Midfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) Board of Airport Commissioners (BOAC) Construction Update #4

Size: px
Start display at page:

Download "Midfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) Board of Airport Commissioners (BOAC) Construction Update #4"

Transcription

1 Midfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) Board of Airport Commissioners (BOAC) Construction Update #4 October 18,

2 Agenda Midfield Satellite Concourse Project (MSC) Procurement, Construction, Budget, and Schedule Status Baggage Optimization Project (BOP) BOP Infrastructure Construction, Budget, and Schedule Status BOP System (TBITEC) Design and Construction Status SBE & Local Hire Performance Risk Management 2

3 MSC & BOP Construction Aerial (as of: Sept 2018) 3

4 MIDFIELD SATELLITE CONCOURSE (MSC) MSC Budget Status Summary (as of: Sept 2018) 4

5 MIDFIELD SATELLITE CONCOURSE (MSC) MSC Budget Status Change Management 83 Change Orders a) Net changes to date: $7.1M b) Remaining LAWA Contingency: $67.9M c) In negotiation: Gate Compatibility for Opening Day and Haz Mat Impacts For approval today: a) PAX Tunnel Video Wall CO: $1.56M PAX Tunnel Interior Current Design 5

6 MIDFIELD SATELLITE CONCOURSE (MSC) MSC Budget Status PAX Tunnel Video Wall Change Order Electrical Design & Construction a) Conduit infrastructure (power and data) to 24 monitor locations (9,270 lf) b) Electrical power circuits to each monitor location c) 6-Strand Fiber Optic Cable to ea. monitor (10,654 lf) plus fiber patch panel at ea. d) Relocation of ACAMS, cameras, fire alarm, and phones e) New electrical panels with feeders at the Gateway and MSC to maintain 25% spare capacity Architectural Mods and Finishes a) Wall furring to achieve flush finish with high-impact wall panels b) Field modifications to custom fabricated high-impact wall panels c) Glazing modifications to accommodate electrical raceways Rendering of the PAX Tunnel Video Wall 6

7 MSC Schedule Status Contractual Substantial Completion a) Base Contract Substantial 11/28/2019 b) 2017 Adverse Weather Days +47 CD c) Revised Substantial Completion 01/14/2020 Potential Schedule Impacts (under review) a) 2018 Adverse Weather Days thus far (7 CD requested by TPJV) b) Hazardous Materials at the PAX West (70 CD requested by TPJV) c) Potential Other Impacts, including: contractor delays, Future Adverse Weather Days, and labor resource shortages Projected Opening: June

8 BAGGAGE OPTIMIZATION PROJECT (BOP) BOP Overview Single Comprehensive Baggage Solution procured in two parts Infrastructure procured under the TPJV contract ( BOP Infrastructure ) Design & Installation of the Individual Carrier System (ICS) Baggage System procured under TBITEC Lease Amendment ( BOP System ) Panorama of ICS installation at the Utilidor Tunnel 8

9 BAGGAGE OPTIMIZATION PROJECT (BOP) BOP Infrastructure Baggage Handling System Infrastructure design and construction through 2 capital projects: 1. MSC scope 2. BOP scope NBHS Facility BOP Supporting MSC BOP Supporting TBIT MSC Facility North Tunnel Far East Tunnel Utilidor Tunnel Crossover Tunnel 9

10 BAGGAGE OPTIMIZATION PROJECT (BOP) BOP Infrastructure Construction Status Mixing Box lid progress at the Far East Tunnel (looking East) Waterproofing installation at the Far East Tunnel (looking East) 10

11 BAGGAGE OPTIMIZATION PROJECT (BOP) BOP Infrastructure Budget Status (as of: Sept 2018) 11

12 BAGGAGE OPTIMIZATION PROJECT (BOP) BOP Infrastructure Change Management 36 Change Orders a) Total changes to date: $842,655 b) Remaining LAWA Contingency: $9.16M c) Unforeseen conditions remain a risk until excavation is complete NBHS Basement level preparation for turnover to TBITEC NBHS Apron level preparation for turnover to TBITEC 12

