No. Secy.CAO/USBRL/JAT/PCDO Dated: 10/08/2018

Size: px
Start display at page:

Download "No. Secy.CAO/USBRL/JAT/PCDO Dated: 10/08/2018"

Transcription

1 व जय शर म vkbzvkj,lb Vijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 10/08/2018 Sub: PCDO for the Month of July, Highlights of the month of July, During this month 2035 m of tunneling (MT+ET) and cumulative progress of 7362 m this financial year has been completed th Apex Committee meeting was held under the chairmanship of Chief Secretary J&K at Srinagar on 30/07/ of tunneling work (Main tunnel) between Katra- Banihal Section S/No Agency Scope (m) (m) during the month (m) 1 KRCL IRCON NR Work Completed 4 Total of tunneling work (Escape tunnel) between Katra- Banihal Section. S/No Agency Scope (m) (m) during the month (m) 1 KRCL IRCON NR 0 0 Work Completed 4 Total

2 1.5 Status of Bridges between Katra- Banihal Section. Agency KRCL IRCON NR Major Minor Total Work in progress Work completed 5 (Minor) 3 (Major) 1 Major + 3 Minor Work yet to start 1 (Br.60) 6 (Br. 61 & Br 1 to 5) Total bridges in Katra-Banihal section : 37 (26 Major + 11 Minor) 2. Important achievements during the month 2.1 Earth Work Earth work and protection work is in progress in Sangaldan station yard, out of 23,60,000 Cum of total quantity 22,67,183 Cum has been done so far. 2.2 Tunneling i. of underground excavation achieved in various tunnels are as follows, 0 of main tunnels (m) of escape tunnels (m) Sr. No. Tunnel During this During this Cumulative Cumulative Month Month 1 T T T T T T T T T T-74R T-77D Total

3 ii. of lining achieved during this month is as follows S/No. Tunnel Scope (m) during this month (m) Cumulative progress (m) (%) 1 T % 2 T % 3 T % 4 T % 5 T % 6 T % 7 T % 9 T-74R % Total Lining iii. of tunnel works/agency wise is as follows, Main Tunnel S/No Agency Scope (m) (m) Balance (m) (%) 1 KRCL IRCON NR Total Escape Tunnel S/No Agency Scope (m) (m) Balance (m) (%) 1 KRCL IRCON NR No scope 4 Total

4 iv. Tunneling progress ( ) Tunnel ( ) Month Main Tunnel (m) Escape Tunnel (m) KRCL IRCON Total KRCL IRCON Total Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Total Linear progress of tunnel excavation (main +escape) for Tunnel Excavation (Main Tunnel) KRCL IRCON Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 4

5 Tunnel Excavation (Escape Tunnel) KRCL IRCON Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 S/No. Tunnel April May June July Total ( ) 1 T-1 Main (m) T-5 Main (m) Escape (m) T-48 Main (m) Escape (m) T-49 Main (m) Escape (m) T-50 Main (m) T- Main (m) R Escape (m) T-15 Main (m) Escape (m) T-2 Main (m) Escape (m) T-13 Main (m) Escape (m) T- 77D Main (m) T-14 Main (m) Escape (m) Total (MT+ET) Total ( ):7362m 5

6 2.3 Ballastless Track (BLT) Nil 2.4 Bridges of bridges between Katra- Banihal section has been shown in Table Miscellaneous Nil 2.6 Chenab Bridge of Chenab Bridge has been summarized in table below: Item Slope Stabilization (Earth Work) Fabrication of Deck Segments Fabrication of Main Arch, Piers & Trestles Launching and Erection of Superstructure Deck Segments Launching of Main Arch, Piers & Trestles Financial Unit of Chenab Bridge: (KRCL) Total Quantity Achieved up to 31/03/18 Balance on 1/4/18 Target for Monthly July for F.Y Cum Balance of Nos/MT 164/ / / /545 15/ MT Nos Nos Trestles Trestles Cr Total expenditure (July 2018) : Cr. 6

7 2.7 Major Contract Awarded All major contract awarded. 2.8 Major Tender Invited/Under Finalisation/Under process Work of balance road Barala to Ind-Tatsun Nala awarded on to M/s ECI Engineering & Construction Co. Ltd. at a total cost of Rs Cr The work for strengthening and improvement to the existing approach road from Sangaldan to Barala for T-15 has been awarded to M/s SRM Contractor Pvt. Ltd.. on for a total cost of Cr Tender for widening and strengthening of 10 km PMGSY road from Sumber to Bajmasta and 3km road from Bajmasta to Urnihal is floated at a tender cost of Rs Cr. 2.9 Budget and Expenditure Abstract Cost = Cr Last Sanctioned Cost = Cr (CCEA Approved 2010) Latest anticipated Cost = 27,949 Cr Budget out lay for (USBRL Project) = 1900 Cr Up to date expenditure = Rs Cr. (Since inception) 7

8 2.9.6 Break up of expenditure under major Plan heads is detailed as under SN Plan Head Total Expenditure up to March 2018 (Cr.) Outlay (Cr.) Year Expenditure up to July 2018 (Cr.) % Expenditure 1 New Line (8300) Expenditure :- NR=73 Cr., KRCL=352 Cr., IRCON= 303 Cr Booking details as shown by USBRL finance : S/No. Section Cost (As per detailed estimate) CCEA Cost (Cr.) Booking up to July Udhampur- Katra Katra- Banihal Banihal-Quazigund Quazigund- Baraumulla Total

9 Expenditure incurred by IRCON and KRCL ( ) Planning of expenditure during ( ) Month ( ) IRCON KRCL Target (Cr.) Acheived (Cr.) Target (Cr.) Acheived (Cr.) April May June July August 90 September 100 October 100 November 110 December 110 January 120 February 125 March 142 Total

