1 DISCOVERY ELEMENTARY SCHOOL COMMUNITY UPDATE #11 April 2015 COMPLETED AND ONGOING CONSTRUCTION ACTIVITIES The north half of the Discovery Elementary School (DES) building referred to below encompasses the gym, admin area, 2 story classroom wing housing grades 1-5, the library, art/music rooms, and the kitchen. The south half of the building is the one story portion that includes the entry canopy, main vestibule, main street hallway, pre-k and K wings, and cafeteria. Footings are 100% complete for the entire building. Insulated Concrete Formwork (ICF) walls and steel structure is 100% complete for the 2 story portion on the north half of the building. Gym structure is 95% complete. ICF and steel structure are approximately 80% complete on the south half. Both gym and south half ICF/steel structure should be complete by the 2 nd week of April. 1
2 Roofing is complete on the 2 story portion on the north half, with the exception of the gym. Roofing will be starting on the gym and the south half of the building in early to mid-april. Brick veneer has started on the north side of the building. Site underground sanitary sewer is 100% complete Site underground storm sewer is 75% complete. Storm sewer associated with the synthetic turf fields and west parking lot remains to be done. Site retaining walls on the south side of the school are complete and installation of veneer stone is 95% complete. Site retaining wall installation is progressing on the east side of the building. The geothermal well field is complete. All wells are drilled and grouted. Horizontal piping connecting the geothermal field to the building is in progress. Underground utility work in the public right of way is largely completed, with the exception of some additional undergrounding in the N Jefferson St cul-de-sac and for a short distance on 36 th St N, near N Jefferson St. This work should be completed during the month of April. Fireproofing of the north half of the building is 90% complete. Metal studwork is nearing completion on the 1 st floor of the north half, and has commenced on the 2 nd floor. Mechanical, electrical, and plumbing rough-ins are following up the metal studwork noted above. Installation of drywall has started and is following completion of MEP rough-ins, and county wall close-in inspections. Davey Tree work at the woods on the western side of the property will recommence in spring to continue bamboo removal for any shoots that reappear. SCHEDULE The project is generally on schedule. As with any large project, some areas are a bit ahead of schedule and some areas are a bit behind. At this time we have no concerns with meeting our contract milestone dates and opening for the September 2015 school year. OF SPECIAL NOTE We received a complaint from a neighbor about lighting levels and glare from the new WMS east parking lot lights. As a result of the complaint, APS forces surveyed the lighting levels in the lot. For comparison purposes, we also surveyed the parking lot lights at the recently re-constructed Yorktown HS on the same night. What we found was that the lighting levels were very much in accord with the design for the WMS lot, with a general lighting level of 2 footcandles (fc). At YHS, the lighting levels were more on the order of 1fc. The WMS parking lot is 2
3 much more evenly lit than the YHS parking lot due to the type of light fixture used LED at WMS vs. metal halide at YHS. In addition, the glare characteristics of the LED lamps at WMS are much more intense than the metal halides at YHS. This has to do with the inherent difference between LED and metal halide lamps and the geometry of the fixture housings. In order to be sensitive to the complaints of the neighbor, while still maintaining minimum safe lighting levels, we recently made adjustments to the lights to reduce the lighting level at the WMS parking lot to 1fc, same as at YHS. We also installed a lower temperature LED lamp in the fixtures nearest to N. Harrison St., resulting in a light color that does not appear as bright and glaring to the eye. In addition, we added anti-glare baffles to these same fixtures. The changes were effective at solving the lighting level and glare issues and we will be employing the lessons learned for the west parking lot lighting. It is also worth noting that the WMS east parking lot lights are on a time schedule such that the lights are