Workshop on Mercury Management Almaden 2013 Decommissioning planning and management in the chlorine- alkali industry
|
|
- Kimberly Hines
- 6 years ago
- Views:
Transcription
1 Workshop on Mercury Management Almaden 2013 Decommissioning planning and management in the chlorine- alkali industry December 13, 2013 Antonio CAPRINO
2 INTRODUCTION Commitment of the European chlor-alkali industry to shut down cell rooms using Hg cell technology by 2020 (at the latest) Mercury based capacity represents today ~30% of the total chlorine production capacity. Beginning of 2013, still 31 chlorine cell rooms using mercury cell technology in Europe. In some of the EU countries, strong pressure to speed up the shut down : National or regional legislations (interdiction of technology or limitation of emissions) Local permits 2
3 INTRODUCTION Manufacturing Processes EUROCHLOR % % of total capacity 60% 50% 40% 3 30% 20% 10% 0% Mercury Diaphragm Membrane Other
4 Conversion mercury cells Eurochlor document of reference Conversion from Mercury to Alternative Technology in the Chlor-Alkali Industry (updated June 2012). World chlorine production capacity in mercury plants (WCC ) 4
5 Factors influencing conversion Energy prices and efficiency Membrane cells consuming less electrical energy, but consuming steam for caustic concentration. Production capacity If the market demand more production, membrane installation or conversion can be the opportunity Selection of current density : lower density requires more electrolysers Product quality Membrane needs a higher quality of brine Chlorine membrane has lower quality Caustic need to be concentrate Market conditions 5
6 Investment and payback In 2008 Prochemics, an independent consultant company made a study for Eurochlor to evaluate the conversion costs, taking to account data of Recently UNEP article about this theme : Story of the month - August 2012 :Converting to a Cost-Effective Mercury Free Technology in the Chlor-Alkali Industry To convert an existent mercury plant into membrane New electrolysers Replacement or adapt rectifiers Purification brine Caustic concentration Cost Cost USd/ton capacity Time schedule for conversion: months Pay back: years 6
7 SOLVAY EXPERIENCE SOLVAY plants around the world (at ) 13 plants, more than 2 Mt Cl 2 /y 4 plants with mercury technology (2 in Spain + 1 in Belgium + 1 in Argentine) SOLVAY Mercury plants conversion ( ) : Rosignano (I) 1 cellroom 120 ktcl 2 /y 2007 : Bussi (I) 1 cellroom 80 ktcl 2 /y 2009 : Santo André (BR) 4 cellrooms 106 ktcl 2 /y SOLVAY Mercury plants conversion projects Lillo (B) : 2012 (done 02/12/12) 1 cellroom 180 ktcl 2 /y Tavaux (F) : 2012 (in execution) 2 cellrooms 240 ktcl 2 /y 7
8 INTRODUCTION Manufacturing Processes SOLVAY SOLVAY - % of total capacity 90% 80% Conversion of Tavaux and Lillo Hg capacities 70% 60% 50% 40% 30% 20% 10% 0% Mercury Diaphragm Membrane
9 Focus of the presentation Reference documents to be used for preparing the decommissioning Management of decommissioning activities within Solvay Central decommissioning project team (Hermes Project) Local management in the plants Experience in Europe Rosignano plant to be transferred to Lillo and Tavaux plants. Experience in Brazil plant. Main lessons & highlights 9
10 Reference Documents EUROCHLOR : Env. Prot. 3 Guideline for Decommissioning of Mercury Chlor-Alkali Plants Env. Prot. 19 Guidelines for the preparation for permanent storage of metallic mercury above ground or in underground mines. LOCAL DOCUMENTS : e.g. French S.H.D Protocole de démantèlement de salle d électrolyse à cathode de mercure COMPANY INTERNAL DOCUMENTS (if any) Procedures Chronogram, plans 10
11 Management of the decommissioning Solvay Hermes Project Objectives : Definition of the process to be followed for Hg cell rooms decommissioning in the Solvay Group Preparing a technical database for Hg contaminated equipments. Project Team Project Leader Process (former Hg Cell room production manager) Specialists of HSE and Corporate Purchasing Departments Local Team on site for management of the decommissioning Starting date :
12 Decommissioning Management on site Early estimation of the different contaminated wastes to be disposed of, and definition of the equipments to be maintained in operation for Hg exposure concern. 12 SOLVAY experience : to t of contaminated materials per unit. Contaminated materials (not exhaustive) : Steal, other metals (Copper, Aluminium) Mercury Graphite, carbon PVC, FRP, other plastics Hard Rubber from rubber-lined equipments Gaskets Sand, sludge Electrical equipments Concrete, bricks
13 13 Decommissioning Management on site Definition of the treatment/disposal solutions for each contaminated equipment/waste, based on the techniques listed by the Hermès team. Provision of the containers for metallic mercury storage/transportation Treatment/disposal solutions for each waste can depend on national regulation. Early discussions and ITB with subcontractors for dismantling activities. Technical solution proposed for each type of waste Solutions for disposal Well documented action plan for discussions with local authorities Definition of people management during dismantling Needs (local, external) Medical and environmental monitoring Cost control
14 14 Decommissioning Phases Phase 1 : Health and Safety preliminary actions Emptying of the equipments (mercury, other fluids) Cleaning of the different equipments, tightening, covering with water if needed. Dismantling of non-hg equipments (incl. anodes, cell covers, ) Skilled people from the plant (e.g. people in charge of the operation of the Hg cell room) Phase 2 : Dismantling of the equipments Dismantling of all the equipments, except equipments kept in operation for HSE concerns Can be subcontracted if no skilled people available. Phase 3 : Dismantling of all remaining equipments Electrical equipments Treatment units, Subcontracted in the most of cases.
