1 Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF APRIL 30, 2016 JUNE 2016

2 Phase 2 Cost Summary April Expenditures $ 17.5 Million Total Expenditures $ Million Total Budget $ Billion Total Forecast $ Billion

3 Phase 2 Contingency Utilization Total Contingency Contingency Utilized through March 2016 Contingency Utilized in April 2016 Total Contingency Utilized through April 2016 Remaining Contingency $ Million $ 79.2 Million $ 1.0 Million $ 80.2 Million $ Million

4 April Contingency Utilization Total Contingency Utilized in April 2016 Package A (CRC) $ 1.0 Million $ 0.8 Million Non-pervious asphalt paving at wayside facilities Construction $ 560,000 Replacing the stainless steel mesh panels at elevator hoistways Design & Construction Herndon Station South Area Facilities additional technical clarification Design & Construction Temporary Access to Pacific Boulevard Yard fire hydrant Design & Construction Repair and replacement of the storm drain inlets and clearing of storm drains at Pacific Boulevard Yard Construction (Settled for $65,250) Design changes at Reston Town Center Station due to revised Fairfax County Maintenance Responsibilities outside the pavilion footprint (Settled for $34,000) Incorporation of Loudoun County 30% Design of the Transit Connector Bridge at Ashburn Station (Settled for $60,000) $ 213,000 $ 68,000 $ 45,500 $ 36,250 $ 24,000 $ 20,000

5 April Contingency Utilization Loudoun Gateway north side sanitary sewer outfall revision to $ 9,000 90% Design & Construction Additional Traction Power Load Flow Study (Settled for $62,000) $ (1,000) Automatic Train Control System specification revisions Design & Construction Package B (HP) $ (126,000) $ 0.2 Million Yard Wi-Fi infrastructure change Design $ 68,000 Modifications to the traction power substation ground grid $ 40,000 Design & Construction Changes to pit guardrails for Service and Inspection Building $ 30,000 Design Updates to the requirements for Service and Inspection Building $ 7,000 Electronics Shop Design Traction Power Substation Ground Grid Criteria Study $ 5,000

6 Current Guideway & Stations Design-Build Activities Advancement of Design Packages: Design complete 3 minor, non-schedule critical packages near 100% 7 packages to be Issued for Construction Issued 17 Permit Amendments due to Design Revisions Project Office Review/Approval Activities: 14 Design Change Packages 75 Contractor Submittals 20 Non-Conformance Reports

7 Guideway & Stations Design-Build Activities Set Girders In Yard Leads

8 Guideway & Stations Design-Build Activities Stripping Column Forms East of Dulles Airport

9 Guideway & Stations Design-Build Activities Form and Pour Corbels for Straddle Bent #3

10 Guideway & Stations Design-Build Activities Drill Caissons for Columns at Airport

11 Guideway & Stations Design-Build Activities Precast Panel Installation at Innovation Station

12 Guideway & Stations Design-Build Activities Install Concrete Foundations at Reston Station

13 Guideway & Stations Design-Build Activities Form Herndon Station Columns, Foundations and Walls

14 Guideway & Stations Design-Build Activities Prepare Column Forms at Dulles Station

15 Guideway & Stations Design-Build Activities Utility Tunnel Casing under Rudder Road

16 Upcoming Guideway & Stations Design-Build Activities Reston Station pour foundations and cast in place concrete walls and continue installation of 34.5 KV. Herndon Station Form and pour station foundations and walls and continue installation of underground systems and utilities. Innovation Station Continue station precast element placement and start structural steel vault roof framing. Dulles Station Continue station foundation and aerial guideway substructures, continue walkway retrofit and tie in to Station mezzanine. Aerial Guideway Pour drilled shafts, columns and pier caps; install decks and girders; at the Airport, cast straddle bent #13 and girder support corbels at straddle bent #2.

17 WMATA Rail Yard & Maintenance Facility Design-Build Activities Current Construction of all at grade and underground facilities has been permitted and is proceeding. Initial efforts are concentrated in the Service and Inspection Building (SIB). Final grading, utilities and yard layout continues. Final design of the Project Wide Package scheduled for completion in August.

