Highway 15 Project Hutchinson, MN

Size: px
Start display at page:

Download "Highway 15 Project Hutchinson, MN"

Transcription

1 Highway 15 Project Hutchinson, MN Adjacent Properties and Businesses Meeting Hutchinson Area Chamber of Commerce 1

2 Agenda Topic 1) Introduce the project scope 2) Project goals and benefits 3) Project timeline 4) Discuss project elements and process 2

3 Project Location Full Reconstruction of Highway 15 and underground utilities between 2nd Ave. N and 5th Ave. S Pavement Resurfacing between 5th Ave. S and just south of Denver Ave. 3

4 Summary of Work Complete reconstruction of Main Street/Highway 15 through downtown Pavement resurfacing of Highway 15 between 5th Ave S and just south of Denver Ave Update sidewalk and pedestrian crossings along project area to meet Americans with Disabilities Act (ADA) standards The City of Hutchinson will also be replacing, updating, and modernizing underground utilities 4

5 Benefits Smoother road surface Modernize sanitary sewer, water main and storm sewer Help ensure city and state infrastructure serves their purpose for many years The City of Hutchinson views this project as an opportunity to enhance downtown and improve livability in the central district 5

6 Downtown Typical Sections 6

7 Hwy 15/Main St. Reconstruction Detour Construction and detours begin in Preliminary detour route utilizes Highway 22 to the east, between Highway 7 and Airport Road (County Road 115). 7

8 Project Timeline 8

9 Construction Process & Timeline Construction begins in Spring 2020 Project will take an entire construction season, with final work occurring in 2021 Construction will be from building face to building face All street, sidewalk & utilities will be replaced Multiple excavations will be required Work will be phased to limit time of disturbance Close coordination with the Chamber of Commerce and others will be required Consider improvements to alternate accesses 9

10 ADA Improvements (Americans with Disabilities Act) Extensive survey, design and construction efforts are required Close coordination with building owners will be required Opportunity for owners to make improvements Chamber of Commerce helping to facilitate 10

11 Building Inspections Project includes inspection of building basements in order to: Identify any potential structural concerns related to the construction Identify potential intrusions into the construction area (old coal chutes, window wells, vents, etc.) Identify sanitary sewer and water service locations and related issues/improvements SEH and City staff to complete inspections in September 2017 Notifications and requests for access pending 11

12 Project Elements Landscaping items to be reviewed/discussed Will use Imagine Hutchinson document and wayfinding study as guides during project design Will coordinate efforts with local groups 12

13 Process / Next Steps Public Involvement and Outreach Open houses, public meetings and outreach Project newsletters Stakeholder meetings Informal sessions at Chamber of Commerce Design process Preliminary design, traffic and environmental studies, outreach and other design efforts in 2017 Final, detailed design starting in 2018 Project letting proposed for November

14 Questions? 14

15 Thank you! 15

MnDOT Contract Exhibit A - Scope of Services

MnDOT Contract Exhibit A - Scope of Services Project Development for Pavement Rehabilitation and Pedestrian Access -Improvements on TH 22 in Glencoe, MN from US 212 to Cedar Ave. (R.P. 106+00.650 to 108+00.141) -Improvements on TH 71 in Olivia, MN

More information

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP &

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP & TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP 4910-29 & 0504-14 Contract No. 1002252 Project Overview is in need of professional and technical assistance to provide detail design for State

More information

Public Open House. Proposed Liberty Village Natural Gas Pipeline Project. Please sign-in at the registration table upon arrival

Public Open House. Proposed Liberty Village Natural Gas Pipeline Project. Please sign-in at the registration table upon arrival Proposed Liberty Village Natural Gas Pipeline Project Public Open House Please sign-in at the registration table upon arrival Feel free to approach any team member to discuss the project Share your thoughts

More information

2017 Resurfacing Project Central Business District Informational Meeting June 13, 2017

2017 Resurfacing Project Central Business District Informational Meeting June 13, 2017 2017 Resurfacing Project Central Business District Informational Meeting June 13, 2017 2017 CBD Improvements Agenda Meeting Agenda Introduction Scope of Improvements Time frames for improvements May vary

More information

Project Need and Evaluation

Project Need and Evaluation City of Brooklyn Center 2011 Palmer Lake East Street and Utility Reconstruction Project Public Hearings February 14, 2011 Public Improvement Hearing: Special Assessments Local public improvements to the

