BIDDING FOR A FIBER PROJECT
|
|
- Ambrose Floyd
- 6 years ago
- Views:
Transcription
1 IMTFIBER NIGERIA BIDDING FOR A FIBER PROJECT PROJECT DOCUMENTATION TIPS 1/1/2016 ADEJOLA JOHNSON Msc. CEO Imt computers Nig. Ltd FOA Representative in Nigeria #718 info@imtfiber.com Page 0
2 BIDDING FOR FIBER PROJECT Telecom infrastructure development business such as fiber optics implementation and maintenance projects involve serious contest and bidding because of what is involved in it. Fiber project Bidding starts with document and documentation, some of which are discussed bellow 1. RFP.. 'Request for Proposal A type of bidding solicitation in which a company or organization announces that funding is available for a particular project or program, and companies can place bids for the project's completion. The Request for Proposal (RFP) outlines the bidding process and contract terms, and provides guidance on how the bid should be formatted and presented. A RFP is typically open to a wide range of bidders, creating open competition between companies looking for work It presents preliminary requirements for the commodity or service, and may dictate to varying degrees the exact structure and format of the supplier's response. Effective RFPs typically reflect the strategy and short/long-term business objectives, providing detailed insight upon which suppliers will be able to offer a matching perspective. info@imtfiber.com Page 1
3 The prospective contractor respond to this document and proceed to collect the SOW (scope of work) document 2. SOW A statement of work (SOW) is a formal document that captures and defines the work activities, deliverables, and timeline a vendor must execute in performance of specified work for a client. The SOW usually includes detailed requirements and pricing, with standard regulatory and governance terms and conditions. It thus overlaps in concept with a contract, and indeed SOWs are often legally equivalent to contracts. In Fiber OSP/ELP projects, there are some key areas to understand if the project contractor should deliver the mindset of the client Areas addressed in SOW Project topic Document (SOW) number Executive summary: This reveals the company, the project and the objective of the project, the project name, the total distance of the project Technical specification: This explains the technical aspect of the project. Which include information about the Site Specification such as the number of sites to connect, the sites name, sites code, longitude and latitude of each affected sites Ducting and Fiber Specifications: This aspect contains what the client wants about the depth of the trench, the laying of the ducts and sub-ducts, info@imtfiber.com Page 2
4 the fiber core number and enclosure configuration, This largely depends on whether the project the Backbone or Metro fiber RoW Strategy: Right of way strategy specifies how the permission from the relevant authority should be taken. Infrastructure Acceptance Process, inspection of all equipment elements and performance of the network checking of the link, the various test to be conducted, certificate of acceptance (CFA) which will qualify the contractor to submit an invoice for payment. Project management/ Project plan: project Organization ( this describes a company profile with a personnel resources, detailed project plan, an organization chart for the project with the name and function of the key persons participating in the project organization and their experience in the fielding, progress Reports, and As-Built Documentation Conclusion 3. RFQ. Request For Quote A Request For Quote is a variation of a Request For Proposal (RFP), and typically provides more information to the bidder about the project's requirements. It often requires the bidder to break down costs for each phase of the project so as to allow the soliciting company to compare different bids The following document is an example of RFQ Template info@imtfiber.com Page 3
5 Item RFQ reference number Trading name Company registration number Company's physical address Date Company telephone and fax numbers Contact name and telephone number Description of goods and/or services Unit of measure Price per unit Quantity of goods and/or services Delivery basis Other charges Currency Exchange rate used for conversion into country currency Total Discounts VAT amount for VAT) Vat number Payment terms Delivery period/schedule Validity Other Information 50% at Mobilization, 50% at PAT/FAC X days X days Validity If any info@imtfiber.com Page 4
