1 Atlas 14: The New Rainfall Atlas Olmsted County Environmental Commission Trends Subcommittee September 17, 2014 Presenter: Art Kalmes, PE, CFM Vice President Barr Engineering Co
2 agenda Overview of TP-40 and new Atlas 14 New Atlas 14 Rainfall Depths Midwest and Statewide Olmsted County Is this a Game Changer? Regional Scale Individual Projects Policies What are others doing? Conclusion and discussion
3 Framing this presentation.... this is an introduction of Atlas 14 our climate did not change the day Atlas 14 was released our understanding of the frequency of rainfall was update. this isn t a presentation on climate change. hydrologic modeling procedure, design practices, and protection standards have changed in the past. it is up to the County stakeholders to determine how they will use this information and their decisions there are few mandates please ask questions during the presentation if you like.
4 Technical Paper 40 (TP-40) created by NOAA in 1961 key document for hydrologists and water planners 63 storms that included dust bowl during 1930s gives rainfall data for every county in every state
5 Technical Paper 40 (TP-40) rainfall frequency or recurrence intervals: 1-year, 2-year, 5-year, 10-year, 25-year, 50-year, and 100-year events rainfall durations: 30-minute, 1-hour, 2-hour, 3-hour, 6-hour, 12-hour, 24-hour, 2-day, and 4-day events
6 Atlas 14 (the new TP-40) 11 states (dark blue) pooled funds to update Source: NOAA, peer technical review document
7 TP-40 Minnesota daily stations Atlas 14 Minnesota daily stations
8 TP-40 Minnesota sub-daily stations Atlas 14 Minnesota sub-daily stations
9 Atlas 14 - improved science average record length now over 50 years more than double the record used in original studies oldest Minnesota data set from 1836 (Ft. Snelling / Minneapolis St. Paul Airport) detailed data provides a clearer picture of the rainfall distribution new detail shows higher intensity during short storms NRCS is developing regional relationship to replace previous methodology
10 Atlas 14 - improved usability interactive web interface click to a specific point: no more estimating s.noaa.gov/hdsc /pfds/
11 Atlas 14 - improved usability station data provided in downloadable tabular form over 190 storms data on extreme events (up to 1000-yr)
12 improved usability or as depthdurationfrequency graphs
13 improved usability Confidence interval information
14 Atlas 14 rainfall depths - Midwest some significant increases in each state vs. TP-40 most of Minnesota and Wisconsin, eastern North Dakota, and the Black Hills of South Dakota percent change in 24 hour/ 100 year depths: Minneapolis, MN to 7.5 inches (+25%) Dakota County, MN to 7.4 inches (+23%) Ashland, WI to 7.3 inches (+38%) Fargo, ND to 6.5 inches (+23%) Rapid City, SD to 6.2 inches (+35%)
15 Atlas 14 rainfall depths - Midwest some decreases for certain storms central Minnesota, western North Dakota, most of South Dakota, and east/central Wisconsin degree of change tends to increase as storm frequency decreases example: MSP International AP Frequency % Change
16 Atlas 14 rainfall depths - Midwest some surprises (large changes over short distances) difference in 24 hour/ 100 year depths (inches): Minneapolis, MN to St. Cloud, MN: 7.5 to 6.4 (1.1 dif) Worthington, MN to Sioux Falls, SD: 7.4 to 5.9 (1.5 dif)
17 St. Cloud (Frequency) (%Change) Minneapolis/St. Paul (Frequency) (%Change)
18 Moorhead (Frequency) (%Change) Alexandria (Frequency) (%Change)
19 Rochester Airport (Frequency) (%Change)
20 Atlas 14 rainfall depths Olmsted County
21 Atlas 14 rainfall depths Olmsted County
22 Minneapolis/St. Paul (Frequency) (%Change)
23 Albert Lea (Frequency) (%Change)
24 Duluth Airport (Frequency) (%Change)
25 any questions?... That concludes the intro to Atlas next we will talk about its implications.
