PART - II Technical Specification

Size: px
Start display at page:

Download "PART - II Technical Specification"

Transcription

1 GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED SARDAR PATEL VIDYUT BHAVAN RACE COURSE, VADODARA TENDER SPECIFICATION FOR Annual rate contract for Laying, Erection, Testing and commissioning of 1C, 300 mm 2 & 1C, 630 mm 2 66kV XLPE Cable for Various Line TENDER SPECIFICATION TENDER NO GETCO / 66KV CABLE ARC/ PART - II Technical Specification Sign & seal of Bidder 1

2 PART II SPECIFICATIONS FOR LAYING, INSTALLATION, TESTING & COMMISSIONING OF 1-CORE 66 KV XLPE POWER CABLES 1.1 SCOPE OF WORK: The installation, testing and commissioning work shall mainly consist of: a. Design, detailed Engineering, transportation at site, storage, laying(including civil works), jointing, terminations, testing at site & commissioning of 66 KV XLPE cable alongwith its accessories. b. Route survey of the entire length under scope of work. c. Loading / unloading of cable drums at site or from stores of Corporation d. Laying of 66 KV grade XLPE cables through buried trench with necessary clamping arrangement as per specification. e. Formation of buried cable trenches for 66 KV cables as per specification including supply and installation of warning tape, providing RCC precast cable protection covers for entire route (underground portion only), construction of jointing chambers, backfilling of trenches & restoration as per specification. f. Trench less digging where the concern authorities do not permit open cut method. g. Road crossings through RCC pipe for each Circuit and restoration of ground surface as per specification h.. Road crossings through PVC pipe (where open Excavation not permitted) for each Circuit and restoration of ground surface. i. Cable markers as per statutory requirement shall be provided all along the route at a maximum distance of 50 meters and other important locations. Also the location of underground cable shall be clearly indicated on the marker. j. Co-ordinating for installation of straight through joints & end termination for complete route. k. Supply and installation of all critical installation materials like trefoil clamps, support brackets, etc as required for complete route to avoid damages of the cable. l. Bonding of screen / sheath to the earth station through disconnecting type link boxes and SVL (sheath voltage limiter). Bidder shall suggest type of bonding for route under scope with detail calculations. Earthing stations / Earthing pits, wherever applicable for complete route shall be in contractor s scope. m. Co-Axial cable laying in PVC pipe along with cables as per attached drawing. n. The successful bidder has to carry out necessary fabrication work for end terminations at sub-station end. Similarly he shall provide ladder / tray for laying cable on towers and to provide required supports to end terminations & LA on towers. Sign & seal of Bidder 2

3 o. In entire cable trench, RCC precast slab of size 600 x 300 x 50 mm is to be provided on both the side & upper side of 1C x 300mm 2 power cable for protection purpose as shown in drawing. p. For End termination & St. through jointing work, Certificate of cable Jointing person from manufacture of cable kit for this type of job is mandatory, Site in charge will asked copy of certificate before taking up cable jointing work. 1.2 General: This specification covers installation, testing and commissioning of 38/66 KV XLPE single core power cables for following line as under. Sr. No Name of line 1 66KV 300 mm2 XLPE Cable (S/C) 2 66KV 300 mm2 XLPE Cable (D/C) 3 66KV 630 mm2 XLPE Cable (S/C) 4 66KV 630 mm2 XLPE Cable (D/C) Provision of special tools / appliances required for cable jointing and stripping / dressing and application of XLPE insulation etc. shall be made by the successful tenderer The successful tenderer shall furnish all necessary information, including drawings, manuals and instructions relating to both cable laying and jointing practice Successful tenderer has to arrange at his own for first-aid, fire protection, electricity and water requirement at site. He shall also arrange for signboard, caution board, safety & security personnel etc. on cable route Approval for installation of the underground cable route from Electrical Inspector shall be arranged by Purchaser. However, permission for commencement of work and permission for commissioning of cable after completion of laying has to be arranged by the successful tenderer Successful tenderer shall arrange space for working office, workshop & store / yard for storing requisite materials like kits, cables etc The cable laying shall have to be done, as per actual site condition at the time of execution, and as per the instruction of the engineer-in-charge The structures for termination of the cable at substation end shall be arranged by the GETCO. Necessary arrangement shall be made by the engineer-in-charge. Laying of cable also includes erection & clamping of 66KV cable on erected structures at sub-station end The Un-priced schedule of the offered item shall also be submitted in technical Bid The end of cut pieces of cables left out during executions shall be sealed to prevent ingress of any moisture in the cable before handing over to consignee. Sign & seal of Bidder 3

4 The consignee shall be concern Executive Engineer (const.), Gujarat Energy Transmission Corporation Limited, Detailed route and sectional view for laying cables are as per attached drawing The rate of laying of 66 KV Cable covers the cost of fixing of 3 phase earth box and laying of Co axial cable Civil work for all other Nala crossings, road crossing, earthing pit, straight joint chambers etc. for all the above lines shall be considered in scope of bidder The construction drawings shall got approved from Chief Engineer (Project) include the longitudinal sectional diagram of the trench for different soil strata and detailed arrangement of crossings, number of pipes, size of pipes, location and position of manholes, other details as per the technical specifications Any other items not specifically mentioned in the specifications but which are required for installation, testing, commissioning and satisfactory operation of the cable as per Indian standards / IE Rules / IE Act and local authority regulations are deemed to be included in the scope of the specification and no deviation in this regard shall be accepted The Contractor shall also be responsible for the overall co-ordination with internal / external agencies, project management, training of Company s manpower, loading, unloading, handling, moving to final destination for successful erection, testing and commissioning of the 66 KV cable Contractor will have to provide complete technical supervision during installation of cables right from transport up to testing and commissioning. The contractor shall arrange for the services of fully qualified and competent supervisors / engineers for monitoring the whole job. Competent and wellversed Semi skill labourers shall be deployed for execution All the associated civil works, which are necessary in cable laying job, shall have to be carried out completely by the Contractor at no additional cost The Cable Arrangement in trench / ground, showing the proposed installation of 66 KV power cables in Single / double (3 Nos. of single core cables per circuit in trefoil arrangement) is as per the attached drawings Contractor has to arrange on his own for the safety and security of his persons and shall also make arrangements for Safety tools and tackles, first aid, fire protection as per safety norms The Contractor has to bear with any temporary interruption that may occur during actual cable laying work, where the work with other agency is involved No idling charges or cost over run for the entire project shall be entertained. 1.3 Route Survey The bidder shall fully familiarize himself with the site and route conditions etc. The bidders are advised to visit the site and acquaint themselves with the topography, infrastructure etc. The contractor shall be fully responsible for providing all accessories, materials, system and services specified or otherwise which are required to complete the erection and successful commissioning, of 66 KV cable in all respects. All materials required for the Civil and construction / installation work shall be supplied by the Contractor. The Contractor shall do the complete design and detailed engineering. The Sign & seal of Bidder 4

