1 WPAFB Hospital Renovation Gateway III Matt White Walsh/Butt JV Jeremy Cobb - USACE US Army Corps of Engineers
2 Overview Scope Phasing Issues/Challenges Questions Topics 2
3 Medical Center Overview The current 786k sf Medical Center was built in 1956 with an addition in Serves approximately 58,000 beneficiaries. Active Duty, Dependents, Retirees Parts of the facility have been upgraded within the last five years to bring outpatient clinical areas and inpatient ward infrastructure up to modern clinical standards. The majority of the Medical Center still required modernization. 3
4 Project Overview Renovation of the Wright Patterson Medical Center, (building 830). The project also includes infrastructure upgrades to the Central Utility Plant, re-roofing and upgrades, and a small landscape/green space dining area. Scope Renovate SF: 258,890 SF of 786,000 SF Electrical Distribution System Replacement AHU Replacement/Upgrades
5 Organizations WPAFB 88 th Medical Group WPAFB 88 th Civil Engineer Directorate Air Force Civil Engineer Center HQ Air Force/Surgeon General Defense Health Agency (DHA) US Army Corps of Engineers, Louisville District Walsh/Butt Joint Venture (Contractor) HKS Inc. (Designer of Record) 5
6 Contract Overview Swing Space-Design Build (Separate Contract) Start: 17 Jun 11 Completion: 28 Nov 11 Primary Construction-Design/Bid/Build Start: 25 Oct 11 Completion: 09 Dec 14 Contract Duration: 1,141 days $90,000,000 +/- 6
7 Construction Safety Review Over 400,000 Man Hours Over 2,000 equipment-hours to date Over 900 New Employee Orientations Zero lost-time accidents Two Full-Time On-Site Safety Professionals Safety Applies to Tradesmen but also Patients, Staff, Visitors Every Action has the potential to Impact the Mission 7
8 Major Renovation Areas Surgery ICU Central Sterile Kitchen Education and Training Resource Management Mental Health Gastro Residency On Call Sleep Lab Medical Command Education and Train. Call Center Radiology/Mammo Orthopedics Perinatal ENT/Audio Opt./Opth. General Surgery Laser Eye
9 Minor Renovation Areas Medical Clinics (3 Clinics) Dental Women s Health Chapel Urology Housekeeping Nutritional Medicine
10 Project Footprint/Phasing Jan 2012 Jun 2013 Dec 2014 Progress: 3rd Floor 4th Floor 5th Floor Basement 1st Floor 2nd Floor
11 Completed Project Footprint
12 Challenges Infection Control Outages Surgery Phase I and II Central Sterile Temp Trailer Food Service Trailers Medical Equipment
13 Infection Control Risk Assessment Type of Work Temporary Partitions Sealing of Existing Establish Negative Air Pressures in Renovation Spaces Maintenance/Monitor/Report
14 Planned/Scheduled Outages Over 300 Outages to date Domestic Water, Heating Hot-water, Power-Normal, Lighting, Emergency, Critical, AHU, Medical Gases Aged Utilities-Non-Working Valves, Breakers, Equipment Coordination with Facilities and Users and scheduled way in advance
15 Surgery Located on the second floor Major Renovation Two Phases with Shutdowns in Between 5 ORs Now-4 More at the end Temporary Utilities to Serve Operations Phasing critical 9 ORs + 1 Hybrid OR (Imaging/Procedure)
16 Surgery Phasing 2A
17 Surgery Phasing 2B
18 Surgery Phasing 2C
19 Before and After Surgery
20 Before and After Surgery OR
21 Central Sterile Located in the Basement Requires a temporary shutdown and out sourcing of the Central Sterile services. Renovation includes a restructure of the flow of operations within the current foot print of the space and replacement of the washers and ultrasonic cleaner. 21
