1 Foundation Preparation and Treatment During Dam Construction John W. France, PE, D.WRE URS Corporation Denver, Colorado October 14, Scope of Discussion Broad discussion of treatment of foundations applicable to: Dam rehabilitation / modification New dam construction Topics addressed: Treatment of exposed rock surfaces Grouting (limited treatment) Treatment of soil foundations (for other than seepage) Foundation seepage reduction Foundation seepage collection and control 2 Foundation Related Issues Support for overlying structures Settlement of overlying structures Foundation seepage Quantity Internal erosion (piping) Uplift pressure Most foundation treatment efforts are aimed at addressing seepage issues 3 1
2 Embankment Foundation Seepage Concerns -1 Foundation filter Filtered exit Unfiltered exit Filtered exit Unfiltered exit Open-work gravel layer Filtered exit Bedrock, open-jointed 4 Embankment Foundation Seepage Concerns -2 5 Embankment Foundation Seepage Concerns
3 Embankment Foundation Seepage Concerns -4 Core Material Cavity pr ogresses to reser voir / high per meabl e zone Coarse downstream shel l Material erodes into downstream em bankment or exits at toe Genera l se epag e gradi ent fro m foundation into embankment Jointed rock foundation 7 Treatment of Exposed Rock Surfaces Foundation shaping Surface treatment Cleaning Dental concrete Slush grouting Shotcrete 8 Shaping of Rock Surface Reduces cracking potential Limits differential settlement Limits stress concentrations Facilitates compaction 9 3
4 Surface Treatment Prevents internal erosion of embankment soil into open joints/discontinuities Prevents internal erosion along the foundation contact Prevents the loss of joint filling materials 10 Rock Treatment Varies With Zones Most critical beneath core and filters Less critical but beneficial beneath shells 11 Foundation Surface Preparation for Earthfill Core and Filter/Drain Zones Fill with dental concrete Fill with slush grout or dental concrete Remove promontories Remove overhang at slope of 0.5:1 or flatter; or fill with dental concrete at a slope of 0.5:1 or flatter Remove loose material and clean Typical Foundation Treatment Details 12 4
5 Shaping and Surface Treatment in Core Trench 1 1 (min) Remove overhangs and steep slopes Remove or shape rock protrusions Fill with concrete Remove loose blocks and backfill with concrete 6 (typical) Fill with concrete 1 Clean depressions and backfill with 2 concrete for depressions greater than 6 Surface Treatment and Shaping in Core Trench Transverse Direction (min) 1 6 (typical) Remove overhangs 2 1 Remove or shape rock protrusions Fill with concrete Surface Treatment and Shaping in Core Trench Longitudinal Direction 13 Details for Foundation Shaping Remove overhangs 0.5H:1V or flatter 6 (min) Greater than 1 foot, excavate OR place dental concrete within core zone (outside core zone higher than 5 feet) 0.5H:1V or flatter 45⁰ (min) 6 (min) 14 Foundation Shaping Remove overhangs Shape to facilitate fill placement Methods Excavator Hoe Rams Jack Hammers Trim Blasting 15 5
6 Foundation Shaping 16 Overhang Formwork 17 Overhang Concrete 18 6
7 10/14/2014 Shaping Facilitates Compaction: Abutment Rolling 19 Shaping Facilitates Compaction : Wheel Rolling 20 Foundation Cleaning- Blade Cleaning Removes majority of loose materials prior to blowing with air/water 21 7
8 Foundation Cleaning- Hand Work Labor Intensive Shovels Jackhammers Picks Crow Bars Rock Hammers Vacuums 22 Foundation Cleaning: Brushing 23 Foundation Cleaning-High Pressure Air / Water Effective in moving and dislodging loose debris form irregular surface 24 8
9 Foundation Cleaning-High Pressure Air / Water 25 Dental Treatment Three types Backfill concrete Dental concrete Slush grout 26 Backfill Concrete for Leveling 27 9
10 Backfill Concrete for Shaping Used to treat steep ledges on abutments 28 Backfill Concrete for Shaping 29 Dental Concrete Used to treat larger discontinuities (joints, fractures, etc.) and smaller irregularities 30 10
11 Dental Concrete 31 Dental Concrete Note Dental concrete placed to just below rock surface to minimize thin edges 32 Dental Concrete 33 11
12 Slush Grout Used to treat Small discontinuities (joints, fractures, etc.) Typically a sanded mortar Individual discontinuities Dig out and clean Place by pouring, pushing, rodding, funneling Do not allow to spread out on rock surface Will need to be chipped off rock surface 34 Slush Grout Multiple closely spaced fractures Broom with stiff bristle broom Place on foundation directly ahead of initial core placement 35 Slush Grout 36 12
13 Slush Grout 37 Slush Grout 38 Shotcrete Used to treat Highly fractured shattered zones of rock Shotcrete Non-fiber reinforced Fiber reinforced Stronger Less likely to crack 39 13
14 Shotcrete Wet-Mix Shotcrete Process Cement, aggregate and water mixed by mechanical methods Air introduced at nozzle Nozzleman has no control over shotcrete mixture Dry-Mix Shotcrete Process Cement, aggregate and air are blown to nozzle where water is added Nozzleman controls amount of water in shotcrete 40 Shotcrete Surface Preparation Place on cleaned approved foundation free of water Surface dampened before shotcrete application Install ground wires or pins on surface to guide placement thickness Placement Discharge from nozzle between 0.5 and 1.5 m from surface Buildup to specified thickness using several passes Cure similar to backfill concrete 41 Slaking Protection: Hard 42 14
15 Slaking Protection: High Rough Excavation 43 Question Session No Grouting Reduce hydraulic conductivity of foundation and thereby seepage under the dam by intersecting and filling factures and voids within the rock mass. By its nature, the extent of the work required for grouting cannot be known until excavation is complete and grouting program is implemented 45 15