18 WMATA Rail Yard & Maintenance Facility Design-Build Activities Upcoming Construction of all facilities. Advance Project Wide design documents to 100% and Issue For Permit. Address open WMATA design refinements. Review shop documents and revised design documents. Process open commercial issues.

19 WMATA Rail Yard & Maintenance Facility Design-Build Activities Inspection Pit Foundations SIB Basement Preparation

20 WMATA Rail Yard & Maintenance Facility Design-Build Activities Site Preparation Continues

21 DULLESMETRO.COM

22 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 MONTHLY COST SUMMARY As of April 30, 2016 Description Budget Total Expenditures to Date Contract Contract Amount 1,3 Forecast 2 Amount Total NTP Substantial 4 DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 Percent b c c/b DESIGN-BUILD Package A 1,193,777,000 1,275,937, ,094,822 34% 8-Jul-13 7-Aug-19 DESIGN-BUILD Package B + S 273,280, ,163,930 49,460,303 19% 18-Nov Jun-18 ROW 58,600,000 58,305,000 5,797,664 10% 8-Jul Sep-17 WMATA 305,324, ,324,718 42,929,307 14% N/A 3-Feb-20 PRELIMINARY ENGINEERING 75,000,000 75,000,000 73,266,056 98% 15-Jul Dec-13 PROJECT MANAGEMENT 320,802, ,264, ,035,332 41% N/A 2-Jan-19 CONTINGENCY 551,451, ,240,510 TOTAL FOR DCMP 2,778,235,564 2,778,235, ,583,483 Notes: 1 Budget Amount includes contingency as separate line item and does not include finance costs. 2 Total Forecast includes funded changes. It does not include finance costs. 3 Budget Amount includes commodity escalation of $20 million for Package A & B+S. 4 Package A Contract Substantial Completion date changed from 7-Jul-2018 to 7-Aug-2019

23 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 CONTINGENCY UTILIZATION As of April 30, 2016 ATTA Description Amount in million ($) DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 Total Contingency $ Contingency Utilized through March 2016 $ 79.2 Expended Contingency in April 2016* $ 1.0 Total Contingency Utilized through April 2016 $ 80.2 Remaining Contingency $ *See table below for details Package A (CRC) $0.8 Million Non-pervious Asphalt Paving at Wayside Facilities - Construction $ 560,000 Replacing the Stainless Steel Mesh Panels at Elevator Hoistways - Design and Construction $ 213,000 Herndon Station South Area Facilities Additional technical Clarification - Design and $ 68,000 Construction Temporary Access to Pacific Boulevard Yard Fire Hydrant - Design and Construction $ 45,500 Repairs and Replacement of the Storm Drain Inlets and Clearing of Storm Drains at $ 36,250 Pacific Boulevard Yard - Construction (Settled at $65,250) Design Changes at Reston Town Center Station due to Revised Fairfax County's $ 24,000 Maintenance Responsibilities outside the pavilion footprint (Settled for $34,000) Incorporation of Loudoun County's 30% Design of the Transit Connector Bridge at $ 20,000 Ashburn Station (Settled at $60,000) Loudoun Gateway North Side Sanitary Sewer Outfall - Revision to 90% Design and $ 9,000 Construction Additional Traction Power Load Flow Study (Settled at $62,000) $ (1,000) Automatic Train Control Systems Specification Revisions - Design and Construction $ (126,000) Package B (HP) $0.2 Million Yard WiFi Infrastructure Change - Design $ 68,000 Modifications to the Traction Power Substation Ground Grid - Design and $ 40,000 Construction Changes to Pit Guardrails for Service and Inspection Building - Design $ 30,000 Updates to the Requirements for Service and Inspection Building Electronics Shop - $ 7,000 Design Traction Power Substation Ground Grid Criteria Study $ 5,000