22 Central Sterile Swing Space Requested of Users to retain Inventory, Staff, and control of services. New Technology, unit, one of kind. Fully Functional CSS Maintenance and Service Challenges
23 Temporary Trailer Site FOOD SERVICE CENTRAL STERILE
24 Food Service Located in basement Renovated in place and will be extensive. Goal of this renovation - right size food preparation kitchen along with improving the customer flow and upgrade current equipment and infrastructure deficiencies. Utilize Kitchen Trailers to Retain Food Service on Site and Renovate in 1 Phase instead of 8 24
25 Medical Equipment Not Typically Purchased By Construction Contractors Months of Meetings to confirm equipment purchases Users want/need latest technology Coordination of Equipment, Options, Accessories-Joint Supply Schedule Re-use
26 Issues Existing/Differing Site Conditions Water Valves Fire rated shafts and chases Electrical Equipment HVAC Balancing, Digital Controls, Air Handlers, Ductwork Project Funding - Changes 26
27 QUESTIONS? 27
State of Kuwait Ministry of Health Infection Control Directorate. The role of infection control In design of health care facilities
State of Kuwait Ministry of Health Infection Control Directorate The role of infection control In design of health care facilities 2007 INTRODUCTION Hospital design should ensure that patients, especially
More informationMechanical Systems Redesign Proposal. Thesis Proposal. Morton Hospital Expansion
Mechanical Systems Redesign Proposal Thesis Proposal Morton Hospital Expansion Taunton, MA Courtney Millett Mechanical Option Advisor: Dr. Bahnfleth December 12, 2014 Revised: January 16, 2015 Revised:
More informationSUNY Hospitals & A Healthier New York. Capital Briefing March 1, 2013
SUNY Hospitals & A Healthier New York Capital Briefing March 1, 2013 Profile of SUNY Capital Programs Square Footage (in millions) 18.9 20.5 58.5 3.3 Educational Facilities Residence Halls Hospitals Community
More informationSTUART-HOBSON MIDDLE SCHOOL
INITIAL YEAR BUILT 1927 BUILDING AREA 105,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 399 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan STUART-HOBSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationFacility Services Update Joint Conference Committee October 8, 2013
Facility Services Update Joint Conference Committee October 8, 2013 14 major buildings on 14 acres Approximately 1.5 million gross sq. ft. 42 Elevators More than150 miles of piping More than 2,000 plumbing
More informationHealthcare Profile + Services About Us Established in 1965, DEDC is a privately owned, full-service, multidisciplined engineering and design firm. We offer inhouse expertise in mechanical HVAC, electrical,
More informationMAURY ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1886 BUILDING AREA 46,800 SF CURRENT PROGRAM CAPACITY 276 ENROLLMENT 2008 238 WARD 6 PROPOSED PROGRAM CAPACITY 325 Site Plan MAURY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationInfection Control Risk Assessment Matrix of Precautions for Construction & Renovation
Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step One: Using the following table, identify the Type of Construction Project Activity (Type A-D) TYPE A TYPE B TYPE
More informationRetrofit of an Existing Californian Hospital to Immediate Occupancy Standards One Year Later Again R. Jay Love, S.E.
