New North Atlanta High School Weekly Construction Report October 26, 2012 THIS WEEK. Lakeside Building: Completion in July, 2013

Size: px
Start display at page:

Download "New North Atlanta High School Weekly Construction Report October 26, 2012 THIS WEEK. Lakeside Building: Completion in July, 2013"

Transcription

1 THIS WEEK October 19, 2012 October 26, 2012 Lakeside Building: Completion in July, 2013 Floating scaffolding nearing completion (top left). Drywall being hung with insulation on the 2 nd floor (top right). Third floor walls being framed around in wall plumbing rough in (bottom left). Third floors HVAC units set and connected to the overhead duct (bottom right). NNAHS Weekly Progress Report October 26, 2012 Page 1

2 Lakeside Building Cont d: Completion in July, 2013 Existing CEP equipment being removed from the Lakeside Building by crane (top left). New window openings cut into the 4 th floor exterior west face of Lakeside (top right). Lakeside CMU shafts and existing duct being demolished (bottom left). SLC stair opening cut into the 11 th floor (bottom right). NNAHS Weekly Progress Report October 26, 2012 Page 2

3 Hillside Building: Completion in December, 2013 JE Dunn Construction sign hanging from the Hillside Building (top left). Explosives and connections wired to the Hillside columns (top right). Trailer with explosives staged in the Hillside Building (bottom left) Column wired with explosives (bottom right). NNAHS Weekly Progress Report October 26, 2012 Page 3

4 Hillside Building Cont d: Completion in December, 2013 Dynamite gel ready for cap and casing (top left). Dynamite being placed in casing (top right). Test blast performed on column (bottom). NNAHS Weekly Progress Report October 26, 2012 Page 4

5 Lean Construction: Finish trades participating in JE Dunn s second Lean Construction Boot Camp for NNAHS (below). NNAHS Weekly Progress Report October 26, 2012 Page 5

6 NEXT WEEK October 22, 2012 October 29, st floor glazing will continue being installed. 2 nd floor drywall will continue being hung. Floating scaffolding will finish being erected and moved under the Lakeside Building. Wall framing will continue on the 2 nd and 3 rd floors. MEP in wall rough in will finish on the 2 nd floor and begin on the 3 rd floor. MEP overhead rough in will continue on the 3 rd and 4 th floors. Wall layout and MEP layout will continue on the 3 rd, 4 th, and 5 th floors. Window systems will continue being installed on the 2 nd, 3 rd, and 4 th floors. 11 th floor SLC stair cutout will be finished. Asbestos abatement will begin on the 9 th floor of the Lakeside Building. Interior demolition will continue on the upper floors of Lakeside. The Hillside Building remains (rubble and debris) will begin being hauled off site for recycling and reuse. Site-work layout for the new Hillside Building will begin. KEY UPCOMING DATES Next OAC Meeting 10:00 am at jobsite office Hillside Building Implosion 10/27/12 NNAHS Weekly Progress Report October 26, 2012 Page 6

7 IMPLOSION The much anticipated implosion of the old IBM building on the New North Atlanta High School project is almost here! If you would like to join us this Saturday, October 27 th, here are the specifics: Everyone must arrive before 7:00am (6:30 is recommended). For safety reasons, the gates will be closed and locked at 7:00am sharp, no exceptions. There will be personnel directing traffic onsite, but you can reference the below logistics plan for the parking and viewing area locations. The actual implosion blast is planned for approximately 7:30am if the winds and weather cooperate. If the winds are not favorable, it will be delayed and nobody will be allowed to leave until the implosion has occurred. The implosion will be loud. Bring ear plugs if you have them (if you forget, we have some extra onsite). The implosion will produce a lot of dust, which may get pushed towards the viewing area. For those of you who may not be able to attend the viewing, here is a link to our webcam which has live video feed. NNAHS Weekly Progress Report October 26, 2012 Page 7

