Mixed-Use Development Site Plan. for. 131 Eliot Street Milton, Massachusetts
|
|
- Randall Hart
- 6 years ago
- Views:
Transcription
1 Mixed-Use Development Site Plan for 131 Eliot Street Milton, Massachusetts August 25, 2010 Prepared for: Carrick Realty Trust c/o Jeremiah Connelly, Trustee 1858 Dorchester Avenue Dorchester, MA Prepared by: DeCelle-Burke & Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
2 Table of Contents Section 1 Project Narrative Offsite Flow Summary Section 2 Supplemental Information USGS Map Assessors Map Soils Map FEMA Panel Section 3 Stormwater Management Supporting Data Hydrologic/Hydraulic Stormwater Models Existing Conditions, (2, 10, 25 & 100 Year) Proposed Conditions, (2, 10, 25 & 100 Year) Pipe Sizing Calculations; Rational Method Infiltration System Design TSS Removal Calculation Sheet Operation & Maintenance plan DeCelle-Burke & Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
3 Existing Conditions SECTION 1 - PROJECT NARRATIVE The property is located on the corner of Eliot Street and Central Avenue in Milton, Massachusetts with a mailing address of 131 Eliot Street. The site is currently improved with a two story brick warehouse with loading docks, surface parking and underground parking. Utilities servicing the building consist of public water, public sewer and gas, as well as overhead and underground power and communication lines. The site is predominantly impervious with small trees and other vegetation protruding through poorly maintained bituminous concrete parking surfaces. A small section of landscaping located at the corner of Eliot Street and Central Avenue provides a minimal amount of green space for the industrial building s entrance. The intersection of Central Avenue and Eliot Street, formerly known as Central Square, is currently known as Edward T. O Neil Square is located in the Central Avenue Business District. The square provides small business service to the neighborhood including an automobile service station, a dry cleaners, a liquor store, a coffee shop, a pizza parlor and several other small business s. The square also has single family and multi-family residential uses adjacent to the businesses. The locus property is abutted directly to the west and across Eliot Street by a single and multi-family homes. The site also directly abuts the MBTA trolley line that connects Mattapan Square and Ashmont Station. A trolley stop abuts this property. Elevations onsite range from a high of 39 on the westerly side of the lot to a low of 23 located at the entrance of the underground garage along Central Avenue and adjacent to the MBTA trolley tracks. The elevations are based on a local site datum used on the most recent existing conditions plan by Anderson Surveys, Inc. The conversion for the local datum to the National Geodetic Vertical Datum of 1929 (NGVD-29) is adding 5.65 feet and the conversion to the Town of Milton datum is adding Stormwater generated on site follows the contours discussed above; generally west to east. The westerly runoff flows to Eliot Street and the easterly portion of the lot to Central Avenue. There are several catch basins located on Eliot Street and Central Avenue which capture the majority of stormwater generated on the site. A single on-site catch basin located within the existing parking structure captures a small portion of the site runoff and conveys it to the public drainage system. The public drain conveys the stormwater to the Neponset River. Existing site soils were mapped by the Natural Resource Conservation Service (NRCS) and were determined to be Urban Land. The abutting soils were mapped as Charlton-Hollis Rock Complex and Woodbridge. The Urban Land is typical of an industrialized site in that the soils are disturbed and have indeterminate characteristics. However, the abutting soils have defined characteristics that ledge may be present or a tight silty till material. Given the unpredictable nature of the soils, this office has used a Hydrologic Group C for hydrologic models. DeCelle-Burke & Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
4 The site is located near two perennial streams which make the property subject to the Massachusetts Rivers Protection Act. The Neponset River is located to the north of the parcel directly abutting the trolley track and Pine Tree Brook is located to the east behind the dry cleaners and service station. The entire site is located within the 200-foot Riverfront Area but the property does not abut the actual riverbank of either perennial stream. Any proposed work for this site will require a filing with the Milton Conservation Commission. Proposed Conditions The proposed Mixed-Use Development includes the construction of a new four-story residential/commercial building consisting of approximately four thousand square feet of commercial space on the ground level and 38 residential units on the upper levels. The commercial space shall enhance the current business uses located in the Square while the residential units will provide a new influx of neighborhood patrons that will use the dry cleaners, the pizza parlor and the trolley. The existing building will be demolished along with the surface and structural parking areas. The existing utilities servicing the building will be cut, capped and abandoned in place. Erosion and construction control measures shall be implemented to prevent off-site sediment transport, minimize fugitive dust and provide public safety while the site preparation and actual construction proceeds. Once the existing building is razed and the demolition debris removed from the site and disposed of in a legal manner, the proposed building construction will begin. The same erosion and construction control measures will continue. The building s foundation will be constructed and then multiple stories framed and weatherproofed. Proposed utilities servicing the new building will include a 6 D.I. fire pipe and a 4 D.I. domestic water service. The two services will be tapped from an existing 12 water main in Eliot Street. An 8 CI sewer service is proposed to connect to the existing 15 sewer main in Central Avenue. An oil/water separator for the parking garage will connect to the proposed sewer service within the building envelope. A gas service will connect to the gas main in Central Avenue. Power and communications will be provided by rerouting an existing underground line that currently services the site. These services will be connected as the building proceeds to be vertically constructed. The proposed stormwater management for the project includes reducing the overall impervious nature of the site and recharging a portion of the site runoff. The site s calculated existing conditions hydrologic curve number (CN) is 97 while the proposed conditions hydrologic curve number (CN) is 91. This translates into an overall reduction in off-site stormwater runoff without introducing any stormwater controls. DeCelle-Burke & Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