16 Grouting Grouting is a specialty construction process and must be directed by people with experienced personnel 46 Grouting Cautions Limited soils for which grouting is effective Soils (and soft rock) can be hydrofractured In rock, grout only penetrates water-and airfilled features Grout may deteriorate over time; or at least effectiveness of a grout curtain may deteriorate over time 47 Types of Grouting Blanket Grouting Low pressure shallow holes located in a pattern across the foundation surface Curtain Grouting Low pressure shallow hole grouting and intermediate to high pressure grouting of deeper zones in rows of holes Stitch Grouting Grouting of fault or shear zones in a pattern of holes designed to intersect and cross the zone at various selected depths 48 16
17 Example Grouting Layout 49 Grouting Program Elements Spacing Depth Number of lines (grout curtain) Sequence Pressure Grout mixes Monitoring and control 50 Foundation Grouting Holes oriented to best intersect defects depends on geology Hole pattern; primary, secondary, tertiary Pressures limited to preclude hydraulic fracture Grouting of bore holes in stages Upstage or ascending stage Downstage or descending stage 51 17
18 Foundation Grouting Grout mixes A range of mixes Start thin and thicken as needed Balanced, stable mixes essentially no bleed Reference points for uplift check Verification water test holes after grouting Procedures highly dependent on nature of foundation Grouting as final exploration 52 Split Spacing Method Primary, secondary, tertiary, etc. to closure P S T T P P S T T P P S T T P First Second Third 53 Stage Grouting Ascending Stage Grouting Grout hole drilled complete to bottom Grout starting with bottom stage and work up to top of hole Descending Stage Grouting Grout hole drilled stopped due to partial or total loss of circulation, artesian flow, caving conditions, or grout flow to adjacent holes Grout stage, washout and continue to drill 54 18
19 Groutability Readily groutable k > 1 x 10-3 cm/sec (100 lugeons) Marginally groutable k ~ 1 x 10-4 cm/sec (10 lugeons) Barely groutable k < 1 x 10-5 cm/sec (1 lugeon) Effective grouting likely does not reduce rock mass permeability to less than about k < 1 x 10-5 cm/sec (1 lugeon) 55 Grouting Drill Rigs 56 Access Challenges 57 19
20 Monitoring / Recording Computerized Real Time Monitoring and Assessment System Records, displays, stores and analyzes Water pressure testing data Grouting data Measures Flow Pressure Lugeon value Cumulative grout volume A number of other parameters 58 More Information on Grouting ASDSO Webinar October 9, 2012 Introduction to Grouting for Dams 59 Question Session No
21 Treatment of Soil Foundations Reasons for soil foundation treatment Control settlement Provide stability (static or seismic) Control seepage this will be dealt with separately later in the presentation 61 Settlement Soils of concern: Generally compressible clays and silts For very high dams, loose sands or even soft rock could possibly be a concern, but unusual Treatment options for compressible soils Remove and replace Wick drains and / or staged construction 62 Excavate and Replace Dewatering often required 63 21
22 Wick Drains 64 Wick Drains Installed on patterns to promote drainage Used to accelerate consolidation and strength gain in staged embankment construction Used to enhance benefits of improvement methods (dynamic compaction, vibroflotation, vibrocompaction piles, compaction grouting) in finer-grained soils Stability Static stability not typically a concern except for soft, plastic clays or silts Seismic stability can be a concern for a wider range of soils particularly for loose, cohesionless soils (liquefaction) Treatment options to improve stability Remove and replace Increase strength with in-situ treatment Reinforce 66 22
23 In-Situ Treatment to Increase Strength Dynamic compaction Vibroflotation Vibro-replacement (stone columns) Compaction grouting For all methods verification testing would be required, and often test sections are needed. 67 Dynamic Compaction Dropping weights to create vibrations that densify the soil Weights are dropped on a controlled pattern Effectiveness verified indirectly through before and after investigations Dynamic Compaction Reference: Densification, Inc
24 Dynamic Compaction - Limitations Effectiveness diminishes with depth practical limit is about 30 feet Most effective in clean, cohesionlesssoil; less effective as fines content increases Not effective in plastic soils Vibroflotaion Densifyingsoil in place with a vibratory probe with water injection Probes completed on a controlled, relatively closely spaced pattern Effectiveness verified indirectly through before and after investigations Vibroflotation Reference: Hayward Baker
25 Vibroflotation Vibroflotation- Limitations Most effective in clean, cohesionlesssoil; less effective as fines content increases Not effective in plastic soils Vibro-Compaction Piles (Stone Columns) Similar to vibroflotation, except that gravel fill is placed in the probe hole Can be done with water (wet method) or without water (dry method) Effectiveness in finer-grained soils can be enhanced with wick drains Effectiveness verified indirectly with before and after investigations
26 Vibro-Compaction Piles Reference: Hayward Baker Vibro-Compaction Piles - Limitations Most effective in clean, cohesionlesssoil; less effective as fines content increases Not effective in plastic soils Mixing of gravel with in situ soil, rather than densification has been observed in some soft or very loose finer-grained soils Compaction Grouting Injection of low mobility (low slump) grout to densify soil Completed in holes drilled on a pattern Effectiveness verified indirectly through before and after investigations
