Teck Coal Ltd. Elkview Operations. Dam Safety Inspection Report Independent Third Party Review. November 2014 M09963A01.730

Size: px
Start display at page:

Download "Teck Coal Ltd. Elkview Operations. Dam Safety Inspection Report Independent Third Party Review. November 2014 M09963A01.730"

Transcription

1 November 2014 M09963A01.730

2 November 28, 2014 Teck Coal Limited Sparwood, British Columbia Mr. Adam Walker Geotechnical Engineer ear Mr. Walker: Please find attached the Third Party Review of the am Safety Inspection (SI) Report for the Elkview Operations Tailings Facilities. The review concludes that the SI meets the requirements of the Ministry of Mines Guidelines for Annual and that the consequence classifications for the tailing dams are appropriate. This report documents our review and identifies areas for ongoing improvement. Yours truly, KLOHN CRIPPEN BERGER LT. Harvey McLeod, P.Eng., P.Geo. Principal HM/W:dl R Elkview 3rd Party Review.docx M09963A Klohn Crippen Berger Ltd Virtual Way Vancouver BC V5M 4X6 CANAA t f

3 cover.docx

4 TABLE OF CONTENTS 1 INTROUCTION BACKGROUN INFORMATION AN SITE VISIT Site Visit and ocument Review Facility escription Site Conditions REVIEW OF AM SAFETY INSPECTION REPORT General Consequence Classification Review Instrumentation Review Stability Review REVIEW OF TAILINGS FACILITY STEWARSHIP SUMMARY CLOSING List of Tables Table 2.1 EVO esign ocuments and Construction Records... 3 Table 2.2 Summary of Tailing Facility Features... 6 Table 2.3 TSF esign Flood and esign PGA... 7 Table 3.1 Summary of SI Conformance... 8 Table 3.2 am Classifications... 9 Table 5.1 Summary of 2014 SI Recommendations () List of Figures Figure 2.1 Location Plan Lagoons A, B, C and... 5 Figure 2.2 Location Plan WFTF R Elkview 3rd Party Review.docx Page i

5 1 INTROUCTION This report presents the results of an of the am Safety Inspection (SI) Report for the (EVO) tailings storage facilities. The SI was prepared by Environment and Infrastructure (). The Klohn Crippen Berger (KCB) review included a site visit by the Review Engineer, Mr. Harvey McLeod, P.Eng., P.Geo. The Elkview Mine is located in south eastern British Columbia near the town of Sparwood. The open pit mine produces approximately 5.5 Mt to 6.0 Mt per year of clean coal. Fine coal refuse has been stored in 5 historic tailings facilities (Lagoons A, B, C, and ) and are currently being stored in the West Fork Tailings Facility (WFTF). Lagoon is used for contingency storage only. The SI Report covers the five facilities. The tailings impoundments are regulated under the Mines Act of British Columbia and must comply with the requirements of the Health Safety and Reclamation Code for Mines (HSRC) in BC (BC MEMPR 2008). The requirements related to tailings impoundments in the code include the following: ams must be designed in accordance with the criteria provided in the Canadian am Association, am Safety Guidelines (HSRC ). The Operation, Maintenance and Surveillance (OMS) manual must be revised regularly during operations (HSRC ). Annual (HSRC ) must be carried out and submitted to the Ministry of Mines. The MEM website provides the document Guidelines for Annual am Safety Inspection Reports. There must be an Emergency Preparedness Plan for any dam with a consequence classification of High or Very High. (HSRC ). KCB have been informed that the Engineer of Record (EOR) for these tailings facilities is Andy Small, P.Eng. of, responsible for the design and performance of the dam including: 1) dam safety inspections; 2) construction monitoring and quality assurance/quality control; 3) instrumentation planning, design and review; and, 4) design modifications. On August 18, 2014, the Chief Inspector s office of the MEM issued orders mandating that the 2014 am Safety Inspection (SI) of tailing dams be completed, and that the report be reviewed by a third party Professional Engineer, and submitted ecember 1, The order required that the third party review: to assess if the SI report meets the requirements of MEM; and the consequence classification of the dam(s) R Elkview 3rd Party Review.docx Page 1

6 2 BACKGROUN INFORMATION AN SITE VISIT 2.1 Site Visit and ocument Review Site Visit The site visit was carried out on October 17, 2014, and included: Mr. Harvey McLeod and Mr. Lowell Constable of KCB; Mr. Adam Walker (Engineering), Mr. Zane Leonard (Engineering) and Laura Gislason (Engineering Superintendent) of EVO; and, Mr. Andrew Bidwell of Teck Coal. The site tour included inspection of Lagoons A, B, C, and, and the West Fork Tailings Facility (WFTF). The relevant observations from the site visit include the following: Tailings are currently being discharged into the southwest corner of the WFTF, and observations in this area include: Tailings beach slopes are approximately 0.5% towards the northeast, where the pond is located. The pond has approximately 300,000 m 3 of decant water. The west (right) flank of the WFTF comprises the Adit Waste Rock ump, which is well above the tailings pond level. EVO staff indicated that there were historic occasions of tailings migrating into the waste rock and, therefore, current practice is to push a dozer road along the waste rock/tailings beach contact using a finer gradation material excavated from a separate location south of the WFTF. EVO indicated that the purpose of the road is to place a finer gradation material between the tailings beach and the Adit waste rock dump toe that is resistant to tailings migration and/or piping. The upstream slope of the main dam section has been graded to an approximate slope of 3H:1V, with a secondary objective of mixing the waste rock particles on the surface to produce a well graded material that could be resistant to piping. The majority of the surface appears to contain well graded material however there were a number of sections of exposed coarse rockfill. Lagoon is used for auxiliary tailings storage. Observations of Lagoon include the following: There was a wide (25 m minimum) zone upstream of the crest in which tailings were spigotted to produce a segregated tailings material in the outer dam shell. The dam slopes were in good condition with no major erosion channels. The west dam slopes are close to the railway line and the Elk River. Lagoons A and B are small tailing ponds that were used for initial start up of the mine and are not active; relevant field observations include: Minor erosion in Lagoon A occurred in the 2014 freshet due to overflow of a 2 m high portion of the dam. The dams have limited ability to pond any significant volumes of water. The ponds are overgrown with cattails and grasslands R Elkview 3rd Party Review.docx Page 2

7 The consequences of failure are low. Lagoon C is inactive for tailings storage and is periodically used for storage of sludge from settling ponds; relevant observations include: The impoundment was dry with no ponded water. The dam slopes are in good condition with no major erosion channels. The west dam slope is close to the railway line and the Elk River. Water is not stored in the impoundment however it does have the ability to store water during extreme flood events. ocument Review The documents listed in Table 2.1 were provided to KCB. The review of documentation was carried out at a high level to obtain an understanding of the design and site conditions. Items of interest, relevant to dam safety are noted. Table 2.1 EVO esign ocuments and Construction Records ate Prepared By Title July 1972 June 1982 March 1985 Phillips, Barratt, Hillier, Jones & Partners Consulting Engineers Golder Associates Golder Associates Report on Tailings Holding Lagoon for the Elkview Coal Preparation plan raft Preliminary Report to Swan Wooster Engineering Co. Ltd. Long Term Refuse Storage B.C. Coal Ltd. Elkview Plant Borehole and CPT Location Plan Lagoon C and Inspection (I), esign () or Construction I Key Items of Interest Lab results, design analysis, hydrology Site conditions, geology, sub surface conditions, test pit logs, grain size analysis June 1986 Golder Associates Interim Report No.3 To Westar Mining Ltd. On Long Term Raising of Lagoons C and Above Elevation 3705 Site Investigations and recommendations includes slope stability analysis, lab testing results, record of boreholes and gradations, CPT results, strength and deformation characteristics, liquefaction potential, collapse potential August 1986 Golder Associates Report to Westar Mining Ltd. On Geotechnical Engineering Study Lagoon E Includes field and lab investigation, recommendations for design and construction, record of boreholes and test pits February 1987 Golder Associates Final Report to Westar Mining Ltd. On Long Term Raising of Lagoons C and Above Elevation 3705 Includes Site Investigation, subsurface conditions, long term analysis and design, construction recommendations, boreholes and gradations, CPT results, strength and deformation characteristics, liquefaction potential, collapse potential R Elkview 3rd Party Review.docx Page 3