15 SOLVAY Rosignano (Italy) SOLVAY Santo Andre (Brazil)
16 Rosignano - Main figures Mercury Cell room Chlorine capacity : 120 kt/y Number of cells : 50 of 30 m 2 Decommissioning activities Shut down : May 2007 End of Safety Preliminary actions : March 2008 Dismantling plan accepted by local authorities in August End of dismantling activities : end
17 Rosignano Plant overview Cell room 17
18 18 Cellroom after the Health & Safety preliminary actions
19 Cells dismantling Cell «confinement» for dismantling 19
20 Cells dismantling Cell «confinement» for dismantling (connected to air treatment unit) 20
21 Working area for safe handling of the contaminated equipments Working area connected to Hg effluents treatment unit and regularly washed 21
22 Specific zone (connected to air treatment) for some Hg equipments dismantling 22
23 Floor of the cell room regularly washed 23
24 Santo Andre - Main figures Mercury Cell room Chlorine capacity : 106 kt/y Number of cells : 52 of 12 m of 10 m 2 Decommissioning activities Shut down : February 2009 End of Safety Preliminary actions : December 2009 Dismantling plan accepted by local authorities: December End of dismantling activities : end
25 Cellroom dismantling phases In process of Health & Safety action End of Health & Safety action 25 End of cells dismantling
26 26 Cell room after the Health & Safety preliminary actions
27 mar Material recuperation: example of tendency Recuperação de material (acumulado) 10000,0 TITANIO (e) COBRE (e) ALUMINIO (e) FERRO (d) MERCÚRIO (e) OUTROS (e) 1000,0 100,0 10,0 1,0 ene-09 mar-09 may-09 jul-09 sep-09 nov-09 ene-10 mar-10 may-10 jul-10 sep-10 nov-10 ene-11 mar-11 may-11 jul-11 sep-11 nov-11 ene-12 mes ton
28 28 Teams and time for dismantling Horas trabalhadas Mão Obra SOLVAY Mão de obra Contratada Externo Total SLV (d) Total contratada (d) Total Acumulado (d) Externo jan/09 fev/09 mar/09 abr/09 mai/09 jun/09 jul/09 ago/09 set/09 out/09 nov/09 dez/09 jan/10 fev/10 mar/10 abr/10 mai/10 jun/10 jul/10 ago/10 set/10 out/10 nov/10 dez/10 jan/11 fev/11 mar/11 abr/11 mai/11 jun/11 jul/11 ago/11 set/11 out/11 nov/11 dez/11 jan/12 fev/12 mar/12 abr/ mês hs
29 Main lessons & highlights Decommissioning of a Hg cell room has to be managed as a specific project : Dedicated project team Project to be structured carefully Study to be started at an early step the Hg cell room shut-down strategy can affect the conversion start-up schedule - in case of a conversion) Early definition of the equipments to be maintained in operation during decommissioning List of contaminated equipments/wastes and treatment solutions to be prepared for further discussions with subcontractors and local authorities. 29
30 Main lessons & highlights Health of workers : Has to be considered at an early step (definition of the equipments to be maintained in operation for Health concerns) Work with skilled people (e.g. from Hg cell room operation team) when possible, at least for safety preliminary actions. Regular monitoring of Hg exposure (air and biomonitoring) 30 Key points : People engaged: internal and external (contractors) Creativity and Innovative solutions. Controls: to have indicators of evolution
31 Thank you for your attention Antonio CAPRINO
Horizon 2020 Initiative to de-pollute the Mediterranean by the year 2020
Horizon 2020 Initiative to de-pollute the Mediterranean by the year 2020 www.h2020.net in collaboration with UNEP/MAP Training on mercury management and remediation of contaminated sites Decommission plan
More informationManagement of Mercury from Decommisioning of Chlor-Alkali Mercury Cell Plants
Management of Mercury from Decommisioning of Chlor-Alkali Mercury Cell Plants UNEP Global Mercury Partnership Supply and Storage Experts Group Meeting Madrid, October 25-26th, 2016 Jorge BARCELÓ Ercros,
More informationGuideline for the Minimisation of Mercury Emissions and Waste from Mercury Chlor-Alkali Plants
Guideline for the Minimisation of Mercury Emissions and Waste from Mercury Chlor-Alkali Plants Env. Prot. 13 January 2014 EURO CHLOR PUBLICATION This document can be obtained from: EURO CHLOR - Avenue
More informationGuideline for Decommissioning of Mercury Chlor-Alkali Plants
Guideline for Decommissioning of Mercury Chlor-Alkali Plants Env Prot 3 August 2012 EURO CHLOR PUBLICATION This document can be obtained from: EURO CHLOR - Avenue E. Van Nieuwenhuyse 4, Box 2 - B-1160
More informationOperational Standards (procedures) how to introduce them to the facility Global Safety Team-Safety Workshop Alfredo Infanzón Gabriel Steiner