Retrofit of an Existing Californian Hospital to Immediate Occupancy Standards One Year Later Again R. Jay Love, S.E. Degenkolb Engineers MCEER 2006 Annual Meeting Diagnostic & Treatment Building Designed
More informationMarketing Prioritization Alignment and Dashboard Reporting
Marketing Prioritization Alignment and Dashboard Reporting Presented by Gundersen Health System: Pamela Maas, Chief Business Development and Marketing Officer Julieann Paulson, Service Line Marketing Consultant
More informationLEVEE SAFETY UPDATE. June 28,2017
LEVEE SAFETY UPDATE 1 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56 48 130 120 111 June 28,2017 The
More informationOptimizing Energy Use in a HealthCare Setting. Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning
Optimizing Energy Use in a HealthCare Setting Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning AIA Quality Assurance The Building Commissioning Association is a Registered
More informationTexas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES
This article was published in ASHRAE Journal, January 2014. Copyright 2014 ASHRAE. Posted at www. ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission
More informationWe are the Army s Home
Society of American Military Engineers (SAME) Muhammad A. Bari, Director of Public Works U.S. Army Garrison, Fort Irwin, CA Our mission is to provide standardized, effective & efficient services, facilities
More information9/13/2011. Mark Hanicits, Director of Facilities and Safety, MetroSouth Medical Center. Terry Malloy P.E., Cxa, Project Manager, Teng & Associates
Mark Hanicits, Director of Facilities and Safety, MetroSouth Medical Center September 21 st, 2011 4:15pm 5:15pm Terry Malloy P.E., Cxa, Project Manager, Teng & Associates Energy consumption (BTU/SF) in
More informationThe Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma
LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using
More informationInfection Control Risk Assessment Matrix of Precautions for Construction & Renovation
Figure 3-6. Sample ICRA Matrix of Precautions Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step 1: Using the following table, identify the Type of Construction
More informationMEMORIAL HOSPITAL GULFPORT A PROJECT STUDY
MEMORIAL HOSPITAL GULFPORT A PROJECT STUDY Building a healthy community together 2005 u HURRICANE KATRINA REPAIRS 2012 u SURGERY MODERNIZATION 2001 u RADIOLOGY RENOVATION 2000 u CLINIC SUPPORT ADDITION
More informationBaffled Openings at Chain Link Fencing: Design shall consist of two end-posts set 4 feet apart, and a 10 foot wide chain-link fence panel equal in height as the adjacent fence. Chain link fence panel shall
More informationLIBRARY ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC
LIBRARY ENERGY WALK- THROUGH Andy Robinson, Training and Education, SEDAC ILLINOIS ENERGY NOW University of Illinois 360 Energy Group 2 WHAT WE DO SEDAC Free Services Outreach and Training Energy Assistance
More informationUniversity Health Network Infection Prevention and Control Requirements during Construction, Renovation and Building Maintenance
University Health Network Infection Prevention and Control Requirements during Construction, Renovation and Building Maintenance Introduction University Health Network follows the Canadian Standard Association
More informationStobill to GRI The Staffing Challenges and Improvements
Stobill to GRI The Staffing Challenges and Improvements Alan Hunter General Manager, Emergency Care & Medical Services North East Sector and Cardiology Wednesday 28 th November 2012 5.10.11 Recession/CRES
More informationKeith Beidel Mechanical Option Centre Community Hospital East Wing Expansion State College, PA 9/30/02
BUILDING AND PLANT ENERGY ANALYSIS REPORT: Part A Keith Beidel Mechanical Option Centre Community Hospital East Wing Expansion State College, PA 9/30/02 Executive Summary Centre Community Hospital East
More informationAllstream Centre Energy Performance Report
