Prior Lake Stormwater Management & Flood Mitigation Study

Size: px
Start display at page:

Download "Prior Lake Stormwater Management & Flood Mitigation Study"

Transcription

1 Prior Lake Stormwater Management & Flood Mitigation Study Prepared for Prior Lake-Spring Lake Watershed District and the City of Prior Lake September, MarketPointe Drive, Suite 200 Minneapolis, MN

2 1.0 Executive Summary 1.1 Introduction In the spring of 2014, the Prior Lake watershed experienced record amounts of precipitation which led to a historic flooding event. This event triggered many questions and highlighted the need to develop watershed modeling and evaluate flood mitigation strategies for future events. Prior Lake Spring Lake Watershed District (PLSLWD) and the City of Prior Lake, in collaboration with Spring Lake Township, retained Barr to complete this study which includes calibrated modeling of the watershed, review of flood-related issues and projects, identification and evaluation of a suite of potential flood reduction strategies and implementation plan recommendations. The study work also included a public input process that has engaged a broad range of stakeholders including local units of government, lake associations, the agricultural community and private landowners. Their input was used to guide the development and evaluation of the available flood mitigation options described herein. The study area included the Prior Lake-Spring Lake watershed upstream of the Lower Prior Lake outlet structure, encompassing approximately 19,000 acres (30 square miles) of land in Scott County, Minnesota with agricultural land predominant in the south and western areas and residential land uses surrounding the study lakes. Lake levels for Upper and Lower Prior Lakes have historically been one of the most important issues for the community, specifically the residents living around the Lakes, since Prior Lake does not have a natural outlet. In 1978 a Flood Insurance Study (FIS) was completed for Prior Lake, which established the regulatory flood zone around Prior Lake and resulted in the calculated 100-year flood elevation of feet mean sea level (MSL). After significant study, public process and agency coordination the establishment of the Prior Lake Outlet and Channel (PLOC) was selected as the first flood mitigation effort by the PLSLWD and the outlet system was first used in In 1987, an operating plan was adopted for outlet control structure which set operating procedures and allowable discharges. The FIS was updated in 1997, but the modeling did not account for the benefit of the outlet structure because the channel capacity downstream of the control structure and legal constraints with the adjoining communities limit the discharge the City of Prior Lake can pass through the control structure (FEMA, 1997). Beginning in 2004, PLSLWD pursued improvements to the outlet structure of the PLOC which included a fixed weir set at an elevation of feet MSL and a slide gate to allow manual discharge of water between lake level elevations of and feet MSL. The current outlet configuration will not allow the outflow rate to exceed 65 cfs. Even with the lake outlet in operation, the 2014 flood level of feet MSL for Prior Lake is significantly higher than any other flood event since 1915 (PLSLWD, 2003). Without the lake outlet, the 2014 flood level would have been more than 6 feet higher. There is a significant incremental increase in the number of homes that are at risk of flooding for each foot above a lake level of feet MSL, while there are linear increases in other types of infrastructure at risk with increasing flood levels. 1

3 1.2 Study Goals The goals of this study were as follows: 1. Update the flood model 2. Compile and review historical studies and projects to summarize efforts already accomplished toward flood damage reduction 3. Identify a universe of flood damage reduction strategies 4. Evaluate the cost/benefit of the strategies and define community goals for flood protection 5. Develop an implementation plan that identifies a suite of projects or mechanisms to reduce flood damage potential 1.3 Community Planning Process This study included a process for gathering input from the community, including advisory groups, study partners, and decision-making bodies that needed to be part of the process (see Section 4). The following describes the results of the community planning process with the meetings listed in chronological order: 1. Public Kick-Off Meeting February 19, This open house format meeting was intended to inform the public of the study goals and objectives, receive input on what they experienced during the 2014 flooding and to obtain their ideas for flood mitigation options. The meeting included specific survey questions to provide feedback, which was also made available on the PLSLWD website. 2. First Advisory Group Meeting May 7, This meeting was used to present preliminary modeling results and gather feedback on potential flood mitigation options and the draft criteria for a selection matrix. 3. Second Public Meeting May 28, Attendees were provided with a study update, including a summary of the watershed modeling and an overview of the matrix. Thirty attendees (with 18 indicating that they live on the lakeshore, eight in the city, and three in rural areas) completed a survey that rated important factors in selecting a potential flood-mitigation project and their feelings about use of public funding for flood mitigation efforts. The survey results indicated the following: a. Water quality was most important factor, followed closely by cost/benefit b. Half of the respondents thought it was important, and another 36% thought it was very important that options should protect properties and public roads below the 100-year FEMA flood level c. Project readiness was the least important factor d. 69% supported use of public money to protect individual homes/businesses e. 60% supported increasing property taxes to finance the options f. City of Prior Lake has obligation to maintain emergency access to properties g. General sentiment that public funds should be used to benefit entire community 4. Farmer Listening Session February 3, This meeting was held to gain a better understanding of how farmers were impacted during the 2014 flood event and receive feedback 2