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main

More information

Southwest Health System Construction Newsletter October 7, 2017

Southwest Health System Construction Newsletter October 7, 2017 Southwest Health System A Week in Review Patient Wing Interior sheetrock is 99% complete in the Patient Wing proper Taping and finishing is following behind sheetrock, and Nunn is preparing rooms for paint

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

Mueller Laboratory Renovation. Technical Report #2 By Mark Jackson Construction Management Option 10/17/14

Mueller Laboratory Renovation. Technical Report #2 By Mark Jackson Construction Management Option 10/17/14 Mueller Laboratory Renovation Technical Report #2 By Mark Jackson Construction Management Option 10/17/14 1 Table of contents Executive Summary 3 Project Schedule 5 Detailed Estimate 8 Site Layout Planning

More information

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:

More information

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION SECTION 02 41 14 SELECTIVE BUILDING DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for systematic removal of site improvements or portions of exterior and interior of buildings

More information

OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS. Schedule "C"

OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS. Schedule C OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS Schedule "C" Building Code All Ready To Move (RTM) Homes are built according to the Alberta Building Code and National Building Code. Please note that

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 024116 - STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Project Status Update & Progress Report

Project Status Update & Progress Report UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update

More information

PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C

PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No. 20140101C CONSTRUCTION ESTIMATE AND PROJECT BUDGET Dated June 7. 2014 Estimated Cost HARD COSTS $ 1,560,284 Core Renovations (Toilet Rooms, Ceilings

More information

Richmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION

Richmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION SECTION 024119 SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Mission Bernal Campus

Mission Bernal Campus Mission Bernal Campus Weekly Construction Bulletin #150 Construction Update March 6, 2017 March 12, 2017 The Mission Bernal Campus Weekly Bulletin intendeds to help inform members of the community about

More information

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C 2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM

More information

IMMC SCHOOL OF NURSING BUILDING IMPLOSION

IMMC SCHOOL OF NURSING BUILDING IMPLOSION IMMC SCHOOL OF NURSING BUILDING IMPLOSION Demolition of the School of Nursing Building is underway. Phase 1 is being razed with traditional methods of demolition. However, Phase 2 Demo is a good candidate

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of: 02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"

More information

Southwest Health System Construction Newsletter October 21, 2017

Southwest Health System Construction Newsletter October 21, 2017 Southwest Health System A Week in Review Patient Wing Asphalt Base was completed this week in the north section of the parking lot Sheetrock is substantially complete and everything should be ready for

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

Project Time Management. Course Objectives. Outline

Project Time Management. Course Objectives. Outline Project Time Management Institute for Facilities Management Course Objectives Explore the challenges with managing a campus project schedule Review industry practices and contractual issues Discuss incentive

More information

TODAY S DATE: January 24th, 2019

TODAY S DATE: January 24th, 2019 TODAY S DATE: January 24th, 2019 Top Left: View of metal panels and louvers on the South elevation. Top Right: Interior storefront glass is getting installed on the atrium side of 1st floor labs. Bottom

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School

More information

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr

More information

Phase B. Site

Phase B. Site Michigan Avenue, NW Washington, DC 2000 Technical Report 2 Table of Contents Executive Summary 2 A. Detailed Project Schedule...3 B. Site Layout Planning.... C. Assemblies Estimate..5 D. Detailed Mechanical

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

DIVISION 02 SELECTIVE DEMOLITION

DIVISION 02 SELECTIVE DEMOLITION DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary

More information

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018 Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior

More information

Technical Assignment 2

Technical Assignment 2 Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

TODAY S DATE: November 15th, 2018

TODAY S DATE: November 15th, 2018 TODAY S DATE: November 15th, 2018 Top Left: Twin City Glass is working on setting the curtain wall at the main entrance on the South side of the Addition. Top Right: TCG has almost finished glazing the

More information

Building Construction Occupations

Building Construction Occupations Job Ready Assessment Blueprint Building Construction Occupations Test Code: 2011 / Version 01 Measuring What Matters Specific Competencies and Skills Tested in this Assessment: Safety and General Knowledge