6 No. Description Unit Qty Unit Price Total Price 4. BOQ.Bill Of Quantity As the name implies this document is an important document that requires much details about the surveyed route. This document will spell out various activities that will be carried out during the project implementation as well as the cost implication or respective column. Ducting Infrastructure-Section 1 Detailed Survey Documentation Cutting and Restoration of Concrete road Excavation of soil and Backfilling o Trench sample S1/R1 o Trench sample S2/R2 o Trench sample S3/R3 Excavation of soil and Backfill including restoration of Lawns and flowers Cutting and Restoration of Asphalt road Bridge crossing route Supply and Installation 110mm PVC Duct Supply and Installation 110mm Steel Duct Supply and Laying/Pulling of 40mm HDPE Sub-Duct info@imtfiber.com Page 5
7 Manhole -Street Type Calibration of existing / new duct Thrust boring of 110mm steel duct Removal and Restoration of paving stones Warning Tape Ducting Infrastructure-Section 2 Detailed Survey Documentation Supply and Laying/Pulling of 40mm HDPE Sub-Duct Calibration of existing / new duct Drilling of Existing Walls & Manhole and Reinstatement (For Joint existing Manhole) Ducting Infrastructure-Section 3 Carried to Summary Detailed Survey Documentation Cutting and Restoration of Concrete road Excavation of soil and Backfill Trench sample S1/R1 Trench sample S2/R2 Trench sample S3/R3 Cutting and Restoration of Asphalt road Supply and Installation 2110mm PVC Duct Supply and Installation 110mm Steel Duct Supply and Laying/Pulling of 40mm HDPE Sub-Duct Manhole -Street Type Calibration of existing / new duct info@imtfiber.com Page 6
8 Thrust boring 110mm steel duct Drilling of Existing Walls & Manhole and Reinstatement(For Joint existing Manhole) Removal and Restoration of paving stones Warning Tape Fibre Optic Cable Supply, Installation and Testing Fibre Optic Cable (ITU-T standards ODF Cabinet Pigtails (of specified length) 96 Port FOC Patch Panel Installation of 96 core OFC Fibre Patch Cords(Duplex)-ITU-T G.652/SC-LC connectors(6m-10m Fibre Patch Cords(Duplex)-ITU-T G.652/SC-SC connectors(6m-10m Fibre Patch Cords Duplex)-ITU-T G.652/SC-FC connectors(6m-10m Closure (96 core) (to include Optical splice point) Splicing of 96 core OFC Termination of 96 core OFC Testing Project Management, As-Built Documentation As-Built Documentation Ducting Civil works Project Management Summary Page 7
9 Maintenance One year maintenance (excludes Manhole or Hand hole, thrust boring, major works and concrete ) 5. PROJECT ORGANISATION CHART Top Management Project Manager (OFC) Civil Site Managers Civil Site Managers OFC Site Manager Head Logistic /Warehousing Trench Supervisors Trench Supervisors OFC Technicians Logistic Officers Trench/Asphalt and concrete Cutting Workmen Trench/Asphalt and concrete Cutting Workmen info@imtfiber.com Page 8
10 6. PROPOSED IMPLEMENTATION PLAN This is a document that states the tasks to be performed, the duration of each task, the start and finish date of each task. This document is very important to the client for monitoring. Microsoft project software is mostly used to prepare this schedule. The work flow is graphical displayed using GANNT Chart ID TASK NAME DURATION START FINISH PRE- FIBRE OPTIC CABLE INSTALLATION PO & ITP received Project/Implementation plan approval Fiber Optic cable drum testing Mobilization of Personnel, Materials and Equipment to site SECTION 1 Excavation of Trench path(200/day) Asphalt cutting Concrete Cutting 1 day 1 day 1 day 3 days 38 days 38 days 20 days 18 days info@imtfiber.com Page 9
11 Excavation of Manhole pits Planting of JBs Crossing of bridge Thrust boring of Asphalt road crossing Laying of PVC ducts Installation of HDPE duct Backfilling/Laying of warning tape Compaction of Normal soil Reinstatement of concrete and Asphalt routes Casting of Reinforced concrete envelope ROW Clearing Civil work acceptance FIBRE OPTIC CABLE INSTALLATION, TESTING AND DOCUMENTATION As-Built Documentation OFC blowing OFC jointing and Splicing OFC termination at BTS Testing of OFC 20 days 18 days 2 days 10 days 27 days 23 days 27 days 17 days 20 days 5 days 22 days 1 day 37 days 20 days 19 days 3 days 3 days 3 days info@imtfiber.com Page 10
12 Final Acceptance Test 2 days NOTE: the task and duration in the table above is just an example of template 7. METHOD STATEMENT DOCUMENT This a project document that states the methodology of project implementation. This document reveals Team composition, Mobilization to site, Civil works (trenching), Cable installation, splicing and testing, Maintenance Services and Equipment Schedule for Fiber Installation and Maintenance. How each will be achieved are given below. A. Team composition. A good implementation team will include the following personalities 1. Team leader 2. Splicing Technician 3. Civil work Technician 4. OTDR Technician 5. Pick-up truck Driver 6. Splice van Driver 7. Casual Labour B. Mobilization to site The materials, equipment and personnel needed for the execution of the project in the various cities shall be transported to the locations. This will take a period of 1-3 days depending on the location info@imtfiber.com Page 11