5 We have proposed the installation of a water quality structure and recharge structure that will improve stormwater quality and further reduce the stormwater flow and volume. The proposed surface parking lot has two proposed catch basins that will connect to the water quality manhole near the entrance to the parking lot. This manhole connects to two 6-foot diameter leaching pits that will have a 12 RCP overflow connecting to a new drain manhole on the property. The overflow will connect to the existing Town drainage system near the Central Avenue and Eliot Street intersection. The stormwater management calculations along with a signed Stormwater Management Form are included in this report. A stormwater flow summary is attached after this narrative for review. Parking lot construction and landscaping will occur toward the end of the project as this provides the property s finished look at the ground surface. The 32-space parking lot located to the west of the proposed building is proposed to be used as shared parking during the day and then revert back to resident only parking during the night. The additional 66 underground spaces, located on two-levels, totaling 98 site spaces (9 handicap spaces) provides the necessary parking volume for the proposed use. The required spaces according to local zoning was calculated to be 86. Landscaping includes stone walls, a pergola, surface lighting and several plants, shrubs and trees as outlined in the plan prepared by William Fleming Associates. DeCelle-Burke & Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
6 Offsite Flow Summary 2-Year Storm (3.2 ) Existing Conditions (ec) Proposed Conditions (pc) Area Description Flow (CFS) Area Description Flow (CFS) Total Flow 3.09 Total Flow Year Storm (4.7 ) Existing Conditions (ec) Proposed Conditions (pc) Area Description Flow (CFS) Area Description Flow (CFS) Total Flow 4.60 Total Flow 4.15 Existing Conditions (ec) 25-Year Storm (5.6 ) Proposed Conditions (pc) Area Description Flow (CFS) Area Description Flow (CFS) Total Flow 5.50 Total Flow Year Storm (7.0 ) Existing Conditions (ec) Proposed Conditions (pc) Area Description Flow (CFS) Area Description Flow (CFS) Total Flow 6.90 Total Flow 6.53 DeCelle-Burke & Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
7 Section 1 Project Narrative Drainage Methodology & Summary DeCelle-Burke & Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
8 Section 2 Supplemental Information USGS Map Assessors Map Soils Map FEMA Panel DeCelle-Burke & Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
9 Section 3 Stormwater Management Supporting Data Hydrologic/Hydraulic Stormwater Models Existing Conditions, (2, 10, 25 & 100 Year) Proposed Conditions, (2, 10, 25 & 100 Year) Pipe Sizing Calculations; Rational Method Infiltration System Design TSS Removal Calculation Sheet Operation & Maintenance plan DeCelle-Burke & Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
10 DATE: TITLE: SCALE: MARCH 10, 2010 USGS MAP NOT TO SCALE PREPARED FOR: Carrick Realty Trust 1858 Dorchester Avenue Dorchester, MA PROJECT TITLE: Mixed Use Development 131 Eliot Street Milton, MA 149 Independence Avenue Quincy, MA (617) (O) (617) (F)
11 Soil Map Legend DATE: TITLE: SCALE: MARCH 10, 2010 Map Unit Symbol Map Unit Name 1 Water 52 Freetown muck, 0 to 1 percent slopes 103B Charlton-Hollis-Rock outcrop complex, 3 to 8 percent slopes 103C Charlton-Hollis-Rock outcrop complex, 8 to 15 percent slopes 104C Hollis-Rock outcrop-charlton complex, 3 to 15 percent slopes 254B Merrimac fine sandy loam, 3 to 8 percent slopes 260B Sudbury fine sandy loam, 2 to 8 percent slopes 305B Paxton fine sandy loam, 3 to 8 percent slopes 305C Paxton fine sandy loam, 8 to 15 percent slopes 305D Paxton fine sandy loam, 15 to 25 percent slopes 310B Woodbridge fine sandy loam, 3 to 8 percent slopes 602 Urban land, 0 to 15 percent slopes 626B Merrimac-Urban land complex, 0 to 8 percent slopes 653 Udorthents, sandy SOILS MAP NOT TO SCALE PREPARED FOR: Carrick Realty Trust 1858 Dorchester Avenue Dorchester, MA PROJECT TITLE: Mixed Use Development 131 Eliot Street Milton, MA 149 Independence Avenue Quincy, MA (617) (O) (617) (F)
12 DATE: TITLE: SCALE: MARCH 10, 2010 ASSESSOR S MAP NOT TO SCALE PREPARED FOR: Carrick Realty Trust 1858 Dorchester Avenue Dorchester, MA PROJECT TITLE: Mixed Use Development 131 Eliot Street Milton, MA 149 Independence Avenue Quincy, MA (617) (O) (617) (F)
13 DATE: TITLE: MARCH 10, 2010 PREPARED FOR: SCALE: FEMA FLOOD MAP NOT TO SCALE PROJECT TITLE: Carrick Realty Trust 1858 Dorchester Avenue Dorchester, MA Mixed Use Development 131 Eliot Street Milton, MA 149 Independence Avenue Quincy, MA (617) (O) (617) (F)
14 EC DRAINAGE Type III 24-hr Rainfall=3.20" Prepared by {enter your company name here} Page 1 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Subcatchment 1S: Existing Site Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=3.20" Area (sf) CN Description 28, Paved parking & roofs 12, Paved parking & roofs 2, % Grass cover, Fair, HSG C 43, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry,
15 EC DRAINAGE Type III 24-hr Rainfall=4.70" Prepared by {enter your company name here} Page 1 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Subcatchment 1S: Existing Site Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=4.70" Area (sf) CN Description 28, Paved parking & roofs 12, Paved parking & roofs 2, % Grass cover, Fair, HSG C 43, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry,