More information

study for 2018 include:

study for 2018 include: MEMORANDUM TO: Mayor and City Council gk FROM: Shawn Sanders irector of Public Works DATE: March 15, 2018 RE: Feasibility Study for the 2018 Street Improvement Project Project No. 2018-02 INTRODUCTION

More information

RPM Phase One: Lawrence to Bryn Mawr Modernization

RPM Phase One: Lawrence to Bryn Mawr Modernization RPM Phase One: Lawrence to Bryn Mawr Modernization Public Update April 2018 Chicago Transit Authority RPM program history 2009-2010 2011 2012-2013 2014-2015 2016-2017 2018 2019-2025 Vision Study Environmental

More information

Commentary on the Model Transition Plan. This is general information that outlines why the agency has developed a transition plan.

Commentary on the Model Transition Plan. This is general information that outlines why the agency has developed a transition plan. Commentary on the Model Transition Plan Introduction This is general information that outlines why the agency has developed a transition plan. Self Evaluation Overview Many policies, practices and programs

More information

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016 Cleveland Opportunity Corridor Project Section 3 Subcontractor Informational Meeting August 12, 2016 Agenda Welcome and Opening Remarks Project Overview Prequalifications & Work Types Procurement Overview

More information

2017 Transportation and Storm Drainage Projects

2017 Transportation and Storm Drainage Projects 2017 Transportation and Storm Drainage Projects Request for Qualifications Pre-Submittal Meeting: Welcome and Introductions Sign-in sheet Meeting Agenda Provide overview of solicitation and selection process

More information

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016 Rehabilitation of West Main Street Culvert and Shirley Street Bridge Town of Ayer November 22, 2016 Agenda Outline Introductions Project Goals and Objectives Existing Conditions Review Design Considerations

More information

City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House. March 27, 2018

City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House. March 27, 2018 City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House March 27, 2018 Agenda 1. Construction Team 2. Anticipated Construction Staging 3. Anticipated Construction Schedule

More information

ENGINEERING DEPARTMENT. Provide engineering and public improvements in the most economical manner.

ENGINEERING DEPARTMENT. Provide engineering and public improvements in the most economical manner. ENGINEERING DEPARTMENT MISSION STATEMENT: Provide engineering and public improvements in the most economical manner. The Engineering Department performs the following services to maintain and improve the

More information

SPECIFICATIONS. There are 18 Infrastructure Stimulus Funding (ISF) projects for 2010 (refer to Attachment A).

SPECIFICATIONS. There are 18 Infrastructure Stimulus Funding (ISF) projects for 2010 (refer to Attachment A). SPECIFICATIONS Project Scope: The City of Guelph requires the following for the Infrastructure projects being done within the City. Phase 1 for the review, analysis, design of detour routes and general

More information

Capital District Transportation Committee November 6, Unit Costs for Non-State Highway Reconstructions with Federal Funds

Capital District Transportation Committee November 6, Unit Costs for Non-State Highway Reconstructions with Federal Funds Capital District Transportation Committee November 6, 2018 Unit Costs for Non-State Highway Reconstructions with Federal Funds CDTC s unit costs for non-state reconstruction projects were last updated

More information

2008 Street and Utility Improvement Project West Golden Lake Road. Public Informational Meeting January 3, 2008

2008 Street and Utility Improvement Project West Golden Lake Road. Public Informational Meeting January 3, 2008 2008 Street and Utility Improvement Project West Golden Lake Road C P Public Informational Meeting January 3, 2008 Presentation Summary Project Location Existing Conditions Proposed Improvements Project

More information

Atlantic Street Bridge Project CTDOT Project Nos (Phase 1) & (Phase 2)

Atlantic Street Bridge Project CTDOT Project Nos (Phase 1) & (Phase 2) Atlantic Street Bridge Project CTDOT Project Nos. 135-326 (Phase 1) & 135-301 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement City of Stamford www.atlanticstreetbridge.com

More information

SECTION MAINTENANCE OF EXISTING CONDITIONS

SECTION MAINTENANCE OF EXISTING CONDITIONS SECTION 02 01 00 MAINTENANCE OF EXISTING CONDITIONS PART 1 GENERAL 1.1 GENERAL A. The CONTRACTOR shall protect all existing utilities and improvements not designated for removal and shall restore damaged

More information

Comprehensive Transportation Study for Glencoe, MN

Comprehensive Transportation Study for Glencoe, MN Comprehensive Transportation Study for Glencoe, MN Introduction and Project Information Introduction There have been a number of planning and preliminary engineering studies completed in the Glencoe area

