1 Logistics Plan Keybridge House 80 South Lambeth Road Vauxhall Page 1 of KBH Logistics Plan

2 Prepared by Mike Hampton Approved by Nyron Higgins Date Plan Approved Issued to Issue Revision Issue Date N Higgins Rev Page 2 of KBH Logistics Plan

3 Contents 1.0 Scope of Work 2.0 Neighbouring Area 3.0 Site Planning and Logistics Overview 4.0 Site and Project Constraints 5.0 Sequencing of Works 6.0 Road and Traffic Management 7.0 Suspension / Road Closures / Footpath 8.0 Site Hoarding and Gate 9.0 Safety and Directional Signs 10.0 Site Offices and Welfare 11.0 Site Operational Hours 12.0 Site Security Access and Egress 13.0 Vehicle Access and Egress 14.0 Delivery and Material Management 15.0 Waste Management 16.0 Noisy Works 17.0 Reducing The Level of Dust 18.0 Tower Crane 19.0 Hoist Strategy 20.0 Scaffold 21.0 Material Distribution 22.0 Loading Platforms 23.0 Protection of the Public 24.0 Temporary Services 25.0 Fire Strategy 26.0 Occupation 27.0 Drawings Page 3 of KBH Logistics Plan

4 1.0 Scope of Work The project consists of constructing 441 Apartments over 5 Blocks Block A contains 171 private residential apartments constructed over 37 floors 36 floors with a concierge / entry foyer on the ground floor, overlooking landscaped areas and Spa within the basement. Block B contains 81 private residential apartments and 7 HA units constructed over, 9 floors with retail units on the ground floor accessible via South Lambeth Rd. Block C contains 81 units over 9 floors, 72 of which are for Private rental scheme with A2 Dominion the remaining 7 for HA. Block D contains 10 duplex apartments over 4 floors for HA. Block F contains 91 apartments over 22 floors all for Private rental scheme with A2 Dominion (See Attached Logistics Drawing 1.0) 2.0 Neighbouring Area Keybridge House site is located in the heart of London s regenerated Vauxhall on South Lambeth Road opposite Vauxhall Park and a short walk from the mainline, tube and bus station. The scheme is registered with the Considerate Constructors scheme which will target high scores against elements of the Code of Practice. All resident enquires and issues are directed to contact Nyron Higgins on Page 4 of KBH Logistics Plan

5 3.0 Site Planning and Logistics Overview The planning and logistics of Keybridge House is key to the construction success of the project. The traffic routes to site have been closely examined taking into account the size and length of vehicles required especially when delivering bulky materials. South Lambeth road, Miles Street & Wyvill Road will all serve as entry points into the project and robust traffic management will be imperative to ensure the construction traffic does not affect the local traffic, TFL bus routes but more importantly the safety and welfare of parents and children attending Wyvil road primary school. Key Points Maintaining free traffic flow along South Lambeth Road, ensure Miles street is kept clear of delivery vehicles directing them on to site upon arrival and adhere to the strict times imposed on Wyvill road so as not to impede with school drop off and pick up times. Ensuring the efficient free flow of operatives onto and away from the Project. Managing the distribution flow of materials within the building and rubbish removal in order to maintain the required levels of productivity whilst achieving the high quality standards expected. Plant and operative segregation during all stages of the Project Robust traffic management principles and practices will need to be enforced at all three entry points to site to ensure construction traffic does not create congestion or pose a hazard to the local community. Accommodating the welfare of 550 personnel at the peak of construction activity Protection to the public for the duration of the Project on all elevations Clear visible Nine Elms Group signage will be used to identify individually the three delivery gates Page 5 of KBH Logistics Plan

6 4.0 Site and Project Constraints The constraints on the Keybridge House project are fully detailed in the WSP Structural Report. A summary of the items are as below: Roads - Buried Services within the pavements & roads. Network Rail Waterloo mainline tracks run adjacent to the site boundary. Existing Basement Footprint of the new site incorporating existing basement requiring extensive and complex alteration. UKPN Assets Chambers, Transformer Rooms & HV Cables UKPN Access - Secondary Access Rights to deliver/maintain plant to their Assets. BT Chamber Encased by the basement diaphragm wall South Lambeth road elevation St Anne and all saints Church Adjacent to site boundary Griffin Public House - Wall that is subject to Party Wall agreement. Water Table Measured at to -15.2mOD Plan extract from WSP Structural Report. Page 6 of KBH Logistics Plan

7 5.0 Sequencing of Works The current buildings will be demolished down to the ground floor retaining a majority of the existing ground floor slab, the existing basement will undergo significant alteration during the demolition period, and steel transfer support beams will be installed for block B also during the demolition stage. Cores for blocks B, C and D will commence from sub basement and tied back into the existing ground floor structure and newly constructed ground floor transfer beams. Blocks B, C & D will then commence there superstructure concrete frames along with the cladding, M&E and Internal Fitout as shown below in a staggered program to release the apartments Q During this period the existing tower will continue to be demolished whilst new piles are introduced below for blocks A & F, on completion of structural demolition the final elements of basement alteration will be completed and substructure completed to ground floor level tied back to the ground floor slab, both blocks will commence superstructure concrete frames along with the cladding, M&E and Internal Fit out as shown below in a staggered program to release the apartments throughout Road and Traffic Management The project is primarily located on South Lambeth rd. between Wyvil and Miles street South Lambeth road is a main link between the A3 (SW London) and Vauxhall bridge into Westminster, It also provides access for many Bus routes that transport passengers about London. Miles Street located to the East of the Site is a no through road with a rail viaduct, at this location additional measure will be in place to ensure the viaduct is protected and is not struck by vehicles entering/exiting site. With the roads around the site perimeter already busy for the majority of the day due to local and construction traffic from local schemes a robust traffic management system will be used to ensure there is no traffic build up or congestion caused as a result of our construction activities. To ensure smooth and efficient traffic management, Traffic Marshals, Banksmen and gatemen will be deployed at strategic locations to receive and depart all site traffic. All Sub-contractors will be informed of the delivery routes and restricted roads that will be used for site deliveries to the Keybridge House Project. All vehicles will be booked in via the delivery booking system. This system will be strictly operating to coordinate / control / manage congestion. There are several other construction projects concurrently being built within 200m radius of Keybridge House Page 7 of KBH Logistics Plan

