1 SEPARATING UNDERGROUND METRO LINES UNDER OPERATION IN BAKU SYSTRA FR: Federico VALDEMARIN, Mott MacDonald CZ: Jan CENEK, Self-employed prof.: Elena CHIRIOTTI

2

3 SEPARATING UNDERGROUND METRO LINES UNDER OPERATION IN BAKU SYSTRA FR: Federico VALDEMARIN, Mott MacDonald CZ: Jan CENEK, Self-employed prof.: Elena CHIRIOTTI SUMMARY The 28 May Station is the only transfer station between the existing Green and Red metro lines in Baku. As part of the huge development strategy of the metro network, the complete separation of the existing underground lines has been planned at this location, in order to simplify the operation of the future metro system. The extreme challenge of the project is represented by the need of achieve the separation of such lines over a breakdown of the operation of just five weeks. The lack of direct access from the surface, a complex geology with artesian water layers, a congested underground space and sensible buildings represent additional constraints. The chosen design solution consists in creating a complex steel pipe jacking frame around the operating tunnels and then excavating under such frame two large caverns where the separation of the existing lines and the construction of the new metro tunnels will be achieved. Soil treatments have been conceived to mitigate the geotechnical risks and to reduce possible impacts on the existing structures. The paper illustrate the challenges of this extraordinary project, one of the most complex underground structures under study, the design solutions and the risk management approach used to manage the complexity and to design the mitigations measures. 2

4 Figure 1. Existing Baku metro network and location of the 28 May Station INTRODUCTION The metro network in the capital of Azerbaijan is rapidly growing together with its metropolitan area. The beginnings of the existing metro system started in Baku in 1967 in Soviet times. To date, only two lines (Green and Red) are in operation with a total length of 34km, including 23 stations. The future network will be much wider: besides the construction of three completely new lines and the extension of two existing lines, the whole metro project includes the development and modernization of the existing metro sections. A consortium formed by SYSTRA (leader), Mott MacDonald (Praha) and Saman (Korea) awarded the contract for the preliminary and detailed design of infrastructures for the extension of Baku Metro Network. This extension consists in 83km of new lines and extension of existing lines. As part of this modernization project, the connection of the Green Line at the 28 May/Cefer Cabbarli Stations, focus of this paper, represent also it s Achilles heel given that the already very congested system have only one transfer station. The Project Prior to the extension of the southern part of the existing Red Line and Green Line, and in order to improve the current transport capacity, a key activity is the removal of the Y operation at the 28 May Station and the separation of the Red and Green Lines tunnels. The 28 May Station in fact, connects today the arrivals on the Red Line in the direction Icharishahar (Old Town) and the Green Line in the direction Darnagul. Passengers wishing to continue along the Green Line, must first go through a complex system of galleries to transfer at Cefer Cabbarli station where the trains are dispatched to the Khatai Station (Figure. 1). The new project aims to simplify the operation of the May 28 Station and to completely separate the tunnels of the two lines. Figure 2 presents the existing and the future layout of the tunnels and station s platforms at the 28 May and Cefer Cabbarli Stations. The Separation of the Red and Green lines at the 28 May Station consists of the construction of two tunnels of 190meters in total as shown in Figure 3. They are created by partially demolishing the existing garage and storage terminals of the Xatai shuttle and making available the connection to Nizami station trough the Green Line. 4

5 Figure 2. Existing (left) and future (right) metro network at 28 May station. Figure 3. 3D model 28 May station after separation THE INPUT DATA AND CONSTRAINTS To get accurate and reliable data for planning infrastructure and underground works in post- Soviet countries is quite complex because for secrecy, confidentiality, topographical information was deliberately distorted or shifted by tens of meters, mostly unavailable as built documents for existing structures. In addition, the local suppliers for exploratory work do not follow international standard methods and their output can be unclear. The Geological Investigations and their Uncertainties Baku urban area lays in the middle of a large syncline responsible for the amphitheatre morphology of the city and the differences between the formations. The folded geological formations present in Baku subsoil are sediments from the Quaternary, and Neogene. These sediments are mainly made of clays, sands, and some banks of limestone and sandstone. Based on the geological data made available from previous project in the area at the feasibility stage, the entire geological profile was considered a huge layer of relatively stiff clay. A first investigation campaign composed by 9 core recovery borehole and 8 SPT vertical logs was launched in 2012 in order to confirm these assumptions. The very first boreholes of the campaign detected loose soils and artesian water under the stiff clays starting 25-30m BGS. After performing laboratory analysis (more than 200 identification tests, 30 shear tests and 16 compressibility tests) the local contractor was not able to satisfactorily characterize the lower layer whose characteristics appeared contradictory and inconsistent with the description of the borehole logs. The designer requested additional geological surveys, which were supposed to satisfactorily identify and characterize the lower strata. For this purpose, 13 cone penetration tests 5

