New North Atlanta High School Weekly Construction Report October 26, 2012 THIS WEEK. Lakeside Building: Completion in July, 2013
|
|
- Marianna Cannon
- 6 years ago
- Views:
Transcription
1 THIS WEEK October 19, 2012 October 26, 2012 Lakeside Building: Completion in July, 2013 Floating scaffolding nearing completion (top left). Drywall being hung with insulation on the 2 nd floor (top right). Third floor walls being framed around in wall plumbing rough in (bottom left). Third floors HVAC units set and connected to the overhead duct (bottom right). NNAHS Weekly Progress Report October 26, 2012 Page 1
2 Lakeside Building Cont d: Completion in July, 2013 Existing CEP equipment being removed from the Lakeside Building by crane (top left). New window openings cut into the 4 th floor exterior west face of Lakeside (top right). Lakeside CMU shafts and existing duct being demolished (bottom left). SLC stair opening cut into the 11 th floor (bottom right). NNAHS Weekly Progress Report October 26, 2012 Page 2
3 Hillside Building: Completion in December, 2013 JE Dunn Construction sign hanging from the Hillside Building (top left). Explosives and connections wired to the Hillside columns (top right). Trailer with explosives staged in the Hillside Building (bottom left) Column wired with explosives (bottom right). NNAHS Weekly Progress Report October 26, 2012 Page 3
4 Hillside Building Cont d: Completion in December, 2013 Dynamite gel ready for cap and casing (top left). Dynamite being placed in casing (top right). Test blast performed on column (bottom). NNAHS Weekly Progress Report October 26, 2012 Page 4
5 Lean Construction: Finish trades participating in JE Dunn s second Lean Construction Boot Camp for NNAHS (below). NNAHS Weekly Progress Report October 26, 2012 Page 5
6 NEXT WEEK October 22, 2012 October 29, st floor glazing will continue being installed. 2 nd floor drywall will continue being hung. Floating scaffolding will finish being erected and moved under the Lakeside Building. Wall framing will continue on the 2 nd and 3 rd floors. MEP in wall rough in will finish on the 2 nd floor and begin on the 3 rd floor. MEP overhead rough in will continue on the 3 rd and 4 th floors. Wall layout and MEP layout will continue on the 3 rd, 4 th, and 5 th floors. Window systems will continue being installed on the 2 nd, 3 rd, and 4 th floors. 11 th floor SLC stair cutout will be finished. Asbestos abatement will begin on the 9 th floor of the Lakeside Building. Interior demolition will continue on the upper floors of Lakeside. The Hillside Building remains (rubble and debris) will begin being hauled off site for recycling and reuse. Site-work layout for the new Hillside Building will begin. KEY UPCOMING DATES Next OAC Meeting 10:00 am at jobsite office Hillside Building Implosion 10/27/12 NNAHS Weekly Progress Report October 26, 2012 Page 6
7 IMPLOSION The much anticipated implosion of the old IBM building on the New North Atlanta High School project is almost here! If you would like to join us this Saturday, October 27 th, here are the specifics: Everyone must arrive before 7:00am (6:30 is recommended). For safety reasons, the gates will be closed and locked at 7:00am sharp, no exceptions. There will be personnel directing traffic onsite, but you can reference the below logistics plan for the parking and viewing area locations. The actual implosion blast is planned for approximately 7:30am if the winds and weather cooperate. If the winds are not favorable, it will be delayed and nobody will be allowed to leave until the implosion has occurred. The implosion will be loud. Bring ear plugs if you have them (if you forget, we have some extra onsite). The implosion will produce a lot of dust, which may get pushed towards the viewing area. For those of you who may not be able to attend the viewing, here is a link to our webcam which has live video feed. NNAHS Weekly Progress Report October 26, 2012 Page 7
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main
More informationSouthwest Health System Construction Newsletter October 7, 2017
Southwest Health System A Week in Review Patient Wing Interior sheetrock is 99% complete in the Patient Wing proper Taping and finishing is following behind sheetrock, and Nunn is preparing rooms for paint
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationMueller Laboratory Renovation. Technical Report #2 By Mark Jackson Construction Management Option 10/17/14
Mueller Laboratory Renovation Technical Report #2 By Mark Jackson Construction Management Option 10/17/14 1 Table of contents Executive Summary 3 Project Schedule 5 Detailed Estimate 8 Site Layout Planning
More informationBIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample
BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS Project Name: Address: Owner: Phone/Fax/Email: Architect / General Contractor Name: : BID DEADLINE DATE: SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME:
More informationSAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION
SECTION 02 41 14 SELECTIVE BUILDING DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for systematic removal of site improvements or portions of exterior and interior of buildings
More informationOWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS. Schedule "C"
OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS Schedule "C" Building Code All Ready To Move (RTM) Homes are built according to the Alberta Building Code and National Building Code. Please note that
More informationUnion County Vocational - Technical Schools Scotch Plains, New Jersey
SECTION 024116 - STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationProject Status Update & Progress Report
UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update
More informationPHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C
PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No. 20140101C CONSTRUCTION ESTIMATE AND PROJECT BUDGET Dated June 7. 2014 Estimated Cost HARD COSTS $ 1,560,284 Core Renovations (Toilet Rooms, Ceilings
More informationRichmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION
SECTION 024119 SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationMission Bernal Campus
Mission Bernal Campus Weekly Construction Bulletin #150 Construction Update March 6, 2017 March 12, 2017 The Mission Bernal Campus Weekly Bulletin intendeds to help inform members of the community about
More informationMinneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C
2 3 4 5 6 7 8 9 0 2 3 4 5 6 7 8 9 20 2 22 23 24 25 26 27 28 29 30 3 32 33 34 35 36 37 38 39 40 4 42 43 44 45 46 DIVISION 02 EXISTING CONDITIONS Demolition; Removal & Disposal: CMU Partitions AD Quan UM
More informationIMMC SCHOOL OF NURSING BUILDING IMPLOSION
IMMC SCHOOL OF NURSING BUILDING IMPLOSION Demolition of the School of Nursing Building is underway. Phase 1 is being razed with traditional methods of demolition. However, Phase 2 Demo is a good candidate
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationC. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:
02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"
More informationSouthwest Health System Construction Newsletter October 21, 2017
Southwest Health System A Week in Review Patient Wing Asphalt Base was completed this week in the north section of the parking lot Sheetrock is substantially complete and everything should be ready for
More informationCherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12
SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and
More informationProject Time Management. Course Objectives. Outline
Project Time Management Institute for Facilities Management Course Objectives Explore the challenges with managing a campus project schedule Review industry practices and contractual issues Discuss incentive
More informationTODAY S DATE: January 24th, 2019
TODAY S DATE: January 24th, 2019 Top Left: View of metal panels and louvers on the South elevation. Top Right: Interior storefront glass is getting installed on the atrium side of 1st floor labs. Bottom
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationCONSTRUCTION COST BREAKDOWN THIS IS FORM CCB
CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr
More informationPhase B. Site
Michigan Avenue, NW Washington, DC 2000 Technical Report 2 Table of Contents Executive Summary 2 A. Detailed Project Schedule...3 B. Site Layout Planning.... C. Assemblies Estimate..5 D. Detailed Mechanical
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationDIVISION 02 SELECTIVE DEMOLITION
DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationOconomowoc Area School District Facility Construction Update July 27, 2018
Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior
More informationTechnical Assignment 2
Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive
More informationThe Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage
The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationTODAY S DATE: November 15th, 2018
TODAY S DATE: November 15th, 2018 Top Left: Twin City Glass is working on setting the curtain wall at the main entrance on the South side of the Addition. Top Right: TCG has almost finished glazing the
More informationBuilding Construction Occupations
Job Ready Assessment Blueprint Building Construction Occupations Test Code: 2011 / Version 01 Measuring What Matters Specific Competencies and Skills Tested in this Assessment: Safety and General Knowledge