8 ate Prepared By Title June 2002 October 2003 May 2004 March 2008 March 2010 March 2011 January 2012 January 2012 January 2012 January 2012 January 2012 March 2012 October 2013 March 2013 March 2014 (a) July 2014 (b) November 2014 (c) Teck Teck Teck Teck Teck Short Term Coal Refuse Management Utilizing Lagoon and CCR umps West Fork Tailings Storage Facility esign Report FINAL West Fork Storage Facility Addendum to esign Report Issued 28 October, 2003 Coal Refuse Facilities Report on 2007 Annual Geotechnical Inspection Final Report Coal Refuse Facilities Report on 2009 Geotechnical inspection Final Report Coal Refuse Facilities Report on 2010 Geotechnical inspection Final Report OMS Inactive Tailings Facilities Lagoons A, B, C, and Inactive Tailings Facilities, EPP & ERP for Flood Emergencies Lagoon Tailings Facility, EPP & ERP for Flood Emergencies OMS tailings eposition West Fork Facility OMS Tailings eposition Lagoon Coal Refuse Facilities Report on 2011 Annual Geotechnical Inspection Final Report Tailings Storage Facilities Lagoon C and 2013 am Safety Review Elkview Coal Refuse Facilities 2012 Geotechnical Inspection West Fork tailings Facility evelopment to El As Built Report West Fork Tailings Facility Results of 2013 Site Inspection Tailings Storage Facilities West Fork Tailings Facility and Lagoons A, B, C, and 2014 am Safety Inspection Final Report Inspection (I), esign () or Construction I I I I C C C C C I I C I I Key Items of Interest Liquefaction of tailings and foundation concluded dam stable for g (975 year return period). eveloped trigger levels for piezometers for static liquefaction for dam raising. Recommended an average Su/P =0.1 CCR/MCR dump cross sections, instrumentation details, refuse facilities inspection reports, inundation evaluation CCR/MCR dump cross sections, instrumentation, refuse facilities inspection reports, OMS manuals, Truck Shop yke esign CCR/MCR dump cross sections, instrumentation, refuse facilities inspection reports CCR/MCR dump cross sections, instrumentation, refuse facilities inspection reports SR prepared under CA Guidelines CCR/MCR dump cross sections, instrumentation, refuse facilities inspection reports, geotechnical drilling program, OMS manuals and ERP s Climate data, instrumentation readings, results of SI, dam safety assessment, recommendations R Elkview 3rd Party Review.docx Page 4

9 2.2 Facility escription The EVO fine tailings storage facilities include five tailings facilities: Lagoons A, B, C, and ; and, the West Fork Tailings Facility (WFTF). The four Lagoons are located in the Elk River floodplain as shown on Figure 2.2. The WFTF is located in the Upper Erickson Valley, upstream of the Erickson am and ump, as shown on Figure 2.2. Elk River N Figure 2.1 Location Plan Lagoons A, B, C and R Elkview 3rd Party Review.docx Page 5

10 West Fork TSF Figure 2.2 Location Plan WFTF Lagoons A and B were the initial storage facilities for the mine when it opened in 1969, until the early 1970 s when two ring dyke tailings dams were constructed, Lagoons C and. From 1985 to 2006, Lagoon served as the primary tailings facility while Lagoon C was used as an emergency water attenuation facility. Table 2.2 provides a summary of the tailings facilities, along with their respective storage capacity, heights and volumes. Table 2.2 Structure Summary of Tailing Facility Features Status Max Embankment Height (m) Approx. Footprint Area (ha) Impounded Tailings Volume (m 3 ) Impounded Water Volume (m 3 ) Lagoon A Inactive , Lagoon B Inactive ,700 0 Lagoon C Inactive* ,658,600 0 Lagoon Secondary storage facility ,004, ,000 WFTF Primary storage facility ,500, ,000 *Note: (1) Lagoon C is used for periodic storage of sludge from settling ponds. The WFTF commenced operation in 2006, taking over as the principle storage facility. The WFTF is bounded by the Adit Waste and West Fork umps to the west and south, respectively. Cowboy Ridge, a massive limestone ridge, bounds the east side of the facility. Lagoon is only used when either the wash plant is producing more coal, which exceeds the pipeline capacity to the WFTF, or if the pumping system to the WFTF is down for maintenance. A second pipeline is currently under construction which will provide the capacity to pump all of the tailings to WFTF and Lagoon would only be used if both pipelines to the WFTF were down R Elkview 3rd Party Review.docx Page 6

11 Lagoons C and are the only two facilities currently classified as major dams and major impoundments under the HSRC. The WFTF is classified as major impoundment but not a major dam as it is currently an infill of a pre existing depression formed between natural ground and waste dumps and has not reached the height designated for a major dam. Lagoons A and B are neither major dams nor major impoundments. Lagoons C and both have operational criteria based on the seismic design and the Inflow esign Flood (IF) criteria, as summarized in Table 2.3. Table 2.3 TSF esign Flood and esign PGA Tailings Facility Classification Seismic Criteria Flood Criteria (IF)* Lagoon C High Consequence 1/2500 (PGA = 0.13 g) 1/3 between the 1/1000 and Probable Maximum Flood (PMF) Lagoon Very High Consequence 1/5000 (PGA = 0.18 g) 2/3 between the 1/1000 and Probable Maximum Flood (PMF) *Note that the assumed duration of the inflow design flood is 24 hours 2.3 Site Conditions The site has warm, dry summers and cool winters. Temperatures range from an average daily maximum of 24 C in the summer to an average daily minimum of 12 C in the winter. Average annual precipitation is on the order of 450 mm. General site topography includes moderate to steep slopes on rolling to gullied terrain, with small streams interspersed throughout the property. The area is moderately seismic and the 1/5000 year return period earthquake is a magnitude M7 and a peak ground acceleration (PGA) of 0.18 g R Elkview 3rd Party Review.docx Page 7

12 3 REVIEW OF AM SAFETY INSPECTION REPORT 3.1 General The contents of the SI have been compared against the MEM Guidelines for Annual SI Reports and the results are summarized in Table 3.1. Table 3.1 Executive Summary Summary of SI Conformance Requirement Classification of the dam(s) in terms of Consequence of Failure in accordance with Table 2 1 of the CA am Safety Guidelines (2007). Significant changes in instrumentation and/or visual monitoring records Significant changes to dam stability and/or surface water control For major impoundments, as defined in Part 10 of the Code, a current Operation, Maintenance and Surveillance (OMS) Manual is required. The annual report shall indicate the latest revision date of the OMS manual. For tailings dams classified as High, Very High or Extreme Consequence, an Emergency Preparedness Plan (EPP) is required. The annual report shall indicate the latest revision date of the EPP document. Scheduled date for the next formal am Safety Review (SR) in accordance with Table 5 1 of the CA am Safety Guidelines (2007). Formal SRs are required every 5 to 10 years (depending on consequence classification) and differ from annual dam safety inspections. The SRs may be conducted by the Engineer of Record with third party review, or by an independent third party with involvement of the Engineer of Record. Summary of past years construction (if any) with a description of any problems and stabilization. Plan and representative cross sections. Site Photographs. Review of climate data. Included in SI KCB Observations Latest revision is January 2012 Update is required. Reviewed revision is January 2012 Update for November 2014 is in preparation Last SR completed 2013 and the next SR is scheduled for 2018 Water balance review. Not completed for Lagoons A and B Low consequence structures Freeboard and storage availability (in excess of the design flood). Water discharge system, volumes, and quality. NA The tailing ponds do not discharge water. EVO is developing a site wide water balance Seepage occurrence and water quality. Water quality reported to Ministry of Environment Surface water control and surface erosion Erosion discussed on each structure Phreatic surfaces Piezometer readings given Instrumentation Review Settlement Only Lagoon Lateral movement Only Lagoon R Elkview 3rd Party Review.docx Page 8

