Powell Substation Transformer T2 Replacement Project

Size: px
Start display at page:

Download "Powell Substation Transformer T2 Replacement Project"

Transcription

1 PAGE UTILITY ENTERPRISES 640 Haul Road Page, Arizona Powell Substation Transformer T2 Replacement Project Volume I - Bidding Documents Bid #226 Bidder s Name and Address July 2018 Intermountain Consumer Professional Engineers, Inc East South Union Avenue Midvale, Utah (801)

2 PAGE UTILITY ENTERPRISES POWELL SUBSTATION TRANSFORMER T2 REPLACEMENT PROJECT INDEX AND CERTIFICATION PAGE SPECIFICATION INDEX DOCUMENT/ DIVISION DESCRIPTION NUMBER OF PAGES INVITATION TO BID INSTRUCTIONS TO BIDDERS PROCEDURES FOR AWARD OF CONSTRUCTION CONTRACT BID FORM BID BOND QUALIFICATION STATEMENT SUBCONTRACTOR INFORMATION PROPOSED EQUIPMENT & MATERIAL DATA 2 Volume I i

3

4 SECTION INVITATION TO BID Select bids for furnishing all labor, equipment, materials and services required for the performance of the Work specified by PAGE UTILITY ENTERPRISES ( OWNER ), entitled Powell Substation Transformer T2 Replacement Project, may be mailed or hand-carried to Page Utility Enterprises, 640 Haul Road, Page, Arizona, and will be received up to and including 3:00 p.m. on August 7, Qualification of Bidders will be required. Due to the specialized nature of the construction, the experience and qualifications of Bidders will be evaluated by the OWNER. Only those Bids submitted by Bidders determined by the OWNER to be qualified shall be considered. The proposed Work is generally described as follows: Work to occur at Page Utility Enterprises 69kV to 21.6kV power distribution substation ( Powell Substation). Demolition of an existing 69kV to 21.6kV substation bay facilities including foundation removal; Construction of a transformer Pad and including oil containment, regulator pad and containment, breaker pad, and switch structure fountains; Installation of regulators, transformer connections, steel structures; installation of conduit and associated cabling system; installation of associated bus work, grounding and earthwork; and system functional testing. Electronic copies of the Bidding Documents may be obtained for bidding purposes from Page Utility Enterprises or from ( Engineer ), on or after July 9, Each set of Bidding Documents includes one (1) copies of Volume I (Bidding Documents), one (1) copy of Volume II (Contract Forms and Conditions), one (1) copy of Volume III (Specifications), one 11 X17 size copy Powell Substations Transformer T2 Replacement Project drawing set. If hard sets are required a charge for document set will be as follows: Complete set of Bidding Documents: $ Charges are not refundable; checks shall be made payable to ICPE. Bid Documents may be obtained at the following location: ICPE ATTN: Mike R. Velarde, P.E East South Union Avenue Midvale, UT Re: Powell Substation Transformer T2 Replacement Project. A mandatory prebid conference will be held on Monday July 23, 2018, at 8:30 a.m. The pre-bid conference will be held at Page Utility Enterprises Offices located at 640 Haul Road, Page, Arizona Copies of the Bid Documents are available for review at, ( ENGINEER ) 1145 East South Union Avenue, Midvale, Utah Bidders must be licensed contractors in the State of Arizona. The Bidder and Bidder s subcontractors shall provide evidence of licensure with the Bid. Bids will be received on a lump sum basis, including allowances and unit price adjustments as described in the Contract Documents. Bid Security in the amount of 5% of the Bid Price must accompany each Bid. Volume I

5 The CONTRACTOR will be required to furnish a Construction Performance Bond and a Construction Payment Bond as security for the faithful performance and the payment of all bills and obligations arising from the performance of the Contract. The CONTRACTOR will also be required to furnish a Guaranty Bond upon Substantial Completion of the Work guaranteeing all Work performed. CONTRACTOR and all Subcontractors will be required to provide insurance as set forth in the Contract Documents. CONTRACTOR will be required, as part of his proposal, a listing of similar projects (minimum three projects) the CONTRACTOR has constructed within the last two years. The list shall include, at a minimum, a description of the project, nature of work performed, total construction cost of the project, the name and phone number of the customers representative for the project, that is thoroughly familiar with the project, to be used as a reference, and Contractor s supervisor/construction foreman for the project. CONTRACTOR must have constructed at least three similar electrical substation projects in the last two years in order to be considered. CONTRACTOR must demonstrate his compliance with this provision. Failure to comply will be cause for rejection of bid. OWNER reserves the right to reject any or all Bids, including without limitation the right to reject any or all nonconforming, nonresponsive, unbalanced, or conditional Bids, and to reject the Bid or any Bidder if OWNER believes that it would not be in the best interest of OWNER to make an award to that Bidder. OWNER also reserves the right to waive informalities. Bids will be evaluated as prescribed in OWNER s Procedure for Award of Construction Contracts for the Project. END OF SECTION Volume I

6 SECTION INSTRUCTIONS TO BIDDERS 1. DEFINED TERMS. Terms used in these Instructions to Bidders shall have the meanings assigned to them in the General Conditions, Specifications and Drawings. 1.1 Additional Terms. Additional terms, not defined in the General Conditions, are defined as follows: Bid Security - A certified or cashier s check or Bid Bond accompanying the Bid in the amount of 5% of the Total Bid Price payable to the OWNER as a guarantee that the Bidder, if its Bid is accepted, will promptly execute the Agreement, and provide the necessary bonds, insurance certificates, and other required documentation. Bidder - The person, firm, or corporation submitting a Bid for the Work to be performed. Successful Bidder - The best bidder as evaluated by the OWNER pursuant to the OWNER s Procedure for Award of Construction Contracts for the Project as published in the OWNER s Bidding Documents and to whom the OWNER makes an award on the basis thereof. 1.2 Bidding Documents. Bidding Documents shall include the following: Volume I - Bidding Documents Invitation to Bid Instructions to Bidders Procedures for Award of Construction Contract Bid Form Bid Bond Qualification Statement Subcontractor Information Proposed Equipment and Material Data Volume II - Contract Forms and General Conditions Agreement Construction Performance Bond Construction Payment Bond Guaranty Bond Certificate of Insurance General Conditions Volumes III - Specifications General Requirements - Division 1 Technical Specifications - Divisions 2 through 16 Drawing Sets Powell Substation Transformer T2 Replacement Drawing Set. Addenda Issued prior to receipt of Bids 2. COPIES OF BIDDING DOCUMENTS. Complete sets of bound Bidding Documents may be obtained from the ENGINEER in the number and for the document charge stated in the Invitation to Bid. Charges are not refundable. Complete sets of Bidding Documents must be used in preparing Bids. Neither the OWNER nor ENGINEER assumes any responsibility for errors or misrepresentations resulting from the use of incomplete sets of Bidding Documents. The OWNER and ENGINEER, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use. Volume I

7 3. QUALIFICATION OF BIDDERS. The OWNER has advertised for bids from qualified construction contractors for the construction of electrical substation facilities. OWNER will consider the qualifications of Bidders and consider Bids pursuant to the selection methodology set forth in Procedures for Award of Construction Contracts (Section 00200). 4. ARIZONA LICENSE REQUIREMENTS. Bidder must be appropriately licensed in the State of Arizona. In the event of joint ventures, each venture partner must be licensed, and unless each joint venturer has an unlimited license, the joint venture must have an additional license for acting in the capacity of such joint venture. The Bidder and Bidder s subcontractors shall provide evidence of licensure with the Bid. The Contract may be awarded to another Bidder if the person to whom the Bid was awarded is not licensed or if the amount of the Bid exceeds the limits of the Bidder s license. If, for any reason, the person to whom the Bid is awarded does not execute the Contract, the OWNER reserves the right to award or re-award the Contract without rebidding. The OWNER reserves the right, without liability to the OWNER, to cancel the award, or any proposal, at any time before the execution of the Contract by all parties. 5. EXAMINATION OF CONTRACT DOCUMENTS AND SITE. It is the responsibility of each Bidder, before submitting a Bid, to: (a) thoroughly examine the Contract Documents and all requirements therein; (b) visit the Site to become familiar with local conditions that may affect cost, progress, performance, or furnishing of the Work; (c) consider federal, state, and local laws and regulations that may affect cost, progress, performance, or furnishing of the Work; (d) study and carefully correlate Bidder s observations with the Contract Documents; and (e) promptly notify the ENGINEER of all conflicts, errors, or discrepancies discovered by Bidder in the Contract Documents. Submission of a Bid shall be conclusive evidence that the Bidder has complied with the requirements of the preceding sentence. 5.1 Underground Facilities. Information and data reflected in the Contract Documents with respect to underground facilities at or contiguous to the Site are based upon information and data furnished to OWNER and ENGINEER by owners of such underground facilities or others, and OWNER and ENGINEER disclaim responsibility for the accuracy or completeness thereof unless it is expressly provided otherwise in these Contract Documents. 5.2 Easements. The lands upon which the Work is to be performed, rights-of-way and easements for access thereto, and other lands designated for use by CONTRACTOR in performing the Work are identified in the Contract Documents. All additional lands and access thereto required for temporary construction facilities or storage of materials and equipment are to be provided by CONTRACTOR. 5.3 Bidder s Representation. The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement concerning examination of the Contract Documents and the Site, that without exception the Bid is premised upon performing and furnishing the Work required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. 6. INTERPRETATIONS AND ADDENDA. All questions about the meaning or intent of the Bidding Documents and the Contract Documents shall be submitted to ENGINEER in writing. Interpretations or clarifications considered necessary by ENGINEER in response to such questions will be issued by Addenda mailed or delivered to all parties recorded by ENGINEER as having received the Bidding Documents. Questions received less than 3 days prior to the date for opening of Bids may not be answered. Only answers issued by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. 7. MANDATORY PREBID CONFERENCE. A mandatory prebid conference will be held at 8:30 a.m., local time, on Monday July 23, Attendance is mandatory for prospective Bidders bidding as prime contractors. Prebid conference will be held at the following location: Page Utility Enterprises 640 Haul Road Page, Arizona A conducted tour of the Project Sites will follow. Approximate substation address: Page, Arizona Volume I

