TIER 1 SEISMIC EVALUATION

Size: px
Start display at page:

Download "TIER 1 SEISMIC EVALUATION"

Transcription

1 TIER 1 SEISMIC EVALUATION Immediate Occupancy Structural Performance Level Campbell, California Prepared For: City of Campbell 70 North First Street Campbell, California Prepared By: Biggs Cardosa Associates, Inc. 101 California Street, Suite 875 San Francisco, California BCA Job No

2 Page i TABLE OF CONTENTS EXECUTIVE SUMMARY...1 PROJECT OVERVIEW...3 AVAILABLE DOCUMENTS...4 BUILDING DESCRIPTION...5 DESCRIPTION OF STRUCTURE...6 EXISTING CONDITIONS...7 SEISMIC EVALUATION AND FINDINGS...8 Evaluation Basis...8 Lateral Load-Resisting System...9 Seismic Evaluation Results...9 RECOMMENDATIONS...11 CONCEPTUAL COST ESTIMATE...11 FURTHER ACTIONS...12 LIMITATIONS AND DISCLAIMERS...12 APPENDICES Appendix 1 Appendix 2 Appendix 3 Appendix 4 Photos Conceptual Seismic Retrofit Plans Conceptual Cost Estimate ASCE 41 Tier 1 Checklists

3 Page 1 EXECUTIVE SUMMARY Biggs Cardosa Associates has been retained by the City of Campbell to provide a Tier 1 seismic assessment of the in order to upgrade the existing building as an Essential Facility. As prescribed in ASCE 41-13, the reference document used for this seismic evaluation, the lateral load-resisting system of an Essential Facility must comply with requirements of the Immediate Occupancy Structural Performance Level. This report contains the structural/seismic findings, qualitative conceptual seismic retrofit recommendations and an order-of-magnitude construction cost estimate for the required retrofit work based on our Tier 1 seismic assessment (using the Immediate Occupancy performance level) as well as our experience with buildings of similar size, age and construction type. The is a 2-story, 32,600 sf structure that was constructed in The building consists of wood-framed roof and second floor, with steel columns, and concrete masonry walls at the 1 st story and wood-framed walls at the 2 nd story. The building is constructed with two rectangular wings that are connected with a smaller rectangular lobby. Foundations consist of isolated spread footing below columns and continuous footings below walls. The lateral system comprises of plywood roof and floor diaphragms, plywood shear walls at the 2 nd story and masonry walls at the 1 st story. The first floor is a slab-on-grade. Overall, the building is currently in good structural condition. The contains a complete vertical load-carrying system with no observed evidence of any significant structural damage, distress or deterioration. There were no visible indications that the building has undergone any significant settlement or differential settlement. The deficiencies identified were based on a review of the available drawings, a limited walkthrough of the building, completion of Tier 1 seismic assessment checklists, and our experience with structures of similar size, age and construction type. No destructive investigation was undertaken to either verify the existing conditions shown in the available documents, to identify unknown conditions, or to ascertain the extent of damage where evidence of potential structural damage was present. Since the City Hall building houses the City of Campbell Police Department, it is therefore, by code, an Essential Service Building. For this type of building, the primary structural elements are required to meet the Immediate Occupancy Structural Performance Level as described in ASCE However, originally as directed by the City, a seismic evaluation was performed using the Life Safety seismic performance criteria based on the assumption that the Police Department would be relocated to a new facility. The findings and recommendations of the Life Safety seismic evaluation were summarized in our Tier 1 Seismic Evaluation (Life Safety) report, dated December 16, 2015.

4 Page 2 As per current direction from the City, the building is likely to continue housing the Campbell Police Department (which makes it an essential facility) and, therefore, a seismic evaluation needs to be performed using the Immediate Occupancy performance criteria. An Immediate Occupancy performance level is significantly more stringent than the Life Safety performance level, and thus requires considerably more seismic retrofit work to upgrade an existing building due to the much higher seismic demands. The findings of this Tier 1 seismic assessment indicate that while the existing City Hall building apparently has a complete lateral load-resisting system, it may have significant deficiencies in the required continuity and/or strength for many of its structural elements/connections that are necessary for satisfactory seismic behavior under the design earthquake. The building is likely to maintain its gravity load-carrying system after the design level earthquake but may experience significant structural damage. Continued postearthquake building operations may not be possible and the repair costs may be too high to be economically feasible. The existing, therefore, does not meet the seismic resistance requirements for the Immediate Occupancy Structural Performance Level and would require considerable seismic retrofit work to reliably serve as an Essential Facility. The order-of-magnitude conceptual cost estimate for the required seismic retrofit work identified through our Tier 1 seismic evaluation to meet the Immediate Occupancy performance level is $1.1 million (refer to Appendix 3 for details and assumptions). This estimate only includes retrofit costs directly related to structural strengthening of the building s primary lateral load-resisting system. Potential costs of all other improvements (related to non-structural elements, MEP equipment and systems, furnishings, utility services, etc.) required to upgrade the building as an Essential Facility are excluded. Further evaluation of the structure using ASCE 41 Tier 2 Deficiency-Based procedures as well as field verification of various as-built conditions are required and recommended before finalizing the seismic retrofit program for the City Hall building. Continued post-earthquake use of a building is not limited just by the extent of earthquake damage to its structural system but, more often than not, might be limited by damage or disruption to non-structural elements of the building, furnishings, MEP components and systems, and availability of utility services. A seismic evaluation of these items is recommended to ensure that all non-structural items of the City Hall are also adequately upgraded to comply with the Essential Facility requirements.

5 Page 3 PROJECT OVERVIEW Biggs Cardosa Associates has been retained by the City of Campbell to provide a Tier 1 seismic assessment (using ASCE methodology) and conceptual seismic retrofit recommendations for the existing in order to upgrade the building as an Essential Facility. As outlined in ASE 41-13, the appropriate seismic performance level for essential facilities is the Immediate Occupancy Structural Performance Level. Since the City Hall building houses the City of Campbell Police Department, it is therefore, by code, an Essential Service Building. For this type of building, the primary structural elements are required to meet the Immediate Occupancy Structural Performance Level as described in ASCE However, originally as directed by the City, a seismic evaluation was performed using the Life Safety seismic performance criteria based on the assumption that the Police Department would be relocated to a new facility. The findings and recommendations of the Life Safety seismic evaluation were summarized in our Tier 1 Seismic Evaluation (Life Safety) report, dated December 16, As per current direction from the City, the building is likely to continue housing the Campbell Police Department (which makes it an essential facility) and, therefore, a seismic evaluation needs to be performed using the Immediate Occupancy performance criteria. An Immediate Occupancy performance level is significantly more stringent than the Life Safety performance level, and thus requires considerably more seismic retrofit work to upgrade an existing building due to the much higher seismic demands. This report contains the structural/seismic findings based on our Tier 1 seismic assessment (using the Immediate Occupancy performance level), our limited observation of existing field conditions, and our experience with buildings of similar size, age and construction type. Potential seismic deficiencies are identified and qualitative conceptual recommendations are outlined for remedial work. An order-of-magnitude conceptual cost estimate is provided for the proposed seismic retrofit work. The findings and recommendations of our Tier 1 assessment outlined herein pertain only to the existing City Hall building s primary lateral load-resisting system. This assessment does not cover seismic anchorage and/or bracing of non-structural items such as electrical/mechanical equipment, ceilings, partitions, or other architectural elements. Further, an assessment of other building systems/features such as mechanical, electrical, plumbing, fire protection, accessibility, egress, drainage, waterproofing, utility services, etc. is beyond the scope of this report. The scope of services for the Tier 1 structural/seismic assessment described in this report is summarized below: 1. Review available as-built structural drawings, previous seismic assessment reports,

6 Page 4 geotechnical reports, etc. for the building. 2. Perform a site visit to observe the existing structural conditions of the building, including the nature and layout of the primary lateral load-resisting system, physical condition of structural members and connections, and damage or deterioration of existing structural framing/connections. [Building finishes will not be disturbed during the site visit and our observation will be limited to the readily visible framing elements]. 3. Perform a Tier 1 seismic assessment of the building based on the methodology outlined in ASCE41-13, using the Immediate Occupancy performance level. 4. Identify structural/seismic deficiencies in the building s framing system based on our field observations during the site visit(s) and the Tier 1 (Immediate Occupancy) seismic assessment. 5. Prepare qualitative conceptual recommendations for the required retrofit work to remedy the identified structural/seismic deficiencies in order to upgrade the building to the Immediate Occupancy performance level as well as for the repair/replacement of the damaged or deteriorated structural framing observed during the site visit. 6. Coordinate with our cost estimating subconsultant, Faithful + Gould (F+G), to prepare an order-of-magnitude conceptual-level construction cost estimate for the proposed structural/seismic retrofit work. 7. Prepare a brief letter report describing the findings of structural/seismic assessment, recommendations for seismic retrofit/repair, and conceptual construction cost estimate for seismic retrofit. AVAILABLE DOCUMENTS The City researched its records for available documents structural drawings, geotechnical reports, previous seismic assessment reports, etc. and provided us the following drawings to review for this seismic assessment: Accessibility Modifications, S-1 to S-3, Steven Duquette, SE and Starks Miers Scott, Architects, dated Aug. 1, Partial Roofing Framing Details, S1, Duquette Engineering, dated July 2004 Police Station Renovations, A2.01, A4.01, and A5.01, Stowers Associates Architects, date Aug. 20, 2004 City Hall Remodel New Steel Rigid Frame, S1 and S2, Duquette Engineering, dated April 14, 2005 Original design drawings (architectural and structural) for. This set included:

7 Page 5 o o Six architectural drawings (sheets 7-12), prepared by William W. Hedley, Jr. Architects, dated March 23, 1970, and Thirteen structural drawings (sheets S1-S13), prepared by Donald R. James, Civil Engineer, dated March 13, The findings and conclusions in this report are based on the available drawings and our site visits on October 22, 2015 and July 18, While most of the structural framing and detailing of the City Hall are covered up by architectural finish materials and cannot be observed directly, areas that could be observed suggest that the building s construction appears to conform with the original design drawings, although this needs to be verified as the project develops. BUILDING DESCRIPTION The 2-story was constructed in the early 1970 s and houses the following city services and departments: Construction Division City Clerk City Manager Code Enforcement Finance Department Human Resources Police Department Public Works The building has administrative offices, meeting rooms, council chambers, staff facilities, and public areas. The existing building is a 2-story, 32,600 sf structure constructed in the early 1970 s. The structure is divided in three areas; the North Wing, which is 15,400 sf; the South Wing, which also is 15,400 sf; and the Central Lobby which is located between the two wings and is 1,800 sf. The building is located on a relatively flat site but has been graded so that the South Wing has full basement walls on south, east and west sides and a partial basement wall on the north side next to the Central Lobby. The North Wing has a full basement wall on the east side and partial basement walls on the south side, next to the Central Lobby, west side and north side which leads to the fenced in parking lot for police vehicles and equipment. Access to the building is available on all four elevations with the primary access for the public through the East and West elevations of the Central Lobby.

8 Page 6 DESCRIPTION OF STRUCTURE The building is constructed with two 70-ft x 110-ft rectangular wings that are offset by 30 feet in the east-west direction. These two wings are separated by a 30-ft x 30-ft central lobby area. The floor- to-floor height of the basement is 12-4 while the second level floor-to-roof heights are divided into two heights of either 12-0 for the lower roof framing and 19-4 for the upper roof framing. The roof and second floor of the building are primarily wood-framed construction, with the second floor constructed with wood-framed exterior walls and steel tubular columns located at the interior and at the exterior perimeter walls. The basement (and partial basement), which serves as the 1 st floor level, is constructed with concrete masonry block walls with some cast-in-place concrete sections and with interior steel tubular columns. The upper roof which is located over the central lobby and the main corridor, which ties the North and South Wings together, has built up roofing on ½ plywood sheathing supported on 2x6 rafters spaced at 24 oc. The 2x6 rafters are supported on either 4x8 or 6x8 timber beams. The 4x and 6x beams are supported on 5x5 steel tubular steel columns located along the outside walls of the corridor. These steel corridor columns are supported at the second floor level. The low roof, which comprises a major portion of the roof, has built-up roofing installed over either ¾ or ½ plywood sheathing. The ¾ sheathing spans a maximum of 48 between fabricated truss-joists while the ½ plywood spans a maximum of 24 between 2x rafters. The truss-joists and rafters are supported on either sawn timber beams, glue-laminated beams or steel wide flange beams. These roof beams are supported on tubular steel columns which are located on the interior of the building and at the exterior perimeter walls. The second floor framing has a 2-inch cellular concrete topping slab poured over 5/8 T&G (tongue and groove) plywood sheathing supported on 2x floor joists spaced at 16 oc. Depending on the span length of the floor joists, 2x6, 2x8, 2x12 and 2x14 floor joists are used. The floor joists are supported on either interior glue-laminated beams of various sizes, 4x sawn timber beams, built-up 2x beams or on the perimeter basement walls of the North and South wings. The perimeter basement walls are 8 inch fully-grouted reinforced concrete masonry block with, in some locations, a cast-in-place reinforced concrete beam located at the top of the concrete masonry block walls. The various size floor beams are supported on interior 5x5 steel tubular columns located in the basement. The basement floor is a 4 slab-on-grade with welded wire mesh reinforcement. The slab is placed on a prepared subgrade consisting of 2 sand layer, membrane vapor barrier and 4 crushed rock layer. The building foundation system consists of continuous reinforced concrete footings below basement masonry walls and isolated reinforced concrete spread footings below steel tube columns.

9 Page 7 The building was designed to resist both wind and seismic loads using the plywood sheathing at the high and low roof levels and at the second floor as horizontal diaphragms. The high roofs are laterally braced using the flexural strength of the 5x5 steel tubular columns which transfer lateral loads to the larger lower roof. The lower roof is laterally supported with either plywood shear walls, which are located at the perimeter of each wing of the building, interior plywood shear walls, which are located on each side and at each end of the main corridor of the building and one steel rigid frame that replaced one of the corridor shear walls in the North Wing during a remodeling project. The second floor diaphragm is laterally braced with the reinforced masonry block basement walls at the perimeter of each wing of the building and interior plywood shear walls at the same approximate locations as the second floor plywood shear walls. There are four entrances to the building at the first story. At grade doors at the north and south ends provide access to finished grade, while a long sloping ramp provides access to both floors near the main entrance located on the east and west sides of the building. The second story has two entrances at each wing of the building and as well as access at the sloping ramps. The roof overhangs the perimeter walls by approximately 3-ft and is supported by exterior steel columns. Selected recent photos of the building are included in Appendix 1. EXISTING CONDITIONS In order to perform a Tier 1 seismic assessment of the, the nature of construction and layout of the current structure had to be determined. The available drawings (noted above) and our site visits on October 22, 2015 and July 18, 2017 provided the basic information to accomplish this task. No destructive investigation or physical testing of existing conditions or materials was performed as part of this assessment. As most of the structural framing is concealed by architectural finishes, not all structural elements of the building were visible during the site visit and not all of the building components relevant for this assessment were able to be verified. The available structural drawings were used to ascertain various details, materials and components. For final design of the retrofit work, a field investigation requiring the removal of finishes in selected areas of the building may be required to verify additional existing conditions and materials. Overall the building appears to be in good physical condition. The wood framing observed at the second floor and roof showed no signs of moisture-related damage or any other type of deterioration. The steel columns and steel connection hardware showed no signs of corrosion. There were no visible indications (cracks in walls, slabs, sidewalks, etc.) that the building has undergone any significant settlement or differential settlement.

10 Page 8 The masonry walls appeared to be in good structural condition. No significant visible cracks were present during the site visits although the masonry wall has been painted and this could obscure small cracks. The presence of steel clips, wood blocking, and other details indicate that the City Hall building was originally designed considering seismic loads. There have been several modifications to the building since its original construction. An existing wood-framed shear wall was removed at the first floor to modify the interior office space. In order to replace the strength of the removed shear wall a new steel moment frame was constructed in a nearby location. Based on the reviewed structural drawings, the moment frame appears to have adequately detailed and constructed to resist seismic loads. Several other non-seismic modifications were made to the building, including new access doors and roof framing strengthening for new rooftop mechanical equipment. SEISMIC EVALUATION AND FINDINGS Evaluation Basis The purpose of this evaluation was to determine whether significant seismic deficiencies exist, to determine the potential seismic risk, and to provide general conceptual recommendations for reduction of seismic risk through mitigation. The Tier 1 methodology of ASCE was used for this preliminary assessment; a full ASCE 41 compliance review using more advanced procedures (such as Tier 2 or Tier 3) was neither intended nor performed. The ASCE 41 Basic Configuration and Structural Checklists for Immediate Occupancy performance level were completed to help identify the potential seismic deficiencies in the City Hall building s lateral load-resisting system. See Appendix 4. The performance criteria used to evaluate a building varies based on the occupancy use of the building. If a building houses a facility such as a police station, fire station, hospital, etc., the building is classified as an essential facility and is required to remain operational after an extreme event such as a major earthquake. The evaluation methodology of ASCE 41 requires an essential facility to be evaluated to the more stringent Immediate Occupancy performance standard. This performance level increases the seismic forces on the structure by a factor of two over the Life Safety criteria (which is commonly used for standard office occupancy buildings). This results in several additional retrofit measures that need to be implemented in order for the building to meet the Immediate Occupancy performance criteria. The analysis methodology of ASCE 41 includes three levels of analytical procedures for seismic assessment of existing structures: a quick check procedure (Tier 1) intended to serve as an aid in quickly identifying high seismic risk structures; a more intensive deficiencybased analysis procedure (Tier 2), and a systematic analysis procedure (Tier 3).

