Dulles Corridor Metrorail Project
|
|
- Rosemary Gardner
- 5 years ago
- Views:
Transcription
1 Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF APRIL 30, 2016 JUNE 2016
2 Phase 2 Cost Summary April Expenditures $ 17.5 Million Total Expenditures $ Million Total Budget $ Billion Total Forecast $ Billion
3 Phase 2 Contingency Utilization Total Contingency Contingency Utilized through March 2016 Contingency Utilized in April 2016 Total Contingency Utilized through April 2016 Remaining Contingency $ Million $ 79.2 Million $ 1.0 Million $ 80.2 Million $ Million
4 April Contingency Utilization Total Contingency Utilized in April 2016 Package A (CRC) $ 1.0 Million $ 0.8 Million Non-pervious asphalt paving at wayside facilities Construction $ 560,000 Replacing the stainless steel mesh panels at elevator hoistways Design & Construction Herndon Station South Area Facilities additional technical clarification Design & Construction Temporary Access to Pacific Boulevard Yard fire hydrant Design & Construction Repair and replacement of the storm drain inlets and clearing of storm drains at Pacific Boulevard Yard Construction (Settled for $65,250) Design changes at Reston Town Center Station due to revised Fairfax County Maintenance Responsibilities outside the pavilion footprint (Settled for $34,000) Incorporation of Loudoun County 30% Design of the Transit Connector Bridge at Ashburn Station (Settled for $60,000) $ 213,000 $ 68,000 $ 45,500 $ 36,250 $ 24,000 $ 20,000
5 April Contingency Utilization Loudoun Gateway north side sanitary sewer outfall revision to $ 9,000 90% Design & Construction Additional Traction Power Load Flow Study (Settled for $62,000) $ (1,000) Automatic Train Control System specification revisions Design & Construction Package B (HP) $ (126,000) $ 0.2 Million Yard Wi-Fi infrastructure change Design $ 68,000 Modifications to the traction power substation ground grid $ 40,000 Design & Construction Changes to pit guardrails for Service and Inspection Building $ 30,000 Design Updates to the requirements for Service and Inspection Building $ 7,000 Electronics Shop Design Traction Power Substation Ground Grid Criteria Study $ 5,000
6 Current Guideway & Stations Design-Build Activities Advancement of Design Packages: Design complete 3 minor, non-schedule critical packages near 100% 7 packages to be Issued for Construction Issued 17 Permit Amendments due to Design Revisions Project Office Review/Approval Activities: 14 Design Change Packages 75 Contractor Submittals 20 Non-Conformance Reports
7 Guideway & Stations Design-Build Activities Set Girders In Yard Leads
8 Guideway & Stations Design-Build Activities Stripping Column Forms East of Dulles Airport
9 Guideway & Stations Design-Build Activities Form and Pour Corbels for Straddle Bent #3
10 Guideway & Stations Design-Build Activities Drill Caissons for Columns at Airport
11 Guideway & Stations Design-Build Activities Precast Panel Installation at Innovation Station
12 Guideway & Stations Design-Build Activities Install Concrete Foundations at Reston Station
13 Guideway & Stations Design-Build Activities Form Herndon Station Columns, Foundations and Walls
14 Guideway & Stations Design-Build Activities Prepare Column Forms at Dulles Station
15 Guideway & Stations Design-Build Activities Utility Tunnel Casing under Rudder Road
16 Upcoming Guideway & Stations Design-Build Activities Reston Station pour foundations and cast in place concrete walls and continue installation of 34.5 KV. Herndon Station Form and pour station foundations and walls and continue installation of underground systems and utilities. Innovation Station Continue station precast element placement and start structural steel vault roof framing. Dulles Station Continue station foundation and aerial guideway substructures, continue walkway retrofit and tie in to Station mezzanine. Aerial Guideway Pour drilled shafts, columns and pier caps; install decks and girders; at the Airport, cast straddle bent #13 and girder support corbels at straddle bent #2.
