TECHNICAL MEMORANDUM (TM) UNDERSTANDING OF THE PROJECT

Size: px
Start display at page:

Download "TECHNICAL MEMORANDUM (TM) UNDERSTANDING OF THE PROJECT"

Transcription

1 TECHNICAL MEMORANDUM (TM) UNDERSTANDING OF THE PROJECT To: Michael Hindle, P.E. Mark Niemiec, P.E. Project Engineer Manager of District Projects Padre Dam MWD Padre Dam MWD PD JN From: Subject: John Harris, P.E. Project Manager RBF Consulting Eastern Service Area Secondary Connection Project I. INTRODUCTION AND PURPOSE PROJECT BACKGROUND The Eastern Service Area Secondary Connection Project (ESA SCP) is Padre Dam Municipal Water District s portion of capital improvements associated with the San Diego County Water Authority s (SDCWA) East County Regional Treated Water Improvement Program (ECRTWIP). The ECRTWIP is a comprehensive program of usage guarantees and capital improvements involving the District, SDCWA, Otay Water District, Lakeside Water District, and Helix Water District. The ESA SCP facilities include a new supply pipeline, a new discharge pipeline (with I-8 tunnel crossing), a new forebay reservoir, a new pump station, a new flow control facility (FCF) and associated facilities. The ESA SCP will assist the District in achieving its strategic goals by: Increasing water supply to meet projected future demands; Ensuring greater reliability on water distribution for the District s ESA as the new connection will provide secondary pumping capacity to the Blossom Valley Pressure Zone Enhancing water quality by decreasing water age to the ESA. The purpose of this TM is to outline the individual elements of the project, define the preliminary design objectives and serve as the basis for the development of final design documents. Page 1 Eastern Service Area Secondary Connection Project October 30, 2014 JN

2 Technical Memorandum Project Understanding SUMMARY OF PROJECT ELEMENTS Pump Station The pump station facility will consist of the following components. Refer to Figure 1 for the concept layout drawing. 12 MGD (ultimate capacity) pump station building approximately 44-feet in length and 37-feet in width with provisions for four (4) vertical turbine pumps housed in a split-face masonry block building with flat metal deck roof and parapet walls that includes an air-conditioned electrical room, and includes: 2 duty pumps installed initially for a total capacity of 9 MGD. Individual pumps shall be designed for 4.65 MGD at 435 feet TDH, 500 Horsepower motors per Figure 1 of TM-8, Pump Selection and Systems Operations; Basis of Design Report, dated June 9, standby pump 1 spare pump can for future 4 th pump 24-inch supply pipeline manifold with maximum velocity at 12 MGD of 5.9 fps, which is slightly over the velocity noted in the WAS design guideline of 5 fps. At the initial station capacity of 9 MGD, the velocity will be 4.4 fps. 16-inch pump suction pipelines to achieve the recommended 5 fps velocity with a maximum flow rate of 4.65 MGD. 20-inch supply pipeline manifold with maximum velocity at 12 MGD of 8.5 fps, which is slightly over the velocity noted in the WAS design guideline of 8 fps. At the initial station capacity of 9 MGD, the velocity will be 6.4 fps. 14-inch pump discharge pipelines will achieve a velocity of 6.7 fps, below the recommended 8 fps, with a maximum flow of 4.65 MGD. 12-inch pipelines will achieve a velocity of 9.1 fps. 12-inch solenoid activated booster pump control valve (PCV) with drop check feature will be provided for each pump discharge line. It should be noted that the cost of a 14-inch pump control valve is approximately $18,000 greater than a 12-inch valve and the 12-inch valve is rated to a maximum flow of 10 MGD. A 14-inch by 12-inch reducer will used on each side the PCV. Overhead crane rail with manual chain operated trolley and hoist. Rail to be centered over the pump control valves. 8-inch pressure relief line connecting the discharge and suction manifolds Stand-by generator with factory weather-proof/sound enclosure. 3.5 ton ceiling mounted air conditioning unit for the electrical room. A split system with interior air handling unit and exterior condensing unit will be investigated for cost savings and maintenance access. 1,200 cubic foot capacity air-over-water surge tank on the discharge pipe as determined in TM-11, Surge Analysis, Basis of Design Report, dated June 9, 2014 Page 2 Eastern Service Area Secondary Connection Project October 30, 2014

3 Technical Memorandum Project Understanding Flow meter in below ground vault on pump station discharge pipe. Floor drain and wash down water system. The floor drain piping shall discharge to the bioretention basin Architectural design to match Padre Dam s recently completed East and West Victoria pump stations. Electrical and Instrumentation features as discussed below. Discharge Pipeline The discharge pipe alignment will consist of: 5,790 lf of 20 diameter CML&C (wall thickness: 0.25 to meet maximum operating pressure of 250 psi) discharge pipe from the SCP facility to the intersection of Pecan Park Lane and Rios Canyon Road. This includes replacement of 3,960 lf of existing 16 PVC pipeline. Approximately 435 lf steel-cased (36-inch OD steel casing pipe with a inch wall) tunnel crossing I-8 from the SCP site to Ridge Hill Road. The tunneling techniques to be considered in order of preference include, auger bore and jack, open shield tunneling and microtunneling. Auger boring is the preferred option since it allows access to the face of the tunnel to remove any obstructions. Caltrans encroachment permit for I-8 tunnel crossing Requires County of San Diego encroachment permit for work within the County right-of-way Supply Pipeline The supply pipe alignment will consist of: New 20 side outlet connection to the 42-inch Helix Flume with isolation valve located along Business Route 8 at the SCP site. A new 42-inch by 20- inch welded steel tee will be cut into the existing 42-inch concrete cylinder pipe. Calculations will be performed to determine the restrained joint length required for the new tee. Interior welding of pipe joints will be performed to achieve the desired restrained joint length. Los Coches Creek crossing by open-trench construction 1,030 ft of 20 diameter CML&C welded steel suction pipe (wall thickness: 0.25 ) from the Helix Flume to the SCP facility. Requires County of San Diego encroachment permit for work within the County right-of-way Requires Streambed Alteration permit to be secured by Helix Environmental Flow Control Facility The FCF will consist of: Building housing with a single 24 pipe train with plunger style flow control valve, venturi meter and shutoff valves in an above-grade building all designed Page 3 Eastern Service Area Secondary Connection Project October 30, 2014

4 Technical Memorandum Project Understanding to SDCWA standards Architectural design to match the pump station SCADA system linked to SDCWA, Padre Dam and Helix Water District. Incorporate two District-owned 24 ball valves. Earthwork and retaining wall design to bury the incoming supply pipeline Wash down water piping and floor drain system to be included with a pumped drain discharge to a small percolation basin and outlet to the north of the facility. The FCF will be prepared as a separate design package utilizing SDCWA title block and design standards. Refer to attached concept design drawings Forebay Tank The Forebay will consist of: 1.75 MG prestressed concrete forebay tank (AWWA D110, Type I) Tank dimensions to be 115-feet in diameter by 24-feet in height Mass grading including rock excavation, over-excavation, remedial fill soil improvement, placement of fill material to partially bury the tank by 5 to 7 feet to achieve drainage and storm water runoff goals (see Civil Site Improvements below). SCADA system level controls and high water alarms Two roof access hatches with intrusion alarms connected to the SCADA system. Interior wash down water system Interior fiberglass ladders at roof hatches Under-slab inlet and outlet piping connections Under-slab drain connection Underdrain & perimeter foundation drain systems Reservoir drain box with sump pump and discharge to the site detention basin. SCADA high water alarms to be provided in the drain box. Overflow (2-16 diameter pipes) to gravity discharge to Caltrans drainage channel. A larger diameter single overflow pipe will be evaluated during the structural design process. Civil Site Improvements The Civil Site Improvements can be divided into the following components. Refer to Figures 2, 3 and 4 for concept site layout drawings. I. Drainage/Stormwater The existing site drains through the mobile home park. Proposed design will divert flow away from mobile home park and into the Caltrans drainage channel south of the site, significantly reducing flows through the mobile home park. Page 4 Eastern Service Area Secondary Connection Project October 30, 2014

5 Technical Memorandum Project Understanding Runoff from site will be treated per local regulations through the implementation of a Bioretention/Detention basin to mitigate peak runoff flow rates and volume, and treat the stormwater before leaving the site. Maintenance will consist of landscape maintenance, trash and debris removal, and clearing of pipes when necessary. The capacity of the Caltrans channel is shown to be adequate in the proposed condition, including overflow rates from the tank, with a freeboard of 2.5 but still contained within the ditch. The County channel downstream was also analyzed and shown to have more than 1-ft of freeboard in the proposed condition. The area including the access road off of El Dorado Pkwy and a portion of the Flow Control Facility will drain northeast into El Dorado Pkwy. Treatment and increased flow rates will be mitigated through the use of a vegetated swale and discharge on site where flows eventually go in the existing condition into El Dorado Pkwy. See further analysis and discussion in the Hydrologic and Hydraulic Analysis memo attached as Appendix A, dated September 25, 2014 II. Earthwork In order to achieve the stormwater goals, the grade at the reservoir and pump station site will be raised to accommodate positive flow for drainage, and will require a wall along the west side of the site adjacent to the mobile home park. The reservoir will sit entirely on fill, requiring overexcavation approximately 5-feet below existing grade Onsite materials are generally suitable for reuse as structural fill in accordance with the Geotechnical Evaluation, prepared by Ninyo & Moore, dated October 21, Material for fill that is granular (i.e. decomposed granite or granitic rock), uniform in depth, and compacted to 95 percent or more relative compaction will not require special material (i.e. soil cement) under the reservoir. Anticipate the fill will have a bearing capacity of 4,000 psf. Cut = 3,000-cy, Fill = 5,500-cy, Net = 2,500-cy import, which also accounts for the buried tank. III. Additional Civil Site Features Primary site access will be provided by a gated entrance road from El Dorado Parkway. The intersection with El Dorado Parkway will require a County of San Diego encroachment permit, which will be obtained by the Contractor during the construction phase. Access control will be provided by an automated gate with an electronic key card system and Fire Department override. The site will be fenced with 8 foot high security fencing (type to be determined). Fencing limits are as shown on Figure 2. Page 5 Eastern Service Area Secondary Connection Project October 30, 2014

