1 ACTION PLAN ABATEMENT OF POLLUTION IN CRITICALLY POLLUTED AREA OF NAJAFGARH DRAN BASIN INCLUDING OKHLA, NARAINA, ANAND PARBAT AND WAZIRPUR INDL AREAS DELHI POLLUTION CONTROL COMMITTEE 4 th Floor, ISBT Building, Kashmere Gate, Delhi-6 March,

2 1.0 Introduction PRESENT ENVIRONMENTAL STATUS OF NAJAFGARH DRAIN BASISN After analyzing the Environmental Status of Industrial Clusters of the country, Central Pollution Control Board in consultation with the Ministry of Environment & Forests has identified 88 critically polluted industrial clusters, of which Najafgarh Drain Basin including Wazirpur, Naraina, Anand Parbat and Okhla industrial areas is one of them in NCT of Delhi. 1.1 GEOGRAPHICAL FEATURES Location The National Capital Territory of Delhi is stretched over an area of 1483 sq km. As far as the location of Delhi is concerned, it stands in the middle of the Indian subcontinent, between the Himalayas and Aravallis range. Bordered by Haryana in the east and by Uttar Pradesh across the river Yamuna, Delhi is located approximately 213 to 305 m above the sea level. It is around 33 miles and 30 miles broad and extends latitude N and longitude E. The location of Delhi is such that a major part of the city falls on the western side of the Yamuna River. Apart from Yamuna, which is the main river of the city, there are 3 canals, Agra Canal, Hindon Canal and western Yamuna Canal. Geography of Delhi has divided it into 3 segments. The three segments consist of the Yamuna flood plain, the 2

3 Ridge and the Plain. The low lying and flood prone area of Yamuna flood plains is also known by the name of Khadar. The area of the Ridge stretches from the Aravalli hills, encircling the city on the northwest and west. One of the highlights of the Ridge area is the Tughlaquabad Fort that stands at its highest point. The Plains consist of all the area of Delhi, apart from the Yamuna flood plain and the Ridge. Majority of the city area, consisting of Delhi, New Delhi and Delhi cantonment, falls in the fertile land of the Plains. Topography The topography of Delhi can be divided into three different parts, the plains, the Yamuna flood plain, and the ridge. As per the topography, Delhi is located on the western fringes of the Gangetic Plains. The low altitude Yamuna flood plains provides an excellent scope of agriculture, as it is covered with the fertile alluvium brought by the river Yamuna and deposited here during the frequent floods. The other topographical feature is the Ridge, which reaches the height of 1043 ft above sea level, and is the highest point in Delhi. The ridge originates in the south and surrounds its western, the northwestern and northeastern part. It is a part of the Aravalli Hills. Climate The climate of Delhi is one of the most varied and purely depends upon the climate of nearby areas of Himachal Pradesh, Rajastan etc. Delhi experiences the extremes of weather. This is because of the geological location of Delhi. The climatic conditions of Delhi are similar to that of the temperate grasslands with hot, dry summers, and cold winters. The summers in Delhi start from the month of April and continue till 3

4 the month of July. It is very hot and dry in the summer months, with temperature soaring up to 45o C. The rainy season provides relief from searing heat and continues till the month of October. The humidity levels very high in Delhi at this time of the year. The winter months are characterized by dip in the temperature levels often reaching 5o C or less than that. Rainfall The city does not witness much of rainy season. The monsoon lasts from July to September. October sees the end of the monsoon but it is reasonably pleasant. Weather Graph for Delhi Note: These are average maximum and average minimum temperature for Delhi. The highest temperature in Delhi for the month is usually higher than the average maximum temperature. Similarly, the lowest temperature in Delhi for the month is usually lower than the average minimum temperature. 4

5 25 Years Average ( ) rainfall data Months Av. Annual Rainfall (mm) Rainy Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total

6 Ground Water Scenario The dependence on ground water is quite considerable in the area. The Ground water availability in the territory is controlled by the hydrogeological situation characterized by occurrence of alluvial formation and hard rocks such as quartzite. The hydrogeological set up and the following distinct physiographic units further influence the ground water occurrence: (1) Older Alluvial Plain on the eastern and western side of the ridge. (2) Yamuna Flood Plain deposits. (3) Isolated and nearly closed Chattarpur alluvial basin. (4) NNE-SSW trending Quartzite Ridge. The yield of tube wells ranges between m3/ hr in Yamuna Flood Plain aquifers. In Older Alluvium of eastern and western sides of the ridge, the yield of tube wells ranges between 12 to 36 m3/ hr. Tube wells constructed in Chattarpur alluvial basin tapping the aquifers of both alluvium and weathered and fractured quartzite yield about 9 to 27 m3 / hr. Discharge of tube wells constructed in Quartzites varies from 6-15 m3 / hr. The groundwater is declining in majority of the areas of Delhi on account of overexploitation of the resources. The rate of decline is as high as 1.7 to 2 meters/year in some areas (South & South west Dist.). Thus seven out of nine districts of Delhi are categorized as overexploited with respect to dynamic groundwater resources. The groundwater quality shows horizontal and vertical variation in space. The deeper aquifers are mostly underlain by saline water in alluvial areas. The extent of fluoride contamination in groundwater is also high in western part of Delhi in areas like Northwest, Southwest & West districts. The groundwater management aspects of Delhi emphasizes on augmentation of groundwater resources and improvement in groundwater quality through measures like rainwater harvesting and artificial 6

7 recharge, conservation of groundwater by limiting withdrawal in overexploited areas and limited development of potential aquifers of Delhi to augment drinking water supply. The quality of ground water is alkaline with ph ranging from 7.1 to 9.2, chloride content ranges between 21 and 1380 ppm. South of Delhi average chloride content is 250 ppm while in Najafgarh area it is around 1000 ppm rendering the water saline covering the area of 32 km. Sq. and marginally saline over the area of 129 sq km. The ground water study done by the NEERI for MoEF revealed high nitrate and fluoride concentrations. High metallic content, particularly manganese and iron have also been observed in the samples collected. The manganese content was found to be 0.1 mg/l against the permissible limit of 0.5-mg/L and iron concentration of 4.05 mg/l to mg/l have been observed. Chemical Quality of Ground Water in South West district Ground water in maximum part of the South district is fresh and potable with electrical conductivity ranging from 320 to 4130 micro-mhos/cm at 25` C. Electrical conductivity values more than the permissible limit are observed at Deragaon, Molarbund and at Gadaipur. High values of nitrate are found at four locations i.e. at Gadaipur, at Rajokri and at Jaunapur. In north Ghitorni and Andheri More, Fluoride is more than permissible limits. Except chromium concentrations at one locality, ground water is devoid of pollution by heavy metals. A comparison of ground water quality from 1983 to 2000 shows quality deterioration in the central part of the Chhattarpur basin and in the areas around Nizamuddin. In central part of the Chattarpur basin, quality deterioration is mainly because of over-development of ground water resources. The exhaustion of fresh water present at shallow depths is resulting into brackish water pumping from the tubewells that are tapping the deeper aquifers of alluvium. 7

8 The electrical conductivity of shallow ground water in the Southwest district varies from 630 to micro-mhos/cm at 25` C. Detailed Electrical Conductivity map prepared for this district, ground water quality is fresh with electrical conductivity 1000 to 2000 micro-mhos/cm at 25` C. Thus, with over-development of ground water resources in the district, more and more areas are becoming brackish. 1.2 Background: Najafgrah Drain Basin is figuring at Sl. No. 61 of the list of 88 clusters/areas. Along with Najafgarh Drain Basin, four more industrial areas of Delhi i.e Wazirpur, Naraina, Anand Parbat and Okhla have been added as critically polluted. The map of area is enclosed as Annexure-I. 8

9 The list of industrial areas whose waste waters are reaching Najafgarh Drain is given below. The number of industries who have applied for consent with DPCC in each area is given below NORTH ZONE 1. G.T. Karnal Road Industrial Rajasthani Udyog Nagar Industrial S.M.A. Industrial S.S.I. Industrial Wazirpur Industrial Lawrance Road Industrial Udyog Nagar Industrial D.S.I.D.C. - Sheds Nagloi 9. Mangol Puri Industrial (Both DDA & DSIDC) Badli Industrial Narela Industrial Bawana Industrial 1995 SOUTH ZONE 1. Okhla Industrial, Ph-I & Ph-II 2107 WEST ZONE 1. Naraina Industrial Ph-I & Ph-II Mayapuri Industrial Ph-I & Ph-II Tilak Nagar Industrial Kirti Nagar Industrial D.F.L. Industrial, Moti Nagar Najafgarh Road Industrial 598 As per the Delhi Master Plan 2021, 20 new industrial areas have been earmarked for redevelopment considering various factors. Anand Parbat Indl area is one of these industrial areas. Other industrial areas falling in the catchment area of Najafgarh Drain are Samaipur Badli, Sultanpur Mazra, Hastsal Pocket A, Naresh Park Extension, Libaspur, Peeragarhi Village. Khyala, Hastsal Pocket-D, Shalimar Village, Nawada, Rithala, Swaran Park Mundka, Haiderpur, Dabri and Basai Darapur. These areas have been approved as industrial areas for redevelopment by Ministry of Urban Development, UOI as per their policy as these areas consists of more than 9

10 70% industries. Though number of industries are in operation, they will be considered authorized/approved only when the areas are redeveloped and notified as industrial areas. The said task has been entrusted with DSIIDC, Govt. of NCT of Delhi. All the units in unauthorized and redevelopment areas shall be allowed to operate with the adequate pollution control systems. 1.3 SOURCES OF POLLUTION: Water Pollution: Water pollution is being caused by the industries engaged in the activities of pickling, dyeing, electroplating and other miscellaneous water polluting units. etc. in the industrial areas as well as non industrial areas falling in the catchment area of Najafgarh Drain. Pickling units use hydrochloric acid for cleaning the surface of the products. Significant amount of wastewater is generated by these units. The main pollutants in the wastewater discharged by the industry are ph & TDS. Same is the case with other water polluting units engaged in different activities. Most of the units are equipped with CETPs to treat the waste waters generated in these industrial areas but there is no provision for controlling the TDS. Pursuant to the order of Hon ble Supreme Court of India, 15 CETPs were proposed to cater to the needs of treatment of waste water generated by the 21 industrial areas of NCT of Delhi. However, only 10 CETPs, out of the above 15 proposed CETPs, have been constructed so far and are operational at present. One more CETP at Narela industrial area has been constructed by DSIIDC which is also operational. Waste water from all the CETPs except for Jhilmil & Friends Colony Indl is entering into Najafgarh Drain, which in turn meets the river Yamuna. 10