8 and many more around the Vauxhall/Nine Elms area that will increase demand on the roads and access into the area that could cause disruption to bus and taxi operations. The booking system adopted will be monitored by the site logistics manager to ensure no overbooking of slots takes place and that the required offloading times are given to minimise the congestion on public highways, in addition regular meetings will be held with local schemes to coordinate any major deliveries, crane erections/dismantles a general activities that may impact each site. Page 8 of KBH Logistics Plan

9 7.0 Suspension / Road Closures / Footpath Closures / Applications It is not anticipated that a full road closure will be required for the Project; Periods during the construction phase will require partial closure of both Wyvill Rd and Miles street to enable the erection/dismantle of tower cranes. The project Logistic Manager will ensure all affected parties have been consulted and an agreement is in place with all associated permits for the intermittent closures. A specific temporary traffic management plan will be produced and implemented for these partial road closures. Wyvill rd footpath adjacent to the site boundary will be closed and hoarding encompassing for the duration of construction phase to blocks B, C and D this will enable works to be completed safely and protect the general public from construction activities overhead. (Wyvill Road hoarding will be positioned on the kerb line) 8.0 Site Hoarding and Gates A high quality pictorial hoarding with a ply backing to give aesthetic continuity around the site will be erected to display marketing information and key components / progress in relation to the project for the general public to view. Page 9 of KBH Logistics Plan

10 Three gates have been located around the site for use and will reduce down to one gate as the project progresses and blocks complete. All gates will be manned by traffic marshals during site working hours. (See Attached Logistics Drawing 8.0) Page 10 of KBH Logistics Plan

11 9.0 Safety and Directional Signs Robust signage will be placed at strategic locations to ensure pedestrian and site personnel are made aware of high risk areas. The signage will highlight the following aspects: Live Constructions Areas Directional Signage Lifting Operations PPE Working Area Safe Zones Emergency Exits Page 11 of KBH Logistics Plan

12 10.0 Site Offices and Welfare The Keybridge project will have standalone office and welfare facilities located either within the site boundary adjacent to the pedestrian entrance or if possible within the arches to the Network rail viaduct running along the north elevation and both will remain in position for the duration of the project.. Facilities to be provided are: Mount Anvil Staff Offices Contractors Project Offices (Project Management staff only) IT & Communications connectivity sub contractor responsibility Canteen (Hot Menu Provided) & Seating Toilets First Aid / Nurse Drying / Changing Rooms Shower The Trade Contractors office will be open plan to encourage communication between them to resolve issues and collective plan requirements. (See Attached Logistics Drawing 10.0) 11.0 Site Operation Hours The general site working hour will be: Monday to Friday: 8:00am to 6:00pm Saturday (As Required) 8:00am to 1:00pm Page 12 of KBH Logistics Plan

13 12.0 Site Security Access and Egress The site will be kept secure at all times with the 3m perimeter hoarding built from plywood with a high quality finish. The hoarding will be maintained and periodically adapted throughout the duration of the Project to suit the progress of the works. 24 hour site security cover will be provided, including a resident night security guard and perimeter CCTV. All Trade Contractors will be responsible for their own materials and equipment. During working hours there will be sufficient security staff and traffic marshals to safely control all pedestrian and vehicle movements on site as noted earlier. A traffic manager will be located at the entrance to control the movement of vehicles coming in from all three gates. All site areas and specifically the site perimeter will be regularly patrolled during working hours. Details of patrols will be recorded and any security breach noted will be escalated and reported immediately. Access and Egress control of personnel onto site will be based on a palm recognition system, via turnstiles. Sub contractors will be required to issue information relating to their operatives contact details, safety training and country of origin etc. All personnel must display ID cards on outer clothing on a quick release lanyard or similar. CCTV cameras with the option to link to a sensor system positioned around the site will be used. When the sensor system is activated, the central control is contacted and the appropriate response is undertaken. Depending on the need, direct audio contact with the intruders can be made or the police and main key holders contacted. Page 13 of KBH Logistics Plan

14 13.0 Vehicle Access and Egress There are three gates positioned around the hoarding on the project and will be adjusted as the project progresses throughout its various stages. (See Attached Logistics Drawing 13.0) 14.0 Delivery and Material Management There will be no long-term materials storage within the loading bays, all materials deliveries will be planned to be off loaded and taken directly to the floor level where the materials are required, or to pre-assigned lay down areas. Effective and efficient delivery and material management will also undoubtedly promote safe operative movement around the site & allow for easier transportation of materials within the site by the sub contractors. To achieve this, a just in time delivery management policy will be implemented and managed by the Logistics Team to prevent excess materials accumulating on site. A Web based booking in system will be provided for booking and the coordination of deliveries monitored and managed by our dedicated Logistics Manager. Page 14 of KBH Logistics Plan

15 15.0 Waste Management Mount Anvil is committed to maintaining the highest environmental standards and complies with the requirements of the BREEAM assessment criteria. Furthermore the same demands are expected from our supply chain and they are actively encouraged to comply. Regular audits will be conducted of the waste recycling company, their transfer facility and landfill sites. These audits are intended to confirm compliance with legislation and to ensure every effort is being made to maximize the recycling of waste generated from site. Audits of waste will be carried out to ensure waste is minimised and percentage waste by waste stream is checked. Special waste will be identified before using on site and will be removed by the sub contractors responsible. Recyclable materials such as concrete, blockwork, timber, metal and plasterboard, will be placed in separate containers for reprocessing. The Concrete contractor will provide their own waste removal. Individual sub contractors will be responsible for breaking down and placing all rubbish arising from their works in the bins provided, segregating recyclable elements where possible. Bins that are full will then be removed by the Logistics Team and taken to the site recycling area. A sufficient number of bins will be held on site to ensure that bins are always available to subcontractors. This waste will then be collected by mobile compactor and transported to a licensed transfer facility where it will be segregated for onward transportation to various recycling houses. Left over waste is sent to landfill. When the waste is received at a recycling facility, all copies of transfer notes and written descriptions of the waste will be submitted. Mixed waste will be deposited in the transfer facility and sorted into its key elements. There will then be a basic pre-sort of the waste into heavy and light material. This will be carried out by a specialist waste recycler. At this stage any material that can be recovered for reuse, for example hoardings, timber, metal, pallets, plastics; tins of paint will be removed. These materials can then be either reused on construction projects or offered to community projects. At this stage any large items of metal, timber, plastic, cabling, packaging materials will be removed and placed into there relevant bays to await processing on site, or for bulk transportation to the relevant re processor. It will be the sub contractor s responsibility to maintain their respective work areas in a clean and safe manner; not at the end of an operation or shift but as soon as the generated waste becomes a safety or potential fire issue. Page 15 of KBH Logistics Plan