26 Is this a game changer? how does Atlas 14 data affect calculated flood levels? who (city, watershed org, state?) will decide which rainfall amounts will be used? permitting, ordinances, policies, and standards legal implications of using or not using Atlas 14 results when to start using Atlas 14 numbers? Barr Engineering Utica Ravine stabilization project in Savage, MN
27 Is this a game changer? How does it change flows and flood levels? Let s look at runoff. NRCS Rainfall Runoff Equation
28 Is this a game changer? How does it change flows and flood levels in residential watershed? NRCS Rainfall Runoff Equation
29 Is this a game changer? Residential Watershed Comparison, TP-40 vs. Atlas 14: 1.7 more precipitation produces 1.6 more runoff 42% increase in 100-yr runoff volume for residential watershed NRCS Rainfall Runoff Equation
30 Is this a game changer? How does it change flows and flood levels in rural (grassland) watershed? NRCS Rainfall Runoff Equation
31 Is this a game changer? rural (grassland) Watershed Comparison, TP-40 vs. Atlas 14: 1.7 more precipitation produces 1.2 more runoff 60% increase in 100-yr runoff volume for rural (grassland) watershed NRCS Rainfall Runoff Equation
32 Is this a game changer? how does it affect things on a regional scale? examined by the City of Rochester for South Fork Zumbro River hydrology based on stream gage data not rainfall Re-examined flood frequency using latest stream gage data
33 Is this a game changer? South Fork Zumbro River in Rochester FIS flows based on stream gage data
34 Is this a game changer? Conclusion: at flooding sources where hydrology was based on stream gage data, the previous evaluations (e.g. Flood Insurance Study or FIS) should be similar to updated evaluation. What Olmsted County stream/rivers are based on stream gage data South Fork Zumbro River Middle Fork Zumbro River (incl. S. Branch) Willow Creek (incl. E. Fork, S. Fork, SE Branch) South Fork of Bear Creek
35 Is this a game changer? How about if hydrology based on rainfall-runoff model (precipitation losses = runoff)? City of Rochester evaluated along Cascade Creek calculated peak flood discharges and flood levels using Atlas 14 rainfall depths compared these to previous values.
36 Is this a game changer? Cascade Creek in Rochester FIS flows based on rainfall-runoff model
37 Is this a game changer? Cascade Creek in Rochester FIS flows based on rainfall-runoff model
38 Is this a game changer? Atlas 14 data will predict more runoff and a larger floodplain than previous studies (e.g. FEMA floodplain maps) TP yr precipitation is similar to Atlas year Rochester Evaluation concluded: Future FEMA 100-year floodplain will be similar to current 500- year floodplain
39 Is this a game changer? the City of Rochester evaluation concluded that it is difficult to predict the amount the flood level will increase when Atlas 14 data is used. therefore, the establishment of future zoning restriction should be based on information specific to the flooding source
40 Is this a game changer? What Olmsted County stream/rivers are based on rainfallrunoff modeling and may be subject to future floodplain map changes? Cascade Creek (Incl. N Fork) Badger Run Bear Creek Hadley Valley Creek Silver Creek Carey Creek Mill Creek N. Branch of Root River S. Fork of Whitewater River
41 Is this a game changer? How about individual projects? newly placed systems (especially detention ponds) may now appear to be undersized for storms larger than 10-year modeled rainfall distribution can change since Atlas 14 provides actual data rather than assumed SCS distribution emergency overflows and freeboard protection will help needs to be assessed on an individual basis
42 Is this a game changer? Design and policy future storm sewer infrastructure sizing detention ponds future development possibly held to higher standards integrating current and future infrastructure capacities water quality features waste containment ponds animal waste storage systems roadway crossings
43 any questions?... that concludes the discussion about implications... next we will talk about what others are doing and conclude
44 possible approaches for water planners, designers, and regulators adopt Atlas 14 for new systems base level of protection on rainfall depth rather than event probability freeboard requirements take advantage of opportunities to mitigate impacts: safe overflow routes increase storage and infiltration larger easements increase conveyance
45 What others are doing? federal agencies have switched to Atlas 14 for design MnDOT has switched to Atlas 14 for design FEMA will incorporate when new maps are published Rochester is requiring on new stormwater infrastructure for design most LGUs and watershed districts are using or will be using for development reviews LGUs and watershed districts are transitioning for regional systems and floodplains most LGUs and watershed districts are assessing and planning
46 What others are doing City or Rochester Flood Forecasting display tool
47 Conclusions Atlas 14 increases rainfall depth for storms greater than 10-year; Rainfall pattern also is more intense the Olmsted County 100-year rainfall increases by approx. 30% runoff volume has larger increase up to 60% for rural grassland areas previous evaluations based on stream gage data will likely have little or no change previous evaluations based on a rainfall-runoff model will likely have measurable changes that could be significant there is no general rule for determining implications regional flood protection systems and infrastructure should focus on assessing risk
48 Conclusions implications will vary on an individual project or property basis local government policies will need to determine how to adopt Atlas 14 rainfall depths for new developments and projects Atlas 14 data, along with proper planning, will help us better manage our streams and rivers. South Fork Zumbro River, Rochester
49 so stay tuned very complex and broad-reaching issues to be addressed in the future Thank You!