Operational Standards (procedures) how to introduce them to the facility 2014 Global Safety Team-Safety Workshop Alfredo Infanzón Gabriel Steiner Some questions about Process Safety Management -PSM GSP
More informationImpact analysis of the Spanish electric energy market liberalization on Chlor-alkali industry
CHEMICAL ENGINEERING TRANSACTIONS Volume 21, 2010 Editor J. J. Klemeš, H. L. Lam, P. S. Varbanov Copyright 2010, AIDIC Servizi S.r.l., ISBN 978-88-95608-05-1 ISSN 1974-9791 DOI: 10.3303/CET1021015 85 Impact
More informationWorkshop 2011 of Asian Network. in Hong Kong. Jeffrey Chan. Hong Kong SAR Government 29 November 2011
Workshop 2011 of Asian Network Update on Waste Import and Export Control in Hong Kong Jeffrey Chan Environmental Protection Department Hong Kong SAR Government 29 November 2011 Waste Import/Export Activities
More informationEU Legislation on Export/Storage/Disposal of Mercury
EU Legislation on Export/Storage/Disposal of Mercury Oscar González Sánchez Spanish Ministry of Agriculture, Food and Environmental Affairs Almaden, December 2012 Framework Legislation Waste Framework
More informationGuideline for Decommissioning of Mercury Chlor-Alkali Plants
Guideline for Decommissioning of Mercury Chlor-Alkali Plants Env Prot 3 September 2009 EURO CHLOR PUBLICATION This document can be obtained from: EURO CHLOR - Avenue E. Van Nieuwenhuyse 4, Box 2 - B-1160
More informationElectro-refining: How it Works
Sign In Forgot Password Register username username password password Sign In If you like us, please share us on social media. The latest UCD Hyperlibrary newsletter is now complete, check it out. ChemWiki
More informationGlobal picture of mercury
Global picture of mercury Heidelore Fiedler Senior Scientific Affairs Officer UNEP/DTIE Chemicals Branch 11-13 chemin des Anémones CH-1219 Châtelaine (GE), Switzerland E-Mail: heidelore.fiedler@unep.org
More informationINFORMALITY AND BEYOND WHAT WE REALLY KNOW THE FOURTH IMF STATISTICAL FORUM LIFTING THE SMALL BOATS: STATISTICS FOR INCLUSIVE GROWTH
INFORMALITY AND BEYOND WHAT WE REALLY KNOW THE FOURTH IMF STATISTICAL FORUM LIFTING THE SMALL BOATS: STATISTICS FOR INCLUSIVE GROWTH Roberto Luis Olinto Ramos Diretor de Pesquisas Washington DC November
More informationMercury stabilization and solidification technologies. Mercury Stabilization - Solidification Technology MAYASA - MTC
Mercury stabilization and solidification technologies Mercury Stabilization - Solidification Technology MAYASA - MTC SUPPLY AND STORAGE EXPERTS GROUP MEETING MADRID, SPAIN 25-26 OCTOBER 2016 INDEX BACKGROUND
More informationGlobal picture of mercury
Global picture of mercury Heidelore Fiedler Senior Scientific Affairs Officer UNEP/DTIE Chemicals Branch 11-13 chemin des Anémones CH-1219 Châtelaine (GE), Switzerland E-Mail: heidelore.fiedler@unep.org
More informationLiquid Filtration for Chlor- Alkali Plants
Liquid Filtration for Chlor- Alkali Plants November 17, 2016 Dwight Davis W.L. Gore & Inc. What are the 3 most important parameters in operating a chlor-alkali plant? 1. Brine Quality 1. Brine Quality
More informationCO 2 Refrigeration Development
Perspectives on the Use of CO CO 2 Refrigeration Development 2 in Light Commercial Refrigeration Cooling with Carbon Dioxide Conference London/UK Mar 07 Ricardo A. Maciel CO 2 Project Manager Outline A
More informationCLEANER PRODUCTION GUIDELINES IN CAUSTIC SODA /CHLOR-ALKALI INDUSTRIES
CLEANER PRODUCTION GUIDELINES IN CAUSTIC SODA /CHLOR-ALKALI INDUSTRIES 2015 Gujarat Cleaner Production Centre (Established by Industries & Mines Department, GoG) ENVIS Centre on: Cleaner Production/Technology
More informationModule: 5. Lecture: 28
Module: 5 Lecture: 28 Chlorine (continued) 4. Diaphragm cell process Raw material Basis: 1000kg of Chlorine Salt Sodium carbonate Sulfuric acid Steam Electricity Refrigeration Direct labour 1820kg 35kg
More informationUpdate Oct 2016-Oct 2017
Update Oct 2016-Oct 2017 Santa Barbara, California Wednesday, October 25, 2017 Fernando Mendizábal Fernández President Main trend themes: Sustainability of the industry Technology, carbon FP Communication
More informationTarget System Transportation and Decommissioning
Target System Transportation and Decommissioning P.T. Spampinato V.B. Graves Hg System Safety Review CERN June 19-20, 2006 Outline Transportation Transportation Plan (incl. schedule) Container Shipment
More informationMercury Waste Treatment Centre. Joachim Fischer - econ industries GmbH