turned off each night at approximately 10:00pm. We are aware of the recent news reports regarding synthetic turf material safety concerns. The safety concerns center on the type of crumb rubber infill used with the turf. The infill material provides the proper cushioning required and gives the synthetic turf a similar character to natural grass. The WMS artificial turf fields are a joint use facility with Arlington County Department of Parks & Recreation (DPR). In conjunction with DPR, we have commissioned a study of infill options for consideration. We should have results and recommendations to report in next month s update. Temporary street lights have been erected on the school side of the street on 36 th St N and N Harrison St along the perimeter of the DES property. These cobra type street lights are required by the county during construction but will be removed once the permanent Carlyle type street lights are installed. See following pages for construction photos of completed and ongoing work. 3
4 COMPLETION OF FOOTINGS/FOUNDATIONS AT UTILITY SPACES WEST OF GYM COMPLETION OF FOOTINGS/FOUNDATIONS AT MAIN HALLWAY 4
5 COMPLETION OF ROOF FRAMING AND DECKING AT NORTH SIDE 2 STORY STRUCTURE GYM ROOF FRAMING IN PROGRESS 5
6 GYM ROOF FRAMING IN PROGRESS ROOF FRAMING AND DECKING FOR CAFETERIA AND VERANDA IN PROGRESS 6
7 ICF WALLS AND STEEL FRAMING AT KINDERGARTEN WING IN PROGRESS ICF WALLS AND STEEL FRAMING AT KINDERGARTEN WING IN PROGRESS 7
8 INSTALLATION OF ROOF AT NORTH SIDE 2 STORY STRUCTURE SCAFFOLDING TENTED FOR INSTALLATION OF BRICK VENEER ON NORTH SIDE OF BUILDING 8
9 ERECTION OF SCAFFOLDING FOR INSTALLATION OF BRICK VENEER ON GYM RETAINING WALL STONE VENEER WITH KINDERGARTEN ICF AND STEEL FRAMING BEHIND 9
10 SPRAY FIREPROOFING OF STRUCTURAL STEEL AT 2 ND FLOOR INTERIOR METAL STUD FRAMING ON 1 ST FLOOR NEAR LIBRARY 10
11 MECHANICAL/ELECTRICAL/PLUMBING ROUGH-IN ON 1 ST FLOOR MECHANICAL/ELECTRICAL/PLUMBING ROUGH-IN ON 2ND FLOOR 11
Fleet Elementary School
Fleet Elementary School Community Newsletter (January 2019) This is the January update on the status and progress of construction for the project. All monthly updates will also be posted to the project
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationUpdate on FCPS Construction/Renovation Projects. November 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationUpdate on FCPS Construction/Renovation Projects. December 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationMONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationFleet Elementary School
Fleet Elementary School Community Newsletter (August 2018) This is the August update on the status and progress of construction for the project. All monthly updates will also be posted to the project website
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationBOND CONSTRUCTION UPDATE
BOND CONSTRUCTION UPDATE March 31, 2015 PROJECTS: 1. CIBOLO VALLEY ELEMENTARY SCHOOL BOND 2013 2. STEELE HIGH SCHOOL ADDITIONS & RENOVATIONS BOND 2013 3. DOBIE MIDDLE SCHOOL ADDITIONS & RENOVATIONS BOND
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationGREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More informationUpdate on FCPS Construction/Renovation Projects. September 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationFleet Elementary School
Fleet Elementary School Community Newsletter () This is the February update on the status and progress of construction for the project. All monthly updates will also be posted to the project website and
More informationUpdate on FCPS Construction/Renovation Projects. August 2015
Update on FCPS Construction/Renovation Projects Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project
More informationLLANO ISD SCHOOL BOARD MEETING. January 2016
LLANO ISD SCHOOL BOARD MEETING January 2016 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationGEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012
GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012 TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-26-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 39% COMPLETE As
More informationWoodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017
Woodbridge Redevelopment Update CLC Meeting #6 Wednesday, December 13, 2017 1. Introductions Agenda 2. Project Updates 3. Construction Updates Progress to Date What s Happening Now 3 Month Schedule 4.