8 8. BIDDING DOCUMENTS. 8.1 Bid Form. The Bid Form is bound in the Bidding Documents and shall not be removed therefrom. The Bid must be completed in ink Bids by corporations must be executed in the corporate name by the president or vicepresident (or other corporate officer accompanied by evidence of authority to sign for the corporation). Bids by partnerships must be executed in the partnership name and signed by a partner. Bids by joint ventures shall be signed by each participant in the joint venture or by a representative of the joint venture accompanied by evidence of authority to sign for the joint venture The names of all persons signing shall be legibly printed below their signatures. A Bid by a person who affixes to his signature the word president, secretary, agent, or other designation without disclosing his principal may be held to be the Bid of the individual signing. When requested by the OWNER, evidence of the authority of the person signing shall be furnished All blanks in the Bid Form shall be filled. A Bid price shall be indicated for each Bid item, allowance item, and adjustment unit price listed therein. The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers and dates of which shall be filled in on the Bid Form No alteration in Bids, or in the printed forms therefor, by erasures, interpolations, or otherwise will be acceptable. 8.2 Bid Pricing. The lump sum amount shall be based on the Work as indicated on the Drawings and as specified. The evaluated price and Award Contract Price will equal the Total Extended Price. The Contract Price subject to the Extended Price limitations, will be adjusted according to final delivered and installed construction units quantities. The adjustment unit prices in the Bid will apply to such final quantities. 8.3 Subcontractors, Suppliers, and Others Each Bidder shall provide, on the form bound in the Bidding Documents entitled Subcontractor Information, the name of each Subcontractor who will provide labor for the portion of the Work indicated, the percentage of the Total Bid anticipated to be paid each Subcontractor, and the Arizona license number of each Subcontractor named The Bidder shall provide an experience statement of Subcontractor(s) with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, supplier, person or organization If the OWNER, after due investigation, has reasonable objection to any proposed Subcontractor, supplier, or other person or organization, the OWNER may, before the Notice of Award is given, request the apparent Successful Bidder to submit an acceptable substitute without an increase in the Bid. If the apparent Successful Bidder declines to make any such substitution, the OWNER may award the Contract to the next best Bidder, in the OWNER s judgment, that proposes to use acceptable Subcontractors, suppliers, and other persons and organizations. Declining to make requested substitutions will not constitute grounds for sacrificing the Bid Security of any Bidder. Any Subcontractor, supplier, or other person or organization listed and to whom the OWNER does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to the OWNER, subject to revocation as provided in paragraph of the General Conditions A Contractor whose Bid is accepted shall not substitute any person for a Subcontractor who is named in the Bid unless: (i) the OWNER objects to the Subcontractor, requests in writing a change in the Subcontractor and pays any increase in cost resulting from the change; or (ii) The substitution is approved by the OWNER and: (1) The Subcontractor, after having a reasonable opportunity, fails or refuses to execute a written subcontract which was offered to the Volume I

9 Subcontractor with the same terms that all other Subcontractors on the Project were offered; (2) The named Subcontractor files bankruptcy or becomes insolvent; or (3) The named Subcontractor fails or refuses to perform his subcontract within a reasonable time or is unable to furnish a performance bond and payment bond. A CONTRACTOR whose Bid is accepted shall not contract with any Subcontractor not listed in its Subcontractor Information forms to perform the Work indicated, without the written approval of the OWNER. 8.4 Bid Preference. In accordance with the Procedure for Award of Construction Contracts for the Project (Section 00200), the OWNER shall award the Contract to the qualified Bidder who submits the best Bid. 8.5 Bid Security. Each Bid must be accompanied by a security made payable without condition to the OWNER in an amount of five percent (5%) of the Bidder s maximum Bid and in the form of a Bid Bond issued by a surety meeting the requirements set forth in the General Conditions. The Bid Bond shall be submitted using a form in substantial compliance with the form provided in the Bidding Documents. The Bid Security of the Successful Bidder will be retained until such Bidder has executed the Agreement, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the Bid Security will be returned. If the Successful Bidder fails to execute and deliver the Agreement and to furnish the required Contract security within the number of days set forth in the Bid Form, the OWNER may annul the Notice of Award and the Bid Security of that Bidder will be forfeited. The Bid Security of other Bidders whom the OWNER believes to have a reasonable chance of receiving the award may be retained by the OWNER until the earlier of 14 days after the effective date of the Agreement or the day after the last day the Bids remain subject to acceptance as set forth in the Bid Form, whereupon Bid Securities furnished by such Bidders will be returned. Bid Security accompanying bids which are deemed by the OWNER to be noncompetitive will be returned within 14 days after the Bid opening. 9. SUBMISSION OF BIDS. Bids shall be submitted at the time and place indicated in the Invitation to Bid, or at the modified time and place indicated by Addendum. Bids shall be enclosed in the envelope provided with the Bidding Documents and sealed. The Bidder shall submit one (1) duplicate copy of the bound Volume I, Bidding Documents, and other documents, as required, in an envelope marked Page Utility Enterprises - Powell Substations T2 Replacement Project - Bidding Documents. Volumes II, III, and drawing sets, of the Bidding Documents are not to be submitted with the Bid. Bid envelope and Bid Documents shall be marked with the name and address of the Bidder. If the Bid is sent through the mail or other delivery system, the sealed Bid envelope shall be enclosed in a separate envelope with the notation Page Utility Enterprises - Powell Substations T2 replacement Project - BID ENCLOSED on the face and addressed to: Phil Faulk, Project Manager Page Utility Enterprises 640 Haul Road Page, Arizona Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids. Bids received after the time and date identified in the Invitation to Bid shall be returned unopened. It is noted that Next Day Delivery generally requires two days for delivery. No Bidder may submit more than one Bid. Multiple Bids under different names will not be accepted from one firm or association. Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids and prequalification documents. Bids received after the time and date identified in the Invitation to Bid shall be returned unopened. 10. MODIFICATION AND WITHDRAWAL OF BIDS. Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a Bid must be executed) and delivered to the place where Volume I

10 Bids are to be submitted at any time prior to the opening of Bids. After the Bid opening, Bids may not be modified for any reason. If, within 48 hours after Bids are opened, any Bidder files a duly signed, written notice with OWNER and promptly thereafter demonstrates to the reasonable satisfaction of OWNER that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid and the Bid Security will be returned. Thereafter, that Bidder will be disqualified from further bidding on the Work to be provided under the Contract Documents. 11. BIDS TO REMAIN SUBJECT TO ACCEPTANCE. All Bids shall remain subject to acceptance for the number of days set forth in the Bid Form, but the OWNER may, in its sole discretion, release any Bid and return the Bid Security prior to that date. 12. OPENING OF BIDS. At the location, date, and time indicated in the Invitation to Bid, the OWNER will Publicly open the Bids. Pursuant to OWNER s Procedure for Award of Construction Contracts (Section 00200), the OWNER and ENGINEER shall consider the Bids. The OWNER may conduct such investigations as the OWNER deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, and other persons and organizations to perform and furnish the Work in accordance with the Contract Documents to OWNER s satisfaction within the prescribed time. The initial Work Plan submitted with the Bids will be reviewed by the OWNER and ENGINEER to determine the Bidder s comprehension of the Work and the Bidder s experience and expertise in the construction of electrical substation facilities. The methods described in Work Plan will also be reviewed for conformance with the Specifications. The OWNER and ENGINEER may consider the qualifications and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other persons and organizations must be submitted as provided in the Contract Documents. The OWNER and ENGINEER also may consider the technical proposal of the Bidder, including the operating costs, maintenance requirements, performance data, and guarantees of items of materials and equipment proposed for incorporation in the Work when such data are required. The OWNER and ENGINEER will then determine the best bid of the prequalified Bidders pursuant to the Procedure for Award of Construction Contracts adopted for the Project. 13. AWARD OF CONTRACT. Pursuant to the OWNER s Procedure for Award of Construction Contract, the OWNER reserves the right to reject any or all Bids, including without limitation the rights to reject any or all nonconforming, nonresponsive, unbalanced, or conditional Bids, and to reject the Bid of any Bidder if the OWNER believes that is would not be in the best interest of the OWNER to make an award to that Bidder. The OWNER also reserves the right to waive informalities. 14. SUBSTITUTE OR OR-EQUAL ITEMS. The procedure for submission of any application for review of substitute or or-equal items by CONTRACTOR and consideration by ENGINEER is set forth in Paragraph 6.8 of the General Conditions (Volume II). The Contract, if awarded, will be on the basis of materials and equipment indicated on the Drawings or specified in the Specifications. Application for review of substitute or or-equal materials or equipment will not be considered by ENGINEER until after the effective date of the Agreement. Proposed substitute and or-equal items will be considered. 15. SIGNING OF AGREEMENT. When OWNER issues a Notice of Award to the Successful Bidder, Within the number of days set forth in the Bid Form, the Successful Bidder shall sign three (3) copies of the Agreement, leaving the dates blank, insert the required Bonds and power of attorney in the appropriate places and deliver all copies of Volume II to the OWNER. OWNER will, thereafter, execute all copies of the Agreement and other Contract Documents submitted by CONTRACTOR (Successful Bidder) and shall insert the date of contract on the Agreement, Bonds, and power of attorney. OWNER will provide the executed Contract Documents for binding and distribution. Distribution of executed copies shall be as stipulated in the Contract Documents. Executed Contract Documents will be accompanied by a complete set of the Drawings, with appropriate identification. If the Volume I

11 Successful Bidder fails to comply with the requirements of this section, the OWNER may nullify its award of the Contract and thereafter accept the Bid of another Bidder. 16. PERMITS. The Bid Price shall include the cost of all required permits and the cost of all measures required to comply with all permit requirements. CONTRACTOR shall obtain and include in the Bid Price the cost of all other permits which are required for the Work. 17. TAXES. All taxes that are lawfully assessed against the OWNER or CONTRACTOR in connection with the Work shall be paid by CONTRACTOR. The Bid Price shall include all such taxes. 18. CONTRACT SECURITY. The CONTRACTOR s Performance and Payment Bonds shall be delivered to the OWNER with the executed Agreement. 19. RETAINAGE. Provisions concerning retainage are set forth in the General Conditions. 20. WORK PLAN. Bidder shall submit a full description of its initial Work Plan with the Bid. If any method does not meet the requirements of this Specification, the Bid may be held to be unresponsive and may be rejected. Descriptions of proposed methods shall be complete and detailed enough to demonstrate full conformance with the Specifications. The methods described in the Work Plan shall not be modified during construction except as authorized by OWNER. 21. EXTENDED WORK WEEK. In General, the Contractor will be allowed to work 12hr days, Seven days a week provided that qualified supervision is present at all times. Work to continue after normal Page Utility Enterprises business hours are to be scheduled in advance. Work involving switching procedures must be scheduled a week in advance. At no additional cost to the owner, the OWNER may require a mandatory 6 day workweek as directed by the OWNER for work activities which are behind schedule and are on the critical path of job completion. 22. COMMUNICATIONS. Prior to opening Bids, all communications relative to the Work shall be directed to the ENGINEER via . The ENGINEER will review communications and issue Addenda if appropriate. The ENGINEER will not provide any formal interpretation of the Bidding Documents other than via addenda. Address communications to: ICPE ATTN: Mike R. Velarde, P.E East South Union Avenue Midvale, UT SCHEDULE MILESTONE AND LIQUIDATED DAMAGES. Schedule milestones and liquidated damages are required by Article of the General Conditions (Section 00700). 24. GUARANTY BOND. The CONTRACTOR will be required to submit a Guaranty Bond, in the amount of five percent (5%) of the final Contract Price, after completion of the Project which warrants the Work for a period of one year after final acceptance of the Work. The cost of this Guaranty Bond shall be included in the CONTRACTOR s Bid. END OF SECTION Volume I