16 16.0 Noisy Works Noisy works will be controlled utilising the hierarchy of risk control and measured using noise monitoring equipment to ensure safe levels are not compromised and noisy work hours are not breached. In all noisy work cases works substitution of equipment for machines or processes which reduce the noise levels to acceptable levels and therefore minimise the impact on both site personnel and the general public will be used. Where this is not possible engineering controls will be employed utilising such control measures as baffles, noise screens and cutting stations shown below 17.0 Reducing the Level of Dust To ensure the level of dust is controlled within the site boundary Mount Anvil will: Provide designated water points to allow sub contractors to wet down any external work area s that may be prone to cause dust to drift outside the site boundaries. All bulk cutting of timber will be carried out in purpose built temporary cutting shops with a dust extraction system within; this will ensure the created dust does not travel out of the designated area. All contractor cutting tools will have an integrated vacuum function for dust extraction. Vacuum cleaning will be used where practicable in lieu of sweeping Page 16 of KBH Logistics Plan

17 18.0 Tower Crane Four Luffing Jib Tower Cranes will be erected during the substructure and superstructure works. The crane specifications and finalised locations are TBC once a Frame contractor has been appointed. TC1 and TC2 will be erected in tandem to minimise disruption on site, both will be at a height of m AOD approx to the underside of slew ring and have a 40m jib. Our preferred option for both cranes is to site the base on a cruciform at ground floor level with back props transferring down to the existing raft foundation TC4 a proposed height of m to underside of slew ring with a 40m jib, the crane base will need to sit within a new pile cap that will eventually form part of the new raft foundation for Block A, for the offset 3 no ties will gradually be introduced fixed back to the core of block A, as the frame progresses these ties will be replaced and the crane tied to the slab minimising any need to leave areas during fit out TC5 will adopt the same The usage of cranes is predominately allocated to the construction of the structure (80% per day) and Cladding Installation (10%) and the remaining time allocated for specialist individual lifts coordinated on the day as required. (See Attached Logistics Drawing s 18.0) Page 17 of KBH Logistics Plan

18 19.0 Hoist Strategy Block A, B, C & F will all be set up with twin hoists with similar specifications to allow for separate goods and passenger transportation. Building A will have an additional Goods hoist located adjacent to the twin that will primarily use for cladding panels and façade material. All hoists will serve the basement and sub basement with the ability to be loaded with a forklift. All goods hoists will be manned. The allocation of the hoist in each subcontract will be strictly controlled. Please refer to the fabricated scope and to the availability to this subcontract. The availability of the hoist will be controlled via a booking system on a first come first severed basis. No claim to delay arising from this will be entertained. Summary of the hoist anticipated specifications are as below: BLOCK A (Goods / Passenger) Twin Hoist 1.5 x 3.7 x 2.0m (2.0T) 2.0 x 3.7 Open Top (2.0T) Top Landing Height 128.5m 39 Gates 13 Ties Installation + 8 Staged Climbs Oct 17 Feb 19 BLOCK A (Goods) Single Hoist 1.5x3.7m Open Top (2.0T) Top Landing Height 128.5m 39 Gates 13 Ties Installation + 8 Staged Climbs Oct 17 Feb 19 BLOCK C/D (Goods / Passenger) Twin Hoist 1.5 x 3.7 x 2.0m (2.0T) 2.0 x 3.7 Open Top (2.0T) Top Landing Height 31.2m 10 Gates 4 Ties Installation + 2 Staged Climbs Dec 16 Sep 17 BLOCK B (Goods / Passenger) Twin Hoist 1.5 x 3.7 x 2.0m (2.0T) 2.0 x 3.7 Open Top (2.0T) Top Landing Height 31.2m 10 Gates 4 Ties Installation + 2 Staged Climbs Nov 16 Oct 17 BLOCK F (Goods / Passenger) Twin Hoist 1.5 x 3.7 x 2.0m (2.0T) 2.0 x 3.7 Open Top (2.0T) Top Landing Height 74m 25 Gates 11 Ties Installation + 5 Staged Climbs Mar 17 Apr 18 Page 18 of KBH Logistics Plan

19 20.0 Scaffold A common user Scaffold Contractors is employed on the Project called TBA. All sub contractors will use this business for any tube and fitting type access Material Distribution All unloading from the loading bays is to be arranged by the trade packages. A forklift and driver will be on site supplied by the logistic package for material distribution around the ground, Basement and Sub-Basement floors. It is the responsibility off each trade to move required materials to your required task areas Loading Platforms To aid the loading out Cantideck type sliding loading platforms will be positioned on certain floors. These could also be used for launching cladding panels if required. These platforms will be located to Blocks A and F. Page 19 of KBH Logistics Plan

20 23.0 Protection of Public at Building Perimeter To manage the risk of constructing the project, the following elements of temporary works are planned to be installed at the perimeter of the building. During concrete frame and cladding bracket installation combi safe, type fans will be installed to the perimeter and moved vertically as the work progresses. Any trade contractors working close to the buildings edge will require tethering all tools and materials to ensure they do not fall off the building edge. Blocks B, C And D Standard Height hand rail will be installed to the perimeter scaffold and will be adjusted as required for cladding installation. Blocks A & F Perimeter full height hydraulic screens that cover 3 levels of the structure and will be installed and jumped as the concrete pours of the slabs progresses. Prior to the perimeter screens being lifted, a full height handrail and mesh panels system will be installed to the floor plates until the cladding panels are installed to enclose the structure. Page 20 of KBH Logistics Plan

21 24.0 Temporary Services POWER Temporary power will be distributed throughout the site from the TBS located / Mains Distribution Unit (MDU) within the basement. Transformer Units (TU) will be distributed on each floor supplying 110v (16amp) 110v (32amp) will be supplied to locations that have requirement. WATER Temporary builders supply for water will be taken from the permanent water supply connection within the basement. Outlets will be positioned on every second floor within each block as illustrated on the attached drawings. (See Attached Logistics Drawing 24.0) 25.0 Fire Strategy Fire Points, evacuations alarms are located as indicated on the drawings. Fire Escape Routes will be updated as the project progresses as identified in the Fire Plan (See Attached Logistics Drawing 25.0) Page 21 of KBH Logistics Plan

