FROM HARD-EARNED LESSONS TO GREAT PROJECTS
|
|
- Alan Bond
- 6 years ago
- Views:
Transcription
1 FROM HARD-EARNED LESSONS TO GREAT PROJECTS 2017 MODERATOR: FRANK GIUNTA, HILL INTERNATIONAL/HKA RICHARD SMYTH, PROJECT EXECUTIVE, LAGUARDIA AIRPORT GREG CAMPBELL, CHIEF AIRPORT S ENGINEER, LAWA KEVIN ROBINS, DIRECTOR ENGINEERING, SALT LAKE CITY INTERNATIONAL Special Thanks To:
2 SUCCESSFUL PROJECT FOCUS ON COMMUNICATION The High Cost of Low Performance: The Essential Role of Communications, PMI s Pulse of the Profession In-Depth Report, Project Management Institute, May
3 1 The project team is lacking in the necessary expertise, experience, breadth, and depth to successfully execute the project. TOP 10 LEADING INDICATORS 2 The project team is experiencing a high turnover rate and instability in team membership. 3 The project team s response to Requests for Information, questions, and changing events that can significantly impact the project results is slow, inadequate, or incomplete. 4 The project team is losing confidence in the accuracy and validity of the project schedule. 5 Project milestones are not being met and are consequently jeopardizing future project milestones. 6 Construction is awarded before adequate completion of project design, including discipline design packages, resulting in an incomplete scope definition at time of award/start of construction. 7 Business goals, project objectives and priorities, and critical success factors are not being consistently used by project team members and key stakeholders to guide decisions. 8 Owner and/contractor are requesting an excessive number of contract changes and/or scope changes during project execution. 9 Significant project scope items are inadvertently omitted from bid packages. 10 Some project participant companies become financially unstable.
4 Surviving the Unexpected LAGUARDIA AIRPORT RICHARD SMYTH, PROJECT EXECUTIVE Early Planning: How a P3 structure enabled LaGuardia s Central Terminal construction to avoid unexpected logistical hiccups on a complex site. LAWA GREG CAMPBELL, CHIEF AIRPORT S ENGINEER Thinking on the fly: How an unexpected safety condition during construction of a 12-gate concourse forced the project team to think on the fly when dealing with troubles from an existing sewer line. SALT LAKE CITY INTERNATIONAL, KEVIN ROBINS, DIRECTOR ENGINEERING Unavoidable Change in Scope: How SLC dealt with an additional car rental facility requirement after design was complete and construction commenced. 4
5 RICHARD SMYTH PORT OF NEW YORK AND NEW JERSEY 2017 Special Thanks To:
6 6
7 7
8 8
9 9
10 10
11 11
12 12
13 13
14 14
15 15
16 GREG CAMPBELL LOS ANGLES WORLD AIRPORTS 2017 Special Thanks To:
17 Midfield Satellite Concourse Over North Outfall Sewer Easement Authority Shifted Concern Risk Assessment Risk Assessment No Mitigation Alternatives Monitoring 17
18 18
19 19
20 20
21 Midfield Satellite Over NORS Easement area/concourse location North Outfall Relief Sewer serves 600,000 residents 21
22 22
23 KEVIN ROBINS SALT LAKE CITY INTERNATIONAL 2017 Special Thanks To:
24 SLC Terminal Redevelopment Program 24
25 All existing terminal area facilities will be replaced. Complex phasing to minimize impacts to airport operations. Construction period 2014 through
26 Existing car rental service facilities required relocation to allow terminal and roadway construction to begin. 26
27 Enabling package included: Site utilities Replacement parking Quick Turn Around Facility (QTA) Rental Car Service Sites (RSS) $89 million GMP QTA Replacement Parking RSS 27
28 QTA and RSS facilities designed for 6 RAC tenants. 28