13 3.2 Consequence Classification Review The Canadian am Association am Safety Guidelines (2007, revised in 2013) provide a classification of dams based on the consequences of failure, which is based on the following: population at risk: none, temporary or permanent; loss of life; environmental and cultural values; and infrastructure and economics. The dam consequence classifications for the various structures are summarized in Table 3.2. Table 3.2 am Classifications Structure Status Consequence Classification MEM Classification (CA, 2013) (HSRC) Lagoon A ecommissioned Low N/A* Lagoon B ecommissioned Low N/A* Lagoon C ecommissioned High Major am and Major Impoundment Lagoon Secondary storage facility Very High Major am and Major Impoundment WFTF Primary storage facility N/A** Major Impoundment Notes: *not classified as major impoundment or major dam *note: does not fall under CA classification KCB agree with the dam classifications, however, for record purposes, EVO should explicitly document the supporting information that provides the basis for dam classification for each of the consequence categories. 3.3 Instrumentation Review The instrumentation program is appropriately summarized and presented in the SI. KCB observations on the piezometer instrumentation include the following: Piezometers and standpipes located in Lagoon indicate that significant portions of the tailings are drained, with a low phreatic surface within most of the perimeter dam. There are numerous perched water levels associated with different stages of construction and, as a result, it is difficult to interpret the spatial extent of the phreatic surface. The relatively low phreatic surface supports the static stability of the structure. The water levels in the standpipes located in WFTF are rising with the associated rise in the tailings surface, which confirms a direct hydraulic connection. Piezometers and standpipes located in Lagoon C indicate that the phreatic surface is just above the original ground surface indicating a well drained structure. The piezometric levels reported do not indicate any dam safety concerns R Elkview 3rd Party Review.docx Page 9

14 The deformation monitoring program is appropriately summarized in the SI. eformation monitoring in Lagoon included two inclinometers, which are showing acceptable horizontal movements. There are no visual signs of deformation in any of the facilities. 3.4 Stability Review The SI indicates that the dams are stable under the design conditions. Lagoon and Lagoon C have been constructed by the upstream construction method and, consequently, contain significant deposits of loose saturated tailings that could liquefy under seismic loading. The stability of Lagoon was addressed in the (2004) report, which indicated that the structure was stable under seismic loading. The SI recommends reassessment of the seismic stability based on an updated understanding of the current seismicity and KCB agree with this recommendation. Lagoons C and comprise outer dam shells constructed of compacted coarse refuse, which is filter compatible with the fine refuse, consequently there is a low risk of piping. The waste rock dumps that abut the west and south slopes of the WFTF comprise mine waste rock that may not be filter compatible with the fine refuse tailings. The SI Report does not consider that the WFTF is yet a dam as the impoundment level is still below the natural ground surface and the piping potential is not addressed. However, the structure will be raised in the future to become a major dam and, accordingly, this aspect should be addressed. The impoundments at Lagoons A, B, C, and and WFTF do not have spillways and flood protection is provided by storage capacity for the Inflow design flood (IF), which is achieved with a freeboard requirement for each impoundment. The SI report provides documentation for freeboard capacity R Elkview 3rd Party Review.docx Page 10

15 4 REVIEW OF TAILINGS FACILITY STEWARSHIP EVO has a good team in place for managing and constructing the facilities and for providing oversight on the technical, environmental and social aspects. EVO manage and maintain the facility adequately and procedures are well documented. The OMS Manual is complete and procedures are in place to manage and respond to emergencies. As part of the KCB preliminary overview of the OMS, we have the following suggestions for improvement: Prepare a separate organization chart that clearly defines the EVO person responsible for the tailings facility, e.g. Tailings Engineer, who is responsible for the tailing facilities. Identify who the person reports to and what other persons report to the Tailings Engineer for matters pertaining to the tailing facilities. ocument the 4 components of the dam consequence classification, in conjunction with the review of the Inundation Study and any other relevant studies R Elkview 3rd Party Review.docx Page 11

16 5 SUMMARY The assessment of the physical conditions of the dams and associated works is thorough and comprehensive and no significant concerns have been identified. Management systems are in place, including OMS Manual and EPPs. The SI Report is compliant with the MEM Guidelines. For reference purposes the recommendations from the SI Report are summarized in Table 5.1. The SI Report does not consider that the WFTF is yet a dam as the impoundment level is still below the natural ground surface. However, the structure will be raised in the future to become a major dam and, accordingly, KCB recommend that the potential for tailings migrating (piping) into the rockfill be assessed and documented by the Engineer of Record by ecember Table 5.1 Summary of 2014 SI Recommendations () No. Recommendation Summary Source of Recommendation Status/Action Timeline Priority 1 etailed risk assessment New Review of development plan 2013 SI None Survey of upstream slope of development area Tailings header pipeline back from edge Flood routing/water management study 6 Repair slumped areas New 7 No discharge spillway or channel and very little freeboard New Jun New ec New ec SI Permission From Geotechnical. epartment Prior to discharge 8 Removal of overhead pipelines 2013 SI Ongoing Prior to spring 2015 Asrequired 2 N/A Comments This Recommendati on is still applicable EVO currently developing a site wide environmental water management model Closed 4 Still applicable 9 Monitor riprap protection 2013 SI+SR OMS updated Closed 10 Assess design evaluations 2013 SR None Still applicable 11 Stability analysis on westembankment 2013 SR None ec Still applicable 12 Compare slopes of lagoons to dam raise designs 2013 SR None ec Still applicable 13 Check standpipes 2013 SR Updating OMS Closed R Elkview 3rd Party Review.docx Page 12

17 No. Recommendation Summary Source of Recommendation Status/Action Timeline Priority 14 Update OMS, EPP, ERP 2013 SR In progress 2014/ Establish reference lines 2013 SR Reference lines marked Comments Updating EPP, ERP and OMS Superseded by no Method for monitoring deformation along reference New ec lines 17 Prepare water balance 2013 SR None Still applicable 18 Piezometer reading frequency 2013 SR Reduced frequency adopted outside of freshet 19 Lagoon C SR 2013 SR None Remove or grout unused buried pipes Continued monitoring of unused pipes Remedial work on Cossarini Creek Consider rerouting Cossarini Creek 2013 SR New 2013 SR 2013 SR Repairs performed in 2013 Culvert upgrade designs completed OMS to be updated in ec Closed Will be completed tentatively by 2018 Superseded by no. 21 Closed 24 Plot piezometer data 2013 SR one Closed Upgrades designed but not implemented 25 Update OMS, EPP, ERP 2013 SR In progress 3 Refer to no Seismic stability analysis of embankments 2013 SR None ec Still applicable 27 Reference lines to replace Ref. lines have Superseded by 2013 SR observation stations been marked no Method for monitoring ground deformation New ec Flood routing study 2013 SR None Reduced 30 Piezometer reading frequencies 2013 SR frequency N/A Closed adopted 31 Lagoon SR 2013 None EVO has planned to complete next SR by R Elkview 3rd Party Review.docx Page 13

18

19 REFERENCES Note that additional references are included in Table 2.1. Environment and Infrastructure () Tailings Storage Facilities West Fork Tailings Facility and Lagoons A, B, C and 2014 am Safety Inspection. November 7, Environment and Infrastructure () West Fork Facility evelopment to El m As Built Report. March 7, Environment and Infrastructure () West Fork Tailings Facility Results of 2013 Site Inspection. July 4, Canadian am Association (CA) Technical Bulletin. am Safety Guidelines (update 2013). Teck Coal (Teck Coal) Inactive Tailings Facilities Emergency Preparedness Plan (EPP) & Emergency Response Plan (ERP). January, Teck Coal (Teck Coal) Lagoon Tailings Facility Emergency Preparedness Plan (EPP) & Emergency Response Plan (ERP). January, Teck Coal (Teck Coal) Operating, Maintenance, and Surveillance Manual Inactive Tailings Facilities Lagoons A, B, & C. January, Teck Coal (Teck Coal) Operating, Maintenance, and Surveillance Manual Tailings eposition Lagoon. January, Teck Coal (Teck Coal) Operating, Maintenance, and Surveillance Manual Tailings eposition West Fork Facility. January, R Elkview 3rd Party Review.docx Page 15

