Anne Arundel Hall Partial Reuse Report

Size: px
Start display at page:

Download "Anne Arundel Hall Partial Reuse Report"

Transcription

1 St. Mary s City, MD Anne Arundel Hall Partial Reuse Report 1850 K Street, NW Washington, DC 20006

2 The purpose of this design study was to define the criteria and frame a decision-making process for the retention or replacement of portions of Anne Arundel Hall. This study is to supplement the 2007 Report Analysis of Adaptive Re- Use for Anne Arundel Hall, which examined a complete reuse of AAH. This report aims to document the analysis of the study and communicate the pros and cons of retaining a portion of Anne Arundel Hall. In this effort studied Anne Arundel Hall as it relates to Site Planning and Development, Sustainability, Program, and Architectural Design Context for the following three options. Option 1: Option 1a: Option 2: Option 3: Retain only the main wing of AAH for new AAH program. Build a new structure for the remaining AAH and MHIC program. Retain the foundation of the main wing of AAH and build a new building on this footprint. Retain only the 2 story block (former library). Build a new structure for the remaining AAH and MHIC program. Demolish the entire AAH building. Build a new structure for the entire AAH and MHIC program. During the study held a design charrette on April 21 with and landscape architect, Michael Vergason, to review the pros and cons of the three options. This report summarizes the site analysis, investigations, and conclusions of the charrette and is organized by Site Considerations, Sustainable Design Considerations, and Program Considerations. 1

3 Views to and from Anne Arundel Hall View from Middle Street toward AAH View from North Campus toward AAH View from roof of AAH toward Middle Street 2 Approach to AAH

4 Site Considerations Site Analysis consisted of studying existing building plans, site documentation, and available archeological data to illustrate existing conditions, constraints, parameters of the site. These backgrounds were used to test a series of over arching campus planning principles and philosophies for the site. Pro: Keeping the existing building preserves the memory of the existing building while adapting it for the new program. Retention minimizes construction disturbances on site that could affect archeology. Con: The existing building blocks the continuation of Middle Street. Reopening of Middle Street will assist in visitor orientation and further integrate the campus into St. Mary s City history. Building on the Street does not send the right message (nor demonstrates sensitivity) for the interpretive center, archeology department nor the museum studies program. Current building dominates the HSMC landscape from the town center. If portions of the existing 2 story building are used for academic class rooms and offices, the interpretive center will need to move south to become visible and obvious from the visitor parking area. This will push the visitor center into saturated areas of archeology. The site topography and demand for contained outdoor space is significantly constrained with retention of the existing building. Aligning floor levels with new construction will be more complicated with the existing levels and will result in ramps and or additional elevators. Keeping only the library wing results in an either free standing pavilion of awkward proportions or would have a negative impact on any new construction connected to it due to the height of the finished floor at several feet above grade. This makes it difficult to satisfy ADA accessibility requirements. 3

5 Trinity Church Anne Arundel Hall and Brent Hall Historic St. Mary s City Reconstructions Historic St. Mary s City Ghost Frames Old State House Road Route 5 St. Mary s River 4

6 Option 1 Keep main wing of AAH Option 1a Build on foundation of main wing of AAH Trinity Church Anne Arundel Hall and Brent Hall Historic St. Mary s City Reconstructions Historic St. Mary s City Ghost Frames Archeological site - high sensitivity area Archeological site - medium sensitivity area 5

7 6

8 Option 2 Keep Library wing of AAH Site Conclusions Retaining the existing building complicates a site already layered with obstacles including subsurface archeology, steeply sloping topography and mature trees. The existing floor levels of the hall will be onerous to connect with the new floor elevations resulting in multiple ramps and/or elevators. The existing building also closes off the original Middle Street axis which, since its construction, has been identified and represented. Retaining the existing main building for the classroom facility will require that the interpretive center encroach on the southern nose of the site, diminishing the city view shed from Route 5. Trinity Church Anne Arundel Hall and Brent Hall Historic St. Mary s City Reconstructions Historic St. Mary s City Ghost Frames 7 Archeological site - high sensitivity area Archeological site - medium sensitivity area

9 8

10 Sustainable Design Considerations The evaluation of the sustainability considerations of reusing a portion of AAH examined a holistic range of environmental impacts, including material conservation and embodied energy, preserving cultural resources, minimizing site disturbances, and promoting operational energy efficiency. These impacts are summarized below. Reduced Embodied Energy 1 Pro: By updating existing buildings for new purposes, adaptive re-use extends the life-cycle of a building by conserving materials. Development will have less embodied carbon if existing structures remain. This fact must be qualified by the following considerations. Even if a portion of AAH is reused, there would be considerable demolition and new construction to restore AAH so that it meets the project s requirements. All interior finishes, mechanical / electrical / plumbing equipment, windows, attic floor would need to be replaced. Portions of the exterior wall, interior walls, interior floors, and existing stairs would need to be replaced. As a result, the reused existing building would have some embodied carbon. The embodied carbon of new development can be reduced by sustainable materials selection and by salvaging or reusing the demolition waste from AAH. If all of the materials that would have been reused in AAH were salvaged and reincorporated into the new development, then the embodied carbon between the energy use to dismantle and reinstall the materials.) The materials that would remain in a reused AAH largely consist of brick, cinder block, concrete, steel, wood doors, and slate roofing. These can be directly and indirectly reused in the new development. Brick can either be salvaged / reused as masonry veneers or can be ground and used as subbase underneath future permeable paving. Cinder block and concrete can be used as subbase as well. The slate roofing is in good condition and can be reused to roof future development. Wood doors can be salvaged and reused in the new development. 1 Embodied energy (or embodied carbon) is a measure of the amount of energy required to extract, manufacturer, transport, and construct the materials that comprise a building. 9