11 The list of these 10 CETPs along with their installed capacities and present utilization is given below: Sl.No. Name and location of the CETP 1 GTK Road Indl CETP Indl areas being catered to GTK Road Indl Installed Capacity being capacity in treated at MLD present in MLD Lawrence Road CETP Lawrence Road Badli Industrial Estate CETP Badli Estate Industrial Mangolpuri CETP Mangolpuri Okhla CETP Okhla Wazirpur Indl CETP Wazirpur Indl 7 DSIIDC Nangloi & Udyog DSIIDC Nangloi Nagar Indl CETP & Udyog Nagar Indl 8 SMA Indl CETP SMA Indl, SSI Indl and Rajastan Udyog Nagar Indl 9 Mayapuri CETP Mayapuri Indl Narela Indl CETP Narela Indl

12 Map showing CETPs of Najafgarh Drain Basin LEGEND Railway line.. Road.. Drain Wazirpur 2. GT Karnal Road 3. Lawrence Road 4. Udyog Nagar & DSIDC Nangloi 5. Mangolpuri 6. SMA, SSI & RUN 7. Badli 8. Narela 9. Mayapuri 10. Okhla 12

13 Apart from the above, the construction of CETPs at industrial areas such as Anand Parbat, Okhla industrial estate and Mohan Co-operative industrial areas have been kept in abeyance by Environmental Pollution Control Authority (EPCA) headed by Sh. Bhure Lal. The construction at Najafgarh Road Indl area is presently not in progress due to dispute with the contractor of CETP and at Naraina Industrial is in the final stages of commissioning. DPCC has been collecting samples of waste water at both inlet and outlet of the all the operational CETPs on monthly basis and appropriate action to rectify the deficiencies has been issued from time to time. The parameters which are not meeting the norms, at each of the CETP, during the period (June 2009 to May 2009) have been tabulated and the same is enclosed as Annexure II. Perusal of the said table establishes that the parameters such as TDS, Chlorides, and Fluorides are not meeting the norms by most of the CETPs on certain occasions and BOD on some occasions by some of the CETPs. The deficiencies are informed to the respective CETP Society and they are directed to remove the same to comply with the norms laid down.the major issue of concern is that the quantity of waste water reaching the respective CETPs and being treated is very low compared to the total installed capacities. This is particularly because entire polluting industries has either been closed or shifted out of Delhi. Domestic Pollution: About 840 MGD of water is required to cater to the needs of the population of NCT of Delhi. Due to consumption of such huge quantity of water by the population, about 672 MGD of waste water is generated. However, the total treatment capacity of STPs as on today is only MGD, which is well below the required capacity, apart from having large number of localities of NCT of Delhi not covered by any sewerage network. Number of steps are being 13

14 taken by both DPCC and other statutory agencies such as Delhi Jal Board, Department of Industries etc to check the water pollution Air Pollution: The environment of NCT of Delhi has degraded a lot during the last few years due to rapid urbanization, industrialization, increase in population, vehicles and commercialization of land available within the town. The main stationary sources of air pollution are the industrial units, which are emitting particulate matter, sulphur di-oxide and oxides of nitrogen etc. But the rate at which the said degradation has occurred has reduced due to various steps taken by DPCC and other agencies to rein in the air pollution levels. Burning of rice and wheat straw by the farmers in the agricultural fields of NCT of Delhi is also affecting the ambient air quality of the town. As per report of Central Pollution Control Board, the Cumulative Environmental Pollution Index (CEPI) in respect of air has been calculated as for Najafgarh Drain basin, on the basis of which the said basin has been declared as critically polluted area. Sources of Air Pollution: (a) Mobile sources: With the development of industries, growth of population and rise in living standards, the demand of two wheelers and four wheelers has increased manifold. At present, there are about 60 lakh registered vehicles on the roads of Delhi, which one of the major contributors towards the deteriorating ambient air quality of the city. The dust lying on the roads reenters the atmosphere resulting in increased levels of Particulate Matter. (b) (i) Stationary Point Sources: Private or public sector organizations are carrying out major construction activity in the city are emitting significant quantity of dust emissions into atmosphere, which need to 14

15 take necessary steps to ensure that no dust emissions are emitted from their activities and the debris generated as a result of these activities are disposed off at a proper place instead of dumping the same in an haphazard manner. (ii) NCT of Delhi consists of agricultural fields and burning of rice/ wheat straw by the farmers in the fields is also affecting the ambient quality of the town. Ambient Air Quality Monitoring Data of NCT of Delhi: In order to determine the status of quality of the ambient air in the catchment area of Najafgarh Drain basin, the Board is monitoring the ambient air quality of at various locations for the last number of years. The ambient air quality monitoring analysis of last 12 years (as given below) reveals that the annual average concentration of Respirable Suspended Particulate Matter (RSPM) is in the range of 160 to 301 µg/m 3 against annual average prescribed standard of 120 µg/m 3 for industrial area, 60 µg/m 3 for residential, rural & other area and 50 µg/m 3 for sensitive area. So, the concentration of RSPM in ambient air is more than the prescribed limit. Concentration (Annual Mean) of Different Pollutants in Delhi Parameter * SO NO SPM RSPM All values in micrograms/m 3 Source: CPCB * averaged upto April 10 Comparison of the values observed in 2010 with values of 2002 shows reduction of 55.8 % in SO 2 Concentration and 9.24in NO 2 concentration whereas Particulate Matter concentration shows an increase of 5 % and 29.7% in respectively in SPM and RSPM concentration 15

16 Parameter Permissible limits Micrograms/Nm 3 Old New RSPM SO NOx In addition to the industrial air pollution, the other factors contributing towards the ambient air quality deterioration are: i) Rapid increase in the vehicular density due to industrialization and commercialization. ii) iii) Haphazard growth of the industries in both industrial as well as non industrial areas. Lack of proper infrastructure such as roads, green belts, buffer zones etc. 1.4 Noise Pollution: Noise pollution is one of the important aspects which has escaped attention of policy makers. However, the said noise pollution is one of the major dangers lurking round the corner. As per the noise monitoring carried out by the DPCC in year on monthly basis is shown in table Noise levels exceeded in most of the locations. Therefore, there is a need to reduce the noise levels and to take precautionary measures in the areas where the noise levels are at the border line. 16

17 1.5 Hazardous Waste: There are numerous units situated in the industrial areas located in the Najafgarh Drain basin and other four industrial areas that generating hazardous waste. The main hazardous waste is generated from arc / induction furnaces as dust from air pollution control device i.e. Category 34.1 of Schedule-I. Also, in steel rolling mills, air pollution control device dust is considered as hazardous waste, which is also covered under 34.1 category of Schedule-I of Hazardous Wastes (Management, Handling and Transboundary Movement) Rules, About Tonnes per annum of hazardous waste is generated by these industries in entire NCT of Delhi as per the inventorisarion carried out by Ramky s. 17

18 1.6 Bio-medical Waste: In Delhi there are 3 Common Bio-Medical Waste Treatment Facilities (CBWTF)s (one in South district, two in North West district) & one more CBWTF (at Nilothi STP, in West district) has been granted Consent to Establish by DPCC on Besides these CBWTFs, many hospitals e.g Safderjung, RML, Lal Bahadur Shastri Hospital, Swami Dayanand, e.t.c are having their own incinerators / Bio Medical Waste Treatment Facilities. All the incinerators for Bio medical Waste are having Venturi Scrubber as Air Pollution Control Device for the control of pollution within the prescribed norms. As per the Annual Report for year 2009, Delhi generates about 10 tonnes ( Kg/day) of Bio Medical Waste (including all the Govt. Hospitals having their own treatment facilities) whereas installed capacities for treatment of Bio Medical Waste with the existing 3 CBWTFs is about 23 tonnes per day which is more than the requirement at present. Besides this Nilothi STP which has been granted Consent to Establish on , will be having treatment capacity of 10 tonnes per day this will enhance the total installed treatment capacity to 33 tonnes per day. As far as the management of this waste is concerned, NCT of Delhi has done tremendous progress. Two manufacturers of B.P.Apparatus /Thermometers in Delhi have agreed to take / buy mercury waste ( from B.P.Apparatus /Thermometers ) from the Health Care Establishments ; 1. M/s Supreme Surgico, 262/ 425, Lane No.8, Friends Colony Industrial,Shahdara, Delhi. 2. M/s Anita Industries, 29, Bhagat Singh Market, New Delhi. 18

19 1.7 Municipal Solid Waste: 1.10 About 9000 T/day of municipal solid waste is generated by entire NCT of Delhi and by 2024 the quantity is expected to be around T/day. Door to door collection of waste has been started in most of the MCD zones which will facilitate in proper collection, transportation and disposal.work has commenced in 61 Wards out of 63 Wards [21 wards out of 22 wards in Civil Line Zone, 35 wards out of 35 wards in Rohini Zone and 5 wards out of 5 wards in Dwarka Pappan Kalan and a part of Vasant Kunj area].the Concessionaire has submitted proposal for setting up of compost plant, RDF Plant and Engineered Landfill facility at Narela Bawana site to MOEF [Ministry of Environment & Forest] and has obtained Environmental Clearance and has submitted CTE application to DPCC in the month of Nov The work of collection of MSW from municipal receptacles & its transportation upto SLF sites has already been awarded to private concessionaires in South, Central, West, City, Karol Bagh and Sadar Paharganj Zone. Najafgarh, Narela Zone: Currently being done by MCD. The department proposes to hire tipper trucks and loaders for collection & transportation of MSW from private parties. Land Fill Site (s): Since 1975 Set up so far: 20 Already Filled up and Closed: 15 Suspended: 2 Active Landfill [Dump] sites 3 19