Engineering Bulletin 11-02
ENGINEERING, SURVEYING & PERMIT SERVICES DEPARTMENT CHARLES LACKEY, P.E., DIRECTOR 2700 M STREET, SUITE 570 BAKERSFIELD, CA 93301-2370 Phone: (661) 862-8603 Fax: (661) 862-5149 E-mail: esps@co.kern.ca.us
More informationNew Castle County, DE. Floodplain Regulations
New Castle County, DE Floodplain Regulations John J. Gysling, PE CFM Department of Land Use New Castle County, DE February 26, 2009 Today s Presentation Floodplain Protection and Uses Terms and Definitions
More informationNRCS Hydrology methodology review Minnesota NRCS recommendation MnDOT recommendation Using Atlas 14 with HydroCAD
Dec, 2015 NRCS Hydrology methodology review Minnesota NRCS recommendation MnDOT recommendation Using Atlas 14 with HydroCAD NRCS - Natural Resource Conservation Service (formerly known as SCS Soil Conservation
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationCity of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017
City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 Phasing of Meetings April Meeting May Meeting October Review of Tax Day Storm Event and Immediate Actions Taken By City Review of Coordination
More informationChapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall
6.0 Introduction This chapter summarizes methodology for determining rainfall and runoff information for the design of stormwater management facilities in the City. The methodology is based on the procedures
More informationPeak discharge computation
Ia/P 4 Peak Dischage Method Graphical Peak Discharge Method This chapter presents the Graphical Peak Discharge method for computing peak discharge from rural and urban areas. The Graphical method was developed
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any
More informationFlash Flood Vulnerability and Climate Adaptation Pilot Project
Flash Flood Vulnerability and Climate Adaptation Pilot Project Philip Schaffner Office of Transportation System Management Minnesota Department of Transportation MnDOT s Pilot Project Objectives Better
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment
More information6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff
October 2003, Revised February 2005 Chapter 6.0, Runoff Page 1 6.1 Introduction 6.0 Runoff The timing, peak rates of discharge, and volume of stormwater runoff are the primary considerations in the design
More informationInflow Design Flood Control System Plan for Louisa Generating Station CCR Impoundment. MidAmerican Energy Company
Control System Plan for Louisa Generating Station CCR Impoundment MidAmerican Energy Company October 10, 2016 Control System Plan for Louisa Generating Station CCR Impoundment Prepared for MidAmerican
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationProject Drainage Report
Design Manual Chapter 2 - Stormwater 2A - General Information 2A-4 Project Drainage Report A. Purpose The purpose of the project drainage report is to identify and propose specific solutions to stormwater
More informationHydrologic Calibration:
Hydrologic Calibration: UPDATE OF EFFECTIVE HYDROLOGY FOR MARYS CREEK October 2010 Agenda Background Hydrologic model Calibrated rainfall Hydrologic calibration 100 year discharges, Existing Conditions
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationAPPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY)
APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY) Hydromodification design criteria for the North Orange County permit area are based on the 2- yr, 24-hr
More informationAPPENDIX L Hydrology and Stormwater Pond Analysis
APPENDIX L Hydrology and Stormwater Pond Analysis This page is left intentionally blank. Hydrology and Stormwater Pond Analysis Liesch Associates, Inc. June 1, 2012 Minneapolis-St. Paul International Airport
More informationRainfall, Runoff and Peak Flows: Calibration of Hydrologic Design Methods for the Kansas City Area
Rainfall, Runoff and Peak Flows: Calibration of Hydrologic Design Methods for the Kansas City Area Bruce McEnroe, Bryan Young, Ricardo Gamarra and Ryan Pohl Department of Civil, Environmental, and Architectural
More informationND Detention Project Development Update
ND Detention Project Development Update Upper Red River Basin Halstad, MN = 8 Upstream Subwatersheds Fargo, ND = 3 Upstream Subwatersheds Halstad, MN Fargo, ND Wild Rice Otter Tail Bois de Sioux Upstream
More informationENVIRONMENTAL ENGINEERING LAND SURVEYING
ENVIRONMENTAL ENGINEERING LAND SURVEYING Inflow Design Flood Control System Plan Scrubber Solids Pond No. 3 Sherburne County Generating Plant Introduction This report presents documentation and certification
More informationEngineering Hydrology Class 3
Engineering Hydrology Class 3 Topics and Goals: I.Develop s (estimate precipitation) II.Develop simple constant intensity design storm III.Develop SCS design storm Ocean s Why do we want to derive the?