More informationVolume 7 November Additions and Alterations to: Tinicum Elementary School Palisades School District. T&W Project 0737
Volume 7 November 2009 Additions and Alterations to: Tinicum Elementary School Palisades School District Monthly Progress Report T&W Project 0737 Additions and Alterations to Tinicum Elementary School
More informationBuilding Construction Occupations
Job Ready Assessment Blueprint Building Construction Occupations Test Code: 3011 / Version 01 Measuring What Matters Specific Competencies and Skills Tested in this Assessment: Safety and General Knowledge
More informationJOB DESCRIPTION. JOB TITLE: Project Superintendent DATE: 2/1/10. DIVISION: Construction EXEMPT STATUS: Exempt
JOB DESCRIPTION JOB TITLE: Project Superintendent DATE: 2/1/10 DIVISION: Construction EXEMPT STATUS: Exempt REPORTS DIRECTLY TO: Vice President-Construction POSITION OBJECTIVE A Model Construction Project
More informationResidential Construction
Structural Insulated Panels (SIPs) are modern engineered building components that combine great structural strength with outstanding energy performance. ERECTING A STRUCTURALLY SOUND THERMALLY EFFICIENT
More informationMONOLITHIC R.C. WALLS
Building Constructions 6. 3rd Lecture MONOLITHIC R.C. WALLS Dr. Bálint Petró Prof. Emeritus Gergely Dobszay Lecturer Zsuzsanna Fülöp Lecturer Dr. Miklós Kézdi Miklós Svéd Formwork Types for In-situ Reinforced
More informationManufacturing Facilities Proposal
Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business
More informationCinema-Dining Terrace Expansion. Suburbia, USA. Technical Report II. Image Courtesy of The Whiting-Turner Contracting Company.
Cinema-Dining Terrace Expansion Suburbia, USA Technical Report II Image Courtesy of The Whiting-Turner Contracting Company Nicholas Kline Cinema-Dining Terrace Expansion 10/16/2013 Executive Summary This
More informationINSULATION. Success with 2015 IECC Northeast & Mid-Atlantic. Techtips for Builders & Trades
Success with 2015 IECC Northeast & Mid-Atlantic Techtips for Builders & Trades COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED TEMPLATE 2015.1.0 PAGE 1 NORTHEAST For vented attics, install wind baffles
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report September 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationFeature Zone IECC 2009 IECC
Feature Zone 3 2006 IECC 2009 IECC Window U factor 0.65 0.50 Skylight U factor 0.65 0.65 Window SHGC 0.40 0.30 Ceiling R value 30 30 Wood frame R value 13 13 Mass wall R value 1 5 5/8 Floor R value 19
More informationProject #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50
Project #1139 Budget #82 $ Budgeted $ Billed to Date $ Paid to Date $ Due 210,087.68 120,979.20 120,979.20 77,158.50 Deposit Paid Deposit Due Phase I: Project Programming and Research $ Budgeted $ Billed
More informationCarpentry/Carpenter CIP Task Grid
Secondary Task List 100 SAFETY/OCCUPATIONAL ORIENTATION 101 Identify and follow all basic safety practices and procedures. 102 Identify and follow all lab safety practices and procedures. 103 Identify
More informationModular Wood Framing Goes Vertical
Modular Wood Framing Goes Vertical By: Troy Bean, P.E., S.E. DCI Engineers January 2013 The Wood Products Council is a Registered Provider with. Credit(s) earned on completion of this program will be reported
More informationBUILDING CODES & DESIGN CRITERIA
BUILDING CODES & DESIGN CRITERIA Adopted Building Codes: 2006 International Building Code (IBC) 2006 International Residential Code (IRC) 2006 International Mechanical Code (IMC) 2006 International Plumbing
More informationWisconsin Technical College System. Curriculum Standards & Program Design Summary CARPENTRY (CONSTRUCTION) APPRENTICE
Program Information Program Curriculum Standards & Program Design Summary 1 CARPENTRY (CONSTRUCTION) APPRENTICE Carpenters construct, erect, install or repair structures and fixtures made of wood; concrete
More informationNational Utility Contractors Association 2016 Member Activation Form Specialty Contractor Companies
Join By June 15 Become an Official Founding Member Don t miss out on this special recognition for your company! National Utility Contractors Association 2016 Member Activation Form Specialty Contractor
More informationCARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report
CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationJob Ready Assessment Blueprint. Test Code: 4012 / Version: 01 Building Trades Maintenance
Blueprint Test Code: 4012 / Version: 01 Building Trades Maintenance Specific Competencies and Skills Tested in this Assessment: Safety Use tools and equipment safely Demonstrate electrical safety Respond
More informationA. The extent of Selective Demolition Work is that Work necessary, and required to facilitate the new construction indicated.