Allstream Centre Energy Performance Report 2012 2014 TABLE OF CONTENTS INTRODUCTION... 1 ELECTRICAL CONSUMPTION... 2 ELECTRICAL ENERGY DISTRIBUTION... 3 BUILDING POWER AND SYSTEMS... 4 FACTORS CONTRIBUTING
More informationHealthcare construction
Healthcare construction Role of the Infection Preventionist FIRAS R. ZABANEH, MT( ASCP), CIC, CIE OCT 1, 2015 ( N O T H I N G T O D I S C L O S E ) Current state Many Infection Preventionists view their
More informationNOYES EDUCATION CAMPUS
INITIAL YEAR BUILT 1930 BUILDING AREA 49,700 SF CURRENT PROGRAM CAPACITY 321 ENROLLMENT 2008 337 WARD 5 PROPOSED PROGRAM CAPACITY 450 Site Plan NOYES - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-8
More informationDEPARTMENT OF THE NAVY HEADQUARTERS UNITED STATES MARINE CORPS WASHINGTON, DC MCO ARCB 14 Oct 93
DEPARTMENT OF THE NAVY HEADQUARTERS UNITED STATES MARINE CORPS WASHINGTON, DC 20380-0001 MCO 12630.3 ARCB MARINE CORPS ORDER 12630.3 From: Commandant of the Marine Corps To: Distribution List Subj: FAMILY
More informationLaker Hall Program Study Intercollegiate Athletics. Preferred Concept & Project Phasing SUCF Project No
Laker Hall Program Study Intercollegiate Athletics Preferred Concept & Project Phasing SUCF Project No. 101009 26 January 2017 Agenda Preferred Concept - Existing Site Plan - Existing Floor Plans - Space
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationOrientation Program for New Infection Control Professionals
Orientation Program for New Infection Control Professionals Module 10: Construction and Renovation Orientation Program for New Infection Control Professionals Table of Contents Module 10: Construction
More informationSTRATEGIC ENERGY MANAGEMENT PLAN FOR ST. THOMAS ELGIN GENERAL HOSPITAL 2015
STRATEGIC ENERGY MANAGEMENT PLAN FOR ST. THOMAS ELGIN GENERAL HOSPITAL 2015 Strategic Energy Management Plan Page 1 Contents About STEGH... 3 Introduction... 4 Energy Management Vision... 6 Guiding Principles
More informationSTATEMENT OF QUALIFICATIONS. Detention/Public Safety Statement of Qualifications DETENTION/PUBLIC SAFETY
STATEMENT OF QUALIFICATIONS 23 DETENTION/PUBLIC SAFETY Since 19 WHO WE ARE HISTORY: Established in 1923 Family-owned, 4th Generation SIZE: 80 Professional Staff 100-150 Tradesmen Annual Project Revenues
More informationSEVEN GENERATIONS ARCHITECTURE & ENGINEERING JANUARY 26, Request for Qualifications from. Potential Teaming Partners
SEVEN GENERATIONS ARCHITECTURE & ENGINEERING JANUARY 26, 2018 Request for Qualifications from Potential Teaming Partners GENERAL FIRM INFORMATION Where tradition fuels innovation Seven Generations Architecture
More informationImproving the Patient Experience Through Facilities Maintenance Programs
Improving the Patient Experience Through Facilities Maintenance Programs Presenters: Jon Utech, Senior Director, Cleveland Clinic John Wood, Senior Facilities Operations Consultant/ Senior Associate, Mazetti+GBA
More informationTechnical Report Three
Technical Report Three Mechanical System Existing Conditions Evaluation Prepared by: Timothy Berteotti Prepared for: Date: November 16, 2011 Table of Contents Executive Summary...3 Design Objectives...3
More informationNorwood High Service Pump Replacement
T E C H N I C A L M E M O R A N D U M 737-02 NORWOOD HIGH SERVICE PUMP REPLACEMENT 737-02 Norwood High Service Pump Replacement PREPARED FOR: JEA Planning PREPARED BY: Joshua M. Brown DATE: February 2017
More informationWILKINSON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationJuvenile Commitment Center Stanislaus County. Corrections Facilities
Juvenile Commitment Center Stanislaus County Corrections Facilities What if......there was a company that could be your one stop Construction Service provider?...this company was knowledgeable of all aspects
More informationEnergy Management Journey
Energy Management Journey Arnold Granger, P.E., CEM Director of Energy Management Dr. Yeqiao Zhu, P.E., MBA Director of Facilities Patient Care and Prevention Facilities Patient Treatment Research Facilities
More informationThe Biggest Loser REDUCING HIGHER EDUCATION COSTS BY 50%