6 Technical Memorandum Project Understanding The existing wooden bridge spanning Los Coches Creek will be removed and the stream channel returned to existing contours. All work within the stream channel shall be performed inside the footprint of the bridge. Landscaping will be provided to screen the site from adjacent properties. Removal of Arundo Donax in the northern portion of the site will be provided. Electrical/Instrumentation The electrical and instrumentation systems for the project can be divided into the following elements: I. Electrical Distribution System II. Standby Power The main electrical service to the Pump Station Building will be connected to the existing 12kV three phase, three wire, 60Hz SDG&E electrical power system along El Dorado Parkway. The connection point for power distribution will be at the existing pole along El Dorado Parkway and to be extended to the project site underground. The service transformer will be 2000kVA 12kV 480Y/277V, three phase, four wire, 60Hz pad mounted transformer. This will be located on the northwest of the water tank. Concrete pad will be provided. Required working clearances will be observed per SDG&E requirements. Service entrance rated Main Switchboard will be provided and located between the Flow Control Facility and the Pump Station Building. It will include underground pull section and meters and will be constructed per SDG&E requirements. The new service entrance switchboard will be rated 480Y/277, three phase, four wire, 65KA interrupting capacity. The main switchboard will be with NEMA 3R enclosure. A bus space shall be provided in the main switchboard to accommodate future PV system. The electrical equipment will be sized and designed to accommodate the full build-out of pumps (4 pumps at 500HP) plus all building loads. The connected load (loads that are expected to be operating concurrently) consist of the HVAC, lighting, and controls. The demand load will vary depending on the amount of water needed to be conveyed at a given time. This demand load is expected to consist of mostly one pump initially, but scaling up to three pumps at peak water demand. The design team will be completing an SDG&E demand load worksheet near the final stages of the design when all loads are identified. A 1000kW generator with sound attenuated, weatherproof enclosure, internal silencer, and sub-base tank will be located near the Pump Station Building to provide back-up power to the facility during power outage. The generator will be sized to run two pumps and miscellaneous electrical loads. The sub-base tank will be sized to support a 16-hour run time. Page 6 Eastern Service Area Secondary Connection Project October 30, 2014

7 III. Pump Station Building Technical Memorandum Project Understanding An Automatic Transfer Switch (ATS) will be provided to ensure continuity of power from normal to emergency. ATS will be located outside the pump station building. The FCF will not be connected to the emergency power system A combination motor control center (MCC) and switchboard will be provided for motor loads, lighting loads, control equipment, and miscellaneous loads. This will provide a compact and expandable method to distribute power throughout the facility. Reduced voltage starters, commonly known as Soft-Starters, and Variable Frequency Drives will be provided to control the starting and stopping on the main pumps. Each pump will be capable of starting on demand to match the demand needed. Selection of equipment will be closely coordinated with the District. Distribution Transformer will be provided to step-down voltage from 480v to 120/240V single phase, three wires, to supply power to receptacles and other general utility loads. Electrical panelboard with adequate spare circuit breakers will be provided. Industrial type lighting will provide general illumination in the space. Automatic controls using occupancy sensors will be provided. IV. Flow Control Facility Building A /240V single phase power will be provided for the Flow Control Facility Building to supply power to receptacles and other general utility loads. This will be supplied from the Main Switchboard with its own meter and run underground to the FCF Building. Industrial type lighting will provide general illumination in the space. Automatic controls using occupancy sensors will be provided. V. Instrumentation and controls The controls and automation for the Pump Station Building and Flow Control Facility will be PLC based with hard-wired sensors, transmitters and associated equipment. At the Pump Station Building, control data points will be relayed back to the District s central SCADA system via a radio antenna and remote SCADA terminal unit. District Standards for SCADA devices and system layout will be utilized. At the Flow Control Facility, a 56k modem connected to a nearby telephone service will provide SCADA connectivity. The RTUs for Helix Water District and SDCWA shall be located in the FCF. Page 7 Eastern Service Area Secondary Connection Project October 30, 2014

8 Technical Memorandum Project Understanding VI. Security system: CCTV, key-pad entry, and electrically operated gates A security system including key-pads access points, a camera monitoring system (CCTV) and electrically operated gates will be included. The design of security features will be closely coordinated with District personnel during design and construction. Ridge Hill Road Valve Vault The Ridge Hill Road Vault will consist of: A motor operated control valve (CV) is required between the East County Square reservoir and the intersection of Ridge Hill Road and Cordial Road. The CV will isolate the East County Square reservoir from the Blossom Valley pressure zone during SCP pumping operations. The CV will eliminate short-circuiting to the East County Square reservoir while the SCP is in operation. The precise location of the CV is currently being evaluated by District staff. The CV will consist of a below-grade valve vault with SCADA connected isolation butterfly valve. The SCADA system and valve actuator will be solar powered. Sierra Alta Drive Improvements The Sierra Alta Drive improvements will consist of: Installation of a pressure reducing valve in a below grade vault along the southerly shoulder of Pecan Park Road. The location of the PRV vault will be determined in the final design Ridge Hill Road Improvements The Ridge Hill Road improvements will be required along the portion of the road that is privately owned and the discharge pipeline will be placed within a common utility easement. Improvements planned include the following: Re-align water services as the current services lines will be in the path of the discharge pipeline. The water lateral relocations will be coordinated with Helix Water District. Restore any surface improvements disturbed during construction Re-pave the upper and lower portions of the roadway through the construction zone. Ninyo & Moore has reviewed the trench alignment and offset distance to the existing slope that separates the westbound and eastbound traffic and has determined that the slope will be stable under anticipated trenching operations and no stabilizing measures will be required. Page 8 Eastern Service Area Secondary Connection Project October 30, 2014

9

10

11

12 FIGURE 4 PADRE DAM ESA SDCWA ESMT AREAS 10/28/14

13 FLOW CONTROL FACILITY CONCEPT DRAWINGS Eastern Service Area Secondary Connection Project October 30, 2014

14 CONSULTING

15 CONSULTING

16 APPENDIX A HYDROLOGY AND HYDRAULIC CALCULATIONS Eastern Service Area Secondary Connection Project October 30, 2014

17 Date: October 22, 2014 To: From: Subject: Padre Dam Municipal Water District Richard S. Tomlinson, Jr. PE, QSP, QSD, CPSWQ, Padre Dam Eastern Service Area Secondary Connection Project Hydrologic and Hydraulic Analysis This report analyzes the effects of the Padre Dam Eastern Service Area Secondary Connection Project (ESASCP) on the existing Caltrans mortar lined ditch and the County of San Diego lined channel. The analysis was performed to determine the effect, if any, the proposed project would have on the existing facilities during a 100-year storm and/or if the proposed facilities were to overflow and discharge from the site. Background The ESA SCP project is a critical project for Padre Dam Municipal Water District and its customers within the Eastern Service Area. The project proposes the addition of a multitude of facilities, but the facilities that are of interest to the content of this memorandum are the facilities located within the ESA site, including a 1.75 million gallon storage tank and associated pipeline facilities. The ESA site is located to the north of Interstate Highway 8, south of Old Highway 80, and is bounded by single family residences to the east, and the Rancho Laguna Estates (mobile home park) to the west. The site, currently, only has access from Old Highway 80, but a new access road connecting to El Dorado Parkway is included with this project. The site is currently undeveloped with numerous rock out-croppings in the central portion of the site. A search of historic aerial photos show the site has in the past has been populated by four single family residences, which have since been demolished. The majority of the work is to be performed on the southerly, level portion of the site where the residence once stood, with improvements on the northerly portion of the site to be limited to the addition of a pipeline, and the removal of an existing unpermitted bridge over the Los Coches Creek. Existing Drainage Drainage from the southerly portion of the site flows from the northeast and southeast towards the middle of the site. Flows are collected within a brow ditch located on the adjacent mobile home park site, along the westerly boundary of the site. Flows then discharge into the walkway of one of the mobile estate spaces. The flow travels down the walkway of the lot before entering the drive aisle of the park. Flows travel westerly through the mobile estate drive before eventually discharging to the - 1 -

18 Los Coches Creek. Our analysis indicates the current 100-year storm runoff from the ESA site onto the mobile home park is 3.3 cubic feet per second (cfs). Proposed Drainage The project is proposing the construction of a number of complex facilities including a potable water storage tank, flow control facility, pump station and various pipelines. The maximum flow rate from the flow control facility is 9 million gallons per day (MGD) and from the pump station, 12 MGD. Under the worst case, if one or more of these facilities malfunction, or should an operational anomaly occur, it is possible the site could experience runoff at a rate as high as 500,000 gallons per hour, or about 18 cfs. The facility and operating systems are designed with safeguards and redundancies aimed at preventing such an event from occurring; including: extra volume in the tank itself, flow monitoring, tank water level monitoring, pump monitoring, and a supervisory control system that relays the information continuously to staff at District Operations center. The system also will alarm staff in the event of an emergency. Although the risk of multiple systems failing and causing a discharge is remote; flows discharging to the mobile home park causing damage could potentially occur. Therefore, it is proposed to route storm runoff and any overflow from the tank and other systems to the Caltrans ditch located between the site and the Interstate 8, and then to the County of San Diego channel, before discharging the flows to the Los Coches Creek. Because the overflow would run through the same system of swales, pipes and basins as the storm runoff, all site runoff that currently discharges to the mobile home park will also be routed to the Caltrans ditch. Since the ESA site flow currently does not go to the Caltrans ditch, an analysis was performed to determine what, if any affects, there would be on downstream facilities between the site, and the Los Coches Creek. The proposed routing of the drainage would be from the site southwest within the Caltrans 5 x 2 ditch, to the County channel, where it would flow northwest to the Los Coches Creek. These two segments were analyzed for this Memorandum. Because these flows ultimately discharge to the Los Coches Creek, the drainage is not being diverted. However, since the drainage is taking a slightly different path, that path was analyzed to ensure that there would be no detrimental impact on the downstream system

