Kuliarchar Sweater Industries Ltd.
|
|
- Geoffrey Harrison
- 5 years ago
- Views:
Transcription
1 Kuliarchar Sweater Industries Ltd. Bada Kalmasher, K.B bazar, Gazipur, Bangladesh ( , ) 9 March 2014 DEA 1
2 2 Observations Made
3 3 High Stress in Columns
4 Cursory calculations indicate that internal and external columns working stress is at a high level in Buildings A and B. A Detailed Engineering Assessment of the building is required (See attached Scope). Engineer is to perform detailed calculations based on as constructed dimensions and concrete tests to prove column size is adequate. High Stress in Columns 4
5 5 Double Height Columns
6 Double height columns in Building B are open to high impact loads from vehicles Double Height Columns 6 One double height column in Building A has some form of vehicle impact prevention measure, but not all.
7 7 Construction of new Concrete Roof in Building A to replace the Existing Steel Roof
8 Construction on the roof 8 On the roof of Building A, work has commenced to remove the steel dining area and replace it with a concrete roof.
9 9 Water Tanks on the Roof
10 2.0m 2.5m 2.5m High water tank placed on the roof of building A. This places a significant load into the columns. Building A 2.0m High water tank placed on the roof of building B. This places a significant load into the columns. Water Tanks on the Roof 10 Building B
11 11 Hairline Cracks in Beams
12 Hairline cracking was observed at mid-span of the supporting beams under the 5 th floor. These are a result of normal structural behaviour of 2-way spanning slabs and supporting beams. Hairline Cracks in Beams 12
13 More cracks in various beams supporting the 5 th floor slab. Hairline Cracks in Beams 13
14 14 Hairline Cracks in Slabs
15 Cracking was observed over the beams on the grid lines on the 4th Floor level of Building A. These are a result of normal structural behaviour of 2- way spanning slabs and supporting beams. Hairline Cracks in Slabs 15
16 16 Deflection in Beams
17 A small number of beams at 6th floor level of Building B, with typical span of 5.4m, appear to have deflected. However, no associated cracking was observed. It is possible that the render may have been poorly applied to give this apparent deflection. Deflection in Beams 17
18 18 Semi Circular Cantilever Areas
19 Minor cracking on one element suggests a small deflection in one cantilever. Cantilever slabs acting compositely with upstand/downstand concrete wall elements constructed on a semi-circular plan shape. In two areas, part of the upstand/downstand has been broken out to facilitate linking walkways connecting Buildings A and B. This has weakened the construction but may be acceptable subject to a detailed design check. Semi Circular Cantilever Areas 19
20 20 Priority Actions
21 Problems Observed 1. High Stress in Columns in Buildings A and B 2. Double Height Columns to Front of Both Buildings 3. Construction of Concrete Roof of Building A currently under way 4. Apparent Deflections/Cracking of Beams at 5 th /6 th Floors 5. Retrofitted Connecting Walkways Part of Concrete Upstand/Downstand Structure Removed 21
22 Item No. Observation Recommended Action Plan Priority 1 High Stress in Columns in Buildings A and B Maintain current use of the floors and don t change use or increase occupation, either of which could increase loading. Floor loadings throughout shall not exceed 1.5 kn/m2 until DEA confirms a greater floor live load allowance is permissable. Immediate - Now 2 3 High Stress in Columns in Buildings A and B High Stress in Columns in Buildings A and B Building Engineer to review design, loads and columns stresses in all columns. A Detail Engineering Assessment of Factory to be commenced, see attached Scope. Immediate - Now Immediate - Now 4 High Stress in Columns in Buildings A and B Produce and actively manage a loading plan for all floor plates within the factory giving consideration to floor capacity and column capacity. 6-weeks 5 High Stress in Columns in Buildings A and B Detail Engineering Assessment to be completed 6-weeks High Stress in Columns in Buildings A and B High Stress in Columns in Buildings A and B High Stress in Columns in Buildings A and B Verify in-situ concrete stresses either by 100mm diameter cores or existing cylinder strength data for cores from 4 columns. Continue to implement load plan Implement strengthening measures if required following the findings of the DEA 6-weeks 6-months 6-months 22
23 Detail Engineering Assessment This Schedule develops a minimum level of information, Analysis and testing expected as part of a Detail Engineering Assessment. The Building(s) have been visually assessed and it is deemed necessary that a detailed engineering assessment be carried out by a competent Engineering Team employed by the factory Owner. This Request should be read in conjunction with the BUET developed Tripartite Guideline document for Assessment of Structural Integrity of Existing RMG Factory Buildings in Bangladesh (Tripartite Document), the latest version of this document should be referenced. T his document also gives guidance on required competency of Engineering Team. We expect that the following will be carried out: 1. Development of Full Engineering As-Built Drawings showing Structure, loading, elements, dimensions, levels, foundations and framing on Plan, Section and Elevational drawings. 2. The Engineering team are to carry out supporting calculations with a model based design check to assess the safety and serviceability of the building against loading as set out in BNBC-2006, Lower rate provisions can be applied in accordance with the Tripartite Guidelines following international engineering practice, justification for these lower rate provisions must be made. 3. A geotechnical Report describing ground conditions and commenting on foundation systems used/proposed. 