MANAGING CONSTRUCTION SCHEDULES. Kelly Selman, P.E. Dallas District. Date. Dallas District October 10, 2017

Size: px
Start display at page:

Download "MANAGING CONSTRUCTION SCHEDULES. Kelly Selman, P.E. Dallas District. Date. Dallas District October 10, 2017"

Transcription

1 MANAGING CONSTRUCTION SCHEDULES Kelly Selman, P.E. Dallas District Dallas District October 10, 2017 Date

2 Types of Schedules Contract Time Schedule A+B Bidding Lane Rental Preliminary Schedule Project Baseline Schedule Progress Update Schedule Time Impact Analysis Dallas District October 10,

3 FHWA Definition: Importance of Contract Time Schedule Contract time is the maximum time allowed in the contract for completion of all work contained in the contract documents When Contract Time is Too short Impacts on bid prices from inefficiency to schedule resources, procure materials, etc. When Contract Time is Too long Inconvenience to the traveling public from construction activities taking forever Dallas District October 10,

4 8.3 Computation of Contract Time for Completion The number of working days is established by the Contract. For Contracts with work orders, the number of working days is established in each work order. Working day charges will begin when work begins as prescribed in Article 8.1., Prosecution of Work. Working day charges will continue in accordance with the Contract. Upon request, the Engineer will provide the conceptual time determination schedule to the Contractor for informational purposes only. The schedule assumes generic resources, production rates, sequences of construction and average weather conditions based on historic data. The Department will not adjust the number of working days and milestones, if any, due to differences in opinion regarding any assumptions made in the preparation of the schedule or for errors, omissions, or discrepancies found in the Department s conceptual time determination schedule. Dallas District October 10,

5 Contract Time Determination (CTD) Guidelines Based on full evaluation of all factors involved: Complexity of the project Typical contractor organization likely to bid on the project Sequence of construction Traffic impacts Local field and weather conditions Overriding factor: Project completion urgency Dallas District October 10,

6 Essential Elements of a CTD Schedule Scope of work Identify the scope of work for scheduling needs Establish production rates Standard rates of production activities Adaption of rates for specific projects Establishing constraints Procurement / fabrication of long lead items Needs of the adjacent businesses / communities that will impact the work Restrictions on nighttime work High profile events Sequencing work to avoid obstacles (utilities, oil wells) Dallas District October 10,

7 Essential Elements of a CTD Schedule (cont.) Impacts of lane-closure restrictions on scheduling and logic Calendars Allow contractors flexibility to work 6 days Seasonal limitations Weather, temperature, daylight hours, etc. Letting month, start of the construction activities Affects from adjacent projects Third party construction projects, i.e., city projects Dallas District October 10,

8 Minimizing Impacts on Traffic: Lane Rental Fees for Lane Closures Use lane rental fees and liquidated damages for lane closures on construction projects as appropriate Establish Time periods in the contract for different volumes of traffic Time Period A = Peak hours of traffic Time Period B = Midday volumes Time Period C/D = Lowest traffic volumes (typically overnight or weekends) Time Period A lane closures are not allowed, but a dollar value is assigned in the event that an overnight lane closure is not picked up on time. These do not come out of the bank balance, but are deducted monthly from the estimate as liquidated damages. Dallas District October 10,

9 Dallas Horseshoe Project Lane Rental Fee Charges: Dallas District October 10,

10 Minimizing Impacts on Traffic - Lane Rental Fees for Lane Closures Dallas Horseshoe Project Example: Full westbound I-30 closure from 11pm Friday to 8am Saturday (9 Hours): 9 hours of Time Period C 9 x $5,048 = $45,432 Full northbound I-35E closure from 10pm Friday to 6am Saturday (8 Hours): 3 hours of Time Period C 5 hours of Time Period D (3 x $5,048) + (5 x $2,019) = $25,239 Total lane rental fees deducted from the bank balance = $70,671 Dallas District October 10,

11 Minimizing Impacts on Traffic - Lane Rental Fees for Lane Closures Dallas Horseshoe Project: Work Accomplished in 8 / 9 Hours: Set 7 Tx62 girders over westbound I-30 Set 8 Tx62 girders over northbound I-35E Placed temporary shoring and work platforms Removed bridge overhangs Removed existing high mast illumination pole Placed 1000 lf of portable concrete barrier Enhanced work volume from lane closures Dallas District October 10,