11 Preserving Cultural Resources Pro: Retaining the existing building preserves the cultural significance of AAH. This fact must be qualified by the following considerations. AAH is not a historically significant structure. It does hold nostalgic value since it has been part of the campus for over 50 years. Reusing portions of the building in the new development, like the entrance portico and the entrance exterior lanterns, can retain its historic features. Salvaging bricks, slates, and doors will retain the memory of the building. Limiting Site Disturbances Neutral: Adaptive Re-use of structures maintains development within previously developed sites. This benefit is not a relevant factor because regardless of whether AAH is preserved, all new development will occur on this previously developed site. If the AAH is demolished and all new development is limited to previously disturbed portions of the site, then the extent of site disturbance is the same regardless of whether AAH is reused or not. 10

12 Promotes Energy Efficiency Buildings use 76% of the US electricity consumption, and the vast majority of electricity in the United States is made by burning fossil fuels, the source of global warming. Over the life of a campus building, the energy used to operate a building is over three times more than the energy used to construct the same building. The US Green Building Council s Leadership in Energy and Environmental Design (LEEDTM) rating system has weighted sustainable design considerations accordingly, prioritizing sustainable goals that reduce operational energy. A balanced sustainable assessment of AAH must factor the potential operational energy use of a renovated AAH against that of building a new, high-performance new green building. Con: The envelope of AAH is poorly insulated. Windows can be replaced with new, efficient glazing, but windows represent a small portion of the building envelope Highly insulated envelopes play a critical role in green buildings, and envelope improvements can result in a 20% increase in energy performance. The existing masonry walls have little insulation and no thermal barrier. Adding insulation and vapor barriers will have limitations, and hygro-thermal analysis would be required to ensure proposed improvements will not create moisture migration issues. The exterior envelope of a new building can out-perform the improved envelope of a renovated AAH. Con: The orientation of AAH does not support passive solar design. The primary axis of the building is to NW-SE, resulting in long elevations oriented to the SW. Low sun angles make solar control difficult to implement on SW facades. The NW and NE facades of the building will receive little solar heat gain during winter months, negating the possibility for passive solar heating. Con: The orientation of AAH does not support daylighting Southwest and Southeast facing facades are subject to low sun angles making glare difficult to control Northwest and Northeast faces will receive little direct natural light during winter months. Con: The orientation of AAH does not support passive cooling (natural ventilation) The long elevations of the building are not oriented perpendicular to prevalent breezes, making cross ventilation difficult to achieve. 11

13 Pro: The building fenestration supports daylighting and natural ventilation. Large and frequently spaced windows provide adequate daylight so that most spaces can be daylit on a sunny day without relying on artificial lighting. Double-hung windows in classrooms can promote natural ventilation. The former library can be restored to its original tall volume. Using the vents in the existing eyebrow dormers as air outlets would promote stack ventilation airflow. These benefits are offset by the undesirable orientation mentioned above. Sustainable Design Conclusions Partial reuse of AAH will result in lower embodied energy for the planned development, but by reusing and salvaging significant portions of the demolition waste from AAH in a newly constructed AAH replacement, the resulting development will have a similar low embodied energy. Even with extensive improvements to the existing AAH, limitations to envelope improvements, and immutable undesirable building orientation suggests that a sustainably designed new development will have a better operational energy use. Given the significance of operational energy use, the holistic sustainable design benefit to reusing AAH is either neutral or less favorable than constructing a state-of-the-art, energy-efficient, new building. Replacing AAH with a conventional, unsustainable building would result in a negative environmental impact. Sustainability is an important consideration for St. Mary s College, and any plans that include the full demolition of AAH should include aggressive construction waste management and salvage of existing building components and high energy-performance goals for the replacement building. 12

14 Program Considerations A series of test fits of all or parts of the AAH and MHIC program were assessed in the Main wing and the Library wing. Important criteria in the test fits include program adjacencies, required heights of spaces, building entry and delivery points, extent of renovation needed, structural restrictions, and building efficiency. Pro: Con: AAH program fits in existing main wing (Option 1a). MHIC program fits on first floor of main wing (Option 1b). Blackistone Room or several classrooms fit in Library wing (Option 2.) Extensive intervention is required to accommodate new programs and bring up to code. Existing structure restricts ability to create public spaces and open up entry. Not suitable for HSMC lab portion due to loading and environmental requirements. Wide floor plate (58 ) and window spacing at 7-9 limits efficient office planning. Not suitable for the image of the interpretive center and not configurable for circular flow of public spaces. Elevation of existing Library wing is several feet above grade which would require excessive ramps to meet ADA code. Program Conclusions It was determined that while different components of the Anne Arundel Hall or Maryland Heritage Interpretive Center programs could fit in the existing structure, the function and efficiency of these programmatic parts would be greatly compromised and extensive renovation would be required. In addition, the existing main wing prescribes a linear and bifurcated experience and does not allow for a circular museum circulation. Window spacing Sectional change Corridor condition 13

15 Option 1a- 1st floor Windows are spaced 7-9 on center; difficult for office layout creating offices that are too narrow or very large. Additional space for small classroom Support Med. Classroom 600 Class Lab 450 Lab Support 120 Stor 100 Stud. Proj. 250 Women s Room Men s Room Small Classroom 500 Seminar 400 Additional Classroom Typ. Office Exhibit display Seminar 480 Multi-Pur. Classroom 500 Blackistone Room 1100 Exhibit display Typ. Office Instructional Technologist Center for Democracy 260 Middle Street Option 1a- 2nd floor Windows are spaced 7-9 on center; difficult for office layout creating offices that are too narrow or very large. Wide floor plate = 58 ; limits efficient office planning Typ. Office Limited live loads Women s Room Support Men s Room Support Seminar 480 Language Lab 770 Stud. Proj. 120 Medium Classroom 600 Middle Street 14