11 Page 9 The Tier 1 quick check employs a set of checklists for each building type, which contain evaluation statements that help identify areas of concern with regard to the structure's ability to adequately transmit earthquake forces to the foundation and supporting grade. This evaluation utilized the Tier 1 checklists, along with the Quick Checks required under this procedure. See Appendix 4. It should be noted that with each building code cycle (every three years), building codes for new design are modified to enhance structural performance during seismic events. However, engineering standards developed to evaluate existing buildings have lagged behind in development. Revisions to ASCE 41 Seismic Evaluation and Retrofit of Existing Buildings were recently completed and this document is intended to replace previous evaluation guidelines as the standard of practice for the seismic evaluation of existing buildings. One of the primary goals of this document is to include lessons learned from past earthquakes. For the, only a structural seismic evaluation of the primary lateral loadresisting system was done per ASCE 41. An assessment of non-structural elements, fire protection, egress, accessibility, mechanical, electrical, plumbing, utility services, waterproofing or drainage requirements was not performed. The would require these other improvements to meet the Essential Facility code requirements, but an assessment of these systems was beyond the scope of this report. Lateral Load-Resisting System Lateral loads for buildings result primarily from earthquake inertia forces acting on structural and non-structural elements. Out-of-plane forces acting on interior and exterior walls are transferred to the roof and floor diaphragms, then to seismic system elements (shear walls, braced frames, etc.) parallel to the direction of the earthquake or wind loads. These elements then transfer the forces to the foundations. At the high roof of the City Hall, the plywood roof diaphragm transfers lateral forces through the steel cantilevered columns into the lower roof diaphragm. At second story the plywood roof diaphragm transfers lateral forces into the perimeter plywood shear walls. At the first story, the plywood second floor diaphragm transfers lateral forces into the masonry shear walls at perimeter of the building. The forces from the second-story plywood shear walls are transferred directly into the first-story masonry shear walls, which then transfer the combined lateral forces to the foundations. Seismic Evaluation Results Our assessment of was based on ASCE 41 Tier 1 analysis, our field observations, our review of the structural drawings, and our experience with buildings of similar size, age and construction type.

12 Page 10 The findings of our Tier 1 seismic assessment indicate that while the City Hall building apparently has a complete lateral load-resisting system, it may have significant deficiencies in the required continuity and/or strength for many of its structural elements/connections that are necessary for satisfactory seismic behavior under the design earthquake. The building is likely to maintain its gravity load-carrying system after the design level earthquake but may experience significant structural damage. Continued post-earthquake building operations may not be possible and the repair costs may be too high to be economically feasible. The existing, therefore, does not meet the seismic resistance requirements for the Immediate Occupancy Structural Performance Level and would require considerable seismic retrofit work to reliably serve as an Essential Facility. Based on the original structural drawings, the masonry shear walls at the first story are fully grouted and reinforced and appear to be adequate for transferring the in-plane seismic loads to the foundations. The in-plane shear connection between the second floor diaphragm and the masonry walls below consists of wood blocking and steel angle clips attached to a continuous wood sill plate with anchor bolts embedded into the masonry wall at each joist. This connection appears to be inadequate for transferring the seismic loads. New anchor bolts will need to be drilled and epoxied through the wood sill and into the masonry walls. The plywood shear walls at the second story appear to be inadequate for transferring the inplane seismic loads at the Immediate Occupancy performance level. Additional shear walls or other seismic resisting elements will be required. Holdowns at the ends of plywood shear walls, while present on the drawings, were concealed by architectural finishes and could not be observed during our site visit. The holdowns shall be field verified and unless their strength is adequate, additional holdowns will need to be added to the existing walls The shear capacities of the roof and second floor plywood diaphragms appear to be adequate for transferring the seismic forces to the shear walls; the details and capacities of the roof diaphragm chords/collectors, however, need strengthening. The steel cantilever columns supporting the high roof appear to be inadequate for transferring the seismic forces into the main roof diaphragm. New lateral elements will need to be added in the clearstory between the high roof and low roof. Based on the Tier 1 evaluation performed (using the Immediate Occupancy performance level), we believe the may have the following potential seismic deficiencies: 1. At low roof level, collectors along shear wall lines are inadequate for transferring the diaphragm load to the shear walls. Addition of new steel straps with blocking between joists is required. 2. At second floor level, building cross-ties are inadequate for transferring out-of-plane masonry wall loads into the floor diaphragm. Addition of new horizontal steel straps or steel rods with holdowns is required at beam splice locations (typically at columns).

13 Page At the second floor level, the wood shear walls are inadequate to transfer in-plane seismic loads. Addition of new plywood at the existing shear walls along with steel straps, and steel rods with holdowns is required. 4. At the second floor level, the masonry wall-to-floor connections appear to be inadequate for both in-plane and out-of-plane wall loads. The addition of new anchor bolts will be required. 5. At the high roof level the steel cantilever columns are inadequate for transferring seismic loads into the main roof diaphragm. New infill stud walls with plywood sheathing are required. RECOMMENDATIONS Based on the seismic deficiencies identified through this preliminary assessment, we believe that the requires, at a minimum, the following retrofit work: 1. At low roof level, provide new collectors along shear wall lines by adding new steel straps over plywood sheathing, with new blocking between the joists. [See Deficiency 1 above]. 2. At second floor level, provide building cross-ties by adding new horizontal steel straps or steel rods with holdowns at beam splice locations (typically at columns). [See Deficiency 2 above]. 3. At second floor level, provide new plywood at several existing shear walls along with new steel straps and steel rods with holdowns. [See Deficiency 3 above]. 4. At the second floor level, provide new anchors bolts drilled through the existing wood sill plate and epoxied into the top of the existing masonry walls. [See Deficiency 4 above]. 5. At the high roof level, provide several new infill wood stud walls with new plywood sheathing at the clearstory between the low roof diaphragm and high roof diaphragm. Refer to Appendix 2 for conceptual seismic retrofit plans showing the extent of this proposed seismic retrofit work. CONCEPTUAL COST ESTIMATE The order-of-magnitude conceptual cost estimate for the required seismic retrofit work identified through our Tier 1 seismic evaluation to meet the Immediate Occupancy performance level is $1.1 million (refer to Appendix 3 for details and assumptions). This estimate only includes retrofit costs directly related to structural strengthening of the building s primary lateral load-resisting system. Potential costs of all other improvements (related to non-structural elements, MEP equipment and systems, furnishings, utility services, etc.) required to upgrade the building as an Essential Facility are excluded.

14 Page 12 FURTHER ACTIONS As indicated by the potential seismic deficiencies in the building outlined above - most of which need further field work, analysis and verification we recommend the following further steps to fully define the scope of required seismic retrofit: 1. Perform an investigative field verification of existing conditions to determine the necessary information on pertinent structural framing and connection details. 2. Perform a detailed ASCE 41 Tier 2 Deficiency-Based Seismic Evaluation of the building using the deficiencies outlined above to allow a more accurate verification and definition of the building s seismic retrofit needs. Develop retrofit concepts. 3. Continued post-earthquake use of a building is not limited just by the extent of earthquake damage to its structural system but, more often than not, might be limited by damage or disruption to non-structural elements of the building, furnishings, MEP components and systems, and availability of utility services. A seismic evaluation of these items is recommended to ensure that all non-structural items of the City Hall are also adequately upgraded to comply with the Essential Facility requirements. The implementation of these actions will help determine the full extent of structural and nonstructural upgrades required for the building and ensure that the upgraded City Hall facility meets the seismic safety requirements for Essential Facilities as well as help define the project s anticipated total construction costs. LIMITATIONS AND DISCLAIMERS The evaluation, findings, conclusions and recommendations outlined in this report were based on limited information. This report has been prepared using the same degree of care and skill ordinarily exercised for this type of professional service by structural engineers practicing in this area at this time. No other warranty, expressed or implied, is made as to the professional advice in this report. This report has been prepared for exclusive use of the City of Campbell and may not be used by any other individual or entity without the express written approval of Biggs Cardosa Associates, Inc.