12 SECTION PROCEDURE FOR AWARD OF CONSTRUCTION CONTRACT FOR THE POWELL SUBSTATION TRANSFORMER T2 REPLACEMENT PROJECT Page Utility Enterprises intends to utilize the following procedures for award of the construction contract for construction of its Powell Substation Transformer T2 Replacement Project. 1. The phrase construct... any facility for... power, including... a facility for the... transformation of electricity shall include the erection or installation, at grade, above or below ground, of a) electrical transformation equipment including major power transformers, power circuit breakers, substation steel, and all related components; b) distribution transformers, distribution breakers, distribution cabling and all associated components; and d) all other components and equipment necessary to construct and complete an operational and fully functioning electrical substation. 2. Upon receipt of bids, the OWNER and ENGINEER shall consider the bids. The OWNER or ENGINEER may meet with any bidder in order to ensure that the OWNER understands each bid. 3. The OWNER s Representative or ENGINEER shall recommend the best bid to the OWNER for consideration. The best bid shall be that bid which, in the opinion of the OWNER: (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) proposes the construction of the Project, or any part thereof, in a manner which meets the design specifications provided by the OWNER and the contract requirements provided by the bid specifications; proposes the construction of the Project, or any part thereof, in a timely manner so as to ensure the completion of the Project. proposes contract prices, either in lump sum or per item as specified in the OWNER s design specifications, which are competitively priced in the market place; provides the most certain and stable quality assurance; provides the most substantial fiscal accountability and performance guarantee in the event of the construction contractor s failure to perform as contracted; demonstrates the construction contractor s general ability to provide substantial post-construction support to the OWNER in the operation of its electrical substation facilities; demonstrates that the construction contractor is experienced in constructing electrical substation facilities of the nature intended to be constructed by the OWNER. demonstrates that the construction contractor is knowledgeable about the engineering, manufacture, assembly, testing and shipping or other ancillary services related to the delivery of major electrical equipment; demonstrates that the construction contractor has experience in the construction of electrical substation facilities in climatological, topographic and geological situations similar to those within which the OWNER intends to construct electric substation facilities (at grade, above or below ground as the case may be); demonstrates that the construction contractor s subcontractors, suppliers, and other persons and organizations proposed for various portions of the work are qualified and experienced; demonstrates that the construction contractor has satisfied other owners with the quality and timeliness of its work. None of the above-listed criteria shall be an exclusive determinant of the best bid. The lowest bid shall be the best bid when all non-cost criteria are equal. 4. Any or all of the bids received may be rejected by the OWNER if it is determined that: (a) the bidder is not responsive or responsible; Volume I

13 (b) (c) the apparent quality of the services, materials, equipment or labor offered does not conform to the approved plan or specifications; or the OWNER s interest would be served by such a rejection. 5. Any contract for the construction of electrical substation facilities shall require that the contractor provide a) a performance bond in an amount of 100% of the contract amount, conditioned upon the faithful performance of the contract in accordance with its terms and exclusively for the protection of the OWNER; and b) a payment bond in an amount not less than 100% of the contract amount, for the protection of claimants supplying labor or materials to the contractor or to any of his subcontractors, in the construction of electrical substation facilities for the OWNER. The performance bond and payment bond shall be issued by a surety company authorized to do business in the State of Arizona. END OF SECTION Volume I

14 SECTION BID FORM PROJECT IDENTIFICATION: PAGE UTILITY ENTERPRISES POWELL SUBSTATION T2 REPLACEMENT PROJECT THIS BID IS SUBMITTED BY: (Bidder) (Bidder Address) THIS BID IS SUBMITTED TO: Page Utility Enterprises 640 Haul Road Page, AZ The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with OWNER in the form included in the Contract Documents to perform and furnish all Work as specified or indicated in the Contract Documents within the specified time and for the amount indicated in the Bid and in accordance with the other terms and conditions of the Contract Documents. 2. Bidder accepts all of the terms and conditions of the Invitation to Bid and the Instructions to Bidders, including without limitation those dealing with the disposition of Bid Security. This Bid will remain subject to acceptance for 45 days after the day of Bid opening. Bidder will sign and submit the Agreement with the Bonds and other documents required by the Bidding Documents within 10 days after the date of OWNER s Notice of Award. 3. In submitting this Bid, Bidder represents that: (a) Bidder has examined copies of all the Bidding Documents and of the following Addenda (receipt of all which is hereby acknowledged): No. No. No. No. Dated Dated Dated Dated (b) (c) (d) Bidder has visited the Site and become familiar with and satisfied itself as to the general local, Site, and labor and working conditions that may affect cost, progress, performance, and furnishing of the Work. Bidder is familiar with, has satisfied itself as to all, and agrees to comply with Federal, State, and local Laws and Regulations and Permits that may affect cost, progress, performance, and furnishing of the Work Bidder is aware of the general nature of Work to be performed by OWNER and others at the Site that relates to Work for which this Bid is submitted as indicated in the Contract Documents. Volume I

15 (e) (f) (g) (h) (i) Bidder has correlated the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the contract Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Contract Documents. Bidder has given ENGINEER written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to bidder, and the Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work for which this Bid is submitted. This Bid is genuine and not made in the interest of or on behalf of any undisclosed person, firm, or corporation and is not submitted in conformity with any agreement or rules of any group, associated, organization, or corporation, Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; Bidder has not solicited or induced any person, firm, or corporation to refrain from bidding; and Bidder has not sought by collusion to obtain for itself any advantage over any other bidder or over OWNER. Bidder is aware of the warranty provisions of the Contract and will guaranty the Work, if awarded the Contract, for the time required in the Contract Documents. Bidder is familiar with and has satisfied itself as to licensing requirements and Bidder licensing limits in accordance with the State of Utah regulatory requirements. (j) Bidder hereby acknowledges that the Work Plan submittals are enclosed with this Bid (Volume I) as described herein. 4. CONTRACT UNITS AND PRICES Description of Construction Units. To aid in identification of the work and in the pricing of the work, the construction is divided into various groups of construction units. Each Construction Unit consists of a complete installation of the designated portion of the substation as specified on the drawings together with connections to associated equipment. Each construction unit represents all labor and material including necessary accessories completely installed and tested in satisfactorily operation. Full identification of each Construction Unit and all necessary specifications of the installation shall be shown on the drawings. The Bidder shall have the cost for the complete construction of the substation distributed among the appropriate listed Construction Units. Should some item of work required for the complete construction of the substation be apparently omitted from the Construction Units, the Bidder shall notify the Owner prior to submittal of Proposal for clarification. Without such notification, such apparently omitted work required for the complete construction of the substation shall be taken as included within the nearest appropriate Unit. Each Construction Unit shall be designated by the letter of the Group to which it belongs and identifying number. The bid sheet shall be prepared for the substation and shall contain all unit prices for Construction Units contained in the substation. It is intended that in all cases the "Name and Description of Construction Unit" column of the Bid Sheets shall contain sufficient information to identify the Construction Unit. Additional description to one or more of the Groups may be provided by the Engineer if deemed necessary to clarify the intent of these Specifications for Construction. A. Structures. A Construction Unit consists of a structure, or structures, with bus supports including insulators, arrestors, fittings, grounding material to connect equipment with the ground bus, and associated material including mounting brackets, supports for equipment, clamps and connectors, all as specified in the drawings. Work includes all verification and modifications as outlines in the drawings and specifications B. Three-Pole Group operated Air Break Switches. A Construction Unit consists of on 3-pole group operated air break switch with all accessories and operating mechanisms as specified in the drawings. Contractor to complete installation and adjustment for all switches. C. Bus Work. A construction Unit consists of all required 69 kv and 21.6kV bus work (rigid and flex) complete with supporting brackets and vibration dampening where appropriate. Work to include verification and installation of all existing and new bus work. Volume I

16 D. Voltage Regulators. This Construction Unit included the work required for installation of three (3) one phase 14.4 kv voltage regulators including associated by-pass switches. E. Relay Panel Relay Panel Construction Unit consists of wiring changes within existing panel PWT2. F. Foundations. A Construction Unit consists of concrete footing and foundations as specified in the drawings. G. Station Service. A Construction Unit consists of the installation/relocation of yard lighting. H. Power Transformers. A Construction Unit consists of interconnection of one 69kV-21.6kV three phase power transformer as specified in the drawings. I. Station Grounding. A Construction Unit consists of the complete ground bus including ground rods, grounding mats or platforms, excepts as otherwise provided in other groups, with connection to structures, equipment, and fence as specified in the drawings. J. Conduit and Cable. A Construction Unit consists of the wire, cable, conduit, and accessories necessary to complete the installation of equipment in accordance with the specification and the drawings. K. Demolition Units. A Construction Unit consists of the cost for demolition of existing facilities as indicated in the project drawings. L. Site Work. A Construction Unit consists of clearing, grading, drainage work, and surfacing, as specified in the drawings. M. Functional Checkout and Testing. A Construction Unit consists of functional checkout and testing of metering/relay controls, relay, field wires, etc. and as described in the functional Checkout and Testing Section of this specification. N. Mobilization/Demobilization/ Material Management. A Construction Unit consists of the cost for project mobilization and demobilization and material management which includes receiving and storing all project material (owner and contractor furnished) and the cost to prepare and operate the storage yard. O. Bonds and Insurance. A Construction Unit consists of the cost for bonds, insurance, and permits. Volume I

17 UNIT NO. GROUP A STRUCTURES PAGE UTILITY ENTERPRISES POWELL SUBSTATION TRANSFORMER T2 REPLACEMENT NAME AND DESCRIPTION OF CONSTRUCTION UNIT NO. OF UNITS A1 69kV LOW BUS SUPPORT STRUCTURE (PS01) 1 A2 21.6kV TRANSFORMER BUS SUPPORT STRUCTURE (PS03) 1 A3 VOLTAGE REGULATOR BYPASS STRUCTURE (PS04) 1 A4 BREAKER OPERATING PLATFORM 1 A5 69kV HIGH SWITCH STRUCTURE 1 GROUP B THREE POLE GROUP OPERATED AIR BREAK SWITCH B1 69 kv GROUP OPERATED AIR BREAK SWITCH AND STRUCTURE REMOVAL AND REINSTALLATION 1 GROUP C BUS WORK C1 69 kv and 21.6 kv BUS WORK LOT LABOR UNIT PRICE CONTRACTOR FURNISHED MATERIAL TOTAL LABOR AND MATERIALS TOTAL GROUP A TOTAL GROUP B EXTENDED PRICE LABOR AND MATERIAL GROUP D VOLATGE REGULATORS D1 866 kva REGULATORS 3 D2 1200A BYPASS SWITCHES 3 TOTAL GROUP C GROUP E RELAY PANELS E1 RELAY/CONTROL PANEL LOT TOTAL GROUP D TOTAL GROUP E Volume I

