inc. (PSC), to prepare

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT BOWEN PRIVATE INDUSTRY SOLID WASTE DISPOSAL FACILITY (ASH LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals

More information

Flood Risk Analysis of Bridge A Case Study

Flood Risk Analysis of Bridge A Case Study ISBN 978-93-84468-11-8 Proceedings of International Conference on Architecture And Civil Engineering (ICAACE'14) Dubai, December 25-26, 2014, pp. 128-134 Flood Risk Analysis of Bridge A Case Study Safa

More information

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows:

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows: UNION PACIFIC RAILROAD SCOPE OF HYDROLOGIC/HYDRAULIC DESIGN ENGINEERING AND PERMITTING SERVICES FOR SIZING WATERWAY OPENINGS AT NEW AND REPLACEMENT STRICTURES These flood passage criteria were developed

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion

More information

CONSTRUCTION PLAN CHECKLIST

CONSTRUCTION PLAN CHECKLIST CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted

More information

IDENTIFYING FLOOD RISK FOR RAPID CREEK

IDENTIFYING FLOOD RISK FOR RAPID CREEK IDENTIFYING FLOOD RISK FOR RAPID CREEK P Saunders 1, S Ruscheinsky 2 L Rajaratnam 3 1 Sinclair, Knight Merz, Darwin, NT 2 Sinclair Knight Merz, Sydney, NSW 3 Department of Land Resources Management, Darwin

More information

Afon Claerwen Hydropower Project. Flood Risk Assessment. February 2018

Afon Claerwen Hydropower Project. Flood Risk Assessment. February 2018 Afon Claerwen Hydropower Project Flood Risk Assessment February 2018 Hydropower Consultancy & Development Document Control Scheme Name: Client Name: Client Address: Afon Claerwen Hydropower Project Elan

More information

CHAPTER 7. San Dieguito River Flooding Adaptation

CHAPTER 7. San Dieguito River Flooding Adaptation CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,

More information

Isle of Wight Strategic Flood Risk Assessment MK2. Appendix P Newport

Isle of Wight Strategic Flood Risk Assessment MK2. Appendix P Newport Isle of Wight Strategic Flood Risk Assessment MK2 Appendix P June 2010 Isle of Wight Strategic Flood Risk Assessment Overview Please review this discussion in conjunction with the mapping provided in this

More information

The study consists of two parts. The same workflow is used in both:

The study consists of two parts. The same workflow is used in both: Results following the workflow The study consists of two parts. The same workflow is used in both: Climate impact indicators of hydrology in a future climate Data collection and hydraulic modelling Identify

More information

CITY OF KIMBERLEY HYDROLOGICAL & HYDRAULIC ASSESSMENT

CITY OF KIMBERLEY HYDROLOGICAL & HYDRAULIC ASSESSMENT HYDROLOGICAL & HYDRAULIC ASSESSMENT ISSUED FOR USE January 31, 2012 FILE: 2011-015 LACAS CONSULTANTS INC. CONSULTING ENGINEERS & HYDROLOGICAL SPECIALISTS, SINCE 1991 Suite 200, 1311 Howe Street, Vancouver,

More information

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 19 CONSTRUCTION GUIDELINES

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 19 CONSTRUCTION GUIDELINES OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 19 CONSTRUCTION GUIDELINES APRIL 2011 MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 19 - CONSTRUCTION GUIDELINES TABLE OF CONTENTS

More information

TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1

TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1 TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SECTION TITLE PAGE 105.1. SPECIFICATIONS AND SCOPE 105.1 105.2. METHODS OF ANALYSIS 105.1 105.2.1. Rational Method

More information

Volume II: Hazard Annex Dam Failure

Volume II: Hazard Annex Dam Failure Volume II: Hazard Annex Dam Failure Causes and Characteristics of Dam Failure Dam Characteristics Dams are impervious structures that block the flow of water in a river or stream, capturing water behind