10 3. Katra-Banihal Section ( in Details) 3.1 For construction convenience and monitoring, this section has been divided into following legs, A. Katra Banganga (km ): Executed by Northern Railway. The work is in progress in full length. The progress of various items is Table-3. B. Km (KRCL, except 33 to 39 and 61 to 91 as transferred to IRCON): of underground excavation for various tunnels being executed by KRCL are shown in Table 1. C. Km : Executed by M/s IRCON. of underground excavation for various tunnels being executed by IRCON are shown in Table Chenab Bridge, Br. No. 44 (KRCL) Chenab Bridge has been divided in four parts for construction point of view, these are A. Construction of Arch Portion (S-10 to S-70) B. Construction of Viaduct Portion (S-70 to S-180) C. Slope Stabilization - Bakkal end and D. Slope Stabilization - Kauri end A. on Arch Portion (S10 to S70) : a. Design: Design of this portion of the bridge has been completed and proof checked by Proof Consultant except the abutment cap of S-10. b. of the Arch: (i) (ii) RCC work: Concreting of S10 (Except 234 Cum), S20, S30, S40, S50, S60 and S70 (Except Pier Cap) has been completed. Workshop: Arch fabrication work at S-180 and Main span deck fabrication at S180 & Bakkal is under progress. Arch fabrication work at wheels India Ltd., Wardha & Trestle fabrication at AIML, Raipur has been completed. 10

11 iii) on Viaduct Portion (S-70 to S-180): a. Design: Design of all parts in this portion is approved and the drawings have been issued. b. : (i) RCC Work: All completed except the pier cap of S-70. (ii) Superstructure work: Deck of Viaduct consists of steel structures of 65 segments which involves approx MT steel fabrication. Fabrication and Erection of segments from AS07 to AS65 have been completed. B. Slope stabilization Kauri end: In progress C. Slope stabilization - Bakkal end: In progress 4. of bridges between Katra- Banihal section has been shown in Table 3. 11

12 Table 1: Tunnel Details: KRCL S/No. Tunnel No Length (m) Award of Contract this month Cumulative 1 T Jul Remarks Tunnel Excavation in progress KRCL Portion Balance (m) Target Achieved ( ) Scope this month Lining Cumulative Balance (m) Target Achieved ( ) T Mar Tunnel Excavation in T Mar progress T Nov Work Completed 0 Completed Completed 4 T Oct Tunnel Excavation in A T-5 (Escape) progress T Sep Completed T Sep Completed T Sep Completed 0 Completed T Sep Completed T Sep Excavation completed. Lining in progress T Work awarded to M/s Jul-16 HCC on 25/7/16. Work T-13 10A Transferred to KRCL (Escape) 11 T Reflect the part that is T-14 Jul-16 clubbed with T-13 11A (Escape) 12 T-40/ Oct' Work Completed 0 13 T- 42/ Oct' Work Completed 0 14 T-44/ Oct' Work Completed 0 15 T Oct' Work Completed 0 16 T Oct' Work Completed Total (Main Tunnel) Total (Escape) Completed % %

13 Table 2: Tunnel Details: IRCON Sr. No Tunnel No Length (m) Award of Contract this month Cumulative Remarks IRCON Portion Balance (m) Target Achieved ( ) 1 T Tender clubbed with that of T-13 and T-14 T-15. Part clubbed with T-13 1A (Escape) transferred to KRCL T Mar T-15 Work in progress. 2A 9912 Mar (Escape) 3 T Sept, Work in progress T-48 3A 9788 Sept, (Escape) 4 T Dec, Work in progress T-49 4A Dec, (Escape) 5 T June, Completed T-74 R 8600 Oct, Work in progress A T-74 R Escape Tunnel 7413 Oct, Work in progress T Completed Completed 0 Completed 8 T-77 A Completed Completed 0 9 T-77D 1760 July, Work in progress T Completed Completed Completed 0 Scope this month Cumulative Lining Balance (m) Target Achieved ( ) Total (Main Tunnel) Total (Escape Tunnel) % %

14 Table 3: Status of bridge works between Katra-Banihal Section A. PROGRESS OF BRIDGE WORK FOR SECTION KATRA-DHARAM (km ) S. No. Br. No. From Km To Km Type of Bridge Details of Bridge span Remarks Position of brdges from Km 25 to Major 1x34+1x64+1x92+1x64M Completed 2 33 RCC Box 3x3m Completed 3 33A RCC Box 5.2x5.585m Completed 4 34 RCC Box 3x3m Completed i. Bridges with KRCL ( Km ) Steel open web girder 1*24.4 Sub structure completed (Anji Khad) Cable Stayed 1x & Work in progress Composite plate Composite plate 1x24.4+1x61+1x45.7 1x x64+1x53.15 Sub structure completed. Foundation A2, P1,P2, P3, P4, P5 & P6 completed. Pier P1, P2,P4 & P6 completed RCC BOX 1x4x3 (minor) Completed RCC BOX 1*5*5 Completed 14

15 RCC BOX 3x5x5 Work in progress Bridge 1*35+1*53+10*64+1*49 Substructure A2, Pier P4 to P12 Completed. Micro Pilling for P-3 completed. 8 44(Chenab bridge) and arch bridge 1*55+2*65+10*48+1*65+1*55+1*40+9*50+1*40 Work in progress, details at Composite Plate Composite Plate 3x30.5m 1x24.4m, Sub structure completed.. Sub structure completed. Erection of Steel Completed Composite Plate 1x24.4m Sub structure completed. Erection of Steel Completed Composite Plate Composite Plate 1x24.4m 3x30.5m Sub structure completed. Erection of Steel Completed. Sub structure completed Composite Plate 1x30.5+1x45.7+1x30.5 Abutment A-1 & A-2 completed. P-2 Foundation completed Composite Plate (CPG) 2x30.5(CPG)+2x61(CT)+1x30.5 (CPG)+1X18.3(CPG)m=231.8m, GT investigation completed, work awarded. GAD to be finalised. 15