Mercury Waste Treatment Centre Joachim Fischer - econ industries GmbH Mercury waste treatment technologies and applicability VacuDry - Vacuum Distillation Unit High Temperature Treatment Unit (HTTU) VaCure
More informationIndustrial Sources of Mercury in Germany a Research Project
Für Mensch & Umwelt LRTAP Convention - TFTEI Meeting 2018 Industrial Sources of Mercury in Germany a Research Project Katja Kraus Dpt. General Aspects of Air Pollution Control Federal Environment Agency
More informationReview Statement for. the OSPAR Background Document on mercury and organic mercury compounds
Hazardous Substances Series ---------------------------------------------------------------------------------------------------------------------------------------- Review Statement for the OSPAR Background
More informationWestern Energy Summit May 10, 2013
Western Energy Summit May 10, 2013 Problems Competing CCS Technologies Traditional CCS Plant Storage problems Can t site projects: community pressure Unknown liability with geologic injection High Cost
More informationSEPA Direct Debits indicator evolution (Spanish basic indicator vs Euro area)
Payment Systems Department Settlement Systems Analysis Division STATISTICS SEPA INDICATORS 100,00% 90,00% 80,00% 70,00% 60,00% 50,00% 40,00% 30,00% 20,00% 10,00% 0,00% SEPA Direct Debits indicator evolution
More informationCHLOR-ALKALI INDUSTRY
CHLOR-ALKALI INDUSTRY The chlor-alkali industry represents of three major industrial chemicals: Soda ash (sodium carbonate-na 2 CO 3 ) Caustic soda (sodium hydroxide-naoh) Chlorine (Cl 2 ) These chemicals
More informationChlor-alkali Electrolysis
Chlor-alkali Electrolysis Richter Process Pumps, Valves and Control Equipment Highly corrosion resistant Raw to ultra-pure NaCl, NaOH, NaOCl, H2SO4, HCl, wet and dry Cl2 gas -75 to +400 F (-60 to +200
More informationENGINEERING & CONSULTING
ENGINEERING & CONSULTING o Contamination Diagnostics o Technical Studies o Project Management WORKS o Decontamination o Remediation/Dismantling o Depollution o Chemical Emergency Response CONTACTS Date
More informationTHE CHEMICALS INDUSTRY OPPORTUNITIES TO INCREASE ENERGY EFFICIENCY, TO REDUCE GREENHOUSE GAS EMISSIONS AND TO LIMIT MERCURY DISCHARGES CONCEPT NOTE
1 THE CHEMICALS INDUSTRY OPPORTUNITIES TO INCREASE ENERGY EFFICIENCY, TO REDUCE GREENHOUSE GAS EMISSIONS AND TO LIMIT MERCURY DISCHARGES CONCEPT NOTE Summary: This note provides a brief overview of the
More informationRenewables investment boost in a global uncertain context
Renewables investment boost in a global uncertain context 31/3/217 Claudio Machetti 1 Technology cost reduction Cost evolution for selected technologies 28-216 12 Index 28 = 1 8 6 4 2 Upstream oil & gas
More informationReview of the current Good Practice Document (Good Practices for Management of Mercury Releases from Wastes)
S3_01 Review of the current Good Practice Document (Good Practices for Management of Mercury Releases from Wastes) UNEP Global Mercury Partnership Waste Management Partnership Area Meeting Manila, The
More informationAdapting Dismantling and Decommissioning Strategies to a Variety of Nuclear Fuel Cycle Facilities 12237
Adapting Dismantling and Decommissioning Strategies to a Variety of Nuclear Fuel Cycle Facilities 12237 Frédéric CHAMBON, Gilles CLEMENT AREVA ABSTRACT AREVA has accumulated over 20 years of experience
More informationGRADE 10: Chemistry 2. UNIT 10AC.2 11 hours. The chemical industry. Resources. About this unit. Previous learning. Expectations
GRADE 10: Chemistry 2 The chemical industry UNIT 10AC.2 11 hours About this unit This unit is the second of six units on chemistry for Grade 10 advanced. The unit is designed to guide your planning and
More informationNuclear Decommissioning and Waste Management Programme. at the Joint Research Centre, Ispra Site
Nuclear Decommissioning and Waste Management Programme at the copyright Monkey Business - Fotolia.com European Commission Joint Research Centre Legal notice Neither the European Commission nor any person
More informationCHAPTER 4 FEASIBILITY ANALYSIS OF PV-WIND-FUEL CELL HYBRID SYSTEM FOR CAUSTIC SODA INDUSTRIES
89 CHAPTER 4 FEASIBILITY ANALYSIS OF PV-WIND-FUEL CELL HYBRID SYSTEM FOR CAUSTIC SODA INDUSTRIES 4.1 INTRODUCTION In this chapter, the feasibility analysis for autonomous power supply of caustic soda plant
More informationEnergy Production From Hydrogen Co-Generated In Chlor-Alkali Plants By The Means Of Pem Fuel Cells Systems