The Biggest Loser REDUCING HIGHER EDUCATION COSTS BY 50% Ian Hadden, PE, LEED AP BD+C, CEM Director, Energy Management Services University of Arkansas at Little Rock 501-313-9597 ithadden@ualr.edu.com
More informationDAVIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1943 BUILDING AREA 71,100 SF CURRENT PROGRAM CAPACITY 507 ENROLLMENT 2008 227 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan DAVIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-
More informationFRANK MILLS INFECTION RATES HVAC ISSUES HVAC IN HEALTHCARE. Developments in ASHRAE and CIBSE
HVAC IN HEALTHCARE Developments in ASHRAE and CIBSE FRANK MILLS ENVIRONMENTAL DESIGN CONSULTANTS, CHORLEY, LANCASHIRE FRANK MILLS VICE CHAIR, CIBSE HEALTHCARE GROUP MEMBER ASHRAE TC 9.6 HEALTHCARE TECH
More informationKEY ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1925 BUILDING AREA 52,000 SF CURRENT PROGRAM CAPACITY 320 ENROLLMENT 2008 328 WARD 3 PROPOSED PROGRAM CAPACITY 325 Site Plan KEY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationBALLOU SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE
More informationSEATON ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1969 BUILDING AREA 65,000 SF CURRENT PROGRAM CAPACITY 428 ENROLLMENT 2008 280 WARD 2 PROPOSED PROGRAM CAPACITY 325 Site Plan SEATON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationSustainable Buildings from LEED to Net Zero
Sustainable Buildings from LEED to Net Zero Col(P) Peter DeLuca Commander US Army Corps of Engineers North Atlantic Division 10 May 2010 US Army Corps of Engineers SUSTAINABLE DESIGN AND CONSTRUCTION The
More informationConservation & Demand Management Plan
Conservation & Demand Management Plan Page 1 of 20 1 Executive Summary Conservation & Demand Management Plan 2014 The following Energy Conservation and Demand Management Plan is written for the Chatham-Kent
More informationTech Assignment 1 University Medical Center of Princeton. Plainsboro Road, Township of Plainsboro, New Jersey
Tech Assignment 1 University Medical Center of Princeton Plainsboro Road, Township of Plainsboro, New Jersey David Bodnar CM Chris Maget 10/5/2009 Table of Contents Executive Summary...3 Project Schedule
More informationOpening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction
Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction Matthew Tunnard, PE, CCP, LEED AP, Senior Engineer Horizon Engineering Associates, LLP AIA Quality Assurance
More informationNSC Shelving & Storage for Epworth
NSC Shelving & Storage for Epworth Providing a complete storage and shelving solution: customised for Epworth HealthCare National Surgical Corporation worked with Epworth HealthCare to design, supply and
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationLEWIS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationJackson Health System Miracle Building Plan Outreach Roundtable. May 16, 2017
Jackson Health System Miracle Building Plan Outreach Roundtable May 16, 2017 $1.5 billion Expanded Footprint Improved Patient Experience World-Class Facilities Innovative, Leading-Edge Care A Stronger,
More informationResource Center. Investigation Areas
Investigation Areas Depth Study: Re-Phasing The Project is a Phased project. The main focus of this analysis is rephasing the project with ICRA requirements in mind. I am looking to reduce the cost of
More informationINFECTION CONTROL ISSUES IN CONSTRUCTION AND RENOVATION
INFECTION CONTROL ISSUES IN CONSTRUCTION AND RENOVATION Evelyn Cook SPICE.unc.edu 919 966 1304 I want to begin with the premise that patients can leave the hospital sicker than they arrived if construction
More informationNON-TRADITIONAL PROJECT DELIVERY MODELS AT UCSF MEDICAL CENTER. Alan Laurlund, Vice President XL Construction Corporation Milpitas, California
NON-TRADITIONAL PROJECT DELIVERY MODELS AT UCSF MEDICAL CENTER Alan Laurlund, Vice President XL Construction Corporation Milpitas, California Kevin Ng, Senior Project Manager XL Construction Corporation
More informationProject : Power & Fuel consumption - an engineering initiative. VPS Rockland, Dwarka.