16 +composite truss +CPG+CPG RCC BOX 2x3x2m (minor) Work in RCC BOX 2x(3x3) (minor) Completed STEEL GIRDER 1x45.7+3x61+1x45.7 A-1, A-2 & P4 completed. Foundation P1 Completed A RCC BOX 1x(3x3) m (minor) Completed COMPOSITE GIRDER 3x61.0 m+1x45.7 m A-1 completed & A2 Foundation completed A RCC BOX 1x3x3M (minor) Completed 16

17 ii. Bridges with IRCON Composite Plate 1x18.3+1x24.4+x30.5m=73.2m Steel 1x Composite Steel Composite Steel RCC Box for rock protection 11x39 8x39 1x35.0 GT investigation completed, work awarded. GAD finalised. GAD finalised. Resources for substructure is being moblised Well Foundation of P-2 is in progress. GAD Approved, Work Awarded GAD approved. Resources for substructure is being moblised RCC Box 1x5 GAD Approved, Work Awarded Steel 1x30.5+1x45.7+2x30.5 Completed Old Ch Composite 3x30.5 Foundation work in progress Old Ch Steel 3x30.48 Completed Old Ch Steel 2x25.6m Completed 17

18 5. of land acquisition in various stretches of Udhampur - Srinagar- Baramulla New Line is enclosed as, Annexure-I भवद य ( ववजय शर म ) 18

19 Annexure-1: Details of land acquisition upto the month of July 2018 for USBRL Project A) Land Acquisition details for Jurisdiction of Dy. CE s Revenue Land Diversion Forest Land S.No Jurisdiction Already Acquired Under Process Total Already Acquired Under Process Total 1 Dy.CE/Banihal (Banihal- Dharam) (Banihal- Baramulla) Dy.CE/Sang Dy.Ce/Reasi Dy.CE/UHP Dy.CE/Anji Dy.CE/Chenab Total B) Abstract of Land Acquisition Status of USBRL: Description Total Land Required (Hectare) Already Acquired (Hectare) Balance (Hectare) Percentage Balance Revenue/ Private Land % Diversion of Forest Land % Total % 19

20 Annexure-II Financials- USBRL Year Estimate Cost (Rs. Crore) Pink Book DPR CCEA Approved Cost Latest Estimate S/No. Section Estimated Cost (Cr.) Remarks 1 UHP- Katra nd Revised Completion cost (with associate finance) 2 Katra (Km 25)-Km Detailed estimate of Banihal- Quazigund Detailed estimate of Quazigund- Baramulla nd Revised Katra (Km 30)- Banihal with Rly. Board 6 USBRL Project Cost Crores Booking up to July-2018 S/No. Section Cost (As per detailed estimate) CCEA Cost (Cr.) Booking up to July Udhampur- Katra Katra- Banihal Banihal-Quazigund Quazigund- Baraumulla Total

PCDO. May Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project

PCDO. May Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project PCDO May-2018 Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project Northern Railway vuqjkx dqekj lpku vkbzvkj,lb Anurag Kumar Sachan

More information

PCDO. April Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project

PCDO. April Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project PCDO April-2018 Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project Northern Railway vuqjkx dqekj lpku vkbzvkj,lb Anurag Kumar Sachan

More information

No. Secy.CAO/USBRL/JAT/PCDO Dated: 10/10/2018

No. Secy.CAO/USBRL/JAT/PCDO Dated: 10/10/2018 व जय शर म vkbzvkj,lb Vijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 10/10/2018 Sub: PCDO for the Month of Sep, 2018. 1. Highlights of the month of Sep, 2018. 1.1 Principal Executive Director/Bridges,

More information

No. Secy.CAO/USBRL/JAT/PCDO Dated

No. Secy.CAO/USBRL/JAT/PCDO Dated lqjsunz dksy आईआरएसइ Surinder Kaul IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated 06.11.2013 Sub: PCDO for the Month of October,2013 Public Accounts Committee visited the project area and discussed the Audit Report

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

Chenab Bridge, India Design and Construction Oslo

Chenab Bridge, India Design and Construction Oslo Chenab Bridge, India Design and Construction 6.11.2017 - Oslo Contents: 1. Location and Terrain 2. Bridge Concept 3. Some Exceptional Design Parameters 4. Wind Engineering 5. Detailed Design 6. Construction

More information

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309

More information

DHUKWAN SHEP (24 MW) (UNDER CONSTRUCTION ON RIVER BETWA IN BABINA, DISTT. JHANSI, UP)

DHUKWAN SHEP (24 MW) (UNDER CONSTRUCTION ON RIVER BETWA IN BABINA, DISTT. JHANSI, UP) DHUKWAN SHEP (24 MW) (UNDER CONSTRUCTION ON RIVER BETWA IN BABINA, DISTT. JHANSI, UP) Dhukwan HEP is being constructed at the toe of existing Dhukwan masonry cum earthen dam across Betwa river. The 8.22

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE PHASE 2 AS OF OCTOBER 31, 2015 DECEMBER 2015 Phase 2 Cost Summary October Expenditures $ 21.9 Million Total Expenditures $ 569.2 Million

More information

COMPANY PROFILE. SPACE ENGINEER S CONSORTIUM (P) LTD.