29 The only constant is change. Concurrent with bidding for trade contractors, SLCDA was soliciting for Rental Car leases. After construction had started, SLCDA determined to add a seventh Rental Car tenant. Design team issued 17 bulletins to construction documents to incorporate required changes. CMAR negotiated and processed 65 change orders totaling $11.25 million in direct trade costs. 29
30 High Performing Integrated Team Teamwork and cooperation between Designer, Program Manager, and CMAR minimized cost and schedule impacts to overall program. QTA and RSS facilities were completed with only a six week impact to schedule. RAC tenants moved in to new facilities in late March
31 Q & A 31
olos Angeles World Airports
i Approval i BY I' olos Angeles World Airports lc W w.00 REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: Iten',. Approved byeg.. Campb- irports Engineer 8/18/2016 Reviewed by: 'og ra. Johnso,/Deputy
More informationAlternative Project Delivery Methods and Procurement
Alternative Project Delivery Methods and Procurement Board of Airport Commissioners Meeting 2 June 2014 Presented by: Roger A. Johnson, Deputy Executive Director Definitions Project Delivery Method o The
More informationPresentation for Business Opportunities & Entrepreneurial Training Summit
Welcome to the Presentation for Business Opportunities & Entrepreneurial Training Summit October 9, 2018 Ned Carey, C.M. Chief - Division of Administration & Performance Management Safety Management System
More informationWHEREAS, a list of the selected capital improvement projects and their key elements is included as Attachment A; and
Los Angeles World Airports RESOLUTION NO. 25681 LAX LA/Ontario Van Nuys City of Los Angeles Eric Garcetti Mayor Board of Airport Commissioners Sean 0. Burton President Valeria C. Velasco Vice President
More informationLAWA Update Ground Transportation Planning and Metro Coordination
LAWA Update Ground Transportation Planning and Metro Coordination SPAS Approved LAX Ground Transportation Projects The Specific Plan Amendment Study (SPAS) includes LAX Ground Transportation Projects:
More informationLos Angeles World Airports
.00 10 01 Los Angeles 00.0 1 World Airports July 31, 2014 LAX LA/Ontario Van Nuys City of Los Angeles Eric Garnett Mayor Board of Airport Commissioners Sean 0. Burton President Valeria C. Velasco Vice
More informationAGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor April 9, :30 a.m.
AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting March 12, 2014 Executive Director Approval
More informationEnter a world of efficiency Page 1
Enter a world of efficiency Page 1 Enter a world of efficiency Page 2 Relations Cooperation Understand Agency Goals Address Issues Openly Find Common Goals Voluntary Without Legislation Enter a world of
More informationBriefing Session: A406 STRATEGIC PROJECTS PROGRAM MANAGEMENT. January 24, 2019
Briefing Session: A406 STRATEGIC PROJECTS PROGRAM MANAGEMENT January 24, 2019 BRIEFING SESSION 1. Introduction to strategic projects at Logan B to C Roadway Improvements Terminal C Canopy and Curbside
More informationSLC Terminal Redevelopment Program. Salt Lake City International Airport
SLC Terminal Redevelopment Program Salt Lake City International Airport Terminal Redevelopment Program Goals and Expectations Address Seismic Risk Provide Right-Sized Facilities Solve Operational Problems
More informationDISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY RFP 18-PR-HCM-12 EXECUTIVE SEARCH SERVICES SCOPE OF WORK ATTACHMENT A
DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY RFP 18-PR-HCM-12 EXECUTIVE SEARCH SERVICES SCOPE OF WORK ATTACHMENT A Table of Content Section Page 1.0 Background 3 2.0 Contractor Qualifications 3 3.0 Scope
More informationAGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor April 11, :30 a.m.
AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting March 14, 2018 Executive Director Approval
More informationMidfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) BOAC Status Update May 4, 2017
Midfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) BOAC Status Update May 4, 2017 Presented by: Robert Gilbert, CDO & Mark Skjervem, MSC Element Manager 1 Agenda Midfield Satellite
More informationLove Field Concessions Options
Love Field Concessions Options Briefing for the City Council Department of Aviation August 18, 2010 Background 6/11/07 Briefed proposal to TEC to extend existing concession contracts through period of
More informationProject Management for the Supply Professional
Project Management for the Supply Professional Dr. Rene G. Rendon, CPSM, C.P.M., CPCM, PMP U. S. Naval Postgraduate School (831) 656-3464 rgrendon@nps.edu 95 th Annual International Supply Management Conference,
More informationOAKLAND ARMY BASE REDEVELOPMENT. May 28 th, 2013 Oakland City Council Community and Economic Development Committee Project Update
OAKLAND ARMY BASE REDEVELOPMENT May 28 th, 2013 Oakland City Council Community and Economic Development Committee Project Update OBJECTIVES Aggressively grow new cargo activity, jobs, and revenue through
More informationLos Angeles World Airports
Los Angeles World Airports m RESOLUTION NO. 26178 BE IT RESOLVED that the Board of Airport Commissioners approved Resolution requesting the Los Angeles City Council consider and approve an ordinance allowing
More informationBOARD OF AIRPORT COMMISSIONERS
I ELy RW BY KV -4.01, 110%,ii ". 1 Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS I. Approved by: GI -g S. Campbell, Chief Airports Engineer II Meeting Date: 10/18/2018 1 1 Completed
More information3. ADOPT the SPAS Mitigation, Monitoring and Reporting Program (MMRP).
, Meeting Date: February 5, 2013 Completed Pending N/A Rev lewev for Capital Budget Operating Budget CEQA 01130/13 01/31/13 01/31/13 01/30/13 APoroval Status EIY D N DNA EIYONDNA Y N MYDNOCand By DS RW
More informationCONSTRUCTRION MANAGEMENT AT RISK ASHE December 13, 2011 Julio Alvarado Construction State Engineer
CONSTRUCTRION MANAGEMENT AT RISK CM@R ASHE December 13, 2011 Julio Alvarado Construction State Engineer 1 Agenda Background What leads DOT s to CMAR? ADOT s Outlook on CMAR Project Updates CMAR Benefits
More informationReport to the BOARD OF AIRPORT COMMISSIONERS
Los A ngeles W orld A irports Report to the BOARD OF ARPORT COMMSSONERS tem h 0 r ApProve b : ntissar am,,s a.-f Airports Engineer Meeting Date: August 20, 2013 - "Af Reviewed by oger A. on, Deputy Executive
More informationREQUEST FOR PROPOSAL PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM PROGRAM MANAGEMENT SERVICES
REQUEST FOR PROPOSAL PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM PROGRAM MANAGEMENT SERVICES The Allegheny County Airport Authority (ACAA) is soliciting proposals from interested and
More informationKNIGHT FRANK COMMERCIAL RESEARCH
KNIGHT FRANK COMMERCIAL RESEARCH K N I G H T F R A N K R E S E A R C H Knight Frank s Commercial Research team, based in London, comprises 16 multi-disciplined professionals who have a considerable depth
More informationMidfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) Board of Airport Commissioners (BOAC) Construction Update #4
Midfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) Board of Airport Commissioners (BOAC) Construction Update #4 October 18, 2018 1 Agenda Midfield Satellite Concourse Project (MSC)
More informationTHE TRUE VALUE OF PROJECT RISK ANALYSIS
THE TRUE VALUE OF PROJECT RISK ANALYSIS Dr. Dan Patterson, PMP Chief Design Officer, PLANNING & SCHEDULING Introduction Much has been written in recent years about the benefits of conducting a project
More informationIdentification Selection Definition Execution. Schedule.
SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification
More informationCertification of Compliance
Certification of Compliance Thi s Certification is del ivered by LaGuardia Gateway Partners, LLC (the "Obligated Person") pursuant to that certain Disclosure Dissemination Agent Agreement dated as of May
More informationSustainability & Environmental Initiatives at Los Angeles World Airports
Sustainability & Environmental Initiatives at Los Angeles World Airports Intissar Durham, P.E. Chief Airports Engineer Major Projects Director May 28, 2008 Los Angeles World Airports Global Leader in Airport
More information[ITEMS IN BOLD REQUIRE APPROVAL BY THE AVIATION AUTHORITY BOARD]
CONSTRUCTION COMMITTEE MEETING AGENDA DATE: Tuesday, February 12, 2019 TIME: 8:30 a.m. ~ GREATER ORLANDO V AVIATION AUTHORITY PLACE: GOAA ANNEX BUILDING, 1ST FLOOR - CONFERENCE ROOMS (APOLLO/GEMINI/TAURUS),
More informationDeyelopment stages & actions to be taken
Deyelopment stages & actions to be taken I. Development stages and actions to be taken - ho 322, disk 162 1.1. By Ralph J. Stephenson PE 1.2. This material is designed to 1.2.1. 1. Provide a direct stimulus
More informationPACKAGING P3 PROCUREMENTS FOR COMPLEX PROJECTS THE LAX EXPERIENCE
PACKAGING P3 PROCUREMENTS FOR COMPLEX PROJECTS THE LAX EXPERIENCE BRIAN C. OSTLER Deputy City Attorney City of Los Angeles ROGER JOHNSON Airport Program Executive Jacobs BRANDON J. DAVIS Partner Nossaman
More informationINFRASTRUCTURE ADVISORY SERVICES
INFRASTRUCTURE ADVISORY SERVICES Circle of Commitment mitment Com Op po rtu n Sp irit ity d it io n s Prosperity Trust m un T ra Co m it y Re s p e c t In today s increasingly cost-conscious environment,
More informationQueen Alia International Airport Expansion
JORDAN Queen Alia International Airport Expansion Image: Aerial view of the terminal after completion by KRISTIN HOOVER, courtesy of Foster and Partners- Photographer Nigel Young / CC BY-NC-ND 3.0 OVERVIEW
More informationSheffield City Council Strategic Partnership Transition Case Study
Sheffield City Council Strategic Partnership Transition Case Study How Capita and Sheffield City Council worked in partnership to successfully transition ICT, Revenues & Benefits, Financial Business Transactions,
More informationLANDSIDE FACILITIES AIRLINE TERMINAL FACILITIES INVENTORY 5.0 INTRODUCTION C H A P T E R 1 CHAPTER 5
C H A P T E R 1 INVENTORY AIRLINE TERMINAL FACILITIES INVENTORY CHAPTER 5 LANDSIDE FACILITIES 5.0 INTRODUCTION This chapter focuses on the landside circulation and access system at the Spokane International
More informationREQUEST FOR QUALIFICATIONS AND PROPOSALS
REQUEST FOR QUALIFICATIONS AND PROPOSALS CONSTRUCTION MANAGER AT RISK SERVICES Preconstruction Phase Services and Construction Phase Services Sheridan Economic and Educational Development Authority Sheridan
More informationCommon Myths and Best Practices. By Gr e g o r y A. Ga r r e t t
Common Myths and Best Practices By Gr e g o r y A. Ga r r e t t 16 Contract Management October 2009 Examining 10 common myths and several best practices of risk management can help you apply an effective
More informationPartnering for Alternative Delivery Projects
Partnering for Alternative Delivery Projects Presented by: Renee L. Hoekstra, CVS Managing Partner RHA, LLC Julie Kliewer, PhD, P.E. State Construction & Materials Engineer - ADOT Training Objectives Understanding
More informationLAX INTERNATIONAL AIRPORT
LAX INTERNATIONAL AIRPORT ACHIEVING OPERATIONAL EXCELLENCE Dominic Nessi Deputy Executive Director/CIO 06.24.2015 WELCOME/INTRODUCTION Los Angeles International Airport 5 th busiest airport in the world
More informationREQUEST FOR PROPOSAL: WIOA Integrated Data Systems Report
REQUEST FOR PROPOSAL: WIOA Integrated Data Systems Report National Association of State Workforce Agencies National Association of Workforce Boards Circulation Date December 18, 2017 Proposal Submission
More informationLeasehold Officer Location: Liverpool with travel across all locations
Job details Job title: Commercial Manager Responsible to: Head of Sales and Commercial Property Responsible for: Leasehold Officer Location: Liverpool with travel across all locations Overview of the role
More informationChief Operating Officer. Building Vibrant Engaged Communities
Chief Operating Officer Building Vibrant Engaged Communities square feet of second floor commercial space in October 2014. The COO is responsible for finalization of new office space configurations and
More informationOakland International Airport-Materials Management Program (MMP) Updated November 2007
Fact Sheet Oakland International Airport-Materials Management Program (MMP) Over the next several years, Oakland International Airport (OAK) has many facilities requiring infrastructure improvements including,
More informationDesign/Build Institute of America Rocky Mountain Region Water/Wastewater Committee. Project Delivery Selection Approach
Design/Build Institute of America Rocky Mountain Region Water/Wastewater Committee Project Delivery Selection Approach Overview This document provides an approach for water and wastewater project delivery
More informationNational Development Programs Manual
National Development Programs Manual August 2014 V5 For further information, please contact: Diabetes Australia GPO Box 3156 Canberra ACT 2601 Fax: (02) 6230 1535 Email: admin@diabetesaustralia.com.au
More informationProject Process Improvement
Project Process Improvement Improving Project Performance through Process Re-Design Better Performance from the Management of Processes Kevin Raum Phil Cooke Welcome Kevin Raum Phil Cooke Principal Consultant
More informationREPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PUBLIC WORKS AND UTILITIES DEPARTMENT NORTH PRIMARY SANITARY GRAVITY MAIN UPGRADE
June 7, 2017 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PUBLIC WORKS AND UTILITIES DEPARTMENT ON NORTH PRIMARY SANITARY GRAVITY MAIN UPGRADE PURPOSE To seek Council s authorization to utilize
More informationPRINCIPAL ENGINEER. 4. Prepare plans and studies to forecast section and division needs; implement recommendations.