4 regarding the proposed flood mitigation. The meeting was hosted by the PLSLWD Farmer-led Council. 5. Second Advisory Group Meeting February 4, This meeting was held to gather feedback on the up-to-date information from the analysis of flood mitigation scenarios as well as responding to public policy questions that included: a. Should public dollars be used to protect public infrastructure (such as sanitary sewer and water utilities)? There was consensus that this should be maintained b. To what degree should access (from streets) be provided during flood events? There was not unanimity on this, except that emergency vehicle access should be maintained c. To what degree should public dollars be used to protect or assist in the protection of private property? There was general consensus that it was a government s responsibility to provide access to properties through public rights-of-way, however not necessarily protect the property itself. However, there was not specific feedback on the allowable frequency and duration of access disturbances. Some felt that public dollars should not be spent on specific improvements to private property (such as floodproofing or buyouts) but did support strategies such as upper watershed storage. Some felt that less frequent flooding with a longer period between events was okay, but we should consider protecting homes that get flooded on a greater frequency (such as 25 years). 6. Joint Policy Group Meetings February 8, 2016 and September 26, The policy makers provided direction on the community goals to be used to complete the study. Those goals and priorities are as follows: a. Protection of Public Safety - Maintain emergency vehicle access at all times b. Protection of Health and Safety - Protect public utility infrastructure (i.e. sanitary sewer and water distribution.) c. Maintain traffic flow through the County Road 21 corridor d. Maintain access to private properties 1.4 Monitoring and Modeling PLSLWD collected lake stage and stream flow data for several sites within the Prior Lake watershed during the 2014 monitoring season which were used for watershed model calibration. More than seven inches of rainfall fell across most of the watershed between June 15 th and the 20 th, which contributed to the peak discharge rates observed at all five monitoring sites. The peak Spring Lake elevation occurred three days after the peak discharge rates occurred in the upper watershed, while Prior Lake did not reach its peak flood level until 11 days after the peak discharge occurred in the upper portion of the Spring Lake watershed. The County Ditch 13 watershed, which represents 29% of the Prior Lake watershed, contributed more than 53% of the flow volume that discharged from the Prior Lake outlet in In addition, watershed yield and peak discharge rates (normalized to drainage area) from the County Ditch 13 watershed were more than 30% higher than any of the monitoring stations used in the model calibration. Barr created a PCSWMM computer model capable of simulating the complexity of watershed runoff from the various types of land surfaces based on the available climate data, land use/land cover characteristics, 3

5 soil type, topography and imperviousness, and then subsequently route the runoff through stream and ditch channels as well as storage areas and storm sewer/culverts, including the lake basins based on the physical constraints of the individual outlets and conveyances. Model development and preliminary use included calibration to observed flow rates and lake elevations throughout the watershed for the June- July 2014 flood event and running the model for design events intended to simulate flood levels for the 2, 10, 25, 50, 100 and 500-year return period with Atlas 14 rainfall amounts for the critical duration (30-days) event. The 100-year design event modeling produces higher lake levels (approximately one-foot higher) than the peak levels that were observed in each lake in However, the predicted flood level for Prior Lake is 1.8 feet lower than the FEMA 100-year elevation of feet MSL, as it accounts for the effect of the existing outlet while the FEMA modeling did not. Analysis of the monitoring and modeling data indicated that enhanced upper watershed storage particularly in the County Ditch 13 watershed and better control of peak discharge from the Spring Lake outlet had the highest potential for reducing peak elevations in Prior Lake. Upper watershed storage is defined as any storage area upstream of Spring Lake and the Prior Lake basins. To have a noticeable effect on the peak Prior Lake elevation, detention storage areas would need to detain water until after Prior Lake had reached its peak. 1.5 Results Summary Based on feedback from the public a list of flood mitigation options was developed. Each mitigation option was then rated according to its relative merits for criteria that were weighted to correspond with the study objectives and what the public viewed as important factors in selecting potential floodmitigation options. The results of this analysis showed that improvement options involving upper watershed and Spring Lake storage, sandbagging and modifications to the Prior Lake outlet (including both increased capacity and proactive outlet management) scored highly. The results also indicated that floodproofing and/or buyouts could also be considered as part of the overall solution. As a result of relative comparisons of the merits of the universe of options the flood mitigation analysis was narrowed down to the following seven options: Option A Enhanced Protection (coordinated temporary protection measures) Option B Spring Lake Storage Option C Prior Lake Outlet Modification (increase capacity) Option D Upper Watershed Storage Option E Combine Options B, C & D Option F Floodproofing (for at-risk primary structures) Option G Actively Manage Prior Lake outlet (low-flow gate) Figure EX-1 shows how each of the potential improvement options are expected to improve the flood impacts for each of the flood frequency events, including summary information pertaining to the total estimated costs and number of primary structures and inaccessible properties at each flood level. The figure shows that, if the conservative cost estimates for securing Spring Lake drainage easements are accurate, then the Spring Lake storage option will not be as cost effective (from a flood control perspective) as increasing the Prior Lake outlet capacity or increasing upper watershed storage. Options involving an increase to the Prior Lake outlet capacity and increasing upper watershed storage are comparable at cost-effectively controlling flooding on Prior Lake. Upper watershed 4