13 C. Civil works (trenching) Here the contractor needs to explain how the civil work of the project will be carried out in succession. The depth of the trench, Duct installation, manhole specification as stated by the client. D. Cable installation, splicing and testing Fiber Cable Installation method (Hand pulling, blowing..) Splicing: splicing techniques (fusion splicing, mechanical splicing or Ribbon splicing) and testing of the installed cable E. Maintenance Services It is expected of the contractor to indicate the maintenance approach to be adopted and the reason for the chosen one 1. Preventive Maintenance 2. Corrective Maintenance 3. Pre-scheduled Corrective Maintenance F. Equipment Schedule for Fiber Installation and Maintenance Apart from revealing the team composition (personnel) it is also expected of the contractor equipment availability and readiness. Some of the basic implementation equipment are stated below Pre-cast manhole manufacturing and curing facility Page 12
14 Nos of Delivery vans 1 No Self loader Truck (Hiab Available Fibre Test Equipment Available Splicing equipment 8. WORK FLOW WORK FLOW TEAM COMPOSITION MOBILISATION TO SITE CIVIL WORK (Trenching) Cable installation, Splicing, Testing Maintenance services Safety Equipment Schedule info@imtfiber.com Page 13
15 Page 14
FIBER OPTIC PROJECT IMPLEMENTATION
FIBER OPTIC PROJECT IMPLEMENTATION Fiber Project Management [Draw your reader in with an engaging abstract. It is typically a short summary of the document. When you re ready to add your content, just
More informationITEM NO SABS SECTION 1 : PRELIMINARY AND GENERAL 1200 A FIXED-CHARGE ITEMS Contractual Requirements Sum 1.0 -
1 SABS 1200 A SECTION 1 : PRELIMINARY AND GENERAL SECTION 1: PRELIMINARY & GENERAL PAYMENT DESCRIPTION UNIT QUANTITIES RATE AMOUNT 1.1 8.3 FIXEDCHARGE S 1.1.1 8.3.1 Contractual Requirements 8.3.2 Establish
More informationOUTSIDE PLANT. Specialized Civil Works Training
OUTSIDE PLANT Specialized Civil Works Training Date/s: Enquiries: danie@fibreonix.co.za/ joebotha@telkomsa.net Cost: R 8700.00 p.p. incl. VAT Duration: 5-days Time: 08h30 to 16h30 daily Registration: Please
More informationSPECIAL SPECIFICATION 6664 Level (3) Communications System
2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,
More informationSPECIAL SPECIFICATION 6658 Time Warner Communications System
2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable
More informationPROJECT: RELOCATION OF FEA ASSETS NEW VATUWAQA BRIDGE TRENCHING WORK SUVA SCHEME: C21/14
MR 309/ 2017 PROJECT: RELOCATION OF FEA ASSETS NEW VATUWAQA BRIDGE TRENCHING WORK SUVA SCHEME: C21/14 Notes : 1. Bidders to provide 2 hardcopies of tender bid. 2. Safety Plan to be incuded in tender bid,
More informationCourse name : Outside Plant - Fibre Optics Civil Works Professional Knowledge and Skills for Certification
Course name : Outside Plant - Fibre Optics Civil Works Professional Knowledge and Skills for Certification Course Detail: DURATION: 5 days TARGET GROUP: Any person who needs to do trenching, duct installation,
More informationFLORIDA ARMY NATIONAL GUARD, CBJTC CACTF FIBER OPTIC CABLE INSTALLATION, PN SCOPE OF WORK, 28 MARCH 2012
1. General. 1.1 The project will require the provisioning and installation of conduits, hand holes, pull boxes and fiber optic cable extending several miles from a point of beginning to the Combined Arms
More informationPROJECT: NEW 11kV FEEDER FROM RARAWAI 33/11kV SUBSTATION TO YALALEVU INDUSTRIAL AREA AS PER SCHEME NO. SR38/14
RE ADVERTISED TENDER MR 85/2015 PROJECT: NEW 11kV FEEDER FROM RARAWAI 33/11kV SUBSTATION TO YALALEVU INDUSTRIAL AREA AS PER SCHEME NO. SR38/14 Notes: 1. Bidders to provide 2 hardcopies of tender bid. 2.
More informationTERMS AND CONDITIONS FORM
TERMS AND CONDITIONS FORM IMPORTANT : READ ALL THE FOLLOWING TERMS AND CONDITIONS AND SIGN THE ACCEPTANCE CLAUSE FOLLOWING IT 1. The offers through post or hand delivery should be addressed to The Head,
More informationLevel 3 Principles of planning telecommunications services (7266/ / )
Level 3 Principles of planning telecommunications services (7266/7267-509/7540-365) e-quals Assignment guide for Candidates Assignment A www.cityandguilds.com/e-quals07 August 2009 Version 1.1 About City
More informationSPECIAL SPECIFICATION 6666 Charter Communications System
2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,
More informationCOMMUNICATIONS NETWORK UPGRADES AT VARIOUS LOCATIONS CITY OF SIOUX FALLS, SOUTH DAKOTA Bid Request No ADDENDUM NO.