Project : Power & Fuel consumption - an engineering initiative VPS Rockland, Dwarka. VPS Rockland Dwarka Well-designed compact 103 bed Multi speciality hospital Plot area of 1250 square meter, and build
More informationRetrocommissioning (RCx)
Retrocommissioning (RCx) Facilities & Services - Engineering Services Saving the planet, two buildings at a time. Mr. Karl Helmink Mr. Damon McFall Creating a Sustainable Campus What is Retrocommissioning
More informationSteve Harrell, LEED AP, CEM, CxA SSRCx Dr. David Claridge, P.E. Energy Systems Lab, Texas A&M University
Post Occupancy Building Commissioning Successes through Continuous Commissioning Steve Harrell, LEED AP, CEM, CxA SSRCx Dr. David Claridge, P.E. Energy Systems Lab, Texas A&M University AIA Quality Assurance
More informationA Building Area: (sf) 80,000 SF + Sky Bridge. Cost per Square Foot: $340 ± Construction Cost $27,422,000. Date of Completion: January 2014
Program Summary: This project involves renovating 80,000 SF of an existing warehouse to provide new classrooms, internal medicine clinics, radiology clinics, and laboratory. Program Statement: The first
More informationEnergy Reduction in Hospitals
Energy Reduction in Hospitals OSBORN ENGINEERING DAVE CHOUINARD, CBCP, LEED AP, DIRECTOR HEALTHCARE CARL SCHULTZ, PE, DIRECTOR ENERGY AND FACILITY SYSTEMS MARK WUTZ, PE, DIRECTOR ENERGY & COMMISSIONING
More informationLegionella Control in Building Systems. Carl Schultz, PE National Healthcare Engineering Leader
Legionella Control in Building Systems Carl Schultz, PE National Healthcare Engineering Leader Legionella Basics Bacterium that causes respiratory diseases such as Legionellosis and Pontiac Fever Present
More informationBID PACKAGES 3-21, Addendum No. 03
WEBER MURPHY FOX Addendum Date: January 23, 2018 Bid Due Date: January 26, 2018 BID PACKAGES 3-21, Addendum No. 03 to the Plans and Specifications for Cuyahoga Community College West Science and IT Labs
More informationARE YOU READY TO OPERATE? Designing ORs to meet new technological advancements
ARE YOU READY TO OPERATE? Designing ORs to meet new technological advancements Gary Hamilton PE, SASHE, LEED AP BD+C, CxA, EDAC Ionel Petrus PE, LEED AP BD+C, CEM 2016 SmithGroupJJR 1 Objectives The audience
More informationApplication for Zoning Certificate and/or Building Permit
Application for Zoning Certificate and/or Building Permit 1. Fill out the Zoning Application and NIRA Application (if applicable) and return it to the Harrison Township Zoning Office. 2. Please allow 10
More informationRisk Assessment and Preventive Measures Checklist for Construction and Renovation. Location of Construction: Project Start Date: Estimated Duration:
Risk Assessment and Preventive Measures Checklist for Construction and Renovation Location of Construction: Project Start Date: Estimated Duration: Project Manager (PM): Contractor(s): Infection Prevention
More informationPuget Sound Green Infrastructure Summit 2017
* 130,000 SF office building 5 stories above-grade * Mixed use, including 15,000 SF retail space * City of Seattle Deep Green Pilot Program Stone34 Project Overview Matt Nielsen 2017-02-13 Seattle Deep
More informationNEIDIG ELEMENTARY SCHOOL ADDITION & RENOVATION PHASING. Neidig Community Meeting July 2018
NEIDIG ELEMENTARY SCHOOL ADDITION & RENOVATION PHASING Neidig Community Meeting July 2018 PROPOSED NEIDIG ELEMENTARY SCHOOL Expanded parking Separate bus loop Gymnasium Addition 2 story classroom wing
More informationA Building Area: (sf) 80,000 SF + Sky Bridge. Cost per Square Foot: $340 ± Construction Cost $27,422,000. Date of Completion: January 2014
Program Summary: This project involves renovating 80,000 SF of an existing warehouse to provide new classrooms, internal medicine clinics, radiology clinics, and laboratory. Program Statement: The first
More informationLOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN
INITIAL YEAR BUILT 1935 BUILDING AREA 47,200 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 418 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan LOGAN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION HS
More informationWATER SAFETY POLICY. Version Water Policy V2. Date to be reviewed June 2019 To by reviewed by Strategic Water Safety Group
East Cheshire NHS Trust WATER SAFETY POLICY Version 2.0 File ref 150820 Water Policy V2 Date approved draftcomments[1] June 2016 Date to be reviewed June 2019 To by reviewed by Strategic Water Safety Group
More informationSummary of Modifications/Changes in this Update
Summary of Modifications/Changes in this Update This Summary of Changes is for information only. It is not a part of the referenced document, and should not be used for project documentation. U.S. Department
More informationContracted Scope ABC of the Carolinas Excellence in Construction Awards Carolinas HealthCare System CMC Kitchen Healthcare.