4. A report on Engineering tests carried out to justify material strengths and reinforcement content in all key elements studied. 5. Detailed load plans shall be prepared for each level showing current and potential future loading with all key equipment items shown with associated loads. 6. The Engineering team will prepare an assessment report that covers the following: As-Built drawings including Plans at each level calling up and dimensioning all structural components Cross sectional drawings showing structural beams, slabs, floor to floor heights, roof build-ups and Basic design information of the structure Highlight any variation between As-built compared to the designed structure Results of testing for strength and materials Results of geotechnical assessment and testing/investigation Details of loading, inputs and results of computer modelling Commentary on adequacy/inadequacy of elements of the structure Schedule of any required retrofitting required for safety or performance of Structure Any proposals for Retrofitting to follow guidance developed in the Tripartite Document 23
24 Item No. Observation Recommended Action Plan Priority 9 Double Height Columns to Front of Both Buildings As part of the Detail Engineering Assessment required under Item 1, the double height columns at the front of both Buildings A and B shall be assessed. Vehicle impact to be considered, as well as considering the columns as key elements of structure. Immediate - Now Double Height Columns to Front of Both Buildings Double Height Columns to Front of Both Buildings Double Height Columns to Front of Both Buildings Complete DEA and identify strengthening measures where required Complete construction of bracing/strengthening measures (if required) Construct column impact protection to protect from vehicle collision. 6-weeks 6-months 6-months 13 Construction of Concrete Roof of Building A currently under way Construction on the roof of Building A to stop immediately until the Detail Engineering Assessment outlined in Item 1 is complete. Immediate - Now 14 Construction of Concrete Roof of Building A currently under way Capacity of existing columns to carry the additional dead and live loads due to the new concrete roof to be confirmed. 6-weeks 15 Construction of Concrete Roof of Building A currently under way Implement strengthening measures if required. 6-months 24
25 Item No. Observation Recommended Action Plan Priority Apparent Deflections/Cracking of Beams at 5th/6th Floors Apparent Deflections/Cracking of Beams at 5th/6th Floors Apparent Deflections/Cracking of Beams at 5th/6th Floors Apparent Deflections/Cracking of Beams at 5th/6th Floors Retrofitted Connecting Walkways Part of Concrete Upstand/Downstand Structure Removed Retrofitted Connecting Walkways Part of Concrete Upstand/Downstand Structure Removed Retrofitted Connecting Walkways Part of Concrete Upstand/Downstand Structure Removed Retrofitted Connecting Walkways Part of Concrete Upstand/Downstand Structure Removed Remove plaster in cracked/deflected areas to ascertain if the apparent problems are manifested in the underlying structure. As part of the DEA required for Item 1, assess if remedial strengthening work is necessary based on the results of the opening up exercise. Monitor cracks and displacements of the beams to identify if the cracking/deflections are getting progressively worse. Implement strengthening measures where required. As part of the DEA required under Item 1, analyse the impact of removing part of the curved concrete structure to allow the walkways to pass through above and below the slab (see page 19). Remove plaster in cracked areas to ascertain if cracks are reflected in the underlying structure. Identify if strengthening measures in the concrete structure are required in the area of the walkways. Implement strengthening measures where required. Immediate - Now 6-weeks 6-months 6-months Immediate - Now Immediate - Now 6-weeks 6-months 25
Panwin Designs Ltd. Baniachala (Bagher Bazar), Bhabanipur, Gazipur , rd May 2014
Panwin Designs Ltd. Baniachala (Bagher Bazar), Bhabanipur, Gazipur 24.166331, 90.420108 3 rd May 2014 1 Observations Building 1 2 Observations Building 1 Stress Levels in Columns 3 Observations Building
More informationSuman Fashion Garments Ltd. Nipunika Ltd. Cha-72/1/B, Moddha Badda, Holland Centre, Progoti Sarani, Dhaka ( N, E) 09 March 2014
Suman Fashion Garments Ltd. Nipunika Ltd. Cha-72/1/B, Moddha Badda, Holland Centre, Progoti Sarani, Dhaka (23.78287N, 90.42559E) 09 March 2014 1 2 Observations 3 Columns appear to be stressed in excess
More informationBadhan Knit Fashions Ltd
1 Badhan Knit Fashions Ltd A-16/17, BSCIC Hoisery Industrial Area, Shashongaon, Enayetnagar Fatullah, Narayangnaj (23.623200, 90.479000) 5 th April 2014 2 Observations 3 High Column Loads: Detailed Engineering
More informationFakir Knitwears Ltd. Kayempur, Fatullah, Narayanganj-1400, Bangladesh ( N, E) 19 December 2013
1 Fakir Knitwears Ltd. Kayempur, Fatullah, Narayanganj-1400, Bangladesh (23.64049N, 90.50106E) 19 December 2013 2 Observations 3 High Column Loads - Main Building Engineering Assessment Required Cursory
More informationMasco Cottons Ltd. 44, Redwan Complex, Gazipura Bustand, Tongi, Gazipur ( N, E) 25 January 2015
1 Masco Cottons Ltd 44, Redwan Complex, Gazipura Bustand, Tongi, Gazipur (23.921111N, 90.392778E) 25 January 2015 2 Observations 3 Observations 2 Columns heavily loaded for following reasons: - Loaded
More informationS B Design Ltd. Famous Design Ltd. 246/1/F, West Agargaon, Sher-E-Bangla Nagar, Dhaka-1207 ( N, E) 17 February 2015
1 S B Design Ltd. Famous Design Ltd. 246/1/F, West Agargaon, Sher-E-Bangla Nagar, Dhaka-1207 (23.782446 N, 90.369530 E) 17 February 2015 2 High stress levels in columns 3 North Building South Building
More informationWarn Knit Fashion Sun Knitwear Ltd. ARS Printing Chanmari, Near New Court, Fatullah, Narayanganj 1400, Bangladesh ( N, 90.