24 Dulles Rail ATTACHMENT 1 Airport Project No Description Budget Amount DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 DESIGN-BUILD Package A DCMP 5401 Package A - Mainline (CRC) 1,177,777,000 DCMP 5406 Commodity Escalation 16,000,000 DCMP 5408 Contingency amount DCMP 5408 Secondary mitgation amount SUBTOTAL - DESIGN-BUILD Package A 1,193,777,000 DESIGN-BUILD Package B+S DCMP 5402 Package B - Yard 269,280,530 DCMP 5402 Package S - Yard Site Preparation incl above DCMP 5406 Commodity Escalation 4,000,000 DCMP 5408 Contingency amount DCMP 5408 Secondary mitgation amount SUBTOTAL - DESIGN-BUILD Package B+S 273,280,530 ROW DCMP 5404 Land & Relocation 47,225,000 DCMP 5404 Support Services 11,375,000 DCMP 5408 Contingency SUBTOTAL - ROW 58,600,000 WMATA DCMP 5405 WMATA Vehicles 205,868,200 DCMP 5405 WMATA other costs 90,205,767 DCMP 5405 WMATA Non Revenue Vehicles 9,250,751 DCMP 5408 Contingency SUBTOTAL - WMATA 305,324,718 PRELIMINARY ENGINEERING DCMP 5406 PRELIMINARY ENGINEERING 75,000,000 SUBTOTAL - PRELIMINARY ENGINEERING 75,000,000 PROJECT MANAGEMENT DCMP 5406 MWAA Staff 34,000,000 DCMP 5406 MWAA Allocated Cost 13,560,000 DCMP 5406 Rent 9,200,000 DCMP 5406 Relocation, IT, Furniture 2,700,000

25 Dulles Rail ATTACHMENT 1 Airport Project No Description Budget Amount DCMP 5406 MWAA ODCs 17,060,000 DCMP 5406 Insurance (OCIP) 49,082,137 DCMP 5406 PMSS 140,000,000 DCMP 5406 VDOT 10,000,000 DCMP 5406 DRC Prof Svcs 2,500,000 DCMP 5406 CTI (Special Inspections) 14,000,000 DCMP 5406 DGS 2,000,000 DCMP 5406 TRIP II 2,000,000 DCMP 5406 Dept of Conservation & Recreation (DCR) 2,000,000 DCMP 5406 MWAA Permits/Inspection 4,000,000 DCMP 5406 Power for System Testing 16,000,000 DCMP 5406 Historical/Archaeologic 2,700,000 DCMP 5408 Contingency SUBTOTAL - PROJECT MANAGEMENT 320,802,137 CONTINGENCY DCMP 5408 Contingency - Package A 289,067,231 DCMP 5408 Secondary mitgation amount - Package A 0 DCMP 5408 Contingency - Package B 109,006,387 DCMP 5408 Secondary mitgation amount - Package B 0 DCMP 5408 Contingency - ROW 5,860,000 DCMP 5408 Contingency - WMATA 30,532,472 DCMP 5408 Contingency Project Management 116,985,089 SUBTOTAL - CONTINGENCY 551,451,179 TOTAL FOR DCMP - PHASE 2 2,778,235,564

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2016 FEBRUARY 2017 Phase 2 Cost Summary December Expenditures $ 79.6 Million Total Expenditures $ 1.068 Billion

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2016 MARCH 2016 Phase 2 Cost Summary January Expenditures $ 8.8 Million Total Expenditures $ 664.4 Million Total

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2015 FEBRUARY 2016 Phase 2 Cost Summary December Expenditures $ 62.9 Million Total Expenditures $ 655.6 Million

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF FEBRUARY 29, 2016 APRIL 2016 Phase 2 Cost Summary February Expenditures $ 25.7 Million Total Expenditures $ 690.1 Million

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2016 NOVEMBER 2016 Phase 2 Cost Summary September Expenditures $ 29.0 Million Total Expenditures $ 901.4 Million

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2017 MARCH 2017 Phase 2 Cost Summary January Expenditures $ 10.6 Million Total Expenditures $ 1.078 Billion

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE PHASE 2 AS OF OCTOBER 31, 2015 DECEMBER 2015 Phase 2 Cost Summary October Expenditures $ 21.9 Million Total Expenditures $ 569.2 Million

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF MARCH 31, 2015 MAY 2015 0 Phase 2 Cost Summary March Expenditures $ 21.8 Million Total Expenditures $ 422.6 Million

More information

Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018

Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 2 Phase 2 Cost Summary September Expenditures $ 19.4 Million Total Expenditures $ 1.868

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASES 1 AND 2 AS OF SEPTEMBER 30, 2014 November 2014 0 Phase 1 Cost Summary September Expenditures $ 2.5 Million Total Expenditures

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President Phase 1 Phase 1 Cost Summary Expenditures (Nov 17 thru Apr 18) Total Expenditures (Thru Apr

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule

More information

Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager

Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager Program Panelist Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager Moderator Kevin Pavuk, Structural Technologies Presentation 5:30 to 7:00 p.m.