16 Option 1b- 1st floor Floor to Clg. Height = 11-0 not ideal for exhibits Opportunity to open up double height space for galleries Limited Environmental Control Opportunity to open ends to take advantage of views Permanent Exhibits Gallery 2025 Women s Room Visitor Center Office 150 Men s Room Video Orientation Theater 800 Special Exhibits Gallery 1000 Visitor Lobby 600 Exhibit Prep/ Storage 250 Permanent Exhibits Gallery 500 Load/ Rec v 100 Permanent Exhibits Gallery 2025 Middle Street Option 1b- 2nd floor Women s Room Men s Room Swing Space Middle Street 15

17 Option 2-1st floor a) Blackistone Room and support space (Bathrooms, Catering Kitchen, Storage) These support spaces currently not in program b) Larger Blackistone Room Enlarge Blackistone Room from 1100 nsf to 1835 nsf c) Classrooms 2 Medium classrooms and Multi-purpose classroom Library wing of AAH from Route 5 16 Interior corridor in Library wing of AAH

18 Summary Based on the challenges of the site planning, sustainability criteria, and programmatic needs it was determined that the challenges of retaining portions of Anne Arundel Hall far outweighed the positives. Proceeding with the existing buildings would severely compromise the site planning principles and would force a program into an inappropriate space. The sustainable design benefit would be neutral or less favorable than constructing a new energy-efficient building. The group decided to pursue Option 3, demolition of Anne Arundel Hall, and to design a new building or buildings to house the Anne Arundel Hall, Historic St. Mary s City, and the Maryland Heritage Interpretive Center programs in order to meet the goals of the project. 17

19

Project Parameters. Project Timeline. APS Strategic Plan - Design Principles. Adjourn

Project Parameters. Project Timeline. APS Strategic Plan - Design Principles. Adjourn Project Parameters Project Timeline Project included in the FY09-8 Capital Improvement Plan (CIP) Renovate the Education Center to both increase the capacity of WashingtonLee initially, and later to adapt

More information

The Butler Gallery at the Evans Home CONSERVATION REPORT. McCullough Mulvin Architects. September 2016

The Butler Gallery at the Evans Home CONSERVATION REPORT. McCullough Mulvin Architects. September 2016 The Butler Gallery at the Evans Home CONSERVATION REPORT McCullough Mulvin Architects September 2016 To be read in conjunction with impact statement and condition survey / recommendations in Carrig reports

More information

INTUITIVE AND OBJECTIVE APPROACHES TO DAYLIGHTING A NEW ENGLAND ELEMENTARY SCHOOL Michael Rosenfeld 1

INTUITIVE AND OBJECTIVE APPROACHES TO DAYLIGHTING A NEW ENGLAND ELEMENTARY SCHOOL Michael Rosenfeld 1 Best2 - Daylighting a New England Elementary School - Session EE 7-3 INTUITIVE AND OBJECTIVE APPROACHES TO DAYLIGHTING A NEW ENGLAND ELEMENTARY SCHOOL Michael Rosenfeld 1 ABSTRACT The Town of Concord,

More information

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3 MEMORANDUM To: Ashley Rosenthal Payne, Indianapolis Historic Preservation Commission Adrienne Schmetzer, Indiana Housing and Community Development Authority Architecture Preservation Interior Design Landscape

More information

Peter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report

Peter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report Peter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report January 2016 Summary In consideration for a potential 2016 Bond measure for the Capital Facilities Program, Kirk Elementary

More information

Consulting Parties Meeting Center Building Concept. February 23, 2010

Consulting Parties Meeting Center Building Concept. February 23, 2010 Consulting Parties Meeting Center Building Concept Presentation Organization Project Team Project Goals Building Evaluation Heritage Existing Conditions Life Safety Evaluation Programmatic Fit Concept

More information

Horticulture Building

Horticulture Building 005 Horticulture Building University of Saskatchewan Heritage Register November 2014 005 Horticulture Building Alternate Names Header Houses Figure 1. A window sill of Indiana limestone set into a greystone

More information

Principle of Planning

Principle of Planning Principle of Planning Building Drawing Planning and Design Principles of Architecture Functional Planning Best utilization of space Purpose of building :residential, commercial, educational, industrial..

More information

Dr. Edward Livingston Trudeau Building. 118 Main Street, Saranac Lake, NY. Building Systems Report. June 24, 2018

Dr. Edward Livingston Trudeau Building. 118 Main Street, Saranac Lake, NY. Building Systems Report. June 24, 2018 G2 Gordon + Gordon Architecture. LLC Dr. Edward Livingston Trudeau Building 118 Main Street, Saranac Lake, NY Building Systems Report June 24, 2018 Harry Gordon, FAIA 164 Otter Slide Road Saranac Lake

More information

HISTORICAL OVERVIEW OPN ARCHITECTS. Home Office Building of The Bankers Life Building, 1940

HISTORICAL OVERVIEW OPN ARCHITECTS. Home Office Building of The Bankers Life Building, 1940 OPN ARCHITECTS Home Office Building of The Bankers Life Building, 1940 HISTORICAL OVERVIEW Designed as the home office of The Bankers Life Insurance Company by architects Tinsley, McBroom & Higgins in