19 Drainage Analysis Methodology A combination of methodologies was used for the analysis. For the volumes within the Caltrans ditch, a modified Rational Method Drainage analysis was performed. This analysis was performed using the AES Rational Method computer program, which is based on the County of San Diego Drainage Design Manual (2003). For the analysis of the County channel, the Caltrans ditch was first routed into the County ditch. This flow was then combined with the inflow from the double box culvert located upstream of the project. For the discharge from the double box culvert, it was assumed the culverts were flowing full. All though this analysis presented the worst case, it was representative of the flows possible within the channel. Results Caltrans Ditch The analysis showed that in the existing condition, in the flattest section of the culvert, the ditch flowed at a depth of 1.62, see Table 1 below. When drainage flows from the site were added, the flow depth increased by less ½ to It should be noted, that this is 100-year flow, and there is a 1% chance that these flows will occur, and when they do, based on our analysis they will occur for only 30-minutes within that 100-year period. In the event of an overflow from the tank, an exceedingly rare event with all of the fail safe redundancies planned for the site, combined with a 100-year storm, also a rare event, the flow depth increased by 2 to Although the free board is less than the 6 typically preferred, the flow is still contained within the ditch. Table 1 Caltrans Ditch Hydraulic Conveyance Summary of Results Event Description Flow Rate Depth in Channel (cfs) 100-year flows Existing Condition year flows, with ESASCP Site year flows, with ESASCP Site and Overflow Because the runoff from a 100-year storm will likely have left the ESA site before the runoff from the upstream basin reached the ESA site, an additional analysis was performed. This analysis, using the Hydraflow Hydrographs flow routing model combined the anticipated hydrographs from the upstream areas with the anticipated hydrograph from the ESA site. This analysis showed that the when the hydrographs were laid upon each other, the peak flow from the site increased the flow within the channel by only 1.07 cfs, with a corresponding increase in depth of only 1/8 to This small amount of flow is less than a 1% increase in the flows with the Caltrans ditch

20 Results County Channel The second section analyzed was the County of San Diego 8 x 6 lined channel. Upstream of the County channel, there are two discharges. The first is the Caltrans channel that was analyzed above. The second is a double 5 x 5 box culvert also owned by Caltrans. This box culvert, when flowing at its maximum capacity of 94% full (flow at 100% full is 480 cfs), has a capacity of cfs per barrel, for a total capacity of 1,080 cfs, see Table 2 below. The existing county channel consists of a trapezoidal channel with a bottom width of 8 feet, a depth of 6 feet, and 2:1 side slopes. Our analysis showed that this channel, under 100-year flow conditions, has a depth of flow of This result is expected as an 8 x 6 channel designed to convey the 100- year flow would have a depth of flow less than 5 feet deep, allowing 1 foot of free board. When combining the overflow from the ESA site, and 100-year flows including the ESA site and upstream flows, the flow depth increased by ½ to This level is nearly 18 below the top of the channel during the 100-year flows and the tank overflowing simultaneously. Table 2 County Channel Hydraulic Conveyance Summary of Results Event Description Flow Rate Depth in Channel 100-year flows Existing Condition year flows, with ESASCP Site and Overflow Conclusions The proposed drainage design will virtually eliminate the storm runoff from the ESA site to the mobile home park to the west. The current 3.3 cfs runoff volume during the 100-year storm will be reduced to incidental amount of less than 0.2 cfs. It is possible for the 100-year flow generated hydraulically upstream of the site, the 100-year flow from the ESA site and the tank overflow to occur simultaneously, though the likelihood of this occurring is remote. Even though the possibility of this occurrence exists, all existing facilities have the capacity to convey the flow without overtopping. It should be noted that the results presented herein are based on the theoretical hydraulic capacity of the existing drainage facilities and have not factored in capacity losses associated with sediment or vegetation. From our field inspection, the Caltrans ditch is overgrown with vegetation thereby compromising its hydraulic capacity. We recommend the ditch be cleared of all vegetation, sediment and other debris to restore the full hydraulic capacity of this facility. Additionally, on-going maintenance of these facilities should be performed to ensure the maximum hydraulic capacity is retained

21 Calculations

22 WorksheetforCaltransDitchExistingCondition ProjectDescription FrictionMethod SolveFor ManningFormula NormalDepth InputData RoughnessCoeficient ChannelSlope LeftSideSlope RightSideSlope Botom W idth Discharge ft/ft 1.00 ft/ft(h:v) 1.00 ft/ft(h:v) 5.00 ft ft³/s Results NormalDepth 1.62 ft Flow Area ft² WetedPerimeter 9.59 ft HydraulicRadius 1.12 ft TopW idth 8.24 ft CriticalDepth 2.44 ft CriticalSlope ft/ft Velocity ft/s VelocityHead 2.62 ft SpecificEnergy 4.24 ft FroudeNumber 2.01 Flow Type Supercritical GVFInputData Downstream Depth 9/25/20142:48:46PM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 1 of 2

23 WorksheetforCaltransDitchExistingCondition GVFInputData Downstream Depth Length NumberOfSteps 0 GVFOutputData Upstream Depth ProfileDescription ProfileHeadloss Downstream Velocity Upstream Velocity NormalDepth CriticalDepth ChannelSlope CriticalSlope Infinity ft/s Infinity ft/s 1.62 ft 2.44 ft ft/ft ft/ft 9/25/20142:48:46PM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 2 of 2

24 WorksheetforCaltransDitchwith100-yearFlow ProjectDescription FrictionMethod SolveFor ManningFormula NormalDepth InputData RoughnessCoeficient ChannelSlope LeftSideSlope RightSideSlope Botom W idth Discharge ft/ft 1.00 ft/ft(h:v) 1.00 ft/ft(h:v) 5.00 ft ft³/s Results NormalDepth 1.66 ft Flow Area ft² WetedPerimeter 9.69 ft HydraulicRadius 1.14 ft TopW idth 8.32 ft CriticalDepth 2.50 ft CriticalSlope ft/ft Velocity ft/s VelocityHead 2.68 ft SpecificEnergy 4.34 ft FroudeNumber 2.01 Flow Type Supercritical GVFInputData Downstream Depth 9/25/20143:01:07PM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 1 of 2

25 WorksheetforCaltransDitchwith100-yearFlow GVFInputData Downstream Depth Length NumberOfSteps 0 GVFOutputData Upstream Depth ProfileDescription ProfileHeadloss Downstream Velocity Upstream Velocity NormalDepth CriticalDepth ChannelSlope CriticalSlope Infinity ft/s Infinity ft/s 1.66 ft 2.50 ft ft/ft ft/ft 9/25/20143:01:07PM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 2 of 2

26 WorksheetforCaltransDitchwithOverflow Flows ProjectDescription FrictionMethod SolveFor ManningFormula NormalDepth InputData RoughnessCoeficient ChannelSlope LeftSideSlope RightSideSlope Botom W idth Discharge ft/ft 1.00 ft/ft(h:v) 1.00 ft/ft(h:v) 5.00 ft ft³/s Results NormalDepth 1.74 ft Flow Area ft² WetedPerimeter 9.92 ft HydraulicRadius 1.18 ft TopW idth 8.48 ft CriticalDepth 2.62 ft CriticalSlope ft/ft Velocity ft/s VelocityHead 2.82 ft SpecificEnergy 4.56 ft FroudeNumber 2.02 Flow Type Supercritical GVFInputData Downstream Depth 9/25/20142:54:16PM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 1 of 2

27 WorksheetforCaltransDitchwithOverflow Flows GVFInputData Downstream Depth Length NumberOfSteps 0 GVFOutputData Upstream Depth ProfileDescription ProfileHeadloss Downstream Velocity Upstream Velocity NormalDepth CriticalDepth ChannelSlope CriticalSlope Infinity ft/s Infinity ft/s 1.74 ft 2.62 ft ft/ft ft/ft 9/25/20142:54:16PM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 2 of 2

28 WorksheetforCaltransDitchwithOverflow Flowsand100-yearFlows ProjectDescription FrictionMethod SolveFor ManningFormula NormalDepth InputData RoughnessCoeficient ChannelSlope LeftSideSlope RightSideSlope Botom W idth Discharge ft/ft 1.00 ft/ft(h:v) 1.00 ft/ft(h:v) 5.00 ft ft³/s Results NormalDepth 1.78 ft Flow Area ft² WetedPerimeter ft HydraulicRadius 1.20 ft TopW idth 8.55 ft CriticalDepth 2.67 ft CriticalSlope ft/ft Velocity ft/s VelocityHead 2.88 ft SpecificEnergy 4.65 ft FroudeNumber 2.02 Flow Type Supercritical GVFInputData Downstream Depth 9/25/20143:00:27PM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 1 of 2

29 WorksheetforCaltransDitchwithOverflow Flowsand100-yearFlows GVFInputData Downstream Depth Length NumberOfSteps 0 GVFOutputData Upstream Depth ProfileDescription ProfileHeadloss Downstream Velocity Upstream Velocity NormalDepth CriticalDepth ChannelSlope CriticalSlope Infinity ft/s Infinity ft/s 1.78 ft 2.67 ft ft/ft ft/ft 9/25/20143:00:27PM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 2 of 2