27 Compaction Grouting Drill Rod Compaction Grout Casing Casing Casing Compaction Grouting - Limitations Does not include vibration, so effectiveness in cohesionlesssoils may be limited May have more effectiveness in finer grained soils, but very low permeabilities may limit effectiveness Reinforcement Shear walls Replaced or modified blocks Structural elements (e.g. piles, anchors, MSER) Composite strengths Can be combined with berms and buttresses
28 Shear Walls Shear Wall Construction Methods Cement deep soil mixing (CDSM) Jet grouting Cement Deep Soil Mixing (CDSM*) Mixing in situ soils with cement grout or other slurries Using multiple shaft mixing tools with cutting heads and mixing paddles, or Using wheels on horizontal axis or trenching techniques Equipment illustrated later in seepage barrier wall discussion * aka DSM, DMM
29 Jet Grouting Can limit treatment to layers at depth. 85 Jet Grout Blocks WickiupDam, OR In Situ Reinforcement - Piles Reinforcing Piles Thin Weak Layer Piles essentially act as shear pins Used at Sardis Dam, MI for seismic rehabilitation
30 Composite Strength Plan View Reinforcing Elements In Situ Soils Composite Strength If: Strength of in situ soil is c i + σ tan φ i Strength of reinforcement is c r + σ tan φ r Replacement ratio = R r = A r / A tot A r = area of reinforcement elements A tot = total area Then: Composite strength: c i + (c r -c i ) R r + tan φ i + (tan φ r -tan φ i ) R r Based strictly on an area ratio Strain incompatibility could be an issue Question Session No
31 Foundation Seepage Cut Off Methods Grouting discussed earlier Low Permeability Blankets Barrier Walls Note: Cut off is in quotes, because it is very difficult to truly cut off seepage. 91 Low Permeability Blankets Upstream blanket Soil Blankets Geomembranes Blankets may need to be very long 92 Limited Effectiveness of Upstream Blankets Reference: Cedergren(1989) 93 31
32 Seepage Barrier Walls: Foundation and Embankment Embankment Pervious Foundation Impervious Foundation 94 Seepage Barrier Walls: Foundation and Partial Embankment Embankment Pervious Foundation Impervious Foundation Wall needs to connect to water barrier in the embankment 95 Seepage Barrier Walls: Foundation Only Embankment Pervious Foundation Impervious Foundation Wall needs to connect to water barrier in the embankment 96 32
33 Seepage Barrier Walls: Partial Cutoff Embankment Pervious Foundation 97 Limited Effectiveness of Partially- Penetrating Cutoffs Reference: Cedergren(1989) 98 Seepage Barrier Walls Continuous Trench Walls Soil Mix Walls Element Walls (Panel) Jet Grouting Walls (not discussed further) Sheet Pile Walls 99 33
34 Continuous Trench Barrier Walls 100 Continuous Trench Barrier Walls Salient Features Slurry Supported Excavation No Backfill Restrictions No Backfill Joints Non-Structural Low Permeability Typical Backfills Soil-Bentonite (SB) Cement-Bentonite(CB) Soil-Cement-Bentonite (SCB) 101 Excavators Long Boom / Long Stick Excavator (to 80 to 90 ft) Clamshell / Grab Trencher (with slurry)
35 Backfill Equipment Bulldozer and Excavator Mixing Box CB Mix Plant No end stops No tremie (except for great depths) 103 Continuous Wall Benefits Low cost Rapid Construction Low permeability Applicable to most soil types No joints 104 Cement Deep Soil Mixing (CDSM*) Mixing in situ soils with cement grout or other slurries Using multiple shaft mixing tools with cutting heads and mixing paddles, or Using wheels on horizontal axis or trenching techniques To depths exceeding 100 ft * aka DSM, DMM
36 RSW (triple auger) 106 Cutter Soil Mixing (CSM) Cutter Soil Mixing (CSM) Herbert Hoover Dike
37 TRD Method (Trench Cutting RemixingDeep Wall Method) Soil-Cement- Bentonite 109 TRD Wall Construction -Herbert Hoover Dike TRD Grout Batch Plant 110 Top of Exposed TRD Wall -Herbert Hoover Dike Top of Wall
38 Element Barrier Walls Constructed of individual elements, connected together to provide continuous wall Different types of equipment Constructed in primary / secondary sequence Practical to large depths, 250 feet plus directional control becomes very important at depth 112 Primary Elements 113 Secondary Elements
39 Element Wall Configurations Primary Elements Installed First Secondary Elements Fill Between P S P P S P S P P S P S P Grab or Clam Shell 116 Hydromill(Hydrofraise)
40 Hydromill(Hydrofraise) 118 Sheetpiles Conventional sheetpiles can be used for temporary or permanent seepage barriers Sheetpiles can be either steel or plastic (vinyl) Issues include Corrosion of steel sheetpile Buckling of steel or plastic sheetpile Lack of advancement Interlock separation Interlock leakage
41 Foundation Seepage Collection and Control Methods Foundation Drains Relief Wells Approaches shown are to address only foundation seepage, not embankments; often combined with embankment treatments 121 Shallow Toe Drain For limited shallow foundation seepage Likely requires dewatering for rehabilitation May require reservoir lowering for rehabilitation 122 Deep Toe Drain For more extensive, deep foundation seepage Almost certainly requires dewatering for rehabilitation Likely requires reservoir lowering for rehabilitation
42 Toe Drain and Berm Berm provides resistance for pressure and improved stability 124 Trench Toe Drain Trench and Berm Drain trench With slurry methods, trench drain can be constructed without dewatering Potential construction issues 125 Relief Wells Low permeability layer Confined aquifer with seepage pressure xx x xx x x
43 Relief Wells Relieve pore pressures and lower piezometric surface within confined pervious foundation strata Reduce uplift and improve stability Control exit gradients and reduce piping potential Maintenance required Drain trench or toe drain may be better alternative 127 Question Session No Post Event Evaluation & Quiz Please click the following link to take the Seminar Evaluation and Quiz: t.php?id=14074 You must complete the Seminar Evaluation and Quiz to receive PDH credit hours