13 BOP Infrastructure Schedule Status Contractual Substantial Completion Org. Substantial Comp. Rev. Substantial Comp. BOP Supporting MSC: Far East Tunnel 11/28/2019 1/14/2020 BOP Supporting TBIT : North BHS Bldg. 11/28/2019 1/14/2020 BOP Supporting TBIT : North Tunnel 01/07/ /23/2020 Potential Schedule Impacts (under review) a) 2018 Adverse Weather Days thus far (7 CD requested by TPJV) b) Potential Other Impacts, including: contractor delays, Future Adverse Weather Days, and labor resource shortages 13

14 BAGGAGE OPTIMIZATION PROJECT (BOP) BOP System Design and Construction Status BOP System achieved 100% design as of May 2018 West Utilidor installation approx. 91% Mechanically complete Upcoming Turnovers a) NBHS Basement: Oct 31, 2018 b) NBHS Apron: Jan 21, 2019 c) MSC Basement phased turnover: Oct 2018 Jan 2019 ICS Operational at MSC: Q ICS Operational at TBIT: Q ICS Installation in Utilidor West Tunnel 14

15 MSC / BOP Contract Cash Flow (thru Aug 2018) 15

16 SBE Contract Achievements 19.6 % SBE Participation to Date 15% Project Req. $649M Invoiced $127M SBE Paid SBE Participation Current: 19.6 % Forecast: 18 % SBE Paid-to-Date Value Current: $127 M Forecast: $232 M First Tier Subcontractor payments occur within 7 days of payment to TPJV 16

17 Local Hire Contract Achievements (as of: Sept 2018) Local Hire Participation Local Hire Paid-to-Date Value Current: 30.4 % Current: $ 29.9 M Forecast: 30 % Forecast: $ 55 M Project Goal of 30% Local Hire Participation Performance to date: a) 1,279 Local Area workers 453 Apprentices, 708 Journeymen, 36 Foreman, and 82 Owner-Operators Includes 55 HireLAX Apprentices Ongoing efforts and successes: a) Conducting meetings with trade unions to optimize involvement b) Working with subcontractors to develop strategic hire plans c) Promotion of local hire initiatives in foremen s meetings 17

18 Risk Management Trade Workforce Availability a) Currently: Welders and Electricians b) Future: Electricians and Terrazzo Installers Schedule Impacts a) Future Weather Impacts b) Contractor Delays c) Gate Compatibility d) HazMat at PAX West Unforeseen Conditions at Taxiway S (PAX East) Steel erection complete at BW Gateway (looking East) Steel erection progress at MSC Core (looking North) 18

19 Questions? 19

Midfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) BOAC Status Update May 4, 2017

Midfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) BOAC Status Update May 4, 2017 Midfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) BOAC Status Update May 4, 2017 Presented by: Robert Gilbert, CDO & Mark Skjervem, MSC Element Manager 1 Agenda Midfield Satellite

More information

olos Angeles World Airports

olos Angeles World Airports i Approval i BY I' olos Angeles World Airports lc W w.00 REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: Iten',. Approved byeg.. Campb- irports Engineer 8/18/2016 Reviewed by: 'og ra. Johnso,/Deputy

More information

BOARD OF AIRPORT COMMISSIONERS

BOARD OF AIRPORT COMMISSIONERS I ELy RW BY KV -4.01, 110%,ii ". 1 Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS I. Approved by: GI -g S. Campbell, Chief Airports Engineer II Meeting Date: 10/18/2018 1 1 Completed

More information

Aviation Capital Construction Program Update

Aviation Capital Construction Program Update Aviation Capital Construction Program Update 2012 Completed Projects 2013 Active Projects Bern Seals Program Manager Parsons Management Consultants April 2013 0 Discussion Agenda Program Safety Performance

More information

PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT

PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGMENT 2 FACILITY SERVICES Facility Development Capital Projects Management

More information

Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. January 2011

Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. January 2011 Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Annual Report TABLE OF CONTENTS

More information

r hief Information Officer

r hief Information Officer Y I I AE MT.401 'Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: Approved by: Aura Reviewed by: Justin E ac i, r hief Information Officer hief Innovation & Technology

More information

Alternative Project Delivery Methods and Procurement

Alternative Project Delivery Methods and Procurement Alternative Project Delivery Methods and Procurement Board of Airport Commissioners Meeting 2 June 2014 Presented by: Roger A. Johnson, Deputy Executive Director Definitions Project Delivery Method o The

More information

PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today!

PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today! PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today! FEBRUARY 12, 2014 FTBA CONSTRUCTION CONFERENCE PROJECT PARTNERS Public Sponsors 90% Equity Partner Contractor 10% Equity Partner Operator Federal

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2015 FEBRUARY 2016 Phase 2 Cost Summary December Expenditures $ 62.9 Million Total Expenditures $ 655.6 Million

More information

Estimating /1.401 Project Management Spring Dr. SangHyun Lee

Estimating /1.401 Project Management Spring Dr. SangHyun Lee 1.040/1.401 Project Management Spring 2007 Estimating Dr. SangHyun Lee Department of Civil and Environmental Engineering Massachusetts Institute of Technology Project Management Phase FEASIBILITY DESIGN

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

ITEM DESCRIPTION EST. QUANT. UNIT UNIT PRICE P

ITEM DESCRIPTION EST. QUANT. UNIT UNIT PRICE P BID FORM (continued) DAYTON INTERNATIONAL AIRPORT TERMINAL APRON RECONSTRUCTION PHASE 2 21% DBE PARTICIPATION) FEDERAL CONSTRUCTION FUNDS) ITEM DESCRIPTION EST. QUANT. UNIT UNIT PRICE P-101-5.1.1 FULL

More information

MINUTES OF MEETING 1. CONTRACT DATA 2. MEETING RECORD. Construction of the extension of the Lycée Josué Hoffet (Vientiane, Laos)

MINUTES OF MEETING 1. CONTRACT DATA 2. MEETING RECORD. Construction of the extension of the Lycée Josué Hoffet (Vientiane, Laos) 1. CONTRACT DATA MINUTES OF MEETING Meeting No. 09 Date: 07/06/2017 Contract No. Project: Contracting Authority: Contractor: Engineer: Lycée Josué Hoffet (Vientiane, (LJH) Chitchareune Construction Company

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May

More information

Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. October 28, 2010

Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. October 28, 2010 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 28, 2010 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 2010 update TABLE OF CONTENTS

More information

Pavement Design and Construction of Taxilane S to Accommodate New Large Aircraft at LAX

Pavement Design and Construction of Taxilane S to Accommodate New Large Aircraft at LAX Pavement Design and Construction of Taxilane S to Accommodate New Large Aircraft at LAX Katie Chou, Ph.D., P.E. Hatch Mott MacDonald, Los Angeles Office Presented to: 2011 SWIFT Conference, Montreal Date:

More information

Construction Progress and Inspection Report

Construction Progress and Inspection Report U.S. Department of Transportation Federal Aviation Administration Airport Name Fayetteville Regional Airport Project Description Airline Terminal Improvements - Part 1 Construction Progress and Inspection

More information

MULTNOMAH COUNTY Health Department Headquarters Project Design & Construction Update Early Work Package

MULTNOMAH COUNTY Health Department Headquarters Project Design & Construction Update Early Work Package MULTNOMAH COUNTY Health Department Headquarters Project Design & Construction Update Early Work Package Board Presentation November 10 2016 Multnomah County HDHQ Project Management Team PURPOSE OF BRIEFING

More information

Interior Architects, P.C REV 2 CONCEPTUAL ESTIMATE. Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY GARDINER AND THEOBALD INC FOR: AT:

Interior Architects, P.C REV 2 CONCEPTUAL ESTIMATE. Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY GARDINER AND THEOBALD INC FOR: AT: REV 2 CONCEPTUAL ESTIMATE FOR: Interior Architects, P.C Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY AT: BY: GARDINER AND THEOBALD INC Issued: 6/20/2013 BROOKLYN HEIGHTS LIBRARY, BROOKLYN

More information

Washington Dulles International Airport EXECUTIVE SUMMARY

Washington Dulles International Airport EXECUTIVE SUMMARY EXECUTIVE SUMMARY The events of September 11, 2001 and the economic uncertainties facing commercial aviation have affected the timing of the Proposed Action. The Metropolitan Washington Airports Authority

More information

BAGGAGE HANDLING SYSTEM RECAPITALIZATION & OPTIMIZATION

BAGGAGE HANDLING SYSTEM RECAPITALIZATION & OPTIMIZATION BAGGAGE HANDLING SYSTEM RECAPITALIZATION & OPTIMIZATION ACI North America Technical & Operations Committee Vancouver, British Columbia March 24, 2015 Emily Underhill, P.E., A.A.E. Division Director Development

More information

CAC Meeting Construction Update April 8, 2014

CAC Meeting Construction Update April 8, 2014 CAC Meeting Construction Update April 8, 2014 Period Summary There have been over 1,000,000 craft hours completed, excluding demolition, through March 31, 2014. An increase of nearly 50,000 hours since

More information

Dulles Corridor Metrorail Project. Project Labor Agreement. Executive Summary. 1.0 Background. 2.0 Project labor agreements (PLAs)

Dulles Corridor Metrorail Project. Project Labor Agreement. Executive Summary. 1.0 Background. 2.0 Project labor agreements (PLAs) Executive Summary In 2009, the Federal Government, through Executive Order 13502, reversed an earlier order and now recommends that all federally funded projects with a total installed cost greater than

More information

Construction Update. July 2015

Construction Update. July 2015 Construction Update July 2015 Current Project Overview Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Status Schedule # Milestone Current 2014 2015

More information

6.0 OTHER ENVIRONMENTAL CONSIDERATIONS 6.1 Significant Unavoidable Impacts

6.0 OTHER ENVIRONMENTAL CONSIDERATIONS 6.1 Significant Unavoidable Impacts 6.0 OTHER ENVIRONMENTAL CONSIDERATIONS 6.1 Significant Unavoidable Impacts Section 15126.2(b) of the California Environmental Quality Act (CEQA) Guidelines requires that an Environmental Impact Report

More information

WESTERN ILLINOIS UNIVERSITY CONSTRUCTION PROJECT PROCEDURES WESTERN ILLINOIS UNIVERSITY CONSTRUCTION POLICY

WESTERN ILLINOIS UNIVERSITY CONSTRUCTION PROJECT PROCEDURES WESTERN ILLINOIS UNIVERSITY CONSTRUCTION POLICY WESTERN ILLINOIS UNIVERSITY CONSTRUCTION PROJECT PROCEDURES WESTERN ILLINOIS UNIVERSITY CONSTRUCTION POLICY Management of all campus construction projects will be provided exclusively through the Facilities

More information

Millennium Line Broadway Extension Project. Cost Report

Millennium Line Broadway Extension Project. Cost Report Millennium Line Broadway Extension Project Cost Report March 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

DIVISION 1- GENERAL REQUIREMENTS

DIVISION 1- GENERAL REQUIREMENTS DIVISION 1- GENERAL REQUIREMENTS This division contains the following elements: 1.1 General 1.2 Summary of Work 1.3 Administration 1.4 Quality 1.5 Temporary Facilities 1.6 Products 1.7 Execution 1.8 Closeout

More information

Construction Update. November 2015

Construction Update. November 2015 Construction Update November 2015 Current Project Overview Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Status Schedule # Milestone Current 1 2

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

Rev. 01/17 APPRENTICES

Rev. 01/17 APPRENTICES Rev. 01/17 APPRENTICES All apprentices working on the contract must be registered with the Office of the Labor Commissioner, Nevada State Apprenticeship Council (currently in Las Vegas). The Request for