Energy Production From Hydrogen Co-Generated In Chlor-Alkali Plants By The Means Of Pem Fuel Cells Systems Rosanna Santorelli, Adrian Schervan UHDENORA SpA Via Bistolfi 35, 2123 Milano - Italy Alessandro
More informationREFRACTORIES & METALLURGY w LUBRICANTS w ENGINEERING w BATTERIES
REFRACTORIES & METALLURGY w LUBRICANTS w ENGINEERING w BATTERIES Who we are Nordic is a leading processor and supplier of rigorously quality inspected natural graphite materials, focused on ensuring the
More informationEuropean Trade Union Confederation (ETUC) comments on the amendment of entry 6 (asbestos fibres) of REACH Annex XVII (May 2014)
European Trade Union Confederation (ETUC) comments on the amendment of entry 6 (asbestos fibres) of REACH Annex XVII (May 2014) 1. Scope of the derogation We have analysed the Commission letter of April
More informationClorosur X Technical Seminar
Clorosur X Technical Seminar High Performance Elastomers and Plastics for the Electrochemical Industry Presented by: Shane Fast Prince Rubber & Plastics Co., Inc. In our 85 th Year Panacea Solutions for
More informationINTRODUCTION. Installed Capacity: The total installed capacity of the plant for the product will be as per details given below:- PRODUCT:
INTRODUCTION Himalaya Alkalies& Chemicals ltd will setup Caustic soda Plant of 400 MTPD. The Plant site is situated in Village Johron, Kala Amb, Tehsil Nahan, District Sirmaur, Himachal Pradesh. It is
More informationSource Water Protection Integrating with Existing Watershed and Water Management Frameworks
Source Water Protection Integrating with Existing Watershed and Water Management Frameworks Steph Neufeld, M.Sc. Watershed Specialist 1 Overview There are multiple, competing land and water planning and
More informationsafer alternatives to asbestos -
- Chlor-alkali producers evaluate safer alternatives to asbestos - By William Stadig Contributing Editor p m s 26932 ntil recently, 75% of all U.S. U capacity for producing chlor-alkali-more than 40% of
More informationSOLVAY GROUP LONDON MORNING MEETING
SOLVAY GROUP LONDON MORNING MEETING June 25, 2008 READY FOR TOMORROW A WARM WELCOME P. Verelst Deputy Investor Relations 2 «CHEMICALS SECTOR : ON THE PATH OF GROWTH» M. V. DECUYPER General Manager of the
More informationOptimizing Effluent and Sludge Treatment for Kraft Pulp Mills with regards to Energy Production, Consumption and Carbon Footprint.
Optimizing Effluent and Sludge Treatment for Kraft Pulp Mills with regards to Energy Production, Consumption and Carbon Footprint. Hans Peter Zwiefelhofer, Paul Woodhead, Mauro Coutinho and David C. Meissner
More informationLas Bambas Project Joe Albright - Project Director 18 September 2011
Las Bambas Project Joe Albright - Project Director 18 September 2011 Agenda Project Overview Highlights Challenges Initiatives Schedule Site Photographs Nueva Fuerabamba construction camp Project Overview
More informationPUMPS FOR CHLOR-ALKALI ELECTROLYSIS
PUMPS FOR CHLOR-ALKALI ELECTROLYSIS RHEINHÜTTE PUMPEN THE RIGHT SOLUTION FOR CHLORINE PRODUCTION Flexibility, reliability, long lifetimes, simple maintenance and low operating costs are the requirements
More informationPreserving scarce resources. Cesare Spreafico Director General, COREPLA, Italy
Preserving scarce resources Cesare Spreafico Director General, COREPLA, Italy RECYCLING PLASTIC PACKAGING WASTE A CHALLENGE FOR A SUSTAINABILE GROWTH Cesare Spreafico Director General 3 KEY CHALLENGES
More informationMercury Contaminated land management state of the art. NICOLE Mercury Working Group Paper
Mercury Contaminated land management state of the art NICOLE Mercury Working Group Paper Context Mercury is a natural element formed primarily through hydrothermal processes. Its occurrence is rare, but
More informationProfit from a unique partnership As a Siemens Partner for protection, power quality & automation
Protection / Substation Automation / Power Quality and Measurements Profit from a unique partnership As a Siemens Partner for protection, power quality & automation siemens.com/energy-automation-products
More informationElectricity and Chemistry
Electricity and Chemistry Electrochemistry: It is a branch of chemistry that deals with the reactions involving the conversion of chemical energy into electrical energy and vice-versa. Electrochemical
More informationNew Insights Into Exposure Through Preferential Pathway Vapor Migration