More information

Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting

Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting June 22, 2016 Discussion Outline Finance Plan for the Metrorail Project Financial Developments Since December 2015

More information

Dulles Corridor Metrorail Expansion. Providing Safe Transportation for Northern Virginia

Dulles Corridor Metrorail Expansion. Providing Safe Transportation for Northern Virginia Dulles Corridor Metrorail Expansion Providing Safe Transportation for Northern Virginia Overview The Washington D.C. Metrorail is the second busiest rail transit network in the United States, with an average

More information

EVALUATION OF ALTERNATIVES CARRIED FORWARD

EVALUATION OF ALTERNATIVES CARRIED FORWARD 1 EVALUATION OF ALTERNATIVES CARRIED FORWARD This chapter presents a comparative evaluation of the alternatives carried forward in this Final Environmental Impact Statement (EIS). The intent of this evaluation

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF REQUEST FOR PROPOSALS

Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF REQUEST FOR PROPOSALS Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF REQUEST FOR PROPOSALS Metropolitan Washington Airports Authority Procurement and Contracts Dept., MA-29 1 Aviation

More information

Customer Service and Operations Committee. Board Information Item III-B. October 9, 2014

Customer Service and Operations Committee. Board Information Item III-B. October 9, 2014 Customer Service and Operations Committee Board Information Item III-B October 9, 2014 Major Red Line Construction Page 12 of 58 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Doing Business with the Metropolitan Washington Airports Authority

Doing Business with the Metropolitan Washington Airports Authority Doing Business with the Metropolitan Washington Airports Authority MWMCA Quarterly Economic Summit Brown Advisory November 7, 2017 Introduction to MWAA Ronald Reagan Washington National Airport Washington

More information

2016 ACEC/PA ANNUAL MEETING

2016 ACEC/PA ANNUAL MEETING 2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015

More information

Eglinton Crosstown LRT Construction Liaison Committee

Eglinton Crosstown LRT Construction Liaison Committee Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report December 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package A Rail Line, Stations, and Systems February 1, 2013 (Rev. 1 - Issued with Final RFP) Final RFP Statement of Work February

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project

More information

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package A Rail Line, Stations, and Systems March 15, 2013 (Rev. 2 - Issued with Final RFP) Final RFP Statement of Work March

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September

More information

7/30/2014 Correspondence

7/30/2014 Correspondence 7/30/2014 Correspondence July 29, 2014 Mr. Mark Canale Fairfax County 4050 Legato Rd Suite 400 Fairfax, VA 221822228 Project [813C001] Dulles Corridor Metrorail Project, Phase 2 Pkg A Location Code (multi)

More information

APPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED

APPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED APPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED APPENDIX H: ALTERNATIVES PREVIOUSLY CONSIDERED This appendix provides an overview of the process that led to the selection of the Locally Preferred Alternative

More information

M E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y. DTR Toll Collection Overview

M E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y. DTR Toll Collection Overview DTR Toll Collection Overview 1 The Dulles Toll Road A Traditional Tolling Facility * Payment Options * EZ Pass * Exact Change (all coins) * Full Service (but no Credit Card capability) * Some higher (but

More information

LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs)

LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs) LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs) 0002.0001 Structural Standard Drawings - Layering Structure n/a Aug 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details n/a Jun 2002 Jul

More information

COMPREHENSIVE MONTHLY REPORT. September 2010

COMPREHENSIVE MONTHLY REPORT. September 2010 COMPREHENSIVE MONTHLY REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC October 26, 2010 PMOC Contract Number: DTFT60-09-D-00016