16 EC DRAINAGE Type III 24-hr Rainfall=5.60" Prepared by {enter your company name here} Page 1 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Subcatchment 1S: Existing Site Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=5.60" Area (sf) CN Description 28, Paved parking & roofs 12, Paved parking & roofs 2, % Grass cover, Fair, HSG C 43, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry,
17 EC DRAINAGE Type III 24-hr Rainfall=7.00" Prepared by {enter your company name here} Page 1 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Subcatchment 1S: Existing Site Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=7.00" Area (sf) CN Description 28, Paved parking & roofs 12, Paved parking & roofs 2, % Grass cover, Fair, HSG C 43, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry,
18 PC DRAINAGE-rev Type III 24-hr Rainfall=3.20" Prepared by {enter your company name here} Page 1 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Subcatchment P-Lot: Exterior Parking Lot Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=3.20" Area (sf) CN Description 10, Paved parking & roofs 2, >75% Grass cover, Good, HSG C 13, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, Subcatchment Rem. Site: P-Bldg & Rem. Area Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=3.20" Area (sf) CN Description 10, >75% Grass cover, Good, HSG C 17, Prop. Roof 2, Impervious Area 30, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, Reach 1R: (new node) Inflow = hrs, Volume= af Outflow = hrs, Volume= af, Atten= 0%, Lag= 0.0 min Routing by Stor-Ind+Trans method, Time Span= hrs, dt= 0.05 hrs Max. Velocity= 20.3 fps, Min. Travel Time= 0.0 min Avg. Velocity = 16.6 fps, Avg. Travel Time= 0.0 min Peak Depth= 0.10' Capacity at bank full= 10, cfs Inlet Invert= 3.00', Outlet Invert= 2.00' 100.0" Diameter Pipe n= Length= 1.0' Slope= '/' Pond 1P: (new node) Inflow = hrs, Volume= af Outflow = hrs, Volume= af, Atten= 0%, Lag= 0.6 min Discarded = hrs, Volume= af Primary = hrs, Volume= af
19 PC DRAINAGE-rev Type III 24-hr Rainfall=3.20" Prepared by {enter your company name here} Page 2 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Routing by Stor-Ind method, Time Span= hrs, dt= 0.05 hrs Peak Elev= 29.71' Storage= 174 cf Plug-Flow detention time= 29.5 min calculated for af (96% of inflow) Elevation Cum.Store (feet) (cubic-feet) Discarded OutFlow (Free Discharge) 2=Exfiltration Primary OutFlow (Free Discharge) 1=Culvert 3=Orifice/Grate # Routing Invert Outlet Devices 1 Primary 29.30' 12.0" x 172.0' long Culvert RCP, groove end projecting, Ke= Outlet Invert= 24.00' S= '/' n= Cc= Discarded 0.00' 0.02 cfs Exfiltration at all elevations 3 Primary 33.00' 24.0" Horiz. Orifice/Grate X 2.00 Limited to weir flow C= 0.600
20 PC DRAINAGE-rev Type III 24-hr Rainfall=4.70" Prepared by {enter your company name here} Page 1 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Subcatchment P-Lot: Exterior Parking Lot Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=4.70" Area (sf) CN Description 10, Paved parking & roofs 2, >75% Grass cover, Good, HSG C 13, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, Subcatchment Rem. Site: P-Bldg & Rem. Area Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=4.70" Area (sf) CN Description 10, >75% Grass cover, Good, HSG C 17, Prop. Roof 2, Impervious Area 30, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, Reach 1R: (new node) Inflow = hrs, Volume= af Outflow = hrs, Volume= af, Atten= 0%, Lag= 0.0 min Routing by Stor-Ind+Trans method, Time Span= hrs, dt= 0.05 hrs Max. Velocity= 23.5 fps, Min. Travel Time= 0.0 min Avg. Velocity = 16.7 fps, Avg. Travel Time= 0.0 min Peak Depth= 0.12' Capacity at bank full= 10, cfs Inlet Invert= 3.00', Outlet Invert= 2.00' 100.0" Diameter Pipe n= Length= 1.0' Slope= '/' Pond 1P: (new node) Inflow = hrs, Volume= af Outflow = hrs, Volume= af, Atten= 1%, Lag= 0.5 min Discarded = hrs, Volume= af Primary = hrs, Volume= af
21 PC DRAINAGE-rev Type III 24-hr Rainfall=4.70" Prepared by {enter your company name here} Page 2 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Routing by Stor-Ind method, Time Span= hrs, dt= 0.05 hrs Peak Elev= 29.83' Storage= 183 cf Plug-Flow detention time= 22.0 min calculated for af (97% of inflow) Elevation Cum.Store (feet) (cubic-feet) Discarded OutFlow (Free Discharge) 2=Exfiltration Primary OutFlow (Free Discharge) 1=Culvert 3=Orifice/Grate # Routing Invert Outlet Devices 1 Primary 29.30' 12.0" x 172.0' long Culvert RCP, groove end projecting, Ke= Outlet Invert= 24.00' S= '/' n= Cc= Discarded 0.00' 0.02 cfs Exfiltration at all elevations 3 Primary 33.00' 24.0" Horiz. Orifice/Grate X 2.00 Limited to weir flow C= 0.600
22 PC DRAINAGE-rev Type III 24-hr Rainfall=5.60" Prepared by {enter your company name here} Page 1 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Subcatchment P-Lot: Exterior Parking Lot Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=5.60" Area (sf) CN Description 10, Paved parking & roofs 2, >75% Grass cover, Good, HSG C 13, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, Subcatchment Rem. Site: P-Bldg & Rem. Area Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=5.60" Area (sf) CN Description 10, >75% Grass cover, Good, HSG C 17, Prop. Roof 2, Impervious Area 30, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, Reach 1R: (new node) Inflow = hrs, Volume= af Outflow = hrs, Volume= af, Atten= 0%, Lag= 0.0 min Routing by Stor-Ind+Trans method, Time Span= hrs, dt= 0.05 hrs Max. Velocity= 24.6 fps, Min. Travel Time= 0.0 min Avg. Velocity = 16.7 fps, Avg. Travel Time= 0.0 min Peak Depth= 0.14' Capacity at bank full= 10, cfs Inlet Invert= 3.00', Outlet Invert= 2.00' 100.0" Diameter Pipe n= Length= 1.0' Slope= '/' Pond 1P: (new node) Inflow = hrs, Volume= af Outflow = hrs, Volume= af, Atten= 1%, Lag= 0.5 min Discarded = hrs, Volume= af Primary = hrs, Volume= af
23 PC DRAINAGE-rev Type III 24-hr Rainfall=5.60" Prepared by {enter your company name here} Page 2 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Routing by Stor-Ind method, Time Span= hrs, dt= 0.05 hrs Peak Elev= 29.89' Storage= 188 cf Plug-Flow detention time= 19.1 min calculated for af (97% of inflow) Elevation Cum.Store (feet) (cubic-feet) Discarded OutFlow (Free Discharge) 2=Exfiltration Primary OutFlow (Free Discharge) 1=Culvert 3=Orifice/Grate # Routing Invert Outlet Devices 1 Primary 29.30' 12.0" x 172.0' long Culvert RCP, groove end projecting, Ke= Outlet Invert= 24.00' S= '/' n= Cc= Discarded 0.00' 0.02 cfs Exfiltration at all elevations 3 Primary 33.00' 24.0" Horiz. Orifice/Grate X 2.00 Limited to weir flow C= 0.600