New Insights Into Exposure Through Preferential Pathway Vapor Migration Megan Hamilton Director of Vapor Intrusion and Risk Assessment Casey McFall, CHMM Vapor Intrusion Project Manager EnviroForensics
More informationConforms to Regulation (EC) No. 1907/2006 (REACH), Annex II - United Kingdom (UK)
Safety Data Sheet Conforms to Regulation (EC) No. 1907/2006 (REACH), Annex II - United Kingdom (UK) 1. IDENTIFICATION OF THE SUBSTANCE/PREPARATION AND OF THE COMPANY/UNDERTAKING Identification of the substance/preparation
More informationConforms to Regulation (EC) No. 1907/2006 (REACH), Annex II - United Kingdom (UK)
Safety Data Sheet Conforms to Regulation (EC) No. 1907/2006 (REACH), Annex II - United Kingdom (UK) 1. IDENTIFICATION OF THE SUBSTANCE/PREPARATION AND OF THE COMPANY/UNDERTAKING Identification of the substance/preparation
More informationDrought Management in the Ebro River Basin
Drought Management in the Ebro River Basin 06 May 2014 Rogelio Galván Plaza surface: 85.500 km 2 inhabitants: 3.020.000 35 inhab/km 2 average precipitation: 622 mm high variability in time and space water
More informationBECC Rodrigo Lagreca HomeCarbon CEO, MSc
BECC 2017 Gathering learnings from a behavioral methodology aimed at Rio de Janeiro low income communities with high incidence of energy commercial losses Rodrigo Lagreca HomeCarbon CEO, MSc Preamble In
More informationUnited Nations Environment Programme
United Nations Environment Programme UNEP(DTIE)/Hg/INC.3/CRP.8 31 October 2011 English only Intergovernmental negotiating committee to prepare a global legally binding instrument on mercury Third session
More informationWater balance and cost evaluation for different scenarios of impermeable covers (raincoats) in heap leach pad operations
Water balance and cost evaluation for different scenarios of impermeable covers (raincoats) in heap leach pad operations Daniel Pulcha, Anddes Asociados S.A.C., Peru Carlos César, Anddes Asociados S.A.C.,
More informationFutureGen The Right Project at the Right Time
FutureGen The Right Project at the Right Time Rice Global E&C Forum September 25, 2007 Agenda Project Overview Clear objectives Organization Technology Current schedule Surface Subsurface Siting Site Comparisons
More informationContractor Insights Monitor March 2018
Contractor Insights Monitor March 2018 Contractor Insights Monitor Research factsheet Research objective To provide manufacturers of construction products with a profound understanding of the European
More informationDecommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M
Decommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M Giorgi Nabakhtiani Grigol Kiknadze Nuclear and Radiation Safety Service Ministry of Environment Protection and Natural
More informationWind Energy Brazil: NEET Workshop - Brasilia. November Considerations on small, intermediate and large size systems
Wind Energy Brazil: Considerations on small, intermediate and large size systems NEET Workshop - Brasilia November 2007 www.cresesb.cepel.br I Introduction Wind energy in the framework of the PNE 2030
More informationChanges in the French Regulations in the light of the lessons learned from the Fukushima Daiichi accident
Changes in the French Regulations in the light of the lessons learned from the Fukushima Daiichi accident French approach in the European context Philippe JAMET ASN Commissioner International Conference
More informationIHS CHEMICAL Chlor-Alkali Process Summary. Process Economics Program Review Chlor-Alkali Process Summary. PEP Review
` IHS CHEMICAL Process Economics Program Review 2016-12 September 2016 ihs.com PEP Review 2016-12 Ron Smith Sr. Principal Analyst IHS Chemical PEP Review 2016-12 PEP Review 2016-12 Ron Smith, Sr. Principal
More informationMETALS AND THEIR COMPOUNDS
METALS AND THEIR COMPOUNDS Metals are elements whose atoms ionize by electron loss, while non-metals are elements whose atoms ionize by electron gain. Metals are in groups 1, 2 and 3 of the periodic table.
More informationBrazilian Economy Overview
Brazilian Economy Overview DEREX Department of Trade and Foreign Affairs Antonio Fernando G. Bessa Deputy Director 1. Institutional. 2. Economic Highlights 3. Foreign Trade 4. Investments Industry FIESP
More informationBiosolids Monthly Report
July-September 217 Biosolids Monthly Report Submitted By: Biosolids Management Program Team Wastewater Treatment Facility 14 Brander St. Richmond, VA 23224 Figure 1: the deputy director Ms. Rosemary Green
More informationDismantling of nuclear facilities in France: what is at stake?
