REQUEST FOR PROPOSALS

Size: px
Start display at page:

Download "REQUEST FOR PROPOSALS"

Transcription

1 Administered by UNIVERSITY OF SOUTHERN MAINE Facilities Management REQUEST FOR PROPOSALS Transformer Pre-Purchase Gorham Central Heat Plant RFP C ISSUE DATE: February 19, 2013 Addendum 1 February 27, 2013 PROPOSALS MUST BE RECEIVED BY March 1, 2013 by 2:00 pm DELIVER PROPOSALS TO: University of Southern Maine Facilities Management Attn: Adam Thibodeau 30 University Way Gorham, ME 04038

2 SECTION ONE NOTICE TO VENDORS (Advertisement) The University of Southern Maine, Gorham Campus is seeking proposals for the following: Gorham Central Heat Plant Transformer Pre-purchase C Project Summary: The University of Southern Maine, a member of the University of Maine System desires to pre-purchase the transformer for the Gorham Central Heat Plant at the Gorham Campus. Proposals will be received until 2:00 PM, March 1, 2013, at the Gorham Facilities Office at which time they will be opened and evaluated. Submissions received after this time will be returned unopened. Submitting firms will be notified of the results. Additional information may be obtained at the following web site: Click on USM Gorham- Transformer Pre-purchase C" General information may also be obtained from Adam Thibodeau, Facilities Management, University of Southern Maine, Portland, ME ( ) or athibodeau@usm.maine.edu.

3 SECTION TWO 2.0 GENERAL INFORMATION: 2.1 Purpose: The University of Southern Maine is seeking proposals for Transformer prepurchase for the Gorham Central Heat Plant. 2.2 The University of Southern Maine will hereinafter be referred to as the "University." Respondents to the RFP shall be referred to as "Vendor(s) or Vendor(s). 2.4 Evaluation Criteria: Award will be made to the low vendor provided that all project requirements are satisfactorily met. However, consideration will be given to delivery, service and warranty 2.5 Award: The University reserves the right to conduct any tests it may deem advisable and to make all evaluations. The University reserves the right to reject any or all proposals, in whole or in part and is not necessarily bound to accept the lowest proposal if that proposal is contrary to the best interests of the University. The University reserves the right to waive minor irregularities. Scholarships, donations, or gifts to the University will not be considered in the evaluation of proposals. A proposal may be rejected if it is in any way incomplete or irregular. When there are tie proposals, there shall be a preference for "in-state vendor". When tie proposals are in-state or out-of-state, the award will be made to the proposal that arrives first at the USM Facilities Management Office. 2.6 Award Protest: Vendor s may appeal the award decision by submitting a written protest to the University of Southern Maine Director of Engineering and Architecture within five (5) business days of the date of the award notice, with a copy of the protest to the successful vendor. The protest must contain a statement of the basis for the challenge. 2.7 Communication with the University: It is the responsibility of the vendor to inquire about any requirement of this RFP that is not understood. Responses to inquiries, if they change or clarify the RFP in a substantial manner, will be forwarded by addenda to all parties that have received a copy of the RFP. Addenda will also be posted on our web site, Gorham -Transformer Pre- Purchase. The University will not be bound by oral responses to inquiries or written responses other than addenda. Inquiries must be made to: Adam Thibodeau University of Southern Maine Facilities Management P.O. Box Bedford Street Portland, Maine (207) athibodeau@usm.maine.edu 2.8 Submission: A SIGNED original of the proposal must be received at the University of Southern Maine, Facilities Management, 30 University Way, Gorham, Maine 04038, in a sealed envelope no later than 2:00 P.M. local time, Friday, March 1, 2013, at which time they will be opened and evaluated. Submitting firms will then be notified of the results. The proposal must be date/time stamped by the Facilities Management Office in order to be considered. Vendors are strongly encouraged to submit proposals in advance of the due date/time to avoid the possibility of missing the 2:00 deadline due to unforeseen circumstances. Vendors assume the risk of the methods of dispatch chosen. The University assumes no responsibility for delays caused by any package or mail delivery service. A postmark on or before the due date WILL NOT substitute for receipt of proposal. In the event

4 of suspended University operations due to weather, the proposal opening will be rescheduled for the next business day at the same time and location. Proposals received after the due date and time will be returned unopened. Additional time will not be granted to any single vendor, however, additional time may be granted to all vendors when the University determines that circumstances require it. FAXED OR PROPOSALS WILL NOT BE ACCEPTED. 2.9 Proposal Envelope: The signed proposal should be returned in an envelope or package, sealed and identified as follows: From March 1, :00 p.m C Name Due Date Time Proposal No Printed copies may be obtained from: USM Facilities Management, 25 Bedford St. Portland, ME Information may also be obtained at the following web site: Click on USM Gorham -Transformer Pre-Purchase C" 2.11 Proposal Understanding: By submitting a proposal, the vendor agrees and assures that the specifications are adequate, and the vendor accepts the terms and conditions herein. Any exceptions should be noted in your response Costs of Preparation: Vendor assumes all costs of preparation of the proposal and any presentations necessary to the proposal process Debarment: Submission of a signed proposal in response to this solicitation is certification that your firm (or any subcontractor) is not currently debarred, suspended, proposed for debarment, declared ineligible or voluntarily excluded from participation in this transaction by any State or Federal department or agency. Submission is also agreement that the University will be notified of any change in this status Proposal Validity: Unless specified otherwise, all proposals shall be valid for sixty (60) days from the due date of the proposal Errors: Proposals may be withdrawn or amended by vendors at any time prior to the proposal opening. After the proposal opening, proposals may not be amended. If a significant mistake has been made by an apparent low vendor, the vendor will be given the option of selling at the price given or withdrawing the proposal. If an extension error has been made, the unit price will prevail.

5 SECTION THREE 3.0 GENERAL TERMS AND CONDITIONS: 3.1 Contract Administration: The University of Southern Maine s Department of Facilities Management or its designee shall be the University's authorized representative in all matters pertaining to the administration of this Contract. 3.2 Contract Documents: If a separate contract is not written, the Contract entered into by the parties shall consist of the RFP, the signed proposal submitted by the Contractor, the specifications including all modifications thereof, and a purchase order, all of which shall be referred to collectively as the Contract Documents. 3.3 Contract Modification and Amendment: The parties may adjust the specific terms of this Contract (except for pricing) where circumstances beyond the control of either party require modification or amendment. Any modification or amendment proposed by the Contractor must be in writing to the University of Southern Maine, Facilities Management Office. Any agreed upon modification or amendment must be in writing and signed by both parties. 3.4 Contract Term: The Transformer, as specified, shall be delivered to the University of Southern Maine, Gorham Campus on or before June 17, The vendor agrees to pay liquidated damages to the University of Southern Maine in the amount of $825.00/Day for damages incurred by the University due to the Vendor s failure to deliver the equipment within the contract time. 3.5 Contract Validity: In the event one or more clauses of the Contract are declared invalid, void, unenforceable or illegal, that shall not affect the validity of the remaining portions of the Contract. 3.6 Non-Waiver of Defaults: Any failure of the University to enforce or require the strict keeping and performance of any of the terms and conditions of this Contract shall not constitute a waiver of such terms, conditions, or rights. 3.7 Clarification of Responsibilities: If the Vendor needs clarification of or deviation from the terms of the Contract, it is the Vendor's responsibility to obtain written clarification or approval from the Contract Administrator. 2.8 Litigation: This Contract and the rights and obligations of the parties hereunder shall be governed by and construed in accordance with the laws of the State of Maine without reference to its conflicts of laws principles. The Vendor agrees that any litigation, action or proceeding arising out of this Contract, shall be instituted in a state court located in the State of Maine. 3.9 Indemnification (Vendor): The Vendor agrees to be responsible for, and to protect, save harmless, and indemnify the University and its employees from and against all loss, damage, cost and expense (including attorney's fees) suffered or sustained by the University or for which the University may be held or become liable by reason of injury (including death) to persons or property or other causes whatsoever, in connection with the operations of the Vendor under this agreement.