EMBANKMENT DAM SEEPAGE MODIFICATIONS CHOICES AND CONSIDERATIONS. John W. France, PE, D.WRE 1 ABSTRACT INTRODUCTION
This paper is reproduced from the Proceedings of the 2014 United States Society on Dams (USSD) Annual Conference, with the permission of USSD. EMBANKMENT DAM SEEPAGE MODIFICATIONS CHOICES AND CONSIDERATIONS
More informationVERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment
VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment rotary drill hydro-mill backhoe Clamshell + Kelly bar VERTICAL BARRIERS SLURRY
More informationGround Improvement. Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting
Ground Improvement Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting www.malcolmdrilling.com Cutter Soil Mixing Multi-Axis Soil Mixing
More informationCompaction and Jet Grouting
Compaction and Jet Grouting Alan Ringen, PE Senior Vice President Breakthroughs in Tunneling Short Course August 16, 2017 Grouting Principles Geotechnical Grouting: The injection of pumpable fluid materials
More informationGround Improvement for Mitigation of Failure Risks to Existing Embankment Dams
Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams by James K. Mitchell, Sc.D., P.E., Dist. M.ASCE University of Alberta, Edmonton, Alberta October 6, 2010 1 SCOPE OF THE LECTURE
More informationMisan University - College of Engineering Civil Engineering Department
CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s
More informationGrouting Bilfinger Spezialtiefbau GmbH
Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com
More informationCHAPTER 8 SEEPAGE CONTROL IN EMBANKMENTS
CHAPTER 8 SEEPAGE CONTROL IN EMBANKMENTS 8-1. General. All earth and rock-fill dams are subject to seepage through the embankment, foundation, and abutments. Seepage control is necessary to prevent excessive
More informationGround Improvement Techniques
GRD Journals Global Research and Development Journal for Engineering Recent Advances in Civil Engineering for Global Sustainability March 2016 e-issn: 2455-5703 Ground Improvement Techniques 1 Nimisha
More informationConstruction Technology B (CON4313)
3 - Basement 1 Quick Revision 1.1 Problems arising from basement construction a. Excavation method. b. Surface and ground water control c. Lateral stability of basement excavation. d. Stability of adjoining
More informationSoldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization
Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization www.malcolmdrilling.com Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning
More informationRIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.
H A Y W A R D B A K E R I N C. RIGID INCLUSIONS Rigid Inclusions offer an economical approach for building on sites underlain by soft soil. Above: HBI installed Rigid Inclusions on a congested downtown
More informationCivil Engineering Construction I (CBE5031)
Civil Engineering Construction I (CBE5031) Basement 1 1 Quick Revision 1.1 Problems arising from basement construction a) Excavation method. b) Surface and ground water control c) Lateral stability of
More informationINSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad CIVIL ENGINEERING
INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad -00 03 CIVIL ENGINEERING QUESTION BANK Course Name : GROUND IMPROVEMENT TECHNIQUES Course Code : A012 Class : III B. Tech IISemester
More informationCOPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii
Preface to the Third Edition xiii About the Authors xv Acknowledgements xvii Contents PART ONE: THEORY...1 1. Groundwater in Construction...3 1.1 Groundwater in the Hydrologic Cycle 3 1.2 Origins of Dewatering
More informationFigure (12.1) Foundation Grouting
Chapter 12 - Foundation Grouting 12. Foundation Grouting 12.1. Introduction: The construction of structures on weak ground often requires the soil to be improved in order to ensure the safety and the stability
More informationLECTURE 35. Module 10 : Improvement of rock mass responses 10.4 UNDERGROUND SUPPORTS. Steel Arch support and steel ribs & laggings
LECTURE 35 10.4 UNDERGROUND SUPPORTS Steel Arch support and steel ribs & laggings Structural steel arch supports and circular ring sets are used for roof support or ground control where severe conditions
More informationGround improvement support using Confined aggregate piers in soft soil. Brian Metcalfe, P.E. Director of Engineering Geopier Foundation Company
Ground improvement support using Confined aggregate piers in soft soil Brian Metcalfe, P.E. Director of Engineering Geopier Foundation Company OUTLINE Ground improvement historical perspective Confined
More informationDESIGN AND CONSTRUCTION OF AN EMBANKMENT DAM IN NEW SOUTH WALES, AUSTRALIA
DESIGN AND CONSTRUCTION OF AN EMBANKMENT DAM IN NEW SOUTH WALES, AUSTRALIA Nor Hamiza Zackaria and Robin Fell Civil Engineering Programme, Universiti Teknologi PETRONAS, Bandar Seri Iskandar, 31750 Tronoh,
More informationJuly 2011 BUREAU OF INDIAN STANDARDS. Draft Indian Standard
FOR COMMENTS ONLY DOC: WRD 8 (551)C July 2011 BUREAU OF INDIAN STANDARDS Draft Indian Standard GUIDELINES FOR DESIGN OF UNDER-SEEPAGE CONTROL MEASURES FOR EARTH AND ROCKFILL DAMS (FIRST REVISION OF IS
More information> GRouTING systems. The experience and expertise to deliver the right grouting solution for the job. Grouting is the most diverse
> GRouTING systems The experience and expertise to deliver the right grouting solution for the job Grouting is the most diverse of all specialty geotechnical disciplines. It encompasses a range of individual
More informationLIMITED MOBILITY GROUTING -- PRACTICE IN NORTH AMERICA. Michael Byle, D.GE, F.ASCE,
LIMITED MOBILITY GROUTING -- PRACTICE IN NORTH AMERICA Michael Byle, D.GE, F.ASCE, Overview INTRODUCTION COMPACTION GROUTING LIMITED MOBILITY GROUTING LMG MATERIALS AND TECHNOLOGY EQUIPMENT GROUT INJECTION
More informationGolder Associates Innovative Applications (GAIA) Inc.