Decommissioning of nuclear facilities Feedback from France L. Vaillant ISPRA, Italy, 16 th September 2015 Content Dismantling of nuclear facilities in France: what is at stake? Radioactive Waste Management
More informationENGINEERING & CONSULTING
ENGINEERING & CONSULTING o Contamination Diagnosis o Technical Studies o Project Management WORKS o Decontamination o Remediation/Dismantling o Depollution o Chemical Emergency Response CONTACTS CURIUM
More informationEstimating emissions from biomass burning in selected pilot areas of the Cerrado-Jalapão Project
Estimating emissions from biomass burning in selected pilot areas of the Cerrado-Jalapão Project G. Ruecker, D. Leimbach, J. Tiemann (ZEBRIS GbR, Germany) fire information from space at your fingertips
More informationSession 4: Inventory Allocation
Session 4: Inventory Allocation Introduction: Slide 57 Issues in Calculating an Inventory -- Allocation Consider adding two elements to the scope of the analysis -- -- Disposal Mineral Metal Ingot Ingots
More informationROMANIA National Commission for Nuclear Activities Control (CNCAN) Report. on in Decommissioning Activities. Dr. Lucian BIRO Director General
ROMANIA National Commission for Nuclear Activities Control (CNCAN) Progress in Report on in Decommissioning Activities Dr. Lucian BIRO Director General IAEA R²D²P Workshop on Cost Estimates Manila, 30
More informationIFL Update: FSC Brazil
IFL Update: FSC Brazil IFL Side Meeting, GA - Vancouver, 10 Oct 2017 Aline T. Bernardes Executive Director FSC Brazil FSC F000100 - FSC A.C. 2017 All rights reserved FSC certified areas 1 FSC certified
More informationImproving usage statistics for RepositóriUM
Improving usage statistics for RepositóriUM Eloy Rodrigues [eloy@sdum.uminho.pt] Ângelo Miranda [amiranda@reitoria.uminho.pt] Ricardo Saraiva [rsaraiva@sdum.uminho.pt] https://repositorium.sdum.uminho.pt
More informationComparison of decommissioning options for the example of 2 research reactors of type TRIGA
Comparison of decommissioning options for the example of 2 research reactors of type TRIGA Dr. Jörg Kaulard *, Barbara Jünger-Gräf ** * Gesellschaft für Anlagen- und Reaktorsicherheit (GRS) mbh ** German
More informationTHE EUROPEAN CHLOR-ALKALI INDUSTRY Steps towards sustainable development
THE EUROPEAN CHLOR-ALKALI INDUSTRY Steps towards sustainable development Progress Report August 2007 Foreword The results of a half-way review of Euro Chlor s groundbreaking 2010 Sustainability Programme
More informationCreamer Environmental. Containment, Caps & Liners. 12 Old Bridge Road C ed ar Grov e, N e w Jer s e y
Containment, Caps & Liners While excavation and treatment are common solutions for many soil and groundwater remediation projects, containment can sometimes be a more appropriate and more economical alternative.,
More informationThis document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and
This document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and suppliers. It is transmitted to you in confidence and trust,
More information2. Drilling operation for oil and gas production. 3. Cleaning, emptying and maintenance of petroleum oil storage tanks including ships
Schedule I [See rules 3 (l)] List of processes generating hazardous wastes S.No. Processes Hazardous Waste * 1. Petrochemical processes and pyrolytic operations 2. Drilling operation for oil and gas production
More informationA Fixed Structure Approach to Mercury Control for Coal Fired Power Plants
A Fixed Structure Approach to Mercury Control for Coal Fired Power Plants John Darrow Paul Barilla W.L. Gore & Associates, Inc. McIlvaine Hot Topic Hour April 18, 2013 Traditional Strategies for Mercury
More informationMANAGING STORMWATER AND TRADE WASTEWATER
MANAGING STORMWATER AND TRADE WASTEWATER 02 Straightforward advice to help vehicle repairers get ahead in today s business environment WHAT DO YOU NEED TO KNOW ABOUT STORMWATER? Rain running off your business
More informationKey Growth Factors Of The Turkish Autogas Market
Key Growth Factors Of The Turkish Autogas Market Yağız EYÜBOĞLU Aygaz - CEO WLPGA Summit, Washington D.C. 09.02.2011 AYGAZ; A Well Diversified Energy Holding Leader in its core business: Fully integrated
More informationIntegrated Pollution Prevention and Control (IPPC) Reference Document on Best Available Techniques in the Chlor-Alkali Manufacturing industry
EUROPEAN COMMISSION Integrated Pollution Prevention and Control (IPPC) Reference Document on Best Available Techniques in the Chlor-Alkali Manufacturing industry December 2001 Executive summary EXECUTIVE
More informationPyro(hydro)lysis of Spent Ion Exchange Resins for Disposal of Organic-Free Radioactive Waste
IGD-TP 7 th Exchange Forum, October 25-26 th, 2016, Córdoba, Spain Pyro(hydro)lysis of Spent Ion Exchange Resins for Disposal of Organic-Free Radioactive Waste Jung, H.G., Brähler, G. & Slametschka, R.