6 3.10 Assignment: Neither party of the Contract shall assign the Contract without the prior written consent of the other, nor shall the Vendor assign any money due or to become due without the prior written consent of the University Equal Opportunity: In the execution of the Contract, the Vendor and all sub vendors agree, consistent with University policy, not to discriminate on the grounds of race, color, religion, sex, sexual orientation, including transgender status or gender expression, national origin or citizenship status, age, disability, genetic information, or veteran s status and to provide reasonable accommodations to qualified individuals with disabilities upon request. The University encourages the employment of individuals with disabilities Sexual Harassment: The University is committed to providing a positive environment for all students and staff. Sexual harassment, whether intentional or not, undermines the quality of this educational and working climate. The University thus has a legal and ethical responsibility to ensure that all students and employees can learn and work in an environment free of sexual harassment. Consistent with the state and federal law, this right to freedom from sexual harassment was defined as University policy by the Board of Trustees. Failure to comply with this policy could result in termination of this Contract without advance notice. Further information regarding this policy is available from the Office of Equity and Compliance, 209 Deering Avenue, Portland, ME, (207) , darylmc@usm.maine.edu 3.13 Contractor s Liability Insurance: During the term of this agreement, the Vendor shall maintain the following insurance: Insurance Type Coverage Limit 1. Commercial General Liability $1,000,000 per occurrence or more (Written on an Occurrence-based form) (Bodily Injury and Property Damage) 2. Vehicle Liability $1,000,000 per occurrence or more (Including Hired & Non-Owned) (Bodily Injury and Property Damage) 3. Workers Compensation Required for all personnel (In Compliance with Applicable State Law) The University of Maine System shall be named as Additional Insured on the Commercial General Liability insurance. Certificates of Insurance for all of the above insurance shall be filed with: University of Southern Maine Facilities Management 25 Bedford Street Portland, Maine Certificates shall be filed prior to the date of performance under this Agreement. Said certificates, in addition to proof of coverage, shall contain the standard Acord statement pertaining to written notification in the event of cancellation, with a thirty (30) day notification period. As additional insured and certificate holder, the University should be included as follows: University of Maine System 16 Central Street Bangor, Maine 04401

7 3.14 Campus Tobacco Use Policy: A tobacco-free campus has been established at The University of Southern Maine to provide a healthy working and learning environment for the entire campus community. 1. The University of Southern Maine is a tobacco-free campus. This policy applies to faculty, staff, students, contractors, vendors and visitors. The use of tobacco and all smoking products is not permitted on any university-owned property, which includes but is not limited to, buildings, university grounds, parking areas, campus walkways, recreational and sporting facilities, and university or personally-owned, rented or leased vehicles. 2. Tobacco use by definition includes the possession of any lighted tobacco products, or the use of any type of smokeless tobacco, including but not limited to chew, snuff, snus, electronic cigarettes, and all other nicotine delivery devices that are non-fda approved as cessation products. 3. It is the shared responsibility of all members of the campus community to respect and abide by this policy. The successful implementation of this policy depends on the courtesy and cooperation of the entire campus community Payments: Payment will be upon submittal of an invoice to the University by the Vendor on a Net 30 basis unless discount terms are offered. Invoices must include a purchase order number. The University is using several, preferred methods of payment: PCard (Visa); Bank of America s epayables and PayMode electronic payment systems. Please indicate your ability to accept payment via any or all of these methods Delivery: on or before June 17, The Vendor will have the complete responsibility for the equipment until it delivered and unloaded to an approved rigging company, at which point it will be turned over to the installing contractor. All transportation and unloading arrangements to the rigging company will be the responsibility of the Vendor. All transportation and unloading arrangements from the rigging company to the Gorham Central Heat Plant will be the responsibility of the installing contractor.

8 SECTION FOUR SPECIFICATIONS Pad Mount Transformer

9 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: SECTION PRE-PURCHASE SPECIFICATION PART 1 - GENERAL 1.1 SCOPE OF WORK A. Provide medium voltage transformer as shown on the Contract Drawings and in conformance with this Section. 1.2 RELATED DOCUMENTS A. Contract Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.3 DIVISION OF RESPONSIBILITY A. Equipment Vendor: 1. Equipment manufacturer contracted by the University to fabricate and supply the specified equipment. Additional responsibilities include equipment submittals, factory testing, delivery of the equipment to the jobsite, field inspections upon arrival at the jobsite, supervision of all pre-functional testing procedures, training and additional activities as listed in this specification. B. Electrical Contractor: 1. Installation contractor contracted by the University to install and integrate the specified equipment for the project. Additional responsibilities include inspection of the equipment upon arrival to the job site, coordination of the equipment delivery, off loading and final placement of the equipment, protection of the equipment between offloading and final placement, field installed wiring, switchgear control wiring verification, assistance in all pre-functional & functional testing procedures, assistance in switchgear as-built submittals, preparation of field as-built drawings and additional activities as listed in this specification. 1.4 SUMMARY A. This Section includes the following types of transformers with medium-voltage primaries: 1. Pad-mounted, liquid-filled transformers. 1.5 DEFINITIONS A. The following definitions apply to this Section: RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

10 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: QUALIFICATIONS 1. AA: air-to-air (dry type, ventilated, self-cooled) 2. AC: alternating current 3. FA: forced-air (cooled) 4. FFA: future forced air (cooled) 5. FCAN: full capacity above normal 6. FCBN: full capacity below normal 7. MOV: metal oxide varistor 8. OA: oil-to-air (liquid-immersed, self-cooled) A. The manufacturer of the core and coil shall procure all other transformer components, and shall assemble, factory test, and prepare the transformer for shipping. B. The transformer manufacturer shall have quality certification to ISO 9000:2000 or equivalent. 1.7 REFERENCE STANDARDS A. Comply with the following standards in effect at the time of bid submittal: 1. IEEE C2 National Electrical Safety Code. 2. IEEE IEEE Standard Test Procedure for Evaluation of Systems of Insulation for Dry-Type Specialty and General Purpose Transformers 3. IEEE IEEE Guide for the Application of High Temperature Insulation Materials in Liquid-Immersed Power Transformers 4. IEEE IEEE Standard for the Electronic Reporting of Transformer Test Data 5. IEEE IEEE Guide for Determination of Maximum Winding Temperature Rise in Liquid-Filled Transformers 6. IEEE C37 Family of Guides and Standards for Circuit Breakers, Switchgear, Relays, Substations, and Fuses, with emphasis on the following: a. ANSI/IEEE C (R1992) American National Standard Specifications for Distribution Fuse Disconnecting Switches, Fuse Supports, and Current-Limiting Fuses b. IEEE C IEEE Standard for Switchgear-Unit Substations- Requirements 7. IEEE C57 Family of Guides and Standards for Distribution, Power, and Regulating Transformers, with emphasis on the following: a. IEEE C IEEE Standard General Requirements for--liquid- Immersed Distribution, Power, and Regulating Transformers b. IEEE C IEEE Standard General Requirements for Dry-Type Distribution and Power Transformers Including Those with Solid Cast and/or Resin Encapsulated Windings c. ANSI/IEEE C American National Standard for Transformers--230 RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