November 27, Bethlehem No. 1 Tailings Storage Facility. Submitted to: Teck Highland Valley Copper Partnership PO Box 1500 Logan Lake, BC V0K 1W0

November 27, Bethlehem No. 1 Tailings Storage Facility. Submitted to: Teck Highland Valley Copper Partnership PO Box 1500 Logan Lake, BC V0K 1W0 INDEPENDENT REVIEW OF 2014 DAM SAFETY INSPECTION AND REVIEW REPORT Bethlehem No. 1 Tailings Storage Facility Submitted to: Teck Highland Valley Copper Partnership PO Box 1500 Logan Lake, BC V0K 1W0 Attention:

More information

New Gold Inc. Independent Third Party Review. Dam Safety Inspection Report. November 2014 M09783A04.730

New Gold Inc. Independent Third Party Review. Dam Safety Inspection Report. November 2014 M09783A04.730 November 2014 M09783A04.730 November 28, 2014 New Gold Inc. New Afton Box 948 Stn. Main, Kamloops, British Columbia V2C 5N4 Mr. Scott Davidson Environment and Social Responsibility Manager Dear Mr. Davidson:

More information

Third Party Review of Dam Safety Inspection Report MAX Molybdenum Mine

Third Party Review of Dam Safety Inspection Report MAX Molybdenum Mine Third Party Review of Dam Safety Inspection Report MAX Molybdenum Mine Prepared for Forty Two Metals Inc. Prepared by SRK Consulting (Canada) Inc. 1CF011.000 December 2014 Third Party Review of Dam Safety

More information

Dankoe Mine. Report on 2014 Dam Safety Inspection of Tailings Storage Facility

Dankoe Mine. Report on 2014 Dam Safety Inspection of Tailings Storage Facility Peter Lighthall, P.Eng Consulting Geotechnical Engineer Dankoe Mine Report on of Tailings Storage Facility Report prepared for 439813 BC Ltd. December 4, 2014 Peter Lighthall, P.Eng. Consulting Geotechnical

More information

The Afton TSF, situated approximately 12 km west of Kamloops, BC has been under care and maintenance since 1997.

The Afton TSF, situated approximately 12 km west of Kamloops, BC has been under care and maintenance since 1997. November 27, 2014 KGHM Ajax Mining Inc. Ajax Project Suite 200-124 Seymour Street Kamloops, BC V2C 2E1 ISSUED FOR USE FILE: V15103098-01 via Email: kate.parsons@kghm.com Attention: Subject: Kate Parsons,

More information

REPORT. Giant Nickel Tailings Dams INDEPENDENT REVIEW OF 2014 DAM SAFETY INSPECTION REPORT. November 26, 2014

REPORT. Giant Nickel Tailings Dams INDEPENDENT REVIEW OF 2014 DAM SAFETY INSPECTION REPORT. November 26, 2014 INDEPENDENT REVIEW OF 2014 DAM SAFETY INSPECTION REPORT Giant Nickel Tailings Dams Submitted to: Barrick Gold Inc. PO Box 788 Penticton, BC V2A 6Y7 Attention: Robbin Harmati REPORT Reference Number: 1412161-003-R-Rev1-2000

More information

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY REPORT ON STAGE 3C CONSTRUCTION (REF.NO. VA-101-1/5-1) Rev. No. Revision Date Approved 0 Issued in Final September 23, 2005 AMEC010485_0001

More information

Understanding of foundation conditions, water balance adequacy and filter adequacy at the closed Nickel Plate tailings impoundment near Hedley, BC

Understanding of foundation conditions, water balance adequacy and filter adequacy at the closed Nickel Plate tailings impoundment near Hedley, BC Barrick Gold Corporation 460 West 50 North, Suite 500 Salt Lake City, Utah 84101 27 June 2015 Al Hoffman, P.Eng. Chief Inspector and Executive Director, Health & Safety British Columbia Ministry of Energy

More information

Review of the 2014 Annual Dam Safety Inspection Report, 2-North Pit Tailings Disposal Facility, Quinsam Coal Mine

Review of the 2014 Annual Dam Safety Inspection Report, 2-North Pit Tailings Disposal Facility, Quinsam Coal Mine November 24, 2014 Quinsam Coal Corporation Hillsborough Resources Limited PO BOX 5000 Campbell River BC V9W 8A3 ISSUED FOR USE FILE: V15103102-01 via Email: gbg@hillsboroughresources.com Attention: Subject:

More information

Peter Lighthall, P.Eng. Consulting Geotechnical Engineer

Peter Lighthall, P.Eng. Consulting Geotechnical Engineer Peter Lighthall, P.Eng. Consulting Geotechnical Engineer Cassiar Gold Corp. China Minerals Mining Corporation Suite 1100 1111 Melville Street Vancouver, BC V6E 3V6 Attn: Re: Ms. Patricia Fong Independent

More information

Reference No L-Rev0-1000

Reference No L-Rev0-1000 June 29, 2015 Reference No. Mr. Mark Slater Teck Coal Limited Greenhills Operations PO Box 5000 Sparwood, BC V0B 1H0 RESPONSE TO MINISTRY OF ENERGY AND MINES MEMORANDUM DATED FEBRUARY 3, 2015, REGARDING

More information

Independent Expert Engineering Investigation and Review Panel. Report on Mount Polley Tailings Storage Facility Breach. Appendix G: Water Balance

Independent Expert Engineering Investigation and Review Panel. Report on Mount Polley Tailings Storage Facility Breach. Appendix G: Water Balance Independent Expert Engineering Investigation and Review Panel Report on Mount Polley Tailings Storage Facility Breach Appendix G: Water Balance January 30, 2015 Report on Mount Polley Tailings Storage

More information

RESPONSE TO BCMEM SCREENING COMMENTS QUANTITATIVE PERFORMANCE OBJECTIVES

RESPONSE TO BCMEM SCREENING COMMENTS QUANTITATIVE PERFORMANCE OBJECTIVES DATE January 27, 2016 REFERENCE No. TO Mr. Luke Moger Mount Polley Mining Corporation FROM Germán Pizarro and Terry Eldridge EMAIL German_Pizarro@golder.com; Terry_Eldridge@golder.com RESPONSE TO BCMEM

More information

19 November 2014 TE VIA COURIER. Glencore Canada Corporation P.O. Box King Street West, Suite 7200 Toronto, ON M5X 1E3

19 November 2014 TE VIA COURIER. Glencore Canada Corporation P.O. Box King Street West, Suite 7200 Toronto, ON M5X 1E3 19 November 2014 TE143006 VIA COURIER Glencore Canada Corporation P.O. Box 405 100 King Street West, Suite 7200 Toronto, ON M5X 1E3 Attention: Mr. John Stroiazzo Reclamation Manager Dear John; Reference:

More information

June 30, 2015 Project No.: C Mr. Kent Christensen, P.Eng. General Manager Huckleberry Mines Limited PO Box 3000 Houston BC, V0J 1Z0

June 30, 2015 Project No.: C Mr. Kent Christensen, P.Eng. General Manager Huckleberry Mines Limited PO Box 3000 Houston BC, V0J 1Z0 Suite 500-980 Howe Street Vancouver, BC Canada V6Z 0C8 Telephone (604) 684-5900 Fax (604) 684-5909 June 30, 2015 Project No.: 1193-005-C Mr. Kent Christensen, P.Eng. General Manager Huckleberry Mines Limited

More information

Understanding of foundation conditions, water balance adequacy and filter adequacy at the closed Snip tailings impoundment in northwest BC

Understanding of foundation conditions, water balance adequacy and filter adequacy at the closed Snip tailings impoundment in northwest BC Barrick Gold Corporation 460 West 50 North, Suite 500 Salt Lake City, Utah 84101 27 June 2015 Al Hoffman, P.Eng. Chief Inspector and Executive Director, Health & Safety British Columbia Ministry of Energy

More information

Dam Safety Inspection Report

Dam Safety Inspection Report Tel. (778) 899-5500 e-mail: JRTGeoEngineering@shaw.ca Dam Safety Inspection Report To: SnipGold Corp. Attention: Mr. Jon Zbeetnoff, President From: J. Roland Tosney, P.Eng. Subject: Johnny Mountain Mine

More information

REPORT. Phase 1: Review Possibility of Mount Polley Mine Conditions at Afton TSF site

REPORT. Phase 1: Review Possibility of Mount Polley Mine Conditions at Afton TSF site GEOTECHNICAL ENGINEERING SERVICES FOR AFTON TAILINGS STORAGE FACILITY Phase 1: Review Possibility of Mount Polley Mine Conditions at Afton TSF site Submitted to: Crystal Vandermeulen KGHM Ajax Mining Inc.