Golder Associates Innovative Applications (GAIA) Inc. Environmental and Geotechnical Applications of Cutter Soil Mixing RemTech October, 2007 Presented by: Brian Wilson www.gaiacontractors.com What is
More informationDIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS
DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com
More informationSECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL
SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division
More informationChapter 1. Introduction to Engineering Ground Modification. The Need for Engineered Ground Improvement
Chapter 1 Introduction to Engineering Ground Modification The Need for Engineered Ground Improvement As more and more land becomes subject to urban or industrial development, good construction sites and
More informationSuccessful Foundation Preparations in Karst Bedrock of the Masonry Section of Wolf Creek Dam
Successful Foundation Preparations in Karst Bedrock of the Masonry Section of Wolf Creek Dam David M. Robison, P.G. Geotechnical and Dam Safety Section, Louisville District, U.S. Army Corps of Engineers
More informationDeep Foundations By. J. Paul Guyer, P.E., R.A. PDHLibrary Course No PDH HOURS
Deep Foundations By J. Paul Guyer, P.E., R.A. PDHLibrary Course No 0010051 3 PDH HOURS An Introduction to Deep Foundations Guyer Partners 44240 Clubhouse Drive El Macero, CA 95618 (530) 758-6637 jpguyer@pacbell.net
More informationBrochure E. The Soilcrete Jet Grouting Process
Brochure 67-03 E The Soilcrete Jet Grouting Process Contents History...3 Soilcrete Jet Grouting Process... 4 Process Variations... 6 Construction Forms... 7 Construction Sequences... 8 Stabilisation...
More informationSECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS
SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE... 44.1 44-1.01 Description... 44.1 44-1.02 Materials... 44.1 44-1.03 Proportions...
More informationGround Improvement. Martin G. Taube, P.E., P.G. February 4, 2003
ODOT Geotechnical Information Exchange Seminar Ground Improvement Martin G. Taube, P.E., P.G. February 4, 2003 Nicholson Construction Company 12 McClane Street Cuddy, PA 15031 ph. (412) 221-4500 fax (412)
More informationBrochure 66-01E. Compaction Grouting
Brochure 66-01E Compaction Grouting Contents The method on the market... 3 Process description... 4 Soil improvement... 6 Foundation rehabilitation... 8 Cavity grouting... 10 2 Development The compaction
More informationLaboratory modeling of erosion potential of seepage barrier material
Utah State University DigitalCommons@USU All Graduate Theses and Dissertations Graduate Studies 5-2013 Laboratory modeling of erosion potential of seepage barrier material Nathan E. Braithwaite Follow
More informationDOUBLE ROW GROUT CURTAIN DESIGN AND CONSTRUCTION FOR CEDAR CREEK DAM IN MALAKOFF, TEXAS. Daniel P. Bole 1 Marc T. Miller, P.E. 2 Billy L.