30 WorksheetforCaltransDitchwith100-yearFlow Routed ProjectDescription FrictionMethod SolveFor ManningFormula NormalDepth InputData RoughnessCoeficient ChannelSlope LeftSideSlope RightSideSlope Botom W idth Discharge ft/ft 1.00 ft/ft(h:v) 1.00 ft/ft(h:v) 5.00 ft ft³/s Results NormalDepth 1.63 ft Flow Area ft² WetedPerimeter 9.61 ft HydraulicRadius 1.12 ft TopW idth 8.26 ft CriticalDepth 2.45 ft CriticalSlope ft/ft Velocity ft/s VelocityHead 2.63 ft SpecificEnergy 4.26 ft FroudeNumber 2.01 Flow Type Supercritical GVFInputData Downstream Depth 9/29/20148:58:32AM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 1 of 2

31 WorksheetforCaltransDitchwith100-yearFlow Routed GVFInputData Downstream Depth Length NumberOfSteps 0 GVFOutputData Upstream Depth ProfileDescription ProfileHeadloss Downstream Velocity Upstream Velocity NormalDepth CriticalDepth ChannelSlope CriticalSlope Infinity ft/s Infinity ft/s 1.63 ft 2.45 ft ft/ft ft/ft 9/29/20148:58:32AM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 2 of 2

32 WorksheetforCaltransDouble5'x5'BoxCulvert ProjectDescription FrictionMethod SolveFor ManningFormula Discharge InputData RoughnessCoeficient ChannelSlope NormalDepth Height Botom W idth ft/ft 4.70 ft 5.00 ft 5.00 ft Results Discharge ft³/s Flow Area ft² WetedPerimeter ft HydraulicRadius 1.63 ft TopW idth 5.00 ft CriticalDepth 7.13 ft PercentFul 94.0 % CriticalSlope ft/ft Velocity ft/s VelocityHead 8.19 ft SpecificEnergy ft FroudeNumber 1.87 DischargeFul ft³/s SlopeFul ft/ft Flow Type Supercritical 9/29/20149:04:24AM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 1 of 2

33 WorksheetforCaltransDouble5'x5'BoxCulvert GVFInputData Downstream Depth Length NumberOfSteps 0 GVFOutputData Upstream Depth ProfileDescription ProfileHeadloss AverageEndDepthOverRise 0.00 % NormalDepthOverRise % Downstream Velocity Infinity ft/s Upstream Velocity Infinity ft/s NormalDepth 4.70 ft CriticalDepth 7.13 ft ChannelSlope ft/ft CriticalSlope ft/ft 9/29/20149:04:24AM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 2 of 2

34 WorksheetforCounty8'x6'Channel ProjectDescription FrictionMethod SolveFor ManningFormula NormalDepth InputData RoughnessCoeficient ChannelSlope LeftSideSlope RightSideSlope Botom W idth Discharge ft/ft 2.00 ft/ft(h:v) 2.00 ft/ft(h:v) 5.00 ft 108³/s Results NormalDepth 4.52 ft Flow Area ft² WetedPerimeter ft HydraulicRadius 2.52 ft TopW idth ft CriticalDepth 5.99 ft CriticalSlope ft/ft Velocity ft/s VelocityHead 4.51 ft SpecificEnergy 9.03 ft FroudeNumber 1.81 Flow Type Supercritical GVFInputData Downstream Depth 9/29/20149:25:01AM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 1 of 2

35 WorksheetforCounty8'x6'Channel GVFInputData Downstream Depth Length NumberOfSteps 0 GVFOutputData Upstream Depth ProfileDescription ProfileHeadloss Downstream Velocity Upstream Velocity NormalDepth CriticalDepth ChannelSlope CriticalSlope Infinity ft/s Infinity ft/s 4.52 ft 5.99 ft ft/ft ft/ft 9/29/20149:25:01AM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 2 of 2

36 WorksheetforCounty8'x6'Channelwith100-yearflows ProjectDescription FrictionMethod SolveFor ManningFormula NormalDepth InputData RoughnessCoeficient ChannelSlope LeftSideSlope RightSideSlope Botom W idth Discharge ft/ft 2.00 ft/ft(h:v) 2.00 ft/ft(h:v) 5.00 ft ft³/s Results NormalDepth 4.56 ft Flow Area ft² WetedPerimeter ft HydraulicRadius 2.54 ft TopW idth ft CriticalDepth 6.05 ft CriticalSlope ft/ft Velocity ft/s VelocityHead 4.57 ft SpecificEnergy 9.13 ft FroudeNumber 1.82 Flow Type Supercritical GVFInputData Downstream Depth 9/29/20149:28:56AM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 1 of 2

37 WorksheetforCounty8'x6'Channelwith100-yearflows GVFInputData Downstream Depth Length NumberOfSteps 0 GVFOutputData Upstream Depth ProfileDescription ProfileHeadloss Downstream Velocity Upstream Velocity NormalDepth CriticalDepth ChannelSlope CriticalSlope Infinity ft/s Infinity ft/s 4.56 ft 6.05 ft ft/ft ft/ft 9/29/20149:28:56AM BentleySystems,Inc.HaestadMethodsSolutionCenter BentleyFlowMasterV8i(SELECTseries1) [ ] 27SiemonsCompanyDriveSuite200W Watertown,CT06795USA Page 2 of 2

38 **************************************************************************** RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE Reference: SAN DIEGO COUNTY FLOOD CONTROL DISTRICT 2003,1985,1981 HYDROLOGY MANUAL (c) Copyright Advanced Engineering Software (aes) Ver Release Date: 06/01/2013 License ID 1264 Analysis prepared by: RBF Consulting, A Michael Baker International Company 9755 Clairemont Mesa Blvd. San Diego, CA ************************** DESCRIPTION OF STUDY ************************** * Padre Dam ESA SCP Drainage Study * * 100-Year Offsite Flows * * September 25, 2014 * ************************************************************************** FILE NAME: C:\9MM\EX.DAT TIME/DATE OF STUDY: 14:25 09/25/ USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: SAN DIEGO MANUAL CRITERIA USER SPECIFIED STORM EVENT(YEAR) = HOUR DURATION PRECIPITATION (INCHES) = SPECIFIED MINIMUM PIPE SIZE(INCH) = SPECIFIED PERCENT OF GRADIENTS(DECIMAL) TO USE FOR FRICTION SLOPE = 0.95 SAN DIEGO HYDROLOGY MANUAL "C"-VALUES USED FOR RATIONAL METHOD NOTE: USE MODIFIED RATIONAL METHOD PROCEDURES FOR CONFLUENCE ANALYSIS *USER-DEFINED STREET-SECTIONS FOR COUPLED PIPEFLOW AND STREETFLOW MODEL* HALF- CROWN TO STREET-CROSSFALL: CURB GUTTER-GEOMETRIES: MANNING WIDTH CROSSFALL IN- / OUT-/PARK- HEIGHT WIDTH LIP HIKE FACTOR NO. (FT) (FT) SIDE / SIDE/ WAY (FT) (FT) (FT) (FT) (n) === ===== ========= ================= ====== ===== ====== ===== ======= /0.018/ GLOBAL STREET FLOW-DEPTH CONSTRAINTS: 1. Relative Flow-Depth = 0.60 FEET as (Maximum Allowable Street Flow Depth) - (Top-of-Curb) 2. (Depth)*(Velocity) Constraint = 6.0 (FT*FT/S) *SIZE PIPE WITH A FLOW CAPACITY GREATER THAN OR EQUAL TO THE UPSTREAM TRIBUTARY PIPE.* **************************************************************************** FLOW PROCESS FROM NODE TO NODE IS CODE = >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< ============================================================================ RESIDENTIAL (1. DU/AC OR LESS) RUNOFF COEFFICIENT =.4100 SOIL CLASSIFICATION IS "D" S.C.S. CURVE NUMBER (AMC II) = 82 INITIAL SUBAREA FLOW-LENGTH(FEET) = UPSTREAM ELEVATION(FEET) = DOWNSTREAM ELEVATION(FEET) =

39 ELEVATION DIFFERENCE(FEET) = SUBAREA OVERLAND TIME OF FLOW(MIN.) = WARNING: INITIAL SUBAREA FLOW PATH LENGTH IS GREATER THAN THE MAXIMUM OVERLAND FLOW LENGTH = (Reference: Table 3-1B of Hydrology Manual) THE MAXIMUM OVERLAND FLOW LENGTH IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = SUBAREA RUNOFF(CFS) = 3.06 TOTAL AREA(ACRES) = 1.15 TOTAL RUNOFF(CFS) = 3.06 **************************************************************************** FLOW PROCESS FROM NODE TO NODE IS CODE = >>>>>COMPUTE NATURAL MOUNTAIN CHANNEL FLOW<<<<< >>>>>TRAVELTIME THRU SUBAREA<<<<< ============================================================================ ELEVATION DATA: UPSTREAM(FEET) = DOWNSTREAM(FEET) = CHANNEL LENGTH THRU SUBAREA(FEET) = CHANNEL SLOPE = CHANNEL FLOW THRU SUBAREA(CFS) = 3.06 FLOW VELOCITY(FEET/SEC) = 3.10 (PER LACFCD/RCFC&WCD HYDROLOGY MANUAL) TRAVEL TIME(MIN.) = 5.94 Tc(MIN.) = LONGEST FLOWPATH FROM NODE TO NODE = FEET. **************************************************************************** FLOW PROCESS FROM NODE TO NODE IS CODE = >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< ============================================================================ 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = RESIDENTIAL (1. DU/AC OR LESS) RUNOFF COEFFICIENT =.4100 SOIL CLASSIFICATION IS "D" S.C.S. CURVE NUMBER (AMC II) = 82 AREA-AVERAGE RUNOFF COEFFICIENT = SUBAREA AREA(ACRES) = SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 15.9 TOTAL RUNOFF(CFS) = TC(MIN.) = **************************************************************************** FLOW PROCESS FROM NODE TO NODE IS CODE = >>>>>COMPUTE STREET FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>(STREET TABLE SECTION # 1 USED)<<<<< ============================================================================ UPSTREAM ELEVATION(FEET) = DOWNSTREAM ELEVATION(FEET) = STREET LENGTH(FEET) = CURB HEIGHT(INCHES) = 8.0 STREET HALFWIDTH(FEET) = DISTANCE FROM CROWN TO CROSSFALL GRADEBREAK(FEET) = INSIDE STREET CROSSFALL(DECIMAL) = OUTSIDE STREET CROSSFALL(DECIMAL) = SPECIFIED NUMBER OF HALFSTREETS CARRYING RUNOFF = 2 STREET PARKWAY CROSSFALL(DECIMAL) = Manning's FRICTION FACTOR for Streetflow Section(curb-to-curb) = Manning's FRICTION FACTOR for Back-of-Walk Flow Section = **TRAVEL TIME COMPUTED USING ESTIMATED FLOW(CFS) = STREETFLOW MODEL RESULTS USING ESTIMATED FLOW: STREET FLOW DEPTH(FEET) = 0.48 HALFSTREET FLOOD WIDTH(FEET) = 17.62