5 survey shall be conducted for underground routes to finalize the route and paths for the underground cable. 1.4 Map Study: The Company shall provide tentative route map of line along with the concerned area. The Contractor shall carry out the survey before commencing the work. Contractor shall submit the final survey report for approval before implementation. The final survey report shall include at least the following: a) The distance of the cable route from the center of the road / rail / river / bridge / culvert etc. shall be indicated on the route maps as well as documented in table. b) Location of all turns, bends and major landmarks, road crossing. The survey report shall be approved by the concern and requisite clearances need to be obtained before the cable installation work is commenced. 1.5 Statutory Clearances and permissions : a) All statutory clearances and permissions from various statutory bodies/govt. authorities like forest Department, Railway, Aviation Authority, Maritime Board, National highway Authority, Municipal Corporation, Gram Panchayat (if any), PWD,Telecom Department, right of way and way leave etc. wherever required along the entire route of the cable lines shall be arranged by the Corporation. b) For necessary forest clearance, the Corporation will do the processing and the payment to the central government/state government for compensation of forest clearance will be paid by the Corporation as necessary. for permission from other Govt. authorities like railway, National highway authority etc. the payment shall be made by the Corporation. c) The scope of work shall also include assistance in obtaining required permission / approval from various statutory authorities i.e. Municipal Corporation, Gram Panchayat (if any), PWD,Telecom Department etc. in the interest of progress of the work. Payment demanded by any statutory authority as compensation shall be reimbursed by GETCO on submission of documentary evidence i.e. receipt of such payment made. d) For clearances, permissions etc. from various authorities, the Contractor shall not remain contended by simply informing the Corporation, but shall invariably assist and arrange for personal follow up to overcome the difficulties in the interest of progress of the work. 2.0 Laying and Installation. 2.1 The 66KV (E) XLPE cable shall be laid and buried in ground in accordance with all applicable standards like IS 1255 & its amendments. 2.2 (6+1) / (3+1) single core, 66 KV cable to form 66 KV Double / Single circuit as per scope indicated above, shall be laid throughout the route. However as per requirement of the field, the cables shall also have to be laid: Sign & seal of Bidder 5

6 1) In ducts 2) In RCC Hume pipes at road crossings 3) In PVC pipes at road crossings. 4) In open air / over steel rack (for end termination) 5) At varying depths due to obstructions. 6) Trench less road crossings. 2.3 The route plan of the cable is enclosed with bid documents to enable the bidder to have assessment of the work involved. However the bidder is advised to visit the site and acquaint himself with the topography, infrastructure etc. The contractor shall be fully responsible for providing all equipment, materials which are required to complete the erection and successful commissioning of 66 KV cables in all respects. 2.4 The sealing of power cable ends during the storage, execution till jointing work is completed, shall be in the scope of Contractor. In no circumstances, the cable ends shall be kept open. The damages done because of water / moisture ingress or penetration in the cables / con doctors during execution shall be recovered form the Contractor. It will be the responsibility of the Contractor to make them good or replace free of cost without affecting the completion schedules. 2.5 The cables shall be completely surrounded by a layer of sand having low thermal resistivity (selected sand) about 250 mm over & below the cable surface throughout the width of cable trench. 2.6 The excavated cable trench shall be drained of all water and the bed surface shall be smooth, uniform and fairly hard before paying out the cable. 2.7 The cable shall be rolled in the trench on cable rollers spaced out at uniform intervals. 2.8 The paying out process must be smooth and steady without subjecting the cable to abnormal tension. The cable on being laid out shall be smoothly and evenly transferred to the ground after providing the cushion. 2.9 The cables shall never be dropped. All snake bends shall be straightened. Suitable size cable stocking pulling eye shall be used for pulling the cable The new cable end seals shall be applied before starting of laying cable and shall be checked after laying and if found damaged shall immediately be resealed. Sufficient number of heat shrinkable cable end sealing caps shall be stocked at site stores for testing and jointing work. Cable end caps shall be in the scope of the Contractor After the cables have been laid in the trench and until the cables are covered with protective covering, no sharp metal, tool shall be used in the trench or placed in such a position that may fall into the trench The cables shall never be bent, beyond the specified bending radius. Minimum bending radius of XLPE insulated Cables shall be 20 X D (overall diameter of the cable) 2.13 The single core cables shall be laid either in trefoil formation or in flat formation depending upon the site exigencies Whenever cables are laid in trefoil formation, plastic cable ties shall be used at every meter to maintain the trefoil arrangement. The cable portion, which is beyond the buried route, shall have trefoil clamps (nonmetallic) of approved design installed at every meter. Sign & seal of Bidder 6