COMMUNICATIONS NETWORK UPGRADES AT VARIOUS LOCATIONS CITY OF SIOUX FALLS, SOUTH DAKOTA Bid Request No. 15-1079 2015 CONTRACTOR S BID DATE: PLACE FOR CONTRACTOR S TO SUBMIT BIDS: Thursday, June 25th, 2015,
More informationTS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE
TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION
More informationBIDDING DOCUMENT. TENDER No. MR 79/2017 PREFERRED CONTRACTOR - TRENCHING WORKS FOR UNDERGROUND CABLES IN THE CENTRAL DIVISION
BIDDING DOCUMENT TENDER No. MR 79/2017 PREFERRED CONTRACTOR - TRENCHING WORKS FOR UNDERGROUND CABLES IN THE CENTRAL DIVISION Note: 1. Bidders to provide 2 hardcopies of tender bid. 2. Safety Plan for trenching
More informationPROJECT: NASRUP SECTION 1B UNDERGROUND RELOCATION STAGE 4 FROM CH SCHEME: C (FROM WAQADRA SUB TO NATALY JUNCTION)
TENDER MR 05/2016.. PROJECT: NASRUP SECTION 1B UNDERGROUND RELOCATION STAGE 4 FROM CH 2900-2300 SCHEME: C 31-14 (FROM WAQADRA SUB TO NATALY JUNCTION) Notes: 1. Bidders to provide 2 hardcopies of tender
More informationPROJECT: SUPPLY TO BERRY ROAD APARTMENT - SUVA SCHEME: G43-13
TENDER NO MR 91/2017 PROJECT: SUPPLY TO BERRY ROAD APARTMENT - SUVA SCHEME: G43-13 Notes : 1. Bidders to provide 2 hardcopies of tender bid. 2. Safety Plan to be incuded in tender bid, and will be part
More informationRequest for Proposal # Cane Creek Park Fiber Optic Cable Upfit
Request for Proposal # 2018-049 Cane Creek Park Fiber Optic Cable Upfit ADDENDUM NO. 1 ISSUE DATE: February 2, 2018 Bidders on this project are hereby notified that this Addendum shall be attached to and
More informationTENDER DOCUMENT MR 52/2015. Installation of 33kV Underground Power Cables
TENDER DOCUMENT MR 52/2015 Installation of 33kV Underground Power Cables Vatuwaqa Substation Kinoya Substation Vatuwaqa Substation Cunningham Substation Cunningham Substation Kinoya Substation TRENCHING,
More informationPROJECT: INCREASE DEMAND FOR UNIVERSITY OF FIJI- KULA STREET SAMABULA SCHEME: G115-15
TENDER NO MR 151/2016 PROJECT: INCREASE DEMAND FOR UNIVERSITY OF FIJI- KULA STREET SAMABULA SCHEME: G115-15 Notes : 1. Bidders to provide 2 hardcopies of tender bid. 2. Safety Plan to be incuded in tender
More informationOUTSIDE PLANT. Specialized Construction of Aggregation Node Training
OUTSIDE PLANT Specialized Construction of Aggregation Node Training Date/s: TBC Cost: R 6000.00 p.p. incl. VAT Duration: 3-days Time: 08h30 to 16h30 daily Registration: Please complete and email Registration
More informationSECTION MEASUREMENT AND PAYMENT
SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following
More informationOfficial-Mail.Tenders@iaea.org ATTACHMENT 1 TO RFQ NO. 29868-AS - Cooling Water Heat Exchangers for Uzbekistan SPECIAL INSTRUCTIONS TO BIDDERS FOR PREPARATION OF THE PROPOSAL These Special Instructions
More informationTECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE
GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GETCO/E/TS LUC058/R1
More informationMaterial will comply with those standards as established by UL or NEMA and shall be commercial grade. All materials will be new and free from defects.
APPENDIX A: OSP INSTALLATION SPECIFICATIONS Material Requirements Material will comply with those standards as established by UL or NEMA and shall be commercial grade. All materials will be new and free
More informationPrequalification of Electrical Contractors
Prequalification of Electrical Contractors \\ 2018 Application Instructions & Forms Prequalified Electrical Contractors Application Checklist To apply for prequalification of utility type work for Tacoma
More informationCITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST
CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST Abbreviations AB 1-3 Section 11 Purpose and Definitions 11-1 Purpose PD 1 11-2 Construction Practice PD 1 11-3 Definitions PD 1 Section 12 Construction Area
More informationUNM IT/Telecommunications Guide Specification Communications Underground Ducts, Raceways and Structures /27/06
Communications Underground Ducts, Structures and Raceways PART 1: GENERAL The Contractor is held responsible to be familiar with the provisions contained herein and with other Sections of this Specification
More informationEmployment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2
Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2 PARTICULAR SPECIFICATIONS FOR THE CONSTRUCITON OF STORM WATER DRAINAGE NETWORK March 2018 BUREAU TECHNIQUE POUR LE DEVELOPPEMENT P.O.B
More informationITEMIZED TENDER DOCUMENTS FOR
IN THE NAME OF ALLAH THE MOST BENEFICIENT AND MOST MERCIFUL PAKISTAN TELECOMMUNICATION COMPANY LIMITED ITEMIZED TENDER DOCUMENTS FOR LAYING OF 8/12/18/24/48/72/96 FIBER, OPTICAL FIBER CABLE FROM THE NEAREST
More informationOff Campus Fiber Build Rev. 2 RFP # Scope of Work
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 Scope of Work I. Scope of Solicitation II. Instructions to Offerors III. Scope of Work
More informationJob Order Sewer Repair Services
Job Order Sewer Repair Services Bid Addendum No. 1 October 10, 2018 All Contractual Requirements as defined within the Contract Documents shall remain in full force to the extent that they are not modified
More informationADDENDUM NO. 1 LAWRENCE MERRIMACK STREET UTILITY IMPROVEMENTS PROJECT RESPONSE TO CONTRACTOR QUESTIONS:
City of Lawrence Office of Planning & Development Merrimack Street Utility Improvements Project IFB ADDENDUM NO. 1 September 15, 2017 To Prospective Bidders and Others on: LAWRENCE MERRIMACK STREET UTILITY
More informationPREQUALIFICATION APPLICATION INSTRUCTIONS
PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.