17 WMATA Rail Yard & Maintenance Facility Design-Build Activities Current Construction of all at grade and underground facilities has been permitted and is proceeding. Initial efforts are concentrated in the Service and Inspection Building (SIB). Final grading, utilities and yard layout continues. Final design of the Project Wide Package scheduled for completion in August.
18 WMATA Rail Yard & Maintenance Facility Design-Build Activities Upcoming Construction of all facilities. Advance Project Wide design documents to 100% and Issue For Permit. Address open WMATA design refinements. Review shop documents and revised design documents. Process open commercial issues.
19 WMATA Rail Yard & Maintenance Facility Design-Build Activities Inspection Pit Foundations SIB Basement Preparation
20 WMATA Rail Yard & Maintenance Facility Design-Build Activities Site Preparation Continues
21 DULLESMETRO.COM
22 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 MONTHLY COST SUMMARY As of April 30, 2016 Description Budget Total Expenditures to Date Contract Contract Amount 1,3 Forecast 2 Amount Total NTP Substantial 4 DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 Percent b c c/b DESIGN-BUILD Package A 1,193,777,000 1,275,937, ,094,822 34% 8-Jul-13 7-Aug-19 DESIGN-BUILD Package B + S 273,280, ,163,930 49,460,303 19% 18-Nov Jun-18 ROW 58,600,000 58,305,000 5,797,664 10% 8-Jul Sep-17 WMATA 305,324, ,324,718 42,929,307 14% N/A 3-Feb-20 PRELIMINARY ENGINEERING 75,000,000 75,000,000 73,266,056 98% 15-Jul Dec-13 PROJECT MANAGEMENT 320,802, ,264, ,035,332 41% N/A 2-Jan-19 CONTINGENCY 551,451, ,240,510 TOTAL FOR DCMP 2,778,235,564 2,778,235, ,583,483 Notes: 1 Budget Amount includes contingency as separate line item and does not include finance costs. 2 Total Forecast includes funded changes. It does not include finance costs. 3 Budget Amount includes commodity escalation of $20 million for Package A & B+S. 4 Package A Contract Substantial Completion date changed from 7-Jul-2018 to 7-Aug-2019
23 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 CONTINGENCY UTILIZATION As of April 30, 2016 ATTA Description Amount in million ($) DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 Total Contingency $ Contingency Utilized through March 2016 $ 79.2 Expended Contingency in April 2016* $ 1.0 Total Contingency Utilized through April 2016 $ 80.2 Remaining Contingency $ *See table below for details Package A (CRC) $0.8 Million Non-pervious Asphalt Paving at Wayside Facilities - Construction $ 560,000 Replacing the Stainless Steel Mesh Panels at Elevator Hoistways - Design and Construction $ 213,000 Herndon Station South Area Facilities Additional technical Clarification - Design and $ 68,000 Construction Temporary Access to Pacific Boulevard Yard Fire Hydrant - Design and Construction $ 45,500 Repairs and Replacement of the Storm Drain Inlets and Clearing of Storm Drains at $ 36,250 Pacific Boulevard Yard - Construction (Settled at $65,250) Design Changes at Reston Town Center Station due to Revised Fairfax County's $ 24,000 Maintenance Responsibilities outside the pavilion footprint (Settled for $34,000) Incorporation of Loudoun County's 30% Design of the Transit Connector Bridge at $ 20,000 Ashburn Station (Settled at $60,000) Loudoun Gateway North Side Sanitary Sewer Outfall - Revision to 90% Design and $ 9,000 Construction Additional Traction Power Load Flow Study (Settled at $62,000) $ (1,000) Automatic Train Control Systems Specification Revisions - Design and Construction $ (126,000) Package B (HP) $0.2 Million Yard WiFi Infrastructure Change - Design $ 68,000 Modifications to the Traction Power Substation Ground Grid - Design and $ 40,000 Construction Changes to Pit Guardrails for Service and Inspection Building - Design $ 30,000 Updates to the Requirements for Service and Inspection Building Electronics Shop - $ 7,000 Design Traction Power Substation Ground Grid Criteria Study $ 5,000