Warn Knit Fashion Sun Knitwear Ltd. ARS Printing Chanmari, Near New Court, Fatullah, Narayanganj 1400, Bangladesh (23.634373N, 90.497889E) 4 th December, 2016 2 High stress levels in columns that require
More informationABA Fashions Ltd. Plot #9, Block F, Tongi, Gazipur-1710 ( N, E) 08 MARCH 2014
ABA Fashions Ltd. Plot #9, Block F, Tongi, Gazipur-1710 (23.885176N, 90.399821E) 08 MARCH 2014 1 2 Observations 3 Highly stressed columns Cursory calculations indicate column at a high working stress.
More informationSonnet Textile Industries Ltd.
Sonnet Textile Industries Ltd. 49/B, Baizid Bostami Road, Nasirabad I/A, Chittagong. (22.31733N,91.80721E) 12 th June 2014 DEA 1 2 Observations 3 High column stresses, uncontrolled live loads and no loading
More informationAl Islam Textile Ltd.
Al Islam Textile Ltd. 9 Kornopara,Savar,Dhaka-1340 (23.824207N, 90.256342E) 27 APRIL 2014 1 2 Observations Item 1 observation Column loads in excess of design loads Verify concrete strengths in columns
More informationPurna Fashions Ltd. RH Attire Ltd
Purna Fashions Ltd. RH Attire Ltd SHAHNUR MARKET, 96 MURADPUR, HATHAZARI ROAD, PANCHLAISH THANA, Chittagong, Bangladesh (22.37245N, 91.83334E) 08 June 2014 1 2 Observations 3 High Column Stresses The columns
More informationBabylon Casualwear Ltd Aboni Fashions Ltd Suravee Garments Ltd
Babylon Casualwear Ltd Aboni Fashions Ltd Suravee Garments Ltd Plot-23,24, Tetulzhora, Hemayetpur, Savar, Dhaka (23.792784N, 90.254587E) 29 March 2014 1 2 Observations 3 Potentially Highly-stressed columns
More informationApparel Gallery Ltd.
Apparel Gallery Ltd. 147-148, Norshinghpur, Asulia, Savar, Dhaka (23.929985N,90.304914E) 23 March 2014 1 2 Observations Building 1 Heavy loading due to raised floor area on Ground Floor 3 Building 1 Raised
More informationSaasco Tex (BD) Ltd Muksudpur Apparels Ltd Expo Dress Ltd Julfikar Fashions Ltd
Ltd Saasco Tex (BD) Ltd Muksudpur Apparels Ltd Expo Dress Ltd Julfikar Fashions Ltd Plot # 27, Holding # I/A, Milk vita Road, Section-7, Pallabi, Mirpur, Dhaka-1216. (23.819805N, 90.360526E) 24 th May
More informationAbanti Color Tex Ltd. Plot-S, A-646, Shashongaon Enayetnager, Fatullah, Narayangonj ( E, N) 28 June 2014
1 Abanti Color Tex Ltd. Plot-S, A-646, Shashongaon Enayetnager, Fatullah, Narayangonj (90.476444E, 23.622806N) 28 June 2014 2 Preliminary calculations suggest columns in Units 1 and 2 are highly stressed
More informationDew Fashions Ltd. Le-Nouveautex Ltd. House-65,Board Bazar, Gazipur, Dhaka ( N, E) 22 June 2014
1 Dew Fashions Ltd. Le-Nouveautex Ltd. House-65,Board Bazar, Gazipur, Dhaka (+23.93941N,90.38554E) 22 June 2014 2 Observations Main Factory Building - Columns appear to be stressed to levels that require
More informationTanzila Textile Ltd.
1 Tanzila Textile Ltd. Baroypara, Ashulia, Savar, Dhaka. (24.017986, 90.243410) 12 April 2014 2 Observations 3 Highly Stressed Columns (Building 03) Cursory calculations indicate column at high working
More informationCamlet Fashions Ltd. Simco Fashions Ltd Fine Craft Ltd Ayesha & Galeya Fashions Ltd
Camlet Fashions Ltd. Simco Fashions Ltd Fine Craft Ltd Ayesha & Galeya Fashions Ltd 24/ka Shahid Minar Road (5 th Floor), Kallyanpur, Dhaka-1217. (23.77907778, 90.35986)- 28 th February 2015 1 2 Observations
More informationStructural Inspection Report
Revision: Issue 2 Date: 23 rd June 2014 Cherry Pvt. Ltd. Florence Fashions Ltd. Ultimate Ltd. Chandand Fashion Ltd. Joy Fashion Ltd. Structural Inspection Report Authors: Adrian Ryan, Cathal Mac an tsearraigh
More informationElite Garments Ind. Ltd.