11 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: SUBMITTALS kv and Below 833/958 through 8333/10,417 kva, Single-Phase, and 750/862 through 60,000/80,000/100,000 kva, Three-Phase without Load Tap Changing; and 3750/4687 through 60,000/80,000/100,000 kva with Load Tap Changing--Safety Requirements d. ANSI/IEEE C (R1998) American National Standard for Transformers-- Pad-Mounted, Compartmental-Type, Self-Cooled, Three- Phase Distribution Transformers with High-Voltage Bushings, 2500 kva and Smaller: High-Voltage, 34,500 GrdY/19,920 Volts and Below; Low Voltage, 480 Volts and Below Requirements e. ANSI/IEEE C IEEE Standard for Pad-Mounted, Compartmental-Type, Self-Cooled, Three-Phase Distribution Transformers for Use with Separable Insulated High-Voltage Connectors (34,500 GrdY/19,920 Volts and Below; 2500 kva and Smaller) f. ANSI/IEEE C American National Standard Pad-Mounted Equipment--Enclosed Integrity g. IEEE C IEEE Standard Terminal Markings and Connections for Distribution and Power Transformers h. IEEE C IEEE Standard Terminology for Power and Distribution Transformers i. IEEE C IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers and IEEE Guide for Short Circuit Testing of Distribution and Power Transformers j. IEEE C (R1999) IEEE Guide for Application of Transformer Connections in Three-Phase Distribution Systems k. IEEE C IEEE Guide for Liquid-Immersed Transformer Through-Fault-Current Duration l. IEEE C (R1995) IEEE Guide for Acceptance of Silicone Insulating Fluid and Its Maintenance in Transformers m. IEEE C IEEE Guide for Acceptance and Maintenance of Less Flammable Hydrocarbon Fluid in Transformers 8. ANSI/IEEE 386 Separable Insulated Connector Systems for Power Distribution Systems Above 600V 9. NFPA 70 National Electrical Code 10. Applicable NRTL standards. A. Compliance statement as described under Quality assurance section of this Specification. B. Product Data: The equipment vendor shall provide rated nameplate data, capacities, weights, dimensions, minimum clearances, installed devices and features, location of each field connection, and performance for each type and size of transformer indicated. C. Shop Drawings: The equipment vendor shall provide diagram power signal and control wiring. 1. Underground primary and secondary conduit stub-up location. 2. Dimensioned concrete base, outline of transformer, and required clearances. 3. Ground rod and grounding cable locations. RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

12 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: D. Manufacturer Seismic Qualification Certification: The equipment vendor shall submit certification that transformer assembly and components will withstand seismic forces up to seismic design category B. Include the following: 1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation. a. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified." 2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions. 3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements. E. Qualification Data: For installer, manufacturer, and testing agency. F. Source quality-control test reports. G. Field quality-control test reports. H. Follow-up service reports. I. Operation and Maintenance Data: Prepared by the equipment vendor for transformer and accessories to include in emergency, operation, and maintenance manuals. 1.9 QUALITY ASSURANCE A. Quality Certification: The transformer manufacturer shall have quality certification to ISO 9000:2000 or an equivalent Quality Management System acceptable to the Engineer. Evidence of certification shall be submitted with equipment shop drawings. B. Electrical Testing Agency Qualifications: An independent electrical testing agency, with the experience and capability to conduct the specified testing, and is a member company of the InterNational Electrical Testing Association. 1. Testing Agency's Field Supervisor: Person currently certified by the InterNational Electrical Testing Association or the National Institute for Certification in Engineering Technologies to supervise on-site testing specified in Part 3. C. Comply with IEEE C2 National Electrical Safety Code, NEC requirements, and Reference Standards listed herein. D. Compliance Statement: The Equipment Vendor shall include a Compliance Statement, at the time of Bid, listing each Specification Section stating paragraph-by-paragraph compliance with the Specification, and proposed nonconformities. Provide short description of minor nonconformities, and detailed explanation of other nonconformities. RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

13 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: COORDINATION A. The Electrical Contractor shall coordinate cable quantities, sizes, and connection requirements specified in other Sections of Division 26 with components to be provided under this Section. B. The Electrical Contractor shall coordinate size and location of concrete equipment pads with the work of other trades. Follow the transformer manufacturer s installation instructions. Set inserts into concrete formwork prior to placement of concrete, and check that inserts remain in place during placement of concrete. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Asea Brown Boveri, Ltd. 2. Eaton / Cutler-Hammer. 3. General Electric. 4. Siemens Energy & Automation, Inc. 5. Schneider Electric / Square D 6. Cooper Industries; Cooper Power Systems Division 2.2 OUTDOOR PAD-MOUNTED, LIQUID-FILLED TRANSFORMER, A. Outdoor pad-mounted liquid-filled transformer, T-1, shall have the following ratings: KVA OA V, three phase, wye, 60 Hz primary /120V, three phase, four wire, solidly grounded wye secondary 4. 2 to 5.5% impedance 5. Outdoor enclosure 6. Basic Impulse Level: 95kV BIL. B. Pad-mounted transformers shall be in compliance with IEEE C , shall have HV and LV compartments located side-by-side and separated by a steel barrier, with concealed-hinge lockable steel HV and LV compartment doors, stainless-steel tank base and cabinet, and furnished with the following: 1. Insulating Liquid: Less flammable, edible-seed-oil based, and UL listed as complying with NFPA 70 requirements for fire point of not less than 300 deg C when tested according to ASTM D 92. Liquid shall be biodegradable and nontoxic. 2. Insulation Temperature Rise: 55 deg C, based on an average ambient temperature of 30 deg C over 24 hours with a maximum ambient temperature of 40 deg C. as defined by ANSI/IEEE C RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

14 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: Transformer coils shall be copper wound on a 5-legged core of electrical grade steel with high magnetic permeability and insulated laminations. C. Full-Capacity Voltage Taps: Four nominal 2.5 percent taps, two above and two below rated primary voltage, with hot-stick operable no-load tap changer for de-energized use and with position indicator and padlock hasp, located in the HV terminal compartment. D. High-Voltage Switch: 200 A, make-and-latch rating of 10-kA RMS, symmetrical, arranged for loop feed with 3-phase, 4-position, closed transition sectionalizing type (feed-from-left, feed-from-right, isolated-from-both, through-feed-to-both), gangoperated, load-break switch that is oil immersed in transformer tank with hot-stick operating handle in primary compartment. E. Primary Fuses: Fuse assembly with fuses complying with IEEE C Bayonet style liquid-immersed weak link (overload sensing) expulsion fuses in series with liquid-immersed current limiting fuses. F. High-Voltage Terminations and Equipment: Dead front ANSI/IEEE C with universal-type bushing wells for dead-front bushing-well inserts, complying with IEEE 386 and including the following: 1. Bushing-Well Inserts: One for each high-voltage bushing well. 2. Surge Arresters: set of three dead-front, elbow-type, metal-oxide-varistor units. 3. Parking Stands: One for each high-voltage bushing well. 4. Portable Insulated Bushings: Arranged for parking insulated, high-voltage, loadbreak cable terminators; one for each primary feeder conductor terminating at transformer. G. LV connections: For cable connected secondary, provide insulated secondary bushings with tin-plated NEMA standard spade terminals to suit the incoming LV cable. H. Grounding: Provide stainless steel grounding terminal welded to the enclosure structural steel base. Provide tin-plated braided copper neutral grounding jumpers between the neutral bushing and the tank. I. Enclosure shall be heavy gauge steel, cleaned, degreased, primed, and finish-coated with two-part epoxy paint, UL-recognized outdoor green. Transformers shall have two stainless steel grounding conductor lugs welded to the enclosure. Transformers shall have lifting eyes, and provisions for jacking. Steel base and frame shall allow use of pipe rollers in any direction. Enclosure hinged door compartments shall be fitted with threepoint latching mechanism and flush lock, and two sets of keys shall be provided. HV compartment door shall be held closed by a closed LV compartment door, and shall be further secured by a recessed penthead bolt. Doors shall be latched in the fully open position by a gravity-operated rod. Non-locking externally accessible parts shall be secured with tamper-resistant hardware to prevent unauthorized entry. J. Accessories: 1. Drain Valve: 1 inch (25 mm), with sampling device. 2. Dial-type thermometer. RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