More information

Administration Building Needs Assessment

Administration Building Needs Assessment Town Hall Meeting with the Habersham County Board of Commissioners Administration Building Needs Assessment JUNE 13, 2016 Detailed Evaluation Performed in 2015 Engineering Evaluation Site/Civil Architectural

More information

McNichols Civic Center Building City & County of Denver Proposed New Terrace and South Facade Rehabilitation Denver, Colorado

McNichols Civic Center Building City & County of Denver Proposed New Terrace and South Facade Rehabilitation Denver, Colorado McNichols Civic Center Building City & County of Denver Proposed New Terrace and South Facade Rehabilitation Denver, Colorado Denver Landmark Preservation Commission Infill Mass & Scale Submittal 04 September

More information

Bronx Community College. Five-Year Capital Plan FY through FY

Bronx Community College. Five-Year Capital Plan FY through FY Five-Year Capital Plan FY 2019-20 through FY 2023-24 Projects in priority order / costs in $ thousands Project Name FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24 (B) Campus-Wide Fire Alarm Replacement DC

More information

Juanita High School Modernization vs. New-in-lieu of Modernization Report

Juanita High School Modernization vs. New-in-lieu of Modernization Report Juanita High School Modernization vs. New-in-lieu of Modernization Report January 2016 Summary In consideration for a potential 2016 Bond measure for the Capital Facilities Program, Juanita High School

More information

DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING

DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING Multi family housing is an increasingly popular form of infill development in Shaker Heights because of the city s built out

More information

Fall 2013 Re-Making the Future. Annie Ranttila. Hazelwood Climate Analysis

Fall 2013 Re-Making the Future. Annie Ranttila. Hazelwood Climate Analysis Fall 2013 Re-Making the Future Annie Ranttila Hazelwood Climate Analysis Pittsburgh Pittsburgh, Pennsylvania is located in southwest Pennsylvania s Allegheny County. With a population of approximately

More information

CITY OF SAVANNAH HISTORIC DISTRICT BOARD OF REVIEW REQUEST FOR CERTIFICATE OF APPROPRIATENESS

CITY OF SAVANNAH HISTORIC DISTRICT BOARD OF REVIEW REQUEST FOR CERTIFICATE OF APPROPRIATENESS CITY OF SAVANNAH HISTORIC DISTRICT BOARD OF REVIEW REQUEST FOR CERTIFICATE OF APPROPRIATENESS STAFF RECOMMENDATION PETITIONER: FILE NUMBER: ADDRESS: Brenda K. Pearson Neil Dawson Architects, PC 1020 Bryan

More information

Community Liaison Committee and Neighborhood Collaborative. American University Hall of Science. August 7, 2017

Community Liaison Committee and Neighborhood Collaborative. American University Hall of Science. August 7, 2017 Community Liaison Committee and Neighborhood Collaborative American University Hall of Science August 7, 2017 Agenda 1. Why a Life Science Building? STEM Growth Obsolete Facilities 2. Options Considered

More information

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW HISTORIC PRESERVATION REVIEW submitted to: DC Historic Preservation Office Office of Planning ARCHITECTS ARCHITECTURAL NARRATIVE Bruce Monroe Elementary School at Park View is among the schools included

More information

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005

More information

Section 106 Consultation, Assessment of Effects September 21, Page 1 of 10. Area of Potential Effects and Identification of Historic Properties

Section 106 Consultation, Assessment of Effects September 21, Page 1 of 10. Area of Potential Effects and Identification of Historic Properties Page 1 of 10 South Mall Campus Master Plan Assessment of Effects This document provides an assessment of effects for the alternatives under consideration for the South Mall Campus Master Plan. The alternatives

More information

Chapter 7. Passive Solar Contents

Chapter 7. Passive Solar Contents Chapter 7. Passive Solar Contents 7.1 Introduction 7.2 Types of Passive Solar Systems 7.3 Advantages and Disadvantages 7.4 General Design Principles 7.5 Design Information for Direct System 7.6 Design

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

Ames Public Library. Ames Public Library

Ames Public Library. Ames Public Library Public Forum Library Planning Associates (Library Planning) Meyer, Scherer & Rockcastle, Ltd. (Architecture, Interior Design, and Furniture) with TSP, Inc. (Architecture and Engineering), CPMI, Inc. (Cost

More information

INTENT OBJECTIVES HISTORIC DESIGNATIONS

INTENT OBJECTIVES HISTORIC DESIGNATIONS TOWN OF LOS GATOS RESIDENTIAL DEVELOPMENT STANDARDS FOR ALL SINGLE FAMILY AND TWO-FAMILY DWELLINGS IN ALL ZONES EXCEPT THE RESOURCE CONSERVATION AND HILLSIDE RESIDENTIAL ZONES INTENT These development

More information

Planning Rationale. A) Family Oriented Development

Planning Rationale. A) Family Oriented Development Planning Rationale A) Family Oriented Development The proposed building at 800 Montreal Road is a place designed to engage and stimulate the local community. The wide range of unit types provided offer

More information

UCC Permit Application Procedures

UCC Permit Application Procedures How do I apply for a permit? UCC Permit Application Procedures 1. Please complete the CodeMaster Pan Review Application 2. Please provide the scope of work description and/or construction documents/plans.

