Alternative Project Delivery for America s Water Infrastructure

Size: px
Start display at page:

Download "Alternative Project Delivery for America s Water Infrastructure"

Transcription

1 Alternative Project Delivery for America s Water Infrastructure Cal Rozario PMP Design-Build Chief Engineer HDR Water & Natural Resources Business Group

2 TOPICS Traditional Project Delivery Brief History of Project Delivery APD Methods in W/WW Ohio State Statutes Ohio Currently Under Consideration Ohio DB Procurement Resources for Learning Discussion

3 TRADITIONAL PROJECT DELIVERY Contract & Communication Lines OWNER DESIGN PROFESSIONAL GENERAL CONTRACTOR CONTRACT COMMUNICATION TRADE SUBCONTRACTORS EQUIPMENT SUPPLIERS

4 PROJECT DELIVERY A Brief History Master Builder Concept 1400 Filippo Brunelleschi

5 Filippo Brunelleschi ( ) Master Builder architect, engineer, general contractor Designed and built the Dome of Santa Maria del Fiore in Florence, Italy The first octagonal dome to be built without a wooden supporting frame

6 PROJECT DELIVERY A Brief History Master Builder Concept 1400 Filippo Brunelleschi Segregated Services Model 1450 Leon Battista Alberti

7 Leon Battista Alberti ( ) Modern-day Architect Began the separation of the art of the design and the craft of the building Directed the construction of the façade on the Santa Maria Novella church in Florence, Italy With drawings and models, not directly supervising the work

8 PROJECT DELIVERY A Brief History Master Builder Concept 1400 Filippo Brunelleschi Segregated Services Model 1450 Early 1700 s Leon Battista Alberti Industrial Revolution added project complexity Specialization of Services

9 INDUSTRIAL REVOLUTION Further separation between design and construction Cities expanded, people moved from rural to urban housing More need for specialized design and construction expertise

10 SPECIALIZATION TIMELINE 1852 ASCE American Society of Civil Engineers 1857 AIA American Institute of Architects 1918 AGC Associated General Contractors 1948 CSI Construction Specifications Institute ABC Associated Builders & Contractors 1950 ASA American Subcontractors Association 1956 AIC American Institute of Constructors 1971 CMAA Construction Management Association of America 1982

11 PROJECT DELIVERY A Brief History Master Builder Concept 1400 Filippo Brunelleschi Segregated Services Model 1450 Early 1700 s Leon Battista Alberti Industrial Revolution added project complexity Miller Act Specialization of Services? E&C collaboration & communication

12 PROJECT DELIVERY A Brief History Why is July 17, 1981 significant for the E&C industry? Kansas City Hyatt Regency Walkway Collapse

13 PROJECT DELIVERY A Brief History Miller Act KC Hyatt DBIA Formed 1993 AD Methods Emerge The day after, open E&C communications ended Traditional delivery became contentious Owner becomes a mediator One positive result AD Methods emerge

14 ALTERNATIVE DELIVERY Market Trends Value, $Billions CMAR Revenues DB Revenues Future Projection SOURCE: ENR, June 2012

15 ALTERNATIVE DELIVERY Owners Satisfaction Survey LEVEL OF SATISFACTION Owner Involvement in Design Quality of Completed Project Overall Experience Communication Transition to Operation Risk Distribution SOURCE: Water-Design Build Council, 2012

16 ALTERNATIVE DELIVERY Owner Drivers Why are clients using AD? Achieve the benefits from team integration Essentially, the benefit of sharing experience and knowledge Delivering best value means focusing on key Design-Build interfaces: Design / Cost Design / Value Design / Construct Design / Performance

17 ALTERNATIVE DELIVERY Owner Drivers Desire for greater role in project execution Another project delivery tool Owner demographics are changing

18 ALTERNATIVE DELIVERY Owner Drivers Simply, Owners are seeking better and faster ways to deliver capital projects with less hassle

19 PREVALENT AD METHODS for America s Water Infrastructure Design/Construction Management At-Risk Design-Build and its variation Traditional (Lump Sum) Design-Build Progressive Design-Build Design-Build-Operate Design-Build-Finance-Operate Design-Build-Own-Operate-Transfer

20 RISK SPECTRUM vs. AD MODEL DBB D/CMAR DB DBO DBFO DBOOT Increasing Owner Shift or Sharing of Risk and Control

21 TRADITIONAL (LS) DESIGN-BUILD Contract & Communication Lines OWNER CONTROL RISK DESIGN-BUILDER CONTRACT COMMUNICATION TRADE SUBCONTRACTORS EQUIPMENT SUPPLIERS

22 TRADITIONAL DESIGN-BUILD Approach Select Owner s Rep. Define Project Concepts & Criteria Produce Contract Doc s & RFQ/RFP Prepare & Submit Proposal Review & Recommend Selection Accept Project Final Design, Construction & QC Select Design- Builder OWNER OWNER S REP DESIGN-BUILDER Review Submittals Conduct Field QA Pay Estimates RFIs