40 AVERAGE FLOW VELOCITY(FEET/SEC.) = 8.02 PRODUCT OF DEPTH&VELOCITY(FT*FT/SEC.) = 3.83 STREET FLOW TRAVEL TIME(MIN.) = 2.14 Tc(MIN.) = YEAR RAINFALL INTENSITY(INCH/HOUR) = RESIDENTIAL (7.3 DU/AC OR LESS) RUNOFF COEFFICIENT =.5700 SOIL CLASSIFICATION IS "D" S.C.S. CURVE NUMBER (AMC II) = 87 AREA-AVERAGE RUNOFF COEFFICIENT = SUBAREA AREA(ACRES) = SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 35.7 PEAK FLOW RATE(CFS) = END OF SUBAREA STREET FLOW HYDRAULICS: DEPTH(FEET) = 0.52 HALFSTREET FLOOD WIDTH(FEET) = FLOW VELOCITY(FEET/SEC.) = 8.64 DEPTH*VELOCITY(FT*FT/SEC.) = 4.51 LONGEST FLOWPATH FROM NODE TO NODE = FEET. **************************************************************************** FLOW PROCESS FROM NODE TO NODE IS CODE = >>>>>COMPUTE NATURAL VALLEY CHANNEL FLOW<<<<< >>>>>TRAVELTIME THRU SUBAREA<<<<< ============================================================================ ELEVATION DATA: UPSTREAM(FEET) = DOWNSTREAM(FEET) = CHANNEL LENGTH THRU SUBAREA(FEET) = CHANNEL SLOPE = CHANNEL FLOW THRU SUBAREA(CFS) = FLOW VELOCITY(FEET/SEC) = 6.74 (PER LACFCD/RCFC&WCD HYDROLOGY MANUAL) TRAVEL TIME(MIN.) = 1.44 Tc(MIN.) = LONGEST FLOWPATH FROM NODE TO NODE = FEET. **************************************************************************** FLOW PROCESS FROM NODE TO NODE IS CODE = >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< ============================================================================ 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = RESIDENTIAL (7.3 DU/AC OR LESS) RUNOFF COEFFICIENT =.5700 SOIL CLASSIFICATION IS "D" S.C.S. CURVE NUMBER (AMC II) = 87 AREA-AVERAGE RUNOFF COEFFICIENT = SUBAREA AREA(ACRES) = SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 69.9 TOTAL RUNOFF(CFS) = TC(MIN.) = **************************************************************************** FLOW PROCESS FROM NODE TO NODE IS CODE = >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ============================================================================ ELEVATION DATA: UPSTREAM(FEET) = DOWNSTREAM(FEET) = FLOW LENGTH(FEET) = MANNING'S N = DEPTH OF FLOW IN 36.0 INCH PIPE IS 26.0 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = ESTIMATED PIPE DIAMETER(INCH) = NUMBER OF PIPES = 1 PIPE-FLOW(CFS) = PIPE TRAVEL TIME(MIN.) = 0.14 Tc(MIN.) = LONGEST FLOWPATH FROM NODE TO NODE = FEET. **************************************************************************** FLOW PROCESS FROM NODE TO NODE IS CODE = 51

41 >>>>>COMPUTE TRAPEZOIDAL CHANNEL FLOW<<<<< >>>>>TRAVELTIME THRU SUBAREA (EXISTING ELEMENT)<<<<< ============================================================================ ELEVATION DATA: UPSTREAM(FEET) = DOWNSTREAM(FEET) = CHANNEL LENGTH THRU SUBAREA(FEET) = CHANNEL SLOPE = CHANNEL BASE(FEET) = 5.00 "Z" FACTOR = MANNING'S FACTOR = MAXIMUM DEPTH(FEET) = YEAR RAINFALL INTENSITY(INCH/HOUR) = RESIDENTIAL (7.3 DU/AC OR LESS) RUNOFF COEFFICIENT =.5700 SOIL CLASSIFICATION IS "D" S.C.S. CURVE NUMBER (AMC II) = 87 TRAVEL TIME COMPUTED USING ESTIMATED FLOW(CFS) = TRAVEL TIME THRU SUBAREA BASED ON VELOCITY(FEET/SEC.) = AVERAGE FLOW DEPTH(FEET) = 1.13 TRAVEL TIME(MIN.) = 0.28 Tc(MIN.) = SUBAREA AREA(ACRES) = 6.47 SUBAREA RUNOFF(CFS) = AREA-AVERAGE RUNOFF COEFFICIENT = TOTAL AREA(ACRES) = 76.3 PEAK FLOW RATE(CFS) = END OF SUBAREA CHANNEL FLOW HYDRAULICS: DEPTH(FEET) = 1.15 FLOW VELOCITY(FEET/SEC.) = LONGEST FLOWPATH FROM NODE TO NODE = FEET. ============================================================================ END OF STUDY SUMMARY: TOTAL AREA(ACRES) = 76.3 TC(MIN.) = PEAK FLOW RATE(CFS) = ============================================================================ ============================================================================ END OF RATIONAL METHOD ANALYSIS

42

43 RATIONAL METHOD HYDROGRAPH PROGRAM COPYRIGHT 1992, 2001 RICK ENGINEERING COMPANY RUN DATE 9/25/2014 HYDROGRAPH FILE NAME Text1 TIME OF CONCENTRATION 15 MIN. 6 HOUR RAINFALL 2.7 INCHES BASIN AREA 76.3 ACRES RUNOFF COEFFICIENT 0.57 PEAK DISCHARGE CFS TIME (MIN) = 0 DISCHARGE (CFS) = 0 TIME (MIN) = 15 DISCHARGE (CFS) = 7.1 TIME (MIN) = 30 DISCHARGE (CFS) = 7.3 TIME (MIN) = 45 DISCHARGE (CFS) = 7.7 TIME (MIN) = 60 DISCHARGE (CFS) = 8 TIME (MIN) = 75 DISCHARGE (CFS) = 8.5 TIME (MIN) = 90 DISCHARGE (CFS) = 8.9 TIME (MIN) = 105 DISCHARGE (CFS) = 9.6 TIME (MIN) = 120 DISCHARGE (CFS) = 10.1 TIME (MIN) = 135 DISCHARGE (CFS) = 11.2 TIME (MIN) = 150 DISCHARGE (CFS) = 11.9 TIME (MIN) = 165 DISCHARGE (CFS) = 13.6 TIME (MIN) = 180 DISCHARGE (CFS) = 14.8 TIME (MIN) = 195 DISCHARGE (CFS) = 18 TIME (MIN) = 210 DISCHARGE (CFS) = 20.5 TIME (MIN) = 225 DISCHARGE (CFS) = 30.2 TIME (MIN) = 240 DISCHARGE (CFS) = 55.4 TIME (MIN) = 255 DISCHARGE (CFS) = TIME (MIN) = 270 DISCHARGE (CFS) = 24.2 TIME (MIN) = 285 DISCHARGE (CFS) = 16.2 TIME (MIN) = 300 DISCHARGE (CFS) = 12.7 TIME (MIN) = 315 DISCHARGE (CFS) = 10.6 TIME (MIN) = 330 DISCHARGE (CFS) = 9.2 TIME (MIN) = 345 DISCHARGE (CFS) = 8.2 TIME (MIN) = 360 DISCHARGE (CFS) = 7.5 TIME (MIN) = 375 DISCHARGE (CFS) = 0