More information

PRELIMINARY DRAINAGE STUDY

PRELIMINARY DRAINAGE STUDY PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,

More information

CLAY STREET BRIDGE REPLACEMENT

CLAY STREET BRIDGE REPLACEMENT HYDROLOGY /HYDRAULICS REPORT. EL DORADO COUNTY CLAY STREET BRIDGE REPLACEMENT Prepared by: Joseph Domenichelli Domenichelli & Associates 1107 Investment Blvd., Suite 145 El Dorado Hills, California 95762

More information

The Land & Infrastructure Resiliency Assessment (LIRA) Project Economic Flood Hazard Assessment

The Land & Infrastructure Resiliency Assessment (LIRA) Project Economic Flood Hazard Assessment The Land & Infrastructure Resiliency Assessment (LIRA) Project Economic Flood Hazard Assessment Robert Armstrong / Cameron Kayter Agri-Environment Services Branch LIRA Background Subcomponent of Climate

More information

Appendix C, Attachment 4 June 11, Diversion Channel Outlet Hydraulic Modeling RAS and ADH

Appendix C, Attachment 4 June 11, Diversion Channel Outlet Hydraulic Modeling RAS and ADH Diversion Channel Outlet Hydraulic Modeling RAS and ADH 11 June 2012 1 Contents Introduction... 3 HEC-RAS modeling of Outlet... 3 Transition Structure Geometry... 3 ADH Modeling of Outlet and Floodplain...

More information

APPENDIX 4 ARROYO MODELING

APPENDIX 4 ARROYO MODELING APPENDIX 4 ARROYO MODELING The existing HEC-HMS model can serve as a baseline for further development and analysis of major arroyos in the city. The model would need to be updated and expanded to consider

More information

REVIEW OF THE BENEFITS OF THE OKERE GATES CONTROL STRUCTURE LAKE ROTOITI

REVIEW OF THE BENEFITS OF THE OKERE GATES CONTROL STRUCTURE LAKE ROTOITI REVIEW OF THE BENEFITS OF THE OKERE GATES CONTROL STRUCTURE LAKE ROTOITI Robert Kelly (Aurecon) ABSTRACT Human intervention to our lakes and channels can take many turns and result in profound immediate

More information

STATEMENT OF EVIDENCE OF PETER BLACKWOOD

STATEMENT OF EVIDENCE OF PETER BLACKWOOD STATEMENT OF EVIDENCE OF PETER BLACKWOOD PALMERSTON NORTH CITY COUNCIL - PROPOSED PLAN CHANGE 15H: AIRPORT ZONE 1. Thank you for the opportunity to present evidence in support of Horizons Regional Council

More information

Review of the Flood Carrying Capacity of the Tarawera River below State Highway 30

Review of the Flood Carrying Capacity of the Tarawera River below State Highway 30 Review of the Flood Carrying Capacity of the Tarawera River below State Highway 30 Prepared by Verna Arts, Engineering Hydrologist Environment Bay of Plenty April 2005 5 Quay Street P O Box 364 Whakatane

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part 257.82 PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part

More information

Gold Coast. Rapid Transit. Hydrology and Hydraulics

Gold Coast. Rapid Transit. Hydrology and Hydraulics Gold Coast Rapid Transit 19 Hydrology and Hydraulics Contents 1. Introduction 19 1 2. Source Data 19 2 3. Methodology 19 3 3.1 Drainage Upgrades 19 3 3.2 Period of Closure 19 6 4. Description of the Existing

More information

Gulf Coast Study, Phase 2 Impacts of Climate Change and Variability on Transportation Systems & Infrastructure

Gulf Coast Study, Phase 2 Impacts of Climate Change and Variability on Transportation Systems & Infrastructure Gulf Coast Study, Phase 2 Impacts of Climate Change and Variability on Transportation Systems & Infrastructure Climate and Weather Risk Management Tools and Findings Rob Hyman, FHWA Robert.Hyman@dot.gov

More information

Understanding and Managing Flood Risk in Perth. Design and implementation of a climate risk management project

Understanding and Managing Flood Risk in Perth. Design and implementation of a climate risk management project Understanding and Managing Flood Risk in Perth Design and implementation of a climate risk management project Overview Climate change risk is uncertain! Flood modelling for this catchment is complicated!!