23 TRADITIONAL DESIGN-BUILD Best Applications/Disadvantages BEST APPLICATIONS DISADVANTAGES Well defined project scope Owner doesn t require direct project involvement Well defined operational requirements Conventional technology Owner has APD experience Added time & cost to develop procurement Design Criteria Owner involvement limited once price is established Change orders likely if Owner wants design changes after pricing Lump sum price may not reflect final project cost

24 PROGRESSIVE DESIGN-BUILD Contract & Communication Lines OWNER CONTROL RISK DESIGN-BUILDER CONTRACT COMMUNICATION TRADE SUBCONTRACTORS EQUIPMENT SUPPLIERS

25 PROGRESSIVE DESIGN-BUILD Approach Cost Estimating, Value Engineering, Constructability Reviews Set Target Price Check Budget Check Budget Select Design-Builder Design to 30% Design to 60% Finish Design Long Lead Items Early Start Items Accept Project Construction by Design-Builder Approve GMP Competitively Bid & Submit GMP OWNER OWNER & DB DESIGN-BUILDER

26 DBB vs. P-DB Design Sequence Comparison Set CIP Budget Select Designer Design to 30% Design to 60% DBB DESIGN Final Design Competitively Bid to Contracting Community Set Target Price Select Design- Builder Design to 30% Design to 60% Finish Design Competitively Bid & Submit GMP P-DB DESIGN

27 PROGRESSIVE DESIGN-BUILD Best Applications/Disadvantages BEST APPLICATIONS DISADVANTAGES QBS speeds project start Owner has technology & equipment preferences Owner desires high degree of involvement in delivery Complex scopes more easily accommodated Owner desires a single point of responsibility Off-ramps are available Firm price set later Owner uncertainty with GMP approach, negotiation New delivery method means educating stakeholders Construction QA/QC approach is different

28 OHIO STATE STATUTES Authorized to Use Design-Build Signed June 30, 2011; effective September 30, 2011 State Agencies State Institutions of Higher Education Counties Townships Municipal Corporations School Districts Other Political Subdivisions

29 OHIO Definitions What are Design-Build Services? Services that form an integrated delivery system for which a person is responsible to a public authority for both the design and construction, demolition, alteration, repair, or reconstruction of a public improvement. Who is a Construction Manager At Risk? A person with substantial discretion and authority to plan, coordinate, manage, direct, and construct all phases of a project for the construction, demolition, alteration, repair, or reconstruction of any public building, structure, or other improvement and who provides the public authority a guaranteed maximum price

30 OHIO Design-Build Services Steps for procurement 1. Pre-design Phase 2. Request for Qualifications published 3. Qualifications-Based Selection 4. Best Value Selection 5. Interview Phase/Short-listing 6. Technical Proposal (scope clarification meeting) 7. Contract Negotiations

31 OHIO Request for Qualifications Request for Qualifications includes: A general description of the project The project delivery method A statement of the specific professional design services or design-build services required A description of the qualifications required for the project, including the EDGE (Encouraging Diversity, Growth, and Equity business development program) participation goal Criteria by which submissions will be evaluated

32 OHIO Design-Build Services Request for Qualifications indicates: How qualified professional design firms or design-build firms may submit a statement of qualifications to be considered for a contract to perform the required services for the project Request for Qualifications identifies: A process for submitting written questions regarding the project

33 OHIO HOUSE BILLS Currently Under Consideration HB 35 (Introduced February 5, 2013 PASSED HOUSE) Makes appropriations for programs related to transportation and public safety for the biennium beginning July and ending June Provides authorization and conditions for the operation of those programs

34 OHIO HOUSE BILLS Recently Signed Into Law HB 51 (Introduced February 12, 2013 PASSED HOUSE & SENATE) Designates qualifications to be considered design-bill among other things

35 RESOURCES For Learning About W/WW DB Delivery Design Build Institute of America General information on Alternative Delivery Owner Resources Owner s Council Thought Leaders Industry research and reports Design-Build Manual of Practice Standard Form DB Contract Documents

36 RESOURCES For Learning About W/WW DB Delivery Water Design-Build Council The Municipal Water and Wastewater Design-Build Handbook, 2 nd Edition water-design-build-handbook

37 RESOURCES For Learning About W/WW DB Delivery Model Procurement Documents Procurement guide for Progressive Design-Build project delivery Single Step Procurements Model RFQ Model RFP Two Step Procurements Model RFQ (step one) Model RFP (step two)

38 IN CLOSING Is this correct? Design Professional + Builder = Integrated Design-Builder Design Professional + Builder + Design-Builder Mentality = Integrated Design-Builder