More information301 Walnut Street Windsor, Colorado phone fax
301 Walnut Street Windsor, Colorado 80550 phone 970-674-2400 fax 970-674-2456 www.windsorgov.com Table of Contents... 2 SECTION 1 Questions & Requests for Clarification... 3 1.1 Question Deadline... 3
More informationSustainable Utility Construction: Methods and Techniques
Sustainable Utility Construction: Methods and Techniques September 19, 2011 APWA Congress Denver, Colorado Murv Morehead ROW Coordinator Overland Park, Kansas Monty Zimmerman Row Manager Lenexa, Kansas
More informationSECTION 503 TEMPORARY PAVEMENT RESTORATION
SECTION 503 TEMPORARY PAVEMENT RESTORATION 503-1 DESCRIPTION: This work consists of furnishing, placing, compacting, and maintaining a temporary pavement surface suitable for driving in accordance with
More informationBID #KP10011 SERVICES TO INSTALL UNDERGROUND CONDUIT TERM CONTRACT
BID #KP10011 SERVICES TO INSTALL UNDERGROUND CONDUIT TERM CONTRACT 1. Purpose: The purpose of this solicitation is to enter into a contract with one or more qualified Contractor(s) to provide and install
More informationAddendum No. 2. Pre-Bid Meeting Notes and Scope of Work Clarifications
Addendum No. 2 Project No. 2016-01EL West Barbour Street 12kV Underground Reconductoring Revisions to Drawings and Specifications Pre-Bid Meeting Notes and Scope of Work Clarifications Replace Section
More informationDocument No Issue Date: May 15, 2012
Professional Engineer Authenticated TELUS Residential Service Conduit Requirements For Stand-Alone Homes and Duplexes in Fibre Only Communities Beginning in January 2010 TELUS began designing new subdivisions
More informationREVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule
1. Mobilization, Insurance, Bonds, General Requirements, BMPs, Record Drawings, Testing Requirements, Utility Location, Demobilization and Site Maintenance. 1 L.S. 2. Supply and install complete 384,238
More informationPART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER
PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER COMMUNICATIONS LIGHTING Street Lighting Plan 710 Riser... 287 730 Collar for street light pole... 289 731 Pull box... 291 732 Trench for street light
More informationFORM OF TENDER RITHET RESERVOIR DRAIN PROJECT ( TITLE OF CONTRACT ) T 34/16 ( OWNER S CONTRACT REFERENCE NO. )
PAGE 1 OF 6 FOR USE WHEN UNIT S FORM THE BASIS OF PAYMENT - TO BE USED ONLY WITH THE GENERAL CONDITIONS AND OTHER STANDARD DOCUMENTS OF THE UNIT MASTER MUNICIPAL CONSTRUCTION DOCUMENTS. Owner: Contract:
More informationREQUEST FOR QUOTATION (RFQ) Person responsible for any additional information and receipt of proposals:
REQUEST FOR QUOTATION (RFQ) For Supply of Laboratory equipment s at Kempegowda International Airport, Bengaluru Name and address of the entity seeking proposal: Bangalore International Airport Limited.