Contracted Scope Provide a detailed description of your scope for this project. Responses should include: type of construction; size of project; contract value; length of project; and percentage of labor
More informationBoth health-care facility classification and area classification, as per CSA, determine the design requirements.
ACCREDITATION STANDA RDS HEATING, VENTILATION AND AIR-CONDITIONING SYSTEM (HVAC) Class 3 Facility: Local Anesthesia Heating, ventilation and air-conditioning system standards are a primary infection prevention
More informationMEDICAL WASTE MANAGEMENT STUDY NOTES
MEDICAL WASTE MANAGEMENT STUDY NOTES UNIT 1 INTRODUCTION Hospital and other health care establishment has a duty of care for the environment and for public health and have particular responsibility in
More informationStanford University Water Efficiency Program Marty Laporte Jennifer Fitch Thomas Bartleman
Pilot Testing New Wi-Fi Weather-Based Irrigation Controller Technology at Stanford University February 2014 October 2015 Initial Pilot Study Findings for Water Conservation College Group Stanford University
More informationAbington Memorial Hospital Abington, PA. Project Description
Project Description Project Description Project Background The expansion is a seven story, 360,000 SF addition with a total project cost of $98 million. Construction began in February 2003 and the project
More informationCORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting
CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening
More informationNo Patient Left Behind: Leading Transition to Modernized Capability
No Patient Left Behind: Leading Transition to Modernized Capability Session #163, February 22, 2017 Colonel Rich Wilson, Chief, Solution Delivery Division, Health Information Technology (J6), Defense Health
More informationBARNARD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 2002 BUILDING AREA 67,000 SF CURRENT PROGRAM CAPACITY 520 ENROLLMENT 2008 329 WARD 4 PROPOSED PROGRAM CAPACITY 450 Site Plan BARNARD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationTime is Money 150,000 sf Hospital in 8 ½months Concept through Construction
Time is Money 150,000 sf Hospital in 8 ½months Concept through Construction Dr. Glenn Mitchell, Mercy Health, Retired Dave Hitchcock, Aspen Street Architects Charlie Walden, Walden Structures Inc. Learning
More informationWater Balance and Roadmap Update Pacific Northwest National Laboratory Kate McMordie and Brian Boyd
Water Balance and Roadmap Update Pacific Northwest National Laboratory Kate McMordie and Brian Boyd Army Net Zero Workshop 18-20 Jan 2012 Assistant Secretary of the Army (s, Energy & Environment) Agenda
More informationMHS GENESIS Transforming the Military Health System
AMSUS 2018 MHS GENESIS Transforming the Military Health System Maj Gen Lee Payne, USAF, MC, CFS Assistant Director-Combat Support & MHS Functional Champion 28 Nov 2018 National Harbor MD Disclosures Presenter
More informationArchitectural & Engineering Services for Air Conditioning Alleghany High School
February 7, 2011 Architectural & Engineering Services for Air Conditioning Alleghany High School October 1, 2012 Who We Are All Architectural/Engineering Services In-House Total Staff of 36 Roanoke Office
More informationNo Patient Left Behind: Leading Transition to Modernized Capability
No Patient Left Behind: Leading Transition to Modernized Capability Session #163, February 22, 2017 Colonel Rich Wilson, Chief, Solution Delivery Division, Health Information Technology (J6), Defense Health
More informationAUTOMATION ZONE BUILDER
AUTOMATION ZONE BUILDER Energy Saving More than 1,000 JOB In JAPAN Come to Thailand Contribution for Your Buildings We would like to propose Energy Saving Solutions to contribute your energy saving activities.