More informationPreliminary Drainage Analysis
Preliminary Drainage Analysis Tanimura and Antle Employee Housing Town of Spreckels County of Monterey, California LIB150205 May 29, 2015 Prepared For: Tanimura and Antle Produce Prepared By: 9699 Blue
More informationIBS Site Drainage: Senior Design Project
IBS Site Drainage: Senior Design Project Len Wright, Ph.D., PE Lecturer, CEAE Wright.Len@gmail.com September 11, 2008 mwsw204i1.ppt/1 OUTLINE Motivation for Stormwater Management Quantity (both onsite,
More informationOffice of Strategic Planning and Projects Connecticut Department of Transportation CLIMATE CHANGE & EXTREME WEATHER PILOT PROJECT
Office of Strategic Planning and Projects Connecticut Department of Transportation CLIMATE CHANGE & EXTREME WEATHER PILOT PROJECT LITCHFIELD HILLS Lake Waramaug, Warren/Kent/Washington LITCHFIELD HILLS
More informationCoordinated Hazard Assessment and Mapping Program
Coordinated Hazard Assessment and Mapping Program Mississippi River flood, 1993 A PREDICTABLE DISASTER Floods are the most common natural disaster in Illinois, accounting for well over 90% of declared
More informationClimate Change Impacts on Joint Riverine and Coastal Flooding on Calleguas Creek in Ventura County, CA
Climate Change Impacts on Joint Riverine and Coastal Flooding on Calleguas Creek in Ventura County, CA James Gregory, James Jackson (ESA) Lily Verdone (TNC) FMA, September 8, 2016 Project Overview Coastal
More informationChehalis Basin Strategy Causes of Extreme Flooding. October 11, 2016 Policy Workshop
Chehalis Basin Strategy Causes of Extreme Flooding October 11, 2016 Policy Workshop Agenda Hydrology o Precipitation o Flow Climate Change Effects Land Use o Channel straightening and incision o Riparian
More informationTHE WATER IS RISING SCALABLE, RELIABLE, AND RELEVANT INFORMATION SUPPORTING FIRST RESPONDERS. May 3, 2017
THE WATER IS RISING SCALABLE, RELIABLE, AND RELEVANT INFORMATION SUPPORTING FIRST RESPONDERS May 3, 2017 Association of State Floodplain Managers 2017 Conference Jim Keith, PE, CFM Walter P Moore Andy
More informationDRAFT. Jacob Torres, P.E.; Nick Fang, Ph.D., P.E.
\ Memorandum SSPEED Center at Rice University Department of Civil & Environmental Engineering 6100 Main MS-317 Houston, Texas 77005-1827 sspeed.rice.edu tel: 713-348-4977 To Andy Yung, P.E. CFM; Lane Lease,
More informationBasic Hydrology Runoff Curve Numbers
Basic Hydrology Runoff Curve Numbers By: Paul Schiariti, P.E., CPESC Mercer County Soil Conservation District The SCS Runoff Curve Number The RCN (Runoff Curve Number) method was originally established
More informationENVIRONMENTAL ENGINEERING LAND SURVEYING
ENVIRONMENTAL ENGINEERING LAND SURVEYING Inflow Design Flood Control System Plan Bottom Ash Pond Sherburne County Generating Plant Introduction This report presents documentation and certification of the
More informationCOON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432
PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:
More informationPorous Pavement Flow Paths
POROUS PAVEMENT MODELING Clear Creek Solutions, Inc., 2010 Porous pavement includes porous asphalt or concrete and grid/lattice systems (nonconcrete) and paving blocks. The use of any of these types of
More informationChapter 4 "Hydrology"
Chapter 4 "Hydrology" Revised TxDOT Hydraulics Manual Jorge A. Millan, P.E., CFM TxDOT Design Division/Hydraulics 2012 Transportation Short Course October 17, 2012 Chapter 4 Sections 1 Hydrology s Role
More informationCity of North Royalton Ohio Turnpike 3 rd Lane Expansion Investigation Study
City of North Royalton Ohio Turnpike 3 rd Lane Expansion Investigation Study Followup Neighborhood Meeting November 10, 2005 1 Agenda Study Objectives and Methodology Evaluation of Flooding Problems Relationship
More information5/11/2007. WinTR-55 for Plan Reviews Small Watershed Hydrology Overview
WinTR-55 for Plan Reviews Small Watershed Hydrology Overview 1 Overview Course Outline Historical Background Program Description Model Capabilities and Limitations This is the Overview portion of the training.