COMPANY PROFILE.   SPACE ENGINEER S CONSORTIUM (P) LTD. COMPANY PROFILE www.seclindia.com SPACE ENGINEER S CONSORTIUM (P) LTD. ABOUT US Space Engineers Consortium (P) Ltd is a growing full-fledged service provide in engineering consultancy, Soil investigations

More information

Non-consolidated Forecast of Income <1>

Non-consolidated Forecast of Income <1> Supplementary Materials, Financial Results for Nine Months Ended December 31, 20 Non-consolidated Forecast of Income FY Forecast FY Forecast Change Current Previous (in Oct.) (A) (B) (A)-(B) Operating

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2016 MARCH 2016 Phase 2 Cost Summary January Expenditures $ 8.8 Million Total Expenditures $ 664.4 Million Total

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF FEBRUARY 29, 2016 APRIL 2016 Phase 2 Cost Summary February Expenditures $ 25.7 Million Total Expenditures $ 690.1 Million

More information

Woking. q business confidence report

Woking. q business confidence report Woking q1 business confidence report Woking q1 report headlines saw a new record in company registrations in Woking when compared to any previous. was a record quarter for company registrations in Woking

More information

CHAPTER 19 RAILWAYS. Europe * %

CHAPTER 19 RAILWAYS. Europe * % CHAPTER 19 RAILWAYS 19.1 Railways in the World : Statistics from International Union of Railways, UIC members does not indicate much change in both passenger & freight traffic (in terms of passenger/tonnes

More information

University of Michigan Eco-Driving Index (EDI) Latest data: August 2017

University of Michigan Eco-Driving Index (EDI)   Latest data: August 2017 University of Michigan Eco-Driving Index () http://www.ecodrivingindex.org Latest data: August 2017 Developed and issued monthly by Michael Sivak and Brandon Schoettle Sustainable Worldwide Transportation

More information

e-procurement in Karnataka Presentation for Euro-African Delegation 2 nd December 2009

e-procurement in Karnataka Presentation for Euro-African Delegation 2 nd December 2009 e-procurement in Karnataka Presentation for Euro-African Delegation 2 nd December 2009 Karnataka a snap shot Karnataka No. of Districts: 29 No. of Talukas: 177 No. of Departments: 48 No. of Tier-1 Cities

More information

MONITORING REPORT. Biomass in Rajasthan Electricity Generation from Mustard Crop Residues Reference no. UNFCCC CDMP

MONITORING REPORT. Biomass in Rajasthan Electricity Generation from Mustard Crop Residues Reference no. UNFCCC CDMP MONITORING REPORT Biomass in Rajasthan Electricity Generation from Mustard Crop Residues Reference no. UNFCCC 00000058-CDMP Project Site: Chak 27 BB, Tehsil Padampur, Distt.- SriGanganagar (Rajasthan)

More information

Traffic Department Anchorage: Performance. Value. Results.

Traffic Department Anchorage: Performance. Value. Results. Traffic Department Anchorage: Performance. Value. Results. Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements.

More information

HARDY AND KIDD ACID DRAINAGE AND METAL LEACHING HISTORIES: CONTRASTS AND COMPARISONS

HARDY AND KIDD ACID DRAINAGE AND METAL LEACHING HISTORIES: CONTRASTS AND COMPARISONS HARDY AND KIDD ACID DRAINAGE AND METAL LEACHING HISTORIES: CONTRASTS AND COMPARISONS Ronald V. Nicholson,Ph.D. Stantec Consulting Ltd. 1 th Annual BC ML/ARD Workshop Vancouver, December 2-3, 23 THE ARD

More information

COMPLICATIONS IN CONSTRUCTION OF METROS IN URBAN AREAS A CASE STUDY OF HYDERABAD METRO. C.Sankarlingam Vice President L & T Ltd.

COMPLICATIONS IN CONSTRUCTION OF METROS IN URBAN AREAS A CASE STUDY OF HYDERABAD METRO. C.Sankarlingam Vice President L & T Ltd. COMPLICATIONS IN CONSTRUCTION OF METROS IN URBAN AREAS A CASE STUDY OF HYDERABAD METRO 2 0 1 7 C.Sankarlingam Vice President L & T Ltd. Abstract Project Brief: Hyderabad is located in the state of Telangana

More information

KONKAN RAILWAY CORPORATION LIMITED NOTIFICATION No. CO/P-R/07/2016

KONKAN RAILWAY CORPORATION LIMITED NOTIFICATION No. CO/P-R/07/2016 KONKAN RAILWAY CORPORATION LIMITED NOTIFICATION No. CO/P-R/07/2016 Konkan Railway Corporation Limited, a Public Sector Undertaking under Ministry of Railways, invites application from dynamic, experienced

More information

Chapter 6 Planning and Controlling Production: Work-in-Process and Finished-Good Inventories. Omar Maguiña Rivero

Chapter 6 Planning and Controlling Production: Work-in-Process and Finished-Good Inventories. Omar Maguiña Rivero Chapter 6 Planning and Controlling Production: Work-in-Process and Finished-Good Inventories Learning Objectives At the end of the class the student will be able to: 1. Describe the production budget process

More information

CAC Meeting Construction Update April 8, 2014

CAC Meeting Construction Update April 8, 2014 CAC Meeting Construction Update April 8, 2014 Period Summary There have been over 1,000,000 craft hours completed, excluding demolition, through March 31, 2014. An increase of nearly 50,000 hours since

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2016 FEBRUARY 2017 Phase 2 Cost Summary December Expenditures $ 79.6 Million Total Expenditures $ 1.068 Billion

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2015 FEBRUARY 2016 Phase 2 Cost Summary December Expenditures $ 62.9 Million Total Expenditures $ 655.6 Million

More information

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot

More information

TENDER DOCUMENT. TENDER No.: BHI/PI-(S)/675/1005 FOR

TENDER DOCUMENT. TENDER No.: BHI/PI-(S)/675/1005 FOR TENDER DOCUMENT TENDER No.: BHI/PI-(S)/675/1005 FOR Tender for Construction of Civil works above pile cap for 5 Nos of RCC Mixing Bins (Silos) of Storage Capacity 500MT (each) and columns, beams independent

More information

Electric Forward Market Report

Electric Forward Market Report Mar-01 Mar-02 Jun-02 Sep-02 Dec-02 Mar-03 Jun-03 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 May-05 Aug-05 Nov-05 Feb-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Apr-08 Jun-08 Sep-08 Dec-08

More information

AUSTIN AREA SUMMARY REPORT ON BUSINESS February 2018

AUSTIN AREA SUMMARY REPORT ON BUSINESS February 2018 INSTITUTE FOR SUPPLY MANAGEMENT- ISM AUSTIN, INC. P.O. Box 26155 Austin, Texas 78755-0155 Steven Leatherwood, CPSM, MCIPS Econ-report@ism-austin.org AUSTIN AREA SUMMARY REPORT ON BUSINESS Region Economy

More information

Traffic Division Public Works Department Anchorage: Performance. Value. Results.