More informationCheldelin Middle School
Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:
More informationCONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO
CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005
More informationPhotos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek
Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School
More informationBuilding & Grounds Committee Meeting Tuesday, 13 September Minutes
Building & Grounds Committee Meeting Tuesday, 13 September 2016 Minutes Present: Johnson, Laverghetta (joined at 8:00 am) and McCarthy. Also present: Kettrich, Koch, Prior, Crolius, Marsenison. Mrs. Johnson
More informationUpdate on FCPS Construction/Renovation Projects. July 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report November 2018 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationAuburn University Construction Project April
Small Animal Teaching Hospital Phase I: Construction Cost: $8.8 million. Phase I consists of (1) constructing an addition to the Overton-Rudd Auditorium to expand classroom and lecture hall capacity, (2)
More informationCity of Rohnert Park Building Department Inspection Descriptions
200 SITE REVIEW: Prior to a permit being issued the Fire / Building Department is authorized to examine existing buildings, structures, and site for which an application has been filed. 201 PRECONSTRUCTION
More informationDrexel Hill Middle School
150004 Drexel Hill Middle School Site Plan for Drexel Hill Middle School Floor Plan for Drexel Hill Middle School 2 150004; Drexel Hill Middle School. This school is located at 3001 State Road, Drexel
More informationArbor Heights Elementary School. Concrete for South Building Foundation Stem Walls
Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report October 2017 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle
More informationProject Time Management. Course Objectives. Outline
Project Time Management Institute for Facilities Management Course Objectives Explore the challenges with managing a campus project schedule Review industry practices and contractual issues Discuss incentive
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationOconomowoc Area School District Facility Construction Update July 27, 2018
Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being
More informationAuxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.
Capital Projects Status Report October 1, 2018 Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah 84119 P 801.974.8365 F 801.974.8375 Current Projects 1. Edison construction update: In Area
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (02-05-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 33% COMPLETE As
More informationLemm Elementary. Restoring the Heart of the Community. Klein Independent School District
Lemm Elementary Restoring the Heart of the Community Target Date: August 2018 June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main
More informationSafety Update Crossing study is in final review stages. Facilities Update Construction Progress
Major Projects Update September 2017 Prepared by Business and Operations September 11, 2017 Transportation Update As of 9/6/17 we have 4,803 students registered for busing, up 643 from last month s update.
More informationCITY OF RICHMOND HEIGHTS DEPARTMENT OF BUILDING ZONING AND HOUSING STANDARDS AND REGULATIONS
CITY OF RICHMOND HEIGHTS DEPARTMENT OF BUILDING ZONING AND HOUSING STANDARDS AND REGULATIONS By ordinance the following codes have been adopted governing construction in their most currently published
More informationOconomowoc Area School District Facility Construction Update June 29, 2018
Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major
More informationSAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )
SAMUEL CLEMENS ADDITIONS & RENOVATIONS (01-22-2018) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 29% COMPLETE SAMUEL
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationConstruction SliDeRulE Case Studies
2015 Construction SliDeRulE Case Studies John Gambatese and Chukwuma Nnaji Oregon State University 2/15/2015 1 Construction SliDeRulE Case Studies Case Study #1: Lonnie Harris Black Cultural Center (LHBCC)
More informationHOMOGENEOUS AREAS LIST Asbestos
Elementary Campus 1985 Elementary uilding Wing (17,600 sq. ft.) uilding 12" floor tile (white/beige) and mastic 3,200 Square Feet Troughout building 2' x 2' ceiling tiles 10,000 Square Feet Gym (4,700
More informationHeritage High School
Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery
More informationPROJECT STATUS REPORT De Anza High School - Replacement Campus Period Ending: 2/10/2011 Scope: Replacement Campus Construction Status: Architect: DLM Architects Project Manager: Jose Chapa, SGI Construction
More informationEvansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data
Evansville Public Schools Facility Assessment Report January 28, 2, 2013 SGN/Wendel Architects, Design Tree Engineering and R.A. Morton Construction Managers were retained by the Evansville Public School
More informationHunter s Point South Project