12 Dallas Horseshoe Project Example Lane Rental Fee Charges: Work Completed that evening: Dallas District October 10,

13 Dallas Horseshoe Project Dallas District October 10,

14 Multiple Crews Mobilized During a Freeway Closure Dallas District October 10,

15 A + B Bidding: Dallas Experience Summary - DAL A+B Projects Eng. Estimate Winning Bid Letting Year County Job # CCSJ # Daily RUC $ For 3 out of 4 contracts, the A part of the bid was under the Engineer s cost estimate For 4 out of 4 contracts, the B part was under the Engineer s duration estimate Competitive bidding yields optimization of cost + time savings # of Bids A (Bid Items $) Time Estimate (Days) A+B encourages potential bidders to develop carefully developed execution plans for achieving cost-time optimization B (Days DRUC $) A (Bid Items $) The road users and the traveling public benefit from both time and cost savings % O/U (A) Time Estimate (Days) % O/U (B) Jan Ellis $3,300 7 $71,229, Days $2,409,000 $61,704,500-13% 687 Days -6% May Dallas $20, $59,686, Days $14,040,000 $59,011,998-1% 468 Days -33% Jun Dallas $50,000 5 $72,032, Days $39,000,000 $78,786,039 9% 618 Days -14% Jul Denton $4,000 7 $36,799, Days $2,760,000 $35,041,150-5% 650 Days -6% Dallas District October 10,

16 Baseline Schedule The Contractor s Plan of Work Prepared by the Contractor and reviewed by TxDOT staff for compliance Must include all contract work Must follow the Traffic Control Plan Must have proper calendars including added weather days, holidays, etc. Clear and logical critical path / longest path Long lead / Fabricated items included Use the full number of contract days A+B resolves issues with contract days Dallas District October 10,

17 Monthly Schedule Updates Follows the approved Baseline Schedule Ensures the schedule is updated to show all work that has been completed Calendars updated to show actual days worked Review logic changes Did they affect the Critical Path? Use of Constraints Is the schedule overly constrained? Dallas District October 10,

18 Schedule Review Checklist for Dallas District Dallas District Review Checklist for Monthly CPM Schedule Updates CSJ: Schedule Name: IH-35E (Denton)-08 Highway: IH 35E Data Date: 8/31/2017 County: Denton Reviewer: Tom Smith Contractor: ABC Contractor Review Date: 9/26/2017 Yes No N/A Item Comments Is the schedule a separate file from the original detailed (baseline) schedule file (or any other previous schedule files)? Is the schedule calculated using retained logic? Is there a hammock activity to calculate contract time and is it associated with a calendar that accurately reflects how time will be charged? If the schedule shows a change in TCP, has a formal request letter been submitted? If the schedule is a "revision" as defined in the specifications, has a written request by the Contractor been submitted non-work and approved? Are calendars set up logically, and do they consider non-work holidays and weather? Do activities use appropriate calendars? Have the calendars been updated to reflect actual days worked/not worked? Are activities properly coded and/or can the schedule be organized logically using the coding structure? Have resources been updated to reflect actual conditions and is resource loading fully implemented? Is/are the critical path(s) clearly discernable and accurately identified? Is the use of constraints kept to a minimum and is there no imposed finish date? Other than start and finish activities, do all activities have predecessors and successors? See attached comment #1 Are there no new/deleted activities? (if no, list) See attached comment #2 If there are new/deleted activities, are they justifiable? If there are any new activities, have the appropriate calendars, activity codes, and resources been associated? Have the relationships been edited accordingly? Do the actual start and actual finish dates correspond with the dates the work was performed in the field? (especially for critical activities in this schedule or previous schedules) See attached comment #3 Are the percentages complete calculated using the given production rates? If there is any out of sequence work, is it acceptable? See attached comment #4 Has there been no gain/loss in time since the last schedule update (use PSSR form; investigate and document the cause for any gain/loss)? See attached comment #5 Has Claim Digger been used to compare this schedule with previous updates? See attached comment #6 Are there no other concerns with the schedule? Dallas District October 10,