39 IN CLOSING Learn from your mistakes and build on your successes. John C. Calhoun Vice President, under Adams and Jackson

40 DISCUSSION

Integrated Project Delivery

Integrated Project Delivery 2014 HDR Architecture, 2014 HDR, Inc., all all rights reserved. Integrated Project Delivery It s A New World, And How It Can Benefit Municipal Owners Rich Atoulikian, PMP, PE Rich.Atoulikian@hdrinc.com

More information

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from

More information

Riverbend Water Reclamation Plant Expansion Using the CMAR Delivery Method

Riverbend Water Reclamation Plant Expansion Using the CMAR Delivery Method Riverbend Water Reclamation Plant Expansion Using the CMAR Delivery Method AGENDA North Texas History Why Owners Select D/CMAR Owner Benefits Riverbend WRP Expansion Construction Progress Filename.ppt/2

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be

CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be Thanks to our host CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be reported to RCEP at RCEP.net. A certificate

More information

Pioneering Alternative Project Delivery in Ohio

Pioneering Alternative Project Delivery in Ohio Pioneering Alternative Project Delivery in Ohio Ali Bahar, PE Principal Engineer Metropolitan Sewer District of Greater Cincinnati Tim Koch, PE, Vice President, Brown and Caldwell 1 Agenda Construction

More information

PROJECT DELIVERY METHODS

PROJECT DELIVERY METHODS Understanding the Construction Contract Project Delivery Methods ISBA April 7,2017 Copyright 2017 by K&L Gates LLP. All rights reserved. Design Bid Build Design Negotiate Build Construction Manager Advisor

More information

SCADA System Procurement Alternatives

SCADA System Procurement Alternatives SCADA System Procurement Alternatives 2017 Automation Committee Seminar August 24, 2017 Terry M. Draper, PE, PMP Discussion Topics SCADA Overview System Hardware / Software Procurement Additional System

More information

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It Jim Mallorey, P.E. Metro Wastewater Reclamation District Chris Harper - University of Colorado Boulder January 23, 2014 1

More information

LB 889 The Political Subdivisions Construction Alternatives Act

LB 889 The Political Subdivisions Construction Alternatives Act 1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.

More information

Procurement Documents for Progressive Design-Build Projects

Procurement Documents for Progressive Design-Build Projects Procurement Documents for Progressive Design-Build Projects March 22, 2013 John Awezec, P.E., DBIA HDR Engineering, Inc. John Doller, P.E. Carollo Engineers, Inc. Peter Hughes Executive Director WDBC Model

More information

Community Workshop October 17, 2015

Community Workshop October 17, 2015 Community Workshop October 17, 2015 Goals for Workshop Education for attendees How City builds projects now Why a different method is being pursued for WRF Other workshops (not today) Architecture Treatment

More information

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA PROGRESSIVE DESIGN-BUILD Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA ADVANTAGES/DISADVANTAGES DESIGN BID BUILD (HARD BID) The traditional project delivery method, which customarily

More information

Progressive Design-Build Discussion

Progressive Design-Build Discussion Presentation for: Progressive Discussion February 4, 2011 1 Project Delivery Options Design-Bid-Build Construction Management at Risk Lump Sum Progressive DESIGNER BUILDER DESIGNER CM TRADITIONAL DELIVERY

More information

Choosing a Project Delivery Method. A Design-Build Done Right Primer

Choosing a Project Delivery Method. A Design-Build Done Right Primer Choosing a Project Delivery Method A Design-Build Done Right Primer DESIGN-BUILD DONE RIGHT PRIMER 1 Choosing a Project Delivery Method A DESIGN-BUILD DONE RIGHT PRIMER A DESIGN-BUILD INSTITUTE OF AMERICA

More information

Is Your District Ready For the New Law?

Is Your District Ready For the New Law? Is Your District Ready For the New Law? Ben Pintabona Operations Manager Scaparotti Construction Group Craig Weise Construction Reform Program Director Ohio School Facilities Commission Sylvia Gillis,

More information

EVOLUTION OF DESIGN BUILD IN THE W/WW INDUSTRY

EVOLUTION OF DESIGN BUILD IN THE W/WW INDUSTRY EVOLUTION OF DESIGN BUILD IN THE W/WW INDUSTRY Thomas O. Crowley, P.E. Carollo Engineers Southwest Section AWWA October 17, 2017 Agenda Project Delivery Overview Oklahoma Legislation Project Delivery Methods

More information

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method Report on Effectiveness of the Construction Manager at Risk Project Delivery Method The project management plans described below, establish several elements or criteria for university project staff to

More information

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should

More information

Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division

Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division Project Delivery Methods Design-Bid-Build (DBB) Indefinite Delivery/Indefinite Quantity (ID/IQ) Construction Management at Risk