24 PC DRAINAGE-rev Type III 24-hr Rainfall=7.00" Prepared by {enter your company name here} Page 1 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Subcatchment P-Lot: Exterior Parking Lot Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=7.00" Area (sf) CN Description 10, Paved parking & roofs 2, >75% Grass cover, Good, HSG C 13, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, Subcatchment Rem. Site: P-Bldg & Rem. Area Runoff = hrs, Volume= af Runoff by SCS TR-20 method, UH=SCS, Time Span= hrs, dt= 0.05 hrs Type III 24-hr Rainfall=7.00" Area (sf) CN Description 10, >75% Grass cover, Good, HSG C 17, Prop. Roof 2, Impervious Area 30, Weighted Average Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, Reach 1R: (new node) Inflow = hrs, Volume= af Outflow = hrs, Volume= af, Atten= 0%, Lag= 0.0 min Routing by Stor-Ind+Trans method, Time Span= hrs, dt= 0.05 hrs Max. Velocity= 25.9 fps, Min. Travel Time= 0.0 min Avg. Velocity = 16.8 fps, Avg. Travel Time= 0.0 min Peak Depth= 0.16' Capacity at bank full= 10, cfs Inlet Invert= 3.00', Outlet Invert= 2.00' 100.0" Diameter Pipe n= Length= 1.0' Slope= '/' Pond 1P: (new node) Inflow = hrs, Volume= af Outflow = hrs, Volume= af, Atten= 1%, Lag= 0.4 min Discarded = hrs, Volume= af Primary = hrs, Volume= af
25 PC DRAINAGE-rev Type III 24-hr Rainfall=7.00" Prepared by {enter your company name here} Page 2 HydroCAD 6.00 s/n Applied Microcomputer Systems 8/25/2010 Routing by Stor-Ind method, Time Span= hrs, dt= 0.05 hrs Peak Elev= 29.98' Storage= 195 cf Plug-Flow detention time= 16.4 min calculated for af (97% of inflow) Elevation Cum.Store (feet) (cubic-feet) Discarded OutFlow (Free Discharge) 2=Exfiltration Primary OutFlow (Free Discharge) 1=Culvert 3=Orifice/Grate # Routing Invert Outlet Devices 1 Primary 29.30' 12.0" x 172.0' long Culvert RCP, groove end projecting, Ke= Outlet Invert= 24.00' S= '/' n= Cc= Discarded 0.00' 0.02 cfs Exfiltration at all elevations 3 Primary 33.00' 24.0" Horiz. Orifice/Grate X 2.00 Limited to weir flow C= 0.600
26 P-Lot Rem. Site 1P 1R Subcat Reach Pond Link Drainage Diagram for PC DRAINAGE-rev Prepared by {enter your company name here} 8/25/2010 HydroCAD 6.00 s/n Applied Microcomputer Systems
27 Project: 131 Eliot Street Prepared by: DeCelle-Burke & Associates Milton, MA 149 Independence Avenue Client: Carrick Realty Trust Quincy, MA Date: 8/25/10 DRAINAGE CALCULATIONS FOR A 25-YEAR STORM, CHEZY-MANNING'S FORMULA, N=0.013, REINFORCED CONC. PIPE STRUCTURE DESC. AREA "C" CA (min.) I Q L S DIA. QFULL VFULL Q/ V/ V D/V RIM INVERTINVERT from to (acres) (acres) PIPE Tc (in/hr) (cfs) (ft) (ft/ft) (in.) (cfs) (ft/s) QFULL VFULL (ft/s) (min.) IN OUT DA 1 CB1&2 PAVE GRASS CB1&2 WQ
28 Infiltration System Design Client: Carrick Realty Trust Project Name: Mixed-Use Development Project Location: 131 Eliot St. Milton, MA Job Number: Date: 8/25/2010 STORAGE VOLUME Number of Drywells = 2 Depth (Stone, Below Drywell) = 1.00 Radius (Drywell, Inside) = 3.00 Depth (Stone, Side Drywell) = 1.00 Drywell Wall Width = 0.5 Percent Voids in Stone = 30.00% Depth (Drywell, Below Invert) = 3 Total Impervious Area On-Site= n/a s.f. Excavation Width= 9 Excavation Length= 18 Volume of Drywell= Volume in Drywell = Volume of Stone Below Drywells = Volume of Stone Surrounding Drywells = Volume of Drywells= Total Drywell System Volume Provided= Bottom Leaching Area = Sidewall Leaching Area = Total Leaching Area = 115 c.f. 85 c.f. 49 c.f. 77 c.f. 231 c.f. 356 c.f. 162 s.f. 162 s.f. 324 s.f. RECHARGE RATE Leaching Area Assumed Infiltration Rate Calculated Recharge Rate 324 s.f. 20 mpi 0.02 cfs DeCelle-Burke Associates, Inc. 149 Independence Avenue Quincy, MA PH: FX:
29 Project: Mixed-Use Development Location: 131 Eliot Street Milton, MA Date: 8/25/2010 Total Suspended Solids Removal Calculations BMP TSS Start Amount Total Remaining Removal Load Removed Removed Load 4' Deep Sump Catch Basins 25% 100% 25% 25% 75% 4' Deep Sump Water Quality MH 25% 75% 19% 44% 56% Remaining Load 44% DeCelle-Burke Associates, Inc. 149 Independence Avenue Quincy, MA PH FX
30 STORMWATER OPERATION AND MAINTENANCE PLAN 131 Eliot Street, Milton, MA OWNER & RESPONSIBLE PARTY DURING CONSTRUCTION: Carrick Realty Trust 1858 Dorchester Avenue Dorchester, MA RESPONSIBLE PARTY FOLLOWING CONSTRUCTION: PROJECT OVERVIEW: Carrick Realty Trust 1858 Dorchester Avenue Dorchester, MA The project consists of constructing a 16,800 square foot mixed use building footprint and bituminous concrete drive and parking area on the corner of Eliot Street and Central Avenue in Milton, MA. The site improvements include the construction of a parking lot, utilities and stormwater management facilities. The exterior parking area will consist of impervious bituminous concrete with cape cod berm. The stormwater will be conveyed along the curbing to two deep-sump catch basins located in the parking area. The catch basins will capture particulates and suspended solids. The stormwater will then be conveyed to a deep sump water quality structure and then to leaching pits that allow stormwater to be discharged into the ground. The water quality structure will capture additional particulates and suspended solids and the leach pits will recharge groundwater. Overflow from the leach pits will be conveyed to a drain manhole that connects to the existing storm sewer in Eliot Street. The Best Management Practices (BMPs) used in this design were chosen for their effectiveness and ease of maintenance. Providing for maintenance requirements that are practical is essential to achieve the desired result of improved water quality and a reductions in overall off-site stormwater flows. It is intended that the project infrastructure will be privately owned and maintained by the developer. Therefore, the owner of the property will be responsible for maintaining the stormwater system located within the project limits. To ensure proper functioning of the proposed systems, periodic inspection and maintenance is necessary. The following document has been prepared as a stand-alone guide for the responsible party to implement an inspection and maintenance program for the proposed stormwater management facilities. Maintenance of the stormwater management system (i.e. Catch basins, etc.) is the responsibility of the final property management or the landowner. This agreement between the Town of Milton and property management shall be recorded at the Norfolk County Registry of Deeds. Stormwater Operation Eliot Street and Maintenance Plan August 25, 2010