6 CPTu (the firsts ever conducted in the country) and 2 pumping tests were recommended and carried out. Based on the results, the bottom layer was characterized and classified as a sandy silt. During the implementation of the additional geological survey, the presence of artesian groundwater was confirmed, which increased the concerns about the underground works being executed in the layer of sandy silt. The pump tests also confirmed a continuous water horizon under a confined pressure of about 3 bars. The Geological Model Based on the results of the CPTu it was possible to clearly identify and distinguish the following Geotechnical Units: Unit 1 (0 to 4m depth): man-made ground unit Unit 2 (4 to 26-30m depth): stiff Silty Clay unit. The unit is composed mainly by silty clay, with subunits of sand and sandy silt. These sand lenses are almost always recognized trough the CPTUs. The connection between such lenses, although not surely established based on the actual data, was considered in the implementation of risk analysis. Unit 3 (26-30 to 60m depth): Silty Sand unit, consisting of silty fine sands laminated with thin to very thin interbedded silty clay and sandy silts. Based on the above characterization, the distribution of the geotechnical units has been studied and a geotechnical 3D model of the studied zone was produced. The study has been developed using the GDM software of BRGM that allows to build an interpretative 3D model of the geology, the existing and the future structures, and to represent such interpretation along oriented sections. The Geotechnical Characterization It must be mentioned that geotechnical campaigns (both in situ and laboratory tests), performed in Baku by local companies, did not comply with international standards in terms of methodology, equipment implementation and calibration, recovery, testing, and interpretation. Specifically, the sampling method (simple core barrel) led to significant sample disturbance and affected the reliability of mechanical test. For such reasons many parameters were derived more from CPTUs results or from designer s experience on Baku s soils than from Lab tests results. Also taking in to account the intrinsic variability of the Units, a set of worst credible values for each Unit has been defined further to the reference values (see Table 1), in order to develop the design by scenarios. Table 1. Geotechnical characterization for the geotechnical Units 6

7 Figure 4. Existing surrounding structures at project location The Existing Structures One of the biggest constraints of such project is represented by the surrounding existing structures. The presence and the sensitivity of such structures limits the jobsite access and space at the surface, potentially interferes with the designed temporary and permanent structures, and requires particular attention to the effects of induced settlement. Figure 4 present a 3D view of the main existing structures at the location of the future works. The main existing structures considered as design constants and for risk analysis are: the 28 May Station: a deep mined station consisting of a central tunnel, two side tunnels and transversal galleries for the connection with the Cefer Cabbarly station; the Cefer Cabbarli Station for the shuttle line to Xataï: a deep mined station consisting of two twin tunnels, two dead-end galleries and a network of adits for ventilation and drainage connected at the end; The existing running metro tunnels: circular shaped, lined by cast iron segments of 5.1m internal diameter with pressure gate chambers with a cast iron segmental lining of 6.2m diameter; an underground shopping passage consisting of a reinforced concrete box which extend foundations to about 5m below the surface; utilities such as a water pipeline (D 500mm), a medium pressure gas pipeline, 0,4 kv electric cables and multiple unspecified manholes, which need to be diverted before any works may take place; the Azerbaijan State Oil Academy: a five storey masonry structure, with 4,5m deep strip foundations considered a sensitive structure due to its public use. 7

8 Figure 5. The three options from the Feasibility Study DESIGN PROCESS AND SOLUTIONS As stated at the previous chapter, the seemingly simple task that involved the construction of two 100m long track tunnels is further complicated by the results of the investigations and by the time constraints imposed by the Client. Those constrains mainly consist of: Topography there is no direct surface access; access located immediately below university building precluded the use of a large excavated open pit, and in proximity to a complex system of existing underground structures; Geology - the risk of encountering saturated sand lenses, soft clays, artesian aquifers; Time - the client requested the work be completed in an extremely short period (during shutdown of the Green Line 5 weeks). During the Feasibility Phase, three different options were analysed, including the direct re-excavation of the existing tunnels (Fig. 5a), the excavation of a cavern preceded by simple side adits (Fig. 5b) or by adits combined with diaphragm walls (Fig. 5c). The client selected the third variant, despite to the longer period of construction and higher costs, because it resulted in the shortest shutdown period. The selected option was subsequently developed to the preliminary design level and then further modified to account for the topographical and geological surveys that allowed to better estimate the possible collisions with the network of existing tunnels, and the possible effects of the artesian waters. This was done in close collaboration with the contractor selected by the Client. The completed design was submitted for comments to the Azerbaijani state expert analysis and the Independent Checker selected by the Client. The Basic Design The challenge consisting of excavating two relatively short tunnels (about 100m long) which encountered a section of an existing tunnel made of cast iron segments and performing this work as quickly as possible to minimize interruptions to the metro operation. The work also has to be done in proximity to a network of existing tunnels without easy access from the surface. The whole design was developed in considering the following key-issues, with taking into consideration the project s risks and constraints: 1. To develop a design based on a systematic risk analysis process shared with the Employer and his representative: the design choices were driven by risk assessment and this process has been traceable and explicit. 2. To develop the design by scenarios: a reference scenario based on a deterministic set of parameters (most likely soil and groundwater characteristics and behaviour, volume loss, deconfinement ratio, works performance, geometry, etc.); a scenario based on worst credible parameters quantitatively considering the impact of a certain number of geotechnical 8