Traffic Division Public Works Department Anchorage: Performance. Value. Results. Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements. Direct Services Design, operate and maintain the

More information

Qatar Rail Doha Metro

Qatar Rail Doha Metro Qatar Rail Doha Metro Dr. Ing. Markus Demmler Stakeholders 11 6 JVs with international companies Project Management Consultants About Qatar Rail Following its establishment in 2011, Qatar Rail is leading

More information

MONTHLY PROGRESS REPORT NO. 98 FOR THE MONTH OF: JUNE,

MONTHLY PROGRESS REPORT NO. 98 FOR THE MONTH OF: JUNE, Six Laning of Chennai Tada section of NH-5 From Km.11+000 To Km.54+400 in the State of Tamil Nadu to be executed as BOT (Toll) on DBFO Pattern under NHDP Phase V Independent Engineer SNC Lavalin International

More information

: Dr. B D V CHANDRA MOHAN RAO. :

: Dr. B D V CHANDRA MOHAN RAO. : Name Designation Department Mail Id : Dr. B D V CHANDRA MOHAN RAO : Professor : Civil : chandramohanrao_bdv@vnrvjiet.in, bdvcmrao@gmail.com Experience (in years) : Teaching 21, Research 2, Others (If any,

More information

5 Star London Hotels - Example Report

5 Star London Hotels - Example Report 5 Star London Hotels - Example Report January 2018 CONTENTS Your Benchmark Report Website Traffic Conversion Rates Ecommerce Performance AdWords Spend Your Traffic Index Your Conversion Rate Index Your

More information

Administration Division Public Works Department Anchorage: Performance. Value. Results.

Administration Division Public Works Department Anchorage: Performance. Value. Results. Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,

More information

Ahmedabad Gandhinagar Metro - MEGA, Ahmedabad. Construction of Helipad Building at V. S. Hospital, Ahmedabad

Ahmedabad Gandhinagar Metro - MEGA, Ahmedabad. Construction of Helipad Building at V. S. Hospital, Ahmedabad Birla Vishvakarma Mahavidyalaya Engineering College, V. V. Nagar 388120 A Report on Industrial/Site Visit Ahmedabad Gandhinagar Metro - MEGA, Ahmedabad Construction of Helipad Building at V. S. Hospital,

More information

Creating Solutions Together The Construction Of The Waiwera Viaduct

Creating Solutions Together The Construction Of The Waiwera Viaduct Waiwera bridge The Construction Of The Waiwera Viaduct Solving the Construction Of Waiwera Bridge Using Balanced Cantilever and Matched Precast Segmental Erection Via Overhead Gantry By David Trayner VSL

More information

STATUS OF MAJOR PROJECT INVESTMENTS BRIEFING TO INLAND WATERWAYS USERS BOARD

STATUS OF MAJOR PROJECT INVESTMENTS BRIEFING TO INLAND WATERWAYS USERS BOARD STATUS OF MAJOR PROJECT INVESTMENTS BRIEFING TO INLAND WATERWAYS USERS BOARD February 20, 2009 Sandy Gore Project Programs Team 1 $ Million 450 400 350 300 250 200 150 100 50 0-50 -100-150 IWTF HISTORY

More information

Terms of Reference Governance Committee

Terms of Reference Governance Committee 1. Purpose Terms of Reference Governance Committee The Governance Committee is responsible for ensuring that BC Assessment and its Board develop and implement an effective approach to corporate governance.

More information

City of San Clemente Water Usage Report

City of San Clemente Water Usage Report Monthly Usage (AF) ACRE FEET City of San Clemente Overview of Usage FY 217-18 Monthly Water Use Type of Supply Total MWDOC 723 722 657 629 - - - - - - - - 2,731 Local Groundwater 33 23 69 84 - - - - -

More information

Appendix C. Construction Programme

Appendix C. Construction Programme Appendix C Construction Programme Activity ID Activity Name Orig Dur Planned Start Planned Finish Revision 2 827d 14-Oct-13 31-Jul-16 0d Preliminaries 827d 14-Oct-13 31-Jul-16 0d Total Float Contract Key

More information

Metro Link Express for Gandhinagar and Ahmedabad (MEGA) Company Limited (50:50 SPV of GOI and GOG)

Metro Link Express for Gandhinagar and Ahmedabad (MEGA) Company Limited (50:50 SPV of GOI and GOG) No. MEGA/HR/RECT/TECH/6-2017/01 Date: 21 st June, 2017 RECRUITMENT NOTIFICATION FOR APPOINTMENT ON CONTRACT BASIS Metro Link Express for Gandhinagar and Ahmedabad (MEGA) Co. Limited, a 50:50 Special Purpose

More information

DELHI METRO RAIL CORPORATION LTD. Contract No: - AMCC-02

DELHI METRO RAIL CORPORATION LTD. Contract No: - AMCC-02 DELHI METRO RAIL CORPORATION LTD. Contract No: - AMCC-02 Contract: AMCC-02: Part design and construction of elevated viaduct (chainage km 1.338 1.458 to km 6.577 6.546) and five elevated stations viz.,

More information

Analyst Meet Siemens Ltd. November 23, 2012

Analyst Meet Siemens Ltd. November 23, 2012 Analyst Meet 2011-12 Siemens Ltd. November 23, 2012 Operational Highlights Financial Analysis Future Outlook Economy facing rough weather 12.9 3832 108 3169 3446 79 15.5 9.6 9.3 6.7 New Investments 127

More information

I2-0 LIST OF ACTIVE SSDs

I2-0 LIST OF ACTIVE SSDs I2-0 0002.0001 Structural Standard Drawings - Layering Structure Aug 1, 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details Jun 1, 2002 Jul 17, 2002 0007.0002 Grout Vent Detail Mar 1, 2006