20 Existing Landfill Sites Land Fill Site Location (Hectare) Start Year Waste Received (T.P.D.)/Waste already dumped/ Remaining life Zone Supply Bhalswa North Delhi Million T Nearly full Civil Line, K.B., Rohini, West and Najafgarh Gazipur East Delhi Million T Nearly Full Shah (N), Shah (S), City, S.P. & N.D.M.C. Okhla South Delhi Million T Nearly Full Central, Najafgarh, South and Cantonment 20

21 1.8 E-Waste: The e-waste is generally generated from dismantling activities of various electrical / electronic appliances / gadgets such as audiovisual components, televisions, VCRs, stereo equipment, mobile phones and computer components. But till date, no inventory of such waste has been prepared. However, for the proper disposal of such type of waste, the Ministry of Environment & Forest has included this waste in the Hazardous Wastes (Management, Handling & Transboundary Movement) Rules, Numbers of initiatives have been taken by the Delhi Govt. towards the implementation of E Waste guidelines and Rules such as placing of E waste collection bins at various locations in Delhi and E-Waste authorized Recyclers to ensure that the collected E-Waste is recycled in a safe manner. All Delhi Computer Traders Association (ADCTA), Nehru Place, Delhi, was directed to advise their members to send their E-Waste only to the registered recyclers with CPCB. Letters were also sent to different Govt. Departments, IT Companies & Hospitals in Delhi advising to dispose their E-Waste & auction through registered recyclers only. Some of the registered recyclers are given below: M/s Earth Sense Recycle Pvt. Ltd. Plot no. 225, Sector-VI, IMT Manesar, Gurgaon, Haryana M/s Attero Recycling Pvt. Ltd. 173, Village Bhagwanpur, Raipur Industrial, Roorkee Distt., Haridwar, Uttarkhand. M/s TIC Group India Pvt. Ltd. J-2 & J-6, SDF Block-J, Noida Special Economic Zone (NSEZ) Noida Dadri Road, Noida

22 2.0 Initiatives/Actions taken by DPCC and other agencies Najafgarh Drain Basin was also figuring in the already identified 24 Critically Polluted areas. After the identification prior to 2000, a number of steps have been taken by DPCC as well as by various other agencies to bring down the pollution levels. Closure of 1328 H category units in year 1996 resulted in closure of large scale and highly polluted units like Shriram Foods and Fertilizers, Hindustan Insecticides Limited, DCM Silk Mills, Birla textile Mills, Swatantra Bharat Mills, Indian Oxygen Limited, Hindustan Vegetable Oils and other Hazardous and Obnoxious industries like Leather Tanneries, Hot Mix Plants, Lead Smelting units, Pesticides, Heavy foundries, Heavy Steel Rolling Mills etc. In year intensive drives have been undertaken by Govt. of Delhi to close down the Polluting industries operating in residential areas of Delhi falling under F-27/33 category of units identified by Nodal Agency (Ministry of Urban Development, UOI) and Group of Experts, constituted by GNCTD. In total 3423 units have been closed down by the Govt of NCT of Delhi. By the continuous efforts of DPCC, about 1191 units were directed to be closed down by SDMs operating in non-conforming/residential areas. Compliance reports for closure have also been received from SDMs in case of most of these 1191 units. Steps taken for the mitigation of water pollution by way of commissioning of CETPs, STPs and installation of ETPs in water polluting units, industrial areas and malls. Extraction of ground water in some of the districts banned to save natural resources and a notification was brought out in the year 2010 empowering DJB and DC to sanction necessary permission to any person/authority to extract ground water. By the continuous efforts of DPCC, about 861 units have installed individual Effluent Treatment Plants to treat their waste water before discharging into the conveyance system 22

23 leading to respective CETPs. List of these 861 units who have installed ETPs is enclosed as Annexure-III. As far as the generation and treatment of domestic waste water is concerned, DJB has till now installed Sewage Treatment Plants at 16 locations with an installed capacity of MGD. This capacity is proposed by DJB to be augmented to 730 MGD by the year Status of generation and installed capacities of various STPs is given as below: Total water supply by DJB 850 MGD Expected effluent generation 680 MGD (80% total water supply) Percentage of effluent treated by STPs about 50%. Total capacity of STPs 512 MGD. Actual treatment through STPs 350 MGD Percentage utilization capacity of STPs is only about 70 %.( this does not include total water quantity extracted from ground water). 23

24 List of STPs operational in the catchment area of Najafgarh Drain S.No. Location of STP Installed Capacity of STP (MGD) 1 Nehru Vihar, Oxidation Pond STP Keshopur STP 60 3 Rithala STP 80 4 Pappankalan STP 20 5 Najafgarh STP 5 6 Nilothi STP 40 7 Rohini STP 15 8 Coronation Pillar STP 40 9 Narela STP 10 24

25 Location of STPs in Najafgarh Drain Basin At present, major water polluting units operating in the industrial areas of Wazirpur, SMA, SSI, Rajastan Udyog Nagar Indl and Badli industrial area and in other industrial areas falling in the catchment areas of Najafgarh Drain are engaged in the activities of Stainless Steel Pickling, electroplating, dyeing etc. The activity of S S Pickling has been placed in the 25

26 Negative list as per Delhi Master Plan 2021 and was supposed to be closed by but are still continuing because of one committee constituted by Ministry of Urban Development, Govt. of India is reexamining the issue. The list of 99 activities which have been placed under Negative/Prohibited category is annexed as Annexure-IV. However, the contribution of pollution load due to industries is only 4-5%. Industrial air pollution sources generally in these areas are boilers, furnaces, DG sets etc which have been addressed in the past and will also be tackled on priority to reduce the air pollution levels. Najafgarh Jheel is located in the village of Najafgarh, starting from Dhandsa basin, which is very near to the border of Haryana state. Najafgarh Jheel is the initial point from where the Najafgarh drain originates. This lake is nearer to Gurgaon which falls in the state of Haryana. Most of the times, it was observed by the joint inspections of CPCB and DPCC that untreated waste water has been coming into the Jheel, which is polluting the jheel to some extent. The water quality found from the analysis of a sample collected on was found to be ph 8.4, TSS 176 mg/l, BOD 56 mg/l and COD 202mg/l. The quality of the water gets further deteriorated on the downstream stretches of the drain, as significant quantities of domestic waste water is flowing into the said drain. This is due to the fact that the unauthorized residential colonies alongside the drain have not been laid with proper sewerage network leading to Sewage Treatment Plants and so the untreated waste water is contributing to very highly deteriorated water quality. The waste water flowing in this drain finally gets into river Yamuna. Delhi Jal Board, after a detailed feasibility study by EIL, has proposed interceptor sewers for both Najafgarh Drain and Supplementary Drain which are contributing majorly towards the water pollution in the river Yamuna. The objective of the interceptor sewer project is to intercept 26

27 and convey for treatment, the flow of untreated waste water into the river via the three major drains. However, here we are keen on only two drains as specified above. The intention is to prevent untreated waste water from reaching the river, hence abating pollution. Implementing the planned interceptions as part of the project will achieve a reduction of BOD from 38.9 mg/l to 12 mg/l at the outfall of Najafgarh and Supplementary drains, as worked out through water quantity modeling. To bring the river water up to class C, treated effluent discharges need to achieve a treated BOD of 10 mg/l and sufficient dilution is to be ensured by neighboring states by releasing additional water in river Yamuna. Once the said project is completed, the waste waters entering into these drains are intercepted and will be treated before its discharge into the river Yamuna. The system includes provision of interceptor sewers along with associated works like interceptor pits, new sewage pumping stations, rising mains etc. along the drains involving the related Sewage Treatment Plants in the catchment areas. The project is an integrated approach towards zero sewage flows in the drains and the river. The cost of the project is about 1350 crores and is being implemented by Delhi Jal Board. The quality of waste water flowing in the drain is monitored on monthly basis and the monitoring dated reveals that the quality was ph 7.4, TSS 136 mg/l, COD 208 mg/l and BOD - 46 mg/l. The quality of the waste water flowing in the Najafgarh drain observed during several months is tabulated and given below: Month ph TSS mg/l BOD mg/l COD mg/l Feb Mar Apr May Jun Jul

28 From the above table it is clear that quality of the waste water is not good to maintain the quality in the river for designated use. For industrial water pollution control, intensive drives were taken up in year 2000 in view of Hon ble Supreme court orders in IA No 725/94 of Maily Yamuna case due to which industrial units are well sensitized for installation of ETPs. Steps taken to control air pollution: Numbers of steps have been taken by DPCC as well as by various other agencies to bring down the air pollution levels to a greater extent. Installation of ECS by air polluting units. List of 353 units which have installed ECS is enclosed as Annexure-V. Closure of coal fired boilers in all industries and conversion to oil or gas based fired. Introduction of CNG as automotive fuel. Introduction of stringent Indian petrol and diesel specifications required to meet Euro-IV equivalent tail pipe emission norms since April Widening of roads, construction of large number of flyovers and under passes in Delhi to reduce traffic congestion thereby reducing vehicular pollution etc have been taken. Implementation of ECBC Code for building activities. Installation of STPs/ETPs in hotels and restaurants besides forcing them to reuse the treated waste water. Insisting all the construction agencies to have proper dust emission control systems during construction. Coal based thermal power plant namely IP Power Station was closed and the power plants which are coming up are all gas based ones thereby reducing air pollution. Even the other 28

29 operational coal based power plants are being pursued to switch over to cleaner fuel to meet stringent emission level of 50 mg/nm 3. BTPS has now proposed to go for 3x350 MW gas based units for which public hearing, as per the provisions of EIA notification dated , has been carried out on Introduction of Metro rail. Introduction of Metro Rail in Delhi has resulted in reduction of about vehicles per day on the roads, which in turn has saved fuel costs to the tune of Rs. 115 crores. Metro Rail has resulted in the following: Reduction in the member of vehicles and vehicle kms. on the roads with corresponding reduction in fuel consumption and vehicular emission Less congestion on the roads with proportionate increase in speed of road vehicles, resulting in further reduction in fuel consumption and vehicular emission Metro rail projects are thus not only environment friendly by themselves but also assist in reducing environmental pollution caused by other road-based modes of urban transport. During the year 2009, following is the reduction in air pollutants into the atmosphere of Delhi. Sl.No. Parameter Reduction in Tonnes 1 CO 2, HC NOx PM SO CO2 1,03,300 Total Data provided by DMRC 29