More information

FACILITY PROJECT BIDDING OPTIONS OVERVIEW

FACILITY PROJECT BIDDING OPTIONS OVERVIEW FACILITY PROJECT BIDDING OPTIONS OVERVIEW A Presentation to the Board of Education Galt Joint Union High School District February 14, 2017 January 10, 2017 GHSD Measure E Bidding Options Overview 2 Overview

More information

Alternative Project Delivery Methods and Procurement

Alternative Project Delivery Methods and Procurement Alternative Project Delivery Methods and Procurement Board of Airport Commissioners Meeting 2 June 2014 Presented by: Roger A. Johnson, Deputy Executive Director Definitions Project Delivery Method o The

More information

REQUEST FOR QUALIFICATIONS AND PROPOSALS

REQUEST FOR QUALIFICATIONS AND PROPOSALS REQUEST FOR QUALIFICATIONS AND PROPOSALS CONSTRUCTION MANAGER AT RISK SERVICES Preconstruction Phase Services and Construction Phase Services Sheridan Economic and Educational Development Authority Sheridan

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN Introduction Becker County is issuing a RFQ for Construction Management at Risk Services

More information

AVIATION AUTHORITY POLICY

AVIATION AUTHORITY POLICY PURPOSE: To establish a policy for the selection of development related professional services firms, including design-build firms for professional services and the Consulting Engineer, pursuant to the

More information

Trinity Well Field and Production Facilities Project Management Using CMAR

Trinity Well Field and Production Facilities Project Management Using CMAR Trinity Well Field and Production Facilities Project Management Using CMAR Ian Taylor, P.E., PMP New Braunfels Utilities David Bennett, P.E. Freese and Nichols Kirby Anderson MGC Contractors February 27,

More information

Alternative Delivery for Municipal Water & Wastewater Projects in 2012

Alternative Delivery for Municipal Water & Wastewater Projects in 2012 Alternative Delivery for Municipal Water & Wastewater Projects in 2012 a OWEA 2012 Making a Pass at Going Green Looking Towards the Future June 20, 2012 Dennis Tinkler, P.E. Agenda Ohio s Methods of Performing

More information

1/4/2014. Alternative Project Delivery Methods 1. Agenda

1/4/2014. Alternative Project Delivery Methods 1. Agenda Steven. C. Thweatt Assistant Vice Chancellor Facilities Management University of Colorado @ Boulder Steven.thweatt@colorado.edu Introduction Fun in the air More Fun in Chattanooga Licensed Architect Georgia

More information

A Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station

A Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station A Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka, PE Karrie Buxton Jim Salerno Brett Burgett Rich Atoulikian, PMP, PE Cal Rozario, PMP 2014 HDR,

More information

Pre Proposal Proposal Meeting

Pre Proposal Proposal Meeting SOUTHERLY WWTC SECOND STAGE RETURN SLUDGE PUMP IMPROVEMENTS Design Build Project Pre Proposal Proposal Meeting August 15, 2012 Introduction Progressive Design-Build Procurement Approach Request For Proposals

More information

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development

More information

Lease-Leaseback Project Delivery Method

Lease-Leaseback Project Delivery Method Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,

More information

Fairfax County Government Construction Management At Risk (CMAR)

Fairfax County Government Construction Management At Risk (CMAR) Fairfax County Government Construction Management At Risk (CMAR) Presented for: CMAA - Owner s Committee Presented by: Matt Doyle Branch Chief, Wastewater Design and Construction Division Department of

More information

Design/Build Institute of America Rocky Mountain Region Water/Wastewater Committee. Project Delivery Selection Approach

Design/Build Institute of America Rocky Mountain Region Water/Wastewater Committee. Project Delivery Selection Approach Design/Build Institute of America Rocky Mountain Region Water/Wastewater Committee Project Delivery Selection Approach Overview This document provides an approach for water and wastewater project delivery

More information

SEPARATED PROJECT DELIVERY SYSTEMS

SEPARATED PROJECT DELIVERY SYSTEMS SEPARATED PROJECT DELIVERY SYSTEMS Separated (aka Traditional) The traditional delivery method typically involves three sequential project phases: The design phase, which requires the services of a designer

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Agency Project Name Stadium Project Response Deadline 1/9/14 12 pm local time

More information

Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119

Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Clark County Department of Aviation Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Professional Service Contracts Construction Contracts Professional Service Contracts

More information

WATERTOWN ELEMENTARY SCHOOLS SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018

WATERTOWN ELEMENTARY SCHOOLS SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018 SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018 Types of Public Construction Delivery Methods Available: Design-Bid-Build (DBB) under M.G.L Ch. 149 Overview Pros Cons Construction Management at Risk

More information

The Owner s Role in Successful Design-Build Project Delivery

The Owner s Role in Successful Design-Build Project Delivery The Owner s Role in Successful Design-Build Project Delivery Northwest Construction Consumer Council Tulalip Resort Casino & Conference Center October 23, 2013 presented by: Barbara Wagner Design-Build

More information

Additional information summarizing the alternatives and development of this recommendation by staff is attached.