7 2.15 The identification marker shall be placed on each cable at every 2 mtrs. Interval, of adequate size fabricated from 3 mm thick, 25 mm wide aluminum strip. The marker shall be embossed by letter as stated below as applicable. GETCO 66KV Name of Line PHASE R OR Y OR B 2.16 The power cable shall be laid generally at a depth of 1500 mm and can vary, if obstacles like power cable of other rating / telephone cable / water pipe line etc, come in the way of installation. At least minimum Depth of 1000 mm shall be maintained from nearest road level The extra protection of pre-cast flat RCC slab with proportion 1:2:4 having size 600 (L) x 300 (B) x 50 (Thk) mm shall be provided about 250 mm over the power cables for complete route of the cable. The RCC slab shall be with proportion not less than 1:2:4 (M-150) and also shall have steel reinforced of 6 / 8 mm dia. steel bar (4 Nos. of 300 mm side and 5 Nos. on 600 mm side) at adequate required distance. The slab shall be given curing time of minimum 15 days The portion of pre cast flat RCC slab having size 300 (L) x 50 (B) x 600 (H) mm shall be provided between two circuits of power cables 150 mm apart from the outermost cables of each circuits for complete route of the cable Normally, the back filling shall consist of the materials earlier excavated, however, bigger stones or piece of rock should be removed OR if required new soil has to be provided and used for back filling with no extra cost The contractor has to keep 66kv power cable & material issued to him in safe custody and transport to the respective sites and will be fully responsible for any damage to or loss of any or all allotted equipments or materials supplied to him at any stage during transportation or erection or taking over of the cable line by the GETCO. The contractor has to return empty cable drum as instructed by E.I.C. The Contractor has to open site store at sub station site or at place nearby the sub station site and ensure for safe custody of all the stored materials at his own cost The Contractor shall have total responsibility for the entire materials stored, loose, semi assembled and/or erected by him at site in his custody. The Contractor shall make suitable security arrangements at his own cost to ensure the protection of all materials, equipment and works from theft, fire pilferage and any other damages and loss. It shall be the responsibility of the contractor to arrange for security till the works are finally taken over by the Corporation. 3.0 Storage and handling of Cable drum: 3.1 The cable drums must be handled correctly and properly with due care during transportation and laying of the power cable, in order to avoid damages to the cable as well as to other persons, properties and works. For damages done to any person or properties because of poor handling, Sign & seal of Bidder 7

8 the Contractor will be held responsible & GETCO reserves all the rights to recover such damages from him. 3.2 Cable drums shall be shifted from stores of the Company to site by the Contractor. Also empty drums and extra cable after laying shall be deposited back to the stores. 3.3 Drum position at work site should be properly consolidated and jacks placed on both sides of the drum to make the pay-off arrangement stable. Suitable arrangement is made to stop the drum rotation, during cable laying. 3.4 The cable shall always be pulled off from the top of the drum. 3.5 The end of cut pieces of cables left cut during execution shall be sealed to prevent ingress of any moisture in the cable and shall be brought back to the stores. 4.0 TRENCHING: 4.1 The excavation of trenches shall be commenced with proper coordination with GETCO; after all necessary clearances for the route have been obtained from the competent authorities by GETCO. 4.2 The cable trench work involves earth excavation for cable trench, back filling and removal of excess earth from site. The work site shall be left as clean as possible. 4.3 Before opening of the section of the trench, the contractor shall satisfy himself the line of the trench is clear of underground obstructions, by taking out trial pits on the line of the trench. 4.4 The exact location of each trench shall be approved at site by engineer in-charge. The trenches shall be excavated to approved formation and dimensions. If necessary, the vertical sides shall be timbered or otherwise secured to avoid damages. 4.5 The trench excavation and filling in shall be so executed that all walls, roads, sewers, drains, pipes, cables, structures, places and things shall be reasonably secured against risk of injury and shall be carried out to the satisfaction of the authorities concerned. However, if any, damages to existing services made, Contractor shall arrange and pay for any necessary repair, to make good the damages. 4.6 Contractor has to provide clearly visible fluorescent caution board painted MAN AT WORK in local language at every 30 Mtr. Distance during the work of cable installation. The caution board shall be prepared from MS structure and shall be of free standing type. The barriers shall be with red and white colored cross stripes. Warning and caution boards should be consciously displayed. Red lights as warning signal should be placed along the trench during the nights. 4.7 If any inconvenience is caused to the trespassers / road traffic during the cable installation work, Contractor has to resolve it immediately at his cost. Sign & seal of Bidder 8

9 4.8 At places where the cables cross private roads, gates of residential houses or buildings, the cables shall be laid in PVC/RCC Hume pipes and should confirm to following specification. 1. PVC Pipes with coupler shall confirm to IS: 4985: 2000, Size : 400 mm O.D. Pressure Rating : 6 kg / cm 2 Straight length : 6 mtrs. 2. RCC Hume Pipes shall confirm to IS: , NP-4 class, 4.9 The excavated material shall be properly stored to avoid obstruction to public and traffic movement. Where, owing to traffic or for reasons of safety the excavated material shall be removed from the site and returned for refilling the trench on completion of laying. The contractor, at his own cost, shall dispose off surplus material The bottom of the excavated trench should be leveled flat and free from any object, which would damage the cables. Any gradient encountered shall be gradual When the excavation of the trenches has been accurately executed, the contractor shall inform engineer in-charge for approval. Laying of cables shall not be started until engineer in-charge approves the trench. 5.0 ROAD CROSSINGS 5.1 The road cutting, whether cement concrete or asphalt road surface shall be taken after obtaining approval for cutting from the various civic authorities and work should be planned to be completed in the shortest possible time. Where necessary the work shall be planned during night or light traffic periods. 5.2 Where road crossing comes in way of laying power cable, the power cable shall be laid through NP-4 RCC Hume pipes. Spare cable shall be laid in PVC 150 mm, 6 Kg/cm 2 rating & rate shall be quoted accordingly. The required length of Hume pipe shall be arranged by the successful tenderer at no extra cost. 5.3 The RCC Hume pipe inner dia-meter shall not be less than 400 mm. 5.4 The RCC pipes to be laid shall have minimum depth in such a way that the back filling on top surface of the pipe shall be at least 600mm in depth. The pipe joints shall be smooth so that cables are not damaged during pulling & operation. 5.5 During the crossing of utilities like water line, drainage lines, telephone lines, gas lines etc, sufficient care shall be taken & protection shall be made available so that other utilities do not damage the cable mechanically and / or electrically or do not effect the performance of the cable. 5.6 NALA CROSSINGS / CULVERT CROSSINGS: The Nala crossings are to be made with separate fly-over bridges of adequate sizes to carry all the cables in required formation. The bridges are to be made at the sufficient distances from the edge of Nala considering the further expansions of roads. The strength shall be such that it should not wash away with the flow of water during heavy rain. 6.0 Trench less Digging: Sign & seal of Bidder 9