More information

Volume 7 November Additions and Alterations to: Tinicum Elementary School Palisades School District. T&W Project 0737

Volume 7 November Additions and Alterations to: Tinicum Elementary School Palisades School District. T&W Project 0737 Volume 7 November 2009 Additions and Alterations to: Tinicum Elementary School Palisades School District Monthly Progress Report T&W Project 0737 Additions and Alterations to Tinicum Elementary School

More information

Building Construction Occupations

Building Construction Occupations Job Ready Assessment Blueprint Building Construction Occupations Test Code: 3011 / Version 01 Measuring What Matters Specific Competencies and Skills Tested in this Assessment: Safety and General Knowledge

More information

JOB DESCRIPTION. JOB TITLE: Project Superintendent DATE: 2/1/10. DIVISION: Construction EXEMPT STATUS: Exempt

JOB DESCRIPTION. JOB TITLE: Project Superintendent DATE: 2/1/10. DIVISION: Construction EXEMPT STATUS: Exempt JOB DESCRIPTION JOB TITLE: Project Superintendent DATE: 2/1/10 DIVISION: Construction EXEMPT STATUS: Exempt REPORTS DIRECTLY TO: Vice President-Construction POSITION OBJECTIVE A Model Construction Project

More information

Residential Construction

Residential Construction Structural Insulated Panels (SIPs) are modern engineered building components that combine great structural strength with outstanding energy performance. ERECTING A STRUCTURALLY SOUND THERMALLY EFFICIENT

More information

MONOLITHIC R.C. WALLS

MONOLITHIC R.C. WALLS Building Constructions 6. 3rd Lecture MONOLITHIC R.C. WALLS Dr. Bálint Petró Prof. Emeritus Gergely Dobszay Lecturer Zsuzsanna Fülöp Lecturer Dr. Miklós Kézdi Miklós Svéd Formwork Types for In-situ Reinforced

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

Cinema-Dining Terrace Expansion. Suburbia, USA. Technical Report II. Image Courtesy of The Whiting-Turner Contracting Company.

Cinema-Dining Terrace Expansion. Suburbia, USA. Technical Report II. Image Courtesy of The Whiting-Turner Contracting Company. Cinema-Dining Terrace Expansion Suburbia, USA Technical Report II Image Courtesy of The Whiting-Turner Contracting Company Nicholas Kline Cinema-Dining Terrace Expansion 10/16/2013 Executive Summary This

More information

INSULATION. Success with 2015 IECC Northeast & Mid-Atlantic. Techtips for Builders & Trades

INSULATION. Success with 2015 IECC Northeast & Mid-Atlantic. Techtips for Builders & Trades Success with 2015 IECC Northeast & Mid-Atlantic Techtips for Builders & Trades COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED TEMPLATE 2015.1.0 PAGE 1 NORTHEAST For vented attics, install wind baffles

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle

More information

Feature Zone IECC 2009 IECC

Feature Zone IECC 2009 IECC Feature Zone 3 2006 IECC 2009 IECC Window U factor 0.65 0.50 Skylight U factor 0.65 0.65 Window SHGC 0.40 0.30 Ceiling R value 30 30 Wood frame R value 13 13 Mass wall R value 1 5 5/8 Floor R value 19

More information

Project #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50

Project #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50 Project #1139 Budget #82 $ Budgeted $ Billed to Date $ Paid to Date $ Due 210,087.68 120,979.20 120,979.20 77,158.50 Deposit Paid Deposit Due Phase I: Project Programming and Research $ Budgeted $ Billed

More information

Carpentry/Carpenter CIP Task Grid

Carpentry/Carpenter CIP Task Grid Secondary Task List 100 SAFETY/OCCUPATIONAL ORIENTATION 101 Identify and follow all basic safety practices and procedures. 102 Identify and follow all lab safety practices and procedures. 103 Identify