Additional information summarizing the alternatives and development of this recommendation by staff is attached. Date: July 5, 206 To: Public Works Commission From: John Tensen Subject: Lander Street Contract Delivery Strategy Issue Public Works Commission recommendation for approval to proceed with a Construction

More information

Tampa Bay Water is a wholesale water

Tampa Bay Water is a wholesale water FWRJ Utilizing The Engineer-Procure-Construction Management Procurement Process To Get A Bang Without Going Bust Suzannah Folsom, Jonathan Kennedy, Jerry Russell, and Eric Peters Tampa Bay Water is a wholesale

More information

Construction Project Delivery Methods

Construction Project Delivery Methods Construction Project Delivery Methods Purchasing Requirements and Applications 9/20/2012 1 General Purchasing Requirements 9/20/2012 2 Governmental Purchasing Requirements Law: Texas Education Code 44.031

More information

THE MUNICIPAL WATER AND WASTEWATER DESIGN-BUILD HANDBOOK. Third Edition Expanded to Include Design-Build-Operate

THE MUNICIPAL WATER AND WASTEWATER DESIGN-BUILD HANDBOOK. Third Edition Expanded to Include Design-Build-Operate THE MUNICIPAL WATER AND WASTEWATER DESIGN-BUILD HANDBOOK Third Edition Expanded to Include Design-Build-Operate ABOUT THE WATER DESIGN-BUILD COUNCIL The Water Design-Build Council seeks to advance the

More information

REQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA

REQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA REQUEST FOR QUALIFICATIONS STATEMENT (RFQ) CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE GREENWOOD HIGH SCHOOL GYMNASIUM GREENWOOD, SOUTH CAROLINA GENERAL INFORMATION Greenwood School District 50 is

More information

Partnering for Alternative Delivery Projects

Partnering for Alternative Delivery Projects Partnering for Alternative Delivery Projects Presented by: Renee L. Hoekstra, CVS Managing Partner RHA, LLC Julie Kliewer, PhD, P.E. State Construction & Materials Engineer - ADOT Training Objectives Understanding

More information

PROVING OUR PROFESSIONALISM

PROVING OUR PROFESSIONALISM PROVING OUR PROFESSIONALISM 49 TH ANNUAL CONFERENCE MAY 22-25, 2016 ORLANDO, FLORIDA DESIGN-BUILD 101 Joanne Flick, CPPO, CPPB TODAY S TOPICS Project Delivery Overview Comparing Project Delivery Methods

More information

Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011)

Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011) Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011) Sec. 153.65. As used in sections 153.65 to 153.73 of the Revised Code: (A)(1)

More information

Complying with Ohio s. Qualifications-Based Selection Law. (Ohio Revised Code ) A Guide for Public Authorities

Complying with Ohio s. Qualifications-Based Selection Law. (Ohio Revised Code ) A Guide for Public Authorities Complying with Ohio s Qualifications-Based Selection Law for Professional Engineers, Architects & Surveyors (Ohio Revised Code 153.65-.73) A Guide for Public Authorities American Council of Engineering

More information

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014 AN OVERVIEW OF DESIGN-BUILD Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014 Design-Build Not a New Concept In California: Multiple statutes govern design-build

More information

Alternate Project Delivery Experience at UOSA and PWCSA

Alternate Project Delivery Experience at UOSA and PWCSA Alternate Project Delivery Experience at UOSA and PWCSA Bob Angelotti, Director of Technical Services at UOSA Samer Beidas, Director of Engineering and Planning at PWCSA Presented at the VWEA 2015 Education

More information

Design-Build (DB) and Construction Manager / General Contractor (CMGC)

Design-Build (DB) and Construction Manager / General Contractor (CMGC) Design-Build (DB) and Construction Manager / General Contractor (CMGC) IDOT and Industry Preliminary Joint Review for Proposed Legislation December 18, 2012 Welcome Introductions Agenda Purpose Definitions

More information

DESIGN CONSTRUCTION: PROJECT DELIVERY METHODS (SUPERPOWERS OPTIONAL!) FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors

DESIGN CONSTRUCTION: PROJECT DELIVERY METHODS (SUPERPOWERS OPTIONAL!) FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors DESIGN CONSTRUCTION: PROJECT DELIVERY METHODS (SUPERPOWERS OPTIONAL!) FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors YOUR SUPERHERO TRAINERS TODAY ADAM NELSON Senior Architectural

More information

Project Delivery Systems

Project Delivery Systems Project Delivery Systems National Society of Professional Engineers Alaska Society of Professional Engineers 2011 Western and Pacific Region Annual Meeting and Conference Jeffrey Callahan April 1, 2011