More information

WELCOME CHAMERA-I DAM

WELCOME CHAMERA-I DAM WELCOME CHAMERA-I DAM HYDRO POWER A CLEAN, GREEN & SUSTAINABLE POWER LEAST GENERATION OF GREEN HOUSE GASES WATER SECURITY SPINNING RESERVE DEVELOPMENT OF REMOTE AREA OF THE COUNTRY FLOOD MODERATION INCORPORATED

More information

PROGRESS MEERUT PROJECT AS ON 18 JAN 18

PROGRESS MEERUT PROJECT AS ON 18 JAN 18 1. The balance work has been awarded to M/s Umaxe Projects Pvt Ltd on 30 Nov 2017. 2. Work has commenced by the contactor on 10 Dec 2017 as per the agreement. 3. The contractor has mobilized the men and

More information

BRIHANMUMBAI MAHANAGARPALIKA

BRIHANMUMBAI MAHANAGARPALIKA BRIHANMUMBAI MAHANAGARPALIKA PROJECTS SANCTIONED UNDER JNNURM A] IV Mumbai - Middle Vaitarna Water Supply Project :- Municipal Corporation of Greater Mumbai (MCGM) has undertaken the Middle Vaitarana Water

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF APRIL 30, 2016 JUNE 2016 Phase 2 Cost Summary April Expenditures $ 17.5 Million Total Expenditures $ 739.6 Million Total

More information

MATERIALS AND SUPPLIES INVENTORY

MATERIALS AND SUPPLIES INVENTORY Filed: August, 0 EB-0-0 Exhibit D Schedule Page of MATERIALS AND SUPPLIES INVENTORY.0 STRATEGY Hydro One Distribution is committed to optimizing materials and supplies inventory in support of our customer

More information

Potential Impact of Biomass Burning on Urban Air Quality: Case-study of Chiang Mai

Potential Impact of Biomass Burning on Urban Air Quality: Case-study of Chiang Mai Potential Impact of Biomass Burning on Urban Air Quality: Case-study of Chiang Mai Sébastien Bonnet, Narongchai Suwanprik and Savitri Garivait The Joint Graduate School of Energy and Environment Chiang

More information

Construction of the Superstructure of Major Sea Crossings

Construction of the Superstructure of Major Sea Crossings Construction of the Superstructure of Major Sea Crossings Matt Carter Associate Director 2 nd International Seminar on Design & Construction of Second Penang Bridge 2 Second Penang Bridge Donghai Bridge

More information

DETAILS OF CONTRACTS PLACED ON NOMINATION/SINGLE TENDER BASIS (For Civil Engg. /Elect. Engg. /S & T/Mech. etc works)

DETAILS OF CONTRACTS PLACED ON NOMINATION/SINGLE TENDER BASIS (For Civil Engg. /Elect. Engg. /S & T/Mech. etc works) DETAILS OF CONTRACTS PLACED ON NOMINATION/SINGLE TENDER BASIS (For Civil Engg. /Elect. Engg. /S & T/Mech. etc works) (Status for the Month : From APRIL 2012 To MARCH 2013) s Awarded : APRIL 2012 LOA and

More information

DATE: JANUARY 24, 2018 HERITAGE VALLEY POLICY ADVISORY COMMITTEE (HVTAC) HEATHER MILLER, TRANSIT PLANNER KEY PERFORMANCE INDICATORS (KPI) REPORT

DATE: JANUARY 24, 2018 HERITAGE VALLEY POLICY ADVISORY COMMITTEE (HVTAC) HEATHER MILLER, TRANSIT PLANNER KEY PERFORMANCE INDICATORS (KPI) REPORT DATE: JANUARY 24, 2018 MEMO TO: FROM: SUBJECT: HERITAGE VALLEY POLICY ADVISORY COMMITTEE (HVTAC) HEATHER MILLER, TRANSIT PLANNER RECOMMENDATION Receive and file report. BACKGROUND In mid-august 2017, service

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2017 MARCH 2017 Phase 2 Cost Summary January Expenditures $ 10.6 Million Total Expenditures $ 1.078 Billion

More information

Technical Talk on HK s Largest Solar Power System at Lamma Power Station

Technical Talk on HK s Largest Solar Power System at Lamma Power Station 15 June 2011 Technical Talk on HK s Largest Solar Power System at Lamma Power Station for HKIE EV Division by C.K. Lau Agenda Fundamentals of PV Project Background Feasibility Study and Site Selection

More information

Tanahu Hydropower Limited

Tanahu Hydropower Limited Tanahu Hydropower Limited (A subsidiary company of Nepal Electricity Authority) Trade Tower Building, 4th Floor, Thapathali, Kathmandu, Website: http://www.thl.com.np NEWS LETTER - 073/074 06 February,

More information

College Football Hall of Fame HAMMOCK R

College Football Hall of Fame HAMMOCK R - Contract Schedule MILESTONES DESIGN / PRECONSTRUCTION PROCUREMENT Construction Procurement CONSTRUCTION Hardscape / Landscape Hall Of Fame Building Sitework Earthwork A1060 Mobilize 5 18-Feb-13 A 22-Feb-13

More information

Arlington East WRF Influent Channel Rehabilitation - Final

Arlington East WRF Influent Channel Rehabilitation - Final T E C H N I C A L M E M O R A N D U M 135-11 ARLINGTON EAST WRF INFLUENT CHANNEL 135-11 Arlington East WRF Influent Channel Rehabilitation - Final PREPARED FOR: PREPARED BY: JEA Capital Budget Planning

More information

Norwegian Timber Bridges: Current Trends and Future Directions Erik Aasheim

Norwegian Timber Bridges: Current Trends and Future Directions Erik Aasheim Norwegian Timber Bridges: Current Trends and Future Directions Erik Aasheim Topic areas Basis for timber bridge construction Typical construction elements Protection measures Possibilities in design and