More information

A part of BMT in Energy and Environment Kosciusko Avenue Main Drain Catchment Drainage / Flood Study Draft Report

A part of BMT in Energy and Environment Kosciusko Avenue Main Drain Catchment Drainage / Flood Study Draft Report A part of BMT in Energy and Environment Kosciusko Avenue Main Drain Catchment Drainage / Flood Study Draft Report R.M7299.003.00.DraftReport January 2011 Kosciusko Avenue Main Drain Catchment Drainage

More information

Recent development and application of a rapid flood spreading method

Recent development and application of a rapid flood spreading method Flood Risk Management: Research and Practice Samuels et al. (eds) 2009 Taylor & Francis Group, London, ISBN 978-0-415-48507-4 Recent development and application of a rapid flood spreading method Julien

More information

A part of BMT in Energy and Environment Portarlington East Drainage / Flood Study Final Report

A part of BMT in Energy and Environment Portarlington East Drainage / Flood Study Final Report A part of BMT in Energy and Environment S Portarlington East Drainage / Flood Study Final Report R.M7373.003.02.FinalReport October 2009 Portarlington East Drainage/Flood Study Final Report Prepared For:

More information

Modeling a Complex Hydraulic Environment Using a 1-D Approach Supplemented with Simple 2-D Principles Manas Borah Ed Dickson June 5, 2014

Modeling a Complex Hydraulic Environment Using a 1-D Approach Supplemented with Simple 2-D Principles Manas Borah Ed Dickson June 5, 2014 ASFPM 2014 Annual Conference Modeling a Complex Hydraulic Environment Using a 1-D Approach Supplemented with Simple 2-D Principles Manas Borah Ed Dickson June 5, 2014 Agenda Overview and Background Hydrology

More information

SCOUR AT COMPLEX BRIDGE STRUCTURES THE BENEFITS OF TWO-DIMENSIONAL HYDRAULIC MODELLING IN THE ESTIMATION OF SCOUR DEPTHS

SCOUR AT COMPLEX BRIDGE STRUCTURES THE BENEFITS OF TWO-DIMENSIONAL HYDRAULIC MODELLING IN THE ESTIMATION OF SCOUR DEPTHS SCOUR AT COMPLEX BRIDGE STRUCTURES THE BENEFITS OF TWO-DIMENSIONAL HYDRAULIC MODELLING IN THE ESTIMATION OF SCOUR DEPTHS M Burgess 1, C Moore 1 1 Arup, Sydney, NSW Abstract Assessing scour potential at

More information

Neil M Craigie Pty Ltd ACN ABN LINCOLN HEATH SOUTH ESTATE POINT COOK ROAD, POINT COOK ADDENDUM TO SWMS

Neil M Craigie Pty Ltd ACN ABN LINCOLN HEATH SOUTH ESTATE POINT COOK ROAD, POINT COOK ADDENDUM TO SWMS Neil M Craigie Pty Ltd ACN 074 582 282 ABN 29 074 582 282 Waterway Management Consultants LINCOLN HEATH SOUTH ESTATE POINT COOK ROAD, POINT COOK ADDENDUM TO SWMS MANAGING THE EVC HYDROLOGY ISSUES For:

More information

Dam Failure Analysis. Olivotti Lake Dam. Houle Enterprises, LLC. (Final) Oshkosh, Wisconsin. Lincoln County, Wisconsin. Report prepared for