More informationE. CONSTRUCTION PROCEDURES
E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications
More informationNAME STREET ADDRESS CITY, STATE & ZIP CODE. GAS ELECTRIC TELEVISION TELECOMMUNICATION OTHER (check one) UNDERGROUND OVERHEAD BOTH (check one)
Des Plaines Utility Permit #: PUBLIC WORKS AND ENGINEERING 1420 Miner Street Des Plaines, IL 60016 P: 847.391.5390 F: 847.391.5619 desplaines.org CITY OF DES PLAINES UTILITY PERMIT APPLICATION All entities
More informationREQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)
SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /
More informationROAD CUT PERMIT APPLICATION & INSTRUCTIONS
Jeremy Robinson Commissioner Ann Fordock Martin E. Davis, L.S. DEPARTMENT OF PUBLIC WORKS Ben Walsh, Mayor ROAD CUT PERMIT APPLICATION & INSTRUCTIONS REQUIRED FOR: Construction in (cutting into) a city
More informationDesktop Computer Model 1 (without. DVD RW and Front USB) Desktop Computer Model 2 ( with DVD. RW and Front USB) Dot Matrix Printer with one printer
Line Item Description of Goods Quantity Physical unit Unit Price 1 2 3 4 5 6 7 8 9 1 11 12 Desktop Computer Model 1 (without 3839 DVD RW and Front USB) Desktop Computer Model 2 ( with DVD 36 RW and Front
More informationRequest for Proposal
Request for Proposal Mountainburg Public Schools Attention: Scott Organ 129 Hwy 71 SW Mountainburg, AR 72946 Phone: 479-369-2121 Email: erate@mountainburg.org E Rate Funding Year 2018-19 (Single-Mode Fiber
More informationSubject: Quotation for Erection of Pre fabricated Buildings in Turbat and Gawadar for UNODC Country Office Pakistan,
REQUEST FOR QUOTATION (RFQ) FACSIMILE/EMAIL Company/Individual Name: Business address: Telephone Fax Email Subject: Quotation for Erection of Pre fabricated Buildings in Turbat and Gawadar for UNODC Country
More informationPROJECT: SUPPLY TO STATE FORESHORE SUB- DIVISION, VIRIA, VATUWAQA PART A.2: UNDERGROUND LV CABLING WORKS STAGE 1 & 2 SCHEME: G74-15
TENDER NO MR 177/2017 PROJECT: SUPPLY TO STATE FORESHORE SUB- DIVISION, VIRIA, VATUWAQA PART A.2: UNDERGROUND LV CABLING WORKS STAGE 1 & 2 SCHEME: G74-15 Notes : 1. Bidders to provide 2 hardcopies of tender
More informationUNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ. Original Issue Bamyan MAC Site Services - Phase 1 Bamyan, Bamyan, Afghanistan
UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ Original Issue Bamyan MAC Site Services Phase Bamyan, Bamyan, Afghanistan Project Components:. Site Services Phase NOTICE TO ALL BIDDERS COMPLETE
More informationBill No.1: Preliminaries
Bill No.1: Preliminaries Item No. Description of Works Qty. 1 Mobilization 1.1 This item should include site office for the use of the Engineer's and Employer's staffs with the necessary facilities, furniture,
More informationREQUEST FOR QUOTATION (RFQ) Person responsible for any additional information and receipt of proposals:
REQUEST FOR QUOTATION (RFQ) For Supply of Honda Portable Generator at Kempegowda International Airport, Bengaluru Name and address of the entity seeking proposal: Bangalore International Airport Limited.
More informationProcurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202
Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 October 26, 2017 ADDENDUM NUMBER: ONE (1) TITLE: Arc-Resistant Metal-Clad Switchgear
More informationFor Addendum No. 6 Revised Bid Form Page 1 of 7. Revised Bid Form
For Addendum No. 6 Revised Bid Form Page 1 of 7 Revised Bid Form Deliver bid to: CITY OF FREDERICK PURCHASING DEPARTMENT 111 AIRPORT DRIVE EAST FREDERICK MARYLAND 21701 CITY OF FREDERICK WWTP ENR UPGRADE
More informationPRELIMINARY ROADWORKS COST ESTIMATE
PRELIMINARY ROADWORKS COST ESTIMATE Project Title : Glounthaune Village Improvement Scheme Client : O Mahony Developments Ltd Date : February 208 From O' Mahony Development Ltd Entrance to Glounthaune
More informationITEM 460 REINFORCED CONCRETE PIPE Description. This Item shall govern for the furnishing of reinforced concrete pipe.
AFTER MARCH 1, 2012 ITEM 460 REINFORCED CONCRETE PIPE 460.1 Description. This Item shall govern for the furnishing of reinforced concrete pipe. 460.2 Materials. A. Except as modified herein, materials,
More informationH. Underground Transmission System Design
H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,
More informationQUALIFICATIONS PACK - OCCUPATIONAL STANDARDS FOR TELECOM INDUSTRY. SECTOR: TELECOM SUB-SECTOR: Network Managed Services
QUALIFICATIONS PACK - OCCUPATIONAL STANDARDS FOR TELECOM INDUSTRY What are Occupational Standards(OS)? OS describe what individuals need to do, know and understand in order to carry out a particular job
More informationCITY OF DE SOTO Miller Park Trail Extension and Picnic Table Pads
CITY OF DE SOTO Miller Park Trail Extension and Picnic Table Pads City of De Soto Johnson County, Kansas PREPARED BY: City of De Soto, Kansas 32905 West 84 th Street De Soto, Kansas 66018 SPECIFICATIONS
More informationSECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.
SECTION 01220 UNIT PRICES PART 1 GENERAL 1.01 SUMMARY A. This Section specifies administrative and procedural requirements for the unit prices. B. The omission of any unit price description from this Section
More informationCHAPTER 11 CONDUITS AND FITTINGS
CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1
More informationREQUEST FOR QUOTATION (RFQ) Person responsible for any additional information and receipt of proposals:
REQUEST FOR QUOTATION (RFQ) For supply of Mobile Phone at Kempegowda International Airport, Bengaluru Name and address of the entity seeking proposal: Bangalore International Airport Limited. Administration
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)
San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation
More informationA. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.