More information

Modular Wood Framing Goes Vertical

Modular Wood Framing Goes Vertical Modular Wood Framing Goes Vertical By: Troy Bean, P.E., S.E. DCI Engineers January 2013 The Wood Products Council is a Registered Provider with. Credit(s) earned on completion of this program will be reported

More information

BUILDING CODES & DESIGN CRITERIA

BUILDING CODES & DESIGN CRITERIA BUILDING CODES & DESIGN CRITERIA Adopted Building Codes: 2006 International Building Code (IBC) 2006 International Residential Code (IRC) 2006 International Mechanical Code (IMC) 2006 International Plumbing

More information

Wisconsin Technical College System. Curriculum Standards & Program Design Summary CARPENTRY (CONSTRUCTION) APPRENTICE

Wisconsin Technical College System. Curriculum Standards & Program Design Summary CARPENTRY (CONSTRUCTION) APPRENTICE Program Information Program Curriculum Standards & Program Design Summary 1 CARPENTRY (CONSTRUCTION) APPRENTICE Carpenters construct, erect, install or repair structures and fixtures made of wood; concrete

More information

National Utility Contractors Association 2016 Member Activation Form Specialty Contractor Companies

National Utility Contractors Association 2016 Member Activation Form Specialty Contractor Companies Join By June 15 Become an Official Founding Member Don t miss out on this special recognition for your company! National Utility Contractors Association 2016 Member Activation Form Specialty Contractor

More information

CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report

CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350

More information

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General

More information

Job Ready Assessment Blueprint. Test Code: 4012 / Version: 01 Building Trades Maintenance

Job Ready Assessment Blueprint. Test Code: 4012 / Version: 01 Building Trades Maintenance Blueprint Test Code: 4012 / Version: 01 Building Trades Maintenance Specific Competencies and Skills Tested in this Assessment: Safety Use tools and equipment safely Demonstrate electrical safety Respond

More information

A. The extent of Selective Demolition Work is that Work necessary, and required to facilitate the new construction indicated.

A. The extent of Selective Demolition Work is that Work necessary, and required to facilitate the new construction indicated. Project No. El611-0l SECTION 02 41 00 - SELECTIVE DEMOLITION PART1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for

LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Physical Plant Division Engineering and Architectural Services Department

More information

Quality Safety Service Value

Quality Safety Service Value Quality Safety Service Value Generating Value Through Sustainable Asset & Energy Solutions MOPAC is a multi-specialty services contractor focused on the design, construction and preservation of commercial,

More information

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations

More information

Smelter Removal & Reclamation Frequently Asked Questions

Smelter Removal & Reclamation Frequently Asked Questions Smelter Removal & Reclamation Frequently Asked Questions Email your questions to us at: info@resolutioncopper.com Q: Why is Resolution Copper taking the Magma Smelter complex down? A: The removal and cleanup

More information

1. Before selective demolition, Owner will remove the following items:

1. Before selective demolition, Owner will remove the following items: SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Demolition and removal of selected portions of building or structure. 2. Demolition and removal of selected

More information

REDLAND TECHNOLOGY CENTER

REDLAND TECHNOLOGY CENTER REDLAND TECHNOLOGY CENTER 540 Gaither Road, Rockville, MD Shawn Pepple Construction Management Technical Assignment #3 November 21, 2008 Dr. Messner TABLE OF CONTENTS 3.1 Executive Summary.. 3 3.2 Constructability

More information

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction Technical Report II The Office Building Rendering courtesy of DAVIS Brett Miller Dr. Gannon Construction 10/16/2013 Executive Summary This technical report analyzes key features of The Office Building

More information

Kitchen Remodel Estimator. Contact Info: Project Summary: Design. Demo

Kitchen Remodel Estimator. Contact Info: Project Summary: Design. Demo Kitchen Remodel Estimator Thinking about remodeling your kitchen? If you would like a free bid from Excel Builders, we have provided a list of questions that will need to be filled out with detail in order