More information

Memorandum. Corey Mathisen, MPCA

Memorandum. Corey Mathisen, MPCA Memorandum engineering planning environmental construction 701 Xenia Avenue South Suite 300 Minneapolis, MN 55416 Tel: 763-541-4800 Fax: 763-541-1700 To: CC: From: Corey Mathisen, MPCA Diane Hankee, WSB

More information

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report BRIDGE DISTRICT Phase 1 Infrastructure Improvement Project (for work completed thru November 2011) Cover Photo: Joint Utility Trench installation along Fifth Street just north of Bridge Street. Page 1

More information

Boise Community Forestry

Boise Community Forestry Boise Community Forestry 2015 Management Plan Our Living City June 25 Public Workshop Workshop Handouts Agenda Public input form Discussion session format Copies of discussion boards Vegetative Resource

More information

Florida Department of Transportation. Lane Elimination

Florida Department of Transportation. Lane Elimination Florida Department of Transportation Lane Elimination FDOT D6 Lane Elimination Review and Approval Process Developed to assure consistency in FDOT D6 s handling of the Lane Elimination Review and Approval

More information

14.0 TRANSPORTATION PLANNING RULE COMPLIANCE

14.0 TRANSPORTATION PLANNING RULE COMPLIANCE 14.0 TRANSPORTATION PLANNING RULE COMPLIANCE As stated earlier in this plan, the Oregon Department of Land Conservation and Development (DLCD), with concurrence from ODOT, adopted Transportation Planning

More information

UTILITY PERMIT INSTRUCTIONS

UTILITY PERMIT INSTRUCTIONS STEELE COUNTY HIGHWAY DEPARTMENT UTILITY PERMIT INSTRUCTIONS REGISTRATION FORM Annual requirement for any new or existing Owner or Contractor that will perform construction or maintenance work on their

More information

LAKE + FOREST CONSTRUCTION TIMELINE

LAKE + FOREST CONSTRUCTION TIMELINE LAKE + FOREST CONSTRUCTION TIMELINE Below is a construction timeline in connection with the project at Lake Street and Forest Avenue. All dates are approximate and subject to change based on weather and

More information

Curb and Gutter Replacement Project Phase I

Curb and Gutter Replacement Project Phase I Phase I Prepared for: Prepared by: Cheyenne Downtown Development Authority / Main Street 1601 Capitol Avenue Cheyenne, WY 82001 307 433 9730 BenchMark Engineers, PC 1920 Thomes Avenue, Suite 620 Cheyenne,

More information

Omaha CSO Program and the South Omaha Industrial Area Lift Station, Force Main and

Omaha CSO Program and the South Omaha Industrial Area Lift Station, Force Main and Omaha CSO Program and the South Omaha Industrial Area Lift Station, Force Main and Gravity Sewer Projects November 16, 2010 Welcome Agenda CSO Program Overview Community Enhancements Project Overview Detours

More information

Public Works Capital Projects Management. Presented by: Joseph Cordts P. E., Portfolio Manager Capital Projects Management

Public Works Capital Projects Management. Presented by: Joseph Cordts P. E., Portfolio Manager Capital Projects Management Public Works Capital Projects Management Presented by: Joseph Cordts P. E., Portfolio Manager Capital Projects Management Overview Capital Projects Management (CPM) is responsible for management of the

More information

STAFF REPORT. Kevin Rohani, P.E. Public Works Director/City Engineer. FY 2017/18 First Quarter Report on the Capital Improvement Program

STAFF REPORT. Kevin Rohani, P.E. Public Works Director/City Engineer. FY 2017/18 First Quarter Report on the Capital Improvement Program STAFF REPORT DATE: November 14, 2017 TO: Bryan Montgomery, City Manager Approved and Forwarded to the City Council FROM: SUBJECT: Kevin Rohani, P.E. Public Works Director/City Engineer FY 2017/18 First

More information

CITY OF SAFETY HARBOR ENGINEERING

CITY OF SAFETY HARBOR ENGINEERING CITY OF SAFETY HARBOR ENGINEERING The Engineering Department provides the city with technical services including design of construction and maintenance projects, review of development plans, field surveys,

More information

Construction Notice: Infrastructure Renewal on York and Talbot Streets

Construction Notice: Infrastructure Renewal on York and Talbot Streets Construction Notice: Infrastructure Renewal on York and Talbot Streets Date: March 22, 2019 To: Business owner, resident and/or property owner Project Details: The City of London in partnership with J-AAR