10 Trench less digging shall also be used where the concerned authorities do not permit open cut method and it is essentially required to carry out for installation of underground cables. The various methods of trench less digging such as hand / manual auguring, HDD (above 40-50m) shall be adopted based on the soil / site conditions and the requirement and exact method for trench less digging shall be finalized during detail engineering as per actual site / soil condition. The equipment used for HDD shall be capable of drilling at least 315mm diameter hole per circuit. The contractor shall propose the exact methods and procedures for implementation of trench less digging at various crossings taking into consideration the following guidelines, for approval by the Engineer In-charge. a) Excavation and backfilling of trial pits and soil investigation (if required) b) Excavation of entry and Exit pits. c) Erection of drill machine. Drilling of pilot hole. d) Placement and driving hand augur e) Reaming and widening of bore holed in steps (if required) f) Pulling of PVC pipes of 6 kg / cm2 ISI make 7.0 Reinstatement: 7.1 Filling in trenches shall not be commenced until engineer in-charge has inspected and approved the cables and accessories. The inspection should be got done on daily basis so that the trenches do not remain open unnecessarily, to avoid inconvenience to public. 7.2 Normally, the back filling shall consist of the materials earlier excavated. However, bigger stones or pieces of rock should be removed and if required new soil has to be used for back filling with no extra cost. 7.3 A pre-warning PVC yellow tape 250 mm wide and 100 microns thick (HDDPE/LLDPE) shall also be laid as per the Drawing. the warning tape shall be printed in RED letter (IN ENGLISH AS WELL AS GUJARATI) as CAUTION: VOLTS GETCO CABLE and to be placed at about 500 mm depth from ground level along the route of cable. 7.4 The contractor shall be responsible for permanent reinstatement of the upper levels, which shall be carried out to the satisfaction of engineer in-charge and the authorities concerned. 7.5 Contractor has to compulsorily spray water on the trench after it is backfilled. In case soil settles due to watering, contractor has to backfill the settled trench. 7.6 After the cables and pipes have been laid and before the trench is backfilled all joints, cable positions and pipe ducts should be carefully plotted and preserved. 8.0 CABLE ROUTE/JOINT MARKER/ IDENTIFICATION 8.1 Permanent means of indicating the position of joints and cable route shall be supplied and laid. Pre cast RCC markers shall be placed as per the field requirement, if the route passes through open fields, markers should be conspicuously visible and above ground surface. The marker should incorporate the following relevant information. Sign & seal of Bidder 10

11 1) The name of the owner GETCO 2) Voltage 66 KV Cable 3) Distance of cable from the marker. 8.2 The minimum size shall be 600 x 300 x 50 mm. It shall be at least embedded in ground up to 500 mm depth. 8.3 The exposed portions shall be painted with non-washable paints. (Preferably yellow paint). Writings shall be painted by red color. 8.4 The interval should be maximum 50 meters between two markers. It should be put at bends, curves, road crossing, etc. of cable route. 8.5 The identification marker shall be of adequate size fabricated from 3 mm thick, 25 mm x 25 mm aluminum strip. The marker shall be embossed with letter as stated below: GETCO - 66KV Line and Phase R or Y or B as the case may be. 8.6 The marker shall be tightened with nylon thread along with each cable at interval of 3 meters in such a way that it does not damage / penetrate the outer sheath of cable because of the dead weight of back filled materials or soil. 9.0 TESTS AFTER INSTALLATION: Pre-commissioning tests on site, to be undertaken by the successful tenderer shall include the following: a) Insulation Resistance of each cable drum length after laying and before jointing. b) Tests for detection of damage to outer sheath, if any. c) Serving insulation resistance after laying each cable length shall withstand a voltage of 10kv DC for one minute between each reinforcement and external conducting surface; In addition, the serving insulation resistance shall be measured and checked with the values obtained during routine factory tests. d) On completion of the cable laying and jointing work, the complete installation shall be checked with a D.C. voltage of 3 Uo applied for 15 minutes between each conductor and sheath. e) Conductor resistance of each cable of each complete circuit. f) Test for 5 min. with system voltage applied between the conductor and the screen. g) Test for 24 hours with normal operating voltage of the system. h) Continuity & Phase confirmation. NOTE: The pre-commissioning test at (f) or (g) at site to be undertaken as an alternative to the test (d) Jointing and Termination of Cables: 10.1 Contractor has to co-ordinate and provide necessary facilities for Carrying out joints / terminations Jointing work shall commence as soon as two or three lengths of cables have been laid Sufficient overlap of cables as shall be allowed for making the joints The joint bay should be of sufficient dimensions to allow jointers to work with as much freedom of movement and comfort as possible The joints of different phases shall be staggered in the jointing bay An enclosure or suitable protection cover shall be used in all circumstances wherever jointing work is carried out in the open Sign & seal of Bidder 11