15 Appendix 1 Photos

16 Page 1-1 Photo 1 West elevation view Photo 2 West elevation view (north end)

17 Page 1-2 Photo 3 South elevation view Photo 4 East entrance view

18 Page 1-3 Photo 5 North elevation view Photo 6 Ramp at East entrance

19 Page 1-4 Photo 7 High roof with steel cantilevered columns Photo 8 Clearstory at High roof

20 Page 1-5 Photo 9 Broken tiles at upper roof Photo 10 Interior steel columns at second floor

21 Page 1-6 Photo 11 Interior open roof framing below upper roof Photo 12 Bolted wood sill plate at masonry wall

22 Page 1-7 Photo 13 Wood floor joists Photo 14 Wood blocking at plywood diaphragm

23 Page 1-8 Photo 15 Simpson steel clips at floor framing Photo 16 Ramp at West elevation

24 Page 1-9 Photo 17 Wood ledger at concrete vault

25 Appendix 2 Conceptual Seismic Retrofit Plans

26 70 ft 30 ft 70 ft (E) Concrete masonry shearwall below, typ 110 ft Holdowns with steel rods, typ 110 ft N Indicates (N) seismic tie - steel rods with holdowns each side of (E) beams below second floor diaphragm Indicates (N) anchor bolts through (E) 2x wood sill epoxied into top of CMU/conc walls at 4'-0" on center SECOND FLOOR PLAN (Immediate Occupancy) 70 N. First St, Campbell, CA

27 70 ft 30 ft 70 ft 110 ft (E) Wood shearwall below, typ 110 ft N Indicates (N) wood blocking below roof diaphragm Indicates (N) steel strap on (E) plywood diaphragm Indicates additional (N) plywood at (E) shearwalls with holdowns Indicates (N) seismic tie - steel rods with holdowns each side of (E) beams below lower rood diaphragm LOWER ROOF PLAN (Immediate Occupancy) 70 N. First St, Campbell, CA

28 Indicates additional (N) plywood and studs at clear story between high roof and low roof Indicates (N) seismic tie steel rods with holdowns each side of (E) beams below high roof HIGH ROOF PLAN (Immediate Occupancy) 70 N. First St, Campbell, CA

29 Appendix 3 Conceptual Cost Estimate

30 Tier 1 - Seismic Assessment (Essential Facility) Campbell, CA Rough Order of Magnitude Cost Estimate (DRAFT) August 15, 2017 Faithful+Gould 332 Pine Street, 5th Floor, San Francisco CA phone: fax:

31 Tier 1 - Seismic Assessment (Essential Facility) Campbell, CA Rough Order of Magnitude Cost Estimate (DRAFT) 15-Aug-17 INTRODUCTION This opinion of probable cost has been prepared to reflect the anticipated construction cost for the proposed seismic retrofit work based on a Tier 1 Seismic Assessment (Essential Facility) for Campbell City Hall, Campbell, California. This document is based on the measurement and pricing of quantities wherever information is provided and/or reasonable assumptions for other works not covered in the drawings and programs as stated in this document. The unit rates reflected herein have been obtained from historical records and discussion with subcontractors and suppliers. All unit rates relevant to subcontractor works include the subcontractors overheads and profit. Project Scope The proposed seismic retrofit work covers 2 levels that includes seismic ties using steel rods and hold downs at existing glu-lam beams and anchor bolts to perimeter walls below the second floor diaphragm. The work on the lower roof plan consists of wood blocking, steel straps and new plywood with steel rods and hold downs at corner walls. The high roof clearstory will be selectively replaced with infill plywood on stud framing. Finishes are replaced only at locations where seimsic work are needed. Documentations Faithful+Gould received the following documents from Biggs Cardosa Associates, Inc. for the preparation of this estimate: Drawings Marked-up existing second floor, lower roof and high roof plans dated August 15, Architectural drawings sheet 7, 8, 9, 10, 11 and 12 dated March 23, 1970 Photographs extracted from Tier 1 Seismic Evaluation dated November 12, Reports No reports or narratives are available Phasing and Temporary Works No phasing or temporary works have been included in the cost estimate. Design Contingency A design contingency of 20% is included for the development of the design drawings to 100% CD set. Escalation No escalation has been included in the cost estimate. Exclusions Legal and accounting fees Relocation of existing owner s furniture, furnishings and equipment Removal of unforeseen obstructions behind walls Overtime and weekend work Hazardous material abatement Faithful+Gould Page 2 of 9

32 Tier 1 - Seismic Assessment (Essential Facility) Campbell, CA Rough Order of Magnitude Cost Estimate (DRAFT) 15-Aug-17 INTRODUCTION Temporary swing space and temporary accommodation for the various functional spaces while under construction. Design-build procurement delivery Phased work is excluded. Escalation Fire inspection fees Special inspection fees Permits, expediting and filing Items that may affect the cost estimate Modifications to the scope of work included in this estimate. Unforeseen sub-surface conditions. Restrictive technical specifications or excessive contract conditions. Non-competitive bid/market situations. Recommendation for Cost Control Faithful+Gould recommends that the owner, architect and engineers carefully review this document, including line item descriptions, unit prices, clarifications, exclusions, inclusions and assumptions, contingencies, escalation, and markups. If the project is over budget, or if there are unresolved budgeting issues, alternative systems/schemes should be evaluated before proceeding into the Bidding phase. Requests for modifications of any apparent errors or omissions to this document must be made to Faithful+Gould within ten (10) days of receipt of this estimate. Otherwise, it will be understood that the contents have been concurred with and accepted. Opinion of Probable Cost This opinion has been based on a competition open bid situation with a recommended 5-7 reputable bids from general contractors and a minimum of 3 bidders for all items of sub-contracted work. Experience indicates that a fewer number of bidders may result in higher bids, conversely an increased number of bidders may result in more competitive bids. Since Faithful+Gould has no control over the cost of labor, materials, or equipment, or over the contractor's method of determining prices, or over competitive bidding or market conditions, the opinion of probable construction cost provided for herein is made on the basis of professional experience and qualifications. The opinion represents Faithful + Gould's best judgment as a professional construction consultant familiar with the construction industry. However, Faithful+Gould cannot and does not guarantee that proposals, bids, or the construction cost will not vary from opinions of probable cost prepared by them. Faithful+Gould Page 3 of 9

33 Rough Order of Magnitude Cost Estimate (DRAFT) Tier 1 - Seismic Assessment (Essential Facility) 15-Aug-17 Campbell, CA Area Tabulation Location Wing (SF) Central Lobby (SF) Total Area (SF) First Floor 15, ,300 Second Floor 15, ,300 Total 30,800 1,800 32,600 FAITHFUL + GOULD Page 4 of 9

34 Tier 1 - Seismic Assessment (Essential Facility) Campbell, CA COST SUMMARY Rough Order of Magnitude Cost Estimate (DRAFT) 15-Aug-17 Descriptions $ 32,600 SF 1 General Requirements Existing Conditions 156, Concrete Masonry Metals 138, Woods and Plastics 104, Thermal Moisture and Waterproofing 51, Doors and Windows Finishes 159, Specialties Equipment Furnishings Special Construction Conveying Equipment Fire Suppression Plumbing Heating, Ventilating and Air-conditioning (HVAC) 6, Integrated Automation Electrical 12, Communications Electronic Safety and Security Earthwork Exterior Improvements Utilities 0.00 TOTAL Building and Siteworks 628, Phasing and Temporary Works 0.00% Insurance and Bond 2.00% 12, General Requirements (4 months construction) 145, Profit 10.00% 78, BASIC CONSTRUCTION ESTIMATE 865, Design Contingency 20.0% 173, TOTAL CONSTRUCTION COST (Present) 1,038, Escalation (Excluded) 0.00% I. TOTAL CONSTRUCTION COST (Future) 1,038, A. Architect and Engineering Fees 0.00% B. Project Management Fees 0.00% C. Miscellaneous Consulting Services 0.00% D. Project/Construction Contingency 0.00% II. TOTAL SOFT COST GROSS TOTAL (I+II (Future Cost) 1,038, Faithful + Gould Page 5 of 9

35 Tier 1 - Seismic Assessment (Essential Facility) Campbell, CA Rough Order of Magnitude Cost Estimate (DRAFT) 15-Aug-17 DETAILED ESTIMATE Description Qty Unit Rate Total 1 GENERAL REQUIREMENTS See Summay page TOTAL GENERAL REQUIREMENTS 2 EXISTING CONDITIONS Selective Demolition Open up ceiling soffits to access work areas hard ceiling (25% assumption) beam below second floor 163 SF ,063 perimeter concrete / CMU wall 348 SF ,688 below roof diaphragm at lower roof 505 SF ,625 - suspended ceiling (75% assumption) beam below second floor 488 SF ,875 perimeter concrete / CMU wall 1,043 SF ,425 below roof diaphragm at lower roof 1,515 SF ,150 Remove roofing tile for new metal strap 864 LF ,640 Remove existing finishes and prepare for new plywood wall lining 3,850 SF ,250 Remove glazed clearstory interior 198 SF ,940 exterior 594 SF ,820 Temporary barricades and protection 56 LOC ,000 Miscellaneous Miscellaneous demolition 1 LS 10, ,748 Haul and dispose 1 LS 10, ,000 TOTAL EXISTING CONDITIONS 156,223 3 CONCRETE Not Applicable TOTAL CONCRETE 4 MASONRY Not Applicable TOTAL MASONRY Faithful + Gould Page 6 of 9

