Bid Package 15A Mechanical

Size: px
Start display at page:

Download "Bid Package 15A Mechanical"

Transcription

1 Bid Package 23A Mechanical & HVAC The successful Subcontractor acknowledges and agrees to the requirements set forth by this bid package and its descriptions and in conjunction with all other Construction Documents, as required to provide, furnish, install, and/or maintain all items necessary for a complete scope of work as listed below. The scope of work shall be inclusive of, but not limited to the following specifications, information, and requirements: I) Specifications a) Division 0 Bid Requirements b) Division 1 General Requirements c) Penetration firestopping d) Fire resistive joints e) Joint Sealants f) Joint sealants interior g) Medical Equipment Systems Responsibility Matrix h) Common Motor Requirements for HVAC Equipment i) Expansion Fittings and Loops for HVAC Piping j) Sleeves and Sleeve Seals for HVAC Piping k) Escutcheons for HVAC Piping l) Meters and Gages for HVAC Piping m) General Duty Valves for HVAC Piping n) Ball Valves for HVAC Piping o) Butterfly Valves for HVAC Piping p) Check Valves for HVAC Piping q) Plug Valves for HVAC Piping r) Hangers and Supports for HVAC Piping and Equipment s) Vibration and Seismic Controls for HVAC t) Identification for HVAC Piping and Equipment u) Testing, Adjusting and Balancing for HVAC v) Duct Insulation w) HVAC Piping Insulation x) Facility Natural Gas Piping y) Hydronic Piping z) Refrigerant Piping aa) Metal Ducts bb) Air Duct Accessories cc) HVAC Power Ventilators dd) Diffusers, Registers and Grilles ee) Condensing Boilers ff) Fuel Fired Unit Heaters

2 gg) Scroll Water Chillers hh) Scroll Water Chillers ii) Water Cooled Rotary Screw Water Chillers jj) Cooling Towers kk) Custom Outdoor Air Handling Units ll) Custom Outdoor Air Handling Units mm) Packaged, Outdoor, Central Station Air Handling Units nn) Split System Air Conditioners oo) Unit Heaters pp) Humidifiers qq) KJWW Commissioning Plan dated September 12, 2016 The successful Subcontractor is responsible for all specification Divisions and Sections included within the Construction Documents as required to provide a complete scope of work for this project. The individual Divisions and Sections listed above are provided as a courtesy only. II) Scope Specific Items: 1) Applicable permitting. 2) Provide heating, ventilating and air conditioning (HVAC) systems as complete operable systems. 3) Motor starters, fuses and disconnects that are integral with mechanical equipment. 4) Furnish all variable frequency drives. Electrical subcontractor will install unless factory mounted and integral with equipment. The MC is responsible for storing, protecting, installation (supervise electrical contractor) and warranty for all VFD S. Coordinate locations of motor controllers and variable frequency drives, provide appropriate NEMA enclosure for the location and provide all accessories required for controls and fire alarm. Provide by-passes and harmonic protection as specified. Review electrical drawings and provide combination VFD disconnects as indicated. Furnish all supports for VFD S. 5) Coordinate delivery, receive, inspect, handle, store and install major pieces of prepurchased equipment. Equipment includes Custom Rooftop AHU s (RTU-1 and RTU-2 only), Water Cooled Rotary Screw Chillers (CH-1 and CH-2 only), and Cooling Tower (CT-1 only). This bid package is responsible for reviewing the proposals of the apparent selected vendors in order to provide a complete, fully functional system. 6) Procure balance of all equipment not prepurchased by owner.

3 7) Provide one (1) laborer for the duration of the project to be utilized as directed by Skanska. 8) Duct and pipe systems provided fully coordinated with all trades. Include all offsets, transitions, re-routing, duct blown out and supports (including supplemental steel for standing) for a complete installation. 9) Pipe and duct system tested as complete systems or as partial systems as required to meet the schedule and flow of work so as not to impede the progression of construction. 10) Review phasing requirements and include all systems whole or in part to meet the requirements. 11) Remove from site all water that is not allowed to be flushed into the sanitary lines. 12) Review architectural plans and life safety plans for rated walls. Provide required fire dampers or fire/smoke dampers at all rated walls per code. 13) Provide all manual volume dampers (remote actuators if required) to each air distribution device. 14) Provide AC condensate P-traps, condensate pumps, condensate drain pipe and insulation for a complete system. 15) Provide auxiliary drain pans for equipment installed in critical areas or in ceilings. Provide float switch, interlock wiring and/or drain pipe 16) All prefabrication supplied to the project must be fully coordinated by the MC with the schedule and all other trades. This is to be accomplished during submittals and coordinated during coordination meetings. 17) Furnish and install louvers and vents integral with mechanical systems. Architectural louvers are also provided by this bid package. Verify location and sizes of louvers with architectural plans and include to the larger dimension. Include insect/bird screening, caulking, blank off backing, plenums, insulation of backing / plenums, collar coordination with the building, specified coatings and ratings. 18) Excavation, backfill, compaction and spoils removal necessary for the work within this package. 19) Dewatering necessary for the work within this package. 20) Pads, curbs, inertia bases and other concrete work necessary for the installation of the work within this package, unless specifically detailed on the architectural or structural documents. 21) Blocking/backing for this scope will be the responsibility of this Bid Package.