Project No. El611-0l SECTION 02 41 00 - SELECTIVE DEMOLITION PART1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationLIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for
LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Physical Plant Division Engineering and Architectural Services Department
More informationQuality Safety Service Value
Quality Safety Service Value Generating Value Through Sustainable Asset & Energy Solutions MOPAC is a multi-specialty services contractor focused on the design, construction and preservation of commercial,
More informationGREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More informationSmelter Removal & Reclamation Frequently Asked Questions
Smelter Removal & Reclamation Frequently Asked Questions Email your questions to us at: info@resolutioncopper.com Q: Why is Resolution Copper taking the Magma Smelter complex down? A: The removal and cleanup
More information1. Before selective demolition, Owner will remove the following items:
SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Demolition and removal of selected portions of building or structure. 2. Demolition and removal of selected
More informationREDLAND TECHNOLOGY CENTER
REDLAND TECHNOLOGY CENTER 540 Gaither Road, Rockville, MD Shawn Pepple Construction Management Technical Assignment #3 November 21, 2008 Dr. Messner TABLE OF CONTENTS 3.1 Executive Summary.. 3 3.2 Constructability
More informationTechnical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction
Technical Report II The Office Building Rendering courtesy of DAVIS Brett Miller Dr. Gannon Construction 10/16/2013 Executive Summary This technical report analyzes key features of The Office Building
More informationKitchen Remodel Estimator. Contact Info: Project Summary: Design. Demo
Kitchen Remodel Estimator Thinking about remodeling your kitchen? If you would like a free bid from Excel Builders, we have provided a list of questions that will need to be filled out with detail in order
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationWORK INSTRUCTIONS COLORADO SPRINGS NNO FACILITY EQUIPMENT SALVAGE PLAN VERIZON WIRELESS PROJECT MANAGER PATRICK SKILLEN PREPARED FOR:
4323 ARROWSWEST DRIVE COLORADO SPRINGS, CO 80907-3451 PREPARED FOR: VERIZON WIRELESS PROJECT MANAGER PATRICK SKILLEN MARCH 10, 2009 VERIZON WIRELESS PAGE 1 PART 1 - GENERAL 1.01 PROJECT DESCRIPTION VzW
More informationPROPOSAL NOTE: ALL SURFACES TO BE PROTECTED AT ALL TIMES. WE ALSO REMOVE AND REHANG DRAPES, MOVE ALL FURNITURE AND PUT IT BACK WHEN JOB COMPLETED.
11424 Mercury Dr. Manassas, VA 20112 Thursday, May 13, 2010 George & Carol Proctor 65 Main St. Sperryville, VA 22740 (555) 555-9999 Phone: (703) 738-4674 Fax: (703) 349-3831 CUSTOMER ID: GP012010 PROJECT
More informationBryant Denny Stadium Bryant Denny Stadium September 15, 2009
Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Project Status September Report 15, 2009 #13 April 27, 2012 TABLE OF CONTENTS SECTION 1: PROJECT SUMMARY SECTION 2: OVERALL PROJECT SCHEUDLE
More informationWoodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017
Woodbridge Redevelopment Update CLC Meeting #6 Wednesday, December 13, 2017 1. Introductions Agenda 2. Project Updates 3. Construction Updates Progress to Date What s Happening Now 3 Month Schedule 4.