31 NON-STRUCTURAL APPROACHES: STREET SWEEPING Post-construction, street sweeping will be performed biannually during the spring and fall. SNOW MANAGEMENT Proper snow management practices will be implemented to minimize runoff and pollutant loading impacts. Plowed snow will be placed in pervious areas where it can slowly infiltrate. Plowed snow will be placed on to pervious areas that are not subject to excessive shade from buildings or vegetation. This will allow snowmelt to run off onto paved areas, enter the stormwater management facilities and be subjected to the majority of the treatment system. All accumulated sediment from snowmelt shall be removed each spring. STRUCTURAL BEST MANAGEMENT PRACTICES: LEACHING PITS Subsurface infiltration chambers are proposed to recharge the site runoff into the ground. The system shall include manholes to finish grade for annual inspection to determine if any loss of infiltration capacity has occurred. If any large amounts of sediment accumulate in the leaching chambers, they shall be removed by vacuum truck. DEEP-SUMP CATCH BASIN AND WATER QULAITY STRUCTURE Deep-sump catch basins and a water quality strucutre manhole will be installed to remove trash, debris, sediment and a limited amount of grease and oil from stormwater. Oil and grease will float on the surface of the pooled water and be trapped by an inverted elbow. To ensure maximum capacity and efficiency, the sumps will be cleaned when half of the available capacity of the deep sump has been used or at a minimum of once per year. The condominium association shall inspect the units a minimum of twice per year to maintain the units and be able to increase the cleaning of the units if necessary based on the inspections. Cleaning will take place following construction at the completion of the project. Stormwater Operation Eliot Street and Maintenance Plan August 25, 2010
SITE DESIGN ENGINEERING, LLC. 11 Cushman Street, Middleboro, MA P: F:
INTRODUCTION This drainage report was prepared for the proposed site re-development at in Burlington, Massachusetts. The project site is approximately 1.05± acres consisting of approximately 70% impervious
More informationUPDATED SITE DESIGN NARRATIVE AND CALCULATIONS
UPDATED SITE DESIGN NARRATIVE AND CALCULATIONS Burlington Summit The Gutierrez Company One Wall Street, Burlington, MA July, Prepared by, Symmes Maini & McKee Associates Cambridge, MA SMMA No. PROJECT
More informationEngineering Report. 1 Garfield Circle
Engineering Report for 1 Garfield Circle a Proposed Office Building in Burlington, Massachusetts Prepared by: DeCelle-Burke and Associates, Inc. 1266 Furnace Brook Parkway Suite 401 Quincy, MA 02169 Prepared
More informationInflow Design Flood Control System Plan
Inflow Design Flood Control System Plan For Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Cherokee Station - CCR Surface Impoundments Public Service Company of Colorado Denver, Colorado
More informationProposed Retail Development
Drainage Report Proposed Retail Development Rochester, New Hampshire Prepared for G.B. New England 2, LLC 14 Breakneck Hill Road, Suite 101 Lincoln, Rhode Island 02865 401 721 1600 Prepared by /Vanasse
More information526 & 528 Boston Post Road Redevelopment Sudbury, MA
PRELIMINARY STORMWATER MANAGEMENT MASTER PLAN 526 & 528 Boston Post Road Redevelopment Sudbury, MA PREPARED FOR BPR Sudbury Development LLC c/o National Development 2310 Washington Street Newton Lower
More informationGreen Station CCR Surface Impoundment
Green Station CCR Surface Impoundment Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule Hydrologic and Hydraulic Capacity Assessment and Initial Inflow Design Flood Control
More informationRun-on and Run-off Control System Plan
Run-on and Run-off Control System Plan CCR Temporary Storage Pad Lewis and Clark Station Prepared for Montana-Dakota Utilities Co. October 2016 Paul T. Swenson 2016.10.13 18:30:03-05'00' 234 West Century
More informationAPPENDIX K OPERATIONS AND FINAL COVER SURFACE WATER MANAGEMENT SYSTEM DESIGN
ONONDAGA LAKE SEDIMENT CONSOLIDATION AREA CIVIL & GEOTECHNICAL FINAL DESIGN APPENDIX K OPERATIONS AND FINAL COVER SURFACE WATER MANAGEMENT SYSTEM DESIGN PARSONS P:\Honeywell -SYR\44483 - Lake Detail Design\9
More informationInflow Design Flood Control System Plan
Inflow Design Flood Control System Plan Scrubber Ponds Lewis and Clark Station Prepared for Montana-Dakota Utilities Co. October 2016 Paul T. Swenson 2016.10.14 17:54:29-05'00' 234 West Century Avenue
More informationEnvironmental Design Group
SEDIMENT CONTROL DURING CONSTRUCTION, STORMWATER MANAGEMENT AND POST CONSTRUCTION BMP REPORT for Hudson Salt Storage and Bus Garage 5810 Hudson Drive HUDSON, OHIO SUMMIT COUNTY Prepared by Environmental
More informationSTORMWATER MANAGEMENT REPORT
3 Industrial Way Tyngsborou STORMWATER MANAGEMENT REPORT Common Driveway at 105 Vaughn Hill Rd. Bolton, MA October 19, 2017 Prepared For: Whitehorse Builders 456 Newtown Rd. Littleton, MA 01460 Prepared
More informationInflow Design Flood Control System Plan
Inflow Design Flood Control System Plan For Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Valmont Station - CCR Surface Impoundments Public Service Company of Colorado Denver, Colorado
More informationRun-on and Run-off Control System Plan
Run-on and Run-off Control System Plan J.H. CAMPBELL GENERATING FACILITY DRY ASH LANDFILL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN West Olive, Michigan Pursuant to 4 CFR 257.81 Submitted To: Consumers Energy
More informationExample 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond)
Chapter 10 Design Examples Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond) Example 2: Filter Design in a commercial development