24 Dulles Rail ATTACHMENT 1 Airport Project No Description Budget Amount DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 DESIGN-BUILD Package A DCMP 5401 Package A - Mainline (CRC) 1,177,777,000 DCMP 5406 Commodity Escalation 16,000,000 DCMP 5408 Contingency amount DCMP 5408 Secondary mitgation amount SUBTOTAL - DESIGN-BUILD Package A 1,193,777,000 DESIGN-BUILD Package B+S DCMP 5402 Package B - Yard 269,280,530 DCMP 5402 Package S - Yard Site Preparation incl above DCMP 5406 Commodity Escalation 4,000,000 DCMP 5408 Contingency amount DCMP 5408 Secondary mitgation amount SUBTOTAL - DESIGN-BUILD Package B+S 273,280,530 ROW DCMP 5404 Land & Relocation 47,225,000 DCMP 5404 Support Services 11,375,000 DCMP 5408 Contingency SUBTOTAL - ROW 58,600,000 WMATA DCMP 5405 WMATA Vehicles 205,868,200 DCMP 5405 WMATA other costs 90,205,767 DCMP 5405 WMATA Non Revenue Vehicles 9,250,751 DCMP 5408 Contingency SUBTOTAL - WMATA 305,324,718 PRELIMINARY ENGINEERING DCMP 5406 PRELIMINARY ENGINEERING 75,000,000 SUBTOTAL - PRELIMINARY ENGINEERING 75,000,000 PROJECT MANAGEMENT DCMP 5406 MWAA Staff 34,000,000 DCMP 5406 MWAA Allocated Cost 13,560,000 DCMP 5406 Rent 9,200,000 DCMP 5406 Relocation, IT, Furniture 2,700,000
25 Dulles Rail ATTACHMENT 1 Airport Project No Description Budget Amount DCMP 5406 MWAA ODCs 17,060,000 DCMP 5406 Insurance (OCIP) 49,082,137 DCMP 5406 PMSS 140,000,000 DCMP 5406 VDOT 10,000,000 DCMP 5406 DRC Prof Svcs 2,500,000 DCMP 5406 CTI (Special Inspections) 14,000,000 DCMP 5406 DGS 2,000,000 DCMP 5406 TRIP II 2,000,000 DCMP 5406 Dept of Conservation & Recreation (DCR) 2,000,000 DCMP 5406 MWAA Permits/Inspection 4,000,000 DCMP 5406 Power for System Testing 16,000,000 DCMP 5406 Historical/Archaeologic 2,700,000 DCMP 5408 Contingency SUBTOTAL - PROJECT MANAGEMENT 320,802,137 CONTINGENCY DCMP 5408 Contingency - Package A 289,067,231 DCMP 5408 Secondary mitgation amount - Package A 0 DCMP 5408 Contingency - Package B 109,006,387 DCMP 5408 Secondary mitgation amount - Package B 0 DCMP 5408 Contingency - ROW 5,860,000 DCMP 5408 Contingency - WMATA 30,532,472 DCMP 5408 Contingency Project Management 116,985,089 SUBTOTAL - CONTINGENCY 551,451,179 TOTAL FOR DCMP - PHASE 2 2,778,235,564
Dulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2016 FEBRUARY 2017 Phase 2 Cost Summary December Expenditures $ 79.6 Million Total Expenditures $ 1.068 Billion
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2016 MARCH 2016 Phase 2 Cost Summary January Expenditures $ 8.8 Million Total Expenditures $ 664.4 Million Total
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2015 FEBRUARY 2016 Phase 2 Cost Summary December Expenditures $ 62.9 Million Total Expenditures $ 655.6 Million
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF FEBRUARY 29, 2016 APRIL 2016 Phase 2 Cost Summary February Expenditures $ 25.7 Million Total Expenditures $ 690.1 Million
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2016 NOVEMBER 2016 Phase 2 Cost Summary September Expenditures $ 29.0 Million Total Expenditures $ 901.4 Million
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2017 MARCH 2017 Phase 2 Cost Summary January Expenditures $ 10.6 Million Total Expenditures $ 1.078 Billion
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE PHASE 2 AS OF OCTOBER 31, 2015 DECEMBER 2015 Phase 2 Cost Summary October Expenditures $ 21.9 Million Total Expenditures $ 569.2 Million
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF MARCH 31, 2015 MAY 2015 0 Phase 2 Cost Summary March Expenditures $ 21.8 Million Total Expenditures $ 422.6 Million
More informationDulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 2 Phase 2 Cost Summary September Expenditures $ 19.4 Million Total Expenditures $ 1.868
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASES 1 AND 2 AS OF SEPTEMBER 30, 2014 November 2014 0 Phase 1 Cost Summary September Expenditures $ 2.5 Million Total Expenditures
More informationDulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,
More informationDulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May
More informationDulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President Phase 1 Phase 1 Cost Summary Expenditures (Nov 17 thru Apr 18) Total Expenditures (Thru Apr
More informationCapital Rail Constructors: Quarterly Update to MWAA Board of Directors
Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule
More informationCapital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager
Program Panelist Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager Moderator Kevin Pavuk, Structural Technologies Presentation 5:30 to 7:00 p.m.
More informationDulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting
Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting June 22, 2016 Discussion Outline Finance Plan for the Metrorail Project Financial Developments Since December 2015
More informationDulles Corridor Metrorail Expansion. Providing Safe Transportation for Northern Virginia
Dulles Corridor Metrorail Expansion Providing Safe Transportation for Northern Virginia Overview The Washington D.C. Metrorail is the second busiest rail transit network in the United States, with an average
More informationEVALUATION OF ALTERNATIVES CARRIED FORWARD
1 EVALUATION OF ALTERNATIVES CARRIED FORWARD This chapter presents a comparative evaluation of the alternatives carried forward in this Final Environmental Impact Statement (EIS). The intent of this evaluation
More informationIronton Russell Bridge Project
Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationMetropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF REQUEST FOR PROPOSALS
Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF REQUEST FOR PROPOSALS Metropolitan Washington Airports Authority Procurement and Contracts Dept., MA-29 1 Aviation
More informationCustomer Service and Operations Committee. Board Information Item III-B. October 9, 2014
Customer Service and Operations Committee Board Information Item III-B October 9, 2014 Major Red Line Construction Page 12 of 58 Washington Metropolitan Area Transit Authority Board Action/Information
More informationDoing Business with the Metropolitan Washington Airports Authority
Doing Business with the Metropolitan Washington Airports Authority MWMCA Quarterly Economic Summit Brown Advisory November 7, 2017 Introduction to MWAA Ronald Reagan Washington National Airport Washington
More information2016 ACEC/PA ANNUAL MEETING
2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA
More informationIronton Russell Bridge Project
Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015
More informationEglinton Crosstown LRT Construction Liaison Committee
Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report December 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationMetropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK
Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package A Rail Line, Stations, and Systems February 1, 2013 (Rev. 1 - Issued with Final RFP) Final RFP Statement of Work February
More informationProject Budget and Schedule Status
Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project
More informationMetropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK
Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package A Rail Line, Stations, and Systems March 15, 2013 (Rev. 2 - Issued with Final RFP) Final RFP Statement of Work March
More informationIronton Russell Bridge Project
Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place
More informationIronton Russell Bridge Project
Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September
More information7/30/2014 Correspondence
7/30/2014 Correspondence July 29, 2014 Mr. Mark Canale Fairfax County 4050 Legato Rd Suite 400 Fairfax, VA 221822228 Project [813C001] Dulles Corridor Metrorail Project, Phase 2 Pkg A Location Code (multi)
More informationAPPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED
APPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED APPENDIX H: ALTERNATIVES PREVIOUSLY CONSIDERED This appendix provides an overview of the process that led to the selection of the Locally Preferred Alternative
More informationM E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y. DTR Toll Collection Overview
DTR Toll Collection Overview 1 The Dulles Toll Road A Traditional Tolling Facility * Payment Options * EZ Pass * Exact Change (all coins) * Full Service (but no Credit Card capability) * Some higher (but
More informationLIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs)
LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs) 0002.0001 Structural Standard Drawings - Layering Structure n/a Aug 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details n/a Jun 2002 Jul
More informationCOMPREHENSIVE MONTHLY REPORT. September 2010
COMPREHENSIVE MONTHLY REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC October 26, 2010 PMOC Contract Number: DTFT60-09-D-00016