ALLIANT ENERGY CENTER PAVILIONS Project No. 2013 027 SECTION 27 05 28 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationSPECIAL SPECIFICATION 5825 AT&T Telecommunication System
2004 Specifications CSJ: 0014-08-075, etc. SPECIAL SPECIFICATION 5825 AT&T Telecommunication System 1. Description. A. This Item will govern the installation of all facilities belonging to Southwestern
More informationPREQUALIFICATION APPLICATION INSTRUCTIONS
PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.
More informationAPPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES
Appendix A RFP No. 894-2014 Page 1 of 1 Template Version: SrC120131129 - Consulting Services RFP APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Revision: 2014-09-22 DEFINITION OF
More informationSpecial Specification 6357 Windstream Telecommunication System
Special Specification Windstream Telecommunication System 1. DESCRIPTION This Item will govern the installation of all facilities belonging to Windstream Communications, hereinafter referred to as Windstream.
More informationCONDUITS AND FITTINGS
CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit
More informationSection 2: Underground
Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,
More informationRFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES
RFP/GRC/LSV/2017-003: RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES 1/7 The Contractor shall consider in his price all costs or expenses of all requirements stipulated
More informationINDIAN INSTITUTE OF TECHNOLOGY MADRAS STORES AND PURCHASE SECTION
INDIAN INSTITUTE OF TECHNOLOGY MADRAS STORES AND PURCHASE SECTION No. S&P/SNC/RC/2017/SPL Dated 17.08.2017 CIRCULAR Sub: Rate contract for Structured Network Cabling [SNC]- Reg It is informed that the
More informationRSU 14 - WINDHAM RAYMOND SCHOOL DISTRICT OFFICE OF THE ASSISTANT SUPERINTENDENT
RSU 14 - WINDHAM RAYMOND SCHOOL DISTRICT OFFICE OF THE ASSISTANT SUPERINTENDENT 228 Windham Center Road, Windham, ME 04062 Telephone (207) 892-1800 FAX (207) 892-1805 INSTRUCTIONS, SPECIFICATIONS, AND
More informationEXHIBIT E SCHEDULE OF UNIT PRICES
SCHEDULE OF UNIT PRICES TO ACCOMPANY THE BID OF (Bidder/Contractor) ON CALL UTILITY SERVICES AND MISCELLANEOUS CONSTRUCTION FOR SEWER AND WATER LINES SOLICITATION NO.: IFB SA1703 Any bidder who enters
More informationSECTION G40 SITE ELECTRICAL UTILITIES 11/10
G40 GENERAL SECTION G40 SITE ELECTRICAL UTILITIES 11/10 RFP Part 3 including the Engineering System Requirements (ESR) provide project specific requirements. The RFP Part 4, Performance Technical Sections
More informationTelecommunications Infrastructure
Telecommunications Infrastructure Table of Contents Contents 1. INTRODUCTION... 2 2. DUCTING CAPACITY... 3 3. SUB DUCT SIZING... 4 4. DUCTING AND SUB DUCTING CONSTRUCTION AND COLOUR... 5 5. BUILDING ENTRANCE:...
More informationSECTION IV. PIPELINE EXCAVATION AND BACKFILL
SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include
More informationSection - 7. General Specifications
Section - 7 General Specifications Section 7.General Specifications Outside Plant (OSP) works 7.1. SCOPE OF WORKS Bangladesh Telecommunications Company Limited (BTCL) is going to provide optical fiber
More informationCommonwealth of Pennsylvania Invitation to Qualify For Electronic Waste Removal and Recycling Services PART I STATEMENT OF WORK
Commonwealth of Pennsylvania Invitation to Qualify For Electronic Waste Removal and Recycling Services PART I STATEMENT OF WORK 1. Purpose: The purpose of this Electronic Waste (E-waste) Removal and Recycling
More informationMulti-Gard PVC Assembly/ Field Cuts
Multi-Gard PVC Assembly/ Field Cuts Assembly 1. Distribute Multi-gard sections along the sides of the trench with male ends pointing towards starting vault entrance.. Remove protective cap and install
More informationRequest For Quotation (RFQ) for goods/services. Supply of Anaesthesia Equipment in Liberia RFQ No: (RFQ-LBR )
Request For Quotation (RFQ) for goods/services Supply of Anaesthesia Equipment in Liberia RFQ No: (RFQ-LBR-2015-095) RFQ-LBR-2015-095 Request For Quotation (RFQ) for Supply of Anaesthesia Equipment in
More informationRapid Axial Load Testing of Drilled Shafts
Supplemental Technical Specification for Rapid Axial Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 4, 2015 1.0 GENERAL This work shall consist of performing a rapid axial
More informationRequest for Electricity Connection Works at: xx Street Name, District, County, Postcode
The Customer, xx, Street Name District County Postcode WPD Reference: 29xxxxx WPD Scheme No: 11xxxxx/1 Herald Way Pegasus Business Park CASTLE DONINGTON DE74 2TU WPD Telephone No 01332 xxxxxx 15/12/2017
More informationBuilding Your Infrastructure. Company Profile. Building Your Infrastructure
Company Profile Introduction AKS East Africa Ltd is an engineering and construction business operated by a team of well trained, highly experienced and motivated staff in both technical and support departments.