More information

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary

More information

WORK INSTRUCTIONS COLORADO SPRINGS NNO FACILITY EQUIPMENT SALVAGE PLAN VERIZON WIRELESS PROJECT MANAGER PATRICK SKILLEN PREPARED FOR:

WORK INSTRUCTIONS COLORADO SPRINGS NNO FACILITY EQUIPMENT SALVAGE PLAN VERIZON WIRELESS PROJECT MANAGER PATRICK SKILLEN PREPARED FOR: 4323 ARROWSWEST DRIVE COLORADO SPRINGS, CO 80907-3451 PREPARED FOR: VERIZON WIRELESS PROJECT MANAGER PATRICK SKILLEN MARCH 10, 2009 VERIZON WIRELESS PAGE 1 PART 1 - GENERAL 1.01 PROJECT DESCRIPTION VzW

More information

PROPOSAL NOTE: ALL SURFACES TO BE PROTECTED AT ALL TIMES. WE ALSO REMOVE AND REHANG DRAPES, MOVE ALL FURNITURE AND PUT IT BACK WHEN JOB COMPLETED.

PROPOSAL NOTE: ALL SURFACES TO BE PROTECTED AT ALL TIMES. WE ALSO REMOVE AND REHANG DRAPES, MOVE ALL FURNITURE AND PUT IT BACK WHEN JOB COMPLETED. 11424 Mercury Dr. Manassas, VA 20112 Thursday, May 13, 2010 George & Carol Proctor 65 Main St. Sperryville, VA 22740 (555) 555-9999 Phone: (703) 738-4674 Fax: (703) 349-3831 CUSTOMER ID: GP012010 PROJECT

More information

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Project Status September Report 15, 2009 #13 April 27, 2012 TABLE OF CONTENTS SECTION 1: PROJECT SUMMARY SECTION 2: OVERALL PROJECT SCHEUDLE

More information

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017 Woodbridge Redevelopment Update CLC Meeting #6 Wednesday, December 13, 2017 1. Introductions Agenda 2. Project Updates 3. Construction Updates Progress to Date What s Happening Now 3 Month Schedule 4.

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities

More information

Table Air Barrier and Insulation Inspection Component Criteria

Table Air Barrier and Insulation Inspection Component Criteria Table 40.4. Air Barrier and Insulation Inspection Component Criteria NUMBER COMPONENT CRITERIA Air barrier and thermal barrier Exterior thermal envelope insulation for framed walls is installed in substantial

More information

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows: ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan

More information

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION

More information

Concrete. Conveying Systems. Doors, Windows & Interiors

Concrete. Conveying Systems. Doors, Windows & Interiors Concrete Concrete : Cast-in-Place Concrete Concrete : Cementitious Decks Concrete : Concrete Accessories Concrete: Concrete Block & Brick Concrete : Concrete Coring & Sawing Concrete : Concrete Curing

More information

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. July 2016 Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000

More information

NARRATIVE REPORT 1.0 BUILDING INFORMATION 2.0 ASBESTOS SURVEY INFORMATION

NARRATIVE REPORT 1.0 BUILDING INFORMATION 2.0 ASBESTOS SURVEY INFORMATION NARRATIVE REPORT 1.0 BUILDING INFORMATION Askanase Hall was originally constructed in 1966; a 1975 addition extended the building to the north and the west. Although specific information could not be located,

More information

Technical Assignment 2 Cost and Schedule Analysis October 24, 2008

Technical Assignment 2 Cost and Schedule Analysis October 24, 2008 Technical Assignment 2 and Schedule Analysis October 24, 2008 Meghan Graber Construction Management Dr. Riley Integrated Science Center College of William & Mary Williamsburg, Virginia Graber TABLE OF