January 2013 Update Hunter s Point South Project New York City Economic Development Corporation The City of New York continues work on the Hunter s Point South project, a waterfront development on a 30-acre
More informationCity of Westerville Guide to Commercial Inspections
City of Westerville Guide to Commercial Inspections FOOTINGS - After the excavation, with the form work and any required reinforcing steel in place. All footings shall have loose soil removed, reinforcing
More informationNAAHB Workgroup Index General Ledger Account
NAAHB Workgroup Index General Ledger Account 1000 Series Preparation/Preliminaries 1000 Permits/Fees 1010 Building Permits 1020 HBA Assessments 1030 Warranty Fees 1100 Architectural/Engineering 1110 Blue
More informationAuburn University Construction Project Update March 2010
New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish
More informationNational Property Inspections
National Property Inspections Anywhere, USA (325) 382-8754 Property Location 9375 Burt Street Anywhere USA Prepared for John Investor Consultant Al Standard (325) 382-8754 Page 1 of 27 TABLE OF CONTENTS
More informationRCT Webinar-Updated 03/18/12
RCT Webinar-Updated 03/18/12 This instructional write up/guide is for the RCT Form that is found on the Main Information screen. When do we do the RCT? The RCT is done when a full exterior or full interior
More informationCTE - CIP Course Details Catalog
Status: Open Start Year: 2011 End Year: Group 1 Minimum Carnegie Units: 2.00 Minimum Course Selection: School: 1 ACC: 0 Regional: 0 13052A001 Production Technology 1.00 2011 11002A001 Communication Technology
More informationCity Of Mendota Construction Procedures
City Of Mendota Construction Procedures Building Permit Application: A permit shall be obtained prior to commencing work of any type. Failure to do so may result in doubling the permit fees. At the time
More informationConstruction, alteration, removal, or repair of any plumbing system.
PERMITS AND INSPECTION PERMITS (IRC R0 IPC 06) REQUIRED (IRC R 0. IPC 06.) Construction, alteration, removal, or repair of any plumbing system. APPLICATION (IRC R0. IPC 06.) Submit application to local
More informationProject Status Update & Progress Report
UCSD Board of Education Project Status Update & Progress Report March 27, 2018 Capital Project Presentation March 2018 1. Kernan Elementary School Addition & Renovations Part 1 Construction Progress Update
More informationNew Ringgold Middle School. Project Slideshow August 26, 2017
New Ringgold Middle School Project Slideshow August 26, 2017 Aerial Photo from West Provided by Hudson Group Taken 8.16.2017 Aerial Photo from North Provided by Hudson Group Taken 8.16.2017 Aerial Photo
More informationEXISTING CONDITIONS BTA PROJECT NO: 1722
1 CAROLINE STREET PUTNAM STREET 3 2 PROJECT SITE LOCATION PLAN 1. INTERSECTION OF CAROLINE ST AND PUTNAM ST - LOOKING SOUTHEAST 2. PUTNAM ST - LOOKING NORTHEAST 3. CAROLINE ST - LOOKING WEST EXISTING CONDITIONS
More informationJuly 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY
July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationTHE STRATA UNIT May 25, 2008
THE STRATA UNIT May 25, 2008 Over the years, we have been asked time and time again from our experience as a cost consultant and a project manager from both a restoration and renovation point of view What
More informationStandards for Single Family Detached Lots
Standards for Single Family Detached Lots 1. Single-Family Detached Lots are a minimum of 4,000 sf. 2. The following standards apply to all structures on Single-Family Detached Lots o Maximum Height to
More informationResidential Construction Minimum Required Inspections
Residential Construction Minimum Required Inspections The permit which you have been issued gives authority for work to commence. The stamped, approved plans, returned with this permit, shall be retained
More informationCONSTRUCTION COST BREAKDOWN THIS IS FORM CCB
CONSTRUCTION COST BREAKDOWN Property Owner s Name or Borrowers Name Brief Description of Project John Homeowner Build single family residence Property Address Property City Property Zip Code 4625 Jillbarr
More informationHMFH ARCHITECTS VO LU M E 3 O F 3. Vo l u m e 3 1. Brookline High School Campus Expansion Feasibility Study Brookline High School Feasibility Study
Brookline High School Campus Expansion Feasibility Study Brookline High School Feasibility Study Vo l u m e 3 1 M AY 2 0 1 7 D R A F T VO LU M E 3 O F 3 130 Bishop Allen Drive Cambridge, MA 02139 617 492
More informationHMFH ARCHITECTS VO LU M E 3 O F 3. Vo l u m e 3 1. Brookline High School Campus Expansion Feasibility Study Brookline High School Feasibility Study
Brookline High School Campus Expansion Feasibility Study Brookline High School Feasibility Study Vo l u m e 3 1 M AY 2 0 1 7 D R A F T VO LU M E 3 O F 3 130 Bishop Allen Drive Cambridge, MA 02139 617 492
More informationG703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project
Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor
More informationBasic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.
Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial
More informationJune 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY
June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationBiddeford School Department
Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6
More informationFacility Improvements
AL-SI-02 ASPHALT PLAY AREA UPGRADE AL-SI-09 CURB RAMP ADDITIONS Asphalt improvements needed around building and playshed to provide a safe play area. Curb ramps needed to provide wheelchair access and
More informationTown of Kingsville. Building Department
Town of Kingsville Building Department GUIDE TO RESIDENTIAL BUILDING PERMITS www.kingville.ca 2017 Disclaimer: The fees and by-law information compiled within this guide are for reference purposes only.
More informationBUILDING PERMIT INFORMATION GUIDE FOR THE HOMEOWNER
THE CORPORATION OF THE MUNICIPALITY OF SOUTH HURON 322 Main Street South, P.O. Box 759, Exeter, Ontario N0M 1S6 PHONE: (519) 235-0310 FAX: (519) 235-3304 TOLL FREE: 1-877-204-0747 WEBSITE: www.southhuron.ca
More informationIntroduction & Project Background
Introduction & Project Background Project Background is located in Pasadena, Maryland and is owned and maintained by Anne Arundel County School District. A new elementary school to replace the existing
More informationMarch 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT
March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationOsceola County Growth Management Division 1 Courthouse Square, Suite 1400 Kissimmee, FL
Osceola County Growth Management Division 1 Courthouse Square, Suite 1400 Kissimmee, FL. 34741 407-742-0200 Permit Type: Permit Number: COMMERCIAL/ADDITION P COMM/CADD (census class 437) Description of
More informationSTRUCTURAL/SEISMIC REPORT Roosevelt Elementary School. Report prepared by DCI Engineers. For. Medford School District. Completed By: DCI Engineers
J. Mark D Amato Guy A. Conversano Elizabeth A. Jensen Roger L. Heeringa Mark D. Aden Harry Jones II Troy E. Bean Tom C. Xia, Ph.D. Richard L. Hemmen Grant C. Buckingham Wade W. Younie STRUCTURAL/SEISMIC
More informationDENNIS TOWNSHIP FEASIBILITY STUDY
DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT
More information1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department.
City of Goshen Instructions for Residential Permit Application Why do you need a building permit? Your home is a large investment, and if your construction project does not comply with the codes adopted
More informationREGULATIONS FOR RESIDENTIAL OPEN WOOD DECKS
REGULATIONS FOR RESIDENTIAL OPEN WOOD DECKS TOTAL PERMIT FEE DUE WILL BE $375.00 ($290.00 IS REFUNDABLE AFTER POST HOLE AN FINAL INSPECTION) Furnish (2) copies of a site/plot plan drawn to scale for wood
More informationChristopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule
Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri
More informationFranklin Elementary School
Facility Information Address: Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Building Capacity: Sept. 2007 Enrollment: 750
More informationPACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS
PACKARD HOUSE 2010 LEED-NC GOLD PENDING PROJECT HIGHLIGHTS Urban infill on a previously developed site. The new building was built over an existing parking lot. Landscaping is composed of all native plants
More informationDécor Design Construction llc
Décor Design Construction llc Exhibit a Standard features Includes: excavating & regrading (extra dirt or not enough dirt is owners cost) blueprints sewer & water hookups 1. Foundation 8 x 20 concrete