PRINCIPAL ENGINEER Class specifications are intended to present a descriptive list of the range of duties performed by employees in the class. Specifications are not intended to reflect all duties performed
More informationPresented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division
Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division Project Delivery Methods Design-Bid-Build (DBB) Indefinite Delivery/Indefinite Quantity (ID/IQ) Construction Management at Risk
More informationALTERNATIVE PROJECT DELIVERY METHODS
ALTERNATIVE PROJECT DELIVERY METHODS Capital Contracting Office April 2016 1 This Class will Cover Overview of Contracts Focus on CMR and JOC Contracting Opportunities Contract Tool Box: Choosing the right
More informationProgressive Design-Build
November 15,2016 Progressive Design-Build A Smart Alternative to Lease/Lease back? PRESENTERS Praful Kulkarni, AIA Rebekah Gladson, FAIA, DBIA Robynne T. Parkinson, JD, DBIA Presentation Outline Value
More informationSUMMARY MINUTES STRATEGIC DEVELOPMENT COMMITTEE MEETING OF APRIL 15, 2015
SUMMARY MINUTES STRATEGIC DEVELOPMENT COMMITTEE MEETING OF APRIL 15, 2015 Mr. Chapman chaired the April 15 Strategic Development Committee Meeting, calling it to order at 10:54 a.m. A quorum was present
More informationPURCHASING DEPARTMENT JOB ORDER CONTRACTING AUDIT JULY 20, 2010
PURCHASING DEPARTMENT JOB ORDER CONTRACTING AUDIT 10-01 JULY 20, 2010 CITY OF TAMPA Pam Iorio, Mayor Internal Audit Department Roger Strout, Internal Audit Director July 20, 2010 Honorable Pam Iorio Mayor,
More informationLos Angeles International Airport (LAX)
Los Angeles International Airport (LAX) LAX 1960 s LAX Today LAX is the largest commercial service airport in southern California 3 rd busiest airport in the United States with approximately 66.6 million
More informationPWCSA CONSTRUCTION MANAGEMENT AT RISK (CMAR) PROJECT DELIVERY
PWCSA CONSTRUCTION MANAGEMENT AT RISK (CMAR) PROJECT DELIVERY Outline What is the CMAR Delivery Method? What are the statutory requirements? Why use it at PWCSA? What are the different roles of the project
More informationVersion 1.0. The Contract Management Standard Final Edition. Version 1.0
The Management Standard Final Edition 1 Purpose of the Management Standard The purpose of the Management Standard is to describe the nature of contract management in terms of the contract management processes
More informationUpdate on the Landside Access Modernization Program (LAMP) & Release of DRAFT ConRAC Request for Proposals (RFP)
Update on the Landside Access Modernization Program (LAMP) & Release of DRAFT ConRAC Request for Proposals (RFP) Board of Airport Commissioners Meeting November 2, 2017 Update: Major LAMP Program Elements
More informationSUBJECT: EVALUATION OF ACTION PLAN - CITYWIDE CHANGE ORDER MANAGEMENT PROCESS
Ron Galperin Controller December 22, 2015 Eugene D. Seroka, Executive Director The Port of Los Angeles 425 S. Palos Verdes Street San Pedro, CA 90733-0151 SUBJECT: EVALUATION OF ACTION PLAN - CITYWIDE
More information0...- Los Angeles W orld Airports
_...4 0...- Los Angeles W orld Airports Report to the BOARD OF AIRPORT COMMISSIONERS 0 i A AI A I Approved7: Denise, : wr, 7 Executive Assistant Airports R 'e y: D.. 1).,:owers, Deputy Executive Director
More informationWhat We Know Now: Lessons Learned Implementing Federal Financial Systems Projects
Forum: Driving Performance Strategies for More Effective Government What We Know Now: Lessons Learned Implementing Federal Financial Systems Projects By Debra Cammer Hines and Angela Carrington This contribution
More informationPosition Description