More information

CITY OF FORT COLLINS BUILDING STANDARDS SPECIFICATIONS/DIV 8

CITY OF FORT COLLINS BUILDING STANDARDS SPECIFICATIONS/DIV 8 CITY OF FORT COLLINS BUILDING STANDARDS SPECIFICATIONS/DIV 8 L. Division 8 - Doors and Windows 1. Windows 2. Doors a. Glazing shall be energy efficient (ie; Low-E) and have an insulated glass certification

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND DIRECTIVE 1A-8 Issue date: October 2014 CONSTRUCTABILITY REVIEW 1. The Consultant shall be required to perform a constructability review with the College, Fund s Design Coordinator, Fund s Construction

More information

HEALTHCARE OF THE FUTURE INTEGRATED CARE + FACILITY DESIGN

HEALTHCARE OF THE FUTURE INTEGRATED CARE + FACILITY DESIGN HEALTHCARE OF THE FUTURE INTEGRATED CARE + FACILITY DESIGN PROJECT INTRODUCTION PROGRAM + DESIGN RESPONSE Built-to-Suit prototype Medical Clinic was designed in response to tenant s extensive development

More information

Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders. insulation

Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders. insulation Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders insulation Copyright 2014 Advanced Energy. All Rights Reserved TEch Tips: 1. Install insulation to meet the 2012

More information

High Stakes. Solutions of Special Projects:

High Stakes. Solutions of Special Projects: Category 2: Meeting the Challenge of a Difficult Job Specialty Contractor Specialty Contractor: Colorado Cleanup Corporation (CCC) Project Name: Monarch Casino Garage Implosion High Stakes After months

More information

Comcast Panorama Tenant Finish

Comcast Panorama Tenant Finish Comcast Panorama Tenant Finish Displaying a nationally known logo throughout an entire building is the goal that ICI set out to achieve when taking on the Comcast Tenant Finish project. This $1.7 million

More information

SECTION DEMOLITION WASTE MANAGEMENT AND DISPOSAL

SECTION DEMOLITION WASTE MANAGEMENT AND DISPOSAL SECTION 017418 PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

CARBON MONOXIDE ALARMS

CARBON MONOXIDE ALARMS 7100 147 th Street West Telephone (952) 953-2588 Apple Valley, MN 55124-9016 www.cityofapplevalley.org BUILDING PERMITS - Are required for all porch additions. PORCH INFORMATION ELECTRICAL PERMITS - Are

More information

Outdoor + Switchgear, Walk-in Equipment Buildings Low & Medium Voltage NEMA 3R

Outdoor + Switchgear, Walk-in Equipment Buildings Low & Medium Voltage NEMA 3R Outdoor + Switchgear, Walk-in Equipment Buildings Low & Medium Voltage NEMA 3R Product Brochure www.apt-power.com 433 N. 36 th Street PROVIDING A COMPREHENSIVE Lafayette, IN 47905 www.apt-power.com 433

More information

The Chapin School Expansion and Renovation Project Community Construction Committee September 6th, :30 p.m. - 8:00 p.m.

The Chapin School Expansion and Renovation Project Community Construction Committee September 6th, :30 p.m. - 8:00 p.m. The Chapin School Expansion and Renovation Project Community Construction Committee September 6th, 2017 6:30 p.m. - 8:00 p.m. Meeting purpose & elected officials represented PURPOSE OF MEETING: Continue

More information

Chapter 14 - Air Sealing

Chapter 14 - Air Sealing Chapter 14 - Air Sealing Contents Chapter 14 - Air Sealing... 14-1 Pre-Mechanicals Activities... 14-3 Insulate Bathtub Enclosures... 14-3 Insulate Double Walls and Chases... 14-3 Pre-Inspection Checklist...