More information

February 27th, 2018 City of Mayville

February 27th, 2018 City of Mayville February 27th, 2018 City of Mayville Project Location and Schedule Construction work Detour Route Business Access During Construction Temporary Business Signs What WisDOT Can Do During Construction What

More information

Urban Planning and Land Use

Urban Planning and Land Use Urban Planning and Land Use 701 North 7 th Street, Room 423 Phone: (913) 573-5750 Kansas City, Kansas 66101 Fax: (913) 573-5796 Email: planninginfo@wycokck.org www.wycokck.org/planning To: From: City Planning

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

Public Meeting. US Highways 18 & 281 and SD Highway 50 From Douglas County Line to SD46 Charles Mix County

Public Meeting. US Highways 18 & 281 and SD Highway 50 From Douglas County Line to SD46 Charles Mix County Public Meeting US Highways 18 & 281 and SD Highway 50 From Douglas County Line to SD46 Charles Mix County Cary Cleland Road Design Engineering Supervisor January 17, 2017 Project Limits US18/US281 US281

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012 Meeting Agenda Phase 2 Design Update Meeting Meeting Purpose and Format Final Design Update Expo Bikeway Update

More information

Administration Building Needs Assessment

Administration Building Needs Assessment Town Hall Meeting with the Habersham County Board of Commissioners Administration Building Needs Assessment JUNE 13, 2016 Detailed Evaluation Performed in 2015 Engineering Evaluation Site/Civil Architectural

More information

Infrastructure Evaluation. Preliminary Scope and Cost Estimates

Infrastructure Evaluation. Preliminary Scope and Cost Estimates Infrastructure Evaluation Preliminary Scope and Cost Estimates January 25, 2016 Infrastructure Evaluation Existing Conditions Street Improvements Pavement Management Street Condition Inventory Underground

More information

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session

Long-Term Capital Improvement Funding Plan. March 18, 2014 City Council Study Session Long-Term Capital Improvement Funding Plan March 18, 2014 City Council Study Session Overview Long-term 10 year view to know what s planned Project Overview Focus on FY 2014-15 and FY 2015-16 Funding Plan

More information

The 2007 Comprehensive Plan

The 2007 Comprehensive Plan The 2007 Comprehensive Plan for Lexington - Fayette County, Kentucky Public Participation Public Participation Public Input 20 Eagle Creek Public Input 2006 - Beaumont Central, Main Street MPO Public Input

More information

FY19 CAPITAL IMPROVEMENT PLAN NON-CONCURRENCY PROJECTS

FY19 CAPITAL IMPROVEMENT PLAN NON-CONCURRENCY PROJECTS FY19 CAPITAL IMPROVEMENT PLAN NON-CONCURRENCY PROJECTS This document may be reproduced upon request in an alternative format by contacting the County ADA Coordinator (772) 32-3131, the County Administration

More information

ODOT ADA Program 10/31/2017. Recent ADA outcomes. What you need to know. Settlement Agreement approved. Updated Transition Plan

ODOT ADA Program 10/31/2017. Recent ADA outcomes. What you need to know. Settlement Agreement approved. Updated Transition Plan Recent ADA outcomes What you need to know ODOT ADA Program Lisa Strader, ODOT ADA Program Manager Settlement Agreement approved Updated Transition Plan What does it mean? Public Transportation Advisory

More information

WORK SESSION ITEM City Council

WORK SESSION ITEM City Council DATE: STAFF: March 27, 2018 Noah Beals, Senior City Planner/Zoning Tom Leeson, Director, Comm Dev & Neighborhood Svrs WORK SESSION ITEM City Council SUBJECT FOR DISCUSSION Sign Code Update, Phase 2. EXECUTIVE

More information

Burton Planning Services

Burton Planning Services Burton Company Overview & Staff Background Burton 252 Electric Avenue Westerville, OH 08 6-92-228 www.burtonplanning.com Sustainable & Environmental Solutions BPS Company Overview Burton was formed in

More information

Preliminary Project Assessment

Preliminary Project Assessment DISCLAIMERS: Date: March 14, 2014 Case No.: 2014.0097U Project Address: Third Street Crossing of Islais Creek Block/Lot: Public Right-of-Way Zoning: Not Applicable Area Plan: Not Applicable Project Sponsor:

More information

COLUMBIA GATEWAY URBAN RENEWAL AGENCY CITY OF THE DALLES

COLUMBIA GATEWAY URBAN RENEWAL AGENCY CITY OF THE DALLES IMPROVING OUR COMMUNITY COLUMBIA GATEWAY URBAN RENEWAL AGENCY CITY OF THE DALLES AGENDA JOINT MEETING OF Urban Renewal Agency and Urban Renewal Advisory Committee City Hall Council Chambers 313 Court Street,

More information

Municipality of Kincardine Kincardine Business Park (KBP) Servicing Master Plan

Municipality of Kincardine Kincardine Business Park (KBP) Servicing Master Plan Municipality of Kincardine Kincardine Business Park (KBP) Servicing Master Plan Public Meeting and Open-House March 27, 2013 Agenda The Master Plan Process History of the Area Draft Servicing Strategy

More information

Research Initiatives at TxDOT Related to Utilities and Right of Way

Research Initiatives at TxDOT Related to Utilities and Right of Way Research Initiatives at TxDOT Related to Utilities and Right of Way Transportation Research Board Workshop on Transportation Law, New Orleans, LA July 17, 2012 Overview 2 TxDOT utility/right of way research

More information

Exhibit A Scope of Work. 0.0 Separation of work Types and Cost Estimate

Exhibit A Scope of Work. 0.0 Separation of work Types and Cost Estimate 0.0 Separation of work Types and Cost Estimate Exhibit A Scope of Work 0.1 Prepare scope of work and cost estimate for MnDOT efforts relating to all items numbered less than 20.0. 0.2 Prepare scope of

More information

Capital Improvement Plan (CIP) Adopted Oct. 17, 2016

Capital Improvement Plan (CIP) Adopted Oct. 17, 2016 2017-2021 Capital Improvement Plan (CIP) Adopted Oct. 17, 2016 Fiscal Year 2017 Adopted Capital Improvement Plan Table of Contents Page Description CIP Project Category Start Timeline N/A 1 Introduction

More information

Request for Qualifications: City Engineering and Architectural Services

Request for Qualifications: City Engineering and Architectural Services Request for Qualifications: City Engineering and Architectural Services The City of Clever, Missouri ( City ) is pleased to issue this Request for Qualifications ( RFQ ) for City Engineering and Architectural

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

WISCONSIN TRANSPORTATION TRIBAL CONFERENCE NOVEMBER 7, 2018 WISCONSIN DEPARTMENT OF TRANSPORTATION, P.E.

WISCONSIN TRANSPORTATION TRIBAL CONFERENCE NOVEMBER 7, 2018 WISCONSIN DEPARTMENT OF TRANSPORTATION, P.E. WISCONSIN TRANSPORTATION TRIBAL CONFERENCE NOVEMBER 7, 2018 WISCONSIN DEPARTMENT OF TRANSPORTATION, P.E. I-94 NORTH-SOUTH FREEWAY UNDER 2 YEARS I-94 NORTH-SOUTH FREEWAY OVERVIEW New mainline pavement on

More information

2018 Street Reconstruction Project Woodside/Huron Neighborhood Street Improvements. December 11, 2017 Public Improvement Hearing

2018 Street Reconstruction Project Woodside/Huron Neighborhood Street Improvements. December 11, 2017 Public Improvement Hearing 2018 Street Reconstruction Project Woodside/Huron Neighborhood Street Improvements December 11, 2017 Public Improvement Hearing Project Objectives Reconstruct Deteriorated Streets Upgrade City Underground

More information

Highway 417 Bridge Replacement

Highway 417 Bridge Replacement Highway 417 Bridge Replacement West of Maitland Avenue to East of Island Park Drive Hampton Iona Community Group June 6, 2006 7:00 p.m. to 9:00 p.m. Overview of Project Area MAITLAND CLYDE CARLING WBL

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT FY 15-20 CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT Department of Public Works Robert B. Boxer, Director PROJECT MODEL PROFESSIONAL SERVICES STUDIES FEASIBILITY CLAIMS 1- PROJECT DEFINITION 2-

More information

STAFF REPORT FOR PLANNING COMMISSION MEETING OF MARCH 28, 2018 FILE NO: SUP AGENDA ITEM: E.2

STAFF REPORT FOR PLANNING COMMISSION MEETING OF MARCH 28, 2018 FILE NO: SUP AGENDA ITEM: E.2 STAFF REPORT FOR PLANNING COMMISSION MEETING OF MARCH 28, 2018 FILE NO: SUP-18-022 AGENDA ITEM: E.2 STAFF CONTACT: Kathe Green, Assistant Planner AGENDA TITLE: For Possible Action: To consider a request