15 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: IDENTIFICATION 3. Liquid-level gauge. 4. Pressure-vacuum gauge. 5. Pressure Relief Device: Self-sealing with an indicator. 6. Busway terminal connection at low-voltage compartment. 7. Alarm contacts for gauges and thermometer listed above. 8. Sudden pressure relay, ANSI Device No Key interlock to permit opening HV compartment door only after LV compartment door is open. A. Nameplates: Engraved, laminated-plastic or metal nameplate for each transformer, mounted with corrosion-resistant screws. 2.4 SEISMIC RESTRAINTS A. Design and fabricate transformers, and anchorage devices for them, to withstand static and seismic forces in any direction. 2.5 QUALITY ASSURANCE A. Factory Tests: Perform design and routine tests according to standards specified for components. Conduct transformer tests according to IEEE C B. Factory Tests: Perform the following factory-certified tests on each transformer: 1. Resistance measurements of all windings on rated-voltage connection and on tap extreme connections. 2. Ratios on rated-voltage connection and on tap extreme connections. 3. Polarity and phase relation on rated-voltage connection. 4. No-load loss at rated voltage on rated-voltage connection. 5. Excitation current at rated voltage on rated-voltage connection. 6. Impedance and load loss at rated current on rated-voltage connection and on tap extreme connections. 7. Applied potential. 8. Induced potential. 9. The Owner retains the right to witness all required factory tests. Notify Engineer of the scheduled date and duration of factory tests. 2.6 SPARE PARTS AND SPECIAL TOOLS A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Fuses: Six of each type and rating for this project. 2. Plug-in lightning arresters: 3 of each type and rating for this project. 3. Plug-in cable termination elbows: 3 of each type and rating for this project. Elbows on line side sized for #2 AWG, 15kV, copper cables. RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

16 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: Touchup Paint: Three containers of paint matching enclosure finish, each 0.5 pint (250 ml). B. Maintenance Tools: Furnish tools and miscellaneous items required for interrupter switchgear test, inspection, maintenance, and operation. Include the following: PART 3 - EXECUTION 3.1 EXAMINATION 1. Hot stick suitable for primary voltage with the following accessories: a. Hook attachment to operate load tap changer b. Neon glow tube attachment to indicate energized cable c. Hook attachment to plug in and unplug separable connectors d. One pair of insulating rubber gloves suitable for primary voltage e. Ten sets of cotton liners for the insulating rubber gloves f. One pair of leather outer gloves to protect the rubber gloves g. One pair of insulating rubber boots suitable for primary voltage h. Ten sets of cotton liners for the insulating rubber boots A. The Electrical Contractor shall examine areas and conditions for compliance with requirements for medium-voltage transformers. B. The Electrical Contractor shall examine roughing-in of conduits and grounding systems to verify the following: 1. Wiring entries comply with layout requirements. 2. Entries are within conduit-entry tolerances specified by manufacturer and no feeders will have to cross section barriers to reach load or line lugs. C. The Electrical Contractor shall examine walls, floors, roofs, and concrete equipment pads for suitable mounting conditions where transformers will be installed. D. The Electrical Contractor shall verify that ground connections are in place. Maximum ground resistance shall be 5 ohms at transformer. E. The Electrical Contractor shall proceed with installation only after unsatisfactory conditions have been corrected. 3.2 DELIVERY, STORAGE, AND HANDLING A. The Equipment Vendor shall deliver, store, and handle the transformer and accessories in accordance with manufacturer s instructions. B. The Equipment Vendor is responsible for all shipping and insurance costs to the jobsite. RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

17 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: INSTALLATION A. The Electrical Contractor shall install transformers on concrete equipment pads. 1. Anchor transformers to concrete equipment pads according to manufacturer's written instructions, and according to seismic design category B. 2. Construct concrete equipment pads of dimensions 7 feet by 7 feet and minimum 6 inches (150 mm) thick outdoors. 3. Use 3000-psi (20.7-MPa), 28-day compressive-strength concrete and reinforcement. 4. Place and secure anchorage devices. Use supported equipment manufacturer's setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded. 5. Tack-weld or bolt transformers to channel-iron sills embedded in concrete equipment pads. Install sills level and grout flush with floor or base. B. Maintain minimum clearances and workspace at equipment according to manufacturer's written instructions and the NEC. 3.4 IDENTIFICATION A. The Electrical Contractor is responsible for identifying field-installed wiring and components and providing warning signs. 3.5 CONNECTIONS A. The Electrical Contractor shall ground equipment according to Equipment Manufacturer s recommendation. B. The Electrical Contractor shall connect wiring according to Equipment Manufacturer s recommendation. C. The Electrical Contractor shall tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B. 3.6 FIELD QUALITY CONTROL A. Manufacturer's Field Service: The Equipment Manufacturer shall engage a factoryauthorized service representative to inspect field-assembled components and equipment installation, including connections, and to assist in field testing. Report results in writing. 3.7 FOLLOW-UP SERVICE A. Voltage Monitoring and Adjusting: The Electrical Contractor shall perform the following voltage monitoring immediately prior to Substantial Completion: RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

18 UNIVERSITY OF SOUTHERN MAINE CHP GORHAM BOILER REPLACEMENT PROJECT #: Perform seven days of three-phase voltage recording at the secondary terminals of each transformer. Use voltmeters with calibration traceable to National Institute of Science and Technology standards and with a chart speed that is capable of showing voltage excursions lasting one minute or longer. Voltage unbalance greater than 1 percent between phases, or deviation of any phase voltage from nominal value by more than plus or minus 5 percent during test period, is not acceptable. 2. Corrective Actions: If test results are unacceptable, perform the following corrective actions, as appropriate: a. Adjust transformer taps. b. Prepare written request for voltage adjustment by electric utility. 3. Retests: After corrective actions have been performed, repeat monitoring until satisfactory results are obtained. 4. Report: Prepare written report covering monitoring and corrective actions performed. B. Thermographic Survey (Infra-Red Scan): After Substantial Completion, but not less than 1 month or more than six months after Final Acceptance, the Electrical Contractor shall perform the following thermograhic survey: 1. Perform as specified NETA Section 9 Thermographic Survey. Remove front and rear panels so joints and connections are accessible to portable scanner. 2. Instrument: Use an infrared scanning device designed to measure temperature or to detect significant deviations from normal values. Provide calibration record for device. 3. Record of Infrared Scanning: Prepare a certified report that identifies switchgear checked and that describes scanning results. 4. Corrective Action: If test results are unacceptable, perform the following corrective action, as appropriate: a. Re-torque connections. b. Replace cable lugs. c. Inform manufacturer of the problem. 5. Retests: Repeat monitoring, after corrective action has been performed, until satisfactory results are obtained. 6. Report: Prepare a written report covering monitoring performed and corrective action taken. END OF SECTION RMF PROJECT NO.: A PRE-PURCHASE DOCUMENTS FEBRUARY 2718, 2013

19 SECTION FIVE 5.0 PROPOSAL FORM: Vendors shall ensure that all information required herein is submitted with the proposal. All information provided should be verifiable by documentation requested by the University. Failure to provide all information, inaccuracy or misstatement may be sufficient cause for rejection of the proposal or rescission of an award. Vendors are encouraged to provide any additional information describing operational abilities. Responses to each requirement below should be in order and clearly marked with the section number to which they respond. 5.1 Equipment: All equipment offered and priced below shall meet or exceed the specifications shown in Section Four above. 5.2 Pricing: As described in paragraph 2.1 above, the University is seeking proposals for Transformer pre-purchase. 5.3 Having carefully examined the specifications contained therein for the Transformer, we the undersigned propose to furnish and deliver to the site and unload, the transformer, equipment and materials necessary for and reasonably incidental to the delivery of this contract for the sum of Dollars ($ ) (written dollars) This proposal must be accompanied by a copy of the appropriate certifications and proposal submittals as delineated in the specifications.