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX

More information

College Football Hall of Fame HAMMOCK R

College Football Hall of Fame HAMMOCK R - Contract Schedule MILESTONES DESIGN / PRECONSTRUCTION PROCUREMENT Construction Procurement CONSTRUCTION Hardscape / Landscape Hall Of Fame Building Sitework Earthwork A1060 Mobilize 5 18-Feb-13 A 22-Feb-13

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

I2-0 LIST OF ACTIVE SSDs

I2-0 LIST OF ACTIVE SSDs I2-0 0002.0001 Structural Standard Drawings - Layering Structure Aug 1, 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details Jun 1, 2002 Jul 17, 2002 0007.0002 Grout Vent Detail Mar 1, 2006

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

AMENDED RECORD OF DECISION. by the Federal Transit Administration. Dulles Corridor Metrorail Project Fairfax and Loudoun Counties, Virginia

AMENDED RECORD OF DECISION. by the Federal Transit Administration. Dulles Corridor Metrorail Project Fairfax and Loudoun Counties, Virginia AMENDED RECORD OF DECISION by the Federal Transit Administration Fairfax and Loudoun Counties, Virginia DECISION The Federal Transit Administration (FTA), in accordance with 23 CFR part 771, the regulation

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200 GRADING 219.101 Light Duty Straw

More information

DULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue

DULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue DULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue Submitted to the Federal Transit Administration For Final Design Submitted by Metropolitan Washington Airports Authority In cooperation with

More information

COMPREHENSIVE MONTHLY REPORT. April 2011

COMPREHENSIVE MONTHLY REPORT. April 2011 COMPREHENSIVE MONTHLY REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC May 27, 2011 PMOC Contract Number: DTFT60-09-D-00016

More information

COMPREHENSIVE MONTHLY REPORT. December 2011

COMPREHENSIVE MONTHLY REPORT. December 2011 COMPREHENSIVE MONTHL REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC January 20, 2012 PMOC Contract Number: DTFT60-09-D-00016

More information

Ø Contents of Price Proposal:

Ø Contents of Price Proposal: ATTACHMENT 4.0.1.2 Addendum#1 February 13, 2015 DESIGN-BUILD PRICE PROPOSAL CHECKLIST Project Name: Route 7 Widening and Bridge Rehabilitation over Dulles Toll Road and Airport Access Highway Contract

More information

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR0013844 & BR0013129 COLUMBIA, CHEROKEE COUNTY, SOUTH CAROLINA I-85 UNDERPASS PROJECT (1) REPLACEMENT OF EXISTING I-85 UNDERPASS BRIDGE MILEPOST SB-141.35 DOT/AAR

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report July 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Report to the Dulles Corridor Advisory Committee. Proposed Dulles Toll Road Toll Rate Adjustment. October 2018

Report to the Dulles Corridor Advisory Committee. Proposed Dulles Toll Road Toll Rate Adjustment. October 2018 Report to the Dulles Corridor Advisory Committee Proposed Dulles Toll Road Toll Rate Adjustment October 2018 Purpose The primary purpose of today s briefing is to: review the reasons for periodic adjustments

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

Project Budget And Schedule Status Report

Project Budget And Schedule Status Report Item 47 Project Budget And Schedule Status Report Presented by Brian Boudreau Executive Director, Program Management Construction Committee June 18, 2015 & Schedule Performance Summary Chart Slide # Project

More information

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 58 Transit Program Project Budget and Schedule Status Report Construction Committee October 16, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments

More information

Results you can rely on

Results you can rely on z 1 I-49 North Segment K Project 2 AGENDA PROJECT OVERVIEW BRIDGE DESIGN ARCHITECTURAL ENHANCEMENTS SPECIAL PROVISIONS COST ESTIMATE AND FINAL BIDS CONSTRUCTION 3 SITE LOCATION PROJECT SITE ARKANSAS 185

More information

G2-0 LIST OF ACTIVE MTODs

G2-0 LIST OF ACTIVE MTODs G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw

More information

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435

More information

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package P Stormwater Management Facilities February 13, 2017 Rev. 0 Statement of Work February 13, 2017 THIS PAGE INTENTIONALLY

More information

Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. January 2011

Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. January 2011 Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Annual Report TABLE OF CONTENTS