18 UNIT NO. PAGE UTILITY ENTERPRISES POWELL SUBSTATION TRANSFORMER T2 REPLACEMENT NAME AND DESCRIPTION OF CONSTRUCTION UNIT NO. OF UNITS GROUP F FOUNDATIONS F1 TRANSFORMER PAD and CONTAINMENT LOT F2 REGULATORS PAD & CONTAINMENT LOT F3 69kV BREAKER PAD 1 F4 SWITCH STRUCTURE PIERS 2 GROUP G STATION SERVICE G1 YARD LIGHT LOT LABOR UNIT PRICE CONTRACTOR FURNISHED MATERIAL TOTAL LABOR AND MATERIALS TOTAL GROUP F EXTENDED PRICE LABOR AND MATERIAL GROUP H TRANSFORMER H1 POWER TRANSFORMER, THREE-PHASE, kv, 15/20/25 MVA 1 TOTAL GROUP G GROUP I STATION GROUNDING I1 GROUND CONDUCTOR LOT I2 BELOW GRADE GROUND CONNECTIONS LOT I3 STEEL STRUCTURE GROUNDING LOT I4 SWITCH HANDLE GROUNDING LOT I5 TRANSFORMER GROUNDING LOT I6 BREAKER GROUNDING LOT I7 PLATFORM GROUNDING LOT TOTAL GROUP H TOTAL GROUP I Volume I

19 UNIT NO. PAGE UTILITY ENTERPRISES POWELL SUBSTATION TRANSFORMER T2 REPLACEMENT NAME AND DESCRIPTION OF CONSTRUCTION UNIT GROUP J CONDUIT AND CABLE NO. OF UNITS J1 600 V CLASS CONDUIT SYSTEM AND FITTINGS (OUTDOORS) LOT J2 600 V CLASS CONDUIT SYSTEM AND FITTINGS (CONTROL BUILDING) LOT J3 CABLE, #12, XHHW LOT J4 CABLE,#10 XHHW LOT J5 INSTALL 600 VOLT CLASS, CONTROL BUILDING WIRING LOT J6 INSTALL 600 VOLT CLASS CABLE AND WIRE CONNECTIONS TO EQUIPMENT IN THE SUBSTATION YARD LOT LABOR UNIT PRICE CONTRACTOR FURNISHED MATERIAL TOTAL LABOR AND MATERIALS EXTENDED PRICE LABOR AND MATERIAL TOTAL GROUP J GROUP K DEMOLITION K1 TRANSFORMER FOUNDATION REMOVAL LOT K2 REGULATOR PAD AND STRUCTURE FOUNDATION REMOVAL LOT K3 CIRCUIT SWITCHER, STRUCTURE AND FOUNDATION REMOVAL LOT K4 SIWTCH, STRUCTURE AND FOUNDATION REMOVAL LOT K5 CONTROL CABLE REMOVAL LOT K6 TOTAL GROUP K GROUP L SITE WORK L1 ROADS AND DRIVABLE AREAS REFINISH LOT L2 SURFACE GRAVEL REFINISH LOT L4 SPOILS DISPOSAL LOT TOTAL GROUP L Volume I

20 UNIT NO. PAGE UTILITY ENTERPRISES POWELL SUBSTATION TRANSFORMER T2 REPLACEMENT NAME AND DESCRIPTION OF CONSTRUCTION UNIT GROUP M FUNCTIONAL CHECKOUT AND TESTING M1 EQUIPMENT FIELD TESTING AND SYSTEM FUNCTIONAL CHECK OUT NO. OF UNITS LOT LABOR UNIT PRICE CONTRACTOR FURNISHED MATERIAL TOTAL LABOR AND MATERIALS EXTENDED PRICE LABOR AND MATERIAL GROUP N MOBILIZATION/DEMOBILIZATION COSTS N1 MOBILIZATION/DEMOBILIZATION LOT TOTAL GROUP M GROUP O BONDING AND INSURANCE O1 BONDING AND INSURANCE LOT TOTAL GROUP N TOTAL GROUP O TOTAL ALL GROUPS (A - O) Volume I

21 BID SUMMARY SLAVENS SUBSTATION T1 REPLACEMENT PROJECT LABOR ($) MATERIALS ($) TOTAL LABOR AND MATERIALS ($) Group A: Structures Group B: Three Pole Group Operated Air Break Switches Group C: Bus Work Group D: Voltage Regulators Group E: Relay/Control Panels Group F: Foundations Group G: Station Service Group H: Power Transformer Group I: Station Grounding Group J: Conduit and Cable Group K: Demolition Group L: Site Work Group M: Functional Checkout and Testing Group N: Mobilization/Demobilization Group O: Bonding And Insurance Group P: Other 1. TOTAL BASE BID 2. Value of Owner Furnished Materials (OFM) 3. TOTAL VALUE OF CONTRACTOR'S BOND BASE BID Page Utility Enterprises: Powell Substation 2 Replacement Project Volume I

22 1. Bidder agrees that the Work will be substantially completed by the dates or durations listed and completed and ready for final payment in accordance with Paragraph of the General Conditions. 2. Communications concerning this Bid shall be sent to Bidder at the following address, telephone and address. Phone No The terms used in this Bid, which are defined in the General Conditions included as part of the Contract Documents, have the meanings assigned to them in the General Conditions. Bidders Name Arizona Contractor s License Number License Expiration Date License Limit If a Corporation By: By: (Corporation Name) (Signature of Authorized Person) (Title) Business address: State of Incorporation: If a Joint Venture By: By: (Joint Venture Name) (Signature of Authorized Person) Business address: (Title) Submitted On:, 2014 END OF SECTION Page Utility Enterprises: Powell Substation 2 Replacement Project Volume I

23 SECTION BID BOND FORM BIDDER (Name and Address): SURETY (Name and Address of Principal Place of Business): OWNER (Name and Address): Page Utility Enterprises 640 Haul Road Page, Arizona BID: BID DUE DATE: PROJECT (Brief Description Including Location): Powell Substations Transformer T2 Replacement Project Page, Arizona BOND: BOND NUMBER: DATE: (Not later than Bid Due Date): PENAL SUM: IN WITNESS WHEREOF, Surety and Bidder, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause this Bid Bond to be duly executed on its behalf by its authorized officer, agent or representative. BIDDER (Seal) Bidder s Name and Corporate Seal By: Signature and Title Attest: Signature and Title SURETY (Seal) Surety s Name and Corporate Seal By: Signature and Title (Attach Power of Attorney) Attest: Signature and Title NOTE: (1) Above addresses are to be used for giving required notice. (2) Any singular reference to Bidder, Surety, Owner or other party shall be considered plural where applicable. Volume I

24 1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. 2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the bidding Documents and Contract Documents. 3. This obligation shall be null and void if: 3.1 Owner accepts Bidder s bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents and Contract Documents, or 3.2 All bids are rejected by Owner, or 3.3 Owner fails to issue a notice of award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by paragraph 5 hereof). 4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due. 5. Surety waives notice of and any and all defenses based on or arising out of any time extension to issue notice of ward agreed to in writing by Owner and Bidder, provided that the time for issuing notice of award including extensions shall not in the aggregate exceed 120 days from Bid Due Date without Surety s written consent. 6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety, and in no case later than one year after Bid Due Date. 7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located. 8. Notice required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned. 9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent or representative who executed this Bond on behalf of Surety to execute, seal and deliver such Bond and bind the Surety thereby. 10. This Bond is intended to conform to all Applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of the Bond conflicts with any applicable provision of any applicable statute, then the provision of said statute shall govern and the remainder to this Bond that is not conflict therewith shall continue in full force and effect. 11. The term bid as used herein includes a bid, offer or proposal as applicable. Volume I

25 SECTION QUALIFICATION STATEMENT PART 1 - GENERAL 1.1 SUMMARY: A. This Section provides information on Bidder s organization, condition, experience, qualifications and references. This information may be used in the consideration of the Bids. 1.2 QUALIFICATION STATEMENT: A. Bidder Identification: Company Name: Company Address: Arizona Contractor s License No. and Classification: Principal Party for this Proposal (signature): Name (printed): Title: Phone: Fax: B. Company Background: Main Office Location: Years in this business: Type of Organization: C. Financial: Have you submitted a valid bid bond? Is a financial statement available and enclosed with the Bidding Documents? D. Similar Project Experience: Provide list of projects completed by your organization for other owners with similar work, magnitude, costs, time period, successful completion schedule and complexity. This list is attached and identified as: Volume I

Powell Substation Control Panels Replacement Project

Powell Substation Control Panels Replacement Project PAGE UTILITY ENTERPRISES 640 Haul Road Page, Arizona 86040 Powell Substation Control Panels Replacement Project Volume I - Bidding Documents Bid #206 Bidder s Name and Address May 2016 Intermountain Consumer

More information

Powell Substation 21.6kV Switching Modification Project

Powell Substation 21.6kV Switching Modification Project PAGE UTILITY ENTERPRISES 640 Haul Road Page, Arizona 86040 Powell Substation 21.6kV Switching Modification Project Volume I - Bidding Documents Bid #207 Bidder s Name and Address October 2016 Intermountain

More information

Specifications. For. Shermco Project Panora Substation Construction. Panora Municipal Electric Panora, Iowa. April 21, 2017 BID ISSUE

Specifications. For. Shermco Project Panora Substation Construction. Panora Municipal Electric Panora, Iowa. April 21, 2017 BID ISSUE Specifications For Shermco Project 91000154 Panora Substation Construction Panora Municipal Electric Panora, Iowa April 21, 2017 BID ISSUE Prepared Under Direction of: Michael Thorson Shermco Industries

More information

TABLE OF CONTENTS. INVITATION TO BID thru INSTRUCTIONS TO BIDDERS thru

TABLE OF CONTENTS. INVITATION TO BID thru INSTRUCTIONS TO BIDDERS thru TABLE OF CONTENTS PAGE INVITATION TO BID...00050-1 thru 00050-2 INSTRUCTIONS TO BIDDERS...00200-1 thru 00200-9 BID FORM...00400-1 thru 00400-8 Attachments: Bid Bond (EJCDC Form C-430)...00400.A-1 thru

More information

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue Bidding Conditions March 22, 2018 (Project# 0192) at the Fresno Chaffee Zoo Project : Warthog Exhibit Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS Addendum - A document issued

More information

Bidding Conditions Attachment C

Bidding Conditions Attachment C Bidding Conditions Attachment C REV Date: November 9, 2018 Project Name (Permit Nos. xxx) at the Fresno Chaffee Zoo Project No. xxxx Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS

More information

Mabton Canal Improvement Project MP Reservoir

Mabton Canal Improvement Project MP Reservoir 100% Submittal Mabton Canal Improvement Project MP 12.48 Reservoir Specifications Prepared By Sunnyside Valley Irrigation District 120 South 11th Street Sunnyside, WA 98944 June 2010 BIDDING REQUIREMENTS

More information

SPECIFICATIONS FOR SIDEWALK REPLACEMENT PROGRAM

SPECIFICATIONS FOR SIDEWALK REPLACEMENT PROGRAM SPECIFICATIONS FOR SIDEWALK REPLACEMENT PROGRAM CITY OF GALENA 101 GREEN STREET GALENA, IL 61036 MAY 2016 Project must be completed between 5 th and 30 th September 2016 CONTENTS Page # ADVERTISEMENT FOR

More information

CITY OF DE PERE PROJECT VOYAGEUR PARK PLAYGROUND BID DATE: FEBRUARY 1, 1:00 PM

CITY OF DE PERE PROJECT VOYAGEUR PARK PLAYGROUND BID DATE: FEBRUARY 1, 1:00 PM CITY OF DE PERE PROJECT 18-12 VOYAGEUR PARK PLAYGROUND BID DATE: FEBRUARY 1, 2018 @ 1:00 PM Bid documents, including plans and specifications, are available for download at www.questcdn.com. The QuestCDN

More information

DOCUMENT BID FORM. Village of Middle Point

DOCUMENT BID FORM. Village of Middle Point DOCUMENT 00300 BID FORM PROJECT IDENTIFICATION: Water Treatment Plant Replacement Village of Middle Point THIS BID IS SUBMITTED TO: Village of Middle Point 103 N. Adams Street Middle Point, OH 45863-0191

More information

CITY OF DE PERE PROJECT HVAC MAINTENANCE RE-BID BID DATE: MAY 5, 1:00 PM

CITY OF DE PERE PROJECT HVAC MAINTENANCE RE-BID BID DATE: MAY 5, 1:00 PM CITY OF DE PERE PROJECT 16-10 HVAC MAINTENANCE RE-BID BID DATE: MAY 5, 2016 @ 1:00 PM Bid documents, including plans and specifications, are available for download at www.questcdn.com. The QuestCDN website

More information

MULLER LANE EAST BROCKLISS SLOUGH BRIDGE SEWER FORCE MAIN RELOCATION

MULLER LANE EAST BROCKLISS SLOUGH BRIDGE SEWER FORCE MAIN RELOCATION CONTRACT DOCUMENTS and CONSTRUCTION SPECIFICATIONS for MULLER LANE EAST BROCKLISS SLOUGH BRIDGE SEWER FORCE MAIN RELOCATION DOUGLAS COUNTY SEWER IMPROVEMENT DISTRICT NO. 1 ZEPHYR COVE, NEVADA Rob Hopkins,

More information

CITY OF FLINT, MICHIGAN

CITY OF FLINT, MICHIGAN CITY OF FLINT, MICHIGAN DEPARTMENT OF PURCHASES & SUPPLIES PROJECT MANUAL FOR 2018 PHASE V HYDROVAC EXPLORATION Proposal No. 18-570 JANUARY 24, 2018 THIS PAGE INTENTIONALLY LEFT BLANK CITY OF FLINT Department

More information

SECTION BID FORM JACKSON AVENUE / 15TH STREET WATER MAIN REPLACEMENT

SECTION BID FORM JACKSON AVENUE / 15TH STREET WATER MAIN REPLACEMENT ARTICLE 1 BID RECIPIENT 1.01 This Bid is submitted to: SECTION 00410 BID FORM JACKSON AVENUE / 15TH STREET WATER MAIN REPLACEMENT WESTERN VIRGINIA WATER AUTHORITY ATTN: Earl Smith Engineering Services

More information

PROJECT MANUAL VILLAGE OF ADDISON STREETSCAPE IMPROVEMENTS. Contract 1 GENERAL CONSTRUCTION

PROJECT MANUAL VILLAGE OF ADDISON STREETSCAPE IMPROVEMENTS. Contract 1 GENERAL CONSTRUCTION PROJECT MANUAL VILLAGE OF ADDISON STREETSCAPE IMPROVEMENTS Contract 1 GENERAL CONSTRUCTION Prepared for: VILLAGE OF ADDISON 35 TUSCARORA STREET ADDISON, NY 14801 Prepared by: LARSON DESIGN GROUP 1 West

More information

The Home Depot U.S.A., Inc. Instructions to Bidders

The Home Depot U.S.A., Inc. Instructions to Bidders The Home Depot U.S.A., Inc. Instructions to Bidders Home Depot Page 1 of 5 Article 1 Definitions 1.1 Bidding Documents include the Bidding Requirements and the proposed Contract Documents. The Bidding

More information

CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS FOR

CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS FOR CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS FOR PARKVIEW / LANTRIP RETAINING WALL REPLACEMENT Project Number KIL001C ISSUED FOR BID Submission Deadline: Tuesday, December 19 th, 2017 at 2 p.m. Submit

More information

IMPROVEMENTS TO THE MUNICIPAL ELECTRIC SYSTEM OF THE CITY OF PIQUA, OHIO

IMPROVEMENTS TO THE MUNICIPAL ELECTRIC SYSTEM OF THE CITY OF PIQUA, OHIO IMPROVEMENTS TO THE MUNICIPAL ELECTRIC SYSTEM OF THE CITY OF PIQUA, OHIO PROJECT MANUAL FOR CONTRACT NO. 016-00781-01 GAS TURBINE GENERATOR NO. 9 ROOF REPLACEMENT PROJECT FEBRUARY 2018 1001 Madison Avenue

More information

SECTION BID FORM

SECTION BID FORM Attachment 1 Contract 13 Addendum 3 ARTICLE 1 BID RECIPIENT 1.01 This Bid is submitted to: SECTION 00300 BID FORM CITY OF CAPE CORAL NORTH 2 UTILITIES EXTENSION PROJECT CONTRACT 13 City of Cape Coral,

More information

Bidders Name: DOCUMENT 330 BID FORM

Bidders Name: DOCUMENT 330 BID FORM Bidders Name: DOCUMENT 330 BID FORM TO: The City of Topeka, Kansas Contracts & Procurement Division 215 S.E. 7th St., Room 60 Topeka, Kansas 66603 Project No. and Description: 1. The undersigned Bidder

More information

SECTION BID FORM LICK RUN INTERCEPTOR REHABILITATION

SECTION BID FORM LICK RUN INTERCEPTOR REHABILITATION SECTION 00410 BID FORM LICK RUN INTERCEPTOR REHABILITATION ARTICLE 1 BID RECIPIENT 1.01 This Bid is submitted to: WESTERN VIRGINIA WATER AUTHORITY ATTN: Earl Smith, P.E. Engineering Services Third Floor,

More information

BID ADVERTISEMENT MARANACOOK LAKE OUTLET DAM MODIFICATIONS TOWNS OF READFIELD AND WINTHROP, MAINE

BID ADVERTISEMENT MARANACOOK LAKE OUTLET DAM MODIFICATIONS TOWNS OF READFIELD AND WINTHROP, MAINE BID ADVERTISEMENT MARANACOOK LAKE OUTLET DAM MODIFICATIONS TOWNS OF READFIELD AND WINTHROP, MAINE The Towns of Readfield and Winthrop, acting by and through the Maranacook Lake Outlet Dam Committee, are

More information

THE CITY OF LAKE FOREST

THE CITY OF LAKE FOREST THE CITY OF LAKE FOREST SPECIFICATIONS FOR Barrell Memorial Gate Restoration Project at the Lake Forest Cemetery January 4, 2019 TABLE OF CONTENTS SECTION 00030... 4 ADVERTISEMENT FOR BIDS... 4 SECTION

More information

BID Addenda No. Date Issued Addenda No. Date Issued

BID Addenda No. Date Issued Addenda No. Date Issued BID - 004113 BID TO: THE CITY AND BOROUGH OF JUNEAU 1. The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with the OWNER in the form included in the Contract

More information

BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION. for the COUNTY OF ORANGEBURG. Project Number: FY

BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION. for the COUNTY OF ORANGEBURG. Project Number: FY BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION for the COUNTY OF ORANGEBURG Project Number: FY13-1206 October 18, 2012 1180 Columbia Avenue Suite 201 29063 (803) 781-1451

More information

HURLEY DECENTRALIZED WASTEWATER TREATMENT PLANT REHABILITATION

HURLEY DECENTRALIZED WASTEWATER TREATMENT PLANT REHABILITATION HURLEY DECENTRALIZED WASTEWATER TREATMENT PLANT REHABILITATION Project Manual prepared for JACKSON COUNTY UTILITY AUTHORITY PREPARED BY: COMPTON ENGINEERING, INC. 1706 CONVENT AVE. PASCAGOULA, MISSISSIPPI

More information

A D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary

A D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary A D D E N D U M 1 TO All Plan Holders ISSUE DATE 20 January 2017 PROJECT # 15-028 REGARDING Switchgear Replacement NARRATIVE PAGES 1 15-02812 KVa Switchgear Replacement Project SPECIFICATION PAGES 10 DRAWING

More information

CONTRACT DOCUMENTS AND BID FORM. FPL Remediation and Redevelopment PROJECT IDENTIFICATION:

CONTRACT DOCUMENTS AND BID FORM. FPL Remediation and Redevelopment PROJECT IDENTIFICATION: CONTRACT DOCUMENTS AND BID FORM PROJECT IDENTIFICATION: THIS BID IS SUBMITTED TO: MANDATORY PRE-BID CONFERENCE: FPL Remediation and Redevelopment City of Biddeford c/o Brian Phinney Environmental Codes

More information

DEAN + TYLER + BURNS ARCHITECTURE

DEAN + TYLER + BURNS ARCHITECTURE DEAN + TYLER + BURNS ARCHITECTURE May 17, 2017 Community Safe Room for the City Springville 580 Indian Crest Drive Indian Springs, AL 35124 tel.: 205.427.7890 email: m@rchitecture-e.com ADDENDUM NO. 3

More information

City of Eagle Point 2017 Paving Instruction to Bidders

City of Eagle Point 2017 Paving Instruction to Bidders City of Eagle Point 2017 Paving Instruction to Bidders Issued: August 2, 2017 Closing Date and Time: Wednesday August 16, 2016 at 2:00 pm Project Summary The City of Eagle Point is requesting bids for

More information

PUBLIC SAFETY BUILDING BUILDING DEMOLITION

PUBLIC SAFETY BUILDING BUILDING DEMOLITION Contract No. BE19-117 File No. 2003 SECTION 00005 - TABLE OF CONTENTS DIVISION 0 - BIDDING AND CONTRACT REQUIREMENTS, CONTRACT FORMS, AND CONDITIONS OF THE CONTRACT BIDDING and CONTRACT REQUIREMENTS No.