Elite Garments Ind. Ltd. Bade Kalmeswer, Board Bazar, Gazipur, Bangladesh (23.954199, 90.380240) 5th April 2014 8th April 2015 1 2 Observations Made 3 Building 5 - Steel Portal Frame Main span varies from
More informationPandora Sweaters Ltd.
1 Pandora Sweaters Ltd. Gilar Chala, Master Bari, Shreepur, Gazipur. (24.187444, 90.424696) 19 th April 2014 2 Observations 3 High stress in columns in the two main production buildings Cursory calculations
More informationLibas Textiles Ltd (9500)
Revision : Issue 01 Date: 28.03.2014 Libas Textiles Ltd (9500) Nishchintopur, Mouchak, Kaliakoir, Gazipur, Bangladesh. (+24.01773N, +90.27978E) 22.MARCH.2014 Client Summary Report Observations & Actions
More informationPosh Garments Ltd Ltd
Posh Garments Ltd Ltd 384/A, Tejgaon Industrial Area, Dhaka 1215 (23.76577, 90.39870) 6 th April 2014 1 2 Observations 3 Stress Levels in Columns Cursory calculations indicate that the working stress of
More informationAmity Design Ltd. House #7&9, Road #9 Block #D, Section #11 Mirpur Dhaka 1216, Bangladesh (23.820N, E) 03.MARCH.2014
Amity Design Ltd. House #7&9, Road #9 Block #D, Section #11 Mirpur Dhaka 1216, Bangladesh (23.820N, 90.366E) 03.MARCH.2014 Site Observations Structural drawing does not match with the existing building
More informationA.M. Design Ltd. Diakhali, Beron, Jamgara, Ashulia, Bangladesh ( N, E) 3 May 2014
1 A.M. Design Ltd. Diakhali, Beron, Jamgara, Ashulia, Bangladesh (23.937403N,90.296808E) 3 May 2014 2 Observations 3 Sensitivity of cantilever areas to loading Northeast cantilever East cantilever South
More informationAlif Apparels Ltd. (9813) Goldstar Garments Ltd. (9844)
Alif Apparels Ltd. (9813) Goldstar Garments Ltd. (9844) 23/8 B&C, Holding #24/2, Khilje Road, Shyamoli Cinema Complex Building (2 nd Floor), Shyyamoli, Dhaka-1207 (+ 23.774489N, 90.365164E) 16.AUGUST.2014
More informationGMS Composite Ltd. Shardagonj, Kashimpur,Gazipur,Bangladesh ( , ) 22 March 2014
GMS Composite Ltd. Shardagonj, Kashimpur,Gazipur,Bangladesh (23.968661, 90.296963) 22 March 2014 1 2 Observations 3 Highly stressed columns Cursory calculations indicate that the working stresses of columns
More informationEchotex Ltd. Chandra, Mouchak, Shafipur, Gazipur, Dhaka ( N, E) 6 February 2014
Echotex Ltd Chandra, Mouchak, Shafipur, Gazipur, Dhaka (+24.03892N, 90.2586 E) 6 February 2014 1 2 Building Observations Garment Factory 3 Columns appear to be stressed in excess of normal design limits
More informationTanaz Fashions Ltd. & Zayantex Ltd. L Usine Fashion Ltd (Unit 1)
Tanaz Fashions Ltd. & Zayantex Ltd. L Usine Fashion Ltd (Unit 1) 216, Sataish Road, Gazipura, Tongi, Gazipur, Bangladesh (23.921458N,90.386581E) 22 September 2013 1 2 Local concrete spalling caused by
More informationAman Graphics and Design Ltd. Nazimnagar, Hemayetpur, Savar, Dhaka ( E, N) 29 April 2014
1 Aman Graphics and Design Ltd. Nazimnagar, Hemayetpur, Savar, Dhaka (23.79418E, 90.26393N) 29 April 2014 2 Building Observations 3 Building 1 - Columns appear to be stressed in excess of normal design
More informationKDS IDR Ltd. CDA Plot # 15 (P)+16, Mohora I/A, Chandgaon, Chittagong ( N, E) Survey Date: 11 th March 2015
1 KDS IDR Ltd. CDA Plot # 15 (P)+16, Mohora I/A, Chandgaon, Chittagong (22.398815N, 91.865572E) Survey Date: 11 th March 2015 2 Observations Office Building - Pipe chased into column at 3rd floor level