22 26.0 Occupation Occupations of the buildings will be phased according to sectional handovers. On the completion of Blocks B, C and D, the hoarding line will be diverted behind Block B to form a new secure boundary whilst Blocks F and F are completed. The open Public space around the perimeter of Blocks B, C and D will available at time of completion. Page 22 of KBH Logistics Plan

23 27.0 Drawings See Below Page 23 of KBH Logistics Plan

Brighton & Sussex University Hospital

Brighton & Sussex University Hospital Brighton & Sussex University Hospital Regional Centre for Teaching, Trauma & Tertiary Care known as the 3Ts Programme Project Address: Eastern Road, Brighton BN2 5BE Principal Contractor: Laing O Rourke

More information

UCL ESTATES & FIRE STANDARD - GENERAL PERFORMANCE FOR SITE HOARDING AND CONTRACTOR CABINS

UCL ESTATES & FIRE STANDARD - GENERAL PERFORMANCE FOR SITE HOARDING AND CONTRACTOR CABINS Mandatory Fire Safety Instruction UCL ESTATES & FIRE STANDARD - GENERAL PERFORMANCE FOR SITE HOARDING AND CONTRACTOR CABINS UCL general hoardings details - what you need to know: Prohibited Note Prior

More information

SHOWCASE NETWORK RAIL

SHOWCASE NETWORK RAIL SHOWCASE NETWORK RAIL Cannon Street, London The Shard, London Bridge, SE1 Kwik-Kilk is an approved supplier of modular hoarding systems for Network Rail. We have a versatile range of systems and fixings

More information

CORPORATE PROCUREMENT UNIT SITE & SECURITY PROCEDURES COLINDALE, MICAWBER STREET & WOOLWICH VERSION 9 APR09

CORPORATE PROCUREMENT UNIT SITE & SECURITY PROCEDURES COLINDALE, MICAWBER STREET & WOOLWICH VERSION 9 APR09 SITE PROCEDURES LONDON OTHER SITES VERSION 9 PAGE 1 OF 13 CONTENTS PAGE...1 2. GENERAL INFORMATION 3 3. ACCESS 4 4. SECURITY 4 5. VEHICLE PARKING 6 6. DELIVERY, UNLOADING AND STORAGE 6 7. HOURS OF WORK

More information

CORPORATE PROCUREMENT UNIT SITE & SECURITY PROCEDURES BOSTON SPA VERSION 7 APR09

CORPORATE PROCUREMENT UNIT SITE & SECURITY PROCEDURES BOSTON SPA VERSION 7 APR09 SITE PROCEDURES BSPA VERSION 7 PAGE 1 OF 12 CONTENTS PAGE 2. GENERAL INFORMATION 3 3. ACCESS 3 4. SECURITY 4 5. VEHICLE PARKING 5 6. PERMITS TO WORK 5 7. DELIVERY, UNLOADING AND STORAGE 5 8. HOURS OF WORK

More information

We re building for your future KEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM TRAFALGAR PLACE HELPLINE ISSUE 01 SUMMER 2013

We re building for your future KEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM TRAFALGAR PLACE HELPLINE ISSUE 01 SUMMER 2013 We re building for your future KEEPING YOU INFORMED ON ALL CONSTRUCTION NEWS FROM TRAFALGAR PLACE HELPLINE 020 3697 6220 elephantandcastle.org.uk ISSUE 01 SUMMER 2013 Investing in Elephant & Castle ISSUE

More information

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver

More information

MAINE MEDICAL CENTER

MAINE MEDICAL CENTER MAINE MEDICAL CENTER Construction Projects at the East Tower, Visitor Garage, Central Utility Plant Construction Management Plan December 15, 2017 Prepared for: Portland Department of Planning & Urban

More information

RE: Jackson Row - truck route

RE: Jackson Row - truck route Will Rasbach From: Sent: To: Cc: Subject: Mayor Pat Patterson Tuesday, January 13, 2015 3:46 PM Will Rasbach; Bart Robinson; Randy Barber (rbarber@oxfordms.net); jowens@oxfordpolice.net

More information

106 TALL BUILDINGS: A STRATEGIC DESIGN GUIDE

106 TALL BUILDINGS: A STRATEGIC DESIGN GUIDE 106 TALL BUILDINGS: A STRATEGIC DESIGN GUIDE KEY TECHNICAL COMPONENTS 107 cost: The cost and scarcity of developable land, the permitted footprint, building bulk, quality of specification, and the time

More information

Trip and slip Hazard policy

Trip and slip Hazard policy Trip and slip Hazard policy Issue No.: 01 Issue Date: February 2012 Version: 05 Reason for version change: Review July 2015 by AR Authorised by: WM Date: 22 nd July 2016 Document Number: STAN0022012 Originator:

More information

Physical Security Assessment Form

Physical Security Assessment Form Physical Security Assessment Form Security Assessment Developed in Partnership with: P a g e 2 Introduction Thank you for taking the time to look at your organization s security. It is a critical component

More information

Box Clever Consulting. Executive Summary Project Report. July Strand Plaza. Liverpool. for. Primesite Developments

Box Clever Consulting. Executive Summary Project Report. July Strand Plaza. Liverpool. for. Primesite Developments Box Clever Consulting Executive Summary Project Report July 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 05/08/17 Strand Plaza - Liverpool Status Report @ End of

More information

Centre Buildings Redevelopment Explaining the impact on LSE staff and students

Centre Buildings Redevelopment Explaining the impact on LSE staff and students Explaining the impact on LSE staff and students Creating a new LSE landmark building & public square Improving facilities for staff and students Contents: Background & Programme Construction Traffic and

More information

ACT Scaffolding Services LTD METHOD STATEMENT Scaffold erection

ACT Scaffolding Services LTD METHOD STATEMENT Scaffold erection Address: 20 Bole Close, Wombwell, Barnsley, South Yorkshire. S73 8AZ Tel: 07883 780704 Email: enquiries@actscaffold.co.uk Web: www.actscaffold.co.uk Project/Contract Boiler Scaffolding Client Example Comp

More information

A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V ) PROJECT:

A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V ) PROJECT: A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V.2 10.5.17) PROJECT: Oakdale Primary School, Peterborough Extension, Refurbishments and Associated Works.