More information

WASTEWATER TREATMENT PLANT MICROTURBINES AND DIGESTER GAS CONDITIONING SKID EQUIPMENT

WASTEWATER TREATMENT PLANT MICROTURBINES AND DIGESTER GAS CONDITIONING SKID EQUIPMENT MARIN COUNTY, CALIFORNIA CONTRACT DOCUMENTS FOR WASTEWATER TREATMENT PLANT MICROTURBINES AND DIGESTER GAS CONDITIONING SKID EQUIPMENT JOB NO. 14600-04 February 2015 DISTRICT BOARD Rabi Elias President

More information

BID FORM This Bid is submitted to: City of Glasgow 126 East Public Square Glasgow, KY 42141

BID FORM This Bid is submitted to: City of Glasgow 126 East Public Square Glasgow, KY 42141 BID FORM PROJECT DESCRIPTION Ellis Avenue Stream Improvements City of Glasgow, KY PROJECT NUMBER GRW Project No.: 4339 ARTICLE 1 BID RECIPIENT 1.01 This Bid is submitted to: City of Glasgow 126 East Public

More information

Main Building Auditorium

Main Building Auditorium Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform

More information

Attached please find the revised Plan Sheet C3 Proposed Conditions Plan.

Attached please find the revised Plan Sheet C3 Proposed Conditions Plan. ADDENDUM NO. 1 124002-4A RE: FROM: TO: Depot Street Drainage Improvements Charlestown, New Hampshire DuBois & King, Inc. P.O. Box 339 Randolph, Vermont 05060 (802) 728-3376 Prospective Bidders DATE: June

More information

This Addendum is directed to all prime Contract Bidders, and all others to whom Drawings and Specifications have been issued by the Architect.

This Addendum is directed to all prime Contract Bidders, and all others to whom Drawings and Specifications have been issued by the Architect. North Campus Entrance and related work Wallace State Community College ADDENDUM 3 PART 1 - GENERAL Project: North Campus Entrance and related work [B.C. # 2016259] Owner: Wallace State Community College

More information

BOILER REPLACEMENT AT SCHOOL OF ENGINEERING FOR ALABAMA A&M UNIVERSITY. Normal, Alabama

BOILER REPLACEMENT AT SCHOOL OF ENGINEERING FOR ALABAMA A&M UNIVERSITY. Normal, Alabama BOILER REPLACEMENT AT SCHOOL OF ENGINEERING FOR ALABAMA A&M UNIVERSITY Normal, Alabama MIMS ENGINEERING, INC., 112B Southside Square, Huntsville, AL 35801 May 2, 2018 BOILER REPLACEMENT AT SCHOOL OF ENGINEERING

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

City of Eagle Point South Shasta Pedestrian Bridge Instruction to Bidders

City of Eagle Point South Shasta Pedestrian Bridge Instruction to Bidders City of Eagle Point South Shasta Pedestrian Bridge Instruction to Bidders Issued: November 15, 2017 Closing Date and Time: January 16, 2018, at 2:00 pm Project Summary The City of Eagle Point is requesting

More information

SECTION BID FORM. Garfield Street Drainage Improvements

SECTION BID FORM. Garfield Street Drainage Improvements SECTION 00410 BID FORM Garfield Street Drainage Improvements ARTICLE 1 - BID RECIPIENT 1.01 This Bid is submitted to: City of Lindsborg, Kansas City Clerk s Office 101 S. Main Street Lindsborg, KS 67456

More information

00900 ADDENDUM #1. All Document Holders of Record. Date: February 16, Bayfield Waterline Replacement Project

00900 ADDENDUM #1. All Document Holders of Record. Date: February 16, Bayfield Waterline Replacement Project 00900 ADDENDUM #1 Issued to: All Document Holders of Record Date: February 16, 2016 Project: Bayfield Waterline Replacement Project This Addendum forms a part of the Contract described above. The original

More information

THIRD STREET WATER MAIN REPLACEMENT PROJECT

THIRD STREET WATER MAIN REPLACEMENT PROJECT MARINA COAST WATER DISTRICT THIRD STREET WATER MAIN REPLACEMENT PROJECT CIP NO. OW-0240 June 2015 00010-1 Third Street Water Main Replacement Project CIP No. OW-0240 Document 00050 Marina Coast Water

More information

SECTION NEW MARTINSVILLE FIREMAN S DOCK BIDS DUE: 4:30 PM LOCAL TIME ON FRIDAY JANUARY 30 TH, 2015

SECTION NEW MARTINSVILLE FIREMAN S DOCK BIDS DUE: 4:30 PM LOCAL TIME ON FRIDAY JANUARY 30 TH, 2015 SECTION 00 91 13.01 NEW MARTINSVILLE FIREMAN S DOCK ADDENDUM #2 ADDENDUM #2 ISSUE DATE: JANUARY 21, 2015 PROJECT NAME: NEW MARTINSVILLE FIREMAN S DOCK BIDS DUE: 4:30 PM LOCAL TIME ON FRIDAY JANUARY 30

More information

CITY OF DE PERE PROJECT CIPP SEWER LINING BID DATE: JANUARY 31, 1:00 PM

CITY OF DE PERE PROJECT CIPP SEWER LINING BID DATE: JANUARY 31, 1:00 PM CITY OF DE PERE PROJECT 19-03 CIPP SEWER LINING BID DATE: JANUARY 31, 2019 @ 1:00 PM Bid documents, including plans and specifications, are available for download at www.questcdn.com. The QuestCDN website

More information

ADDENDUM NUMBER ONE (1) December 6, The following Addendum shall be incorporated into the Contract Documents for the above referenced project.

ADDENDUM NUMBER ONE (1) December 6, The following Addendum shall be incorporated into the Contract Documents for the above referenced project. TO: ALL HOLDERS OF CONTRACT DOCUMENTS FOR: City of Carlsbad, New Mexico Sanitary Sewer Interceptor 118 Upgrades Phase I Wade M. Chacon P.E. HDR Project Manager/Engineer Bid # 2016-32 ADDENDUM NUMBER ONE

More information

SECTION BID FORM (REVISED ) ADDENDUM No. 1

SECTION BID FORM (REVISED ) ADDENDUM No. 1 SECTION 00300 BID FORM (REVISED - 06-14-2010) ADDENDUM No. 1 PROJECT IDENTIFICATION: ITB No. 10-045 Sebring Parkway Phase II Signing and Pavement Markings Project No. 01101 THIS BID IS SUBMITTED TO: Highlands

More information

CENTENNIAL HALL FLOOR RENOVATION

CENTENNIAL HALL FLOOR RENOVATION Contract No. BE17-156 File No. 1935 ENGINEERING DEPARTMENT SECTION 00005 - TABLE OF CONTENTS DIVISION 0 - BIDDING AND CONTRACT REQUIREMENTS, CONTRACT FORMS, AND CONDITIONS OF THE CONTRACT BIDDING and CONTRACT

More information

Invitation for Bid - Standard Office Furniture / Task Chair

Invitation for Bid - Standard Office Furniture / Task Chair Invitation for Bid - Bid#2016-09-001 Instructions to Bidders 1. General Information Rice University is issuing this Invitation for Bid (IFB) for the procurement of goods and/or trade services as described

More information

August 19, Addendum No. 2 Roosevelt Hall Interior Renovation Brooklyn College Project No.: BY

August 19, Addendum No. 2 Roosevelt Hall Interior Renovation Brooklyn College Project No.: BY The City University Of New York August 19, 2010 Addendum No. 2 Roosevelt Hall Interior Renovation Brooklyn College Project No.: BY600-006 This Addendum is for the purpose of conveying the below Documents

More information

2. Provide a revised Section 17 and 27 to our Instructions to Bidders (attached)

2. Provide a revised Section 17 and 27 to our Instructions to Bidders (attached) Philadelphia Regional Port Authority 3460 North Delaware Ave. 2 nd Floor Philadelphia, PA 19134 November 19, 2018 To: All Bidders From: Kate Bailey Director of Procurement Re: ADDENDUM NO. 1 Project 18-152.0

More information

DIMOND PARK AQUATIC CENTER WHIRLPOOL HVAC & AHU-1 UPGRADES \

DIMOND PARK AQUATIC CENTER WHIRLPOOL HVAC & AHU-1 UPGRADES \ WHIRLPOOL HVAC & AHU-1 UPGRADES \ Contract No. BE17-185 File No. 1916 SECTION 00005 - TABLE OF CONTENTS DIVISION 0 - BIDDING AND CONTRACT REQUIREMENTS, CONTRACT FORMS, AND CONDITIONS OF THE CONTRACT BIDDING

More information

IMMEDIATE RESPONSE REQUESTED

IMMEDIATE RESPONSE REQUESTED DATE: June 1, 2018 IMMEDIATE RESPONSE REQUESTED ADDENDUM NO. 3 Project No. 833450 Owner: City of Dexter Project: 2018 Wastewater Treatment Plant Improvements ADDENDUM ACKNOWLEDGMENT Upon receipt of this

More information

A new Proposal Form is being issued with this Addendum, the following is an explanation of the changes, disregard originally issued form.

A new Proposal Form is being issued with this Addendum, the following is an explanation of the changes, disregard originally issued form. Courtyards Phase ADDENDUM NO. 1 May 2, 2016 PROJECT: Courtyards at the Oaks Phase 2 Paving & Incidental Drainage Improvements BID DATE: Tuesday, May 3, 2016, at 2:00 PM City Hall, City of Derby 611 Mulberry

More information

PROJECT MANUAL FOR: CP AGRICULTURAL ENGINEERING RAIN TOWER REPAIRS CP HULSTON HALL STAIR TOWER REPAIRS

PROJECT MANUAL FOR: CP AGRICULTURAL ENGINEERING RAIN TOWER REPAIRS CP HULSTON HALL STAIR TOWER REPAIRS ADDENDUM #01 DATE: MAY 6, 2016 Page 1 of 2 TO CONTRACT DOCUMENTS ENTITLED: PROJECT MANUAL FOR: CP151322 AGRICULTURAL ENGINEERING RAIN TOWER REPAIRS CP160372 HULSTON HALL STAIR TOWER REPAIRS AT UNIVERSITY

More information

Augusta County Greenville Village Sanitary Sewer Project 03/12

Augusta County Greenville Village Sanitary Sewer Project 03/12 THESE DOCUMENTS ARE PROVIDED FOR REFERENCE ONLY AND ARE NOT TO BE USED FOR BID PURPOSES CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONS GREENVILLE VILLAGE SANITARY SEWER PROJECT May 12, 2012 Prepared for

More information

1. Provide a revised bid form that reflects revisions to Bidder Responsiveness Section(attached)

1. Provide a revised bid form that reflects revisions to Bidder Responsiveness Section(attached) Philadelphia Regional Port Authority 3460 North Delaware Ave. 2 nd Floor Philadelphia, PA 19134 October 17, 2018 To: All Bidders From: Kate Bailey Director of Procurement Re: ADDENDUM NO. 1 Project 18-074.1