More informationK.L. Fashion Ltd. (10982) 75/1, Master Bari, Tongi, Gazipur ( N, E) 01.July.2014
K.L. Fashion Ltd. (10982) 75/1, Master Bari, Tongi, Gazipur (+23.903394N, +90.369739E) 01.July.2014 Identified Priority 1 Concerns None Identified Priority 2 Concerns The building does not contain any
More informationA-One Polar Ltd. Bhulta,Rupgonj,Narayangonj. ( , ) 27th April 2014
1 A-One Polar Ltd Bhulta,Rupgonj,Narayangonj. (23.754782,90545710) 27th April 2014 2 Observations Observations Knitting & Garments building Building 1 1 3 4 Observations Roof structure: no roof bracing
More informationEpcot Apparels Ltd Epcot Jeans Ltd Chandana, Joydebpur, Gazipur ( N, E) 11 May 2014
1 Epcot Apparels Ltd Epcot Jeans Ltd Chandana, Joydebpur, Gazipur (23.991163N, 90.394333E) 11 May 2014 2 Observations 3 Minor discrepancies between drawings and asbuilt structure At roof level the typical
More informationMondol Fabrics Ltd. Nayapara,kasimpur, Gazipur ( N, E0) 8th March 2014
Mondol Fabrics Ltd Nayapara,kasimpur, Gazipur (23.990028N, 90.317336E0) 8th March 2014 1 2 Observations 3 Column Stresses in Toilet Area North of Building Cursory calculations indicate that column size
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory Name: FCI BD, Ltd. Plot-36-39 Dhaka EPZ, Ganakbari, Savar Savar Dhaka Bangladesh The Alliance for Bangladesh Worker Safety Page 1/9 Introduction
More informationStructural Safety Inspection
Structural Safety Factory Name ABANTI COLOUR TEX LTD ID 9468 Factory Address Date Date of Review Inspected by Shashongaon, Plot - S, A-646, Enayet nagar, Fatullah,Narayanganj 8/06/014 6-Jun-17 Md. Mostakin
More informationCassiopea Fashions Ltd. Cassiopea Apparels Ltd.
1 Cassiopea Fashions Ltd. Cassiopea Apparels Ltd. Bokran, Monipur, Vabanipur, Gazipur. (24.127427, 90.399544) 15 April 2014 2 Observations Made 3 No apparent stability system Steel Building 6 th floor
More informationShin Shin Apparels Ltd. (9615) Dag RS. 228, JL 73, Gorat, East Norshinghapur, Zirabo, Savar ( N, E) 27.MAY.2014
Shin Shin Apparels Ltd. (9615) Dag RS. 228, JL 73, Gorat, East Norshinghapur, Zirabo, Savar (+23.94071N, 90.30929E) 27.MAY.2014 Identified Priority 1 Concerns 1 st Priority 1 Concern Based on the Detail
More informationNatural Sweater Village Ltd
Natural Sweater Village Ltd Raju Tower, Gouripur, Ashulia, Dhaka (23.887817E,90.318335N) 19 December 2013 1 2 Building 1 Building Observations 3 Drawings do not correspond with constructed condition in
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory 81, Kalmessar, "Jalal Shopping Complex" Board Bazar, Gazipur. 20 May 2014 The Alliance for Bangladesh Worker Safety Page 1/11 20 May 2014 Introduction
More informationEQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT
EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT 171-181, Baizid Bostami Road Nasirabad I/A, Chittagong Chittagong The Alliance for Bangladesh Worker Safety Page 1/11 Introduction to the Report The following
More informationGraphic Textiles Ltd.
Graphic Textiles Ltd. Sreeampur, Kalampur, Dhamrai, Dhaka (23.919114N 90.124967E) 17 th May 2014 1 2 Observations 3 Column capacity to be reviewed Preliminary calculations indicate that columns at Basement
More informationSpring Trade Ltd. (9522) Plot # 42, Konapara Tenguri, Zirani Bazar, B.K.S.P, Savar, Dhaka, Bangladesh. ( N, E) 28.APRIL.