9 uncertainties and their variability to test the robustness of the proposed technical solution, and to incorporate the necessary corrective measures in the design. 3. To define mitigation and contingency measures to control the effects induced by the installation, excavation, and completion of the underground work, for both the reference (mitigation measures) and the worst (contingency measures) scenarios. 4. To define a set of driving parameters with their respective operational ranges (when applicable), and attention and alert thresholds to be used during construction to monitor the work and assist in decision making. 5. To predefine the sequence of actions when attention or alert thresholds are reached. 6. Given the multiple excavations and mutual interferences, the correct design method is a 3D approach. In particular, numerical, coupled analyses have been considered (combining mechanical and hydraulic challenges). 7. To select in a traceable way the most adequate construction methods and ground treatment, taking into consideration the soil and groundwater conditions and required space for jobsite logistics. 8. To cope with time and environmental constraints. The Basic Design s Solution The separation of the red and green lines is to be performed mainly the under protection of two underground caverns, both constructed below the Oil Academy Building. The depth of the new tunnel alignment is approximately 18 22m below the surface. The overburden of the upper lateral adits is around 12 15m. The caverns themselves are planned to have a maximum width of approximately 17m and a height of approx. 10m. The ground bearing structure of the caverns are to be built before the excavation of the caverns. The 3D model of Figure 6 gives an overview of the project at the 28 May station. The magenta show the new separation tunnels, while the objects in green, yellow and pink represent all the preliminary works needed to install the new separation tunnels in the cavern. Figure 6. 3D model of the basic design s solution The access shafts are excavated to the level of an intermediate slab. From there, the upper level adits are excavated. At the same time, the shafts are completed to the bottom level. If necessary, ground treatment (e.g. jet grouting, ground freezing) from the upper level adits is performed to support the excavation phase of the lower adits. Between the lateral adits, vertical and horizontal pipe jacks are installed. These pipes are then filled with concrete and reinforced at their ends (corner connections), within the adits, to ensure a stiff frame around the caverns excavated at a later time. Longitudinal adits will be kept close to the future and existing Green Line tunnel to form a square cavern shape which has 3 adits in 3 corners of the rectangle. The distribution of the longitudinal adits and pipe jacking frame can be seen in Figure 7. The access to the cavern excavation is opened from the shaft with an approximately 6.0x6.5m window to facilitate the excavation progress. From there, the first level of the cavern (5.5m under pipe jacking roof) is excavated as well as the head walls. The drainage system is also installed. After this phase, the operation of the green line needs to be interrupted. Then, the caverns excavation is completed and the existing running tunnel demolished. The invert and construction elements for the new running tunnel are installed in sequence. Once the connecting structures are built, the caverns are filled and traffic operation is resumed. 9

10 Figure 7. The section type for basic design s solution This solution allows reducing the traffic interruption on the green line for a period not to exceed 5 weeks. RISK MANAGEMENT The main geotechnical hazards identified for the construction phases are: The presence of the artesian groundwater during excavation of the lower adits and the connection between the pipejackings tubes may result in the instability of the excavation and unsafe conditions for the workers. Although the low permeability values registered during the tests, the presence of artesian groundwater in the Silty Sand Unit may result in water inflows and in stability problems at the base of the caverns. The presence of sand lenses interbedded in the Silty Clay Unit may contain water or, if thick enough and continuous, may be connected to the artesian aquifer, results in possible water inflows and instability during the excavations phases. The uncertainties due to poor recovery of the samples and questionable reliability of lab results oblige to carry out the design through parametric studies, analyzing the influence of key input parameters in the engineering solutions. The identified hazards have also to been considered in the context of a densely urbanized environment and heavily utilized underground space, which strongly limit the investigations distribution and that present a significant constraints for the geometry of the excavation and the application of soil support. The geotechnical hazards above mentioned have been thoroughly considered in the Risk Register Matrix. The process of minimizing of such risks has been an integrated part of the design phase and will be completed and implemented in the future stages of this project, together with: Non deterministic approach in design (most likely and worst credible conditions) Identification of mitigation measures, where and when needed Definition of predefined countermeasures (to be fully shared with the Contractor) Observational method during construction (role of monitoring) A preliminary Risk Register has been drafted in accordance with ISO: 3100 and other relevant standards [1-4] by the designer in the basic design phase of the 28 May Station Upgrade project. This has allowed to properly communicate and share the risks among the project s actors, establish shared geotechnical baselines to access the impact of geotechnical uncertainties, and to define the provisions for risk. The risk related to the uncertainty of certain geotechnical parameters and to the response of the soil to excavation and soil treatment, has pushed the designer and the Owner to propose that the access shafts be used as the location for the field trial tests for the soil treatment work and to confirm/ update as much as possible the geotechnical characterization by means of additional vertical and inclined boreholes and in situ tests. Consequently, the contractor has the responsibility of updating the design based on the results of such tests and on the surveys carried out through excavation of the shafts. This has led the project s actor to select a design -build form of contract in which the steps of the design update are formalized, together with the procedure in which such results are used to update the project. 10

11 CONCLUSIONS The project which consists in separating the running tunnels of the Red and Green Metro Lines in Baku is particularly challenging for many reasons: the Client s requirement of interrupting the metro traffic for no longer than 5 weeks; the complexity of the existing underground structures; the sensitivity of the buildings above the future work; the limited access space on the surface and the limitations in placing and dimensioning access shafts to support the excavation of the underground work; the existing condition of the subsoil and the pressurized aquifer; the uncertainties related to the ground characterization. This has led to develop a very challenging design involving innovative technical solutions requiring high accuracy and latest technologies for the first time used not only in Azerbaijan such as: two huge caverns supported by rigid closed water resistant pipe jacked frame completely jacked from small underground access galleries, the massive ground treatment measures (in alternatives, also installed from the underground) and taking in to account existing and operating tunnels and buildings in the close proximity, replacement of old by new metro tunnels including rail and MEP in extremely short time. Where the contractor s experience has been involved as early as possible in the study of the construction method. This was combined to a systematic risk management approach and to the definition of the most adequate form of contract considering the project constraints and characteristics. REFERENCES [1] The Code of Practice for Risk Management of Tunnel Works (2006). International Tunnelling Insurance Group (ITIG), presented at the ITA World Congress, Seoul, April [2] Guidelines for Tunnelling Risk Management: International Tunnelling Association, Working Group n 2 (2004). Tunnelling and Underground Space Technology, N.19, 2004, pp [3] The Joint Code of Practice for Risk Management of Tunnel Works in the UK (2003). Published by the British Tunnelling Society (BTS), prepared jointly by BTS and the Association of British Insurers. [4] A Guide to the Systematic Management of Risk from Construction (1996), CIRIA, Special Publication