More information

FAST FIT TEMPORARY HOARDING SY COMBINED BASE & PANEL SYSTEM FAST FIT TEMPORARY HOARDING SY

FAST FIT TEMPORARY HOARDING SY COMBINED BASE & PANEL SYSTEM FAST FIT TEMPORARY HOARDING SY SHOWCASE BIRMINGHAM NEW STREET STATION FAST FIT TEMPORARY HOARDING SY Ultrahord on a mainline platform in 2009 A footbridge is removed. Hoardings on bottom left. FAST FIT TEMPORARY HOARDING SY ultrahord

More information

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018 SITE SAFETY RULES - SILVERSTONE CLASSIC 2018 The following is an outline of the Safe Working Requirements for all Companies, staff and any other persons for this event. Please note that the terms Company

More information

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan Possible solution to past CM exam question Question 2 July 2015 New city centre office block by Rajavel Inbarajan The information provided should be seen as an interpretation of the brief and a possible

More information

BsecB. The ultimate perimeter security solution

BsecB. The ultimate perimeter security solution INTERNATIONAL SAFETY SOLUTIONS BsecB The ultimate perimeter security solution The threat from terrorist or criminal attack remains both serious and real Today s most significant threat derives from international

More information

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017 Premier Inn, Wilson Street, Middlesbrough, TS1 1AE Site progress report February 2017 Site set up Currently 4 weeks in to the build the site has been cleared and hoardings have been erected. Welfare cabins

More information

Case examples for the construction of complex basement

Case examples for the construction of complex basement Case examples for the construction of complex basement Project Case 1 Urban Renewal Authority s Redevelopment project at Wanchai Road, H K Site area 7500 m 2 (divided into 2 sites by the Wanchai Road)

More information

Local Authority Borough: Caerphilly County Borough Council. Contact: Huw Morgan

Local Authority Borough: Caerphilly County Borough Council. Contact: Huw Morgan Case Study Theme: Our Environment Local Authority Borough: Caerphilly County Borough Council Good Practice: Blackwood Transport Interchange Contact: Huw Morgan - 01495 235089 - morganash@caerphilly.gov.uk

More information

Issue 7 24 February Job number

Issue 7 24 February Job number 11/39341499_1 1 Cuadrilla Bowland Limited Temporary Shale Gas Exploration at Preston New Road LCC Application Ref: LCC/2014/0096 Issue 7 24 February 2017 This report takes into account the particular instructions

More information

Existing Project Conditions. General Conditions Estimate. Michael Vergari Construction Management Advisor: Dr. Riley

Existing Project Conditions. General Conditions Estimate. Michael Vergari Construction Management Advisor: Dr. Riley Existing Project Conditions General Conditions Estimate The Center for Health Research and Rural Advocacy is constructed under the supervision of the Geisinger Facilities Division. The project team develops

More information

The Merits of Structural Steelwork

The Merits of Structural Steelwork B309 12pp Final 11/12/02 11:14 AM The Merits of Structural Steelwork Page 2 The Purpose of this Reference Manual The guide, which has been prepared by BCSA, should be used in discussions with clients and

More information

District of North Vancouver Construction Traffic Management Plan Guidelines

District of North Vancouver Construction Traffic Management Plan Guidelines District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction

More information

2 Ensure there are arrangements in place for managing and organising the project

2 Ensure there are arrangements in place for managing and organising the project A principal contractor is required to plan, manage and coordinate the construction work. Appoint them as early as possible so they are involved in discussions with the principal designer about the work.

More information

Vertical Transportation Planning Retail/Mixed-Use

Vertical Transportation Planning Retail/Mixed-Use Fortune Consultants LTD Elevator Consulting Vertical Transportation Planning Retail/Mixed-Use This paper is to provide design guidance for the initial planning of vertical transportation in either a standalone

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

Configuration. User Guide. Version: Copyright 2017 Computer and Design Services Ltd GLOBAL CONSTRUCTION SOFTWARE AND SERVICES

Configuration. User Guide. Version: Copyright 2017 Computer and Design Services Ltd GLOBAL CONSTRUCTION SOFTWARE AND SERVICES Configuration User Guide Version: 2018.0 Copyright 2017 Computer and Design Services Ltd GLOBAL CONSTRUCTION SOFTWARE AND SERVICES Contents Introduction... 1 Create a new project... 2 Open the configuration...

More information

SCHEDULE 1 CONDITIONS OF USE RELATING TO FALKIRK BUS STATION (THE BUS STATION )

SCHEDULE 1 CONDITIONS OF USE RELATING TO FALKIRK BUS STATION (THE BUS STATION ) SCHEDULE 1 CONDITIONS OF USE RELATING TO FALKIRK BUS STATION (THE BUS STATION ) These Conditions of Use set out the terms on which all operators (including First) ( Operator(s) ) who use, or wish to use

More information

RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL

RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL 1st Edition January 2007 RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL GUIDANCE ON COMPLYING WITH THE OCCUPATIONAL HEALTH AND SAFETY (ASBESTOS) REGULATIONS 2003 The information presented in Recycling

More information

6.0 CONSTRUCTION PROGRAMME

6.0 CONSTRUCTION PROGRAMME 6.0 CONSTRUCTION PROGRAMME Introduction 6.1 This chapter of the ES describes the expected construction works programme and the key activities that will be undertaken. Detailed consideration of potential

More information

Corporate Safety Procedure Grid Mesh, Handrail and Flooring Removal. Table of Contents

Corporate Safety Procedure Grid Mesh, Handrail and Flooring Removal. Table of Contents Table of Contents 1. Purpose... 2 2. Scope... 2 3. Roles and Responsibilities... 2 3.1 Manager/Supervisor... 2 3.2 Workers... 2 3.3 Technical Specialist/Engineer... 2 4. Definitions... 2 5. Procedure...