Spring Trade Ltd. (9522) Plot # 42, Konapara Tenguri, Zirani Bazar, B.K.S.P, Savar, Dhaka, Bangladesh. (+23.990869N, +90.244843E) 28.APRIL.2014 Identified Priority 1 Concerns 1 st Priority 1 Concern Typical
More informationMark Sweater Ltd. Structural Inspection Report Observations & Actions Authors: Dariusz Tomiak Checked by: Dariusz Tomiak Approved by: Dariusz Tomiak
Mark Sweater Ltd. Surabari, Kashimpur, Gazipur-Sadar, Gazipur. (23.9716797, 90.3213635) 1 st March 2015 Structural Inspection Report Observations & Actions Authors: Dariusz Tomiak Checked by: Dariusz Tomiak
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory Address: 50, New Chaktai (4th & 5th Floor), Haji Delware Hosen Sowdagar Market, Chittagong Chittagong Chittagong Bangladesh 05 May 2014 The
More information4A Yarn Dyeing Ltd. Kaichabari, Savar, Dhaka-1340, Bangladesh ( , ) 25 March 2014
4A Yarn Dyeing Ltd. Kaichabari, Savar, Dhaka-1340, Bangladesh (23.945831, 90.261923) 25 March 2014 1 2 Observations 3 Highly stressed columns Outline calculations indicate that the working stresses of
More informationIMPRESS FASHION LTD. Dag No. 2224, Matuial, Konapara Katherpool, Jatrabari, Dhaka-1362 ( N, E) 27 August 2015
IMPRESS FASHION LTD. Dag No. 2224, Matuial, Konapara Katherpool, Jatrabari, Dhaka-1362 (23.713984N, 90.462352E) 27 August 2015 1 2 Observations 3 Building 1 4 High stress on column. Overstressed Columns
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory Gilarchala, Gorgaria Master bari Sreepur, Gazipur Sreepur, Gazipur 22 Apr 2014 The Alliance for Bangladesh Worker Safety Page 1/10 Factory
More informationEH Textiles Ltd EH Fabrics Ltd
EH Textiles Ltd EH Fabrics Ltd 221 225 Sataish Rd, Khortoil, Dhaka (23.9208N, 90.3880E) 31 October, 2013 1 2 Building Observations 3 Engineering Checks on columns required C2 perimeter columns drawings
More informationLevel 6 Graduate Diploma in Engineering Structural analysis
9210-111 Level 6 Graduate Diploma in Engineering Structural analysis Sample Paper You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler, drawing
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory Name: 10, HSS Road Chittagong Chittagong Chittagong Bangladesh 21 May 2014 The Alliance for Bangladesh Worker Safety Page 1/12 21 May 2014
More informationUtah Knitting & Dyeing Ltd #9533. Boran, Monipur, Mirzapur, Gazipur 03.May.2014
Utah Knitting & Dyeing Ltd #9533 Boran, Monipur, Mirzapur, Gazipur 03.May.2014 Identified Priority 2 Concerns Chemical & Sewing Buildings No loading plan in effect. Washing Building Cracks in upstand beams
More informationHELA Clothing Bangladesh Ltd
1 HELA Clothing Bangladesh Ltd Plot No. : 53, 54, 66, 67; Sector 01, Karnaphuli Export Processing Zone, North Patenga, Chittagong - 4204 (+91.792172E, 22.27145N) 01 July 2014 2 Steel columns in the Production
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Assessor: South Panishail, Kashimpur, Gazipur Gazipur Dhaka Bangladesh Emkay Enterprises The Alliance for Bangladesh Worker Safety Page 1/9 Introduction
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) The Alliance for Bangladesh Worker Safety Page 1/12 Introduction to the Report The following report contains a site profile and summary of non-conformities
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Plot 33-35, Dhaka (EPZ), Savar Savar Dhaka Bangladesh The Alliance for Bangladesh Worker Safety Page 1/11 Introduction to the Report The following
More informationEQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT
EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT Plot No.: 74-77, Sector -02, Karnaphuli EPZ North Patenga, Chittagong Chittagong Chittagong Bangladesh The Alliance for Bangladesh Worker Safety Page 1/11
More informationEQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT
EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT A-23, 24, 25, 26 BSCIC, Industrial Estate, Kalurghat, Chittagong The Alliance for Bangladesh Worker Safety Page 1/15 Introduction to the Report The following
More informationAmena (Pvt.) Ltd. (9817) Abdul Latif Market, Ahalia,Sector #5,Road #9-C,Uttara ( N, E) 15.June.2014
Amena (Pvt.) Ltd. (9817) Abdul Latif Market, Ahalia,Sector #5,Road #9-C,Uttara (+23.863478N, 90.388429E) 15.June.2014 Identified 1 st Priority 3 Concern 1 st Priority 3 Concern Uncontrolled storage loading
More informationNew Era Fashions Mfrs (BD) Ltd
New Era Fashions Mfrs (BD) Ltd Ltd Plot 10,11 & 12 Sector 8, Road 3, CEPZ, Chittagong (22.279298N, 91.776438E) 21 st June 2014 1 2 Observations Safety Hazard Water ingress through unsealed expansion joint
More informationLida Textile & Dyeing Ltd. Structural Inspection Report
Revision: Issue 1 Date: 9 th February 2015 Lida Textile & Dyeing Ltd. Ltd Holding No. 100/2, Block-B, East Chandura, Ward-8, Shafipur, Kaliakair, Gazipur. (24.036527, 90.272019) 4 th February 2015 Structural
More informationGK Garments Ltd (10378) Global Fashion Garments Ltd (10380) Global Outerwear Ltd (9991) Savar Shirts (10394)
GK Garments Ltd (10378) Global Fashion Garments Ltd (10380) Global Outerwear Ltd (9991) Savar Shirts (10394) 89, Berulia Road, Tati, Savar, Dhaka, Bangladesh. (+23.84843N, +90.25978E) 20.MARCH.2014 Identified
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Plot 47-52 & 68-73, KEPZ North Patenga Chittagong Chittagong The Alliance for Bangladesh Worker Safety Page 1/10 Introduction to the Report The following
More informationEQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT
EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT The Alliance for Bangladesh Worker Safety Page 1/9 Introduction to the Report The following report contains a site profile and summary of non-conformities
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory Haribaritek, Pubail College Gate, Pubail, Gazipur Gazipur Dhaka 09 Jul 2014 The Alliance for Worker Safety Page 1/11 09 Jul 2014 Introduction
More informationL Usine Fashions Ltd. (Ref. 9258) 36, Gazipura, Sataish Road, Tongi, Gazipur-1712, Bangladesh ( N, E) 08.MARCH.