44

45

46

47

48

49

50

51 RATIONAL METHOD HYDROGRAPH PROGRAM COPYRIGHT 1992, 2001 RICK ENGINEERING COMPANY RUN DATE 9/25/2014 HYDROGRAPH FILE NAME Text1 TIME OF CONCENTRATION 5 MIN. 6 HOUR RAINFALL 2.7 INCHES BASIN AREA 2.36 ACRES RUNOFF COEFFICIENT 0.64 PEAK DISCHARGE 5.78 CFS TIME (MIN) = 0 DISCHARGE (CFS) = 0 TIME (MIN) = 5 DISCHARGE (CFS) = 0.2 TIME (MIN) = 10 DISCHARGE (CFS) = 0.2 TIME (MIN) = 15 DISCHARGE (CFS) = 0.2 TIME (MIN) = 20 DISCHARGE (CFS) = 0.3 TIME (MIN) = 25 DISCHARGE (CFS) = 0.3 TIME (MIN) = 30 DISCHARGE (CFS) = 0.3 TIME (MIN) = 35 DISCHARGE (CFS) = 0.3 TIME (MIN) = 40 DISCHARGE (CFS) = 0.3 TIME (MIN) = 45 DISCHARGE (CFS) = 0.3 TIME (MIN) = 50 DISCHARGE (CFS) = 0.3 TIME (MIN) = 55 DISCHARGE (CFS) = 0.3 TIME (MIN) = 60 DISCHARGE (CFS) = 0.3 TIME (MIN) = 65 DISCHARGE (CFS) = 0.3 TIME (MIN) = 70 DISCHARGE (CFS) = 0.3 TIME (MIN) = 75 DISCHARGE (CFS) = 0.3 TIME (MIN) = 80 DISCHARGE (CFS) = 0.3 TIME (MIN) = 85 DISCHARGE (CFS) = 0.3 TIME (MIN) = 90 DISCHARGE (CFS) = 0.3 TIME (MIN) = 95 DISCHARGE (CFS) = 0.3 TIME (MIN) = 100 DISCHARGE (CFS) = 0.3 TIME (MIN) = 105 DISCHARGE (CFS) = 0.3 TIME (MIN) = 110 DISCHARGE (CFS) = 0.4 TIME (MIN) = 115 DISCHARGE (CFS) = 0.4 TIME (MIN) = 120 DISCHARGE (CFS) = 0.4 TIME (MIN) = 125 DISCHARGE (CFS) = 0.4 TIME (MIN) = 130 DISCHARGE (CFS) = 0.4 TIME (MIN) = 135 DISCHARGE (CFS) = 0.4 TIME (MIN) = 140 DISCHARGE (CFS) = 0.4 TIME (MIN) = 145 DISCHARGE (CFS) = 0.4 TIME (MIN) = 150 DISCHARGE (CFS) = 0.4 TIME (MIN) = 155 DISCHARGE (CFS) = 0.5 TIME (MIN) = 160 DISCHARGE (CFS) = 0.5 TIME (MIN) = 165 DISCHARGE (CFS) = 0.5 TIME (MIN) = 170 DISCHARGE (CFS) = 0.5 TIME (MIN) = 175 DISCHARGE (CFS) = 0.5 TIME (MIN) = 180 DISCHARGE (CFS) = 0.6 TIME (MIN) = 185 DISCHARGE (CFS) = 0.6 TIME (MIN) = 190 DISCHARGE (CFS) = 0.6 TIME (MIN) = 195 DISCHARGE (CFS) = 0.7 TIME (MIN) = 200 DISCHARGE (CFS) = 0.7 TIME (MIN) = 205 DISCHARGE (CFS) = 0.8 TIME (MIN) = 210 DISCHARGE (CFS) = 0.8 TIME (MIN) = 215 DISCHARGE (CFS) = 1 TIME (MIN) = 220 DISCHARGE (CFS) = 1 TIME (MIN) = 225 DISCHARGE (CFS) = 1.3 TIME (MIN) = 230 DISCHARGE (CFS) = 1.4 TIME (MIN) = 235 DISCHARGE (CFS) = 2.1 TIME (MIN) = 240 DISCHARGE (CFS) = 8 TIME (MIN) = 245 DISCHARGE (CFS) = 5.78 TIME (MIN) = 250 DISCHARGE (CFS) = 1.7 TIME (MIN) = 255 DISCHARGE (CFS) = 1.1 TIME (MIN) = 260 DISCHARGE (CFS) = 0.9 TIME (MIN) = 265 DISCHARGE (CFS) = 0.7 TIME (MIN) = 270 DISCHARGE (CFS) = 0.7 TIME (MIN) = 275 DISCHARGE (CFS) = 0.6 TIME (MIN) = 280 DISCHARGE (CFS) = 0.5 TIME (MIN) = 285 DISCHARGE (CFS) = 0.5 TIME (MIN) = 290 DISCHARGE (CFS) = 0.4 TIME (MIN) = 295 DISCHARGE (CFS) = 0.4 TIME (MIN) = 300 DISCHARGE (CFS) = 0.4 TIME (MIN) = 305 DISCHARGE (CFS) = 0.4 TIME (MIN) = 310 DISCHARGE (CFS) = 0.4 TIME (MIN) = 315 DISCHARGE (CFS) = 0.3 TIME (MIN) = 320 DISCHARGE (CFS) = 0.3 TIME (MIN) = 325 DISCHARGE (CFS) = 0.3 TIME (MIN) = 330 DISCHARGE (CFS) = 0.3 TIME (MIN) = 335 DISCHARGE (CFS) = 0.3 TIME (MIN) = 340 DISCHARGE (CFS) = 0.3 TIME (MIN) = 345 DISCHARGE (CFS) = 0.3 TIME (MIN) = 350 DISCHARGE (CFS) = 0.3 TIME (MIN) = 355 DISCHARGE (CFS) = 0.3 TIME (MIN) = 360 DISCHARGE (CFS) = 0.2 TIME (MIN) = 365 DISCHARGE (CFS) = 0

52 Reference Material

53

54

55

56

Appendix H Amanda Estates Drainage Study

Appendix H Amanda Estates Drainage Study Appendix H Amanda Estates Drainage Study Hunsaker & Associates 2015 Contents 1 Scope... 1 2 Existing Conditions... 1 3 Project Description... 3 4 Methodology... 5 4.1 Hydrology... 5 4.2 Hydraulics...

More information

City Plaza Residential (TPM ) Preliminary Hydrology Report

City Plaza Residential (TPM ) Preliminary Hydrology Report Hydrology Study City Plaza Residential (TPM 2016-127) Preliminary Hydrology Report Orange, Orange County, California Prepared For: Greenlaw Partners 18301 Von Karman Avenue, Suite 250 Irvine, CA 92612

More information

APPENDIX F HYDROLOGY REPORT

APPENDIX F HYDROLOGY REPORT APPENDIX F HYDROLOGY REPORT UCSD LONG RANGE DEVELOPMENT PLAN HYDROLOGY STUDY MAY 2004 PREPARED FOR: UNIVERSITY OF CALIFORNIA, SAN DIEGO 10280 NORTH TORREY PINES ROAD, SUITE 340 LA JOLLA, CA 92093-0965

More information

PRELIMINARY DRAINAGE REPORT FOR THE EDI MASTER PLAN

PRELIMINARY DRAINAGE REPORT FOR THE EDI MASTER PLAN PRELIMINARY DRAINAGE REPORT FOR THE EDI MASTER PLAN April 5, 2015 Wayne W. Chang, MS, PE 46548 Chang Civil Engineering Hydrology Hydraulics Sedimentation P.O. Box 9496 Rancho Santa Fe, CA 92067 (858) 692-0760

More information

PRELIMINARY DRAINAGE STUDY

PRELIMINARY DRAINAGE STUDY PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,

More information

Contents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek

Contents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek Contents SITE LOCATION / DESCRIPTION... 3 WESTPOINTE STORMWATER MANAGEMENT PLAN... 3 THE ENCLAVE AT WESTPOINTE DETENTION POND... 3 Table

More information

LAKE COUNTY HYDROLOGY DESIGN STANDARDS

LAKE COUNTY HYDROLOGY DESIGN STANDARDS LAKE COUNTY HYDROLOGY DESIGN STANDARDS Lake County Department of Public Works Water Resources Division 255 N. Forbes Street Lakeport, CA 95453 (707)263-2341 Adopted June 22, 1999 These Standards provide

More information

HYDROLOGY STUDY PREPARED FOR: MARKHAM PERRIS LLC 302 WEST FIFTH STREET, SUITE 103 SAN PEDRO, CA (310) FOR THE PROJECT:

HYDROLOGY STUDY PREPARED FOR: MARKHAM PERRIS LLC 302 WEST FIFTH STREET, SUITE 103 SAN PEDRO, CA (310) FOR THE PROJECT: HYDROLOGY STUDY PREPARED FOR: MARKHAM PERRIS LLC 302 WEST FIFTH STREET, SUITE 103 SAN PEDRO, CA 90731 (310) 241-2992 FOR THE PROJECT: PERRIS VALLEY COMMERCE CENTER BUILDING PERRIS, CALIFORNIA PROJECT NUMBER:

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion

More information

Hydrology Study. For Bella Terrazza Portion of Lot 1, Block 39, Subdivision of S Tract, Rancho El Cajon El Cajon, CA 92021

Hydrology Study. For Bella Terrazza Portion of Lot 1, Block 39, Subdivision of S Tract, Rancho El Cajon El Cajon, CA 92021 Hydrology Study For Bella Terrazza Portion of Lot 1, Block 39, Subdivision of S Tract, Rancho El Cajon El Cajon, CA 92021 Prepared for Daryl Priest - Priest Development Corporation 124 West Main Street,

More information

Sump Pumps Office procedures for the Drainage & Grading section

Sump Pumps Office procedures for the Drainage & Grading section County of Los Angeles Department of Public Works Building and Safety Division Grading and Drainage Section Sump Pumps Office procedures for the Drainage & Grading section Introduction This manual provides

More information

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth

More information

CONSTRUCTION PLAN CHECKLIST

CONSTRUCTION PLAN CHECKLIST CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted

More information

Appendix G Preliminary Hydrology Study

Appendix G Preliminary Hydrology Study Appendix G Preliminary Hydrology Study Preliminary Hydrology Study VESTING TTM 72608 Long Beach, CA Prepared for: The Long Beach Project, LLC 888 San Clemente, Suite 100 New Port Beach, CA May 28, 2014

More information

STORM DRAINAGE DESIGN MANUAL

STORM DRAINAGE DESIGN MANUAL Appendix I STORM DRAINAGE DESIGN MANUAL by: SUNGATE DESIGN GROUP, P.A. GEN ERAL DESIGN STAN DARDS AN D POLICIES 1. STREET AND LOCAL DRAINAGE Discharge estimates for specified design storms shall be calculated

More information

CUYAHOGA COUNTY ENGINEER

CUYAHOGA COUNTY ENGINEER CUYAHOGA COUNTY ENGINEER DRAINAGE MANUAL Supplement to O.D.O.T. LOCATION and DESIGN MANUAL, Volume 2, Drainage Design, Section 1000 and 1100 May 28, 2010 Revisions to the July 29, 2009 edition are noted

More information

DRAINAGE SUBMITTAL CHECKLIST

DRAINAGE SUBMITTAL CHECKLIST Project Name: Firm Name: Map ID: Engineer: Address: City: State: Zip: Phone Number: Fax Number: Property Owner: Address: City: State: Zip: Reviewed By: Date Received: Date Accepted for Review: The following

More information

APPENDIX J-3. Orcem Stormwater Management and Treatment Facilities Design Summary

APPENDIX J-3. Orcem Stormwater Management and Treatment Facilities Design Summary APPENDIX J-3 Orcem Stormwater Management and Treatment Facilities Design Summary Stormwater Management & Treatment Facilities Design Summary INTRODUCTION KPFF Consulting Engineers has compiled this report

More information

RETENTION BASIN EXAMPLE

RETENTION BASIN EXAMPLE -7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary

More information

THE CROSSROADS IN WINCHESTER 4. DRAINAGE PLAN. 4. Drainage Plan. a. Drainage Plan Description

THE CROSSROADS IN WINCHESTER 4. DRAINAGE PLAN. 4. Drainage Plan. a. Drainage Plan Description THE CROSSROADS IN WINCHESTER 4. DRAINAGE PLAN 4. Drainage Plan a. Drainage Plan Description The Specific Plan area drains naturally into two separate watersheds: approximately 6 percent of the Specific

More information

Preliminary Drainage Analysis

Preliminary Drainage Analysis Preliminary Drainage Analysis Tanimura and Antle Employee Housing Town of Spreckels County of Monterey, California LIB150205 May 29, 2015 Prepared For: Tanimura and Antle Produce Prepared By: 9699 Blue

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Jacobi, Toombs, and Lanz, Inc.