30 In Delhi, almost all the industries are of small scale and the statistics have always shown that the vehicular sector is responsible for 70% air pollution in Delhi as it contributes significantly towards ambient air pollution. It is a very well known fact that Delhi is getting accumulated with about 800 vehicles per day and there are about 60 lakh registered vehicles in Delhi apart from vehicles plying from other states. Though the increase in the number of vehicles is rapid, the percentage of increase in air pollution levels has been kept under check by taking above cited steps. All commercial vehicles have been converted to less polluting CNG mode and by improving the automotive fuel quality air pollution levels have been kept under check. Further increase in the network of the Metro rail will result in significant reduction in air pollution levels of Delhi. One of the major contributors towards air pollution in NCT of Delhi is rapidly increasing building activity, which is being taken very seriously and the agencies are being asked to take all the necessary steps to control dust emissions from the excavation stage itself. The same is being specified while issuing Environmental Clearance and Consent to Establish and the same is monitored through periodic inspections. For industrial pollution control the matter remains is only to operate the existing ETPs/ECS/CETPs regularly and to keep a vigil to stop new illegal units. The profile of the industries which are in operation has changed drastically since Number of control measures have been taken reduce air as well as water pollution which has brought down the levels of these pollution to a significant extent. MCD is taking various steps to manage Municipal Solid Waste and is expected to collect, transport, treat and dispose off the entire waste in very near future. Regarding management of HW is concerned, due to no availability of adequate land and opposition from local people, the Government was not able to 30

31 construct TSDF for hazardous waste disposal in Delhi. However, it has been proposed to have the facility at Khanjawla and a land of 50 acres has been acquired and an amount of Rs. 35 crores has already been paid to DSIIDC. Once all the clearances such as getting EC is over, about one year time is required to complete the project and the same will be made operational. In view of the steps taken/being taken by DPCC and various other agencies, CPCB is requested to drop the Najafgarh Drain basin including 4 other industrial areas from the list 88 of critically polluted areas. However, DPCC will strive very hard to ensure pollution levels of various nature are controlled and kept below the levels intended for. However, DPCC will take action as per the details given below: 1.0 Water Pollution Control: 1.1 Treatment of effluents, by the individual units, Individual connection to conveyance system, before discharging into conveyance system leading to CETP: Due to continuous efforts of DPCC, about 1305 units, in entire NCT of Delhi, have installed individual Effluent Treatment Plants to treat their waste water before discharging into the conveyance system leading to respective CETPs. In all, 10 CETPs, catering to the needs of 13 industrial areas falling in the catchment area of the drain are operational to treat the industrial effluents. CETP at Naraina Industrial area is yet to be commissioned. CETP at Anand Parbat has been kept in abeyance by EPCA. Pretreatment of waste water is done by the individual units in case of the industrial area wherever the CETP is installed and full treatment is required to be done by the units in the absence of any CETP. Continuous action is required to ensure all the units pretreat their effluents before discharging into the conveyance system to achieve the waste water quality at the inlet of the CETP as envisaged in the EP Rules,

32 Also it is to be ensured that all the individual units get connected to the conveyance system. Specific instructions are required to be issued to DJB to ensure the connections to conveyance systems as specific permissions are given by DJB for this purpose. In NCT of Delhi most of the units, looking at the economics, have been using lime as neutralizing chemical to increase the ph which is increasing the sludge generation immensely. This sludge is generally Hazardous Waste as per the provisions of HWM Rules, 2008 amended to date. Collection, storage, transportation, treatment and disposal of the HW is becoming tedious and unviable economically. So as to reduce the HW generation, concerned units are required to be compelled to use NaOH in place of lime. This is the case with the CETPs, which are to be educated to use NaOH in place of lime to reduce HW generation. Sincere efforts are required by all the industries and CETPs to switch over to NaOH from lime to achieve significant reduction in HW generation. Action by: DPCC/Individual Inds/CETP Societies/Dept. of Inds/DJB 1.2. Reuse of treated water from various CETPs: 10 CETPs with the installed MLD are operational with enormous costs for installation and operation. After spending significant amounts for treatment, the treated waste water is again joining the adjoining drains and getting polluted again. By doing so, the money spent is getting wasted without any tangible usage, which is against the prudence. It is necessary to reuse this treated waste water for useful purpose, by further treating if required. This will become necessity in future looking at the very scarce water resources. Action by: CETP Societies/DJB/MCD/DDA/DFS/DPCC 1.3. Closure of units engaged in the activities listed in negative list / prohibited list as per MPD 2021: As per the provisions of Delhi Master Plan 2021, certain activities have been placed in the negative list, which are not permitted to operate after Highly polluting units are 32

33 falling in the above said list and are required to be closed down. By closing these units water pollution can be reduced to very significant extent. Industries department and DDA are required to close down the units engaged in the activities listed in negative/prohibited list of MPD Action by: Delhi Govt./DDA 1.4. Construction of Interceptor Sewer on Najafgarh Drain and Supplementary Drain: Water pollution, in these drains, is majorly caused due to discharge of untreated domestic sewage especially during the dry season. Delhi Jal Board has recently, after a detailed feasibility study by EIL, has proposed interceptor sewers for both Najafgarh Drain and Supplementary Drain which are contributing majorly towards the water pollution in the river Yamuna. Once the said project is completed the waste waters entering into these drains are intercepted and then treated before discharging the same into the river Yamuna. The system includes provision of interceptor sewers along with associated works like interceptor pits, new sewage pumping stations, rising mains etc. along the drains involving the related Sewage Treatment Plants in the catchment areas. The project is an integrated approach towards zero sewage flows in the drains and the river. Budget has also been sanctioned by the Delhi Government and Ministry of Urban Development, GOI for accomplishing the said project. Regular interactions with Delhi Jal Board are required to ensure the project is completed as per the time schedule. Action by: DJB/DPCC 2.0. Air Pollution Control: 2.1. Conversion of coal/ oil based boilers to gas based mode and ensuring strict usage of approved fuels: Coal/oil based boilers in Delhi are one of the air pollution sources which are to be addressed in a time bound manner and on priority. DPCC has decided not to permit the coal fired boiler and the units are being forced to convert their boiler on alternate fuel like oil/gas. 33

34 1. Action Converting into gas based mode is required to reduce the air pollution caused due to the former fuels. Continuous public campaigns such as issuance of Public Notices and subsequent inspections will discourage the units to use coal/oil and other unapproved fuels. by: Industries/IGL/DPCC 2.2. Ensuring operation of DG sets only with acoustic enclosure(s): There are number of DG sets in operation in the four industrial areas and significant number of these DG sets is provided with acoustic enclosures which are causing noise pollution. As per the notification of MoEF, GOI, all the DG sets are required to be provided with acoustic enclosure to reduce noise pollution and all the new DG sets are to be provided with the noise control system by the manufacturer itself. Old DG sets are required to be phased out or provided with sound reducing systems. NDPL/BSES is to ensure sufficient/required power supply in these industrial areas. Action by: NDPL/BSES/DPCC 2.3. Thrust on Gas based power plants: Looking at the pollution threat posed by coal based power plants in any urban area, coal based plants are being discouraged and only gas based power plants are being given go ahead to boost up the power generation. Two power plants by Pragathi Power Corporation Limited (PPCL) at Bawana (1600 MW) and at Bamnauli (750 MW) and one by NDPL at Rohini (108 MW) have been proposed power generation and it is worth to see that all the plants will operate on gas. The combined power generation of all the three plants will be to the tune of 2458 MW. NDPL will start its generation by October 2010 and other plants will be made operational by Out of these three, one plant of 750 MW capacity at Bamnauli is awaiting EC from MoEF, GOI. Action by: DPCC/Dept. of Power/MoEF, GOI 34

35 3.0 Land and Soil Pollution: 3.1 Construction of TSDF for disposal of Hazardous Waste and Identification of illegal HW dump sites in the industrial areas & remediation of identified illegal HW dump sites: Due to no availability of adequate land and opposition from local people, the Government is not able to initiate proceedings to construct TSDF for hazardous waste disposal in Delhi, which is allowing people to dump their HW in an open land indiscriminately thereby causing ground water pollution by way of leachate percolation into the ground water resources. It has been proposed to have the facility at Khanjawla and it has been decided to acquire land of 50 acres and the process of acquisition is underway. Once all the clearances such as getting EC is over, about one year time is required to complete the project and the same will be made operational. TSDF site is to be commissioned for HW treatment and its disposal in a time bound manner by pursuing with all the concerned stakeholders. As per report of Ramky Infra Consulting Pvt ltd report of August 2007, 12 illegal HW dump sites have been found in the industrial areas falling in the catchment area of the Drain and there is a possibility of more illegal HW dump sites. Already identified sites are required to be remediated on priority to avoid ground water contamination. This task is to be carried out by the land owning agency by engaging any expert external agency/consultant. Further inspections are to be carried out done to identify any new sites for immediate action. Action by: MCD/DDA/DSIIDC/Revenue Dept. /Dept of Environment 3.1 Integrated MSW Management Facility at Narela: Management of Municipal Solid Waste in Delhi is one of the important tasks which require immediate attention. The municipal authorities are doing their best to address this problem. Recently, MCD in partnership with Ramky 35

36 Action by: MCD/DPCC/Ramky Infrastructure Ltd. Summary: Looking at the submissions and facts of the development took place in the preceding years and also the proposed construction of interceptor sewer on major drains and other developments such as expansion of metro rail, widening of roads, BRT Corridors etc there is a clear evidence, from the environmental data given in page No. 16 of this report, that the scenario compared to the year 1997 has changed tremendously which requires removal of the area/cluster form the list of critically polluted areas. Steps proposed and other continuing actions will surely bring down the pollution levels in various spheres in NCT of Delhi and the CEPI of Najafgarh Drain Basin including other four industrial areas of Delhi will get reduced in a significant way. In view of the above, MoEF, GOI and CPCB are requested to look into the matter and remove the said area/cluster from the list of 88 critically polluted areas. 36