More information

Progressive Design-Build

Progressive Design-Build November 15,2016 Progressive Design-Build A Smart Alternative to Lease/Lease back? PRESENTERS Praful Kulkarni, AIA Rebekah Gladson, FAIA, DBIA Robynne T. Parkinson, JD, DBIA Presentation Outline Value

More information

CM AT RISK VS. DESIGN BID BUILD

CM AT RISK VS. DESIGN BID BUILD CM AT RISK VS. DESIGN BID BUILD A TEXAS CASE STUDY ON PROCUREMENT AND IMPLEMENTATION September 28, 2010 Acknowledgement Mike Adams, P.E Executive Director of Engineering and Utilities City of Midlothian

More information

Design-Build Trifecta A joint presentation of DBIA WESTERN PACIFIC REGION

Design-Build Trifecta A joint presentation of DBIA WESTERN PACIFIC REGION Design-Build Trifecta A joint presentation of DBIA WESTERN PACIFIC REGION and AIA LOS ANGELES September 16, 2014 Design-Build Trifecta MODERATOR: SPEAKERS: Robert J, Hartung, Hon AIA, DBIA President, Alternative

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

DESIGN BUILD: CHARLOTTE-MECKLENBURG UTILITIES DEPARTMENT PROCESS FOR THE MCALPINE CREEK WWMF EFFLUENT FILTER UPGRADE AND EXPANSION

DESIGN BUILD: CHARLOTTE-MECKLENBURG UTILITIES DEPARTMENT PROCESS FOR THE MCALPINE CREEK WWMF EFFLUENT FILTER UPGRADE AND EXPANSION DESIGN BUILD: CHARLOTTE-MECKLENBURG UTILITIES DEPARTMENT PROCESS FOR THE MCALPINE CREEK WWMF EFFLUENT FILTER UPGRADE AND EXPANSION Barry Shearin, P.E. - Charlotte-Mecklenburg Utilities Department Jackie

More information

A Primer Indianapolis, Indiana June 16, 2010

A Primer Indianapolis, Indiana June 16, 2010 Alternative Project Delivery Methods A Primer Indianapolis, Indiana June 16, 2010 Michael Kenig, Holder Construction Company, Past chair of AGC of America s s Project Delivery Committee Jayne O Donnell,

More information

Finalize Implementation Plan Conduct Introductory Campus Meetings Kickoff Several Comprehensive Projects Secured Program Managers

Finalize Implementation Plan Conduct Introductory Campus Meetings Kickoff Several Comprehensive Projects Secured Program Managers CBOC: Bond Update Since the Bond Passed Finalize Implementation Plan Conduct Introductory Campus Meetings Kickoff Several Comprehensive Projects Secured Program Managers Bond Implementation Plan Considers

More information

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours)

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours) Session THREE Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: What type of tendering methods are there? What does qualification mean? Do you (the MC) bid for every job? Do you (the MC) price

More information

VDOT DESIGN-BUILD PROGRAM

VDOT DESIGN-BUILD PROGRAM VDOT DESIGN-BUILD PROGRAM ASCE Richmond Branch Meeting Bryan Stevenson, PE, DBIA - Senior Project Delivery Engineer December 11, 2018 ALTERNATIVE PROJECT DELIVERY(APD) DIVISION ORG CHART Shailendra Patel,

More information

Design Build. What everyone ought to know about positioning their Design Build Projects for success

Design Build. What everyone ought to know about positioning their Design Build Projects for success Design Build What everyone ought to know about positioning their Design Build Projects for success San Francisco March 7, 2017 CMAA has met the standards and requirements of the Registered Continuing Education

More information

PUBLIC ANNOUNCEMENT REQUEST FOR DESIGN-BUILD SERVICES STATEMENTS OF QUALIFICATIONS (GREENVILLE CITY SCHOOL DISTRICT)

PUBLIC ANNOUNCEMENT REQUEST FOR DESIGN-BUILD SERVICES STATEMENTS OF QUALIFICATIONS (GREENVILLE CITY SCHOOL DISTRICT) PUBLIC ANNOUNCEMENT REQUEST FOR DESIGN-BUILD SERVICES STATEMENTS OF QUALIFICATIONS (GREENVILLE CITY SCHOOL DISTRICT) The Greenville City School District (the "District") invites interested parties to submit

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

Alternative Delivery Methods in the Post-Davis World

Alternative Delivery Methods in the Post-Davis World CASBO 2017 Annual Conference April 2017 Alternative Delivery Methods in the Post-Davis World Alan Reising Long Beach Unified School District areising@lbschools.net Phil Henderson Orbach Huff Suarez & Henderson

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

Rick Carr, Arcadis U.S., Inc. Tim O Malley, The O Malley Group Bill Brannen, Mohave Educational Services Cooperative