19 Schedule Review Project Schedule Status Report Project: STP 2017(083) MM CSJ: Exhibit "B" Project Schedule Status Report County: Denton Contractor: ABC Contractor Schedule Name Contract Days: 442 Data Date Completion Date Working Days Rem Duration Percent Complete Workweek: 6 Day Calendar Days Working Days Days Granted by TxDOT Period Gain/Loss Cumulative Gain/Loss Period Gain/Loss Cumulative Gain/Loss Calendar Days Working Days Explanation for Loss/Gain Feb-17 1-Aug Baseline Schedule Submittal (Not approved) Mar Aug Baseline (Rev 2) Schedule Submittal (Approved) Apr Dec % IH35E May Dec % IH-35E (Denton) Jun Dec % IH-35E (Denton) Jul Jan % IH-35E (Denton) Aug Feb % The project lost 89 workdays due to the delay in pipe delivery for the waterline, added activities, and the change in schedule logic by the contractor in which the Phase 1 Step 1 SB Frontage Roadwork could not begin until the waterline was installed. No Change this update period. The project gained 13 workdays due to the contractor beginning to install the new water line sooner than previously planned last update period. The project lost 36 workdays due to the procurement of the new water line valves. The project lost a total 26 workdays this update perior due to the 1) lack of progress on the new water line - 8 days; 2) the contractor making schedule logic changes to the water line installation - 13 days; and 3) the contractor adding a new water line installation activity (Activity No. A Install Water System Sta New Water System) - 5 days. Schedule Name: The unique filename assigned to the original schedule, updates and revisions. Data Date: The calendar date when the project has been updated and the network revised, statussed or progressed. Completion Date: The unconstrained, unrestricted calculated project completion date as calculated by Primavera Project Planner (P6). Working Days: Calculated by P6 using a hammock activity and with an updated calendar reflecting actual time charges. Period Loss/Gain: The number of calendar days or working days the project completion date has been delayed (positive figures) or accelerated in current period. Cumulative Loss/Gain: The total number of calendar days or working days the project completion date has been delayed or accelerated since the original schedule. Days Granted by TxDOT: Enter the contract days added by Change Order. Dallas District October 10,

20 Time Impacts Analysis Contractor submits a Notice of Potential Impact and utilizes the 4-Step process Step 1 Establish the Status of the project before the impact. Step 2 Predict the effect of the impact on the schedule. Step 3 Track the effects of the impact on the schedule Step 4 Establish the status of the project after the impact. All four steps must be completed to analyze the impact on the project. Dallas District October 10,

21 Summary Scheduling is a tool to help achieve project objectives and meet the public s expectations for timely project delivery Ensure accurate documentation of project progress Engagement of the AO and District staff in: Developing/reviewing contract time schedules Reviewing Baseline schedules Reviewing progress update schedules Dallas District October 10,

Schedule Guidance Document

Schedule Guidance Document Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

INNOVATIVE CONTRACTING GUIDELINES

INNOVATIVE CONTRACTING GUIDELINES Office of Construction and Innovative Contracting INNOVATIVE CONTRACTING GUIDELINES A+B Bidding Lane Rentals Incentives/ Disincentives Liquidated Savings Design-Build Warranties Pay for Performance No

More information

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation

More information

Estimating and Scheduling

Estimating and Scheduling Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202 Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 June 28, 2017 ADDENDUM NUMBER: TWO (2) TITLE: Riverview Water Main Extension Phase

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax:

More information

HAWTHORNE AND THAD WATER & WASTEWATER IMPROVEMENTS ITB #124D 16F CITY OF IRVING ADDENDUM # 1 MAY 10, 2016

HAWTHORNE AND THAD WATER & WASTEWATER IMPROVEMENTS ITB #124D 16F CITY OF IRVING ADDENDUM # 1 MAY 10, 2016 HAWTHORNE AND THAD WATER & WASTEWATER IMPROVEMENTS ITB #124D 16F CITY OF IRVING ADDENDUM # 1 MAY 10, 2016 1. THIS ADDENDUM IS HEREBY MADE AS PART OF THIS CONTRACT SPECIFICATION. THIS ADDENDUM IS ISSUED

More information

Jacksonville District Master

Jacksonville District Master USACE / NAVFAC / AFCEC / NASA UFGS-01 32 01 (August 2008) Change 1-08/13 --------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (July 2007) UNIFIED FACILITIES GUIDE

More information

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain: Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The

More information

Selecting Projects for Accelerated Bridge Construction

Selecting Projects for Accelerated Bridge Construction Selecting Projects for Accelerated Bridge Construction In January of 2017, the Engineering Services and Operations Division Directors issued a memo instructing Districts to consider accelerated bridge

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Electric Forward Market Report

Electric Forward Market Report Mar-01 Mar-02 Jun-02 Sep-02 Dec-02 Mar-03 Jun-03 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 May-05 Aug-05 Nov-05 Feb-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Apr-08 Jun-08 Sep-08 Dec-08