20 SIGNATURE PAGE COMPANY NAME: B y: (Signature) (Print Name) (Title) (Phone) (Cell Phone) ( Address) (Date)

SECTION MEDIUM VOLTAGE TRANSFORMERS

SECTION MEDIUM VOLTAGE TRANSFORMERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 1200 - MEDIUM-VOLTAGE TRANSFORMERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

A. This Section includes the following types of dry-type transformers rated 600 V and less, with capacities up to 1000 kva:

A. This Section includes the following types of dry-type transformers rated 600 V and less, with capacities up to 1000 kva: SECTION 16461 - LOW-VOLTAGE TRANSFORMERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES SECTION 262500 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

B. Provide liquid-filled secondary substation transformers as indicated on drawings.

B. Provide liquid-filled secondary substation transformers as indicated on drawings. SECTION 26 12 13 PART 1 - GENERAL 1.01 WORK INCLUDED A. Comply with the provisions of Sections 26 05 00. B. Provide liquid-filled secondary substation transformers as indicated on drawings. 1.02 RELATED

More information

SECTION SECONDARY UNIT SUBSTATIONS

SECTION SECONDARY UNIT SUBSTATIONS SECTION 26 12 16 SECONDARY UNIT SUBSTATIONS PART 1 GENERAL 1.1 SUMMARY This section describes metal-clad, indoor or outdoor, secondary unit substations with integral primary fused disconnect switches,

More information

1 29SEP03 ALL General update with miscellaneous changes in entire document.

1 29SEP03 ALL General update with miscellaneous changes in entire document. REVISION RECORD SECTION 16461 Dry-Type Transformers (600 V and Less) REV DATE PAGE PARA NO. DESCRIPTION APPROVED BY 28SEP01 ALL Initial issue. 1 29SEP03 ALL General update with miscellaneous changes in

More information

Administered by UNIVERSITY OF MAINE SYSTEM Office of Strategic Procurement REQUEST FOR BIDS VEHICLE BID UNIVERSITY OF MAINE AT AUGUSTA RFB # 30-10

Administered by UNIVERSITY OF MAINE SYSTEM Office of Strategic Procurement REQUEST FOR BIDS VEHICLE BID UNIVERSITY OF MAINE AT AUGUSTA RFB # 30-10 Administered by UNIVERSITY OF MAINE SYSTEM REQUEST FOR BIDS VEHICLE BID UNIVERSITY OF MAINE AT AUGUSTA RFB # 30-10 ISSUE DATE: May 21, 2010 BIDS MUST BE RECEIVED BY: Friday, June 4, 2010 2:00 pm DELIVER

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

Houston First Corporation Package 1 SECTION MEDIUM VOLTAGE FUSED SWITCH INTERRUPTER

Houston First Corporation Package 1 SECTION MEDIUM VOLTAGE FUSED SWITCH INTERRUPTER PART 1 - GENERAL 1.1 SUMMARY SECTION 26 13 16 MEDIUM VOLTAGE FUSED SWITCH INTERRUPTER A. The scope of this section includes providing and assembling materials and equipment for the dead-front, medium voltage

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS. Use for Southeast projects only **************************************************************************

UNIFIED FACILITIES GUIDE SPECIFICATIONS. Use for Southeast projects only ************************************************************************** USACE / NAVFAC / AFCESA / NASA UFGS-26 13 00.00 25 (July 2006) ------------------------------- Preparing Activity: NAVFAC Superseding Southeast UFGS-S-16345N (March 2001) Use in lieu of UFGS-26 13 00.00

More information

SECTION SECONDARY UNIT SUBSTATIONS SECONDARY LESS THAN 1000 V

SECTION SECONDARY UNIT SUBSTATIONS SECONDARY LESS THAN 1000 V SECONDARY UNIT SUBSTATIONS SECONDARY LESS THAN 1000 V PART 1 GENERAL 1.01 1.02 SCOPE The Contractor shall furnish and install the secondary unit substation(s) complete from the incoming line terminals

More information

SERIES 800 / 810 SPECIFICATION 15KV & 25KV PADMOUNTED LIQUID-INSULATED VACUUM LOAD INTERRUPTER ASSEMBLIES

SERIES 800 / 810 SPECIFICATION 15KV & 25KV PADMOUNTED LIQUID-INSULATED VACUUM LOAD INTERRUPTER ASSEMBLIES SERIES 800 / 810 SPECIFICATION 15KV & 25KV PADMOUNTED LIQUID-INSULATED VACUUM LOAD INTERRUPTER ASSEMBLIES MANUALLY OPERATED / REMOTELY OPERATED DEAD FRONT PADMOUNTED SWITCHGEAR WITH VACUUM LOAD INTERRUPTING

More information

SECTION BUSWAYS

SECTION BUSWAYS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 25 11 BUSWAYS SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable to the section and

More information

SECTION SECONDARY UNIT SUBSTATIONS

SECTION SECONDARY UNIT SUBSTATIONS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 11 16 SECONDARY UNIT SUBSTATIONS SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable

More information

SECTION LOW-VOLTAGE TRANSFORMERS

SECTION LOW-VOLTAGE TRANSFORMERS PART 1 GENERAL 1.1 DESCRIPTION SECTION 26 22 00 SPEC WRITER NOTE: Use this section only for NCA projects. Delete between // // if not applicable to project. Also, delete any other item or paragraph not

More information

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS SINGLE-PHASE PADMOUNTED TRANSFORMERS

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS SINGLE-PHASE PADMOUNTED TRANSFORMERS CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS SINGLE-PHASE PADMOUNTED TRANSFORMERS Original Issue 1/84 Revised 1/91 Revised 6/02 Revised 11/05 Revised 11/09 Revised 1/12 Revised 11/12 Revised 5/14 Revised

More information

A. Section includes busway and fittings including plug-in units.

A. Section includes busway and fittings including plug-in units. SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:

More information

PRIMARY UNIT SUBSTATIONS SECONDARY 1000 V AND ABOVE SECTION SECTION

PRIMARY UNIT SUBSTATIONS SECONDARY 1000 V AND ABOVE SECTION SECTION PRIMARY UNIT SUBSTATIONS SECONDARY 1000 V AND ABOVE PART 1 GENERAL 1.01 SCOPE A. The Contractor shall furnish and install the primary unit substation(s) complete from the incoming line terminals to the

More information

SECTION METAL-ENCLOSED BUS MEDIUM VOLTAGE

SECTION METAL-ENCLOSED BUS MEDIUM VOLTAGE METAL-ENCLOSED BUS MEDIUM VOLTAGE PART 1 GENERAL 1.01 1.02 1.03 1.04 1.05 SCOPE The Contractor shall furnish and install the equipment as specified herein and as shown on the contract drawings. The medium

More information

SECTION to 5000 AMPERE PLUG-IN AND FEEDER BUSWAYS - SPECTRA. A. Low-Voltage Plug-in Busway to 5000 ampere, 600 VAC