12 72 rue Henry Farman CS Paris Cedex SYSTRA 2016, M.Kadri/CAPA Pictures

Risk Management of the Restoration of Shanghai Metro Line 4

Risk Management of the Restoration of Shanghai Metro Line 4 ISGSR2007 First International Symposium on Geotechnical Safety & Risk Oct. 18~19, 2007 Shanghai Tongji University, China Risk Management of the Restoration of Shanghai Metro Line 4 X. P. Yu, W. J. Zhu

More information

Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro

Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro P. Kontothanassis, N. Koronakis, A. Karinas & S. Massinas Omikron Kappa

More information

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater Introduction to Soft Ground Tunnelling in Urban Environment Dr. Noppadol Phienwej Geotechnical and Geo-environmental environmental Engineering School of Engineering and Technology Asian Institute of Technology

More information

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk dr inż. Marcin Blockus INGEO Sp. z o.o. Mobile: +48 505 24 38 37 E-mail: blockus@ingeo.com.pl The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in

More information

Subsurface Investigations PDCA Professor s Driven Pile Institute. Loren R. Anderson Utah State University June 25, 2015

Subsurface Investigations PDCA Professor s Driven Pile Institute. Loren R. Anderson Utah State University June 25, 2015 Subsurface Investigations PDCA Professor s Driven Pile Institute Loren R. Anderson Utah State University June 25, 2015 Ralph B. Peck (1962) Subsurface engineering is an art; soil mechanics is an engineering

More information

GeoEng2000 An International Conference on Geotechnical & Geological Engineering

GeoEng2000 An International Conference on Geotechnical & Geological Engineering GeoEng2000 An International Conference on Geotechnical & Geological Engineering 19-24 November 2000 Melbourne Exhibition and Convention Centre Melbourne, Australia Barrettes : A versatile foundation for

More information

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS 4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS This section discusses the geology, soils, seismicity, hazardous materials, and subsurface obstructions along Flower Street, and evaluates their potential

More information

TBM rescue projects using shafts and ground freezing

TBM rescue projects using shafts and ground freezing TBM rescue projects using shafts and ground freezing Dipl.-Ing. Michael Löffler, Dipl.-Ing. Helmut Haß (CDM Consult GmbH, Germany) Dipl.-Ing. Thomas Ahlbrecht (Deilmann-Haniel Shaft Sinking GmbH, Germany)

More information

Prof. Dipl.-Ing. H. Quick Ingenieure und Geologen GmbH provides geotechnical engineering services e. g. for high-rise buildings in Germany and abroad.

Prof. Dipl.-Ing. H. Quick Ingenieure und Geologen GmbH provides geotechnical engineering services e. g. for high-rise buildings in Germany and abroad. Prof. Dipl.-Ing. Hubert Quick City Hall of Dubai, March, 7 th, 2005 o Prof. Dipl.-Ing. H. Quick Ingenieure und Geologen GmbH provides geotechnical engineering services e. g. for high-rise buildings in

More information

June i TABLE OF CONTENTS

June i TABLE OF CONTENTS June 2005 - i - 05-526 TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 1 1.1 Purpose of the Investigation... 1 1.2 Description of the Project and Scope of Work... 1 1.3 Site Geology... 1 1.4 Site Description

More information

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST

More information

4th International Engineering and Construction Conference - July 28, 2006

4th International Engineering and Construction Conference - July 28, 2006 4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast

More information

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know?

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know? BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know? Chris Raison BEng MSc CEng MICE MASCE Raison Foster Associates Introduction A few

More information

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN BASEMENT CONSTRUCTION 01 content 1.DEFINITION 2. CONSTRUCTION CONSIDERATION 3. DESIGN REQUIREMENT 4.METHOD OF CONSTRUCTION a. Open Cut Construction

More information

The HKIE Structural Examination Written Examination

The HKIE Structural Examination Written Examination The HKIE Structural Examination Written Examination Section 2: Design Questions (80% of the Written Examination) Date: 28 November 2014 (Friday) Time: 12:00 nn - 06:00 pm Answer ONE question only Question

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) 3 - Basement 1 Quick Revision 1.1 Problems arising from basement construction a. Excavation method. b. Surface and ground water control c. Lateral stability of basement excavation. d. Stability of adjoining

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

Northport Berth 3 design and construction monitoring

Northport Berth 3 design and construction monitoring Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Lucy Coe, Nicola Ridgley, Do Van Toan Beca Infrastructure Limited, Auckland, NZ Keywords: retaining wall, deflections,

More information

Groundwater management during the construction of underground hydrocarbon storage in rock caverns

Groundwater management during the construction of underground hydrocarbon storage in rock caverns Groundwater management during the construction of underground hydrocarbon storage in rock caverns Amantini Eric, Cabon François, Moretto Anne. Géostock. 7 rue E. et A. Peugeot. 92563 Rueil-Malmaison. France.