36 Tier 1 - Seismic Assessment (Essential Facility) Campbell, CA Rough Order of Magnitude Cost Estimate (DRAFT) 15-Aug-17 DETAILED ESTIMATE Description Qty Unit Rate Total 5 METALS Seismic tie comprising steel rods with hold-downs each side of glu-lam beams where indicated - intersecting cross beams 18 LOC 1, ,609 - longitudinal beams at interior walls 6 LOC ,228 - longitudinal beams at exterior walls 8 LOC ,459 - longitudinal beams below high roof 8 LOC ,638 New anchor bolts including drilling through existing 2 x wood sill and epoxied into top of CMU / concrete wall 174 EA ,031 Prepare existing plywood roof diaphragm and install steel straps 864 LF ,880 Hold downs at plywood wall lining 30 LOC ,000 Miscellaneous metal allowance 1 LS 10, ,321 Scaffolding, allowance 9,828 SF ,655 TOTAL METALS 138,821 6 WOODS AND PLASTICS 3 x Wood blocking between roof joists 540 LF ,900 1/2" thick plywood wall sheathing 3,850 SF ,500 Clearstory window infill comprising plywood on wood stud framing interior (plywood lining both sides) 198 SF ,900 exterior (plywood lining one side) 594 SF ,760 Miscellaneous rough carpentry etc 1 LS 13, ,659 TOTAL WOODS AND PLASTICS 104,719 7 THERMAL MOSITURE AND WATERPROOFING Replace roofing tiles to match including membrane underneath 864 LF ,600 Wall insulation at infill to clearstory opening 594 SF ,782 Flashing at clearstory infill 486 LF ,010 Caulking and sealants 1,638 LF ,465 TOTAL THERMAL MOSITURE AND WATERPROOFING 51,857 8 DOORS AND WINDOWS Not Applicable TOTAL DOORS AND WINDOWS 9 FINISHES Exterior Finishes Cement plaster including paint finish at clearstory infill to match existing exterior walls 594 SF ,790 Faithful + Gould Page 7 of 9

37 Tier 1 - Seismic Assessment (Essential Facility) Campbell, CA Rough Order of Magnitude Cost Estimate (DRAFT) 15-Aug-17 DETAILED ESTIMATE Description Qty Unit Rate Total Interior Finishes Wall Finishes Patch and paint gypsumboard wall sheathing 3,850 SF ,500 Paint plywood infill at clearstory 990 SF ,375 Allowance for wall tiles in restroom walls 481 SF ,219 Ceiling Finishes Patch and paint gypsumboard ceiling soffits 1,015 SF ,525 Replace suspended ceiling tiles 3,045 SF ,450 Miscellaneous Make good adjacent finishes, allowances 1 LS 14, ,486 TOTAL FINISHES 159, SPECIALTIES Not Applicable TOTAL SPECIALTIES 11 EQUIPMENT Not Applicable TOTAL EQUIPMENT 12 FURNISHINGS Not Applicable TOTAL FURNISHINGS 13 SPECIAL CONSTRUCTION Not Applicable TOTAL SPECIAL CONSTRUCTION 14 CONVEYING EQUIPMENT Not Applicable TOTAL CONVEYING EQUIPMENT 21 FIRE SUPPRESSION Not Applicable TOTAL FIRE SUPPRESSION Faithful + Gould Page 8 of 9

38 Tier 1 - Seismic Assessment (Essential Facility) Campbell, CA Rough Order of Magnitude Cost Estimate (DRAFT) 15-Aug-17 DETAILED ESTIMATE Description Qty Unit Rate Total 22 PLUMBING Not Applicable TOTAL PLUMBING 23 HEATING, VENTILATING AND AIR-CONDITIONING (HVAC) Allowances for diffuser removal and relocation etc 1 LS 6, ,000 TOTAL HEATING, VENTILATING AND AIR-CONDITIONING (HVAC) 6, INTEGRATED AUTOMATION Not Applicable TOTAL INTEGRATED AUTOMATION 26 ELECTRICAL Allowances for light fixture removal and relocation etc 1 LS 12, ,000 TOTAL ELECTRICAL 12, COMMUNICATIONS Not Applicable TOTAL COMMUNICATIONS 28 ELECTRONICS SAFETY AND SECURITY Not Applicable TOTAL ELECTRONICS SAFETY AND SECURITY 31 EARTHWORK Not Applicable TOTAL EARTHWORK 32 EXTERIOR IMPROVEMENTS Not Applicable TOTAL EXTERIOR IMPROVEMENTS 33 UTILITIES Not Applicable TOTAL UTILITIES Faithful + Gould Page 9 of 9

39 Appendix 4 ASCE 41 Tier 1 Checklists

40

41

42

43

44

45

TIER 1 SEISMIC EVALUATION

TIER 1 SEISMIC EVALUATION TIER 1 SEISMIC EVALUATION Immediate Occupancy Structural Performance Level Campbell, California Prepared For: City of Campbell 70 North First Street Campbell, California Prepared By: Biggs Cardosa Associates,

More information

TIER 1 SEISMIC EVALUATION

TIER 1 SEISMIC EVALUATION TIER 1 SEISMIC EVALUATION Campbell Library Campbell, California Draft Report Prepared For: City of Campbell 70 North First Street Campbell, California Prepared By: Biggs Cardosa Associates, Inc. 101 California

More information

Structural Inspection

Structural Inspection General: Background: An inspection and structural analysis have been performed for the purpose of evaluating the buildings structural systems and components. A full set of structural drawings was utilized

More information

Project Seismic Vulnerability Assessment For SFCC District Building 33 Gough Street San Francisco, California 94103

Project Seismic Vulnerability Assessment For SFCC District Building 33 Gough Street San Francisco, California 94103 Project For SFCC District Building 33 Gough Street San Francisco, California 94103 Prepared For San Francisco Community College District 33 Gough Street San Francisco, California 94103 Prepared By Thornton

More information

Framing Methods Structural Components

Framing Methods Structural Components Framing Methods Structural Components Balloon Framing *Balloon framing or Eastern framing the exterior studs run from the top of the foundation to the top of the highest level. Benefits of this type of

More information

SEATTLE CENTRAL COLLEGE BROADWAY PERFORMANCE HALL SEATTLE, WASHINGTON STRUCTURAL EVALUATION FOR PREPARED BY PCS STRUCTURAL SOLUTIONS

SEATTLE CENTRAL COLLEGE BROADWAY PERFORMANCE HALL SEATTLE, WASHINGTON STRUCTURAL EVALUATION FOR PREPARED BY PCS STRUCTURAL SOLUTIONS STRUCTURAL EVALUATION FOR SEATTLE CENTRAL COLLEGE BROADWAY PERFORMANCE HALL SEATTLE, WASHINGTON PREPARED BY PCS STRUCTURAL SOLUTIONS NOVEMBER 1, 2017 17-733 TABLE OF CONTENTS Page I. PREFACE ii II. EXECUTIVE

More information

STRUCTURAL EVALUATION OF TARA HILLS ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD)

STRUCTURAL EVALUATION OF TARA HILLS ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) STRUCTURAL EVALUATION OF TARA HILLS ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) For WLC Architects Kaiser Building 1300 Potrero Avenue Richmond, CA 94804 By DASSE Design, Inc.

More information

STRUCTURAL EVALUATION OF WASHINGTON ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD)

STRUCTURAL EVALUATION OF WASHINGTON ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) STRUCTURAL EVALUATION OF WASHINGTON ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) For WLC Architects Kaiser Building 1300 Potrero Avenue Richmond, CA 94804 By DASSE Design, Inc.

More information

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax:

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax: ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA 02144 Tel: 617.628.1700 Fax: 617.628.1711 March 3, 2016 Mr. Jeff Hoover, Principal Tappe Architects, 6 Edgerly Place

More information

STRUCTURAL EVALUATION OF DOVER ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD)

STRUCTURAL EVALUATION OF DOVER ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) STRUCTURAL EVALUATION OF DOVER ELEMENTARY SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) For WLC Architects Kaiser Building 1300 Potrero Avenue Richmond, CA 94804 By DASSE Design, Inc. 33 New

More information

Building Division Informational Handout

Building Division Informational Handout CITY OF SAN JOSÉ, CALIFORNIA Building Division Informational Handout Conventional Light Frame Construction Design Provisions 2007 CBC Handout No. 2-21 Published: 1/1/08 Page 1 of 3 This document summarizes

More information

Plan Check No. Checked by: An Appointment Is Required for Verification

Plan Check No. Checked by: An Appointment Is Required for Verification SUPPLEMENTAL CORRECTION SHEET UNREINFORCED MASONRY (URM) RETROFIT ( 2002 LABC ) Plan Check No. Checked by: Permit Appl. # An Appointment Is Required for Verification Job Address: For appt. call: APPLICATION

More information

Supplemental Plan Check List for Unreinforced Masonry (URM) Retrofit

Supplemental Plan Check List for Unreinforced Masonry (URM) Retrofit Supplemental Plan Check List for Unreinforced Masonry (URM) Retrofit Plan Check/PCIS App #: Job Address: P.C. Engineer: Phone: (E -mail: first name.last name@ lacity.org) For instructions and other information,

More information

UCC Permit Application Procedures

UCC Permit Application Procedures How do I apply for a permit? UCC Permit Application Procedures 1. Please complete the CodeMaster Pan Review Application 2. Please provide the scope of work description and/or construction documents/plans.