4 22) Caulking, sealants and firestopping. All fire resistive caulking and through wall assemblies are to be products manufactured by Hilti. 23) Access doors (installed by others) as necessary or specified for work within this package. 24) Sleeves, block-outs, coring, supports, bracing, brackets, guide wires, link seals, inserts, shims, escutcheon plates, anchors, pipe guides and expansion loops necessary for the work within this package. 25) Insulation for mechanical systems as specified. 26) Coding of piping, systems and equipment as necessary for work within this package. 27) Painting of mechanical systems as specified. 28) Sound attenuation and vibration control requirements 29) Seismic requirements. 30) Chemical treatment and cleaning for water systems. Provide coil bypasses and clean strainers for all coils. Provide portable circulation pumps to meet the requirements. 31) Install all piping, ductwork and sleeves to or at right angles to the building structure. 32) Install hangers prior to fireproofing when possible and patch otherwise at the expense of this package. 33) Provide pipe and duct systems supported from ground if ceiling can not support the weight. Provide all spanning steel to accomplish this. 34) Provide metal angles at duct penetrations as required. 35) Authorized factory start up and owner training. 36) Specified warranties and extended warranties to cover early start-up of the mechanical systems. 37) Warranties per specifications; if not listed, two year minimum to be provided. 38) Warranties shall begin at project substantial completion. 39) Testing and system certifications as required. Included but not limited to: HEPA filter test, water sample testing, pipe system weld testing and video taping, fume hood testing, vibration testing and sound testing. Provide all as required to meet specifications. 40) If a conflict exist between specifications, plans and bid manual, you are required to identify it prior to bidding the project or it will considered included to the more expensive way.

5 41) See special conditions requirements for electrical distribution in excess of the temporary electric provided for the project as required for welders, hoists, etc. 42) Coordination with plumbing: a. Provide all make up water connections up to the PC provided backflow preventor. Include pressure reducing valve and all final connections. 43) HVAC control systems, including the complete building automation system and all associated control/interlock wiring (regardless of voltage), pneumatic tubing, etc. 44) Provide Temporary AHU Filters and labor for replacement once a week for a period of 8 months during temporary use of permanent systems. 45) Include all related control wiring, conduits, interlock wiring and control devices for a complete operable system including but not limited to the following (review electrical drawings for miscellaneous power wiring & if not shown on electrical drawings by EC include in your estimate) : a. Control panels. b. Chemical treatment systems. c. Refrigerant alarm controls. d. Cooling tower vibration switch. e. Solenoids f. Hood, fans and makeup air interlocking. g. Power to low voltage VAV boves and CAV boxes. h. Fire/smoke dampers, control dampers, smoke dampers interlocking for controls and related end switch requirements. Verify if electrical drawings show actuator power that the quantity is correct, if not it will be this contractor s responsibility to provide. i. Built-up, custom or packaged systems internal wiring not indicated on electrical drawings. j. Electric heat trace on all exposed to ambient temperature pipe systems. k. Stream traps where required to prevent condensation in the steam lines. 46) owner-furnished equipment

6 a. Install owner-furnished equipment that is related to this scope of work. Provide connections, fittings, dielectric unions, valves, hoses, dampers, ductwork etc. as necessary for installation. b. Lab Fume Hoods c. Walk In Cooler d. Temporary storing of equipment e. Protection of equipment f. Shimming and leveling of equipment 47) Provide independent Test and balance Contractor. a. Water and Air b. Use test instruments that have been calibrated within a time period as recommended by the certifying agency or the manufacturer, whichever is more recent. Instruments shall be checked for accuracy prior to the start of the testing, adjusting and balancing activity. The Subcontractor shall be responsible for the selection of the test instruments used to perform this work, and shall submit a complete list of instruments it proposes for approval. The list shall include the manufacturers name, model and serial number of each instrument and copies of calibration certificates prior to beginning work. No work shall commence until the list has been approved by Skanska. Re-measurement of air distribution devices shall be accomplished utilizing the same instruments used in the original balance report. c. Measure up to ten percent (10%), or higher if required by specifications, of air distribution devices in the presence of the Owner, Architect, Engineers and Skanska, to demonstrate the final balance report is correct. d. Submit the final balancing report for approval. Promptly address all listed deficient items including re-balancing as necessary. Resubmit a revised final report if required. This process shall be repeated at the Subcontractor s