More informationProject Budget and Schedule Status Report
Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX
More informationCollege Football Hall of Fame HAMMOCK R
- Contract Schedule MILESTONES DESIGN / PRECONSTRUCTION PROCUREMENT Construction Procurement CONSTRUCTION Hardscape / Landscape Hall Of Fame Building Sitework Earthwork A1060 Mobilize 5 18-Feb-13 A 22-Feb-13
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationI2-0 LIST OF ACTIVE SSDs
I2-0 0002.0001 Structural Standard Drawings - Layering Structure Aug 1, 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details Jun 1, 2002 Jul 17, 2002 0007.0002 Grout Vent Detail Mar 1, 2006
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA
ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationAMENDED RECORD OF DECISION. by the Federal Transit Administration. Dulles Corridor Metrorail Project Fairfax and Loudoun Counties, Virginia
AMENDED RECORD OF DECISION by the Federal Transit Administration Fairfax and Loudoun Counties, Virginia DECISION The Federal Transit Administration (FTA), in accordance with 23 CFR part 771, the regulation
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200 GRADING 219.101 Light Duty Straw
More informationDULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue
DULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue Submitted to the Federal Transit Administration For Final Design Submitted by Metropolitan Washington Airports Authority In cooperation with
More informationCOMPREHENSIVE MONTHLY REPORT. April 2011
COMPREHENSIVE MONTHLY REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC May 27, 2011 PMOC Contract Number: DTFT60-09-D-00016
More informationCOMPREHENSIVE MONTHLY REPORT. December 2011
COMPREHENSIVE MONTHL REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC January 20, 2012 PMOC Contract Number: DTFT60-09-D-00016
More informationØ Contents of Price Proposal:
ATTACHMENT 4.0.1.2 Addendum#1 February 13, 2015 DESIGN-BUILD PRICE PROPOSAL CHECKLIST Project Name: Route 7 Widening and Bridge Rehabilitation over Dulles Toll Road and Airport Access Highway Contract
More informationNORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR
NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR0013844 & BR0013129 COLUMBIA, CHEROKEE COUNTY, SOUTH CAROLINA I-85 UNDERPASS PROJECT (1) REPLACEMENT OF EXISTING I-85 UNDERPASS BRIDGE MILEPOST SB-141.35 DOT/AAR
More informationIronton Russell Bridge Project
Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report July 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationReport to the Dulles Corridor Advisory Committee. Proposed Dulles Toll Road Toll Rate Adjustment. October 2018
Report to the Dulles Corridor Advisory Committee Proposed Dulles Toll Road Toll Rate Adjustment October 2018 Purpose The primary purpose of today s briefing is to: review the reasons for periodic adjustments
More informationRt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016
Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb
More informationProject Budget And Schedule Status Report
Item 47 Project Budget And Schedule Status Report Presented by Brian Boudreau Executive Director, Program Management Construction Committee June 18, 2015 & Schedule Performance Summary Chart Slide # Project
More informationThe Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects
The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationProject Budget and Schedule Status Report
Item 58 Transit Program Project Budget and Schedule Status Report Construction Committee October 16, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments
More informationResults you can rely on
z 1 I-49 North Segment K Project 2 AGENDA PROJECT OVERVIEW BRIDGE DESIGN ARCHITECTURAL ENHANCEMENTS SPECIAL PROVISIONS COST ESTIMATE AND FINAL BIDS CONSTRUCTION 3 SITE LOCATION PROJECT SITE ARKANSAS 185
More informationG2-0 LIST OF ACTIVE MTODs
G2-0 LIST OF ACTIVE MTODs DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings Apr 1, 1994 Jan 4, 1994 TOS/TO For use with Pavement Marking items. DIVISION 200- GRADING 219.101 Light Duty Straw
More informationPAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV
NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435
More informationMetropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK
Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package P Stormwater Management Facilities February 13, 2017 Rev. 0 Statement of Work February 13, 2017 THIS PAGE INTENTIONALLY
More informationAnnual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. January 2011
Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Annual Report TABLE OF CONTENTS
More informationTechnical Assignment 2
Chris Glinski Construction Management Faculty Advisor: Dr. Messner Columbia Heights Community Center 1480 Girard St. NW Washington, DC 20009 10-31-2005 Technical Assignment 2 Table of Contents A. Executive
More informationFY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT
FY 15-20 CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT Department of Public Works Robert B. Boxer, Director PROJECT MODEL PROFESSIONAL SERVICES STUDIES FEASIBILITY CLAIMS 1- PROJECT DEFINITION 2-
More informationQuarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. October 28, 2010
Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 28, 2010 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 2010 update TABLE OF CONTENTS
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 5484» Total Man Hours on Project: 135019» Crafts On Project This Week: 11» OSHA Recordable Rate: 0 February 28, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST
More informationProject Budget and Schedule Status
Item 47 Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee January 16, 2014 & Schedule Performance Summary Chart Project Performance
More informationVRE Gainesville-Haymarket Extension (GHX) Study. December 16, 2016
VRE Gainesville-Haymarket Extension (GHX) Study December 16, 2016 1 Project Origins System Plan 2040 and Financial Plan Follow Natural Growth profile to run longer trains Continue to pursue funding for
More informationConceptual Design Report
Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE
More informationProject Budget and Schedule Status
Item Program Management Project Budget and Schedule Status Transit Project Delivery Construction Committee November 21, 2013 & Schedule Performance Summary Chart 2 1 Crenshaw/LAX Transit 1,749 2,058 2,058
More informationEXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10
EXECUTIVE SUMMARY Background The proposal for Rail Deck Park (RDP) comprises the construction of a decking structure over the rail corridor in downtown Toronto between Blue Jays Way and Bathurst Street
More informationPUBLIC INFORMATION MEETING June 24, 2015
Gallows Road (RTE. 650) over Arlington Boulevard (RTE. 50) Fairfax County Bridge Rehabilitation, Preventive Maintenance and Pier Repairs Phase 1 - Project No. 0650-029-235; UPC 106956, Pier Repair Phase
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report April 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationI-64 Pavement Rehabilitation
LETTER OF SUBMITTAL I-64 Pavement Rehabilitation From: Hampton Roads Bridge Tunnel (East Abutment) To: Little Creek Road Bridge (West Abutment) A Design-Build Project Norfolk, Virginia Proposal Submitted
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationReport to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016
Report to the Finance Committee 2015 Comprehensive Annual Financial Report Prepared by the Office of Finance April 2016 Audit Opinion date April 11, 2016 Unmodified or clean audit opinion on financial
More informationTECHNICAL MEMORANDUM
California High-Speed Train Project TECHNICAL MEMORANDUM 15% Design Scope Guidelines TM 0.1 Signed document on file Prepared by: 12 May 08_ Ken Jong, PE Checked by: Signed document on file 12 May 08_ John
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 18810» Total Man Hours on Project 395795» Crafts On Project This Week: 22» OSHA Recordable Rate: 0 July 31, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East
More informationTri-State Oversight Committee. Three-Year Safety and Security Review. of the Washington Metropolitan Area Transit Authority. Structures Maintenance
Tri-State Oversight Committee Three-Year Safety and Security Review of the Washington Metropolitan Area Transit Authority Structures Maintenance Elements 14, 15 and 16 Review Conducted: April/May 2015
More informationTAMPA BAY NEXT MAJOR PROJECTS UPDATE