Rick Carr, Arcadis U.S., Inc. Tim O Malley, The O Malley Group Bill Brannen, Mohave Educational Services Cooperative Rick Carr, Arcadis U.S., Inc. Tim O Malley, The O Malley Group Bill Brannen, Mohave Educational Services Cooperative This presentation will cover: What is JOC? JOC contracting terms JOC experience Types

More information

Construction Manager as Constructor (CMc) Manual

Construction Manager as Constructor (CMc) Manual Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements

More information

Contracting Methods and Risk Management

Contracting Methods and Risk Management Contracting Methods and Risk Management In Tunneling and Underground Construction Michael S Schultz Senior Vice President CDM Smith Boston, Massachusetts September 12, 2016 Topics What is a Contract and

More information

Committee Meeting. Procurement Processes for Professional Services and Contractors

Committee Meeting. Procurement Processes for Professional Services and Contractors Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional

More information

Phase 1B Report on Water Treatment Plant Improvements Project Delivery Options

Phase 1B Report on Water Treatment Plant Improvements Project Delivery Options 56 Exchange Terrace, Fourth Floor Providence, Rhode Island 02903 tel: 401 751-5360 fax: 401 751-5499 October 31, 2008 Ms. Julia A. Forgue, P.E. Director City of Newport Department of Utilities 70 Halsey

More information

FACILITIES CONFERENCE

FACILITIES CONFERENCE FACILITIES CONFERENCE April 24-26, 2013 Construction Manager at Risk Lessons Learned Minnesota State Colleges and Universities The Minnesota State Colleges and Universities system is an Equal Opportunity

More information

ADDENDUM NO. 1 TO SOUTHERLY TRUCK SCALE REPLACEMENT DESIGN BUILD PROJECT (TSR-2) RFP FOR THE NORTHEAST OHIO REGIONAL SEWER DISTRICT AUGUST 13, 2012

ADDENDUM NO. 1 TO SOUTHERLY TRUCK SCALE REPLACEMENT DESIGN BUILD PROJECT (TSR-2) RFP FOR THE NORTHEAST OHIO REGIONAL SEWER DISTRICT AUGUST 13, 2012 ADDENDUM NO. 1 TO SOUTHERLY TRUCK SCALE REPLACEMENT DESIGN BUILD PROJECT (TSR-2) RFP FOR THE NORTHEAST OHIO REGIONAL SEWER DISTRICT AUGUST 13, 2012 PROPOSALS DUE: 4:30 P.M. (OFFICIAL LOCAL TIME) ON TUESDAY,

More information

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

ConsensusDocs. Catalog. Updated Docs Inside

ConsensusDocs. Catalog. Updated Docs Inside ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even

More information

Qualifications Based Selection of Contractors

Qualifications Based Selection of Contractors Qualifications Based Selection of Contractors AGC of America Project Delivery Committee QBS Working Group 1 Table of Contents QBS & The Industry: An Introduction Pages 3-4 Selection Criteria for QBS Page

More information

Campus Project Manager Measure CC Management Range: 16

Campus Project Manager Measure CC Management Range: 16 Board Approved: 04/11/2019 P. 1 5 Class specifications are intended to present a descriptive list of the range of duties performed by employees in the class. Specifications are not intended to reflect

More information

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request

More information

Keynotes RLGA. QA and QC: Are They Different?

Keynotes RLGA. QA and QC: Are They Different? QA and QC: Are They Different? By Ronald L. Geren, AIA, CSI, CCS, CCCA, SCIP Quality assurance (QA) and quality control (QC) are often used interchangeably to mean the same thing or together as if one

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Bishop Woods Landscape Restoration Response

More information

Qualifications Based Selection

Qualifications Based Selection Qualifications Based Selection Saving Municipalities More Money Than A Low-Bid RFP Cal Harrison MBA, CMC, President, Beyond Referrals About Us Does Your Municipality? The Brooks Act In 1972 The Brooks

More information

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

Design Build - Project Delivery Model Trends

Design Build - Project Delivery Model Trends Drag picture to placeholder or click icon to add Drag picture to placeholder or click icon to add Drag picture to placeholder or click icon to add Design Build - Project Delivery Model Trends Sean M. Collins,

More information

ConsensusDocs CONTRACTS CATALOG. See What s New at ConsensusDocs.org

ConsensusDocs CONTRACTS CATALOG. See What s New at ConsensusDocs.org ConsensusDocs CONTRACTS CATALOG See What s New at ConsensusDocs.org ConsensusDocs Building A Better Way! Whether working at the office, from the road or even at home, the ConsensusDocs platform provides

More information

FEATURES FOR SUCCESS DESIGN-BUILD- OPERATE WASTEWATER PROJECTS

FEATURES FOR SUCCESS DESIGN-BUILD- OPERATE WASTEWATER PROJECTS FEATURES FOR SUCCESS DESIGN-BUILD- OPERATE WASTEWATER PROJECTS Linda Hanifin Bonner, Ph.D., WDBC Mark Halleman, P.E., Parsons Produced by the Water Design-Build Council 1 Key Factors Design-Build-Operate