7 expense until the report is accepted by the Architect and Engineers without corrections needed. e. Cost to replace sheaves and belts required for correct balance. f. A test & balance representative must participate in and provide guidance during the development of coordination drawings. Identify and locate where additional dampers, valves, etc. are needed for proper balancing of the system. 48) Assist Commissioning Agent with HVAC systems. Provide assistance to the commissioning agent as necessary. 49) Participate in Coordination Drawing Process in accordance with Section 12 of the Supplemental Instructions to Bidders and Special Conditions. 50) Compliance and adherence to KJWW s Commissioning Plan dated September 12, III) Cost Breakdown: 1) Permits $ 2) Firestopping, sealants, and Caulking $ 3) Coordination Drawing Process $ 4) Ductwork $ 5) Pipe Insulation $ 6) Ductwork Insulation $ 7) Hydronic Piping $ 8) Natural Gas Piping $ 9) Refrigerant Piping $ 10) Valves $ 11) Handling/Installing Prepurchased Equip $ 12) Air Cooled Chillers $ 13) Heat Recovery Chillers $ 14) Hot Water Boilers $ 15) Condensing Boilers $ 16) Exhaust Fans $ 17) Grilles & Diffusers $

8 18) Pumps $ 19) Fan Coil Units $ 20) AHU 3&4 $ 21) Expansion Tanks $ 22) Miscellaneous Equipment $ 23) Terminal Units $ 24) Building Automation System $ 25) Duct Heating Coils $ 26) Designated Laborer $ 27) Commissioning Plan and Assistance $ 28) $ 29) $ 30) $ Sales Tax $N/A on Building Materials Bid Package Total Cost $ Bond Cost Premium $ (Add if Required) IV) Estimated Quantities: 1) Ductwork Sheetmetal LBS 2) Hydronic Piping LF 3) Valves Each 4) Natural Gas Piping LF 5) Refrigerant Piping LF 6) Fire/Fire-Smoke Dampers Each 7) Grilles & Diffusers Each 8) BAS points Each 9) Coordination Man Hours Hours 10) unit 11) Unit

9 V) Labor Units: Regular Premium 1) Superintendent $ $ per hour 2) Plumber/Pipefitter Foreman $ $ per hour 3) Journeyman Plumber/Pipefitter $ $ per hour 4) Sheet Metal Foreman $ $ per hour 5) Sheet Metal Journeyman $ $ per hour 6) Controls Technician $ $ per hour 7) Insulator Foreman $ $ per hour 8) Insulator Journeyman $ $ per hour 9) Equipment Operator $ $ per hour 10) Laborer $ $ per hour VI) Man Hours: 1) Bidder's Field Supervision hours 2) Bidder's Field Labor hours 3) Subcontracted Field Labor hours 4) Off-Site/Shop/Fabrication Labor hours Total Project Man Hours hours

10

Bid Package 22A Plumbing Systems

Bid Package 22A Plumbing Systems Bid Package 22A Plumbing Systems The successful Subcontractor acknowledges and agrees to the requirements set forth by this bid package and its descriptions and in conjunction with all other Construction

More information

CONSTRUCTION REQUIREMENTS

CONSTRUCTION REQUIREMENTS CONSTRUCTION REQUIREMENTS Note: The buildings on the UCCS campus are divided into two categories: General Fund and Auxiliaries. General Fund Buildings include academic and administrative functions. Auxiliary

More information

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Plumbing - 220000 Without limiting the application of all of the Contract Documents to the Subcontract,

More information

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,

More information

Bid Package 6A General Trades

Bid Package 6A General Trades Bid Package 6A General Trades The successful Subcontractor acknowledges and agrees to the requirements set forth by this bid package and its descriptions and in conjunction with all other Construction

More information

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...

More information

University of Delaware

University of Delaware SECTION 22 05 00_COMMON WORK FOR PLUMBING SYSTEM University Contact: Energy & Engineering Group (302) 831-1744 Part 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality

More information

SECTION COOLING TOWER

SECTION COOLING TOWER PART 1 GENERAL 1.1 SECTION INCLUDES A. Mechanical induced draft Cooling Tower B. Controls C. Ladder and handrails 1.2 REFERENCES SECTION 23 65 00 COOLING TOWER A. ANSI/AFBMA 9 - Load Rating and Fatigue

More information

DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED

DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED EVERY ITEM WILL BE REVIEWED AND NOTED FOR COMPLIANCE (C), OR NON- APPLICABILITY (NA). 1. HEATING SYSTEMS: A. GENERAL

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

B. System Design and Performance Requirements

B. System Design and Performance Requirements 15625 Water Chillers This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or in notes