More information

UAF Combined Heat & Power Replacement (CPHR)

UAF Combined Heat & Power Replacement (CPHR) davis JV UAF Combined Heat & Power Replacement (CPHR) REQUEST FOR BIDS Limited 2015 Mechanical Scope PROPOSALS DUE: THURSDAY JULY 2 ND, 2015 2:00PM LOCAL ALASKA TIME Submit to: Haskell Corporation /Davis

More information

Sunnycrest Manor Roosevelt Street Dubuque, IA Sunnycrest Manor Kitchen Ventilation MEP Engineers Project #1735

Sunnycrest Manor Roosevelt Street Dubuque, IA Sunnycrest Manor Kitchen Ventilation MEP Engineers Project #1735 Sunnycrest Manor 2375 Roosevelt Street Dubuque, IA 52001 Sunnycrest Manor Kitchen Ventilation MEP Engineers Project #1735 Sunnycrest Manor Kitchen Ventilation SUNNYCREST MANOR KITCHEN VENTILATION 2375

More information

NOTICE TO BIDDERS FOR

NOTICE TO BIDDERS FOR CITY OF SAN LEANDRO STATE OF CALIFORNIA ENGINEERING AND TRANSPORTATION DEPARTMENT NOTICE TO BIDDERS FOR MONARCH BAY DRIVE BRIDGE REPAIR PROJECT NO. 12-144-38-324 BID NO. 12-13.013 1. BID OPENING: The bidder

More information

City of Ketchum and Sun Valley Water and Sewer District

City of Ketchum and Sun Valley Water and Sewer District City of Ketchum and Sun Valley Water and Sewer District CITY OF KETCHUM AND SUN VALLEY, ID Headworks Improvements - Screen and Washer/Compactor Procurement Issued for Bid February 2018 HDR Project No.

More information

Middle School Sewer Main Improvements Project Contract Documents & Specifications

Middle School Sewer Main Improvements Project Contract Documents & Specifications Middle School Sewer Main Improvements Project Contract Documents & Specifications For: Prepared By: Hardin County Water District No. 1 1400 Rogersville Road Radcliff, KY. 40160 Phone: 270-351-3222 FAX:

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS CONTENTS I. Bid Documents II. Ethical Business Practices III. Contractor Qualifications IV. Performance and Quality Standards V. Bid Evaluation VI. Contract Award VII. Work Operations

More information

BIDDING DOCUMENTS KRULL DITCH/PARK AVENUE CULVERT REPLACEMENT PROJECT WHEELER, INDIANA

BIDDING DOCUMENTS KRULL DITCH/PARK AVENUE CULVERT REPLACEMENT PROJECT WHEELER, INDIANA BIDDING DOCUMENTS FOR THE KRULL DITCH/PARK AVENUE CULVERT REPLACEMENT PROJECT IN WHEELER, INDIANA SEPTEMBER 8, 2017 PREPARED BY: PORTER CO. DEPT. OF DEVELOPMENT & STORM WATER MANAGEMENT 155 INDIANA AVE.,

More information

MEMORANDUM. Taylor Schoel with Walter Schoel Engineering. DATE: August 29, Addendum 1 - Green Drive Culvert Replacement.

MEMORANDUM. Taylor Schoel with Walter Schoel Engineering. DATE: August 29, Addendum 1 - Green Drive Culvert Replacement. MEMORANDUM TO: FROM: Bidders Taylor Schoel with Walter Schoel Engineering DATE: August 29, 2013 SUBJECT: Addendum 1 - Green Drive Culvert Replacement The following is part of Addendum 1 and should be included

More information

ADDENDUM #3. GRW Project No.: Date: March 19, 2019 Subject: City of Nicholasville Fire Station #4

ADDENDUM #3. GRW Project No.: Date: March 19, 2019 Subject: City of Nicholasville Fire Station #4 ADDENDUM #3 GRW Project No.: Date: March 19, 2019 Subject: City of Nicholasville Fire Station #4 Please address inquiries to: Aaron R. Nickerson GRW, Inc. anickerson@grwinc.com TO ALL PROSPECTIVE BIDDERS:

More information

1. Bid Form The Bid Form has been revised. All Bidders shall utilize the Bid Form attached to this Addendum for the submission of Bids.

1. Bid Form The Bid Form has been revised. All Bidders shall utilize the Bid Form attached to this Addendum for the submission of Bids. SSM GROUP, INC. 1047 N. Park Road > P.O. Box 6307 > Reading PA 19610-0307 610.621.2000 > F. 610.621.2001 > SSMGROUP.COM October 10, 2016 TO ALL PROSPECTIVE BIDDERS Re: ADDENDUM #1 UPPER MERION AREA SCHOOL

More information

SECTION BID FORM. Construction of Water Mains: Jonestown, PA. Market Street Project No. W-1-19

SECTION BID FORM. Construction of Water Mains: Jonestown, PA. Market Street Project No. W-1-19 SECTION 00410 BID FORM Construction of Water Mains: Jonestown, PA. Market Street Project No. W-1-19 THIS BID IS SUBMITTED TO: CITY OF LEBANON AUTHORITY 2311 Ridgeview Road Lebanon, Pennsylvania 17042 1.01

More information

PROJECT MANUAL for Phantom Canyon Tunnel Repair Project. Location On Fremont County Road miles North of Intersection US Highway 50 with FCR 67

PROJECT MANUAL for Phantom Canyon Tunnel Repair Project. Location On Fremont County Road miles North of Intersection US Highway 50 with FCR 67 August 28, 2018 PROJECT MANUAL for Phantom Canyon Tunnel Repair Project Location On Fremont County Road 67 7.5 miles North of Intersection US Highway 50 with FCR 67 Fremont County, Colorado OWNER: Fremont

More information

GYMNASIUM RENOVATION WASHINGTON HIGH SCHOOL

GYMNASIUM RENOVATION WASHINGTON HIGH SCHOOL PROJECT MANUAL FOR CONSTRUCTION OF GYMNASIUM RENOVATION WASHINGTON HIGH SCHOOL WASHINGTON COMMUNITY SCHOOLS Washington, Indiana PROJECT MANUAL FOR CONSTRUCTION OF GYMNASIUM RENOVATION WASHINGTON HIGH SCHOOL

More information

CITY OF PANAMA CITY BEACH WWTF INFLUENT SCREENS REPLACEMENT April 14, 2017

CITY OF PANAMA CITY BEACH WWTF INFLUENT SCREENS REPLACEMENT April 14, 2017 CITY OF PANAMA CITY BEACH WWTF INFLUENT SCREENS REPLACEMENT April 14, 2017 ADDENDUM NO. 1 (This Form Must Be Signed and Submitted With Bid Form) Addendum No. 1 addresses the following issues: QUESTIONS

More information

Item #19 - CC Agenda - 06/09/ Sanitary Sewer Rehabilitation Project Plan Approval [Page 1 of 118]

Item #19 - CC Agenda - 06/09/ Sanitary Sewer Rehabilitation Project Plan Approval [Page 1 of 118] [Page 1 of 118] RD S Item #19 - CC Agenda - 06/09/2014 [Page 2 of 118] 1150 BAY 1130 YST AL 2640 OLD CR 1200 2430 2685 2683 NO 2655 RT H 2605 2625 SH OR ED R 2565 2545 2515 2485 CRYSTAL BAY 2465 2455 2445

More information

ADDENDUM NO. 1 FOR CITY OF CUMMING 900-HP RAW WATER INTAKE PUMP. ADDENDUM DATE: February 10, BID DATE: February 15, 2017, 11:30 a.m.

ADDENDUM NO. 1 FOR CITY OF CUMMING 900-HP RAW WATER INTAKE PUMP. ADDENDUM DATE: February 10, BID DATE: February 15, 2017, 11:30 a.m. ADDENDUM NO. 1 FOR CITY OF CUMMING 900-HP RAW WATER INTAKE PUMP ADDENDUM DATE: February 10, 2017 BID DATE: February 15, 2017, 11:30 a.m. This ADDENDUM is issued to institute the included changes and/or

More information

extrudesection 00301 BID FORM PROJECT IDENTIFICATION: CONSTRUCTION OF PROPOSED DRAINAGE IMPROVEMENTS THIS BID IS SUBMITTED TO: THE CITY OF FREDERICKSBURG, TEXAS, herein after referred to as OWNER. 1. Enter

More information

BERRYESSA UNION SCHOOL DISTRICT PURCHASING DEPARTMENT 1376 PIEDMONT RD SAN JOSE, CA OFC FAX

BERRYESSA UNION SCHOOL DISTRICT PURCHASING DEPARTMENT 1376 PIEDMONT RD SAN JOSE, CA OFC FAX BERRYESSA UNION SCHOOL DISTRICT PURCHASING DEPARTMENT 1376 PIEDMONT RD SAN JOSE, CA 95132 408-923-1871 OFC 408-926-8329 FAX PREQUALIFICATION PACKAGE INSTRUCTIONS FOR PROSPECTIVE MEP SUBCONTRACTORS FEBRUARY

More information

NORTH BAY VILLAGE, FLORIDA INVITATION TO BID BID NO. NBV

NORTH BAY VILLAGE, FLORIDA INVITATION TO BID BID NO. NBV NORTH BAY VILLAGE, FLORIDA INVITATION TO BID FOR WATERMETERREPLACEMENT PROGRAM BID NO. NBV 2017-001 SEALED PROPOSALS WILL BE RECEIVED BY THE VILLAGE CLERK, 1666 KENNEDY CAUSEWAY,SUITE 300, NORTH BAY VILLAGE,

More information

DOUGLAS FIRE HALL/LIBRARY & SKATE PARK ROOFS REPLACEMENT

DOUGLAS FIRE HALL/LIBRARY & SKATE PARK ROOFS REPLACEMENT DOUGLAS FIRE HALL/LIBRARY & SKATE PARK ROOFS REPLACEMENT Contract No. BE18-150 File No. 1992 Engineering Department SECTION 00005 - TABLE OF CONTENTS DIVISION 0 - BIDDING AND CONTRACT REQUIREMENTS, CONTRACT

More information

SECTION CONTRACT DOCUMENTS TABLE OF CONTENTS

SECTION CONTRACT DOCUMENTS TABLE OF CONTENTS SECTION 00020 CONTRACT DOCUMENTS TABLE OF CONTENTS PAGE(S) BIDDING REQUIREMENTS, CONTRACT FORMS, AND CONDITIONS OF THE CONTRACT SECTION PAGE(S) PART 1 - BIDDING REQUIREMENTS 00010 Title Page... 00001-1

More information

ADVERTISEMENT TO BID PARTIAL

ADVERTISEMENT TO BID PARTIAL ADVERTISEMENT TO BID The City of Elkton will receive separate, sealed Bids for their East Main Street Lift Station Generator Pad Addition Project until 10:30 a.m. local time, Tuesday, January 8, 2019 at