More information

ADVERTISEMENT FOR QUALIFICATIONS CHARTER TOWNSHIP OF SHELBY MACOMB COUNTY, MICHIGAN JOB ANALYSIS AND COMPENSATION STUDY

ADVERTISEMENT FOR QUALIFICATIONS CHARTER TOWNSHIP OF SHELBY MACOMB COUNTY, MICHIGAN JOB ANALYSIS AND COMPENSATION STUDY ADVERTISEMENT FOR QUALIFICATIONS CHARTER TOWNSHIP OF SHELBY MACOMB COUNTY, MICHIGAN JOB ANALYSIS AND COMPENSATION STUDY Sealed proposals will be received by the at the office of the Clerk, 52700 Van Dyke,

More information

PROFESSIONAL PRACTICE 544

PROFESSIONAL PRACTICE 544 PROFESSIONAL PRACTICE 544 April 20, 2015 Contracting Methods Alternative Project Delivery Methods Michael J. Hanahan, Esq. Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com

More information

Construction Manager at Risk Delivery Method

Construction Manager at Risk Delivery Method County of Alameda Board of Supervisors Transportation and Planning Committee May 4, 2015 Caroline Judy, Acting Director Construction Manager at Risk Delivery Method Briefing and Discussion Purpose Briefing

More information

Standard Form of Agreement Between Owner and Architect with Standard Form of Architect s Services

Standard Form of Agreement Between Owner and Architect with Standard Form of Architect s Services B-Series B- S E R I E S The documents in the B Series relate to various forms of agreement between an owner and an architect for professional services. B141 Standard Form of Agreement Between Owner and

More information

Alternative Delivery Methods for Construction Projects at WATER AND WASTEWATER SUMMIT 2012 LAS VEGAS, NV MAY 3, 2012

Alternative Delivery Methods for Construction Projects at WATER AND WASTEWATER SUMMIT 2012 LAS VEGAS, NV MAY 3, 2012 Alternative Delivery Methods for Construction Projects at WATER AND WASTEWATER SUMMIT 2012 LAS VEGAS, NV MAY 3, 2012 Presenter Nilaksh Kothari, P.E. General Manager Manitowoc, Wisconsin Outline of Presentation

More information

MODEL FORMS FOR A QUALITY BASED SELECTION PROCESS

MODEL FORMS FOR A QUALITY BASED SELECTION PROCESS NHQBS P.O. Box 398, Keene New Hampshire 03431-0398 Telephone 603.357.2863 Fax 603.357.0835 E-mail: info@nhqbs.org www.nhqbs.org MODEL FORMS FOR A QUALITY BASED SELECTION PROCESS NEW HAMPSHIRE QBS COALITION

More information

AIA Contract Documents

AIA Contract Documents AIA Contract Documents Contract Relationship Diagrams April 2017 Conventional (A201) Design-Bid-Build For use when the s project is divided into separate contracts for design () and construction (Contractor).

More information

PENINSULA CORRIDOR JOINT POWERS BOARD STAFF REPORT. Executive Officer, Caltrain Modernization Program

PENINSULA CORRIDOR JOINT POWERS BOARD STAFF REPORT. Executive Officer, Caltrain Modernization Program PENINSULA CORRIDOR JOINT POWERS BOARD STAFF REPORT AGENDA ITEM # 8 SEPTEMBER 5, 2013 TO: THROUGH: FROM: SUBJECT: Joint Powers Board Michael J. Scanlon Executive Director Marian Lee Executive Officer, Caltrain

More information

VILLAGE OF GLENDALE, OHIO REQUEST FOR QUALIFICATIONS CIVIL ENGINEERING SERVICES JULY 2015

VILLAGE OF GLENDALE, OHIO REQUEST FOR QUALIFICATIONS CIVIL ENGINEERING SERVICES JULY 2015 VILLAGE OF GLENDALE, OHIO REQUEST FOR QUALIFICATIONS CIVIL ENGINEERING SERVICES I. INVITATION JULY 2015 The Village of Glendale requests firms submit proposal and qualifications for ongoing Civil Engineering

More information

Construction Management at Risk

Construction Management at Risk Construction Management at Risk Implementation and Lessons Learned Virginia Water Environment Association Webinar Janelle Wright Okorie Director, Engineering and Technology Programs 21 October 2015 Alexandria

More information

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR February 5, 2018 SUMMARY OF CM/GC SELECTION PROCESS FOR DIMMIT II APARTMENT BUILDING The Town of Winter Park requests proposals from qualified Construction Manager / General Contractor (CM/GC) firms for

More information

DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD

DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD OWNER OWNER OWNER DESIGNER GC DESIGNER DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD Contracts Communications

More information