SECTION to 5000 AMPERE PLUG-IN AND FEEDER BUSWAYS - SPECTRA. A. Low-Voltage Plug-in Busway to 5000 ampere, 600 VAC PART 1 GENERAL A. The requirements of the Contract, Division 1, and Division 16 apply to work in this Section. 1.01 SECTION INCLUDES A. Low-Voltage Plug-in Busway - 225 to 5000 ampere, 600 VAC 1.02 RELATED

More information

BUSWAY LOW VOLTAGE (POW-R-WAY III) SECTION SECTION 16466

BUSWAY LOW VOLTAGE (POW-R-WAY III) SECTION SECTION 16466 BUSWAY LOW VOLTAGE (POW-R-WAY III) PART 1 GENERAL 1.01 1.02 SCOPE The Contractor shall furnish and install the busway system including all necessary fittings, hangers and accessories as specified herein

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-26 13 01 (August 2013) --------------------------- Preparing Activity: NAVFAC NEW UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated

More information

SECTION MOTOR CONTROL CENTER

SECTION MOTOR CONTROL CENTER SECTION 16445 MOTOR CONTROL CENTER PART 1 GENERAL 1.01 DESCRIPTION A. This section covers the contract item Motor Control Center (MCC). The contract item includes demolition and removal of existing MCC;

More information

TOWN OF LABRADOR CITY FORM OF TENDER TLC SUPPLY & INSTALLATION OF CONCRETE FLOOR

TOWN OF LABRADOR CITY FORM OF TENDER TLC SUPPLY & INSTALLATION OF CONCRETE FLOOR TOWN OF LABRADOR CITY FORM OF TENDER TLC-04-18 SUPPLY & INSTALLATION OF CONCRETE FLOOR Tenderer Address Telephone # The undersigned bidder has carefully examined the Form of Tender, Instructions to Bidders,

More information

SECTION SUBSTATION BUS ASSEMBLIES ERGLE SUBSTATION

SECTION SUBSTATION BUS ASSEMBLIES ERGLE SUBSTATION SECTION 16-372 SUBSTATION BUS ASSEMBLIES ERGLE SUBSTATION 1. GENERAL SPECIFICATIONS The work of this Section includes furnishing all labor, equipment, materials (unless specifically identified as Owner-furnished)

More information

ADDENDUM NO. 1 BID AND CONTRACT DOCUMENTS FOR. BID No. 2019PW299

ADDENDUM NO. 1 BID AND CONTRACT DOCUMENTS FOR. BID No. 2019PW299 ADDENDUM NO. 1 BID AND CONTRACT DOCUMENTS FOR BID No. 2019PW299 CHAFFEY COMMUNITY COLLEGE DISTRICT TRANSFORMER REPLACEMENT PROJECT RANCHO CUCAMONGA, CALIFORNIA COUNTY OF SAN BERNARDINO CHAFFEY COMMUNITY

More information

SECTION PARK NON-SEGREGATED BUS SPECIFICATION

SECTION PARK NON-SEGREGATED BUS SPECIFICATION Page 1 of 5 SECTION ------- PARK NON-SEGREGATED BUS SPECIFICATION 1.0 SCOPE 1.1. This specification describes assemblies of 600V, 5Kv and 15Kv non-segregated bus duct, which will be installed indoors and

More information

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number PART 1 GENERAL 01 02 03 04 SCOPE Furnish and install Manual Transfer Switches (MTS) and

More information

A&E Standards Electrical Substations & Transformers Division 26 Electrical

A&E Standards Electrical Substations & Transformers Division 26 Electrical A&E Standards Electrical Substations & Transformers Division 26 Electrical Version 3.0 SEP Subgroup 4.4 December 2017 PREFACE PURPOSE OF THIS DOCUMENT The intent of this document is to disseminate the

More information

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein.

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein. 16470 PANELBOARDS ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 26 24 16 An optional keynote to

More information

SECTION CONVECTORS

SECTION CONVECTORS SECTION 23 82 33 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph

More information

SECTION GROUNDING

SECTION GROUNDING SECTION 16450 GROUNDING PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies general grounding and bonding requirements of electrical and telecommunication installations for personnel safety, equipment

More information

SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard

SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard PART 1 GENERAL 1.1 Scope A. The intent of this specification is to provide power control for the parallel operation of generator

More information

Capital Projects Group Liquid Filled Transformer Specification

Capital Projects Group Liquid Filled Transformer Specification Capital Projects Group Specification Specification 26 12 13 Revision 0 Date: August 2018 Specification Specification 26 12 13 Publication Date: August 2018 COPYRIGHT 2018 Metrolinx, an Agency of the Government

More information

56-SDMS-01 REV. 01 SPECIFICATIONS FOR

56-SDMS-01 REV. 01 SPECIFICATIONS FOR 56-SDMS-01 REV. 01 SPECIFICATIONS FOR 13.8KV UNIT SUBSTATIONS This specification is property of SEC and subject to change or modification without any notice CONTENTS PAGE No. 1.0 SCOPE 3 2.0 CROSS REFERENCES

More information

LEVEL 2 Application For Interconnection And Net Metering

LEVEL 2 Application For Interconnection And Net Metering LEVEL 2 Application For Interconnection And Net Metering Use this Application form when generating facility is not inverter-based or is not certified by a nationally recognized testing laboratory to meet

More information

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 05 26 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph

More information

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202 Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 October 26, 2017 ADDENDUM NUMBER: ONE (1) TITLE: Arc-Resistant Metal-Clad Switchgear

More information

Standard of Practice - Campus Electrical Distribution System

Standard of Practice - Campus Electrical Distribution System A26.3 Standard of Practice - Campus Electrical Distribution System NOTE: Significant revisions or additions to the previous standards are highlighted in italics. GENERAL Designers shall verify that all

More information

FIELD TEST AND OPERATIONAL CHECK SECTION A. Refer to Section 16010, Electrical General Requirements.

FIELD TEST AND OPERATIONAL CHECK SECTION A. Refer to Section 16010, Electrical General Requirements. FIELD TEST AND OPERATIONAL CHECK SECTION 16080 PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. Refer to Section 16010, Electrical General Requirements. 1.2 WORK INCLUDED A. General Scope: 1. The Contractor

More information

A. The work consists of furnishing a Chiller Noise Reduction System as listed in the specifications.

A. The work consists of furnishing a Chiller Noise Reduction System as listed in the specifications. SECTION 32 31 14 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply

More information

Request for Proposal Maintenance 30X50 Storage Building Located West of Maintenance Office 902 West Trimble Berryville School District 27

Request for Proposal Maintenance 30X50 Storage Building Located West of Maintenance Office 902 West Trimble Berryville School District 27 Page 1 of 5 Request for Proposal 2014.11.01 Maintenance 30X50 Storage Building Located West of Maintenance Office 902 West Trimble Berryville School District 27 Notice to prospective venders: The Berryville

More information

16300 HIGH VOLTAGE DISTRIBUTION

16300 HIGH VOLTAGE DISTRIBUTION 16300 HIGH VOLTAGE DISTRIBUTION PART 1: GENERAL 1.01 WORK INCLUDED A. Most new loads will be served from the underground electric distribution system. This system is a primary open loop configuration served

More information

SECTION ELECTRIC FOUR FOLD DOORS MODEL 46 FLAT SHEETED

SECTION ELECTRIC FOUR FOLD DOORS MODEL 46 FLAT SHEETED SECTION 08350 ELECTRIC FOUR FOLD DOORS MODEL 46 FLAT SHEETED PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

REQUEST FOR BID. PURCHASE AND INSTALL OF 3 GATE OPERATORS AND GATES FOR THE NORTHWEST ARKANSAS REGIONAL AIRPORT February 18, 2019

REQUEST FOR BID. PURCHASE AND INSTALL OF 3 GATE OPERATORS AND GATES FOR THE NORTHWEST ARKANSAS REGIONAL AIRPORT February 18, 2019 REQUEST FOR BID PURCHASE AND INSTALL OF 3 GATE OPERATORS AND GATES FOR THE NORTHWEST ARKANSAS REGIONAL AIRPORT February 18, 2019 1. INTRODUCTION The Northwest Arkansas Regional Airport is seeking bids

More information

SECTION LOW-VOLTAGE SWITCHGEAR

SECTION LOW-VOLTAGE SWITCHGEAR PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 23 00 LOW-VOLTAGE SWITCHGEAR SPEC WRITER NOTE: This specification is not for general use. Use Section 26 24 13, DISTRIBUTION SWITCHBOARDS for most applications.