More information

SECTION NETWORK ANALYSIS SCHEDULES (NCA)

SECTION NETWORK ANALYSIS SCHEDULES (NCA) PART 1- GENERAL 1.1 DESCRIPTION: SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULES (NCA) SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Coordinate this section with the paragraphs of FAR

More information

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

Operations Management

Operations Management 17-1 Project Management Operations Management William J. Stevenson 8 th edition 17-2 Project Management CHAPTER 17 Project Management McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

Project Engineers and Supervisors Conference. CPM Scheduling

Project Engineers and Supervisors Conference. CPM Scheduling Project Engineers and Supervisors Conference March 15 th and 16 th 2010 CPM Scheduling Prepared and Presented By Project Engineers and Supervisors Conference Benefits of CPM Scheduling Lessons Learned

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

Consulting Newsletter

Consulting Newsletter Spring 2014 Newsletter In this, our 2014 Spring newsletter, are 2 articles. The first article is Programme Review and Acceptance. Our second article is titled, Acceleration Roger Gibson June 2014 PROGRAMME

More information

Construction Administration Updates

Construction Administration Updates Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director Construction Administration Updates Clint Bishop Construction Administration Updates Construction Administration Updates

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

Administration Division Public Works Department Anchorage: Performance. Value. Results.

Administration Division Public Works Department Anchorage: Performance. Value. Results. Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

Managing Schedule Change

Managing Schedule Change Managing Schedule Change Ted Douglas, CCP, PSP, FAACE CPM Construction Conference Orlando, Florida January 11, 2017 Managing Schedule Change Outline Change Drivers Contract Changes Clause Schedule Change

More information

WINDFARM DEVELOPMENT. FM 1847, Pharr District, Cameron County. Date. Footer Text

WINDFARM DEVELOPMENT. FM 1847, Pharr District, Cameron County. Date. Footer Text WINDFARM DEVELOPMENT FM 1847, Pharr District, Cameron County Table of Contents 1 2 3 4 Location Map Windfarm Planning Activities Windfarm Construction Closeout/Negotiations 5 Lessons Learned 2 Location

More information

Project Forecast Survey Results Good Scheduling Practices June 2016

Project Forecast Survey Results Good Scheduling Practices June 2016 Good Scheduling Practices 5 June 6 Good Scheduling Practices 5 June 6 Executive Summary There is a saying failing to plan is planning to fail, but what if the plan itself is a failure? The scheduling of

More information

Dulles Corridor Metrorail Project. Project Labor Agreement. Executive Summary. 1.0 Background. 2.0 Project labor agreements (PLAs)

Dulles Corridor Metrorail Project. Project Labor Agreement. Executive Summary. 1.0 Background. 2.0 Project labor agreements (PLAs) Executive Summary In 2009, the Federal Government, through Executive Order 13502, reversed an earlier order and now recommends that all federally funded projects with a total installed cost greater than

More information

Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director,

Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director, Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director, Risk Integration Management Pty Ltd Presentation Outline

More information

Document No: SB002-P3 Revision No: Last Updated: April

Document No: SB002-P3 Revision No: Last Updated: April BRIEF People often are confused with the term - Out-of-Sequence, and use them in inappropriate ways. While we talk about Out-of-Sequence, we also need to discuss the difference between Retained Logic and

More information

PUBLIC HEARING LOOP 9

PUBLIC HEARING LOOP 9 PUBLIC HEARING LOOP 9 From Interstate (I)-35E to I-45 Dallas and Ellis Counties, Texas CSJ: Loop 2964-10-005 9: I-35E to I-45 Tuesday, June 20, 20, 2017 2017 Public Hearing Introductions ELECTED & PUBLIC

More information

State of Ohio. Department of Transportation ~ Innovative Contracting Manual

State of Ohio. Department of Transportation ~ Innovative Contracting Manual State of Ohio Department of Transportation ~ Innovative Contracting Manual 4/10/2006 Copies of this manual and reference materials may be obtained at: Ohio Department of Transportation Division of Construction

More information

Maryland Transportation Authority (MDTA)

Maryland Transportation Authority (MDTA) Maryland Transportation Authority (MDTA) I-95 Major Deck and Superstructure Rehabilitation South of the Fort McHenry Tunnel Northeast Bridge Preservation Partnership Conference September 20, 2016 David

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Fifth Quarterly Update to the Estimate to Complete May 2013 - July 2013 Published October 2013 Table of Contents Section 1 - Executive Summary... 3 Quarterly

More information

Scope Management Guideline January, 2016

Scope Management Guideline January, 2016 Scope Management Guideline January, 2016 Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Scope Management Overview... 1 Charter... 4 Scope Statement...