37 37 Annexure-I

38 Details of Parameters Exceeding at Inlet of CETPs Annexure-II Jhilmil GTK Lawrence Rd Badli Mayaprui Jun 2009 TSS- 388, TSS-412 TSS-388 TSS-408 TSS-760 Cr(Total) Cr(Total)-2.42 July 2009 TSS-320 TSS-468 TSS-604 TSS-352 Cr(Total)-2.36 TSS-440 Aug 2009 TSS-1448 TSS-832 Non-Functional TSS-304 TSS-288 Sept 2009 TSS-780 TSS-480 Non-Functional TSS-52 TSS-264 Oil & Grease Oct 2009 TSS-256 TSS-1085 Non-Functional Non-Functional TSS-760 Nov 2009 TSS-296 Cr(Total)-2.67 TSS-292 Non-Functional TSS-560 TSS-460 Cr(Total)-2.43 Dec 2009 TSS-277 Meeting Stds Non-Functional TSS-1690 Cr(Total)-3.1 Meeting Stds Jan 2010 Meeting Stds TSS-1156 TSS-304 TSS-644 TSS-292 Cr-7.14 Cr(Total)-4.02 Feb 2010 Cu-4.1 TSS-1072 TSS-284 TSS-488 TSS-408 Mar 2010 TSS-228 TSS-472 Non-Functional TSS-456 TSS-372 Cu-5.91 Cr(Total)-5.65 Apr 2010 TSS-440 TSS-1132 Non-Functional TSS-2720 TSS-252 May 2010 Meeting Stds Meeting Stds TSS-372 TSS-204 TSS

39 ANNEXURE-II Details of Parameters Exceeding at Inlet of CETPs Mangolpuri Wazirpur DSIIDC & Nangloi Jun 2009 Meeting Stds ph-2.2 TSS-340 TSS-540 Ni-9.93 Cu Cr Cd-1.27 SMA Okhla Narela ph-3.2 TSS-308 Cu-3.1 Cr(Total) TSS-388 Cr(T) TSS-360 July 2009 TSS-812 TSS-912 Ni-11.5 Cu-1.1 Cr-76.2 Aug 2009 TSS-546 Ni-9.42 Cu TSS-96 Cr Sept 2009 Oct 2009 TSS-580 Oil & Grease TSS-528 Oil & Grease TSS-546 Ni-9.42 Cu Cr ph-1.7 TSS-544 Ni-28.4 Cu-21.2 Cr-82.6 Nov 2009 TSS-348 ph-2.4 TSS-376 Ni-10.8 Cu-12.4 Cr Dec 2009 TSS-512 TSS-412 Ni-15 Cu-25.4 Cr-52.2 Jan 2010 TSS-384 Cu-3.1 Non- Functional Feb 2010 TSS-404 TSS-484 Ni-47.5 Cu-35.5 Mar 2010 TSS-304 Cu-15 Apr 2010 TSS-304 ph-2.7 TSS-628 May 2010 TSS-284 ph-2.53 Meeting Stds Meeting Stds Meeting Stds ph-5.1 TSS-696 TSS-664 Cr(Total) TSS-464 TSS-456 Ni-3.84 Cr(Total) TSS-780 Ni TSS-504 Ni-4.88 Cu-3.81 Cr(Total) Pb-1.2 ph-2.7 TSS-684 Ni-3.46 Cu-3.12 Cr(T)-24.4 TSS-296 Cr(T)-2.67 TSS-704 Oil & Grease-22.4 Meeting Stds TSS-280 TSS-776 Oil & Grease Non Funtional TSS-432 TSS-320 Meeting Stds TSS-352 TSS-440 TSS-1472 TSS-600 Meeting Stds TSS-332 ph-5.3 TSS-280 TSS-272 Pb-4.45 TSS-896 TSS-372 TSS-388 TSS-372 TSS-400 TSS-420 TSS-528 TSS-252 Cr(T)-2.46 TSS-360 TSS-1010 TSS-476 TSS-328 TSS-7580 Cu-4.62 TSS-512 TSS-296 Meeting Stds 39

40 Jun 2009 July 2009 Aug 2009 Sept 2009 Oct 2009 Nov 2009 Dec 2009 ANNEXURE-II Details of Parameters Exceeding at Outlet of CETPs Jhilmil GTK Lawrence Rd Badli Mayapuri Cl-1440 Fluoride-2.4 TDS-2850 Cl-2600 TDS-2700 Meeting std Cl-1960 TDS-2570 Fluoride- 2.4 Cl-2100 TDS-2570 Fluoride-2.8 Cl-1500 TDS-3450 Fluoride-2.4 Meeting Stds Fluoride-2.4 Meeting Stds Meeting Stds Cl-1250 Meeting Stds Meeting Stds TSS-116 BOD-54 Cl-2580 TDS-4660 Meeting Stds Meeting Stds BOD-54 TDS-2950 Fluoride-2.8 Sulphide-3.2 Meeting Stds Meeting Stds Non-Functional Meeting Stds Meeting Stds Non-Functional Chlorine-1040 Fluoride-2.2 Sulphide-3.5 Sulphide-3.4 Non-Functional Chlorine-1740 Oil & Grease Non-Functional TDS-2270 Non-Functional Non-Functional Cl-1450 TDS-2420 Meeting Stds Cl-1470 Meeting Stds Jan 2010 BOD-37 Cl-1100 Cl-1600 Chlorine Cr(Total)-4.02 TDS-4490 Fluoride-2.45 Feb 2010 Cl-1020 Cl-1120 TDS-4820 TDS-2740 TDS-2200 Mar 2010 Fluoride-3.8 Meeting Stds Non-Functional Fluoride-2.6 Apr 2010 Non-Functional May 2010 Cl-1680 TDS-2470 Fluoride-3.5 Cl-4300 TDS-3620 Sulphide-4 Fluoride-2.3 Cl-1180 BOD-38 Cl-1320 TDS-2180 TDS-2150 TDS-2430 Sulphide-3.6 Fluoride-2.6 Chlorine-1600 Fluoride-2.4 BOD-36 Chlorine-1400 Fluoride-3 Meeting Stds 40

REPORT ON COMMON EFFLUENT TREATMENT PLANTS (CETPS)

REPORT ON COMMON EFFLUENT TREATMENT PLANTS (CETPS) REPORT ON COMMON EFFLUENT TREATMENT PLANTS (CETPS) (IN THE MATTER OF W.P.(C) NO.4677 OF 1985; M.C. MEHTA V/S UOI & OTHERS) APRIL, 2008 ENVIRONMENTAL POLLUTION (PREVENTION AND CONTROL) AUTHORITY FOR THE

More information

Rajasthan State Pollution Control Board

Rajasthan State Pollution Control Board M/s Raj West Power Private Limited Village- Bhadresh, Tehsil:Barmer District:Barmer Sub: Ref: Sir, Consent to Operate under section 25/26 of the Water (Prevention & Control of Pollution) Act, 1974 and

More information

CHAPTER 13 WATER SUPPLY AND SEWERAGE

CHAPTER 13 WATER SUPPLY AND SEWERAGE CHAPTER 13 WATER SUPPLY AND SEWERAGE Delhi Jal Board, an autonomous body under Govt. is responsible for procurement and treatment of bulk water in Delhi. It is responsible for supply of drinking water

More information

Water Supply & Sanitation

Water Supply & Sanitation Water Supply & Sanitation 1. Delhi Jal Board is responsible for procurement and treatment of allocated raw water to Delhi. Delhi Jal Board make bulk supply of treated potable water to Delhi Cantonment

More information

Annual Review Report of DPCC w.r.t MSW for the year (based on data provided by local bodies)

Annual Review Report of DPCC w.r.t MSW for the year (based on data provided by local bodies) Annual Review Report of DPCC w.r.t MSW for the year 2015-16 (based on data provided by local bodies) 1. 2. Name of the State/Union territory Name & Address of the State Pollution Control Board/Pollution

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Six Monthly Compliance Report June-2015 M/s Mahagun Real Estate Pvt. Ltd SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex Mahagunpuram AT VILLAGE Mehrauli, Dasna, Ghaziabad, U.P. Being developed

More information

Conceptual plan. Table 1:Area Statement for proposed Corporate Office Complex AREA STATEMENT: -

Conceptual plan. Table 1:Area Statement for proposed Corporate Office Complex AREA STATEMENT: - Conceptual plan Table 1:Area Statement for proposed Corporate Office Complex AREA STATEMENT: - Area of plot= 5293SQM, Sanctioned FAR = 10586SQM as per earlier sanctioned.(2) Sanctioned Built up Area=19480.63

More information

ENVIRONMENTAL STATEMENT FORM-V SYNTHETIC GYPSUM MANUFACTURING PLANT M/S SHREE CEMENT LIMITED, BEAWAR, (RAJASTHAN) APRIL, 2010 to MARCH 2011 PART A

ENVIRONMENTAL STATEMENT FORM-V SYNTHETIC GYPSUM MANUFACTURING PLANT M/S SHREE CEMENT LIMITED, BEAWAR, (RAJASTHAN) APRIL, 2010 to MARCH 2011 PART A ENVIRONMENTAL STATEMENT FORM-V SYNTHETIC GYPSUM MANUFACTURING PLANT M/S SHREE CEMENT LIMITED, BEAWAR, (RAJASTHAN) APRIL, 2010 to MARCH 2011 PART A 1. Name and address of the Owner / Occupier of the Industry

More information

SHREE CEMENT LTD..~..~..~ ii. Regd. Office:. 0. ~ ~. ~ BANGUR NAGAR, POS': BOX NO.33, BEAWAR , RAJASTHAN, INDIA ~ 66~~'" 'Its ~s 71 66

SHREE CEMENT LTD..~..~..~ ii. Regd. Office:. 0. ~ ~. ~ BANGUR NAGAR, POS': BOX NO.33, BEAWAR , RAJASTHAN, INDIA ~ 66~~' 'Its ~s 71 66 CIN No. : L26943RJ1979PLC001935 Phone : 01462228101-6 Toll Free : 18001806003/6004 Fax: 01462228117/228119 E-Mail: shreebwr@shreecementltd.com (I." Website : www.shreecement.in SHREE CEMENT LTD..~..~..~