More information

SECTION PART 1 GENERAL

SECTION PART 1 GENERAL SECTION 16060 GROUNDING AND BONDING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Grounding of electrical systems and equipment and basic requirements for ground for equipment, circuits, and systems.

More information

Point Eight Power, Inc. Switchgear Specification Low Voltage UL 1558 Metal-Enclosed Switchgear

Point Eight Power, Inc. Switchgear Specification Low Voltage UL 1558 Metal-Enclosed Switchgear Table of Content 1.0 General... 2 2.0 Scope... 2 3.0 Applicable Codes, Standards and Qualifications... 2 4.0 Service and Environmental Conditions... 3 5.0 Construction... 3 6.0 Front Breaker Compartment

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-33 77 19.00 40 (August 2016) --------------------------------- Preparing Activity: NASA Superseding UFGS-33 77 19.00 40 (August 2013) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

SECTION The specification section is organized by placing information in three standard parts:

SECTION The specification section is organized by placing information in three standard parts: SECTION 14244 LIMITED USE HYDRAULIC ELEVATOR ***** Since 1982 Liftavator, Inc. has provided limited use/limited application (LU/LA) elevators, residential elevators, hydraulic vertical platform wheelchair

More information

SECTION HEAT TRACING FOR PLUMBING PIPING

SECTION HEAT TRACING FOR PLUMBING PIPING SECTION 22 05 33 SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable in the section

More information

31-SDMS-03 REV. 01 SPECIFICATIONS FOR

31-SDMS-03 REV. 01 SPECIFICATIONS FOR 31-SDMS-03 REV. 01 SPECIFICATIONS FOR LOW VOLTAGE CABINET FOR POLE MOUNTED TRANSFORMER This specification is property of SEC and subject to change or modification without any notice CONTENTS Clause Description

More information

DISTRIBUTION TRANSFORMER SPECIFICATION #

DISTRIBUTION TRANSFORMER SPECIFICATION # DISTRIBUTION TRANSFORMER SPECIFICATION #1212.03 15kV Single Phase Submersible Transformer Stainless Steel 12/2/2011 Page 1 of 8 1. SCOPE This specification covers single-phase submersible transformers

More information

Bus Facility

Bus Facility SECTION 32 31 13.53 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

C o u n t y o f F a i r f a x, V i r g i n i a

C o u n t y o f F a i r f a x, V i r g i n i a 001961 Page 2 C o u n t y o f F a i r f a x, V i r g i n i a A D D E N D U M DATE: August 2, 2016 ADDENDUM NO. 4 TO: REFERENCE: FOR: DUE DATE/TIME: ALL PROSPECTIVE BIDDERS Government Center Generator System

More information

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue Bidding Conditions March 22, 2018 (Project# 0192) at the Fresno Chaffee Zoo Project : Warthog Exhibit Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS Addendum - A document issued

More information

Important Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008

Important Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008 Important Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008 (Above 1000V and up to 38kV for Surface Mining) Key Components of Specification:

More information

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1 INDEX Page SECTION 1.0: SCOPE 1 1.1 Toronto Hydro Requirements 1 1.2 Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1 SECTION 3.0: DEFINITIONS AND THE INTERNATIONAL SYSTEM OF UNITS 1 3.1 Definitions

More information

OPERATING PROCEDURE NO. 310

OPERATING PROCEDURE NO. 310 OPERATING PROCEDURE NO. 310 Related Operating Procedures: 310A; 310B; 310C; 310D SUBJECT: Conditions of Service Issued: February 10, 2014 Revised: March 28, 2016 OBJECTIVE: To establish the rules, regulations

More information

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS SECTION 26 05 26 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Medium Voltage Switchgear. Basis of Design.

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Medium Voltage Switchgear. Basis of Design. Basis of Design This section applies to the design and selection of medium voltage switchgear, primarily for use in substations. Design Criteria 13.8kV equipment shall be 15kV class, 4.16kV and 2.4kV equipment

More information

SECTION HEAT TRACING FOR PLUMBING PIPING

SECTION HEAT TRACING FOR PLUMBING PIPING SECTION 22 05 33 HEAT TRACING FOR PLUMBING PIPING PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Delete between //----// if not applicable to project. Also delete any other item or paragraph not

More information

Ground Fault Protection. Medium Voltage Artificial Neutrals

Ground Fault Protection. Medium Voltage Artificial Neutrals Ground Fault Protection Medium Voltage Artificial Neutrals Installation and Maintenance Instruction Manual 7615 Kimbel Street, Mississauga, Ontario Canada L5S 1A8 Tel: (905)673-1553 Fax: (905)673-8472

More information

CONTENTS. B. System Design and Performance Requirements

CONTENTS. B. System Design and Performance Requirements 16060 Grounding and Bonding This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or

More information

SECTION BASIC ELECTRICAL REQUIREMENTS

SECTION BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions, apply to work of this section. 1.2 SUMMARY A. This section specifies

More information

ENGINEERING SPECIFICATION

ENGINEERING SPECIFICATION ENGINEERING SPECIFICATION No. Page 1 CATEGORY: TRANSFORMERS DATE: 11/16/2006 Subject: TABLE OF CONTENTS PURPOSE...2 SCOPE...2 REFERENCES...2 DEFINITIONS...2 SPECIFICATION...2 General... 2 High Voltage

More information

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION SPECIFICATION EO- 4035 REVISION 12 OCTOBER, 2006 OPERATION AND MAINTENANCE

More information

SECTION GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT

SECTION GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT SECTION 23 05 12 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Delete between // // if not applicable to project. Also delete

More information

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS 23 HEATING, VENTILATING AND AIR CONDITIONING TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING - Basic HVAC Requirements 238239.19 - Wall and Ceiling Unit Heaters

More information

N-SERIES: NTH2700 SPECIFICATIONS Tubular Composite Top Hung Sliding Door System

N-SERIES: NTH2700 SPECIFICATIONS Tubular Composite Top Hung Sliding Door System Version 5.22.13 N-SERIES: NTH2700 SPECIFICATIONS Tubular Composite Top Hung Sliding Door System OPTIONS ARE LISTED IN BOLD, PLEASE MODIFY THESE AREAS AS NEEDED BASED ON YOUR PROJECT CONSULT MANUFACTURER

More information

Bidding Conditions Attachment C

Bidding Conditions Attachment C Bidding Conditions Attachment C REV Date: November 9, 2018 Project Name (Permit Nos. xxx) at the Fresno Chaffee Zoo Project No. xxxx Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS

More information

Request for Proposal Robstown Independent School District ERate

Request for Proposal Robstown Independent School District ERate Request for Proposal Robstown Independent School District ERate 2016 2017 Wireless Upgrades at Three Campuses, Local and Long Distance Phone Service, and POTS Lines Bid Due Date: February 23, 2016 at 5:00