More information

Sgt. Alvin C. York Historic School

Sgt. Alvin C. York Historic School Sgt. Alvin C. York Historic School TABLE OF CONTENTS I. Introduction II. III. IV. Historical Evaluation Architectural Evaluation Preservation Plan V. Design Parameters VI. VII. Master Plan/ Site Design

More information

Case Study: Golisano Institute for Sustainability

Case Study: Golisano Institute for Sustainability Case Study: Golisano Institute for Sustainability Rochester Institute of Technology - Golisano Institute for Sustainability Sustainability Hall at Rochester Institute of Technology A001.01 (RIT) is a LEED-Platinum

More information

A Program Summary: Complete renovation and addition with code upgrades for a historic academic building

A Program Summary: Complete renovation and addition with code upgrades for a historic academic building Program Summary: Complete renovation and addition with code upgrades for a historic academic building Program Statement: Damaged in Hurricane Katrina, the circa-1929 former high school in the historic

More information

RR Program Summary: Complete renovation with addition and code upgrades for a historic academic building

RR Program Summary: Complete renovation with addition and code upgrades for a historic academic building Program Summary: Complete renovation with addition and code upgrades for a historic academic building Program Statement: Damaged in Hurricane Katrina, the circa-1929 former high school in historic Marigny

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior

More information

building audit & site analysis

building audit & site analysis bowen island firehall bowen island municipality & bowen island fire department bowen island, b.c. building audit & site analysis issued june 30, 2008 johnston davidson architecture + planning inc. 200-1300

More information

Hartsville Area Schools - Building Evaluations

Hartsville Area Schools - Building Evaluations Darlington County School District Darlington, South Carolina August 8, 2012 Hartsville Area Schools - Building Evaluations School Name: West Hartsville Elementary Observed By: Cannon/Carter Principal:

More information

Board Work Session Feasibility Study. January 9, 2017

Board Work Session Feasibility Study. January 9, 2017 Board Work Session Feasibility Study January 9, 2017 1 Process Staff Input Sessions at all schools What can you tell us about your building, your site, your space? Group collaboration exercise looking

More information

PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016

PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016 PRESENTATION TO THE FARMINGTON CITY COUNCIL FOR THE PROPOSED FARMINGTON CIVIC CENTER EXPANSION SEPTEMBER 20, 2016 WORK LEGEND OVERALL WORK TO BOTH BUILDINGS 1 2 3 4 Existing corridors will receive new

More information

Phillips Family Offices: Preservation & LEED-NC

Phillips Family Offices: Preservation & LEED-NC Phillips Family Offices: Preservation & LEED-NC Deborah Everson, AIA LEED AP Michael Everson, J.D. LEED AP, BD + C Jason Briles, Associate AIA Daniel Katzenberger, P.E., LEED AP, CEM, CSDP, DSMP, GBE The

More information

Neighborhood Suburban Single-Family District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations

Neighborhood Suburban Single-Family District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations Section 16.20.020 - Neighborhood Suburban Single-Family Districts ( NS ) Sections: Typical Block in a Neighborhood Suburban District 16.20.020.1 History and Composition of Suburban Neighborhoods 16.20.020.2

More information

Overall Existing Conditions Summary

Overall Existing Conditions Summary September 12, 2002 Overall Executive Summary: The multi-use project on 250 West Street is a 7-story building with space for offices, retail, storage and parking. The project is a small part of the development

More information

04/05/2014. Introductions. Agenda. Heritage Adaptive Reuse: A Catalyst for Revitalization

04/05/2014. Introductions. Agenda. Heritage Adaptive Reuse: A Catalyst for Revitalization Heritage Adaptive Reuse: A Catalyst for Revitalization Susan Spencer Lewin, OAA, CS&P Architects Scott Weir, OAA, ERA Architects Introductions Susan Spencer Lewin, CS&P Architects Scott Weir, ERA Architects

More information

KNOXVILLE HISTORIC ZONING COMMISSION STAFF REPORT CERTIFICATE OF APPROPRIATENESS APPLICATION

KNOXVILLE HISTORIC ZONING COMMISSION STAFF REPORT CERTIFICATE OF APPROPRIATENESS APPLICATION KNOXVILLE HISTORIC ZONING COMMISSION STAFF REPORT CERTIFICATE OF APPROPRIATENESS APPLICATION PROPERTY ADDRESS: 227 Leonard Pl FILE NO.: 8 F 15 HZ DISTRICT: Ft. Sanders NC 1 MEETING DATE: 8/20/2015 APPLICANT:

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

CHAPTER 6 CONCLUSION

CHAPTER 6 CONCLUSION 255 CHAPTER 6 CONCLUSION This study thoroughly assessed the design principles employed in simple, durable and eco-friendly vernacular dwellings in the coastal regions of Tamil Nadu and their effectiveness

More information

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School

More information

transformation: 1908 schoolhouse

transformation: 1908 schoolhouse transformation: 1908 schoolhouse katrina e. huber thesis submitted to the faculty of virginia polytechnic institute and state university in partial fulfillment of the requirements for the degree of master

More information

INTERNATIONAL BUILDING CODE

INTERNATIONAL BUILDING CODE INTERNATIONAL BUILDING CODE MODEL BUILDING CONDITIONS ASSESSMENT The Reid and Hughes building is a four-story, four-bay, brick building, constructed in 1869 with a later addition known as the Williams

More information

Becker Morgan Group, Inc. (architectural and site systems) Gipe Associates, Inc. (mech./elec./plumbing systems) Morabito Associates, Inc.

Becker Morgan Group, Inc. (architectural and site systems) Gipe Associates, Inc. (mech./elec./plumbing systems) Morabito Associates, Inc. AGENDA REVIEW PROJECT BACKGROUND & PURPOSE REVIEW PROJECT FINDINGS REVIEW THE 4 OPTIONS DEVELOPED OPTION COMPARISONS REVIEW PROJECT SCHEDULE COMMUNITY COMMENTS / QUESTIONS TEAM Becker Morgan Group, Inc.