More information

2017 ACEC/WisDOT Transportation Improvement Conference February 2017

2017 ACEC/WisDOT Transportation Improvement Conference February 2017 2017 ACEC/WisDOT Transportation Improvement Conference February 2017 Scott Lawry, P.E., WisDOT Bureau Project Development Fred Schunke, P.E., WisDOT Bureau Project Development Cheryl Simon, P.E., WisDOT

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile

More information

City of Denton On-system Project Status Report Prepared by ITS

City of Denton On-system Project Status Report Prepared by ITS City of Denton On-system Project Status Report Prepared by ITS December 2017 PROJECTS FM 2181 North-South... page 2 US 377/Fort Worth Drive... page 3 FM 2499, Section 5... page 5 IH-35E/Mayhill/FM 2499

More information

Report to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016

Report to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016 Report to the Finance Committee 2015 Comprehensive Annual Financial Report Prepared by the Office of Finance April 2016 Audit Opinion date April 11, 2016 Unmodified or clean audit opinion on financial

More information

Sunrise Project South I-205 Corridor Improvement Project

Sunrise Project South I-205 Corridor Improvement Project Sunrise Project South I-205 Corridor Improvement Project January 24, 2007 Sunrise and I-205 Project Summary Conclusions Sunrise Scoping Study Key Results South I-205 Scoping Study Key Results South I-205

More information

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

Andrew Avalon, P.E., PSP

Andrew Avalon, P.E., PSP Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Andrew Avalon,

More information

Pattullo Bridge Replacement Project. Cost Report

Pattullo Bridge Replacement Project. Cost Report Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

Business Practice Manual for The Transmission Planning Process

Business Practice Manual for The Transmission Planning Process Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...

More information

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SECTION: WSIP CONSTRUCTION MANAGEMENT APPROVED: PROCEDURE NO.: 015 DATE: 08I'4I09 TITLE: CONSTRUCTION

More information

A Structured Approach to Minimum Cost Recovery Scheduling

A Structured Approach to Minimum Cost Recovery Scheduling A Structured Approach to Minimum Cost Recovery Scheduling Chris Carson, PSP Project Controls Manager Alpha Corporation Norfolk, Virginia Email: chris.carson@alphacorporation.com Background Project management

More information

PROJECT MANUAL BID DOCUMENT 95% REVIEW CHECKLIST PROJECT BID NO EPWU PEM. CONSULTANT SUBMITTED ON / / as a 95% (A) original

PROJECT MANUAL BID DOCUMENT 95% REVIEW CHECKLIST PROJECT BID NO EPWU PEM. CONSULTANT SUBMITTED ON / / as a 95% (A) original PROJECT BID NO EPWU PEM CONSULTANT SUBMITTED ON / / as a 95% (A) original RESUBMITTED ON / / as a 95% (B) revision 1.0 FRONT COVER 1.1 1.2 1.3 1.4 Title begins with location key words, otherwise with program/project

More information

Final Design Guideline

Final Design Guideline Final Design Guideline May, 2016 July, 2011 Check the Capital Project Delivery website to ensure this is the current version Table of Contents Purpose... 1 Introduction... 1 FD Support... 1 Roadway and

More information

Miami River Freight Improvement Plan Financial Management Number:

Miami River Freight Improvement Plan Financial Management Number: Miami River Commission January 8, 2018 Miami, FL Carlos A. Castro, District Freight Coordinator Miami River Freight Improvement Plan Financial Management Number: 437946-1-22-01 Agenda Study Background

More information

Chapter 18. Quality Assurance and Quality Control

Chapter 18. Quality Assurance and Quality Control Chapter 18 Quality Assurance and Quality Control The following are changes, additions or deletions to the January 2016, Topic #625-000-007, Plans Preparation Manual (PPM), for use on Turnpike projects

More information

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404

PROJECT INFORMATION REPORT INFORMATION. Date: February 25, Owner s Rep: Alrich Lynch. 123 Project Address Drive, Savannah GA 31404 LDG Consulting Providing Orientation, Direction, and Execution to the Design, Construction, and Real Estate Industries REPORT INFORMATION Date: February 25, 2015 Owner s Rep: Alrich Lynch Electronic Copy:

More information

State Project No.: , N501 Contract ID Number: C DB66

State Project No.: , N501 Contract ID Number: C DB66 Request for Proposal Letter of Submittal Design-Build I-64 Pavement Rehabilitation From: Hampton Roads Bridge Tunnel (East Abutment) To: Little Creek Road Bridge (West Abutment) Norfolk, Virginia State

More information

Understanding Import & Export with NetPoint 4.2

Understanding Import & Export with NetPoint 4.2 Understanding Import & Export with NetPoint 4.2 Eric Lowther PMA Consultants 1 Primary Differences Regarding Import/ Export CPM Tools F9 and Early/Late Dates Float & Total Float Gantt Charts (Waterfall

More information

Traffic Division Public Works Department Anchorage: Performance. Value. Results.

Traffic Division Public Works Department Anchorage: Performance. Value. Results. Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements. Direct Services Design, operate and maintain the

More information

National Capital Region Congestion Report

National Capital Region Congestion Report NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD National Capital Region Congestion Report 2nd Quarter 2014 Metropolitan Washington Council of Governments 777 North Capitol Street, N.E., Suite 300,

More information

DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 2 FOR

DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 2 FOR DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 2 FOR TAXIWAY Y BRIDGE REINFORCEMENT FOR GROUP VI AIRCRAFT CONTRACT NO. 9500498 November 30, 2017 The Request

More information

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show THIS SLIDE REQUIRES NEW PICTURE Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 8.4 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Administration Evacuation

More information

(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.

(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged. Inspiration Water & Sewer Adjustments Bid No. 16-217-05-17 Page 3 of 26 Addendum #1, RFB 16-217-05-17, May 13, 2016 be furnished to all bidders as an amendment to the solicitation, if such information

More information

STATE PERSONNEL SYSTEM

STATE PERSONNEL SYSTEM DIVISION OF HUMAN RESOURCE MANAGEMENT POLICY GUIDELINE STATE PERSONNEL SYSTEM SUBJECT: Emergency Conditions: Administering Essential Services Performed During Facility Closures and Administering Extraordinary

More information

COUNTY OF SAN JOAQUIN

COUNTY OF SAN JOAQUIN August 1, 2012 COUNTY OF SAN JOAQUIN General Services Department 44 North San Joaquin Street, Suite 590 Stockton, California 95202-2778 (209) 468-3357, Fax (209) 468-2186 GABRIEL E. KARAM Director Capital

More information

Ronald J. Rider, MBA

Ronald J. Rider, MBA Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Ronald J. Rider,

More information

Retained Logic and Progress Override in Primavera P6

Retained Logic and Progress Override in Primavera P6 By Pat Hendricks TEPCO, LLC www.tepco.us Retained Logic and Progress Override The retained logic and progress override setting can drastically affect a schedule depending on which is used, so understanding

More information

UNDERSTANDING PMIS: RIDE, PATCHING, AND OTHER FACTORS. Darlene C. Goehl, P.E. Dist. Pavement-Materials Engr. TxDOT - BRY

UNDERSTANDING PMIS: RIDE, PATCHING, AND OTHER FACTORS. Darlene C. Goehl, P.E. Dist. Pavement-Materials Engr. TxDOT - BRY UNDERSTANDING PMIS: RIDE, PATCHING, AND OTHER FACTORS Darlene C. Goehl, P.E. Dist. Pavement-Materials Engr. TxDOT - BRY Outline 1 What is PMIS 3 2 3 Data Collection Distresses 4-6 7-9 4 How Scores are

More information

CONSTRUCTION PROCEDURES HANDBOOK

CONSTRUCTION PROCEDURES HANDBOOK CONSTRUCTION PROCEDURES HANDBOOK SECTION VI SUBSECTION K DATE CONSTRUCTION OPERATIONS UTILITY COORDINATION 1. Utility Agreements Utility Agreements Modifications (UAMs) authorizing utility construction

More information

IT BACK TO KDOT, EVEN IF NOT BIDDING.