More information

AMERICAN ELECTRIC POWER (SWEPCO)

AMERICAN ELECTRIC POWER (SWEPCO) 2016 DAM & DIKE INSPECTION REPORT ASH PONDS GERS-16-163 WELSH POWER PLANT AMERICAN ELECTRIC POWER (SWEPCO) CASON, TEXAS NATIONAL INVENTORY NO. TX4357 PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

KLONDIKE SILVER - SILVANA MINE Annual Dam Safety Inspection

KLONDIKE SILVER - SILVANA MINE Annual Dam Safety Inspection KLONDIKE SILVER - SILVANA MINE 2014 Annual Dam Safety Inspection Submitted to: Klondike Silver Corp. 430-609 Granville Street Vancouver, BC V7Y 1G5 Attention: Mark Luchinski REPORT Reference Number: 1406428-007-R-Rev0-2000

More information

Mount Polley Mining Corporation IMPERIAL METALS CORPORATION

Mount Polley Mining Corporation IMPERIAL METALS CORPORATION Mount Polley Mining Corporation IMPERIAL METALS CORPORATION 1--\Poo l4 ;;L- February 16, 2006 Nick Rose, P. Eng. Piteau Associates Engineering Ltd. 215-260 West Esplanade North Vancouver, BC V7M3G7 Dear

More information

Keeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement

Keeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement Keeyask Generation Project Environmental Impact Statement Supporting Volume Physical Environment June 2012 KEEYASK GENERATION PROJECT SUPPORTING VOLUME EFFECTS OF THE ENVIRONMENT ON THE PROJECT June 2012

More information

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources Division. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act)

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources Division. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) MINISTRY OF ENERGY AND MINES Mines and Mineral Resources Division REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) Name of Property: Permit No.: M-29 Mine Manager: Don

More information

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL SLI Doc. No. 505573-3000-40EC-0003 01 5-Dec-2013 ii TABLE OF CONTENTS Page No. 1 INTRODUCTION... 1 2 CREST ELEVATIONS... 2 2.1 Cofferdams... 2 2.2 North Spur... 3 3 STABILITY ANALYSIS LOADING CASES AND

More information

FINAL REPORT DAM SAFETY REVIEW. Mount Polley Mine Likely, British Columbia. Submitted to:

FINAL REPORT DAM SAFETY REVIEW. Mount Polley Mine Likely, British Columbia. Submitted to: AMEC Earth & Environmental a division of AMEC Americas Limited 2227 Douglas Road, Burnaby, BC Canada V5C 5A9 Tel +1 (604) 294-3811 Fax +1 (604) 294-4664 www.amec.com FINAL REPORT DAM SAFETY REVIEW Mount

More information

Dirk J.A. van Zyl, Ph.D., P.Eng. P.E. Tailings and Mine Rock Management

Dirk J.A. van Zyl, Ph.D., P.Eng. P.E. Tailings and Mine Rock Management Dirk J.A. van Zyl, Ph.D., P.Eng. P.E. Tailings and Mine Rock Management MEMORANDUM To: From: Subject: Mr. Brent Murphy, Vice President Environment Affairs Dirk van Zyl, Principal Engineer Review Comments

More information

Tailings Storage Facility Conceptual Closure Plan Alternatives Assessment

Tailings Storage Facility Conceptual Closure Plan Alternatives Assessment Appendix 17.4-C Tailings Storage Facility Conceptual Closure Plan Alternatives Assessment AJAX PROJECT Environmental Assessment Certificate Application / Environmental Impact Statement for a Comprehensive

More information

AMERICAN ELECTRIC POWER (SWEPCO)

AMERICAN ELECTRIC POWER (SWEPCO) 2015 DAM & DIKE INSPECTION REPORT ASH PONDS GERS-15-034 WELSH POWER PLANT AMERICAN ELECTRIC POWER (SWEPCO) CASON, TEXAS NATIONAL INVENTORY NO. TX4357 PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION

More information

Knight Piésold TAILINGS FACILITY 2014 DAM SAFETY INSPECTION REPORT BARRICK GOLD INC. GIANT NICKEL MINE. C O N S U L T I N G

Knight Piésold TAILINGS FACILITY 2014 DAM SAFETY INSPECTION REPORT BARRICK GOLD INC. GIANT NICKEL MINE. C O N S U L T I N G TAILINGS FACILITY PREPARED FOR: Barrick Gold Nickel Plate Mine PO Box 788 Penticton, BC V2A 6Y7 PREPARED BY: Knight Piésold Ltd. Suite 1400 750 West Pender Street Vancouver, BC V6C 2T8 Canada p. +1.604.685.0543

More information

Teck Coal Limited Coal Mountain Operations P.0. Box 3000 Sparwood, BC Canada VOB 2GO

Teck Coal Limited Coal Mountain Operations P.0. Box 3000 Sparwood, BC Canada VOB 2GO Teck Coal Limited P.0. Box 3000 Sparwood, BC Canada VOB 2GO +1 250 425 6305 Tel +1 250 425 7373 Fax www.teck..com Teck April 19, 2017 Brent Beattie Senior Geotechnical Inspector Ministry of Energy and

More information

Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria

Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria Terry Eldridge Golder Associates S.A., Chile Ben Wickland Golder Associates Ltd., Canada Adrian Goldstone Dundee Precious Metals

More information

Central Region GeoHazard Assessment H597:02, km Slide May 2011 Site Inspection and Instrumentation Monitoring Report

Central Region GeoHazard Assessment H597:02, km Slide May 2011 Site Inspection and Instrumentation Monitoring Report Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 July 14, 2011 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region GeoHazard Assessment H597:02,

More information

Golder Associates Ltd. (Golder) was retained by Greenstone Gold Mines to complete a peer review for the Hardrock Project in Geraldton, Ontario.

Golder Associates Ltd. (Golder) was retained by Greenstone Gold Mines to complete a peer review for the Hardrock Project in Geraldton, Ontario. DATE January 5, 2016 PROJECT No. 1543540 TO Mr. Bertho Caron, Ing., Engineering Manager Greenstone Gold Mines FROM Reza Moghaddam and Ken Bocking EMAIL Ken_Bocking@golder.com A PEER REVIEW REGARDING THE

More information

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY OPERATION, MAINTENANCE AND SURVEILLANCE MANUAL Rev. No. Revision Date Approved 0 Issued in Final December 22, 2004 1 Issued in

More information

BRALORNE TAILINGS STORAGE FACILITY UPDATED 2014 ANNUAL DAM SAFETY INSPECTION

BRALORNE TAILINGS STORAGE FACILITY UPDATED 2014 ANNUAL DAM SAFETY INSPECTION BRALORNE TAILINGS STORAGE FACILITY UPDATED 2014 ANNUAL DAM SAFETY INSPECTION PREPARED FOR NOVEMBER 21, 2014 ISSUED FOR USE FILE: V15103090-01 Tetra Tech EBA Inc. 150, 1715 Dickson Avenue Kelowna, BC V1Y

More information

Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps. Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band

Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps. Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band Mining, Tailings and Dam Safety: the Mt. Polley Disaster and Next Steps Dr. Andrea Kennedy, Ph.D. Bridgeway Consulting for Adams Lake Indian Band 11 August 2014 Presentation Outline General Introduction