Jacobi, Toombs, and Lanz, Inc. Area 5: Blackiston Mill Road at Dead Man's Hollow Flooding Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations

More information

Technical Memorandum

Technical Memorandum Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum To: Kathy Arnold From: Greg Hemmen, P.E. Company: Rosemont Copper Company Date:

More information

APPENDIX A. Hydraulic Investigations: Cascade Mall at Burlington

APPENDIX A. Hydraulic Investigations: Cascade Mall at Burlington APPENDIX A m SUMMARY REPORT FOR E.I.S. Hydraulic Investigations: Cascade Mall at Burlington July 12, 1982 John E. Norman, P.E. 14779 Northeast 32nd, #A201 Bellevue, WA 98007 (206) 882-1767 92 General A

More information

Preliminary Drainage Study: Town of Hillsboro Pedestrian & Traffic Safety Project Traffic Calming Project UPC# 70587

Preliminary Drainage Study: Town of Hillsboro Pedestrian & Traffic Safety Project Traffic Calming Project UPC# 70587 Preliminary Drainage Study: Town of Hillsboro Pedestrian & Traffic Safety Project Traffic Calming Project UPC# 70587 Introduction: The intent of this study was to perform a preliminary drainage study of

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability

More information

Municipal Stormwater Ordinances Summary Table

Municipal Stormwater Ordinances Summary Table APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which

More information

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1 CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1

More information

CLAY STREET BRIDGE REPLACEMENT

CLAY STREET BRIDGE REPLACEMENT HYDROLOGY /HYDRAULICS REPORT. EL DORADO COUNTY CLAY STREET BRIDGE REPLACEMENT Prepared by: Joseph Domenichelli Domenichelli & Associates 1107 Investment Blvd., Suite 145 El Dorado Hills, California 95762

More information

Introduction to Storm Sewer Design

Introduction to Storm Sewer Design A SunCam online continuing education course Introduction to Storm Sewer Design by David F. Carter Introduction Storm sewer systems are vital in collection and conveyance of stormwater from the upstream

More information

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements This checklist is to be completed and submitted with all Subdivision Applications. The Town reserves

More information

January 20, Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO (303)

January 20, Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO (303) January 20, 2017 Nate Hatleback Project Manager, City of Thornton Development Engineering 9500 Civic Center Drive Thornton, CO 80229 (303) 538-7694 RE: Riverdale Five Retail Drainage Conformance Letter

More information

DRAINAGE STUDY PHASE 2 REPORT HORRY COUNTY STORMWATER DEPARTMENT HIGHWAY 9 & 57 HORRY COUNTY, SC PREPARED FOR: APRIL 07, 2016 J

DRAINAGE STUDY PHASE 2 REPORT HORRY COUNTY STORMWATER DEPARTMENT HIGHWAY 9 & 57 HORRY COUNTY, SC PREPARED FOR: APRIL 07, 2016 J DRAINAGE STUDY PHASE 2 REPORT FOR: HIGHWAY 9 & 57 HORRY COUNTY, SC PREPARED FOR: HORRY COUNTY STORMWATER DEPARTMENT APRIL 07, 2016 Prepared by: Savannah, GA Charleston, SC Myrtle Beach, SC Brunswick, GA

More information

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials.

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials. I. Drainage Report A. Executive Summary - Brief Overview of Project Drainage Design B. Project Description 1. Existing Conditions 2. Proposed Project Conditions 3. Project Justification Narrative - Basin

More information

HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR

HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR 1 INTRODUCTION 1.1 Project Description and Location Isabella Ocean Residences is a residential development to be constructed

More information

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES 4.1 GENERAL REQUIREMENTS 4.1.1 Water and fire protection distribution facilities are to be provided solely for the purpose of supplying potable

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

Warner Robins Stormwater Local Design Manual

Warner Robins Stormwater Local Design Manual Warner Robins Stormwater Local Design Manual Prepared for Houston County City of Warner Robins City of Perry City of Centerville May 17, 2005 Version 4 (As presented with adopted Stormwater Ordinance)

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

MODEL Stormwater Local Design Manual. City of Centerville

MODEL Stormwater Local Design Manual. City of Centerville MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge

More information

HYDROLOGY STUDY LA MIRADA BOULEVARD La Mirada, California

HYDROLOGY STUDY LA MIRADA BOULEVARD La Mirada, California HYDROLOGY STUDY 12000 LA MIRADA BOULEVARD La Mirada, California TTM 73119 Prepared for: The Olson Company 3010 Old Ranch Parkway, Suite 100 Seal Beach, CA 90740 Contact: Mr. Aaron Orenstein (562) 370-9531

More information

Chapter 3 Dispersion BMPs

Chapter 3 Dispersion BMPs Chapter 3 Dispersion BMPs 3.1 BMP L611 Concentrated Flow Dispersion 3.1.1 Purpose and Definition Dispersion of concentrated flows from driveways or other pavement through a vegetated pervious area attenuates

More information

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1 CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm

More information

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK COST EVALUATION FOR ROLLING HILLS AREA WATER MAIN EXTENSION PROFESSIONAL CONSULTING, LLC. Octagon 10, Office Center 1719 Route 10, Suite 225 Parsippany,

More information

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

ENGINEERING REVIEW CHECKLIST City of Mount Clemens

ENGINEERING REVIEW CHECKLIST City of Mount Clemens (To be completed by the Developer s & Submitted with ing Plans) DATE: PROJECT NAME: Site Plan Approved: Date DESIGN ENGINEERING COMPANY: ing Company Contact Information: Name: Phone: Email: Owner Contact

More information

T a b l e o f C o n t e n t s

T a b l e o f C o n t e n t s C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General

More information

Location Drainage Study

Location Drainage Study Location Drainage Study PROJECT ROUTE: LIMITS: MUNICIPALITY/COUNTY: JOB NUMBER: IL 47 at Burlington Road 750ft NW to 750ft SE of IL 47(Burlington), & 1000ft S to 1000ft N of Burlington (IL47) Kane County

More information

DRAFT. Technical Memorandum. Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update. Prepared For:

DRAFT. Technical Memorandum. Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update. Prepared For: DRAFT Technical Memorandum Whitney Road Drainage & Safety Enhancements Phase III Hydraulic Update Prepared For: Pinellas County Department of Environment and Infrastructure Division of Engineering and

More information

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification 7. Introduction This chapter summarizes methods to evaluate runoff conveyance in various street cross sections and curb types in the Town of Castle Rock and identifies acceptable upper limits of street

More information

Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond)

Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond) Chapter 10 Design Examples Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond) Example 2: Filter Design in a commercial development

More information

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established

More information

PART V - STORM DRAIN DESIGN CRITERIA

PART V - STORM DRAIN DESIGN CRITERIA PART V - STORM DRAIN DESIGN CRITERIA A. Hydrology Studies and Hydraulic Analyses 1. Drainage area master plans and calculations are to be submitted with all subdivision improvement plans, permit improvement

More information

PART V - STORM DRAIN DESIGN CRITERIA

PART V - STORM DRAIN DESIGN CRITERIA PART V - STORM DRAIN DESIGN CRITERIA A. Hydrology Studies and Hydraulic Analyses 1. Drainage area master plans and calculations are to be submitted with all subdivision improvement plans, permit improvement

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

4. FISH PASSAGE CONCEPTS

4. FISH PASSAGE CONCEPTS Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group 4. FISH PASSAGE CONCEPTS Fish passage could be improved by rehabilitating the existing fish passage,

More information

3.11 Sand Filter Basin

3.11 Sand Filter Basin 3.11 Sand Filter Basin Type of BMP Priority Level Treatment Mechanisms Maximum Drainage Area Flow-Through Treatment Priority 3 Treatment Control BMP Filtration 25 acres Description The Sand Filter Basin

More information

Attachment D-1: Civil/Structural Scope of Work

Attachment D-1: Civil/Structural Scope of Work Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,

More information

A Stormwater Management Plan and Sediment Control Plan are required for all proposed developments within the City of Richmond.