12 irrespective of the weather conditions. The joint shall be in dust free, moisture free and clean atmosphere If the cable ends seals or cable ends are found to have suffered damage the cable should not be jointed, without tests and rectification The instructions furnished by the termination manufacturer shall be strictly followed for jointing/ termination work Sufficient length of spare cable shall be left in the ground, for future needs The cable shall be fixed properly using non-metallic clamps All the pre commissioning tests shall be carried out by the Bidder If any abnormality found during testing, bidder will have to rectify the same at no extra costs. Sign & seal of Bidder 12

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

TECHNICAL SPECIFICATION OF MS TOR BARS FOR TRANSMISSION LINES

TECHNICAL SPECIFICATION OF MS TOR BARS FOR TRANSMISSION LINES GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATION OF MS TOR BARS FOR TRANSMISSION LINES GETCO/E/TS-MS024/R2 DT08-02-2012 TECHNICAL

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 604 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE TABLE OF CONTENTS 604.01 SCOPE 604.02 REFERENCES 604.03 DEFINITIONS - Not Used

More information

TECHNICAL SPECIFICATION FOR MS BEAMS 116X100 11MTR LONG FOR SUB-STATIONS

TECHNICAL SPECIFICATION FOR MS BEAMS 116X100 11MTR LONG FOR SUB-STATIONS GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATION FOR MS BEAMS 116X100 11MTR LONG FOR SUB-STATIONS GETCO/E/TS-MS024/R0DT01-04-2008

More information

CHAPTER 11 CONDUITS AND FITTINGS

CHAPTER 11 CONDUITS AND FITTINGS CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1

More information

CONDUITS AND FITTINGS

CONDUITS AND FITTINGS CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. "Beit Hanoun Emergency Water Supply Project"

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. Beit Hanoun Emergency Water Supply Project "Beit Hanoun Emergency Water Supply Project" " Rehabilitation and Construction of Beit Hanoun Water Network " BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE Bill of Quantities PREAMBLE TO

More information

NPS/002/020 Technical Specification for 11 & 20kV Power Cables

NPS/002/020 Technical Specification for 11 & 20kV Power Cables Version:- 3.1 of Issue:- Nov - 09 Page 1 of 11 NPS/002/020 Technical Specification for 11 & 20kV Power Cables 1. Purpose The purpose of this document is to detail Northern Powergrid (the Company) requirements

More information

Tender No. : GAIL/PA14/51603/ /RK [E-Tender Bid Invitation No ]

Tender No. : GAIL/PA14/51603/ /RK [E-Tender Bid Invitation No ] 1.1 SCHEDULE OF RATES SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF 8A RATING, MMO VERTICAL ANODE BED: Supply, installation, testing and commissioning of 8 A rating, MMO tubular anode in vertical type

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

Specifications for Electrical Underground Residential Distribution Systems

Specifications for Electrical Underground Residential Distribution Systems Specifications for Electrical Underground Residential Distribution Systems Specification DDS-2 Revision 13, February 2010 ONCOR ELECTRIC DELIVERY COMPANY SPECIFICATIONS FOR ELECTRICAL UNDERGROUND RESIDENTIAL

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

ORDINANCE ON TECHNICAL REQUIREMENTS FOR CABLE DUCTS

ORDINANCE ON TECHNICAL REQUIREMENTS FOR CABLE DUCTS Pursuant to Article 12, paragraph 1, item 1 and Article 24, paragraph 8 of the Electronic Communications Act (Official Gazette No. 73/08), the Council of the Croatian Post and Electronic Communications

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

SCOPE OF WORK FOR PILING JOB

SCOPE OF WORK FOR PILING JOB SCOPE OF WORK FOR PILING JOB 1.0 PURPOSE This document defines the scope of works and specific requirements for the tank pad construction including pile foundation system for the proposed tanks at Wadala

More information

Quotation Notice for installation of 20 Street Lights in Kaloor JLN Stadium premises

Quotation Notice for installation of 20 Street Lights in Kaloor JLN Stadium premises Quotation Notice for installation of 20 Street Lights in Kaloor JLN Stadium premises Kochi Metro Rail Ltd (KMRL), Invites quotation for Supply, Installation, Testing and Commissioning of decorative cast

More information

ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL DESCRIPTION OF ITEMS PRICES TO BE FULLY INCLUSIVE...

ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL DESCRIPTION OF ITEMS PRICES TO BE FULLY INCLUSIVE... ANNEX 3 DETAILED PRICE SCHEDULE RELATED TO THE BILL OF QUANTITIES 1. GENERAL... 3 2. DESCRIPTION OF ITEMS... 5 3. PRICES TO BE FULLY INCLUSIVE... 5 4. COVERAGE... 6 5. BIDDER TO PRICE EACH ITEM... 6 6.

More information

PROJECT: INCREASE DEMAND FOR UNIVERSITY OF FIJI- KULA STREET SAMABULA SCHEME: G115-15

PROJECT: INCREASE DEMAND FOR UNIVERSITY OF FIJI- KULA STREET SAMABULA SCHEME: G115-15 TENDER NO MR 151/2016 PROJECT: INCREASE DEMAND FOR UNIVERSITY OF FIJI- KULA STREET SAMABULA SCHEME: G115-15 Notes : 1. Bidders to provide 2 hardcopies of tender bid. 2. Safety Plan to be incuded in tender

More information

SPECIFICATION : BORING AND JACKING

SPECIFICATION : BORING AND JACKING SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in

More information

You are also similarly responsible for any part crossing any neighbouring land, including any length of private service pipe in the public highway.