6 storage provides better flood control for the larger flood events than any of the other individual options. For the 100-year event, the upper watershed storage option would protect an additional primary structures and maintain accessibility to an additional 50 properties. Implementing a combination of the first three options would drop the 100-year flood level to within a half-foot of the OHW for Prior Lake (see Figure EX-1), which is likely more protection than would be necessary for this event. However, the predicted 500-year flood level for Option E would still approach the high water level experienced during Implementation of some combination of upper watershed storage (Option D), increased Prior Lake outlet capacity (Option C) and actively managing the Prior Lake outlet low-flow gate (Option G) is expected to meet the study goals in the most cost-effective manner. The biggest limitation of this combination of options is that it may take several years for full implementation. As a result, it is expected that some combination of Options G and A will need to represent the short-term implementation measures. A scaled-down version of Option B, that involves less inundation on Spring Lake and less easement cost, may also represent a more cost-effective and viable short-term implementation measure. It is also expected that floodproofing (Option F) and/or buyouts will be a cost-effective measure for the lowest primary structures. 1.6 Preferred Option and Implementation Plan ********************** To be completed ********************** Based on feedback and direction from the Joint Policymaker Meeting on September 26, 2016, this section will be developed for the final report. 5

7 Figure EX-1 Cost/Benefit Summary of Potential Improvement Options 6

FLOOD RESPONSE POLICY Adopted June 26, 2017

FLOOD RESPONSE POLICY Adopted June 26, 2017 FLOOD RESPONSE POLICY Adopted June 26, 2017 SUMMARY/PURPOSE The purpose of this Policy is to define and outline the City s response to lake flooding within the City. Lake levels have historically been

More information

SEWRPC Staff Memorandum

SEWRPC Staff Memorandum SEWRPC Staff Memorandum EVALUATION OF PROPOSED STORMWATER QUANTITY MANAGEMENT FOR THE DES PLAINES RIVER WATERSHED PORTION OF THE PROPOSED FOXCONN DEVELOPMENT IN THE VILLAGE OF MOUNT PLEASANT June, 2018

More information

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1 To: From: The City of Virginia Beach Lewis White and Rachael Johnson on behalf of WSP Date: June 6, 2017 Subject: s Drainage Alternatives Analysis This memorandum represents the summary of findings from

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall 6.0 Introduction This chapter summarizes methodology for determining rainfall and runoff information for the design of stormwater management facilities in the City. The methodology is based on the procedures

More information

City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017

City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 Phasing of Meetings April Meeting May Meeting October Review of Tax Day Storm Event and Immediate Actions Taken By City Review of Coordination

More information

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY Project #08223 CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY PREPARED FOR: City of Crystal Lake 100 West Woodstock Street Crystal Lake, Illinois 60014 FEBRUARY 11, 2009 26575 W. COMMERCE DRIVE, SUITE 601,

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW Mississippi Dr Coon Rapids, MN SQ FT Residence on 0.64 Acre Lot

COON CREEK WATERSHED DISTRICT PERMIT REVIEW Mississippi Dr Coon Rapids, MN SQ FT Residence on 0.64 Acre Lot 17-082 Van Sloun Residence, Page 1 of 5 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: May 8, 2017 AGENDA NUMBER: 17 FILE NUMBER: 17-082 ITEM: Van Sloun Residence RECOMMENDATION: Approve with

More information

Cokato Lake (86-263) Wright County. Hydrologic Investigation

Cokato Lake (86-263) Wright County. Hydrologic Investigation Cokato Lake (86-263) Wright County Hydrologic Investigation April 14, 2005 Cokato Lake (86-263) Wright County Hydrologic Investigation April 14, 2005 Problem Statement In recent years, heavy rainfall has

More information

Engineering Report Preliminary Floodplain Study. Executive Summary

Engineering Report Preliminary Floodplain Study. Executive Summary Executive Summary Engineering Report Preliminary Floodplain Study The Federal Emergency Management Agency (FEMA) has updated the Flood Insurance Rate Maps (FIRM) for Finney County, including the City of

More information

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac)

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac) Permit Application No.: 17-181 Rules: Erosion Control, Wetland Protection, and Waterbody Crossings & Structures Applicant: Hennepin County Received: 4/27/17 Project: CSAH 112 Phase II Complete: 9/5/17

More information

3.3 Acceptable Downstream Conditions

3.3 Acceptable Downstream Conditions iswm TM Criteria Manual - = Not typically used or able to meet design criterion. 1 = The application and performance of proprietary commercial devices and systems must be provided by the manufacturer and

More information

Collaboration: Sea Level Marin Adaptation Response Team Phase II

Collaboration: Sea Level Marin Adaptation Response Team Phase II Collaboration: Sea Level Marin Adaptation Response Team Phase II 2018-2020 Scope of Work Background Climate experts estimate that by 2100, sea level could rise by up to 70 inches, though recent projections

More information

Rainwater Harvesting at Stillwater Country Club

Rainwater Harvesting at Stillwater Country Club technical memo Project Name BCWD Community Demonstration BMP Projects Date 12/05/2018 / Contact info Cc / Contact info From / Contact info Regarding BCWD Board of Managers Karen Kill, District Administrator