More information

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS 669.7403.001 West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS Page C-111 Advertisement for Bids 1-2 C-200 Instruction to Bidders 1-10 C-410 Bid Form for Construction Projects

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION Section 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Invitation

More information

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section. SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Northwestern Facilities

Northwestern Facilities Northwestern Facilities NU Master Specification - Issuances Record & Summary of Changes Only the most current version of an NU Master Specification is included as a PDF for download on this website. The

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: ARCHITECT/ENGINEER ADDRESS:

More information

CM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements

CM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements SECTION A CM INSTRUCTIONS TO BIDDERS SECTION B BID CATEGORY DESCRIPTIONS & BID FORMS BC-07: Building HVAC and Plumbing BC-08: Building Electric BC-09: General Trades BC-10: Masonry BC-11: Precast Structural

More information

University of Delaware

University of Delaware SECTION 23 05 00_COMMON WORK FOR HVAC SYSTEMS University Contact: Energy & Engineering Group (302) 831-1744 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality Control

More information

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Automatic Fire Suppression - 210000 Without limiting the application of all of the Contract Documents to

More information

Mechanical (HVAC)* * MasterFormat Specifications Division 23

Mechanical (HVAC)* * MasterFormat Specifications Division 23 40 Mechanical (HVAC)* The mechanical subcontractor (more commonly referred to as the heating, ventilation, and air conditioning, or HVAC, subcontractor) will furnish and install all equipment, ductwork,

More information

SECTION AIR TERMINAL UNITS

SECTION AIR TERMINAL UNITS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION Section 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Invitation

More information

A. Section includes busway and fittings including plug-in units.

A. Section includes busway and fittings including plug-in units. SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities

More information

Carter's Oshkosh (SIS) # The Center at Pearland Parkway - Pearland, TX Scope Of Work / Bid Qualifications

Carter's Oshkosh (SIS) # The Center at Pearland Parkway - Pearland, TX Scope Of Work / Bid Qualifications Carter's Oshkosh (SIS) #1185 - The Center at Pearland Parkway - Pearland, TX 77581 - Scope Of Work / Bid Qualifications Please fill out the blanks associated with your trade scope or work with the words

More information

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina Project Manual for Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina DWG Consulting Engineers 1009 Anna Knapp Blvd. Suite 202 Mt Pleasant, South Carolina 29464

More information

Division 00 Procurement and Contracting Requirements

Division 00 Procurement and Contracting Requirements SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders

More information

TABLE OF CONTENTS Public Safety Building

TABLE OF CONTENTS Public Safety Building DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

City Of Mendota Construction Procedures

City Of Mendota Construction Procedures City Of Mendota Construction Procedures Building Permit Application: A permit shall be obtained prior to commencing work of any type. Failure to do so may result in doubling the permit fees. At the time

More information

BID PACKAGES 3-21, Addendum No. 03

BID PACKAGES 3-21, Addendum No. 03 WEBER MURPHY FOX Addendum Date: January 23, 2018 Bid Due Date: January 26, 2018 BID PACKAGES 3-21, Addendum No. 03 to the Plans and Specifications for Cuyahoga Community College West Science and IT Labs

More information

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing.

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing. PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 230593 TESTING, ADJUSTING, AND BALANCING A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification

More information

A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions.

A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions. SECTION 23 0800 COMMISSIONING HVAC PART 1 - GENERAL 1.1 OWNER FURNISHED 1.2 RELATED DOCUMENTS A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary

More information

Capital Projects Group Air Terminal Units Specification

Capital Projects Group Air Terminal Units Specification Capital Projects Group Air Terminal Units Specification Specification 23 36 00 Revision 0 Date: August 2018 Air Terminal Units Specification Specification 23 36 00 Publication Date: August 2018 COPYRIGHT

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES SECTION 262500 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION HVAC INSTRUMENTATION AND CONTROLS INSTALLATION. (Applicable to IUPUI Only)

SECTION HVAC INSTRUMENTATION AND CONTROLS INSTALLATION. (Applicable to IUPUI Only) SECTION 15957 (Applicable to IUPUI Only) I. GENERAL A. NOTES 1. The University has a pre-purchase agreement (PPA) with Johnson Controls (JCI) and Siemens Building Technologies (SBT). The University will

More information

210 WEST 27TH STREET NEW YORK, NY 10001

210 WEST 27TH STREET NEW YORK, NY 10001 210 WEST 27TH STREET BUILDING DEPARTMENT NOTES (FILED UNDER NEW DECEMBER 31, 2014 NYC CODE) 1. THE OWNER SHALL ENGAGE THE SERVICES OF AN AGENCY APPROVED BY THE NYC DEPARTMENT OF BUILDINGS TO PERFORM ALL