More information

MSHA s Review of Impoundment Plans

MSHA s Review of Impoundment Plans MSHA s Review of Impoundment Plans Kelvin K. Wu, Ph.D, P.E. Harold L. Owens, P.E. John W. Fredland, P.E. Chief, Mine Waste and Geotechnical Engineering Division, Pittsburgh, PA Supervisory Civil Engineer,

More information

Controlling Surface Water at One of Canada s Largest Base Metals Operations: From Legacy Challenges to Environmental Award Winner

Controlling Surface Water at One of Canada s Largest Base Metals Operations: From Legacy Challenges to Environmental Award Winner Controlling Surface Water at One of Canada s Largest Base Metals Operations: From Legacy Challenges to Environmental Award Winner Greg Noack, P.Eng., Associate, Klohn Crippen Berger Ltd., Toronto ON. Lawrence

More information

McElroy s Run Impoundment Structural Stability Assessment Report

McElroy s Run Impoundment Structural Stability Assessment Report Allegheny Energy Supply Company, LLC A FirstEnergy Company Pleasants Power Station Pleasants County, West Virginia October 2016 Prepared for: Allegheny Energy Supply Company, LLC A FirstEnergy Company

More information

December 12, 2014

December 12, 2014 www.knightpiesold.com File No.:VA101-246/41-A.01 Cont. No.:VA14-01866 Kate Parsons Environmental Manager KGHM Ajax Mining Inc. 200-124 Seymour St. Kamloops, British Columbia Canada, V2C 2E1 Dear Kate,

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY (i) Site Name and Ownership Information: Site Name: Plant Hammond Site Location: Site Address:

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116 (i) Site Name and Ownership Information: HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY Site Name: Site Location: Site Address: Owner: Owner Address:

More information

Tailings System Safety Review for the Quirke Tailings Management Area in Elliot Lake

Tailings System Safety Review for the Quirke Tailings Management Area in Elliot Lake Tailings System Safety Review for the Quirke Tailings Management Area in Elliot Lake Shiu N. Kam (Golder Associates Ltd.) Maxine A. Wiber (Rio Algom Limited) Roger A. Payne (Consultant) John B. Davis (Golder

More information

Reference: 24 Mile Lake Geotechnical Assessment and Standard Operating Procedure

Reference: 24 Mile Lake Geotechnical Assessment and Standard Operating Procedure 20 November 2014 AMEC File: VM00615 VIA EMAIL Teck Highland Valley Copper Partnership P.O. Box 1500 Logan Lake, British Columbia V0K 1W0 Attention: Mr. Chris Fleming Dear Chris, Reference: 24 Mile Lake

More information

Coal Combustion Residuals Inflow Design Flood Control System Plan

Coal Combustion Residuals Inflow Design Flood Control System Plan gaiconsultants.com I transforming ideas into reality., Coal Combustion Residuals Inflow Design Flood Control System Plan Virginia Electric and Power Company Possum Point Power Station Surface Impoundment

More information

2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio

2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio Prepared for: FirstEnergy Generation, LLC 76 South Main St Akron, Ohio 44308 2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio Prepared by: 10211 Wincopin Circle, Floor 4 Columbia,

More information

Active Coal Combustion Residuals Landfill Annual Inspection Escalante Generating Station

Active Coal Combustion Residuals Landfill Annual Inspection Escalante Generating Station REPORT Active Coal Combustion Residuals Landfill Annual Inspection Escalante Generating Station Submitted to: Tri-State Generation and Transmission Association, Inc. 1100 West 116th Avenue Westminster,

More information

DAM SAFETY REVIEW. Mount Polley Mine Likely, British Columbia DRAFT. Submitted to: Imperial Metals Corporation Hornby Street Vancouver, BC

DAM SAFETY REVIEW. Mount Polley Mine Likely, British Columbia DRAFT. Submitted to: Imperial Metals Corporation Hornby Street Vancouver, BC DAM SAFETY REVIEW Mount Polley Mine Likely, British Columbia DRAFT November 2006 Submitted to: Imperial Metals Corporation 200 580 Hornby Street Vancouver, BC Submitted by: AMEC Earth & Environmental Limited

More information

Coal Combustion Residuals Unit Structural Stability Assessment

Coal Combustion Residuals Unit Structural Stability Assessment Coal Combustion Residuals Unit Structural Stability Assessment Virginia Electric and Power Company Chesterfield Power Station Upper (East) Pond Chesterfield County, Virginia GAI Project Number: C1500035.00

More information

2017 ANNUAL DAM AND DIKE INSPECTION REPORT

2017 ANNUAL DAM AND DIKE INSPECTION REPORT 2017 ANNUAL DAM AND DIKE INSPECTION REPORT ASH PONDS WELSH POWER PLANT CASON, TEXAS November, 2017 Prepared by: American Electric Power Service Corporation 1 Riverside Plaza Columbus, OH 43215 GERS-17-067

More information

Modified Centreline Construction of Tailings Embankn1ents

Modified Centreline Construction of Tailings Embankn1ents Modified Centreline Construction of Tailings Embankn1ents J.P. Haile & K.J. Brouwer Knight Piesold Ltd. Consulting Engineers Suite 1400-750 West Pender Street Vancouver, B.C., Canada V6C 2T8 Abstract:

More information

VICINITY MAP AND SITE MAP. Page 1 of 9

VICINITY MAP AND SITE MAP. Page 1 of 9 INTRODUCTION... 2 1. Background Information of West Bottom Ash Pond (BAP)... 2 1.1 Facility Location Description...2 1.2 Description of West BAP CCR Unit...2 1.2.1 Embankment Configuration...2 1.2.2 Construction

More information

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Updated: November 2010 Directive 74 Appendix C Requirement Approval: 8512D Submitted to SHELL CANADA ENERGY MRM DDA PLAN-UPDATE NOV

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

1 INTRODUCTION. 1.1 General. 1.2 Project Background. August 9, City of Nanaimo 2020 Labieux Road Nanaimo, British Columbia B9T 6J9

1 INTRODUCTION. 1.1 General. 1.2 Project Background. August 9, City of Nanaimo 2020 Labieux Road Nanaimo, British Columbia B9T 6J9 August 9, 2013 City of Nanaimo 2020 Labieux Road Nanaimo, British Columbia B9T 6J9 Bill Sims, A.Sc.T. Manager, Water Resources Dear Mr. Sims: Nanaimo, BC 1 INTRODUCTION 1.1 General Klohn Crippen Berger

More information

2018 Annual Dam and Dike Inspection Report

2018 Annual Dam and Dike Inspection Report 218 Annual Dam and Dike Inspection Report Bottom Ash Pond Northeastern 3&4 Plant Public Service Company of Oklahoma Oologah, Oklahoma September 218 Prepared for: Public Service Company of Oklahoma Northeastern

More information

Central Region GeoHazard Assessment Site C8 SH597:02 East of Blackfalds May 2007 Site Assessment and Instrumentation Monitoring Report

Central Region GeoHazard Assessment Site C8 SH597:02 East of Blackfalds May 2007 Site Assessment and Instrumentation Monitoring Report Alberta Infrastructure & Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 May 18, 2007 Mr. Alain Momedi, P.Eng. Project Engineer Dear Mr. Momedi: Central Region GeoHazard Assessment

More information

Barkerville Gold Mines Ltd.