More information

Building Permit Application

Building Permit Application Building Permit Application Building Use: Single Family Dwelling Duplex / Semi-detached 3+ Units Commercial Temporary Class of Work Other Building Address: Legal: Lot: Block: Plan: Subdivision: Applicant

More information

IMPACT NOTIFICATION PLAN #57 (3/5/2018 3/25/2018)

IMPACT NOTIFICATION PLAN #57 (3/5/2018 3/25/2018) 6 IMPACT NOTIFICATION PLAN #57 The following areas will be affected the greatest: ACC WP Level 2 & 3 Emergency Department SPECIAL NOTES: - Click here to watch our progress via the webcam. SCHEDULED SHUTDOWNS:

More information

TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018

TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018 TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018 The February 5, 2018 meeting of the Manchester Building Committee was held in the Manchester Room at the Town Hall. Manchester Building

More information

Building Architecture

Building Architecture The front of the building consists of the three story town homes with facades to remain, as well as one leg of the condominium tower that reaches the street. The main condo portion of the building is L

More information

Technical Assignment 1

Technical Assignment 1 Technical Assignment 1 Construction Project Management Oct 5 th, 2009 Shane Flynn Construction Management Dr. Magent 700 6 th Street Washington, DC Table of Contents 1. Executive Summary.......3 2. Project

More information

STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION SKI PATROL HUT PROJECT #: CAP 1804

STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION SKI PATROL HUT PROJECT #: CAP 1804 STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION PROJECT #: CAP 1804 FRANCONIA NOTCH STATE PARK FRANCONIA, NEW HAMPSHIRE BID SET 8/4/2017 DRAWING LIST:

More information

Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process

Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process NC Energy Code Requirements ENERGY STAR and NC Energy Code in Alignment RESNET Standards HERS Index A scoring

More information

Adolfson & Peterson Construction, Megan Bond; ; CATEGORY 3: Meeting the Challenge of a Difficult Job General Contractor

Adolfson & Peterson Construction, Megan Bond; ; CATEGORY 3: Meeting the Challenge of a Difficult Job General Contractor Vanguard Classical School K-12 Adolfson & Peterson Construction, Megan Bond; 303-326-5842; mbond@a-p.com CATEGORY 3: Meeting the Challenge of a Difficult Job General Contractor Overview Statement: Every

More information

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Project Status September Report 15, 2009 #15 June 27, 2012 TABLE OF CONTENTS SECTION 1: PROJECT SUMMARY SECTION 2: OVERALL PROJECT SCHEUDLE

More information

Construction Update. April 2016

Construction Update. April 2016 Construction Update April 2016 Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Overview 1. Recent Activity 2. Upcoming Activity 3. Safety & Labor

More information

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014 New Stadium Project Construction Activity Mitigation Program January 22, 2014 Construction Mitigation Plan Introduction It is the primary goal of HHRM, JV to minimize negative effects on traffic and the

More information

MPA Project No. L1429-C1 Project Title: Terminal C Enhancements Location: Logan International Airport

MPA Project No. L1429-C1 Project Title: Terminal C Enhancements Location: Logan International Airport MPA Project No. L1429-C1 Project Title: Terminal C Enhancements Location: Logan International Airport RESPONSES TO QUESTIONS and/or RFI s Date: 6/1/2018 The attention of Contractors submitting Filed Sub-Bids

More information

Page(s)

Page(s) Robert M. Leicht Construction Management Option Advisor: Dr. John Messner Bldg: Smithsonian Institution Patent Office building Washington, DC 10/4/04 Technical Assignment 1 Executive Summary: The Smithsonian

More information

229 Rehoboth Avenue Telephone P.O. Box 1163 Fax

229 Rehoboth Avenue Telephone P.O. Box 1163 Fax Building & Licensing City of Rehoboth Beach 229 Rehoboth Avenue Telephone 302-227-6181 P.O. Box 1163 Fax 302-227-4504 Rehoboth Beach, Delaware 19971 www.cityofrehoboth.com NOTICE TO CONTRACTORS BUSINESS

More information

GH Phipps Construction Co. OAC 17D Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, :00 AM

GH Phipps Construction Co. OAC 17D Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, :00 AM GH Phipps Construction Co. OAC 17D5780 - Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, 2017 10:00 AM Meeting ID 003 Subject Weekly OAC Meetings Location 6000 Spine Rd #101,

More information