More informationGENERAL AND FLOODING STANDARDS SUBMISSION BRUNSWICK LAYOVER FACILITY BRUNSWICK, MAINE PREPARED FOR:
APPENDIX H GENERAL AND FLOODING STANDARDS SUBMISSION BRUNSWICK LAYOVER FACILITY BRUNSWICK, MAINE PREPARED FOR: NORTHERN NEW ENGLAND PASSENGER RAIL AUTHORITY (NNEPRA) 75 WEST COMMERCIAL STREET, SUITE 104
More informationMOODY FLATS QUARRY STORMWATER, EROSION CONTROL, AND DRAINAGE PLAN SHASTA COUNTY, CALIFORNIA. Prepared by:
MOODY FLATS QUARRY STORMWATER, EROSION CONTROL, AND DRAINAGE PLAN SHASTA COUNTY, CALIFORNIA Prepared by: Trevor Crawford, Civil Engineer 3M Facilities Engineering St. Paul, Minnesota Dr. Andrew A. Kopania,
More informationDRAINAGE DESIGN REPORT
Scannell Properties Development Sales Distribution Center Drainage Design Report DRAINAGE DESIGN REPORT JUNE 2018 SALES DISTRIBUTION CENTER SCHODACK, NEW YORK RENSSELAER COUNTY 1 Scannell Properties Development
More informationENGINEERING REVIEW CHECKLIST City of Mount Clemens
(To be completed by the Developer s & Submitted with ing Plans) DATE: PROJECT NAME: Site Plan Approved: Date DESIGN ENGINEERING COMPANY: ing Company Contact Information: Name: Phone: Email: Owner Contact
More informationInflow Design Flood Control System Plan
Inflow Design Flood Control System Plan Scrubber Ponds Lewis & Clark Station Prepared for Montana-Dakota Utilities Co. November 2018 234 West Century Avenue Bismarck, ND 58503 701.255.5460 www.barr.com
More informationRETENTION BASIN EXAMPLE
-7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary
More informationWater Resources Management Plan
P L Y M O U T H M I N N E S O T A Appendix D: The developed a to analyze and minimize the impact of existing and future development on the City s natural resources. It is important to the City to have
More informationStormwater Analysis Report
Stormwater Analysis Report Solar Panel Array Temple Street (Rt. 14) West Boylston, MA February 24, 216 SITE Prepared for: West Boylston Municipal Lighting Plant 4 Crescent Street West Boylston, MA 1583
More informationDesign Example Residential Subdivision
Design Example Residential Subdivision Rhode Island Stormwater Design and Installation Standards Manual December 2010 Public Training March 22, 2010 Richard Claytor, P.E. 508-833-6600 Appendix D: Site
More informationSTORMWATER MANAGEMENT PLAN
STORMWATER MANAGEMENT PLAN GLEN LAKE APARTMENTS Minnetonka, MN DATE: 10-26-2018 PREPARED FOR: Campion Engineering Services, Inc. 1800 Pioneer Creek Center Maple Plain, MN 55359 PREPARED BY: Civil Methods,
More informationInitial Inflow Design Flood Control System Plan
Initial Inflow Design Flood Control System Plan Brunner Island Ash Basin No. 6 Prepared for: Brunner Island, LLC October 11, 2016 This page intentionally left blank. Initial Inflow Design Flood Control
More information100-yr Design Runoff (cfs) Basin ID 103b A a B B C Totals
PROPOSED DEVELOPMENT The drainage for this site has been designed to be less than the maximum allowable runoff from each basin as stated in the Overall Rigden Farm drainage plan. Table 1 compares the actual
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment
More informationCENTRALIZED BMPS TYPICALLY PUBLICLY OWNED & MAINTAINED BMPS, TREATING A LARGE (>20 ACRES) URBAN DRAINAGE WITH MULTIPLE LAND
BMP RAM BMP Type Definitions 1 CENTRALIZED BMPS TYPICALLY PUBLICLY OWNED & MAINTAINED BMPS, TREATING A LARGE (>20 ACRES) URBAN DRAINAGE WITH MULTIPLE LAND USES AND OWNERSHIP STRUCTURAL BMP TYPE OTHER NAMES
More informationNEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL
NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by
More informationPRELIMINARY DRAINAGE STUDY
PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,
More informationINITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257
INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT BOWEN PRIVATE INDUSTRY SOLID WASTE DISPOSAL FACILITY (ASH LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals
More informationHYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR
HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR 1 INTRODUCTION 1.1 Project Description and Location Isabella Ocean Residences is a residential development to be constructed
More information4.8. Subsurface Infiltration
4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration
More informationExtended Detention Basin Design
Extended Detention Basin Design 1 Extended Detention 2 Ohio Department of Transportation 1 Extended Detention Basin L&D Vol. 2 Section 1117.3 Provides quality and quantity treatment 3 Extended Detention
More informationINITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257
INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion
More information4.28 Underground Detention
4.28 Underground Detention Detention Structural Stormwater Control Description: Detention storage located in underground tanks or vaults designed to provide water quantity control through detention and/or
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or
More informationModeling Infiltration BMPs
Modeling Infiltration BMPs CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) 696-4150 www.thcahill.com Design Goals for Calculations 1. Mitigate Peak Rates 2-Year to 100-Year 2. No Volume
More informationINITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR
INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR 257.82 EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part 257 and Part
More informationSUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields
4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater
More informationMunicipal Stormwater Ordinances Summary Table
APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which
More information4.8. Subsurface Infiltration
4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration
More informationStormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)
Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater
More informationAttachment 6 Hydrologic and Hydraulic Analysis
Attachment 6 Hydrologic and Hydraulic Analysis HYDROLOGIC AND HYDRAULIC ANALYSIS COMBINATION POND DAM VT Dam #173.03 City of Rutland, Vermont Prepared for: City of Rutland Prepared by: February 23, 2012
More informationCover Letter to the Town of Ashland Planning Board, dated February 3, 2016, prepared by: Connorstone Engineering, Inc.