Barkerville Gold Mines Ltd. Barkerville Gold Mines Ltd. Goldstream Tailings Storage Facility Background Report for Response to MEM Memorandum M09967A03 June 2015 June 30, 2015 Barkerville Gold Mines Ltd. 11 th Floor, 1111 Melville

More information

INSPECTION REPORT. Third Annual RCRA CCR Unit Inspection Report January 2018 WASTE DISPOSAL AREA SURFACE IMPOUNDMENT

INSPECTION REPORT. Third Annual RCRA CCR Unit Inspection Report January 2018 WASTE DISPOSAL AREA SURFACE IMPOUNDMENT INSPECTION REPORT NORTHERN INDIANA PUBLIC SERVICE COMPANY R.M. SCHAHFER GENERATING STATION Third Annual RCRA CCR Unit Inspection Report January 2018 WASTE DISPOSAL AREA SURFACE IMPOUNDMENT Submitted To:

More information

Greg Noack, P.Eng. Greg Puro, P.Eng. and Trevor Ross, P.Eng. 2

Greg Noack, P.Eng. Greg Puro, P.Eng. and Trevor Ross, P.Eng. 2 MANAGING SURFACE WATER AT CVRD INCO S INTEGRATED MINING, MILLING AND SMELTING OPERATIONS IN SUDBURY ONTARIO: IMPLEMENTING MODERN SOLUTIONS TO LEGACY CHALLENGES 1 Greg Noack, P.Eng. Greg Puro, P.Eng. and

More information

Dam Safety and Seismicity

Dam Safety and Seismicity Dam Safety and Seismicity January 13, 2014 Fort St. John, BC John Nunn, P.Eng, M.Sc., M.I.C.E Chief Project Engineer Tim Little, P. Eng. Topics 1. The Practice of Dam Safety in BC Hydro 2. Bennett Dam

More information

DTE Energy St. Clair Power Plant

DTE Energy St. Clair Power Plant DTE Energy St. Clair Power Plant Unit 6 Scrubber Basins CCR Rule Compliance Project Annual Inspection Report - 2017 Project Number: 60546402 June 30, 2017 Prepared by: 27777 Franklin Road, Suite 2000 Southfield,

More information

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE DESIGN OF THE TAILINGS STORAGE FACILITY TO ULTIMATE ELEVATION (REF. NO.

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE DESIGN OF THE TAILINGS STORAGE FACILITY TO ULTIMATE ELEVATION (REF. NO. MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE DESIGN OF THE TAILINGS STORAGE FACILITY TO ULTIMATE ELEVATION (REF. NO. VA101-001/08-1) Rev. No. Revision Date Approved 0 Issued for Report March 14, 2005

More information

SCHEDULE. 1 Part 10 of the Health, Safety and Reclamation Code for Mines in British Columbia is repealed and the following is substituted:

SCHEDULE. 1 Part 10 of the Health, Safety and Reclamation Code for Mines in British Columbia is repealed and the following is substituted: REVISIONS TO PART 10 EFFECTIVE AS OF JULY 20, 2016 SCHEDULE 1 Part 10 of the Health, Safety and Reclamation Code for Mines in British Columbia is repealed and the following is substituted: TABLE OF CONTENTS

More information

Dewatered Tailings Management ARD Aspects. Todd Martin, P.Eng., P.Geo. AMEC Vancouver

Dewatered Tailings Management ARD Aspects. Todd Martin, P.Eng., P.Geo. AMEC Vancouver Dewatered Tailings Management ARD Aspects Todd Martin, P.Eng., P.Geo. AMEC Vancouver Overview This presentation will more introduce the tailings continuum and nature of dewatered tailings Expectation is

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

STRUCTURAL STABILITY ASSESSMENT. Bremo Power Station CCR Surface Impoundment: North Ash Pond STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT. Bremo Power Station CCR Surface Impoundment: North Ash Pond STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT Bremo Power Station CCR Surface Impoundment: North Ash Pond ~,Dominion Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff,

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO. 0200-S3N-R2 AFIN: 32-00042 JANUARY 15, 2016 ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

Material properties of Tailings from Swedish mines

Material properties of Tailings from Swedish mines Material properties of Tailings from Swedish mines I. Jantzer Luleå University of Technology, Sweden, Isabel.Jantzer@ltu.se A. Bjelkevik Sweco AB, Sweden, Annika.Bjelkevik@sweco.se K. Pousette Luleå University

More information

30 June 2015 NX14001F. Nyrstar Myra Falls Ltd. P.O. Box 8000 Campbell River, British Columbia V9W 5E2 VIA & COURIER. Environmental Manager

30 June 2015 NX14001F. Nyrstar Myra Falls Ltd. P.O. Box 8000 Campbell River, British Columbia V9W 5E2 VIA  & COURIER. Environmental Manager NX14001F Nyrstar Myra Falls Ltd. P.O. Box 8000 Campbell River, British Columbia V9W 5E2 VIA EMAIL & COURIER Attention: Ms. Nicole Pesonen Environmental Manager Dear Ms. Pesonen: Re: Nyrstar Myra Falls

More information

IN THE MATTER OF THE ENGINEERS AND GEOSCIENTISTS ACT R.S.B.C. 1996, CHAPTER 116. and. IN THE MATTER OF Todd Martin, P.Eng., P.Geo.

IN THE MATTER OF THE ENGINEERS AND GEOSCIENTISTS ACT R.S.B.C. 1996, CHAPTER 116. and. IN THE MATTER OF Todd Martin, P.Eng., P.Geo. IN THE MATTER OF THE ENGINEERS AND GEOSCIENTISTS ACT R.S.B.C. 1996, CHAPTER 116 and IN THE MATTER OF Todd Martin, P.Eng., P.Geo. NOTICE OF INQUIRY TO: Todd Martin, P.Eng., P.Geo. c/o Harris & Company 14

More information

MOUNT POLLEY MINE Tailings Storage Facility Stage 8/8A 2012 As-Built Report. Submitted to: Mount Polley Mining Corporation, Likely, BC.

MOUNT POLLEY MINE Tailings Storage Facility Stage 8/8A 2012 As-Built Report. Submitted to: Mount Polley Mining Corporation, Likely, BC. AMEC Environment & Infrastructure, a division of AMEC Americas Limited Suite 600-4445 Lougheed Highway, Burnaby, BC Canada V5C 0E4 Tel +1 (604) 294-3811 Fax +1 (604) 294-4664 www.amec.com MOUNT POLLEY

More information

Phone (604) Local 233 Fax (604) RGC REPORT NO /7

Phone (604) Local 233 Fax (604) RGC REPORT NO /7 ROBERTSON GEOCONSULTANTS INC. A Robertson Group Company Consulting Geotechnical and Environmental Engineers Suite 640, 580 Hornby St., Vancouver BC, Canada V6C 3B6 Phone (604) 684-8072 Local 233 Fax (604)

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO. 0199-S3N-R3 AFIN: 35-00110 JANUARY 15, 2016 ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

DTE Energy Monroe Power Plant

DTE Energy Monroe Power Plant DTE Energy Monroe Power Plant Inactive Bottom Ash Impoundment CCR Rule Compliance Project Annual Inspection Report - 2018 Project Number: 60516675 September 7, 2018 Prepared by: 27777 Franklin Road, Suite

More information

Request Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects

Request Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects Request Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects References: EIS Guidelines Sec. 23.2; EIS Vol. 5, Section 37.2; EIS, Vol. 6, Technical Memo Dam Safety; Meeting Notes BC Hydro,

More information

Northern Indiana Public Service Company (NIPSCO) 2723 East 1500 North, Wheatfield, Indiana USA Golder Associates Inc.

Northern Indiana Public Service Company (NIPSCO) 2723 East 1500 North, Wheatfield, Indiana USA Golder Associates Inc. Northern Indiana Public Service Company R.M. Schahfer Generating Station Fourth Annual RCRA CCR Unit Inspection Report Waste Disposal Area Surface Impoundment Submitted to: Northern Indiana Public Service

More information

2018 TAILINGS AND MINE WASTE CONFERENCE ALTERNATIVE APPROACHES TO MANAGEMENT FACILITIES AND CLOSURE OF TAILINGS STORAGE

2018 TAILINGS AND MINE WASTE CONFERENCE ALTERNATIVE APPROACHES TO MANAGEMENT FACILITIES AND CLOSURE OF TAILINGS STORAGE 2018 TAILINGS AND MINE WASTE CONFERENCE ALTERNATIVE APPROACHES TO MANAGEMENT AND CLOSURE OF TAILINGS STORAGE FACILITIES Professor David Williams Director Geotechnical Engineering Centre The University

More information

POST CLOSURE PLAN. CFR (d) Pond 1. Clinch Power Plant Russell County, West Virginia. November Prepared for: Appalachian Power Company

POST CLOSURE PLAN. CFR (d) Pond 1. Clinch Power Plant Russell County, West Virginia. November Prepared for: Appalachian Power Company POST CLOSURE PLAN CFR 257.104(d) Pond 1 Clinch Power Plant Russell County, West Virginia November 2016 Prepared for: Appalachian Power Company Prepared by: Amec Foster Wheeler Environment & Infrastructure,