You are also similarly responsible for any part crossing any neighbouring land, including any length of private service pipe in the public highway. Shared supply or lead water pipe replacement connections guidance notes Up to 25mm diameter supplies Introduction Our aim is to deliver an excellent standard of service. In order for us to do this and

More information

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The work covered by this Section includes all labour, materials, equipment, and supervision necessary to complete the site services as shown

More information

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT 1.1 General 1.1.1 These Special Conditions of Contract supplement the General Instructions.

More information

Installation Information 2016

Installation Information 2016 Installation Information 2016 DENDRO-SCOTT Root Barrier... why use anything else? DENDRO-SCOTT Root Barrier, recognised by the Environment Agency, is known for its quality and reliability. It is flexible

More information

Section 2: Underground

Section 2: Underground Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

Excavations and Blind Penetrations into Walls & Floors

Excavations and Blind Penetrations into Walls & Floors Excavations and Blind Penetrations into Walls & Floors (Instructions for using JLab DIGGING, EXCAVATING, FLOOR/WALL PENETRATION PERMIT REQUEST) Permits are required on JLAB property for any penetrations

More information

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics HEKAPLAST PE-HD twin wall cable ducts and cable protection pipes for underground installation HEGLER HEKAPLAST III/ HEKAPLAST: Twin wall cable ducts or cable protection pipes to DIN 696, manufactured from

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

Estimate FOR THE SEPTIC TANK

Estimate FOR THE SEPTIC TANK Estimate FOR THE SEPTIC TANK S.NO ITEM DESCRIPTION. 1 Excavation in soil,soft & hard murum... Qty UNIT Rate Excavation for footing, machine foundation, plinth beams, wall footing, gutters,brick wall, tanks

More information

BIDDING FOR A FIBER PROJECT

BIDDING FOR A FIBER PROJECT IMTFIBER NIGERIA BIDDING FOR A FIBER PROJECT PROJECT DOCUMENTATION TIPS 1/1/2016 ADEJOLA JOHNSON Msc. CEO Imt computers Nig. Ltd FOA Representative in Nigeria #718 www.imtfiber.com info@imtfiber.com 08039576767

More information

WIRING METHODS CHAPTER 38

WIRING METHODS CHAPTER 38 CHAPTER 38 WIRING METHODS SECTION E3801 GENERAL REQUIREMENTS E3801.1 Scope. This chapter covers the wiring methods for services, feeders and branch circuits for electrical power and distribution. E3801.2

More information

PART A : CPVC PIPES AND FITTNGS (EXTERNAL WATERSUPPLY):

PART A : CPVC PIPES AND FITTNGS (EXTERNAL WATERSUPPLY): PART A : CPVC PIPES AND FITTNGS (EXTERNAL WATERSUPPLY): 01 Providing and Fixing of CPVC pipes confirming to ASTM standard including all CPVC fittings like tees, elbows, bends, unions, coupling, reducer

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

Bill of Quantity (BOQ)

Bill of Quantity (BOQ) United Nation Development Programme Construction Salah El Deen Road Median From Al Zawaida entrance to Al Maghazi Northern entrance PAL 10-00071488 Bill of Quantity (BOQ) PREAMBLE TO BILL OF QUANTITY (BOQ)

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

PRECAST CEMENT PRODUCTS

PRECAST CEMENT PRODUCTS Profile No.: 30 NIC Code: 23959 PRECAST CEMENT PRODUCTS 1. INTRODCUTION: Reinforced cement concrete products are becoming popular as modular house and apartment buildings are based on standard designs.

More information

GV 001 Equipment Bases and Enclosures General Information

GV 001 Equipment Bases and Enclosures General Information Eq u ip me n tba s e s a n d En c lo s u re s Ge n e ra lin fo rma tio n E n g in e e r :R.An th o n GV0 0 1 Ap p r o v e r :Jo s h u a Jo n e s Ap r 1 7 2 0 Ap r1 7 GV 001 Equipment Bases and Enclosures

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES RFP/GRC/LSV/2017-003: RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES 1/7 The Contractor shall consider in his price all costs or expenses of all requirements stipulated

More information

Basic Service. This Section provides information regarding a. Introduction

Basic Service. This Section provides information regarding a. Introduction Basic Service Introduction This Section provides information regarding a new electric Basic Service for a single phase service less than or equal to 400 amps, and a three phase service less than 50kW.

More information

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

***************************************************************************************************************

*************************************************************************************************************** 02735 WASTE WATER DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 22 14 00 ***************************************************************************************************************

More information

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS SECTION 270528 PATHWAYS FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Communications equipment coordination and installation. 2. Sleeves for pathways and cables. 3. Raceway

More information

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 401 NOVEMBER 2010 CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING TABLE OF CONTENTS 401.01 SCOPE 401.02 REFERENCES 401.03 DEFINITIONS

More information

An introduction to. pipe jacking

An introduction to. pipe jacking An introduction to pipe jacking The pipe jacking technique The major applications for pipe jacking and microtunneling include new sewerage and drainage construction, sewer replacement and lining, gas and

More information

TECHNICAL SPECIFICATION FOR CLAMPS & CONNECTORS FOR 66/132/220/400 KV SUB-STATION

TECHNICAL SPECIFICATION FOR CLAMPS & CONNECTORS FOR 66/132/220/400 KV SUB-STATION GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATION FOR CLAMPS & CONNECTORS FOR 66/132/220/400 KV SUB-STATION GETCO/E/TS-C&C

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION IV. PIPELINE EXCAVATION AND BACKFILL SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include

More information

TECHNICAL SPECIFICATION A.B. CABLE

TECHNICAL SPECIFICATION A.B. CABLE TECHNICAL SPECIFICATION A.B. CABLE 1.0 NATURE OF WORK The work covered by this Specification is for L.T lines in A.B cable as specified herein and in the attached Schedules. The overhead distribution lines