More information

F International Fire Code

F International Fire Code 210500- COMMON WORK RESULTS FOR FIRE SUPPRESSION PART 1 -GENERAL REQUIREMENTS AND EXECUTION REQUIREMENTS 1.1 CODE SECTIONS A. 2012 International Mechanical Code B. 20121nternational Building Code C. 2012

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York

More information

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6

FRANKLIN VILLAGE APARTMENTS Building I Franklin Street Morristown, NJ Block: 3901 Lots: 4,5,6 PROJECT MANUAL for: FRANKLIN VILLAGE APARTMENTS Building I Morristown, NJ 07960 Block: 3901 Lots: 4,5,6 Owner: Atlantic Health Investment Corp. 200 American Road Morris Plains, NJ 07950 Architect NETTA

More information

"SRMZ" ROOFTOP PACKAGED MULTIZONE UNITS Self Contained Single Package Units 17.5 to 43 Ton Cooling Capacities

SRMZ ROOFTOP PACKAGED MULTIZONE UNITS Self Contained Single Package Units 17.5 to 43 Ton Cooling Capacities "SRMZ" ROOFTOP PACKAGED MULTIZONE UNITS Self Contained Single Package Units 17.5 to 43 Ton Cooling Capacities Packaged Rooftop Multizone shall be Spinnaker Industries Inc. Model Series SRMZ. Units shall

More information

B. American Society for Testing and Materials: 1. ASTM F708 - Standard Practice for Design and Installation of Rigid Pipe Hangers.

B. American Society for Testing and Materials: 1. ASTM F708 - Standard Practice for Design and Installation of Rigid Pipe Hangers. SECTION 230529 - HANGERS AND SUPPORTS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe hangers and supports. 2. Hanger rods. 3. Inserts. 4. Flashing. 5. Sleeves. 6. Mechanical sleeve seals. 7. Firestopping

More information

Architect's Project Number of 13 Basic HVAC Requirements District Master Specs 2013 Edition

Architect's Project Number of 13 Basic HVAC Requirements District Master Specs 2013 Edition PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 23 05 00 BASIC HVAC REQUIREMENTS A. The general provisions of the Contract, including General Conditions, General Requirements, and Division 1 of the Specifications,

More information

SECTION COMMON HVAC REQUIREMENTS

SECTION COMMON HVAC REQUIREMENTS SECTION 23 0501 COMMON HVAC REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Includes But Not Limited To: 1. Common requirements and procedures for HVAC systems. 2. Responsibility for proper operation of electrically

More information

TYP. SINGLE PLY ROOFING ROOF SHEETING BROAN VENT CAP #10 x 1" GASKETED SMS TYP. 4 SIDES 8" FRAMED CURB HVAC SYSTEMS "BASIS OF DESIGN" ROOF INSULATION R-19 WALL INSULATION R-13 LIGHTING EFFIECNCY PER STANDARDS

More information

SECTION AIR DISTRIBUTION

SECTION AIR DISTRIBUTION SECTION 15880 AIR DISTRIBUTION PART 1 GENERAL 1.1 SUMMARY A. This section describes minimum requirements, products and methods of execution relating to the project air distribution systems. PART 2 PRODUCTS

More information

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS Watercrest - Sand Hill - Columbia, SC 00 0110-1 TABLE OF CONTENTS DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION Document 00 0101 Document 00 0110 Project Title Page CONTRACTING

More information

SECTION HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

SECTION HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION 23 05 29 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 SUMMARY A. Section includes pipe and equipment supports, hangers, anchors, bases sleeves and the sealing of work

More information

VOLUME 4 DIVISION SPECIFICATIONS

VOLUME 4 DIVISION SPECIFICATIONS Page 1 Section Title Consultant Pages VOLUME 4 DIVISION 00-01 SPECIFICATIONS Division 00 - Procurement and Contracting Requirements 00 01 07 SEALS PAGE All 5 00 01 11r6 TABLE OF CONTENTS All 7 00 21 13r1

More information

Price High Performance Horizontal Fan Coil Units

Price High Performance Horizontal Fan Coil Units Price High Performance Horizontal Fan Coil Units Division 23 Heating, Ventilating, and Air Conditioning Section 23 82 19 Fan Coil Units The following specification is for a defined application. Price would

More information

Architect s Project Number of 5 Decentralized HVAC Equipment District Master Specs 2013 Edition

Architect s Project Number of 5 Decentralized HVAC Equipment District Master Specs 2013 Edition PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 23 81 00 DECENTRALIZED HVAC EQUIPMENT A. The other Contract Documents complement the requirements of this section. The General requirements apply to the work

More information

PROJECT SPECIFICATIONS

PROJECT SPECIFICATIONS PROJECT SPECIFICATIONS CITY OF PORTLAND BUREAU OF ENVIRONMENTAL SERVICES PROJECT SPECIFICATIONS FOR ANKENY PUMP STATION UPGRADE BES project number E07833 STANDARD REQUIREMENTS (DIVISION 0) GENERAL REQUIREMENTS