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW

COON CREEK WATERSHED DISTRICT PERMIT REVIEW 16-054 Woodland Creek Wetland Banking Restoration Project, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 11 FILE NUMBER: 16-054 ITEM: Woodland Creek

More information

Upper Lightning Lake Water Level Management Environmental Assessment Worksheet. Attachment D Design Report for Upper Lightning Lake

Upper Lightning Lake Water Level Management Environmental Assessment Worksheet. Attachment D Design Report for Upper Lightning Lake Upper Lightning Lake Water Level Management Environmental Assessment Worksheet Attachment D Design Report for Upper Lightning Lake DESIGN REPORT for Upper Lightning Lake Wetland Enhancement MN-332-2 I

More information

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228 Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA 30534 (706) 344-3500 x 42228 DAWSON COUNTY STORM WATER REVIEW CHECKLIST Project Name: Property Address: Engineer: Fax #/Email: Date:

More information

Minneapolis Impound Lot Facility Improvements Minneapolis, MN BCWMC

Minneapolis Impound Lot Facility Improvements Minneapolis, MN BCWMC Memorandum BCWMC May 17, 2018 Meeting Agenda Project: 23270051 2017 2144 5C Minneapolis Impound Lot Facility Improvements Minneapolis, MN BCWMC 2017-37 Summary: Proposed Work: Temporary surcharge for new

More information

Problem Assessment: The Bee Branch Watershed, where over 50% of Dubuque s

Problem Assessment: The Bee Branch Watershed, where over 50% of Dubuque s Problem Assessment: The Bee Branch Watershed, where over 50% of Dubuque s residents either live or work, has been hit hard with flash flooding that inundates basements and rushes down streets. In the early

More information

CCSD#1 Stormwater Standards

CCSD#1 Stormwater Standards SECTION 5 STORMWATER MANAGEMENT PLAN This Section of the Stormwater Management Design Standards describes the methods and criteria necessary to integrate infiltration, water quality, and flow control stormwater

More information

PRELIMINARY DRAINAGE STUDY

PRELIMINARY DRAINAGE STUDY PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,

More information

Dry Creek Flood Control Improvement Project

Dry Creek Flood Control Improvement Project Dry Creek Flood Control Improvement Project The following is a brief overview of the planned IRWM Stormwater Flood Management Grant Application from the Fresno Metropolitan Flood Control District (FMFCD)

More information

DRAINAGE SUBMITTAL CHECKLIST

DRAINAGE SUBMITTAL CHECKLIST Project Name: Firm Name: Map ID: Engineer: Address: City: State: Zip: Phone Number: Fax Number: Property Owner: Address: City: State: Zip: Reviewed By: Date Received: Date Accepted for Review: The following

More information

AS A COURTESY, PLEASE TURN OFF CELL PHONES AND PAGERS WHILE MEETING IS IN PROGRESS.

AS A COURTESY, PLEASE TURN OFF CELL PHONES AND PAGERS WHILE MEETING IS IN PROGRESS. Table of Contents Agenda 2 Wastewater Treatment Plant (WWTP) Hydraulic Capacity Update Staff Report 3 WWTP Capacity Outline 5 WWTP Capacity Charts 6 Drainage Concerns on Oak Hill Drive and Quail Drive

More information

Review Budget and Timeline for XP-SWMM Phase II Project and Determine Next Steps

Review Budget and Timeline for XP-SWMM Phase II Project and Determine Next Steps Memorandum To: Item 5C - Review Budget and Timeline for XP-SWMM Phase II Project and Determine Next Steps Project: 23/27-0051 2015 5C Review Budget and Timeline for XP-SWMM Phase II Project and Determine

More information

Sea Level Rise and Recurrent Flooding Update

Sea Level Rise and Recurrent Flooding Update Sea Level Rise and Recurrent Flooding Update Informational Briefing City Council Meeting September 18, 2018 Thomas M. Leahy, Deputy City Manager The Sea, Inland Waters, & Groundwater are Rising Projected

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

Little Bear Brook Flood Hazard Assessment and Redevelopment Area Regional Stormwater Management Analysis. Progress Meeting

Little Bear Brook Flood Hazard Assessment and Redevelopment Area Regional Stormwater Management Analysis. Progress Meeting Little Bear Brook Flood Hazard Assessment and Redevelopment Area Regional Stormwater Management Analysis Progress Meeting June 30, 2014 Princeton Hydro, LLC and SWM Consulting, LLC Project Team West Windsor

More information

SECTION IV WATERSHED TECHNICAL ANALYSIS

SECTION IV WATERSHED TECHNICAL ANALYSIS A. Watershed Modeling SECTION IV WATERSHED TECHNICAL ANALYSIS An initial step in the preparation of this stormwater management plan was the selection of a stormwater simulation model to be utilized. It

More information

Public Works and Engineering

Public Works and Engineering 6.C Exhibit Incorporated in 1909 Public Works and Engineering Committee Report To: From: Mayor and Board of Trustees Bill Emmerich For Village Board Meeting of: November 27, 2017 Subject: Division and

More information

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR 257.82 EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part 257 and Part

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Stormwater Management Under a Changing Climate

Stormwater Management Under a Changing Climate Stormwater Management Under a Changing Climate North Carolina WRRI Conference Raleigh, NC March 15, 2017 Presenter: Scott Job, Tetra Tech Acknowledgements Office of Research and Development, Global Change

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or

More information

Hey and Associates, Inc.