A Stormwater Management Plan and Sediment Control Plan are required for all proposed developments within the City of Richmond. Engineering Page 3-1 3.0 STORM DRAINAGE 3.1 GENERAL Good drainage is vital to flat urban areas such as Lulu Island. It is essential that every storm sewer must be designed accurately minimizing conflicts

More information

HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS

HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS HYDROLOGY CHECKLIST FOR LAND DISTURBANCE PERMITS Project Name: Project Number: Reviewed By: Date: Telephone: Email: Address all items marked with an X Minimum Submittal Requirements 1. Conceptual Review

More information

EROSION AND SEDIMENT CONTROL STANDARDS CITY OF OVERLAND PARK DRAFT

EROSION AND SEDIMENT CONTROL STANDARDS CITY OF OVERLAND PARK DRAFT A. Authority EROSION AND SEDIMENT CONTROL STANDARDS CITY OF OVERLAND PARK DRAFT 06.15.2005 As set forth in the Overland Park Municipal Code (OPMC), Chapter 16.200, the Director of Planning and Development

More information

WASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS

WASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS GRAVITY SEWER COLLECTION DESIGN This section of the manual contains the Washoe County Community Services Department (CSD) standards for: INDEX Designing Gravity Sewer Collection Facilities ( Sewer Design

More information

Summary of Detention Pond Calculation Canyon Estates American Canyon, California

Summary of Detention Pond Calculation Canyon Estates American Canyon, California July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i

More information

DRAINAGE & DESIGN OF DRAINAGE SYSTEM

DRAINAGE & DESIGN OF DRAINAGE SYSTEM Drainage on Highways DRAINAGE & DESIGN OF DRAINAGE SYSTEM P. R.D. Fernando Chartered Engineer B.Sc.(Hons), M.Eng. C.Eng., MIE(SL) Drainage Requirement of Highway Drainage System Introduction Drainage means

More information

PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS

PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS 39 AUGUST 2005 TABLE OF CONTENTS PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS PAGE SECTION 1 DESIGN CRITERIA 41 SECTION 2 SUBMITTAL 44 SECTION 3 STRUCTURES

More information

Hydrology Study. Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated)

Hydrology Study. Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated) Hydrology Study Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated) Prepared for San Mateo Real Estate & Construction March 9, 21 Rev. 1 11-8-211 Rev.

More information

DRAINAGE REPORT. Project Name: PG&E Gas Operations Technical Training Center Winters, CA. Date: February 4, Prepared by: BKF Engineers

DRAINAGE REPORT. Project Name: PG&E Gas Operations Technical Training Center Winters, CA. Date: February 4, Prepared by: BKF Engineers DRAINAGE REPORT Project Name: PG&E Gas Operations Technical Training Center Winters, CA Date: February 4, 2015 Prepared by: BKF Engineers Client: Pacific Gas & Electric Company This report has been prepared

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

DIVISION 5 STORM DRAINAGE CRITERIA

DIVISION 5 STORM DRAINAGE CRITERIA DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the

More information

STORM WATER MANAGEMENT REPORT

STORM WATER MANAGEMENT REPORT Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek

More information

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm

More information

City of Logan Sanitary Sewer Design Standards

City of Logan Sanitary Sewer Design Standards City of Logan Sanitary Sewer Design Standards 2011 http://www.loganutah.org/public_works/engineering/stdsspecsdesign.cfm Table of Contents PART 1. CITY OF LOGAN SANITARY SEWER SYSTEM DESIGN STANDARDS FOR

More information

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

APPENDIX F RATIONAL METHOD

APPENDIX F RATIONAL METHOD 7-F-1 APPENDIX F RATIONAL METHOD 1.0 Introduction One of the most commonly used procedures for calculating peak flows from small drainages less than 200 acres is the Rational Method. This method is most

More information

SWFWMD RAI No. 1 Comments 8a & 8b Response Appendix G Proposed Drainage Design Criteria

SWFWMD RAI No. 1 Comments 8a & 8b Response Appendix G Proposed Drainage Design Criteria SWFWMD RAI No. 1 Comments 8a & 8b Response Appendix G Proposed Drainage Design Criteria I-75 from North of Fruitville Road to North of University Parkway FPID No: 201032-4-32-01 & 201277-2-32-01 Manatee

More information

MIDAS CREEK PROJECT. FINAL DESIGN REPORT SKR Hydrotech 4/11/2012

MIDAS CREEK PROJECT. FINAL DESIGN REPORT SKR Hydrotech 4/11/2012 2012 MIDAS CREEK PROJECT FINAL DESIGN REPORT SKR Hydrotech 4/11/2012 Executive Summary... 1 Section 1 Introduction... 1 Background Information... 1 Purpose of Study... 1 Scope of Work... 1 Section 2 Description

More information

MEMORANDUM. The general findings of the assessment are as follows:

MEMORANDUM. The general findings of the assessment are as follows: November 28, 2006 MEMORANDUM Project No.: 030009-002-01 To: From: Re: WRIA 31 Planning Unit Steve Germiat, LHG, CGWP, and Timothy J. Flynn, LHG, CWGP Evaluation of Winterizing Existing River Pump/Conveyance

More information

Chapter 8. Inlets. 8.0 Introduction. 8.1 General

Chapter 8. Inlets. 8.0 Introduction. 8.1 General . Introduction This chapter provides criteria and design guides for evaluating and designing storm sewer inlets in the City of Centennial. The review of all planning submittals will be based on the criteria

More information

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc. ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975 Source: Hey and Associates, Inc. DEFINITION A bridge or culvert crossing installed across a stream or watercourse for short-term

More information

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012 Bridge Planning Updates Bridge Planning Practitioners Workshop April 2012 Bridge Website Bridge Website Bridge Website Bridge Website BPG 11 Stormwater Management at Rural Bridges Released July 2010 Documents

More information

SECTION 4 STORM DRAINAGE

SECTION 4 STORM DRAINAGE 4.01 GENERAL SECTION 4 STORM DRAINAGE These standards shall provide minimum requirements for the design of Storm Drainage and related appurtenances within the City of West Sacramento rights of way and

More information

CHAPTER 5 WATER SYSTEM DESIGN STANDARDS

CHAPTER 5 WATER SYSTEM DESIGN STANDARDS CHAPTER 5 WATER SYSTEM DESIGN STANDARDS TABLE OF CONTENTS CHAPTER 5 WATER SYSTEM DESIGN STANDARDS 5.00 Objective Page 1 5.01 Additional Referenced Standards Page 1 5.02 Special Design Problems Page 2 5.03

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any

More information

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES 3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment

More information

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES GRAVITY SEWER COLLECTION DESIGN STANDARDS

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES GRAVITY SEWER COLLECTION DESIGN STANDARDS GRAVITY SEWER COLLECTION DESIGN This section of the manual contains the Washoe County Department of Water Resource s (DWR) standards for: Designing Gravity Sewer Collection Facilities ( Sewer Design Standards

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW7 September 2017 SW7.01 Purpose The purpose of this Chapter is to establish a basis for inlet design utilizing City of Fort Wayne standard inlets and

More information

AGENDA Board of Directors Special Board Meeting Monday, October 30, :30 AM 9300 Fanita Parkway, Santee, CA 92071

AGENDA Board of Directors Special Board Meeting Monday, October 30, :30 AM 9300 Fanita Parkway, Santee, CA 92071 CALL TO ORDER PLEDGE OF ALLEGIANCE AGENDA Board of Directors Special Board Meeting Monday, October 30, 2017 9:30 AM 9300 Fanita Parkway, Santee, CA 92071 OPPORTUNITY FOR PUBLIC COMMENT Opportunity for

More information

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN SITUATED IN THE SW ¼ OF SECTION 18, T.2S., R.67W., OF THE 6 TH P.M. COUNTY OF ADAMS, STATE OF COLORADO PREPARED FOR: Thornton Cornerstone

More information

Local Stormwater Design Manual. City of Fairburn

Local Stormwater Design Manual. City of Fairburn APPENDIX D LOCAL STORMWATER DESIGN MANUAL Local Stormwater Design Manual City of Fairburn May 2008 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS...

More information

California Department of Toxic Substances Control

California Department of Toxic Substances Control Prepared for: California Department of Toxic Substances Control Prepared by: March, 2017 Note: URS Corporation Americas (URS) is under contract with the California Department of Toxic Substances Control.

More information

CORBIN AND NORDHOFF IV. ENVIRONMENTAL IMPACT ANALYSIS ENV EIR F. HYDROLOGY

CORBIN AND NORDHOFF IV. ENVIRONMENTAL IMPACT ANALYSIS ENV EIR F. HYDROLOGY F. HYDROLOGY ENVIRONMENTAL SETTING Project Site The Project Site is located at 19601 Nordhoff Street in the Chatsworth area of the City of Los Angeles, California, within the Chatsworth - Porter Ranch

More information

Project: Developer/Designer: Reviewer:

Project: Developer/Designer: Reviewer: City of Charlottesville, Virginia Engineering Plan Review Checklist (Site Plans, Site Plan Amendments, and Major Subdivisions) 610 East Market Street, Charlottesville, VA 22902 Telephone 434-970-3182;

More information

SUBDIVISION CHECKLIST. Subdivision Name. Prior To Review. Preliminary plan approved by Planning Commission / Council as required.

SUBDIVISION CHECKLIST. Subdivision Name. Prior To Review. Preliminary plan approved by Planning Commission / Council as required. SUBDIVISION CHECKLIST Subdivision Name Account Number Review Engineer Prior To Review Preliminary plan approved by Planning Commission / Council as required. Review fee paid. Statement of Responsibility

More information

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements 4.0 Introduction The requirements presented in this section shall be used to aid the design engineer or applicant in the preparation of drainage reports, drainage studies, and construction drawings for

More information

CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL. New Chevrolet and Cadillac Dealership Jasper, AL

CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL. New Chevrolet and Cadillac Dealership Jasper, AL CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL New Chevrolet and Cadillac Dealership Jasper, AL Andrew Kennedy Homework #6 July 24, 2007 0 Table of Contents Table of

More information

Appendix J: The Project Stormwater Control Plan by Lea & Braze Engineering, Inc.

Appendix J: The Project Stormwater Control Plan by Lea & Braze Engineering, Inc. Appendix J: The Project Stormwater Control Plan by Lea & Braze Engineering, Inc. STORMWATER CONTROL PLAN 23 LOT SUBDIVISION ON PROCTOR ROAD CASTRO VALLEY, CALIFORNIA Owner/Developer: Hue Tran 4584 Ewing

More information