More information

SECTION WOOD FRAMING. A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents.

SECTION WOOD FRAMING. A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents. SECTION 06110 WOOD FRAMING PART 1 GENERAL 1.1 SUMMARY A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents. B. Products Installed But Not Supplied

More information

ADDENDA #9- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services

ADDENDA #9- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services ADDENDA #9- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services Addenda Dated: 01/25/2019 PURPOSE: The purpose of this Addenda #9 is to provide a

More information

Attachment A. USG Minimum Design and Construction Requirements for Wood Framed Structures

Attachment A. USG Minimum Design and Construction Requirements for Wood Framed Structures Attachment A USG Minimum Design and Construction Requirements for Wood Framed Structures 1. General Design Criteria 1.1. Per Adopted Georgia State Minimum Standard Building Code 1.2. Minimum Live Loads

More information

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings Building Safety Department 400-2 nd Street South St. Cloud, MN 56301 (320) 255-7239 A building permit is required for any accessory

More information

FEMA P-593 STEP-BY STEP PRESCRIPTIVE RETROFIT FOR CRIPPLE WALL BRACING & ANCHORAGE TO FOUNDATION

FEMA P-593 STEP-BY STEP PRESCRIPTIVE RETROFIT FOR CRIPPLE WALL BRACING & ANCHORAGE TO FOUNDATION INTRODUCTION Objective of provisions: The provisions of IEBC Appendix Chapter A3 are intended to reduce hazard of earthquake-induced damage (IEBC A301.1). These provisions are not intended to eliminate

More information

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No 000130 1 PURPOSE: Professional Engineering Consultants, P.A. (PEC) was engaged by University of Kansas Design & Construction Management to perform an assessment of Stouffer Place Apartment Building 20

More information

SECTION WOOD FRAMING. A. Includes But Not Limited To: 1. Furnish and install wood framing and blocking as described in Contract Documents.

SECTION WOOD FRAMING. A. Includes But Not Limited To: 1. Furnish and install wood framing and blocking as described in Contract Documents. SECTION 06 1100 WOOD FRAMING PART 1 - GENERAL 1.1 SUMMARY A. Includes But Not Limited To: 1. Furnish and install wood framing and blocking as described in Contract Documents. B. Products Installed But

More information

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC)

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC) Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC) Plan Check Submittal Date: Plan Check #: Permit App.# Job Address: Applicant: Phone: ( ) P.C. Engineer: Phone:

More information

Structural Assessment Report 2118 Milvia Street Berkeley, California

Structural Assessment Report 2118 Milvia Street Berkeley, California 2118 Milvia Street Berkeley, California REPORT PREPARED FOR: PERALTA COMMUNITY COLLEGE DISTRICT REPORT PREPARED BY: KPW STRUCTURAL ENGINEERS, INC KPW PROJECT NO. 14C199.00 19 JUNE 2014 Table of Contents

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM Project Name: Finish Water Pump Station (FWPS) Date: October 15, 2015 Client: City of Vallejo Project Number: 07784B.10 Prepared By: Reviewed By: Subject: Crystal Starr, P.E. Mike

More information

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.)

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.) DIVISION 94 VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.) SEC. 91.9401. PURPOSE. (Amended by Ord. No. 172,592, Eff. 6/28/99,

More information

SEISMIC DESIGN GUIDELINES

SEISMIC DESIGN GUIDELINES INTRODUCTION The purpose of these Seismic Design Guidelines is to provide additional information and clarification to Civil or Structural engineers in order to comply with Ordinance No. 18-O- 2767 for

More information

Administrative Changes

Administrative Changes Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings

More information

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows: ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan

More information

Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation SCI Project Number:

Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation SCI Project Number: 27 June 2016 Mr. Shane Chism, AIA Breckenridge Group 4625 E. Fort Lowell Road Tucson, Arizona 85712 Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation

More information

Structural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/

Structural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/ 120 Montgomery Street, Suite 1410 San Francisco, California 94104 415/781-1505 Fax 415/781-2718 sde@sdesf.com Rajendra Sahai, SE Principal John W. Laws, SE Principal Steven Lepisto, SE Principal STRUCTURAL

More information

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity System Codes and Criteria Design Codes and Standards The design code used is the Wisconsin Administrative Code along with the State of Wisconsin Department of Commerce-Safety & Buildings Chapters Comm

More information

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC)

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC) Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC) Plan Check Submittal Date: Plan Check #: Permit App.# Job Address: Applicant: Phone: ( ) Plan Check Engineer:

More information

HOLDOWN & STRAP SCHEDULE

HOLDOWN & STRAP SCHEDULE SHEAR WALL SCHEDULE STRUCTURAL DESIGN CRITERIA GOVERNING CODE SOIL BEARING PRESSURE HOLDOWN & STRAP SCHEDULE MARK SHEATHING SHEATH BOTH SIDES NAILS EDGE SPACING NOTES MARK SW 7/" OSB NO 8d " OC - A SW

More information

WOOD I-JOIST AWARENESS GUIDE

WOOD I-JOIST AWARENESS GUIDE WOOD I-JOIST AWARENESS GUIDE American Wood Council Flange Web Flange American Forest & Paper Association WOOD I-JOIST AWARENESS GUIDE The American Wood Council is part of the wood products group of the

More information

Mandatory Wood Frame Soft-story Retrofit Program PERMITTING AND INSPECTION PROCESS GUIDELINES

Mandatory Wood Frame Soft-story Retrofit Program PERMITTING AND INSPECTION PROCESS GUIDELINES INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LAMC Division 93 Effective: 11/22/2015 DOCUMENT NO.: P/BC 2017-136 Revised: 1/11/2017 Previously Issued As: N/A Mandatory Wood Frame Soft-story

More information

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage The following list of code requirements is intended to assist you in complying with the Code of Public

More information

STRUCTURAL CONDITION ASSESSMENT

STRUCTURAL CONDITION ASSESSMENT STRUCTURAL CONDITION ASSESSMENT ALLEN JAY ROCK GYM 1201 FAIRFIELD ROAD HIGH POINT, NC Prepared for: Prepared by: Guilford County Schools 617 West Market Street Greensboro, NC Adrian S. Durham, PE, SE,

More information

City of Hughson Building Safety Division 7018 Pine Street Hughson, CA (209)

City of Hughson Building Safety Division 7018 Pine Street Hughson, CA (209) City of Hughson Building Safety Division 7018 Pine Street Hughson, CA 95326 (209) 883-4054 RESIDENTIAL ATTACHED PATIO COVERS Patio covers are one story roofed structures not more than 12 feet above grade,

More information

Shaft Wall Solutions for Wood-Frame Structures. Ricky McLain, PE, SE WoodWorks Wood Products Council Boston & Waltham Workshops, December 6 & 7, 2017

Shaft Wall Solutions for Wood-Frame Structures. Ricky McLain, PE, SE WoodWorks Wood Products Council Boston & Waltham Workshops, December 6 & 7, 2017 Shaft Wall Solutions for Wood-Frame Structures Ricky McLain, PE, SE WoodWorks Wood Products Council Boston & Waltham Workshops, December 6 & 7, 2017 Shaft Walls Shaft Walls Form Shaft Enclosures The purpose

More information

NCMA TEK RESIDENTIAL DETAILS FOR HIGH WIND AREAS. TEK 5-11 Details (2003)

NCMA TEK RESIDENTIAL DETAILS FOR HIGH WIND AREAS. TEK 5-11 Details (2003) NCM TEK National Concrete Masonry ssociation an information series from the national authority on concrete masonry technology RESIDENTIL DETILS FOR HIGH WIND RES TEK 5-11 Details (2003) Keywords: architectural

More information

Mandatory Wood Frame Soft-story Retrofit Program STRUCTURAL DESIGN GUIDELINES

Mandatory Wood Frame Soft-story Retrofit Program STRUCTURAL DESIGN GUIDELINES INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LAMC Division 93 Effective: 11/22/15 DOCUMENT NO.: P/BC 2014-137 Revised: 06/07/16 Previously Issued As: N/A Mandatory Wood Frame Soft-story

More information

The designer shall also submit additional information required by the University as described and underlined below.