GCG ASSOCIATES, INC. CIVIL ENGINEERING AND LAND SURVEYING 84 Main Street Wilmington, Massachusetts 01887 Phone: (978) 657-9714 Fax: (978) 657-7915 February 12, 2016 Mr. Nathaniel Strosberg, Town Planner
More informationSTORM DRAINAGE DESIGN MANUAL
Appendix I STORM DRAINAGE DESIGN MANUAL by: SUNGATE DESIGN GROUP, P.A. GEN ERAL DESIGN STAN DARDS AN D POLICIES 1. STREET AND LOCAL DRAINAGE Discharge estimates for specified design storms shall be calculated
More informationPEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION
US Army Corps of Engineers Philadelphia District PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION CECIL COUNTY MARYLAND STORMWATER MANAGEMENT PLAN NARRATIVE INITIAL SUBMISSION JUNE 2014 1 PEARCE CREEK
More informationGCG ASSOCIATES, INC. CIVIL ENGINEERING AND LAND SURVEYING 84 Main Street Wilmington, Massachusetts 01887
GCG ASSOCIATES, INC. CIVIL ENGINEERING AND LAND SURVEYING 84 Main Street Wilmington, Massachusetts 01887 Phone: (978) 657-9714 Fax: (978) 657-7915 November 17, 2017 Ms. Sheila Page, Town Planner 101 Main
More informationIntroduction to Storm Sewer Design
A SunCam online continuing education course Introduction to Storm Sewer Design by David F. Carter Introduction Storm sewer systems are vital in collection and conveyance of stormwater from the upstream
More information6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON
6 STOREY CONDOMINIUM 7480 DERRY ROAD WEST, MILTON STORM WATER MANAGEMENT DESIGN BRIEF NEW DEVELOPMENT DRAINAGE SYSTEM REV 0 August 29, 2017 PREPARED BY: HALLEX PROJECT #170532 HALLEX NIAGARA HALLEX HAMILTON
More informationAugust Chapter 1: Introduction to the Manual
Chapter 1: Introduction to the Manual Section 1.1 Purpose of the Manual The purpose of this manual is threefold: 1. To protect the waters of the State of New York from the adverse impacts of urban stormwater
More informationDawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228
Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA 30534 (706) 344-3500 x 42228 DAWSON COUNTY STORM WATER REVIEW CHECKLIST Project Name: Property Address: Engineer: Fax #/Email: Date:
More informationSubmittal Requirements. Post Construction Verification Document Plan Requirements
Submittal Requirements Post Construction Verification Document survey plan in accordance with the items of this Checklist Supporting calculations in accordance with the items of this Checklist A copy of
More information4.4.6 Underground Detention
4.4.6 Underground Detention Limited Application Water Quality BMP Description: Detention storage located in underground pipe systems or vaults designed to provide water quantity control through detention
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any
More informationBMP 6.4.4: Infiltration Trench
BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a
More informationPractices that capture and temporarily store the WQ v before allowing it to infiltrate into the soil.
Chapter 5: Acceptable Stormwater Management Practices (SMPs) This section presents a list of practices that are acceptable for water quality treatment. The practices on this list are selected based on
More informationHydrology Study. Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated)
Hydrology Study Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated) Prepared for San Mateo Real Estate & Construction March 9, 21 Rev. 1 11-8-211 Rev.
More informationWQ-06 SAND FILTER. 1.0 Sand Filter. Greenville County Technical Specification for: 1.1 Description
Greenville County Technical Specification for: WQ-06 SAND FILTER 1.0 Sand Filter 1.1 Description Sand Filters remove pollutants through sedimentation and filtration within the sand. The primary components
More informationWarner Robins Stormwater Local Design Manual
Warner Robins Stormwater Local Design Manual Prepared for Houston County City of Warner Robins City of Perry City of Centerville May 17, 2005 Version 4 (As presented with adopted Stormwater Ordinance)
More informationShelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT
Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) Activity: Infiltration Systems PLANNING CONSIDERATIONS: Design Life: Short IS Acreage
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationTABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1
TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SECTION TITLE PAGE 105.1. SPECIFICATIONS AND SCOPE 105.1 105.2. METHODS OF ANALYSIS 105.1 105.2.1. Rational Method
More informationSTORMWATER MANAGEMENT
STORMWATER MANAGEMENT This narrative summarizes the stormwater management analysis conducted for the proposed DCP Terminal. The purpose of this narrative is to describe and quantify the pre- and post-development
More informationDRAINAGE PLAN AND REPORT OLD DENVER ROAD
DRAINAGE PLAN AND REPORT 16140 OLD DENVER ROAD PART OF THE NW1/4 SEC. 28, T.11S., R.67W., 6 th P.M. EL PASO COUNTY February 3, 2017 Revised January 5, 2018 Prepared for All About Outdoor Storage Oliver
More informationSIZING WATER SERVICE LINES AND METERS
SIZING WATER SERVICE LINES AND METERS COUNTY OF CURRITUCK Water Customer Data Sheet Customer: Address: Building Address: 2 Lark Drive Zip Code: Subdivision: Lot #: Block #: Type of Occupancy: FIXTURE FIXTURE
More informationCHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN
CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth
More informationJanuary 20, Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO (303)
January 20, 2017 Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO 80229 (303) 538-7694 RE: Riverdale Five Retail Drainage Conformance Letter
More informationPreliminary Drainage Analysis
Preliminary Drainage Analysis Tanimura and Antle Employee Housing Town of Spreckels County of Monterey, California LIB150205 May 29, 2015 Prepared For: Tanimura and Antle Produce Prepared By: 9699 Blue
More informationCity of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development
City of Redwood City Stormwater Pollution Prevention Program Drainage Guidelines for Residential Development General Requirements A. Plot & Finished Grading Plan must be submitted with Building Permit
More informationA Stormwater Management Plan and Sediment Control Plan are required for all proposed developments within the City of Richmond.