DOUBLE ROW GROUT CURTAIN DESIGN AND CONSTRUCTION FOR CEDAR CREEK DAM IN MALAKOFF, TEXAS Daniel P. Bole 1 Marc T. Miller, P.E. 2 Billy L. Fisher 3 ABSTRACT This case history presents the design and construction
More informationSlurry Trench / Diaphragm Walls
UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Temporary Structures Slurry Trench / Diaphragm Walls CM 420 TEMPORARY
More informationGround Improvement Specialists
is a design-build specialty geotechnical contractor offering expertise on ground improvement for sites with poor soil. We combine value engineering and innovative techniques to deliver practical, sustainable
More informationAgenda. Alternative Measures (for Cutoffs) for Dams on Karst. Failure Modes Three Techniques. 1. Introduction and Background
Alternative Measures (for Cutoffs) for Dams on Karst Louisville, KY Dr. Donald A. Bruce, Geosystems, L.P. 724-942-0570 Agenda 1. Introduction and Background Failure Modes Three Techniques i. Category I
More informationCE 6012 Ground Improvement Techniques Question Bank
CE 6012 Ground Improvement Techniques Question Bank Unit I INTRODUCTION Role of ground improvement in foundation engineering - methods of ground improvement Geotechnical problems in alluvial, laterite
More informationA Case Study: Foundation Design in Liquefiable Site
RESEARCH ARTICLE OPEN ACCESS A Case Study: Foundation Design in Liquefiable Site Tahar Ayadat* *(Department of Civil Engineering, College of Engineering, PMU University, P.O. Box 1664, Al-Khobar, 31952,
More informationAssalamualaikum & Good Morning (May All Of You Gain A Better Understanding)
Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding) Always Try To Do The Best In Your Life TYPES OF FOUNDATION TYPES OF FOUNDATION a) Shallow Foundation System i) Spread Foundation
More informationIntroduction to Foundations on Fill and Backfilling
Introduction to Foundations on Fill and Backfilling Course No: G01-003 Credit: 1 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm Court
More informationSECTION EROSION CONTROL DEVICES
SECTION 02374 PART 1 GENERAL EROSION CONTROL DEVICES 1.1 SUMMARY A. Section Includes: 1. Diversion Channels. 2. Rock Energy Dissipator. 3. Paved Energy Dissipator. 4. Rock Basin. 5. Rock Barriers. 6. Sediment
More informationConstruction and Geotechnical Issues
AECOM port project images here Original must be proportionate to 25.4cm x 8cm Image here Original must be square Image here Original must be square Image here Original must be square Construction and Geotechnical
More informationGround Modification Applications for Bio-Fuel Plants Raymond J. Franz, P.E. Roselle, IL
Geotechnics and Supplying Future Energy Needs: Ground Modification Applications for Bio-Fuel Plants Raymond J. Franz, P.E. Roselle, IL Bio-Fuel Facilities Current and future energy needs demand consideration
More informationAPPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014
GEOTECHNICAL INVESTIGATION UPDATE. CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014 October 5, 2013 Project No. SCR-0720 SANTA CRUZ SEASIDE COMPANY Craig French 911 Center Street, Suite B Santa
More informationGeotechnical Engineering
Geotechnical Engineering Part of a diversified family of solutions www.jmt.com An Employee Owned Company Geotechnical Engineering JMT s very experienced staff in design and construction testing services
More informationTypical flow net for the flow beneath the dam with heel cutoff wall [Lambe & R.V. Whitman (1979)]
Typical flow net for the flow beneath the dam with heel cutoff wall [Lambe & R.V. Whitman (1979)] Typical flow net for the flow beneath the dam with toe cutoff wall [Lambe & R.V. Whitman (1979)] Exit gradient
More informationtwenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013
ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013 lecture twenty six concrete construction: www.tamu.edu foundation design Foundations 1 Foundation the engineered
More informationKIEWIT FOUNDATIONS CO.
KIEWIT FOUNDATIONS CO. KIEWIT ADVANTAGE LOCAL CONTRACTOR, EXPANSIVE REACH With a strong local presence, access to a vast network of resources throughout North America and a focus on self-performing work,
More informationChapter 8 Anchoring Structures
Chapter 8 Anchoring Structures 8-1. General Structural anchors are often used to improve the stability of existing structures but, generally, should not be used as a primary means to stabilize new, large
More informationAn Introduction to Seepage, Slope and Settlement of Levees
An Introduction to Seepage, Slope and Settlement of Levees Course No: G02-011 Credit: 2 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm
More informationRemedial grouting works to two dams in Hong Kong
Remedial grouting works to two dams in Hong Kong D. GALLACHER, AECOM, Edinburgh, UK SYNOPSIS. Tai Tam Upper and West Col Dams in Hong Kong had experienced substantial leakage over an extended period. Recommendations
More informationPonds: planning, design, and construction
Ponds: planning, design, and construction Ponds for many purposes: Fish Production Recreation Water Supply Esthetics Wildlife Habitat Natural ponds: Formed in natural depressions in the landscape Not man-made
More informationGEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO
GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST
More informationModular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000
The Institution of Engineers of Ireland Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000 MODULE 4 RETAINING STRUCTURES DEEP EXCAVATIONS
More informationCUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT
CUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT By John Kvinsland Malcolm Drilling Company, Kent, Washington Bob Plum ASCE, P.E., Principal Kleinfelder Consultants, Seattle
More informationTSAILE DAM MODIFICATION PROJECT Unearthing a Safer Dam
TSAILE DAM MODIFICATION PROJECT Unearthing a Safer Dam Bureau of Indian Affairs Navajo Regional Safety of Dams Program Stephen G. Brown, PE Kleinfelder Acknowledgements C. Scott Goss BIA Chief Safety of
More informationtwenty seven concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design
ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SRING 2017 lecture twenty seven Foundation the engineered interface between the earth and the structure it supports that transmits
More informationtwenty four foundations and retaining walls Foundation Structural vs. Foundation Design Structural vs. Foundation Design
ALIED ARCHITECTURAL STRUCTURES: STRUCTURAL ANALYSIS AND SYSTEMS DR. ANNE NICHOLS SRING 2018 lecture twenty four Foundation the engineered interface between the earth and the structure it supports that
More informationTunnelling and Underground. Construction Technology
Construction Technology Course Lectures Part 2.2 Ground Improvement Dr Ákos TÓTH 1 Ground Treatment and Improvement In order to improve the construction process when tunnelling through poor ground, a double
More informationSOIL AND FOUNDATION INVESTIGATION PROPOSED DUPLEX 3966 VRAIN STREET DENVER, COLORADO
SOIL AND FOUNDATION INVESTIGATION PROPOSED DUPLEX 3966 VRAIN STREET DENVER, COLORADO Prepared for: G.J. GARDNER HOMES ATTN: DAVE PAGANO 7660 RALEIGH STREET WESTMINSTER, COLORADO 80030 PROJECT NO. 1090
More informationChapter 3: Summaries of Case Histories
Chapter 3: Summaries of Case Histories This chapter presents summaries of 30 case studies on the performance of seepage barriers in dams that were reviewed for this study. Information was collected on
More informationSECTION EROSION CONTROLS
SECTION 31 25 13 EROSION CONTROLS PART 1 GENERAL 1.1 SUMMARY A. Section Includes installing, maintaining and removing: 1. Silt Fence. 2. Temporary Construction Entrances. 3. Diversion Channels. 4. Sediment
More informationAPPLICATIONS SOILFRAC SOILCRETE PERMEATION COMPACTION INFILL. Underpinning. Settlement Control. Settlement Reversal. Void Grouting.