The designer shall also submit additional information required by the University as described and underlined below. I. Structural Engineering Submissions The designer shall submit all information required by the State Construction Office (SCO) as described in the State Construction Manual Chapter 300 - Project Design

More information

Supplemental Concrete Tilt Up Retrofit Plan Check Correction Sheet (2014 LABC)

Supplemental Concrete Tilt Up Retrofit Plan Check Correction Sheet (2014 LABC) Supplemental Concrete Tilt Up Retrofit Plan Check Correction Sheet (2014 LABC) Plan Check Submittal Date: Plan Check / PCIS App #: Job Address: Applicant: P.C. Engineer: (Print first / last name) Phone:

More information

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: IRC CODE UPDATES TO: RESIDENTIAL BUILDING CONTRACTORS FROM: GARY STABER, BUILDING OFFICIAL SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: 6/1/2003 INTERNATIONAL RESIDENTIAL CODE (IRC) APPLICABILITY:

More information

ADDENDA #4- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services

ADDENDA #4- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services ADDENDA #4- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services Addenda Dated: 01/16/2018 PURPOSE: The purpose of this Addenda #4 is to provide a

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

Lonsdale Building Inspections Department 415 Central Street W. PO Box 357 Lonsdale, MN (507) fax (507)

Lonsdale Building Inspections Department 415 Central Street W. PO Box 357 Lonsdale, MN (507) fax (507) Lonsdale Building Inspections Department 415 Central Street W. PO Box 357 Lonsdale, MN 55046 (507) 744-2327 fax (507) 744-5554 2006 RESIDENTIAL CONSTRUCTION CHECKLIST The following checklist has been designed

More information

PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C

PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No. 20140101C CONSTRUCTION ESTIMATE AND PROJECT BUDGET Dated June 7. 2014 Estimated Cost HARD COSTS $ 1,560,284 Core Renovations (Toilet Rooms, Ceilings

More information

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT 1 East Franklin Street Phone: 301-790-4163 Third Floor Hagerstown, MD 21740 Fax: 301-791-2650 BUILDING PERMIT APPLICATION FOR RESIDENTIAL ACCESSORY

More information

THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS

THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE II RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING

More information

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program ENTRY FORM DVASE 2014 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M Other Structures Under $5M Buildings

More information

BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS

BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS Please note: This construction plan component list is to be used as a guide to assist you with your project. There may be elements unique to your project not

More information

GARAGE MAIN FLOOR PLAN

GARAGE MAIN FLOOR PLAN BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS. SHED TO BE BUILT AS PER IRC, UBC OR CURRENT LOCAL CODE To the best of my knowledge

More information

The Homeowner s Building Application Checklist for Constructing a Residential Addition

The Homeowner s Building Application Checklist for Constructing a Residential Addition The Homeowner s Building Application Checklist for Constructing a Residential Addition This checklist provides homeowners a summary of the Building Permit submission requirements for constructing a residential

More information

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012) Gaines Charter Township 8555 Kalamazoo Ave SE Caledonia MI 49316 PH: 616 698-6640 Fax: 616 698-2490 www.gainestownship.org Building Department Statement of Special Inspections Michigan Building Code 2012

More information

Garage/Accessory Structures

Garage/Accessory Structures Garage/Accessory Structures City of New Prague Building Inspections Department 118 Central Ave N New Prague, MN 56071 (952) 758-4401 Fax (952) 758-1149 Requirements for submitted Building Plans Signed

More information

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM

More information

Project. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal

Project. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal Project San Jose City College Physical Education Building PLACE IMAGE HERE Prepared For Ken Bauer, AIA Principal LPAS 2484 Natomas Park Drive Sacramento, CA 95833 916.443.0335 Prepared By Steve Ratchye,

More information

How to Estimate the Cost of a Medical Office Building Using Conceptual BIM (DProfiler)

How to Estimate the Cost of a Medical Office Building Using Conceptual BIM (DProfiler) How to Estimate the Cost of a Medical Office Building Using Conceptual BIM (DProfiler) CPE Candidate No. 0115805 July 2015 1 P age How to Estimate the Cost of a Medical Office Building Using Conceptual

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

Home Not Anchored to Foundation

Home Not Anchored to Foundation IDENTIFY WEAKNESSES Home Not Anchored to Foundation Houses that are not bolted to the foundation can move off their foundations during earthquakes. Go down into the crawl space the area between the first

More information

Structural Condition Assessment

Structural Condition Assessment 108 6 th Street, Garland, Texas Engineering Report Date: September 29, 2016 RLG No. : 16729 Prepared for: Mr. Jeff D. Bulls III AIA 3030 LBJ Freeway, Suite 1220 Dallas, TX 75234 PM: Harold F. Phillips

More information

Exterior Elevated Elements Inspection Guidelines

Exterior Elevated Elements Inspection Guidelines Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code

More information

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Executive Summary:, located in Pigeon Forge, Tennessee, is designed as a multifunctional space and

More information

U.S. EDITION RESIDENTIAL CONSTRUCTION DETAILS SAMPLE. A visual guide to construction detailing. Emma Walshaw

U.S. EDITION RESIDENTIAL CONSTRUCTION DETAILS SAMPLE. A visual guide to construction detailing. Emma Walshaw RESIDENTIAL CONSTRUCTION DETAILS U.S. EDITION A visual guide to construction detailing Emma Walshaw Contents INTRODUCTION 4 PRINCIPLES OF CONSTRUCTION DETAILING 6 FOUNDATIONS 9 PRINCIPLES OF FOUNDATION

More information

Division 00 Procurement and Contracting Requirements

Division 00 Procurement and Contracting Requirements SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders

More information

Stone and Masonry Veneer

Stone and Masonry Veneer Stone and Masonry Veneer R703.7 Stone and masonry veneer, general. Stone and masonry veneer shall be installed in accordance with this chapter, Table R703.4 and Figure R703.7. These veneers installed over

More information

NOTE: For construction other than new commercial or additions (renovations), only those areas below describing the scope of work will be applicable.

NOTE: For construction other than new commercial or additions (renovations), only those areas below describing the scope of work will be applicable. Applicant s Name: New Commercial - Commercial Additions Renovations Permit Plan Submittal Check List Applicant s Phone Number (s): Project Address: Project Type: _New Commercial or Commercial Addition

More information

CODE ANALYSIS REPORT SECOND FLOOR

CODE ANALYSIS REPORT SECOND FLOOR CODE ANALYSIS REPORT SECOND FLOOR 384 DWIGHT STREET HOLYOKE, MA Prepared by Dietz & Company Architects, Inc. 17 Hampden Street Springfield, MA March 2014 INTRODUCTION The following report is a preliminary

More information

Single Family Residential Building Permit Questions & Answers

Single Family Residential Building Permit Questions & Answers City Of Edwardsville Public Works Department 200 East Park Street Edwardsville, IL 62025 (618)692-7535 (618)692-7505 Fax Hours: Monday thru Friday 8:00 AM to 5:00 PM Single Family Residential Building

More information

HATFIELD TOWNSHIP DECK/PATIO PERMIT PROCEDURES

HATFIELD TOWNSHIP DECK/PATIO PERMIT PROCEDURES HATFIELD TOWNSHIP DECK/PATIO PERMIT PROCEDURES A deck/patio permit is required for all construction including decks, renovation of existing decks/patio, paver patios, and retaining walls (over 30 inches).

More information

Interior Architects, P.C REV 2 CONCEPTUAL ESTIMATE. Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY GARDINER AND THEOBALD INC FOR: AT:

Interior Architects, P.C REV 2 CONCEPTUAL ESTIMATE. Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY GARDINER AND THEOBALD INC FOR: AT: REV 2 CONCEPTUAL ESTIMATE FOR: Interior Architects, P.C Brooklyn Heights Library, Brooklyn Public Library, Brooklyn, NY AT: BY: GARDINER AND THEOBALD INC Issued: 6/20/2013 BROOKLYN HEIGHTS LIBRARY, BROOKLYN

More information

Table 3. Detailed Comparison of Structural Provisions of IRC 2000 and 1997 NEHRP (Continued)

Table 3. Detailed Comparison of Structural Provisions of IRC 2000 and 1997 NEHRP (Continued) 2000 IRC 1997 NEHRP Section Provision Section Provision Comments CHAPTER 3 BUILDING PLANNING R301 DESIGN CRITERIA R301.2.2 Seismic Provisions R301.2.2.1 Determination of Seismic Design Category R301.2.2.1.1

More information

ALTERNATE DESIGN METHODOLOGY FOR UNREINFORCED MASONRY BUILDINGS

ALTERNATE DESIGN METHODOLOGY FOR UNREINFORCED MASONRY BUILDINGS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC 8808 Effective: 01-01-2011 DOCUMENT NO. P/BC 2011-053 Revised: Previously Issued As: P/BC 2008-053 I. GENERAL ALTERNATE DESIGN METHODOLOGY