More information

4-200 CONTRACTOR LICENSING; REGISTRATION. The following information must be submitted for registration:

4-200 CONTRACTOR LICENSING; REGISTRATION. The following information must be submitted for registration: ARTICLE 2. CONTRACTOR LICENSING 4-200 CONTRACTOR LICENSING; REGISTRATION. The following information must be submitted for registration: (a) Registration form, which includes: (1) Name of company, contact

More information

TABLE OF CONTENTS Public Safety Building

TABLE OF CONTENTS Public Safety Building DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary

More information

Modification No. 91 Publication Date: (5 pages)

Modification No. 91 Publication Date: (5 pages) TO: FROM: All Users of the City of Denver Prevailing Wage Schedules Meredith Creme, CSA Compensation and Classification DATE: July 16, 2010 SUBJECT: Latest Update to Prevailing Wage Schedules Please find

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule

More information

B. Accept materials on site in original factory packaging, labeled with manufacturer s identification.

B. Accept materials on site in original factory packaging, labeled with manufacturer s identification. SECTION 26 05 02 - BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Work Included: Furnish all labor, material, services and skilled supervision necessary for the construction, erection, installation,

More information

Construction Progress and Inspection Report

Construction Progress and Inspection Report U.S. Department of Transportation Federal Aviation Administration Airport Name Fayetteville Regional Airport Project Description Airline Terminal Improvements - Part 1 Construction Progress and Inspection

More information

The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2017 MARCH 2017 Phase 2 Cost Summary January Expenditures $ 10.6 Million Total Expenditures $ 1.078 Billion

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 47 Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee January 16, 2014 & Schedule Performance Summary Chart Project Performance

More information

Port of Seattle Commission. Policy Directive on Priority Hire. As Amended April 24, 2018

Port of Seattle Commission. Policy Directive on Priority Hire. As Amended April 24, 2018 Port of Seattle Commission Policy Directive on Priority Hire As Amended April 24, 2018 Document last updated June 6, 2018 SECTION 1. Purpose. The purpose of this policy directive is to provide good family-wage

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,

More information

Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018

Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 2 Phase 2 Cost Summary September Expenditures $ 19.4 Million Total Expenditures $ 1.868

More information

Business Education Courses Facility Services Project Review DAVID MASHBURN, DIRECTOR DENVER INTERNATIONAL AIRPORT JANUARY 25 TH, 2017

Business Education Courses Facility Services Project Review DAVID MASHBURN, DIRECTOR DENVER INTERNATIONAL AIRPORT JANUARY 25 TH, 2017 Business Education Courses Facility Services Project Review DAVID MASHBURN, DIRECTOR DENVER INTERNATIONAL AIRPORT JANUARY 25 TH, 2017 AGENDA Facility Services Organization at DEN Project Lifecycle Design

More information

Division 00 Procurement and Contracting Requirements

Division 00 Procurement and Contracting Requirements SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders

More information

Question 2: Regarding Section VII, part 10, which jurisdiction issues permits for work performed at Ronald Reagan Washington National Airport?

Question 2: Regarding Section VII, part 10, which jurisdiction issues permits for work performed at Ronald Reagan Washington National Airport? RONALD REAGAN WASHINGTON NATIONAL AIRPORT METROPOLITAN WASHINGTON AIRPORTS AUTHORITY SOLICITATION RFP 1-11-C138 TERMINAL B/C PRE-SECURITY RESTROOM RENOVATIONS RESPONSES TO CONTRACTOR QUESTIONS Question

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,

More information

of Members of the Contracting Team

of Members of the Contracting Team Study Guide Project Business Management Grammar III: Roles & Composition and Responsibilities of Members of the Contracting Team May 2014 June 2014 National Association of Elevator Contractors Contents

More information

Peter Dahl Technical Assignment #1 Executive Summary

Peter Dahl Technical Assignment #1 Executive Summary Primary Faculty Consultant: Riley Due Date: Wednesday, October 8 th, 2003 Technical Assignment #1 Existing Site Conditions Executive Summary The construction of any tunnel is unique, but when you put that