More informationTechnical Memorandum Mine Plan of Operations Stormwater Assessment
Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum Mine Plan of Operations Stormwater Assessment To: Kathy Arnold From: David R.
More informationSTORMWATER MANAGEMENT LEGISLATION IN COOK COUNTY (P.A )
STORMWATER MANAGEMENT LEGISLATION IN COOK COUNTY (P.A. 093-1049) Summary of the Act In November 2004, the responsibility of Stormwater Management* in Cook County was placed under the authority of the MWRDGC
More informationEvaluating Release Rates for Specific Watersheds in Cook County
Evaluating Release Rates for Specific Watersheds in Cook County IAFSM March 8, 2017 Summary of MWRD Facilities 7 Water Reclamation Plants (including one of the worlds largest) ~ 554 Miles of Interceptors
More informationiswm TM Technical Manual Hydrology:
: 1.0 2.0 Downstream Assessment 3.0 Streambank Protection 4.0 Water Balance 5.0 Rainfall Tables 6.0 Hydrologic Soils Data Table of Contents 1.0... HO-1 1.1 Estimating Runoff... HO-1 1.1.1 Introduction
More informationStormwater Management Studies PDS Engineering Services Division ES Policy # 3-01
Stormwater Management Studies PDS Engineering Services Division Revised Date: 2/28/08 INTRODUCTION The City of Overland Park requires submission of a stormwater management study as part of the development
More informationAppendix B. Storm Drain System Data
MENIFEE VALLEY CAMPUS MASTER PLAN FINAL EIR MT. SAN JACINTO COMMUNITY COLLEGE DISTRICT Appendix Appendix B. Storm Drain System Data June 2017 MENIFEE VALLEY CAMPUS MASTER PLAN FINAL EIR MT. SAN JACINTO
More informationFargo-Moorhead Metropolitan Area Flood Risk Management Project
Fargo-Moorhead Metropolitan Area Flood Risk Management Project 52ND ANNUAL IOWA ASCE ENVIRONMENTAL & WATER RESOURCES CONFERENCE 03 April 2014 Aaron W. Buesing Senior Hydraulic Engineer Corps of Engineers,
More informationCHAPTER 3 STORMWATER HYDROLOGY. Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF
CHAPTER 3 STORMWATER HYDROLOGY Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF 3.1.1 Introduction to Hydrologic Methods...3.1-1 3.1.2 Symbols and Definitions...3.1-3 3.1.3 Rainfall
More informationHYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR
HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR 1 INTRODUCTION 1.1 Project Description and Location Isabella Ocean Residences is a residential development to be constructed
More informationMinnesota River Basin Interagency Study
650 Minnesota River Basin Interagency Study Agencies collaborate for basin water quality and ecosystem restoration in Minnesota, Iowa, North Dakota, and South Dakota A multi-state effort is underway to
More informationEFFECT OF UPSTREAM DEVELOPMENT ON THE CLEAR CREEK AREA
EFFECT OF UPSTREAM DEVELOPMENT ON THE CLEAR CREEK AREA Technical Memorandum Farming in the Floodplain Project Prepared for May 2017 PCC Farmland Trust Photo credit: Google Earth TABLE OF CONTENTS Page
More informationCOUNTY OF KANE. Kishwaukee River Headwaters Study Stakeholder Meeting Monday, February 26, :30 am Hampshire Village Hall
COUNTY OF KANE ENVIRONMENTAL AND BUILDING MANAGEMENT Timothy Harbaugh, P.E., DEE Director County Government Center 719 Batavia Avenue Geneva, IL 60134 www.co.kane.il.us Environmental Management: (630)
More informationActivity Calculating Property Drainage
Page 1 of 5 Activity 2.3.11 Calculating Property Drainage Introduction When a property is developed, it is important to understand that changes to watershed characteristics (i.e., land use, slope, soil
More informationReview Zone Application for D&R Canal Commission Decision
Review Zone Application for D&R Canal Commission Decision MEETING DATE: June 15, 2016 DRCC #: 15-4748 Phase I and II Latest Submission Received: May 4, 2016 Applicant: Kevin Hayes Country Club Meadows,
More informationSECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1
CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1
More informationStormwater Volume and Treatment Methods Simplifying the Numbers. IAFSM March 10, Presented by: Tom Powers P.E., CFM, LEED AP, CPESC
Stormwater Volume and Treatment Methods Simplifying the Numbers IAFSM March 10, 2011 Presented by: Tom Powers P.E., CFM, LEED AP, CPESC Introduction GOALS: Improve understanding of Rate and Volume (Quantity)
More information2A Stormwater Regulations and Permitting A. Iowa Drainage Law and Resources 1 B. Regulated Activities 1
Design Manual Chapter 2 - Stormwater Table of Contents TOC Table of Contents Chapter 2 - Stormwater 2A General Information 2A-1--------------------------------General Information A. Concept... 1 B. Informing
More informationStorm Water and Sanitary Sewer
Public Works Department Summary Report on Planned Capital Improvements Storm Water and Sanitary Sewer Introduction Public Works has assembled this summary report to highlight major capital improvements
More informationChapter 6 Hydrology TABLE OF CONTENTS CHAPTER 6 - HYDROLOGY
Chapter 6 Hydrology TABLE OF CONTENTS CHAPTER 6 - HYDROLOGY... 6-1 6.1 Introduction... 6-1 6.1.1 Objective... 6-1 6.1.2 Definition... 6-1 6.1.3 Factors Affecting Floods... 6-1 6.1.4 Sources of Information...
More informationHYDROLOGIC MODELING CONSISTENCY AND SENSITIVITY TO WATERSHED SIZE
HYDROLOGIC MODELING CONSISTENCY AND SENSITIVITY TO WATERSHED SIZE by James C.Y. Guo. Professor, Civil Engineering, U. Of Colorado at Denver, James.Guo@cudenver.edu.. And Eric Hsu, Project Engineer, Parson
More informationUrban Flooding: How can planners help?
Urban Flooding: How can planners help? Kate Evasic & Nora Beck Chicago Metropolitan Agency for Planning IAFSM 2018 Conference March 14, 2018 Agenda CMAP background Impacts of urban flooding Urban flooding
More informationJacobi, Toombs, and Lanz, Inc.
Area 5: Blackiston Mill Road at Dead Man's Hollow Flooding Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations
More informationE. STORMWATER MANAGEMENT
E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson
More informationPresentation Overview
Little Dry Creek Restoration Deep River Flood Risk Management Final Presentation to LCRBDC June 10, 2015 Presentation Overview Project Overview & Background Information Data Collection Model Development
More informationDRAINAGE PLAN OF NAU S EASTBURN EDUCATION AND GAMMAGE BUILDINGS FINAL PROPOSAL
MAY 10, 2016 DRAINAGE PLAN OF NAU S EASTBURN EDUCATION AND GAMMAGE BUILDINGS FINAL PROPOSAL Connor Klein, Jiangnan Yi, Yuzhi Zhang, Yi Yang NORTHERN ARIZONA UNIVERSITY NAU Water Buffalo Engineering Table
More informationModel Results Operation and Maintenance (O& M) Results Cost-Benefit Analysis Results Conclusions
BMP Performance and Outline Background Model Results Operation and Maintenance (O& M) Results Results Conclusions Melissa Baker, Water Resource Technician Capitol Region Watershed District, St. Paul, MN
More informationWestern Washington Hydrology Model (WWHM) Software Introduction. Doug Beyerlein, P.E., P.H., D.WRE Clear Creek Solutions, Inc. Mill Creek, Washington
Western Washington Hydrology Model (WWHM) Software Introduction Doug Beyerlein, P.E., P.H., D.WRE Clear Creek Solutions, Inc. Mill Creek, Washington Clear Creek Solutions Hydrology Expertise Clear Creek
More informationUrbanizing Watersheds: Green Infrastructure and Hydrologic Function. Jay Dorsey, PE, PhD ODNR-DSWR October 30, 2014
Urbanizing Watersheds: Green Infrastructure and Hydrologic Function Jay Dorsey, PE, PhD ODNR-DSWR October 30, 2014 Green Infrastructure Objectives Intentional about maintaining/replacing ecosystem functions