More informationPershing Hill Elementary School. Fort Meade, MD. Revised Proposal for Spring Thesis Project. January 15, Mitchell Reiners
Pershing Hill Elementary School Fort Meade, MD Revised Proposal for Spring Thesis Project January 15, 2010 Mitchell Reiners Faculty Consultant: Dr. Magent Proposal for Spring Thesis Project Mitchell Reiners
More informationStatement of Special Inspections
Statement of Special Inspections Project: Location: Owner: Design Professional in Responsible Charge: This Statement of Special Inspections is submitted as a condition for permit issuance in accordance
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationTODAY S DATE: January 24th, 2019
TODAY S DATE: January 24th, 2019 Top Left: View of metal panels and louvers on the South elevation. Top Right: Interior storefront glass is getting installed on the atrium side of 1st floor labs. Bottom
More informationChino Valley Unified School District Monthly Construction Update
h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:
More informationOUTLINE SPECIFICATION ALL-WEATHER PLAYING PITCHES
OUTLINE SPECIFICATION FOR THE CONSTRUCTION OF ALL-WEATHER PLAYING PITCHES AT PORTARLINGTON SWIMMING POOL AND LEISURE CENTRE PEOPLES PARK, LINK ROAD, PORTARLINGTON, CO. LAOIS Date: July, 2011. INTRODUCTION
More informationFranklin & Marshall College Row Lancaster, PA Franklin & Marshall College Row Lancaster, PA Aimee Bashore Senior Thesis 2007 Construction Management
Elkus Manfredi Architects Outline of Presentation Topics 1. Project Overview 2. Analysis 1 Building Information Modeling (BIM) Utilization 3. Analysis 2 Composite Metal Deck v. Precast Concrete Plank Flooring
More informationPershing Hill Elementary School. Fort Meade, MD. Final Proposal for Spring Thesis Project. December 15, Mitchell Reiners
Pershing Hill Elementary School Fort Meade, MD Final Proposal for Spring Thesis Project December 15, 2009 Mitchell Reiners Faculty Consultant: Dr. Magent Proposal for Spring Thesis Project Mitchell Reiners
More informationL K J H F E OPEN ADMIN. AREA V.S. MANAGER WOMEN L.I.C. STN. STL. FLASHING, TYP. UPPER ROOF EL. +41'-0" METAL ROOFING SYSTEM
Museum Fndtn 60 W. 3th Street Overland Park, KS 663 L K J H F E Boston, MA 008 SERVICE WING ROOF EL. +9'-0" Section 3/3" = '-0" LOWER ROOF EL. +37'-6" Q P N M MECHANICAL MOPF COLLECTION STORAGE CRATE STORAGE
More informationAPPENDIX DETAIL (1) INSULATION HAS 3-INCH TOP INSPECTION GAP AND EXTENDS 24 INCHES BELOW GRADE
The sections and construction details in Details 502.2.1.5(1), 502.2.1.5(2), 502.2.1.5(3), 502.2.1.5(4) and 502.2.1.5(5), and Tables 502.2.3.1(1), 502.2.3.1(2), 502.2.3.1(3), 502.2.3.2, 502.2.3.3, 502.2.3.5
More informationINTUITIVE AND OBJECTIVE APPROACHES TO DAYLIGHTING A NEW ENGLAND ELEMENTARY SCHOOL Michael Rosenfeld 1
Best2 - Daylighting a New England Elementary School - Session EE 7-3 INTUITIVE AND OBJECTIVE APPROACHES TO DAYLIGHTING A NEW ENGLAND ELEMENTARY SCHOOL Michael Rosenfeld 1 ABSTRACT The Town of Concord,
More informationArchitectural Standards
Page 1 PROJECT INFORMATION Project Name: Applicant/Agent: Date: File # OFFICIAL USE NON-RESIDENTIAL STANDARDS INDUSTRIAL DISTRICTS Cohesive Design, Non-Residential Standards (cds) 1.00 Promote visually
More informationMARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD
MARCH 2018 2016 BOND & TIF PROJECT UPDATE Grapevine-Colleyville ISD GHS Agricultural Sciences Building Renovation Multipurpose Activity Centers Additions and Renovations to TES and GMS Cannon Elementary
More information