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number Exhibit B SCHEMATIC DESIGN BRIEFING for Dr. JOE A. HAIRSTON TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS September 9, 2008 Design Collective Project Number 149-08 Towson West Elementary

More information

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012 Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap

More information

A Building Area: (sf) 13,165 sf. Cost per Square Foot: $258. Construction Cost $3.4 million. Date of Completion: January 2011

A Building Area: (sf) 13,165 sf. Cost per Square Foot: $258. Construction Cost $3.4 million. Date of Completion: January 2011 Program Summary: New headquarters facility for the largest municipal park in New Orleans, to replace a 1990s office building destroyed by Hurricane Katrina. Program Statement: The firm was commissioned

More information

Assessment Report Burgess Park Gymnasium. Summary

Assessment Report Burgess Park Gymnasium. Summary Assessment Report Burgess Park Gymnasium Summary The existing Burgess Park Gymnasium is an approximately 17,460 gross square feet singlestory structure built of concrete, wood and steel. The building,

More information

MCER Study for Little Powder K-8

MCER Study for Little Powder K-8 MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives

More information

2017 City of Ortonville Northridge Study

2017 City of Ortonville Northridge Study 2017 City of Ortonville Northridge Study HASSLEN CONSTRUCTION AND RICE STROMGREN ARCHITECTS / STUDY / Page 1 CONTENTS Existing City Facilities Executive Summary 3 Location of Facilities 4 City Hall/Community

More information

TABLE OF CONTENTS Page

TABLE OF CONTENTS Page TABLE OF CONTENTS Page Executive Summary i Facility Profile and Summary 1 Section 1 Site Conditions 4 Section 2 Building Exterior 7 Section 3 Building Interior 11 Section 4 Mechanical Systems 14 Section

More information

DESIGN STANDARDS & GUIDELINES for THE EMILY GRIFFITH OPPORTUNITY SCHOOL WELTON STREET and 1261 GLENARM PLACE

DESIGN STANDARDS & GUIDELINES for THE EMILY GRIFFITH OPPORTUNITY SCHOOL WELTON STREET and 1261 GLENARM PLACE DESIGN STANDARDS & GUIDELINES for THE EMILY GRIFFITH OPPORTUNITY SCHOOL 1250 WELTON STREET and 1261 GLENARM PLACE Adopted by Denver City Council May 2016 INTRODUCTION 1. View of the Emily Griffith Opportunity

More information

TOWN OF BELMONT, NH - TOWN CENTER FACILITIES - CONCEPTUAL PROJECT BUDGET December 20, 2018

TOWN OF BELMONT, NH - TOWN CENTER FACILITIES - CONCEPTUAL PROJECT BUDGET December 20, 2018 POLICE DEPARTMENT OPTION A - Addition/Renovation to Existing Site 6,662 S.F. Interior demolition $ 12/SF $ 79,944 Foundation and structural frame $ 35/SF $ 233,170 Thermal and moisture protection $ 30/SF

More information

MITTERSILL WARMING HUT

MITTERSILL WARMING HUT STATE OF NEW HAMPSHIRE DEPARTMENT OF RESOURCES AND ECONOMIC DEVELOPMENT DIVISION OF PARKS AND RECREATION PROJECT #: CAP 1786 FRANCONIA NOTCH STATE PARK FRANCONIA, NEW HAMPSHIRE DRAWING LIST: COVER SHEET

More information

Neighborhood Traditional Single-Family District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations

Neighborhood Traditional Single-Family District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations Section 16.20.010 - Neighborhood Traditional Single-Family Districts ( NT ) Typical Houses in a Neighborhood Traditional District Typical Block in a Neighborhood Traditional District Common Features of

More information

137 Beechwood Avenue Design Brief. Prepared by

137 Beechwood Avenue Design Brief. Prepared by Design Brief Prepared by Existing Site Plan The proposal requests permission of the City of Ottawa for Site Plan Control of. The proposed development of the site envisions the intensification of the lot,

More information

Village of Glen Ellyn Basement Remodeling Project Guidelines

Village of Glen Ellyn Basement Remodeling Project Guidelines Village of Glen Ellyn Basement Remodeling Project Guidelines Existing unfinished basement space is often remodeled to create more habitable (living, sleeping, eating, dining) space in a home. Building

More information

Update on FCPS Construction/Renovation Projects. November 2015

Update on FCPS Construction/Renovation Projects. November 2015 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

Scripps Ranch High School

Scripps Ranch High School Scripps Ranch High School 10410 Treena St. San Diego, CA 92131 Sub-district: B Cluster: Scripps Ranch Year School Opened: 1993 Grades: 9-12 4 3 1 2 1 2 3 4 Sustainable Technologies Buildings Synthetic

More information

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements % 8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior

More information

Sangren Hall Western Michigan University

Sangren Hall Western Michigan University Sangren Hall Western Michigan University 11 August 2009 11 August 2009 2 Site Site relation 11 August 2009 4 Sangren Hall Project Departments & Groups Sangren Hall ATIS - Academic Technology and Instructional

More information

SUSTAINABLE ARCHITECTURAL DESIGN JOSH DYGERT, AIA EDWARD TUCKER ARCHITECTS, INC.