Hey and Associates, Inc. Hey and Associates, Inc. Table 1: 100-Year Study Existing Conditions Discharges and Elevations vs. FIS Results Location Existing FIS Q (cfs) Existing FIS Elevation Existing XP- SWMM Q (cfs) Existing XP-SWMM

More information

TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1

TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1 TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SECTION TITLE PAGE 105.1. SPECIFICATIONS AND SCOPE 105.1 105.2. METHODS OF ANALYSIS 105.1 105.2.1. Rational Method

More information

Memorandum. Creekside Woods I & II Plymouth, MN BCWMC Summary: General Background & Comments. Floodplain

Memorandum. Creekside Woods I & II Plymouth, MN BCWMC Summary: General Background & Comments. Floodplain Memorandum To: Bassett Creek Watershed Management Commission BCWMC June 15, 2017 Meeting Agenda Project: 23270051 2017 2128 4F Creekside Woods I & II Plymouth, MN BCWMC 2017-21 Summary: Proposed Work:

More information

Big Creek Watershed Retrofit Ranking Project

Big Creek Watershed Retrofit Ranking Project Big Creek Watershed Retrofit Ranking Project John Stein and Jennifer Olson Tetra Tech, Inc. Bob Gardin, FOBC Innovative Stormwater Conveyance Through Green Infrastructure May 13, 2014 Presentation Outline

More information

Atlas 14: The New Rainfall Atlas

Atlas 14: The New Rainfall Atlas Atlas 14: The New Rainfall Atlas Olmsted County Environmental Commission Trends Subcommittee September 17, 2014 Presenter: Art Kalmes, PE, CFM Vice President Barr Engineering Co. akalmes@barr.com 952-832-2990

More information

DRAINAGE STUDY PHASE 2 REPORT HORRY COUNTY STORMWATER DEPARTMENT HIGHWAY 9 & 57 HORRY COUNTY, SC PREPARED FOR: APRIL 07, 2016 J

DRAINAGE STUDY PHASE 2 REPORT HORRY COUNTY STORMWATER DEPARTMENT HIGHWAY 9 & 57 HORRY COUNTY, SC PREPARED FOR: APRIL 07, 2016 J DRAINAGE STUDY PHASE 2 REPORT FOR: HIGHWAY 9 & 57 HORRY COUNTY, SC PREPARED FOR: HORRY COUNTY STORMWATER DEPARTMENT APRIL 07, 2016 Prepared by: Savannah, GA Charleston, SC Myrtle Beach, SC Brunswick, GA

More information

STORM DRAINS AND IRRIGATION

STORM DRAINS AND IRRIGATION TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 STORM DRAINS AND IRRIGATION 105.1. STORM DRAINS... 105.1 105.2. METHODS OF ANALYSIS... 105.1 105.2.1. Rational Method... 105.1 105.2.2.

More information

Will County Site Development Permit Submittal Checklist TAB 1 PROJECT OVERVIEW

Will County Site Development Permit Submittal Checklist TAB 1 PROJECT OVERVIEW Applicant: Reviewer: Permit No.: The following tables contain a checklist of the requirements before a review for a Site Development Permit submittal will be accepted. Not all requirements pertain to every

More information

SECTION III: WATERSHED TECHNICAL ANALYSIS

SECTION III: WATERSHED TECHNICAL ANALYSIS Trout Creek Watershed Stormwater Management Plan SECTION III: WATERSHED TECHNICAL ANALYSIS A. Watershed Modeling An initial step this study of the Trout Creek watershed was the selection of a stormwater

More information

CEDAR RUN WATERSHED ACT 167 STORMWATER MANAGEMENT PLAN FINAL REPORT

CEDAR RUN WATERSHED ACT 167 STORMWATER MANAGEMENT PLAN FINAL REPORT CEDAR RUN WATERSHED ACT 167 STORMWATER MANAGEMENT PLAN FINAL REPORT I. PURPOSE OF THE REPORT The purpose of this report is to summarize the findings and recommendations of the Cedar Run Watershed Act 167

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of April 21, 2007 DATE: April 20, 2007 SUBJECT: Approve the Award of a Contract to Sagres Construction Corp. for the construction of Phase I

More information

The Beckett s Run Experience. Fort Wayne, Indiana

The Beckett s Run Experience. Fort Wayne, Indiana The Beckett s Run Experience Fort Wayne, Indiana Introductions Charlie Cochran City of Fort Wayne, Wet Weather Storm & Sewer Engineering Jason Durr, PE Christopher B. Burke Engineering, LLC 2 A Little

More information

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

5/11/2007. WinTR-55 for Plan Reviews Small Watershed Hydrology Overview

5/11/2007. WinTR-55 for Plan Reviews Small Watershed Hydrology Overview WinTR-55 for Plan Reviews Small Watershed Hydrology Overview 1 Overview Course Outline Historical Background Program Description Model Capabilities and Limitations This is the Overview portion of the training.