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

STATE POLLUTION CONTROL BOARD, ORISSA Paribesh Bhawan, A/118, Nilakanthanagar,Unit-VIII, Bhubaneswar , INDIA

STATE POLLUTION CONTROL BOARD, ORISSA Paribesh Bhawan, A/118, Nilakanthanagar,Unit-VIII, Bhubaneswar , INDIA OPERATING GUIDELINES FOR PROCESSING OF CONSENT TO ESTABLISH APPLICATION FOR ESTABLISHMENT OF COAL WASHERIES IN THE STATE OF ORISSA STATE POLLUTION CONTROL BOARD, ORISSA Paribesh Bhawan, A/118, Nilakanthanagar,Unit-VIII,

More information

Urban impacts on groundwater quality in the Delhi region

Urban impacts on groundwater quality in the Delhi region Impacts of Urban Growth on Surface Water and Groundwater Quality (Proceedings of IUGG 99 Symposium HS5, Birmingham, July 1999). IAHS Publ. no. 259, 1999. 227 Urban impacts on groundwater quality in the

More information

Rajasthan State Pollution Control Board

Rajasthan State Pollution Control Board M/s Raj West Power Private Limited Village- Bhadresh, Tehsil:Barmer District:Barmer Sub: Ref: Consent to Operate under section 25/26 of the Water (Prevention & Control of Pollution) Act, 1974 and under

More information

The NGT, Ganga, U.P. And Uttaranchal-Implications for the Sugar & Distillery Sector by: Dr. Yashpal Singh. Environmental Counselor

The NGT, Ganga, U.P. And Uttaranchal-Implications for the Sugar & Distillery Sector by: Dr. Yashpal Singh. Environmental Counselor The NGT, Ganga, U.P. And Uttaranchal-Implications for the Sugar & Distillery Sector by: Dr. Yashpal Singh Environmental Counselor IF ALL THE WATER ON EARTH WERE STORED IN A 18 LITER BOTTLE. FRESH WATER

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

EXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT

EXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT EXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT For CHHATTISGARH ENVIRONMENT CONSERVATION BOARD CHHATTISGARH 0 P a g e 1.0 INTRODUCTION SUMIT ISPAT PVT. LTD. has proposed to establish Submerged

More information

Health and safety norms of CPWD should be followed during construction.

Health and safety norms of CPWD should be followed during construction. Status of Compliance of Conditions of the Environmental Clearance Issued to Riveria Commercial Developers Ltd. DLF Center, Sansad Marg, New Delhi 110001- Construction of "YASHWANT PLACE COMMUNITY CENTRE"

More information

2. The expected cost of the project is Rs.50 crores.

2. The expected cost of the project is Rs.50 crores. Subject Application for obtaining Environmental Clearance for development of an "Integrated Municipal Solid Waste Management System for Pathankot Cluster" by Municipal Council, Pathankot at Village Kalanaur,

More information

BRIHANMUMBAI MAHANAGARPALIKA

BRIHANMUMBAI MAHANAGARPALIKA BRIHANMUMBAI MAHANAGARPALIKA PROJECTS SANCTIONED UNDER JNNURM A] IV Mumbai - Middle Vaitarna Water Supply Project :- Municipal Corporation of Greater Mumbai (MCGM) has undertaken the Middle Vaitarana Water

More information

Pre-Feasibility Report For

Pre-Feasibility Report For Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

ADITYA BIRLA. EMil. Please find enclosed herewith the environmental statement report duly filled-in Form-V

ADITYA BIRLA. EMil. Please find enclosed herewith the environmental statement report duly filled-in Form-V / ADITYA BIRLA EMil Ref. No. EMILIGEOLI '35, 12017-18 Date-07.09.2017 0V The Member Secretary, State Pollution Control Board, Odisha Department of Forests ft Environment, Govt. of Odisha, Paribesh Bhawan,

More information

PART A. 3. Production Capacity 3.6 Million TPA Cement 4. Year of Establishment th September 2015 PART B WATER AND RAW MATERIAL CONSUMPTION

PART A. 3. Production Capacity 3.6 Million TPA Cement 4. Year of Establishment th September 2015 PART B WATER AND RAW MATERIAL CONSUMPTION Page 1 of 8 Environmental Statement for Clinker Grinding Unit of M/s Bihar Cement Plant (A Unit of Shree Cement Ltd.), situated at Jasoia Mor, BIADA, Industrial Growth Centre, Aurangabad, Tehsil & Dist.

More information

Action taken (NGT Order dated 07 th August vide OA No. 138, 139/2018)

Action taken (NGT Order dated 07 th August vide OA No. 138, 139/2018) Action taken (NGT Order dated 07 th August vide OA No. 138, 139/2018) Till date, eight meetings of the Executing Committee have been conducted i.e. one at Shimla and seven at Chandigarh where HPPCB participated

More information

Excreta Matters: 7 th Citizens Report on the state of India s Environment. An agenda for water-prudent and waste-wise India.

Excreta Matters: 7 th Citizens Report on the state of India s Environment. An agenda for water-prudent and waste-wise India. Excreta Matters: 7 th Citizens Report on the state of India s Environment An agenda for water-prudent and waste-wise India Need to reinvent Rapid urbanization is creating new water stresses Violence is

More information

THE 3R S FOR CLEAN WATER - SAVING INDIA S RIVERS: INDIAN EXPERIENCES

THE 3R S FOR CLEAN WATER - SAVING INDIA S RIVERS: INDIAN EXPERIENCES THE 3R S FOR CLEAN WATER - SAVING INDIA S RIVERS: INDIAN EXPERIENCES NATIONAL MISSION FOR CLEAN GANGA MINISTRY OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION Central Water Commission India

More information

meeting held on meeting held on The SEAC observed that:

meeting held on meeting held on The SEAC observed that: Excerpt pertaining to item no. 147.14 of 147 th meeting of SEAC held on 30.06.2016 Item no.147.14: Application for obtaining Environmental Clearance under EIA notification dated 14.09.2006 for area development

More information

J-11011/45/2009- IA II (I)

J-11011/45/2009- IA II (I) SL SPECIFIC CONDITIONS STATUS 1 Continuous stack monitoring facilities to monitor gaseous emissions from all the stacks shall be provided. The particulate emissions shall be controlled within 50 mg/nm

More information

M/S. HETERO INFRASTRUCTURE SEZ LIMITED

M/S. HETERO INFRASTRUCTURE SEZ LIMITED ENVIRONMENTAL STATEMENT (FORM - V) FOR THE FINANCIAL YEAR ENDING MARCH-2016. M/S. HETERO INFRASTRUCTURE SEZ LIMITED N.NARASAPURAM(V),NAKKAPALLI(M) VISAKHAPATNAM DISTRICT. SUBMITTED TO : ANDHRA PRADESH

More information

COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated

COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated 10.08.2009 Period : January 2018 to June 2018 Sl.No. CONDITIONS STIPULATED BY MoEF COMPLIENCE Specific Conditions

More information

Accord Energy Corporation India Pvt. Ltd.

Accord Energy Corporation India Pvt. Ltd. Accord Energy Corporation India Pvt. Ltd. PRE-FEASIBILITY REPORT ON ENVIRONMENTAL ASPECTS OF PROPOSED INCREASE IN CAPACITY 2 x 150 MW to 2 x 180 MW OF EXISTING ENVIRONMENTAL CLEARANCE ( J-13012/107/ 2009-IA-II

More information

COMPLIANCE STATUS REPORT

COMPLIANCE STATUS REPORT COMPLIANCE STATUS REPORT Sona Alloys Pvt. Ltd. Additional Director (IA) Ministry of Environment & Forests, Paryavaran Bhavan, CGO Complex, Lodhi Road, New Delhi 11003 Date: 08.02.2014 Sub: Compliance Status

More information

A Dialogue on Cities and Climate Change. Mr. Dharmendra Secretary (Environment & Forests) Govt. of NCT Delhi, India

A Dialogue on Cities and Climate Change. Mr. Dharmendra Secretary (Environment & Forests) Govt. of NCT Delhi, India A Dialogue on Cities and Climate Change Delhi and Its Progress on Tackling Climate Change Issues Mr. Dharmendra Secretary (Environment & Forests) Govt. of NCT Delhi, India INDIA DELHI Latitude :28.38 N

More information

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative)

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative) Six Monthly Progress Report reg. Construction of Group Housing Colony at village Sarai Aurangabad in Sector 3-A, Bahadurgarh (Distt. Jhajjar), Haryana by M/s Prabhu Shanti Real Estate Pvt. Ltd., due in

More information

ANNEXURE- II Proposed TOR

ANNEXURE- II Proposed TOR ANNEXURE- II Proposed TOR Annexure II Terms of Reference for EIA for Setting up of Ligno-Cellulosic Biomass based second generation (2G) Ethanol Bio-Refinery with capacity of 100 KLPD at village-sainjani,

More information

7 th REPORT ON PK KAUL COMMITTEE RECOMMENDATIONS In Writ Petition{C} No 914/1996 in response to the letter from the Amicus Curiae

7 th REPORT ON PK KAUL COMMITTEE RECOMMENDATIONS In Writ Petition{C} No 914/1996 in response to the letter from the Amicus Curiae 7 th REPORT ON PK KAUL COMMITTEE RECOMMENDATIONS In Writ Petition{C} No 914/1996 in response to the letter from the Amicus Curiae January, 2007 ENVIRONMENTAL POLLUTION (PREVENTION AND CONTROL) AUTHORITY

More information

6. ENVIRONEMNTAL IMPACT

6. ENVIRONEMNTAL IMPACT 6. ENVIRONEMNTAL IMPACT 6.1 Introduction Any development activity invariably involves some changes in the existing natural environment. Of late, there has been a considerable awareness regarding the need

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Collection of Base line data in any season other than Monsoon season in study area of 10 kms radius from Lease Area. Based on the Meteorological data from

More information

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad 1. EXECUTIVE SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT : TYPE OF PROJECT : Proposed Project for manufacturing of pharma intermediates by Halcyon Labs Pvt.Ltd. LOCATION : Proposed Project of Halcyon