Position Description Position: Location: Department: Reports to: Status: Senior Project Manager Gold Coast Planning and Projects General Manager Planning and Projects Full Time Purpose of the role: The
More informationConstruction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119
Clark County Department of Aviation Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Professional Service Contracts Construction Contracts Professional Service Contracts
More informationREPORT TO THE BOARD OF DIRECTORS
REPORT TO THE BOARD OF DIRECTORS RECOMMENDATION TO AWARD A CONTRACT FOR THE ON-CALL ARCHITECTURAL/ENGINEERING DESIGN SERVICES FOR CAMPUS UTILITY DISTRIBUTION AND CENTRAL PLANT IMPROVEMENTS AT RONALD REAGAN
More informationCAPITAL INVESTMENT SYSTEMS MAKING THE RIGHT INVESTMENT DECISIONS
INTRODUCTION CAPITAL INVESTMENT SYSTEMS MAKING THE RIGHT INVESTMENT DECISIONS Neil Cusworth Managing Director Enthalpy Pty Ltd Investment decisions to develop or acquire new capital assets should be made
More informationKPMG LLP Suite 1500 550 South Hope Street Los Angeles, CA 90071-2629 September 16, 2015 Mr. Ron Galperin City Controller City of Los Angeles 200 North Main Street Los Angeles, CA 90012 Dear Mr. Galperin:
More informationReport on Effectiveness of the Construction Manager at Risk Project Delivery Method
Report on Effectiveness of the Construction Manager at Risk Project Delivery Method The project management plans described below, establish several elements or criteria for university project staff to
More informationTrinity Well Field and Production Facilities Project Management Using CMAR
Trinity Well Field and Production Facilities Project Management Using CMAR Ian Taylor, P.E., PMP New Braunfels Utilities David Bennett, P.E. Freese and Nichols Kirby Anderson MGC Contractors February 27,
More informationAirport of the Future. Air Cargo Conference June 2017
Airport of the Future Air Cargo Conference June 2017 How CVG landed its biggest deal in history. The deal at $1.49 billion is the largest ever one-time capital investment by a company in Northern Kentucky,
More informationCCMS. Construction Cost Management Services. Celebrating 27 Years.. Construction Cost Estimating Expertise
CCMS Construction Cost Management Services Celebrating 27 Years.. Construction Cost Estimating Expertise Credibility and Confidence at Each Stage of the Planning and Design Process CCMS CCMS ensures that
More informationVersion 1.0. The Contract Management Standard Final Edition. Version 1.0
The Management Standard Final Edition 1 Purpose of the Management Standard The purpose of the Management Standard is to describe the nature of contract management in terms of the contract management processes
More informationAgenda. 2. Consider the Authority s Storm Water Pollution Prevention Plan (Director of Engineering)
Notice of Public Meeting of the DES MOINES AIRPORT AUTHORITY BOARD DATE: March 12, 2019 TIME: 9:00 a.m. PLACE: Airport Board Room, 2nd Floor, Airport Terminal Call to Order and Roll Call Agenda 1. Consider
More informationPROJECT DELIVERY METHODS
Understanding the Construction Contract Project Delivery Methods ISBA April 7,2017 Copyright 2017 by K&L Gates LLP. All rights reserved. Design Bid Build Design Negotiate Build Construction Manager Advisor
More informationReflections on Planning & Scheduling By Chris Carson, PSP, CCM, PMP
Reflections on Planning & Scheduling By Chris Carson, PSP, CCM, PMP Corporate Director of Project Controls, Alpha Construction and Engineering Corporation 1 The key to successful projects is effective
More informationAGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor July 8, :30 a.m.
AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting June 10, 2015 Approval of Minutes: Special
More informationCentralized Receiving and Distribution Facilities Are They Right for Your Airport?
Centralized Receiving and Distribution Facilities Are They Right for Your Airport? Survey Does your Airport: Want to enhance security and safety? Want to streamline operations? Want to reduce terminal
More information6.0 OTHER ENVIRONMENTAL CONSIDERATIONS 6.1 Significant Unavoidable Impacts
6.0 OTHER ENVIRONMENTAL CONSIDERATIONS 6.1 Significant Unavoidable Impacts Section 15126.2(b) of the California Environmental Quality Act (CEQA) Guidelines requires that an Environmental Impact Report
More informationReport to the BOARD OF AIRPORT COMMISSIONERS
09/10/13 r -osoll. L os A ngeles 7 nil A Donis I, Report to the BOARD OF AIRPORT COMMISSIONERS Ap roved Inti.1. Dur -m, Chief Airports Engineer is Revii es pr 2( hnson, Deputy Executive Director 1.1 lr,
More informationPhase I Submission Name of Program: QF-16 Full-Scale Aerial Target (FSAT) Program
Phase I Submission Name of Program: QF-16 Full-Scale Aerial Target (FSAT) Program Name of Program Leader: Thomas Tom R Lepe (Jun 2012 present) Phone Number: 314-777-9286 Email: thomas.r.lepe@boeing.com
More informationBull Arm Site Corporation Board Activity Plan. Fiscal Year
Bull Arm Site Corporation Board Activity Plan Fiscal Year 2007-2008 Message from the Chairperson The Bull Arm Site Corporation was incorporated by the Province of Newfoundland and Labrador on September
More informationIIL s International Project Management Day, 2007 The Power of the Profession:
IIL s International Project Management Day, 2007 The Power of the Profession: A Lesson Learned and Solution Implemented Becomes a Best Practice in Project Management by Tresia Eaves, PMP IRS RGS Project
More informationINTERNAL AUDIT REPORT
REPORT LIMITED OPERATIONAL AUDIT CAPITAL PROGRAM - INTERNATIONAL ARRIVALS FACILITY ISSUE DATE: November 2, 2017 REPORT NO. 2017-14 TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 BACKGROUND... 5 AUDIT SCOPE AND
More informationJuly 29, 2009 MEMORANDUM FOR THE HEADS OF DEPARTMENTS AND AGENCIES
EXECUTIVE OFFICE OF THE PRESIDENT OFFICE OF MANAGEMENT AND BUDGET WASHINGTON, D.C. 20503 THE DIRECTOR July 29, 2009 M-09-25 MEMORANDUM FOR THE HEADS OF DEPARTMENTS AND AGENCIES FROM: SUBJECT: Peter R.
More informationFISCAL YEAR 2017 STRATEGIC PLAN
FISCAL YEAR 2017 STRATEGIC PLAN Fiscal Year 2017 Strategic Plan LONG BEACH BOARD OF HARBOR COMMISSIONERS Lori Ann Guzmán President Lou Anne Bynum Vice President Tracy J. Egoscue Secretary Doug Drummond
More informationTHANKS TO OUR SPONSORS! Hill International Consulting, Inc.