More information

www.fastformsystems.com info@fastformsystems.comm South Tel: 00 44 (0) 207 1481274 North Tel: 00 44 (0) 8456 171152 Fast-Form The Complete Formwork system Safer / Faster / Greener / Cheaper One system,

More information

Hastings District Council. Whakatu Arterial Link Traffic Management Plan

Hastings District Council. Whakatu Arterial Link Traffic Management Plan Hastings District Council Whakatu Arterial Link Traffic Management Plan June 2014 Table of contents 1. Introduction... 2 1.1 Purpose of this report... 2 1.2 The Whakatu Arterial Link... 2 2. Traffic Management...

More information

VIENNA JUNE 2017

VIENNA JUNE 2017 EXHIBITION STANDS SPACE ONLY STANDS The space contracted refers solely to the floor and its perimeter. Therefore, exhibitors must decorate this surface area in accordance with their needs. The Organiser

More information

ABN: LICENCE: AD PHONE: (02) FAX: (02)

ABN: LICENCE: AD PHONE: (02) FAX: (02) ABN:64 146 561 453 LICENCE: AD 211 896 PHONE: (02) 8021 1784 FAX: (02) 9517 1555 EMAIL: info@perfectcontracting.com.au www.perfectcontracting.com.au LEADERS OF THE CONSTRUCTION AND DEMOLITION Perfect Contracting

More information

DIEMERSFONTEIN WINE & COUNTRY ESTATE BUILDING CONTRACTORS CODE OF CONDUCT

DIEMERSFONTEIN WINE & COUNTRY ESTATE BUILDING CONTRACTORS CODE OF CONDUCT DIEMERSFONTEIN WINE & COUNTRY ESTATE BUILDING CONTRACTORS CODE OF CONDUCT 1. CODE OF CONDUCT AGREEMENT The building contractor is a builder/contractor ( the contractor ) appointed by the owner ( the employer

More information

Assessing the costs and benefits of reducing waste in construction

Assessing the costs and benefits of reducing waste in construction Assessing the costs and benefits of reducing waste in 20 new build timber-framed houses Value Percentage of 1.36m cost Cost saving potential 21,470 1.58% Additional costs to achieve these savings TOTAL

More information

Innovative waste management approach achieves exemplary recovery rates

Innovative waste management approach achieves exemplary recovery rates : University of the West of Scotland, Ayr Campus Innovative waste management approach achieves exemplary Key facts The new campus was designed to achieve a BREEAM rating of Excellent. 96% of the 1,200

More information

BNSF RAILWAY COMPANY

BNSF RAILWAY COMPANY BNSF RAILWAY COMPANY GUIDELINES FOR PREPARATION OF BRIDGE DEMOLITION & REMOVAL PLAN OVER THE BNSF RAILWAY OFFICE OF DIRECTOR BRIDGE ENGINEERING KANSAS CITY, KANSAS August 21, 2008 INDEX ITEM PAGE I. General

More information

SCAFFOLDS AND SCAFFOLDING WORK

SCAFFOLDS AND SCAFFOLDING WORK SCAFFOLDS AND SCAFFOLDING WORK Code of Practice TABLE OF CONTENTS FOREWORD... 4 SCOPE AND APPLICATION... 4 1. INTRODUCTION... 5 1.1 What is a scaffold and scaffolding work?... 5 1.2 Who has health and

More information

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

D7: TUNNEL CONSTRUCTION AND METHODOLOGY HIGH SPEED TWO INFORMATION PAPER D7: TUNNEL CONSTRUCTION AND METHODOLOGY This paper outlines the proposed tunnelling methodology. It will be of particular interest to those potentially affected by the

More information

RISK ASSESSMENT As exhibitions and events are deemed as hazardous environments, it is a legal requirement that all exhibitors and contractors

RISK ASSESSMENT As exhibitions and events are deemed as hazardous environments, it is a legal requirement that all exhibitors and contractors RISK ASSESSMENT As exhibitions and events are deemed as hazardous environments, it is a legal requirement that all exhibitors and contractors undertake a suitable and sufficient Risk Assessment prior to

More information

1107 E. Madison Street Student Housing Project. Monthly Update May 12, 2017

1107 E. Madison Street Student Housing Project. Monthly Update May 12, 2017 1107 E. Madison Street Student Housing Project Monthly Update May 12, 2017 Anticipated Completion: Fall 2018 About the Project: This newly constructed building will be ten stories providing eight floors

More information

Government Gazette Staatskoerant

Government Gazette Staatskoerant Government Gazette Staatskoerant REPUBLIC OF SOUTH AFRICA REPUBLIEK VAN SUID AFRIKA Regulation Gazette Vol. 629 No. 10177 10 November November Regulasiekoerant 2017 No. 41237 PART 1 OF 3 N.B. The Government

More information

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department: Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,

More information

Roma Park. Development Framework Design Guidelines. Version 3: March 2014

Roma Park. Development Framework Design Guidelines. Version 3: March 2014 Roma Park Development Framework Design Guidelines Version 3: March 2014 Roma Park development will comprise of a number of phases in a mixed use development. As a planned development offering a high level

More information

ELVORON LU/LA ELEVATOR

ELVORON LU/LA ELEVATOR Creating An Accessible World ELVORON LU/LA ELEVATOR DESIGN AND PLANNING GUIDE www.garaventalift.com Please note: Dimensions provided in this Guide are for REFERENCE ONLY and should not be used for site

More information

Jobsite Layout Considerations

Jobsite Layout Considerations 1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration

More information

Standards of Performance. Mariane Ewbank Chairperson Standards and Customs WG

Standards of Performance. Mariane Ewbank Chairperson Standards and Customs WG Standards of Performance Mariane Ewbank Chairperson Standards and Customs WG Please hold for instructions to open packs 1 and 2 Can we consider this an official doc???? Second version And this invoice?

More information

store for Buckshaw Village and Euxton

store for Buckshaw Village and Euxton A new Aldi food store for Buckshaw Village Aldi, the premium discount food retailer, with local developer Primrose Holdings, is proposing to develop land off Ordnance Road,. The site is currently vacant

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

9.3.9 Industry uses code

9.3.9 Industry uses code 9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of

More information

INDUSTRIAL GUARDRAIL SYSTEMS

INDUSTRIAL GUARDRAIL SYSTEMS INDUSTRIAL GUARDRAIL SYSTEMS STRONGEST GUARDRAIL ON THE MARKET MANUFACTURED IN THE U.S.A. BEST PRICES MOST VARIETIES HEAVY DUTY ONE-LINE OR TWO-LINE Posts: 4 Sched 80 pipe Rail: 6 Sched 40 pipe Sleeved

More information

Smarter. Safer. Leaner.