More information

Progressive deteriortaion of groundwater quality in Vrishabhavathi Valley Basin, Bangalore, India

Progressive deteriortaion of groundwater quality in Vrishabhavathi Valley Basin, Bangalore, India Progressive deteriortaion of groundwater quality in Vrishabhavathi Valley Basin, Bangalore, India Dr.Balasubramanya N Professor & Dean, Civil Dept Acharya Institute of Technology, Bangalore Dr Shankar

More information

Environment protection measures / technology

Environment protection measures / technology Sr. No. Conditions A. Specific Conditions: i. The gaseous and particulate matter emissions from various units should conform to the standards prescribed by the State Pollution Control Board. At no time,

More information

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS 1. Name of the Project: M/s MCC PTA India Corp. Private Limited Haldia ( WB) Note: Company Name was change from MCC PTA India Corp.Private

More information

Ministry of Environment & Forests (C.P. Division) Revised Guidelines for the Centrally Sponsored Scheme of Common Effluent Treatment Plants (CETPs)

Ministry of Environment & Forests (C.P. Division) Revised Guidelines for the Centrally Sponsored Scheme of Common Effluent Treatment Plants (CETPs) Ministry of Environment & Forests (C.P. Division) ++ Revised Guidelines for the Centrally Sponsored Scheme of Common Effluent Treatment Plants (CETPs) 1. Introduction: Under the Water (Prevention and Control

More information

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests Madhya Pradesh Pollution Control Board E 5. Arera Colony Bhopal 4620 16 visit us

More information

An Analysis of the Annual and Seasonal Trends of Air Quality Index of Delhi

An Analysis of the Annual and Seasonal Trends of Air Quality Index of Delhi DOI 10.1007/s10661-006-9474-4 An Analysis of the Annual and Seasonal Trends of Air Quality Index of Delhi Manju Mohan & Anurag Kandya Received: 10 June 2006 / Accepted: 21 August 2006 # Springer Science

More information

Calcom Cement India Limited

Calcom Cement India Limited Calcom Cement India Limited (Subsidiary of DALMIA BHARAT CEMENT LIMITED) 2 No. Pipalpukhuri, Lanka, Dist. Nagaon, Assam 782446 Ref: MOEF, New Delhi Environment Clearance F. No. J-1101/312/2006-IA.II (I)

More information

The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT

The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT ABOUT PROJECT The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In earlier project planning the total plot area

More information

COMPREHENSIVE ACTION PLAN FOR CRITICALLY POLLUTED INDUSTRIAL CLUSTERS OF GHAZIABAD (U.P.)

COMPREHENSIVE ACTION PLAN FOR CRITICALLY POLLUTED INDUSTRIAL CLUSTERS OF GHAZIABAD (U.P.) COMPREHENSIVE ACTION PLAN FOR CRITICALLY POLLUTED INDUSTRIAL CLUSTERS OF GHAZIABAD (U.P.) (Progress of Action Plan as per Review Meeting held by District Magistrate Ghaziabad on 5-2-2011) U.P. POLLUTION

More information

3. DATA COLLECTION 3.1 DATA COLLECTION 3.2 DATA COLLECTION AGENCIES

3. DATA COLLECTION 3.1 DATA COLLECTION 3.2 DATA COLLECTION AGENCIES 3. DATA COLLECTION 3.1 DATA COLLECTION Systematic data collection helps for effective outcome of research work. Record of the data helps to identify the characteristics of the selected plant. In the present

More information

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated Environmental Clearance; Letter No J-11011 / 152 / 2006-IA-II (I) Dt. 21.05.2007 and corrigendum dated 18.09.2007 For Revamping of Ammonia and Urea Plant at Gadepan, Kota; Rajasthan by M/S Chambal Fertilisers

More information

We are sending herewith the following for the month of September 2016.

We are sending herewith the following for the month of September 2016. ZZJ/CLAB-KSPCB/04/6499 07-10-2016 Environmental Officer, Regional Office, Karnataka State Pollution Control Board, Parisara Bhavan, LIG II, B 217, B-1, Main Road, A-16th Cross, Near Hari Om Trust, Habbuwada,

More information

REVISED NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS)

REVISED NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS) REVISED NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS) Background PEPC in its first meeting held on 10 th May 1993 approved the NEQS. The approved NEQS were uniform standards applicable to all kind of

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT FOR RESIDENTIAL TOWNSHIP WITH VACATION RESORTS PROJECT AT ALIBAUG, RAIGAD, MAHARASHTRA PROPOSED TERMS OF REFERENCE Submitted to State Level Environment Impact Assessment

More information

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated Environmental Clearance; Letter No J-11011 / 152 / 2006-IA-II (I) Dt. 21.05.2007 and corrigendum dated 18.09.2007 For Revamping of Ammonia and Urea Plant at Gadepan, Kota; Rajasthan by M/S Chambal Fertilisers

More information

Environmental Clearance Compliance Half Yearly Report

Environmental Clearance Compliance Half Yearly Report Environmental Clearance Compliance Half Yearly Report HALF YEARLY COMPLIANCE REPORT- April 2015 to September 2015 Ref: 1. MOEF, New Delhi Environment Clearance F. No. J-11011/119/2007- IA II (I) dated

More information

A Short term study of Dissolved Oxygen behavior in Adyar River, Chennai

A Short term study of Dissolved Oxygen behavior in Adyar River, Chennai A Short term study of Dissolved Oxygen behavior in Adyar River, Chennai Dr. Lavanya Vaithyanathan 1, Salome Solomon 2, Sunkara Krishna priya 3 Department of Civil Engineering, Assistant professor 1, Department

More information

The data for the period, April 2016 September 2016, is enclosed at Annexure III (1 nos. of pages)

The data for the period, April 2016 September 2016, is enclosed at Annexure III (1 nos. of pages) 1.0 Treated Liquid Effluent Data The data for the period, April 2016 September 2016, is enclosed at Annexure III (1 nos. of pages) 2.0 Ambient Air Quality The data for the period, April 2016 September

More information

Submitted by: M/s Panasonic India Ltd

Submitted by: M/s Panasonic India Ltd Environmental Monitoring Report (June-2014) FOR Industrial Building of Panasonic India Ltd At Jhajjar, Haryana Submitted by: M/s Panasonic India Ltd INDUSTRIAL PLOT NO-1, VILLAGE- BID DADRI JHAJJAR (HARYANA)

More information

MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL SAFEGUARDS Ministry of Environment & Forests Regional Office (W), Bhopal Monitoring Report Part-I

MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL SAFEGUARDS Ministry of Environment & Forests Regional Office (W), Bhopal Monitoring Report Part-I MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL SAFEGUARDS Ministry of Environment & Forests Regional Office (W), Bhopal Monitoring Report Part-I DATA SHEET 01 Project type : Cement Date: 24.11.2015 02

More information

REPORT ON PERFORMANCE EVALUATION OF SEWAGE TREATMENT PLANT TIRUNELVELI, TAMILNADU

REPORT ON PERFORMANCE EVALUATION OF SEWAGE TREATMENT PLANT TIRUNELVELI, TAMILNADU REPORT ON PERFORMANCE EVALUATION OF SEWAGE TREATMENT PLANT TIRUNELVELI, TAMILNADU As per mandate of Ministry of Environment & Forest, New Delhi, Central Pollution Control Board has taken up study on performance

More information

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan () would consist of all mitigation measures for each component of the environment due to the activities increased during the, operation and the

More information

. 0.:'. e:. :'} BANGUR NAGAR, POST BOX NO.33, BEAWAR , RAJASTHAN, INDIA Jji'665~" 1tS8;0 b AiS77..c,b

. 0.:'. e:. :'} BANGUR NAGAR, POST BOX NO.33, BEAWAR , RAJASTHAN, INDIA Jji'665~ 1tS8;0 b AiS77..c,b CIN No. : L26943RJ1979PLC001935 Phone : 01462228101-6 Toll Free: 18001806003/6004 Fax: 0146222811'71228119 E-Mail: shreebwr@shreecementltd.com Website : www.shreecement.in,-:,0 900, ~s}.s18(),9>01400,

More information

Looking beyond the boundaries: An approach for Water Neutral Electricity Production

Looking beyond the boundaries: An approach for Water Neutral Electricity Production Looking beyond the boundaries: An approach for Water Neutral Electricity Production Shresth Tayal 1 *, Dharmesh Kumar Singh 1,Shiv Kumar Dube 1,GopiKanta Nayak 2 and Sonia Grover 1 * Corresponding Author;

More information

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT Subject: Compliance report of Environmental Clearance for Plant 3 Reference: J-11011/603/2010-IA,

More information

WATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS

WATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS WATER CODE TITLE 2. WATER ADMINISTRATION SUBTITLE D. WATER QUALITY CONTROL CHAPTER 26. WATER QUALITY CONTROL SUBCHAPTER A. ADMINISTRATIVE PROVISIONS Sec. 26.001. DEFINITIONS. As used in this chapter: (1)

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

Study on performance evaluation of. sustainability

Study on performance evaluation of. sustainability Study on performance evaluation of STPs in Lucknow and dissue of wastewater t sustainability REGIONAL WORKSHOP Sustainable Water and Sanitation: Best management Practices Potential and Challenges May 1,

More information

Indian Standard DRINKING WATER SPECIFICATION (Second Revision)

Indian Standard DRINKING WATER SPECIFICATION (Second Revision) APPENDIX I BIS (IS 10500: 2012) Indian Standard DRINKING WATER SPECIFICATION (Second Revision) Sl No. Characteristic Requirement (Acceptable Limit) Permissible Limit in the Absence of Alternate Source

More information

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT Subject: Compliance report of Environmental Clearance for CDR & Revamp Reference: J-11011/272/2007-IA,

More information

THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2

THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2 THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2.6 MILLION TPA CEMENT & THERMAL POWER PLANT 36 MW EC Lr. No. : J-11011/403/2006-IA-II

More information

Mars Power & Steel Ltd.