More information

a. Title of Report Example: Final Hydrologic and Hydraulic Drainage Report For Tract #### (or Planning and Zoning Permit ##-###-###)

a. Title of Report Example: Final Hydrologic and Hydraulic Drainage Report For Tract #### (or Planning and Zoning Permit ##-###-###) CITY OF OXNARD ENGINEERING DIVISION REQUIRED FORMAT AND CONTENTS HYDROLOGIC AND HYDRAULIC DRAINAGE REPORTS This report will provide a basis for design of the drainage system for the subject project. The

More information

Model Results Operation and Maintenance (O& M) Results Cost-Benefit Analysis Results Conclusions

Model Results Operation and Maintenance (O& M) Results Cost-Benefit Analysis Results Conclusions BMP Performance and Outline Background Model Results Operation and Maintenance (O& M) Results Results Conclusions Melissa Baker, Water Resource Technician Capitol Region Watershed District, St. Paul, MN

More information

A Hydrologic Study of the. Ryerson Creek Watershed

A Hydrologic Study of the. Ryerson Creek Watershed A Hydrologic Study of the Ryerson Creek Watershed Dave Fongers Hydrologic Studies Unit Land and Water Management Division Michigan Department of Environmental Quality May 8, 2002 Table of Contents Summary...2

More information

Municipal Stormwater Ordinances Summary Table

Municipal Stormwater Ordinances Summary Table APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which

More information

HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS

HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS Project Name: Project Number: Reviewed By: Date: Telephone: Email: Address all items marked with an X Minimum Submittal Requirements 1. Conceptual Review

More information

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014 MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of

More information

LAKE COUNTY HYDROLOGY DESIGN STANDARDS

LAKE COUNTY HYDROLOGY DESIGN STANDARDS LAKE COUNTY HYDROLOGY DESIGN STANDARDS Lake County Department of Public Works Water Resources Division 255 N. Forbes Street Lakeport, CA 95453 (707)263-2341 Adopted June 22, 1999 These Standards provide

More information

Project Drainage Report

Project Drainage Report Design Manual Chapter 2 - Stormwater 2A - General Information 2A-4 Project Drainage Report A. Purpose The purpose of the project drainage report is to identify and propose specific solutions to stormwater

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

DEKALB COUNTY STORMWATER MANAGEMENT PLAN PHASE 2

DEKALB COUNTY STORMWATER MANAGEMENT PLAN PHASE 2 DEKALB COUNTY STORMWATER MANAGEMENT PLAN PHASE 2 Introduction DeKalb County, Illinois, located approximately 50 miles west of Lake Michigan, is rectangular in shape, with a north/south dimension of 36

More information

Town of Friday Harbor PO Box 219 / Friday Harbor / WA / (360) / fax (360) /

Town of Friday Harbor PO Box 219 / Friday Harbor / WA / (360) / fax (360) / Town of Friday Harbor PO Box 219 / Friday Harbor / WA / 98250 (360) 378-2810 / fax (360) 378-5339 / www.fridayharbor.org LAND CLEARING, GRADING, OR FILLING PERMIT APPLICATION APPLICATION DATE GRD No. APPLICANT/FRANCHISE

More information

EXECUTIVE SUMMARY DES PLAINES RIVER WATERSHED-BASED PLAN WHY A WATERSHED-BASED PLAN? WHAT IS A WATERSHED?

EXECUTIVE SUMMARY DES PLAINES RIVER WATERSHED-BASED PLAN WHY A WATERSHED-BASED PLAN? WHAT IS A WATERSHED? Des Plaines River Watershed-Based Plan EXECUTIVE SUMMARY June 2018 EXECUTIVE SUMMARY DES PLAINES RIVER WATERSHED-BASED PLAN WHY A WATERSHED-BASED PLAN? Water is elemental to our lives. Plants and animals,

More information

Final TMDL Implementation Plan. Prepared for Minnesota Pollution Control Agency

Final TMDL Implementation Plan. Prepared for Minnesota Pollution Control Agency Wirth Lake Final TMDL Implementation Plan Prepared for Minnesota Pollution Control Agency September 2010 4700 West 77 th Street Minneapolis, MN 55435-4803 Phone: (952) 832-2600 Fax: (952) 832-2601 wq-iw11-03c

More information

Hiawatha Golf Course Area Water Management Alternatives Assessment

Hiawatha Golf Course Area Water Management Alternatives Assessment Hiawatha Golf Course Area Water Management Alternatives Assessment Water Management Alternatives Prepared for Minneapolis Park and Recreation Board, City of Minneapolis, & Minnehaha Creek Watershed District

More information

HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR

HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR 1 INTRODUCTION 1.1 Project Description and Location Isabella Ocean Residences is a residential development to be constructed

More information

Final Drainage Report

Final Drainage Report Thornton Electric Substation Project Final Drainage Report December 14, 2016 DRAFT Prepared for: Xcel Energy, 1800 Larimer Street, Suite 400, Denver, Colorado 80202 Prepared by: 350 Indiana Street, Suite

More information

NOVATO WATERSHED PROGRAM

NOVATO WATERSHED PROGRAM NOVATO WATERSHED PROGRAM NOVATO CITY COUNCIL Photo Credit: Sue Lattanzio AGENDA OVERVIEW OF TONIGHT S TALK Slide 2 Context what is a watershed? Process how did we implement the watershed approach? Content

More information

DRAFT. Jacob Torres, P.E.; Nick Fang, Ph.D., P.E.