More information2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY
PART 1 - GENERAL SECTION 01 01 11 MULTIPLE CONTRACT SUMMARY 1.01 SCOPE OF WORK A. This Section includes a summary of each Contract, including responsibilities for coordination and temporary facilities
More informationTable Air Barrier and Insulation Inspection Component Criteria
Table 40.4. Air Barrier and Insulation Inspection Component Criteria NUMBER COMPONENT CRITERIA Air barrier and thermal barrier Exterior thermal envelope insulation for framed walls is installed in substantial
More informationADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:
ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan
More informationSTRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC
CARROLL DANIEL CONSTRUCTION CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 STRATTON CONSTRUCTION SCHEDULING & SEQUENCING 509 CROWE DRIVE HIGHLANDS, NC 28741 404.944.5298 (f CARROLL DANIEL CONSTRUCTION
More informationConcrete. Conveying Systems. Doors, Windows & Interiors
Concrete Concrete : Cast-in-Place Concrete Concrete : Cementitious Decks Concrete : Concrete Accessories Concrete: Concrete Block & Brick Concrete : Concrete Coring & Sawing Concrete : Concrete Curing
More informationUpdate on FCPS Construction/Renovation Projects. July 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationNARRATIVE REPORT 1.0 BUILDING INFORMATION 2.0 ASBESTOS SURVEY INFORMATION
NARRATIVE REPORT 1.0 BUILDING INFORMATION Askanase Hall was originally constructed in 1966; a 1975 addition extended the building to the north and the west. Although specific information could not be located,
More informationTechnical Assignment 2 Cost and Schedule Analysis October 24, 2008
Technical Assignment 2 and Schedule Analysis October 24, 2008 Meghan Graber Construction Management Dr. Riley Integrated Science Center College of William & Mary Williamsburg, Virginia Graber TABLE OF
More informationCITY OF FORT COLLINS BUILDING STANDARDS SPECIFICATIONS/DIV 8
CITY OF FORT COLLINS BUILDING STANDARDS SPECIFICATIONS/DIV 8 L. Division 8 - Doors and Windows 1. Windows 2. Doors a. Glazing shall be energy efficient (ie; Low-E) and have an insulated glass certification
More informationSTATE UNIVERSITY CONSTRUCTION FUND
DIRECTIVE 1A-8 Issue date: October 2014 CONSTRUCTABILITY REVIEW 1. The Consultant shall be required to perform a constructability review with the College, Fund s Design Coordinator, Fund s Construction
More informationHEALTHCARE OF THE FUTURE INTEGRATED CARE + FACILITY DESIGN
HEALTHCARE OF THE FUTURE INTEGRATED CARE + FACILITY DESIGN PROJECT INTRODUCTION PROGRAM + DESIGN RESPONSE Built-to-Suit prototype Medical Clinic was designed in response to tenant s extensive development
More informationSuccess with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders. insulation
Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders insulation Copyright 2014 Advanced Energy. All Rights Reserved TEch Tips: 1. Install insulation to meet the 2012
More informationHigh Stakes. Solutions of Special Projects:
Category 2: Meeting the Challenge of a Difficult Job Specialty Contractor Specialty Contractor: Colorado Cleanup Corporation (CCC) Project Name: Monarch Casino Garage Implosion High Stakes After months
More informationComcast Panorama Tenant Finish
Comcast Panorama Tenant Finish Displaying a nationally known logo throughout an entire building is the goal that ICI set out to achieve when taking on the Comcast Tenant Finish project. This $1.7 million
More informationSECTION DEMOLITION WASTE MANAGEMENT AND DISPOSAL
SECTION 017418 PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationCARBON MONOXIDE ALARMS
7100 147 th Street West Telephone (952) 953-2588 Apple Valley, MN 55124-9016 www.cityofapplevalley.org BUILDING PERMITS - Are required for all porch additions. PORCH INFORMATION ELECTRICAL PERMITS - Are
More informationOutdoor + Switchgear, Walk-in Equipment Buildings Low & Medium Voltage NEMA 3R
Outdoor + Switchgear, Walk-in Equipment Buildings Low & Medium Voltage NEMA 3R Product Brochure www.apt-power.com 433 N. 36 th Street PROVIDING A COMPREHENSIVE Lafayette, IN 47905 www.apt-power.com 433
More informationThe Chapin School Expansion and Renovation Project Community Construction Committee September 6th, :30 p.m. - 8:00 p.m.
The Chapin School Expansion and Renovation Project Community Construction Committee September 6th, 2017 6:30 p.m. - 8:00 p.m. Meeting purpose & elected officials represented PURPOSE OF MEETING: Continue
More informationChapter 14 - Air Sealing
Chapter 14 - Air Sealing Contents Chapter 14 - Air Sealing... 14-1 Pre-Mechanicals Activities... 14-3 Insulate Bathtub Enclosures... 14-3 Insulate Double Walls and Chases... 14-3 Pre-Inspection Checklist...