More information

WESTERN ENGINEERING CONSULTANTS, Inc LLC

WESTERN ENGINEERING CONSULTANTS, Inc LLC WESTERN ENGINEERING CONSULTANTS, Inc LLC 127 S. Denver Avenue, Ft. Lupton CO 80621 2501 Mill St. Brush, CO 80723 Ph. 303-913-7341, Fax 720-294-1330 Email: firstname.lastname@westerneci.com August 24, 2017

More information

Florida Gas Transmission Section #1 Hydrostatic Test

Florida Gas Transmission Section #1 Hydrostatic Test Florida Gas Transmission Section #1 Hydrostatic Test 14-Inch Saint Petersburg Lateral Pipeline From Compressor Station 30 (Plant City West) to Main Line Valve 26-10 (Tampa East Regulator) Hillsborough

More information

Table Related Arlington County Standards, Specification and Policies

Table Related Arlington County Standards, Specification and Policies 2.1 GENERAL 2.1.1 DESCRIPTION SITE WORK V02000 2.1 GENERAL 2.1.1 Description This standard identifies minimum requirements that shall be met for all site work in the design and construction of elements

More information

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement

More information

MEMORANDUM #4. DATE: November 4, Warrenton TSP Project Management Team. Ray Delahanty, AICP, DKS Associates Kate Petak, EIT, DKS Associates

MEMORANDUM #4. DATE: November 4, Warrenton TSP Project Management Team. Ray Delahanty, AICP, DKS Associates Kate Petak, EIT, DKS Associates MEMORANDUM #4 DATE: November 4, 2015 TO: FROM: SUBJECT: Warrenton TSP Project Management Team Ray Delahanty, AICP, DKS Associates Kate Petak, EIT, DKS Associates Warrenton Transportation System Plan Update

More information

SUCCESSFUL COMMUNITY ENGAGEMENT. Presentation by Jennifer Raitt, Town of Arlington Chapter 40B Conference, May 4, 2018

SUCCESSFUL COMMUNITY ENGAGEMENT. Presentation by Jennifer Raitt, Town of Arlington Chapter 40B Conference, May 4, 2018 SUCCESSFUL COMMUNITY ENGAGEMENT Presentation by Jennifer Raitt, Town of Arlington Chapter 40B Conference, May 4, 2018 Presentation Overview Planning Issues and Opportunities Recent Zoning Success Stories

More information

Measuring Access to Opportunity: 21st Century Transportation Performance Measurement

Measuring Access to Opportunity: 21st Century Transportation Performance Measurement Measuring Access to Opportunity: 21st Century Transportation Performance Measurement New Partners for Smart Growth Baltimore, MD January 31, 2015 Measuring Access to Opportunity: 21st Century Transportation

More information

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING FEBRUARY

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING FEBRUARY TO: FROM: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING FEBRUARY 21 2017 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR OF ENVIRONMENTAL AND ENGINEERING SERVICES & CITY ENGINEER SUBJECT: CONTRACT AWARD:

More information

City of Richmond. Report to/committee CNCL - 230

City of Richmond. Report to/committee CNCL - 230 City of Richmond Report to/committee To: From: Re: Public Works and Transportation Committee Victor Wei, P. Eng. Director, Transportation Date: June 17, 2015 File: Southwest Area Transport Plan - Structure

More information

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS Section Page 13-1 GENERAL... 13.1 13-1.01 Preservation of Property... 13.1 13-1.02 Overloading, Pavement Protection & Repair... 13.1 13-2 REMOVING EXISTING

More information

Mega Projects at WSDOT

Mega Projects at WSDOT Mega Projects at WSDOT Managing multiple projects in major urban corridors LINEA LAIRD, WSDOT ASSISTANT SECRETARY ENGINEERING & OPERATIONS Presentation to Oregon State Legislature Congestion Work Group

More information

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Americans with Disabilities Act Requirements of Maintenance and Operational

More information

MnDOT Overview. Charlie Zelle Commissioner, MnDOT Jan. 23, 2017

MnDOT Overview. Charlie Zelle Commissioner, MnDOT Jan. 23, 2017 MnDOT Overview Charlie Zelle Commissioner, MnDOT Jan. 23, 2017 Creation of MnDOT Minnesota Statutes, Sections 174.01-174.03 Created by the Legislature in 1976 Combined former Department of Aeronautics,