More information

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends

More information

Feasibility Report Madian Hydropower Project. Conclusions and Recommendations. 7166P02/Vol. II, Recommendations

Feasibility Report Madian Hydropower Project. Conclusions and Recommendations. 7166P02/Vol. II, Recommendations 13 Conclusions and Recommendations 7166P02/Vol. II, Recommendations Table of Contents 13. Conclusions and Recommendations 13-1 13.1 Conclusions 13-1 13.2 Summary of Results of Feasibility Study 13-2 13.3

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF MARCH 31, 2015 MAY 2015 0 Phase 2 Cost Summary March Expenditures $ 21.8 Million Total Expenditures $ 422.6 Million

More information

Sr No Description Page No

Sr No Description Page No Contents Sr Description Page 1 About the Index 3 2 Carbon Intensity Estimation Methodology 4 3 Index Methodology 6 4 Index Performance 8 5 Frequently Asked Questions 10 6 Contact 12 2 About the Index The

More information

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT 325.0 957 100.130 F.L.=99.780 12205 2300 2300 2300 2720 125 EXPANSION GAP 125 EXPANSION GAP OUTER COVER PLATE 640X40X1070 938.5 1350 1350 1350 1282.5 1350 1350 1122.5 1350 1356.5 1356.5 1350 1122.5 1350

More information

KONKAN RAILWAY CORPORATION LIMITED. NOTIFICATION No.CO/P-R/10/2017

KONKAN RAILWAY CORPORATION LIMITED. NOTIFICATION No.CO/P-R/10/2017 KONKAN RAILWAY CORPORATION LIMITED NOTIFICATION No.CO/P-R/10/2017 Konkan Railway Corporation Limited, a Public Sector Undertaking under Ministry of Railways, invites application from dynamic, experienced

More information

Making a Dramatic Impact on Water Loss. Robert Horvat, PE cell:

Making a Dramatic Impact on Water Loss. Robert Horvat, PE cell: Making a Dramatic Impact on Water Loss Robert Horvat, PE rhorvat@entecheng.com cell: 412-759-3140 Overview The Problem Management 3 Success Stories Water Loss the problem EPA Fact Sheet: Water Audits and

More information

DELHI METRO RAIL CORPORATION LTD. Contract No: - AMCC-01

DELHI METRO RAIL CORPORATION LTD. Contract No: - AMCC-01 DELHI METRO RAIL CORPORATION LTD. Contract No: - AMCC-01 Contract: AMCC-01: Part design and construction of elevated viaduct (chainage km 6.577 6.546 to km 12.689), depot connection and six elevated stations

More information

GOVERNMENT OF INDIA MINISTRY OF STATISTICS AND PROGRAMME IMPLEMENTATION CENTRAL STATISTICS OFFICE New Delhi Dated: November 12, 2014 PRESS RELEASE

GOVERNMENT OF INDIA MINISTRY OF STATISTICS AND PROGRAMME IMPLEMENTATION CENTRAL STATISTICS OFFICE New Delhi Dated: November 12, 2014 PRESS RELEASE GOVERNMENT OF INDIA MINISTRY OF STATISTICS AND PROGRAMME IMPLEMENTATION CENTRAL STATISTICS OFFICE New Delhi Dated: November 12, 2014 PRESS RELEASE QUICK ESTIMATES OF INDEX OF INDUSTRIAL PRODUCTION AND

More information

San Francisco Housing Authority (SFHA) Leased Housing Programs as of January 31, 2016

San Francisco Housing Authority (SFHA) Leased Housing Programs as of January 31, 2016 San Francisco Housing Authority (SFHA) Leased Housing Programs as of January 31, 2016 Table of Contents Program Utilization Summary 3-5 PIC Reporting Rate 6-7 Operational Updates Recertifications and Inspections

More information

Basarab Cable Stayed Bridge in Bucharest

Basarab Cable Stayed Bridge in Bucharest Basarab Cable Stayed Bridge in Bucharest Javier MANTEROLA Pr. Dr. Civil Engineer Carlos Fernández Casado,S.L. Madrid, SPAIN jmanterola@cfcsl.com Antonio MARTÍNEZ Dr. Civil Engineer Carlos Fernández Casado,S.L.

More information

Department of Transportation Rapid City Region Office 2300 Eglin Street P.O. Box 1970 Rapid City, SD Phone: 605/ FAX: 605/

Department of Transportation Rapid City Region Office 2300 Eglin Street P.O. Box 1970 Rapid City, SD Phone: 605/ FAX: 605/ Connecting South Dakota and the Nation Department of Transportation Rapid City Region Office 2300 Eglin Street P.O. Box 1970 Rapid City, SD 57709-1970 Phone: 605/394-2244 FAX: 605/394-1904 July 9, 2014

More information

Raynet Software Lifecycle

Raynet Software Lifecycle Raynet Software End of End of RMSi 10.6 2016-Dec 2018-Dec* 2020-Dec* RMSi 10.5 2016-Jan 2018-Jan 2020-Jan RMSi 10.4 2014-May 2016-May 2018-May RMS/RMSi 10.3 2014-Feb 2016-Feb 2018-Feb RMS/RMSi 10.2 2013-Nov

More information

Long Term Control Plan Consent Decree Status Report: Quarter No

Long Term Control Plan Consent Decree Status Report: Quarter No DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Serving the Public Protecting the Environment Long Term Control Plan Consent Decree Status Report: Quarter No. 3-2013 Consolidated Civil Action No. 1:00CV00183TFH

More information

MONTHLY INSPECTION REPORT

MONTHLY INSPECTION REPORT NATIONAL HIGHWAYS AUTHORITY OF INDIA (Ministry of Road Transport and Highways) Government of India Four Laning of Hajipur-Muzaffarpur Section of N.H- 77 from Km. 0.000 to Km. 46.300 and construction of