Smarter. Safer. Leaner. Smarter. Safer. Leaner. Fast Installation and Removal Decrease Leading Edge Exposure by 87% OSHA Compliant Versatile and Reusable Use Perimeter Protection Posts During Construction: At Building Perimeter

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction) Civil Engineering Services Highways Maintenance (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

CONTINENTAL FERRY PORT SITE INDUCTION

CONTINENTAL FERRY PORT SITE INDUCTION CONTINENTAL FERRY PORT SITE INDUCTION Port activities As landlord of the Commercial Port, the Port Authority must be informed of all works conducted on these premises The Authority is committed to the

More information

SHELVING, RACKING AND STORAGE CONCEPTS

SHELVING, RACKING AND STORAGE CONCEPTS SHELVING, RACKING AND STORAGE CONCEPTS 1 JULY 2017 FREE GUIDE ABOUT SUPERMARKET SHELVING Supermarket Shelving has been in the second hand shelving and racking Industry for over 30 years and we are able

More information

Construction Environmental Management Plan

Construction Environmental Management Plan Construction Environmental Management Plan Revision 10 September 2015. Contents 1 Introduction... 4 1.2 The Triangle Site... 4 1.3 Olive Morris House... 5 1.4 Stakeholders... 5 1.5 General Provisions...

More information

PRESCRIPTIVE COMPLIANCE METHOD

PRESCRIPTIVE COMPLIANCE METHOD CHAPTER PRESCRIPTIVE COMPLIANCE METHOD 3 SECTION 301 GENERAL 301.2 Building materials. Building materials shall comply with the requirements of this section. 301.2.1 Existing materials. Materials already

More information

Detailed information on the Proposed Wilberforce House Development

Detailed information on the Proposed Wilberforce House Development October 2017 Detailed information on the Proposed Wilberforce House Development This leaflet is to inform parents, neighbours and other interested parties about building work proposed at Wilberforce House

More information

Construction Site Waste Management Process.

Construction Site Waste Management Process. Construction Site Waste Management Process. EMS DOCUMENT TYPE: ENVIRONMENTAL ASPECT: PURPOSE: Operational Control Document Waste Management To ensure we manage our waste in compliance with legislation

More information

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER EDUCATION 3835 East Thousand Oaks Boulevard, #365 Westlake Village, California 91362 Telephone: (805) 494-0444 Facsimile: (805) 494-0441

More information

HFM Asset Management Contractor Induction Queens Riverside Apartments

HFM Asset Management Contractor Induction Queens Riverside Apartments HFM Asset Management Contractor Induction Queens Riverside Apartments Contents Purpose About HFM Asset Management HFM Asset Management s Responsibilities Contractors Responsibilities Commencing Work Working

More information

(1) Site Suitability PURPOSE

(1) Site Suitability PURPOSE 3.3 Code for Development and Use of Rural Service Industries PURPOSE This purpose of this code is to encourage the development and use of suitable rural service industries on rural, industrial or suitable

More information

concrete Precast car park The Avenue MSCP, Bracknell Sustainability by the sea Colwyn Bay seafront Clean water Treating hydro-demolition waste

concrete Precast car park The Avenue MSCP, Bracknell Sustainability by the sea Colwyn Bay seafront Clean water Treating hydro-demolition waste concrete THE MAGAZINE OF THE CONCRETE SOCIETY Volume 51 November 2017 Issue09 Visit: www.concrete.org.uk Precast car park The Avenue MSCP, Bracknell Clean water Treating hydro-demolition waste Sustainability

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction) Civil Engineering Services Construction Operations (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 4 Qualification structure 5 Centre requirements

More information

CORMAC. Construction Traffic Management Plan. Cornwall Energy Recovery Centre Restowrack Farm St Dennis Cornwall 1/35 HM: 9/25/2011

CORMAC. Construction Traffic Management Plan. Cornwall Energy Recovery Centre Restowrack Farm St Dennis Cornwall 1/35 HM: 9/25/2011 CORMAC Construction Traffic Management Plan Cornwall Energy Recovery Centre Restowrack Farm St Dennis Cornwall Revision Revision Date Originator Checked Draft 0 May 11 AD AD Draft 01 June 11 HM AD Draft

More information

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

SPACE TYPE: OUTSIDE PARKING (STRUCTURE) SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

ELEVATORS, LULAS AND PLATFORM LIFTS

ELEVATORS, LULAS AND PLATFORM LIFTS ELEVATORS City of Los Angeles Plan Check No: 1. Elevators provided for passengers shall comply with 11B-407 Elevators. Where multiple elevators are provided, each elevator shall comply with 11B-407 Elevators;

More information

This paper compares a number of traditional load in/out techniques against a single LoadFast advanced rolling platform and Beam Hoist

This paper compares a number of traditional load in/out techniques against a single LoadFast advanced rolling platform and Beam Hoist Cost Comparison of Load In/Out Techniques Summary This paper compares a number of traditional load in/out techniques against a single LoadFast advanced rolling platform and Beam Hoist It considers the

More information

D2: SELECTION OF THE LOCATION OF CONSTRUCTION COMPOUNDS

D2: SELECTION OF THE LOCATION OF CONSTRUCTION COMPOUNDS HIGH SPEED TWO INFORMATION PAPER D2: SELECTION OF THE LOCATION OF CONSTRUCTION COMPOUNDS This paper outlines the range of construction compounds and the criteria used to select them for Phase One of HS2.

More information

Topic: Site Formation

Topic: Site Formation Topic: Site Formation Presentation prepared by Raymond Wong January 2010 Purpose of site formation is for: Forming of land by cutting & leveling of an uneven, sloppy or congested area. Accommodate building/s

More information

Fire safety issues with balconies

Fire safety issues with balconies Fire safety issues with balconies By Ciara Holland, Martin Shipp and David Crowder of BRE Global Introduction BRE Global carries out fire investigation activities on behalf of the Department for Communities

More information

Newton Group CANADACAR SYSTEM. Basic Construction of the CANADACAR System. CANADACAR Module Format

Newton Group CANADACAR SYSTEM. Basic Construction of the CANADACAR System. CANADACAR Module Format Basic Construction of the CANADACAR System The CANADACAR System is a prefabricated, engineered and constructed freestanding parking garage structure that utilizes superior technology combining pre-cast

More information

Contractor Induction Manual

Contractor Induction Manual Contractor Induction Manual Contractor Management September, 2014 Authored by: OHS Services Version 1.1 Contractor Induction Manual Table of Contents 1. INTRODUCTION... 2 2. CONTRACTOR MANAGEMENT INFORMATION...