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project

More information

Airport visit for HKIE Environmental Division 11 January 2014

Airport visit for HKIE Environmental Division 11 January 2014 Airport visit for HKIE Environmental Division 11 January 2014 1 Corporate Video 2 Agenda 1. HKIA Overview 2. Short-, medium- and long-term plan of HKIA 3. EIA for the Three-Runway System 4. Environmental

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

LAWA Update Ground Transportation Planning and Metro Coordination

LAWA Update Ground Transportation Planning and Metro Coordination LAWA Update Ground Transportation Planning and Metro Coordination SPAS Approved LAX Ground Transportation Projects The Specific Plan Amendment Study (SPAS) includes LAX Ground Transportation Projects:

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

Phone Joan Daniels. Line # Item Number Item/Description Category Co Item UOM Contract Price

Phone Joan Daniels. Line # Item Number Item/Description Category Co Item UOM Contract Price 1 of 12 1 000000000000031501 Construction Manager Services 81101513 EA 1.00 2 000000000000032537 CMH Roofing Restoration 81101513 EA 1.00 3 000000000000032538 CMH Wall Renovations 81101513 EA 1.00 4 000000000000032539

More information

INTERNAL AUDIT REPORT

INTERNAL AUDIT REPORT REPORT LIMITED OPERATIONAL AUDIT CAPITAL PROGRAM - INTERNATIONAL ARRIVALS FACILITY ISSUE DATE: November 2, 2017 REPORT NO. 2017-14 TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 BACKGROUND... 5 AUDIT SCOPE AND

More information

Covering the Pacific Northwest with QUALITY

Covering the Pacific Northwest with QUALITY 2 Covering the Pacific Northwest with QUALITY 3 Finding a reputable painting company that completes projects in a timely manner from the planning stages to completion can be a difficult task. Yet Long

More information

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina Project Manual for Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina DWG Consulting Engineers 1009 Anna Knapp Blvd. Suite 202 Mt Pleasant, South Carolina 29464

More information

External Affairs Specialized Marketing Services, Jan Fambro, and Harvey Mudd College Contracts Audit Report

External Affairs Specialized Marketing Services, Jan Fambro, and Harvey Mudd College Contracts Audit Report Report Report Office of the General Auditor Audit Department Report for February 2015 Summary Three reports were issued during the month: External Affairs Specialized Marketing Services, Jan Fambro, and

More information

ADDENDUM NO. 1. SERVICE TUNNEL RENEWAL/REPLACEMENT PROJECT MC / WP # at Seattle-Tacoma International Airport

ADDENDUM NO. 1. SERVICE TUNNEL RENEWAL/REPLACEMENT PROJECT MC / WP # at Seattle-Tacoma International Airport THIS DOCUMENT AND ATTACHMENT(S) ARE AVAILABLE FOR DOWNLOAD AT HTTPS://HOSTING.PORTSEATTLE.ORG/PRMS/. AN EMAIL NOTIFICATION WAS SENT TO REGISTERED PLANHOLDERS. FAILURE TO ACKNOWLEDGE RECEIPT ON THE BID

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF FEBRUARY 29, 2016 APRIL 2016 Phase 2 Cost Summary February Expenditures $ 25.7 Million Total Expenditures $ 690.1 Million

More information

White Rock Wind Farm Project Update for Community Consultative Committee 4th February 2016

White Rock Wind Farm Project Update for Community Consultative Committee 4th February 2016 White Rock Wind Farm Project Update for Community Consultative Committee 4th February 2016 1 Content 1. Project Status 2. Early Works 3. Modification Application 4. Expected Program 5. Project Organisation