More information

Indo-Swiss Building Energy Efficiency Project. Case Study: Aranya Bhawan, Jaipur

Indo-Swiss Building Energy Efficiency Project. Case Study: Aranya Bhawan, Jaipur Indo-Swiss Building Energy Efficiency Project Case Study: Aranya Bhawan, Jaipur OVERVIEW Aranya Bhawan, the office building of the Rajasthan Forest Department in Jaipur, was one of the first projects selected

More information

Chakachamna Hydro. AEA Geothermal Conference

Chakachamna Hydro. AEA Geothermal Conference Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings

More information

Raynet Software Lifecycle

Raynet Software Lifecycle Raynet Software End of End of RMSi 11.0 2018-Jun 2020-Jun* 2022-Jun* RMSi 10.6 2016-Dec 2018-Dec 2020-Dec RMSi 10.5 2016-Jan 2018-Jan 2020-Jan RMSi 10.4 2014-May 2016-May 2018-May EOL RMSi 10.3 2014-Feb

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 5484» Total Man Hours on Project: 135019» Crafts On Project This Week: 11» OSHA Recordable Rate: 0 February 28, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST

More information

LIST OF DIRECTIVES AND MEMORANDA

LIST OF DIRECTIVES AND MEMORANDA LIST OF DIRECTIVES AND MEMORANDA Technical Policies and Standards HSBM DO 2014-01 Format and Method for Policies Issued by HSB To provide guidance for the format and method of communicating the implementation

More information

INDIRA GANDHI NATIONAL OPNE UNIVERSITY CONSTRUCTION & M AINTENANCE DIVISION MAIDAN GARHI NEW DELHI

INDIRA GANDHI NATIONAL OPNE UNIVERSITY CONSTRUCTION & M AINTENANCE DIVISION MAIDAN GARHI NEW DELHI ` INDIRA GANDHI NATIONAL OPNE UNIVERSITY CONSTRUCTION & M AINTENANCE DIVISION MAIDAN GARHI NEW DELHI-110068 NOTICE INVITING QUOTATION IG/CMD/NIQ-civil/2014 Dated: - 26/06/2014 Name of work:- Construction

More information

Bidding Strategy I Day-Ahead Market 8 th February 2017 I New Delhi

Bidding Strategy I Day-Ahead Market 8 th February 2017 I New Delhi Bidding Strategy I Day-Ahead Market 8 th February 2017 I New Delhi Rajesh K Mediratta Business Development +91-9654125157 I rajesh.mediratta@iexindia.com 1 For office use In this presentation Type of Market

More information

MOH AND ASSOCIATES, INC., TAIWAN Design of Taiwan Friendship Bridge River Tempisque, Costa Rica

MOH AND ASSOCIATES, INC., TAIWAN Design of Taiwan Friendship Bridge River Tempisque, Costa Rica Design of Taiwan Friendship Bridge River Tempisque, Costa Rica Huat-Yoo Chua Moh And Associates, Inc. Taiwan Jack Chang RSEA Engineering Corporation Taiwan 1. Introduction Taiwan Friendship Bridge spans

More information

Industry Perspective on Well Decommissioning Pennsylvania Orphaned and Abandoned Well Workshop May 16, 2018

Industry Perspective on Well Decommissioning Pennsylvania Orphaned and Abandoned Well Workshop May 16, 2018 Industry Perspective on Well Decommissioning Pennsylvania Orphaned and Abandoned Well Workshop May 16, 2018 Abandoned wells present a significant danger to the public. 2 Understanding the tactical nuances

More information

PRE PROJECT PLANNING : IMPORTANCE IN HOSPITAL PROJECTS

PRE PROJECT PLANNING : IMPORTANCE IN HOSPITAL PROJECTS PRE PROJECT PLANNING : IMPORTANCE IN HOSPITAL PROJECTS Pankaj Kumbhare, Abhijit Warudkar, PG Scholar, Department of Civil Engineering, Imperial College of Engineering and Research, Wagholi, Maharashtra,

More information

Forecasting With History

Forecasting With History Forecasting With History Santiago Gallino Tuck School of Business Toni Moreno Kellogg School of Management January 2017 July 2013 LBS London, UK Learning Modules 1. Demand forecasting 2. Inventory Decisions

More information

Bridge Erection Techniques and their influence on Permanent Designs

Bridge Erection Techniques and their influence on Permanent Designs Bridge Erection Techniques and their influence on Permanent Designs Paper by Er. Vivek G. Abhyankar C.Eng. थ पय तथ व त अभय त Mumbai Abstract : Bridge engineering has significantly grown-up in past 50 years

More information

1.0 CONSUMPTION : The growth (%) in consumption of petroleum products, category-wise, for the month of April, 2015 is given in Table-1.

1.0 CONSUMPTION : The growth (%) in consumption of petroleum products, category-wise, for the month of April, 2015 is given in Table-1. 1 P a g e This report analyses the trend of consumption of petroleum products in the country during the month of April, 2015.Data on product-wise monthly consumption of petroleum products for April, 2015

More information

TL 9000 Quality Management System. Measurements Handbook. BRR Examples

TL 9000 Quality Management System. Measurements Handbook. BRR Examples Quality Excellence for Suppliers of Telecommunications Forum (QuEST Forum) TL 9000 Quality Management System Measurements Handbook Copyright 2012 QuEST Forum Version 1.0 7.2 7.2.1 Basic Calculation Example

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200 GRADING 219.101 Light Duty Straw

More information

Northeast Bridge Preservation Partnership Meeting

Northeast Bridge Preservation Partnership Meeting Northeast Bridge Preservation Partnership Meeting Superstructure Preservation Strategies Aetna Viaduct Superstructure Repairs Route I-84 City of Hartford, CT State Project No. 63-648 David A. Cutler, P.E.

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 13462» Total Man Hours on Project: 268272» Crafts On Project This Week: 17» OSHA Recordable Rate: 0 June 5, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East

More information