Specialist Grouting GROUTING SOLUTIONS Keller Ground Engineering has sixty years grouting experience. Whether a common application or one that draws upon our unparalleled experience and creativity throughout
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-31 60 00 (November 2008) ----------------------------- Preparing Activity: USACE Superseding UFGS-31 60 00 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
More informationSECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS
SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE... 44.1 44-1.01 Description... 44.1 44-1.02 Materials... 44.1 44-1.03 Proportions...
More informationA COLLABORATIVE SUCCESS CONSTRUCTION OF THE MORMON ISLAND AUXILIARY DAM KEY-BLOCK FOR SEISMIC REHABILITATION. Abstract
A COLLABORATIVE SUCCESS CONSTRUCTION OF THE MORMON ISLAND AUXILIARY DAM KEY-BLOCK FOR SEISMIC REHABILITATION M. Jonathan Harris, P.E. 1 Eric S. Lindquist, P. E. 2 Rob Jameson 3 Trace Porter 4 Abstract
More informationPassion for Progress... and Progress in Water Resource Development
BAUER on Large Dams Passion for Progress... and Progress in Water Resource Development Based on experience of more than fifty years BAUER Spezial tiefbau GmbH as the parent company within the BAUER Group,
More informationSECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS
SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE 44-1 44-1.01 Description 44-1 44-1.02 Materials 44-1 44-1.03 Proportions 44-1 44-1.04
More informationGround Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan
Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan INSERT DATE HERE Ground Improvement - What is it? Ground Improvement = Black Box? Ground Improvement - Introduction Ground
More informationSECTION XXXXX STONE COLUMNS PART 1 - GENERAL
SECTION XXXXX STONE COLUMNS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division 01
More informationReview and Feasibility Assessment of Offshore Ground Improvement Methods
Review and Feasibility Assessment of Renmin Zhang, Postgraduate Student AOG 2017 Background Final semester study project (6 months) Course completion fulfillment Master of Subsea Engineering (MC-SBSENG)
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationProblems in Improvement Evaluation, QA and QC
Problems in Improvement Evaluation, QA and QC Specifying test types, locations, and frequency Representativeness of samples Variability in treatment and uncertainty about acceptable amount of variability
More informationIV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec- 2014
Set No. 1 1 a) What is dewatering? What are the objectives of dewatering? b) Explain in detail about the Electro-osmosis theory with neat sketch. 2 a) What are different types of grouts available and what
More informationC. Foundation stabilization for pipe and utility structures.
PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization
More informationSECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)
PART 1 GENERAL 1.01 WORK INCLUDED SECTION 02360 / 31 34 30.13 ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) A. Provide all equipment, material, labor and supervision to design and
More informationPaul Brunner, Larry Dacus, Doug Handen. Repairs to Concrete-Lined V-Ditch Alternatives Evaluation
Memo To: Paul Brunner, Larry Dacus, Doug Handen From: Alberto Pujol /Dan Wanket Date: 09/10/2010 Re: Feather River Levee Site 7 Extension Repairs to Concrete-Lined V-Ditch Alternatives Evaluation This
More informationA COLLABORATIVE SUCCESS CONSTRUCTION OF THE MORMON ISLAND AUXILIARY DAM KEY-BLOCK FOR SEISMIC REHABILITATION. Abstract
A COLLABORATIVE SUCCESS CONSTRUCTION OF THE MORMON ISLAND AUXILIARY DAM KEY-BLOCK FOR SEISMIC REHABILITATION M. Jonathan Harris, P.E. 1 Eric S. Lindquist, P. E. 2 Rob Jameson 3 Trace Porter 4 Abstract
More informationNPTEL Course on Ground Improvement
NPTEL Course on Ground Improvement Prof. G. L. Sivakumar Babu (Questions) Module I - Introduction to Ground Improvement L1: Need for Ground Improvement 1. What are different types of engineering problems
More informationThe Problem. Embankment Dams on Karstic Limestone, Soluble and Erodible Foundations: Challenges and Solutions GEOSYSTEMS, L.P.