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction) Civil Engineering Services Construction Operations (Construction) Qualification Specification ProQual 2014 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile

More information

Freight Elevator Series GFM-T

Freight Elevator Series GFM-T Freight Elevator Series GFM-T Mitsubishi Freight Elevators Can Improve our Goods-Handling Ability Elevator Selection 1. Rated capacity and car size What is the maximum weight or size of goods to be transported

More information

Box Clever Consulting. Executive Summary Project Report. June Strand Plaza. Liverpool. for. Primesite Developments

Box Clever Consulting. Executive Summary Project Report. June Strand Plaza. Liverpool. for. Primesite Developments Box Clever Consulting Executive Summary Project Report June 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 06/07/17 Strand Plaza - Liverpool Status Report @ End of

More information

MACH 2018 STAND REGULATIONS IMPORTANT INFORMATION

MACH 2018 STAND REGULATIONS IMPORTANT INFORMATION Organised By: The Manufacturing Technologies Association 62 Bayswater Road London W2 3PS Tel: 020 7298 6400 MACH 2018 STAND REGULATIONS IMPORTANT INFORMATION IT IS IMPORTANT THAT ALL STAND CONTRACTORS

More information

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON.

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON. REQUEST FOR TENDER - SERVICES 1. PURPOSE AND SCOPE This specification is intended to govern the supply of all labour, materials and equipment for the dismantling, demolition of a single dwelling on the

More information

Introduction. Disclaimer. Table of contents

Introduction. Disclaimer. Table of contents Updated July 18, 2012 Introduction The Cambridge Elevating Limited-Use / Limited-Application Elevator is designed to service schools, libraries, low rise, low occupancy commercial buildings, churches and

More information

Your Checklist Guide for Effortless Crane Hire

Your Checklist Guide for Effortless Crane Hire Your Checklist Guide for Effortless Crane Hire (Plus Frequently Asked Questions) There are 6 key Processes that can make your Crane Hire experience effortless if we work together to manage them efficiently:

More information

Pre- Construction Information. For. Internal Alteration and Associated Works. London College of Communication Elephant & Castle London SE1 6SB

Pre- Construction Information. For. Internal Alteration and Associated Works. London College of Communication Elephant & Castle London SE1 6SB Pre- Construction Information For Internal Alteration and Associated Works At London College of Communication Elephant & Castle London SE1 6SB May 2014 Prepared By GEP Safety Consultants Ltd First Floor,

More information

BHC-P-03.1 Training, Competence and Induction

BHC-P-03.1 Training, Competence and Induction BHC-P-03.1 Training, Competence and Induction Contents 1.0 Purpose 2.0 Scope 3.0 Definitions 4.0 Main requirements 5.0 Guidance documents and references 6.0 Appendices Revision register Date Version Description

More information

Company s Name: GHI Warehouse Date of Risk Assessment:

Company s Name: GHI Warehouse Date of Risk Assessment: Company s Name: GHI Warehouse Date of Risk Assessment: 10-01-06 What are the hazards? Falls from height Who might be harmed and how? Staff could suffer severe or even fatal injuries if they fell whilst

More information

Whittier Bridge/I-95 Improvement Project. Public Information Meeting

Whittier Bridge/I-95 Improvement Project. Public Information Meeting Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project

More information

Access Chambers Systems

Access Chambers Systems 2011 Access Chambers Systems S y s t e m s Pioneers in PE Pipe Technologies Index QuadBox Access Chamber p.4 QuadBox Fittings p.6 RadBox Access Chamber p.8 RadBox Fittings p.10 Specialist Chambers p.11

More information

The Ton-Tel Weighbridge

The Ton-Tel Weighbridge The Ton-Tel Weighbridge Plug-and-Weigh Technology Built to last in a tough environment Proven reliability, lower total cost of ownership. Digital Load Cell weight sensors sealed to IP68. Plug-and-Weigh

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

Property Risk Assessment Report

Property Risk Assessment Report Esplanade Apartments Devonport Auckland New Zealand Introduction Health & Safety New Zealand Ltd were commissioned to undertake a Property Risk Assessment (PRA) of the subject site. The purpose of the

More information

Xerox Supplier Security Requirements

Xerox Supplier Security Requirements Xerox Supplier Security Requirements Suppliers who are involved in the manufacture, storage, and transportation of Xerox products ( Suppliers ) for Xerox Corporation and / or its subsidiaries under Xerox

More information

2007 Title 24 Accessibility Code Updates and ADA Issues

2007 Title 24 Accessibility Code Updates and ADA Issues 2007 Title 24 Accessibility Code Updates and ADA Issues C.A.S.H. Workshop June 2007 Introduction Update on ADA Certification of the California Building Code Overview of significant changes to accessibility

More information

Section 1 OBC FADS /13 Access to Parking Areas

Section 1 OBC FADS /13 Access to Parking Areas Section 1 OBC 3.8.2.2 4.3.12/13 Access to Parking Areas A barrier-free path of travel is provided from: a) the entrance to the exterior parking area b) at least one parking level where a passenger elevator

More information

ERINVALE COUNTRY ESTATE HOME OWNERS' ASSOCIATION

ERINVALE COUNTRY ESTATE HOME OWNERS' ASSOCIATION ERINVALE COUNTRY ESTATE HOME OWNERS' ASSOCIATION REGULATIONS GOVERNING BUILDING CONTRACTOR ACTIVITY and CODE OF CONDUCT (ALTERATIONS) Effective 1 April 2002 THIS DOCUMENT MUST FORM PART OF ANY BUILDING

More information

Transit Service Guidelines

Transit Service Guidelines G R E AT E R VA N CO U V E R T R A N S P O RTAT I O N A U T H O R I T Y Transit Service Guidelines PUBLIC SUMMARY REPORT JUNE 2004 Greater Vancouver Transportation Authority TRANSIT SERVICE GUIDELINES

More information