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

3. ADOPT the SPAS Mitigation, Monitoring and Reporting Program (MMRP).

3. ADOPT the SPAS Mitigation, Monitoring and Reporting Program (MMRP). , Meeting Date: February 5, 2013 Completed Pending N/A Rev lewev for Capital Budget Operating Budget CEQA 01130/13 01/31/13 01/31/13 01/30/13 APoroval Status EIY D N DNA EIYONDNA Y N MYDNOCand By DS RW

More information

Courthouse Update August 19, 2014

Courthouse Update August 19, 2014 1 Courthouse Update August 19, 2014 2 Project Discussions Courthouse Tower Project Status Forthcoming Agenda Items Courthouse Campus Parking 1,000-Car Garage 500-Car Garage Parking Strategy & Rates 3 The

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

Doing Business with the Metropolitan Washington Airports Authority

Doing Business with the Metropolitan Washington Airports Authority Doing Business with the Metropolitan Washington Airports Authority MWMCA Quarterly Economic Summit Brown Advisory November 7, 2017 Introduction to MWAA Ronald Reagan Washington National Airport Washington

More information

WELCOME. NEW NORTH CONCOURSE PACKAGE #3 Open House 10/20/2017

WELCOME. NEW NORTH CONCOURSE PACKAGE #3 Open House 10/20/2017 WELCOME NEW NORTH CONCOURSE PACKAGE #3 Open House 10/20/2017 Today s with Turner Team Introductions Project Overview Pre-Qualification Requirements & Bid Process Contracting Opportunities Introductions:

More information

MOTION NO. M Contract for Security Technology Services PROPOSED ACTION

MOTION NO. M Contract for Security Technology Services PROPOSED ACTION MOTION NO. M2017-149 Contract for Security Technology Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION 12/07/2017 Final Action Brian McCartan,

More information

Report to the BOARD OF AIRPORT COMMISSIONERS

Report to the BOARD OF AIRPORT COMMISSIONERS 09/10/13 r -osoll. L os A ngeles 7 nil A Donis I, Report to the BOARD OF AIRPORT COMMISSIONERS Ap roved Inti.1. Dur -m, Chief Airports Engineer is Revii es pr 2( hnson, Deputy Executive Director 1.1 lr,

More information

UNDERGROUND ISSUE. Granite Construction. Digging Deep on Midfield Satellite Concourse North Project at the Los Angeles International Airport

UNDERGROUND ISSUE. Granite Construction. Digging Deep on Midfield Satellite Concourse North Project at the Los Angeles International Airport UNDERGROUND ISSUE Digging Deep on Midfield Satellite Concourse North Project at the Los Angeles International Airport Above: Need caption. Digging Deep on Midfield Satellite Concourse North Project at

More information

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update December 3, 2015

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update December 3, 2015 Expo Board Presentation Monthly Project Status Update December 3, 215 Expo Phase 1 Phase 1 Project Status Closeout Status Completing Closeout of Remaining Elements of Work Working with Metro and City of

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

PREVAILING WAGE RATE DETERMINATION

PREVAILING WAGE RATE DETERMINATION The New Jersey Prevailing Wage Act (N.J.S.A. 34:11-56.25 et seq.) requires that the Department of Labor and Workforce Development establish and enforce a prevailing wage level for workers engaged in public

More information

Agenda. Agenda. Project Overview. Project Overview. CM In-House Building Commissioning. Virtual MEP Coordination. Virtual MEP Coordination

Agenda. Agenda. Project Overview. Project Overview. CM In-House Building Commissioning. Virtual MEP Coordination. Virtual MEP Coordination Pump Truck Materials Science Engineering & Nanotechnology --- Materials Science Engineering & Nanotechnology Depth Analysis: CM In-House Breadth Analysis: Virtual MEP The Pennsylvania State University

More information

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2

OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2 OMAHA BASEBALL STADIUM May 21, 2009 Report No. 2 METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority Omaha, Nebraska

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2016 MARCH 2016 Phase 2 Cost Summary January Expenditures $ 8.8 Million Total Expenditures $ 664.4 Million Total