Mars Power & Steel Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Mars Power & Steel Ltd. Village : Baihamura Tehsil : Ghargoda District : Raigarh Submitted to: Page 1 CHHATTISGARH ENVIRONMENT CONSERVATION BOARD Executive

More information

ENVIRONMENTAL AUDIT REPORT [STATEMENT] CONSTRUCTION WORK [ HALF YEARLY ] PERIOD OCTOBER 2012 TO MARCH 2013 FOUNDRY PARK

ENVIRONMENTAL AUDIT REPORT [STATEMENT] CONSTRUCTION WORK [ HALF YEARLY ] PERIOD OCTOBER 2012 TO MARCH 2013 FOUNDRY PARK ENVIRONMENTAL AUDIT REPORT [STATEMENT] ON CONSTRUCTION WORK [ HALF YEARLY ] PERIOD OCTOBER 2012 TO MARCH 2013 FOUNDRY PARK HOULI BAGAN, RANIHATI AMTA ROAD, HOWRAH Prepared by: FOUNDRY CLUSTER DEVELOPMENT

More information

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

Design of Sewerage System for Jaffarpur area in Southwest New Delhi International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 1 (2014), pp. 29-34 Research India Publications http://www.ripublication.com/ijcer.htm Design of Sewerage System for

More information

BRIEF SUMMARY OF THE PROJECT

BRIEF SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT Office Complex at Plot No. 5A & 5B, Shopping Mall, Vasant Kunj Phase - II, New Delhi Developed by M/s Oil and Natural Gas Corporation Limited BRIEF DESCRIPTION OF THE PROJECT

More information

International Journal of Advance Engineering and Research Development EFFECT OF NEARBY CITIES ON WATER QUALITY OF CHAMBAL RIVER

International Journal of Advance Engineering and Research Development EFFECT OF NEARBY CITIES ON WATER QUALITY OF CHAMBAL RIVER Scientific Journal of Impact Factor (SJIF): 4.72 International Journal of Advance Engineering and Research Development Volume 4, Issue 6, June -217 e-issn (O): 2348-447 p-issn (P): 2348-646 EFFECT OF NEARBY

More information

ENVIRONMENTAL STATEMENT FOR THE YEAR

ENVIRONMENTAL STATEMENT FOR THE YEAR ENVIRONMENTAL STATEMENT FOR THE YEAR 2016-17 6 MTPA STEEL PLANT OF TATA STEEL AT KLAINGANAGAR INDUSTRIAL COMPLEX, ODISHA ENVIRONMENTAL DEPARTMENT TATA STEEL KALINGANAGAR Kalinga Nagar Industrial Complex,

More information

PROJECT NAME: UTKAL ALUMINA INTERNATIONAL LTD. PERIOD OF COMPLIANCE: APRIL, 2013 TO SEPTEMBER, 2013.

PROJECT NAME: UTKAL ALUMINA INTERNATIONAL LTD. PERIOD OF COMPLIANCE: APRIL, 2013 TO SEPTEMBER, 2013. STATUS OF CONDITIONS IMPOSED IN ENVIRONMENTAL CLEARANCE FOR 3 MTPA REFINERY & 3X30 MW CO-GENERATION POWER PLANT VIDE LETTER NO. J-11011/753/2007-IA II (I), DATED 29.01.2008. PROJECT NAME: UTKAL ALUMINA

More information

ZZH/CLAB-KSPCB/04/ Environmental Officer,

ZZH/CLAB-KSPCB/04/ Environmental Officer, ZZH/CLAB-KSPCB/04/ 21273 08-12-2014 Environmental Officer, Regional Office, Karnataka State Pollution Control Board Parisara Bhavan, LIG II, B 217 B-1, Main Road, A-16 th Cross Near Hari Om Trust, Habbuwada

More information

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors 1. Increased water demand (12 KLD) due water usage for, dust suppression and for workers 2. Sewage generation (11 KLD) and disposal 3. Municipal solid waste generation (15 kg/day) by workers 4. Construction

More information

State Expert Appraisal Committee, Punjab Ministry of Environment and Forests, Government of India

State Expert Appraisal Committee, Punjab Ministry of Environment and Forests, Government of India State Expert Appraisal Committee, Punjab Ministry of Environment and Forests, Government of India O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala 147 001 Telefax:- 0175-2215802

More information

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests Madhya Pradesh Pollution Control Board E 5. Arera Colony Bhopal 4620 16 visit us

More information

The following were present to supervise the proceedings:- 1. Sh. Varun Roojam, IAS. Additional Deputy Commissioner. Muktsar. 2. Er. G.S.

The following were present to supervise the proceedings:- 1. Sh. Varun Roojam, IAS. Additional Deputy Commissioner. Muktsar. 2. Er. G.S. Proceeding of the Public Hearing conducted on 27.01.2009 for grant of environmental clearance to M/s Universal Bio-Mass Energy Pvt. Ltd. for setting up of 14.5 MW capacity Biomass based Independent power

More information

ENVIRONMENTAL MONITORING REPORT BASED ON DATA GENERATED FROM OCTOBER 2016 MARCH 2017 FOR OCL INDIA LIMITED At/Po: RAJGANGPUR, District: SUNDARGARH, ODISHA AT LANJIBERNA LIMESTONE & DOLOMITE MINES PROJECT

More information

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

4. The ambient air quality monitoring stations We are monitoring the ambient air quality GLOBAL CALCIUM PRIVATE LTD., 125&126, SIPCOT COMPLEX, HOSUR 635 126 Ref : No. J-11011/411/2006-IA-II(I) dated 1 st August 2007. Compliance Report for the Period ending 31.3.2015 Sl. Specific Conditions

More information

ENVIRONMENTAL MANAGEMENT PLAN. Hotel Project for Mohamed Ilyas & Ms. Alamzahan

ENVIRONMENTAL MANAGEMENT PLAN. Hotel Project for Mohamed Ilyas & Ms. Alamzahan ENVIRONMENTAL MANAGEMENT PLAN Of Hotel Project for Mohamed Ilyas & Ms. Alamzahan at Khasra No. 269Ga, 269Kh, 266Kh & 270 Village Majra, Tehsil Central Doon, District Dehradun (Uttarakhand) GENERAL ENVIRONMENTAL

More information

Panasonic India Pvt. Ltd.

Panasonic India Pvt. Ltd. Panasonic India Pvt. Ltd. December-2014 FOR Industrial Building of Panasonic India Ltd At Jhajjar, Haryana 1 Details of Environmental Monitoring INTRODUCTION M/s Panasonic India Pvt Ltd granted its Environmental

More information

Sewage Canal: How to Clean the Yamuna

Sewage Canal: How to Clean the Yamuna The tale of Delhi, its river, its water and its excreta Making the connections to clean the river About Yamuna. But not just Yamuna Every river, every lake, every water body getting polluted. Full of our

More information

HARDY AND KIDD ACID DRAINAGE AND METAL LEACHING HISTORIES: CONTRASTS AND COMPARISONS

HARDY AND KIDD ACID DRAINAGE AND METAL LEACHING HISTORIES: CONTRASTS AND COMPARISONS HARDY AND KIDD ACID DRAINAGE AND METAL LEACHING HISTORIES: CONTRASTS AND COMPARISONS Ronald V. Nicholson,Ph.D. Stantec Consulting Ltd. 1 th Annual BC ML/ARD Workshop Vancouver, December 2-3, 23 THE ARD

More information

TATA STEEL LIMITED. Environment Compliance Report (Oct 2017 to Mar 2018)

TATA STEEL LIMITED. Environment Compliance Report (Oct 2017 to Mar 2018) TATA STEEL LIMITED Construction of Residential Complex For Tata Steel Plant located at Kalinganagar Industrial Complex, at Environment Compliance Report (Oct 2017 to Mar 2018) Environment Department Tata

More information

Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi , Taluka - Shirol, Dist Kolhapur, Maharashtra

Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi , Taluka - Shirol, Dist Kolhapur, Maharashtra Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi - 416108, Taluka - Shirol, Dist Kolhapur, Maharashtra Compliance of Conditions Stipulated in environmental clearance granted

More information

: Industrial Projects - 2. : 26th October, 2016

: Industrial Projects - 2. : 26th October, 2016 1. Proposal No. : IA/AP/IND/26243/2014, 2. MoEFCC File No. : J-11011/408/2014-IA II (I) 3. Category of the Proposal : Industrial Projects - 2 4. Name of the proposal : M/s Divis laboratories limited, Unit

More information

Telefax: 011: Dated:10 th May, 2013

Telefax: 011: Dated:10 th May, 2013 F. No. J-11011/41/2011-IA-II (I) Government of India Ministry of Environment and Forests (I.A. Division) Paryavaran Bhawan CGO Complex, Lodhi Road New Delhi 110 003 E-mail:vp.upadhyay@nic.in Telefax: 011:

More information

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3" N to 20 44' 20.7"N Longitude " E to 85 35'27.5 "E

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3 N to 20 44' 20.7N Longitude  E to 85 35'27.5 E EXECUTIVE SUMMARY 1.0 INTRODUCTION Sri Mahesh Prasad Mishra proposes to mine Sand Quarry from an approved Mining Lease over an area of 14.85 Ac or 6.01 hectares (Non-Forest Land) which is located in at

More information

ENVIRONMENTAL MONITORING REPORT

ENVIRONMENTAL MONITORING REPORT ENVIRONMENTAL MONITORING REPORT BASED ON DATA GENERATED FROM APRIL 2018 SEPTEMBER 2018 FOR OCL INDIA LIMITED At/Po: RAJGANGPUR, District: SUNDARGARH, ODISHA AT LANJIBERNA LIMESTONE & DOLOMITE MINES PROJECT

More information

Shriram Vinyl & Chemical Industries, : Kota Compliance Report of Environmental Clearance dated 12 th July 2017 and amended on 23 rd November 2017

Shriram Vinyl & Chemical Industries, : Kota Compliance Report of Environmental Clearance dated 12 th July 2017 and amended on 23 rd November 2017 Shriram Vinyl & Chemical Industries, : Kota Compliance Report of Environmental Clearance dated 12 th July 2017 and amended on 23 rd November 2017 PART A : SPECIFIC CONDITIONS 1. CONSTRUCTION PHASE S. 1

More information

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA. A. CONSENT TO ESTABLISH UNDER THE PROVISIONS OF WATER (PREVENTION & CONTROL OF

More information