More information

Training Certification Categories

Training Certification Categories Training Certification Categories Residential Residential Building Inspector structures are free from hazardous structural conditions and comply with the UCC. Duties include inspection of footings and

More information

Chapter 9 - Design Guides 9.18 HVAC GUIDE

Chapter 9 - Design Guides 9.18 HVAC GUIDE A. GENERAL 9.18 HVAC GUIDE 1. The purpose of this guide is to convey general basis-of-design, standard of quality, and OGS preferences as they relate to building HVAC system design. Specific client agency

More information

MINNESOTA STATE SECTION ADVERTISEMENT FOR BIDS

MINNESOTA STATE SECTION ADVERTISEMENT FOR BIDS MINNESOTA STATE SECTION 00 11 13 ADVERTISEMENT FOR BIDS Sealed Bids for: will be received by: Ridgewater College Commercial Chiller Purchase Ridgewater College Willmar Campus 2101 15 th Ave. N.W Willmar,

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-23 82 19.00 40 (May 2017) ------------------------------ Preparing Activity: NASA Superseding UFGS-23 82 19 (May 2014) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

Price Fan Powered Terminal Units

Price Fan Powered Terminal Units Price Fan Powered Terminal Units Division 23 Heating, Ventilating, and Air Conditioning Section 23 3600 Air Terminal Units The following specification is for a defined application. Price would be pleased

More information

PLUMBING BUILDING SCOPE OF WORK

PLUMBING BUILDING SCOPE OF WORK PLUMBING BUILDING SCOPE OF WORK 1. The Contractor shall furnish all supervision, materials, labor, equipment, tools, supplies, incidental items, including construction cleanup, etc for accomplishing the

More information

EXHIBIT A SCOPE OF SERVICES MAINTENANCE OF TRANE HVAC SYSTEMS

EXHIBIT A SCOPE OF SERVICES MAINTENANCE OF TRANE HVAC SYSTEMS EXHIBIT A SCOPE OF SERVICES MAINTENANCE OF TRANE HVAC SYSTEMS DISTRICT VII, HEADQUARTERS FACILITY AND TAMPA BAY SUNGUIDE REGIONAL TRAFFIC MANAGEMENT CENTER I. PURPOSE: DISTRICT VII, HEADQUARTERS FACILITY

More information

PROJECT TITLE PROJECT NO.: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO.: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA PRE-START-UP/START-UP CHECKLIST CHILLED WATER SYSTEM NOTE: University s Representative must be notified and scheduled to witness test prior to any start up of equipment. A. Chilled Water Pumps 1. Submittal

More information

PRESTON HEALTH SERVICES ARCHITECT S NO. 2700

PRESTON HEALTH SERVICES ARCHITECT S NO. 2700 SECTION 23 0510 - BASIC MATERIALS AND METHODS PART 1 - GENERAL 1.1 DESCRIPTION OF WORK: A. Provide equipment, labor, materials, etc. required to make a complete working installation as shown or as specified.

More information

Cherokee Nation W.W. Keeler Second Story Addition and Remodel Tahlequah, Oklahoma. WORK PACKAGE # 23A Heating Ventilating and Air Conditioning 3/4/15

Cherokee Nation W.W. Keeler Second Story Addition and Remodel Tahlequah, Oklahoma. WORK PACKAGE # 23A Heating Ventilating and Air Conditioning 3/4/15 SCOPE SUMMARY: Cherokee Nation W.W. Keeler Second Story Addition and Remodel Tahlequah, Oklahoma WORK PACKAGE # 23A Heating Ventilating and Air Conditioning 3/4/15 DIVISION: 0 - LEGAL DOCUMENTS As Applicable;

More information

SECTION LOW-VOLTAGE TRANSFORMERS

SECTION LOW-VOLTAGE TRANSFORMERS PART 1 GENERAL 1.1 DESCRIPTION SECTION 26 22 00 SPEC WRITER NOTE: Use this section only for NCA projects. Delete between // // if not applicable to project. Also, delete any other item or paragraph not

More information

SECTION GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT

SECTION GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT SECTION 23 05 12 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Delete between // // if not applicable to project. Also delete

More information

ADDENDUM 1. Repair and Maintenance of Landfill Gas Chiller System. Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018

ADDENDUM 1. Repair and Maintenance of Landfill Gas Chiller System. Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018 ADDENDUM 1 Date: June 13, 2018 Bid No.: Title: 18-11/AL Repair and Maintenance of Landfill Gas Chiller System Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018 This Addendum

More information

ADDENDUM 2 - JULY 14, 2015

ADDENDUM 2 - JULY 14, 2015 7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures

More information

OAKDALE CHILLED WATER PLANT CAPACITY UPGRADES UI PROJECT INSTALL CHILLERS SECTION COMMISSIONING

OAKDALE CHILLED WATER PLANT CAPACITY UPGRADES UI PROJECT INSTALL CHILLERS SECTION COMMISSIONING PART I GENERAL 1.01 SECTION INCLUDES A. Commissioning objectives. B. Roles and responsibilities. C. Test Equipment. D. Systems to be commissioned. E. Construction Checklist requirements. SECTION 01 91

More information

KIPLING SCHOOL RENOVATION AND EXPANSION PHASE 2 KIPLING, SASKATCHEWAN

KIPLING SCHOOL RENOVATION AND EXPANSION PHASE 2 KIPLING, SASKATCHEWAN 2012-07-26 00 91 14 31/2011 ADDENDUM NO. 2 Kipling School Renov. & Expansion Phase 2, Kipling, SK. Page 1 of 2 ADDENDUM NUMBER: ISSUED BY: PROJECT: TWO SEPW Architecture Inc. 109 3725 Pasqua St., Regina,

More information

2015 Fourth Quarter. (Base Year 2013) Detailed by: Main building materials and. services groups. Construction Cost Index

2015 Fourth Quarter. (Base Year 2013) Detailed by: Main building materials and. services groups. Construction Cost Index To w e r b u i l d i n g s p r o j e c t s 2015 Fourth Quarter (Base Year 2013) Detailed by: Main building materials and Release Date: March Construction Cost2016 Index 1 services groups Table of Contents

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

City of Westerville Guide to Commercial Inspections

City of Westerville Guide to Commercial Inspections City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing

More information

CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist

CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist This checklist is a convenient reference to the 2012 Michigan Building Code. The checklist

More information

DUKE UNIVERSITY CONSTRUCTION STANDARDS

DUKE UNIVERSITY CONSTRUCTION STANDARDS 1 23 08 00 Commissioning of HVAC Systems 1. GENERAL A. GENERAL PROVISIONS 1. Drawings and general provisions of the Contract, including General Conditions and Division - 1 Specifications Sections, apply

More information

State of Ohio Ohio School Facilities Commission TABLE OF CONTENTS

State of Ohio Ohio School Facilities Commission TABLE OF CONTENTS State of Ohio Ohio School Facilities Commission TABLE OF CONTENTS TABLE OF CONTENTS DEFINITIONS NOTICE TO BIDDERS INSTRUCTIONS TO BIDDERS BID FORM. BID GUARANTY AND CONTRACT BOND Article 1 Contract Information

More information

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT. A. ASME B31.1 (American Society of Mechanical Engineers) - Power Piping

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT. A. ASME B31.1 (American Society of Mechanical Engineers) - Power Piping SECTION 22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 SUMMARY A. Section includes pipe and equipment supports, hangers, anchors, bases sleeves and the sealing of

More information

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE STAFF USE ONLY RECEIVED BY: DATE: Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE Applicant must complete numbered items

More information

LIST OF DRAWINGS PLAN TITLE

LIST OF DRAWINGS PLAN TITLE LANDFILL SITE [CLOSED 00] PLAN.... 5. TITLE LIST OF DRAWINGS EXISTING PROCESS DIAGRAM PROPOSED PROCESS DIAGRAM EXISTING EQUIPMENT LAYOUT PLAN PROPOSED EQUIPMENT LAYOUT PLAN ELEVATION D AND DETAILS TREATMENT

More information

SECTION MECHANICAL INSULATION

SECTION MECHANICAL INSULATION SECTION 15250 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification sections, apply to work

More information

DESIGN BASIS FOR AIR CONDITIONING AND VENTILATION SYSTEM FOR SUBSTATION AND CONTROL BUILDING HINDUSTAN PETROLEUM CORPORATION LTD.

DESIGN BASIS FOR AIR CONDITIONING AND VENTILATION SYSTEM FOR SUBSTATION AND CONTROL BUILDING HINDUSTAN PETROLEUM CORPORATION LTD. CONDITIONING AND VENTILATION FOR SUBSTATION AND CONTROL BUILDING HINDUSTAN PETROLEUM CORPORATION LTD. VISAKH REFINERY DHT PROJECT TEIL JOB NO.: 6261 DOCUMENT NO.: 6261-HVAC-PKG-300 TEIL SPECIFICATION NO.:---

More information

SECTION DUCTS PART 1 GENERAL 1.01 SUMMARY

SECTION DUCTS PART 1 GENERAL 1.01 SUMMARY 1 1 1 1 1 1 1 1 0 1 0 1 SECTION 1 DUCTS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Duct Materials.. Insulated flexible ducts.. Single wall spiral round ducts.. Ductwork fabrication.. Duct cleaning.