L Usine Fashions Ltd. (Ref. 9258) 36, Gazipura, Sataish Road, Tongi, Gazipur-1712, Bangladesh (+23.920227N, 90.379468E) 08.MARCH.2014 Identified Priority 1 Concerns Heavy machinery at 1 st floor level
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory Name: Karardi, Shibpur, Narsingdi, Narsingdi Dhaka Bangladesh 10 May 2013 The Alliance for Bangladesh Worker Safety Page 1/15 10 May 2013 Introduction
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Assessor: Plot M-4/3, Road 7, Section 7 Mirpur, Dhaka Dhaka Dhaka Bangladesh Emkay Enterprises The Alliance for Bangladesh Worker Safety Page 1/7 Introduction
More informationStar Garments (Pvt Ltd.)
Star Garments (Pvt Ltd.) Sha-23, Middle Badda, Dhaka. (23.780094N, 90.426299E) 02 July 2014 1 2 Observations 3 Inconsistencies between the drawings and the as constructed building Irregularities on drawings
More informationEQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT
EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT Factory C.D.A Plot No. C-49, Sagarika Road, Pahartaly, Chittagong Chittagong 18 May 2014 The Alliance for Bangladesh Worker Safety Page 1/12 18 May 2014
More informationBUILDING INTEGRITY SUMMARY REPORT
BUILDING INTEGRITY SUMMARY REPORT SUPPLIER NAME Kenpark Bangladesh Pvt.Ltd (Unit 1) UNITS AUDITED SUPPLIER ADDRESS Dry Process Building Sector 8, Plot 31-42, Chittagong Export Processing Zone, Chittagong,
More informationDESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,
DESIGN OF SLABS Dr. G. P. Chandradhara Professor of Civil Engineering S. J. College of Engineering Mysore 1. GENERAL A slab is a flat two dimensional planar structural element having thickness small compared
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory Assessor: 936, Vogra Chowdhury Bari, Joydevpur, Gazipur Joydebpur, Gazipur Emkay Enterprises 16 May 2015 The Alliance for Bangladesh Worker
More informationIntegrity of Compartmentation in Buildings During a Fire. Tom Lennon 30 th September 2004, BRE, Garston
Integrity of Compartmentation in Buildings During a Fire Tom Lennon 3 th September 24, BRE, Garston Background Review of Approved Document B Use of structural fire engineering New forms of construction
More information2016 DESIGN AND DRAWING OF REINFORCED CONCRETE STRUCTURES
R13 SET - 1 DESIGN AND DRAWING OF REINFCED CONCRETE STRUCTURES 1 Design a simply supported rectangular beam to carry 30kN/m superimposed load over a span of 6m on 460mm wide supports. Use M20 grade concrete
More informationLEARNING OF ETABS. 15 ft
LEARNING OF ETABS Ram Krishna Mazumder, Institute of Earthquake Engineering Research, Chittagong University of Engineering and Technology, Chittagong 4349, Bangladesh rkmazumder@gmail.com +8801712862281
More informationCork Institute of Technology. Summer 2006 Structural Design & Detailing I (Time: 4 Hours)
Cork Institute of Technology Bachelor of Engineering (Honours) in Structural Engineering Stage 2 (NFQ Level 8) Summer 2006 Structural Design & Detailing I (Time: 4 Hours) Instructions: 1. The examination
More informationBUILDING INTEGRITY DEA SUMMARY REPORT
BUILDING INTEGRITY DEA SUMMARY REPORT SUPPLIER NAME OPEX Apparels Ltd. UNITS AUDITED Washing Plant 3 WG -5 WG 5 Extension (SKL) WG -3 Security Building SUPPLIER ADDRESS Kanchipur, Narayangonj, Dhaka, Bangladesh
More informationBUILDING INTEGRITY DEA SUMMARY REPORT
BUILDING INTEGRITY DEA SUMMARY REPORT SUPPLIER NAME UNITS AUDITED SUPPLIER ADDRESS Kenpark Bangladesh Pvt. Ltd. AUDIT DATE 10 th May, 2014 AUDIT PERFORMED BY AUDIT TEAM 1-storied prefabricated steel structure-
More informationBUILDING INTEGRITY SUMMARY REPORT
BUILDING INTEGRITY SUMMARY REPORT SUPPLIER NAME Karnafuli Shoes Industries Ltd (Garments Unit) SUPPLIER ADDRESS Building No 17, Building No 16, Canteen Building No 2, Canteen Building No 1; Building No
More informationPimkie Apparels Ltd. (9205) Plot #328, Bloc #F, Tongi Industrial Area, Tongi ( N, E) 27.May.2014
Pimkie Apparels Ltd. (9205) Plot #328, Bloc #F, Tongi Industrial Area, Tongi (+23.882757N, 90.396797E) 27.May.2014 Identified Priority 1 Concerns Garment Building Steel columns 1 st Priority 1 Concern
More informationLateral System Analysis and Confirmation Design
Andrew Covely Structural Dr. Linda Hanagan The Helena New York City, NY November 15, 2004 Pictures courtesy of Fox & Fowle Architects Lateral System Analysis and Confirmation Design Executive Summary This
More informationBUILDING INTEGRITY DEA SUMMARY REPORT