More information

#4) UN NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING

#4) UN NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING #4) UN-60-16 NUVEDA - CULTIVATION SPECIAL USE PERMIT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: September 14, 2016 Item: UN-60-16 Prepared by: Robert Eastman GENERAL INFORMATION:

More information

Zoo Interchange Reconstruction

Zoo Interchange Reconstruction May 14, 2013 Roberto Gutierrez, PE WisDOT Chris Hager, PE - WisDOT Zoo Interchange Reconstruction Overview of Presentation overview WisDOT Southeast Region I-94 North-South I794/I-94 restriping Hoan bridge

More information

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018 Topics of Presentation 1. Team Introductions 2. Project Overview Location, Aerial View & Site Plan 3. Overall Schedule 4. Sequence

More information

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK MTP VISION In order to create a framework for the 2040 Metropolitan Transportation Plan (MTP), a vision statement was drafted by the Vision/Goals Committee and

More information

Joint Study Session #12 August 23,

Joint Study Session #12 August 23, Preliminary Draft General Plan Economic Development and Public Facilities and Service Elements Town Council / Planning Commission Joint Study Session #12 August 23, 2016 Joint Study Session #12 August

More information

UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT CONSTRUCTION, INC. PG. 6

UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT CONSTRUCTION, INC. PG. 6 UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN CONSTRUCTION, INC. PG. 6 TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT TRAUTWEIN CONSTRUCTION, INC. TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT

More information

Please ensure receipt of this Addendum is acknowledged on page 1 of the Form of Tender.

Please ensure receipt of this Addendum is acknowledged on page 1 of the Form of Tender. No. 1 Project: 47th Ave Road Reconstruction Owner: District of Chetwynd Date: March 5, 2019 Ref. No.: 1320.0095.01 This Addendum is issued prior to Tender Closing Date, in accordance with the Tender Documents

More information

CITY OF NORTH ST. PAUL CITY COUNCIL WORKSHOP AGENDA JANUARY 2, :00 PM. North St. Paul City Hall Sandberg Room 2400 Margaret Street

CITY OF NORTH ST. PAUL CITY COUNCIL WORKSHOP AGENDA JANUARY 2, :00 PM. North St. Paul City Hall Sandberg Room 2400 Margaret Street CITY OF NORTH ST. PAUL CITY COUNCIL WORKSHOP AGENDA JANUARY 2, 2018 5:00 PM North St. Paul City Hall Sandberg Room 2400 Margaret Street I. CALL TO ORDER II. ROLL CALL Council Member Furlong Council Member

More information

Public Notice for Comment

Public Notice for Comment Water Pollution Control District Public Notice for Comment The Logan County Water Pollution Control District is revising its Construction Standards regarding the installation, repair and inspection of

More information

Hamilton Green. Draft Environmental Impact Statement (DEIS)

Hamilton Green. Draft Environmental Impact Statement (DEIS) Hamilton Green Draft Environmental Impact Statement (DEIS) June 2017 HAMILTON GREEN DRAFT ENVIRONMENTAL IMPACT STATEMENT (DEIS) June 14, 2017 Lead Agency: SEQRA Classification: City of White Plains Common

More information

Chapter 4: Transportation and Land Use

Chapter 4: Transportation and Land Use Chapter 4: Transportation and Land Use Transportation and land use together make possible the wide range of destination opportunities in the region. Transportation provides the connections, and, in turn,

More information

Dodge City s, General Information For Driveway/Sidewalk Permits, Utility Permits.

Dodge City s, General Information For Driveway/Sidewalk Permits, Utility Permits. Dodge City s, General Information For Driveway/Sidewalk Permits, Utility Permits. All private construction and/or maintenance activities which take place within the City right-of-way are subject to oversight

More information

2018 Utility & Street Reconstruction

2018 Utility & Street Reconstruction 2018 Utility & Street Reconstruction Public Hearing On Proposed Special Assessments/Hookup Fees for Installation and Construction of Public Improvements Introduction of the Village technical staff Laura

More information

APPLICATION FOR A SITE CONSTRUCTION PERMIT

APPLICATION FOR A SITE CONSTRUCTION PERMIT CITY OF KLAMATH FALLS PUBLIC WORKS ENGINEERING 226 S. 5 th St., Klamath Falls, OR 97601 Phone (541) 883-5368 Fax (541) 883-5287 APPLICATION FOR A SITE CONSTRUCTION PERMIT For City Use Only: APPLICATION