More informationBuilding Permit Application
Building Permit Application Building Use: Single Family Dwelling Duplex / Semi-detached 3+ Units Commercial Temporary Class of Work Other Building Address: Legal: Lot: Block: Plan: Subdivision: Applicant
More informationIMPACT NOTIFICATION PLAN #57 (3/5/2018 3/25/2018)
6 IMPACT NOTIFICATION PLAN #57 The following areas will be affected the greatest: ACC WP Level 2 & 3 Emergency Department SPECIAL NOTES: - Click here to watch our progress via the webcam. SCHEDULED SHUTDOWNS:
More informationTOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018
TOWN OF MANCHESTER BUILDING COMMITTEE MINUTES OF FEBRUARY 5, 2018 The February 5, 2018 meeting of the Manchester Building Committee was held in the Manchester Room at the Town Hall. Manchester Building
More informationBuilding Architecture
The front of the building consists of the three story town homes with facades to remain, as well as one leg of the condominium tower that reaches the street. The main condo portion of the building is L
More informationTechnical Assignment 1
Technical Assignment 1 Construction Project Management Oct 5 th, 2009 Shane Flynn Construction Management Dr. Magent 700 6 th Street Washington, DC Table of Contents 1. Executive Summary.......3 2. Project
More informationSTATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION SKI PATROL HUT PROJECT #: CAP 1804
STATE OF NEW HAMPSHIRE DEPARTMENT OF NATURAL AND CULTURAL RESOURCES DIVISION OF PARKS AND RECREATION PROJECT #: CAP 1804 FRANCONIA NOTCH STATE PARK FRANCONIA, NEW HAMPSHIRE BID SET 8/4/2017 DRAWING LIST:
More informationPresentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process
Presentation Overview: NC Energy Code RESNET Standards HERS Index HERS Verification Process NC Energy Code Requirements ENERGY STAR and NC Energy Code in Alignment RESNET Standards HERS Index A scoring
More informationAdolfson & Peterson Construction, Megan Bond; ; CATEGORY 3: Meeting the Challenge of a Difficult Job General Contractor
Vanguard Classical School K-12 Adolfson & Peterson Construction, Megan Bond; 303-326-5842; mbond@a-p.com CATEGORY 3: Meeting the Challenge of a Difficult Job General Contractor Overview Statement: Every
More informationBryant Denny Stadium Bryant Denny Stadium September 15, 2009
Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Project Status September Report 15, 2009 #15 June 27, 2012 TABLE OF CONTENTS SECTION 1: PROJECT SUMMARY SECTION 2: OVERALL PROJECT SCHEUDLE
More informationConstruction Update. April 2016
Construction Update April 2016 Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Overview 1. Recent Activity 2. Upcoming Activity 3. Safety & Labor
More informationNew Stadium Project. Construction Activity Mitigation Program. January 22, 2014
New Stadium Project Construction Activity Mitigation Program January 22, 2014 Construction Mitigation Plan Introduction It is the primary goal of HHRM, JV to minimize negative effects on traffic and the
More informationMPA Project No. L1429-C1 Project Title: Terminal C Enhancements Location: Logan International Airport
MPA Project No. L1429-C1 Project Title: Terminal C Enhancements Location: Logan International Airport RESPONSES TO QUESTIONS and/or RFI s Date: 6/1/2018 The attention of Contractors submitting Filed Sub-Bids
More informationPage(s)
Robert M. Leicht Construction Management Option Advisor: Dr. John Messner Bldg: Smithsonian Institution Patent Office building Washington, DC 10/4/04 Technical Assignment 1 Executive Summary: The Smithsonian
More information229 Rehoboth Avenue Telephone P.O. Box 1163 Fax
Building & Licensing City of Rehoboth Beach 229 Rehoboth Avenue Telephone 302-227-6181 P.O. Box 1163 Fax 302-227-4504 Rehoboth Beach, Delaware 19971 www.cityofrehoboth.com NOTICE TO CONTRACTORS BUSINESS
More informationGH Phipps Construction Co. OAC 17D Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, :00 AM
GH Phipps Construction Co. OAC 17D5780 - Thistle-Valmont Square Interior & Exterior Renovation Thursday, November 2, 2017 10:00 AM Meeting ID 003 Subject Weekly OAC Meetings Location 6000 Spine Rd #101,
More information