SUSTAINABLE ARCHITECTURAL DESIGN JOSH DYGERT, AIA EDWARD TUCKER ARCHITECTS, INC. SUSTAINABLE ARCHITECTURAL DESIGN JOSH DYGERT, AIA WHAT DOES IT MEAN TO BE GREEN? Sustainable of, or relating to, or being a method of harvesting or using a resource so that the resource is not depleted

More information

Accepted Architectural Styles 1. Classical Revival 2. French 3. Texas Regional Vernacular 4. Tudor 5. Mediterranean 6. Modern Classical Revival Classical Revival design seeks to emulate elements of Ancient

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % BartelsRode Gymnasium 8/11/ Building Rating System Percent Site: 1.0 Total 0 13 77% Building: 2.1 Building Exterior Elements 0 8 8% 2.2 Accessibility 0 74 74% 2.3 Structural 0 76 76% 2.4 Building Envelope

More information

These findings and the Mitigation Monitoring Program ( MMP, attached as Exhibit B) address only the impacts of the West Branch Library Project.

These findings and the Mitigation Monitoring Program ( MMP, attached as Exhibit B) address only the impacts of the West Branch Library Project. Page 1 of 6 FINDINGS OF FACT REGARDING ENVIRONMENTAL IMPACTS, MITIGATION MEASURES, ALTERNATIVES AND OVERRIDING CONSIDERATIONS FOR THE BERKELEY WEST BRANCH LIBRARY PROJECT INTRODUCTION: The Berkeley Branch

More information

Corridor Residential Suburban District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations

Corridor Residential Suburban District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations Section 16.20.070 - Corridor Residential Suburban Districts ( CRS ) Sections: Typical Buildings in the CRS District 16.20.070.1 Composition of Suburban Residential Corridors 16.20.070.2 Purpose and Intent

More information

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School HILLSIDE ELEMENTARY SCHOOL Overview: The is located at 98 Belmont Drive and consists of a two-story building which has had a number of additions added to it over the years, the latest of which was a two-story

More information

NORTHEAST IOWA COMMUNITY COLLEGE 2018 FACILITY ASSESSMENT MAY 15, 2018

NORTHEAST IOWA COMMUNITY COLLEGE 2018 FACILITY ASSESSMENT MAY 15, 2018 NORTHEAST IOWA COMMUNITY COLLEGE 2018 FACILITY ASSESSMENT MAY 15, 2018 INTENT The overriding goal of this assessment was to evaluate existing facilities to determine a scope of work that should be done

More information

Central Valley Research and Technology Business Park

Central Valley Research and Technology Business Park Central Valley Research and Technology Business Park Architectural Guidelines Clovis Planning and Development Services Background The Central Valley Research and Technology Business Park (CVRTBP) was established

More information

On March congressional authorization was received for:

On March congressional authorization was received for: Building History, Description and Significance Chronology of Development and Use 1.2 A Description of the Building as Initially Constructed Located at 900 Jefferson Drive, SW, Washington D.C., the AIB

More information

MINIMUM REQUIREMENTS FOR CONSTRUCTION PLANS, GRADING AND/OR DRAINAGE PLANS, LOW IMPACT DEVELOPMENT PLANS, AND WATER EFFICIENT LANDSCAPE PLANS

MINIMUM REQUIREMENTS FOR CONSTRUCTION PLANS, GRADING AND/OR DRAINAGE PLANS, LOW IMPACT DEVELOPMENT PLANS, AND WATER EFFICIENT LANDSCAPE PLANS Planning and Community Preservation Department Public Works Department 232 West Sierra Madre Boulevard Sierra Madre, CA 91024 (626)355-7135 MINIMUM REQUIREMENTS FOR CONSTRUCTION PLANS, GRADING AND/OR DRAINAGE

More information

TOWN OF HAGUE GUIDELINES FOR PERMIT APPLICATION

TOWN OF HAGUE GUIDELINES FOR PERMIT APPLICATION TOWN OF HAGUE GUIDELINES FOR PERMIT APPLICATION Town of Hague Building Inspector: Dale Wagner Home #: 306-225-2265 Cell #: 306-241-4741 Fill all part of the permit application including the date and signature.

More information

Residential Building Permits

Residential Building Permits JWS INSPECTION SERVICE 3407-43B Avenue Lloydminster, Saskatchewan S9V-2G1Ph:780-808-5704 Email: jsydoruk@sasktel.net Residential Building Permits A residential building is a one or two unit dwelling, along

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

date: 10 july 2012 the pennsylvania state university: burrowes building

date: 10 july 2012 the pennsylvania state university: burrowes building the pennsylvania state university: burrowes building. faculty/staff committee project overview introductions goals of the renovation critical considerations exterior envelope mechanical systems interior

More information

171: An urban office designed for the southern Brazilian climate

171: An urban office designed for the southern Brazilian climate 171: An urban office designed for the southern Brazilian climate Marianne Costella Elemento 5 Bioclimatic Architecture, Brazil marianne@elemento5.com Abstract The climate in southern Brazil is characterised

More information

Bioclimatic designs for the student housing of new University of Cyprus

Bioclimatic designs for the student housing of new University of Cyprus International Workshop on Energy Performance and Environmental 1 Bioclimatic designs for the student housing of new University of Cyprus D.K. Serghides Civil Engineering, Higher Technical Institute, Nicosia,

More information

TORONTO GREEN STANDARD v3

TORONTO GREEN STANDARD v3 TORONTO GREEN STANDARD v3 AIR QUALITY ENERGY/ GHG & RESILIENCE WATER BALANCE, QUALITY AND EFFICIENCY SOLID WASTE ECOLOGY SUSTAINABILITY REQUIREMENTS FOR NEW DEVELOPMENT IN TORONTO Low-Rise Residential

More information

NARI National 2018 CotY Program Categories Please read category descriptions carefully as some criteria have changed.