More information

Informational Meeting- March 31, Boxelder B-2/B-3 Watershed Planning Study

Informational Meeting- March 31, Boxelder B-2/B-3 Watershed Planning Study Informational Meeting- March 31, 2016 Boxelder B-2/B-3 Watershed Planning Study Agenda Introductions Work Completed to Date Phase 1 Evaluations Alternatives Evaluations Economic Evaluations Draft Watershed

More information

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY OPERATION, MAINTENANCE AND SURVEILLANCE MANUAL Rev. No. Revision Date Approved 0 Issued in Final December 22, 2004 1 Issued in

More information

CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park

CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park CBC Case Study-1212 1 of 5 CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park More Than Geotechnical Engineering DAYTON 125 Westpark Road Centerville, OH 45459 Phone: 937-428-6150 HAZARD

More information

Coal Combustion Facility Assessment Report. October 20, 2010

Coal Combustion Facility Assessment Report. October 20, 2010 Coal Combustion Facility Assessment Report October 20, 2010 Introduction Stantec Consulting Services Inc. North American Consulting Firm 10,000 Engineers, Geologists, Architects, Scientists and Technicians

More information

BAP or BAT? A review of some dramatic changes in tailings management in the recent past and potential changes in the future

BAP or BAT? A review of some dramatic changes in tailings management in the recent past and potential changes in the future BAP or BAT? A review of some dramatic changes in tailings management in the recent past and potential changes in the future Andy Fourie School of Civil, Environmental & Mining Engineering 1 BAP or BAT?

More information

TAILING & HEAP LEACH FACILITY MANAGEMENT PURPOSE & OBJECTIVES CONTENT. 1. Planning & Design

TAILING & HEAP LEACH FACILITY MANAGEMENT PURPOSE & OBJECTIVES CONTENT. 1. Planning & Design PURPOSE & OBJECTIVES This Tailing & Heap Leach Facility Management Standard (the Standard ) sets the minimum Newmont requirements for the design and management of tailing storage facilities (TSF) and heap

More information

CCR Rule Annual Inspection Report 2

CCR Rule Annual Inspection Report 2 Inspection Description An ARCADIS team performed the Trimble County Gypsum Storage Pond (GSP) 2015 annual inspection by a qualified professional engineer. The overall goal of the inspection was to ensure

More information

2014 Spring Geotechnical Inspection

2014 Spring Geotechnical Inspection 2014 Spring Geotechnical Inspection Prepared by: Minto Explorations Ltd. Minto Mine August, 2014 2014 Spring Geotechnical Inspection Page ii Table of Contents 1 Introduction...1 1.1 License Requirements...

More information

MOUNT POLLEY MINE Tailings Storage Facility 2011 Construction. As-Built Report and Annual Review

MOUNT POLLEY MINE Tailings Storage Facility 2011 Construction. As-Built Report and Annual Review AMEC Environment & Infrastructure, a division of AMEC Americas Limited Suite 600-4445 Lougheed Highway, Burnaby, BC Canada V5C 0E4 Tel +1 (604) 294-3811 Fax +1 (604) 294-4664 www.amec.com MOUNT POLLEY

More information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information Table of Contents Section Page 5.1 GENERAL... 5.1-1 5.1.1 Overview... 5.1-1 5.1.2 Investigation and Engineering Information... 5.1-2 5.2 PRELIMINARY GEOTECHNCIAL REPORTS... 5.2-1 5.2.1 Preliminary Geotechnical

More information

July 7, 2008 File: Mine No.:

July 7, 2008 File: Mine No.: .._. i53s4 BRITISH COLUMBIA The Best Place on Earth July 7, 2008 File: 18040-02-07 Mine No.: 1101163 Tim Fisch Mount Polley Mining Corporation Po Box 12 Likely BC, VOL 1 NO Dear Sir: Re: Mine Inspection

More information

Newmont Mining Corporation Tailing & Heap Leach Facility Management Standard

Newmont Mining Corporation Tailing & Heap Leach Facility Management Standard Page No: Page 1 of 5 1 PURPOSE AND OBJECTIVES This (the Standard ) sets the minimum Newmont requirements for the design and management of tailing storage facilities (TSF) and heap leach facilities (HLF)

More information

2015 INSPECTION REPORT FLY ASH DAM and BOTTOM ASH POND COMPLEX JOHN AMOS PLANT ST. ALBANS, WEST VIRGINIA. June 2015

2015 INSPECTION REPORT FLY ASH DAM and BOTTOM ASH POND COMPLEX JOHN AMOS PLANT ST. ALBANS, WEST VIRGINIA. June 2015 2015 INSPECTION REPORT FLY ASH DAM and BOTTOM ASH POND COMPLEX JOHN AMOS PLANT ST. ALBANS, WEST VIRGINIA June 2015 PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS,

More information

2016 DAM AND DIKE INSPECTION REPORT CCR PONDS COMPLEX

2016 DAM AND DIKE INSPECTION REPORT CCR PONDS COMPLEX 2016 DAM AND DIKE INSPECTION REPORT CCR PONDS COMPLEX GERS-16-168 OKLAUNION POWER STATION VERNON, TEXAS PREPARED BY AEP SERVICE CORPORATION CIVIL ENGINEERING DIVISION GEOTECHNICAL ENGINEERING SECTION 1

More information

Santa Clara Valley Water District Page 1 of 4

Santa Clara Valley Water District Page 1 of 4 Santa Clara Valley Water District File No.: 17-0256 Agenda Date: 4/28/2017 Item No.: 6. BOARD AGENDA MEMORANDUM SUBJECT: Discussion on the Anderson Dam Seismic Retrofit Project. RECOMMENDATION: A. Receive

More information

2016 ANNUAL DAM AND DIKE INSPECTION REPORT. Bottom Ash Ponds. Rockport Plant Spencer County, Indiana. December 6 th, 2016

2016 ANNUAL DAM AND DIKE INSPECTION REPORT. Bottom Ash Ponds. Rockport Plant Spencer County, Indiana. December 6 th, 2016 2016 ANNUAL DAM AND DIKE INSPECTION REPORT Bottom Ash Ponds Rockport Plant Spencer County, Indiana December 6 th, 2016 Prepared for: Indiana Michigan Power Company Rockport Plant 2791 North US 231 Rockport,

More information

Enviable water recovery in a desert environment a case study

Enviable water recovery in a desert environment a case study Mine Water Solutions 2013 J. Obemeyer, J. Enriquez and T. Alexieva 2013 InfoMine Inc, Vancouver, Canada, ISBN XXX Enviable water recovery in a desert environment a case study James R. Obermeyer, MWH Americas,

More information

VISUAL SITE INSPECTION REPORT 2018

VISUAL SITE INSPECTION REPORT 2018 VISUAL SITE INSPECTION REPORT 2018 SOUTHERN INDIANA GAS AND ELECTRIC A. B. BROWN GENERATING STATION TYPE III RESTRICTED WASTE LANDFILL WEST FRANKLIN, IN ATC PROJECT NO. 170LF00614 January 9, 2019 PREPARED

More information

DAM AND CANAL SAFETY GUIDELINES

DAM AND CANAL SAFETY GUIDELINES WATER ACT WATER (MINISTERIAL) REGULATION PART 6 DAM AND CANAL SAFETY GUIDELINES Prepared by: Dam Safety and Water Projects Branch Alberta Environmental Protection 8th Floor, Oxbridge Place 9820-106 Street

More information

Fly Ash Reservoir II Dam Initial Safety Factor Assessment. Cardinal Power Plant Brilliant, Ohio S&ME Project No A

Fly Ash Reservoir II Dam Initial Safety Factor Assessment. Cardinal Power Plant Brilliant, Ohio S&ME Project No A Fly Ash Reservoir II Dam Initial Safety Factor Assessment Cardinal Power Plant Brilliant, Ohio S&ME Project No. 7217-15-006A Prepared for: American Electric Power 1 Riverside Plaza, 22 nd Floor Columbus,

More information