More information

Project Budget And Schedule Status Report

Project Budget And Schedule Status Report Item 47 Project Budget And Schedule Status Report Presented by Brian Boudreau Executive Director, Program Management Construction Committee June 18, 2015 & Schedule Performance Summary Chart Slide # Project

More information

AMENDMENT OF SOLICITATION

AMENDMENT OF SOLICITATION Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF SOLICITATION PAGE 1 Metropolitan Washington Airports Authority 1A. AMENDMENT OF SOLICITATION NO. 1B. DATED Procurement

More information

Construction Update. March 2018

Construction Update. March 2018 Construction Update March 2018 Project Overview Western Zone Grid Line 1-10 Central Zone Grid Line 10-20 Eastern Zone Grid Line 20-35 2 Recent Activity 3 Recent Activity 4 Construction Activity Transit

More information

CONSTRUCTION SUMMIT. Alex Leon Deputy Commissioner. February 7, 2018 CDA DESIGN AND CONSTRUCTION

CONSTRUCTION SUMMIT. Alex Leon Deputy Commissioner. February 7, 2018 CDA DESIGN AND CONSTRUCTION 2018 CONSTRUCTION SUMMIT CDA DESIGN AND CONSTRUCTION Alex Leon Deputy Commissioner February 7, 2018 TERMINAL AREA PLAN O HARE CAPITAL PROGRAMS OVERVIEW O Hare is taking steps to reconfigure and modernize

More information

Owner perspective on immigrant labor for industrial construction projects

Owner perspective on immigrant labor for industrial construction projects Owner perspective on immigrant labor for industrial construction projects Types of Projects Petrochemical Manufacturing Utilities Typical Owner Small professional construction organization Using Best Practices

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Port of Seattle IAF Overview

Port of Seattle IAF Overview Item No. 9a_supp Meeting Date: March 27, 2018 Port of Seattle IAF Overview March 27, 2018 Project Briefing Benefits of the IAF Construction Progress Photos Project Delivery Strategy Key IAF Project Initiatives

More information

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor April 11, :30 a.m.

AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor April 11, :30 a.m. AGENDA Regular Commission Meeting Port of Portland Headquarters 7200 N.E. Airport Way, 8 th Floor 9:30 a.m. Minutes Approval of Minutes: Regular Commission Meeting March 14, 2018 Executive Director Approval

More information

UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management)

UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management) UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management) DESIGN PHASE PROJECTS BCT - Building Program Development and Design for Maintenance and Administration

More information

Town of Milton Halton Paramedic Services Station No. 17 and Milton Fire Station No. 5 Tender No and

Town of Milton Halton Paramedic Services Station No. 17 and Milton Fire Station No. 5 Tender No and Town of Milton No. 17 and Milton Fire Station No. 5 Tender No. 19-500-1 and 19-500-2 BID SUBMISSION 19-500-2 Part Two In accordance with Tender No. 19-500-2, Tender Form Part Two must be submitted electronically

More information

June Principal Contractor. Case study. Phil Danks Project Manager Abigroup

June Principal Contractor. Case study. Phil Danks Project Manager Abigroup June 2010 Principal Contractor Case study Phil Danks Project Manager Abigroup GOLD COAST RAPID TRANSIT Local Suppliers & Construction Briefing Gold Coast Convention & Exhibition Centre Gold Coast Highway,

More information

Prevailing Wage Overview

Prevailing Wage Overview City and County of Denver 201 West Colfax Avenue, Dept. 705 Denver, Colorado 80202 Prevailing Wage Overview Why Must Denver Contractors Pay Prevailing Wage? It's the Law. Denver Revised Municipal Code

More information

B. Sections and all references contained therein form a part of this Section of the Specifications.

B. Sections and all references contained therein form a part of this Section of the Specifications. KARGES-FAULCONBRIDGE, INC. KFI: 14-044.00 SEWARD MONTESSORI SCHOOL ADDITION & REMODELING SECTION 260010 - PART 1 - GENERAL 1.01 SCOPE OF WORK A. Drawings and general provisions of the Contract, including

More information