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

***************************************************************************************************************

*************************************************************************************************************** 02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************

More information

UNDERGROUND SERVICES SECONDARY

UNDERGROUND SERVICES SECONDARY Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-

More information

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu INSTALLATION INSTRUCTIONS Note: The following installation instructions are based off of ASTM E 1643 (Standard Practice for Installation of Water Vapor Retarders Used in Contact with Earth or Granular

More information

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil United Nations Development Programme Programme of Assistance to the Palestinian People-PAPP Construction and Rehabilitation of wadi Gaza Bridges PAL10-00054031 Funded by Government of Brazil BILL OF QUANTITIES

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information

LANDSCAPE RETAINING WALLS

LANDSCAPE RETAINING WALLS SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls

More information

NSP/002 Policy for the Installation of Distribution Power Cables

NSP/002 Policy for the Installation of Distribution Power Cables Version:- 3.1 Date of Issue:- November 2016 Page 1 of 27 NSP/002 Policy for the Installation of Distribution Power Cables 1. Purpose The purpose of this document is to detail Northern Powergrid s (the

More information

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR PART 1 - GENERAL Section 26 05 15 SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR 1.1 Cable shall be 15 kv, shielded, three conductor with ground, stranded copper, with continuously welded and corrugated

More information

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the

More information

Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11

Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11 Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11 Underground Residential Distribution (URD) Index General Discussion... 1-2 Description... 3-7 Drawings (Available

More information

Collection of standards in electronic format (PDF) 1. Copyright

Collection of standards in electronic format (PDF) 1. Copyright Collection of standards in electronic format (PDF) 1. Copyright This standard is available to staff members of companies that have subscribed to the complete collection of SANS standards in accordance

More information

NUCLEAR POWER CORPORATION OF INDIA LTD. (A GOVT. OF INDIA ENTERPRISE) SPECIFICATION NO.PB-E-542/REV. No.0

NUCLEAR POWER CORPORATION OF INDIA LTD. (A GOVT. OF INDIA ENTERPRISE) SPECIFICATION NO.PB-E-542/REV. No.0 REVISION NO. 0 NUCLEAR POWER CORPORATION OF INDIA LTD. (A GOVT. OF INDIA ENTERPRISE) SPECIFICATION NO.PB-E-542/REV. No.0 PAGE NO. 1 OF 24 DATE OF ISSUE (MONTH/YEAR) TOTAL NO. OF PAGES (Including cover

More information

GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Division Office,Jamla, 220 kv Sub-Station Compound

GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Division Office,Jamla, 220 kv Sub-Station Compound GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Division Office,Jamla, 220 kv Sub-Station Compound Website : www.gseb.com Phone No. 02764 280551 E-mail : eetrjamla.getco@gebmail.com TENDER NO : JTD 14 Technical

More information

UNDERGROUND DROP CABLE CONDUIT INSTALLATION AND SPECIFICATION GUIDELINES FOR SINGLE DWELLING RESIDENTIAL APPLICATIONS

UNDERGROUND DROP CABLE CONDUIT INSTALLATION AND SPECIFICATION GUIDELINES FOR SINGLE DWELLING RESIDENTIAL APPLICATIONS UNDERGROUND DROP CABLE CONDUIT INSTALLATION AND SPECIFICATION GUIDELINES FOR SINGLE DWELLING RESIDENTIAL APPLICATIONS 1. SPECIFICATIONS This document details the specifications for the installation of

More information

Effective June, Eaton-Durham Model # UTRS223ACH. Siemens, Model # SUAS877-PG. (or Landis & Gyr # UAS877-PG) Milbank. Model # U1980-O.

Effective June, Eaton-Durham Model # UTRS223ACH. Siemens, Model # SUAS877-PG. (or Landis & Gyr # UAS877-PG) Milbank. Model # U1980-O. Siemens, Model # SUAS877-PG (or Landis & Gyr # UAS877-PG) Eaton-Durham Model # UTRS223ACH Milbank Midwest Model # U980-O UTRS223AMEP These are some examples of the single meter sockets we require for underground

More information

ComEd Customer Requirements for An Underground Service

ComEd Customer Requirements for An Underground Service 1 st Edition /\n 1:xclon Company ComEd Customer Requirements for An Underground Service Thank you for your recent interest in new or revised underground electrical service. If you proceed with this project,

More information

YOUR GROUND DRILLING PARTNERS.

YOUR GROUND DRILLING PARTNERS. YOUR GROUND DRILLING PARTNERS INDEX 2. ABOUT US 3. OUR SERVICES 4. OUR LOCATION 5. HORIZONTAL DRILLING 6. DIRECTIONAL BORING PROCESS 9. HDD DRILLING METHOD 12. MACHINE DETAILS 13. POLYETHYLENE PIPE CONDUIT

More information

2.1 Backfill - General

2.1 Backfill - General 2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ. Original Issue Bamyan MAC Site Services - Phase 1 Bamyan, Bamyan, Afghanistan

UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ. Original Issue Bamyan MAC Site Services - Phase 1 Bamyan, Bamyan, Afghanistan UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ Original Issue Bamyan MAC Site Services Phase Bamyan, Bamyan, Afghanistan Project Components:. Site Services Phase NOTICE TO ALL BIDDERS COMPLETE

More information

INTER-BUILDING CONDUIT & MANHOLE SYSTEM. Table of Contents PART 1 GENERAL 1 A. RELATED DOCUMENTS 1 B. SCOPE OF WORK 1 PART 2 PRODUCTS 6