DRAFT. Jacob Torres, P.E.; Nick Fang, Ph.D., P.E. \ Memorandum SSPEED Center at Rice University Department of Civil & Environmental Engineering 6100 Main MS-317 Houston, Texas 77005-1827 sspeed.rice.edu tel: 713-348-4977 To Andy Yung, P.E. CFM; Lane Lease,

More information

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40

More information

RETENTION BASIN EXAMPLE

RETENTION BASIN EXAMPLE -7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary

More information

Hackensack River Flood Reduction Study Update

Hackensack River Flood Reduction Study Update Township of River Vale Hackensack River Flood Reduction Study Update November 11, 2013 Purpose of Study To Analyze Where Frequent Flooding Is Impacting Property and How It Might Be Reduced Hackensack River

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW th Ave NE Ham Lake, MN 55304

COON CREEK WATERSHED DISTRICT PERMIT REVIEW th Ave NE Ham Lake, MN 55304 18-151 Meyer Garage, Page 1 of 5 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: January 28, 2019 AGENDA NUMBER: 9 FILE NUMBER: 18-151 ITEM: Meyer Garage RECOMMENDATION: Approve with 2 Stipulations

More information

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements This checklist is to be completed and submitted with all Subdivision Applications. The Town reserves

More information

Traffic Impact Analysis (TIA) POLICY

Traffic Impact Analysis (TIA) POLICY Ascension Parish Planning Commission Traffic Impact Analysis (TIA) POLICY This policy establishes requirements for studies that provide information on traffic projected to be generated by all proposed

More information

INDIAN CREEK WATERSHED PLAN EXECUTIVE SUMMARY

INDIAN CREEK WATERSHED PLAN EXECUTIVE SUMMARY INDIAN CREEK WATERSHED PLAN EXECUTIVE SUMMARY The Indian Creek Watershed covers a 38 square mile area in southern Lake County, Illinois that drains 24,116 acres before discharging into the Des Plaines

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. KTJ 314, LLC Blaine, MN 55449

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. KTJ 314, LLC Blaine, MN 55449 18-118 ABRA Auto Body, Page 1 of 8 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 13, 2018 AGENDA NUMBER: 14 FILE NUMBER: 18-118 ITEM: ABRA Auto Body RECOMMENDATION: Approve with 6 Stipulations

More information

DICKINSON BAYOU WATERSHED STEERING COMMITTEE FINAL MEMBER CRITERIA COMPARISON

DICKINSON BAYOU WATERSHED STEERING COMMITTEE FINAL MEMBER CRITERIA COMPARISON DICKINSON BAYOU WATERSHED STEERING COMMITTEE FINAL MEMBER CRITERIA COMPARISON May 25, 2006 INTRODUCTION The Dickinson Bayou Watershed covers approximately 95.5 square miles and stretches from western Brazoria

More information

Drainage Report. New Braunfels Municipal Airport. Master Plan Update 2005

Drainage Report. New Braunfels Municipal Airport. Master Plan Update 2005 Drainage Report Master Plan Update 2005 General The Texas Department of Transportation (TxDOT), Aviation Division, retained the consulting engineering team of Parkhill, Smith & Cooper, Inc. (PSC), to prepare

More information

BMP Description: The GSWMD will work with NIRPC and local groups to mark existing storm sewer structures.

BMP Description: The GSWMD will work with NIRPC and local groups to mark existing storm sewer structures. Sewer Marking Projects is this The GSWMD will work with NIRPC and local groups to mark existing storm sewer structures. NIRPC By marking the storm sewer structures, it alerts the public that the structures

More information

Final Report Section 319 and Clean Water Partnership Projects

Final Report Section 319 and Clean Water Partnership Projects Grant Project Summary Final Report Section 319 and Clean Water Partnership Projects Project title: Wetland 639W Nutrient Export Reduction Organization (Grantee): Shingle Creek Watershed Management Commission

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY ENVIRONMENTAL SETTING The project site is located in the Wilshire community of the City of Los Angeles and is bound by S. Wetherly Drive to

More information

Drainage Criteria Manual Review

Drainage Criteria Manual Review City of Colorado Springs Stormwater Management Assessment and Standards Development Drainage Criteria Manual Review March 8, 2013 Springsgov.com/City Agencies/Stormwater/Stormwater Engineering/ Stormwater

More information

New Castle County, DE. Floodplain Regulations

New Castle County, DE. Floodplain Regulations New Castle County, DE Floodplain Regulations John J. Gysling, PE CFM Department of Land Use New Castle County, DE February 26, 2009 Today s Presentation Floodplain Protection and Uses Terms and Definitions