More information

Integrating SHRP 2 Into NMDOT Projects

Integrating SHRP 2 Into NMDOT Projects Integrating SHRP 2 Into NMDOT Projects WHAT is SHRP 2? Strategic Highway Research Program Provides proven methods and tools from transportation case studies Focuses on 5-dimensional project management

More information

If you have any questions during the review of the enclosed materials, please call me at (207) or me at

If you have any questions during the review of the enclosed materials, please call me at (207) or  me at October 21, 2016 Ms. Amanda Lessard Town Planner Town of Windham 8 School Road 04062 RE: Response to Comments - Minor Site Plan Application Dear Ms. Lessard: St.Germain Collins has prepared responses to

More information

Highway Construction Program

Highway Construction Program Highway Construction Program Monthly Delivery Progress Report Watch List October 2018 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule,

More information

BUSINESS DISTRICT REVITALIZATION FUND $450,000 FOR DMP IMPLEMENTATION

BUSINESS DISTRICT REVITALIZATION FUND $450,000 FOR DMP IMPLEMENTATION BUSINESS DISTRICT REVITALIZATION FUND $450,000 FOR DMP IMPLEMENTATION Perform Master Plan Implementation Consulting: $50,000 Perform Post Office Site Evaluation (if necessary): $50,000 11 Agenda Packet

More information

Proposed Sites for Relocation of Butte-Silver Bow County Shops

Proposed Sites for Relocation of Butte-Silver Bow County Shops Proposed Sites for Relocation of Butte-Silver Bow County Shops Presented by: November 9, 2015 Presentation Outline Why the shops must be moved Current location of County Shops Parrot Removal Area Locations

More information

41 st & Fox Station Area Property Owner Meeting August 16, 2018

41 st & Fox Station Area Property Owner Meeting August 16, 2018 Parking Maximum Overlay 41 st & Fox Station Area Property Owner Meeting August 16, 2018 1 Agenda What is this all about? Background 41 st & Fox Station Area Plan Vision Major Implementation Steps What

More information

District of North Vancouver Construction Traffic Management Plan Guidelines

District of North Vancouver Construction Traffic Management Plan Guidelines District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction

More information

City of Reno Public Works

City of Reno Public Works City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE11-00XXX Applicant: Job Description:

More information

Florida Gas Transmission Section #3 Hydrostatic Test

Florida Gas Transmission Section #3 Hydrostatic Test Florida Gas Transmission Section #3 Hydrostatic Test 14-Inch Saint Petersburg Lateral Pipeline From East of Lake Magdalene to West of County Line Hillsborough and Pinellas Counties Today s Outline Who

More information

That Report PW Caledon East Flood Mitigation Study be received, and;

That Report PW Caledon East Flood Mitigation Study be received, and; PW- 2014-038 To: From: Mayor and Members of Council Public Works, Engineering and Enforcement Date: 2014-07-08 Subject: Caledon East Flood Mitigation Study RECOMMENDATION That Report PW-2014-038 Caledon

More information

PUBLIC NOTICE MEDINA COUNTY HIGHWAY ENGINEER SHAW ROAD BRIDGE REPLACEMENT - DESIGN REQUEST FOR STATEMENT OF QUALIFICATIONS (RFQ)

PUBLIC NOTICE MEDINA COUNTY HIGHWAY ENGINEER SHAW ROAD BRIDGE REPLACEMENT - DESIGN REQUEST FOR STATEMENT OF QUALIFICATIONS (RFQ) PUBLIC NOTICE MEDINA COUNTY HIGHWAY ENGINEER SHAW ROAD BRIDGE REPLACEMENT - DESIGN REQUEST FOR STATEMENT OF QUALIFICATIONS (RFQ) The Medina County Highway Engineer is soliciting statement of qualifications

More information

PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE

PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE GENERAL Final restoration of areas within the public right-of-way associated with Street Excavation Permits shall be completed as determined

More information

Transportation and Utilities

Transportation and Utilities 4 Section 4 Transportation and Utilities 4.0 Introduction Transportation and utility systems are essential to accommodate and support development proposed in the Future Land Use Map. The following pages

More information

Join the Conversation!

Join the Conversation! Stage 2 ION: Light Rail Transit (LRT) from Kitchener to Cambridge Transit Project Assessment(TPA) Process Public Consultation Centre (PCC) No.1 November 18, 2015 November 19, 2015 Join the Conversation!

More information