Dam Failure Analysis. Olivotti Lake Dam. Houle Enterprises, LLC. (Final) Oshkosh, Wisconsin. Lincoln County, Wisconsin. Report prepared for Dam Failure Analysis (Final) Olivotti Lake Dam Lincoln County, Wisconsin Report prepared for Houle Enterprises, LLC Oshkosh, Wisconsin Report prepared by www.meadhunt.com July 2012 Table of Contents Table

More information

Appendix D. Flood Study Report

Appendix D. Flood Study Report Appendix D Flood Study Report New Hope Coal Horse Creek Base Case (Natural Conditions) and Diversion Flood Study for Elimatta Mine 28 March 2014 Contents Page number 1. Introduction 1 1.1 Background 1

More information

APPENDIX G DIVERSION AND PELICAN LAKE CUTOFF CHANNELS HYRAULICS AND BRIDGE TECHNICAL MEMORANDUM

APPENDIX G DIVERSION AND PELICAN LAKE CUTOFF CHANNELS HYRAULICS AND BRIDGE TECHNICAL MEMORANDUM APPENDIX G DIVERSION AND PELICAN LAKE CUTOFF CHANNELS HYRAULICS AND BRIDGE TECHNICAL MEMORANDUM To: File Memo From: Matt Redington, P.E. Project: Watertown South Connector CC: Date: March 6, 2007; revised

More information

San Luis Obispo Creek Watershed Hydrologic Model Inputs

San Luis Obispo Creek Watershed Hydrologic Model Inputs Jeff Werst San Luis Obispo County Department of Public Works 1050 Monterey Street San Luis Obispo CA 93408 December 14, 2007 Subject: San Luis Obispo Creek Watershed Hydrology and Hydraulic Model Dear

More information

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established

More information

PART 5D - NATURAL HAZARDS

PART 5D - NATURAL HAZARDS CONTENTS...PAGE 5D.1 CONTENT AND STRUCTURE...3 5D.2 RESOURCE MANAGEMENT ISSUES...3 5D.3 RESOURCE MANAGEMENT OBJECTIVE AND POLICIES...4 5D.4 RESOURCE MANAGEMENT STRATEGY...4 5D.5 IMPLEMENTATION...4 5D.6.RULES

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Application for resource consent Form B Damming and diversion of water

Application for resource consent Form B Damming and diversion of water Application for resource consent Form B Damming and diversion of water Notes Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan or

More information

Appendix K Civil Engineering

Appendix K Civil Engineering Appendix K Civil Engineering Fargo-Moorhead Metropolitan Area Flood Risk Management Final Feasibility Report and Environmental Impact Statement Prepared by: U.S. Army Corps of Engineers St. Paul District

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment

More information

Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring

Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring Prepared for: Urban Drainage and Flood Control District 2480 W. 26 th Avenue Suite 156-B Denver, CO 80211 May 19, 2006 (Rev

More information

RETENTION BASIN EXAMPLE

RETENTION BASIN EXAMPLE -7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary

More information

3.0 HYDROLOGIC AND HYDRAULIC CONDITIONS

3.0 HYDROLOGIC AND HYDRAULIC CONDITIONS 3.0 HYDROLOGIC AND HYDRAULIC CONDITIONS This chapter describes the existing hydrological resources within the project area, including the regional hydrology, project hydrology, and flood control benefits

More information

Calibration and Testing of a Hydrodynamic Model of the Gippsland Lakes

Calibration and Testing of a Hydrodynamic Model of the Gippsland Lakes r Calibration and Testing of a Hydrodynamic Model of the Gippsland Lakes M.J. McMaster a,b, D.G. Provis b, R.B. Grayson a and W.A. Bishop b a Centre for Environmental Applied Hydrology, Department of Civil

More information

Contents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek

Contents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek Contents SITE LOCATION / DESCRIPTION... 3 WESTPOINTE STORMWATER MANAGEMENT PLAN... 3 THE ENCLAVE AT WESTPOINTE DETENTION POND... 3 Table

More information

Migration of the Morse River into Back Dunes at Popham Beach State Park, Phippsburg, Maine