More information

Presentation Overview

Presentation Overview Little Dry Creek Restoration Deep River Flood Risk Management Final Presentation to LCRBDC June 10, 2015 Presentation Overview Project Overview & Background Information Data Collection Model Development

More information

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01 Stormwater Management Studies PDS Engineering Services Division Revised Date: 2/28/08 INTRODUCTION The City of Overland Park requires submission of a stormwater management study as part of the development

More information

Georgia s Unified Stormwater Sizing Criteria The Old, the New, and the Misunderstood

Georgia s Unified Stormwater Sizing Criteria The Old, the New, and the Misunderstood WATER RESOURCES Georgia s Unified Stormwater Sizing Criteria The Old, the New, and the Misunderstood Charles Crowell, PE Stormwater Section Manager October 2016 WATER RESOURCES The Old Traditional Stormwater

More information

TABLE OF CONTENTS. 1.0 Background Watershed Description Hydrology - HEC-HMS Models Hydraulics - HEC-RAS Models...

TABLE OF CONTENTS. 1.0 Background Watershed Description Hydrology - HEC-HMS Models Hydraulics - HEC-RAS Models... TABLE OF CONTENTS 1.0 Background... 1 2.0 Watershed Description... 1 3.0 Hydrology - HEC-HMS Models... 2 3.1 Hydrologic Approach... 2 3.2 Drainage Areas... 2 3.3 Curve Numbers... 2 3.4 Lag Times... 3 3.5

More information

Redevelopment Introduction

Redevelopment Introduction Redevelopment 11 11.1 Introduction Design standards for new development sites have been established in previous chapters of this document. Redevelopment sites, however, often present unique challenges

More information

2. DEFINITIONS. American Association of State Highway and Transportation Officials.

2. DEFINITIONS. American Association of State Highway and Transportation Officials. 2. DEFINITIONS 2.010 Definitions [See Amendment 2] In addition to words and terms that may be defined elsewhere in this manual, the following words and terms shall have the meanings defined below: AASHTO:

More information

LIST OF TABLES... ii LIST OF FIGURES... iii LIST OF APPENDICES... iv. Section 1 - Introduction Purpose of Study... 1

LIST OF TABLES... ii LIST OF FIGURES... iii LIST OF APPENDICES... iv. Section 1 - Introduction Purpose of Study... 1 Preliminary Hydrologic Analysis for Alberhill Villages April 2015 TABLE OF CONTENTS Section Name Page Number LIST OF TABLES... ii LIST OF FIGURES... iii LIST OF APPENDICES... iv Section 1 - Introduction...

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

Appendix B Stormwater Site Plan Submittal Requirements Checklist

Appendix B Stormwater Site Plan Submittal Requirements Checklist Stormwater Site Plan Submittal Requirements Checklist The Submittal Requirements Checklist is intended to aid the design engineer in preparing a Stormwater Site Plan. All items included in the following

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

3.0 Planning and Submittal Requirements

3.0 Planning and Submittal Requirements October 2003, Revised February 2005 Chapter 3.0, Planning and Submittal Requirements Page 1 3.0 Planning and Submittal Requirements 3.1 Drainage Studies and Drawings The City of Greenwood Village (Village)

More information

Genesee County Storm Water and Flood Control Design Standard Requirements

Genesee County Storm Water and Flood Control Design Standard Requirements Genesee County Storm Water and Flood Control Design Standard Requirements Effective date: 6/1/2018 TABLE OF CONTENTS Introduction 1 Role of the Genesee County Drain Commissioner 1 Table 1: Hierarchy of

More information

Appendix F. Flow Duration Basin Design Guidance

Appendix F. Flow Duration Basin Design Guidance Appendix F Flow Duration Basin Design Guidance Appendix F FINAL REPORT F:\SC46\SC46.31\HMP Mar 05\Appendices\Appendix F FLY_HMP.doc MARCH 2005 Appendix F Flow Duration Basin Design Guidance Prepared by

More information

Flooding - Tidal and Rainfall. Presentation to City Council Informal Session May 24, John M. Keifer PE

Flooding - Tidal and Rainfall. Presentation to City Council Informal Session May 24, John M. Keifer PE Flooding - Tidal and Rainfall Presentation to City Council Informal Session May 24, 2011 John M. Keifer PE Purpose of Presentation 1. Review flooding causes and implications to the City 2. Discuss mitigation

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS

DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS DESIGN CRITERIA FOR TERMINAL STORAGE RESERVOIRS Joint Booster Pump Station #3 Reservoir Nicole Rutigliano, P.E. May 29, 2014 PROJECT BACKGROUND Integrated Pipeline Project 149 miles of pipeline 3 booster

More information

Calculating System Development Charges for Stormwater Facilities

Calculating System Development Charges for Stormwater Facilities Calculating System Development Charges for Stormwater Facilities Arthur C. Nelson Reprinted with permission from Nelson, Arthur C. 1995. System Development Charges for Water, Wastewater, and Stormwater

More information

9.0 General Infrastructure Element

9.0 General Infrastructure Element 9.0 PURPOSE The purpose of this element is to ensure adequate provision of public facilities and services required to meet the future needs of the University, including the following: a) Ensure provision

More information