More information

Technical Assignment 2

Technical Assignment 2 Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive

More information

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT FY 15-20 CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT Department of Public Works Robert B. Boxer, Director PROJECT MODEL PROFESSIONAL SERVICES STUDIES FEASIBILITY CLAIMS 1- PROJECT DEFINITION 2-

More information

Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. October 28, 2010

Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. October 28, 2010 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 28, 2010 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 2010 update TABLE OF CONTENTS

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 5484» Total Man Hours on Project: 135019» Crafts On Project This Week: 11» OSHA Recordable Rate: 0 February 28, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 47 Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee January 16, 2014 & Schedule Performance Summary Chart Project Performance

More information

VRE Gainesville-Haymarket Extension (GHX) Study. December 16, 2016

VRE Gainesville-Haymarket Extension (GHX) Study. December 16, 2016 VRE Gainesville-Haymarket Extension (GHX) Study December 16, 2016 1 Project Origins System Plan 2040 and Financial Plan Follow Natural Growth profile to run longer trains Continue to pursue funding for

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Construction Committee November 21, 2013 & Schedule Performance Summary Chart 2 1 Crenshaw/LAX Transit 1,749 2,058 2,058

More information

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10 EXECUTIVE SUMMARY Background The proposal for Rail Deck Park (RDP) comprises the construction of a decking structure over the rail corridor in downtown Toronto between Blue Jays Way and Bathurst Street

More information

PUBLIC INFORMATION MEETING June 24, 2015

PUBLIC INFORMATION MEETING June 24, 2015 Gallows Road (RTE. 650) over Arlington Boulevard (RTE. 50) Fairfax County Bridge Rehabilitation, Preventive Maintenance and Pier Repairs Phase 1 - Project No. 0650-029-235; UPC 106956, Pier Repair Phase

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report April 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

I-64 Pavement Rehabilitation

I-64 Pavement Rehabilitation LETTER OF SUBMITTAL I-64 Pavement Rehabilitation From: Hampton Roads Bridge Tunnel (East Abutment) To: Little Creek Road Bridge (West Abutment) A Design-Build Project Norfolk, Virginia Proposal Submitted

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

Report to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016

Report to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016 Report to the Finance Committee 2015 Comprehensive Annual Financial Report Prepared by the Office of Finance April 2016 Audit Opinion date April 11, 2016 Unmodified or clean audit opinion on financial

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM California High-Speed Train Project TECHNICAL MEMORANDUM 15% Design Scope Guidelines TM 0.1 Signed document on file Prepared by: 12 May 08_ Ken Jong, PE Checked by: Signed document on file 12 May 08_ John

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 18810» Total Man Hours on Project 395795» Crafts On Project This Week: 22» OSHA Recordable Rate: 0 July 31, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Tri-State Oversight Committee. Three-Year Safety and Security Review. of the Washington Metropolitan Area Transit Authority. Structures Maintenance

Tri-State Oversight Committee. Three-Year Safety and Security Review. of the Washington Metropolitan Area Transit Authority. Structures Maintenance Tri-State Oversight Committee Three-Year Safety and Security Review of the Washington Metropolitan Area Transit Authority Structures Maintenance Elements 14, 15 and 16 Review Conducted: April/May 2015

More information

TAMPA BAY NEXT MAJOR PROJECTS UPDATE

TAMPA BAY NEXT MAJOR PROJECTS UPDATE TAMPA BAY NEXT MAJOR PROJECTS UPDATE Marshall Hampton, FDOT District Seven Tampa Bay Next Program Manager January 18, 2019 1 2 Program Overview Funding Priorities Fiscal Year 2018 2019 2020 2021 2022 2023

More information

Phase 1 Final Revised Baseline Budget Approved June 9, 2016

Phase 1 Final Revised Baseline Budget Approved June 9, 2016 Phase 1 Final Revised Baseline Budget Approved June 9, 2016 1 1 Phase 1 Budget History ($ millions) May 2010 Baseline Budget July 2013 Budget Revisions June 2016 Final Baseline Budget Revisions Total Adjustments