Migration of the Morse River into Back Dunes at Popham Beach State Park, Phippsburg, Maine Maine Geologic Facts and Localities January, 2010 at Popham Beach State Park, Phippsburg, Maine 43 o 44 0.38 N, 69 o 48 33.49 W Text by Stephen M. Dickson, Department of Agriculture, Conservation & Forestry

More information

Flood Consequence Assessment. Proposed Commercial Development, Tank Farm Way, Sully

Flood Consequence Assessment. Proposed Commercial Development, Tank Farm Way, Sully Flood Consequence Assessment Proposed Commercial Development, Tank Farm Way, Sully Client O Reilly Concrete Group Larchfield Kingscourt County Cavan Ireland By RVW Consulting 6 Neptune Court Vanguard Way

More information

14 NATURAL HAZARDS Background Resource Management Issues

14 NATURAL HAZARDS Background Resource Management Issues 14 NATURAL HAZARDS 14.1 Background The particular geology, hydrology and topography of the Hutt Valley make Upper Hutt vulnerable to a variety of natural hazards. Earthquakes and flooding are the most

More information

COACHELLA VALLEY WATER DISTRICT GUIDELINE K-2 SLOPE (BANK) PROTECTION DESIGN GUIDANCE

COACHELLA VALLEY WATER DISTRICT GUIDELINE K-2 SLOPE (BANK) PROTECTION DESIGN GUIDANCE COACHELLA VALLEY WATER DISTRICT GUIDELINE K-2 SLOPE (BANK) PROTECTION DESIGN GUIDANCE K.2.1 General Requirements The design and construction of slope protection works may be required for several types

More information

REBUTTAL STATEMENT OF EVIDENCE OF BRETT BEAMSLEY (DREDGE DISPOSAL AND COASTAL PROCESSES)

REBUTTAL STATEMENT OF EVIDENCE OF BRETT BEAMSLEY (DREDGE DISPOSAL AND COASTAL PROCESSES) BEFORE THE NORTHLAND REGIONAL COUNCIL IN THE MATTER of the Resource Management Act 1991 AND IN THE MATTER APPLICATION NO: of a resource consent application by The New Zealand Refining Company Limited under

More information

Attachment H: Engineering Documentation

Attachment H: Engineering Documentation Attachment H: Engineering Documentation Part 2: Hydrologic and Hydraulic Consistency Worksheet Inland Water Resources Division Permit Activities This worksheet has four sections; only complete the section(s)

More information

WDC FMS. Whangarei CBD Flood Management Study. Flood Damage Assessment REPORT. Whangarei District Council. Prepared for.

WDC FMS. Whangarei CBD Flood Management Study. Flood Damage Assessment REPORT. Whangarei District Council. Prepared for. REPORT WDC FMS Whangarei CBD Flood Management Study Flood Damage Assessment Prepared for Whangarei District Council Private Bag 9023 Whangarei 13 September 2006 42744310/FLOOD DAMAGES REPORT - FINAL Project

More information

5/25/2017. Overview. Project Background Information. Project Background Information Modeling Approach Model Development Results Next Steps

5/25/2017. Overview. Project Background Information. Project Background Information Modeling Approach Model Development Results Next Steps City of Corpus Christi Downtown 2D Mapping Effort Brandon Hilbrich, PE, CFM Jake Fisher, PE, CFM Curtis Beitel, PE, CFM 2016 HDR, Inc., all rights reserved. Overview Project Background Information Modeling

More information

Technical Memorandum No. 8 June 3, 2013 Page 2. FEMA Floodplain Mapping Flood Elevations at WWTP

Technical Memorandum No. 8 June 3, 2013 Page 2. FEMA Floodplain Mapping Flood Elevations at WWTP Page 2 FEMA Floodplain Mapping Flood Elevations at WWTP Existing Flood Control Facilities The City of Davis WWTP is located immediately north of the Willow Slough Bypass and west of the Yolo Bypass (see

More information