THANKS TO OUR SPONSORS! Hill International Consulting, Inc. CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will
More informationManaging the Bid Process
Managing the Bid Process This document is concerned with the process suppliers of goods and services will typically go through when they are asked to submit a price for undertaking a piece of work. In
More informationDefining FM excellence
Your guide to the IFMA-RICS suite of credentials and professional development The IFMA-RICS collaboration The most significant evolution in the history of facility management Suite of credentials Together,
More informationidesc Reviewed AA - t*1 w41.11 Los Angeles World Airports F AIRPORT COMMISSIONERS BOARD REPORT TO THE SA/- k Deborah Flint - Ch -f Executive Officer
05/30/17 05/26/17 Date 05/30/17: Approval EY MY 1 AE MT BOARD t*1 w41.11 Los Angeles World Airports REPORT TO THE F ARPORT COMMSSONERS AA - Approved bylgrestampbell, Chief A rts Engineer Meeting Date:
More informationIT Governance and the Audit Committee Recognizing the Importance of Reliable and Timely Information
IT ADVISORY IT Governance and the Audit Committee Recognizing the Importance of Reliable and Timely Information KPMG INTERNATIONAL IT Governance and the Audit Committee: Recognizing the Importance of
More informationAspen/Pitkin County Airport Environmental Assessment BOCC Update. October 2017
Aspen/Pitkin County Airport Environmental Assessment BOCC Update October 2017 Meeting Goals Update BOCC on: EA Public Comments Public Process going forward Approximate Timeline Next Steps EA Reminders
More informationData Center Migrations and Conso olidations: Someone Else s Problem?
Data Center Migrations and Consolidations: Someone Else s Problem? Table of Contents The Situation: Risk... 2 IT s job is to Protect the Business. Every Move Bets Someone s Job.... 2 An Inherently Complex
More informationAirport Passenger Terminals
ARC International Associates Inc. Architects Engineers Planners 14 Sand Hill Road Sandy Hook, CT USA 06482-1624 Airport Passenger Terminals ARC International Associates Inc. Architects Engineers Planners,
More informationMONTGOMERY STREET. Construction Manager at Risk (CMAR) Services
2 nd PRE-PROPOSAL CONFERENCE March 6, 2015 MONTGOMERY STREET (City Project #02432) Construction Manager at Risk (CMAR) Services PROCUREMENT MARCH 19, 2015 1 Michael Weiss, P.E. City of Fort Worth Project
More informationContractors may report to this position as required by projects
POSITION DESCRIPTION 1. POSITION DETAILS Position Title: Division: Unit: Management Level: Community Property Manager City Projects & Property Property Services Professional 2. ORGANISATIONAL RELATIONSHIPS
More informationCHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12
3.01 GENERAL A. Design the project to meet the authorized scope, budget, and schedule. B. Upon initiation of the project, arrange to review with the Owner the service and administrative requirements as
More informationCORPORATE. CAPABILITIES Providing the highest quality professional services to our clients. jmt.com. 1
CORPORATE CAPABILITIES Providing the highest quality professional services to our clients jmt.com www.jmt.com 1 Contents About us 1 Safety. Quality. Integrity. Relationships. Our Markets Transportation
More informationPMI LUNCH AND LEARN OCTOBER 29, 2018
PMI LUNCH AND LEARN OCTOBER 29, 2018 Agenda Project Update Procurement Activities Lessons Learned PMI Lunch and Learn 10/29/2018 PMI Lunch and Learn 10/29/2018 Florida PALM Project Update Establishment
More informationLAX Terminals 2 and 3 Modernization Project DRAFT EIR PUBLIC MEETING. Tuesday, March 21, :00 pm to 8:00 pm
DRAFT EIR PUBLIC MEETING Tuesday, March 21, 2017 6:00 pm to 8:00 pm Project Site Project Site Terminal 3 Terminal 2 Existing Conditions TICKETING HALL Overcrowded Security Checkpoints Dated Concourse Areas
More informationTHE NORTHWEST SEAPORT ALLIANCE MEMORANDUM
THE NORTHWEST SEAPORT ALLIANCE MEMORANDUM MANAGING MEMBERS Item No. 4B ACTION ITEM Date of Meeting February 6, 2018 DATE: January 18, 2018 TO: FROM: Managing Members, John Wolfe, Chief Executive Officer
More informationUpdate on State Audit and Operations of MSD
Update on State Audit and Operations of MSD presented by Greg C. Heitzman Interim Executive Director Louisville MSD May 8, 2012 Presentation Outline 1. The State Audit and Corrective Action Plan 2. Executive
More informationPROJECT SCHEDULING & CONTROL
PROJECT SCHEDULING & CONTROL Project Project Management PM Knowledge Areas Time Management 1 Project What is a PROJECT? Definition used by PMI: A temporary endeavor undertaken to create a unique product,
More information