More information

STRUCTURAL EVALUATION OF JOHN F. KENNEDY HIGH SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD)

STRUCTURAL EVALUATION OF JOHN F. KENNEDY HIGH SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) STRUCTURAL EVALUATION OF JOHN F. KENNEDY HIGH SCHOOL WEST CONTRA COSTA UNIFIED SCHOOL DISTRICT (WCCUSD) For WLC Architects Kaiser Building 1300 Potrero Avenue Richmond, CA 94804 By DASSE Design, Inc. 33

More information

CALIFORNIA BUILDING PLANS EXAMINER CONTENT OUTLINE 01. GENERAL ADMINISTRATION 3 % Project Administration 3%

CALIFORNIA BUILDING PLANS EXAMINER CONTENT OUTLINE 01. GENERAL ADMINISTRATION 3 % Project Administration 3% CALIFORNIA BUILDING PLANS EXAMINER CONTENT OUTLINE EXAM ID: I6 80 multiple-choice questions 3-1/2-hour time limit Open book 01. GENERAL ADMINISTRATION 3 % 0101. Project Administration 3% Verify that plans,

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

ASCE Structural Evaluation Report

ASCE Structural Evaluation Report ASCE 31-03 Structural Evaluation Report For 2 Dinkelspiel Station Lane Atherton, California February 11, 2009 Prepared for: Prepared by: Town of Atherton Crosby Group Office of the City Clerk 726 Main

More information

A. Remove Table of Contents and insert new attached Table of Contents.

A. Remove Table of Contents and insert new attached Table of Contents. ADDENDUM NO. 01 PROJECT Colby Glass E.S. Window Upgrades and ADA Work PROJECT NO. 16043 DATE February 07, 2018 TO: All Prime Contract Bidders and all others to whom Drawings and Specifications have been

More information

GARAGE MAIN FLOOR PLAN

GARAGE MAIN FLOOR PLAN 30 year dimensional shingles and Metal Verticle siding over structural sheathing. Nailing schedule is " on ends 12" on centers d nails. Trusses are engineered on 24" and framing is 2" x " on 1" centers.

More information

Detailed Structural Assessment Southern Nevada Health District Main Building Las Vegas, NV

Detailed Structural Assessment Southern Nevada Health District Main Building Las Vegas, NV Detailed Structural Assessment Southern Nevada Health District Main Building Las Vegas, NV Prepared for PGAL, Inc. Prepared by Walter P. Moore and Associates, Inc. 3883 Howard Hughes Parkway, Suite 190

More information

ACCESSORY STRUCTURES (Garages/Sheds) BUILDING AND ZONING REQUIREMENTS (REVISED 4/21/16)

ACCESSORY STRUCTURES (Garages/Sheds) BUILDING AND ZONING REQUIREMENTS (REVISED 4/21/16) ACCESSORY STRUCTURES (Garages/Sheds) BUILDING AND ZONING REQUIREMENTS (REVISED 4/21/16) NOTE: No building permit shall be issued for the construction of more than one (1) detached accessory building on

More information

Residential Patio Cover Specifications

Residential Patio Cover Specifications Residential Patio Cover Specifications This information bulletin describes the minimum requirements for obtaining patio cover permits for residential buildings using the City of Vista standard plan or

More information

Project Address: Name of Person Completing Form:

Project Address: Name of Person Completing Form: Statement of Inspections This form is provided as a way to list aspects of the project that require special inspection and testing in accordance with IBC Sections 107.1, 1704, and 1705 and define duties

More information

EXECUTIVE SUMMARY INTRODUCTION Terms of Reference Building Description Documents Reviewed SUMMARY OF FIELD DATA 4

EXECUTIVE SUMMARY INTRODUCTION Terms of Reference Building Description Documents Reviewed SUMMARY OF FIELD DATA 4 Abbott Place Wood Framed Window Condition Assessment May 30, 2012 TABLE OF CONTENTS EXECUTIVE SUMMARY 1 1.0 INTRODUCTION 2 1.1 Terms of Reference 2 1.2 Building Description 3 1.3 Documents Reviewed 3 2.0

More information

CONTRACT NO. DOL-ETA-16-C-0043

CONTRACT NO. DOL-ETA-16-C-0043 CONTRACT NO. DOL-ETA-16-C-0043 EXTERIOR FAÇADE WALL BRACING GULFPORT JOB CORPS CENTER GULFPORT, MISSISSIPPI SEPTEMBER 2016 PREPARED FOR: U.S. DEPARTMENT OF LABOR PREPARED BY: September 30, 2016 Maria J.

More information

Details for Exterior Brick Masonry Veneer Supported by Metal Plate Connected Wood Trusses

Details for Exterior Brick Masonry Veneer Supported by Metal Plate Connected Wood Trusses Details for Exterior Brick Masonry Veneer Supported by Metal Plate Connected Wood Trusses Released May 20, 2009 Updated March 9, 2011 Introduction: Wood frame structures with attached brick masonry veneer

More information

* RESIDENTIAL PLAN REVIEW *

* RESIDENTIAL PLAN REVIEW * CITY OF DES MOINES, IOWA COMMUNITY DEVELOPMENT DEPARTMENT PERMIT AND DEVELOPMENT CENTER 602 Robert D. Ray Drive DES MOINES, IOWA 50309 Phone: 515.283.4200 Facsimile: 515.283.4270 Based on the scope of

More information

Chapter 2 QUALITY ASSURANCE

Chapter 2 QUALITY ASSURANCE Chapter 2 QUALITY ASSURANCE 2.1 GENERAL 2.1.1 Scope. This chapter provides minimum requirements for quality assurance for seismic-forceresisting systems and designated seismic systems. These requirements

More information

Shaft Wall Solutions for Wood-Frame Structures. Ricky McLain, PE, SE WoodWorks Wood Products Council Charlotte WSF, November 2, 2017

Shaft Wall Solutions for Wood-Frame Structures. Ricky McLain, PE, SE WoodWorks Wood Products Council Charlotte WSF, November 2, 2017 Shaft Wall Solutions for Wood-Frame Structures Ricky McLain, PE, SE WoodWorks Wood Products Council Charlotte WSF, November 2, 2017 Course Description It is fairly common for light wood-frame commercial

More information

4.1.3 Project Manual

4.1.3 Project Manual 4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01

More information

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,

More information

RESIDENTIAL BUILDING PLAN REQUIREMENTS

RESIDENTIAL BUILDING PLAN REQUIREMENTS CITY OF MANSFIELD BUREAU OF BUILDING AND CODES 30 NORTH DIAMOND STREET 3RD FLOOR MANSFIELD, OHIO 44902 Phone (419) 755-9688 Fax (419) 755-9453 www.ci.mansfield.oh.us RESIDENTIAL BUILDING PLAN REQUIREMENTS

More information

PG&E BUILDING AT 215 MARKET STREET

PG&E BUILDING AT 215 MARKET STREET San Francisco, CA ICRI Northern California Chapter 2017 Concrete Repair Awards Simpson Gumpertz & Heger Inc. OVERVIEW The historic 215 Market Street Annex is a seven-story office building in downtown San

More information

Included in our report are our visual observations, recommendations for follow-up evaluation, and conceptual repair recommendations.

Included in our report are our visual observations, recommendations for follow-up evaluation, and conceptual repair recommendations. Ms. Pamela J. Irwin Community Management Associates 384 Ralph McGill Blvd Atlanta, GA 30312 Re: Phase I Condition Assessment Central City Condominiums Pool Deck Atlanta, Georgia Walter P Moore Project

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1 SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1 PROJECT: 300 Seneca New Academic Campus DATE: September 23, 2013 300 Seneca Ave., S.F.,

More information

STRUCTURAL ISSUES IN RESIDENTIAL CONSTRUCTION. Presented by: Susan L. Lasecki P.E., S.E.

STRUCTURAL ISSUES IN RESIDENTIAL CONSTRUCTION. Presented by: Susan L. Lasecki P.E., S.E. STRUCTURAL ISSUES IN RESIDENTIAL CONSTRUCTION Presented by: Susan L. Lasecki P.E., S.E. Presentation Outline Gravity Design Load Paths from Roof to Foundation Roof Framing Floor Framing Wall Framing Lateral

More information

PRELIMINARY STRUCTURAL INVESTIGATION REPORT

PRELIMINARY STRUCTURAL INVESTIGATION REPORT 124 E. Broadway Tucson, AZ Prepared for: CBRE Brokerage Services 3719 N. Campbell Ave. Tucson, AZ 85719 BACKGROUND: The Tucson Veterans of Foreign Wars building, located at 124 E. Broadway, Tucson, AZ

More information

Structural Training - Part 1:

Structural Training - Part 1: Structural Training - Part 1: Structural Training Residential Wood-Framed Construction Presented by: City of Santa Clarita Building & Safety Division February, 2014 The information provided in this presentation

More information