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St

More information

Dulles Corridor Metrorail Project Phase 2 Package B

Dulles Corridor Metrorail Project Phase 2 Package B Dulles Corridor Metrorail Project Phase 2 Package B Quarterly Update to MWAA Board of Directors Michael Barker Hensel Phelps June 2018 Phase 2 Package B - Agenda Contract/Project Overview Safety Schedule

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 9086» Total Man Hours on Project: 188636» Crafts On Project This Week: 13» OSHA Recordable Rate: 0 April 24, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES» Continued

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School

More information

MTA CAPITAL CONSTRUCTION NEW YORK BUILDING CONGRESS NOVEMBER 7, MTA Capital Construction 0

MTA CAPITAL CONSTRUCTION NEW YORK BUILDING CONGRESS NOVEMBER 7, MTA Capital Construction 0 MTA CAPITAL CONSTRUCTION NEW YORK BUILDING CONGRESS NOVEMBER 7, 2013 MTA Capital Construction 0 UPCOMING MTA CAPITAL CONSTRUCTION SOLICITATIONS Presented by David K. Cannon Sr. Director and Chief Procurement

More information

Massachusetts Water Resources Authority Alewife Brook Pump Station Rehabilitation Design/CA/RE Services Contract 7034 Amendment No.

Massachusetts Water Resources Authority Alewife Brook Pump Station Rehabilitation Design/CA/RE Services Contract 7034 Amendment No. Massachusetts Water Resources Authority Alewife Brook Pump Station Rehabilitation Design/CA/RE Services Contract 7034 Amendment No. 3 April 12, 2017 Alewife Brook Pump Station 14 Rehabilitation Work to

More information

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009

Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Project Status September Report 15, 2009 #16 July 31, 2012 TABLE OF CONTENTS SECTION 1: PROJECT SUMMARY SECTION 2: OVERALL PROJECT SCHEUDLE

More information

301 Walnut Street Windsor, Colorado phone fax

301 Walnut Street Windsor, Colorado phone fax 301 Walnut Street Windsor, Colorado 80550 phone 970-674-2400 fax 970-674-2456 www.windsorgov.com Table of Contents... 2 SECTION 1 Questions & Requests for Clarification... 3 1.1 Question Deadline... 3

More information

PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT

PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGMENT 2 FACILITY SERVICES Facility Development Capital Projects Management

More information

CAC Meeting Construction Update April 8, 2014

CAC Meeting Construction Update April 8, 2014 CAC Meeting Construction Update April 8, 2014 Period Summary There have been over 1,000,000 craft hours completed, excluding demolition, through March 31, 2014. An increase of nearly 50,000 hours since

More information

FEDERAL TRANSIT ADMINISTRATION REGION 3 FINDING OF NO SIGNIFICANT IMPACT

FEDERAL TRANSIT ADMINISTRATION REGION 3 FINDING OF NO SIGNIFICANT IMPACT FEDERAL TRANSIT ADMINISTRATION REGION 3 FINDING OF NO SIGNIFICANT IMPACT Project: Dulles Corridor Metrorail Project, Phase 2 Preliminary Engineering Design Refinements Project Sponsor: Metropolitan Washington

More information

City of St. Catharines Standard Drawings SEPTEMBER Revised September 6, 2018 TES-ENG (SH)

City of St. Catharines Standard Drawings SEPTEMBER Revised September 6, 2018 TES-ENG (SH) City of St. Catharines Standard Drawings SEPTEMBER 2018 Revised September 6, 2018 TES-ENG (SH) Roads Dwg No. Revision Standard Sidewalk Detail 110-2001 2 Monolithic Curb-Faced Sidewalk 110-2002 3 Sidewalk

More information

Norwood High Service Pump Replacement

Norwood High Service Pump Replacement T E C H N I C A L M E M O R A N D U M 737-02 NORWOOD HIGH SERVICE PUMP REPLACEMENT 737-02 Norwood High Service Pump Replacement PREPARED FOR: JEA Planning PREPARED BY: Joshua M. Brown DATE: February 2017

More information

PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows:

PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows: PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD LCB File No. R090-08 May 14, 2008 EXPLANATION Matter in italics is new; matter in brackets [omitted material] is material to be omitted. AUTHORITY: 1,

More information

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2

More information

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information