More information

Design of Izmir Bay Crossing Bridge

Design of Izmir Bay Crossing Bridge Design of Izmir Bay Crossing Bridge Burak Kurtman Dpt. Manager of Bridge Group, Yüksel Project International, Ankara, Turkey Tel: +90 (312) 4957000 E-mail: bkurtman@yukselproje.com.tr Abstract The Izmir

More information

Typical set up for Plate Load test assembly

Typical set up for Plate Load test assembly Major disadvantages of field tests are Laborious Time consuming Heavy equipment to be carried to field Short duration behavior Plate Load Test Sand Bags Platform for loading Dial Gauge Testing Plate Foundation

More information

SITE INVESTIGATION. Foundation Engineering

SITE INVESTIGATION. Foundation Engineering SITE INVESTIGATION Assist. Prof. Berrak TEYMUR Foundation Engineering Analysis Design Construction As a foundation engineer, you need to consider geotechnical/structural issues (involves geology, subsurface

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International

More information

A Case Study: Foundation Design in Liquefiable Site

A Case Study: Foundation Design in Liquefiable Site RESEARCH ARTICLE OPEN ACCESS A Case Study: Foundation Design in Liquefiable Site Tahar Ayadat* *(Department of Civil Engineering, College of Engineering, PMU University, P.O. Box 1664, Al-Khobar, 31952,

More information

Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS

Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS (Emergency Concepts, Security Exits, Cross-section Design, Guideway Types in the tunnel, Sonic-Boom-Effects, Shocks) (*) Author: Dipl.-Ing. Andreas WERTH,

More information

Application of Vibro Techniques for Infrastructure Projects in India

Application of Vibro Techniques for Infrastructure Projects in India Application of Vibro Techniques for Infrastructure Projects in India Rainer Wegner Contract Manager, Keller Grundbau GmbH, Germany Dr. V.R. Raju Director, Keller Ground Engineering India Pvt Ltd, India

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 7.4 PERMEATION GROUTING 7.4.1 Definitions 7.4.1.1 Geotechnical Data Report (GDR)

More information

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more. TECHNOLOGY Diaphragm walls Diaphragm walls are one of the most important technologies of special foundation engineering. A diaphragm wall is constructed using a trench excavated in ground and supported

More information

E-Power Pipe : A new trenchless method for underground cable installation

E-Power Pipe : A new trenchless method for underground cable installation E-Power Pipe : A new trenchless method for underground cable installation Dr. Gerhard Lang Jan 31, 2018 - UCT 2018, Track XI High Voltage Power Grid in Germany. Intention to replace nuclear power plants

More information

Civil Engineering Construction I (CBE5031)

Civil Engineering Construction I (CBE5031) Civil Engineering Construction I (CBE5031) Basement 1 1 Quick Revision 1.1 Problems arising from basement construction a) Excavation method. b) Surface and ground water control c) Lateral stability of

More information

Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines

Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines Joseph Donohue 1, R. Greg Eberhardt 2 and Ildiko Juhasz 3 1 Associate, Arup 2

More information

Cost Estimating Framework

Cost Estimating Framework Cost Estimating Framework Water and Wastewater Master Study Prepared by: GM BluePlan Engineering for: Project No. 717022 TABLE OF CONTENTS 1 Introduction... 1 2 Cost Estimation Framework... 2 2.1 Approach

More information

Numerical analysis of a 36 m deep diaphragm wall parametric study

Numerical analysis of a 36 m deep diaphragm wall parametric study Geotechnical Aspects of Underground Construction in Soft Ground Yoo, Park, Kim & Ban (Eds) 2014 Korean Geotechnical Society, Seoul, Korea, ISBN 978-1-138-02700-8 Numerical analysis of a 36 m deep diaphragm

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

These challenges can only be mastered by a partner familiar with the complexity of building metros.

These challenges can only be mastered by a partner familiar with the complexity of building metros. METROs Tunnel construction straight through large cities requires special skills Underground railways are fast, environmentally friendly, efficient and an ideal solution for moving people, particularly

More information

Ground Freezing for Tunnel, Shafts, and Adits

Ground Freezing for Tunnel, Shafts, and Adits Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction

More information

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone Gue See Sew G&P Professionals Sdn Bhd www.gnpgroup.com.my 20 July 2016 CONTENTS INTRODUCTION SOIL PARAMETERS

More information

Dulles Corridor Metrorail Project Phase 1 NATM Tunnel Construction at Tysons Corner

Dulles Corridor Metrorail Project Phase 1 NATM Tunnel Construction at Tysons Corner Dulles Corridor Metrorail Project Phase 1 NATM Tunnel Construction at Tysons Corner Committee on Tunnels and Underground Structures (AFF60) 23 January 2012 Vojtech Gall, PhD, PE Project Overview Project

More information

Shallow Cover Tunnel Under Heritage Listed Brick Buildings: Brisbane Boggo Road Busway Tunnel

Shallow Cover Tunnel Under Heritage Listed Brick Buildings: Brisbane Boggo Road Busway Tunnel Shallow Cover Tunnel Under Heritage Listed Brick Buildings: Brisbane Boggo Road Busway Tunnel by Ted Nye, Tunnel Designer Manager, Sinclair Knight Merz and Max Kitson, Senior Geotechnical Engineer, Sinclair

More information

Compensation grouting for TBM tunnelling beneath shallow-cover

Compensation grouting for TBM tunnelling beneath shallow-cover Compensation grouting for TBM tunnelling beneath shallow-cover E. Chiriotti, N. Avagnina & P. Grasso Geodata S.p.A., Torino, Italy G. Tripoli IGM S.r.l., Basiglio (MI), Italy ABSTRACT: The last section