More information

Capital Projects Group Mechanical Work Commissioning Specification

Capital Projects Group Mechanical Work Commissioning Specification Capital Projects Group Mechanical Work Commissioning Specification Specification 20 05 40 Revision 0 Date: August 2018 Mechanical Work Commissioning Specification Specification 20 05 40 Publication Date:

More information

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

PRICE AW-D PACKAGED OUTDOOR HEATING AND COOLING MAKE-UP AIR UNITS

PRICE AW-D PACKAGED OUTDOOR HEATING AND COOLING MAKE-UP AIR UNITS PRICE AW-D PACKAGED OUTDOOR HEATING AND COOLING MAKE-UP AIR UNITS Division 23 Heating, Ventilating, and Air Conditioning Section 23 75 33 Custom-Packaged, Outdoor, Heating and Cooling Makeup Air-Conditioners

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/06/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/06/2013 BUILDING SURVEY DATE 0067 1110 WEST GREEN STREET URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.810 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 18,640,900 OFFICE BUILDING GROSS SQUARE FEET 175,513

More information

Special Provisions. Service Line Item Index

Special Provisions. Service Line Item Index Special Provisions - General Description of Site and Requirements - General Description of Mechanical System - Inspection of Facilities - Contractor Notification - Mobilization - Response Time - Contractor

More information

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

CSO / BSU NW2 NORTH RESIDENTIAL NEIGHBORHOOD PHASE #2 VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP VOLUME 1 PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 01 Project Title Page 00 01 10 Table of Contents 00 01 15 List of Drawing Sheets 00 21

More information

Unit Substation Transformer Construction Checklist (under 500 kva)

Unit Substation Transformer Construction Checklist (under 500 kva) Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

PROJECT MANUAL PROJECT LABOR AGREEMENT

PROJECT MANUAL PROJECT LABOR AGREEMENT June 30, 2017 ISSUED FOR BID: January 25, 2018 PROJECT MANUAL PROJECT LABOR AGREEMENT VOLUME 6 OF 6: DIVISIONS 26 33 City School District of Albany Albany High School Additions & Renovations Phase 1 CSArch

More information

SECTION ROTARY SCREW WATER CHILLERS

SECTION ROTARY SCREW WATER CHILLERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information

SECTION EXHAUST FANS PART 1 GENERAL

SECTION EXHAUST FANS PART 1 GENERAL SECTION 15800 EXHAUST FANS PART 1 GENERAL 1.01 DESCRIPTION A. The Contractor shall furnish all labor, materials, accessories and all incidentals required to install wet well and control building ventilation

More information

DIVISION 15-MECHANICAL PN SECTION BASIC MECHANICAL MATERIALS AND METHODS PART 1 - GENERAL 1.01 APPLICATION OF THIS SECTION

DIVISION 15-MECHANICAL PN SECTION BASIC MECHANICAL MATERIALS AND METHODS PART 1 - GENERAL 1.01 APPLICATION OF THIS SECTION PART 1 - GENERAL 1.01 APPLICATION OF THIS SECTION A. This Section applies to all other Sections in Division 15, as the work is applicable. 1.02 SECTION INCLUDES A. Drawing intent. B. Arrangement of work.

More information

Permit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2)

Permit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2) STAFF USE ONLY RECEIVED BY: DATE: Permit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2) Applicant must complete

More information

1. ARI 410 Standard for chilled water, hot water and steam coils. 2. ARI 430 Central Station Air Handling Units

1. ARI 410 Standard for chilled water, hot water and steam coils. 2. ARI 430 Central Station Air Handling Units PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is

More information

Attachment 1: RAE Corporation Technical Specification

Attachment 1: RAE Corporation Technical Specification Attachment 1: RAE Corporation Technical Specification RAE Corporation Phone: 918-825-7222, ext. 105 Steve Corbin Quote# XXXX Qty Customer Tag Technical Systems Model Number 1 ACC-4 10A0-162-S General Scope

More information

Our Shop is Your Shop

Our Shop is Your Shop Our Shop is Your Shop Company Number: Company Name: Address: 294 Lee Company 311 Mallory Station Road City: Franklin State: TN Zip: 3767 Company Phone: Fax: 615-567-126 Company Contact: Brad Gipson Job

More information

Absolute Energy Raters Commissioning Plan Outline Template

Absolute Energy Raters Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. Absolute Energy Raters is not rendering advice concerning any commission project or practices. This document is neither

More information

5. AMCA 301 Method of Publishing Sound Ratings for Air Moving Devices. 6. AMCA 500 Test Methods for Louver, Dampers, and Shutters

5. AMCA 301 Method of Publishing Sound Ratings for Air Moving Devices. 6. AMCA 500 Test Methods for Louver, Dampers, and Shutters PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is

More information