TAMPA BAY NEXT MAJOR PROJECTS UPDATE Marshall Hampton, FDOT District Seven Tampa Bay Next Program Manager January 18, 2019 1 2 Program Overview Funding Priorities Fiscal Year 2018 2019 2020 2021 2022 2023
More informationPhase 1 Final Revised Baseline Budget Approved June 9, 2016
Phase 1 Final Revised Baseline Budget Approved June 9, 2016 1 1 Phase 1 Budget History ($ millions) May 2010 Baseline Budget July 2013 Budget Revisions June 2016 Final Baseline Budget Revisions Total Adjustments
More informationSecond Avenue Subway
Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St
More informationDulles Corridor Metrorail Project Phase 2 Package B
Dulles Corridor Metrorail Project Phase 2 Package B Quarterly Update to MWAA Board of Directors Michael Barker Hensel Phelps June 2018 Phase 2 Package B - Agenda Contract/Project Overview Safety Schedule
More informationHOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett
SAFETY» Total Man Hours Worked This Week: 9086» Total Man Hours on Project: 188636» Crafts On Project This Week: 13» OSHA Recordable Rate: 0 April 24, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES» Continued
More informationNEW MIDDLE SCHOOL PROJECT
Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School
More informationMTA CAPITAL CONSTRUCTION NEW YORK BUILDING CONGRESS NOVEMBER 7, MTA Capital Construction 0
MTA CAPITAL CONSTRUCTION NEW YORK BUILDING CONGRESS NOVEMBER 7, 2013 MTA Capital Construction 0 UPCOMING MTA CAPITAL CONSTRUCTION SOLICITATIONS Presented by David K. Cannon Sr. Director and Chief Procurement
More informationMassachusetts Water Resources Authority Alewife Brook Pump Station Rehabilitation Design/CA/RE Services Contract 7034 Amendment No.
Massachusetts Water Resources Authority Alewife Brook Pump Station Rehabilitation Design/CA/RE Services Contract 7034 Amendment No. 3 April 12, 2017 Alewife Brook Pump Station 14 Rehabilitation Work to
More informationBryant Denny Stadium Bryant Denny Stadium September 15, 2009
Bryant Denny Stadium Bryant Denny Stadium September 15, 2009 Project Status September Report 15, 2009 #16 July 31, 2012 TABLE OF CONTENTS SECTION 1: PROJECT SUMMARY SECTION 2: OVERALL PROJECT SCHEUDLE
More information301 Walnut Street Windsor, Colorado phone fax
301 Walnut Street Windsor, Colorado 80550 phone 970-674-2400 fax 970-674-2456 www.windsorgov.com Table of Contents... 2 SECTION 1 Questions & Requests for Clarification... 3 1.1 Question Deadline... 3
More informationPLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT
PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGMENT 2 FACILITY SERVICES Facility Development Capital Projects Management
More informationCAC Meeting Construction Update April 8, 2014
CAC Meeting Construction Update April 8, 2014 Period Summary There have been over 1,000,000 craft hours completed, excluding demolition, through March 31, 2014. An increase of nearly 50,000 hours since
More informationFEDERAL TRANSIT ADMINISTRATION REGION 3 FINDING OF NO SIGNIFICANT IMPACT
FEDERAL TRANSIT ADMINISTRATION REGION 3 FINDING OF NO SIGNIFICANT IMPACT Project: Dulles Corridor Metrorail Project, Phase 2 Preliminary Engineering Design Refinements Project Sponsor: Metropolitan Washington
More informationCity of St. Catharines Standard Drawings SEPTEMBER Revised September 6, 2018 TES-ENG (SH)
City of St. Catharines Standard Drawings SEPTEMBER 2018 Revised September 6, 2018 TES-ENG (SH) Roads Dwg No. Revision Standard Sidewalk Detail 110-2001 2 Monolithic Curb-Faced Sidewalk 110-2002 3 Sidewalk
More informationNorwood High Service Pump Replacement
T E C H N I C A L M E M O R A N D U M 737-02 NORWOOD HIGH SERVICE PUMP REPLACEMENT 737-02 Norwood High Service Pump Replacement PREPARED FOR: JEA Planning PREPARED BY: Joshua M. Brown DATE: February 2017
More informationPROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows:
PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD LCB File No. R090-08 May 14, 2008 EXPLANATION Matter in italics is new; matter in brackets [omitted material] is material to be omitted. AUTHORITY: 1,
More informationARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company
James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2
More informationWell Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.
Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan
More information