More information

Both envelopes must have the following information in the lower left hand corner:

Both envelopes must have the following information in the lower left hand corner: SECTION 001116 INVITATION TO BID The City of Morgantown is requesting a bid for masonry restoration for the City Hall Building in Morgantown, WV. The Project is for building envelope rehabilitation including

More information

CITY OF LAKE FOREST PARK EXTERIOR PAINTING OF CITY HALL BUILDING. Bid Document. Specifications, Proposal and Contract Documents

CITY OF LAKE FOREST PARK EXTERIOR PAINTING OF CITY HALL BUILDING. Bid Document. Specifications, Proposal and Contract Documents CITY OF LAKE FOREST PARK EXTERIOR PAINTING OF CITY HALL BUILDING Bid Document Specifications, Proposal and Contract Documents July 2013 CITY OF LAKE FOREST PARK Exterior Painting of City Hall Building

More information

woodardcurran.com Town of Westbrook Town Center Parking Improvement Plan Bidding Documents For Construction Bid # 2016 TC01

woodardcurran.com Town of Westbrook Town Center Parking Improvement Plan Bidding Documents For Construction Bid # 2016 TC01 Town of Westbrook Town Center Parking Improvement Plan Bid # 2016 TC01 Bidding Documents For Construction 226692.10 Town 226692.10 of Town of 1520 Highland Avenue Cheshire, Connecticut 06410 888-265-8969

More information

Black Creek Consolidated Drain (Dirkes Drain)

Black Creek Consolidated Drain (Dirkes Drain) Black Creek Consolidated Drain (Dirkes Drain) CONTRACT SPECIFICATIONS ISSUED FOR BID Prepared For: Muskegon County Drain Commissioner Prepared By: Project No. 14-111 May 2016 Table of Contents Division

More information

Water Meter Material Contract City of Ashville DWSRF # FS All Record Holding Contract Documents

Water Meter Material Contract City of Ashville DWSRF # FS All Record Holding Contract Documents 105 W. 2 nd Street Tuscumbia, AL 35674 T (256) 248-7030 F 1-866-225-7488 PROJECT: Water Meter Material Contract City of Ashville DWSRF # FS010200-01 ADDENDUM NO. Two (2) DATE: February 20, 2018 TO: All

More information

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina Project Manual for Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina DWG Consulting Engineers 1009 Anna Knapp Blvd. Suite 202 Mt Pleasant, South Carolina 29464

More information

2. Provide a revised bid form which includes revised language in Section II, Bidder Responsiveness Section. (attached to this Addendum 1)

2. Provide a revised bid form which includes revised language in Section II, Bidder Responsiveness Section. (attached to this Addendum 1) Philadelphia Regional Port Authority 3460 North Delaware Ave. 2 nd Floor Philadelphia, PA 19134 October 30, 2018 To: All Bidders From: Kate Bailey Director of Procurement Re: ADDENDUM NO. 1 Project 18-110.1

More information

CONTRACT DOCUMENTS 2018 AERATION OF WWTP EFFLUENT CITY OF DURAND 215 WEST CLINTON STREET DURAND, MI JULY 2018 PREPARED BY:

CONTRACT DOCUMENTS 2018 AERATION OF WWTP EFFLUENT CITY OF DURAND 215 WEST CLINTON STREET DURAND, MI JULY 2018 PREPARED BY: CONTRACT DOCUMENTS 2018 AERATION OF WWTP EFFLUENT CITY OF DURAND 215 WEST CLINTON STREET DURAND, MI 48429 JULY 2018 PREPARED BY: 555 S. SAGINAW STREET SUITE 201 DUR 2001.01F FLINT, MI 48502 Table of Contents

More information

JUNEAU SCHOOL DISTRICT (JSD) SECURITY CAMERA INSTALLATIONS

JUNEAU SCHOOL DISTRICT (JSD) SECURITY CAMERA INSTALLATIONS JUNEAU SCHOOL DISTRICT (JSD) SECURITY CAMERA INSTALLATIONS VOLUME I OF II Contract No. E13-164 File No. 1789 ENGINEERING DEPARTMENT SECTION 00005 - TABLE OF CONTENTS DIVISION 0 - BIDDING AND CONTRACT REQUIREMENTS,

More information

Request for Proposal Internet Access Columbus Urban League

Request for Proposal Internet Access Columbus Urban League Request for Proposal Internet Access Columbus Urban League 1 REQUEST FOR PROPOSAL Internet Access Columbus Urban League The Columbus Urban League invites vendors to submit proposals in accordance with

More information

OCONEE COUNTY PROCUREMENT OFFICE 415 S. PINE STREET, ROOM 100 WALHALLA, SC Robyn M. Courtright, CPPO, Procurement Director

OCONEE COUNTY PROCUREMENT OFFICE 415 S. PINE STREET, ROOM 100 WALHALLA, SC Robyn M. Courtright, CPPO, Procurement Director OCONEE COUNTY PROCUREMENT OFFICE 415 S. PINE STREET, ROOM 100 WALHALLA, SC 29691 Robyn M. Courtright, CPPO, Procurement Director Tronda Spearman, CPPB, Assistant Procurement Director Telephone: 864-638-4141

More information

Blatt PE Center Fire Alarm Upgrades November 12, 2012 State Project No. H27-I851-B

Blatt PE Center Fire Alarm Upgrades November 12, 2012 State Project No. H27-I851-B Blatt PE Center Fire Alarm Upgrades November 12, 2012 State Project No. H27-I851-B Addendum No. 2 TO: ALL BIDDERS OF RECORD The following items shall take precedence over the drawings and specifications

More information

ACKNOWLEDGMENT OF RECEIPT OF ADDENDUM NO.

ACKNOWLEDGMENT OF RECEIPT OF ADDENDUM NO. Philadelphia Regional Port Authority 3460 North Delaware Ave. 2 nd Floor Philadelphia, PA 19134 February 19, 2019 To: All Bidders From: Kate Bailey Director of Procurement Re: ADDENDUM NO. 4 Project 19-011.3

More information

MARYLAND STADIUM AUTHORITY

MARYLAND STADIUM AUTHORITY MARYLAND STADIUM AUTHORITY REQUEST FOR QUALIFICATIONS (RFQ) GENERAL CONTRACTOR RENOVATIONS TO OPERATIONS OFFICE M&T BANK STADIUM MSA Project No. 19-013 ISSUE DATE: October 9, 2018 MARYLAND STADIUM AUTHORITY

More information

InterceptorSewerLi ContractDocuments

InterceptorSewerLi ContractDocuments WestErdaRegi onal InterceptorSewerLi ne ContractDocuments ERDA WEST REGION INTERCEPTOR SEWER LINE Contract Documents & Specifications November 16, 2018 Prepared By: 231 West 800 South Salt Lake City, Utah

More information

REQUEST FOR PROPOSAL (RFP) No.: J-19 PRECONSTRUCTION AND CONSTRUCTION SERVICES, MEDIUM VOLTAGE SUBSTATION REPLACEMENT, LAS POSITAS COLLEGE

REQUEST FOR PROPOSAL (RFP) No.: J-19 PRECONSTRUCTION AND CONSTRUCTION SERVICES, MEDIUM VOLTAGE SUBSTATION REPLACEMENT, LAS POSITAS COLLEGE REQUEST FOR PROPOSAL (RFP) No.: J-19 PRECONSTRUCTION AND CONSTRUCTION SERVICES, MEDIUM VOLTAGE SUBSTATION REPLACEMENT, LAS POSITAS COLLEGE To: All Prospective Bidders Addendum No. One This Addendum One

More information

INSTRUCTIONS TO BIDDERS Sealed proposals shall be addressed to: For legal address, contact contracting office.

INSTRUCTIONS TO BIDDERS Sealed proposals shall be addressed to: For legal address, contact contracting office. INSTRUCTIONS TO BIDDERS PART ONE: GENERAL 1.1 Bid Proposals/Invitation to Tender 1.1.1 Sealed proposals shall be addressed to: For legal address, contact contracting office. and delivered enclosed in a

More information

700 CMR: MASSACHUSETTS DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS 700 CMR 14.00: PREQUALIFICATION OF CONTRACTORS FOR HORIZONTAL CONSTRUCTION

700 CMR: MASSACHUSETTS DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS 700 CMR 14.00: PREQUALIFICATION OF CONTRACTORS FOR HORIZONTAL CONSTRUCTION 700 CMR 14.00: PREQUALIFICATION OF CONTRACTORS FOR HORIZONTAL CONSTRUCTION Section 14.01: Definitions 14.02: Application for Prequalification of Contractors 14.03: Aggregate Bonding Capacity and Single

More information

SPECIFICATIONS & CONTRACT DOCUMENTS Sanitary Sewer Manhole Replacement and Bypass Contract 2013 FOR. The Town of Tyrone

SPECIFICATIONS & CONTRACT DOCUMENTS Sanitary Sewer Manhole Replacement and Bypass Contract 2013 FOR. The Town of Tyrone SPECIFICATIONS & CONTRACT DOCUMENTS Sanitary Sewer Manhole Replacement and Bypass Contract 2013 FOR The Town of Tyrone March 2013 Map of Approximate Vicinity Where Sewer Manhole Replacement and By Pass

More information

CONTRA COSTA COMMUNITY COLLEGE 500 Court St, Martinez, CA 94553

CONTRA COSTA COMMUNITY COLLEGE 500 Court St, Martinez, CA 94553 ADDENDUM #4 CONTRA COSTA COMMUNITY COLLEGE 500 Court St, Martinez, CA 94553 CLASSROOM NOTIFICATION DEVICE INSTALLATION - DISTRICTWIDE Contra Costa College / Diablo College / Los Medanos College Date: May

More information

Richmond Heights, MO. Prepared for: City of Richmond Heights Chris Boyd, P.E., Public Works Director 7997 Elinor Ave. Richmond Heights, MO 63117

Richmond Heights, MO. Prepared for: City of Richmond Heights Chris Boyd, P.E., Public Works Director 7997 Elinor Ave. Richmond Heights, MO 63117 PROJECT MANUAL 2016 CONCRETE SLAB REPLACEMENT PROGRAM Richmond Heights, MO Prepared for: City of Richmond Heights Chris Boyd, P.E., Public Works Director 7997 Elinor Ave. Richmond Heights, MO 63117 Prepared

More information

Refer to Section Proposal Form/All Trades (issued) a. Revised Alternate No. 2 b. Added Alternate No. 3

Refer to Section Proposal Form/All Trades (issued) a. Revised Alternate No. 2 b. Added Alternate No. 3 WAKELY ASSOCIATES, INC. ADDENDUM NO. ONE ARCHITECTS 30500 Van Dyke Avenue Suite 209 Warren, Michigan 48093 NEW LED LIGHTING Page 1 of 1 (write up only) January 23, 2018 ADDENDUM NO. ONE to the plans and

More information