More informationHYDROLOGY REPORT HEACOCK & CACTUS CHANNELS MORENO VALLEY, CALIFORNIA NOVEMBER 2005 REVISED APRIL 2006 REVISED AUGUST 2006
HYDROLOGY REPORT HEACOCK & CACTUS CHANNELS MORENO VALLEY, CALIFORNIA NOVEMBER 2005 REVISED APRIL 2006 REVISED AUGUST 2006 RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT TABLE OF CONTENTS
More informationIowa Climate Change Adaptation and Resilience: Applying Climate Data to Plans & Ordinances
Iowa Climate Change Adaptation and Resilience: Applying Climate Data to Plans & Ordinances Christopher J. Anderson, PhD Assistant Director, Climate Science Program Iowa State University Integrating Hazard
More informationNEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL
NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by
More informationHydrologic Study Report for Single Lot Detention Basin Analysis
Hydrologic Study Report for Single Lot Detention Basin Analysis Prepared for: City of Vista, California August 18, 2006 Tory R. Walker, R.C.E. 45005 President W.O. 116-01 01/23/2007 Table of Contents Page
More informationPennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines
Pennsylvania Stormwater Best Management Practices Manual Chapter 3 Stormwater Management Principles and Recommended Control Guidelines 363-0300-002 / December 30, 2006 Chapter 3 Stormwater Management Principles
More informationEstimating Future Floods to Manage Flood Risk
Estimating Future Floods to Manage Flood Risk Michael Anderson California State Climatologist Extreme Precipitation Symposium 2012 Talk Overview Statistics Physics Climate Change Flood Management and the
More informationWMS Tools For Computing Hydrologic Modeling Parameters
WMS Tools For Computing Hydrologic Modeling Parameters Lesson 9 9-1 Objectives Use the drainage coverage as a basis for geometric parameters as well as overlaying coverages to compute important hydrologic
More informationMunicipal Stormwater Management Planning
Municipal Stormwater Management Planning Christopher C. Obropta, Ph.D., P.E. Water Resources Extension Specialist with Rutgers Cooperative Extension Assistant Professor with Department of Environmental
More informationNorman Maclean Snowmelt Flow rate Storm flows fs (c flow m a tre S
Eventually, all things merge into one, and a river runs through it. Norman Maclean Understanding Streamflow ADEQ SW Short Course June 13, 213 Phoenix, AZ Hydrographs Discharge (Q) USGS flow data & plots
More informationHEC-RAS 2D Modeling in Support of Ascension Parish Levee Certification
HEC-RAS 2D Modeling in Support of Ascension Parish Levee Certification OFMA 2017 Annual Conference September 19, 2017 Presented by: Jeff Doudrick, PE, ENV SP Project Manager HNTB Corporation Agenda Project
More informationSmart modelling for future proof rainwater systems: Sirio & Scan software
Smart modelling for future proof rainwater systems: Sirio & Scan software Stormwater Poland 2018 15-16 March, Gdansk dr. ir. Vincent Wolfs Situation in Belgium Climate change Floods Droughts Urbanisation
More informationIV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY
IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY ENVIRONMENTAL SETTING The project site is located in the Wilshire community of the City of Los Angeles and is bound by S. Wetherly Drive to
More informationPlan Rollout Presentation July 31, Michael G. Hahn, P.E., P.H. Chief Environmental Engineer. Southeastern Wisconsin Regional Planning Commission
Plan Rollout Presentation July 31, 2014 Michael G. Hahn, P.E., P.H. Chief Environmental Engineer Southeastern Wisconsin Regional Planning Commission # 219703 Racine County Flooding Recommendations and
More informationFIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials.