More informationSpecial Provisions for Pavement Open Cuts
1. All patches are to be replaced in accordance with the following requirements and as shown in Figure 1. 2. All Excavations or Open Cuts shall comply with OSHA Technical Manual, Chapter 2, Title Excavation:
More informationSection - 7. General Specifications
Section - 7 General Specifications Section 7. General Specifications Outside Plant (OSP) works 7.1. SCOPE OF WORKS Bangladesh Telecommunications Company Limited (BTCL) is going to provide optical fiber
More informationA Study on Cost-Benefit Analysis of Fibre-Optic Co-Deployment with the Asian Highway Connectivity
A Study on Cost-Benefit Analysis of Fibre-Optic Co-Deployment with the Asian Highway Connectivity Asia-Pacific Information Superhighway (AP-IS) Working Paper Series The Economic and Social Commission for
More informationSCOPE OF WORK FOR ELECTRICAL WORK
Sl.Pg.No.552 SCOPE OF WORK FOR ELECTRICAL WORK GENERAL 1.0 The scope of work in general consists of Construction of Fire Station in Sector 19A at Ulwe Node, Navi Mumbai. 2.0 The work includes:- a) Preparing
More informationThere will be a technical and financial evaluation. Technical evaluation will be 70% and 30% for financial.
ANNEX H (EVALUATION CRITERIA & FINANCIAL PROPOSAL TEMPLATE) There will be a technical and financial evaluation. Technical evaluation will be 70% and 30% for financial. Technical evaluation The returned
More informationRFB for Fiber Optic Cabling Attachment A Project Scope October 6, 2016
RFB for Fiber Optic Cabling Attachment A Project Scope October 6, 2016 1.0 Project Description 1.1 General 1.1.1 Drawings and general provisions of Contract, including General and Supplementary Conditions,
More informationNotification to Super Sea Cable Networks Pte Ltd (the SEAX ) for Earthwork Procedures
Notification to Super Sea Cable Networks Pte Ltd (the SEAX ) for Earthwork Procedures 1. Introduction With effect from 1 July 2000, The Info-Communications Media Development Authority (IMDA) has introduced
More informationDETAILED SCOPE OF WORK IN-STREAM TIDAL GENERATING PLANT TISEC COLLECTOR CIRCUITS DEVELOPMENT
PAGE I TABLE OF CONTENTS SECTION DESCRIPTION PAGE 1 GENERAL 1 1.1 OVERVIEW 1 1.2 PREPARATORY WORK CARRIED OUT BY OTHERS 2 1.3 MATERIALS TO BE SUPPLIED BY THE OWNER 2 1.4 PROJECT SCHEDULE 3 1.5 PROJECT
More informationADDENDUM NO. 1 NOVEMBER 8, 2016
SAN ANTONIO WATER SYSTEM C_13 BROADWAY CORRIDOR PROJECT SEWER REHABILIATION PACKAGE 2.C AND 4.C SAWS JOB NO. 15-45111 (2.C) & 15-4514 (4.C) SOLICITATION NO. CO-00097 ADDENDUM NO. 1 NOVEMBER 8, 2016 TO
More informationApplication for Permit for Installation of Utilities or Placing Underground Construction
Application for Permit for Installation of Utilities or Placing Underground Construction City of Hanover, MN / cityhall@ci.hanover.mn.us City of Hanover Permit No. Applicant is responsible for all locations
More informationPILING WORKS FOR PROPOSED NEW BUILDING OF IIT MADRAS RESEARCH PARK AT KANAGAM ROAD, TARAMANI, CHENNAI
PILING WORKS FOR PROPOSED NEW BUILDING OF IIT MADRAS RESEARCH PARK AT KANAGAM ROAD, TARAMANI, CHENNAI- 600 113 PRE MID MEETING DATE OF MEETING:- 07-5-2013 DECISIONS MADE IN THE MEETING Note : These decisions
More informationITEM NO. 824 SERVICE SUPPLY LINES (WATER)
ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines installation and adjustment installed in accordance with these specifications and as directed
More informationDepartment of Transportation Pierre Region Office 104 S. Garfield Bldg. A Pierre, South Dakota / FAX: 605/
Connecting South Dakota and the Nation Department of Transportation Pierre Region Office 104 S. Garfield Bldg. A Pierre, South Dakota 57501-5405 605/773-3464 FAX: 605/773-6215 May 6, 2011 RE: 0009-391
More information