More informationClorosur Technical Seminar & WCC Safety Workshop. New Flemion Membranes for Zero Gap Configuration
Clorosur Technical Seminar & WCC Safety Workshop New Flemion Membranes for Zero Gap Configuration Contents Influence of Zero Gap on the membrane F-8080A : New Type of F-8080 series for Zero Gap Next Generation
More informationRevenue Protection based on AMI
Revenue Protection based on AMI San Antonio, May 9th, 2006 Information contained in this document is subject to change without notice and is presented without express or implied warranty. V2 and V2 Telecom
More informationExample of using detailed statistics: The case of poplar markets in EU
Example of using detailed statistics: The case of poplar markets in EU Arvydas Lebedys FAO Forestry Officer (Statistics) Eurostat Forestry Statistics Working Group Meeting, Luxembourg, 16-17 November 2011
More informationEconomic, Social & Environmental Management Program for Brazilian Soybeans
Economic, Social & Environmental Management Program for Brazilian Soybeans Organizers Partners UFV SENAR/MT Scenario Economic and Social Importance Soybean is Brazil s main crop, both in volume and income
More informationSULAKSH CHEMICALS. SAFETY DATA SHEET Poly Aluminium Chloride 10% 1: Identification of the substance/preparation and of the company/undertaking
1 SAFETY DATA SHEET Poly Aluminium Chloride 10% 1: Identification of the substance/preparation and of the company/undertaking Identification of the substance or preparation Product Name: Poly aluminium
More informationSouthside Wastewater Treatment Plant Renewable Energy Leasing Project
City of Dallas Water Utilities Department Southside Wastewater Treatment Plant Renewable Energy Leasing Project Presented to the TEC September 8, 2008 Southside Wastewater Treatment Plant Renewable Energy
More informationIntroduction and purpose of this meeting. A New Day in Energy Management
Introduction and purpose of this meeting A New Day in Energy Management Facilitator Names UNIDO International Energy Efficiency Experts Location Date Would you allow this man to make a $500 purchase on
More informationCONCEPT NOTE AND DRAFT AGENDA
Inception Workshop Norway ODA Mercury Storage and Disposal Project in the Caribbean (Jamaica, Suriname, Trinidad and Tobago) 12-13 August, Port of Spain A. Objectives of the Inception Workshop: CONCEPT
More informationISOE INFORMATION SHEET
General Distribution April 1999 ISOE INFORMATION SHEET WORKSHOP ON IMPLEMENTATION AND MANAGEMENT OF THE ALARA PRINCIPLE IN NUCLEAR POWER PLANT OPERATIONS IAEA, Vienna, 22-23 April 1998 IAEA Technical Centre
More informationChemicals sector : earning the right to growth. Vincent De Cuyper General Manager of Solvay Chemicals. SOLVAY INVESTORS DAY September 26, 2007
Chemicals sector : earning the right to growth Vincent De Cuyper General Manager of Solvay Chemicals SOLVAY INVESTORS DAY September 26, 2007 Positioning Strategy drivers Execution : Soda Ash in Bulgaria,
More informationGlobal Market Pulp Statistics
Global Market Pulp Statistics Bleached Kraft Pulp November Data 217 Global Statistics for Bleached Kraft Market Pulp The statistics in this file is based on EPIS (European Pulp Industry Sector) data, distributed
More informationKLORIGEN. On-site Generation of Chlorine & Sodium Hypochlorite. Bringing Technology to Life
KLORIGEN On-site Generation of Chlorine & Sodium Hypochlorite Bringing Technology to Life DISCUSSION TOPICS Section I Disinfection Practices Comparison Section II Klorigen Technical Overview Section III
More informationMEMO. 1. Introduction
MEMO Job TNG Energy from Waste Facility, Eastern Creek, Cl, Br and Hydrocarbons in floc waste Date 2016-08-30 From Martin Brunner, Ahmet Erol 1. Introduction It has been questioned to give further information
More informationOverview of the European Wood-Based Panels market with a focus on wood availability & recycling
Overview of the European Wood-Based Panels market with a focus on wood availability & recycling European Recycling Workshop LIGNA, Hannover, 13 May 2015 Kris Wijnendaele Technical Director CONTENT EPF
More informationHow We Obtained LEED Certification pertaining to the Indoor Environmental Quality Category. Ron Fields, CAFS, NCT General Dynamics C4 Systems
How We Obtained LEED Certification pertaining to the Indoor Environmental Quality Category Ron Fields, CAFS, NCT General Dynamics C4 Systems Outline What is LEED EB? GD LEED Costs and savings IEQ Prerequisites
More informationThe Chemical Industry and Climate Change. A Snapshot from India
The Chemical Industry and Climate Change A Snapshot from India B.H. Rahill Lead Environmental Specialist South Asia Environment June 14, 2006 Presentation Outline The Indian Situation (Part of) LBNL Benchmarking
More informationREFFIBRE workshop in Darmstadt on April 19, 2016 Environmental aspects of side stream applications
For our Environment REFFIBRE workshop in Darmstadt on April 19, 2016 Environmental aspects of side stream applications Dipl. Ing. Almut Reichart UBA III 2.1 Cross sectorial Aspects of Pollution Control,
More information