BUILDING INTEGRITY DEA SUMMARY REPORT SUPPLIER NAME UNITS AUDITED Opex Mills SSL2 Building 4X Generator Building 6X Generator Building Denim Generator Building Rope Denim Generator Building SSL Generator
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) 234/8, Kafrul Tower Kachukhate Road Kafrul, Dhaka Cantonment Dhaka The Alliance for Bangladesh Worker Safety Page 1/10 16 Apr 2014 Introduction to
More informationBUILDING INTEGRITY SUMMARY REPORT
BUILDING INTEGRITY SUMMARY REPORT SUPPLIER NAME SUPPLIER ADDRESS AUDIT DATE January 2014 AUDIT PERFORMED BY Cosmopolitan Industries Pvt Ltd Khejur Bagan, Bara Ashulia, Savar, Dhaka, Bangladesh Department
More informationECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE
ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE Introduction to Echo Floors The oldest company in the group, established in Gauteng in 1982. The core business is the manufacture
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory Name: Tianye (BD) Camping Tent Co. Ltd SFB#3, Ishwardi, EPZ, Paksey, Pabna Pabna Rajshahi Bangladesh 25 Oct 2016 The Alliance for Bangladesh
More informationEQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT
EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT Factory Kandi Boilarpur, Horindhora, Hemayetpur, Savar Savar Dhaka 27 May 2014 The Alliance for Worker Safety Page 1/10 Factory 27 May 2014 Introduction
More informationSTORAGE RACKS PLAN REVIEW LIST (2011 LABC)
STORAGE RACKS PLAN REVIEW LIST (2011 LABC) Plan Check Submittal Date: Plan Check / PCIS Application #: Job Address: Applicant (name & phone #): Reviewed by (print first / last name): Telephone #: E-mail:
More informationJohn Jay College Expansion Project
Technical Report #3 Michael Hopper Mike AE Consultant: Dr. Lepage [Type the company name] November 21 st, 2008 Technical Report #3 Table of Contents Executive Summary.3 Introduction.4 Existing Composite
More informationBUILDING INTEGRITY SUMMARY REPORT
BUILDING INTEGRITY SUMMARY REPORT SUPPLIER NAME UNITS AUDITED Opex Mills 4X 6X Denim Rope Denim SSL SSL3 Utility Diesel SUPPLIER ADDRESS AUDIT DATE January 2014 AUDIT PERFORMED BY AUDIT TEAM Kanchpur,
More informationCommercial Structures
Commercial Structures Structural Components Footing Piles Foundation Beams Joists Column Substructure Superstructure Reinforced concrete Re-bar Pre-cast concrete panel Deflection Cantilever Footings A
More informationA COMPARATIVE STUDIES ON ELEVATED WATER TANK DUE TO DYNAMIC LOADING
A COMPARATIVE STUDIES ON ELEVATED WATER TANK DUE TO DYNAMIC LOADING SANDEEP T D Assistant Professor, civil engineering department, New Horizon College of Engineering Banglore-560103, Karnataka, India ---------------------------------------------------------------------***---------------------------------------------------------------------
More informationBUILDING INTEGRITY SUMMARY REPORT
BUILDING INTEGRITY SUMMARY REPORT SUPPLIER NAME Kenpark Bangladesh Apparel Pvt. Ltd (Unit 2) UNITS AUDITED SUPPLIER ADDRESS Wash Building Plot # 69-85, Karnaphuli Export Processing Zone, Chittagong, Bangladesh
More informationVOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.)
DIVISION 94 VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.) SEC. 91.9401. PURPOSE. (Amended by Ord. No. 172,592, Eff. 6/28/99,
More informationINITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR)
INITIAL STRUCTURAL INTEGRITY ASSESSMENT REPORT (SIAR) Factory SFB 2 Adamjee EPZ, Siddergonj, Narayangonj, Siddhirgonj Dhaka 22 Feb 2017 The Alliance for Worker Safety Page 1/11 22 Feb 2017 Introduction
More informationEQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT
EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT Factory Name: 4 YOU CLOTHING LTD 367/1 Senpara Parbata, Mirpur-10, Dhaka Dhaka Dhaka Bangladesh The Alliance for Bangladesh Worker Safety Page 1/5 Introduction
More informationCADS A3D MAX. How to model shear walls
CADS A3D MAX How to model shear walls Modelling shear walls in A3D MAX Introduction and synopsis This paper explains how to model shear walls in A3D MAX using the `wide column rigid arm sub-frame described
More informationPushover Analysis of RC Frame for effective column design
Pushover Analysis of RC Frame for effective column design Lekshmi Nair 1, Aswathy S Kumar 2 1 M.Tech Student, Sree Buddha College of Engineering for Women, Elavumthitta, Kerala, India 2 Staff, Sree Buddha
More information