More information

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /

More information

THE ADVANTAGES OF THE USE OF GPS BASED LOGGING SYSTEMS FOR VERTICAL DRAIN INSTALLATION PROJECTS

THE ADVANTAGES OF THE USE OF GPS BASED LOGGING SYSTEMS FOR VERTICAL DRAIN INSTALLATION PROJECTS International Conference on Soft Ground Engineering (ICSGE2015) 3-4 December 2015, Singapore THE ADVANTAGES OF THE USE OF GPS BASED LOGGING SYSTEMS FOR VERTICAL DRAIN INSTALLATION PROJECTS JEROEN DIJKSTRA

More information

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. Roger Woodhead, PhD, P.Eng., SNC-Lavain Inc. Paper prepared for

More information

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering DATE: August 31, 2000 Earth Mechanics, Inc. Geotechnical & Earthquake Engineering TECHNICAL MEMORANDUM EMI PROJECT NO: 99-136 PREPARED FOR: COPIES: PREPARED BY: Tayfun Saglam / Parsons Brinckerhoff Juan

More information

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

Passage under Lövstavägen at Bypass Stockholm From Design to Realization Passage under Lövstavägen at Bypass Stockholm From Design to Realization Roslin Mattias 1, Borio Luca 2 and Tomas Hellström 3 1 Swedish Transport Administration, Solna Strandväg 98, 171 54 Solna, mattias.roslin@trafikverket.se

More information

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall Geotechnical Aspects of Underground Construction in Soft Ground Yoo, Park, Kim & Ban (Eds) 2014 Korean Geotechnical Society, Seoul, Korea, ISBN 978-1-138-02700-8 Case study of deep excavation in existing

More information

Concrete Pipe Jacking

Concrete Pipe Jacking Concrete Pipe Jacking Technical Brief CPAA Introduction Concrete pipe jacking is a method of installing pipelines without disrupting existing surface facilities or activities. Pipe jacking has been used

More information

Steel screw settlement reduction piles for a raft foundation on soft soil

Steel screw settlement reduction piles for a raft foundation on soft soil Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Alexei Murashev Opus International Consultants Limited, Wellington, New Zealand. Keywords: piled raft, settlement

More information

Introduction to CPT. Peter K. Robertson. Santiago, Chile. CPT in Geotechnical Practice. July, 2014

Introduction to CPT. Peter K. Robertson. Santiago, Chile. CPT in Geotechnical Practice. July, 2014 Introduction to CPT Peter K. Robertson CPT in Geotechnical Practice Santiago, Chile July, 2014 Ground Investigation To investigate ground and groundwater conditions in and around site consistent with project

More information

Class I and Class II Micro-Piles with Hollow- Bar Reinforcement. Load Tests and Performance Measurements

Class I and Class II Micro-Piles with Hollow- Bar Reinforcement. Load Tests and Performance Measurements Class I and Class II Micro-Piles with Hollow- Bar Reinforcement Load Tests and Performance Measurements Introduction Hollow-Bar Characteristics (based solely upon our observations and the comments of other

More information

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective Purdue Geotechnical Society Workshop Digging Deep April 8, 2011 Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective David Chapman, P.E. Lachel & Associates, Inc. Morristown, NJ Hudson

More information

11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE

11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE 11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE 11.1 introduction 11.1.1 The objective of this section and the statements presented is to assess the existing hydrological and hydrogeological conditions to understand

More information

Compaction and Jet Grouting

Compaction and Jet Grouting Compaction and Jet Grouting Alan Ringen, PE Senior Vice President Breakthroughs in Tunneling Short Course August 16, 2017 Grouting Principles Geotechnical Grouting: The injection of pumpable fluid materials

More information

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata Open Journal of Geology, 2013, 3, 44-48 http://dx.doi.org/10.4236/ojg.2013.32007 Published Online April 2013 (http://www.scirp.org/journal/ojg) Behavior of Surrounding Soil during Construction and Its

More information

Building Construction

Building Construction Building Construction Shallow Foundations Module-III Introduction The foundation can be classified broadly into two types: Shallow foundations Deep foundations Shallow foundations Shallow Foundations When

More information

Grouting Bilfinger Spezialtiefbau GmbH

Grouting Bilfinger Spezialtiefbau GmbH Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com

More information

The HKIE Structural Examination Written Examination 2017

The HKIE Structural Examination Written Examination 2017 The HKIE Structural Examination Written Examination 2017 Section 2: Design Questions (80% of the Written Examination) Date: 5 December 2017 (Tuesday) Time: 12:00 nn 06:00 pm (Duration: 6 hours) Question

More information

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL Submission for Hulme Prize 2017 LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL F. Saffiyah BADURDEEN 1, G. T. SENTHILNATH 2, 1 Ed. Zublin AG Singapore 2 Geoconsult Asia Singapore

More information

(Old examination format for reference only)

(Old examination format for reference only) The Institution of Structural Engineers Associate-Membership Examination 11 APRIL 2003 INSTRUCTIONS TO CANDIDATE 1. The examination comprises two sessions separated by a lunch break of 1 2 hour, during

More information

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high 1 2 Demand for space in cities often makes it essential to use space below buildings. The concept of deep basement technology has been employed since the middle of last century, but is becoming more popular

More information

Appendix C. Gallery Place Chinatown Station Structural Assessment

Appendix C. Gallery Place Chinatown Station Structural Assessment Appendix C Gallery Place Chinatown Station Structural Assessment Washington Metropolitan Area Transit Authority February 2018 Gallery Place Chinatown Station Passageway RFI Contents APPENDIX C 1.0 Introduction:

More information

Performance review of a pipe jacking project in Hong Kong

Performance review of a pipe jacking project in Hong Kong Geotechnical Aspects of Underground Construction in Soft Ground Ng, Huang & Liu (eds) 2009 Taylor & Francis Group, London, ISBN 978-0-415-48475-6 Performance review of a pipe jacking project in Hong Kong

More information

ALMEDA TUNNEL PAST, PRESENT AND FUTURE

ALMEDA TUNNEL PAST, PRESENT AND FUTURE ALMEDA TUNNEL PAST, PRESENT AND FUTURE Ravi Kaleyatodi, P.E., CPM Senior Assistant Director, City of Houston Ravi.kaleyatodi@cityofhouston.net Paul C. Wallick, P.E., Senior Project Manager Patricia Frayre,

More information

Supervision of Piling Works

Supervision of Piling Works Page 1 of 7 Supervision of Piling Works Sayeed Ahmed Assistant Director (Planning & Development) Independent University Bangladesh, Dhaka, Bangladesh e-mail ABSTRACT Supervision is utmost important in

More information

Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS

Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS Table of Contents APPENDIX SECTION HEADINGS 3-G.1.0 INTRODUCTION 3-G-2 3-G.1.1 Construction Inspections 3-G-2 3-G.1.2. As-Built Survey and Plan 3-G-2 3-G.1.2.1

More information

Performance of high capacity jack-in pile for high-rise building with preboring in weathered sedimentary rock formation

Performance of high capacity jack-in pile for high-rise building with preboring in weathered sedimentary rock formation Performance of high capacity jack-in pile for high-rise building with preboring in weathered sedimentary rock formation Chee-Meng, Chow i), Jason A.H. Lim ii) and Yean-Chin, Tan iii) i) Director, G&P Geotechnics

More information

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS fib Symposium Keep Concrete Attractive, Budapest 2005 COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS Kolic D. 1, Hörlein N. 2, Schneider K. 3, Steiner H. 3 NEURON Consult ZT 1, PORR Tunnelbau GmbH 2, ÖBB-Infrastruktur

More information

WATER LINE IN TUNNELS

WATER LINE IN TUNNELS Section 02517 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Handling, transporting, and installing water line in primary liner tunnels, including invert cleanup and blocking and water line in casings that

More information

PILE CAPACITY REDUCTION OF JACK-IN PILES WITH EMPTY PREBORED HOLE AT META-SEDIMENTARY FORMATION IN PENINSULAR MALAYSIA

PILE CAPACITY REDUCTION OF JACK-IN PILES WITH EMPTY PREBORED HOLE AT META-SEDIMENTARY FORMATION IN PENINSULAR MALAYSIA PILE CAPACITY REDUCTION OF JACK-IN PILES WITH EMPTY PREBORED HOLE AT META-SEDIMENTARY FORMATION IN PENINSULAR MALAYSIA Liew Shaw Shong, Ho Shu Feng and Voon Boo Chuan G&P Geotechnics Sdn Bhd, Wisma G&P,

More information

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii Preface to the Third Edition xiii About the Authors xv Acknowledgements xvii Contents PART ONE: THEORY...1 1. Groundwater in Construction...3 1.1 Groundwater in the Hydrologic Cycle 3 1.2 Origins of Dewatering

More information

Access Road Construction of the Larsi Building Using Reinforced Earth Walls

Access Road Construction of the Larsi Building Using Reinforced Earth Walls Missouri University of Science and Technology Scholars' Mine International Conference on Case Histories in Geotechnical Engineering (2013) - Seventh International Conference on Case Histories in Geotechnical

More information

Contract No. NE/2016/01 Site Formation and Infrastructure Works for Development of Anderson Road Quarry Site

Contract No. NE/2016/01 Site Formation and Infrastructure Works for Development of Anderson Road Quarry Site Contract No. NE/2016/01 Site Formation and Infrastructure Works for Development of Anderson Road Quarry Site Award submission for Temporary Works Excellence Award 2017 PROJECT BACKGROUND This Contract

More information

Downloaded from Downloaded from /1

Downloaded from  Downloaded from  /1 PURWANCHAL UNIVERSITY VI SEMESTER FINAL EXAMINATION-2003 LEVEL : B. E. (Civil) SUBJECT: BEG359CI, Foundation Engineering. Full Marks: 80 TIME: 03:00 hrs Pass marks: 32 Candidates are required to give their

More information

Forensics by Freezing

Forensics by Freezing Forensics by Freezing Joseph A. Sopko, Ph.D., P.E., M.ASCE Moretrench American Corporation, 100 Stickle Avenue, Rockaway, NJ 07866, e-mail: jasopko@moretrench.com ABSTRACT Subsurface conditions in water

More information

Prepared by Elie F. Issa, Eng. D.E.C. August 2016

Prepared by Elie F. Issa, Eng. D.E.C. August 2016 Prepared by Elie F. Issa, Eng. D.E.C. August 2016 SAMA BEIRUT Sama Beirut is the tallest reinforced concrete tower in Lebanon soaring at a height of 220m from ground level Project Entities Owner Antonios

More information

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2 Slide 1 PIPE JACKING An introduction to pipe jacking prepared by the Pipe Jacking Association This introduction to pipe jacking has been prepared by the Pipe Jacking Association as an aid to engineers

More information

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Overall Information Location: Singapore Date of Completion: 2010 Cost: $5.7 billion Architect: Moshe Safdie Executive Architect: Aedas, Pte

More information

Deformation monitoring and analysis of deep foundation pit of Xiaoshan rainbow Boulevard