NARI National 2018 CotY Program Categories Please read category descriptions carefully as some criteria have changed. Please read category descriptions carefully as some criteria have changed. New for 2018! Green and Universal Design Categories *Cost is defined as contract price, all extras, change orders and the fair

More information

EI The Following Information Should be Completed Here: Project Total Square Footage: 6,935 SF. Cost per Square Foot: $89/sf

EI The Following Information Should be Completed Here: Project Total Square Footage: 6,935 SF. Cost per Square Foot: $89/sf EI010.01 The Following Information Should be Completed Here: Project Total Square Footage: 6,935 SF Cost per Square Foot: $89/sf The uppermost floor of an office building dating to 1940 was completely

More information

SITE AND EXISTING BUILDING INFORMATION

SITE AND EXISTING BUILDING INFORMATION SITE AND EXISTING BUILDING INFORMATION Version June 1, 2011 GENERAL This competition is focused on a specific site located in the 1300 block of Oretha C. Haley Boulevard between Thalia Street and Erato

More information

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923 INITIAL YEAR BUILT 1923 BUILDING AREA 288,800 SF CURRENT PROGRAM CAPACITY 1,425 ENROLLMENT 2008 565 WARD 6 PROPOSED PROGRAM CAPACITY 1,100 Site Plan EASTERN - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

W. EDWARD BALMER SCHOOL

W. EDWARD BALMER SCHOOL W. EDWARD BALMER SCHOOL NORTHBRIDGE, MA SCHEMATIC DESIGN SCHOOL BUILDING COMMITTEE MEETING FEBRUARY 28, 2018 N O R T H B R I D G E PUBLIC SCHOOLS 1. SITE PLANNING UPDATE 2. BUILDING DESIGN UPDATE 3. MECHANICAL

More information

CHAPTER 4: ALTERNATIVES ANALYSIS

CHAPTER 4: ALTERNATIVES ANALYSIS CHAPTER 4: ALTERNATIVES ANALYSIS 4.1 Introduction and Overview According to CEQA, an EIR must describe a reasonable range of alternatives to a proposed project that could feasibly attain most of the basic

More information

Facility Improvements

Facility Improvements CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation

More information

REQUEST FOR PROPOSALS March 4, 2010 PROJECT OVERVIEW:

REQUEST FOR PROPOSALS March 4, 2010 PROJECT OVERVIEW: Police Headquarters Project REQUEST FOR PROPOSALS March 4, 2010 PROJECT OVERVIEW: General description The objective is to renovate an approximately 18 x 24 section of the two-bay attached garage at Town

More information

ST. BENEDICT ELEMENTARY SCHOOL CALGARY, ALBERTA

ST. BENEDICT ELEMENTARY SCHOOL CALGARY, ALBERTA ST. BENEDICT ELEMENTARY SCHOOL CALGARY, ALBERTA School Facility Evaluation Project Calgary Roman Catholic Separate School South Region, District #1 Prepared For Alberta Infrastructure March 2000 Prepared

More information

Drexel Hill Middle School

Drexel Hill Middle School 150004 Drexel Hill Middle School Site Plan for Drexel Hill Middle School Floor Plan for Drexel Hill Middle School 2 150004; Drexel Hill Middle School. This school is located at 3001 State Road, Drexel

More information

Collins Middle School

Collins Middle School Contents Collins Middle School...2 General comments, campus capacity, and student demographics:...2 1.0 School Site...4 2.0 Building Systems and Components...5 3.0 Building Safety and Security...19 4.0

More information

EXETER COLLEGE OXFORD

EXETER COLLEGE OXFORD EXETER COLLEGE OXFORD A New Quad at Walton Street Ruskin Building Structural Intervention Statement March 2013 18 Bowling Green Lane London EC1R 0BW Exeter College. Oxford 02.03.12 tel: 0207 253 2977 www.stockley.com

More information

East Los Angeles College Project Priority List Occupancy Date

East Los Angeles College Project Priority List Occupancy Date East Los Angeles College Project Priority List Priority Project Name Occupancy Date Notes 1 Fine Arts/Performing Arts Center 2010 11 Need NOC, DSA Cert and DSA 6 Forms for closeout in FUSION. 2 Multi Media

More information

Radical POTENTIAL!! COMFORT ZONE WHAT IS IT? WHAT DOES IT HAVE TO DO WITH GREEN BUILDING + ZERO CARBON?

Radical POTENTIAL!! COMFORT ZONE WHAT IS IT? WHAT DOES IT HAVE TO DO WITH GREEN BUILDING + ZERO CARBON? Radical POTENTIAL!! COMFORT ZONE WHAT IS IT? WHAT DOES IT HAVE TO DO WITH GREEN BUILDING + ZERO CARBON? Where is your Comfort Zone? This famous illustration is taken from Design with Climate, by Victor

More information

PRODUCER'S PRODUCE CONCEPT MASTER PLAN 501 North Main, Springfield, Missouri. Prepared for: Joe Costello and Charlie Hoke October 12, 2009

PRODUCER'S PRODUCE CONCEPT MASTER PLAN 501 North Main, Springfield, Missouri. Prepared for: Joe Costello and Charlie Hoke October 12, 2009 PRODUCER'S PRODUCE CONCEPT MASTER PLAN 501 North Main, Springfield, Missouri Prepared for: Joe Costello and Charlie Hoke Southeast Corner looking Northwest Aerial View looking Northeast 0' 8 16 32 64'

More information

NALLE ELEMENTARY SCHOOL

NALLE ELEMENTARY SCHOOL INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Edmonton Public School District No. 7

Edmonton Public School District No. 7 EXECUTIVE SUMMARY 1. Overall Impressions The 1966 non-core school has actively pursued an ongoing maintenance and upgrade program to improve a number of past problem areas within the school. Extensive

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information