IT BACK TO KDOT, EVEN IF NOT BIDDING. Promptly sign and date on the line below, then EMAIL IT BACK TO KDOT, EVEN IF NOT BIDDING. Or you may still FAX IT TO the Estimating Section at (785) 296-0999. Any instructions not followed will result

More information

IH 820 Corridor Improvement Study Randol Mill Road To North SH 121 Interchange. Public Meeting. Thursday April 4, 2013

IH 820 Corridor Improvement Study Randol Mill Road To North SH 121 Interchange. Public Meeting. Thursday April 4, 2013 IH 820 Corridor Improvement Study Randol Mill Road To North SH 121 Interchange Public Meeting Thursday April 4, 2013 1 Project Contacts: TxDOT-Fort Worth District John R. Tillinghast, P.E. IH 820 Project

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 10 Congestion and Marginal Losses Congestion and Marginal Losses The Locational Marginal Price (LMP) is the incremental price of energy at a bus. The LMP at any bus is made up of three components:

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

Facilities Management. FM Key Performance Indicators

Facilities Management. FM Key Performance Indicators Facilities Management FM Key Performance Indicators September 21, 2017 Facilities Management Key Volume Indicators Key Volume FM Change Evanston Chicago Full Time Equivalent (FTE) 369 +5 304 65 Acres 296

More information

TxDOT Chip Seal Over Geotextile Fabric. Research Project

TxDOT Chip Seal Over Geotextile Fabric. Research Project TxDOT Chip Seal Over Geotextile Fabric Research Project Project Background FHWA Pavement Preservation International Scanning Tour Identified potential use of Treatment in the U.S. TxDOT agrees to conduct

More information

WAIKOLOA RESERVOIR NO. 1 EARTHQUAKE REPAIR PROJECT Information Sheet

WAIKOLOA RESERVOIR NO. 1 EARTHQUAKE REPAIR PROJECT Information Sheet March 5, 2015 WAIKOLOA RESERVOIR NO. 1 EARTHQUAKE REPAIR PROJECT Information Sheet Overview The purpose of this Project is to repair damages to the Waikoloa Reservoir No. 1 which were sustained during

More information

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4. Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Testinside

More information

Facilities Management. FM Key Performance Indicators

Facilities Management. FM Key Performance Indicators Facilities Management FM Key Performance Indicators August 15, 2017 Facilities Management Key Volume Indicators Key Volume FM Change Evanston Chicago Full Time Equivalent (FTE) 364 +11 299 65 Acres 296

More information

Accelerated and Innovative Bridge Construction In Washington State

Accelerated and Innovative Bridge Construction In Washington State Accelerated and Innovative Bridge Construction In Washington State Bijan Khaleghi Bijan.Khaleghi@WSDOT.WA.Gov Washington State Department of Transportation Bridge and Structures Office Olympia Washington

More information

Accelerated Bridge Construction (ABC) National Status

Accelerated Bridge Construction (ABC) National Status Accelerated Bridge Construction (ABC) National Status by Mary Lou Ralls, P.E., Ralls Newman, LLC 88 th Annual Transportation Short Course Texas A&M University College Station, Texas Session: Construction

More information

Route 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing

Route 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing Project Reston Avenue to Jarrett Valley Drive Public Hearing Nicholas J. Roper, P.E. District Project Development Engineer Email: nicholas.roper@vdot.virginia.gov Phone: (703)259-1953 Agenda 7:00-7:15

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.05 EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 The bid opening date is Thursday March 15, 2018 at 11:00 a.m. The following changes

More information

District of North Vancouver Construction Traffic Management Plan Guidelines

District of North Vancouver Construction Traffic Management Plan Guidelines District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction

More information

Richard J. Long, P.E.

Richard J. Long, P.E. Richard J. Long, P.E. LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Construction Contract

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

September 30, Re: Formal Case No. 1116

September 30, Re: Formal Case No. 1116 ^pepco A PHI Comparnj Andrea H. Harper Associate General Counsel EP1132 701 Ninth Street, NW Suite 1100. 10*^ Floor Washington. DC 20068 202 331-6649 202 331-6767 Fax ahharper'

More information

PROJECT SHOWING MINUTES

PROJECT SHOWING MINUTES PROJECT SHOWING MINUTES Jones Branch Connector Project No. (NFO) 8102-029-065, P101, R201, C501, B628, B627, B629, D610 UPC No. 103907 September 7, 2016 10:00 a.m. Fairfax County EMS Simulation Center

More information

REPORT Condition D19 Permanent Noise Barriers

REPORT Condition D19 Permanent Noise Barriers REPORT Condition D19 Permanent Noise Barriers Project Name: WestConnex New M5 Project number: 15.7020.2597 Revision date: 19/08/2016 Revision: 1 Document Approval Rev. Prepared by Reviewed by Recommended