Deformation monitoring and analysis of deep foundation pit of Xiaoshan rainbow Boulevard Available online www.jocpr.com Journal of Chemical and Pharmaceutical Research, 2014, 6(4):69-74 Research Article ISSN : 0975-7384 CODEN(USA) : JCPRC5 Deformation monitoring and analysis of deep foundation

More information

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

ROTARY DRILLING TECHNIQUES LARGE DIAMETER INTRODUCTION This paper presents details about large diameter rotary drilling techniques typically employed in the civil engineering industry. These techniques have also been applied to the resources /

More information

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5 .364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. Due: Friday December 2. This question concerns the stability of an open slope cutting that will be used to provide construction access for a 3.2m deep

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5 Turbine Foundation Construction Method Statement Copyright ESB International Limited, all rights reserved. Farm Contents 1 Introduction

More information

Comparison of Liquefaction Mitigation Options: A Christchurch Case Study

Comparison of Liquefaction Mitigation Options: A Christchurch Case Study Comparison of Liquefaction Mitigation Options: A Christchurch Case Study 2013 NZSEE Conference D.P. Mahoney & J. Kupec Aurecon New Zealand Limited. ABSTRACT: Following the 4 September 2010 M w 7.1 Darfield

More information

Structural design and construction of the Carouge-Bachet underground railway station in Switzerland

Structural design and construction of the Carouge-Bachet underground railway station in Switzerland Structural design and construction of the Carouge-Bachet underground railway station in Switzerland Franco ROJAS Civil Engineer BG Consulting Engineers Lausanne, CH franco.rojashorna@bg-21.com Franco Rojas

More information

Contracts and Risk. Building blocks for success. Miami, November 14 th, 2016

Contracts and Risk. Building blocks for success. Miami, November 14 th, 2016 Contracts and Risk Building blocks for success Miami, November 14 th, 2016 Risk, what risk? Heathrow 100% Cost Overrun 6 month delay Channel Tunnel 80% cost overrun Hallandsas 300% Cost overrun 10+ years

More information

Better ZSOIL, Better Geotechnical Analysis

Better ZSOIL, Better Geotechnical Analysis SYMPOSIUM : NUMERICS IN GEOTECHNICS & STRUCTURES 26 YEARS ZSOIL.PC DATE :1-2.09.2011 Better ZSOIL, Better Geotechnical Analysis Practice of Pile Foundation Treatment Based on ZSOIL.PC YIN JI 1,2 Email:sh_geofem@hotmail.com

More information

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel.

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel. Rock Tunnel Engineering INTRODUCTION Tunnel a hole in the ground to provide for desired movement or as mobility channel. Serves as highway, railroad, pedestrian passageway, water conveyance, waste water

More information

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL Roger BREMEN Engineer of the Hydraulic Department Lombardi Engineering Limited Via Simen 19 CH 6648 Minusio Switzerland ABSTRACT: A 7.5 km long

More information

Technical Data Sheet NEC/GRAN/95:01

Technical Data Sheet NEC/GRAN/95:01 Technical Data Sheet NEC/GRAN/95:01 Installation Guidance Notes Granular Surround Note : These guidance notes refer only to the installation of Granular surround underground tanks. These guidance notes

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

Research on the Effects of Foundation Excavation by the Environment

Research on the Effects of Foundation Excavation by the Environment 2015 2 nd International Conference on Material Engineering and Application (ICMEA 2015) ISBN: 978-1-60595-323-6 Research on the Effects of Foundation Excavation by the Environment Manxia Wu 1, Wen Wang

More information

CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD

CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD North American Society for Trenchless Technology (NASTT) No-Dig Show 2012 Nashville, TN Paper A-2-04 CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD Christopher

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Site Investigation MUHAMMAD AZRIL HEZMI

Site Investigation MUHAMMAD AZRIL HEZMI Site Investigation MUHAMMAD AZRIL HEZMI Definition Essential part of the preliminary design workon any important structure in order to provide adequateand reliable geotechnical informationand site condition,

More information

The construction of deep excavation ditch in weak soil in St. Petersburg

The construction of deep excavation ditch in weak soil in St. Petersburg Geotechnical Aspects of Underground Construction in Soft Ground Viggiani (ed) 2012 Taylor & Francis Group, London, ISBN 978-0-415-68367-8 The construction of deep excavation ditch in weak soil in St. Petersburg

More information

reinforced besser block retaining walls

reinforced besser block retaining walls reinforced besser block retaining walls Preface The designs shown in the brochure are based on limit state design in accordance with the provisions of AS4678-2002 Earth retaining structures standard including

More information

Geotechnical Investigation Reports and Foundation Recommendations -Present status in India -Examples

Geotechnical Investigation Reports and Foundation Recommendations -Present status in India -Examples Geotechnical Investigation Reports and Foundation Recommendations -Present status in India -Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: rajuvs_b@yahoo.com

More information

Relationship between twin tunnels distance and surface subsidence in soft ground of Tabriz Metro - Iran

Relationship between twin tunnels distance and surface subsidence in soft ground of Tabriz Metro - Iran University of Wollongong Research Online Coal Operators' Conference Faculty of Engineering and Information Sciences 2012 Relationship between twin tunnels distance and surface subsidence in soft ground

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

EXTRACT. MONITOR. CONTROL.

EXTRACT. MONITOR. CONTROL. GUIDANCE OF ABSTRACTION AND DISCHARGE PERMITS FOR OPERATIONS When considering any potential dewatering requirement, it is necessary to consider the following questions: Are we allowed to abstract groundwater,

More information

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document

More information