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS CONTENTS I. Bid Documents II. Ethical Business Practices III. Contractor Qualifications IV. Performance and Quality Standards V. Bid Evaluation VI. Contract Award VII. Work Operations

More information

Recycling/Roll-off bins/containers for the Solid Waste Division of the Boone County Fiscal Court

Recycling/Roll-off bins/containers for the Solid Waste Division of the Boone County Fiscal Court Boone County, Kentucky Bid #: 120816SW Recycling/Roll-off bins/containers for the Solid Waste Division of the Boone County Fiscal Court ACCEPTANCE DATE: Prior to 2:00 p.m., December 8, 2016 Local time

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 22 0548 - PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

37-SDMS-01 REV. 03 SPECIFICATIONS FOR

37-SDMS-01 REV. 03 SPECIFICATIONS FOR 37-SDMS-01 REV. 03 SPECIFICATIONS FOR LOW VOLTAGE MOLDED CASE CIRCUIT BREAKERS FOR SERVICE CONNECTIONS This specification is property of SEC and subject to change or modification without any notice CLAUSE

More information

TABLE OF CONTENTS. FOREWORD... Error! Bookmark not defined. INTRODUCTION SCOPE NORMATIVE REFERENCES DRAWING...4

TABLE OF CONTENTS. FOREWORD... Error! Bookmark not defined. INTRODUCTION SCOPE NORMATIVE REFERENCES DRAWING...4 TITLE SPECIFICATION FOR FREE- STANDING 11 DATE: AUGUST 2006 PAGE: 1 OF 15 TABLE OF CONTENTS Page FOREWORD... Error! Bookmark not defined. INTRODUCTION...3 1 SCOPE...3 2 NORMATIVE S...3 3 DRAWING...4 4

More information

S. C. Electric Cooperative s Specification for a Single-Phase, Two Bushing Overhead Distribution Transformer (Revised 10/2013)

S. C. Electric Cooperative s Specification for a Single-Phase, Two Bushing Overhead Distribution Transformer (Revised 10/2013) S. C. Electric Cooperative s Specification for a Single-Phase, Two Bushing Overhead Distribution Transformer (Revised 10/2013) 1.0 GENERAL 1.1 This specification covers the electrical and mechanical characteristics

More information

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS SECTION 270536 - CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1- GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 48-05 Van Dam Street Long Island City, NY 11101 ELECTRIC METER SHOP DEPARTMENT METER ENGINEERING SPECIFICATION MES-350 REVISION 3 June 2016 EFFECTIVE DATE

More information

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number: SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract apply to this Section. 1.2 SUMMARY A. This Section

More information

SECTION REQUIREMENTS FOR ELECTRICAL INSTALLATIONS

SECTION REQUIREMENTS FOR ELECTRICAL INSTALLATIONS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 11 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS SPEC WRITER NOTE: Delete between // // if not applicable to project. Also delete any other item or paragraph

More information

SECTION EXTERIOR ATHLETIC LIGHTING

SECTION EXTERIOR ATHLETIC LIGHTING PART 1 GENERAL 1.1 SECTION INCLUDES A. Sports luminaries and accessories B. Poles 1.2 REFERENCES SECTION 26 58 68 EXTERIOR ATHLETIC LIGHTING A. ANSI C78.379 - Classification of Beam Patterns of Reflector

More information

ANSI/ ASME HST Performance Standard For Overhead Electric Wire Rope Hoists

ANSI/ ASME HST Performance Standard For Overhead Electric Wire Rope Hoists SECTION 412213- BRIDGE CRANES Part 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

33-SDMS-02 SPECIFICATIONS FOR

33-SDMS-02 SPECIFICATIONS FOR SPECIFICATIONS FOR MV AUTOMATIC LINE SECTIONLIZER UP TO 36 KV This specification is property of SEC and subject to change or modification without any notice TABLE OF CONTENTS SECTION T I T L E PAGE NO.

More information

SECTIONAL OVERHEAD DOORS SECTION SECTIONAL OVERHEAD DOORS PART 1 GENERAL

SECTIONAL OVERHEAD DOORS SECTION SECTIONAL OVERHEAD DOORS PART 1 GENERAL 13686.00 SECTIONAL OVERHEAD DOORS 083613-1 1.1 RELATED DOCUMENTS SECTION 083613 - SECTIONAL OVERHEAD DOORS PART 1 GENERAL A. Drawings and general provisions of Contract, including General and Supplementary

More information

INVITATION TO BID CITY OF HOPKINSVILLE

INVITATION TO BID CITY OF HOPKINSVILLE INVITATION TO BID CITY OF HOPKINSVILLE Office of the Procurement Specialist 715 South Virginia Street P. O. Box 707 Hopkinsville, Kentucky 42241-0707 TITLE: DESIGN BUILD BUIDLING FOR THE CITY OF HOPKINSVILLE,

More information

Automated Cantilevered Aluminum Sliding Gate

Automated Cantilevered Aluminum Sliding Gate Town of Derry, New Hampshire REQUEST FOR PROPOSALS B18-128 January 25, 2018 The Town of Derry - Department of Public Works is seeking proposals for: Automated Cantilevered Aluminum Sliding Gate Introduction

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB #

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # SECTION 26 0529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

FENCING AND FENCE REPAIR

FENCING AND FENCE REPAIR INVITATION FOR BIDS FOR FENCING AND FENCE REPAIR As Requested by THE SOUTHERN SANDOVAL COUNTY ARROYO FLOOD CONTROL AUTHORITY IFB No. 2018-04 BID DUE DATE: August 8, 2018 TABLE OF CONTENTS Submission Instructions

More information

SECTION A. NEC Compliance: Comply with NEC as applicable to installation and construction of electrical power/distribution transformers.

SECTION A. NEC Compliance: Comply with NEC as applicable to installation and construction of electrical power/distribution transformers. N 16461 DRY TYPE TRANSFORMERS PART 1 - GENERAL 1.01 WORK INCLUDED: A. Copper-wound transformer optimized for light loading, meeting US Department of Energy proposed Candidate Standard Level (CSL) 3 efficiency,

More information

SECTION (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS SECTION 26 05 48 (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.01 SUMMARY A. This Section includes seismic restraints and other earthquake-damage-reduction measures for

More information

SECTION MANUAL FOUR FOLD DOORS MODEL 38 DECORATIVE PANEL DESIGN

SECTION MANUAL FOUR FOLD DOORS MODEL 38 DECORATIVE PANEL DESIGN SECTION 08350 MANUAL FOUR FOLD DOORS MODEL 38 DECORATIVE PANEL DESIGN PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

SECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT

SECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT Page 220548-1 SECTION 220548 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

BID PROPOSAL CONTRACT NO. AOPC

BID PROPOSAL CONTRACT NO. AOPC BID PROPOSAL CONTRACT NO. AOPC 201801.2 BID PROPOSAL INDEX PAGE NO. GENERAL INFMATION 2 BASE BIDS 3 BIDDER GANIZATION INFMATION 4 CERTIFICATION AND BID SIGNATURE 5 NOTE: Please read all pages of this Bid

More information

A. Basket Cable Tray: A fabricated structure consisting of wire mesh bottom and side rails.

A. Basket Cable Tray: A fabricated structure consisting of wire mesh bottom and side rails. SECTION 16714 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

1. Telecommunications mounting elements. 2. Backboards. 3. Telecommunications equipment racks and cabinets. 4. Grounding.

1. Telecommunications mounting elements. 2. Backboards. 3. Telecommunications equipment racks and cabinets. 4. Grounding. ALLIANT ENERGY CENTER PAVILIONS Project No. 2013 027 SECTION 27 11 00 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information