More information

National Capital Region Congestion Report

National Capital Region Congestion Report Item #6 TPB Technical Committee May 2, 2014 NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD National Capital Region Congestion Report 4th Quarter 2013 (DRAFT) Metropolitan Washington Council of Governments

More information

Solar Power Realities

Solar Power Realities Solar Power Realities Supply-Demand Characteristics, Storage and Capital Costs by Peter Lang Abstract This paper provides a simple analysis of the capital cost of solar power and energy storage sufficient

More information

Short Span Steel Bridges

Short Span Steel Bridges Short Span Steel Bridges MINK 2015 Michael Barker, PE University of Wyoming & SSSBA Bridge Technology Center Outline of Today s Presentation SSSBA & espan140 Design Competitiveness of Steel Bridges Economics

More information

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) SPECIAL PROVISION August 31, 2009 PROJECT # S-R399(42) PROJECT # S-R399(59) PIN # 6697/7236 SECTION 03253S BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) Add Section 03253S: PART

More information

Facilities Management. FM Key Performance Indicators

Facilities Management. FM Key Performance Indicators Facilities Management FM Key Performance Indicators October 20, 2017 Facilities Management Key Volume Indicators Key Volume FM Change Evanston Chicago Full Time Equivalent (FTE) 370 +1 301 69 Acres 296

More information

New Hope Crushed Stone. Monthly Update Solebury Communications Group October 2017

New Hope Crushed Stone. Monthly Update Solebury Communications Group October 2017 New Hope Crushed Stone Monthly Update Solebury Communications Group October 2017 Tom Wolf, Governor Patrick McDonnell, Secretary October 2017 Project Status STATUS AS OF: October 31, 2017 PROJECT START

More information

Statement of Work Tree Planting Services 202 Parkway, Montgomery County

Statement of Work Tree Planting Services 202 Parkway, Montgomery County Statement of Work Tree Planting Services 202 Parkway, Montgomery County SPECIAL PROVISIONS Governing Specifications Service Requirements Purchase Order Validity Period Option to Renew Option to Extend

More information

Advantages of Financing Continuous Commissioning As An Energy Conservation Retrofit Measure

Advantages of Financing Continuous Commissioning As An Energy Conservation Retrofit Measure Advantages of Financing Continuous Commissioning As An Energy Conservation Retrofit Measure Guanghua Wei, P.E. Malcolm Verdict, C.E.M Joseph T. Martinez Energy Systems Laboratory, 3581 TAMU Texas A&M University

More information

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS Edwin Castro CNEE Guatemala Viena, september 2009 What is the reason to develop this model? In our own electricity market

More information

Click to edit Master title style I N D U S T R Y D AY O C T O B E R 1,

Click to edit Master title style I N D U S T R Y D AY O C T O B E R 1, Click to edit Master title style I N D U S T R Y D AY O C T O B E R 1, 2 0 1 4 Welcome Nevada Governor Brian Sandoval Nevada DOT Director Rudy Malfabon, PE Goals Goals Obtain the best value for the costs

More information

2017 LOSS PREVENTION / RISK MANAGEMENT SEMINARS APRIL 20, 2017 DALLAS, TEXAS

2017 LOSS PREVENTION / RISK MANAGEMENT SEMINARS APRIL 20, 2017 DALLAS, TEXAS 2017 LOSS PREVENTION / RISK MANAGEMENT SEMINARS APRIL 20, 2017 DALLAS, TEXAS Theft Viruses Crypto Ransomware Locker MANAGING YOUR CYBER RISKS Suspicious Cloud Cloud 08.02.2017 Email Storage Storage 1ST

More information

December 19, 2012 ADDENDUM NO. 11. To Prospective Bidders and Others on:

December 19, 2012 ADDENDUM NO. 11. To Prospective Bidders and Others on: 601096-12 December 19, 2012 ADDENDUM NO. 11 To Prospective Bidders and Others on: Technical/Price Proposals Postponed To: Thursday, January 17, 2013 @ 2:00 PM Transmitting the following Documents and Clarifications:

More information

Whittier Bridge/I-95 Improvement Project. Public Information Meeting

Whittier Bridge/I-95 Improvement Project. Public Information Meeting Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project

More information

Project Location. Pensacola Bay Bridge Replacement Design Build 03/02/16. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer

Project Location. Pensacola Bay Bridge Replacement Design Build 03/02/16. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer Pensacola Bay Bridge Replacement Design Build Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer Project Location 2 1 GENERAL PROJECT INFORMATION Replacement of the structurally deficient

More information