Embankment Dams on Karstic Limestone, Soluble and Erodible Foundations: Challenges and Solutions Donald A. Bruce, Geosystems, L.P. Keith Ferguson, Kleinfelder, Inc. GEOSYSTEMS, L.P. The Problem Centerhill
More informationWater Well Decommissioning Guidelines
Water Well Decommissioning Guidelines Approval Date: June 1, 2007 Effective Date: September 10, 2007 Approved By: Gerard MacLellan Version Control: This is a new guideline I. Introduction The Water Well
More informationTHENI KAMMAVAR SANGAM COLLEGE OF TECHNOLOGY CE2033- GROUND IMPROVEMENT TECHNIQUES UNIT 1 INTRODUCTION
CE2033- GROUND IMPROVEMENT TECHNIQUES UNIT 1 INTRODUCTION 1. What is expansive soil? Give one example. Expansive soils contain minerals such as smectite clays that are capable of absorbing water. When
More information3.5 GEOLOGY, SOILS, AND GROUNDWATER
TIER II DRAFT ENVIRONMENTAL IMPACT STATEMENT 3.5 GEOLOGY, SOILS, AND GROUNDWATER The analyses conducted in this section of the Tier II Draft EIS focus on the potential impacts on adjacent resources. Potential
More informationUSE OF TRENCH DRAINS TO IMPROVE CHRONIC EMBANKMENT STABILITY PROBLEMS. and SHANNON & WILSON, INC. ABSTRACT
USE OF TRENCH DRAINS TO IMPROVE CHRONIC EMBANKMENT STABILITY PROBLEMS by Steven R. McMullen, P.E. Principal Engineer and Dexter N. McCulloch, C.E.G. Senior Vice President SHANNON & WILSON, INC. ABSTRACT
More informationSeepage Cutoffs for Dams: Reassertion of the Composite Wall Concept
Seepage Cutoffs for Dams: Reassertion of the Composite Wall Concept Dr. Donald A. Bruce GEOSYSTEMS, L.P. Contents of Today s Presentation 1. Review of Concrete Cut-Off Wall Construction 2. Review of Contemporary
More informationDHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE FOUNDATION ENGINEERING UNIT 1
DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE6502 - FOUNDATION ENGINEERING Subject Code: CE6502 UNIT 1 1. What are the informations obtained
More informationPlastic concrete cutoff walls have been used for
The world s largest cutoff wall at Karkheh dam A.A. Mirghasemi, Mahab Ghodss Co. and University of Tehran, Iran M. Pakzad, Mahab Ghodss Co., Iran B. Shadravan, University of Ottawa, Canada The Karkheh
More informationProceedings of the 10 th Australia New Zealand Conference on Geo-Mechanics, Common Ground Brisbane Australia, October 2007
Page 1 of 6 Proceedings of the 10 th Australia New Zealand Conference on Geo-Mechanics, Common Ground Brisbane Australia, October 2007 Vertical groundwater barriers for contaminated site reclamation Christopher
More informationASSOCIATION OF STATE DAM SAFETY OFFICIALS VOLUME 14 ISSUE ISSN
ASSOCIATION OF STATE DAM SAFETY OFFICIALS VOLUME 14 ISSUE 2 2016 ISSN 1944-9836 IN THIS ISSUE: Depression at Nesbitt Dam Developing a Dam Emergency Intervention Toolbox Lake Delhi Dam Reconstruction Technology
More informationGROUND ENGINEERING. Vibro Ground Improvement
Vibro Ground Improvement Deep vibro techniques present flexible solutions for soil improvement. They are mainly used under foundations of structures that are to be constructed on soils of low bearing capacity
More informationAPPENDIX 5: CONSTRUCTION CHECKLISTS
APPENDIX 5: CONSTRUCTION CHECKLISTS This appendix presents the construction checklists for the various retaining wall mitigation strategies: 10.1 Void Fill 10.2 Surface Bond Overlay 10.3 Reinforced Overlay
More information1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK
1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for
More informationSECTION TRENCHING
SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.
More informationSLURRY WALLS FOR SEEPAGE CUTOFF IN LEVEE APPLICATIONS RECENT EXPERIENCE AND CONSTRUCTION CHALLENGES IN THE NORTHERN CENTRAL VALLEY OF CALIFORNIA
SLURRY WALLS FOR SEEPAGE CUTOFF IN LEVEE APPLICATIONS RECENT EXPERIENCE AND CONSTRUCTION CHALLENGES IN THE NORTHERN CENTRAL VALLEY OF CALIFORNIA Deep Foundation Institute Slurry Wall Committee July 22,
More informationSITE INVESTIGATION. Foundation Engineering
SITE INVESTIGATION Assist. Prof. Berrak TEYMUR Foundation Engineering Analysis Design Construction As a foundation engineer, you need to consider geotechnical/structural issues (involves geology, subsurface
More informationBehavior of Geosynthetic-Reinforced Earth
Behavior of Geosynthetic-Reinforced Earth Presented by Kousik Deb Assistant Professor Department of Civil Engineering IIT Kharagpur Problems for Foundations on Weak Soils Experience excessive settlement
More informationJune i TABLE OF CONTENTS
June 2005 - i - 05-526 TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 1 1.1 Purpose of the Investigation... 1 1.2 Description of the Project and Scope of Work... 1 1.3 Site Geology... 1 1.4 Site Description
More informationEarth Retaining System
Hashemite University Department of Civil Engineering Foundation Engineering Dr. Omar Al-Hattamleh Earth Retaining System Earth slopes and earth retaining structures Used to maintain two different ground
More informationUS ARMY CORPS OF ENGINEERS ALASKA DISTRICT BUILDING STRONG. 21 September Coleman Chalup, P.E. Lead Engineer USACE Alaska District
US ARMY CORPS OF ENGINEERS ALASKA DISTRICT Chena River Lakes Flood Control Project/Moose Creek Dam, North Pole, Alaska - USACE Design, Cost, And Constructability Considerations For CSM Barrier Walls In
More information