More informationCivista Medical Center Thad Maugle RESEARCH. The construction at Civista Medical Center consists of three phases; a main
RESEARCH Problem The construction at Civista Medical Center consists of three phases; a main building addition, a vertical expansion of the existing building, and selective renovations. All three areas
More informationProject Narrative Why is this project special? Self Regional Healthcare (SRH), in Greenwood South Carolina, is a 358-bed, non-profit healthcare system
Contracted Scope Project Description/Type of Construction The project scope included the complete demolition and removal of the top four floors of the Old Main Patient Tower, built in the 1950s, plus the
More informationCreating a Lean Culture Transformational Leadership for Lean Health Care
Creating a Lean Culture Transformational Leadership for Lean Health Care Bruce Roe, MD President and CEO Executive Champion, Transformation February 15, 2017 St.Boniface Hospital 180 Departments 7 Separate
More informationMedical Military Facilities
MEDICAL TEMPLATES Medical Military Facilities prepared for: United States Army United States Navy United States Air Force Purpose The purpose this document is to supplement UFC 451001 in providing detailed
More informationSHEPHERD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1932 BUILDING AREA 79,700 SF CURRENT PROGRAM CAPACITY 332 ENROLLMENT 2008 355 WARD 4 PROPOSED PROGRAM CAPACITY 400 Site Plan SHEPHERD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationWATKINS ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1962 BUILDING AREA 69,300 SF CURRENT PROGRAM CAPACITY 578 ENROLLMENT 2008 550 WARD 6 PROPOSED PROGRAM CAPACITY 550 Site Plan WATKINS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationAdaptation of Scrum to Facility Planning and Design. U.S. Army Health Facility Planning Agency (HFPA)
Welcome Adaptation of Scrum to Facility Planning and Design U.S. Army Health Facility Planning Agency (HFPA) Session Description Changes in local health care support for soldiers and their families in
More informationSGH Competency Framework: GLF
SGH Competency Framework: GLF 6 th December 2009 Dr Camilla Wong Deputy Director, Allied Health Division 6 DECEMBER 2009 Set up Adapted CoDEG GLF to SGH setting & mapped competencies to experience of pharmacist
More informationLeading Techniques for Energy Savings in Healthcare Facilities
Healthcare Leading Techniques for Energy Savings in Healthcare Facilities Learn how building automation products and services can reduce energy costs at healthcare facilities. This paper outlines proven
More informationHEALTHCARE SOLUTIONS TRANSCAR AUTOMATED GUIDED VEHICLE
HEALTHCARE SOLUTIONS TRANSCAR AUTOMATED GUIDED VEHICLE 2 TRANSCAR GENERATION 3 SWISSLOG IS A LEADING PROVIDER OF INNOVATIVE, INTEGRATED LOGISTICS SOLUTIONS FOR HOSPITALS Answering tomorrow s hospital logistics
More informationAPPENDIX A DEFINITIONS OF BUILDING AREAS
A. GENERAL REQUIREMENTS DEFINITIONS OF BUILDING AREAS 1. The Project Architect/Engineer shall submit an estimate with the Schematic Design Phase submission, and shall submit calculations with the Design
More informationFor efficient interventions
For efficient interventions 37 % more information per image may be crucial for an optimal workflow. You can see all the surrounding structures at a glance and can accurately plan and perform your intervention.
More informationConstruction in Healthcare: Does it put Patients or Workers at Risk? Not if we do ICRA correctly! Infection Control Risk Assessment (ICRA)
Infection Control Risk Assessment (ICRA) What Does it Mean? Deb Hess, RN, CIC Supervisor Infection Control & Prevention Lancaster General/Penn Medicine Construction in Healthcare: Does it put Patients
More informationCivil District Court Parish of New Orleans. Image Courtesy of EDR MA. Renovation & Utilization Feasibility
Civil District Court Parish of New Orleans Image Courtesy of EDR MA Renovation & Utilization Feasibility Challenges with Courthouse Design Courthouse Space Standards and Requirements Charity Hospital Building
More information