I. Drainage Report A. Executive Summary - Brief Overview of Project Drainage Design B. Project Description 1. Existing Conditions 2. Proposed Project Conditions 3. Project Justification Narrative - Basin
More informationSECTION 4 SURFACE WATER MANAGEMENT DESIGN AND CONSTRUCTION REQUIREMENTS
SECTION 4 SURFACE WATER MANAGEMENT DESIGN AND CONSTRUCTION REQUIREMENTS Page 4-1 INTRODUCTION 4-3 4-1.01 Applicability of VMCs 14.24, 14.25, 14.26 4-4 4-1.02 Minimum Requirements - Projects Below Threshold
More information1. Stream Network. The most common approach to quantitatively describing stream networks was postulated by Strahler (1952).
1. Stream Network The most common approach to quantitatively describing stream networks was postulated by Strahler (1952). First Order Streams streams with no tributaries. Second Order Streams begin at
More informationClimate Vulnerability Assessment Localized Flood Risk
Climate Vulnerability Assessment Localized Flood Risk Metropolitan Council Committee of the Whole November 1, 2017 Today s Discussion Overview Localized Flooding (Bluespot) Approach and Limitations Methodology
More informationNutrient Management in. A presentation to the West Metro Water Alliance
Nutrient Management in Developing and Agricultural Areas A presentation to the West Metro Water Alliance Chris Meehan, P.E. May 25, 2011 Agenda Physical Improvements Planning Improvements How to get it
More informationInflow Design Flood Control System Plan
Inflow Design Flood Control System Plan B.C. COBB GENERATING FACILITY BOTTOM ASH POND INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN Muskegon, Michigan Pursuant to 40 CFR 257.82 Submitted To: Consumers Energy
More informationRhode Island Stormwater Design and Installations Standards Manual
Rhode Island Stormwater Design and Installations Standards Manual Public Workshop Required Management Volume Calculations and Redevelopment Considerations March 22, 2011 Presentation Outline Recap of How
More informationLID & Detention Pond Sizing Tool to Address Hydromodification and Water Quality in Clackamas County
LID & Detention Pond Sizing Tool to Address Hydromodification and Water Quality in Clackamas County Leah Johanson, Water Environment Services February 12 th, 2015 Agenda» WES History/Stormwater Standards»
More informationKing County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds
News Release Contact: Al Sanders 206-477-1016 August 31, 2015 Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds The Flood Control District
More informationModeling catchment scale infiltration
Modeling catchment scale infiltration Serena Ceola, DICAM, University of Bologna Advanced Hydrology & Water Resources Management INTRODUCTION OBJECTIVE: Understanding the processes and the methods for
More informationStormwater Maintenance. Committee of the Whole Middleton Common Council Updated March 12, 2013
Stormwater Maintenance Committee of the Whole Middleton Common Council Updated March 12, 2013 What is Stormwater Runoff? The waters derived from rains falling or snowmelt or ice melt occurring within the
More informationPre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015
Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Urban Runoff Background How we got here What Problem?? Provenance of the Problem Unified Sizing Criteria What
More informationFort Leonard Wood, Missouri. September 2013
Fort Leonard Wood, Missouri September 2013 1 Presenters Shannon Kelly, Physical Scientist Clean Water Act Program Manager Directorate of Public Works Environmental Division Environmental Compliance Branch
More informationPOLICY FOR NATURAL RESOURCE MANAGEMENT AREAS
POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS I. POLICY STATEMENT Auburn University's (the University's) "Policy for Natural Resource Management Areas" implements the Campus Master Plan Land Use Element
More informationRunoff Volume: The Importance of Land Cover
Runoff Volume: The Importance of Land Cover Grade Level: 9-12 Time: 1-2 class periods Learning Objectives: - Quantify the volume of water that runs off different land uses in a watershed. - Analyze the
More informationWhat to Expect When You re Expecting A LOMR. Mark Seidelmann, PE, GISP ASFPM 2015, Atlanta Georgia
What to Expect When You re Expecting A LOMR Mark Seidelmann, PE, GISP ASFPM 2015, Atlanta Georgia Thursday, June 4 th, 2015 Agenda 1 Why File a Letter Of Map Revision (LOMR)? 2 Basic Requirements and Common
More information4.1 General Methodology and Data Base Development
Chapter 4 METHODOLOGY 4.1 General and Data Base Development This report project utilized several computer software models and analysis techniques to create the numeric data on which decisions for this