INTER-BUILDING CONDUIT & MANHOLE SYSTEM. Table of Contents PART 1 GENERAL 1 A. RELATED DOCUMENTS 1 B. SCOPE OF WORK 1 PART 2 PRODUCTS 6 UNIVERSITY CONTACT: Network Services (302) 831-3722 INTER-BUILDING CONDUIT & MANHOLE SYSTEM Table of Contents PART 1 GENERAL 1 A. RELATED DOCUMENTS 1 B. SCOPE OF WORK 1 PART 2 PRODUCTS 6 A. MATERIALS AND

More information

Electric Service Standards

Electric Service Standards V: 1 of 6 A. Padmounted Requirements Complete requirements are contained in FPL specifications given to Customers for individual projects. Typical pad mounted transformer requirements include, but are

More information

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ADVANCE WORLD LIMITED Lalkha Shair Char, Fatullah, Narayanganj, Dhaka, Bangladesh Factory List: 1.. Inspected by: Sherub Tenzin & Md. Moin Hasan Report Generated by:

More information

RAILTEL CORPORATION OF INDIA LTD (A Govt. of India Undertaking)

RAILTEL CORPORATION OF INDIA LTD (A Govt. of India Undertaking) RailTel /Tender/OT/WR/HQ/2007-08/100 RAILTEL CORPORATION OF INDIA LTD (A Govt. of India Undertaking) TENDER DOCUMENT FOR Supply trenching and laying of 6 Quad cable & OFC along with associated accessories.

More information

ITEM 458 WATERPROOFING FOR STRUCTURES

ITEM 458 WATERPROOFING FOR STRUCTURES ITEM 458 WATERPROOFING FOR STRUCTURES 458.1. Description. This Item shall govern for the furnishing and placing of waterproofing on concrete and steel bridge decks of railroad structures and on other structures

More information

Underground Service Requirements and Instructions

Underground Service Requirements and Instructions This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page

More information

HINDUSTAN PETROLEUM CORPORATION LIMITED ADDL. TANKAGE PROJECT- MUNDRA TERMINAL

HINDUSTAN PETROLEUM CORPORATION LIMITED ADDL. TANKAGE PROJECT- MUNDRA TERMINAL NOTICE FOR INVITATION OF BIDS (DOMESTIC) FOR AUTOMATION TENDER FOR MUNDRA ADDL. TANAKGE PROJECT MUNDRA TERMINAL 1.0 BRIEF SCOPE OF SUPPLY Hindustan Petroleum Corporation Limited (HPCL) intends to augment

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

16. Design of Pipeline Structures.

16. Design of Pipeline Structures. 16. Design of Pipeline Structures. a. General. 1) The following guidelines are for the design of structures for water and sewer pipelines including structural concrete and miscellaneous metals design.

More information

1. Approved Manufacturers: Carlon Electrical Products, Cantex, or approved equal.

1. Approved Manufacturers: Carlon Electrical Products, Cantex, or approved equal. PART 1: GENERAL 1.01 Scope of Standard A. This standard provides general guidance concerning the specific preferences of Texas State University for for Electrical System. B. Texas State University recognizes

More information

Cement Stabilized Soil (CSS) (Portland cement)

Cement Stabilized Soil (CSS) (Portland cement) Cement Stabilized Soil (CSS) (Portland cement) 1.0 DESCRIPTION. This specification shall govern the process known as Cement Stabilized Soil (CSS). CSS consists of mixing the existing base, subbase and

More information

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS December 2012 CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions Specifications...

More information

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703) Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA 20155 Phone (703) 754-6750 Work Request # UNDERGROUND DISTRIBUTION FACILITIES AGREEMENT (FOR COMMERCIAL CUSTOMER) Developer/Builder/Owner

More information

CHAPTER 5 METERING REQUIREMENTS

CHAPTER 5 METERING REQUIREMENTS CHAPTER 5 METERING REQUIREMENTS CHAPTER 5 METERING REQUIREMENTS 5.1 General 1. All installations connected to, or intended to be connected to HK Electric s supply of electricity must comply with HK Electric

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (4th)

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (4th) Factory Name Address Joyna Bazer Road, Jamirdia, Valuka Factory ID 9504 Electrical Safety dates Initial Date 06/07/2014 Date of 5 th Follow Up Report Received Date 07/27/2015 Date of 6 th Follow Up Date

More information

Technical Specifications of 8 M and 9 M PCC Poles (F.O.S.-2.5) with working load 200 Kg.

Technical Specifications of 8 M and 9 M PCC Poles (F.O.S.-2.5) with working load 200 Kg. DAKSHIN HARYANA BIJLI VITRAN NIGAM LIMITED Specification No. S-95/DD-177 Technical Specifications of 8 M and 9 M PCC Poles (F.O.S.-2.5) with working load 200 Kg. Chief Engineer/P&D, DHBVN, Hisar. Issue

More information

Amendment to OPSS 493 (Nov 2015) Construction Specification for Temporary Potable Water Supply Services

Amendment to OPSS 493 (Nov 2015) Construction Specification for Temporary Potable Water Supply Services Engineering & Construction Services Division Standard Specifications for Sewers and Watermains TS 493 September 2017 Amendment to OPSS 493 (Nov 2015) Construction Specification for Temporary Potable Water

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

MACHINE-LAY Installation Manual

MACHINE-LAY Installation Manual MACHINE-LAY Installation Manual PaveDrain Installation Manual Table of Contents Section 1: Base Preparation (pages 3 6) Section 2: Machine-Lay PaveDrain Blocks (pages 8 11) Section 3: Edge Restraints (pages

More information

BUILDER S CONSTRUCTION SUPPLIES (Temporary in permanent position) REQUIREMENTS. March 2014

BUILDER S CONSTRUCTION SUPPLIES (Temporary in permanent position) REQUIREMENTS. March 2014 BUILDER S CONSTRUCTION SUPPLIES (Temporary in permanent position) REQUIREMENTS March 2014 Energy Safe Victoria (ESV) continues to receive complaints concerning defective builder s construction supplies.

More information