Engineering Page 3-1 3.0 STORM DRAINAGE 3.1 GENERAL Good drainage is vital to flat urban areas such as Lulu Island. It is essential that every storm sewer must be designed accurately minimizing conflicts
More informationHYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS
HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS Project Name: Project Number: Reviewed By: Date: Telephone: Email: Address all items marked with an X Minimum Submittal Requirements 1. Conceptual Review
More informationE. STORMWATER MANAGEMENT
E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson
More informationChapter 21 Stormwater Management Bylaw
Chapter 21 Stormwater Management Bylaw SECTION 1. PURPOSE The purpose of this Bylaw is to: implement the requirements of the National Pollutant Discharge Elimination System (NPDES) General Permit for Storm
More informationSC-01 Surface Outlet and Baffle Sediment Basin
Greenville County Technical Specification for: SC-01 Surface Outlet and Baffle Sediment Basin 1.0 Surface Outlet and Baffle Sediment Basin This Specification contains requirements for the design and construction
More informationPART V - STORM DRAIN DESIGN CRITERIA
PART V - STORM DRAIN DESIGN CRITERIA A. Hydrology Studies and Hydraulic Analyses 1. Drainage area master plans and calculations are to be submitted with all subdivision improvement plans, permit improvement
More informationPART V - STORM DRAIN DESIGN CRITERIA
PART V - STORM DRAIN DESIGN CRITERIA A. Hydrology Studies and Hydraulic Analyses 1. Drainage area master plans and calculations are to be submitted with all subdivision improvement plans, permit improvement
More informationMODEL Stormwater Local Design Manual. City of Centerville
MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge
More informationCONSTRUCTION PLAN CHECKLIST
CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted
More informationORDINANCE # 854. Stormwater Management / Operation and Maintenance Requirements
ORDINANCE # 854 Stormwater Management / Operation and Maintenance Requirements Section 1. Purpose and Authority In accordance with the provisions of Chapters 98, 124, 126, 440, 444, and 446h of the General
More informationGrass Channel STORMWATER MANAGEMENT SUITABILITY KEY CONSIDERATIONS
4.0 Structural Stormwater Control Description: Vegetated open channels designed to filter stormwater runoff and meet velocity targets for the water quality design storm and the Streambank Protection storm
More informationPre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015
Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Urban Runoff Background How we got here What Problem?? Provenance of the Problem Unified Sizing Criteria What
More informationAppendix F HYDROLOGY/WATER QUALITY REPORT TIESLAU CIVIL ENGINEERING
Appendix F HYDROLOGY/WATER QUALITY REPORT TIESLAU CIVIL ENGINEERING T IE S L A U C I V IL E N G I NE E R IN G, IN C. P.O. B o x 2 2 9 7, K i n g s B ea c h, C A 9 6 1 4 3 p h : (5 3 0 )5 4 6-0 8 6 1 8
More informationTown of Friday Harbor PO Box 219 / Friday Harbor / WA / (360) / fax (360) /
Town of Friday Harbor PO Box 219 / Friday Harbor / WA / 98250 (360) 378-2810 / fax (360) 378-5339 / www.fridayharbor.org LAND CLEARING, GRADING, OR FILLING PERMIT APPLICATION APPLICATION DATE GRD No. APPLICANT/FRANCHISE
More informationStormwater Local Design Manual For Houston County, Georgia
Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.
More informationSECTION 4 STORM DRAINAGE
4.01 GENERAL SECTION 4 STORM DRAINAGE These standards shall provide minimum requirements for the design of Storm Drainage and related appurtenances within the City of West Sacramento rights of way and
More informationDIVISION 5 STORM DRAINAGE CRITERIA
DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the
More informationFinal Drainage Report
Thornton Electric Substation Project Final Drainage Report December 14, 2016 DRAFT Prepared for: Xcel Energy, 1800 Larimer Street, Suite 400, Denver, Colorado 80202 Prepared by: 350 Indiana Street, Suite
More informationStormwater Management Report Bachman Terrace Residential Development
Stormwater Management Report Bachman Terrace Residential Development Project # 160401069 Prepared for: Tega Developments Prepared by: Stantec Consulting Ltd. April 14, 2014 Sign-off Sheet This document
More informationCUYAHOGA COUNTY ENGINEER
CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL Supplement to O.D.O.T. LOCATION and DESIGN MANUAL, Volume 2, Drainage Design, Section 1000 and 1100 May 28, 2010 Revisions to the July 29, 2009 edition are noted
More informationJacobi, Toombs, and Lanz, Inc.
Area 5: Blackiston Mill Road at Dead Man's Hollow Flooding Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations
More informationLAKE COUNTY HYDROLOGY DESIGN STANDARDS
LAKE COUNTY HYDROLOGY DESIGN STANDARDS Lake County Department of Public Works Water Resources Division 255 N. Forbes Street Lakeport, CA 95453 (707)263-2341 Adopted June 22, 1999 These Standards provide
More informationHydrologic Study Report for Single Lot Detention Basin Analysis
Hydrologic Study Report for Single Lot Detention Basin Analysis Prepared for: City of Vista, California August 18, 2006 Tory R. Walker, R.C.E. 45005 President W.O. 116-01 01/23/2007 Table of Contents Page
More informationAppendix G Preliminary Hydrology Study
Appendix G Preliminary Hydrology Study Preliminary Hydrology Study VESTING TTM 72608 Long Beach, CA Prepared for: The Long Beach Project, LLC 888 San Clemente, Suite 100 New Port Beach, CA May 28, 2014
More informationTypical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)
Module 2: Selection of Controls and Site Planning for Construction Site Erosion Prevention Robert Pitt Department of Civil, Construction, and Environmental Engineering University of Alabama Tuscaloosa,
More informationPRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY
PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established
More informationStandards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition
STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm
More informationC-1. Infiltration System
C-1. Infiltration System Design Objective An infiltration system captures surface stormwater runoff and allows it to infiltrate into the soil. This SCM is typically the work horse of a runoff volume match
More informationManaged Release Concept December 13, 2018
Bureau of Clean Water Managed Release Concept Description Managed Release Concept (MRC) is a post-construction stormwater management (PCSM) strategy that involves the collection, storage, and filtration
More information